New Fetter Place London EC43 London EC43 London EC42
262122323441
IntroductionLocationSchedule of AreasFloor Areas & PlansSpecificationLocal OccupiersContacts
New Fetter Place London EC4London EC41 London EC44
New Fetter Place is a new environmentally
designed development by Kirkbi Real Estate
Investments A/S which provides 92,000 sq ft
of Grade A office accommodation. The development is located opposite New Street Square in the heart of Midtown and is arranged around a central courtyard. The two buildings can be occupied separately or together via interconnecting bridge links.
The high quality architectural design provides occupiers with a stunning double height reception, panoramic lifts and fantastic views across Central London.
New Fetter Place London EC43New Fetter Place London EC4
New Commercial CourtNew Street Square Lincoln’s Inn Centre Point
2 3
New Fetter Place London EC4
This distinctive development has been designed
as two self contained but interconnected buildings
to provide maximum flexibility to occupiers.
The west building provides a unique opportunity
to acquire a self contained building of 15,000 sq ft
with its own dedicated reception, lifts and WCs.
54
New Fetter Place London EC4
Connectivity bridge
6 7New Fetter Place London EC4
The building has been finished to an exacting
standard throughout. The double height
reception area provides a fantastic sense of
light and space, which is continued throughout
the building. The concrete finishes give the
building a contemporary feel.
8New Fetter Place 9 London EC4
10 11New Fetter Place London EC4
12 13New Fetter Place London EC4
There is approximately 66,000 sq ft available in the
East building. Typical floors are just over 6,000 sq ft.
New Fetter Place London EC4New Fetter Place London EC4
Schedule of areas & site plan
Floor areas are indicative only.
14 15
Floor West East Totals sq ft sq ft sq ft sq m11 Let 10 Let 9 Let 8 Let 7 6,140 6,140 5706 6,139 6,139 5705 2,893 6,135 9,028 8394 3,070 6,154 9,224 8573 3,064 6,131 9,195 8542 3,064 6,144 9,208 8561 1,676 4,703 6,379 593G (Reception) 465 3,872 4,337 403LG 2,894 2,894 269B (Storage only) 547 3,326 3,873 360Total 14,779 51,638 66,427 6,171
New Fetter Place London EC4
New Fetter PlaceGround Floor3,872 sq ft / 360 sq m
Floor plans
Refuse/vehicle
Courtyard
Public Access
PublicAccess
PublicAccess
Bartletts Passage
NORTH
Office West Reception West Office East Reception East
16 17
New
Fetter Lane
Fetter Lane
New Fetter PlaceTypical second to fifth floor
New
Fetter Lane
Floor plans not to scale. For indicative purposes only
Office West Office East Bridge
NORTH
New Fetter Place London EC4
New Fetter Place London EC418 19New Fetter Place London EC4
Reception
Fantastic opportunity to acquire a fully
self contained building of 15,000 sq ft
New Fetter Place West14,779 sq ft / 1,373.8 sq m
5
4
3
2
1
G Office West Reception West
NORTH
Floor plans not to scale. For indicative purposes only
New Fetter Place London EC420 21New Fetter Place London EC4
Floor plans
New Fetter Place EastFirst floor4,703 sq ft / 437 sq m
New
Fetter Lane
Office East
NORTH
New Fetter Place EastSixth floor6,204 / 576 sq m
New
Fetter Lane
Floor plans not to scale. For indicative purposes only
New Fetter Place London EC4
Legal layout Second floorNIA 9,208 sq ft / 856 sq m
Reception 2Cellular 30Open plan 3Total headcount 35 Occupancy ratio per person1 person per 263 sq ft/24 sq m
Boardroom x 14 1Meeting room x 10 1Meeting room x 8 3Meeting room x 4 1
Financial East layout Sixth floorNIA 6,139 sq ft / 570 sq m
Reception 2Cellular 2Open plan 40Total headcount 44 Occupancy ratio per person1 person per 139 sq ft/13 sq m
Meeting room x 10 1Meeting room x 6 1Meeting room x 8 1
New
Fetter Lane
Bartletts PassageFinancial layout Second floor NIA 9,208 sq ft / 856 sq m
Reception 2Open plan 74Total headcount 76 Occupancy ratio per person1 person per 121 sq ft/11 sq m
Boardroom x 16 1Meeting room x 10 1Meeting room x 8 2Meeting room x 4 2
Corporate layout Second floor NIA 9,208 sq ft / 856 sq m
Reception 2Cellular 2Open plan 60Total headcount 64 Occupancy ratio per person1 person per 144 sq ft/13 sq m
Boardroom x 16 1Meeting room x 10 1Meeting room x 8 2Meeting room x 4 1
New
Fetter Lane
Bartletts Passage
New
Fetter Lane
Bartletts Passage
Space plans
22 23New Fetter Place London EC4
New
Fetter Lane
Office West Office East Bridge
NORTH
Floor plans not to scale. For indicative purposes only
New Fetter Place London EC4
Corporate East layoutSixth floorNIA 6,139 sq ft / 570 sq m
Reception 2Open plan 47Cellular 2Total headcount 51 Occupancy ratio per person1 person per 128 sq ft/11 sq m
Meeting room x 16 1Meeting room x 6 1Meeting room x 4 1Meeting room x 3 2
Legal East layoutSixth floorNIA 6,139 sq ft / 570 sq m
Reception 2Cellular 19Open plan 10Total headcount 31 Occupancy ratio per person1 person per 203 sq ft/19 sq m
Meeting room x 10 1Meeting room x 6 2
Space plans
Legal West layout Second floorNIA 3,064 sq ft / 285 sq m
Reception 1Cellular 11Open plan 4Total headcount 16 Occupancy ratio per person1 person per 192 sq ft/16 sq m
Meeting room x 8 1Meeting room x 6 1
Bartletts Passage
Financial West layoutSecond floorNIA 3,064 sq ft / 285 sq m
Reception 1Cellular 2Open plan 22Total headcount 25 Occupancy ratio per person1 person per 123 sq ft/12 sq m
Meeting room x 6 1Meeting room x 4 1
Bartletts Passage
New Fetter Place London EC424 25New Fetter Place London EC4
New
Fetter LaneN
ew Fetter Lane
Office West Office East
NORTH
Floor plans not to scale. For indicative purposes only
New Fetter Place London EC426New Fetter Place
1.0 Base Building Structure
1.1 Structure The office floors of the East building are generally reinforced concrete frame and slabs with lateral stability provided by the shear walls of the North and South cores. The Southern tip of the East building is concrete on metal decking supported on steel beams and columns tied back into the main concrete frame. The West building has composite metal deck floors supported by a braced steel frame. The floor to ceiling height on the typical floors of the East building is 2.6m and 2.7m in the West building. The upper 2 storeys have a floor to ceiling height of 2.8m. Raised floor void 150mm (110mm clear). Slab to slab height 3.7m (typical).
1.2 Superimposed loads – General office areas 3.5kN/m2. – Raised floor 1.2kN/m2. – Ceiling and services 0.4kN/m2.
– Partitions 1.0kN/m2.
1.3 Structural grid East building Perimeter concrete columns with two central columns and core with a 1.5m planning grid (typical). West building Perimeter steel columns with a 1.5m planning grid (typical). 1.4 External façades The East building is clad in black granite panels with projecting aluminium double glazed windows and insulated spandrel panels. The North core has exposed concrete fins and glazed windows to the panoramic lifts. The cladding to the West building is a combination of a rainscreen zinc panels system and a doubleglazed curtain walling with insulated spandrel panels.
2.0 Finishes 2.1 Entrance halls and lift lobbiesWalls Painted plasterboard, exposed concrete and feature wall finishes.Ceilings Painted plasterboard with a combination of recessed and feature lighting with decorative features.Floors Blue Bateig Limestone slabs.
2.2 Toilets in central core – Toilet provision based upon one person per 10m2. Net Internal Area
(60/60 % Male/Female).– Walls: timber panelling to East building, ceramic wall tiling
to West buildings.– Ceilings painted plasterboard.– Floors high quality porcelain tiles finish and matching skirting.– Shower facilities comprising one unisex shower and lockers in
basement changing area with finishes to match adjacent toilet areas.
2.3 Offices Walls plasterboard linings to core walls and columns decorated with paint finish.Ceilings fully accessible perforated metal tiles in a 1.5m grid. Floors fully accessible raised floor tile system with MDF skirting.
3.0 Mechanical Services
3.1 Design parameters External conditions – Winter -4°C. – Summer 29°C dry bulb 20°C wet bulb. Internal conditions – Office 22°C +/- 2°C Summer;
21°C +/- 2°C Winter.– Stairs 18°C Winter. – Toilets 18°C Winter. Central plant cooling and ventilation generally – 1:10m2 occupancy. – Fresh air 12 L/s/person. Internal heat gains – Lighting 10 W/m2. – Tenants’ small power 25 W/m2.
3.2 Air conditioning Offices and reception areas are provided with heating and comfort cooling via 2 pipe fan coil units with electric re-heat. All systems are controlled and monitored by a building management system.
3.3 Hot water installation Hot water generation is by the centralised gas fired hot water cylinders positioned in the basement.
3.4 Cold water installation Domestic water is provided from a potable water storage tank. Boosted water services are distributed via pumps to service risers and ducts to serve each range of sanitary appliance.Capped drainage and water is provided for the connection of Tenant services.
3.5 Toilet and shower change area ventilation Toilets on each floor level are mechanically ventilated by dedicated floor by floor extract systems providing 10 air changes per hour. The toilet make up air is pulled from the offices via dedicated ductwork.
3.6 Plumbing systems A complete water system is provided for all WCs each equipped with all plumbing fittings including low water flow WCs and counter-mounted basins. Flow WCs and counter-mounted basins. 4.0 Electrical Services
4.1 Design parameters– Offices 300 – 500 lux at desk top.– Circulation areas & Reception 200 lux.– Plant rooms 150 lux.– Staircases & Toilets 100 lux.
Specification
27 London EC4
4.2 Services description The building is served by a metered 11KV high voltage supply from the site wide Infrastructure. An internal Landlord owned sub-station provides an LV electricity supply via the 1500kva transformer for use in the building. Core areas, stairs, plant rooms, mechanical service plant, lifts and external lighting are arranged for metering as Landlord’s services and in accordance with Building Regulations Part L. In addition, each floor has a number of electrical riser cupboards from which the small power and lighting are capable of being sub-metered at Tenant’s cost.Electric meter is located on the HV service located in the South UKPN Substation. Generally sub-meters are located within the main risers or within the Landlords main switchboard. To accommodate floor by floor metering (in whole and part) for Tenants, meters are provided by an intelligent metering system and are integrated into the compositedistribution boards on the relative floor.
4.3 Small power insulation Office area Provision for small power services is covered by distribution boards located within the relative Tenant riser. Floor socket outlets are provided around the periphery to serve cleaning facilities. Outlets are located within the ceiling Void to serve office fan coil units, with supply derived from the local Tenant distribution board. General purpose 13 amp switched sockets are installed in core circulation areas for cleaning purposes. Spur units are installed in toilet areas for fixed equipment. 4.4 Internal lighting installation Integral lighting to the office areas is provided by high efficiency, high frequency, recessed modular dimmable fluorescent luminaires, with full LG7 compliance achieved by Tenant fit out. The main office lighting is supplemented by high frequency fluorescent LED down-lights around the perimeter of the office floor plates and compact fluorescent wall wash luminaires around the core circulation. Control of lighting in open areas is in accordance with Building Regulations Part L incorporating daylight energy efficient controls. Lighting is controlled by PIR sensors. Each floor is wired to allow work areas to be illuminated out of normal operational hours via the PIR arrangement. Staircases are lit with surface fixed, low energy efficient fluorescent luminaries. 4.5 Emergency lighting installation In the open plan office areas, emergency lighting is provided to B S 5266, Part 1 2005, which is the whole area and consists of conversion packs to the main office luminaries. Emergency lighting is also provided in toilets, circulation areas, staircases and plant rooms as appropriate. 4.6 Fire alarm installation – Means of escape occupancy standards – 1:10 m2.– The fire system is designed and installed in accordance with
B S 5839, Part 1 Category L3 as a system for the protection of life.– The system features automatic fire detection installed for the
purposes of life safety and also includes call points for manual actuation by occupants.
– Sprinkler protection is provided and installed to comply with the requirements of B SEN 12845, OH1 and additional requirements for a life safety system.
4.7 Telephone and data trays Within the communication risers, an appropriate sized cable basket is installed for future installation of telephones and data cabling by Tenant’s telecoms providers.
4.8 Reception areas Reception area is provided with fitted out reception desk, CCTV coverage and door intercom system.
4.9 Generators A single packaged generator is provided at roof level for life safety use only; space also allocated at roof level for a Tenant’s future back-up generator.
4.10 Lightning protection A complete lightning protection is installed utilising the steel structure as down-tapes to B S6651:1999.
5.0 Lifts
5.1 Passenger lifts BCO 2009 criteria of an up-peak average waiting time of 25 seconds will be achieved in the East building via four 13 persons [email protected]/s rated speed. Three 1000kg lifts will be semi – panoramic and one standard lift as a dual purpose passenger/fire fighting lift. The West building will be served by two 10 person electro traction lifts @ 1.6m/s rated speed. Door openings are suitable for disabled access. Lift cars are finished to the following specification: – Doors, frames skirting and fittings in stainless steel.– Walls: stainless steel, glass or mirror. – Floor: Limestone to match entrance halls.– Ceiling: reflecting or light coloured.
6.0 Parking Provisions
6.1 Covered bicycle spaces.
7.0 Sustainability
7.1 Environmental design Designed to achieve a BREEAM 2008 ‘Very Good’ standard and achieve an EPC ‘B’ Rating. 7.2 Energy An array of PVs is provided on the roof of the East building. 7.3 Waste Water consumption limited through sustainable supply and drainage systems. Waste recycling facilities provided for all occupants.
1:10Density
Occupation
62Covered bicycle spaces
24Hour Access
New Fetter Place London EC4New Fetter Place 28
Gray’s Inn Gardens
BO
UVERIE STREET
WH
ITEFRIARS STREET
Lincoln’s Inn Gardens
Lincoln’s Inn Fields
1
2 3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
31
32
33
28
29
30
34
35
36
37
38
39
40
41
42
43
44
45
46
51
52
4748
4950
Local occupiers
29 London EC4
Corporate
1 Aecom2 Weber Shandwick3 De Beers4 J Sainsbury plc5 Bechtel6 GDF Suez7 WSP Group8 Lexisnexis9 Unilever10 Thomson Reuters11 Towers Watson12 Genesis Oil and Gas13 Mitsubishi14 Capgemini
Professional
15 PWC16 KPMG17 Deloitte18 Crowe Clark Whitehill19 Pannell Kerr Forster20 Davis Langdon
Financial
21 Child & Co22 Goldman Sachs23 OBSt24 AXA Investment Managers25 Bank of New York Mellon26 Brewin Dolphin27 JP Morgan
Legal
28 Hogan Lovells29 Macfarlanes30 Bird & Bird31 Sullivan & Cromwell32 Beachcroft33 The Law Society34 Freshfields Bruckhaus Deringer35 Charles Russell36 Jones Day37 Baker Mckensie38 Wragge & Co39 Irwin Mitchell40 Lewis Silkin41 Taylor Wessing42 Speechly Bircham43 Dechert44 Weil, Gotshal & Manges
Media + Tech
45 Amazon46 Saatchi & Saatchi47 Skype48 Weber Shandwick49 Karmarama50 Grey London51 Media.com52 Hachette
New Fetter Place London EC4
New Fetter Place, in the heart of midtown, enjoys
a wealth of local amenities.
These include Hotel accommodation at Apex Temple Court hotel and Premier Inn Blackfriars and Gym facilities at Fitness First on Fetter Lane and two nearby Gymbox gyms. Nearby Clerkenwell and Farringdon provide an eclectic mix of vibrant restaurant and bars.
New Street Square, which is just opposite, also provides a varied and interesting array of shops, cafés and restaurants.
Amenities
30 31
New Fetter Place London EC4
Communications
Source: TfL
Waterloo line
Northern line
Piccadilly line
Crossrail
WalkBakerloo line
Victoria line
Central line
DLR
Rail
Heathrow Express
London Underground
Chancery Lane Bond Street
06 minutes
Chancery Lane Liverpool Street
06 minutes
12 minutes
Chancery Lane King’s CrossHolborn
Chancery Lane Bank
04 minutes
11 minutes
Chancery Lane WaterlooBank Liverpool StreetChancery Lane Stansted Airport
1 hour
13 minutes
Chancery Lane EustonOxford Circus
17 minutes
Chancery Lane PaddingtonOxford Circus
30 minutes
Chancery Lane City AirportBank
Oxford Circus Chancery Lane Heathrow Express
46 minutes
Farringdon Liverpool Street
02 minutes
Farringdon Canary Wharf
09 minutes
Crossrail
03 minutes
New Fetter Place Chancery Lane
New Fetter Place St Paul’s
10 minutes
New Fetter Place Farringdon
05 minutes
08 minutes
New Fetter Place Blackfriars
10 minutes
New Fetter Place Holborn
New Fetter Place Barbican
10 minutes
Walking distance
36 37
London EC4New Fetter Place 35 London EC4
MISREPRESENTATION ACT 1967 and PROPERTY MISDESCRIPTIONS ACT 1991 Cushman & Wakefield LLP, their clients and any joint agents, give notice that: (i) These particulars do not form part of any offer or contract and must not be relied upon as statements or representations of fact. (ii) No person in the employment of the agent(s) has any authority to make or give any representation or warranty whatever in relation to this property. (iii) Floor areas, measurements or distances given are approximate. Unless otherwise stated, any rents, or outgoings quoted are exclusive of VAT. (iv) Any descriptions given of the property cannot be taken to imply, it is in good repair, has all necessary consents, is free of contamination, or that the services and facilities are in working order. Interested parties are advised to carry out their own investigations as required. June 2014.
Holding and Investment company Kirkbi Real Estate Investments A/S
Project Manager Cushman & Wakefield LLP
Architect Tate Hindle Limited
Structural Engineer Hilson Moran Partnership
Contacts