17
IPTC 18062-MS Innovative Risk Management on the Barzan Onshore Project Robert E. DeHart II, RasGas Barzan Onshore Project Johnny Brand, JGC Barzan Onshore Project Copyright 2014, International Petroleum Technology Conference This paper was prepared for presentation at the International Petroleum Technology Conference held in Kuala Lumpur, Malaysia, 10-12 December 2014. This paper was selected for presentation by an IPTC Programme Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the International Petroleum Technology Conference and are subject to correction by the author(s). The material, as presented, does not necessarily reflect any position of the International Petroleum Technology Conference, its officers, or members. Papers presented at IPTC are subject to publication review by Sponsor Society Committees of IPTC. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the International Petroleum Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of where and by whom the paper was presented. Write Librarian, IPTC, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., fax +1-972-952-9435 Abstract The Barzan Gas Project is being developed by Barzan Gas Company Limited, a joint venture between Qatar Petroleum and ExxonMobil Barzan Limited, with RasGas Company Limited as the developer and operator. The project’s objective is the economic development of a high quality, reliable and fully integrated sales gas facility that further monetizes Qatar's North Field resources to supply gas to the domestic market for power generation and water desalination. JGC was awarded the Engineering, Procurement, and Construction (EPC) contract for the Barzan Onshore Project on January 1, 2011 for design, procurement, and construction of two of the largest natural gas processing trains in the world. The workforce on site has peaked with 29,500 workers from 45 countries representing 20+ languages. The project has displayed world-class Safety, Health, Environment and Security (SHE&S) performance due in part to its SHE&S Management System. For the EPC phase, the current Lost Time Incident Rate (LTIR) is 0.006 and Total Recordable Incident Rate (TRIR) is 0.169 based on 195 million man-hours worked as of October 1, 2014. Only six (6) Lost Time Incidents (LTI) have occurred project to date. Between July 11, 2012 and March 25, 2014, the project attained 130 million man-hours without an LTI. The paper provides an overview of four (4) areas that have significantly contributed to the success of the project. The areas include emergency response and coordination; medical management; man-machine interface and heat stress management. Although the areas are standard in most projects of this scale, the organisation, effectiveness and level of implementation are very unique, with pioneering work being done in certain elements within these areas.

IPTC 18062-MS - Innovative Risk Management on the Barzan Onshore Project (2 Oct 14)

Embed Size (px)

Citation preview

IPTC 18062-MS

Innovative Risk Management on the Barzan Onshore Project Robert E. DeHart II, RasGas Barzan Onshore Project Johnny Brand, JGC Barzan Onshore Project

Copyright 2014, International Petroleum Technology Conference This paper was prepared for presentation at the International Petroleum Technology Conference held in Kuala Lumpur, Malaysia, 10-12 December 2014. This paper was selected for presentation by an IPTC Programme Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the International Petroleum Technology Conference and are subject to correction by the author(s). The material, as presented, does not necessarily reflect any position of the International Petroleum Technology Conference, its officers, or members. Papers presented at IPTC are subject to publication review by Sponsor Society Committees of IPTC. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the International Petroleum Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of where and by whom the paper was presented. Write Librarian, IPTC, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., fax +1-972-952-9435

Abstract The Barzan Gas Project is being developed by Barzan Gas Company Limited, a joint venture between Qatar Petroleum and

ExxonMobil Barzan Limited, with RasGas Company Limited as the developer and operator. The project’s objective is the

economic development of a high quality, reliable and fully integrated sales gas facility that further monetizes Qatar's North

Field resources to supply gas to the domestic market for power generation and water desalination.

JGC was awarded the Engineering, Procurement, and Construction (EPC) contract for the Barzan Onshore Project on January

1, 2011 for design, procurement, and construction of two of the largest natural gas processing trains in the world. The

workforce on site has peaked with 29,500 workers from 45 countries representing 20+ languages.

The project has displayed world-class Safety, Health, Environment and Security (SHE&S) performance due in part to its

SHE&S Management System. For the EPC phase, the current Lost Time Incident Rate (LTIR) is 0.006 and Total Recordable

Incident Rate (TRIR) is 0.169 based on 195 million man-hours worked as of October 1, 2014. Only six (6) Lost Time

Incidents (LTI) have occurred project to date. Between July 11, 2012 and March 25, 2014, the project attained 130 million

man-hours without an LTI.

The paper provides an overview of four (4) areas that have significantly contributed to the success of the project. The areas

include emergency response and coordination; medical management; man-machine interface and heat stress management.

Although the areas are standard in most projects of this scale, the organisation, effectiveness and level of implementation are

very unique, with pioneering work being done in certain elements within these areas.

2 IPTC 18062-MS

1. INTRODUCTION

The Barzan Onshore Project is located in Ras Laffan Industrial City (RLC) in Qatar, and is situated on a green-field site. The

facilities are designed to receive full well stream fluids via two pipelines from offshore and process the fluids to final products

of; sales gas, ethane, propane, butane, condensate, and molten sulphur. This will be achieved through two gas processing trains

integrated with utilities and other onshore processing facilities.

As of October 1, 2014, the project has displayed world-class Safety, Health, Environment and Security (SHE&S) performance.

A comparison has been drawn between the project’s performance indicators and the International Oil & Gas Producers 2012

annual report1 (Global & Middle East Region), including Fatal Accident Rate (FAR), Total Recordable Incident Rate (TRIR)

2

and Lost Time Incident Rate (LTIR) 3.

Indicator* Barzan OGP Global OGP Middle East

FAR 0 0.005 0.004

LTIR 0.006 0.096 0.050

TRIR 0.169 0.348 0.204

* OGP data has been normalized from 1 million man-hours to 200,000 man-hours (OSHA reporting criteria)

Table 1: Barzan vs OGP Lagging Indicators

The project manpower peaked at 29,000 with a multi-cultural workforce of 45 nationalities, speaking 20+ languages. Although

projects of this magnitude are not uncommon in the region, there are numerous challenges in terms of safety, quality, and

production. At the same time, ample opportunity exists for great achievements in worker safety, project quality, and

production.

The project’s SHE&S performance is attributed to several factors and a good performance is typically indicative that the

foundation and pillars of the SHE&S management system are developed and implemented from the start. It is a common

practice in construction to evaluate and benchmark performance through lagging indicators, e.g. LTI free man-hours, LTIR,

TRIR, (shown in Table # 1 above). Good performance in lagging indicators is typically a clear indication that good

management systems are in place while leading indicators such as SHE&S training hours and the number of SHE&S audits

and close-out of audit actions may be lost in the world of figures and statistics.

This paper provides an overview of four (4) areas that have significantly contributed to the success of the project. The areas

include emergency response and coordination, health management, man-machine interface, and heat stress management.

Although implementation of programmes in these areas are standard in most projects of this scale, the organisation,

effectiveness, and level of implementation is unique, and pioneering work has been done in certain elements within these areas

which are shared on the following pages.

2. EMERGENCY RESPONSE AND COORDINATION

The Barzan Onshore Project’s emergency response and coordination have been planned as an essential part of the overall

SHE&S Management System. The innovative parts within this element includes a fully equipped rope and confined space

rescue team supported by excellent tools such as a central information hub (Security Operations Centre - SOC) and a central

coordination centre (Incident Coordination Centre - ICC).

Figure 1: Incident Coordination Centre and Security Operations Centre

1 OGP Publications, OGP Performance Indicators 2012 Data, Report # 2012s, June 2013, pp-42-43

2 TRIR = (Recordable Incidents)*200,000/Total Man-hours (as per OSHA report and record keeping criteria).

3 LTIR = (LTI’s)*200,000/ Total Man-hours (as per OSHA report and record keeping criteria).

ICC – Incident Coordination Centre SOC – Security Operations Centre

IPTC 18062-MS 3

A risk assessment for emergency preparedness was conducted at the start of the project which was used as the basis for the site

emergency response plan. The risk assessment included a review of the RasGas’ existing procedures followed by credible

scenario identification, consequence and probability definitions, risk assessment; hazard scenarios and proposed mitigation

measures, and a review of the interface and coordination with local emergency services. Some of the credible emergency

scenarios included injuries at site, rescue from height (up to 65 meters), confined space rescues, fires, labour unrest, and major

spill of hazardous materials, to list a few.

The assessment further reviewed details such as: manpower at site (including day and night shift), activities to be undertaken,

resources available which resulted in the development of the emergency preparedness and response plan. Once developed and

implemented, the plan has been tested regularly and periodically revised as required.

2.1 Emergency Coordination

Emergency coordination is carried out through the Security Operations

Centre (SOC) and the ICC. The SOC is a centralised hub that receives

and cascades information for incidents and emergencies at site. A single

emergency number has been provided for the project and widely

communicated at site. All emergencies and / or incidents are reported to

the SOC through the dedicated emergency number; once a call is

received, the SOC operators take action depending on the type of

information they receive. The typical actions include logging the

emergency call, activating emergency response teams, providing SMS

information to a fixed group, contacting key personnel and in some cases

activating the ICC and / or requesting support from external emergency

services.

The principal concept of the SOC is very similar to that of a courier service. The packages (information) are received at a

central point (SOC), where the information is sorted and distributed to the end user. In this manner, the information can

be sent and received by the intended recipients in the quickest and most accurate manner. The SOC is equipped with

multiple phone lines, radio communications, site layout drawings, weather stations, SMS (text) notification system,

internet and e-mail service and a back-up power supply. The SOC is also manned 24 / 7 with multiple operators who have

been trained in their responsibilities. The SOC supports other key activities and systems such as incident notification,

emergency response team activation, weather monitoring and reporting (including adverse temperature and wind) and

interface with external emergency services, including RLC emergency services and other RLC mutual aid resources.

The ICC is linked, but independent of the SOC. The ICC’s main purpose is

to provide a central point where responsible project management

representatives will meet and coordinate significant emergencies. Thus, the

ICC is activated based on the type of emergency, which normally requires a

relatively serious emergency, such as a rescue from height or an emergency

which requires outside emergency service support (severity and type of

emergency is classed under specific tiers). All key personnel have been

trained in major emergency management to help ensure they clearly

understand their specific roles and responsibilities. The ICC is equipped

similar

to the SOC, but with dedicated seats for relevant ICC designations such as the incident commander, deputy incident

commander, subcontractor management representatives and other key parties. The ICC is also equipped with dedicated

phones lines, radio communications, information boards for collecting information, call out lists and plot plans of the site.

Although the SOC and the ICC are typical elements within an emergency plan, the standard and level of implementation

on the project is unique and has proven to be highly effective. Due to the nature and scale of the project, both of these

facilities are fundamental to the overall success of emergency response. Approximately 3,000 calls have been logged in

the SOC project to date.

To illustrate the volume and type of the information managed by the SOC, the following typical emergency scenario is

illustrated: a pipe fitter sustains a laceration wound from a grinder. The SOC would require information such as: extent

of injuries, location of the injured person, access route to the location, nearest muster point, hazards present in the area,

responsible organisation, and cause of injury. This information will be collected at the SOC, packaged in the correct

manner and sent to the intended recipients. These “information packages” must be communicated to the correct personnel

Figure 2: SOC in action

Figure 3: ICC in Action

4 IPTC 18062-MS

at the correct time to ensure that emergency response and incident command and control take the proper action in any

given situation.

Thus, information management in the SOC (and the actions taken by the ICC in some cases) can quickly become a

complex and time-sensitive task. The SOC requires a very organised and systematic approach, as mistakes, or the “wrong

delivery” can mean that a non-serious injury or illness could escalate into a far more serious situation.

2.2 Emergency Response Teams

The main purpose of the emergency response teams is to act as first responders to site emergencies. They primarily focus

on medical emergencies, confined space and elevated rescues, monitoring workers for potential heat stress exposures

during the summer months, and support proactive inspections as part of safe work pre-planning activities.

The emergency response teams,

known collectively as the Project

Rescue Team (PRT), consists of a

ten (10) man rope rescue team and

a ten (10) man medical response

team, including an emergency

physician. Due to RLC land lease

and Qatar regulatory requirements,

JGC is permitted to provide first

response and first aid treatment

with further treatment provided by

RLC medical facilities and local

hospitals.

The PRT team is based at three (3)

locations, from which they can

mobilise within two (2) minutes to

any location at site. The team is

equipped with four (4) emergency vehicles and relevant tools and equipment to carry out first response and retrieval,

which includes specialised harnesses, ropes and emergency kits. The teams (ERS* North and ERS* South) are based

within the main construction area in the north and south sections of the construction site, respectively.

(*ERS – Emergency Response Station).

The teams carry out daily site tours, to ensure they are familiar with access routes, which change frequently due to

ongoing construction activities. Daily surveys are also undertaken for confined space activities and access points to

elevated areas (maximum rescue at height could be 60 meters). During the construction peak, over 500 confined space

permits were active on a daily basis, of which the PRT would evaluate and prioritize those considered the highest risk.

The “high risk” confined space rescue plans are prepared in advance of the work, with the PRT being an integral part of

this planning process. The team then visits the confined spaces during the course of the day and ensures compliance

through checklists to the project’s confined space and work permit procedures, and the relevant rescue plans.

The guiding principal for the PRT is that all rescues shall be “non-committal” in that a rescuer should not be exposed to a

fall or confined space hazard while undertaking a rescue. “Fail safe systems” are always in place when rope rescue

techniques are used, where the main rope is coloured blue and the safety rope is coloured red, which is standard

international rescue practice.

The PRT operates under a series of basic hierarchy of control, which includes;

1. Rescue from height hierarchy

Make work at height (WAH) as safe as practicable

Rescue from within collective controls, e.g. existing working platforms, scaffold, mechanically elevated working

platforms (MEWPS) and cranes

Rescue using work restraint techniques

Minimize the consequences of falls by using fall arrest equipment

Figure 4: Project Response Team

IPTC 18062-MS 5

2. Rescue from confined space hierarchy

Do not enter the confined space for rescue

Endeavour to engineer a solution to eliminate entry for rescue

Enter only when the access system can be reversed during rescue

The PRT is a very unique element within the project’s emergency response plan. This professional team has “individual”

strengths and “team” capabilities, which supplements the external emergency service provider capabilities. The key to the

success of emergency teams can be attributed to the level of expertise available within the organisation but also in the pro-

active and planning work that the teams carry out in preparation for emergency scenarios. Emergency coordination and

response work in tandem, and are a fundamental and integral part of site emergency planning.

2.3 Key Achievements

Since April 2013, there have been 20 rescues from height (two at the 40-metre level) and 445 calls for medical assistance

at the worksite. As part of rescue planning, the PRT has a confined space protocol established through the Permit to Work

office. The PRT performs site visits to confined space activity to become familiar with the activity, and to verify rescue

plans are in place. At peak construction, over 200 such visits have been done in a month. The team also does surveys for

access at height. An example is the safe erection of the 152-m flare, which was accomplished over a 50-day period. This

erection was done without the services of a professional abseil team.

Emergency Coordination

In terms of emergency coordination, the following key activities have been completed as of October 1, 2014:

2,995 emergency calls logged (SOC reports)

18 ICC call outs

Emergency Response Teams

For the PRT and MRT, the following key activities have been completed:

4,382 completed confined space entry and working at height task inspections

640 Confined Space Permit To Work Protocol surveys completed

737 training hours spent

24 rescues from height carried out

3. HEALTH MANAGEMENT

3.1 Introduction

Health management on the Barzan Onshore Project is a fundamental part of the overall organisation at the work site and in

the workers’ camps. The site manpower, which peaked at 29,000, can be compared to a small town. As such, health

management (including occupational and non-occupational health) is essential in the execution of the work and the well-

being of the workers for their camp living environment. Most of the project’s workforce has camp accommodations

which are located only five kilometres from the work site.

The welfare of workers is a top management priority, and the project’s worker welfare programme together with the level

of health care can be seen as good examples of what is possible with the commitment and the resources to ensure that

worker welfare is as important as the successful completion of the project.

The JGC Health Department has the capacity to handle diverse set of issues starting from common minor illnesses and

work related injuries, to occurrences of communicable diseases. It also has the ability to manage and track non-

communicable diseases such as hypertension, diabetes and cardiovascular disease.

The Project’s Health Department performs many important functions, such as: pre-employment screening, absence

management, fitness and return to work recommendations, health monitoring, counselling and rehabilitation, stress

management, heat stress management, drug and alcohol management, non-occupational acute and chronic disease

management advise, interface with regulatory bodies for medical issues, maintenance of medical records and

confidentiality, and data collection and recordkeeping. The Health Department is common and fundamental to any

6 IPTC 18062-MS

construction project. However, the nature, scale and the level of care provided by JGC’s facilities and organisation, with

support of RasGas and relevant subcontractor organisations, are unique to this project, particularly when considering the

level of worker care for the region.

3.2 System Overview

Risk Management

At the worksite, the major health and safety hazards identified on the project are associated with: excavation, formwork

and carpentry work, steel fixing, concrete casting, manual handling, transportation / traffic (personnel, material and

equipment), lifting and rigging (including heavy and critical lifts), scaffolding (erection, alteration, dismantling), working

at heights, confined space entry (excavations, vessels, pipes, tanks, storm water pits), radiography; transportation, storage

and use of gas cylinders; electrical, welding (carbon and stainless steel, pipes, flanges supports, structures), hydrostatic

and pneumatic testing; transportation, storage and handling of chemicals and hazardous materials, and mechanical

completions (vessel dry-out, air and steam blowing of lines and vessels, motor solo runs, mechanical test runs). These

hazards are not exhaustive, but highlight the most concerning ones.

The Health Risk Assessment (HRA) captures all project health hazards, from which specific actions are identified for

mitigation. The most common hazards identified through this assessment include communicable diseases and heat stress

due to the extreme Qatari weather (very hot and very humid). For this project, the 29/30 day Ramadan fasting period has

occurred during peak heat stress for the 2011-2014 seasons. Approximately 40% of the workers have been fasting and

working during this time which poses extreme health challenges for the fasting workers, and also the non-fasting workers,

supervision and management. During the summer months, the work activities at height and confined space pose increased

risks as recovery for potential heat illness victims becomes even more complicated and challenging.

Based on the control measures identified in the HRA, the Health Department, including the Industrial Hygienist, carries

out regular health monitoring with the focus on exposure limits and alcohol testing for occupational drivers and equipment

operators. The fitness for duty programme requires all newly employed personnel on the project to undergo a health

screening in the Site Medical Aid Centre (SMAC) where general fitness is evaluated and possible existing medical

conditions can be identified. JGC recognises that stress is a health and safety issue caused by pressures in the workplace,

and / or the stress for dealing with family issues at home. Excessive stress has the potential to directly impact the worker

and his co-workers as it increases the chance of incidents, can create poor performance and health issues. The project’s

Stress Prevention programme aims to assist workers in coping with their individual stress in a healthy manner. The

Ergonomic Control programme focuses on hazards that affect worker fatigue and discomfort, and aims to reduce the

potential for injury and ill-health, such as repetitive strain injury, carpal tunnel syndrome, musculoskeletal disorders and

back strain from improper lifting.

The following document controlled procedures provide the management framework for the programme:

Health Risk Assessment

Fitness for Duty (Health Screening)

Camp Operation and Maintenance Plan

Camp Health and Welfare Programme

Occupational Hygiene Programme

Respiratory Protection and Hearing Protection

Ergonomics Control

Heat Stress Management Programme

Incident Investigation and Reporting

Medical Case Management

Medical Aid Centre Management Plan

First Aid Unit Procedure for Patient Referral

Infection Control

Communicable Disease Risk Assessment

Stress Awareness and Prevention Programme

Potable Water Programme

IPTC 18062-MS 7

Alcohol and Drug Monitoring Programme

Safety Suggestion Programme

Absence Management Programme

Organisation and Resources

The organisation for the Health Department includes medical facilities at the site and the camps, as well as relevant health

personnel. On the project, the medical facilities includes a main site medical facility known as the SMAC, and the

Emergency Response Stations (ERS) within the construction areas known as ERS North and ERS South as noted earlier.

The project’s main camp areas also have dedicated MAC’s.

In accordance with Qatari regulatory requirements, the project medical

facilities may only provide first aid treatment, whereas primary,

secondary and tertiary care is given at the RLC clinics and local clinics

and hospitals. Thus, the project facilities are set up for first aid

provision and registered as such, although the health organisation

includes registered nurses and medical doctors. Not including sub-

contractor medical personnel, the overall contractor organisation

includes some 100 medical staff which includes nurses, doctors,

administrative and management personnel.

Data, information and recordkeeping management make up a large part of the health department’s organisation. The

volume of data and information the health facilities manage is immense and a patient history database captures all project

specific data. Once a new worker has joined the project and has passed his fitness to work examination, he is registered in

the database and all follow up consultations are logged into this database. Over 1.6 million records have been created for

personnel either joining (primary work force) or visiting the project (e.g. vendors, suppliers). Confidentiality to ensure the

privacy of the individuals is of utmost importance to the health department.

In addition to data management, the MAC’s facilitate medical care in case of illness. In many cases, this requires external

referral to the primary care or other facilities, whereby the patient is tracked and supported through the entire process.

The typical external communication includes those with RasGas and Ras Laffan Industrial Security, Emergency Services,

and Medical Services and facilities. With regards to patient health care, as appropriate, JGC is in in contact with the

Supreme Council of Health, Qatar Petroleum HSE Regulation & Enforcement Directorate, third party training providers

and testing and certification bodies, and sub-contractors and vendors. All formal communications with relevant external

parties are done in English. To ensure patients and injured parties with poor or no English language skills can

communicate with medical staff of public health care facilities, JGC and its sub-contractors require a designated medical

case manager (also, referred to as patient escorts) with a medical background, such as a nurse, to accompany the patient

and facilitate communication with the external medical providers.

Only registered medical staff (nurses and doctors) are allowed to physically review and treat patients. Once this process is

complete and referrals or other recommendations are made, the patient escort team will take over and follow up on the

treatment of patients. The process for illness is systematic; however, for injuries the process is very quick and begins

immediately once an injured person is brought into the medical facilities. Regular updates are provided to key personnel

including project management and the process only completes once the case file is closed and the relevant person is fully

fit and returns to his initial duties.

Figure 6: Consultation Area and Patient Escort Team

Figure 5: Site Medical Aid Centre (SMAC)

8 IPTC 18062-MS

In addition to the site facilities, the JGC managed camps within RLC each has its own medical facility, which includes

nurses and doctors, and an isolation unit for any communicable disease or cases requiring isolation. For communicable

illnesses, close coordination and strict policies and procedures are applied. The success of communicable disease

management relies upon the early identification and isolation of sick personnel.

Specific Health Issues

Communicable disease management is a very important function of the Health Department, even more so considering the

amount of personnel that reside together in the camp. Communicable diseases are a key health concern, and worker

health and hygiene must be closely tracked and managed. Ineffective management of communicable disease can be

detrimental to workers’ health and have a significant project impact. The management of communicable disease

fundamentally starts with surveillance and tracking of disease data, and ongoing observation and communication with the

workforce about hygienic practices and personal hygiene. In case a communicable disease is diagnosed, the relevant

government body is immediately notified. The patient would be isolated and relevant treatment provided. Weekly

inspections are done at isolation facilities to ensure that all procedural requirements are strictly followed and that sterile

and hygienic facilities are always available.

Barzan Onshore Project has an infectious disease control procedure, and if a communicable disease is diagnosed, certain

protocols would be followed. In case of certain communicable diseases, the following protocols have been established

and would be implemented upon diagnosis. The infected person’s room will be disinfected (as not to infect his

roommates) and close contact tracing of personnel is started. The infected person is isolated and again strict protocols are

followed, such as daily room cleaning, disposable bed linen, trained catering, security and medical personnel as well as

welfare provisions such as newspapers, books, internet access and TV are provided.

Absence management is another area that is important to track and control. With a peak workforce of 29,000 people, the

management of absent workers can be challenging. With accurate tracking, communication and policies, absence

management can improve the overall health of the workforce and the productivity of such personnel. Data is collected on

a monthly basis and shared with relevant EPC Contractor and sub-contractor project management. Workers with high

levels of absenteeism are reviewed and supported or counselled depending on the situation. Through this system, absences

have been managed at reasonable levels.

3.3 Key Achievements

The presence of the health department makes the safe and healthy execution of the work possible. In line with the

project’s goals for worker welfare, the workers’ health is a top project priority and the management of health is

accomplished through systematic, organised and sustainable resources and facilities.

The health department has managed the following project to date:

61,375 fitness to work exams

1,570,324 consultations carried out

898,860 daily alcohol screenings for classified positions

25,491 random alcohol screenings

737 communicable diseases identified, registered and managed

2,419 chronic illness patients identified, registered and managed

4. MAN-MACHINE INTERFACE

4.1 Introduction

The “Man-Machine Interface” programme is an essential part of the

safe execution of work at the Barzan construction site. With a

workforce of 29,000 and more than 5,000 vehicles and equipment at

site during peak, the risk of “man-machine” interface has been one of

the project’s higher risks requiring effective mitigation measures. The

frequency of exposure to the hazard of moving vehicles and

equipment is further compounded by the potential severity of contact

with the vehicles and equipment.

Figure 7: A Flagman Guiding Vehicles

IPTC 18062-MS 9

Using the lessons learned from a lost time incident (LTI), project

management re-tooled the “Man-Machine” programme to ensure that additional measures and controls were put in place

for the safe use of vehicles and equipment at the site. The system now includes several strict requirements and practical

control measures to help ensure the safety of workers near man-machine interfaces. Man-Machine interface has been and

will continue to be until project completion, a big challenge, especially from a behavioural perspective. With workers

from many different countries, backgrounds, and cultures, the control of equipment and personnel is a complex, daily

challenge with a basic safety message that has to be constantly re-enforced and re-communicated.

In addition to the interface, the use of heavy equipment and vehicles is a dangerous construction activity in itself. Heavy

equipment brings additional challenges, and the tough climatic and environmental conditions in Qatar further complicate

the use of this equipment.

For all things considered, Man-Machine interface is an area that requires a very organised and systematic approach to

ensure the safety of site personnel. The project continues to strive towards striking the correct balance between

prescriptive requirements, creative tools, strong leadership and frequent educational site wide reminders, which to date has

resulted in the Man-Machine interface being a success story.

4.2 System Overview

The Man-Machine interface programme has three main elements which include: the site interface, vehicle and equipment

inspections and maintenance, and safe driving. The requirements of these elements are clearly detailed within the EPC

contract which includes:

Development and implementation of a Transport and Pedestrian Safety programme to help ensure that workers

remain safe at all times.

In-Vehicle Monitoring Systems (IVMS) for all project vehicles, buses, tipper trucks and concrete delivery trucks to

track critical operating parameters and safe driver performance.

Hand held speed monitoring radars and static radar units deployed site wide to monitor maximum speed limits.

All project drivers are required to complete an eight-hour defensive driving course.

Daily alcohol testing for all vocational drivers and equipment operators including a fitness for duty check.

A plant and equipment inspection and maintenance programme to be managed through daily, monthly, quarterly and

annual inspections. At peak, this programme was in place for more than 5,000 units of plant and equipment.

A tipper truck control programme to ensure safe operation at the work site to help ensure the safe segregation of

people and heavy earthmoving equipment. As a note, all tipper trucks used on site are to be no more than 5 years old.

A bus rodeo programme to evaluate bus drivers’ skills and recognise the best safe drivers. All buses used be on the

project are to be no more than 10 years old; equipped with air conditioning and seat belts; and are overseen by bus

captains and line supervisory staff.

A heavy equipment rodeo programme for equipment operators and flagmen / banksmen to evaluate and recognise

operators and flagmen / banksmen. A flagmen/banksmen is assigned to each industrial vehicle / equipment at site.

A vehicle reduction programme to reduce the number of small vehicles on-site, and to promote the use of the drop-

off/pick-up bus service.

Implementation of a Traffic Violations Tribunal (TVT) which is based on a point system to adjudicate on site and

outside of site traffic safety violations. To date, more than 1,450 cases have been adjudicated by the TVT.

All vehicle and equipment usage is in full compliance with applicable national / international laws and regulations.

Site Interface

Site interface is managed primarily through the application of “separation” risk management techniques using barricades,

exclusion zones, flagmen and riggers (for lifting activities). A flagman receives specialty training for his daily work

routine that includes how to use two flags (a green flag for “go” and a red flag for “stop”), how to safely position himself

around vehicles / equipment and how to perform omni-directional monitoring. In addition, the flagman is provided with a

whistle and a high visibility vest to improve the equipment operator’s ability to locate the flagman. A critical element in

the process is that the flagman is trained with his equipment operator with the overriding principle that the flagman is in

control of the (vehicle) equipment’s movement. As the equipment moves around at site, the flagman will guide its

movement and ensure that the equipment’s route of travel is safe and eliminates the potential interface between the

equipment and pedestrians and nearby workers, and other equipment and structures.

10 IPTC 18062-MS

Apart from the physical control of the safe zone around the moving equipment, physical barricades have also been erected

to separate personnel and equipment from interface. Typically, barricades are erected on the side of the roads to create

clear road ways and working areas. High congestion areas are the bus pick up and drop off points at the worksite and in

the camps. These pick up points help ensure that 29,000 workers are being safely dropped off and picked up over the

course of the day. The bus loading and movements create a very high frequency of exposure requiring the installation of

Vehicle Interface Protection Units (VIPS) to help mitigate the risks. VIPS act as a physical barricade between passengers

or pedestrians and the vehicles or buses, and are installed at all drop off and pick up points at the worksite and camps.

Early in the project, a design for traffic signs and pedestrian crossings at the site and camps was implemented using old

tyres and scaffold tubes (which also supports the project’s environmental programme). The tube was secured inside the

tyre and relevant signs were then mounted on the tube. In this manner, the signs could be shifted when site conditions

changed. Pedestrian crossings have also been a major concern, and crossings have been equipped with stop signs to

emphasize that pedestrians always have the right of way at site. In addition to the signs and zebra crossings (either with

paint on the asphalted roads or temporary ropes on the dirt roads), traffic marshals are used at the crossings.

Traffic sign locations are updated on the plot plan and regular surveys are done to ensure that they remain current. Street

names are also placed on traffic signs, especially at intersections, and this supports the traffic arrangements at site and the

overall organisation of the construction site for equipment / material deliveries and road closures for construction works.

The surveys also include other elements of traffic safety and man-machine interface and reports are generated that are

transferred to responsible parties for follow up and closure. Although a robust system is in place, regular follow up and

emphasis are required to ensure that the integrity of the overall man-machine interface system is maintained.

The Bus Rodeo and Man-Machine Rodeo are programmes to focus on the improvement of key skills for bus drivers,

heavy equipment operators and flagmen. Due to the size of the site and its 29,000 workers, the interface between

equipment and machinery is an omnipresent risk. Both programmes provide for additional training for the participants

upon which they enter a tournament for skills evaluation via theoretical and practical tests. They are managed in different

phases which include initial evaluation on enrolment, training and then practical assessment of actual skills. The driver

and / or operator then receive grading by RasGas and JGC transportation and SHE professionals. The programme runs on

a 12-month cycle and top drivers and operators selected and receive a recognition award.

Figure 9: Rodeo Winners and Rodeo Assessment

Figure 8: Traffic Signs and Marshalls

IPTC 18062-MS 11

Vehicle and Equipment Inspection and Maintenance

A vehicle and equipment inspection and maintenance programme has been developed based on a risk-based approach, and

implemented on the project. During peak construction, the equipment and vehicles on the project exceeded 5,000. The

vehicles include buses, pick ups and other vehicles, and the equipment includes cranes, forklifts, manlifts, trucks, wheel

loaders, dump trucks, pumps and welding machines.

The vehicles and equipment have been split into five (5) main categories each with its own inspection frequency, third

party inspeciton requirements, checklist requirements and identification of inspections (stickers or color coding). For the

purpose of tracking and controlling, a database has been developed that captures all the relevant information of such

equipment including expiry dates based on the relevant requirements. The system has been streamlined in its use as

improvements were noted, and is now considered to be highly effective.

Apart from the regular inspections, spot checks are also carried out on a daily basis, whereby vehicle and equipment

issues are identified and captured. For the more serious issues, “Do Not Use Tags” are installed and the deviation has to

be corrected before the vehicle or equipment can be placed in service again. Monthly meetings are carried out with

management of the relevant subcontractor maintenance sections in which the status of the vehicle and equipment

inspections are reviewed, and key issues are discussed including a review of statistics on main deviations in the field.

Figure 10: Spot Check Inspection Data

As part of the EPC contract requirements, an annual review is performed on all

lifting and rigging equipment by an independent lifting and rigging company. The

review includes a physical inspection at site as well as a review of the procedural

and document requirements on the project. The review proves to be highly effective

as these specialist inspection teams are able to provide fresh eyes on the execution of

lifting and rigging activities. One of the major issues identified during the project

has been the maintenance and inspection of crane wire ropes mainly due to

previously mentioned wire rope failures. As part of the annual lifting and rigging

review, the specialist company also provides detailed training and certification on

wire rope inspection to all project inspectors. This training provides sufficient skill

and expertise to thoroughly inspect and maintain the crane wire ropes and avoid

recurrence of similar incidents. ANSI (American National Standards Institute)

charts are used in the assessment of wire ropes.

Safe Driving

In addition to the rodeo programmes and VIPS, IVMS are fitted on all project vehicles and mobile equipment. These

systems detect over-speeding, harsh breaking and sudden acceleration through satellite transponders. In case of

violations, the driver or operator is brought before the Traffic Violation Tribunal for possible disciplinary action. The data

is downloaded daily from the IVMS records and violations are identified and transferred to a register. The IVMS

combined with the TVT system has had very positive results on the project and more than 86+ million kilometres have

been driven without a serious traffic incident to date.

Figure 11: ANSI Wire Rope Inspection

Chart (Damage Tolerances)

12 IPTC 18062-MS

A programme has also been implemented to carry out alcohol screening for all vocational drivers and operators. The

programme helps ensure that very strict disciplinary actions are taken against violators. As part of the traffic management

system, a team also responds immediately to any traffic incident within RLC. The purpose is to help ensure the safety of

the involved parties, secure the scene, collect initial data and also carry out an alcohol test on the driver.

Figure 12: Road Traffic Incident (RTI) Scene Management and IVMS data

Apart from the IVMS data, practical measures are also implemented at site to control safe driving. Speed monitoring is

done on a random basis and fixed

monitors are also installed in strategic

locations to act as a deterrent for over-

speeding. Regular inspections and spot

checks are also carried out by Security

and Transport personnel to monitor safe

driving and violators are brought before

the TVT. The system has proven highly

effective and a high level of awareness

is present on the project related to traffic

safety.

4.3 Key Achievements

For the Man-Machine interface programme, some of the key achievements include:

7,300 plus vehicles and equipment inspected regularly over 3+ years of project life

1,976 IVMS units fitted with 2262 registered IVMS users

95.1 million KM driven without a serious incident

Over 2,000 flagman trained

300 participants in the bus rodeo programme and more than 1,600 participants in the man-machine rodeo programme

Over 50,000 multi-language (8 different languages) Pedestrian and Vehicle safety brochures published and issued site

wide

1,709 persons brought before the TVT with a total of 1,069 persons given counselling, 507 persons issued verbal and

written warnings and 26 persons issued with final written warning

Figure 14: Drivers Tool Box Talk and Site Man-Machine Interface

Figure 13: Speed Monitoring (Portable and Fixed)

IPTC 18062-MS 13

5. HEAT STRESS MANAGEMENT

5.1 Introduction

Qatar has a very hot and humid climate with summer temperatures ranging from 25C to 49C and an average relative

humidity of 75%. With a peak workforce of 29,000 persons performing multiple activities, heat stress must be managed

very carefully. The heat season officially required by Qatari authorities is April 1 – October 31, during which all heat

illnesses are to be reported to the government. The heat index (combination of humidity and temperature) may exceed

60oC during the peak summer months. Also, the Ramadan fasting period coincided with peak heat stress during the

construction of the project (2011-2014) with approximately 40% of the workers fasting and working during this period

which poses extreme health and safety challenges for the fasting workers, non-fasting workers and supervisory and

management personnel. Also, work activities at height and in confined spaces appreciably increase the risks as recovery

becomes more complicated and challenging.

The heat stress mitigation programme, updated each year with the requirement of refresher training for all personnel at

site, details key control measures as well as tools for monitoring effectiveness of the system. Control measures include:

training and education, balanced diets (including potassium rich food and drink supplements), cool drinking water,

acclimatisation (including fitness to work), local heat index monitoring, ample water stations and rest areas (many are air

conditioned), work rest cycles and stoppages of work, and the use of “cool garments” (e.g. cool vests, head covers, wrist

bands).

In accordance with Qatari labour law, fasting workers work fewer hours during Ramadan. Heat stress awareness is

promoted site-wide and workers and supervisors are expected to observe fasting workers for signs and symptoms of heat

illness or fatigue. All personnel are required to carry insulated water bottles as part of basic PPE requirements year-round

and are encouraged to have a healthy breakfast. Water parades are held on the buses to and from the work site and at the

start of work during Tool Box Talks and Task Instruction meetings and throughout the day. A water parade is a joint

activity where a group of workers drink water together as a reminder and reinforcement that adequate hydration is needed

throughout the day.

An acclimatisation period is required for new workers, vendors, visitors and workers returning from illness or extended

leave. New workers must acclimatize gradually over a period of one week (in line with the Qatari Directorate General

HSE Guidelines) before being allowed a full day of work. Workers who have been sick or are returning from leave must

be reviewed for fitness to work and undergo similar acclimatization periods depending on the type of illness and the

period of their illness. Heat Index (HI) monitoring is conducted throughout the day and night through a centralised site

weather station. Updates are communicated through text message and colour coded flags (representing different HI

bands) are then raised in all site areas to indicate the actual heat index. HI information boards are updated within the work

areas. Local monitoring is done with hand-held Kestrel monitors with work being executed according to pre-defined work

rest cycles based on the actual localized heat index reading.

All the control measures described below are monitored daily and performance reports are generated. During the hottest

summer months (May – September), weekly meetings are held with project management, including RasGas, JGC and all

sub-contractors, where key indicators are reviewed and evaluated, including pro-active indicators (e.g. daily inspections,

use of cool vests) and reactive indicators (e.g. heat illness trends and incident reports).

5.2 System overview

The heat stress prevention programme control measures consists of four (4) main categories which include engineering

controls, administrative controls, personal controls and control of high risk activities. Within these categories, control

measures are clearly detailed within the project procedures which includes shade, ventilation, work / rest cycles (based on

heat index monitoring), communication, fluid replacement, buddy system, acclimatisation, food, PPE, fitness to work,

heat stress monitors and control of high risk activities. These control measures are quite conventional; however for some

of the controls, unique features, outlined below, have been built into the programme.

Fluid replacement

A high level of focus is placed on hydration. To help condition site personnel to regularly hydrate and monitor their own

hydration levels, water parades have been implemented. A water parade is a joint activity where a group drinks water

together as a reminder and reinforcement to maintain adequate hydration while on the job site. These parades are

14 IPTC 18062-MS

typically conducted on the bus to and from the camp to the work site, at the tool-box talks and during Task Instructions

and rest breaks.

Acclimatisation

An acclimatisation period is a standard element within a typical heat illness prevention programme; however the Barzan

acclimatisation programme has been further enhanced to include detailed requirements for return to work from illness.

Table 2 provides information on the levels of acclimatization implemented on the project during the summer months.

Food

A balanced diet is encouraged and menus are carefully selected at camps to ensure site personnel receive adequate

nutrition to cope with the arduous task of working in extreme temperatures. In addition, supplementary food and drinks

are provided in the mess halls at the camps that are rich in potassium and electrolytes.

Personal Protective Equipment (PPE)

Throughout the year, a mandatory part of site basic PPE is to carry an insulated water flask. In 2014, the project invested

in cooling garments and some 30,000 cool vests were purchased for use at site. Two types of vests have been used:

‘evaporative cooling vests’ and ‘phase change vests’. The first type works on the basis of evaporation that cools the

fabric and in turn cools the user. The second type utilises a frozen polyurethane insert that is changed out when the solid

fluid turns to liquid. The vests have been considered partially successful, when used properly, except during a month-long

period with very high humidity conditions (60% and above). The phase change vests were most effective particularly in

high humidity conditions and were used for crafts such as welders who must work in an enclosed booth (welding habitat)

and must complete a weld once welding has started to achieve quality and integrity.

High Risk Activities

The key high risk activities during the heat stress period included working at height and working in confined spaces. For

work at height, work has been controlled by providing suitable and sufficient safe access to elevated areas. This has been

achieved by ensuring that access is provided with green tagged scaffolding or permanent structure to enable easier

movements up and down from elevated locations. The confined space entry work is only permitted if the heat index

within the space is less than 50oC and engineering controls such as ventilation are used. The entire site is shut down when

the heat index reaches 60oC. From 2013 experience, it was found that in the event the heat index reaches 60

oC, a

minimum of six (6) hours was required before the heat index dropped below 54oC and work was allowed to re-commence.

Table 2 – Acclimatisation Guidelines

IPTC 18062-MS 15

Heat Stress Monitors

Heat Stress Monitors (HSM) is nurses who are appointed during the heat stress period and monitor workers in the field.

Approximately 4,000 checks are performed each week by the monitors. Every check includes a questionnaire that

includes questions relating to heat illness and heat stress related symptoms. Data is then collated and monitored on a

weekly basis to identify possible trends and areas of concern.

Regular Review

Weekly review meetings with senior management are held to review the implementation status of the heat stress

programme as well as the lagging indicators from actual heat stress cases. The review meeting typically includes heat

index data compared to the previous years, a comparison of heat stress frequency rates and an analysis of illnesses that

occur. Actions are also developed during the meeting and the meetings help ensure that immediate steps are taken on

potential areas of concern and that valuable lessons are shared. Examples of the data are listed below.

Figure 15 – Heat index comparison (2012 / 2013 / 2014)

16 IPTC 18062-MS

Figure 16 – Heat index and frequency graph (2013 vs. 2014)

Figure 17 – Heat stress monitors data (key stats)

IPTC 18062-MS 17

5.3 Key achievements

The key achievements for 2014 include:

Refresher training carried out for approximately 29,000 persons on the 2014 programme

Approximately 48,000 surveys carried out in field

Cooling garments were distributed to over 29,000 persons on the project

Overall heat stress frequency rate in 2014 (per 200,000 man-hours) is 0.140 as of October 1, 2014

6. CONCLUSION

To date, the Barzan Onshore Project has delivered world-class SHE&S performance in keeping workers safe and has made

workers’ health, hygiene and welfare a top priority at the worksite and in the camps. Leadership and commitment by RasGas,

JGC and the sub-contractors’ senior management have ensured that a solid foundation has been laid for worker safety and

worker welfare, which are essential for any successful system and organisation and ultimately the success of the project.

Some of the key elements within the SHE&S Management programme that supported these achievements include the

Emergency Response and Coordination; Health Management; Man-Machine Interface programme; and the Heat Stress

Management programme. The project has numerous challenges to manage through mechanical completion with the remaining

activities. The focus to project completion remains on supporting the schedule and the safe delivery of the plant, through

proper planning and execution, continued engagement on site and ongoing communications.

Any major project is unique and creates a very dynamic and interesting working environment. The journey on the Barzan

Onshore Project is no exception and the importance of care and concern for the workers has truly helped drive the exceptional

SHE&S results. A testament of this is the manner in which workers engage with all levels of the organisation, as the barriers

of communication and hierarchy are removed. This is one of the less tangible but more significant achievements on the

project. The unique culture that has been established on Barzan will be entrenched in the memory of those who contributed

and invested their time as part of the project team, even more so than the SHE&S results that have been obtained by these

collective efforts.