1 2 3 4 5 6 +29.3 +28.5 +31.1 THIS DRAWING IS COPYRIGHT © Rev. Passed Chd. Drn. Status Drawing No. Date Job No. Scales job drg. notes DO NOT SCALE figured dimensions only to be taken from this drawing description drawn rev date Kevin Fitzpatrick│Landscape Architecture 7 Abbey Business Park Grange Drive Dublin 13 T- 00353 (0)1 8326715 E- [email protected] W- www.kfla.ie PLANNING KF MM 1:200 @ A2 15.04.19 102 0340 Knockboy Housing, Co. Waterford Open Space 1 and Entrance Area Open Space 1 + Entrance Area | 1:200 Proposed native hedgerow and tree planting to site boundary enhances local biodiversity, improves green infrastructure links and provides extra screening to the development. Planted bank - Maximum 1 in 2 embankment planted with shrub and groundcover planting. Informal flat lawn area suitable for active play and passive recreation. Copses of native parkland trees define lawn space and provide visual interest throughout the space. Formal clipped hedges frame the open space and provide screening from the entrance road. Proposed steps between upper and lower levels. Planted terrace - consisting of 2x 1.5m high retaining walls planted with a mix of ornamental shrub and groundcover planting and multi-stemmed trees. Line of fastigiate trees planted to the front of the wall to reduce visual effects. Entrance Feature - contrasting bands of feature paving, a mix of ornamental shrub and groundcover planting with multi-stemmed trees and space for signage. Proposed 1.2m high stub wall and railing to site boundary, refer to dwg no. 105. Formal hedge planting to inside of railing. Planted buffer between apartments and public footpath. Existing line of mature trees to site boundary to be retained. Proposed wildflower meadow improves local biodiversity and reduces repetitive maintenance operations.

KF 102 Open Space 1 and Entrance Area - Knockboy · 0340 102 Knockboy Housing, Co. Waterford Open Space 1 and Entrance Area Open Space 1 + Entrance Area | 1:200 Proposed native hedgerow

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: KF 102 Open Space 1 and Entrance Area - Knockboy · 0340 102 Knockboy Housing, Co. Waterford Open Space 1 and Entrance Area Open Space 1 + Entrance Area | 1:200 Proposed native hedgerow

1

2

3

4

5

6

+29.3

+28.5

+31.1

THIS DRAWING IS COPYRIGHT ©

Rev.

PassedChd.Drn.

Status

Drawing No.

Date

Job No.

Scalesjob

drg.

notes DO NOT SCALE figured dimensions only to be taken from this drawing

descriptiondrawnrev date

Kevin Fitzpatrick│Landscape Architecture7 Abbey Business ParkGrange DriveDublin 13T- 00353 (0)1 8326715 E- [email protected] W- www.kfla.ie

PLANNING

KFMM

1:200 @ A2

15.04.19

1020340

Knockboy Housing, Co. Waterford

Open Space 1 and Entrance Area

Open Space 1 + Entrance Area | 1:200

Proposed native hedgerow and tree planting tosite boundary enhances local biodiversity,improves green infrastructure links andprovides extra screening to the development.

Planted bank - Maximum 1 in 2 embankmentplanted with shrub and groundcover planting.

Informal flat lawn area suitable for active playand passive recreation.

Copses of native parkland trees define lawnspace and provide visual interest throughoutthe space.

Formal clipped hedges frame the open spaceand provide screening from the entranceroad.

Proposed steps between upper and lowerlevels.

Planted terrace - consisting of 2x 1.5m highretaining walls planted with a mix ofornamental shrub and groundcover plantingand multi-stemmed trees. Line of fastigiatetrees planted to the front of the wall to reducevisual effects.

Entrance Feature - contrasting bands offeature paving, a mix of ornamental shrub andgroundcover planting with multi-stemmedtrees and space for signage.

Proposed 1.2m high stub wall and railing tosite boundary, refer to dwg no. 105. Formalhedge planting to inside of railing. Plantedbuffer between apartments and publicfootpath.

Existing line of mature trees to site boundaryto be retained.

Proposed wildflower meadow improveslocal biodiversity and reduces repetitivemaintenance operations.