GD&T Inspection in SpatialAnalyzer

Jeremy WinnApplication Engineer

New River Kinematics

Philip WilsonApplication Engineer

New River Kinematics

Page 2: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Inspection

Incorporating

Standardized Inspection within SpatialAnalyzer

Page 3: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Inspection

GD&T “Regular Inspection” Alignments Datum Structure Current Position

Check Specific

Computation Bounding Tol. Zone RMS (root mean square)

Outlier Pts = Part Error User controls rejection rules

Goals: Pass/Fail at Tolerance Is the part good and if not..,

how do I fix it?

Page 4: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Inspection

1. Defining the Checks

Building Annotations • Tolerance Structure• Nominal designation

GD&T Inspection can be Divided into 2 Distinct Steps

1. Measurement ProcessData Gathering & Association

• Inspection/ inspect scripting• Toolkit or direction Association • or Measurement Plan (MP)

Page 5: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T and CAD Import

Page 6: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

Page 7: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

• SA Objects/CAD Face

• Datum Assignment

• Tolerance Definition

Page 8: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

Datum Annotations:

• SA Objects/CAD Face

Page 9: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Annotations

Page 10: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

• Annotation View Orientation:

• CAD Faces vs. SA Objects SA Objects (Fit to Points)

Page 11: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

Datum and Datum Target Designations• (Hold down A-Z to pick a letter)• Click-point defines leader line anchor point

Page 12: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

Feature Checks Designation:

Page 13: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

– Form Checks• Datum Independent

– Orientation Checks• Depend on 1 Datum

– Location Checks• Can Include 1-3 Datums • Can Include 1-2 Tiers

Feature Checks Designation:

Page 14: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

• Required for Material Modifiers– MMC, LMC

• Dimensional Tolerances– Datum Independent

Page 15: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Annotations Demo

Page 16: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Inspection

1. Defining the Checks

Building Annotations • Tolerance Structure• Nominal designation

GD&T Inspection can be Divided into 2 Distinct Steps

1. Measurement ProcessData Gathering & Association

• Inspection/ inspect scripting• Toolkit or direction Association • or Measurement Plan (MP)

Page 17: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Feature Checks

• Tree Structure– Annotations

• Tolerance & check definition

– Datums & Feature Checks1. Link points to annotations

2. Point offset & evaluation control

3. Contain guided inspection controls

Page 18: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Feature Checks

Page 19: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Inspection

Direct Point Association

Page 20: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Inspection

Guided Inspection• Design• Rehearse• Inspect

Page 21: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Demo- Basic Fit & Link

Page 22: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Check Details

Feature Checks come in 3 Categories:

– Orientation Checks

– Location Checks

– Form Checks

Page 23: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Flatness

Flatness Evaluation Process within SA:1. Two parallel planes are built bounding the

extents of the data.2. These planes are allowed to freely rotate to

establish the minimum distance between them while still containing the data.

Page 24: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Flatness

Standard Inspection (RMS):

Page 25: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Flatness

Flatness Evaluation Process within SA:1. Two parallel planes are built bounding the

extents of the data.2. These planes are allowed to freely rotate to

establish the minimum distance between them while still containing the data.

Page 26: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Cylindricty

Cylindricity Evaluation Process within SA:1. Two coaxial cylinders are built bounding the

extents of the data.2. The cylinders are allowed to freely rotate to

establish the minimum distance between them while still containing the data.

Page 27: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Orientation Checks

Datum

Nominal Angle

Deviation = Distance btw Planes

Page 28: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Surface Profile

Surface Profile Evaluation Process within SA:

1. An inner and outer tolerance boundary is established2. The profile is allowed to rotate based on the datum

constraints to minimize the deviations3. The extent of the max and min deviation is used to

establish the measured profile deviation

Page 29: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

Feature Checks Categories:

Cross SectionChecks

Page 30: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

Cross Section Checks:

RunoutCross Section

Check

Total RunoutSurface Check

Page 31: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Concentricity

Cross Section Checks:

ConcentricityCross Section

Check

Page 32: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

GD&T Annotations

Cross SectionChecks

Page 33: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Datum Alignment

Right- Click Datum Category• Select “Align”

Page 34: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Feature Checks

• Cylinder Evaluation Method• Probe Compensation

Page 35: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Datums and Degrees of Freedom• Geometry Type is the Key

Datum Alignment

Page 36: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

The number of datums specified and the feature type selected controls the degrees of freedom for the check:

Datum Alignment

• SA Objects/CAD Face• SA Offset object

Page 37: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Demo- Basic Fit & Link

Page 38: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Feature Checks

Inspection Controls

Evaluation Method

Page 39: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Feature Checks

• Cylinder Evaluation Method

Page 40: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Feature Checks

• Cylinder Evaluation Method

Page 41: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Feature Checks

• Cylinder Evaluation Method

Page 42: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Building Feature Checks

• Cylinder Evaluation Method

Page 43: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Composite True Position

Composite Checks:

Page 44: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Automatic Point Association

GD&T Inspection

• Proximity Filter

• Based on Initial Alignment

Page 45: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Automatic Point Association

GD&T Inspection

Page 46: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Automatic Point Association

GD&T Inspection

Page 47: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Reporting

Page 48: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Reporting

Summary Table• Fit Transform• Datum Statistics

Details Table• Point Deviations

Page 49: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Reporting

Vectors for Visualization:• Specific Alignment• DoF Understanding

Page 50: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Reporting

Page 51: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Reporting

Page 52: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Evaluations Tools

Page 53: Jeremy Winn Application Engineer New River Kinematics Philip Wilson Application Engineer New River Kinematics

Thank You