OCHA UNDP/PAPP INTERNAL FINISHING WORKS FOR THE SECOND FLOOR (ROOF) OF OCHA Jerusalem Bill of Quantities August 2008

Jerusalem Bill of Quantities - UNDP · and removing the old pointings and all the stuck concrete, ... • Concrete filling including reinforcing steel to ... preservative before erection

Embed Size (px)

Citation preview

OCHA

UNDP/PAPP

INTERNAL FINISHING WORKS FOR THE SECOND FLOOR (ROOF) OF OCHA

Jerusalem

Bill of Quantities

August 2008

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 1Demolishing for any kind of block, concrete, wood,and metal works, etc. needed to clean the areaand not affecting the stability of the woodstructure of the cieling. Leveling the ground andcomplete cleaning for the roof floor from all typesof soil, wood, metals and unnecessary materials.All as per the approval of the Engineer.

1-1 Demolishing all the existing concrete blocks on thepartitions and the windows and moving all thesurplus to a location where the Engineer instruct,removing all the garbage, sand, cocrete blocks andstones on the roof floor, and all surplus debrismaterial from the roof floor and from the workingarea in preparation for works. Unit rate shall alsoinclude removing damaged stone walls, damagedceilings, damaged floor tiles, dismantling existingwooden, metal or other elements, wire mesh,cables, metal sheets and all related elements.Then, all the working area should be cleaned andprepared for finishing works, taking intoconsideration to keep and maintain the woodstructure and supporting it properly. All asdirected by the Engineer.

JOB 1

1-2 Cleaning all the roof floor and the roof tilescompletely, and removing all the birds nests andall related birds products, disinfecting all the floor,walls and ceiling with required insectdisinfectants, and preparing the windows, floorand ceiling for the next works. All as directed bythe Engineer.

JOB 1

1-3 Cleaning all the internal stone works on the wallsand removing the old pointings and all the stuckconcrete, wood or metal peices from the stonewalls completely. All as directed by the Engineer.

JOB 1

Total Bill NO. 1 Sum Of Items [(1-1) - (1-3)] carried to summary

Cleaning, Demolishing & Dismantling Works:

UNDP - PAPPEngineering Unit 1 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 2Maintenance includes, fixing all the damagedneeded items and maintaining floor and ceiling ingood condition. All as per the approval of theEngineer.

2-1 Complete maintenance for the floor, includingsupplying and casting concrete where needed andmaintain the floor slab in level and ready for tilingand other partision works. All as directed by theEngineer.

JOB 1

2-2 Complete maintenance for the ceiling, includingdismantling all roof tiles and store them in a safeplace, supplying and installing special wood beamsto support the roof tiles, reinforcing all the woodenstructure with special fixing elements from boltsand metal elements; price includes changing anybroken wooden beam or any damaged roof tile orany related item with new ones. In addition,solving the rain water leakage in the roof tiles andsupporting the tiles properly and supply andperforming the required materials and water proofmaterials to fix all the leakage and supportproblems after implementing item 8.2. All asdirected by the Engineer.

JOB 1

Maintenance Works:

Total Bill NO. 2 Sum Of Items [(2-1) - (2-2)] carried to summary

UNDP - PAPPEngineering Unit 2 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 3PREAMBLE.All works of this bill shall be of Concrete blocks Grade 35 of high quality standards and as per specifications.Block works shall be measured in meter square. The net measurement of the seen elevations, excluding all openings and voids more than 0.1 M. S. in area. No allowance for thickness used other than those shown in the drawings. Rates of Block works include:-• Vertical and horizontal joints. • Cement and mortar,• Galvanized angles and butter fly ties.• Closed end blocks at all ends, door and window jambs, reveals and the like.• Pointing of the uncovered block surfaces.• Concrete filling including reinforcing steel to cavities at quoins and door and window openings.• Lintels and bond beams to the full length of the wall, 20 cm. high and in the same wall thickness of reinforced concrete grade B-200 with due reinforcement steel, on top of doors and windows or at the height of 2.00 M.• and all needed to complete job as per drawings and specifications.

Supply and Build Concrete Block Walls, 'Grade 35' of any size blocks.

A. Hollow Blocks ( 10 Ten) cm. thick . M2 205

B. Hollow Blocks (20 Twenty) cm. thick. M2 40

Concrete Blocks Works:

Total Bill NO. 3 Sum Of Item [(3-1)] carried to summary

3-1

UNDP - PAPPEngineering Unit 3 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 4PREAMBLE.Plastering to all areas shall be measured net,including openings which are less than 0.25 MeterSq.The price shall include for running rules , allnarrowwidths, for taking out joints on block walls orbacking concrete face for key, for making good toframes around pipes and other fittings ,plastering to jambs and reveals of openings, sideof columns, window sills; all of which shall bemeasured as plastering .

Price shall also include Expanded metal lath,angle beads at all corners and plaster stops atopening edges, expansion joints, sills, labor,curing, erecting and dismantling of scaffoldings,additives, pigments and all incidentals required as

Supply and apply Two Coats of Cement and SandPlaster over one slurry coat to walls and ceilingsand where required including metal Lath ,angle

beads , plaster stops and all required as per Specsand drawings .

A.Three coats Internal plaster. M2 210

4-2 Supply and apply Two Coats of Cement and SandPlaster over one slurry coat to walls and ceilingsand where required including metal Lath ,angle

beads , plaster stops and all required as per Specsand drawings .

M2 250

4-3 Supply and apply pointing to all the internal wallstone, including all the required works to completethe job as per the approval of the Engineer. JOB 1

4-1

Total Bill NO. 4 Sum Of Item [(4-1) - (4-3)] carried to summary

Plastering and Pointing:

UNDP - PAPPEngineering Unit 4 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 5PREAMBLE.1. All tilling works ( terrazzo, ceramics and marble ) shall be measured net in square meters. deducting all opening and voids more than 0.25 m.s.2. Skirting shall be measured in leaner meter.3. Marble works for steps and treads of stairs shall be measured in linear meter. The tread and the riser shall be measured as a single unit.4. Marble works for window sills and other openings shall be measured in squared meter .5. Parapet copping shall be measured in squared meter.6. Marble works for stair flight’s skirting shall be measured in linear meter.7. Rate shall include preparation of surfaces under tiles, Finnish to falls and cross falls, special tile peace’s for edges and the like, tile surface finishing, Plastic spacers. Pointing and cleaning and all incidental as per specifications.8. Rates shall include also providing and mounting in place “Title Marble Plate” of white clear local marble polished, finished and engraved according to the design provided by UNDP.

5-1 Supply, Install and finish Pre-cast Terrazzo Tiles Size ( 30 x 30 x 2.7 ) cm, with Italian marble chipping # 6. Price to include, bedding and jointing in cement and sand mortar, pointing with white cement, required sand fill, and on site grinding, polishing and cleaning and skirting size (30*7.5*1.5)cm

M2 95

Supply and Install Local Marble Sills, Thresholds and Parapet Coping. ( 3 cm. thick ).Set in cement mortar bedding price to include grouting, polishing of face and chamfered edges .

A. Window Sills Size( 15 - 37.5 x 3 ) cm. M2 5

B. Kitchenette Sink Size( 50- 60 x 3 ) cm. M2 0.5

5-3 Supply and Install White Porcelain Glazed Wall Tiles, class "A" free from all defects. (Spanish or Italian high quality make or equivalent).

M2 8

5-4 Ditto but non slippery tiles for the W.C floor. M2 3

Total Bill NO. 5 Sum Of Item [(5-1)-(5-4)] carried to summary

5-2

Tiling, Flooring and Marble Works:

UNDP - PAPPEngineering Unit 5 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 6PREAMBLE.Sizes of carpentry works given in the Bills of Quantities are finished sizes and shall be as per Drawings.Sizes of doors and other items mentioned in the Bills of Quantities shall allow for tolerance to suit the structural openings shown in the Drawings.• Wooden doors and pair of doors shall be measured in number for each structural opening, unless stated otherwise in the Bills of Quantities.Rates for carpentry and joinery work shall include :a) Shop and coordinated drawings.b) Cutting and fitting around obstructions, Bedding and painting.c) Grounds, blocking and backings.

d) Plugging concrete, block work, and stone work , and making good.e) Ironmongery including cylindrical locks, handles, stoppers, screws, temporary fixing, re-fixing, oiling and adjusting.f) Providing two keys for each lock including tagging.g) Providing and fixing Room Title Plat, Painted Steel (30*20) cm. mounted on wooden plate (35*25) with varnish finish.h) Steel legs, brackets, bearers and other supports including painting.i) Glass and glazing including cutting to size and putty.j) Fly screening including cutting to size.k) Preparing surfaces to receive finishes.l) Painting, varnishing, polishing, oiling, and the like, to any area or width in any location including work in multicolor and cutting in edges and putty.

Carpentry And Joinery Works:

UNDP - PAPPEngineering Unit 6 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

6-1 Supply and Fix Flush Panel Solid Core Doors 4.5cm Thick single or double sashes of size 210x90cm. with ( Frame ). (4.5*10) cm. Edge stripbanding of Hardwood ( Swedish ) , with 5 mm.thick plywood veneer on both sides, door panelingto be of soft wood 3.5*3.5 cm. each 2.5 cm. ,frames of hardwood ( Swedish) width according tothe wall thickness’ and Allowance of 4 - 6 cm,clearence from tiles to be 2 cm. thickness forplastering and tiling purposes, emerged in woodpreservative before erection then embeddedcompletely in sand - cement mortar andcompletely anchored as per specification . Priceshall include Domicile or equally approved doorhandles, cylinder & lock. All as per the approval ofthe Engineer.

No. 5

6-2 Ditto, but size 210x80 cm. M2 1

6-3 Supply and install lower Kitchen Cupboard cosisting of the neccessary doors, drawers of different depths and shelves; of hight 90 cm and depth of 60 cm. Exterior and interior Formica covering and all hardware hinges, handles, telescopic drawer rails, shelf brackets. The unit price shall also include cost of local marble topping 3 cm thick and making the neccessary openings for installing the sink and other services. All as directed and approved by the engineer.

Unit 1

Total Bill NO. 6 Sum Of Item [(6-1)-(6-3)] carried to summary

UNDP - PAPPEngineering Unit 7 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 7Preamble. Metal works shall be measured in number.Rates for metalwork shall include for :Preparing shop drawings, Drilling, counter sinking, screwing, bolting and riveting.Sub frames, including galvanized steel frames for Aluminum windows and architrave.Lugs, plugs, holdfasts and the like.Gaskets, sashes, double weather strips and external and internal approved quality silicon filling around frames.Ironmonger including cylindrical locks (Union or equal) , stoppers, handles, temporarily fixing, refitting, oiling and adjusting.Providing two keys for each lock and padlock including tagging.Hardware including cramps, dowels and the like.Glass and glazing including cutting to size, putty and rubber.Preparing surfaces for and painting one coat of primer before fixing. Painting one undercoat and two finish paint.Sealing and Painting to any area or width in any location including work in multicolor and cutting in edges.All other accessories and incidentals required to execute the work.

7-1 Supply and install Mul-T-Lock door of size 210X90 cm to seperate the working area from the other roof floor area. Price includes the required frame and accessories, locks, handles and hinges, the needed support with ground, fine welding with the security metal frame and the direct support to the steel columns and the top edje of the steel structure where needed. All as per drawings and to the approval of the Engineer.

NO. 1 216.00 216.00

7-2 Supply and install metal stair rails (same as existing) for the roof staircase including all fixation elements and welding needed to fix the rails with the walls and ground. Price to include painting the rails with anti-rust coat and then oil painting of the collor choosen by the Engineer. All works are done according to Engineer's instruction.

MR 4

Total Bill NO. 7 Sum Of Item [(7-1) - (7-2)] carried to summary

Metal Works:

UNDP - PAPPEngineering Unit 8 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 8Preamble. The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract. Rates for all suspended ceilings works includes suspension system with anchors to the structure, L& Z, main & main profiles, omega profiles. clips, gaskets and all necessary fittings in accordance to the manufacture technical data and related standards covering this type of works, The rate includes also cutting and preparation for installing lighting fixtures, ceiling recess, maintenance openings, grills, ceiling utilities... etc.

8-1 Supply and install vertical and horizontal gypsum boards 12mm thick fire and water proof for ceiling cladding and for other decorative works. The price shall include all decorative beams, edges, recessed slab, squares, cuts, suspension& structural profiles, fixing with the wooden structure and extra support where required-- etc to any shape and patterns to complete the works. The unit rate shall also include acoustic and thermal rock wool mats, 25mm thick and 25kg/m3 density, wrapped in black non inflammable dust proof sags in accordance with specifications and the related Standards. as approved by the Engineer.

M2 105

8-2 Supply and install Galvanized steel sheets to cover the lower edge of the ceiling wooden frame to forbid leaking rain water to get down to the roof floor. The unit rate shall include storm water collectors on the edges of the building and also include acoustic and thermal rock wool mats between metal sheets and roof tiles, 25mm thick and 25kg/m3 density, wrapped in black non inflammable dust proof sags in accordance with specifications and the related Standards. The galvanized sheets should be spread on all the brick tiles until the external edges where storm water collectors are installed and draged to the corners of the building. All works shall be done as per the instructions of the Engineer.

M2 300

Gypsum Boards and False Ceiling Works:

Total Bill NO. 8 Sum Of Item [(8-1) - (8-2)] carried to summary

UNDP - PAPPEngineering Unit 9 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 9Preamble. Painting and decorating to walls, ceilings and the like shall be measured net in meter square.Painting to other works shall be included in the related items.Paints shall be supplied to site in sealed container, as approved by the Engineer, and site mixing shall not be permitted.The Contractor rates shall include for supply of all materials, workmanship, samples, primers , surface preparation , protection of painted surfaces , application to all heights as required of works, repair of all damaged surface at the contractor's expenses , and all other requirements as stated in the Specifications .

9-1 Supply and paint high quality Emulsion PVA-Based Paint, for internal walls. Price includes one priming coat and two finishing coats , for application to walls , using putty from Delux or equivalent

M2 300

9-2 Supply and paint Polycide paint for gypsun boards ceilings, price shall include painting and putty. All as directed and approved by the Engineer. M2 95

Total Bill NO. 9 Sum Of Item [(9-1)-(9-2)] carried to summary

Painting Works:

UNDP - PAPPEngineering Unit 10 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 11Preamble.All items price to include Supply, Installing, Connecting and testing unless otherwise indicated, the contractor are requested to have approved full coordinated work shop drawings before starting contract activities, the price also includes all works necessary to implement electrical works in approved manner.The contractor intended to order main and final distribution panel boards according to approved manufacturer drawings.The price to include submittals, catalogs, any manufacturer instruction .The contractor should install and construct allworks according to drawings , specification tender documents, and requirement of Electrical Co.Contractor should also test & submit the electricalWork to the Electricity Co. & Municipality.

11.1 Electrical Points:

a The electrical power supply from electrical switchboard to first point in circuit shall be included in the unit price of that point (by means of wires, cables or leads in self extinguishing conduits and cables). All as per specifications and as required.

b. All wiring accessories shall be as made by Legrand or equivalent.

11.1.1 Supply, install , connect ,and test a standard lighting point internal or external, in slab or over false ceiling, to include a 16 mm diameter conduit, 1.5 or 2.5 sq. mm cross-section leads or cable, and, as required single, double, two way or push bottom lighting switch Legrand type or equivalent, and outlet for luminare with junction box and terminals.

No. 55

11.1.2 Ditto but for emergency lighting point No. 0

Electrical Works:

UNDP - PAPPEngineering Unit 11 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

11.1.3 Supply, install , connect,and test a 16A wall socket point - to include a 16 mm dia. Conduit, (3x2.5) sq. mm cross-section leads or cables, and as required 16 A wall socket Legrand type or equivalent approved.

No. 4

11.1.4 Ditto as item 14.1.3 but double socket. No. 15

11.1.5 Ditto as item 14.1.3 but with water proof cover.

No. 3

11.1.6 Ditto as item 14.1.4 but with water proof cover.

No. 1

11.1.7 UPS Power Supply Socket No. 14

11.1.9 Supply, install , connect and test Fire Alarmconnection point (Price includes 16 mmdiameter conduit with cable, leading frompoint to the LV box or to the nearest point).

No. 16

11.1.10 Supply, install , connect and test TVconnection point (Price includes 23 mmdiameter conduit with cable, boxes, and thesocket outlet leading from point to the LV box).

No. 1

11.1.11 Supply, install ,connect and test Computer socket point in a 23 mm conduit - to include a 23 mm diameter conduit .

No. 15

11.1.12 Supply, install, connect ,and test a Three phase 25A Isolator Switch .The price include the conduits , cable , cable tray and any accessories needed, all according to drawings and specifications for the exhaust fans and splits units.

No. 3

11.2 Conduit, Rigid Piping and Excavation Works:

UNDP - PAPPEngineering Unit 12 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Supply, install, connect and test Self-extinguishing type plastic conduit, processed over or under plaster or inside castings, including junction boxes, unions, connectors, etc. including excavation, backfilling , sand , tape , and galvanized draw-strings, ready for use (for works not included in points works).

11.2.1 23 mm diameter. ML 30

11.2.2 29 mm diameter. ML 30

11.2.3 36 mm diameter. ML 45

11.2.4 50 mm diameter. ML 30

11.3 Cables:

Supply, install, connect and test XLPE non-armored type thermoplastic copper cables, including insertion into conduit or attachment to structural elements or laying in ductwork, including all associated materials, insulation materials, unions,Z construction, ladders, cable shoes and connection of cable at both ends.

11.3.1 3x35+16 sq.mm cross section+16 Cu.. M.L. 50

11.4 Electrical Switchboards:

a. Supply, install, connect and test the electrical switchboards to the site, including all associated materials and labour, as described in the technical specifications.

b. Cabinets with no access from the rear, made up of transparent polycarbonate cells, or sheet-metal cabinets with a 25% surplus space.

c. The switchboards are to be placed on the floor, in a niche against the wall.

d. Main supply lines enter from the switchboard bottom, top or side, while outgoing lines exit the switchboard from both its bottom and top sides.

UNDP - PAPPEngineering Unit 13 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

e. Price to include all structural elements required in order to install the switchboard, including bus-bars, terminals, wiring, bolts, clamps, etc. and for the equipment listed below.

f. The switchboards shall contain accessories made by one of the following manufacturers: SIMENS, MERLIN GERIN, KLOCKNER-MOELLER or Equal Approved.

g. Prices for supply, installation and connection of various accessories including all associated labour and materials such as bus-bars, terminals, wiring reinforcements, mounts, engraved "sandwich" type identification plates, etc. including connection to mains supply - complete ready for use.

11.4.1 DBR Unit 1

11.5 Lighting Fixture:

a. Supply, install ,connect and, test of lighting fixtures as described below, including all necessary accessories, required in order to light it with lamps and electronic rapid starter, complete, similar to Philips or approved equal and according to the following:

b. All lamps shall be of the energy-saving type (135, 18,36, 58 Watts).

11.5.1 Type (A)1X8W emergency EXIT sign for 3 hours duration Maintained Wall Mounted.

Unit 1

11.5.2 Type (B) 2x13W downlight horizontal mounting with a cover.

Unit 5

11.5.3 Type(BE) Ditto,but with emergency Kitt 3 hours backup battery and charger.

Unit 0

11.5.4 Type (C) 2D 28W surface mounted circular luminarie with white base and white polycarbonate diffuser IP54.

Unit 2

11.5.5 Type (D) 4X18W surface mounted light fixture with double parabolic Aluminum Louver.

Unit 38

UNDP - PAPPEngineering Unit 14 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

11.5.6 Type (DE) 4X18W surface mounted light fixture with double parabolic aluminum louver with 3 hours backup battery and charger.

Unit 0

11.5.7 Type (O) 250 watt metal halide projector Unit 0

11.6 Fire Alaram System:

Supply, install , connect and test complete inplace and in an operable manner the firealarm system. The work is to include thesupply of the equipment specified, installationof same connection, wiring, cables,commissioning and all of the details andconnecting to the existing system as specifiedin the technical specifications and drawingtype to be similar to Telefire or equalapproved.

11.6.1 Intelligent manual call point. Unit 3

11.6.2 Indoor fire alarm siren Unit 3

11.6.3 Intelligent photo electric smoke detector, complete with base

Unit 11

11.6.4 Intelligent heat detector, complete with base Unit 2

11.6.5 Outdoor fire alarm siren Unit 1

11.7 LV Boxes:

Supply, install,connect and test the following LV boxes. Rate to include all required materials, conduits, wires, cables and accessories manufacturing from galvanized sheet metal sheets , painted with the same color of the switch boards all as specified in the technical specification and drawings.

11.7.1 LVB Approximate dim.( 60x60x25) cm No. 1

Total Bill NO. 12 Sum Of Bills [(11-1)-(11-7)] carried to summary

UNDP - PAPPEngineering Unit 15 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

Bill No 12 Plumbing, Sanitary And Mechanical Works:Preamble:The measurement for the supply and installation of the mechanical works items shall be as stipulated below:

All water supply valves, faucets and fixtures shall be measured by number.Domestic water supply network pipes and fittings (excluding valves) from roof tanks to water collector shall be measured in linear meter.Water tanks shall be measured by number. Sanitary fixtures, including PVC syphon, pedestals, fixing screws, and all required fixation gadgets, shall be measured by number. Floor drains, floor traps, clean outs, rain water roof drains shall be measured by number. Vents and vertical stacks shall be measured in linear meter.Manholes and gulleys shall be measured by number.External and internal sewer pipes shall be measured in linear meter for each individual Rates of all fittings , fixtures , appliances and pipe laying shall include:-Supply of material, workmanship, installation, testing and commissioning. Supply, install and testing of pexgol pipes including all the needed fittings, sleeves, (excluding valves) between water collectors and fixtures.Rates to include also all pieces and fittings, including by-passes , floats, automatic vents, stack covers, valves and non return valves, tees, joints, tee bolts and rods, brackets, elbows, reducers, fixing materials and all the required elements needed to complete the works as per specifications. Insulation and painting shall be done as called for in the specifications.Rates shall include excavation and cutting for all pipe laying works, bedding, back filling and all works connected with pipe laying.Rates to include workmanship, storing, correspondences, shop drawings and as-built drawings, all as approved by the Engineer.

UNDP - PAPPEngineering Unit 16 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

12-1 Supply and install 4" UPVC pipes (UAP, Royal, or equally approved) for internal sewage network, vent pipes, and rain water drain pipes. Price includes all kinds of excavation in any type of soil and rock, backfilling, digging in concrete slabs and walls, supports, hangers and all rubber joints and sealants. All done as per specifications, drawings and the approval of the Engineer.

MR 5

12-2 Ditto but 2" UPVC pipes for the Sanitary fixtures. MR 6

12-3 Ditto but 1 1/4" UPVC pipes for Air Conditioning d i

MR 20

12-4 Supply , install and test heavy duty chrome plated 4" floor drain with mesh cover, as made by Ritco or equivalent, including 4" syphon trap as made by Royal, UAP, or equivalent, all complete with the required fittings and connections, as per the specifications, drawings, and the approval of the Engineer.

NO 2

12-5 Supply , install and test heavy duty chrome plated 4" clean-out with air tight cover , as made by Ritco or equivalent, complete with all required fittings and connections.

NO 1

12-6 Supply and install porcelain kitchen sink of size 55 x 45 cm from Ideal Standard/Egypt, Vetara/Turkey, Shona/India as shown on drawings, to be placed on the Marble platform. Price shall include all fixation and hanging bracket, sealants, support, PVC syphon, and all other required materials, including connection to floor drain system.

NO 1

12-7 Supply and install Chrome plated gear type mixer of Ideal Standard/Egypt, Lirane or equal for kitchen. Price shall include, connections to water pipes outlets, angle valves and wall sockets. All as specifications, drawings and the approval of the site Engineer.

NO 1

UNDP - PAPPEngineering Unit 17 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

12-8 Supply and install plated gear type mixer of Ideal Standard/Egypt, Lirane or equal for bathroom. Price shall include, connections to water pipes outlets, angle valves and wall sockets. All as specifications, drawings and the approval of the site Engineer.

NO 1

12-9 Supply and install porcelain W.C. bowl class "A" white color of Ideal Standard/Egypt, Vetara/Turkey, Shona/India, with heavy duty white seat and cover. Price includes flush tank, hanging iron steel bracket, bolts and nuts, as well as flexible flush hand hose and valve and all fixing materials.

NO 1

12-10 Supply and install porcelain wall hung wash basin white color of size 45 x 35 cm such as Ideal Standard/Egypt, Vetara/Turkey, Shona/India. Price shall include all fixation and hanging bracket, white plastic syphon and all other required materials, including connection to drainage system.

NO 1

Supply, install and test Schedule 40 galvanized steel pipes "Akko make or equal" at riser, roof piping, sanitary block, etc. Price includes all necessary fittings such as elbows Tees, unions, air vents, supports, hangers, shields, saddles, etc. All pipes imbedded in walls shall be coated with 3-layers of extruded polyethylene. All pipe joints imbedded in walls shall be coated with thick asphalt layer. All done as per specifications, drawings and the approval of the Engineer.

a- 3/4" diameter pipe MR 20

b- 1" diameter pipe MR 10

c- 1 1/4" diameter pipe MR 5

d- 2" diameter pipe MR 10

12-11

UNDP - PAPPEngineering Unit 18 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

12-12 Supply, install and test Copper Collectors 3/4" dia., as made by NTM / Italy or equivalent. Price shall be per opening (eye), and shall include the required copper glands, and air vents all the required fittings, price also includes wooden closet as required and approved. Collectors shall be installed and fixed in recessions on walls by adequate hangers and tees, as shown on drawings in the corridor. The work shall be completed as specified and according to the Engineer's instructions.

Eye 6

12-13 Supply, install and test Pexgol pipes 16mm dia. Price to include copper glands, connectors, elbows, and all needed fittings and external protective sleeve of 25mm dia.

MR 30

12-14 Supply and Install of forward curve ducted splitunit heat pump made by York, Daikin, Carrier orEqually approved (condenser and evaporator) ofsize 8.4 kw. The unit shall be a single coil withdrain pan made of stainless steel and with allparts such as copper valves, washable flat filter,multi speed electric motor and room thermostatwith three speed switch (wall mounted), distanceremote controll. The rate includes drilling anddiggings needed, concrete works, copper pipes ofproper diametres with 9 mm insulation and 10 cmplastic wrap strips, all the required fittingsinternally and externally, flexible pipe for drainwater to be connected to the PVC A/C drain pipein wall, electrical control cable. Price also includeall flexible ducts between the unit and thediffusers of different sizes as shown in thedrawings, all done as per specifications and theapproval of the Engineer.

No. 2

12-15 Supply and Install supply air aluminum ceilingdiffusers made by cooling industries or Equallyapproved, square four-way type , with removablecore, key operated opposed-blade volume damperand equalizing grid, suitable for mounting flushwith false ceiling. The unit price shall includeconnection to duct, and all accessories and worksrequired to complete the work. All done accordingto drawings specifications and approval of theEngineer. Size 12"X12"

No. 6

UNDP - PAPPEngineering Unit 19 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No Description Unit Quantity Rate (US$) Amount (US$)

12-16 Supply and Install return air aluminum grilles ofsize 24"X24" made by cooling industries or Equallyapproved, fixed 45-degree blades, doubledeflection, 1" thick frame, 3/4" spacing. The unitprice shall include connection to duct, and allaccessories and works required to complete thework. All done according to drawings specificationsand approval of the Engineer.

No. 2

12-17 Supply and Install Wall mounted fire cabinet120x80x30 cm type Lahavot or equally approved ofcabinet thickness 2mm equiped with 1" swinginghose reel 30 m polystrene hose 1" aluminumnozzle, 12 kg powder extinguisher, 2" linen hose (2x 25 m) with quick coupling, 2" nozzle, 2" landingvalve, and all required fittings and valves.

No. 1

Total Bill NO. 12 Sum Of Item [(12-1)-(12-17)] carried to summary

UNDP - PAPPEngineering Unit 20 - 21

OCHA Roof FloorCost Estimation

August 2008

Item No TotalBill 1Bill 2Bill 3Bill 4Bill 5Bill 6Bill 7Bill 8Bill 9Bill 11Bill 12

SIGNATURE :

DATE :

Grand TotalDiscount

Discount AmountNet Total

NET TOTAL SUM (in words ) :

SIGNED AND SEALED :

AUTHOURIZED :

TITLE :

Metal Works:Gypsum Boards and False Ceiling Works:Painting Works:Electrical Works:Plumbing, Sanitary And Mechanical Works:CONTINGENCIES ( ____%)

Concrete Blocks Works:Plastering and Pointing:Tiling, Flooring and Marble Works:Carpentry And Joinery Works:

SummaryDescriptionCleaning, Demolishing & Dismantling Works:Maintenance Works:

UNDP - PAPPEngineering Unit SUMMARY