LAMPIRAN DATA UJI PEMOMPAAN
E.1 SUMUR TBT-14DATA UJI PEMOMPAAN BERTAHAP
No.Sumur= TBT 14 Debit Pemompaan = Step I 8.15 ltr/detTanggal= 30 September 1994 Step II 12.11 ltr/detElevasi m.at= 15.22 m dari top casing Step III 16.10 ltr/detElevasi m.at= 14.72 m dari muka tanah Step IV 20.50 ltr/detWaktuKedalaman m.a.t dari top Casing (m)Penurunan m.a.t (m)
(menit)IIIIIIIVIIIIIIIV
117.2319.522.0124.062.014.286.798.84
218.1519.5422.4824.32.934.327.299.08
318.5919.5622.5224.53.374.347.39.28
418.6519.5922.5724.673.434.377.359.45
518.719.6422.624.753.484.427.389.53
618.7319.722.6224.883.514.487.49.66
718.7419.7222.6424.973.524.57.429.75
818.7519.7422.6525.053.534.527.439.83
918.7619.7822.6625.13.544.567.449.88
1018.7619.8122.6725.173.544.597.459.95
1218.7619.8522.6825.283.544.637.4610.06
1418.7619.9622.6925.363.544.747.4710.14
1618.7620.0522.7225.53.544.837.510.28
2018.7720.1522.7425.613.554.937.5210.39
2518.7720.2522.7725.663.555.037.5510.44
3018.7720.422.825.713.555.187.5810.49
3518.7720.5122.8425.733.552.297.6210.51
4018.7720.622.8725.763.555.387.6510.54
4518.7720.6822.9125.783.555.467.6910.56
5518.7720.7622.9425.793.555.547.7210.57
6018.7720.8222.9725.83.555.67.7510.58
Sumber : North Bali Groundwater Irrigation and Water Supply Project
Project Management Unit Singaraja
DATA UJI PEMOMPAAN MENERUS
No. Sumur= TBT-14Sumur pengamat= TBT-15Data pemompaan= 20 ltr/detJarak= 30 meterKedalaman m.a.t= 15,05 m dari top casingElvasi awal m.a.t= 14,50 m dari top = 14,15 m dari muka tanah casingElevasi titik bor= 15,85 m dari muka lautJarak sumur dari laut= 660 mTanggal= 1-4 Oktober 1994Waktu (menit)M.A.T (m)S (m)Waktu (menit)M.A.T (m)S (m)
TBT 14TBT 15TBT 14TBT 15TBT 14TBT 15TBT 14TBT 15
124,2414,69,190,130026,4114,8911,560,39
225,5314,7510,480,2536026,6414,8911,590,39
325,8514,7810,80,2842026,6814,8911,630,39
425,9114,810,860,348026,7114,8911,660,39
526,0214,8210,970,3254026,7314,8911,6890,39
626,0614,8411,010,3460026,7514,8911,70,39
726,0914,8611,040,3666026,7614,8911,710,39
826,1114,8711,060,3772026,7714,8911,720,39
926,1314,8711,080,3778026,7814,8911,730,39
1026,1514,8711,10,3784026,7914,8911,740,39
1226,1814,8711,130,3790026,814,8911,750,39
1426,214,8711,150,3796026,8114,8911,760,39
1626,2114,8711,160,37108026,8214,8911,770,39
1826,2214,8811,170,38120026,8314,8911,780,39
2026,2314,8811,180,38132026,8414,8911,790,39
2526,2514,8911,20,38144026,8514,8911,80,39
3026,2614,8811,210,39156026,914,8911,850,39
3526,2714,8811,220,38168026,9514,8911,90,39
4026,2814,8811,230,38180026,9814,8911,930,39
4526,2914,8811,240,38192027,0614,8912,010,39
5026,314,8811,250,38204027,114,8912,050,39
5526,3114,8811,260,38216027,1414,8912,090,39
6026,3214,8811,270,38228027,1714,8912,120,39
7026,3514,8811,30,38240027,1914,8912,140,39
8026,3714,8811,320,38252027,2314,8912,180,39
9026,3914,8811,340,38264027,2714,8912,220,39
10026,4114,8811,360,38276027,314,8912,250,39
11026,4214,8811,370,38288027,3214,8912,270,39
12026,4314,8711,380,37306027,3614,8912,310,39
13526,4514,8811,40,38324027,4114,8912,360,39
15026,4714,8811,420,38342027,4314,8912,380,39
16526,4914,8911,440,39360027,4514,8912,40,39
18026,514,8911,450,39378027,4614,8912,410,39
20026,5114,8911,460,39396027,4714,8912,420,39
22026,5214,8911,470,39414027,4814,8912,430,39
24026,5314,8911,480,39432027,4914,8912,440,39
27026,5914,8911,540,39
DATA UJI PEMULIHAN PEMOMPAANWaktu (menit)M.A.T (m)S' (m)
TBT 14TBT 15TBT 14TBT 15
127,4914,8912,440,39
215,3114,60,260,1
315,1914,570,140,07
415,1314,530,080,03
515,1114,510,060,01
615,0814,50,030
715,060,01
815,050
Sumber : North Bali Groundwater Irrigation and Water Supply Project
Project Management Unit Singaraja
E.2 Sumur TTM-18DATA UJI PEMOMPAAN BERTAHAP
No.Sumur= TTM-18 Debit Pemompaan = Step I 8.15 ltr/detTanggal= 18 Oktober 1994 Step II 12.6 ltr/detElevasi m.at= 18.10 m dari top casing Step III 16.7 ltr/detElevasi m.at =17.33m dari muka tanah Step IV 20.50 ltr/det
WaktuKedalaman m.a.t dari top casing (m)Penurunan m.a.t (m)
(menit)IIIIIIIVIIIIIIIV
121.2626.0429.534.043.167.9411.415.94
221.8326.1629.6734.063.738.0611.5715.96
322.126.1729.7634.248.0711.6616.1
422.3526.229.8234.44.258.111.7216.3
522.426.2629.8734.424.38.1611.7716.32
622.4626.329.9134.444.368.211.8116.34
722.5626.3129.9534.484.468.2111.8516.38
822.5926.333034.534.498.2311.916.43
922.6426.3530.0534.594.548.2511.9516.49
1022.656.3730.0834.644.558.2711.9816.54
1222.6626.3930.0834.644.568.2911.9816.54
1422.6726.4330.0834.684.578.3311.9816.58
1622.6826.4530.0834.684.588.3511.9816.58
1822.6926.4830.0934.714.598.3811.9916.61
2022.726.5130.134.774.68.411216.67
2522.7226.5530.2235.054.628.4512.1216.95
3022.7326.630.2835.114.638.512.1817.01
3522.7526.6530.3235.144.658.5512.2217.04
4022.7626.6730.3635.24.668.5712.2617.1
4522.7826.6830.4735.284.688.5812.3717.18
5022.7926.6930.535.434.698.5912.417.33
5522.8126.730.5835.474.718.612.4817.37
6022.8226.7230.6435.354.728.6212.5417.25
Sumber: North Bali Groundwater Irrigation and Water Supply ProjectProject Management Unit Singaraja
DATA UJI PEMOMPAAN MENERUS
No.Sumur= TTM 18Data pemompaan= 15 ltr/detKedalaman m.a.t=17,93 m dari top casing17,13 m dari muka tanahElevasi titik bor= 18 m dari muka lautJarak sumur dari laut = 540 m Sumur pengamat = TTM-20Jarak= 30 meterElevasi awal m.a.t= 15,82 m dari Top CasingTanggal = 19 - 21 Oktober 1994WaktuM.A.T (m)S (m)WaktuM.A.T (m)S (m)
(menit)TTM 18TTM 20TTM 18TTM 20TTM 18TTM 18TTM 18TTM 18TTM 18
12415,856,070,0320027,08169,150,18
224,6315,876,70,0522027,116,019,170,19
325,315,887,370,0624027,1216,039,190,21
425,4515,887,520,0627027,1616,049,230,22
525,5415,887,610,0630027,1816,059,250,23
625,6115,887,680,0636027,216,059,270,23
725,7215,887,790,0642027,2116,049,280,22
825,7515,897,820,0748027,22169,290,18
925,7715,897,840,0754027,2315,569,30,14
1025,7915,897,860,0760027,2515,889,320,06
1225,8315,897,90,0766027,2915,839,360,01
1425,8915,897,960,0772027,3315,799,40,03
1625,9615,898,030,0778027,3515,829,420
1826,0315,898,10,0784027,3815,879,450,05
2026,1915,898,260,0790027,4215,969,490,14
2526,3115,98,380,0896027,4916,019,560,19
3026,4115,98,480,08108027,5816,169,650,34
3526,4715,98,540,08120027,616,19,670,28
4026,5115,98,580,08132027,6315,999,70,17
4526,5615,98,630,08144027,6515,969,720,14
5026,6115,918,680,09156027,6915,99,760,08
5526,6315,918,70,09168027,76169,830,18
6026,6815,918,750,09180027,8516,039,920,21
7023,7215,928,790,1192027,9215,999,990,17
8026,7615,928,830,1204027,9615,9610,030,14
9026,7815,928,850,1216028,021610,090,18
10026,7615,938,90,11228028,116,0610,170,24
11026,8715,948,940,12240028,1616,110,230,28
12026,8915,948,960,12252028,2216,1610,290,34
13526,9315,9590,13264028,2816,1510,350,33
15026,9715,969,040,14276028,3316,0710,40,25
16527,0215,989,090,16288028,3216,0110,390,19
18027,0615,999,130,17
Sumber: North Bali Groundwater Irrigation and Water Supply ProjectProject Management Unit Singaraja
DATA UJI PEMOMPAAN BERTAHAP
Nomor Sumur = TTM-19 Debit pemompaan = Step I8.00 ltr/detTanggal = 23 Desember 1994 Step II12.00 ltr/detElevasi m.a.t = 26.85 m dari top casing Step III16.00 ltr/detElevasi m.a.t = 26.35 dari muka tanah Step IV20.00 ltr/det
Waktu (menit)Kedalaman m.a.t dari top casing (m)Penerimaan m.a.t (m)
IIIIIIIVIIIIIIIV
127.4328.2229.229.930.581.372.353.08
227.5828.5629.2329.940.731.712.383.09
327.628.5929.2329.940.751.742.383.09
427.6728.5929.2329.940.821.742.383.09
527.7228.5929.2429.950.871.742.393.1
627.828.5929.2429.960.951.742.393.11
727.8728.5929.2429.961.021.742.393.11
827.928.5929.2429.961.051.742.393.11
927.9528.5929.2429.961.11.742.393.11
102828.5929.2429.961.151.742.393.11
1228.0428.629.2529.961.191.752.43.11
1428.0628.629.2629.961.211.752.413.11
1628.0728.6129.2629.961.221.762.413.11
1828.0828.6129.2629.961.231.762.413.11
2028.0828.6129.2629.961.231.762.413.11
2528.0828.6329.2629.961.231.782.413.11
3028.0828.6529.2629.961.231.82.413.11
3528.0828.6629.2629.961.231.812.413.11
4028.0828.6729.2629.961.231.822.413.11
4528.0828.6729.2629.961.231.822.413.11
5028.0828.6729.2629.961.231.822.413.11
5528.0828.6729.2629.961.231.822.413.11
6028.0828.6729.2629.961.231.822.413.11
DATA UJI PEMOMPAAN MENERUS
No. Sumur= TTM-19Debit Pemompaan = 20,46 ltr/detElevasi awal m.a.t= 26,97 dari top casing= 26,47 m dari muka tanahElevasi titik bor= 28,07 m dari muka lautJarak sumur dari laut= 710 mTanggal= 24-27 Desember 1994Waktu M.A.T S Ec Waktu M.A.T S Ec
(menit)(meter)(meter)(uS/cm)(menit)(meter)(meter)(meter)
128.11.1330030.43.43
229.162.1936030.413.44
329.792.8242030.413.441738
429.993.0248030.413.44
530.093.1254030.413.44
630.183.2160030.413.44
730.223.2566030.43.431746
830.253.2872030.43.43
930.273.378030.43.43
1030.283.3184030.43.43
1230.33.3355390030.413.441746
1430.313.3496030.413.44
1630.313.34108030.423.451750
1830.313.34120030.423.45
2030.313.34132030.423.45
2530.333.36144030.423.45
3030.343.37553156030.423.45
3530.343.37168030.423.45
4030.343.37180030.433.461750
4530.343.37192030.433.46
5030.353.38204030.433.46
5530.353.38216030.433.461750
6030.353.38555228030.433.46
7030.363.39240030.443.471750
8030.363.39252030.443.47
9030.363.39264030.453.48
10030.363.39276030.463.491752
11030.363.39288030.473.5
12030.363.39741306030.483.51
13530.373.4324030.483.511752
15030.383.41342030.483.511756
16530.383.41360030.483.511756
18030.383.41980378030.483.511756
21030.393.42396030.483.511941
22030.393.42414030.483.511975
24530.393.421575432030.483.511975
27030.343.43
Waktu (menit)M.A.T (meter)S (meter)
030.4830.48
126.9726.97
SUMBER : North Bali Groundwater Irrigation and Water Supply Project
Project Management Unit Singaraja