Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
KYRGYZ REPUBLIC: RURAL
WATER SUPPLY AND
SANITATION PROJECT
IFI Coordination in Provision of Rural
Water and Sanitation Services
Presentation by Jonathan Kamkwalala
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
Project Details
Project Objectives:
– (a) improve access to potable water in the villages of Issyk-Kul, Naryn and Talas regions in northern Kyrgyzstan through a community approach
– (b) improve hygiene, sanitation and water related practices in a sustainable manner
Total Project Cost and Financing:
Project Cost: US$24.5 million
IDA Financing: US$15.0 million
DFID Financing: US$ 6.2 million
GOK/Community Financing: US$ 3.3 million
Implementation Period:
March 2002 to October 2008
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
Main Project Features
Project uses demand driven approach at village level involving all community members
Project strengthens capacity to manage water/sanitation systems by supporting establishment of Community Drinking Water Users Unions (CDWUUs) at the local level
The Project has helped establish a decentralized system for the management of rural water supply, by facilitating the dissolution of a Soviet style central institution that was responsible for operation of rural water systems
Instead, a more streamlined central department largely responsible for policy making has been established
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
IFI Partnerships
WB financed water supply activities in villages selected on a demand driven basis
DFID financed hygiene promotion and good sanitation in villages selected for water supply sub-projects
In addition, DFID financed technical assistance for project implementation and institutional capacity building
DFID/WB Project approach and methodology was adopted in Southern Regions with similar parallel project financed by Asian Development Bank (ADB)
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
Project Achievements
By end 2007, project activities had been completed in 120 villages covering 138,000 village residents.
The health impact of hygiene and sanitation activities was significant; water borne diseases in participating villages dropped significantly
The population to receive clean water from the project will exceed original estimates
Community development approach has been internalized and communities participation in selection, implementation of water supply systems is satisfactory
Together, the Bank/DFID and ADB projects will cover over 60% of Kyrgyz rural areas
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
Main Challenges in Scaling Up
Acceptance by communities of simpler, more rudimentary but sustainable water supply systems from those provided under the former Soviet Union, which are no longer sustainable
Acceptance by communities of cost recovery principle and community contribution to project costs after a legacy of Soviet provided subsidized water systems
Continued capacity to operate and manage the systems after project completion
Weak institutional capacity of Central Government for policy making
Possible politicization in the selection of participating villages
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
Lessons Learned
Sustained dialogue with communities to ensure acceptance of approach is critical (at the expense of delays to project implementation)
Simple project design with activities initially focusing on demonstration effect and scaling up later
Community involvement oriented towards engaging communities on priorities, options, and empowering them with information on project and technical solutions helped overcome some of the initial resistance to project approach
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
Benefits of IFI Collaboration
WB/DFID Collaboration allowed for greater leverage in discussing policy reforms with Government and promoted harmonization
DFID grant resources leveraged Bank credit sources for effective use of resources
DFID/Bank Collaboration allowed other donors, e.g., ADB to “join the bandwagon”
Complementary Support in strategic financing now being provided under OECD National Policy Dialogue Initiative, thus increasing potential of scaling up of donor support
Bank/DFID collaboration will continue in a follow-up project
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
Challenges of IFI Collaboration and
Lessons Learned Differences in donor policies created potential for conflict in
such areas as procurement, fund disbursements, etc
Co-financing effectiveness would benefit from better complementarities in activities financed; i.e. DFID financing was sometime seen as separate project by stakeholders
Ownership at the Central Government level was inadequate as project was seen as donor owned
14-May-2008EU Water Initiative Working Group
Meeting, May 12-13, 2008
Thank You!