5
Name of the Engineer : M.Mohan Kumar Name of the title holder : Mr………………………………………………………………………………………………………………….. ESTIMATE FOR LAND IMPROVEMENTS WORK (ON THE EXISTING LAND PROPERTY IN S.F.NO……………………………………………………………………………… Name of the title holder : Mr. …………………………………. Total Abstract estimate for the proposed land improvements work is about RS………………………….. (Rupees …………………………………………………………………………………………………………) Estimate done by( for Corporation bank ) Address

Land Improvement Work

Embed Size (px)

Citation preview

Page 1: Land Improvement Work

Name of the Engineer : M.Mohan Kumar

Name of the title holder : Mr…………………………………………………………………………………………………………………..

ESTIMATE FOR LAND IMPROVEMENTS WORK

(ON THE EXISTING LAND PROPERTY IN S.F.NO………………………………………………………………………………

Name of the title holder : Mr. ………………………………….

Total Abstract estimate for the proposed land improvements work is about RS…………………………..

(Rupees …………………………………………………………………………………………………………)

Estimate done by( for Corporation bank ) Address

Page 2: Land Improvement Work

Name of the Engineer : M.Mohan Kumar

Name of the title holder : Mr…………………………………………………………………………………………………………………..

Er. M.MOHAN KUMAR

DETAILED AND ABSTRACT ESTIMATE

Name of work: ESTIMATE FOR THE PROPOSED ADDITION AND DEVELOPMENTS WORK IN THE EXISTING AGRICULTURAL LAND IN S.F. NO…………………………………

Name of the owner : Mr……………………………………………………….

Sl no

Description of work Estimated amount

Rate / Acre

12345Total (Rupees ……………………….

Declaration

*This is to certify that I have inspected the land in which proposed land improvement work in the existing agriculture land owned by Mr………………….

.*At this date, the estimated amount of proposed land development work is about Rs………………

*This estimate is prepared to get loan from Corporation bank, Kunnathur Branch.

Place : Arni Signature of the Engineer

Date :

Page 3: Land Improvement Work

Name of the Engineer : M.Mohan Kumar

Name of the title holder : Mr…………………………………………………………………………………………………………………..

Part I – Abstract Estimate for land clearing

Sl no

Description of items Qty Rate (Rs)

Per Amount (Rs)

1 Clearing scrub jungle including cutting all trees, scrubs and others vegetation and depositind them beyond the site as directed by the applicant including all labour charges etc., complete

1,750 m2 5 m2 8,750

2 Clearing jullifora jungle including cutting all trees, scrubs and others vegetation and depositind them beyond the site as directed by the applicant including all labour charges etc., complete

2,475 m2 15 m2 37,125

3 Provision for other unforeseen items Lump sum 4,125Total (Rupees……………………………………….. 50,000

Part II – Detailed Estimate for Deepening of existing well

Sl no

Description of items Qty Rate (Rs)

Per Amount (Rs)

1 Earth work excavation in well 265.32 m2 275 m3 72,963Extra for every addition 1 lead (or) part there of over the initial lead

265.32 m2 25 m3 6,633

Extra for every addition 2 lead (or) part there of over the initial lead

265.32 m2 70 m3 18,572

Extra for every addition 1 lift (or) part there of over the initial lead

265.32 m2 25 m3 6,633

Extra for every addition 2 lift (or) part there of over the initial lead

265.32 m2 70 m3 18,572

2 Provision for other unforeseen items Lump sum 1,627Total (Rupees……………………………………….. 1,25,000

Page 4: Land Improvement Work

Name of the Engineer : M.Mohan Kumar

Name of the title holder : Mr…………………………………………………………………………………………………………………..

Part III – Abstract Estimate for Construction of RR masonry wall

Sl no

Description of items Qty Rate (Rs)

Per Amount (Rs)

1 Random Rubble Masonary in CM 1:2 for streering wall using rough stones the rate including the cost of rough stones and scaffolding charges etc.,

46.74 m2 1500 m3 70,110

2 Pointing with CM 1:2 in R.R masonary streering wall including the cost of materials, labour and scaffolding charges etc., complete.

76.62 m2 400 m2 30,648

3 Provision for other unforeseen items Lump sum 4,242Total (Rupees……………………………………….. 1,05,000