Upload
dangbao
View
225
Download
0
Embed Size (px)
Citation preview
Joint Water Purification Project-Colorado's First Planned Indirect
Potable Reuse
April 25, 2013
Joint Water Purification Project-Colorado's First Planned Indirect
Potable Reuse
April 25, 2013
California WATEREUSE –Central Valley Sierra Foothills
California WATEREUSE –Central Valley Sierra Foothills
Project OverviewProject Overview• Joint venture with two
owners:– Arapahoe County W&WW
Authority (ACWWA)– Cottonwood W&S District
(CWSD)• Location
– Southeast Denver metro area
• System Capacity– Initial= 9 mgd– Build out= 12 mgd
Water Supply SourcesWater Supply Sources
• Sources– Non-renewable deep aquifer sources– Renewable Cherry Creek alluvial water
• The renewable alluvial water has several water quality issues:– High percentage of effluent form upstream
WWTPs– (≈ 60% current, up to ≈ 80% in the future)– Emerging contaminants of concern– Aesthetics (Iron, color, hydrogen sulfide)– Uranium and radon gas
Cherry Creek and a typical alluvial well house
Alluvial / Indirect Potable Reuse Water Quality Issues
Alluvial / Indirect Potable Reuse Water Quality Issues
Water Quality Concerns
Microbial Re-growth
in Wastewater
Project GoalsProject Goals• Original Project Goals:
– Provide treatment for the alluvial water supply, thereby protecting its long term usability
– Long-term implementation of Indirect Potable Reuse to the extent possible
– Provide an appropriate level of treatment that would have public support
– Maximize use of renewable alluvial supply
– Address aesthetic concerns
→ Many of these are policy level decisions
Key Components of the Indirect Potable Reuse System
Key Components of the Indirect Potable Reuse System
• Expansion and upgrades to the Lone Tree Creek Water Reclamation Facility (LTCWRF)
• Development of a Raw Water Delivery system that provided 6 months of travel time
• Development of a water treatment facility and associated waste stream treatment processes
The LTCWRF, which includes tertiary treatment/ filtration, was placed into operation August 2009
Overall System ConfigurationOverall System Configuration
Water Treatment
Brine Treatment
WastewaterTreatment
Alluvial Recharge
Deep Aquifer Wells
Dedicated Alluvial Wells
Dedicated Alluvial Wells
Brine to Discharge
JWPP WTP
Park/ Greenbelt Irrigation
Potable Water Use
Waste Discharges to Sewer
Project TimelineProject Initiation
2003 July2005
Sept2005
Jan 2006
June 2006
Oct2007
Feb 2008
Aug 2009
June2010
JWPP WTP Pre-Design Complete
LTCWRF Pre-Design CompleteLTCWRF Design Complete
LTCWRF Construction Begins
JWPP WTP Design Complete
JWPP WTP Construction Begins
LTCWRF Construction CompleteJWPP Producing Water
Project DevelopmentProject Development• Developed a Technical Advisory
Committee (TAC)• Hired a Public Relations firm to assist
with developing the message• Evaluation & comparison to CA Indirect
Potable Reuse Systems, site visits• Implementation of multiple barrier
concepts• Progress design meetings with Colorado
Dept of Public Health and Environment• Presentations to engineering community• Public participation and presentations• Value Engineering during design
Technical and Institutional IssuesTechnical and Institutional Issues• Development in a high end commercial park• Fouling of RO membranes due to
wastewater colloidal particles• Treatment of RO brine to remove
phosphorus and other permit requirements• Impacts of waste streams to the sewer
system• Accumulation of salts in the alluvium due to
RO brine discharge• Challenges in developing the raw water
system, including yield and locating wells with acceptable water quality for membranes
Significant capital and O&M costs are realized for the RO brine treatment system
Comparison of System Configurations
Comparison of System Configurations
Joint Water Purification Project
AdvancedWater Treatment
Advanced WastewaterTreatment
Alluvial/Aquifer Discharge and Treatment
Advanced WastewaterTreatment
AdvancedWater Treatment
Alluvial/Aquifer Discharge and Treatment
California IPR Systems
ACWWA/CWSD have little control over other WW discharges and urban runoff
Customers
Customers
Potable Treatment ConfigurationPotable Treatment ConfigurationWater Quality Monitoring RO Skids Oxidation
Reactors (UV/H2O2)
Air Strippers
Clearwell/
DisinfectionAlluvial Filtration/ 6 month Travel Time
Advanced Wastewater Treatment
Plant Multiple Barrier ConceptsPlant Multiple Barrier Concepts
1. Will generally remove organics except volatiles with MW < 200-3002. Will remove radionuclides with the exception of radon gas3. Will remove light volatile organics4. Will remove radon gas only
TREATMENTPROCESS
CONTAMINANTS OF CONCERN
Pathogens/Microbial
Inorganic Radionuclides Organics
TOC VOC/SOC Emerging
Alluvial Filtration
X1 X1 X1 X1
ReverseOsmosis
X X X2 X X3 X3
Advanced Oxidation
X X
Air Strippers X4 X5
Chemical Disinfection
X
Construction Cost SummaryConstruction Cost SummaryITEM COST
Bid Package 1-Water Treatment Plant
$27,500,000
Potable Treatment Processes $23,000,000
Concentrate Treatment System $4,500,000
Bid Package 2-Pipelines
$3,500,000
Bid Package 3-Raw Water Supply Wells
$2,000,000
TOTAL $33,000,000