22
23 rd IAEA FEC 2010 : 10 th ~ 16 th October, Daejeon, Korea ITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 1 ITER The way to a benign and limitless new energy source A global collaboration has been formed to test the feasibility of fusion

ITER The way to a benign and limitless new energy source

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 1

ITER The way to a benign and limitless new energy source

A global collaboration has been formed to test the feasibility of fusion

Page 2: ITER The way to a benign and limitless new energy source

Page 2

Preparations of the ITER Vacuum Vessel Construction

11 October, 201023rd IAEA FEC, Daejeon, Korea

Presented by J. S. BakPrepared by IO, F4E, INDA, KODA, RFDA and VV IPT

ITR/1-1

Page 3: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 3

I. Current Design StatusI.1 Overall DescriptionI.2 Design Development since 1998I.3 Technical & Regulatory Requirements

II. Procurement StatusII.1 Procurement Sharing and DeliveryII.2 Status of the PA and Contract AwardII.3 Procurement Schedule

III. Manufacturing PreparationIII.1 R&D ActivitiesIII.2 Fabrication of Mock-ups

IV. Summary

Contents

Page 4: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 4

Overall Description of the ITER Vacuum VesselA torus shaped double wall structure

• To provide high vacuum for plasma and primary radioactivity confinement boundary

• To support in-vessel components (blanket, divertor, etc)

Main vessel9 x 40 deg. Sector

In-wall shieldingVV supports(Dual hinge type)

Ports

Upper

Lower

Equatorial

Major dimensions Weight (ton)Outer diameter (m) 19.4 Main vessel 1611Height (m) 11.4 Shielding 1733Double wall thickness (m) 0.34–0.75 Ports 1781Interior surface (m2) 850 Supports 111Interior volume (m3) 1600 Total 5236

Page 5: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 5

Design Development since 1998• Size reduction- Height: 14.4 m � 11.3 m- Width: 8.9 m � 6.4 m

•New flexible support housing

• Reduced No. of lower ports• Relocation of VV supports

• 3D shaped inner shell in outboard area• Design modifications for interfaces - In-vessel coil (IVC), field joint, ports,

VV supports, IWS, etc

2009 (MRD : ALT)

Self supportingblanket

Segmented blanket

IVC

1998EDA

2001EDA

2008FDR

2010MRD

Page 6: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 6

Technical & Regulatory Requirements

Requirements DescriptionMaterial 316L(N)-ITER Grade with special requirementsDesign load Dead weight, coolant pressure, various electromagnetic loadsTolerance Accurate field joint fit-up and precise assembly of in-vessel componentsWeldingInspection

Full penetration welding100% volumetric NDE even at single side accessing region

Testing Baking condition: 200 oCTesting pressure: 3.72 MPa, Vacuum leak rate: < 10-8 Pa-m3/s

Code and standard RCC-MR 2007 edition (based on French Fast Breeder Reactor)

Requirements DescriptionQuality and safety SIC (Safety Important Class) components

Implementation of French safety and quality order 1984Nuclear pressure vessel

French order of nuclear pressure equipment (ESPN)Agreed Notified Body (ANB) involvement for conformity assessment

Technical requirements

Regulatory requirements

Page 7: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 7

Technical Requirement: Materials304L316L(N)-IG

304B7304B4

“A”

“B”

Items DescriptionMaterial types • Main vessel: SS 316L(N)-IG

• Port: SS 316L(N)-IG, 304, 304L• VV support: steel 660, Inconel 718• In-wall shielding: 304B4, 304B7, 430

Special requirements for 316L(N)-IG

• Nitrogen control (0.06 ~ 0.08 wt.%) to keep consistent strength

• Limitation of impurities:- Co (0.05 wt.%): reduction of contact dose and gamma heating- Nb (0.01 wt.%): reduction of activated waist- Boron (0.0001 wt.%): limit He production

Main features of VV materials

Status of material supplier contractsItems KO RF IN EUPlate

TBDForging N/ABoratedsteel TBD N/A TBD N/A

660304-IG

430

“A” “B”

Page 8: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 8

Regulatory RequirementsStatus of ITER VV conformity assessment by the ANB

Phases DescriptionPhase I Preliminary design assessmentPhase II Fabrication assessment at supplier’s factoryPhase III Final assembly and installation assessment at the ITER site

• According to regulatory requirement such as ESPN,the conformity of the ITER VV shall be assessed by the ANB (Agreed Notified Body).Conformity assessment procedure by the ANB

Status Detail descriptionPhase I (on going)

ANB’s approval of the preliminary design: Oct 2009Additional approval for modified reference design: Jul 2010

Additional approval for modified port & VV supports: Mar 2011

Current status

Page 9: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 9

Procurement SharingEU DescriptionItems 7 Sectors of Main Vessel Total Cost 92.06 kIUA (39%)

RF DescriptionItems 18 Upper PortsTotal Cost 20.86 kIUA (9%)

KO DescriptionItems 2 Sectors of Main Vessel

17 Eq. & 9 Lower PortsTotal Cost 84.06 kIUA (36%)

IN DescriptionItems In-Wall Shields/ribsTotal Cost 37.30 kIUA (16%)

Total 234.28 kIUA8% of total In-kind

Page 10: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 10

Procurement Delivery

I WS

I WS

Upper Po rt Centra l

Upper Po rt Centra l

PSE (7 EA)PSE (7 EA)

Upper P ort

NB Port PSE (2 EA)NB Port PSE (2 EA)Lower Port PSE (7 EA)Lower Port PSE (7 EA)

7 S ectors

7 S ectors

2 Se c t

ors ,

2 Se c t

ors ,

EQ &

NB,

Low

e r P o

r tEQ

& N

B, L

owe r

P or t

Upper Port Central

Upper Port Central

PSE (2 EA)

PSE (2 EA)

IWS

IWS

ITER site

DA to DADA to ITER site

Page 11: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 11

DA EU KO RF IN

Item MV: 7 Sectors MV: 2 Sectors Eq. & lower ports

Upper ports In wall shieldingShield ribs

PAsignature

19 Nov 2009 19 Nov 2008 09 Jun 2009 24 Sep 2009

Contract award

08 Oct 2010

AMW Consortium (Ansaldo, Mangiarotti, Walter Tosto)

15 Jan 2010

Hyundai Heavy Industries (HHI)

09 Jun 2009

Efremov Institute

01 Sep 2010

M/s Avasarala Tech.

Status of Procurement Arrangements and Contract Awards

Page 12: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 12

Procurement Schedule (Based on IPS 2019 1st Plasma)

• Integrated Project Schedule (IPS) approval: IC Extraordinary Meeting (Jul 2010)• Free issued items (in-wall shielding, port stub extension) to sector fabrication shop can become

a critical path. Schedule for interfaces is under discussion.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

First PlasmaVV Fabrication and assembly

Vacuum Vessel (by EU)

Vacuum Vessel (by KO)

2019 2020 2021

Contract awarded Fabrication of VV Sector 5Fabrication of VV Sector 4Fabrication of VV Sector 3Fabrication of VV Sector 2

Fabrication of VV Sector 9Fabrication of VV Sector 8

Fabrication of VV Sector 7

In-wall shield by INDAPort stub extension (PSE)• Upper PSE by RF• Lower PSE by KO

Free issues items

Preparation for fabrication(material, drawing, procedure)

Procurement Arrangement (PA)Contract awarded

Sector #6 Sector #7

Fabrication of VV Sector 6Fabrication of VV Sector 1

Procurement Arrangement (PA)

Page 13: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 13

R&D Activity for Manufacturing: EU (1/2)1. Welding distortion analysis• Verification: heat input experiment• Very close results between analysis and test

2. Bolted shield rib concept•Alternative method to reduce weld quantity•Assessment of both technology and costs

3. Two parts housing concept design• Background: difficult outer shell assembly• Preliminary results show feasibility

Bolts pre-stress

SYSWELD (AREVA)

Ref: ITR/P1-38

Inner shell

Outer shell

60 mmTwo parts housing

Flexible support housing

Page 14: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 14

1. Local machining tool • Inner shell: thread and bore• Outer shell: welding preparation (J-groove)

R&D Activity for Manufacturing: EU (2/2)3. UT device (phased array)•Machine I for automatic outer shell tests•Machine II for circular tests

2. Auto-TIG welding machine• Automatic narrow gap welding• Verified by mock-up R&D

Machine I Machine II

LECAD & TRITECH (Slovenia)

SIMIC S.p.A.

Ref: ITR/P1-38

Page 15: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 15

R&D Activity for Manufacturing: KO (1/2)1. Assessment of shell thickness reduction• Nominal design thickness of shell: 60 mm• Expected maximum thickness reduction from industrial experience < 7%.

Min.

58.8

mm2%

(1.2 m

m)

Min. 55.8 mm7%(4.2 mm)

Min. 57.6 mm4%(2.4 mm)

Thickness reduction map

Min. 55.8 mm7%(4.2t)

Thickness = 60 mm(Nominal thickness)

Thickness = 54 mm(10% reduced thickness)

Membrane plus Bending

Stress Intensity (MV)

Load condition: VDE(SD)TM + ICE II, Allowable stress = 220 MPa

PL+Pb = 177 MPa PL+Pb = 198 MPa

• The VV with 10% reduced thickness has structural margin according to the RCC-MR.• Confirmation from the ANB is expected before the start of fabrication.

Ref: ITR/P1-42

Page 16: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 16

R&D Activity for Manufacturing: KO (2/2)

0o

160o

R

θθθθ

ΦΦΦΦ

R

θθθθ

ΦΦΦΦ

0o

160o

R

θθθθ

ΦΦΦΦ

R

θθθθ

ΦΦΦΦ

0.0 45.0 90.0 135.0 180.0theta, θ (o)

0.0

50.0

100.0

150.0

200.0

250.0

Radia

l Dist

ortio

n (mm

)

Before distortion controlAfter distortion control

Allowable Limit : ±15mm

Welding distortion with jigs

3. Design analysis of the VV support•From elastic & limit analyses, the structural design of the hinge support complies with the RCC-MR code.•Thermal design of the support is feasible according to heat transfer analysis.

Displacement contour Temperature contour

2. Welding distortion analysis (upper segment)•Assessments before and after distortion control by conventional jigs: out of tolerance•Additional control: Tensioning method (heating restraint jigs)

Ref: ITR/P1-42

Page 17: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 17

Status of Mock-up Fabrication

VLTM

In-wall shielding(water jet cutting)

EU

RF

IN

KO KO

Upper port stubextension (partial)VVPSM

VATS

VISMVUSM

VLPM

VVPSM: VV Poloidal Sector Mock-upVATS: VV Advanced Technology Seg.VISM: VV Inboard Segment Mock-upVLTM: VV Lower-seg. Triangular-

support Mock-upVUSM: VV Upper Segment Mock-upVLPM: VV Lower Port Mock-up

Page 18: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 18

Mock-up Fabrication: EU1. E-beam welding evaluation•Full scale inboard segment mock-up•Horizontal EBW•Long seam EBW to minimize distortion � 1/10 of conventional TIG welding

2. VVPSM: VV Poloidal Sector Mock-up•Full scale poloidal sector (40o) fabrication•Heavy restraint structure to minimize distortion •Successful assembly welding of inboard and upper segments � 85%: ±±±± 5 mm, 15%: ±±±±10 mm

Ref: ITR/P1-38

Page 19: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 19

Mock-up Fabrication: KO (1/2)

2. VUSM: VV Upper Segment Mock-up• Narrow gap TIG welding + PT/RT/UT evaluation• Process of outer shell fit-up (flexible support housing interface)• Fixture design + analysis + distortion minimization

1. VISM: VV Inboard Segment Mock-up• Electron beam welding: Housings, manifold supports, intermodular keys• Assembly welding of divertor rail to inboard segment• Distortion minimization

3. VLPM: VV Lower Port Mock-up• Development of fabrication procedure• R150 bending without severe thickness reduction•Welding and NDE method with narrow welding space

4. VLTM: VV Lower segment Triangular support Mock-up• Copper cladding feasibility (3 mm)• Design simplification• Fabrication feasibility study

Ref: ITR/P1-42

Page 20: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 20

Mock-up Fabrication: KO (2/2)

Forming die (inside)Forming die (inside) Inboard shell bendingInboard shell bending

Hole machiningHole machining

Manifold supportManifold support

Forming die (outside)Forming die (outside)

Inboard EBW (LN Laser in Daejeon)Inboard EBW (LN Laser in Daejeon)

Forming die (preForming die (pre--test)test)

Intermodular keyIntermodular key

Centering keyCentering key

Ref: ITR/P1-42

Page 21: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 21

Summary1. After more than 10 years of evolution, the ITER Vacuum Vessel design was frozen in May 2010 and was subsequently approved by the ANB as the preliminary design.

2. The Procurement Arrangements with each DA involved in the VacuumVessel and the resulting industry contracts have been signed by October 2010.

3. The procurement schedule for the Vacuum Vessel is being adjusted to satisfy the requirements for First Plasma in 2019 with delivery of the first sector to IO in March 2015.

4. Preparations for manufacturing the main Vacuum Vessel are proceeding well with the DAs responsible for the main Vacuum Vessel performing R&D and building mock-ups to minimize mistakes and errors during manufacturing.

5. Nuclear codes apply in the manufacturing of the ITER Vacuum Vessel which consequently will have to go through stringent controls necessitating close cooperation between the IO, ANB, responsible DAs and industry.

Page 22: ITER The way to a benign and limitless new energy source

23rd IAEA FEC 2010 : 10th ~ 16th October, Daejeon, KoreaITR/1-1 ITER : Preparation of the ITER Vacuum Vessel Construction Page 22

Cooperation makes work easier.