1

· Issue 2014 · No. 04 · € 24 ... · Wind turbine erection Grouting activities Offshore site investigation Jacket installation ... It’s “only” a steel pipe stuck in the

Embed Size (px)

Citation preview

The industry made a promise : a30 % lower cost for offshore wind power. With high cost reduction potential, the foundation can make a major contribution towards this goal.

www.offshorewindindustry.com · Issue 2014 · No. 04 · € 24

Vessels

Full steam ahead

access

Walk-to-work solutions

Germany

The second wave

Wind industryOffshore

Colossal foothold

Powered by

Innovative marine and offshore solutions

member of the Deme Group

GeoSea nvHaven 1025 – Scheldedijk 30

B-2070 Zwijndrecht, BelgiumT +32 3 250 53 12F +32 3 250 55 41

[email protected]/geosea

Drilling and piling of large diameter monopiles

Wind turbine erection

Grouting activities

Offshore site investigation

Jacket installation (pre-piling / post-piling)

Foundation and wind turbine logistics

Installation works with jack-up platforms

Accommodation units

EPCI contracts

Directional drilling

Foundation and wind turbine maintenance and repair services

Installation of transition pieces

Adv140515_OffshoreWindIndustry_200x280mm_final.indd 1 15/05/2014 16:11:22

3

U ntil now offshore wind power develop-

ment has concentrated on the European

North Sea and Baltic, plus a few hundred

megawatts in shallow Chinese coastal waters. But

global momentum is slowly building up.

Half way through the year, the U.S. Department

of Energy announced a US$ 150 million loan guaran-

tee to assist the financing of the Cape Wind project,

which has been lacking in forward drive for years. It

now looks as if the installation of the foundations can

finally be begun in 2015, with 130 offshore turbines ac-

tually turning in the wind off the coast of south-eastern

Massachusetts two years after that. This could be the

beginning of offshore wind power in the USA.

Japan has already been strengthening its activities

in the field of offshore wind power since the Fukushima

catastrophe in 2011. That things have not moved along

as fast as planned is mainly due to European technology

not being transferable one-to-one to Japanese condi-

tions. Japan is thus having to invest strongly in its own

research and development – but is thus also benefitting

from achieving its own value creation.

And now India is on the move. Thanks to a coastline

7,600 km long and a large demand for energy, the

potential in the country is huge and plans for the

first Indian offshore wind farm are taking shape. The

Ministry of New and Renewable Energy, public sector

companies and other partners signed a Memorandum

of Understanding in October for a 100 MW pilot

project off the northern part of the west coast (state

of Gujarat).

Just a few days later, Tulsi Tanti, Chairman of

the Indian Suzlon Group, presented plans to build a

300 MW offshore wind farm in the same state. The

announced start of construction in 2015 does sound

a bit too optimistic, however.

But still, with Suzlon as one of the largest turbine

manufacturers in the world, with masses of experience

and over 20 GW of onshore wind power, something

could indeed be brewing in India – in a positive sense.

editorial

Looking beyond the horizon

Katharina Garus

Editor

[email protected]

4 offshore Wind industry 4|2014

imprint � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � 5

project update � � � � � � � � � � � � � � � � � � 6

news � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � 8

interview

Gary Maddison, RES

OWI talked to Gary Maddison, Offshore Operations and

Maintenance Business Developer at RES-Offshore � � � 12

spotlight foundationsHeavy duty

The foundation can make a major contribution towards

the goal of 30 % lower cost for offshore wind power� � 14

Size matters

It’s “only” a steel pipe stuck in the seabed� But it is not

quite that simple – the secrets of the monopile � � � � � �16

Stability without the racket

Cost-optimized production, less costly installation,

quiet and environmentally friendly – the suction bucket

jacket seems to be the solution to many problems� � � �20

From top to bottom

Rust inside the monopile, scoured foundations or abun-

dant marine growth on the pipe: too little consideration

is given to sensor-supported foundation monitoring� �22

science & technologyDouble checking

A test rig for functional tests of 10 MW nacelles has

been installed in Lindø, Denmark � � � � � � � � � � � � � � � � � �26

GERMany

The second wave is rolling in

Phot

o: D

ong

Ener

gy

FounDaTionS

Size matters

40

16

Cover photo: TAG Energy Solutions

Phot

o: V

atte

nfal

l

5

imprint Publishing company:BVA Bielefelder Verlag GmbH & Co. KG Richard KaselowskyNiederwall 5333602 BielefeldGermany

Publisher: Prof. Dr. Bernhard von Schubert

Publishing Manager: Lutz Bandte

Editors:Dr. Volker Buddensiek (responsible), Katharina Garus, E-mail: [email protected]

Freelance authors:Jörn Iken, Detlef Koenemann, Torsten Thomas

advertising:Martin Haase, Phone: +49/5 21/59 55 90E-mail: [email protected] Fedeler, Phone: +49/5 21/59 55 81E-mail: [email protected]

Customer Service:E-mail: [email protected]

Layout: Bernd Schulte zur Wissen, Virginie BecluDSV Deutscher Sportverlag GmbH, Cologne, Germany

Print: Dierichs Druck + Media GmbH & Co. KG, Frankfurter Str. 16834121 KasselGermany

Translation:Raymond Culp, Timothy Hanes, Übersetzungsbüro Hartmann, Jeremy Heighway, Thomas Schickling, Mark Wigfall

Website: www.offshorewindindustry.com

OFFSHORE WIND INDuSTRY is an independent journal. Ma-terial in this publication may not be reproduced, reprinted or stored in any form without the publisher’s written permission.

a job with potential risks

Welding comes into play when steel struc tures are

built or repaired – even underwater � � � � � � � � � � � � � � � �28

logistics & operationsFull steam ahead

The market for service vessels is undergoing a massive

boom� Designers are showing their creative side� � � � �30

Walk-to-work solutions

From the ship onto a platform and back – actually just

a few steps, but for many service technicians still often

a courageous grab � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �34

Playing it save

Offshore converter platforms have to guarantee the

highest levels of operation safety under maritime

conditions � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � �38

politics & businessThe second wave is rolling in

In Germany, policy makers have cleared up the confu-

sion and investors are coming out of hiding again� � �40

How to do it

In a manifesto, DNV GL shows how the costs for off-

shore wind energy can be reduced by 25 % � � � � � � � � �44

events � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � 46

dates � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � 47

wab internal� � � � � � � � � � � � � � � � � � � � 48

outlook � � � � � � � � � � � � � � � � � � � � � � � � � � � � � � 50

contents

Burbo Bank Extension granted development consent from the Secretary of State for Energy and Climate Change.

At Kentish Flats a rotor blade had to be replaced as it was damaged due to lightning strikes.

Dalby Offshore’s wind farm support vessel “Dalby Esk” has started work on Gwynt y Mor, and will soon be joined by the “Dalby Tees”.

Dong Energy reported that it has delivered the first power from a next generation 6 MW turbine installed at Westermost Rough.

At London Array cable reburial is required at some locations. CWind’s vessels “Athenia” and “Endeavour” will provide further logistical support.

RWE has shelved Galloper. The company will discuss the next steps with its existing partner SSE.

Masdar will invest £ 525 million for a 35 % stake in the planned Dudgeon off-shore wind farm, alongside Norwegian partners Statoil and Statkraft.

Swire Blue Ocean will pro-vide a wind farm installation vessel to work together with Van Oord’s own wind farm transport and installation vessel “Aeolus” at Gemini.

Reef Subsea awarded a contract with Areva to provide field support for Global Tech 1. The charter is anticipated to continue until at least February 2015.

Wind industryOffshore

6 offshore Wind industry 4|2014

Project update

On September 19th, Alstom’s Haliade 150-6MW, installed at Belwind, produced its very first kWh.

Sumitomo Corporation have completed the purchase of shares in the two Belgian wind farms Belwind and Northwind from Parkwind.

Germanischer Lloyd and TÜV Süd granted a contract for the certification of Sand-bank. Swire Blue Ocean has signed a key contract with Bilfinger for the provision of an installation vessel.

Within the German Renewables Award Riffgat was honoured as “Project of the Year”.

Three months after the installation kicked off, 24 of 48 turbines at Nordsee Ost are installed.

After the weather did not play along several times, EnBW has meanwhile anchored the offshore substation for Baltic 2.

WPD has installed the first Siemens turbines at the 288 MW Butendiek offshore wind farm.

Iberdrola has launched a pile testing campaign for its Wikinger offshore wind farm following the com pletion of the site’s geotechnical investigation.

The cable connecting Anholt to the Danish grid was out of operation. Meanwhile, it is repaired.

in operation

partially in operation

under construction

planned

7

8 offshore Wind industry 4|2014

The converter platform BorWin alpha has been back

on the grid since 23 September. The world’s first

high-voltage direct current transmission system for

an offshore wind farm was shut down for months

due to technical problems. However, the grid opera-

tor TenneT has not found the error yet.

The wind farm Bard Offshore 1 is connected to the

converter, which was built by ABB AG and has a trans-

mission capacity of 400 MW. After maintenance work,

which took over three months to complete, as well as a

fire that occurred in March this year, the platform was

temporarily reconnected to the grid in June. Shortly

thereafter, it had to be shut down again due to harmon-

ic currents.

The search for the source of the electrical fault has

not yet yielded any results. The best professionals of

TenneT, Bard and ABB, as well as external specialists,

have been working on the problem. “There are many

possible causes for the error, which may lie in any of

the conceivable interactions within the entire system,

ranging from the wind turbines to the platform. As yet,

we still cannot say for certain what the cause or causal

chain for the malfunction was,” says Wilfried Breuer,

Managing Director of TenneT Offshore GmbH, remain-

ing vague.

The failure not only increases the loss of income

from Bard Offshore 1 to a three-digit million euro sum,

it also has the rest of the industry worrying. The ques-

tion arises whether this is a specific problem in the grid

connection or the transmission technology. TenneT is

now putting four further converters into trial operation.

There have been no problems with these installations

so far.

A Memorandum of Understanding (MOU) for setting

up a joint venture towards undertaking a first

demonstration offshore wind project in India has

been signed.

Involved in the MOU are the Ministry of New and

Renewable Energy, the National Institute of Wind Energy,

and a consortium of partners consisting of National

Thermal Power Corporation, Power Grid Corporation

of India Ltd, Indian Renewable Energy Development

Agency, Power Finance Corporation, Power Trading

Corporation, and Gujarat Power Corporation Ltd.

The joint venture will undertake feasibility study

based on the inputs received from pre-feasibility studies

and necessary steps for implementation of the first off-

shore demon stration wind power project along the Gu-

jarat coast. The planned project will be of about 100 MW

capacity. It has been proposed to provide subsidy for the

setting up of evacuation and transmission infrastructure

of the offshore wind power to the main land including

financial support for carrying out studies such as Wind

Resource Assessment, Environmental Impact Assess-

ment, oceanographic surveys and bathymetric studies.

Troubleshooting continues

India moves forwardPh

oto:

ABB

The offshore converter BorWin alpha

has been running again since the end

of September, but the cause of the

harmonics has not yet been found.

The ETSO 2C-503, a new directive from the European

Aviation Safety Agency (EASA), has been in effect

for helicopter pilots and passengers from 29 October

on. It mandates that life jackets that are worn in

helicopters during offshore flights must not inflate

automatically.

The directive makes sense. If a helicopter crashes

into the sea, the occupants of the sinking helicopter

cannot free themselves if the life jackets have inflated

automatically. By contrast, this feature is essential if

people fall into the sea from ships or platforms. For this

reason, operators need to adjust their thinking.

In addition to special rescue suits for transport on

boats or in helicopters, work suits are also worn, and

these are also subject to specific safety requirements.

Some suppliers, such as Skylotec or Hansen Protection,

have already reacted. They offer one certified life jacket

for helicopter flights and another for working on the

wind farm, both of which match the work suit.

This creates a new cost factor for operators because

survival suits for helicopters cost more than € 1,000

apiece, even without a life jacket or personal protec-

tive equipment. “When it comes to correct protective

equipment, operators should cooperate with qualified

suppliers. After all, the risk analysis and evacuation

plans for the wind farm also play an important role,”

says Alexander Merl, Sales Director at Skylotec.

Four offshore wind farms off the Scottish coast have

received development consent. Once completed,

the projects in the Forth and Tay region – Neart Na

Gaoithe, Inch Cape Offshore Limited, Seagreen Alpha

and Seagreen Bravo – could be capable of generating

up to 2.284 GW of electricity.

Neart Na Gaoithe will have 75 wind turbines and

a generating capacity of up to 450 MW. The Alpha and

Bravo Seagreen projects combined will consist of up to

150 wind turbines with a generating capacity as high

as 1,050 MW. The Inch Cape development will have

110 wind turbines and a generating capacity of up to

784 MW. Consent was granted under strict conditions,

including a range of measures to monitor and mitigate

any potential impact such as the effect on birds and

other environmental areas.

The Scottish Government aims to transition to a

low-carbon society that generates the equivalent of

100 % of Scotland’s gross annual electricity consump-

tion from renewable sources by 2020. Energy Minister

Fergus Ewing said: “Renewable energy is extremely

valuable to Scotland’s economy. These wind farms

alone could generate a combined gross added value of

between £ 314 million and £ 1.2 billion in Scotland over

their service life, and they could create between 2,567

and 13,612 jobs within Scotland during the construc-

tion period.”

New standard for life jackets

Scottish farms receive consent

Read more about Bladt Industries on www.bladt.dk

Bladt Industries is the market leading specialist in complex steel solutions for the offshore wind energy sector. We contribute with first class steel structures, expert knowledge and essential hands-on experience to wind energy projects all over Europe.

Harnessing

the wind

news

Dav

id P

las

- EW

EA O

FFS

HO

RE

20

13

“Cost reduction in the offshore wind industry is a global issue. Our focus at EWEA OFFSHORE 2015 will be on helping companies � nd ef� ciencies across the whole of the supply chain.” Malgosia Bartosik, Deputy CEO, EWEA

Global issues Cutting the costs of offshore wind

Born 20 years ago off the coast of Denmark, offshore wind is a young, vibrant industry and will be a central pillar of Europe’s energy mix for decades to come. With a total of 7.3 GW of offshore capacity installed in Europe and a further 4.9 GW under construction this year, signs are encouraging for Europe’s fastest-growing power sector.

But there are challenges. Offshore wind is facing a contraction that may continue into 2015 and 2016. To combat this, investors need long-term visibility and a clear post-2020 framework. The sector itself must also cut costs.

As Norbert Giese, Vice Chairman of Wind Energy Agency WAB noted, growth is crucial to cost cutting: one third of cost reduction in the next ten years depends on expansion in Germany and around the world.

Cost reduction is an obstacle that can be overcome by tackling issues in the supply chain from the cost of manufacturing turbines and substructures to optimising current installation methods.

Fortunately, � nanciers, executives and engineers will have the chance to unite and address these challenges in March 2015 when delegates convene at the European Wind Energy Association’s (EWEA) offshore conference and exhibition in Copenhagen.

As well as being able to visit companies from across Europe in 3 exhibition halls, participants will have the opportunity to meet and listen to industry leaders and respected specialists in 24 conference sessions, spanning three days from 10-12 March. The industry-leading event will look in-depth at key issues including supply chain cost reduction, operations and maintenance, turbine technology, grid development and health and safety.

Participants who register for a 3-day conference pass before 16 November can receive a discount of up to 20%. Find out more about EWEA OFFSHORE 2015 - the world’s largest offshore wind energy conference and exhibition: www.ewea.org/offshore2015

400x280-OFFHSORE2015-DP-SWW.indd 2-3 08/10/14 12:30

Dav

id P

las

- EW

EA O

FFS

HO

RE

20

13

“Cost reduction in the offshore wind industry is a global issue. Our focus at EWEA OFFSHORE 2015 will be on helping companies � nd ef� ciencies across the whole of the supply chain.” Malgosia Bartosik, Deputy CEO, EWEA

Global issues Cutting the costs of offshore wind

Born 20 years ago off the coast of Denmark, offshore wind is a young, vibrant industry and will be a central pillar of Europe’s energy mix for decades to come. With a total of 7.3 GW of offshore capacity installed in Europe and a further 4.9 GW under construction this year, signs are encouraging for Europe’s fastest-growing power sector.

But there are challenges. Offshore wind is facing a contraction that may continue into 2015 and 2016. To combat this, investors need long-term visibility and a clear post-2020 framework. The sector itself must also cut costs.

As Norbert Giese, Vice Chairman of Wind Energy Agency WAB noted, growth is crucial to cost cutting: one third of cost reduction in the next ten years depends on expansion in Germany and around the world.

Cost reduction is an obstacle that can be overcome by tackling issues in the supply chain from the cost of manufacturing turbines and substructures to optimising current installation methods.

Fortunately, � nanciers, executives and engineers will have the chance to unite and address these challenges in March 2015 when delegates convene at the European Wind Energy Association’s (EWEA) offshore conference and exhibition in Copenhagen.

As well as being able to visit companies from across Europe in 3 exhibition halls, participants will have the opportunity to meet and listen to industry leaders and respected specialists in 24 conference sessions, spanning three days from 10-12 March. The industry-leading event will look in-depth at key issues including supply chain cost reduction, operations and maintenance, turbine technology, grid development and health and safety.

Participants who register for a 3-day conference pass before 16 November can receive a discount of up to 20%. Find out more about EWEA OFFSHORE 2015 - the world’s largest offshore wind energy conference and exhibition: www.ewea.org/offshore2015

400x280-OFFHSORE2015-DP-SWW.indd 2-3 08/10/14 12:30

12 offshore Wind industry 4|2014

IntervIew | RES

OWI: Please describe the RES Group’s main area of busi-ness.Gary Maddison: The company

was founded 30 years ago as an

offshoot of the Robert McAlpine

Group in the onshore wind busi-

ness area. For this reason, the bulk

of project development that we

have carried out has been onshore

wind, particularly in the United

States. This has developed further

across into Europe. In the 1990s,

we moved into the offshore market

as well.

OWI: So your main market is Europe?Maddison: Yes, currently it is.

In the onshore business area, we

have quite a presence in the United

States, but in the offshore area it’s

predominantly Europe for us at

the moment. We are also active in

Japan, Chile and Turkey. As well as

in South Africa, now.

OWI: We are currently hav-ing a discussion in Germany

In Hamburg OwI talked to Gary Maddison, Offshore Operations & Maintenance Business Developer of the reS-Offshore.

“Cost reduction is challenging”

about tendering. The idea is to replace feed-in tariffs with a tendering process. In Britain, tenders for offshore wind parks are common practice. Could you share the lessons you’ve learned in this area? Maddison: I think the tender-

ing process has benefits as well

as drawbacks. In the UK, The

Crown Estate manages the rights

for the seabed. I think this is a

benefit because it provides some

consistency in that area. You don’t

have a disconnect, where certain

areas of the seabed are owned by

different entities, like it is in the

United States. There, the seabed is

often owned by individual states.

Another benefit is the ability to

survey and understand the seabed

conditions of the area you intend to

build a wind farm in ahead of time,

instead of at a later point in the

consent process. We have had in-

stances where the rights have been

handed back, because the company

says: “We will not be able to do

this at a reasonable price, therefore

it’s not worthwhile.” I suppose the

ideal would be if everywhere has

already been surveyed and people

can access that information before

committing to something. So I

suppose that one of the lessons

learned is that the information that

has been collated in those areas

has been opened up to the public.

OWI: So it is possible to hand the rights for a project back? That means that there are at least two reasons to say ‘no’ to the new system of tendering. The first reason is the quality. Quality may suf-fer because the cheapest offer will win, not necessarily the best one.Maddison: Yes.

OWI: The second reason is that projects may be delayed.Maddison: I think the most

important thing is that the project

is viable and able to go forward. I

think any additional work that can

13

Phot

o: R

ES

is Offshore O&M Business Developer at reS-Offshore. the reS

Group is a UK based project developer. they develop renewable

projects not only within the UK, but as well as across various

locations around the world.

Gary Maddison

be done to provide more certainty

and reduce the risk, whether it is in

Germany, the UK or anywhere else,

is going to be welcomed and must

assist in projects going forward.

OWI: In my experience, the potential of the site must be checked first and then an offer can be made. But you are saying that it is possible to make an offer first and then examine the site, is that correct?Maddison: Yes, because it costs

money at the end of the day to

generate the surveys and every-

thing else, so unless you have

some certainty, carrying out a

project may turn out to be eco-

nomically unviable.

OWI: Do you believe it’s possible to reduce the cost by, let’s say, 30 %?Maddison: I think it’s certainly

going to be challenging, but some

of the areas where the benefits will

probably be achievable are founda-

tions, design and cables as well

as an increase in turbine size. The

physical size and output from the

turbines will be greater. Thirdly,

I think there will probably be

benefits in the area of O&M strate-

gies, maintenance and access to

the wind farms. Some of the major

developers and energy companies

are also looking at the concept of

clustering wind farms around the

particular type or make of turbine.

This is going to assist in looking at

the maintenance of clusters rather

than individual parks. I think there

are some benefits and cost savings

in that.

OWI: Do you think it will be possible to develop some of the undeveloped regions in the UK, such as the North- East, with industry-quality projects?Maddison: Yes, there is still a

commitment there for those larger

projects. The idea behind those

projects was to achieve the benefits

of scale and cost reduction during

round 1, round 2 and round 3.

Larger projects are the evolution

of the development of offshore

wind to bring costs down. That has

always been the plan, and there are

certainly challenges with it being

further offshore, but the scale

makes the difference. We have

recently seen Siemens committing

to building a large factory in Hull,

for example.

OWI: The supply chain for offshore wind parks is not closed. Do you think we will see wind turbines made by a British manufacture in the future, and if so, when?Maddison: Yes, that’s a good

question. I suppose it’s always pos-

sible, but I think maybe currently

the closest we are going to get to

that is seeing existing manufac-

turers producing in the UK. Our

wish would be for the UK content

within those machines to increase,

as well as the amount of labour. At

the moment, I am not aware of any

people that are actively developing

wind turbines on a large, industrial

scale. There are quite a few major

players out there now and only a

large company would be able to

develop at the level that Siemens,

Vestas and so on have been work-

ing at. They have had a big com-

mitment for a long time, so that

would be a challenge.

The interview was conducted

by Jörn Iken.

14 offshore Wind industry 4|2014

Phot

o: V

atte

nfal

l

Heavy dutyThe industry made a promise: a 30 % lower cost for offshore wind power. With high cost reduction potential, the foundation can make a major contribution toward this goal.

tion concept is limited to flat water under 30 m deep.

This limitation is down to the dimensions of the mono-

piles, which – and this is the third problem – is increas-

ingly overtaxing manufacturing and logistics.

These issues define the requirements for alterna-

tive solutions: they have to overcome the 30 m thresh-

old, abstain from the use of pile drivers, and have

reasonable dimensions. It takes a lot of brain power

to prepare an alternative process for practical use. The

Danish energy company and world’s largest project

planner for offshore wind farms, Dong Energy, as well

as a consortium led by RWE Innogy have developed

and tested their solutions for just such a process.

several approachesThe spring of this year saw the start of a pilot project

within the framework of the Carbon Trust Offshore Wind

Accelerator (OWA), a leading global research and de-

i t has been 20 years since

the first monopile was

driven into the seabed

off the Baltic coast of

Sweden. Even today,

monopiles are the least expensive way to securely

install offshore wind turbines. And because they

require relatively little welding, monopiles are

certainly one of the fastest procedures.

It is thus much more astounding that after such

a long time and such broad experience, people are

still looking for alternatives to the pile-driven steel

pipe. There are three main factors that limit the use of

monopiles. First, there is the ramming process itself,

which damages the hearing, orientation, and balance

organs of marine mammals. Noise protection systems

currently in use are either expensive or ineffective.

Next, the general belief is that the monopile founda-

spotlight Foundations | DeVeloPmenT

15

the installation of founda-

tions is a logistical master-

work but one which is the

subject of a continuous search

for optimisation potential.

Heavy duty

spotlight

velopment programme aimed at reducing the cost of

offshore energy. The offshore wind farm developers

RWE, Dong, EnBW, E.on and Vattenfall carried out the

programme in cooperation with the offshore supplier

industry and partners, such as Bilfinger Construction.

Specifically, the project focussed on so-called vibratory

pile driving. The researchers sought an answer to the

question of how the horizontal load-bearing capacity of

vibratory driven piles compared with that of convention-

ally driven piles.

The groundbreaking ceremony at the 7,200 m2

test field near Cuxhaven, Germany took place in early

June (see OWI 3/2014, page 28).The term “vibratory

pile driving” may be deceptive for a layperson be-

cause unlike conventional pile driving the piles are

not, strictly speaking, “driven.” In a nutshell, there is

no pounding noise, and that benefits sea life. Build-

ing foundations for offshore windmills with the

vibration process is much quieter than pile driving,”

says Heinrich Schlick, an instructor at the Karlsruhe

Institute of Technology.

Low noise is also the advantage of Dong Energy’s

Suction Bucket Jacket. Anchoring an object to the sea-

bed using suction is an innovative idea – for the wind

industry, at least; the oil and gas industry has used the

technique for some 20 years (see page 20).

Whether a vibratory driven monopile or Suction

Bucket Jacket is used, the challenge is to withstand

horizontal loading from wind and waves, which a prop-

erly built monopile can handle without a problem. Can

the vibrated pilings and inverted buckets hold their

own? ”We won’t have the initial results until the end

of 2014,” says an RWE spokesperson. “Once we have

those, we can begin the approval process.” Dong is a

bit farther along. The Danish company says that is has

conducted a successful plot project. Jörn Iken

16 offshore Wind industry 4|2014

spotlight foundations | Production

Size matters

it’s “only” a steel pipe stuck in the seabed. But it is not quite that simple. oWi attempts to unravel the secrets of the monopile. Shaping and welding are the essential steps. Ph

oto:

Vat

tenf

all

h ollywood in

Rostock: in an

episode of the

German detective series “Polizeiruf

110” the TV cops investigate the

murder of the boss of an offshore

wind energy company. Pipe seg‑

ments for offshore foundations at

the premises of EEW Special Pipe

17

spotlight foundations | Production

the quality of a monopile is

largely dependent on the welding

of the individual segments.

Constructions were part of

the set for the filming of

the story. For technically

interested viewers they were

the real stars of the episode.

A lot of know‑how goes into

the pipe segments – both in the

shaping technology and in the

welding procedures.

standard products still workThe pipes used have a diameter of up

to ten metres and a wall thickness of

up to 120 mm. Apart from the logis‑

tical problems caused by these large

dimensions, the shaping technol‑

ogy required is anything other than

trivial. There are not many firms that

can do this – either the know‑how

or the equipment for such a power

act is not available. The dimensions

given above are, however, still the

exception. The specifications for

wind farms currently being built are

around one third smaller than this.

At the end of May the energy

companies Vattenfall and Stadtwerke

München signed a delivery con‑

tract with EEW for 72 monopiles

and transition pieces for the Ger‑

man offshore wind farm Sandbank.

The depth of the water at the site

is up to 34 m – the generally held

opinion is that this is right on the

limit for the use of a monopile. With

an average diameter of the steel

pipe of 6.5 m the total weight of the

ordered monopiles and transition

pieces comes to 78,000 t. For EEW

the contract has come at the right

time, securing the capacity utilisa‑

tion of the production plant until

mid 2015.

From a technical point of view

this order is the current standard.

The constructors generally use a

harder steel such as S355 and pro‑

duce the pipe sections with the

same wall thickness throughout. In

future, however, they will not get far

with this standard, say the scientists

from the Fraunhofer Institute for

Manufacturing Engineering and

Automation (IPA). The transition

to two‑figure megawatt capacities

has already been initiated by the

prototype of an 8 MW turbine; a

10 MW machine is on the drawing

board.

With our XL Monopiles of up to 10 m diameter we are ready for the future.

EEW Special Pipe Constructions GmbH [email protected]

Erndtebrücker Eisenwerk GmbH & Co. KG [email protected]

www.eew-group.comOur products for the Offshore Wind Market:Monopiles / Transition Pieces, Pipes for Jackets, Piles

Pho

to: B

alla

st N

edam

More Meters today. More poWer toMorroW.

10 m

18 offshore Wind industry 4|2014

spotlight foundations | Production

Wind turbines with a higher

performance are heavier and sweep

a larger area with their rotors.

In other words: the loads on the

foundations are increasing – and

exponentially rather than linearly.

This leads the IPA scientists to the

conclusion that the quasi‑standard

currently used by the industry will

no longer suffice: foundations for

10 MW turbines are not economi‑

cally realisable with the current

constructions and materials.

new monopiles for the industry The Fraunhofer IPA is therefore

working together with the in‑

dustry partner EEW and the TBI

Technologie‑Beratungs‑Institut

(Technology Consultancy Institute)

on the development of high‑strength

foundation structures for the off‑

shore industry (“HoGfos”). The

project comes to a close at the end

of 2014. There are already some sug‑

gestions for solutions:

• Development of a structurally

optimised foundation design adapt‑

ed to local load conditions (“tailored

tubes”). An old but useful trick: the

manufacturers of high‑quality racing

bicycles with steel frames used tubes

that were conical on the inside. The

sections of the tubes carrying a high

load had walls that were several

tenths of a millimetre thicker.

• Use of high‑strength fine‑grain

steel (S690) and new UP‑welding

technology. “Statistically seen,

S690 has a higher elastic limit and

tensile strength”, says Robert Hein,

Project Engineer at the Fraunhofer

IPA. “The notch‑rupture strength is

unfortunately independent of the

steel type, so there is no advantage

gained from high‑strength steel in

this respect.”

• Development of a manufactur‑

ing and process technology opti‑

mised construction system, a task

which has been requested by the in‑

dustry but so far neglected and, as a

side‑effect, has a high potential for

reducing costs.

The quality of a monopile

essentially depends on the welding

of the individual segments. A single

faulty welded seam can create enor‑

mous problems – not only for the

welder but also for the component.

Water collecting in defective seams

is a common starting point for cor‑

rosion. In the longer term this kind

of mistake can even cause the struc‑

tural stability of an offshore wind

turbine to become questionable.

Welding, which many people only

understand as a simple “sizzling” pro‑

cedure, actually requires extremely

careful preparation and skilled exe‑

cution. The components to be welded

must be constructed to be suitable for

this process and must be mechani‑

cally prepared. After setting up the

welding equipment, the welders pre‑

heat the components. Especially with

heavy components for the offshore

wind energy industry, pre‑heating

is essential. Without additional heat,

the components would not reach the

correct welding temperature, which

would have a negative effect on the

quality of the seams.

Even after welding, a temperature

of around 100 °C must be maintained

for two to three hours. This prevents

hydrogen embrittlement, which oc‑

curs when hydrogen collects in the

matrix of the metal. This leads to

hydrogen‑induced corrosion with

the formation of cracks. The warm‑

ing of the component also reduces

the possibility of cold cracks, which

could develop in the component

after welding.

heating before and afterwards with a new burner Linde AG has developed a process

under the name Lindoflamm that

can be used to heat the components

before and after welding. Its central

feature is a compressed air burner

that is fuelled by acetylene. Accord‑

ing to Linde, the special feature is

the high performance of the primary

flame, which, they say, guarantees

preheating in exactly the right spot.

“In comparison, for example, to pro‑

pane, acetylene burns with a very

high speed, which leads to a fast and

concentrated transfer of heat into the

metal”, explains Ronald Steusloff,

Head of Thermal Applications at

Linde, regarding the improve‑

ment over the burners previously

used. “The flame temperature that

can be achieved with an ace tylene

compressed air burner – around

2,400 °C – is significantly higher

than the temperatures reached

using other gases and compressed

air. With the Lindoflamm burner

the steel can be heated up twice

19

as quickly as with conventional

burners .”

The interesting application for

the offshore wind energy industry

is the use of the burner in the man‑

ufacture

of mono‑

piles. The weld‑

ing of the segments takes

place automatically. The burner,

which Linde developed for EEW

in Rostock, has a large number of

burner jets located on a 5 m long

tube. The distance between the

jets is only a few centime‑

tres. One of the problems in

designing the burner was to

get the same amount of gas to

come out of each of the jets. This

was necessary to ensure an even

distribution of heat at the welding

seam. In the meantime, Linde has

developed a Lindoflamm burner for

EEW for the longitudinal seams and

another for circumferential welding.

The maximum diameter is 10 m.

So Rostock remains a spectacular

address for the filming of the next

TV series.

Jörn IkenPhot

o: t

AG E

nerg

y So

lutio

ns

the secret of our success over 25 years?The wind is what drives us.

www.enova.de

enova-anz-bruemmer-200x143,5-GB.indd 1 22.10.14 09:37

20 offshore Wind industry 4|2014

Phot

o: D

ong

Ener

gy

stability without the racket

i n August, Dong

Energy installed

the first suction

bucket jacket. The new foundation

type is to be put through its paces

in the German offshore wind farm

Borkum Riffgrund 1. It could very

well become a serious rival for

monopiles in the medium and long

term, since the new technology

has a number of advantages over

Cost-optimized production, less costly installation, quiet and environmentally friendly – the suction bucket jacket seems to be the solution to many problems.

its competition. Like many other

offshore wind energy technolo-

gies, the foundation was modelled

on an original from the oil and gas

industry, where the suction bucket

technology has been successfully

deployed for about 20 years. It will

now be tested as the foundation of

an offshore wind turbine for the

first time. “We installed the first

suction bucket jacket in the off-

shore wind industry, thereby taking

another step toward bringing down

the costs for building an offshore

wind farm in future,” says Tove

Feld, Vice President and head of the

Civil, Engineering and Wind Power

Division at Dong. The floating load

out, transport and installation of

the prototype were executed by

GeoSea, while the suction process

was done by SPT Offshore.

21

Spotlight FoundationS | SuCtion buCkEt jaCkEt

a 3.6 MW Siemens turbine is installed on the suction bucket

jacket prototype in the Borkum Riffgrund 1 wind farm.

sucking instead of pile driving Costs will mostly be reduced by the

fact that it is considerably easier and

quicker to install a suction bucket

jacket than the usual method of

installing a monopile. Instead of

driving a pile into the seabed using a

hammer that weighs several tonnes,

the suction bucket sucks itself into

the ground.

To this end, it is first placed on the

seabed in one go. Pumping systems

then create a negative pressure in

the three sleeve foundations. This

makes the buckets sink slowly into

the ground until they finally reach

8 m, quite a different depth from the

25 to 30 m that a monopile needs

to be driven into the sea bottom.

The negative pressure ensures the

required stability, supplemented by

a thin layer of concrete that is cast

into the sleeve foundations at the

end of the process.

The foundation prototype is

equipped with a measuring sys-

tem that records all data during the

construction and operation phases.

Together with the Leibniz University

Hanover and the German Federal

Institute for Materials Research

and Testing, Dong will undertake

comprehensive studies and meas-

urements of the foundation. The re-

sults will then be made available to

companies that are involved in the

offshore wind industry and become

part of future approval procedures.

The German Federal Agency for

Shipping and Hydrography (BSH)

has awarded permission to deploy

the prototype in the North Sea. The

agency is especially interested in

another advantage of this method

of installation: the suction bucket

can help to finally stay within the

underwater noise protection lim-

its set for the German North Sea.

Because whether it is two-, three-

or fourfold bubble curtains, none of

the noise protection systems used

for pile driving have so far been able

to prove their practical suitability

without limitations.

hotbed for innovation“The new foundation type clearly

shows that regulatory requirements

encourage innovation – and the

industry quickly turns the require-

ments into new technologies. This

is clearly a type of cooperation that

is geared towards the future,” says

Monika Breuch-Moritz, President of

the BSH. “The new foundation is also

excellent proof of how co-operation

pays off when it comes to innovation,”

Feld adds. During develop ment,

after all, Dong was supported by the

British Carbon Trust Offshore Wind

Accelerator (OWA).

However, the suction bucket

jacket does have one problem: it is

dependent on the seabed’s properties.

Silty soil makes using suction bucket

jackets difficult, and rocky ground

Fast facts • Totalheight:57m

• Totalweight:850tonnes

• Heightanddiameterofsleeve

foundations:8meach

• Deployableinwaterdepthsof

30to60m

• Alsosuitablefor6to10MW

turbines

or larger rock inclusions make it

completely impossible. Smaller slip

rocks and boulders, on the other

hand, can be moved aside during in-

stallation, a spokesperson for Dong

says when asked about the situation.

Larger geological formations such

as adobe or limestone only exist in

deeper soil layers, where they do not

have an effect on the suction bucket

jacket.

Ultimately, the suction bucket

will boast another advantage over

conventional foundations at the end

of its lifetime. While it remains quite

unclear how monopiles can ever be

removed from the seabed, this will

not be too much of a problem with

suction buckets: when water is

pumped into the sleeve foundations,

they release themselves from the

ground and the foundation can be

completely decommissioned without

leaving any residue. However, there

is still a long way to go until this is

tested in practice for the first time.

Katharina Garus

www.offshorewindindustry.com/

suction_bucket

22 offshore Wind industry 4|2014

Rust inside the monopile, scoured foundations or abundant marine growth on the pipe: in offshore turbine monitoring, too little consideration is often given to sensor-supported foundation monitoring. Instead, divers and ROVs have been expected to perform this task – until now.

From top to bottom

Sensors cannot replace

ROVs entirely, but they

can reduce the use of this

costly equipment.

Phot

o: D

MC

SpOtlight FOundatiOnS | SenSORS

n ecessity is not

only the mother

of invention, it

also creates new markets. So far,

most operators have assumed that

foundations should be inspected by

divers and ROVs. In principle, this

works well. The downside is that

regular checks are fairly costly, time

consuming and even dangerous. On

the one hand, the piles often show

heavy growth of shells or algae

that requires a lot of effort to be

removed. On the other, divers have

already lost their lives performing

their dangerous work in offshore

wind farms.

As a result, sensors are becoming

increasingly popular. As part of the

condition monitoring system (CMS),

they are serial standard equipment

in nacelles. However, the picture is

a totally different one under the wa-

ter. “The problems at the foundation

and its inspection were simply un-

derestimated,” says Søren Granskov,

Sales Manager at Force Technology

of Denmark, adding that this is true

for not only the crumbling grouting

between pile and transition piece

and the vegetation, but also the rust

on and especially inside the pil-

ing pipe. “The demand for sensor-

monitored systems is increasing.

There are examples of severe rust

that unexpectedly developed inside

the pile. We have therefore designed

monitoring systems that are used

in the UK, Germany and Denmark,”

Granskov explains.

Rust inside a pile could be caused

by, for example, fluctuating water

levels inside the pipes or the seals

for the cable entry. One solution for

detecting the rust consists of a sys-

tem that runs along the foundation

autonomously and checks the steel’s

thickness or the condition of weld-

ing seams with ultrasound sensors.

Force has tailored a clever structural

monitoring system for continuous

surveillance. Its sensors not only

capture corrosion on the pile and in

what is called the mud zone, they

also measure tide-dependent water

levels, temperature and the oxygen

content inside the pile as well as in

the seabed surrounding the founda-

tion. The monitoring system can

thus detect at an early stage whether

rust is forming inside the structure,

among other issues. “With the help

of this system, trouble spots can

be quickly located,” Granskov

promises.

inventive engineersOther suppliers offer similar so-

lutions. Kongsberg Maritime of

Norway, for example, is also refining

a system that works autonomously.

Their hydroacoustic monitoring

system works with a sonar scanner.

It is designed to provide crucial

information on the structure and

changes in the sediment surrounding

the structure to detect scour early. “A

scan takes 30 minutes. The system is

completely waterproof and equipped

with interfaces for data evaluation,”

explains Mathias Meyer, Technical

Manager of the engineering service

team at Kongsberg.

www.skylotec.com

HIGH

• Field approved.• All fittings in sea water proofed stainless steel quality to ensure an even better off-shore suitability.• S, M-L, XL - three different sizes for perfect comfort. • high-grade salt spray tested.

OFFSHORE MASTERMore safety in corrosive environment

PROTECTION

24 offshore Wind industry 4|2014

SpOtlight FOundatiOnS | SenSORS

The GMA Group, part of the

Mistras Group from the US, already

has some experience of their own to

show. The company has equipped

36 foundations for the English

wind farm Greater Gabbard. There,

the quality of the monopiles from

China posed problems when install-

ing 140 turbines. “However, this is

just one reason for the monitoring.

The other is that the costs for sub-

sea inspections are spiralling,” says

Thomas Korzeniewski, head of the

Wind Energy Division at the GMA

Group. Mistras uses a passive sys-

tem for their sensors that captures

structure-borne sound in the foun-

dations. These frequencies create a

continuous background noise that

can be used to detect changes. In or-

der to do so, piezo sensors measure

the surface tension at regular inter-

vals. If this suddenly drops because

of cracks or small changes in the sur-

face, mechanical waves are produced

that hit the sensor. This principle

has long been used for monitoring

bridges.

It also makes sense to fit at least

some of the foundations with sensors

for an entirely different reason. Eval-

uating the data allows conclusions to

be drawn about more than just the

condition of the other, sensor-free

structures. In addition to stability

and corrosion, dimensioning is also

of interest. After all, the steel struc-

tures are calculated with considerable

safety margins. Using accelerometers

the Federal Agency for Shipping and

Hydrography (BSH) mandates that

about 25 % of all foundations need to

be checked and 10 % need to be mon-

itored by means of a suitable CMS

for foundations each year. However,

the agency does not stipulate what

exactly is to be measured and which

technology is to be used. For now, it

is sufficient to simply stick a sensor

anywhere on the structure. Without

clear measurement requirements,

there is currently quite a bit of con-

fusion on the market. “By monitor-

ing the load cycles, costs for divers or

underwater robots can be reduced,”

says Jens Krieger of Airwerk GmbH.

The company provides its own so-

lutions for foundation monitoring

which are currently in the imple-

mentation phase.

Holger Fritsch, CEO of Bachmann

Monitoring GmbH, also believes

that sensors could reduce the efforts

required underwater. His company

has started by equipping three tur-

bines in the Global Tech 1 offshore

wind farm with an extended struc-

tural monitoring system. Fritsch be-

lieves that operators should invest

in this type of systems. He explains

that “there are currently two trains

of thought. One group has a minimal

concept while the other uses more

measurement technology so that it

is not necessary to check just about

every welding seam during the peri-

odic inspections.”

Torsten Thomas

Strain gauges sensors on-site

to measure actual loads can help to

verify these assumptions. “In so do-

ing, on the one hand, we can calculate

the real loads at the foundations and

the most important node points and

compare the calculations to the origi-

nal design values. Secondly, possible

risks for towers and foundations can

be minimised, and sometimes effects

come to light that had previously

not been considered at all,” explains

Lorenz Meesenburg of P.E. Concepts

GmbH. In this context, the engineer-

ing service provider is interested not

in every welded joint, but in saving

on materials by reducing safety mar-

gins. To this end, one of the projects

that P.E. Concepts is involved in is

RWE’s Nordsee Ost, whose wind tur-

bines have been installed on jacket

foundations.

A delicate issueAlthough the sensor industry is not

lacking in inventiveness, there is so

far no standard that defines what a

CMS for foundations would be like

and what it should actually be capable

of doing. The Association of German

Engineers (VDI) is currently prepar-

ing such a standard. The title has

already been determined: Structural

monitoring and evaluation of wind

turbines and platforms, VDI 4551.

According to the association, the

standard’s aim is to respond to regu-

latory requirements and establish a

sensor-supported alternative to reg-

ular visual inspections. In Germany, Phot

o: F

orce

Tec

hnol

ogy

www.hempel.com

THORNTON BANKREALISATION: 2012COATING SYSTEM DESCRIPTION:HEMPADUR MULTI-STRENGTH 45753HEMPATHANE TOPCOAT 55214

PROTECTINGYOUR INVESTMENTSANTICORROSIVE COATINGS FOR

• Oil & Gas

• Chemical plants

• Wind turbines

• Infrastructure

• Bridges

• Power generation

Offshore wind turbine coatings according to NORSOK M501 and ISO 12944.

Hempel brings professional consulting, technical supportand efficient coating solutions tailored to your needs.

14-H-135_WIND-OFFSHORE_ENG_200x280_tisk.indd 1 20.08.14 18:15

26 offshore Wind industry 4|2014

f or 30 years, Denmark has been one of

the leading nations when it comes to

wind energy technology, and to keep

it that way, the sector sets up test centres with strong

financial backing from the government. Before now, they

focussed on Jutland’s northern tip. Siemens and Vestas

put their offshore protoypes to the test in Høvsøre and

Østerild, while test rigs in Sparkær check large rotor

blades.

A test rig for functional tests of 10 MW nacelles has been installed in Lindø, at the northern tip of Funen, a Danish island. Another one of the same size will soon be added right next to it.

Now, Lindø has joined the league of major test

centres, thanks to the location’s history. Until 2012, it

was home to Denmark’s largest shipyard, where ship-

ping company A. P. Møller Mærsk had their boxships

built – but only until the shipyard could no longer hold

its own against the competition from East Asia.

The shipyard’s closure was actually already a done

deal about six years ago. Together with Mærsk, the

Danish government went to great lengths to safeguard

science & technology | TesT rig

DoubleDoublechecking

27

science & technology

the test rig provides comprehensive functional

testing of a nacelle, including controlling the pitch

system.

Phot

os (2

): LO

rC

doubling the heartbeatThe second test rig, planned for the other half of the

hall, will only be completed in about a year. It has been

reserved for Siemens for the time being. Here, nacelles

will be tested without a hub by making bending mo-

ments impact directly on the main shaft and in so do-

ing simulate turbulence, gusts and oblique inflows. Its

design is similar to that of a test rig which is currently

installed in Bremerhaven (see OWI 04/2013, page 40).

These static and dynamic tests are a basis for Highly

Accelerated Lifetime Testing (HALT) and provide man-

ufacturers with important indicators of whether the

prototype will reach a service life of 20 to 25 years.

The first nacelle in this test rig will most likely be

from the 6 MW turbine. The next test subject is not dif-

ficult to guess now that Henrik Stiesdal, who will leave

his post as CTO of Siemens Wind Power later this year,

announced a 10 MW turbine with a rotor diameter of

210 m in Lindø. The test rig is exactly the right size for

this prototype.

Detlef Koenemann

the location, in order to save as many jobs as possible

and prevent the facilities that had just been modernised

from falling into disrepair.

The Danish offshore wind energy industry was able

to benefit from this strategy. Steel contractor Bladt

Industries, for example, set up shop in Lindø, where it

currently builds the roughly 40 metre tall jacket foun-

dations for the Baltic 2 wind farm in the Baltic Sea. A

neighbouring hall was reserved for the Lindø Offshore

Renewables Centre (LORC), with room for two nacelle

test rigs with a rated capacity of some 10 MW each. The

first rig was inaugurated on 11 September.

ideal conditionsThe site in the Lindø Industrial Park provides ideal

conditions. The nacelles, which weigh several hundred

tonnes each, can be transported by ship very close to

the hall, at which point, after removing the hall roof,

the former shipyard’s gigantic gantry crane can lift the

nacelles from above into the hall and onto the test rig.

The hall boasts enough space for two different test

rigs, each with a rated capacity of 10 MW, so that two

manufacturers can test their prototypes simultaneously.

A dividing wall prevents competitors from seeing more

than they should, as requested by the only two manu-

facturers that produce wind turbines in Denmark, Vestas

and Siemens.

The first rig, the Function Tester, is for testing na-

celles with hubs. A special flange is attached to the hub

in such a way that the pitch system is still movable. As

a result, the functional test can also check wind turbine

control with rotor blade pitch under almost real-world

conditions. An artificial medium-voltage grid can simu-

late short circuits and other short-term incidents in the

grid that affect the nacelle as a complete system.

Currently, there is a Vestas V112 on the test rig.

There is not much left to learn about this 3 MW tur-

bine, which has already been installed 1,300 times. It is

therefore ideal for running test trials of the rig, and in

a few months it will be replaced with the nacelle of a

V164, an 8 MW turbine that will make much better use

of the test rig’s features.

As all necessary infrastructure is available, lindø

industrial park offers perfect conditions for a

necelle test centre.

E lectricity and wa-

ter? This sounds

like an extreme-

ly dubious proposition, and prob-

ably reminds you more of stories

of people getting killed by dropping

a hair dryer in the bathtub than of

a working technology for offshore

structures. But that is exactly how

it works: welding underwater in-

volves a powerful electric current.

Nevertheless, the divers performing

the work are not in danger. Provided

they follow the rules, that is.

Water is vaporisedThere are four types of connection

for steel structures: adhesive bond-

ing, bolting, riveting and welding.

The number of options available

for working underwater is limited:

Adhesive bonding will not work be-

cause of the water. Riveting is out

of the question because the rivets

immediately cool down and cannot

develop the necessary shrinkage ten-

sion. That leaves bolts and welding.

Since bolted connections require

relatively complex structural and

mechanical preparation, welding

is the method of choice for quickly

connecting two pieces of steel, pro-

ducing a gas-tight connection or

applying overlay-welded material.

The process of welding under-

water is the same as dry welding on

land. Although it is possible to dry-

weld underwater, this can only be

done with considerable effort: The

spot to be welded has to be encapsu-

lated in a water-tight chamber filled

with pressurised air.

Wet welding also uses an

electric arc. Electric current arcs Phot

o: U

.S. f

eder

al g

over

nmen

t

Underwater welding is a

profession with risks. However,

equipment and materials have now

reached a high level of safety.

A job with potential risks Welding comes into

play when steel struc tures are built or

repaired. In the offshore industry, this even

happens underwater.

28 offshorE Wind industry 4|2014

Science & tecHnology | UnderWater WeldIng

electrode melt and form the weld

when they solidify.

Potential danger for diversThe risk for an accident in connection

with the electricity in the water is

higher than on land, but according

to relevant publications for safety

experts, the risk can be ‘managed’.

Insulating gloves, special weld-

ing electrodes and equipment that

are suitable for underwater use are

essential. The divers also use a lower

open circuit voltage for welding than

when on land.

However, the equipment used

is not the only factor that ensures

success during an underwater

welding dive. The primary ingre-

dients for success are the crew of

the diving platform and of course

the divers themselves. The latter

in particular have to endure high

physical and psychological pres-

sure. The German Association for

Welding and Associated Processes

(DSV) has established a working

group that deals exclusively with

the requirements of wet weld-

ing. Working Group V 4 empha-

sises: “Only a qualified training

programme that concludes with

an appropriate exam can reduce

the risks and ensure a quality of

welding that is comparable to the

quality of welding on land under

normal atmospheric conditions.”

The standards experts point out

that there is a common misconcep-

tion: “A test in accordance with EN

287-1 does not qualify a person

to perform underwater welding.”

Dual training is necessary for this:

persons interested in underwater

welding must have training as pro-

fessional divers as well as submit

the certificates for welding under

normal atmospheric conditions.

Only then can they be allowed to

train for underwater welding.

Jörn Iken

INTELLIGENT TRANSPORT FOR WIND POWER PLANTS

We don’t want to make a big show of it. But you really cannot use a run-of-the-mill trailer to transport a 60 meter long blade for a wind power plant. Especially for the challenges in this market – no matter whether you are transporting tower segments, nacelles or extremely long rotor blades – you need intelligent and powerful transport solutions.

Goldhofer offers robust and economical special systems for this purpose to ensure smooth and secure transportation. You can count on our experience and competence. We will find a solution for you.

Invest in your future. Goldhofer – The Original.

LONG OR HEAVY? NOT LONG OR HEAVY ENOUGH.

Fast factsThe German Association

for Welding and Related

Processes (DVS) offers

training courses in

accordance with the

DVS-EWF Directive 1186,

which conclude with an

exam in accordance with the

international standard DIN

EN ISO 15618 “Qualification

Testing of Welders for

Underwater Welding” or the

American standard AWS

D3.6.

between the workpiece and the

welding electrode as soon as it gets

close to the workpiece, which is

the opposite pole. The temperature

in the arc is well above 1000 °C.

Water in the vicinity is vaporised,

pro viding conditions similar to dry

welding. The workpiece and the

Phot

o: B

TM

Full steam ahead

The market for service vessels is undergoing a massive boom. Following after testing the waters, designers are now show-ing their creative side. Starting in 2015, the first big service operations vessels will steam out of the dry docks.

logistics & operations | Service veSSelS

30 offshore Wind industry 4|2014

Full steam ahead

s carcely any new market

is developing quite as

quickly as the market

for crew transfer ves­

sels, or CTV for short.

With innovative ideas, designers are opening up new

weather windows for CTV use and a lucrative market

for themselves. In a recent tally, 4C Offshore count­

ed 270 ships in operation and a further 70 expected

to launch on the European market by the end

of the year. And with every new large

wind farm project, demand

just keeps growing.

this extreme semi-sWatH is

yet another ship type designed

to be a game changer.

Leading ship brokers estimate that this figure will

climb to an additional 50 to 100 CTVs by 2016. In

addition to turbine builders and operators, purcha­

sers of these vessels include maritime service provi­

ders, who specialize in offshore wind service and are

expanding their fleets.

A paradigm shift is taking place in the designs of

these new ships. Whereas service technicians in the

initial phase still had to ride the waves aboard refitted

fishing boats or small catamarans with modest horse­

power, the new generation of CTV vessels has much

more to offer. Comfort tops the list. That goes on the

one hand for technicians, who will enjoy greater lux­

ury and thanks to the new designs will not be tossed

about by wind and waves, and on the other hand for

the well­appointed cabins of the two­ to three­person

crews on the new ships, which will enable the CTV

to stay put at a wind farm for several days at

a stretch.

Big vs. smallIn addition to creature comforts,

speed and flexibility also play a

central role. The specifications

now list significant wave heights

of up to 3 m as the upper limit.

The main ship types still dominat­

ing the market are aluminium catama­

rans up to 27 m long. They are relatively

sprightly at sea and can carry loads of up

to 20 t on deck. But hard on the heels of these

workhorses more and more SWATH ships (small

waterplane area twin hull) are coming from the ship­

yards. Although this ship type can take only a few

tons aboard and is slower, it has better seakeeping

characteristics and thus larger weather windows.

31

logistics & operations

32 offshore Wind industry 4|2014

The shipyards are developing concepts aimed at

improving the radius and range of applications of their

ships and thus stay in the market. Up to now in the ser­

vice and maintenance business, the smaller CTVs have

been regarded as playthings and poorly suited to use

as transfer vessels. This is particularly true for wind

farms that are located far out to sea with very small

weather windows for when they are accessible. However,

large ships mean high­flying charter rates and greater

costs for operators. “The radius for the new generation

of CTV is approximately 30 nautical miles,” says Erik

Schultz, the Sales Director for Damen Shipyards. Beyond

that, large service operations vessels (SOV) are needed.

“Ultimately, it’s all about how much it costs to transport

a technician. Although fast CTVs use more fuel, heli­

copters or large ships are of course far more expensive.

Right now we’re building one of these SOVs at our own

risk because we believe that the demand is coming,”

Schultz explains.

The Dutch company has already made good head­

way with this strategy in the catamaran segment. Since

introducing them in 2011, the shipyard has already

managed to sell 30 of its 26 m Twin Axe catamarans

with a top speed of 26 knots. A smaller, 20 m long ver­

sion for near­shore wind farms has already sold four

units. Damen, however, builds the ships on spec. That

not only reduces production and materials costs but also

shortens the time between order and delivery. “Offshore

wind farm construction will accelerate in Europe and

will stoke the market for CTVs,” says Schultz.

international standard lackingThe English Maritime and Coastguard Agency (MCA)

standard for work vessels of up to 24 m in length and car­

rying a maximum of 12 passengers has been the subject

of much criticism. Because the UK is the leading market,

some 50 % of all CTVs are built to the MCA standard. In

Germany, however, this code is not recognised because

German authorities do not see the safety standards as

adequate. While a number of German associations press

the International Maritime Organization for uniform

standards, the shipbuilding industry frequently builds

in accordance with the Windfarm Service Vessel (Class

1/2) classification specified by DNV GL. This guideline

has higher standards. Schultz regards as nonsense the

idea that Dutch, Scandinavian, and English shipyards are

at an advantage to German shipyards because they are

subject to lower standards. “The countries set the stand­

ards. They are the same for everyone and they make

ships flying German flags more expensive than ships

built to the MCA code, which is why the real question

is: what quality standard and what conditions are ships

built to for different markets,” says Schultz.

And that is where the foreign competition has an

edge. That goes not only for Damen but also for com­

petitors, such as South Boats IOW. The English market

leader now belongs to the Gardline Group and is usher­

ing in a new phase with its work ships. The DNV GL

certified catamaran, which is 24 m long and can travel

at 29 knots, has an increased radius and can be used at a

significant wave height of up to 3 m. The experience of

South Boats over the past five years is not all that went

into the new design, but rather practical expertise of

Seacat Services as well. The maritime service provider

ordered its own fleet of nine catamarans and three ships

from South Boats. “As the European offshore wind mar­

ket continues to evolve with a need for larger vessels

and more stringent guidelines, we are constantly look­

ing at ways in which this evolution can be incorporated

into the design of our workboats. We now have one of

the largest crew transfer vessels ready for deployment

to European offshore wind projects,” says Ian Baylis,

Managing Director, Seacat Services.

speed is trumpThe Norwegian shipyard Umoe Mandal AS is currently

building a rocket of a catamaran. The new Wave Craft

vessel is a component of a British Carbon Trust project

for new and innovative ship types. With the throttle full

out, the 26 m long catamaran can do a blazing 45 knots.

That is 83 km/h. The secret behind the new design is that

Umoe used an air­cushion concept derived from military

technology for the construction the catamaran. The air

cushion underneath both hulls does not make extreme

cWind wants to expand its fleet with

fast, lightweight sWatH ships. the

service provider landed a two-year

contract for a sWatH with Dong energy.

Phot

o: c

Truk

33

logistics & operations | Service veSSelS

speeds possible, but also holds 80 % of the weight of the

ship above the waterline. With full air cushions the cata­

maran draws just 0.7 m of water and can carry up to 4 t

of cargo. At the same time, the technology stabilises the

ship and ensures a smooth ride, even in rough weather

while enabling transfer to a turbine in significant wave

heights of 2.5 m.

The zippy vessel will go into service in March 2015

at Borkum Riffgrund 1 in the German North Sea. The

subsidiary Umoe Mandal Wind AS has concluded a char­

ter agreement with wind farm operator Dong Energy for

eight months and already has a follow­on order on its

books. “We are very happy to have a second order for

our vessel,” says Are Søreng. Now the Vice President

Sales & Marketing is hoping for an even wider response.

“Umoe Mandal is confident that the Wave Craft will be

an operations and maintenance game changer for the

offshore wind industry.”

Shipbuilders in the SWATH camp are taking a simi­

lar tack. The shipyard Danish Yachts is a prime example.

It has already built its fifth carbon­fibre SWATH vessel

and reduced its weight by 15 % over the original design.

The Odfjell Wind AS shipping line is purchasing the

24 m long ships to expand its SWATH fleet to eight

vessels and charter them to wind farm operators. “We

are pushing the boundaries of design, innovation, and

advancing with carbon composite production techniques

to improve safety standards of crew and passengers,”

says Patrik von Sydow, CEO of Danish Yachts.

CWind also wants a piece of the pie. The English

service provider has a fleet of 20 service ships with

carbon­fibre composite hulls. All of its boats are manu­

factured by the subsidiary CTruk. Previously, however,

CWind had only two SWATHs in its fleet. “Due to their

better sea handling characteristics, we plan to use these

boats more in the future and we’ll order more SWATHs

from CTruk,” says Petra Ernst­Gutierrez, the Marketing

Manager for CWind.

taking it up a notchThe SOVs are in another league than CTVs. The Danish

shipping line Esvagt is currently having two of these

ships built in Turkey. The 84 m long ships will be com­

missioned in 2015 and 2016 and chartered by Siemens.

One ship will be permanently assigned to the Baltic 2

wind farm. The other ship is at the heart of the main­

tenance concept for the two Vattenfall wind farms,

Sandbank and Dan Tysk.

These ships are a first for the offshore wind industry.

In addition to ample comfort for the crew and 30 service

technicians, the ship not only has a DP II system, it

also serves as a floating workshop and spare parts ware­

house. Both ships will be equipped with Ampelmann

systems for personnel transfer to turbines, a helipad,

and smaller auxiliary boats. “It is a new concept to in­

crease access to wind turbines in neighbouring wind

farms,” says Gunnar Groebler, Head of the Renewables

Business Unit at Vattenfall. The SOV will be stationed

continuously between the two wind farms.

Other players are also working on new ships. The

shipbuilder Fassmer, for instance, has continued devel­

opment on proven designs for offshore wind energy.

One example is the 34 m long CTV Seakat, in which

the shipyard has combined the benefits of catamarans

and SWATHs in a new ship type. “That has to do with

the speed and load­carrying capacity, among other

things. This variant can carry two standard containers

on board and has an additional four cabins for the crew,”

says Thorsten Sass of Fassmer. Another ripe design is

a 68 m long SOV with DP II which can accommodate

40 people. The vessel is comfortably appointed with a

recreation area, complete with sauna, cinema, and work­

out rooms. And the design has other useful features. “It

will have two tender boats, a transfer system of our own

design, as well as a helipad, and a large working deck.

There is huge interest for both concepts on the market,”

says Sass. Torsten Thomas

Workboats in actionFor the offshore conference Windforce 2015

in Bremerhaven, WAB is once again planning a

road show for workboats from 9 to 11 June. Last

year a number of companies took advantage of

the opportunity to present their ships to a broad

conference audience with viewings and test runs.

Those who want to be part of next year’s exhibit

should contact project head Steffen Schleicher.

E-mail: [email protected],

Phone: +49 (0)471 39177 14.

34 offshore Wind industry 4|2014

Upon large ships with DP systems

the Ampelmann is a practical thing.

Phot

o: J

umbo

Mar

ine

Walk-to-work solutions

From the ship onto a platform and back – actually just a few steps, but for many service technicians still often a courageous grab to catch the railings of the boat landing. Special access systems have failed to gain popularity to date – for a variety of reasons.

benefit,” says Martin Bech, Sales Manager at Fred Olsen

Windcarrier. The video instead shows that considerable

thought has been invested in the development of new

fender systems. “They are hollow and possess a crash

zone to keep the pressure of the vessel against the foun-

dations within a permissible range. At the same time,

the fenders give a better hold against the boat landing

and in that way minimise the vertical movement of the

vessel,” Bech explains.

Puzzling over new solutionsTo ensure that this remains so, scientific expertise is

called for. After all, the fenders also wear rather quickly

in frequent use. And that can tear a significant hole in

the operator’s pocket. “We test new fenders and materi-

als for manufacturers, so that they can optimise their

systems,” says Thomas Rung from the Institute for Fluid

Dynamics and Ship Theory at Hamburg University of

Technology. One important question, as he explains,

concerns “the extent of the frictional force arising from

the pressure and the vertical movement of the vessel,

and up to which wave height the fender provides for

reliable contact without slipping.” The results are to flow

into a project of the UK Carbon Trust (“Offshore Wind

t here is plenty of talk

going on about Offshore

Access Systems (OAS)

to facilitate transfers

between service vessels

and a wind turbine. But despite a variety of prototypes,

functioning systems and even more concept ideas, it is

seldom that such systems are actually to be found at

the bows of the transfer vessels. “The demand is still

very limited. Most systems are either error-prone,

too expensive or simply too heavy for smaller trans-

fer vessels,” says Jan Zander, Chartering Manager at

WindFarmBase, to name just three of the reasons.

A further answer is provided by a very informative

video from maritime service providers Fred Olsen, who

tested an OAS on its vessels on behalf of customers.

The short film shows a Windcarrier vessel which, de-

spite the prevailing high seas, nestles almost tenderly

against the boat landing and quickly reduces the vertical

movement to a more than tolerable extent. “We took

vessels with and without OAS out to a wind farm under

identical conditions. Our conclusion was that there is

no need for an additional system, because it makes no

real difference to the transfer and thus offers no added

35

logistics & oPerAtions | AcceSS SySteMS

36 offshore Wind industry 4|2014

Accelerator”), whose foremost objectives include the de-

velopment of new access systems and means to reduce

costs for the new far-offshore wind projects.

An industrially oriented jury has identified two new

concepts as particularly worthy of further support. One

of these is the Turbine Access System (TAS) from BMT

Nigel Gee and Houlder, which has already been proven

in practical use at two wind farms, where wave heights

of 2.5 metres could compensated for a vessel 28 metres

in length. The concept basically comprises an extend-

able gangway mounted at the bows and three hydraulic

cylinders to compensate the roll, pitch and heave mo-

tions of the vessel. To this end, a Motion Reference Unit

measures the real vessel movement and passes the cor-

responding data to a central controller. A further test was

conducted at the Thanet wind farm in the summer. This

time, the TAS was mounted on an 18-metre catamaran

from CWind. “The system achieved good compensation

of the vertical movement and is simply a top solution,”

says CWind Fleet Manager Lee Child in praise of the

engineers. Nevertheless, he can see two hairs in the

soup: “Firstly the price, and then the weight.”

Lots of ideas, but only few customersPerhaps he will soon be able to try out the more favour-

ably priced solution of the second competition winner,

the Autobrow personnel transfer system from Otso and

Ad Hoc Marine Designs, which is expected to cost only

around £ 250,000. That, at least, is the price target of

Otso Director Mark Warren. And it is at the same time

why the designers are concentrating their attention

on essential necessities. Their system will weigh only

around one tonne, and is to be brought aboard packed in

a mobile container. That serves to maximise flexibility.

According to Otso, it only takes 10 minutes to connect

the ready-to-use system to the on-board hydraulics.

From the technical point of view, it consists similar-

ly of a gangway, but only two hydraulic cylinders. They

serve to compensate exclusively the vertical motions dur-

ing transfer. “Everything else is too expensive, too heavy

and very complex in its practical handling. If you want to

MaXccess is one of many systems for smaller ships

that were tested by siemens.

Perhaps a new star on our horizon. the first tests

with tAs in British windparks were conducted

without a hitch.

Phot

o: S

iem

ens

Phot

o: H

ould

er

37

logistics & oPerAtions | AcceSS SySteMS

accommodate for absolutely all motions, you should per-

haps look at the system from Momac,” as Warren recently

mentioned in an interview for Ship & Boat International.

It seems that quite a few operators took up that re-

commendation, though without actually opening their

wallets. The Momac system is to date the only fully

functional electrical system. The heart of the system is

an industrial robot which compensates all movements

of the vessel in real time and fully automates the per-

sonnel transfer by basket. The Mots 500 for service ves-

sels weighs 3.4 t and offers a reach of 3.5 m in front

of the bows. A larger variant with gangway for DP ves-

sels achieves a reach of 5 m and weighs 5.7 t. Easily

€ 1 million was spent on development of the prototype.

“There is no shortage of interest being shown in the

different access systems, but the market is not prepared

to actually pay for the available solutions,” says Momac

Managing Director Stefan Leske. That has also led to a

change of approach. “We are happy to take on the devel-

opment risk, but not that for marketing. Consequently,

potential customers must provide a suitable vessel on

which are system can be tested,” he says.

interest and experienceThomas Boekholt is similarly unable to complain about a

lack of interest. As Head of R&D of the Fassmer Group, he

likewise favours an electrical system, and already has the

design for a Smart Access System (SAS) with an output

rating of 40 kW in the drawer. “In contrast to a hydrau-

lic system, an electrical solution delivers its full power

immediately,” he says. The SAS is again based around a

gangway, and uses three motors to compensate the ves-

sel motions. “The gangway, however, is not extendable.

Instead, we adjust the system on board so that it is posi-

tioned correctly relative to the boat landing, and no longer

dock directly to the structure. Our solution can also be

mounted on smaller vessels.” That is by all means an im-

portant point, because many captains are loathe to place

their trust in the hydraulic grippers which must hug their

vessel to the boat landing in all weathers and seas.

The only manufacturer to record any real success

so far is Ampelmann Operations from the Netherlands.

Rental

Pronomar

Pronomar

Prohold

Some 35 Ampelmann systems are already in use and

have together clocked up over 800,000 safe transfers.

In most cases, this refers to crew transfers from large

DP II vessels, because the system with its six cylinders

and a 20 to 25 metre long gangway is already quite

large and heavy in its basic version. In return, however,

the technology offers a luxurious “walk to work”, as it

compensates significant wave heights up to 3 metres

with absolute ease.

The only catch is that these systems cannot be

purchased, but only rented for a hefty fee. According to

information from the market, a six-figure sum is due for

a year’s use. On the bottom line, that is quite an attrac-

tive business model, but one which above all the gas and

oil industries are willing and able to afford.

Torsten Thomas

38 offshore Wind industry 4|2014

Phot

os (3

): Si

emen

s

Playing it safeOffshore converter platforms have to guarantee the highest levels of operation safety under maritime conditions. Accordingly powerful fire-detection and fire-extinguishing systems play a key role here.

f our huge wind

farm clusters are

currently under

construction off the German North

Sea coast: BorWin (off Borkum),

DolWin (near Dollart), HelWin (off

Helgoland) and SylWin (off Sylt).

All have one thing in common; high

voltage direct current transmission

lines (HVDC) are used. The conver-

sion of the three-phase alternating

current generated by the wind tur-

bines to direct current takes place

at sea on huge offshore converter

platforms. Currently, nine such

platforms are being constructed in

the North Sea for the German-Dutch

grid operator TenneT.

extreme conditionsThe extreme surrounding condi-

tions, with damp and salty air, call

for special solutions. The sea air

is kept away from the sensitive

equipment by a complicated air-

conditioning and ventilation system,

for example. But offshore platforms

also pose high and far from regular

challenges when it comes to avail-

ability and safety; mostly unmanned,

they run around the clock far off

the coast. This means that all the

systems must have full redundancy,

require low maintenance, and be re-

mote controlled. At the same time,

dangers and interruptions to opera-

tion must be reliably ruled out. Fire

prevention measures are of a high

importance here.

Siemens is supporting the trans-

mission grid operator TenneT as a

general contractor in five projects

and apart from supplying the HVDC

technology it is also providing build-

ing and safety technology solutions.

“For every type of environment re-

quiring protection there is a special

fire-protection and fire-extinguish-

ing concept, which has been jointly

logistics & operations | Fire PrOtectiOn

in cases of fire, gas, foam,

sprinkler and deluge extin ­

guishing systems are automati­

cally activated. the extinguishing

system has in­built redundancy

with a reserve battery.

39

spotlight | titel GeSchichte

The two high-power transform-

ers are a further sensitive area with

a high risk of causing a fire. Siemens

has implemented a multi-step fire

protection and extinguishing con-

cept for this. “It is important to

choose suitable extinguishing sys-

tems. Depending on the site, a foam

extinguishing system may or may

not be implemented, for example.

To put out electrically caused fires

– the greatest risk on an offshore

converter platform – gas extinguish-

ing systems can be used,” explains

Schütz.

The various fire detectors thus

control different fire-extinguishing

systems depending on the type

of fire, and put the fire out using

inert gas or foam depending on the

requirements. Not only should the

fire be optimally dealt with, but

the rest of the platform should be

optimally protected too.

Nico Strüfing

nico strüfing is

overall project Man­

ager for offshore

converter platforms

at siemens Build­

ing technologies

Division.

right fire protection, the weather

and environmental conditions and

their effects on the technology

must be taken into consideration,

so that false alarms can be kept to

an absolute minimum on the mostly

unmanned platforms, he adds.

On SylWin alpha smoke detec-

tors, multi-sensor detectors, gas

detectors, aspirating smoke detec-

tors, plus infrared and ultraviolet

flame detectors thus monitor the

entire platform for all conceivable

causes of fires. In the case of a fire,

a comprehensive range of gas, foam,

sprinkler and deluge fire-extinguish-

ing systems are automatically acti-

vated. Video monitoring and access

controls complement the security

system. All the data is visualised and

sent to the control centre onshore

for remote control and maintenance.

From there, cameras can be zoomed

in, for example, or pumps control-

led for fire extinguishing. The ex-

tinguishing system has redundancy

built in with a reserve battery and

can also be reset remotely.

focussing on the transformer system The transformer units in the convert-

er halls, where AC is converted to DC,

make up a particularly sensitive area.

Infrared and ultraviolet flame detec-

tors can identify arc faults and switch

off the converter before a fire or more

serious damage occurs. Additionally,

an access control system makes sure

that nobody may be present while

the system is running.

19 fire detection centres cover all the

fire­fighting areas and have networked

redundancy with each other in

accordance with norm en­54.

designed by the operators, insurance

companies, the responsible authori-

ties and the fire brigade,” says Ralf

Jock, Senior Consultant Sales and

Marketing at the Siemens Build-

ing Technologies Division. “Among

other things, the expected dangers

and fire risks were analysed for this.

Protection targets and suitable fire-

protection and fire-extinguishing

systems were derived from this

for each area,” adds his colleague

Joachim Schütz, Senior Consultant

Strategic Marketing.

sylWin alpha is setting new standardsOne of the largest offshore converter

platforms constructed by Siemens to

date was put up at the wind farm

site SylWin. The SylWin alpha plat-

form, which with its cranes and ex-

tensions is 67 m high, 56 m wide

and 83 m long, was manufactured at

the Rostock-Warnemünde shipyard

by Nordic Yards. SylWin alpha sets

new standards not only in terms of

its dimensions, but also in its safety

and building technology. According

to Siemens the concept implement-

ed there is the most comprehensive

of its type so far. By using a combi-

nation of different technologies and

systems, the greatest possible plat-

form availability is to be achieved.

“For the early detection of smoke

we use optical smoke detectors and

for the quick detection of heat, rapid

temperature rises and smoke we

use so-called multi-sensor detec-

tors,” says Jock. When choosing the

40 offshore Wind industry 4|2014

Dong Energy has

confidence in the

energy turnaround

and has acquired a

number of projects.

Construction is under

way on the first wind

farm Riffgrund.

the second wave is rolling inFor a long time, the German offshore market was considered an important anchor for the industry. Then, political decisions spooked international financiers and burned a big hole in the value chain. Policy makers have now cleared up the confusion and investors are coming out of hiding again.

Phot

o: D

ong

Ener

gy

politiCs & businEss | GErmany

41

i nvestors no longer trust

German politics. During

the past three years, hopes

were built up and then

dashed by abrupt changes

in direction by the government in Berlin. In the midst

of the discussion about the rising cost of electricity

caused by the development of renewable energy, which

overshadowed everything else, the offshore wind in-

dustry was trampled underfoot. The debates about sig-

nificantly delayed grid connections and liability issues

for the transmission system operators, which remained

unresolved for a long time, were equally damaging.

For this reason, investors decided to wait and see

whether the promises that the new German government

was making verbally could also be found in writing in the

new EEG directive, which has been in effect since August.

It is true that the new EEG has reduced expansion tar-

gets for offshore wind. However, policymakers have now

provided the framework that everyone was waiting for.

Current remuneration rates will remain valid in an almost

unchanged state until 2019. Payment will either come in

the form of an increased remuneration of 19.4 €-ct./kWh

over eight years, which already includes a bonus for the

mandatory direct marketing of the electricity generated,

or as a basic remuneration. This version provides for

15.4 €-ct./kWh to be paid over a period of 12 years. How-

ever, the industry did have to swallow one bitter pill: Re-

muneration for wind farms that are connected to the grid

after 2018 will decrease by between 0.5 and 1 €-ct./kWh.

This explains why investors are in a hurry to get back

in on the action. „Together with Vattenfall, we will use this

framework immediately to begin building the offshore

wind farm Sandbank in 2015,“ says Florian Bieberbach,

Chairman of Management at Stadtwerke München.

The two partners will be channelling investments of

€ 1.5 billion into a new German project after the DanTysk

wind farm project.

There have also been other positive reports

concerning new investment decisions since September.

The financially stricken company RWE AG is apparently

quite happy with its role as a junior partner in its own

project Nordsee One and has transferred an 85 % stake

in the 1,000 MW project to Northland Power. Construc-

tion on the first section, which will have a capacity of

332 MW, is scheduled to start in 2016 and will cost

€ 1.2 billion, most of which will be shouldered by the

Canadian energy provider.

hotly-traded and caught out in the coldThe deal was mediated by the international law firm CMS

Hasche Sigle. The firm also provides consulting services

to the British Laidlaw Capital Group, which acquired the

remnants of the failed offshore pioneer Bard. It already

owns the rights to the project Deutsche Bucht and also

purchased the project Veja Mate shortly after the new EEG

came into effect. „Now that we have reliable framework

conditions, the second wave is rolling in. This is a very pos-

itive development, but it cannot hide the fact that new fi-

nancial decisions were postponed for a period of more than

two years due to political uncertainties. This is becoming

a problem for suppliers and manufacturers,“ says Knud

Rehfeldt, Director of the Offshore Wind Energy Foundation

and Managing Director of Deutsche WindGuard.

His company regularly provides statistics on the

expansion of wind energy. The situation looks good for

the first phase of the German offshore projects. Currently,

there are four wind farms with 628 MW connected to the

grid, a further seven projects with 3,224 MW are under

construction, and two finished wind farms with 830 MW

are waiting for a grid connection. If all goes well, then

there should be a capacity of at least 1,000 MW connected

to the grid by the end of the year, and a further 1,500 MW

in 2015. WindGuard has calculated that there are currently

199 finished turbines sitting in the North Sea without a

grid connection and that 315 foundations were driven into

the seabed by mid-2014.

This means that the industry will most likely be able to

achieve the politically-adjusted goal of 6,500 MW by 2020.

After that, an additional annual capacity of 800 MW will be

constructed to achieve a nominal power of 15 GW by 2030.

This is only half as much as the previous target. „Of course,

the new EEG has positive effects that we are already seeing

politics & business

42 offshore Wind industry 4|2014

now. But the industry is not getting the orders it needs and

the lower goals do not exactly inspire mental images of

building up or restarting an industry,“ says Ronny Meyer,

Managing Director of the industry network WAB.

no industrial policy in sightHe has a point. The hole created by policymakers will run

its course through the entire value chain and leave its

traces. The dismissal of temporary workers and perma-

nent employees working short-time are some of the tan-

gible effects we are already seeing. Lower targets are not

necessarily the right medicine in this situation. „Reducing

the goals is not sustainable, especially since the energy is

definitely needed and Germany is an important market. In

order to reduce costs through industrialisation, we need

volume,“ Michael Hannibal says. This statement by the

CEO of Siemens Windpower hits two nails squarely on

the head with one blow. Siemens would have been quite

willing to build a factory in Germany if clear industrial

policy had pointed in this direction, as it does in France.

Political pressure on major players such as Siemens

is also growing in the UK because the country hardly

benefits at all from the enormous value chain. „Instead,

Siemens is building new factories in England to fulfil the

local content requirements,“ Jens Eckhoff, President of

the Offshore Foundation, complains. And from the per-

spective of the world market leader, this is only logical.

„There is no significant volume left over for new produc-

tion sites in Germany because we already have over half

of the objectives envisaged by 2020 in our order books,“

says Bernd Eilitz, spokesman for Siemens.

An EU-compliant free market economy is the status

quo in Germany, and the German value chain will have

to restructure itself in order to benefit from the next ex-

pansion wave. Government agencies are currently in the

process of meticulously preparing that new expansion

wave. The German Federal Maritime and Hydrographic

Agency (BSH) has now issued a spatial offshore grid plan,

which reserves the cabling routes in the North and Baltic

Seas, as well as a grid development plan. For this, the

transmission system operators consult with the Federal

Grid Agency and determine which wind farms in which

offshore wind cluster will be the next to be connected

to the grid.

The Federal Grid Agency initiated a procurement

procedure in October for the last 1,722 MW of connec-

tion capacity available up through 2018. This remainder

is in high demand because lucrative funding conditions

still apply. If there is overbooking in one of the clusters,

then the capacity will be auctioned in a second process.

In order to achieve the objective of 6.5 GW by 2020 at all,

the Federal Grid Agency has approval to toss connection

capacity of 7.7 GW onto the market as a buffer.

Better late than neverThis veneer of order and planned economy comes at a

late point in time. The grid operator TenneT, which is

responsible for the North Sea, is already complaining

about a huge 3 GW hole and will not commission any

new converters during the next two years. These 3 GW

are the gap between grid connections that have already

been commissioned and offshore wind farms that are ready

to be built: Financing for many approved wind farms was

delayed due to the controversies surrounding the EEG.

One example is the HVDC converter BorWin gamma

with 900 MW installed capacity, which has already been

commissioned. The only wind farm connected to it is

Strabag SE‘s Albatros. Originally, the construction compa-

ny intended to test ten gravity foundations there as well as

build a factory in Cuxhaven. Even though Strabag threw in

the towel in 2013, it still holds the rights to the project.

And those rights might now be worth something again.

„The legislature has now paved the way for investment

certainty for offshore wind farms. Next year will show

whether this is sufficient to close the existing gap between

grid connection capacity and wind turbines,“ says Wilfried

Breuer, Managing Director for the offshore business area

at TenneT.

Torsten Thomas

leaving the port fully loaded: RWE innogy reached

the halfway mark in mid-october and has completed

the installation of the first 24 wind turbines.

Phot

o: r

WE

Inno

gy

On a firm

footing

vessels

Jack of all

trades

education

One goal,

many paths

turbines

All nicely

shared out

The offshore wind industry needs a

solid foundation. The sector has made

great strides in technology, but policy

is struggling to keep up.

www.offshore-wind-industry.com · Issue 2013 · No. 01 · € 24

Wind industry

OffshorePowered by

C

M

Y

CM

MY

CY

CMY

K

Offshore_A

NZ_200x280

_ok.pdf

2 14.08.

12 11:33

On a firm

footingThe offshore wind industry needs a

solid foundation. The sector has made

great strides in technology, but policy

is struggling to keep up.

www.offshore-wind-industry.com · Issue 2013 · No. 01 · € 24

Wind industry

Offshore

Full commitment for maximum availability

Ports

Cooperation and competition

Blades

Prevention matters

Service & maintenance in offshore wind farms demands

skilled hands and personal commitment. Solid HSE

concepts and quality equipment ensure maximum safety.

www.offshore-wind-industry.com · Issue 2013 · No. 02 · € 24

Wind industryOffshorePowered by

Politics

Not without offshore wind

Why not contact us?

Together we will find new ways!

[email protected]

www.weserwind.de

... stands for innovative solutions in the field of

wind energy and, through such solutions, we

service a future-oriented market in Germany.

At three locations – two in Bremerhaven and one

in Georgsmarienhütte – the company produces

structures used as offshore foundations for wind

turbines that meet the highest safety and durability

standards. WeserWind is playing an important role

in the construction of numerous wind farms in the

North and Baltic Seas and is the first company in

the world to produce foundation structures serially

to a fixed schedule.

Our portfolio of services also includes the building

of offshore substations as well as

the erection of complete wind metmasts.

SyNerGy fOr eNerGy –

ThAT’S Our mOTTO.

WeserWind GmbH …

GMH_WeserWind_ANZ_EN_210x297_11.05.indd 1

15.05.12 08:09

You go off shore, we go inside. OWI – your inside look to the European off shore wind industry.

Subscribe to OFFSHORE WIND INDUSTRY…

… and get a LorryBag* LorryBags are made from truck tarpaulins. They are tough, practical and trendy.*Notebook-bag inside

→ only for subscribers

Politics

Not without → 10% discount for

Prevention Not without Not without

vessels

Jack of all

trades

vessels

Jack of all

trades

Cooperation and competition

Prevention matters offshore windoffshore wind

O r i g i n a l

→ 4 Issues/Year→ OFFSHORE WIND INDUSTRY

→ EUR 86.40 1-year domestic rate

→ EUR 94.40 1-year international rate

→ Send your subscription as fax to: +49 (0)221/2587-249:

→ Company

→ Name

→ Address

→ Country

→ Email

→ Signature

Subscribe here or at www.off shorewindindustry.com/magazine/subscribe

→ the English-language trade magazine

Customer Service: Phone +49 / 221 / 25 87 248, E-mail: [email protected]

WIND INDUSTRYOff shore

owi_

1401

_JA_

owi

44 offshore Wind industry 4|2014

politics & business | Cost reduCtion

Many regard cost savings of

40 % as the necessary target

in order to make offshore wind

energy competitive.

how to do itin a manifesto, dnV GL shows how the costs for offshore wind energy can be reduced by 25 %. “doing it right”, “doing it better” and “doing it differently” are the strategies.

Gra

phic

: dn

V G

LAndreas Schröter, Executive Vice

President – Renewables Certification

at DNV GL says that the complex of

measures “Doing it right” can con-

tribute cost savings of 7 % through

the definition of standards for in-

stallation and operation. “Doing it

better” describes, a savings potential

of a further 6 %, for example through

optimised monopiles. Finally, he

sees cost-saving potential of another

12 % under the heading “Doing it

differently”. Here, he names floating

turbines as an example.

The cost-reduction strate-

gies outlined in the manifesto are

categorised into three basic types:

“Doing it right” (by mitigating risk

and increasing certainty), “Doing it

better” (by improving the efficiency

of existing processes) and “Doing

it differently” (by innovating for

the future). According to DNV GL,

working with industry partners, the

actions the company commits itself

to in the manifesto have the poten-

tial to achieve reductions in the cost

of energy of up to 25 %.

i ndustry action on

reducing costs is

widely regarded as

essential to secure the future of off-

shore wind energy. “Offshore Wind:

A Manifesto for Cost Reduction” pre-

sented by DNV GL at WindEnergy

Hamburg goes beyond simply list-

ing and quantifying the cost-saving

potentials: the manifesto defines

the challenges and formulates 14

specific self-obligations through

which DNV GL intends to combat

the most important problems.

If these savings were also

combined with other trends such as

improved supply chain efficiency,

DNV GL thinks that a cost reduc-

tion of 40 % would be possible.

This is exactly the target regarded

by many stakeholders as the level

required to safeguard the future of

the industry.

“This is about securing the future

of offshore wind energy. Achieving

cost reduction is about more than

just new technology and innovation.

It also requires us to get the basics

right, which means getting people

together, assessing the issues in de-

tail and defining best practice”, said

CEO of DNV GL – Energy, David

Walker. He warns against seeing

this as “incremental or even un-

glamorous”. This is exactly what a

maturing industry looks like and it

is exactly what is required to drive

down costs, he thinks. And Walker

has good news: “We are seeing signs

of progress but we need to do much

more as an industry.”

Katharina Garus

The manifestoThe document contains 14 specific pledges across a wide range of

topics from reducing subsea cable installation risks through to acceler-

ating the commercialisation of floating offshore wind technology:

Doing it right:

•Launchajointindustryproject(JIP)toimprovemarineoperationsin

both the installation and operation phases;

•CompleteacableinstallationJIPwhichfollowsonfromourrecently

published recommended practice guide on tackling subsea cable risks;

•Helptoshareoperationsdataasakeytechnicaladvisortothe

SPARTAinitiative(SystemPerformance,AvailabilityandReliability

TrendAnalysis);

•Providetheindustrywithinterfaceriskmanagement;

•Implementamethodologyforassessingcrewtransfertechnologies

and techniques;

•HelptoensurethesafeandeffectiveapplicationofHVDCtechnology;

Doing it better:

•Launch“OffshoreUNITED”–aJIPtodrivecollaborativeandinte­

gratedapproachestoprojectdevelopment,designandengineering;

•Optimisemonopiledesignstandards;

•Deliverbettersitedesignthroughanenhancedrangeofplanning

and optimisation tools;

•Helptheindustryoptimisethesizingofexportelectricalsystems;

•Helpmovejacketfabricationtowardsserialproductionmethods;

Doing it differently:

•UsetheFORCE–acollaborativeR&Dprojecttoshowhowcost

reductionpotentialcanbeappliedtoareal­worldproject;

•Continuetopushthetechnologicallimitsofturbinedesign–

especiallywithregardtolargerturbines;and,

•Continuetodrivethecommercialisationoffloatingwindturbines.

source: dnV GL

Providing answers to your questions

Offshore Wind IntelligenceComplete service featuring specifications, development dates and supply chain for planned and commissioned projects.

Submarine Cable Consultancy Experienced marine consultants committed to mitigating issues raised by route design, installation and operation.

Market AnalysisTailored reports to help secure your future in the offshore wind industry: - market share, forecasts, political policy and more.

www.4coffshore.com |+44 (0) 1502 307037

46 offshore Wind industry 4|2014

events

t he WindEnergy exhibition, which took

place in Hamburg for the first time after

there had been a disagreement between

Husum and Hamburg,

has clearly proven its

internationality: More

than 33,000 trade visitors

from around the world

had an opportunity to

see new innovations by

1,250 exhibitors from

33 countries. A third of

the visitors came from

abroad to Hamburg, in-

cluding 24 delegations

from 22 countries. “Both

the companies that rep-

resent the industry as

well as the visitors have

clearly shown that they

recognise Hamburg

as an optimal location

for this leading global

trade fair,” says Bernd

Aufderheide, Chairman of Management at

Hamburg Messe und Congress. “The industry immedi-

ately accepted WindEnergy Hamburg as the new lead-

ing international trade fair. Many exhibitors congratu-

lated us on the very successful premiere,” Aufderheide

summed it up.

Among other things, visitors praised the good op-

portunities to establish international contacts at the

exhibition, the comprehensive presentation of inno-

vations and the attractive location in Hamburg. The

subject of storage technology, which was also show-

cased at the accompanying trade fair H2Expo, attracted

great interest. The lectures were very well-attended.

According to a representative survey of visitors by

an independent market research institute, half of the

visitors belonged to the decision-making level of their

companies. Visitors to the WindEnergy Hamburg were

equally interested in the onshore and offshore areas.

Manufacturers of wind turbines were the focus of at-

tention, closely followed by research and development.

Numerous exhibitors expressed satisfaction at the

highly professional orientation of the visitors.

Katharina Garus

Tailor-made premiereFor four days, the WindEnergy trade fair hosted the wind industry in Hamburg for the first time instead of Husum. Both the organisers as well as the exhibitors were pleased.

Phot

o: d

pa

The WindEnergy Hamburg was well

attended and the mood was good.

47dates

Offshore-Repowering ConferenceNovember 11, 2014

Leer, Germany

Decision-makers from business and politics should be set

early on the challenges to repower offshore wind turbines.

The conference will provide expert opinions on selected

topics with regard to the repowering process, including

decommissioning.

www.mariko-leer.de/news/termine

RenewableUK 2014 November 11 – 13, 2014

Manchester, England

The UK’s Premier Renewable Energy Event. Widely

recognised as the renewables event to attend in the UK –

the flagship event covering wave & tidal energy, small &

medium wind systems, onshore and offshore wind.

www.renewableuk.com/en/events/conferences-and

-exhibitions/renewableuk-2014

13th Wind Integration WorkshopNovember 11 – 13, 2014

Berlin, Germany

The 13th International Workshop on Large-Scale

Integration of Wind Power into Power Systems as

well as on Transmission Networks for Offshore Wind.

Power Plants will be held in Berlin, directly after the 4th

International Workshop on Integration of Solar Power into

Power Systems.

www.windintegrationworkshop.org

Subsea Power Cables Installa-tion for Offshore RenewablesNovember 19 – 20, 2014

London, England

The fundamentals of power cable design, installation,

protection and repair in marine environments.

www.ibcenergy.com/event/subsea-power-cables

Offshore Substations SeminarDecember 8 – 9, 2014

London, England

Specific focus on the future of converter stations for

offshore wind farms: update on designs, installation and

maintenance.

www.ibcenergy.com/event/Offshore-substations-seminar

Health & Safety 2015 January 29, 2015

Birmingham, England

Celebrating its 11th year, the industry’s premier health and

safety event will gather together over 200 industry H&S

professionals. RenewableUK anticipates running parallel

onshore & offshore sessions.

www.renewableuk.com/en/events/conferences-and-

exhibitions/health-safety-2015

WINDFORCE Baltic SeaFebruary 4 – 5, 2015

Helsinki, Finland

The two day conference targets on experiences and ques-

tions concerning offshore wind energy in the Baltic Sea.

www.windforcebalticsea.com

EWEA OffshoreMarch 10 – 12, 2015

Copenhagen, Denmark

EWEA Offshore is the world’s largest offshore wind en-

ergy conference and exhibition. The biennial event unites

the whole of the wind energy supply chain under one roof.

www.ewea.org/offshore2015

Hannover Messe WINDApril 13 – 17, 2015

Hannover, Germany

As part of the world leading industry traid fair, WIND

presents all systems, components and services for wind

energy applications.

www.hannovermesse.de

Phot

o: W

AB

internal

48 offshore Wind industry 2|2012

Just one year after the successful “China 2013”

journey of innovation, a delegation of WAB members

set off once again on 14 September to find out about

the wind industry market in another country.

Led by Ronny Meyer, Managing Director of

WAB and germanwind, the week-long trip this time

was to Great Britain. In the delegation were various

representatives from Germany’s wind industry

and the Bremen Economic Development company

Wirtschaftsförderung n Bremen (WFB). Visiting two

offshore wind clusters, East of England and Hull and

Humber, WAB members were provided insight into the

English offshore wind market. The visit was designed

to develop contacts with potential project partners and

Trip with a speedboat to

offshore windfarm Scroby

Sands

Offshore wind clusters visited during the 2014 trip

to England

WAB members learn about England’s offshore wind market

49

Register now to make sure of your early booking discount!

encourage new cooperative ventures with English

businesses. Supporting the journey from the British

side were the cluster organisations OrbisEnergy

and East of England Energy Group as well as Team

Humber Marine Alliance.

This year, too, the programme was very diverse.

Together with a gala dinner and B2B events, the

agenda also included business presentations

and excursions to port facilities. Visits to British

companies and institutes engaged in the offshore

wind industry, such as E.ON UK, Sembmarine

SLP, Associated British Ports, Siemens, Able UK,

OrbisEnergy and Tata Steel, were a particularly

important component of the programme.

The third WINDFORCE Baltic Sea conference will be

held on 4 and 5 February 2015. This time the venue

is the Finnish capital, Helsinki.

For two days, the development of offshore wind

energy in the Baltic Sea region will be the focus of

talks and discussions. Representatives from S weden,

Denmark, Estonia, Lithuania, Poland, Germany and

Finland will provide an overview of the current

situation in their countries. WAB members enjoy

favourable terms. The early booking discount applies

until 31 October 2014. We look forward to welcoming

you to Helsinki! For information and registration go to

www.windforcebalticsea.com.

About wAb and germanwind

The WAB Wind Energy Agency is

the leading business network for the wind energy

industry in Germany’s northwest region and

is the national point of contact for the offshore

wind energy sector in Germany.

www.wab.net

As a project company and wholly-

owned subsidiary of WAB, germanwind initi-

ates and coordinates innovative projects in wind

energy.

www.germanwind.info

Follow WAB and germanwind on

50 offshore Wind industry 4|2014

Fit for the jobBad for some, good for others: whilst offshore wind energy

companies increasingly complain about a lack of suitable

personnel, training centres see the situation as a good

opportunity.

EWEA OffshoreThe year has not yet begun but the first big event is on the

horizon. EWEA Offshore in Copenhagen will be a test of the

situation for the new year and will show the industry where

it is heading in 2015.

The next issue will be published on February 2, 2015For further information see www.offshorewindindustry.com

Tough cookiesThey not only have to transport the components

of wind turbines in a way that takes up the least

space, they also have to install them. Installation

ships have to be absolute all-rounders.

outlookPh

oto:

Min

es R

escu

e

Phot

o: V

atte

nfal

l

Phot

o: E

WEA

www.senvion.com

You’re looking for a partner with in-depth knowledge of offshore projects. Is 147 feet deep enough?

With well over 100 multi-megawatt turbines up and running, we can confidently say that we know about the special challenges of installing turbines at sea. And by building on the proven technology of our 5M model, our engineers have developed the 6.2M126, the most powerful serial offshore turbine ever installed. Our in-depth experience in the large-scale production of multi-megawatt turbines extends to their installation and all related operation and maintenance activities, far from shore and in deep water. This makes Senvion a powerful partner when it comes to the economic success of your offshore projects.

DAMEN OFFSHORE WIND

WALK2WORK VESSEL

As energy recovery from renewable and fossil fuel sources pushes farther offshore, keeping maintenance staff comfortable is a key challenge. Damen Shipyards’ high performance ‘Walk-to-Work’ vessel addresses the expectations as set by the industry.

The vessel has on-site work and storage facilities, plus accommodation for up to 40 maintenance personnel and management and a crew of 20. It will be able to stay out at sea for voyages of up to one month duration, feature dynamic positioning (DP2) and a telescopic, motion-compensated transfer gangway to allow for transfer of maintenance teams to walk between vessel and the offshore structure.

WWW.DAMEN.COM | [email protected] | +31 183 63 99 11

NEW DESIGN: WHY? BECAUSE THE MARKET TOLD US SO!

adv2013_033_Walk2Work Vessel Text Peter Robert 200*280.indd 1 09-10-14 14:50