IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate materials and equipment for the job. Choose appropriate personal protective clothing and equipment for the job. Learning Objectives

IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate

Embed Size (px)

Citation preview

Page 1: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-1

MODULE IV-PLANNING THE JOB

Plan a lead-based paint maintenance job.

Recognize an activity as either low risk or high risk.

Choose appropriate materials and equipment for the job.

Choose appropriate personal protective clothing and equipment for the job.

Learning Objectives

Page 2: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-2

LEAD JOB CHECKLIST

If you don’t know when the building was built, treat the paint as lead-based paint. If the building was built after 1978,then lead-based paint is probably not present and this is not a lead job. If the building was built before 1978, then treat the paint as lead-based paint, unless a paint inspection report says that no lead-based paint is present.

1.1. Was the building built before 1978? Yes No

Page 3: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-3

LEAD JOB CHECKLIST

2. Could this job: (Y=Yes, N=No)

Create dust that may contain lead? Disturb known or suspected lead-based paint ? Require cleanup of dust or debris that may contain lead? Disturb known or suspected lead contaminated soil?

Y NY NY NY N

Page 4: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-4

HIGH RISK =

High levels of dust

expected to be generated, or Surface and paint in poor condition, or

Greater than two (2) square feet.

LEAD JOB CHECKLIST

3. If “Yes” to any of the above, or if you don’t know the answer to any of the questions, assume you are dealing with lead-based paint, and circle the level of risk below.

LOW RISK =

Low levels of dust expected to be generated, and

Surface and paint in good condition, and

Less than two (2) square feet.

Page 5: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-5

LEAD JOB CHECKLIST

LOW RISK = • LOW RISK = • Low levels of dust Low levels of dust expected to be expected to be

generated, generated, and and • • Surface and paint in Surface and paint in good condition, and good condition, and • • Less than two (2) Less than two (2) square feet. square feet.

Page 6: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-6

LOW RISK MAINTENANCE JOBS

Repair window panes Repair doors Replace or repair door locks Repair radiator leaks Patch walls Grounds keeping Routine vacancy preparation

Page 7: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-7

LEAD JOB CHECKLIST

High Risk = • High levels of dustHigh Risk = • High levels of dust expected to be generated, or expected to be generated, or • • Surface and paint in poor Surface and paint in poor condition, or condition, or • • Greater than two (2) square Greater than two (2) square feet. feet.

Page 8: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-8

POTENTIALLY HIGH RISK REHABILITATION JOBS

Stabilize large amounts of badly deteriorated paint

Knock out walls Replace windows Replace old or worn carpet Kitchen/bath remodel Replace kitchen cabinets

Page 9: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-9

HIGH RISK MAINTENANCE JOBSBEYOND SCOPE OF TRAINING

The following high risk jobs are beyond the scope of this training: Replacing major building components Demolition Major Renovation Fire Restoration

Page 10: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-10

LEAD JOB CHECKLIST

4. Who will do the job? Personnel must be properly trained and skilled, if they will have to wear a respirator, they must be medically qualified, fit-tested, and trained.

Name ____________ Name _____________

Page 11: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-11

LEAD JOB CHECKLIST

5. 5. How will residents be notified and affected? Notification: Phone ______ Letter _____ Time_______ Date______ Work area instructions to residents Job scheduled: FROM: Time/Date ___TO: Time/ Date___ Resident asked to leave unit: FROM: Time/Date ___TO: Time/ Date___

Resident asked to move personal items? Yes No Temporary accommodations needed for resident? Yes No If “Yes” accommodation provided? Yes No If “Yes”WHERE ___________ PHONE # _______________

Page 12: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-12

LEAD JOB CHECKLIST

6. How will work be performed to minimize exposure to lead? Circle specific cards to use for this job:

Materials Card Cleanup CardsEquipment Card Carpet Removal CardPersonal Protection Card Decontamination CardWork Practices Card Quality Control CardProhibited and Unsafe Practices

Page 13: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-13

MATERIALS

All-Purpose Cleaner, or cleaner made specifically for lead

RAGS

LEADWASTE

Heavy Duty Plastic Sheeting

Tape

String Mop HeadsRags

Tack Pads

Disposable Towels

Circle Needed equipment ( Note for high risk.)

Heavy Duty Plastic Bags

Page 14: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-14

EQUIPMENT

Circle Needed equipment ( Note for high risk.)

HEPA

Spray Mister

Stapler

Scraper

Utility Knife

Broom(Wet Sweep Only)

Dust Pan

HEPA Vacuum

Mop & Bucket

Mini - Containment

Signs & Barriers

WARNING

LEAD

HAZARD

Page 15: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-15

PERSONAL PROTECTION

Circle needed protection (Note: for high risk)

ProtectiveEye Wear

Disposable Cotton Gloves

Latex/ Rubber Gloves

Page 16: IV-1 MODULE IV-PLANNING THE JOB  Plan a lead-based paint maintenance job.  Recognize an activity as either low risk or high risk.  Choose appropriate

IV-16

Disposable Full-BodyDisposable Full-BodyCoveralls/RecyclableCoveralls/RecyclableClothingClothing

RespiratorsRespirators w/HEPA Filtersw/HEPA Filters

PERSONAL PROTECTION - CONTINUED

Circle needed protection (Note: for high risk)