Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 1
ITER The way to a benign and limitless new energy source
A global collaboration has been formed to test the feasibility of fusion
Page 2
Preparations of the ITER Vacuum Vessel Construction
11 October, 201023rd IAEA FEC, Daejeon, Korea
Presented by J. S. BakPrepared by IO, F4E, INDA, KODA, RFDA and VV IPT
ITR/1-1
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 3
I. Current Design StatusI.1 Overall DescriptionI.2 Design Development since 1998I.3 Technical & Regulatory Requirements
II. Procurement StatusII.1 Procurement Sharing and DeliveryII.2 Status of the PA and Contract AwardII.3 Procurement Schedule
III. Manufacturing PreparationIII.1 R&D ActivitiesIII.2 Fabrication of Mock-ups
IV. Summary
Contents
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 4
Overall Description of the ITER Vacuum VesselA torus shaped double wall structure
• To provide high vacuum for plasma and primary radioactivity confinement boundary
• To support in-vessel components (blanket, divertor, etc)
Main vessel9 x 40 deg. Sector
In-wall shieldingVV supports(Dual hinge type)
Ports
Upper
Lower
Equatorial
Major dimensions Weight (ton)Outer diameter (m) 19.4 Main vessel 1611Height (m) 11.4 Shielding 1733Double wall thickness (m) 0.34–0.75 Ports 1781Interior surface (m2) 850 Supports 111Interior volume (m3) 1600 Total 5236
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 5
Design Development since 1998• Size reduction- Height: 14.4 m � 11.3 m- Width: 8.9 m � 6.4 m
•New flexible support housing
• Reduced No. of lower ports• Relocation of VV supports
• 3D shaped inner shell in outboard area• Design modifications for interfaces - In-vessel coil (IVC), field joint, ports,
VV supports, IWS, etc
2009 (MRD : ALT)
Self supportingblanket
Segmented blanket
IVC
1998EDA
2001EDA
2008FDR
2010MRD
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 6
Technical & Regulatory Requirements
Requirements DescriptionMaterial 316L(N)-ITER Grade with special requirementsDesign load Dead weight, coolant pressure, various electromagnetic loadsTolerance Accurate field joint fit-up and precise assembly of in-vessel componentsWeldingInspection
Full penetration welding100% volumetric NDE even at single side accessing region
Testing Baking condition: 200 oCTesting pressure: 3.72 MPa, Vacuum leak rate: < 10-8 Pa-m3/s
Code and standard RCC-MR 2007 edition (based on French Fast Breeder Reactor)
Requirements DescriptionQuality and safety SIC (Safety Important Class) components
Implementation of French safety and quality order 1984Nuclear pressure vessel
French order of nuclear pressure equipment (ESPN)Agreed Notified Body (ANB) involvement for conformity assessment
Technical requirements
Regulatory requirements
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 7
Technical Requirement: Materials304L316L(N)-IG
304B7304B4
“A”
“B”
Items DescriptionMaterial types • Main vessel: SS 316L(N)-IG
• Port: SS 316L(N)-IG, 304, 304L• VV support: steel 660, Inconel 718• In-wall shielding: 304B4, 304B7, 430
Special requirements for 316L(N)-IG
• Nitrogen control (0.06 ~ 0.08 wt.%) to keep consistent strength
• Limitation of impurities:- Co (0.05 wt.%): reduction of contact dose and gamma heating- Nb (0.01 wt.%): reduction of activated waist- Boron (0.0001 wt.%): limit He production
Main features of VV materials
Status of material supplier contractsItems KO RF IN EUPlate
TBDForging N/ABoratedsteel TBD N/A TBD N/A
660304-IG
430
“A” “B”
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 8
Regulatory RequirementsStatus of ITER VV conformity assessment by the ANB
Phases DescriptionPhase I Preliminary design assessmentPhase II Fabrication assessment at supplier’s factoryPhase III Final assembly and installation assessment at the ITER site
• According to regulatory requirement such as ESPN,the conformity of the ITER VV shall be assessed by the ANB (Agreed Notified Body).Conformity assessment procedure by the ANB
Status Detail descriptionPhase I (on going)
ANB’s approval of the preliminary design: Oct 2009Additional approval for modified reference design: Jul 2010
Additional approval for modified port & VV supports: Mar 2011
Current status
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 9
Procurement SharingEU DescriptionItems 7 Sectors of Main Vessel Total Cost 92.06 kIUA (39%)
RF DescriptionItems 18 Upper PortsTotal Cost 20.86 kIUA (9%)
KO DescriptionItems 2 Sectors of Main Vessel
17 Eq. & 9 Lower PortsTotal Cost 84.06 kIUA (36%)
IN DescriptionItems In-Wall Shields/ribsTotal Cost 37.30 kIUA (16%)
Total 234.28 kIUA8% of total In-kind
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 10
Procurement Delivery
I WS
I WS
Upper Po rt Centra l
Upper Po rt Centra l
PSE (7 EA)PSE (7 EA)
Upper P ort
NB Port PSE (2 EA)NB Port PSE (2 EA)Lower Port PSE (7 EA)Lower Port PSE (7 EA)
7 S ectors
7 S ectors
2 Se c t
ors ,
2 Se c t
ors ,
EQ &
NB,
Low
e r P o
r tEQ
& N
B, L
owe r
P or t
Upper Port Central
Upper Port Central
PSE (2 EA)
PSE (2 EA)
IWS
IWS
ITER site
DA to DADA to ITER site
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 11
DA EU KO RF IN
Item MV: 7 Sectors MV: 2 Sectors Eq. & lower ports
Upper ports In wall shieldingShield ribs
PAsignature
19 Nov 2009 19 Nov 2008 09 Jun 2009 24 Sep 2009
Contract award
08 Oct 2010
AMW Consortium (Ansaldo, Mangiarotti, Walter Tosto)
15 Jan 2010
Hyundai Heavy Industries (HHI)
09 Jun 2009
Efremov Institute
01 Sep 2010
M/s Avasarala Tech.
Status of Procurement Arrangements and Contract Awards
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 12
Procurement Schedule (Based on IPS 2019 1st Plasma)
• Integrated Project Schedule (IPS) approval: IC Extraordinary Meeting (Jul 2010)• Free issued items (in-wall shielding, port stub extension) to sector fabrication shop can become
a critical path. Schedule for interfaces is under discussion.
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
First PlasmaVV Fabrication and assembly
Vacuum Vessel (by EU)
Vacuum Vessel (by KO)
2019 2020 2021
Contract awarded Fabrication of VV Sector 5Fabrication of VV Sector 4Fabrication of VV Sector 3Fabrication of VV Sector 2
Fabrication of VV Sector 9Fabrication of VV Sector 8
Fabrication of VV Sector 7
In-wall shield by INDAPort stub extension (PSE)• Upper PSE by RF• Lower PSE by KO
Free issues items
Preparation for fabrication(material, drawing, procedure)
Procurement Arrangement (PA)Contract awarded
Sector #6 Sector #7
Fabrication of VV Sector 6Fabrication of VV Sector 1
Procurement Arrangement (PA)
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 13
R&D Activity for Manufacturing: EU (1/2)1. Welding distortion analysis• Verification: heat input experiment• Very close results between analysis and test
2. Bolted shield rib concept•Alternative method to reduce weld quantity•Assessment of both technology and costs
3. Two parts housing concept design• Background: difficult outer shell assembly• Preliminary results show feasibility
Bolts pre-stress
SYSWELD (AREVA)
Ref: ITR/P1-38
Inner shell
Outer shell
60 mmTwo parts housing
Flexible support housing
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 14
1. Local machining tool • Inner shell: thread and bore• Outer shell: welding preparation (J-groove)
R&D Activity for Manufacturing: EU (2/2)3. UT device (phased array)•Machine I for automatic outer shell tests•Machine II for circular tests
2. Auto-TIG welding machine• Automatic narrow gap welding• Verified by mock-up R&D
Machine I Machine II
LECAD & TRITECH (Slovenia)
SIMIC S.p.A.
Ref: ITR/P1-38
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 15
R&D Activity for Manufacturing: KO (1/2)1. Assessment of shell thickness reduction• Nominal design thickness of shell: 60 mm• Expected maximum thickness reduction from industrial experience < 7%.
Min.
58.8
mm2%
(1.2 m
m)
Min. 55.8 mm7%(4.2 mm)
Min. 57.6 mm4%(2.4 mm)
Thickness reduction map
Min. 55.8 mm7%(4.2t)
Thickness = 60 mm(Nominal thickness)
Thickness = 54 mm(10% reduced thickness)
Membrane plus Bending
Stress Intensity (MV)
Load condition: VDE(SD)TM + ICE II, Allowable stress = 220 MPa
PL+Pb = 177 MPa PL+Pb = 198 MPa
• The VV with 10% reduced thickness has structural margin according to the RCC-MR.• Confirmation from the ANB is expected before the start of fabrication.
Ref: ITR/P1-42
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 16
R&D Activity for Manufacturing: KO (2/2)
0o
160o
R
θθθθ
ΦΦΦΦ
R
θθθθ
ΦΦΦΦ
0o
160o
R
θθθθ
ΦΦΦΦ
R
θθθθ
ΦΦΦΦ
0.0 45.0 90.0 135.0 180.0theta, θ (o)
0.0
50.0
100.0
150.0
200.0
250.0
Radia
l Dist
ortio
n (mm
)
Before distortion controlAfter distortion control
Allowable Limit : ±15mm
Welding distortion with jigs
3. Design analysis of the VV support•From elastic & limit analyses, the structural design of the hinge support complies with the RCC-MR code.•Thermal design of the support is feasible according to heat transfer analysis.
Displacement contour Temperature contour
2. Welding distortion analysis (upper segment)•Assessments before and after distortion control by conventional jigs: out of tolerance•Additional control: Tensioning method (heating restraint jigs)
Ref: ITR/P1-42
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 17
Status of Mock-up Fabrication
VLTM
In-wall shielding(water jet cutting)
EU
RF
IN
KO KO
Upper port stubextension (partial)VVPSM
VATS
VISMVUSM
VLPM
VVPSM: VV Poloidal Sector Mock-upVATS: VV Advanced Technology Seg.VISM: VV Inboard Segment Mock-upVLTM: VV Lower-seg. Triangular-
support Mock-upVUSM: VV Upper Segment Mock-upVLPM: VV Lower Port Mock-up
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 18
Mock-up Fabrication: EU1. E-beam welding evaluation•Full scale inboard segment mock-up•Horizontal EBW•Long seam EBW to minimize distortion � 1/10 of conventional TIG welding
2. VVPSM: VV Poloidal Sector Mock-up•Full scale poloidal sector (40o) fabrication•Heavy restraint structure to minimize distortion •Successful assembly welding of inboard and upper segments � 85%: ±±±± 5 mm, 15%: ±±±±10 mm
Ref: ITR/P1-38
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 19
Mock-up Fabrication: KO (1/2)
2. VUSM: VV Upper Segment Mock-up• Narrow gap TIG welding + PT/RT/UT evaluation• Process of outer shell fit-up (flexible support housing interface)• Fixture design + analysis + distortion minimization
1. VISM: VV Inboard Segment Mock-up• Electron beam welding: Housings, manifold supports, intermodular keys• Assembly welding of divertor rail to inboard segment• Distortion minimization
3. VLPM: VV Lower Port Mock-up• Development of fabrication procedure• R150 bending without severe thickness reduction•Welding and NDE method with narrow welding space
4. VLTM: VV Lower segment Triangular support Mock-up• Copper cladding feasibility (3 mm)• Design simplification• Fabrication feasibility study
Ref: ITR/P1-42
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 20
Mock-up Fabrication: KO (2/2)
Forming die (inside)Forming die (inside) Inboard shell bendingInboard shell bending
Hole machiningHole machining
Manifold supportManifold support
Forming die (outside)Forming die (outside)
Inboard EBW (LN Laser in Daejeon)Inboard EBW (LN Laser in Daejeon)
Forming die (preForming die (pre--test)test)
Intermodular keyIntermodular key
Centering keyCentering key
Ref: ITR/P1-42
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 21
Summary1. After more than 10 years of evolution, the ITER Vacuum Vessel design was frozen in May 2010 and was subsequently approved by the ANB as the preliminary design.
2. The Procurement Arrangements with each DA involved in the VacuumVessel and the resulting industry contracts have been signed by October 2010.
3. The procurement schedule for the Vacuum Vessel is being adjusted to satisfy the requirements for First Plasma in 2019 with delivery of the first sector to IO in March 2015.
4. Preparations for manufacturing the main Vacuum Vessel are proceeding well with the DAs responsible for the main Vacuum Vessel performing R&D and building mock-ups to minimize mistakes and errors during manufacturing.
5. Nuclear codes apply in the manufacturing of the ITER Vacuum Vessel which consequently will have to go through stringent controls necessitating close cooperation between the IO, ANB, responsible DAs and industry.
23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 22
Cooperation makes work easier.