1 In This Issue ——————————————–— Land Acquisition Status & Critical Issues Phase-2 Civil Progress at a Glance Launching of Tunnel Boring Machine Track Progress E-News Letter for BMRC Website only https://english.bmrc.co.in/News/NewsSection U Can Contact us Email: [email protected]; [email protected] Toll-free Helpline: 1800-425-12345 Shri Durga Shanker Mishra, IAS Secretary to GoI, Ministry of Housing & Urban Affairs, & Chairman, Bangalore Metro Rail Corporation Limited Shri Ajay Seth, IAS Managing Director Bangalore Metro Rail Corporation Limited Address: Bangalore Metro Rail Corporation Limited 3rd Floor, BMTC Complex, K H Road, Shanthinagar, Bengaluru - 560 027. Web: www.bmrc.co.in May 2020 Issue 121 Jayadeva Flyover Demolition Jayadeva Flyover demolition work was done in Two Phases. Phase-1-Banneraghatta Loop-from 15.08.2019 to 31.10.2019 and Phase-2-Main Flyover–from 20.01.2020 to 05.06.2020. A total of 1,03,272 Man hours have been spent along with heavy machines.

Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

1

In This Issue

——————————————–—

Land Acquisition Status & Critical Issues

Phase-2 Civil Progress at a Glance

Launching of Tunnel Boring Machine

Track Progress

E-News Letter for BMRC Website only https://english.bmrc.co.in/News/NewsSection

U Can Contact us

Email: [email protected]; [email protected] Toll-free Helpline: 1800-425-12345

Shri Durga Shanker Mishra, IAS

Secretary to GoI, Ministry of Housing & Urban Affairs, &

Chairman, Bangalore Metro Rail Corporation Limited

Shri Ajay Seth, IAS

Managing Director

Bangalore Metro Rail Corporation Limited

Address: Bangalore Metro Rail Corporation Limited

3rd Floor, BMTC Complex, K H Road, Shanthinagar,

Bengaluru - 560 027. Web: www.bmrc.co.in

May 2020 Issue 121

Jayadeva Flyover Demolition

Jayadeva Flyover demolition work was done in Two Phases. Phase-1-Banneraghatta Loop-from 15.08.2019 to

31.10.2019 and Phase-2-Main Flyover–from 20.01.2020 to 05.06.2020. A total of 1,03,272 Man hours have been

spent along with heavy machines.

Page 2: Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

2

Critical issues faced regarding Land Acquisition for Phase-2 of the Project

Reach-6 Underground Section

Langford Town Station:- Local Military Authorities (LMA) have sent the proposal for

transfer of 2137.334. sqm of land on permanent basis and 5866.569 sqm on

temporary basis to Army Head Quarters. Matter is being pursued with Defence

Authorities.

Lakkasandra Village Sy. No. 14 and 15:- The re-location of 101 encroachers at

Lakkasandra land is under consideration of Deputy Commissioner, Bangalore

Urban and Karnataka Slum Development Board.

Phase-2 Progress up to 31st May, 2020

27

45

80

76

90

60

84

96

78

65

0 20 40 60 80 100 120

REACH-6-ELEV (GOTTIGERE TO SWAGATH CROSS ROAD)

REACH-5-P-3 (BOMMANAHALLI TO R V ROAD)

REACH-5-P-2 (HOSA ROAD TO BOMMANAHALLI)

REACH-5-P1 (BOMMASANDRA TO HOSA ROAD)

REACH-4B (PUTTENAHALLI CROSS TO ANJANAPURA TOWNSHIP)

REACH-3C (HESSARAGHATTA CROSS TO BANGALORE INTERNATIONAL EXHIBITION CENTER)

REACH-2B (PATTANAGERE TO CHELLAGHATTA DEPOT)

REACH-2A (MYSURU ROAD TO PATTANAGERE)

REACH-1B (VISVESVARAYA INDUSTRIAL AREA TO WHITEFIELD)

REACH-1A (BAIYAPPANAHALLI TO VISVESVARAYA INDUSTRIAL AREA)

PHASE-2 CIVIL WORKS PROGRESS IN PERCENTAGE

Page 3: Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

3

Sl. No

Reaches

No. of properties Required

No. of properties Acquired

[As per 28(4) & 3(1)]

Handed over to Eng. Section up to

May - 2020

Balance to be Handed over to Engg. Section

Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total

1

Reach-1 Extn 38 487 525 38 479 517 38 479 517 0 8 8

Forest Land 21 0 21 0 0 0 21 0 21 0 0 0

2

Reach-2 Extn Station & Viaduct

25 99 124 25 97 122 25 97 122 0 2 2

Challaghatta Depot 10 24 34 10 24 34 10 24 34 0 0 0

3 Reach-3C Extn 3 105 108 3 105 108 3 105 108 0 0 0

4

Reach-4B Extn. 12 294 306 12 294 306 12 294 306 0 0 0

Anjanapura Depot 1 20 21 1 20 21 1 1 2 0 19 19

5

Reach-5 New Line 46 798 844 46 798 844 46 790 836 0 8 8

Hebbagodi Depot 1 57 58 1 57 58 1 57 58 0 0 0

6

Reach-6 (Elevated) 34 222 256 34 222 256 34 222 256 0 0 0

Reach - 6 (UG) 52 289 341 52 276 328 49 279 328 3 10 13

Kothnur Depot 4 64 68 4 64 68 4 64 68 0 0 0

Total 247 2459 2706 226 2436 2662 244 2412 2656 3 47 50

7 ORR Line 31 56 87 30 55 85 29 51 80 2 5 7

8 Airport line 59 179 238 59 179 238 13 12 25 46 167 213

Total 90 235 325 89 234 323 42 63 105 48 172 220

Grand Total 337 2694 3031 315 2670 2985 286 2475 2761 51 219 270

Land Acquisition Status for the month of May, 2020 of Phase-2, ORR -2A & Airport -2B Line

Page 4: Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

4

Phase– 2 Progress Photos at a glance

R-1A: Garudacharpalya Station Roof Truss erection work in progress R-1B : Whitefield Station I-Girder Erection work in progress

R-2A: Viaduct view from Jnanabharathi Station towards

Pattanagere Station R-2B: Track laying work in progress along Viaduct

R-3C: Parapet Gantry-2 Launching works in progress R-4B: Hand Rail work in Ground Floor Entrance at

Anjanapura Road Cross

Page 5: Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

5

Phase– 2 Progress Photos at a glance:

R-5-P1: Electronic City-I Station works in progress R-5-P2: Oxford Station- Grid C to E Platform Level slab

concreting completed.

R-5-P3: Sump Raft concrete completed at Ragigudda station R-6-Ele: Swagath Station – 04 Pier location P2, P3, P9 & P10 Pier Arm Erection done at Concourse Level

R-6-UG-RT1: Aerial view of works at Dairy Circle UG Station R-6-UG-RT1: Barricading works in progress at Lakkasandra Station

Page 6: Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

6

Lowering of 1st TBM cutter head

at Shivajinagar UG Station

Launching of Tunnel Boring Machine-R6-UG-RT-2

Contractor - M/s Larson & Toubro Ltd—RT-02

Sl No RT-02 Details of TBM

1 Name of the two TBM’s Avni Lavi

2 TBM Procured from China Railway Construction Heavy Industry, China

3 Launched / Lowered into the Tunnels 28th May 2020

4 Will Tunnel Between Shivajinagar & Rashtriya Military School Underground Stations

5 Length of the two Twin Tunnels 2141 Meters

6 Diameter of the Cutter Head 6.74 Meters

7 Finished inside diameter of Tunnels 5.80 Meters

Page 7: Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

7

Lowering of 2nd TBM cutter head

at Cantonment UG Station

Contractor - M/s Larson & Toubro Ltd—RT-03

Sl No RT-03 Details of TBM

1 Name of the two TBM’s Urja Vindya

2 TBM Procured from China Railway Construction Heavy Industry, China

3 Launched / Lowered into the Tunnels 28th April 2020 3rd June 2020

4 Will Tunnel Between Cantonment & Shivajinagar Underground Stations

5 Length of the two Twin Tunnels 860 Meters

6 Diameter of the Cutter Head 6.74 Meters

7 Finished inside diameter of Tunnels 5.80 Meters

Launching of Tunnel Boring Machine-R-6-UG-RT-3

Page 8: Jayadeva Flyover Demolition · Lakkasandra land is under consideration of Deputy Commissioner, Bangalore Urban and Karnataka Slum Development Board. Phase-2 Progress up to 31st May,

8

Track Progress at a glance

Contractor - M/s Texmaco Rail & Engineering Limited

Sl No Item Description Unit Track Plinth Casting

Sections Track Meters Reach 4

(May 2020) Reach 2

(May 2020)

1 Scope of Work Trm 12580 17628

2 Progress for the month Trm Nil 70

3 Cumulative progress Trm 11700 5193

4 Access Handed over Trm 11700 14000

View of Track work completed at Reach-4Extn

up to Anjanapura Station