Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
1
In This Issue
——————————————–—
Land Acquisition Status & Critical Issues
Phase-2 Civil Progress at a Glance
Launching of Tunnel Boring Machine
Track Progress
E-News Letter for BMRC Website only https://english.bmrc.co.in/News/NewsSection
U Can Contact us
Email: [email protected]; [email protected] Toll-free Helpline: 1800-425-12345
Shri Durga Shanker Mishra, IAS
Secretary to GoI, Ministry of Housing & Urban Affairs, &
Chairman, Bangalore Metro Rail Corporation Limited
Shri Ajay Seth, IAS
Managing Director
Bangalore Metro Rail Corporation Limited
Address: Bangalore Metro Rail Corporation Limited
3rd Floor, BMTC Complex, K H Road, Shanthinagar,
Bengaluru - 560 027. Web: www.bmrc.co.in
May 2020 Issue 121
Jayadeva Flyover Demolition
Jayadeva Flyover demolition work was done in Two Phases. Phase-1-Banneraghatta Loop-from 15.08.2019 to
31.10.2019 and Phase-2-Main Flyover–from 20.01.2020 to 05.06.2020. A total of 1,03,272 Man hours have been
spent along with heavy machines.
2
Critical issues faced regarding Land Acquisition for Phase-2 of the Project
Reach-6 Underground Section
Langford Town Station:- Local Military Authorities (LMA) have sent the proposal for
transfer of 2137.334. sqm of land on permanent basis and 5866.569 sqm on
temporary basis to Army Head Quarters. Matter is being pursued with Defence
Authorities.
Lakkasandra Village Sy. No. 14 and 15:- The re-location of 101 encroachers at
Lakkasandra land is under consideration of Deputy Commissioner, Bangalore
Urban and Karnataka Slum Development Board.
Phase-2 Progress up to 31st May, 2020
27
45
80
76
90
60
84
96
78
65
0 20 40 60 80 100 120
REACH-6-ELEV (GOTTIGERE TO SWAGATH CROSS ROAD)
REACH-5-P-3 (BOMMANAHALLI TO R V ROAD)
REACH-5-P-2 (HOSA ROAD TO BOMMANAHALLI)
REACH-5-P1 (BOMMASANDRA TO HOSA ROAD)
REACH-4B (PUTTENAHALLI CROSS TO ANJANAPURA TOWNSHIP)
REACH-3C (HESSARAGHATTA CROSS TO BANGALORE INTERNATIONAL EXHIBITION CENTER)
REACH-2B (PATTANAGERE TO CHELLAGHATTA DEPOT)
REACH-2A (MYSURU ROAD TO PATTANAGERE)
REACH-1B (VISVESVARAYA INDUSTRIAL AREA TO WHITEFIELD)
REACH-1A (BAIYAPPANAHALLI TO VISVESVARAYA INDUSTRIAL AREA)
PHASE-2 CIVIL WORKS PROGRESS IN PERCENTAGE
3
Sl. No
Reaches
No. of properties Required
No. of properties Acquired
[As per 28(4) & 3(1)]
Handed over to Eng. Section up to
May - 2020
Balance to be Handed over to Engg. Section
Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total
1
Reach-1 Extn 38 487 525 38 479 517 38 479 517 0 8 8
Forest Land 21 0 21 0 0 0 21 0 21 0 0 0
2
Reach-2 Extn Station & Viaduct
25 99 124 25 97 122 25 97 122 0 2 2
Challaghatta Depot 10 24 34 10 24 34 10 24 34 0 0 0
3 Reach-3C Extn 3 105 108 3 105 108 3 105 108 0 0 0
4
Reach-4B Extn. 12 294 306 12 294 306 12 294 306 0 0 0
Anjanapura Depot 1 20 21 1 20 21 1 1 2 0 19 19
5
Reach-5 New Line 46 798 844 46 798 844 46 790 836 0 8 8
Hebbagodi Depot 1 57 58 1 57 58 1 57 58 0 0 0
6
Reach-6 (Elevated) 34 222 256 34 222 256 34 222 256 0 0 0
Reach - 6 (UG) 52 289 341 52 276 328 49 279 328 3 10 13
Kothnur Depot 4 64 68 4 64 68 4 64 68 0 0 0
Total 247 2459 2706 226 2436 2662 244 2412 2656 3 47 50
7 ORR Line 31 56 87 30 55 85 29 51 80 2 5 7
8 Airport line 59 179 238 59 179 238 13 12 25 46 167 213
Total 90 235 325 89 234 323 42 63 105 48 172 220
Grand Total 337 2694 3031 315 2670 2985 286 2475 2761 51 219 270
Land Acquisition Status for the month of May, 2020 of Phase-2, ORR -2A & Airport -2B Line
4
Phase– 2 Progress Photos at a glance
R-1A: Garudacharpalya Station Roof Truss erection work in progress R-1B : Whitefield Station I-Girder Erection work in progress
R-2A: Viaduct view from Jnanabharathi Station towards
Pattanagere Station R-2B: Track laying work in progress along Viaduct
R-3C: Parapet Gantry-2 Launching works in progress R-4B: Hand Rail work in Ground Floor Entrance at
Anjanapura Road Cross
5
Phase– 2 Progress Photos at a glance:
R-5-P1: Electronic City-I Station works in progress R-5-P2: Oxford Station- Grid C to E Platform Level slab
concreting completed.
R-5-P3: Sump Raft concrete completed at Ragigudda station R-6-Ele: Swagath Station – 04 Pier location P2, P3, P9 & P10 Pier Arm Erection done at Concourse Level
R-6-UG-RT1: Aerial view of works at Dairy Circle UG Station R-6-UG-RT1: Barricading works in progress at Lakkasandra Station
6
Lowering of 1st TBM cutter head
at Shivajinagar UG Station
Launching of Tunnel Boring Machine-R6-UG-RT-2
Contractor - M/s Larson & Toubro Ltd—RT-02
Sl No RT-02 Details of TBM
1 Name of the two TBM’s Avni Lavi
2 TBM Procured from China Railway Construction Heavy Industry, China
3 Launched / Lowered into the Tunnels 28th May 2020
4 Will Tunnel Between Shivajinagar & Rashtriya Military School Underground Stations
5 Length of the two Twin Tunnels 2141 Meters
6 Diameter of the Cutter Head 6.74 Meters
7 Finished inside diameter of Tunnels 5.80 Meters
7
Lowering of 2nd TBM cutter head
at Cantonment UG Station
Contractor - M/s Larson & Toubro Ltd—RT-03
Sl No RT-03 Details of TBM
1 Name of the two TBM’s Urja Vindya
2 TBM Procured from China Railway Construction Heavy Industry, China
3 Launched / Lowered into the Tunnels 28th April 2020 3rd June 2020
4 Will Tunnel Between Cantonment & Shivajinagar Underground Stations
5 Length of the two Twin Tunnels 860 Meters
6 Diameter of the Cutter Head 6.74 Meters
7 Finished inside diameter of Tunnels 5.80 Meters
Launching of Tunnel Boring Machine-R-6-UG-RT-3
8
Track Progress at a glance
Contractor - M/s Texmaco Rail & Engineering Limited
Sl No Item Description Unit Track Plinth Casting
Sections Track Meters Reach 4
(May 2020) Reach 2
(May 2020)
1 Scope of Work Trm 12580 17628
2 Progress for the month Trm Nil 70
3 Cumulative progress Trm 11700 5193
4 Access Handed over Trm 11700 14000
View of Track work completed at Reach-4Extn
up to Anjanapura Station