Integration Progression Criteria Workshop 3/28/18
Simon CraigSystems Engineering
What’s it all about?
• This is a Workshop!!!– No Pass/Fail– Interactive discussion encouraged!!– Follow-‐up actions identified
• SIMs 1-‐7a (First Light Initiative)– Subsequent Workshops for SIM 7b onwards
• What is an Integration Progression Criteria (IPCs)– Defines an acceptable level of performance at a particular point in the IT&C activities.
Integration Progression Criteria Workshop: 3/28/18 2
Systems Integration Modules
3
• SIMs are not quite the same as the “phases” of DKIST SOWs
• SIMs are not strictly sequential
• Developed by engineers and a scientists
• Starting point is generating flowcharts, working with subsystem experts
• At the end of any given SIM, we may not have achieved any end science goals.
Integration Progression Criteria Workshop: 3/28/18
SIM BASIS
• The Systems Integration Modules are the basis for organizing the SOW
• Each of the 15 SIMs has a section in the SOW
4
SIM 1: Telescope Pointing MapSIM 2: M1 IntegrationSIM 3: M1 + M2 IntegrationSIM 4: M1 to M6 IntegrationSIM 5: Coudé Optics Plus FIDO IntegrationSIM 6a: VBI IntegrationSIM 6b: WFC IntegrationSIM 7: First Light Initiative, VBI+WFCSIM 8: GOS IntegrationSIM 9a: Cryo-‐NIRSP IntegrationSIM 9b: DL-‐NIRSP IntegrationSIM 9c: ViSP IntegrationSIM 9d: VTF IntegrationSIM 10: Polarization CalibrationSIM 11:Multi Instrument Verification
Integration Progression Criteria Workshop: 3/28/18
IPC Example: Pointing Map
5
1. SIM 1: Obtain a rough pointing map with the Target acquisition telescope (no M1 yet)
2. SIM 2: Obtain an improved pointing map after M1 is installed and forming an image at prime focus
3. SIM 3: Obtain an improved pointing map in the Gregorian focal plane
4. SIM 5: Obtain an improved pointing map in the coudé IT&C wavefront sensor's context viewer
5. SIM 6b: Obtain an improved pointing map with the WFCS Context Imager
Integration Progression Criteria Workshop: 3/28/18
IPC Example: Pointing Map
6
SIM 3: 7.2.3. Nighttime pointing map for Gregorian focal plane obtained.A nighttime pointing map shall be developed for the Gregorian focal plane utilizing the Gregorian focus wavefront sensor’s context viewer.
Integration Progression Criteria: The pointing map shall allow for the acquisition of stars so that they fall within the 30 arcsec field of view of the coudé IT&C wavefront sensor’s context imager.
Integration Progression Criteria Workshop: 3/28/18
IPC Development Example: First Light Initiative (FLI, SIM 7)
7Statement of Work -‐ NSF PEP/CS Review Sep 19-‐21, 2017
• FLI was loosely defined as obtaining the first diffraction limited images, but what does that mean in detail?
• Integration Progression Criteria must be detailed, measureable, and unambiguous.
• For FLI, the progression criteria negotiated between SysEngand science.
SIM 1 Telescope Pointing Map
SIM 1 Definition
9Integration Progression Criteria Workshop: 3/28/18
SIM 1: Pointing Map
10Integration Progression Criteria Workshop: 3/28/18
SIM 1: Target Acquisition Telescope
• Note 1.2.3 is not required for early SIM 2 activities. Thermal testing only.
11Integration Progression Criteria Workshop: 3/28/18
SIM 2 M1 Integration
SIM2 Definition
13Integration Progression Criteria Workshop: 3/28/18
M1 Coating IPC
14
Should be 2.2.1
M1 Coating IPC
15
Changed following discussion with TR. Document need updating
M1 Assy; M1 Aperture plate
16Integration Progression Criteria Workshop: 3/28/18
GIS
17Integration Progression Criteria Workshop: 3/28/18
Prime Focus Wavefront Error IPC
18Integration Progression Criteria Workshop: 3/28/18
Prime Focus Pointing Model
19Integration Progression Criteria Workshop: 3/28/18
SIM 3: M1 and M2 Alignment
M1+M2
21Integration Progression Criteria Workshop: 3/28/18
M1 and M2 Optically aligned, Wavefront error
22
M1 & M2 Optically aligned pointing map
23
TEOA GIS
24Integration Progression Criteria Workshop: 3/28/18
M1 and M2 Thermal Tuning
25Integration Progression Criteria Workshop: 3/28/18
SIM 4, M3-‐6 Install
M3-‐6 install
27Integration Progression Criteria Workshop: 3/28/18
M3-‐6 Thermal Testing and Tuning
28Integration Progression Criteria Workshop: 3/28/18
SIM-‐5 M8-‐9(FIDO not covered)
M8-‐9 Installed
30Integration Progression Criteria Workshop: 3/28/18
M7-‐9 aligned
31Integration Progression Criteria Workshop: 3/28/18
Coudé pointing Map, M7-‐9 Thermal Tuning
32Integration Progression Criteria Workshop: 3/28/18
SIM 6a: VBI
Confirm continuing compliance
34Integration Progression Criteria Workshop: 3/28/18
VBI Install
35Integration Progression Criteria Workshop: 3/28/18
VBI Alignment
36Integration Progression Criteria Workshop: 3/28/18
VBI Functional testing
37Integration Progression Criteria Workshop: 3/28/18
VBI Performance Testing
38Integration Progression Criteria Workshop: 3/28/18
SIM 6b: WFC
M5 Install
40Integration Progression Criteria Workshop: 3/28/18
Install
41Integration Progression Criteria Workshop: 3/28/18
Context Viewer Install
42Integration Progression Criteria Workshop: 3/28/18
LOWFS Install
43Integration Progression Criteria Workshop: 3/28/18
HOWFS Install
44Integration Progression Criteria Workshop: 3/28/18
WFC SystemTesting
45Integration Progression Criteria Workshop: 3/28/18
SIM 7a First Light Initiative
FLI IPC
47
Thank You!!!!