Joint Rail and Road Project Ringerike Line and E16 Highway Project Director Morten Klokkersveen 06.06.2019 1 Ringeriksbanen og E16

Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Joint Rail and Road ProjectRingerike Line and E16 HighwayProject Director Morten Klokkersveen

06.06.20191

Ringeriksbanen og E16

Page 2: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Film

06.06.2019 Ringeriksbanen og E162

Page 3: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Project status• Zoning plan filed for State approval 20th May 2019

• Approval expected Autumn 2019

• Final Investment Decision Autumn 2020

• Preparation of Invitations to Tender are ongoing at full pace

• Extensive geological and geotechnical mapping of ground condition • Full scale testing still ongoing

• Start-up for main preparatory works in 2020• Preparation of roads and traffic safety works• Access tunnels at Nordby and Avtjerna (190.000 solid m3)• Preparation of rig areas at Nordby and Avtjerna • Forest clearing• Noise prevention measures

06.06.2019 Ringeriksbanen og E163

Page 4: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Ringerike Line and E16 Highway

06.06.2019 Ringeriksbanen og E164

TK07

ERTMS

Page 5: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Requirements for model based engineering

• The project will be fully model based and according to the Road and Rail Authorities' BIM-strategies

• Standardised requirements for model based engineering and building are now implemented across the contracts focusing on:

• Standardised formats per discipline• Standardised information per discipline• Model based reviews and interface checks

06.06.2019 Ringeriksbanen og E167

Page 6: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Distribution and reuse of excavated materials

• Excavated materials will be distributed and reused in the project

• Quality masses will be produced from excavated materials at Avtjerna for distribution to the different contracts

06.06.2019 Ringeriksbanen og E168

Page 7: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Contract Structure

06.06.2019 Ringeriksbanen og E169

TK-01 Jong TK-02 Sollihøgda TK-05 Mælingen

Tracks, overhead

contact line, high/low woltage, telecom

Signal

Ringerike Line and E16 Highway TK-03 Sundvollen TK-04 Vik TK-06 Hønefoss

TK-06 (ECI/EPC)

Build substructure rail and road

TK-07 (EPC)

ERTMS

Preparatory / Enabling works Several contracts (construction only)

Design substructure rail and road

TK-01 (EPC) TK-02 (EPC) TK-03 (EPC) TK-04 (EPC) TK-05 (EPC)

Railway Technique

Page 8: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Project Managers

06.06.2019 Ringeriksbanen og E1610

TK-06 Hønefoss

Per Kristian SkjølåsProject Manager

TK-05 MælingenTK-04 VikTK-03 SundvollenTK-01 Jong / TK-02 Sollihøgda

Gørild Malm KristiansenProject Manager

Odd JohansenProject Manager

John RingerudProject Manager

Henning VardøenProject Manager

TK-07 Railway Systems

Eivind Aslaksen HamreProject Manager

Page 9: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

EPC Jong/EPC SollihøgdaProject Manager Henning Vardøen

06.06.201911

Ringeriksbanen og E16

Page 10: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

23km tunnels from Jong to Sundvollen• Two tubes; one double track tunnel with one parallel escape and service tunnel• Excavation method; drill and blast

06.06.2019 Ringeriksbanen og E1612

Page 11: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

3 EPC tunnel contracts from Jong to Sundvollen

06.06.2019 Ringeriksbanen og E1613

TK-01 JONG TK-02 SOLLIHØGDA TK-03 SUNDVOLLEN

Page 12: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Preparatory works for Jong and Sollihøgda during 2020/21• Rig areas and access tunnels at Nordby and Avtjerna• Access roads and crossings at Avtjerna including traffic safety works• Preparation of Avtjerna for large scale mass handling and production of quality masses

06.06.2019 Ringeriksbanen og E1614

TK-01 JONG TK-02 SOLLIHØGDA TK-03 SUNDVOLLEN

Page 13: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Jong – Civil works

• Two 2,5 km single track tunnels and one 6 km double track tunnel

• 8,5 km parallel escape and service tunnel

• Connection to existing tunnel at Jong

• Excavated volume: 1.640.000 solid m3

• Rig areas at tunnel portals of access tunnels at Jong and Nordby

06.06.2019 Ringeriksbanen og E1615

Page 14: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Sollihøgda

06.06.2019 Ringeriksbanen og E1616

Page 15: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Sollihøgda – Civil works

• 8,5km double track tunnel

• 8,5 km parallel escape and service tunnel

• Firefighting point at tunnel center point

• Excavated volume: 1.430.000 solid m3

• Handling of excavated materials and production of quality masses at Avtjerna

• Rig areas at tunnel portals of access tunnels at Avtjerna

• Rock from tunneling to be refined and reused in the project

06.06.2019 Ringeriksbanen og E1617

Page 16: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Sollihøgda – Avtjerna rig and production area for quality masses

06.06.2019 Ringeriksbanen og E1618

Page 17: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

EPC Sundvollen/EPC VikProject Manager John Ringerud

06.06.201919

Ringeriksbanen og E16

Page 18: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Sundvollen

06.06.2019 Ringeriksbanen og E1620

Page 19: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Sundvollen – Civil works railway line

• Railway station with platforms, bus stop, car parking, stairs and elevators

• Railway bridge: 770 m total length, 2 tracks

• Fillings in the lake: 340.000 solid m3 / 610.000 m3

• 6 km double track tunnel

• 6 km parallel escape and service tunnel

• Excavated volume: 990.000 solid m3

• Rock from tunneling to be reused in the project

06.06.2019 Ringeriksbanen og E1621

Page 20: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Sundvollen – Civil works highway

• Highway bridge: 640 m total length, 4 lanes

• Intersection at Elstangen with bridges and “roundabouts” for local roads and pedestrians

• Total cuts = fillings: 370.000 solid m3

06.06.2019 Ringeriksbanen og E1622

Page 21: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Vik

06.06.2019 Ringeriksbanen og E1623

Page 22: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Vik – Civil works railway and highway

• Tunnels (3 x 3,2 km) with some low overburden through urban areas partly in soil

• Excavation methods: Drill & blast + cut & cover (rail: 440m + 260m cut & cover, road: 2 x 260m cut & cover)

• Excavated volume: 820.000 solid m3

• Excavated material from tunneling to be reused in the project

• 3 km of rail- and highway in parallel through high value nature resorts

• 9 smaller bridges• Cuts in soil • Embankments

06.06.2019 Ringeriksbanen og E1624

Page 23: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Vik – Railway and Highway Tunnels

06.06.2019 Ringeriksbanen og E1625

Page 24: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

EPC MælingenProject Manager Gørild Malm Kristiansen

06.06.201926

Ringeriksbanen og E16

Page 25: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Mælingen

06.06.2019 Ringeriksbanen og E1627

Page 26: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Mælingen

• Crossing of unique wetlands and high value natural resorts

• 1.800 m of alternative bridge and/or embankment crossings

• Alternative with or without embankments to be decided by the authorities during autumn 2019

• Challenging soil conditions, typically 70 - 130 m to solid rock

• We seek to find the best combination of concept, technical solution and cost

• High focus on foundation methods

06.06.2019 Ringeriksbanen og E1628

Page 27: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Alternative 1, Crossing by embankment and bridge

06.06.2019 Ringeriksbanen og E1629

• Embankment at Helgelandsmoen

• Two double track railway bridges with embankment, 600 m

• 300 m (Storelva) + 900 m

• Highway bridges with embankment, 600 m

• 4-lane, 300 m (Storelva)

• 2-lane, 900 m

Page 28: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Alternative 2, Crossing by bridge

06.06.2019 Ringeriksbanen og E1630

• One double track railwaybridge, 1800 m

• Two two-lane highway bridges, each 1800 m

Page 29: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Storelva crossing

• No columns or foundations in the river.

• Free height under bridge has to be 7.5 to 8 m so that wetland birds can cross below the bridge.

• Soil conditions: about 80 m to solid rock.

06.06.2019 Ringeriksbanen og E1631

Examples Storelva Crossing, illustration only

Page 30: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Full scale testing - ongoing• Major costs related to the foundation• Input to design• Risk reduction• Expected results

• Bearing capacity of friction piles and direct foundations • Level of ground deformations• Time required for pile installation• Schedule effects

06.06.2019 Ringeriksbanen og E1632

Page 31: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

06.06.2019 Ringeriksbanen og E1633

Full scale testing

Page 32: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

EPC HønefossProject Manager Per Kristian Skjølås

06.06.201934

Ringeriksbanen og E16

Page 33: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Hønefoss

06.06.2019 Ringeriksbanen og E1635

Page 34: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Hønefoss – Civil works railway

• New two track railway from Prestmoen to Hønefoss station and Ve (23 km tracks in total)

• Complete rebuild of Hønefoss railway station with surrounding areas

06.06.2019 Ringeriksbanen og E1636

Page 35: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Hønefoss – Civil works railway

• 400 m concrete tunnel

06.06.2019 Ringeriksbanen og E1637

• Train parking for 8 x 220 m trains• Railway systems (excl. signal) at the

station and the surrounding areas

Page 36: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Hønefoss – Civil works highway

• 5 km new E16 Highway from Prestmoen to Ve including two intersections

06.06.2019 Ringeriksbanen og E1638

Page 37: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Hønefoss – Civil works railway and highway

• More than 25 constructions incl. bridges and concrete tunnels of variable sizes

• Large scale movement of masses

• 5 million m³ of masses to be deposited, of which 3 million m³ from the tunneling

• Logistically challenging enterprise with continuous rail and road traffic on existing lines and roads through the entire construction period

• Large areas covered by marine deposits including quick clay, of various depths. Typically 50-100 m to solid rock

• Early Contractor Involvement (ECI to EPC or alliance)

06.06.2019 Ringeriksbanen og E1639

Page 38: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Quick clay film

06.06.2019 Ringeriksbanen og E1640

Page 39: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

EPC Railway systemsEngineering Manager Kerstin Fischer

06.06.201941

Ringeriksbanen og E16

Page 40: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

TK07 Railway systems Jong – Styggdalen (Hønefoss)

• 35 km double track from Jong to Styggdalen

• 23 km tunnel (2x3 km single track and 20 km double track) with parallel service tunnel

• Station at Sundvollen

• 3 km tunnel double track

• 9 km double track through open landscape

• Civil works

06.06.2019 Ringeriksbanen og E1642

Page 41: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Civil works

• Water and frost protection in the service tunnel where needed• Concrete works in cross passages• Substructure in service tunnel• Parts of substructure in railway tunnels• Cable conduits

06.06.2019 Ringeriksbanen og E1643

Page 42: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Permanent way• Connection to existing line (Askerbanen), ballasted track

• 26,5 km slab track in tunnels and on the bridge at Sundvollen.

• 8,5 km ballasted track from Bymoen to Styggdalen (Hønefoss)

• 10 turnouts• 8 in slab track • 2 in ballasted track at connection to existing line (Askerbanen)

Rails, turnouts and sleepers will be company provided

06.06.2019 Ringeriksbanen og E1644

Page 43: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Overhead contact line system

• Standard Bane NOR S25 overhead contact line system • Autotransformer-system +/-15kV (16,7Hz) and conductors• Earthing system

06.06.2019 Ringeriksbanen og E1645

Page 44: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Power supply 50 Hz and telecom• 22kV, 50 Hz power supply

• 22/0,4 kV Substations

• Low voltage installations• Emergency lighting in both tunnels

• Telecommunication• Radiating cables (5 in double track tunnel, 1 in service tunnel)• Fibre cables• Public information systems at Sundvollen station

Most of the deliveries for the telecommunication systems shall be handled by using Bane NORs frame agreements.

06.06.2019 Ringeriksbanen og E1646

Page 45: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Interfaces between the contracts

Systems design and engineering define interfaces between• Substructure contracts TK01-TK06 and TK07 • Railway technique contract TK07and ERTMS (contract awarded)

Results are definitions of• Specified requirements for each contractor

• Responsibility• Quality

06.06.2019 Ringeriksbanen og E1647

Page 46: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Project Values and Key Dates

06.06.201948

Ringeriksbanen og E16

Page 47: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Ringerike Line and E16 Highway

06.06.2019 Ringeriksbanen og E1649

• Total project value:34 BILLION NOK

• Railway in operation: 2029/30

• Highway in operation: 2028

Page 48: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Preliminary Dates for Prequalification

06.06.2019 Ringeriksbanen og E1650

Civilworks

Railway systems

EPCTK-01Tunnel

Prequal. 2021

EPCTK-03

Tunnel, station and bridges

Prequal. 2021

EPCTK-05

Bridges

Prequal. 2021

EPCTK-02

Tunnel

Prequal. 2020/21

EPCTK-04

Tunnels, bridges and openlandscape

Prequal. 2022

ECI / EPC TK-06

Civil works and railway systems

Prequal. 2022

EPCTK-07

Railway systems excl. ERTMS(Excl. Hønefoss railway station)

Prequal. 2022/23

Oslo SLysaker

Hønefoss

Sundvollen

Sandvika

Page 49: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Thank you for your attention

06.06.201951

Ringeriksbanen og E16

Page 50: Joint Rail and Road Project Ringerike Line and E16 Highway · • Excavated material from tunneling to be reused in the project • 3 km of rail- and highway in parallel through high

Ringerike Line and E16 Highway

For project information, please see: Bane NOR’s home page: www.banenor.noProject home page: www.banenor.no/prosjekter/prosjekter/RingeriksbanenogE16

Supplier contact: [email protected]

06.06.2019 Ringeriksbanen og E1652