  • LEAN CONSTRUCTION PRINCIPLES AND RAILWAY MAINTENANCE

    PLANNING

    Daria Ivina

    PhD student, Lund University, Sweden

    [email protected]

    Nils O. E. Olsson

    Professor, Norwegian University of Science and

    Technology, Norway

    [email protected]

  • Background – Organizational model

    2

    5 contractor companies:

    • Infranord

    • Strukton Rail

    • NRC i Sverige

    • Infratek Sverige

    • BDX Företagen

    34 basic mantenance contracts

  • 3

    37869

    73531

    20000

    30000

    40000

    50000

    60000

    70000

    80000

    20000

    22000

    24000

    26000

    28000

    30000

    32000

    34000

    36000

    38000

    40000

    2015 2016 2017 2018 2019

    Planned maintenance activities

    Planned working hours

    Background – Track works

  • Purpose and Method

    4

    Purpose - study maintenance planning processes based on Last Planner framework

    Method

    • Literature study

    • Interviews

    • Data analysis

  • Lean philosophy

    5

    1. Value for customer

    2. Value stream

    3. Flow4. Pull

    5. Perfection

    Lean

    Last Planner® System

    Percentage Plan Completed

  • (1) unproductive maintenance

    (2) waiting for maintenance resources

    (3) centralized maintenance

    (4) poor inventory management

    (5) unnecessary motion

    (6) poor maintenance

    (7) ineffective data management

    (8) underutilization of resources

    6

    Wastes in Maintenance

    Arkivbild Bild: Magnus Hjalmarson Neideman SVDTT Bild

  • Planninglevels

    7

    STRATEGICAL PLANNING

    ANNUAL PLANNING

    DETAIL PLANNING

    OPERATIONAL

    PLANNING

  • Barriers in Lean implementation

    8

    • lack of knowledge about lean principles

    • knowledge management

    • inefficiency in source planning

    • lack of trust

  • Percentage Plan Completed

    • Southern Sweden

    • 4 companies A, B, C and D

    • 1 month (April 2019)

    • Time on track planned vs used

    9

    -6%

    -29%

    -40%

    94%

    71%

    100%

    60%

    +24%

    -50 0 50 100

    A

    B

    C

    D

    % time not used

    % used possesions

    % over used

  • Conclusions

    10Arkivbild Bild: Magnus Hjalmarson Neideman SVDTT Bild

    • Last Planner principles have a potential to improve effectiveness in maintenance processes

    • Establishing changes to contractors work routine based on lean principles may face some barriers

    • The data available at Trafikverket can be utilized to analyze the performance of contractors

  • 11

    Thank you for your attention!Questions?

    [email protected]

    Study is a part of BANDAT project supported by the Swedish Transport Administration (Trafikverket)