LAPORAN PROJEK SIAP
FASA 1(3 JANUARI 2013)
PROJEK KERJA-KERJA MENAIKTARAFSURAU AL-IZZAH FASA 1
TAMAN SAMUDERA A FASA 1, BATU CAVES
SELANGOR
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
2/10
2
1. MAKLUMAT PROJEK
BIL PERKARA
1. NAMA PROJEK KERJA-KERJA MENAIKTARAF SURAU AL-IZZAHFASA 1 ,TAMAN SAMUDERA A FASA 1, BATU
CAVES , SELANGOR
2. NAMA KONTRAKTOR 1. HIJRAH ENTERPRISE (000825356-P)
NO.80-2B , JALAN 3,
BATU CAVES CENTRE POINT,
68100 BATU CAVES,SELANGOR DARUL EHSAN
2. KONTRAKTOR ELEKTRIKAL - MASRI
3. NO KONTRAK 1/SH/SA-FASA 1/2012
4. HARGA KONTRAK (BANGUNAN)
HARGA KONTRAK
(KERJA ELKTRIKAL)
KOS KONTRAK KESELURUHAN
RM 99,429.00
RM 2,338.00
RM 101,767.00
5. TEMPOH KONTRAK 15 MAC 2012 HINGGA 31 MEI 2012
LANJUTAN MASA NO.1- 18 JUN 2012
6. TARIKH SIAP ASAL
TARIKH SIAP SEBENAR
31 MEI 2012
6 JULAI 2012
7. TEMPOH MEMBAIKI KECACATAN 7 JULAI 2012 – 7 JANUARI 2013 (6 BULAN )
8. PENGARAH PROJEK / WAKIL
PENGARAH PROJEK
HJ.SUHAIRY BIN HJ.SAYUTI /
MOHD RAHIM BIN HJ.KAWANGIT
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
3/10
3
2. LAPORAN KEMAJUAN BERGAMBAR
GAMBAR SEBELUM KERJA-KERJA PEMBINAAN
TARIKH GAMBAR KEMAJUAN AKTIVITI
15.3.2012 PERBINCANGAN ANTARA
KONTRAKTOR DENGAN
SUB KONTRAKTOR
15.3.2012 PERBINCANGAN ANTARA
KONTRAKTOR DENGAN
SUB KONTRAKTOR
18.3.2012 KERJA UKUR ARAS
SEDANG DIJALANKAN
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
4/10
4
18.3.2012 KERJA UKUR ARAS
SEDANG DIJALANKAN
GAMBAR SEMASA KERJA-KERJA PEMBINAAN
TARIKH GAMBAR KEMAJUAN AKTIVITI
22.3.2012 KERJA-KERJA
PEMBERSIHAN TAPAK DI
BAHAGIAN SURAU
22.3.2012 KERJA-KERJA
PEMBERSIHAN TAPAK DI
TEMPAT LETAK KERETA
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
5/10
5
25.3.2012 KERJA-KERJA PENYEDIAAN
FOOTING
27.3.2012 KERJA-KERJA KONKRIT
UNTUK FOOTING
30.3.2012 KERJA-KERJA MEMBINARASUK TANAH
3.4.2012 KERJA-KERJA KONKRIT
RASUK TANAH
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
6/10
6
10.4.2012 KERJA-KERJA KONKRIT
LANTAI & STRUKTUR
TIANG
20.4.2012 KERJA-KERJA
PEMASANGAN DINDING
BATA , KEKISI KONKRIT
DAN BUMBUNG
20.4.2012-
30.4.2012
KERJA-KERJA PLASTERING
20.4.2012 -
30.4.2012
KERJA-KERJA
PEMASANGAN BUMBUNG
DAN PLASTERING
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
7/10
7
2.5.201 KERJA-KERJA
PEMBERSIHAN TAPAK
LETAK KERETA KALI KE 2
2.5.2012 KERJA-KERJA
PEMASANGAN TANGKI
NAJIS
5.5.2012 KERJA-KERJA
PEMASANGAN PAIP AIRDALAMAN
15.5.2012 KERJA-KERJA MEMBINA
STRUKTUR MENARA
TANGKI AIR
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
8/10
8
GAMBAR KEMAJUAN KERJA SIAP
TARIKH GAMBAR KEMAJUAN AKTIVITI
8.7.2012 PANDANGAN SISI
BANGUNAN
8.7.2012 PANDANGAN SISI
BANGUNAN
8.7.2012 PANDANGAN BELAKANG
BANGUNAN
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
9/10
9
8.7.2012 TEMPAT WUDHU’ LUAR
8.7.2012 PANDANGAN TIPIKAL
TEMPAT WUDHU
8.7.2012 BASIN BASUH TANGAN
TIPIKAL
8.7.2012 TANDAS JENIS DUDUK
TIPIKAL
8/17/2019 LAPORAN-SIAP-PERLAKSANAAN-PROJEK-NAIKTARAF-SURAU-AL-IZZAH-FASA-1-1.pdf
10/10
10
8.7.2012 BESIN BASUH DAN ‘TABLE
TOP’ DI RUANG DAPUR
8.7.2012 PEMASANGAN ‘SWITCH
BOX’ BARU
8.7.2012 PEMASANGAN POINT
LAMPU DAN POINT KUASA