2018. 6. 27 Korean Perspective of SDP <KHNP(Korea Hydro & Nuclear Power) case> Jungsup Oh ([email protected])

Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

2018. 6. 27

Korean Perspective of SDP

<KHNP(Korea Hydro & Nuclear Power) case>

Jungsup Oh ( [email protected])

Page 2: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Content

KHNP Design Change Process

Standard Design Process

Ⅲ KHNP’s CM Software

Page 3: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

3

Ⅰ. Standard Design Process

No. Plant Reactor Type

1 Shinhanul 1 - 2 APR-1400

ShinKori 3 - 4 APR-1400

2 Shinkori 1 - 2 OPR-1000

Shinwolsung 1 - 2 OPR-1000

Hanul 3 - 6 KSNP

Hanbit 3 - 6 KSNP

3 Hanul 1 - 2 PWR (Framatome)

Hanbit 1 - 2 PWR (Westinghouse)

Kori 2 - 4 PWR (Westinghouse)

4 Wolsung 1 - 4 CANDU

➢ Total Application of CMIS to Korean NPPs

1.0 Induction of KHNP

Page 4: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

4

Ⅰ. Standard Design Process1.1 SDP Flowchart

① Initial Scoping Phase② Conceptual/Common Design Phase③ Detailed Design Phase④ Planning Phase⑤ Installation / Testing Phase⑥ Design Closure Phase

➢ Design Change Phases

Page 5: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

5

Ⅰ. Standard Design Process1.1 SDP Flowchart

➢ Design Change Type

① Document Only Change② Commercial Change③ Design Equivalent Change④ Temporary Modification⑤ Design Change⑥ Item Equivalency Evaluation

Page 6: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

6

Ⅰ. Standard Design Process

Initial Scoping Phase

Modification Request

Change Type.

Document-Only Change Package

Multiple Plant

Temp. Mod.

Installation Work Order

Field Change

Installation

InstallTemp. Mod.

Doc. Only

Yes

Yes

No

No

No

No

Common Design Package

Design Equivalent Change Package

Commercial Change Package

Design Change Package

Yes

Remove Temp. Mod.

Update Documentation

Closeout

Schedule Work Order

Schedule Work Order

Common DesignPhase

PlanningPhase

Detail Design Phase

Installation/TestingPhase

Design Closure Phase

1.2 Summary of SDP Flowchart

Page 7: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Ⅱ. KHNP Design Change Process

7

Level 1[SSC Temp. Mod.]

Level 2[SSC Change]

Level 3[Non-SSC Change]

Need a Modification

Temp. Mod.

Temp. Mod. Process

Physical Change

Design Equivalent Change

Equivalent Evaluation

Design Change Request

Design Change

Installation / Closeout

SW Change

SW Configuration Management

Param. Change

Parameter Change Process

Quality Class

Change

Quality Class Management

Document ChangeEngineering

Document Change Process

Yes

Yes Yes

Yes

Yes

Yes

Yes

No

No

No

No

No

2.1 KHNP’s Design Change Process

No Design Change Process

Page 8: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Ⅱ. KHNP Design Change Process

8

2.2 Scope of Design Change Process

KHNP SDP

SSC Temp. Mod.

Temporary Modification Temporary Modification

SSC Change

Design Equivalent Change

Equivalent Evaluation Item Equivalent Evaluation

Commercial Change

DesignChange

Design Change Request

Design ChangeDesign Change

Installation/Closeout

Non-SSC Change

SW Configuration Management

Parameter Change Process

Quality Class Management

Engineering Document Change Document Only Change

Page 9: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Ⅲ. SDP Software

9

• Promote/implement design sharing mechanism.

• Automate/streamline SDP Process Forms

• Flexible solution – Tailor to existing software

• Automated final records capture

• Output Key Performance Indicators to measure SDP effectiveness

• SSO (Single Sign On) for users

• Provides EC cloning capabilities

• Automatically creates reviews based upon results of the Design Attribute

Review (DAR)

• Allows Stakeholders (other departments) to provide direct input to EC Sections

• Interfaces with existing Utility software to feed source data to SDP

3.1 SDP Software Expectation

Page 10: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Ⅲ. SDP Software

10

• Promote/implement design sharing mechanism.

• Automate/streamline SDP Process Forms (Electric Signature and workflow)

• Flexible solution – Tailor to existing software

• Automated final records capture (Upload to Document management server)

• Output Key Performance Indicators to measure SDP effectiveness

• SSO (Single Sign On) for users

• Provides EC cloning capabilities (Provide waiting list and cloning basic info.)

• Automatically creates reviews based upon results of the Design Attribute

Review (DAR)

• Allows Stakeholders (other departments) to provide direct input to EC Sections

• Interfaces with existing Utility software to feed source data to SDP

• Integrated Solution for DBD management and FCI explorer

3.2 KHNP’s Software Expectation

Page 11: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Ⅱ. KHNP Design Change Process

11

3.3 Scope of Design Change Process SW

KHNP SDP

SSC Temp. Mod.

Temporary Modification Temporary Modification

SSC Change

Design Equivalent Change

Equivalent Evaluation Item Equivalent Evaluation

Commercial Change

DesignChange

Design Change Request

Design ChangeDesign Change

Installation/Closeout

Non-SSC Change

SW Configuration Management

Parameter Change Process

Quality Class Management

Engineering Document Change Document Only Change

Page 12: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Ⅲ. SDP Software

12

No. Plant Start Date(Design change Only)

1 Shinkori 1 - 2 2016.10

2 ShinKori 3 - 4 2018.01

Shinwolsung 1 - 2 2018.01

Hanul 3 - 6 2018.01

Hanbit 3 - 6 2018.01

3 Hanul 1 - 2 (2018.01)2018.08

Hanbit 1 - 2 (2018.01)2018.08

Wolsung 1 - 4 (2018.01)2018.08

Kori 2 - 4 (2018.01)2018.08

4 Shinhanul 1 - 2 (2018.01)2018.08

Total Application

➢ Total Application of CMIS to Korean NPPs

3.5 SILKROAD CMIS

Page 13: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Ⅲ. SDP Software

13

Hard Version Management

Easy to do change management

Minimization of Human Error

Various Technical Analysis

One-Stop services for Design change process

3.16 Benefits of SILKROAD CMIS

Integrated Change Management Support(Design Change, Temporary Change, Document Change, SW Configuration Management etc.)

Provides Dashboard that Indicates Various Statistics

Digitalization of Entire Change Document Format

When Registering Documents, Linking Data and Assigning Approval Line can be done by “One-Step”

Systematic Drawings Version Control and Prevention of Simultaneous Design Change on the Same Drawing

➢ Improvements

Page 14: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Ⅲ. SDP Software

14

3.17 Future Works

CM Performance Indicators (related to ECs)

Integrate Equivalency Evaluation Process

Page 15: Korean Perspective of SDP - Benchmarkingcmbg.org/papers/2018Presentations/CMBG 2018_Korean... · 2018. 6. 29. · Update Documentation Closeout Schedule Work Order Schedule Work Order

Thank you!