PROJECT MANAGEMENT OF FLY OVER CONSRTUCTION
Citation preview
1
PROJECT MANAGEMENT
• A project is an organized Endeavour which take significant amount of time to complete and are large-scale or complex enough to be recognized and so managed as separate undertakings.
• Operation manger must often organize project team to plan and control projects.
• The project team must work to tight time schedule, adhere to strict budgets, report to top management personal of the organization and be temporarily removed from their regular jobs.
PROJECT LIFE CYCLE:
• PLANNING PHASE:• Planning of sufficient for initial scheduling of
activities, budgeting of projects is done.• ORGANISATION PHASE:• In this phase the bill of material and division of the
total work in to major packages is to be accomplished.
• Personal and other resources necessary to accomplish the project are then made available for all or portion of the project’s duration through temporary assignments from other parts of the organization or subcontracting portions of the project.
• EXECUTION PHASE:• The various activities planned are completed as per
the schedule, utilizing the allotted resources.
• TERMINATION PHASE:• This is the phase during which the project is
terminated or disbanded after completion.
• The personnel who were working in the project are assigned back their regular jobs or to the other jobs in the organization or to other projects in this phase.
HIGHLIGHTS OF FLY OVER BRIDGE
• Flyover Bridge will be constructed at palroad,surat• Length of bridge 500 meters with 25 degree slope• 4 lane, each lane width 8 foot• Beam type bridge• Estimated period for completion 1* year• Each side will have foot path of 5 foot• Central lighting arrangement• Estimated cost 15-20 crore *
5
Planning Phase
• Preparation of bridge design
• Estimation of cost for it includes,
– Estimation of raw material & inventory requirement
– Storage space for raw material
– Estimation of unskilled human resource
– Estimation of skilled human resource
– Estimation of Material Handling Equipment
– Utility Equipment Requirement
6
PREPARATION OF BRIDGE DESIGN INCLUDES
– Civil Department : This department prepares blue print design of bridge structure and estimate requirement of raw material. This department includes civil engineers and architectures.
– Mechanical Department: This departments deals with checking strength of material, Load carrying capacity, stability and designing of actual structure of fly over bridge that gives stable and reliable and long life of flyover bridge. It includes mechanical engineers.
7
• Electrical department: This department is dealing with providing supporting activities such as providing power necessary for carrying out processes involved in project. It includes electrical engineers. Equipment such as motor and generators, lighting are required at site.
• Procurement Department: This department coordinate with all departments and procure all the required raw materials, equipments according to quality specified by them and provide it at right time.
8
HUMAN RESOURCE REQUIREMENT
• 5 Architectures• 5 Civil engineers• 3 Electrical and 3 Mechanical engineers• 50 Unskilled workers daily • 5 Site supervisors
9
MATERIAL REQUIREMENT ESTIMATION
• Cement • Bricks• Steel/iron rods• Stones• Sand• Tar• Metal sheets
10
APPROXIMATE DAYS REQUIRED FOR ACTIVITIES
1. Preliminary mapping survey : 2 days
2. Diverting road traffic : 2-3 days
3. Foundation of soil preparation : 10-15 days
4. Initial Procurement of material : 1 month before
5. Lead time for order : 1 day
6. Preparation of steel works : 1 day before
7. Preparation of 50 girder : 2 months before
8. Preparation of each pillar : 5-7 days
9. Total Slab time period : 2-3 months11
10. Road leveling and tar bedding : 10-20 days11. Lighting on bridge : 10-15 days 12. Footpath & parapet wall : 25-30 days13. Finishing work : 20-40 days
• Schedule meeting are arranged between supervisor, head engineers and project managers after every 20 days or completion of 10% of total work.
12
13
SCHEDULE FOR CONSTRUCTION
Project time period
2009 2010 N D j f M A M J J A S O N
Ground breaking
Design committee
Site preparation
Foundation
Pillar construction
Segment casting
Super construction
Segment eraction
Finish work
Ribbon cutting
14
SAFETY & DIVERTING TRAFFIC
15
STORAGE• We have an established central store & fabrication & maintenance
workshop near KAMRAG CIRCLE, SURAT in an area of 15787 Sq.m.
• Storage and Inventory for all equipment and spares are maintained by qualified personnel.
• It also stores raw material required for construction.• Central Store is well connected with all sites and Head Office by
Telephone, Fax, Mobile Phone, Wireless system.• It includes cranes for moving raw material, • Girders and other building blocks which fit on girders blocks.
Girder
16
MATERIAL HANDLING EQUIPMENT
REQUIREMENT
Cement mixer
Cement mixer is used at site for prepare mixer of cement, sand and Stone.
No of quantity: 5 on site
17
• We have bull dozers which are used to move heavy material, dig soil and also to remove some obstacles.
• Quantity : 4
Bull dozer
18
• Trucks are widely used to transport raw material from store to on-site location.
• No of quantity: 6
truck
19
• Roller are used for leveling the road.
• Quantity : 4
Roller
20
Crane are used to hoist or pull heavy part such as iron framework, any equipment such as welding machine etc. Quantity : 2
21
Crane
Preparation & arrangement of iron frames
22