Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Ishkonige Nawadide Solar Project UpdateDecember 17, 2020
Bad River Band of Lake Superior Tribe of Chippewa Indians
Daniel Wiggins Jr, Project lead
Bad River Band of Lake Superior Tribe of Chippewa Indians
Located on a 125,000+ acre reservation in Northern Wisconsin on the south shore of Lake Superior
Territory ceded by the tribe to the U.S. government includes the upper one third of what is now the State of Wisconsin.
Has over 7,000 members, the majority living off the reservation, about 2,000 live on/near the reservation.
Overview
Phase 1: Ishkonige Nawadide Objectives Project Details Planning & Development Execution of Project Challenges Accomplishments Next Steps Partners
Long-term Planning Phase 2: Giwiijiiwaaganinaan
Gitigan Microgrid Project Questions
Phase 1: Ishkonige Nawadide Solar Project
Ishkonige Nawadide Objectives The Bad River Tribe was awarded a USDOE Grant in 2019 for the Ishkonige
Nawadide (It Catches Fire) Solar Microgrid Project. 2 Million Dollar Project 50% USDOE Contribution
Focused on resiliency after the 2016 Flood and while experiencing lengthy electrical outages at crucial facilities, such as the Health & Wellness Center, the Tribe’s community Clinic.
Tribe is installing over 500 kW of solar with over 1000 kWh of battery storage at three tribal facilities located in the Odanah Community: The Chief Blackbird Administration Building Wastewater Treatment Plant (WWTP) Health & Wellness Center (H&WC)
Systems at the H&WC and the WWTP will offset the entire facility electrical loads and offer a level of resiliency if power goes out that can last projected days if not weeks.
Ishkonige Nawadide Details Chief Blackbird Administration Building
PV Size: 24kW DC
Battery Size: 22 kWh
Health & Wellness Center PV Size: 300 kW DC
Battery Size: 568 kWh (250 kW or discharge rate)
Wastewater Treatment Plant PV Size: 200 kW DC
Battery Size: 426 kWh (200 kW or discharge rate)
All Systems operate on a DC Bus System Everything (PV and batteries) is connected on the DC side.
Cloud Monitoring System
Odanah Community
Ishkonige Nawadide Planning & Development The Ishkonige Nawadide Project was guided with both Strategic Energy
Planning done in 2012 and 2017.
The Tribe used the newly adopted 2018 Emergency Preparedness Plan (EPP) to identify critical infrastructure that was affected by power outages and the 2016 Flood.
Several buildings and scenarios were identified for possible solar projects
The 2018 EPP clearly identify the Health & Wellness Center, Wastewater Treatment Plant, and the Chief Blackbird Administration Building as critical infrastructure.
Ishkonige Nawadide Execution of Project Request For Proposals:
Investor and Developer come together Started Nov 2019 Concluded May of 2020 Awarded Faith Technologies
Contracts & Documents Leasing and Energy Services Agreement (Several Attachments) Started June 2020 Concluded and executed October 2020
Began Construction in October of 2020 Anticipated Commissioning in March of 2021 Interconnection Agreement and PPA process has started
Administration
WWTP
Health & Wellness Center
Ishkonige Nawadide Challenges COVID-19
Tribe issued Declaration of Public Health Emergency with Respects to the 2020 COVID-19 Pandemic in March of 2020 along with Safer at Home orders once COVID begun to hit the community in June
Made meetings difficult Decision making by leadership
Utility Task Force Meetings
Overall Team Meetings
Virtual Meetings have created a great level of communication
Construction Limited building access and extra precautions
Contractors coming from out of town
Required all contractors to have strict COVID-19 policies
Ishkonige Nawadide Challenges Community Acceptance
Replacing land with solar or any infrastructure is not always accepted by elders and environmentalists. “ I don’t know how I’ll feel about it until I see the panels…. The trees were nice.”
Community Elder
There is a level of sovereignty given up when involving partners and investors. Any time this is said it will not be accepted by many tribal members
Emphasizes the need for clarity and transparency
Community meetings and presentations around financing strategies
Ishkonige Nawadide Accomplishments Completed RFP Process Executed Construction and Contracts Developed a Long-term Strategy once Ishkonige Nawadide has been
commissioned
Working with Faith Technologies to develop Tribal workforce Workers knowing how to install and handle panels
One tribal worker during Construction of racking and PVs
Working with education to support training module within 18–24-year-old program.
OMCO has offered complete training for Tribe with racking and PVs
Facility Managers will identify technicians to work with Faith Technology Staff or (Itians) in order to develop skills to fully operate the microgrids.
Ishkonige NawadideNext Steps
Batteries and interior electrical
Interconnection and Commissioning scheduled for March
Execute Long-term Phased Energy Plan Phase 2 USDOE Application Submittal in February of
2021
Identify Other funding strategies
Ishkonige NawadidePartners Bad River Tribe Utility Task Force Team
Cheq Bay Renewables
Madison Solar Consulting
muGrid Analytics
Faith Technologies
Long-term Planning
Conducted November of 2019, led by Amy Simpkins of MuGrid Analytics.
Concentrated on a strategic phased approach incorporating the Ishkonige Nawadide Solar Project as Phase 1.
Two-day collaborative meeting with Department heads, leadership, and community representatives.
Long-Term Poster and Report was developed for the Tribe Report: https://tinyurl.com/y6xl9gt7
Poster: https://tinyurl.com/y5ffqnem
https://tinyurl.com/y6xl9gt7https://tinyurl.com/y5ffqnem
Phase 2: Giwiijiiwaaganinaan Gitigan Microgrid Project
Giwiijiiwaaganinaan Gitigan means Community Garden or Three Sisters Garden. This was the original Project title for Clinic, Head Start and Elderly Buildings when Clinic was originally built.
Connects new Head Start and existing Elderly buildings adjacent to the Clinic to the Ishkonige Nawadide Solar Microgrid
Applying for USDOE funds and using same financing strategy
Team is also working with the Bad River Housing Authority on Phase 3 Elderly Apartments and other infrastructure 1MW solar garden specifically for residential benefits Challenges are land availability and Utility capability
Miigwech! (Thank you)
Daniel Wiggins JrAir Quality Technician/ Renewable Energy
Mashkiiziibii Natural Resources Department
Ph: 715-979-1486
Email: [email protected]
mailto:[email protected]
Ishkonige Nawadide Solar Project UpdateBad River Band of Lake Superior Tribe of Chippewa IndiansOverview Phase 1: Ishkonige Nawadide �Solar ProjectIshkonige Nawadide �ObjectivesIshkonige Nawadide �DetailsOdanah CommunityIshkonige Nawadide �Planning & DevelopmentIshkonige Nawadide �Execution of ProjectAdministration WWTPHealth & Wellness CenterSlide Number 13Slide Number 14Ishkonige Nawadide �ChallengesIshkonige Nawadide �ChallengesIshkonige Nawadide �AccomplishmentsIshkonige Nawadide�Next StepsIshkonige Nawadide�Partners Long-term Planning Slide Number 21Phase 2: Giwiijiiwaaganinaan Gitigan Microgrid Project�Miigwech! �(Thank you)