114
Initial Environmental Examination This report has been submitted to ADB by the Government of Tamil Nadu, Chennai and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB. Project Number: 40648-033 December 2014 IND: Infrastructure Development Investment Program for Tourism – Tranche 2 Submitted by Department of Tourism and Culture, Government of Tamil Nadu

Initial Environmental Examination - Asian …Tharangambadi), Nagapattinam District, Tamilnadu. Revised Initial Environmental Examination - Tharangambadi July 2014 IND: Infrastructure

Embed Size (px)

Citation preview

Initial Environmental Examination

This report has been submitted to ADB by the Government of Tamil Nadu, Chennai and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB.

Project Number: 40648-033 December 2014

IND: Infrastructure Development Investment Program for Tourism – Tranche 2

Submitted by

Department of Tourism and Culture, Government of Tamil Nadu

TABLE OF CONTENTS

EXECUTIVE SUMMARY………………………………………………… 03

1.0 INTRODUCTION

1.1 Background……………………………………….………………………. 07

1.2 Project Components……………………………………….……………… 07

1.3 Project Cost - Component Wise…………………………….………….… 07

1.4 Operation & Maintenance Cost………………………………………….. 08

1.5 Purpose of the IEE……………………………………………………….. 08

1.6 Environmental Regulatory Compliance………………………………….. 09

1.7 Report Structure ………………………………………………………….. 14

2.0 DESCRIPTION OF PROJECT COMPONENTS

2.1 Components & Need of the project………………………………………. 15

2.2 Proposed Facilities………………………………………………………... 15

2.3 Components of the Subproject…………………………………………… 17

2.4 Sanitray Complex…………………………………………………………. 17

2.5 Deployment Schedule……………………….……………………………. 18

3.0 DESCRIPTION OF THE EXISTING ENVIRONMENT

3.1 Environmental Profile ………………………………………….………… 19

3.1.1 Physical Characteristics……………………….…………….. 19

3.1.2 Accessibility ………………………………………………… 20

3.1.3 Physical & Geographical features ………………………….. 20

3.1.4 Trade and Commerce……………………………………….. 21

3.1.5 Administration……………………………………………… 21

3.1.6 Tourism Places………………………………………………. 22

TABLE OF CONTENTS

3.1.7 Socio-Economic Condition…………………………………. 23

3.1.8 Population Details………………………………………….. 24

3.1.9 Geomorphology and Soil Types……………………………. 24

3.1.10 Ground Water Quality……………………………………… 25

3.1.11 Ground Water Development……………………………….. 28

3.1.12 Ground Water Related Issues and Problems……………….. 28

3.1.13 Hydrogeology………………………………………………. 29

3.1.14 Ecological Resources………………………………………. 29

3.2 Environmental Profile – Site Specific …………………………………… 30

3.2.1 Description of Project………………………………………. 30

3.2.2 Site Details…………………………………………………. 30

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

4.1 Location Impacts…………………………………………………………. 31

4.2 Design Impacts and Pre-Construction Impacts ………………………….. 32

4.3 Construction Impacts …………………………………………………….. 33

4.4 Operation and Maintenance Impacts …………………………………….. 33

4.5 Cumulative Impact Assessment………………………………………….. 33

4.6 Environment Management Plan ………………………………………….. 36

5.0 ENVIRONMENTAL MANAGEMENT PLAN

5.1 Institutional Arrangements……………………………………………….. 37

5.2 Program Management …………………………………………………… 37

5.2.1 Safeguards Management…………………………………….. . 40

TABLE OF CONTENTS

5.3 Environmental Management Plan ………………………………………... 42

5.4 Envrionmental Monitoring Plan…………………………………………… 57

5.5 Capacity Building …………………………………………………………. 61

5.5.1 Target Audience………………………………………………. 61

5.5.2 Envirionmental Awareness Building…………………………. 66

5.6 Environmental Budget ……………………………………………………. 67

5.7 Environmental Monitoring and Reporting ……………………………….. 67

6.0 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

6.1 Process for Consultation followed ……………………………………… 69

6.2 Plan for Continued Public Participation ………………………………….. 69

6.3 Grievance Redress Mechanism …………………………………………… 73

7.0 FINDINGS & RECOMMENDATIONS …………………………………… 75

8.0 CONCLUSIONS …………………………………………………………….. 76

List of Tables

Table 1 Applicability of Acts and Ruels………………………………… 09

Table 2 Sanitary complex Location……………………………………… 17

Table 3 Population Details & Tourist Inflow……………………………. 24

Table 4 Air Quality Monitoring …………………………………………. 26

Table 5 Noise Level Monitoring…………………………………………. 26

Table 6 Water Quality……………………………………………………. 26

Table 7 Environmental Management Plan……………………………….. 43

Table 8 Environmental Monitoring Plan………………………………….. 58

TABLE OF CONTENTS

Table 9 Traning Modules For Environmental Managment……………….. 62

Table 10 Envrionmental Budget…………………………………………… 67

Table 11 Consultations with Local Community……………………………. 71

List of Figures

Figure No. 1 District Map …………………………………………………… 19

Figure No. 2 Danish Fort…………………………………………………… 22

Figure No. 3 Danish Museum………………………………………………. 23

Figure No. 4 New Jerusalem Church……………………………………….. 23

Figure No. 5 Zion Church…………………………………………………… 23

List of Appendix

Appendix 1……Contract Clauses To Be Integrated Into Bid Documents…… 77

1.0 Construction of Sanitary Complex………………………………………. 77

2.0 Provision of Deep Earth Bins……………………………………………. 80

3.0 Provison of Street Lighting……………………………………………… 80

4.0 Installation of Signage’s…………………………………………………. 82

5.0 Provision of Street Furniture’s…………………………………………... 83

6.0 Improvements to Dansborg Fort…………………………………………. 83

7.0 General ………………………………………………………………….. 84

Appendix 2…………Rapid Environmental Assessment (REA) Checklist…… 95

Appendix 3…………Deployment Sequence of Key Experts ……………….. 102

Appendix 4…………Environmental Monitoring Format……………………. 104

Appendix 5…………Sample Grievance Registration Form…………………. 106

Initial Environmental Examination Construction of sanitary complexes for the floating population, placement of gravity entailed

deep earth bins for garbage collection (2.5 cubic meters), Placement of energy efficient

heritage street lighting, Placement of tourism friendly uniform signage’s for convenience of

the tourists and Placement of street furniture such as litter bins & benches and Conservation &

Restoration of Dansborg Fort for the comforts of travelling tourists in Tranquebar

(Tharangambadi), Nagapattinam District, Tamilnadu.

Revised Initial Environmental Examination - Tharangambadi

July 2014 IND: Infrastructure Development Investment Program for Tourism (IDIPT) — Project 2: Tamil Nadu ADB Loan: 2833 IND Prepared by the Government of Tamil Nadu for the Asian Development Bank

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 3 [[[[ [

ABBREVIATIONS

ADB - Asian Development Bank

CPCB - Central Pollution Control Board

CRZ - Coastal Regulation Zone

CPHEEO – Central Public Health and Environmental Engineering Organization, GoI

DOT - Department of Tourism

DSC- Design and Supervision Consultants

EIA - Environmental Impact Assessment

EMP - Environmental Management Plan

IEE - Initial Environmental Examination

PIU- Project Implementation Unit

PMU - Project Management Unit

RCC - Reinforced cement concrete

ROW - Right-of-way

SPS - Safeguard Policy Statement

TA - Technical Assistance

TNPCB – Tamil Nadu Pollution Control Board

TTDC - Tamil Nadu Tourism Development Corporation

WEIGHTS AND MEASURES

ha – Hectare

km – Kilometer

m – Meter

mm – Millimeter This initial environmental examination is a document of the borrower. The views

expressed herein do not necessarily represent those of ADB's Board of Directors,

Management, or staff and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document, the

Asian Development Bank does not intend to make any judgments as to the legal or other

Status of any territory or area.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 4 [[[[ [

EXECUTIVE SUMMARY

1. Tharangambadi (formerly Tranquebar) is a Town Panchayat in Nagapattinam

district in the Indian state of Tamil Nadu, 15 km north of Karaikal, near the mouth of a

distributary of the Kaveri River. Tharangambadi is the headquarters of Tharangambadi

taluk. Its name means "place of the singing waves". It was a Danish colony from 1620

to 1845, and in Danish it is still known as Trankebar.

2. Description of the Project: The India Infrastructure Development

Investment Program for Tourism (the Investment Program) envisages

environmentally and culturally sustainable and socially inclusive tourism

development in the project states of Himachal Pradesh and Punjab, Tamil Nadu

and Uttarakhand, delivered through a multi-tranche financing facility (MFF)

modality. Project 2 includes the states of Uttarakhand and Tamil Nadu.

3. Description of the Subproject: (i) Conservation and Restoration of Dansborg

Fort (ii)Provision of sanitary complexes for the floating population, (iii) Placement

of gravity entailed deep earth bins for garbage collection, (iv) Placement of energy

efficient heritage street lighting, (v) Placement of tourism friendly uniform

signages for convenience of the tourists and (vi) Placement of street furniture such

as litter bins and benches for the comforts of travelling tourists

4. The IEE was based on a careful review of subproject site plans and reports defined

management plans; field visits, and secondary data to characterize the

environment and identify potential impacts; and consultations/ discussions with

stakeholders. An environmental management plan (EMP) outlining the specific

environmental measures to be adhered to during implementation of the subproject

has been prepared. Subprojects will provide needed environmental and tourist

infrastructure to improve the environmental management and quality of the sites

towards preserving their ecological and cultural integrity. The subproject will

conform to all Government regulations, policies, and standards, as well as Asian

Development Bank’s Safeguard Policy Statement (2009).

5. Categorization of Projects and Activities:

(i) Under the EIA Notification, 2006 promulgated under Environment

(Protection) Act 1986 of the MOEF, Govt of India, all developmental

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 5 [[[[ [

projects and activities listed under the schedule of the Notification are

broadly categorized in to two categories - Category A and Category B, based

on the spatial extent of potential impacts on human health and natural & man

made resources.

(ii) All projects or activities under Category ‘A’ in the Schedule, including

expansion and modernization of existing projects or activities and change in

product mix, shall require prior environmental clearance from the Central

Government in the Ministry of Environment and Forests (MoEF) on the

recommendations of an Expert Appraisal Committee (EAC) to be constituted

by the Central Government for the purposes of this Notification;

(iii) All projects or activities under Category ‘B’ in the Schedule, including

expansion and modernization of existing projects or activities as specified in

sub paragraph (ii) of paragraph 2, or change in product mix as specified in

sub paragraph (iii) of paragraph 2, but excluding those which fulfill the

General Conditions (GC) stipulated in the Schedule, will require prior

environmental clearance from the State/Union territory Environment Impact

Assessment Authority (SEIAA). The SEIAA shall base its decision on the

recommendations of a State or Union territory level Expert Appraisal

Committee (SEAC) as to be constituted for in this Notification. In the

absence of a duly constituted SEIAA or SEAC, a Category ‘B’ project shall

be treated as a Category ‘A’ project;

6. Considering the likely impacts and subproject location which does not pass

through or is located near any national park, wildlife sanctuary, reserved forests,

or any other ecologically sensitive area, it is concluded that no adverse impacts

will result due to the proposed project. Further, no archaeological/protected

monument ( other than Dansforg Fort and Jerusalem Church) is located in the

vicinity of the project sites. The subproject is not listed under the Schedule and

hence is exempted from environmental clearance of MOEF. Hence, the subproject

is classified as Category-B in compliance to the ADB Safeguard Policy Statement

(2009).

7. The likely environmental impacts of the project are not significant and at Category

B level, as per ADB's Safeguards Policy Statement. The specific measures stated

in the EMP will address all adverse environmental impacts if any due to the

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 6 [[[[ [

subproject.

8. The selection of components are consistent with the subproject selection criteria

outlined in the Environmental Assessment and Review Framework (EARF) aimed

at enhancing protection of these sites and enhancing their environmental quality.

Subprojects are consistent with defined management plans designed to protect

environmentally sensitive and cultural locations. Management plans guided

subproject design and location; therefore, all proposed facilities in natural areas

are located outside sensitive areas and sited in designated tourist development

zones.

9. Impacts are readily mitigated through careful sitting, specific selection

criteria for procuring contractors with demonstrated experience; execution of

proven mitigation measures during the design; and adoption of good engineering

practices during construction and implementation. A detailed monitoring plan

prepared as part of this IEE will further mitigate negative environmental impacts

during implementation.

10. Potential induced impacts are addressed through the following: (i)

awareness- building of local management plans at proposed sites specifically

addressing the need to regulate tourism related development and planning in the

area through coordination with related Government Departments and local land

use committees; and (ii) project-supported environmental awareness campaigns in

surrounding communities to encourage participatory sustainable development

consistent with eco-tourism principles and in compliance with the state's tourism

policy ecotourism aspects.

11. The Investment Program includes upfront and on-going supervision and training

assistance for environmental monitoring reporting in project management

structures. The effective implementation of the measures proposed will be ensured

through the building up of capacity towards environmental management within the

project management unit (PMU) supplemented with the technical expertise of a

Safeguards Specialist as part of the Design Supervision Consultants (DSC) and

Project Management Consultants (PMC). Further, the environmental monitoring

plans provide adequate opportunities towards course correction to address any

residual impacts during construction or operation stages.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 7 [[[[ [

12. The Project 2 includes additional environmental awareness-building to raise

conservation values consistent with management plans and Tamil Nadu’s

environmental and tourism policies (which emphasize ecotourism) amongst local

communities and local governments in order to ensure future sustainable

development in and around these locations.

13. Anticipated Impacts and Mitigation Measures: All pre-construction,

construction, and operation activities that are likely to cause environmental

impacts were identified, and evaluated to assess their magnitude, duration, and

potential receptors in consultation with the stakeholders. Consultations were held

with the government representatives (Tamilnadu Tourism Department, Town

Panchayat Office, Tharangambadi division) and local communities. Accordingly,

an EMP has been prepared to mitigate any adverse impacts that may occur during

implementation of the project.

14. Conclusion: In the light of the foregoing, this initial environmental examination

(IEE) ascertains the temporary impacts likely to arise during various stages of

implementation of the project could be eliminated / mitigated through proper

implementation of EMP as outlined in the report. Hence, the subproject is unlikely

to cause any significant environmental impacts. No need for undertaking detailed

EIA is envisaged.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 8 [[[[ [

1.0 INTRODUCTION

1.1 Background

1. The proposed Project 2 (the Project) targets enhanced economic growth and

provision of livelihood opportunities for local communities through tourism

infrastructure development with a focus on preservation and development of natural

and cultural heritage and incidental services. The Project supports the states of

Uttarakhand and Tamil Nadu to develop the tourism sector as a key driver for

economic growth.

2. The Project aims to enhance contribution of the tourism industry to sustainable and

inclusive economic growth for each participating state. Increased visits of domestic

and international tourists to tourist destinations within each participating state would

be the outcome of the Project.

1.2 Project Components - Project activities aims at

(i) Improvements to Dansborg Fort

(ii) Construction of sanitary complexes for the floating population,

(iii) Placement of gravity entailed deep earth bins for garbage collection,

(iv) Placement of energy efficient heritage street lighting,

(v) Placement of tourism friendly uniform signages and

(vi) Placement of street furniture

1.3 Project Cost - Component Wise

Sl. No. Description Amount (Rs. in lakhs)

1 Improvements to Dansborg Fort 432.00

2 Sanitary complexes (3 Nos.) 51.06

3 Gravity entailed deep earth bins for garbage collection (10 Nos.)

12.30

4 Aesthetic energy efficient heritage lighting(10 Nos) 5.04

5 Retro-reflective road signage Details. (8 Nos.) 13.45

6 Street furniture - Benches (6 Nos.), litter bins (100 Nos)` 7.76

Total 521.61

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 9 [[[[ [

Various Designs / Types of Sanitary Complex (S1, S3, S4, S5, S6, S7 & S8) and Deep Earth Bins has been enclosed in Annexure – A (Common for all locations)

1.4 Operation & Maintenance Cost

1.5 Purpose of the IEE

1. This Initial Environmental Examination (IEE) assesses a subproject under Project 2

for the state of Tamil Nadu, ‘Construction of sanitary complexes for the floating

population, placement of gravity entailed deep earth bins for garbage collection (2.5

cubic meters), Placement of energy efficient heritage street lighting, Placement of

tourism friendly uniform signages for convenience of the tourists and Placement of

street furniture such as litter bins, and benches for the comfortable travelling of the

tourists in Tharangambadi Town Panchayat , Nagapattinam District, Tamilnadu. The

IEE was based on a careful review of subproject site plans, detailed design and reports

defined management plans; field visits, and secondary data to characterize the

environment and identify potential impacts; and consultations/discussions with stake

holders.

2. An environmental management plan (EMP) outlining the specific environmental

measures to be adhered to during implementation of the subproject has been prepared.

These EMPs will be appended to the respective contract documents to enable

integration of environmental provisions in the contract. The IEE goes further and

provides sample contract clauses (Appendix 1) to be added to contract documents.

Subproject will provide needed environmental and tourist infrastructure to improve

the environmental management and quality of the sites towards preserving their

ecological and cultural integrity. The subproject will conform to all Government

Sl. No. Description Amount (Rs. in lakhs)

1 Sanitary complexes 2.55

2 Gravity entailed deep earth bins for garbage collection 10.00

3 Aesthetic energy efficient heritage lighting 0.25

4 Retro-reflective road signage Details. 0.68

5 Street furniture such as Benches and litter bins 2.30

Total 15.78

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 10 [[[[ [

regulations, policies, and standards, as well as Asian Development Bank’s Safeguard

Policy Statement (2009).

3. In accordance with ADB’s Safeguard Policy Statement (2009), the project

belongs to Category “B” as no significant impacts are anticipated.

1.6 Environmental Regulatory Compliance

1. The realm of environmental regulations and mandatory requirements for the

proposed subproject is shown in Table 1.The EIA Notification (2006) by the

Government of India Ministry of Environment and Forests (MOEF) specifies the

mandatory environmental clearance requirements. Accordingly, all projects and

activities are broadly categorized in to two categories1 - Category A and

Category B, based on the spatial extent of potential impacts and potential

impacts on human health and natural and man-made resources.

Various policy guidelines, acts and regulations pertaining to sustenance of

environment those applicable to various developmental projects have been presented

in the following section.

Table: 1 Applicability of Acts and Rules

Sl. No Acts / Rules Year Compliance Criteria

1 Environmental (Protection)

Act 1986

This act is applicable all environmental

notifications, rules and schedules are issued under

this act.

2 Environment Impact

Assessment Notification 2006

As per the notification, Projects categorized as A

& B need prior Environmental clearance from the

Central and State Expert Appraisal Committee

respectively. But, this Sub-project does not come

under the purview of the above categories

hence this notification is not applicable.

3 Forest Conservation Act 1927

1980

This Act will be applicable in case the proposed

project road is passing through the Forest Areas

which requires the diversion of forest land to the

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 11 [[[[ [

Sl. No Acts / Rules Year Compliance Criteria

non-forestry purposes.

This is not applicable as there is no forest land

involved for the project development.

Permission and clearance for cutting and

transportation of trees will be required from

Divisional Forest Officers, which is not applicable

for this sub-project.

4 Wild Life (Protection) Act 1972

This act will be applicable in case the project road

traverses through wildlife protected areas for

which permission will be sought from National

Board for wildlife.

This is not applicable as there is no wildlife

protected area is involved for the project

development.

5

Coastal Regulation Zone

Notification

1991

2011

• Buildings shall be permitted only on the

landward side of the existing road, or on the

landward side of existing authorized structures;

• Buildings permitted on the landward side of the

existing and proposed roads or existing

authorized structures shall be subject to the

existing local town and country planning

regulations including the ‘existing’ norms of

Floor Space Index or Floor Area Ratio, Provided

that no permission for construction of buildings

shall be given on landward side of any new

roads which are constructed on the seaward side

of an existing road

6 Water (Prevention and

Control of Pollution) Act 1974

The Sub-projects require consent to establish from

the State Pollution Control Board if it involves

discharge waste water from labour camps which is

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 12 [[[[ [

Sl. No Acts / Rules Year Compliance Criteria

applicable during construction phase of the

project.

But, it is being ensured that no discharges will

be there to any inland water bodies or

sea/ocean, hence this Act will not be applicable.

Moreover, the excreta from the toilets will be

collected in septic tanks/soak pits ensuring no

discharges to water bodies.

7 Air (Prevention and Control

of Pollution) Act 1981

The project requires consent to establish from the

State Pollution Control Board if it involves

operation of Hot Mix Plants and Diesel Generator

Sets. This act will be applicable to the project

during construction phase of projects as use of DG

sets is being envisaged.

8 Noise Pollution Regulation

and Control Act 1990

The project requires consent to establish from the

State Pollution Control Board if the noise level

from the construction machinery and the vehicles

are above the standards. This act will apply to the

project especially during the construction phase if

such machineries will be used which is unlikely.

9 Land Acquisition Act 1894

1989

This act will be applicable in case land is being

acquired for the project road.

This act will not be applicable as no land

acquisition is required for the project

development. The project is being developed on

Town Panchayat owned land.

10

Ancient Monuments and

Archaeological Sites and

Remains Act

1958

This act is applicable is case of any chance finds

during construction phase of the project which

may be remains/ monuments which are deemed to

be protected by ASI or the State Directorate of

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 13 [[[[ [

Sl. No Acts / Rules Year Compliance Criteria

Archaeology .

This act will not be applicable as no

archeological sites are affected because of the

project development. However, provision has

been made so that chance found ancient

properties are protected.

11

The Hazardous Wastes

(Management, Handling

&Tran boundary

movement) Rules,

1989

2003

2008

These rules will be applicable if contractors

during construction phase will store and handle

hazardous material such HSD and paints etc. But,

the EMP spells that all such materials will be

procured from licensed depots and consumed

immediately so storage is ruled out.

12 The Explosives Act (&

Rules)

1884

1983

This Act specifies regulations regarding the use of

explosives and precautionary measures while

blasting and quarrying. Provisions of these rules

are not applicable to this project as materials

will be procured from 3 rd party licensed

holders.

� Further, for sand, soil and stone quarrying, prior permission is to be obtained from the

state authorities for the purpose. However, considering the project profile, it is

preferred to procure materials from the licensed third party owners.

� However, considering the kind and quantum of activities, it is envisaged that no borrow

areas and quarry sites will be established as a part of activity / sub project. Raw

materials will be procured from licensed quarry owners. Similarly, no crusher sites will

be opened by the contractor. Also, No borrow area shall be made available by the

Employer for this work. The arrangement for the source of supply of the material for the

civil works shall be the sole responsibility of the Contractor.

� But, the contractor might be using DG sets for which the permission will be required

under Air act 1981.

� No fuel storage takes place in this project and for construction purposes, the fuel shall

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 14 [[[[ [

be procured from the existing petrol bunks

� For labour accommodation, no labour camp will be established and for accommodation

of labours nearby construction sites, rented houses will be engaged by the contractor.

2. All projects or activities included as Category A in the Schedule, including

expansion and modernization of existing projects or activities and change in product

mix, will require prior environmental clearance from the Central Government in the

Ministry of Environment and Forests (MOEF) on the recommendations of an Expert

Appraisal Committee (EAC) to be constituted by the Central Government for the

purposes of this notification.

3. All projects or activities included as Category B in the Schedule, including

expansion and modernization of existing projects or activities as specified in sub

paragraph (ii) of paragraph 2, or change in product mix as specified in sub

paragraph (iii) of paragraph 2, but excluding those which fulfill the General

Conditions (GC) stipulated in the Schedule, will require prior environmental

clearance from the State/Union territory Environment Impact Assessment Authority

(SEIAA). The SEIAA will base its decision on the recommendations of a State or

Union territory level Expert Appraisal Committee (SEAC) as to be constituted for

in this notification. In addition, GC of the notification specifies that any project or

activity specified in Category B will be treated as Category A, if located in whole

or in part within 10 km from the boundary of (i) protected Areas notified under the

Wild Life Protection) Act, 1972, (ii) critically polluted areas as notified by the

Central Pollution Control Board from time to time, (iii) notified eco-sensitive areas,

and (iv) inter-State boundaries and international boundaries.

4. Level of environmental assessment required for each category of Project, as per

ADB’s Safeguard Policy Statement (2009) is as follows:

• Category A. Subproject components with potential for significant adverse

environmental impacts. An environmental impact assessment (EIA) is required

to address significant impacts;

• Category B. Subproject components judged to have some adverse

environmental impacts, but of lesser degree and/or significance than those for

Category A projects. An initial environmental examination (IEE) is required

to determine whether significant environmental impacts warranting an EIA are

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 15 [[[[ [

likely. If an EIA is not needed, the IEE is regarded as the final environmental

assessment report.

• Category C. Sub-components unlikely to have adverse environmental impacts.

No EIA or IEE is required, although environmental implications are still

reviewed.

5. The above table indicates that the proposed subproject will comply with necessary

government regulations and ADB's Safeguard Policy Statement (2009). ADB's

Safeguard Policy Statement (2009) stipulates addressing environmental concerns, if

any, of a proposed activity in the initial stages of project preparation. For this, the

ADB guidelines categorize the proposed components into categories (A, B or C) to

determine the level of environmental assessment required to address the potential

impacts. The subproject has been categorized as B.

6. Accordingly this IEE is prepared to address the potential impacts, in line with the

recommended IEE content and structure for Category B projects. The IEE was based

mainly on secondary sources of information and field reconnaissance surveys and

stakeholder consultations. Stakeholder consultation was an integral part of the IEE.

An EMP outlining the specific environmental measures to be adhered to during

implementation of the subproject has been prepared.

1.7 Report Structure

This IEE contains eight sections: (i) Introduction; (ii) Description o f Project

Components; (iii) Description of the Existing Environment; (iv) Environmental

Impacts and Mitigation Measures; (v) Environmental Management Plan; (vi) Public

Consultation and Information Disclosure; (vi) Findings and Recommendations; and

(vii) Conclusions.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 16 [[ [[ [

2.0 DESCRIPTION OF PROJECT COMPONENTS

2.1 Description & Need of the project.

The existing Infrastructure of the town is inadequate to cater to the needs of the

Tourist as well as the resident population. It is therefore necessary to improve the

basic amenities to the public. The identified key interventions and improvements

have a direct bearing on the tourist wellbeing.

The core tourist areas of the Town need to be provided with improved infrastructure

facilities that would in addition to providing a facelift for the town would bring in a

paradigm shift in the approach to provision of Basic infrastructure facilities. Therefore

modern and state of the art facilities are to be provided, which can be replicated in

other parts of the town, and can trigger better management of assets. Each tourist

location has a unique architectural context. 2.2 Proposed Facilities

The existing Infrastructure under the proposed project – 2 is inadequate to cater the

needs of the tourist as well as the resident population. It becomes imperative to

improve the basic amenities to the public. Some of the key interventions and

improvements that have a direct bearing on the tourist wellbeing are discussed

below.

1 Improvements to Dansborg Fort: Conservation & Restoration of Dansborg

Fort, Renovation works at Museum, Provision of Tourist Infrastructure and

landscape & Horticulture works and all other Tourism and general infrastructure

requirements within the Fort Precincts.

2 Improved Sanitary Facilities: Sanitation facilities form a key element of tourist

convenience at any destination. The present facilities for public toilets/sanitary

complexes are limited and do not address the needs of the large floating

population of pilgrims / tourists. This has led to unhygienic conditions during the

festival seasons with people resorting to open defecation. Overall, sanitary toilet

complexes help in ensuring social dignity and privacy, and maintaining the health

status of the Urban Local Body (ULB). The key considerations for toilets /

sanitary complexes are that they should be aesthetically appealing for use for all

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 17 [[ [[ [

age group without difficulty easy approach and maintenance eco-friendly,

hygienic and cost effective.

3 Improvements to solid waste collection system: In line with the objective of

‘Cleaner and Greener Tourism’ in Tamil Nadu, it is proposed to provide the

appropriate garbage bins to reduce the littering of garbage on streets as the

garbage collection in few places of Tamilnadu State is through open garbage bins.

This exposure system leads to bad odour, over flow, spilling, and attack by

rodents, dogs and cats, besides a site of nuisance and major distraction to tourists.

The key considerations for unique design for bins (say Deep Earth Bins and Litter

Bins) are that they are eco-friendly, having sufficiently large capacities to prevent

spillage, provide easy and efficient transfer of garbage to trucks, stray dogs & bird

proof, aesthetically appealing and provides an odour free environment.

4 Improved street lighting in the core tourist areas: The key considerations for

lighting include safety & security, energy-saving & cost-effectiveness and

facilitating night tourism. The existing illuminations levels are poor and

inadequate due to old, damaged and inefficient fixtures. Good level of

illumination is necessary to manage the heavy traffic, pedestrians, tourists for

safety and crime reduction. The existing luminaries mounted on EB poles lack

aesthetic appeal and are not uniform. Further, luminaries are missing at many

places. It is therefore necessary for a well-planned and integrated installation of

street lighting comprising of decorative columns with energy efficient light and

fixtures and with underground cabling. This will enhance the appeal of the town,

and provide safety to the people, reduce crime and boost night tourism activities.

5 Provision of signages and good road furniture on important roads connecting the

transport centers like bus-stand and railway stations to the core tourist areas is a

vital infrastructural need in a tourist town. The signages act as guide to the visiting

tourists. Clarity and aesthetic appeal of such signages makes a destination user

friendly and popular. The route signages guide visitors to go in their intended

tourist circuits, and to navigate to their destinations without any interruption. The

basic considerations are to provide uniform retro reflective road signages with

proper visibility, earmarking the street names including way dividing signs,

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 18 [[ [[ [

centers/ mandatory/warning signs, land mark signs and tourist information signs.

as per Indian Road Congress (IRC) / National Building Code (NBC) norms.

6 Improved Street Furniture: Street furniture is a collective term for objects and

pieces of equipment (Benches, and Litter Bins etc) installed on streets and roads

for various purposes. The existing Street furniture is inadequate to cater the

requirements of road users and other public. It is required to install high quality

street furniture on the identified road networks to improve the service levels to the

tourists / & to achieve Cleaner and Greener Tourism in Tamil Nadu.

2.3 Components of the Subproject

The following infrastructure services have been identified in Tharangambadi Town

Panchayat with respective to improved basic urban infrastructure and services at

tourist destinations and attractions as follows:

• Improvements to Dansborg Fort

• Provision of sanitary complexes for the floating population

• Provision of gravity entailed deep earth bins for garbage collection (2.5 cu.m)

• Provision of energy efficient heritage street lighting

• Provision of tourism friendly uniform signage’s for convenience of the tourists

• Provision of street furniture such as litter bins and benches for the comfortable

travelling of the tourists

2.4 Sanitary Complex Location

Except in the case of sanitary complexes, all other components of the project are along

the Road and do not require any additional land. The roads where the components are

proposed belong to the Tharangambadi Town Panchayat. In the case of sanitary

complexes, the following sites have been identified in the table below:

Table 2

Sl. No. Location Survey Number

1 New bus stand 117

2 Erukattanchery 579

3 Ichuladi street 87

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 19 [[ [[ [

The above sites are under the full ownership of the Tharangambadi Town Panchayat

and are free of all encumbrances. Necessary approval from the Municipal council

shall be taken before implementing the projects. (Various Designs / Types of Sanitary

Complex (S1, S3, S4, S5, S6, S7 & S8) and Deep Earth Bins has been enclosed in

Annexure – A (Common for all locations)

2.5 Deployment Schedule

A total of 18 months construction period is being considered. (Refer Appendix – 3.

However, detailed implementation Schedule depending on contractor’s work

programme considering pilgrimages, climate, tourist’s seasonal timings and other

critical factors would be provided on finalization of the contract)

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 20 [[ [[ [

3.0 DESCRIPTION OF THE EXISTING ENVIRONMENT

3.1 Environmental Profile – Tharangambadi Town Panchayat, Tamil Nadu

3.1.1 Physical Characteristics

Introduction: (History & Heritage)

Tharangambadi (formerly Tranquebar) is

a Town Panchayat in Nagapattinam

district in the Indian state of Tamil Nadu,

15 km north of Karaikal, near the mouth of

a distributaries of the Cauvery River.

Tharangambadi is the headquarters

of Tharangambadi Taluk. Its name means

"place of the singing waves". It was

a Danish colony from 1620 to 1845, and

in Danish it is still known as Tranquebar. As

of 2001 India census, Tharangambadi had a population of 20,841.

During 1620 A.D., Tanjore province was under the rule of the mighty King Vijaya

Raghunatha Nayak. The Danes left Denmark in search of Sri Lanka and the Far Eawt,

but the monsoons and other hardships brought them to Tranquebar. On 5th May 1620

A.D., King Vijaya Raghunatha Nayak granted permission to the king of Denmark to

set up their trading centre at Tranquebar.

Tranquebar came under the control of the British in February 1808, during the

Napoleonic Wars in Europe, but was restored to Denmark following the Treaty of

Kiel in 1814. Along with the other Danish settlements in India (Serampore and

the Nicobars), it was sold to the British in 1845.

Tranquebar was then still a busy port, but it later lost its importance after a railway

was opened to Nagapattinam. Apart from its cultural and historical background this

city is also popular for its wonderful handicrafts all across the world. People across

many places come to visit the exquisite ancient handicrafts made out of bronze icons.

Tharangambadi is also considered as the most popular city under the thirteenth coastal

district of the Tamil Nadu state.

Figure No.1: District Map

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 21 [[ [[ [

Location: The town is situated on 11.03° north latitude and 79˚ 84’ east longitude,

15 km north of Karaikal, near the mouth of a15 km north of Karaikal, near the mouth

of a distributaries of the Cauvery River.

Coastal Regulation Zone (CRZ): With reference to the Coastal Zone Management

Plan for Tamil Nadu, Tharangambadi and Velankanni have been classified as CRZ I.

3.1.2 Accessibility

Tharangambadi is located on the National Highway (NH 45A) connecting

Pondicherry and Nagapattinam. Tharangambadi is well connected with Nagapattinam,

the district headquarters and Chennai, the state headquarters and with other towns of

Karaikal, Cuddalore and Velankanni by road transport facilities. The main mode of

transportation is buses operated mainly by Government Transport Corporation and by

some private agencies. The nearest airport is located in Trichy at a distance of 128

Km. Tharangambadi itself has one railway station connecting Tharangambadi and

Mayiladurai but not in much usage as on today.

Laying on the Coromandel Coast, Tranquebar is a Vestige of Danish Heritage in

India. Distance from Major Settlements and important tourist destinations are given

here under:

• 277 kms from Chennai

• 117 kms from Puducherry

Distance from other important Tourist Destinations

• 25 kms from Poompuhar

• 52 kms from Chidambaram

• 17 kms from Karaikal

• 26 kms from Nagore, Nagapattinam

3.1.3 Physical & Geographical features

Tharangambadi is a coastal town, with a spread over an area of 13KM2. The historical

Fort Dansborg at Tharangambadi, arelic of the Danishera in India, is back in the

limelight with the initial phase of restoration work. The fort was constructed nearly

four centuries ago, the monument which served as the residence of Danish Governor

for 150 years, had been in ruins, because of age, weathering.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 22 [[ [[ [

Climate

Temperature in Nagapattinam district is in the range of Maximum 32.00˚C and

Minimum 24.60˚C. Normal rainfall during North East Monsoon varies between 908.8

mm to 969.2 mm and during South West Monsoon it varies between 250.60 and 265.2

mm.

3.1.4 Trade and Commerce

Major work force in Tharangambadi is still engaged in primary sector activity like

fishing and agriculture and its dependency on primary sector is more when compared

to district urban and state urban areas. Its economic base is again reflected in its

dependency on other service related activity like Tourism which is more or less

equivalent to the Cuddalore district urban and state urban occupational figures.

3.1.5 Administration:

Tharangambadi is selection grade town Panchayat and it is ruled by local self-

government in the form of elected body of councilors headed by the chairman.

Citizens of Tharangambadi town elect the councilors and the chairman. There are total

18 wards and from each ward one councilor is elected.

Fort is under the control of Archaeological and Museum Department, Government of

Tamil Nadu. The site museum is being set-up and run by the Department.

Fort is declared monument on 01.10.1980 as per the GO Ms. No.906/ Education

Department / 07.06.1979- Gazette No. 26/04.07.1979 Part II, Section 2 Page – 369

and GO No. 2610/Education Department, dated 06.12.1980 – Gazette No.

6/18.02.1981. Part II Section 2 Page 123. Area of the fort complex is 7.17 Hectare.

Land Survey No Area in Ha

104/A-16 1.76

104/A-14 0.80

104/14B 2.03

104/15A 2.69

104/15B 0.11

104/17 0.40

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 23 [[ [[ [

3.1.6 Tourism Places

Tharangambadi town has several places of interest for the tourism. The majestic

Dansborg Fort, the New Jerusalem Church and the quaint Danish homes off King's

Road in Tranquebar are popular sightseeing spots. The first building that welcomes

the visitor at the entrance of the town is an old gateway with wooden doors,

builtbytheDanishin1792.The arch leads to the main street of the town, called King

Street. Along this grandly named Road is a memorial at the spot where the Danes

landed.

Danish Fort: it is a Danish 17th century fort

facing the coast. The construction of the fort

began immediately after the arrival of the first

Danish trading expedition and the

establishment of a treaty regulating trading

rights between the NayakRaghunatha in

Thanjavur and the Danish East India Company

in 1620. Until the end of the 17th century the

fort was used for residential and storage purposes; subsequent increase in population

forced the Danes to move out and occupy surrounding areas as well. While it was

previously crumbling away, the Fort has received substantial renovation efforts

recently, by both Indian volunteers and Danish non-profit organizations. It houses a

small museum inside that has some artifacts and a history of the Danish Settlement

Construction of Fort Dansborg started in 1620. Most parts of the fort have been

reconstructed several times. The rampart wall is a fairly large four sided structure,

with bastions at each cardinal point.

A single storied building was constructed along three inner sides of the rampart, with

barracks, warehouse, kitchen and jail. The rooms on the southern side remain in good

condition, but the rooms on the western and northern sides have been substantially

damaged. On the eastern side of the fort, there was a two storied building facing the

sea. It was the main building of the fort. The vaulted lower storey served as a

magazine and a warehouse, while the vaulted upper storey contained the church and

the lodging of the governor, the senior merchants and the chaplain. The sea on the

eastern and western side protected the fort. The fort was surrounded by a moat, access

to the fort being over a drawbridge. The moat has completely disappeared.

Figure No.2: Danish Fort

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 24 [[ [[ [

Danish Museum: The antiquities connected

with the colonial period and Danish settlement

at Tharangambadi is exhibited. The museum

contains porcelain ware, Danish manuscripts,

glass objects, Chinese tea jars, steatitle lamps,

decorated terracotta objects, figurines, lamps,

stones, sculptures, swords, daggers, spears,

sudai (stucco) figurines and wooden objects. There is also part of a whale skeleton.

New Jerusalem Church, situated on the King's

Street was constructed in 1718 by Rev.

Bartholomaeus Ziegenbalg, First protestant

Missionary. This church was established after

the arrival of German missionaries in India, as

the existing church proved to be small for the

rising Christian population. It was established

mainly for the converted Indians. The church

has a small cemetery that has tombstones belonging to the 18th century.

The Zion Church: Consecrated in 1701, it is the

oldest protestant Church in India. Prominent with

its combination of colonial and Indian architectural

features, its construction together with the

fortification of the town marked the moving out

and spreading of the Danish population into the

surrounding settlement. The structure went through

many reconstructions before it reached its present

form.

3.1.7 Socio-Economic Condition

Major work force in Tharangambadi is still engaged in primary sector activity like

fishing and agriculture and its dependency on primary sector is more when compared

to district urban and state urban areas. Its economic base is again reflected in its

dependency on other service related activity like Tourism. However, non-workers

Figure No. 4: New Jerusalem

Church

Figure No.3: Danish Museum

Figure No. 5: Zion Church

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 25 [[ [[ [

percentage to total population is very high and state urban non workers share to total

population.

3.1.8 Population Details

The population of the town is 20841, with growth percentage of 10.4 % as per the

2001 census.

Table -3 - Population

Sl. No Year Population Growth

rate

1 1971 17318 ---

2 1981 18610 7.5

3 1991 18881 1.5

4 2001 20841 10.4

5 2011 22254 6.76

Table – 3 - Tourist Inflow

Sl.no Year Domestic Foreign Total

1 2007 30264 472 30736

2 2008 58620 320 58940

3 2009 65719 2985 68704

4 2010 94337 2257 96594

5 2011 98755 2369 101124

6 2012 133738 1788 135526

3.1.9 Geomorphology And Soil Types

The present geomorphic set up in the district is the result of action of the major rivers

with their distinct tributaries, oscillations in the sea level, tidal effects of Bay of

Bengal and forces of wind. The landforms are delineated under erosional and

depositional regime. The depositional regime comprises of a coastal plain under

marine influence, a flood plain of fluvial regime with an intermixing section of both

fluvial and marine influence. The entire area is a pene plained terrain with a gentle

slope towards east and southeast. The maximum elevation is about 21 m above mean

sea level in the west.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 26 [[ [[ [

Soils

The major part of the district is covered by black clay and isolated patches of brown

clay loam in the area bordering the NE boundary of Karaikal Region are seen. Some

patches of Arenacious soils are also found along the coastal line.

3.1.10 Ground water Quality

i. Presence of chemical constituents more than permissible limit…TH as CaCO3 and

NO3

ii. Type of water……..NaCl, Mg HCO3 and NaHCO3

• Ground water in phreatic aquifers, in general, is colourless, odourless and

predominantly alkaline in nature. In more than 50% of the samples, pH value is

>8.00. The specific electrical conductance of groundwater in the phreatic zone

during May 2006 was in the range of 714 to 3640 micro Siemens at 25° C, in the

district. Conductance below 750 has been observed only in select pockets of the

district. Saline ground waters (EC>10,000) are observed at southern part of the

district.

• It is observed that the ground water is suitable for drinking and domestic uses in

respect of all the constituents except total hardness and nitrate in about 83% of

samples. The hardness as CaCO3 as well as nitrate is observed to be in excess of

permissible limits of drinking water standard of BIS, in about 17% of samples. The

incidence of high total hardness is attributed to the composition of litho units

constituting the aquifers in the district, whereas nitrate pollution is most likely due

to the use of fertilizers for agriculture and other improper waste disposal practices.

• With regard to irrigation suitability based on specific electrical conductance and

Sodium Adsorption Ration (SAR), it is observed that ground water in the phreatic

zone may cause high to very high Salinity hazard and medium to very high alkali

hazard when used for irrigation. Proper soil management strategies are to be adopted

in the major part of the district while using ground water for irrigation.

• Water Supply / Resources

� At present, the water supply demand has been addressed by bore wells.

� For the proposed sanitary complex, the water requirement will be pleased

using borewells or under the scope of Town Panchayat

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 27 [[ [[ [

Table – 4 - Air Quality Monitoring

Locations

SPM

mg/m3

RSPM

mg/m3

Nox

mg/m3

SO2

mg/m3

Lead

mg/m3

CO

mg/m3

Thiruvarur(54.5 km from Tranqubar) 142 63 31.7 22.1 <0.1 2259

Nagapattinam(15.3 km from Tranqubar) 142 61 27.9 19.6 <0.1 1815

Table – 5 - Noise Level Monitoring

Sl.No. Location Date of Sampling Average Noise Level in dB

Day Time Night Time

1. Thiruvarur(54.5 km from Tranqubar) 03.02.06 59.0 48.0

2. Nagapattinam(15.3 km from Tranqubar) 10.02.06 52.0 40.0

Table – 6 - Water Quality

Sl.No. PARAMETERS

Vennar River

(70.1km) from

Tharangambadi

Thiruvarur Bore

well (76.3km)

from

Tharangambadi

Needamangalam

Bypass (82.5km)

from

Tharangambadi

Limits as per

10500 & IS :

2296

1. pH 7.4 7 7.2 6.5 - 8.5

2. Dissolved Oxygen, mg /

l 7.5 6.8 7.0 6 min

3. Turbidity, NTU < 5 < 5 < 5 5 max

4. Colour, Hazen units < 5 < 5 < 5 5 max

5. Odour Unobjectionable Unobjectionable Unobjectionable Unobjectionable

6. Taste * Agreeable * Agreeable

7. Fluoride ( as F ), mg / l 0.2 0.2 0.4 1.0 max

8. Cadmium ( as cd ), mg /

l < 0.01 < 0.01 < 0.01 0.01 max

9. Chlorides ( as Cl ), mg /

l 122 733 290 250 max

10. Hexavalent Chromium

( as Cr+6 ), mg / l < 0.05 < 0.05 < 0.05 0.05 max

11. Cyanide ( as CN ), mg / l < 0.01 < 0.01 < 0.01 0.05 max

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 28 [[ [[ [

Sl.No. PARAMETERS

Vennar River

(70.1km) from

Tharangambadi

Thiruvarur Bore

well (76.3km)

from

Tharangambadi

Needamangalam

Bypass (82.5km)

from

Tharangambadi

Limits as per

10500 & IS :

2296

12. Total Dissolved Solids,

mg / l 396 1278 740 500 max

13. Total Hardness

( as CaCO3 ), mg / l 192 220 180 300 max

14. Calcium Hardness

( as ca ), mg / l 38.6 59.5 44.11 75 max

15. Magnesium Hardness

( as Mg ), mg / l 14.8 25.5 20.7 30 max

16. Selenium ( as Se ), mg / l < 0.01 < 0.01 < 0.01 0.01 max

17. Sulphates ( as SO4 ), mg

/ l 28.6 60.6 55.7 200 max

18. Lead ( as Pb ), mg / l < 0.05 < 0.05 < 0.05 0.05 max

19. Copper ( as Cu ), mg / l < 0.05 < 0.05 < 0.05 0.05 max

20. Arsenic ( as As ), mg / l < 0.05 < 0.05 < 0.05 0.05 max

21. Iron ( as Fe ), mg / l < 0.05 0.2 < 0.05 0.3 max

22. Phenolic Compounds

( as C6H5OH ), mg / l < 0.001 < 0.001 < 0.001 0.001 max

23. Zinc ( as Zn ), mg / l < 0.05 < 0.05 < 0.05 5 max

24. Anionic Detergents

( as MBAS ), mg / l < 0.1 < 0.1 < 0.1 0.2 max

25. Nitrates ( as NO3 ), mg /

l < 1 < 1 1 45 max

26. Barium ( as Ba ), mg / l < 0.05 0.17 0.1 1 max

27. Silver ( as Ag ), mg / l < 0.05 < 0.05 < 0.05 0.05 max

28. Mercury ( as Hg ), mg / l < 0.001 < 0.001 < 0.001 0.001 max

29. Manganese

( as Mn ), mg / l < 0.05 0.44 < 0.05 0.1 max

30. Alkalinity 201 310 405 200 max

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 29 [[ [[ [

Sl.No. PARAMETERS

Vennar River

(70.1km) from

Tharangambadi

Thiruvarur Bore

well (76.3km)

from

Tharangambadi

Needamangalam

Bypass (82.5km)

from

Tharangambadi

Limits as per

10500 & IS :

2296

( as CaCO3 ), mg / l

31. Aluminium ( as Al ), mg

/ l < 0.03 < 0.03 < 0.03 0.03 max

32. Boron ( as B ), mg / l < 0.05 0.11 0.1 1 max

33.

Biochemical Oxygen

Demand for 5 days at

200C, mg / l

4 < 2 < 2 2 max

34. Microbiological

Parameters :

a. E - Coli / 100 ml Present Absent Present Absent

b. Total Coliforms / 100 ml > 1600 Absent > 1600 10 max

3.1.11 Ground Water Development

In Nagapattinam district, the bulk of rural water supply is from ground water by

means of dug wells, hand pumps (filter point) and tube wells owned by individuals.

The TWAD Board, an apex body for the rural and urban water supply in Tamil Nadu

has provided water supply in rural and urban sectors from the ground water sources

through the implementation of various schemes with the assistance of Govt. of India

and with funds of State Govt.

3.1.12 Ground Water Related Issues And Problems

The hydrogeological environment in the Nagapattinam district has been subjected to

pollution considerably. The eastern part of the district being tail end of the canal

system, and due to inferior quality of ground water, the agricultural prosperity in the

eastern part attained a setback. The agricultural lands are brought under aquaculture

use. The mushrooming and unregulated growth of aquaculture may lead to an

alarming magnitude of pollution.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 30 [[ [[ [

In the eastern part of the district near the coast, a ground water is saline. The fresh

water pocket in the sand dune areas are used for drinking purposes. The discharge of

untreated wastewaters of aquaculture farms and chemicals used for the growing

prawns will also affect the shallow fresh water pockets.

Agriculture, which is the mainstay of the populace of the district, forms the chief

socio economic base. The environmental hazards may arise in two kinds. (1) Due to

the infiltration of irrigation water saturated with chemicals, insecticides, pesticides,

fertilizers (2) the water of Cauvery is highly polluted with industrial effluents. The

river water is reported to be polluted by the effluents discharged into the river by

several textile processing industries in the upstream.

3.1.13 Hydrogeology.

1. Major water bearing formations - Lower Miocene deeper aquifers and Pliocene

quaternary shallow aquifers

2. Pre- monsoon depth to water level (May 2006) - 2.0 – 9.45 m bgl

3. Post- monsoon depth to water level (Jan’2007) - GL -2.641 m bgl

4. Long term water level trend in 10 years (1998-2007)(m/yr)

Annual Rise - Min: Nil, Max: 0. 31

Annual fall - Min: 0.022, Max: 0. 29

3.1.14 Ecological Resources

Tropical dry-evergreen forest covers nearly 15 sq.kms of Pt. Calimere Wildlife

sanctuary. The forests are mostly of the nature of scrubland that stands on low sand

dunes located on the western half of the sanctuary. Manilkarahexandra, locally called

Palai is the most important evergreen species of the sanctuary forest. In the sanctuary

grasslands the dominant graminoid is Aeluropuslagopoides followed by

Sporobulutremulus and Cressacretica. The forest is home to 154 species of medicinal

plants like Mucunapruriens, Solanumtrilobatum, Tinosporacordifolia

Randiadumatorum and Cissusquadrangularis. A Forest Rest House at Kodiakkarai is

available for visitors to the sanctuary.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 31 [[ [[ [

3.2 Environmental Profile – Site Specific

3.2.1 Description of Project:

Construction of sanitary complexes for the floating population, placement of gravity

entailed deep earth bins for garbage collection (2.5 cubic meters), Placement of

energy efficient heritage street lighting, Placement of tourism friendly uniform

signages for convenience of the tourists and Placement of street furniture such as litter

bins, & benches and improvements to Dansborg Fort for the comforts of travelling

tourists in Tharangambadi Town, Nagapattinam District, TamilNadu.

3.2.2 Site Details:

Sl.no Description Yes / No

1. Protected area Yes

2. Archaeological site Yes

3. Forest area No

4. CRZ area Yes

Notes: Protected Area includes wildlife sanctuary, bird sanctuary, or national park; CRZ =

Coastal Regulation Zone

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 32 [[ [[ [

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

The assessment for each of the subprojects has been carried out for potential impacts

during the following stages of the project planning and implementation:

• Location impacts. Impacts associated with site selection, including impacts on

environment and resettlement or livelihood related impacts on communities;

• Design impacts. Impacts arising from project design, including the technology used,

scale of operations, discharge standards, etc.;

• Construction impacts. Impacts resulting from construction activities including site

clearance, earthworks, civil works, etc.; and

• O&M impacts. Impacts associated with the operation and maintenance of the

infrastructure built in the project.

The ADB Rapid Environmental Assessment Checklist for Urban Development was

used during preparation of this IEE to screen the subproject for environmental impacts

and categorization of the project (Appendix 2).

4.1 Location Impacts

1) Land Acquisition and Resettlement. The proposed subproject locations are within

the lands available with the government. There are no impacts envisaged on land

acquisition or resettlement due to the proposed subproject components.

2) Site Selection. The locations considered for the subproject are within the areas

designated for tourism support infrastructure development as part of

developing Tamil Nadu’s conservation, heritage, natural and cultural attractions, and

are outside areas demarcated for habitat protection and conservation. The proposed

infrastructures will not impact any environmentally-sensitive or protected areas

rather it will enhance the tourism experience and livelihood of the local people in

total. The public, Govt & local bodies are very much keen into taking up these

proposed works. The entire town and adjoining areas are under Town Panchayat

control who has proposed this project. This proposal suggests areas which are

uncovered with the needed basic amenities. Further, there is no possibility of

presence of non-titled street vendors and no displacement or shifting of non-titled

street vendors would be required in these sites that have been identified for sub

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 33 [[ [[ [

projects.

3) Priority is to locate construction work camps, stockpile areas, storage areas, and

disposal areas near the subproject sites. However, if it is deemed necessary to locate

elsewhere, sites to be considered will not promote instability and result in destruction

of property, vegetation, irrigation, and drinking water supply systems. Residential

areas will not be considered to protect the human environment (i.e., to curb accident

risks, health risks due to air and water pollution and dust, and noise, and to prevent

social conflicts, shortages of amenities, and crime).

4.2 Design Impacts and Pre-Construction Impacts

1) Impacts arising from the inappropriate designs of proposed facilities would in general

include the inadequate collection and conveyance system for solid waste,

construction materials sourcing and c o n s t r u c t i o n techniques to be adopted, site

selection, etc. The results of interventions are unobtrusive and will be integral part of

the overall ambience so as to avoid impacts on the livelihood of the site.

A structural design has been worked out in such a manner that exposed steel

and concrete structures are avoided.

2) All component designs have been worked out to minimize any impacts on the

adjoining properties, and considering the need of the facilities for the floating

population. Given that the there is a need for disposal of construction wastes, the

contractors will be required to consult with the Project Implementation Unit (PIU),

Panchayat offices, and Tamil Nadu Pollution Control Board for safe disposal sites.

3) Telephone lines, electric poles and wires, water and drainage lines within the

existing right-of- way (ROW) may be damaged. To mitigate the adverse impacts due

to relocation of the utilities, the Design and Supervision Consultants (DSC) and PIU

will:

(i) Identify and include locations and operators of these utilities in the detailed

design documents to prevent unnecessary disruption of services during

construction phase; and

(ii) Require construction contractors to prepare a contingency plan to include actions

to be done in case of unintentional interruption of services

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 34 [[ [[ [

4.3 Construction Impacts

1) The impacts are generic to the construction activities in all subproject locations.

All construction activities to be undertaken at the site will be approved by competent

authority before start of any such activity in the vicinity of the site so that the

history and sanctity as well as the usability of the site by the local people and

projected number of tourists are not hampered. Hence, the EMP emphasizes on the

construction impacts and necessary mitigation measures to be strictly followed by the

contractor and supervised by the DSC. Key impacts during construction, are

envisaged on the following aspects: (i) drainage, (ii) slope cutting and slope Stability

(iii) water bodies and drainage courses (iv) dust generation, air and noise from

construction activities, (v) handling of construction materials at site, (vi) adoption of

safety measures during construction; and (vii) community health and safety.

4.4 Operation and Maintenance Impacts

1) The impacts pertaining to waste collection, cleaning of septic tanks and soakpits,

maintaining hygienic conditions of the toilet facilities, will be addressed through an

assessment of the Operation and Management of the proposed facilities in frequent

intervals/regular inspection. Planning of the extent of facilities and infrastructure in

line with the Maintenance plan as well as the involvement of the local communities

in the management facilities created in the project will address the operation stage

impacts.

2) The proposed facilities will greatly improve the environmental quality in and

around the destinations, and also enhance the livelihood of the local

population. While the enhanced tourist generation due to these improvements may

not be significant, the facilities will enhance the site experience of the

tourist/pilgrim. The project will facilitate environmental improvements through the

provision of training to operators for all sanitation and solid waste facilities

provided by the Project, in order to sustain any improvements made.

4.5 Cumulative Impact Assessment

1) The cumulative impact assessment (CIA) examined the interaction between the

subproject’s residual effects (i.e., those effects that remain after mitigation measures

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 35 [[ [[ [

have been applied) and those associated with other past, existing and reasonably

foreseeable future projects or activities.

2) Two boundaries, spatial and temporal, were used. Spatial boundary refers to the area

immediately surrounding the subproject location; while the temporal area considers

the potential cumulative effects associated with subproject construction, and

operation and maintenance, and those associated with other past, existing and

reasonably foreseeable projects in the vicinity of the subproject. For the subproject,

the spatial boundary is the area of the subprojects including existing ROWs. The

temporal boundary can be considered as the districts where the subproject sites are

located.

3) The subproject’s potential cumulative effects were considered with respect to valued

components (VCs), identified in the IEE as air quality, noise, surface water quality,

geophysical (hydrogeological), traffic management, social-economic and socio-

community, and human health. The cumulative impacts were assessed in four areas:

• Of any potential residual project effects that may occur incrementally

over time;

• Consideration of other known relevant projects or activities within the specified

study area boundaries, even if not directly related to the subproject;

• Potential overlapping impacts that may occur due to other developments, even if

not directly related to the proposed project; and

• Future developments that is reasonably foreseeable and sufficiently certain to

proceed.

4) Air Quality: The air environment of the sub project areas is generally found to be

good and is free from industries polluting the atmospheric environment. The

ambient air quality in the sub project areas is generally found to be within

acceptable standards. Impact on air quality (if any) during construction stage are due

to operation of various construction equipments and transport vehicles.

Consequently, although emissions of common air contaminants (CAC) and fugitive

dust may be elevated in proximity to the active work sites, this impact will be of

short-term and localized to the immediate vicinity of the project site.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 36 [[ [[ [

Greenhouse Gas (GHG) emissions may increase as a result of project activities (i.e.,

vehicle and equipment operation, concrete production, disposal of excavated

material, land filling of residual wastes). Given the subproject’s relatively minor

contribution to CAC and GHG emissions during construction, the overall

significance rating of both these potential residual effects is considered to be

negligible during construction.

5) Noise Quality: Most part of the sub project area is in quite environment. Noise

intensive industrial operations are not observed along the project influence area.

However ambient noise levels both at day and night times as observed during the

year 2006 is in Table 3 which reveals that the noise level is within permissible

levels.

Noise levels in the immediate proximity of most work sites are expected to increase

during construction. The duration of this exposure will be relatively brief. This

exposure represents temporary, localized, adverse residual effect of low to moderate

significance for affected receptors. While building damage due to ground vibrations

is unlikely, there may annoyance to spatially located receptors during construction.

Noise levels associated with the subproject operations will be largely imperceptible

as civil works will be confined in relatively small sites within the district proper.

6) Since the subproject will be built in existing infrastructures, it will not conflict with

existing or planned land use. However, traffic management concerns will occur

spatially during construction. Site-specific mitigation measures will be

implemented during construction to address temporary disruptions to land use,

limitations on access to roads, sidewalk closures, traffic delays and detours, parking

modifications, and increased volumes of construction–related traffic. There should

be improved traffic movement along the access routes once construction is

completed. During operations of the improved infrastructures and services, added

residential developments, commercial and business facilities and increased densities

are expected to develop and enhance the subproject area. This can be considered a

long-term cumulative benefit of the subproject. (Refer Environmental Management

plan for Sub project Specific impacts and their mitigation measures)

7) No adverse residual effects to human health will occur as a result of subproject

construction or operation. While exposure to elevated noise levels and fugitive dust

and CAC emissions will occur in proximity to subproject work sites during

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 37 [[ [[ [

construction, due to their short term, localized nature, these effects are expected to be

minor and insignificant with no measurable effects on human health. The subproject

operations will benefit the general public by contributing to the long-term

improvement of tourism in Tamil Nadu and livelihood opportunities to the local

people.

4.6 Environment Management Plan

i. The specific measures stated in the EMP will address all adverse environmental

impacts due to the subproject. A detailed monitoring plan prepared as part of this IEE

will ensure negative environmental impacts during implementation are mitigated.

During the Construction stage, the IEE/EMP will be further updated and stand-alone

EMPs will be prepared. EMPs will be appended to the respective contract documents

to enable integration of environmental provisions in the contract.

ii. The project sub-components proposed has been classified as Category B, as it is likely

to have minimal or no adverse environmental impacts and therefore does not require

conducting EIA or IEE. However, an Environmental Management Plan for the

interventions is prepared as described in Chapter 5.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 38 [[ [[ [

5.0 ENVIRONMENTAL MANAGEMENT PLAN

5.1 Institutional Arrangements

1. The Government of Tamil Nadu through Department of Tourism and Culture

(DOT&C), is the Executing Agency (EA). The EA (i) assumes overall responsibility

for the execution of the Project and reporting; (ii) engage adequate permanent or fixed-

term staff to implement the Project; (iii) setup a state-level project management unit

(PMU) and project implementation units (PIU); (iv) provide overall strategic guidance

on technical supervision and project execution; and (v) ensure overall compliance with

the loan covenants.

2. The implementing agency (IA) is the Tamil Nadu Department of Tourism (DoT). The

IA’s responsibilities include (i) project planning and budgeting; (ii) day-to-day

assistance, supervision and guidance for the project implementation units and their

consultants; (iii) review subprojects for due diligence requirements and approve

subproject proposals; (iv) bidding, evaluation and contract award; (v) managing and

disbursing funds; (vi) review compliance with loan covenants, contract specifications,

work plans and quality control; and (vii) consolidate and submit progress reports,

finance and accounting / audit reports, and matters requiring higher-level decision to

state-level empowered committee (SLEC) and ADB.

5.2 Program Management

1) State Level steering committee chaired by Minister of Tourism and Chief Secretary

2) State Level Empowered Committees. An SLEC has been established in Tamil

Nadu, chaired by s t a te Chief Secretary, with Principal Secretary/Secretary of the

Department of Tourism as member secretary and comprised of secretaries from relevant

line departments. The SLEC have been empowered to take all decisions on behalf of

the State and will (i) act as a policy making body, (ii) provide overall advice and

guidance to the State’s executing agency and PMU, and (iii) accord all approvals under

the Project.

3) Project Management unit. DoT has established a PMU, headed by a full-time Program

Director (PD), and consisting of personnel drawn from relevant line Departments and

market. The PMU is the nodal agency for overall management of all program activities

and will be responsible for: (i) project planning and budgeting; (ii) providing day-to-day

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 39 [[ [[ [

assistance, supervision and guidance for the PIUs and their consultants; (iii) reviewing

subprojects to satisfy ADB’s due diligence requirements and approving subproject

proposals submitted by PIU and line departments; (iv) bidding, evaluation and contract

award; (v) managing and disbursing funds; (vi) reviewing compliance with loan

covenants, contract specifications, work plans and quality control; (vii) consolidating and

submitting progress reports, finance and accounting/audit reports, and matters requiring

higher-level decision, to the SLEC and ADB. The PMU will be supported by a team of

consultants.

4) State Level steering committee chaired by Minister of Tourism and Chief Secretary

The members of the Tamil Nadu SLEC will be: Chief Secretary, (chair); Principal

Secretary/Secretary, Tourism and Culture; Secretary, Department of Finance; Secretary,

Planning and Special Initiatives; Secretary, Public Works Department; Secretary,

Highways and Minor Ports; Secretary Forests and Environment; Secretary, Housing and

Urban Development; Secretary, Municipal Administration, Water and Sanitation;

Secretary, Rural Development; Secretary Power; Secretary, Revenue Department;

Secretary, Department of Health and family Welfare; Secretary, Agriculture; Secretary,

Hindu Religious and Charitable Endowments (HR&CE), Commissioner, Department of

Archaeology; Secretary, Department of Transport; and Commissioner, Department of

Tourism.

5) Project Implementation Unit. The IA will have PIUs for the implementation and

monitoring of subprojects, comprising of personnel drawn from relevant line

Departments and outside of Government (market) and each headed by a Project

Manager. The PIUs will be responsible for: (i) prioritizing and preparing subproject

proposals; (ii) providing day-to- day assistance, supervision and guidance to the design

and supervision consultants; (iii) conducting detailed assessments and surveys including

public consultation and input from stakeholders; (iv) preparing detailed designs,

specifications, schedule of quantity, bidding documents, and related documentation; (v)

implementing civil works and related activities; (vi) reporting to PMU; (vii) preparing

regular progress reports for the SLEC, the executing agency and ADB through PMU;

and (viii) supervising construction, conducting quality control, approving progress

payments to contractors; and (ix) maintaining records and accounts on an up-to-date

basis and making these available to ADB, its missions, or auditors for inspection.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 40 [[ [[ [

6) Project Management Consultants. The Project Management Consultants (PMC)

will be engaged to provide support to the PMU in overall planning, risk

management, implementation, monitoring and evaluation of projects under the

Investment Program. The PMC will also assist the PMU and PIUs in meeting the

relevant requirements of ADB, Government of Tamil Nadu, and Government of India

for project implementation. The PMC will report to and work under the overall guidance

of the PMU. The scope of services of the PMCs will include but not necessarily be

limited to: (i) planning, reporting, and communication; (ii) establishment of

procedures and systems; (iii) review and preparation of plans, manuals and reports; (iv)

overall Investment Program management, monitoring and implementation of PPMS; and

(v) social, environmental, archaeological, occupational health and safety, community

participation and gender action compliance monitoring.

7) Design and Supervision Consultants. The DSCs will be engaged to provide all

necessary support to and coordination with the EA, IAs, PMU and any other consultants

engaged by the authorities to achieve the desired outcomes of the Investment Program.

The DSCs will report to and work under the overall guidance of the PIUs. The scope of

services of the DSCs will include but not necessarily be limited to: (i) surveys,

verification of feasibility studies and base maps; (ii) project planning and management

support to the PIU; (iii) finalization of design criteria, preparation of manuals, guidelines

and systems; (iv) preparation of detailed design and bid documents; (v) construction

management and contract administration; (vi) environmental, social, archaeological,

cultural heritage, community participation and gender action compliance

monitoring; and (vii) capacity building of the service providers for operational

sustainability.

The Implementation Strategy have been prepared with reference to available data and

however it would be revised depending on the contractors work programme and also since

the volume and nature of balance project work under Tranche - 1 and the new projects to be

identified under Tranche -2 is unknown and have not been finalized, the above mentioned

schedule is tentative and shall be revised at the later stage based on the award of contract or

commencement of work.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 41 [[ [[ [

5.2.1 Safeguards Management

1) An Environmental Staff is to be deputized to the PMU, and responsible

for implementations of the environmental safeguard provisions.

2) Within the PMC team, a Safeguards Specialist provides overall direction

for management of environmental and social issues, and provides technical support to

the PMU including implementation of the environmental requirements, according to

ADB requirements, and assists in monitoring impacts and mitigation measures

associated with subprojects. The responsibilities of t he PMC Safeguards Specialist

– Environment include but not limited to:

• Review the updated IEE prepared by the DSCs for Project 2 after the

detailed designs, and guide the DSCs/PIUs to address observations from

ADB on the IEEs/EMPs;

• Ensure that the project design and specification adequately reflect the

IEEs/EMP;

• support PMU in ensuring conformance to the ADB Safeguards Policy Statement

(SPS) 2009 on environmental safeguards and the provisions of the EARF;

• Prepare IEEs and other safeguards reports for subsequent projects under the

Investment Program;

• Assist PMU in establishing grievance redress mechanism under the Investment

Program;

• Guide and monitor DSC safeguard specialists works on environmental

safeguards;

• Based on the project requirements, carry out site visits along with the PMU to

address issues if any, with respect to EMP implementation;

• Carry out capacity building of the PMU/PIU environmental safeguards

personnel;

• Assist PMU in review of the monthly monitoring reports from PIU of

EMP Implementation, and in preparation and submission of semi-annual

monitoring

Reports to ADB;

• Coordinate in obtaining of requisite clearances, permits, and approvals for the

project;

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 42 [[ [[ [

• Monitor construction activities to ensure in compliance with the IEE/EMP and

Advise DSCs/PIUs for compliance with statutory requirements;

• Review and approve the Contractor’s Implementation Plan for the

environmental measures as per IEE/EMP;

• Establish dialogue with affected communities and ensure that the environmental

concerns and suggestions are incorporated and implemented in the project;

• Review environmental performance of the project through an assessment of the

periodic environmental monitoring reports submitted by the DSC, and initiate

necessary follow-up actions;

• Provide support and assistance to government agencies and ADB to supervise

the implementation of the IEE/EMP during the construction as well as operation

stage of the project;

• Assist the PMU/PIUs in disclosure of the safeguards documents in accordance

with the EARF requirements

• Ensure IEEs/EMPs are reviewed and approved by ADB prior to contract award.

3) The Environmental Specialist of the DSC team will:

• Assist in preparing and update subproject IEEs in respect to

environmental management plans (EMPs) in compliance with the ADB

Safeguard Policy Statement, national- and state-level environmental policies,

rules, and regulations;

• Interact on a regular basis with the sector specialists of the DSC and integrate

environmentally sound practices into the detailed design of project components.

Include mitigation measures in designs where appropriate, and to specify other

measures in construction contracts;

• Assist the PIU in monitoring impacts and mitigation measures associated with

subprojects in accordance with the IEEs, EMPs, and/or environmental mitigation

action plan as well as any other environmental issues and take corrective actions

where needed;

• Assist in the review and approval of site specific environmental enhancement

/mitigation designs worked out by the Contractor to ensure compliance

with the IEE and EMP;

• Assist the PIU in preparing monthly and annual environmental compliance

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 43 [[ [[ [

reports for all works in accordance with the EMP for each of the subprojects and

the overall Project;

• Develop, organise and deliver environmental training programs and workshops

for the staff of the PIU and Contractors and in accordance to the Capacity

Building Program as specified in the IEE. Provide training to the PIU for

environmental management and monitoring during construction and operation;

• Advise PMU/PIU for compliance with statutory clearances;

• Develop good practice construction guidelines to assist the contractors in

implementing the provisions of IEE;

• Work with local NGOs to conduct environmental awareness events

which highlight conservation and benefits of eco-tourism principles; and

• Assist Environmental Specialist of the PMU to prepare good practice

dissemination notes based on the experience gained from site supervision.

4) Contractors will be required by their contracts to implement all specified

mitigation, monitoring, and reporting assigned to contractors as presented in

subproject IEE. Environmental monitoring will be undertaken by the PMU supported

by the PMC Environmental Specialist.

5) The project includes upfront and ongoing supervision and training assistance for

environmental monitoring reporting in project management structures. The effective

implementation of the measures proposed will be ensured through the building

up of capacity towards environmental management within the PMU supplemented

with the technical expertise of a Safeguards Specialist as part of the DSC Consultants.

5.3 Environmental Management Plan

As per the Asian Development Bank’s (ADB) Environmental Assessment

Guidelines, the subproject components have been categorized as ‘B’ and an IEE

carried out. Towards addressal of the construction impacts, this Environmental

management plan (EMP) outlining the specific environmental measures to be

adhered to during implementation of the subproject has been prepared. This will

enable integration of environmental provisions / management measures in the

Contract Document.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 44

Table – 7 – Environmental Management Plan

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

Pre-Construction Stage

1 Clearances

All clearance required for Environmental aspects during construction shall be

ensured and made available before start of work.

ULB / PIU / Concerned

Departments & agency /

contractor

2 Tree Cutting • No trees will be felled for establishing these facilities. Trees will be saved by

changing the infrastructure component. Adequate protection to the trees to will be

ensured by providing tree guards (e.g. masonry tree guards, l ow level RCC

tree guards and c ircular iron tree guard with bars) as required.

• Compensatory plantation by wa y of re plantation of at least thrice the number of

trees cut should be carried out in the project area.

Contractor / PIU

3 Utility

Relocation

i) Identify the common utilities to be affected such as: telephone cables, electric

cables, electric poles, water pipelines, public water taps, etc ii) Affected

utilities shall be relocated with prior approval of the concerned agencies before

construction starts.

PIU / Concerned

departments/DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 45

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

4 Baseline

Data generation

Prior to commencement of construction activities, environmental monitoring will be

conducted through an approved agency towards generating baseline parameters.

Further, adequate measures shall be implemented as per EMP to check the Baseline

parameters of Air, Water, soil and Noise pollution. Base line parameters shall be

monitored and recorded and ensured conformance intermittently as per the monitoring

plan till the completion of the project.

Contractor / PIU / DSC

5 Planning

of

temporary

Traffic

arrangement

i) If necessitated during project construction phase, temporary diversion will be

provided with the approval of the engineer. Detailed traffic control plans will be

prepared and submitted to the engineers for approval, one week prior to

commencement of works.

ii) The traffic control plans shall contain details of temporary diversion, details of

arrangements for construction under traffic, details of traffic arrangement after

cessation of work each day, sign boards, safety measures for transport of

hazardous materials and arrangement of flagmen.

Contractor / PIU / DSC

6 Disposal of

treated Waste

Waste water generated if any will be contained, desilted, treated and disposed in

sewerage lines. Alternatively, the waste water will be sprinkled for dust

Contractor/ PIU/DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 46

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

water suppression.

7 Storage of

materials

The contractor shall identify the site for temporary use of land for

construction sites /storage of construction materials, etc.

Contractor / PIU/DSC

Construction Stage

1.1 Shifting of

common

utilities

Ensure community consensus and minimum impact to common utilities like

telephone cable, electric cables, electric poles, water taps and etc., Proper clearance is

to be obtained from the concerned authorities before commencement of works.

Concerned departments

and PIU

1.2 Compensatory

plantation of

trees

Attempts will be made by altering the locations of these facilities so that the issue of

tree felling does not arise. If inevitable, trees will be felled with prior permission and

compensatory plantation will be carried out as per the directives of the Forest

department.

Contractor / PIU

1.3 Disposal of

Construction

debris and

excavated

The contractor shall identify the sites for debris disposal prior to start of the

earthworks; taking into account the following:

(a) The dumping does not impact natural drainage courses

(b) no endangered / rare flora is impacted by such dumping

Prospective

Contractor / PIU / DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 47

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

materials. (c) Settlement area located at least

1.0 km away from the site.

(d) Should be located in non residential areas located in the downwind side

(e) located at least 100m from the designated forest land.

(f) Avoid disposal on productive land.

(g) Should be located with the consensus of the local community, in consultation with

the engineer and shall be approved by the highways department Minimize the

construction debris by balancing the cut and fill requirements.

(Preferably reused as filling or spread material and covered with a productive

layer of soil)

1.4 Planning for

temporary

traffic

diversions

Before taking up of construction activity, a Traffic Control Plan shall be prepared if

necessary and implemented to the satisfaction of the Engineer

Construction shall be taken in a phased manner . Temporary diversion will be

provided with the approval of the engineer.

The arrangement for the temporary diversion of the road shall ensure to minimize

Contractor/ PIU/DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 48

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

the environmental impacts, like loss of vegetation, productive lands etc., prior to the

finalization of diversion and detours.

Special consideration will be given to the preparation of the traffic control

plan for safety of pedestrians and workers at night. The contractor will ensure that

the diversion / detour is always maintained in running condition, particularly

during the monsoon to avoid disruption to traffic flow. He shall inform local

community of changes to traffic routes, conditions and pedestrians access

arrangements.

This plan will be periodically reviewed with respect to site conditions.

The temporary traffic detour will be kept free of dust by frequent application of

water.

1.5 Protection of

top soil

The top productive soil to be scooped out is protected and reused over a piece of land

for enhancing productivity.

Contractor

1.6 Potential risk

of cross

connection

Adequate precautions should be taken while laying the sewer lines to avoid the

possibility of cross connection with water supply lines.

contractor/PIU/DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 49

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

1.7 Flooding in

the low lying

areas

Low lying areas in the project site can get flooded during monsoon period; to prevent

the situation proper drainage arrangements has to be planned and implemented

Contractor/ PIU/DSC

1.8 Temporary

flooding due to

excavation.

Proper drainage arrangements to be made, to avoid the overflowing of existing drains

due to excavation during the laying of sewer mains/pipe lines.

Contractor / PIU/DSC

1.9 Temporary

water supply

interruptions

i) Establish coordination with the concerned department to avoid or minimize the

interruption of regular supply of drinking water to the residents.

ii) Proper alternative arrangements to be planned when interruption of drinking water

supply to the nearby residents.

Contractor/ PIU

1.10 Use of modern

machinery

Using of modern machinery such as JCBs, Backhoes etc, shall be used to minimize

the construction period; it will also reduce the construction impacts to the nearby

residents.

Contractor

1.11 Traffic

diversion

i) Temporary traffic arrangements to be planned during construction. This plan shall be

periodically reviewed with respect to site condition and concerned departments.

Contractor/ PIU/DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 50

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

1.12 Prevention of

accidents

Prevention o f accidents involving humanbeings, animals or vehicles falling or

accidents due to open trenches during construction period. This needs to be ensured

with proper barricading, signage boards and lighting etc.

Contractor/ PIU/DSC

1.13 Barricading

site

The construction site should be barricaded at all time till its completion with adequate

marking, flags, reflectors etc. for safety of general traffic movement and pedestrians.

Contractor/DSC/PIU

1.14 Dust

Pollution near

settlements

i) All earth work will be protected in the manner acceptable to the engineer to

minimize generation of dust. Area under construction shall be intermittently

sprinkled with water towards dust suppression.

ii) Construction material shall be kept covered or stored in such a manner so as to

avoid being airborne because of the wind flow.

iii) Trucks carrying construction material to be adequately covered to avoid the dust

pollution and to avoid the material spillage.

Contractor/ PIU/DSC

1.15 Protection of

Residential /

sensitive

i) Noisy construction operations in residential and sensitive areas shall be carried out

only between 6.00 am and 6.00 pm.

ii) Preventive maintenance of construction equipment and vehicles are to be carried

Contractor /DSC/ PIU

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 51

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

receptors. out to meet emission standards and to keep them with low noise.

iii) Provision of generators and concrete mixers with acoustic enclosures are to be

made at site.

iv) Sound barriers in inhabited areas shall be installed during the construction phase.

v) Adequate barricading / other measures to protect dust pollution near sensitive

receptors like schools and hospital to be ensured.

1.16 Vehicular

Noise

pollution at

residential /

sensitive

receptors.

i) Idling of temporary trucks or other equipment should not be permitted during

periods of loading / unloading or when they are not in active use. This shall be

ensured especially near residential / commercial / sensitive areas.

ii) Stationary construction equipment will be kept at least 500m away from sensitive

receptors.

iii) All possible and practical measures to control noise emissions during drilling shall

be employed. The project manager may direct to take adequate controls measures

depending on site conditions.

Contractor /DSC/PIU

1.17 Noise from iv) Servicing of all construction vehicles and machinery will be carried out regularly

and during routine servicing operations, the effectiveness of exhaust silencers will

Contractor / DSC/PIU

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 52

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

vehicles,

plants and

equipment

be checked and if found defective will be replaced.

v) Maintenance of vehicles, equipment and machinery shall be regular and up to

the satisfaction of the Engineer to keep noise levels at the minimum as per the

PCB norms.

1.18 Storage of

construction

materials

Site for storage of construction materials to be identified, without obstructing the traffic

and other common utilities.

Contractor/PIU/DSC

1.19 Labour

facilities

Adequate potable water facilities, sanitation and drainage , in conformity with the

Indian labour laws shall be ensured.

The contractor shall also guarantee the following:

i) The construction of temporary toilets to labours will commence only upon the written

approval of the Engineer.

ii) The Contractor shall make arrangements towards potable water is available for

drinking, cooking and washing.

iii) Supply of sufficient quantity of potable water as per BIS in every workplace site at

Contractor / PIU/DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 53

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

suitable and easily accessible places and regular maintenance of such facilities.

iv) The sewer lines for the sanitary complex shall be designed, built and operated in

such a fashion that no health hazards occurs and no pollution to the air, ground

water or adjacent water courses take place; ensure adequate water supply to all

toilets and urinals.

1.20 Waste

Disposal

i) The contractor shall provide garbage bins in the work site and ensure that

these are regularly emptied and disposed off in a hygienic manner as per the

Comprehensive Solid Waste Management Plan approved by the Engineer.

Contractor/DSC/PIU

1.21 Pollution from

fuel and

lubricants

i) The contractor shall ensure that all construction vehicle parking location,

fuel / lubricants storage sites; vehicle, machinery and equipment maintenance and

refuelling sites shall be located away from rivers, irrigation canal/ponds and

water bodies.

ii) Contractor shall ensure that all vehicle / machinery and equipment operation,

maintenance and refuelling will be carried out in such a fashion that spillage of

fuels and lubricants does not contaminate the ground.

iii) Contractor shall arrange for collection, storing and disposal of oily wastes to the

Contractor/DSC/PIU

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 54

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

pre- identified disposal sites (list to be submitted to Engineer) and approved by

the Engineer. All spill and collected petroleum products will be disposed off in

accordance with MoEF and state PCB guidelines.

iv) Engineer will certify that all arrangements comply with the guidelines of PCB/

MoEF or any other relevant laws.

1.22 Pollution from

Construction

Wastes

The Contractor shall take all precautionary measures to prevent the wastewater

generated during construction from entering into streams, water bodies or the

irrigation system. All waste arising from the project is to be disposed off in the

manner that is acceptable by the engineer.

The engineer shall certify that all liquid wastes disposed off from the sites meet the

discharge standard.

Contractor / DSC/PIU

1.23 Risk from

Electrical

Equipment(s)

The contractor shall take all required precautions to prevent danger from

electrical equipment and ensure that -

i) No material will be so stacked or placed as to cause danger or inconvenience to

any person or the public.

ii) All necessary fencing and lights will be provided to protect the public in

Contractor/DSC/PIU

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 55

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

construction zones. All machines to be used in the construction will conform to

the relevant Indian Standards (BIS) codes, will be free from patent defect, will

be kept in good working order, will be regularly inspected and properly

maintained as per BIS provision and to the satisfaction of the Engineer.

1.24 Safety

aspects

i) Adequate precautions shall be taken to prevent the accidents and from the

machineries. All machines used shall conform to the relevant Indian standards

Code and shall be regularly monitored by the Project Manager.

ii) Where loose soil is met with, shoring and strutting as per standard shall be

provided to avoid collapse of soil.

iii) Protective footwear and protective goggles shall be provided to all workers

employed on mixing of materials like cement, concrete etc.

iii) Welder’s protective eye-shields shall be provided to workers who are engaged in

welding works.

iv) Earplugs shall be provided to workers exposed to loud noise and workers working

in crushing, compaction, or concrete mixing operation.

v) The contractor shall supply all necessary safety appliances such as safety goggles,

Contractor/DSC/PIU

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 56

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

helmets, safety belts, ear plugs, mask etc to workers and staff.

The contractor shall comply with all the precautions as required for ensuring the

safety of the workmen as per the International Labour Organization(ILO)

Convention No. 62 as far as those are applicable to this contract.

The contractor will make sure that during the construction work all relevant

provisions of the Factories Act, 1948 and the Building and other Cons t ruc t i on

Workers ( regulation of Employment and Conditions of Services) Act, 1996 are

adhered to. The contractor shall not employ any person below the age of 14 years for

any work and no woman will be employed on the work of painting with products

containing lead in any form.

1.25 First Aid The contractor shall arrange for:

i) A readily available first aid unit including an adequate supply of sterilized dressing

materials and appliances as per the Factories Rules in every work zone

ii) Availability of suitable transport at all times to take injured or sick person(s) to the

nearest hospital for treatment.

Contractor/DSC/PIU

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 57

Sl.no

Activity /

Potential

Impacts

Mitigation Measures Responsible

agencies

1.26 Chance found

Flora and

Fauna

The contractor will take reasonable precaution to prevent his workmen or any

other persons from removing and damaging any flora (plant/vegetation) and

fauna (animal) including fishing in any water body and hunting of any animal.

If any, upon discovery thereof acquaint the Engineer and carry out the Engineer's

instructions for dealing with the same.

The Engineer will report to the nearest

forest office (range office or divisional office) and will take appropriate steps/

measures, if required in consultation with the forest officials.

Contractor/DSC/PIU

1.27 Environmental

Monitoring

The PMU/PIU with the help of DSC shall undertake seasonal monitoring of air,

water, noise and soil quality through an approved professional environmental

monitoring agency. The parameter to be monitored, frequency and duration of

monitoring plan shall be accordingly decided as per the norms of PCB.

PMU/PIU/DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 58

5.4 Environmental Monitoring Plan

Environmental monitoring will be done during construction at three levels; namely

monitoring development of project performance indicators by the DSC Environmental

Specialist, monitoring (by DSC and PMC) over the implementation of mitigation

measures done by the Contractor and overall regulatory monitoring of the

environmental issues by the PMU Environmental Specialist. The proposed monitoring

of all relevant environmental parameters, with a description of the sampling stations,

frequency of monitoring, applicable standards and responsible agencies are presented.

The environmental monitoring plan for the project is presented in Table 8.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 59

Table 8: Environmental Monitoring Plan

Attribute Project

Stage Parameter Special Guidance Standards Frequency Duration Location Implementation

Air

Construction

SO2, NOx,

PM10,

PM2.5, CO

Use method specified by

CPCB for analysis.

Environmental

monitoring shall be

conducted by NABL

aggregated laboratory.

Air

(prevention

and Control

of

Pollution)

Rules,

CPCB, 2009

Three

seasons

per year 24 hours

Sampling

Along the

road

Not Applicable

Operation1

Three

seasons for

one year

Along the

road

Noise

Construction

Noise levels

on dB (A)

scale

Equivalent noise levels

using an integrated

noise level meter kept at

a distance of 15 from

edge of pavement

Equivalent noise levels

using an integrated

noise level meter kept at

a distance of 15 from

MoEF

Noise

Rules, 2000

Three

seasons

per year Leq in

dB(A) of

day time

and night

time

Along the

road

Not Applicable

Operation

Three

seasons for

one year

Along the

road

1 Parameters to be monitored for Operation stage is same as Construction stage

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 60

Attribute Project

Stage Parameter Special Guidance Standards Frequency Duration Location Implementation

edge of pavement.

Environmental

monitoring shall be

conducted by NABL

aggregated laboratory.

Water Construction

All essential

characteristi

cs and some

of desirable

characteristi

cs as

decided by

the

Environmen

tal

Specialist of

the SC and

PIU

Grab sample collected

from source and

Analyse as per Standard

Methods for

Examination of Water

and Wastewater.

Environmental

monitoring shall be

conducted by NABL

aggregated laboratory.

Indian

Standards

for

Inland

Surface

Waters (IS:

2296, 1982

Three

seasons

per year

Grab

Sampling

In the

periphery

of sanitary

complex

Contractor under

the supervision of

the Engineer

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 61

Attribute Project

Stage Parameter Special Guidance Standards Frequency Duration Location Implementation

Soil Construction

Monitoring

of Pb, SAR

and Oil &

Grease

Sample of soil collected

to acidified and

analysed using

absorption

Spectrophotometer.

Environmental

monitoring shall be

conducted by NABL

aggregated laboratory.

Threshold

for each

contaminant

set by IRIS

database of

USEPA

until

national

standards

are

promulgated

Once in a

year

Grab

Sampling

In the

periphery

of sanitary

complex

Contractor under

the supervision of

the Engineer

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 62

Apart from the above mentioned monitoring requirements, any major accidents

/spillage during bulk transport of hazardous materials. Depending on the type of

spillages / accidents the parameters to be monitored will be decided by the engineer

and should be carried out by the contractor through approved monitoring agencies

and supervised by the Implementing agency at their own cost.

Formats for reporting:

Formats for reporting / monitoring the progress / parameters achieved will be

finalized in consultation with the successful bidder.

However, the suggested monitoring report format is in Appendix 4

Environmental Compliance Report:

� The contractor should deploy Environmental and Social Safeguard (ESS)

Manager to have uninterrupted communication with the DSC’s Environmental

specialist.

� The contractor shall submit a monthly progress report as per the reporting

format approved by the engineer, on the status of the implementation of the

EMP, and get it duly approved by the engineer for its compliance and for

proceeding with the work.

� The monthly report should necessarily address the EMP clauses vs. the status

of the compliances, deviations if any future course of actions with photographic

evidences.

5.5 Capacity Building

5.5.1 Target Audience

The Environmental Specialist of the DSC will provide the basic training required

for environmental awareness followed by specific aspects of infrastructure

improvement projects along with Environmental implications for projects located

within / in the vicinity of natural and cultural heritage sites. Specific modules

customized for the available skill set will be devised after assessing the capabilities

of the members of the Training Programme and the requirements of the project. The

entire training would cover basic principles of environmental assessment and

management; mitigation plans and programmes, implementation techniques,

monitoring methods and tools. The proposed training program along with the

frequency of sessions is presented in Table 9

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 63

Table 9: Training Modules for Environmental Management

Programme Description Participants Form of

Training

Duration /

Location

Training Conducting

Agency

A. Pre-Construction Stage

Sensitization

Workshop

Introduction to Environment: Basic

Concept of Environmental

Regulations, Guidelines, EIA

notification, process and methodology

for IEE, EMPs and their use and

Statutory requirements as per

Government of India and ADB.

Tourism / Forest / Roads /

Culture Department

Officials, Project Director

(PD) and Environmental

Specialist (ES) of the

PMU/PIU & PMC

Lectures cum interaction &

Workshop

½ Working

Day

Environmental

Specialist of the DSC

Session I

Module I

Introduction to Environment: Basic

Concept of Environment Safeguards

Regulations and Statutory

requirements as per Govt. of India and

ADB guidelines on cultural resources,

Environmental considerations in

planning, design and implementing

projects.

PMU/PIU (including the

ES), PMC and Engineering

staff of the implementing

Agencies

Lecture 1 Working

Day

Safeguards Specialist

of the DSC

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 64

Module II

Environmental components impacted

in constructions and operation stages

Activities causing pollution during

Construction and Operation stages

Environmental Management

Environmental Provisions

Implementation Arrangements

Methodology of Assessment Good

Engineering Practices to be integrated

into Contract Documents.

PMU/PIU/PMC (including

the ES) and Engineering

staff of Tourism Dept.

Workshop ¼ Working

Day

Safeguards Specialist

of the DSC.

Module III

Implementation of EMPs:

Basic features of an EMP, Planning,

designing and execution of

environmental mitigation and

enhancement measures, monitoring

and evaluation of environmental

conditions – during construction and

operation

PMU/PIU (including the

ES) Engineering staff of

Tourism Dept.

Lecture /

Interactive

sessions and

site visits

2 Working

Days

Safeguards Specialist

of the PMC with

support from the

conservation

specialist of the

PMC.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 65

Module IV

Improved co-ordination with other

Departments: Statutory permissions –

Procedural requirements co-operation

and co- ordination with other

Departments.

PMU/PIU (including the

ES) Engineering staff of

Tourism Dept. & PMC

Lecture /

Interactive

sessions

1 Working

Day

Safeguards Specialist

of the DSC.

Module V

Environmental principles of eco-

tourism and training and awareness

building

Local community groups,

NGOs

Lecture /

Interactive

sessions

½ Working

Day

Institutes as the Wild

Life Institute of India

B. Construction Stage

Session II

Module VI

Role during Construction Roles and

Responsibilities of Officials /

Contractors / Consultants towards

protection of Environment

Implementation Arrangements

Monitoring Mechanisms

Engineers and Staff of Line

Departments of the Govt. of

Tamil Nadu and PMU/PIU

(including the ES)

Lecture /

Interactive

sessions

½ Working

Day

Safeguards Specialist

of the DSC

Session III

Module VI

Identification of birds species in Pong

Wetland, habits of species, biology,

ecology of important species, basic

Staff of Forest

Department, Youth in the

villages, periphery of the

Site visits,

Interactive

sessions

5-7 working

days

Institutes as

the Wild Life

Institute of India

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 66

knowledge of reptiles of amphibians

and fauna

identification of plants, including

medicinal plants orientation on

wetland ecology, monitoring methods,

use of instruments as binoculars,

digital camera, GPS, etc.

Wetland, and other NGOs

in the District.

Module VII

Skill up gradation on eco-tourism and

nature guides dealing with tourists

interpretational skills, micro planning,

natural resources, management of self-

help groups, etc.

Youth in the villages,

periphery and other NGOs

in the District

Site visits,

Interactive

sessions

5-7 Working

Days

Tourism Department,

and Institutes as the

Wild Life Institute of

India.

Module VIII

Monitoring Environmental

Performance during Construction:

Air, Water, Soil and Noise, tree

survival Monitoring requirement and

techniques, Evaluation and Review of

results, Performance indicators and

their applicability, possible corrective

actions, reporting requirements and

mechanisms

PIU/ PMC/NGOs and

community representatives

Lectures,

Workshop and

site visits

4 – 5 Working

Days

Safeguards Specialist

of the DSC – During

initial stage of

Construction

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 67

5.5.2 Environmental Awareness Building

• Distribution of Pamphlets, Posters, Brochures etc.,

Building an Environmental Awareness by elaborating the Do’s and Don’ts in the

form of Posters, Pamphlets etc sub project specific in selected locations. For

example sub project wise do’s and don’ts is as follows

Sanitary Complex

S. No Do’s Don’ts

1. Periodical Cleaning should be done Improper Cleaning to be avoided

2. Periodical cleaning of septic tank to be

done without any spillage or leakage Septic Tank should not be kept open

3. Sufficient Water supply to be ensured

for flushing and floor cleaning

No plastic waste and other wastes to

be dumped into the water closet

4.

Emergency Contact Numbers to be

displayed nearby (Hospital, red cross,

Child welfare etc)

No driving or parking over any part

of the septic system.

5. Proper flushing of Water Closets to be

ensured

6. Appropriate Cleaning materials to be

used for cleaning

Deep Earth Bins

S. No Do’s Don’ts

1. Periodical Empting / Maintenance

should be done before spillage

It should not be placed in the traffic

zone

2.

Bins should be placed along the road

side such that no disturbance for

public to be ensured

It should not be placed in the

vehicle’s traffic zone

3. Bins to be covered properly to avoid

bad odour into the environment

Placement of bins at the road’s

junction points to be avoided

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 68

5.6 Environmental Budget

As part of good engineering practices in the project, there have been several

measures as erosion prevention, rehabilitation of borrow areas, safety, signage, provision

of temporary drains, etc., the costs for which will be included in the design costs of

specific subprojects. Therefore, these items of costs have not been included in the IEE

budget. Only those items not covered under budgets for construction and RP are

costed in the IEE budget. The IEE costs include mitigation, monitoring and capacity

building costs.

Table: 10 Environmental Budgets

Item Quantity Unit Cost (US $) Sub-total Cost (US $) Source of Funds

Environmental

Monitoring

(a) Design stage to establish baseline environmental data

Lump sum $2,000 (Per component) $7000 DSC cost

(b) Construction phase

$5,000 (Per component)

-

Construction

contractor’s costs

(c) O&M -

-

Implementing

Agencies cost

(d) Capacity Building

Expenses

$25,000 $25,000 PMC/DSC cost

5.7 Environmental Monitoring and Reporting

1) The PMU will monitor and measure the progress of EMP implementation.

The monitoring activities will be corresponding with the project’s risks and impacts

and will be identified in the EIAs/IEEs for the subprojects. In addition to

recording information of the work, deviation of work components from original

scope, the PMU and PIU will undertake site inspections and document review to

verify compliance with the EMP and progress toward the final outcome.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 69

2)

3) DSC will submit monthly monitoring and implementation reports to PIU, who will

take follow-up actions, if necessary. PIU will submit the quarterly monitoring and

implementation reports to PMU who will then submit to the PD. The PMU will

submit semi-annual monitoring reports to ADB. The suggested monitoring report

format is in Appendix 4. Project budgets will reflect the costs of monitoring and

reporting requirements. For subprojects likely to have significant adverse

environmental impacts during operation, reporting will continue at the minimum on

an annual basis. Monitoring reports will be posted in a location accessible to the

public.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 70

6.0 PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

6.1 Process for Consultation followed

Along with town panchayat officials, discussions/consultations were held with the local

people, shop owners, Auto-Rickshaw owners, residents, tourist on the pros and cons of

the sub-projects implementation on July 2014 and their views have been integrated in the

EMP.

6.2 Plan for Continued Public Participation

1) To ensure continued public participation, provisions to ensure regular and continued

stakeholder participation, at all stages during the project design and

implementation is proposed. A grievance redressal cell will be set up within the

PIU to register grievances of the people regarding technical, social and

environmental aspects. This participatory process will ensure that all views of the

people are adequately reviewed and suitably incorporated in the design and

implementation process. Further, to ensure an effective disclosure of the project

proposals to the stakeholders and the communities in the vicinity of the subproject

locations, an extensive project awareness campaigns will be carried out.

2) The implementing agency will submit to ADB the following documents for

disclosure on ADB’s website: (i) the final IEE; (ii) a new or updated IEE and

corrective action plan prepared during project implementation, if any; and (iii) the

environmental monitoring reports.

3) For the benefit of the community the Summary IEE will be translated in the

local language (Tamil) and made available at: (i) Office of the PMU; and, (ii) Office

of the District Collectors at the Nagapattinam district. These copies will be made

available free of cost to any person seeking information on the same. Hard copies

of the IEE will be available in the PMU/PIU as well as the district library at

Nagapattinam, and accessible to citizens as a means to disclose the document and at

the same time creating wider public awareness. On demand, the person seeking

information can obtain a hard copy of the complete IEE document at the cost of

photocopy from the office of the PMU/PIU, on a written request and payment for the

same to the Project Director. Electronic version of the IEE will be placed in

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 71

the official website of the Tourism Department and the website of ADB after

approval of the documents by Government and ADB. The PMU will issue

notification on the disclosure mechanism in local newspapers, ahead of the initiation

of implementation of the project, providing information on the project, as well as the

start dates, etc. The notice will be issued by the PMU in local newspapers one month

ahead of the implementation works. This will create awareness of the project

implementation among the public. Posters designed to mass campaign the basic

tenets of the IEE will be distributed to libraries in different localities that will be

generating mass awareness.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 72

Table 11 - Consultations with Local Community

Sl. No. Place Name of the Participants Existing conditions and Findings from Participants Photographs

1 Ichuladi street 1. Sivakmar ,JA, (944579648); 2. Mariappan, Kumar(Resident)

• The site is located in the residential area. • Power and water supply does exist. • The sanitary complex will be utilized by the local populace

(about 200 people) as well as floating populace.

2 New bus stand 3. Mrs.Dhanalaxmi(Housewife)

• The site is located in the bus stand area where sanitary

complex facility is highly required • Power and water supply does exist. • The sanitary complex will be utilized by the vendors and

travellers.

3 Erukattan cherry

4. Mrs.Amina(Housewife) 5. Mr.murukayan(Localite)

• The site is located in the residential area. • Power and water supply does exist. • Borewell need to be dug as source of water. • The site is being used as timber depot. • Developing the sanitary complex will be beneficial to local

people as well as floating populace.

• Further, discussion held with the Town Panchayat staff. The sites have been selected in populated areas where toilet facility is being necessitated by local

populace.

• It was opined and agreed upon that most of the proposed locations being on prime locations, the Town Panchayat will take up aesthetic enhancement

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 73

measures plant planting Shrubs/Trees around the complexes.

• Regular cleaning will be ensured by engaging Self Help Groups which was the biggest demand of the public.

• Waste yard and Compost yard is in place and operational. Waste is being collected daily through trucks, vans; disposed, segregated and composted

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 74

6.3 Grievance Redress Mechanism

1) The EA will establish a mechanism to receive and facilitate resolution of

affected peoples’ concerns, complaints, and grievances about the Project’s

environmental performance. The project-specific grievance redress mechanism

(GRM) is not intended to bypass the government’s own redress process; rather it is

intended to address affected people's concerns and complaints promptly, making it

readily accessible to all segments of the affected people and is scaled to the risks and

impacts of the Project.

2) The PMU and PIUs will make the public aware of the GRM through public

awareness campaigns. Grievances can be filed in writing using the Complaint

Register and Complaint Forms (Appendix 5) or by phone with any member of the

PMU or PIU. The contact phone number of the PIUs and the PMU will serve as a

hotline for complaints and will be publicized through the media and placed on

notice boards outside their offices and at construction sites. The safeguard

documents made available to the public in an accessible version will include

information on the GRM and will be widely disseminated throughout the corridor

by the safeguards officers in the PMU and PIUs with support from the NGO

engaged to implement the Community Awareness Program.

3) The PIUs will convene Grievance Redress Committees (GRC) within one week of

the voiced grievance at the project level consisting of members of local government,

NGOs, project staff, and representatives of the affected people. Decisions on the

grievance are to be made within 15 days voiced grievances. If the grievance cannot

be solved, the PMU is notified to further advice on the situation with higher

government and legal bodies.

4) The GRC will ensure rights of vulnerable and poor are included. The

grievance mechanism will be scaled to the risks and adverse impacts of the Project. It

will address affected people's concerns and complaints promptly, using an

understandable and transparent process that is gender responsive, culturally

appropriate, and readily accessible to all segments of the affected people at no costs

and without retribution. The mechanism developed will be in a manner that it shall

not impede access to the existing judicial or administrative remedies. The affected

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 75

people will be appropriately informed about the mechanism.

5) The PMU officers will be responsible for processing and placing all papers before the

GRC, maintaining database of complaints, recording decisions, issuing minutes of

the meetings and monitoring to see that formal orders are issued and the decisions

carried out. All costs involved in resolving the complaints (meetings, consultations,

communication and reporting / information dissemination) will be borne by the

PMU.

6) The safeguard monitoring reports will include the following aspects pertaining to

progress on grievances:

(i) Number of cases registered with the GRC, level of jurisdiction (first, second

and third tiers), number of hearings held, decisions made, and the status of

pending Cases; and

(ii) Lists of cases in process and already decided upon may be prepared with details

such as Name, ID with unique serial number, date of notice, date of application,

Date of hearing, decisions, remarks, actions taken to resolve issues, and status of

Grievance (i.e., open, closed, pending).

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 76

7.0 FINDINGS & RECOMMENDATIONS

1. The proposed subproject components involve various interventions in the

Tharangambadi Town Panchayat area, a major tourist destination in Tamil Nadu.

The selection of components in line with the subproject selection criteria laid down

by ADB, and the recommendations of the CPHEEO Sewerage Manual avoids any

significant encroachment / direct impact on tourist attractions and the livelihood of

the people in the area. Further, the siting of the components has been based on

appropriate considerations to minimize environmental impacts. The subproject will

conform to all Government of India/Tamil Nadu and ADB regulations, policies, and

standards including all necessary government permits and clearances.

2. The significance of the environmental impacts will be primarily due to the

construction related activities. The resultant potential impacts from these

proposals can be offset through provision of proven mitigation measures

during the design and adoption of good engineering practices during

construction and implementation. Further, the provision of environmental

infrastructure, including access to sanitation and waste management facilities

within the tourist areas, will enhance the environmental conditions and minimize

the pollution related aesthetic quality near the tourist areas and the other

destinations.

3. The specific management measures laid down in the IEE will effectively address

any adverse environmental impacts due to the subproject. The effective

implementation of the measures proposed will be ensured through the capacity

building for environmental management within the PMU supplemented with the

technical expertise of a Safeguards Specialist of the DSC. Further, the

environmental monitoring plans provide adequate opportunities towards course

correction to address any residual impacts during construction or operation stages.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 77

8.0 CONCLUSIONS

1) The IEE carried out for the subproject show that the proposed sub-components will

result in net environmental benefits, and that any adverse environmental impact can

be addressed through proper location, planning, and design of the proposed

subproject; control of construction activity and mitigation measures. The EMP

provides for mitigation of all identified impacts and the contract clauses for the

environmental provisions will be part of the civil works contracts. Further, the

proposed subproject elements have been consulted with the stakeholders and no

significant issues requiring redressal in terms of environmental safeguards exist.

2) Based on the findings of the IEE, the classification of the subproject as Category “B”

is confirmed, and no further special study or detailed EIA needs to be undertaken to

comply with ADB SPS (2009).

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 78

APPENDIX 1

CONTRACT CLAUSES TO BE INTEGRATED INTO BID

DOCUMENTS

1.0 Construction of Sanitary Complex

1.0.1 Movement / Circulation Plan during Construction

• For all construction activities in active tourist destinations, the Contractor will

prior to initiation of construction activities, prepare and get approved by the

Engineer, a construction plan including the staging, sequencing of construction

activities, circulation plans to ensure smooth movement to pilgrims and tourists,

including provision of alternative routes, etc. The plans will be disseminated at

key entry points to these tourist locations.

1.0.2 Quarry and Borrowing

• Considering the quantum of activities, it is envisaged that no borrow areas and

quarry sites will be opened. Raw materials will be procured from licensed

quarry owners. Similarly, no crusher sites will be opened by the contractor.

Also, No borrow area shall be made available by the Employer for this work.

The arrangement for the source of supply of the material for the civil works shall

be the sole responsibility of the Contractor.

1.0.3 Debris Disposal

• Dismantled material shall be stacked, collected and disposed at suitable

locations so that no such pollution arises out of this. Those shall be neatly piled

at points designated by the Engineer with all lifts and leads. Materials, which

can be used or auctioned, shall be stored in neat piles at locations designated by

Engineer with all lifts and leads.

• The contractor will identify potential sites for disposal of hazardous construction

debris and general construction wastes prior to start of construction and

dismantling operations. The contractor will obtain approval on identified sites

from the Engineer of Supervision Consultant and disposal will be only after

consent letter from the Engineer.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 79

1.0.4 Precautions for Protection of Environmental Resources

• The Contractor will ensure that construction activities do not result in any

contamination of land or water by polluting substances.

• Unless otherwise provided in the specifications, the Contractor will ensure that

no trees or shrubs or waterside vegetation are felled or harmed except those

required to be cleared for execution of the works. The Contractor will protect

trees and vegetation from damage to the satisfaction of the Engineer.

• The Contractor will not use or permit the use of wood as a fuel for the execution

of any part of the works and to the extent practicable, will ensure that fuels other

than wood are used for cooking and heating in all camps and living

accommodations. Any wood so used must be harvested legally, and the

Contractor will provide the Engineer with copies of the relevant permits, if

required.

• The Contractor will take all precautions necessary to ensure that vegetation

existing adjacent to the project site is not affected by fires arising from the

execution of the contract. Should a fire occur in the natural vegetation or

plantation adjacent to the project site for any reason, the Contractor will

immediately suppress it. Areas of forest, shrub, or plantation damaged by fire

considered by the Engineer to have been initiated by the Contractor’s staff or

labourers will be replanted or otherwise restored.

• The Contractor will confine operations to the dry season, use silt traps and

dispose spoils in locations approved by the Engineer that will not promote

instability and result in destruction of property, vegetation, irrigation and water

supply. Disposal near wetlands, protected areas, and other areas that will

inconvenience or deprive local residents of their livelihood will not be allowed.

Acidic and saline spoils will not be spread into agricultural land.

• The Contractor will consult with local residents and local government before

locating project offices, sheds, and construction plant.

• The Contractor will maintain ecological balance by preventing felling of trees,

water pollution and defacing of natural landscape.

• In the conduct of cleaning activities and operation of equipment, the Contractor

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 80

will utilize such practicable methods and devices as are reasonably available to

control, prevent and otherwise minimize air/noise pollution.

1.0.5 Noise And Air Pollution

• The Contractor will monitor the environmental parameters periodically as

specified in the monitoring plan and report to the Engineer.

• The Contractor will indemnify and keep indemnified the Employer from and

against any liability for damages on account of noise or other disturbance

created while carrying out the work, and from and against all claims, demands,

proceedings, damages, costs, charges, and expenses, whatsoever, in regard or

in relation to such liability.

1.0.6 Quality Assurance Plan / Manual

• Post the signing of the contract and prior to commencement of civil works, the

contractor shall produce the Quality Assurance Plan covering the following

items:

(i) Names, roles, responsibilities of the key Personnel of the Contractor’s staff

responsible for overseeing each major activity;

(ii) Methodology and work plan for each subproject

1.0.7 Utilities Diversion

• For the utilities diversion and restoration, the lines Departments are to be

consulted for planning and temporary diversion and final restoration

1.0.8 Avoidance of Interference

• The Contractor shall not interfere unnecessarily or improperly with the

convenience of the public, or the access to and use and occupation of all roads

and footpaths, irrespective of whether they are public or in the possession of the

Employer or of others.

• The Contractor shall indemnify and hold the Employer harmless against and

from all damages, losses and expenses (including legal fees and expenses)

resulting from any such unnecessary or improper interference.

• The Contractor shall be deemed to have been satisfied as to the suitability and

availability of access routes to the Site. The Contractor shall use reasonable

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 81

efforts to prevent any road or bridge from being damaged by the Contractor’s

traffic or by the Contractor’s Personnel. These efforts shall include the proper

use of appropriate vehicles and routes. Except as otherwise stated in these

Conditions:

• The Contractor shall (as between the Parties) be responsible for any

maintenance which may be required for his use of access routes;

• The Contractor shall provide all necessary signs or directions along access

routes, and shall obtain any permission which may be required from the relevant

authorities for his use of routes, signs and directions; All fossils, coins, articles

of value or antiquity, and structures and other remains or items of geological or

archaeological interest found on the Site shall be placed under the care and

authority of the Employer.

• The Contractor shall take reasonable precautions to prevent Contractor’s

Personnel or other persons from removing or damaging any of these findings.

The Contractor shall, upon discovery of any such finding, promptly give notice

to the Engineer, who shall issue instructions for dealing with it.

2.0 Provision of Deep Earth Bins

• The exact location of the Deep Earth Bins shall be confirmed with Project

Implementation Unit (PIU) and local municipal body

• Appropriate Stock yard to be arranged by the contractor for storage of the

materials

3.0 Provision of Street Lighting

3.0.1 Traffic Management

• Two weeks prior to undertake any work which would involve any types of

obstruction to traffic and public utilities, the Contractor shall submit, for the

Engineer’s approval, a Traffic Control Plan and utility restoration plan; and the

plan shall include:

(i) Drawings for any temporary diversions and utilities management plan;

Details of the traffic management measures to be used .These shall include

the traffic arrangements proposed to be in place after the cessation of work

each day.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 82

(ii) The Traffic Control Plan shall conform to the typical arrangements being

practiced and as otherwise directed by the Engineer.

(iii) Special Consideration shall be given in the preparation of the Traffic

Control/Utility diversion Plan to the safety of pedestrians and workers and

delineation of the roadway at night.

(iv) The Engineer’s approval of the Traffic Control Plan/utility diversion plan,

including any temporary Diversions, shall be obtained by the Contractor

before any work is commenced.

(v) The Contractor shall appoint a Safety Officer who shall have day to-day

responsibility for implementing and maintaining all safety measures

towards the above.

(vi) The entire Contractor's staff shall wear high-visibility orange or yellow

jackets or waistcoats while at the construction site and Persistent breaches

of the safety provisions by the Contractor and his employees shall

constitute a sufficient cause for action. At night the construction sites are

to be illuminated and STOP / GO Slow signs shall be illuminated.

(vii) Warning and informatory signs shall be erected on all approaches to the

works site in accordance with the prevailing adopted measures and the

Traffic Control Plan, or as otherwise directed by the Engineer. At all

times, the Contractor shall provide safe and convenient passage for

vehicles, pedestrians and livestock to and from side roads and property

accesses connecting to the roadway. Work which affects the use of side

roads and existing accesses shall not be undertaken without providing

adequate provisions to the satisfaction of the Engineer.

(viii) All signs, lights, barricades and other traffic control devices, as well as the

riding surface of diversions, shall be maintained in a satisfactory condition

and The Contractor shall be responsible for replacing or repairing all signs,

lights, barricades, and other traffic control devices that are lost, stolen,

damaged or defaced. Any temporary roadway shall be kept free of dust by

frequent applications of water if necessary.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 83

(ix) The sole responsibility for the safety and adequacy of the methods adopted

by the Contractor shall rest on the Contractor irrespective of any approval

given by the Engineer.

3.0.2 Utilities Diversion

• For the utilities diversion and restoration, the lines Departments are to be

consulted for planning and temporary diversion and final restoration

4.0 Installation of Signage’s

4.0.1 Traffic Management

• Two weeks prior to undertake any work which would involve any types of

obstruction to traffic and public utilities, the Contractor shall submit, for the

Engineer’s approval, a Traffic Control Plan and utility restoration plan; and the

plan shall include:

(i) Drawings for any temporary diversions and utilities management plan;

Details of the traffic management measures to be used. These shall include

the traffic arrangements proposed to be in place after the cessation of work

each day.

(ii) The Traffic Control Plan shall conform to the typical arrangements being

practiced and as otherwise directed by the Engineer.

(iii) Special Consideration shall be given in the preparation of the Traffic

Control/Utility diversion Plan to the safety of pedestrians and workers and

delineation of the roadway at night.

(iv) The Engineer’s approval of the Traffic Control Plan/utility diversion plan,

including any temporary Diversions, shall be obtained by the Contractor

before any work is commenced.

(v) The Contractor shall appoint a Safety Officer who shall have day to-day

responsibility for implementing and maintaining all safety measures

towards the above

(vi) The entire Contractor's staff shall wear high-visibility orange or yellow

jackets or waistcoats while at the construction site and Persistent breaches

of the safety provisions by the Contractor and his employees shall

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 84

constitute a sufficient cause for action. At night the construction sites are

to be illuminated and STOP / GO Slow signs shall be illuminated.

(vii) Warning and informatory signs shall be erected on all approaches to the

works site in accordance with the prevailing adopted measures and the

Traffic Control Plan, or as otherwise directed by the Engineer. At all

times, the Contractor shall provide safe and convenient passage for

vehicles, pedestrians and livestock to and from side roads and property

accesses connecting to the roadway. Work which affects the use of side

roads and existing accesses shall not be undertaken without providing

adequate provisions to the satisfaction of the Engineer.

(viii) All signs, lights, barricades and other traffic control devices, as well as the

riding surface of diversions, shall be maintained in a satisfactory condition

and The Contractor shall be responsible for replacing or repairing all signs,

lights, barricades, and other traffic control devices that are lost, stolen,

damaged or defaced. Any temporary roadway shall be kept free of dust by

frequent applications of water if necessary.

(ix) The sole responsibility for the safety and adequacy of the methods adopted

by the Contractor shall rest on the Contractor irrespective of any approval

given by the Engineer.

5.0 Provision of Street Furniture’s

• The exact location of the Street Furniture’s shall be confirmed with Project

Implementation Unit (PIU) and local municipal body

• Appropriate Stock yard to be arranged by the contractor for storage of the

materials

6.0 Improvements to Dansborg Fort

• Conservation & Restoration of Dansborg Fort,

• Renovation works at Museum,

• Provision of Tourist Infrastructure and landscape & Horticulture works and

• All other Tourism and general infrastructure requirements within the Fort

Precincts.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 85

7.0 General

� The Contractor will be responsible for implementation of environmental

provisions outlined in the EMP, in addition to adhering to all environmental

provisions in the applicable specifications for the works will be adhered to as

part of good engineering practices.

� The contractor might be using DG sets for which the permission will be

required under Air act 1981.

� No fuel storage takes place in this project and for construction purposes, the

fuel shall be procured from the existing petrol bunks

� For labour accommodation, no labour camp will be established and for

accommodation of labours nearby construction sites, rented houses will be

engaged by the contractor. Further, labour licence from the District Labour

commissioner shall be provided by the contractor.

� All works undertaken towards protection of environmental resources as part of

the EMP and as part of good engineering practices while adhering to relevant

specifications will be deemed to be incidental to works being carried out and no

separate payment will be made unless otherwise specified explicitly. The

costs towards environmental management as per EMP unless otherwise

provided as a separate head, will be deemed to be part of the BOQ of the

project. The scope of works of the contractor towards the implementation of the

environmental provisions will be as follows:

• Abide by all existing Environmental regulations and requirements of the

Government of India , during implementation,

• Compliance with all mitigation measures and monitoring requirements set

out in the Environmental Management Plan (EMP)

• Submission of a method statement detailing how the subproject

EMP will be complied with. This will include methods and schedule of

monitoring.

• Monitoring of project environmental performance and periodic submission

of monitoring reports.

• Compliance of all safety rules at work, and Provision of adequate health and

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 86

safety measures such as water, food, sanitation, personal protective

equipment, workers insurance, and medical facilities.

� The detailed provisions for specific environmental issues will be as outlined

in the EMP table on impacts and mitigation measures.

� Occupational Health And Safety During Construction

• The Contractor will, in accordance with the safety and health provisions

specified in the EMP, provide workers with a safe and healthy working

environment, in the work areas, through application of preventive and

protective measures consistent with international good practice, as reflected in

internationally recognized standards such as the World Bank Group’s

Environment, Health and Safety Guidelines. The borrower/client will take

steps to prevent accidents, injury, and disease arising from, associated with, or

occurring during the course of work by

� Providing preventive and protective measures, including

modification, substitution, or elimination of hazardous conditions or

substances; Providing appropriate equipment to minimize risks and

requiring and enforcing its use;

� Training workers and providing them with appropriate

incentives to use and comply with health and safety procedures

and protective equipment;

� Documenting and reporting occupational accidents, diseases, and

incidents; and

� Having emergency prevention, preparedness, and response

arrangements in place.

• Goggles and gas masks shall be worn at the time of dismantling. Leather

gloves shall be worn by the workers. Screens made of G.I. Sheets shall be

placed wherever necessary to prevent the flying pieces from injuring the

workers.

� The Contractor shall comply with all applicable safety regulations by

taking care for the safety of all persons entitled to be on the Site, Use

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 87

reasonable efforts to keep the Site and Works clear of unnecessary

obstruction so as to avoid danger to these persons.

� Provide fencing, lighting, guarding and watching of the Works until

completion and taking over

� Provide any Temporary Works (including roadways, footways,

guards and fences) which may be necessary, because of the

execution of the Works, for the use and protection of the public and

of owners and occupiers of adjacent land.

� Clause for Non conformity to EMP - Protection of the Environment

The Contractor shall implement all mitigation measures for which

responsibility is assigned to him as stipulated in the EMP Report. Any lapse in

implementing the same will attract the damage clause as detailed below:

1) All lapse in obtaining clearances / permissions under statutory regulations

and violations of any regulations with regard to eco-sensitive areas shall be

treated as a major lapse.

2) Any complaints of public, within the scope of the Contractor, formally

registered with the DSC, PMC or with the PIU and communicated to the

Contractor, which is not properly addressed within the time period

intimated by the DSC / PMC, PIU shall be treated as a major lapse.

3) Non-conformity to any of the mitigation measures stipulated in the EMP

Report (other than stated above) shall be considered as a minor lapse.

4) On observing any lapses, DSC shall issue a notice to the Contractor, to

rectify the same.

5) Any minor lapse for which notice was issued and not rectified, first and

second reminders shall be given after ten days from the original notice date

and first reminder date respectively. Any minor lapse, which is not

rectified, shall be treated as a major lapse from the date of issuing the

second reminder.

6) If a major lapse is not rectified upon receiving the notice DSC shall invoke

reduction, in the subsequent interim payment certificate.

7) For major lapses, 10% of the interim payment certificate will be withheld,

subject to a maximum limit of about 0.5% of the contract value.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 88

8) If the lapse is not rectified within one month after withholding the payment,

the amount withheld shall be forfeited.

� Post Construction Clearance

• On completion of work, wherever applicable, the Contractor will clear away

and remove from the sites surplus materials, rubbish, scaffoldings, and

temporary works of every kind and leave the whole of the sites and works in a

clean condition to the satisfaction of the Engineer.

� All temporary sedimentation and pollution control works, which are not

provided in the Bill of Quantities, shall be deemed as incidental to the civil

work and other items of work and as such no separate payment shall be made

for the same.

� Labour Welfare

(i) The Contractor shall make arrangements for the engagement of all staff and

labour, local or otherwise, and for their payment, housing, feeding and

transport.

(ii) The Contractor is encouraged, to the extent practicable and reasonable, to

employ staff and labor with appropriate qualifications and experience from

sources within the State/Country.

(iii) The Contractor shall pay rates of wages, and observe conditions of labour,

which are not lower than those established for the trade or industry where

the work is carried out. If no established rates or conditions are applicable,

the Contractor shall pay rates of wages and observe conditions which are

not lower than the general level of wages and conditions observed locally

by employers whose trade or industry is similar to that of the Contractor.

(iv) The Contractor shall inform the Contractor’s Personnel about their liability

to pay personal income taxes in the Country in respect of such of their

salaries, wages, allowances, and any benefits as are subject to taxes under

the Laws of the Country for the time being in force, and the Contractor

shall perform such duties in regard to such deductions thereof as may be

imposed on him by such Laws.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 89

(v) The Contractor shall comply with all the relevant labour Laws applicable to

the Contractor’s Personnel, including Laws relating to their employment,

health, safety, welfare, immigration and emigration, and shall allow them

all their legal rights.

(vi) The Contractor shall require his employees to obey all applicable Laws,

including those concerning safety at work. The Contractor shall provide and

maintain all necessary accommodation and welfare facilities for the

Contractor’s Personnel .No temporary dwelling units are envisaged to be

build for the labour force accommodation but rented premises will utilised

for the same with all basic amenities. The Contractor shall at all times take

all reasonable precautions to maintain the health and safety of the

Contractor’s Personnel.

(vii) In collaboration with local health authorities, the Contractor shall ensure

that medical staff, first aid facilities, sick bay and ambulance service are

available at all times at the Site and at any accommodation for Contractor’s

and Employer’s Personnel, and that suitable arrangements are made for all

necessary welfare and hygiene requirements and for the prevention of

epidemics.

(viii) The Contractor shall appoint an accident prevention officer at the Site,

responsible for maintaining safety and protection against accidents. This

person shall be qualified for this responsibility, and shall have the authority

to issue instructions and take protective measures to prevent accidents.

Accident records are to be maintained at site for the Engineer’s vigilance.

(ix) The contractor shall acquire appropriate labour licence and labour insurance

as per the labour act.

(x) The Contractor shall keep complete and accurate records of the

employment of labour at the Site. The records shall include the names,

ages, genders, hours worked and wages paid to all workers. These records

shall be summarized on a monthly basis and shall be available for

inspection by the Engineer during normal working hours.

(xi) The Contractor shall ensure that during continuance of the contract, the

Contractor and his Sub-contractors shall abide at all times by all existing

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 90

enactments on environmental protection and rules made there under,

regulations, notifications and bye-laws of the State or Central Government,

or local authorities and any other law, bye-law, regulations that may be

passed or notification that may be issued in this respect in future by the

State or Central Government or the local authority.

• The Water (Prevention and Control of Pollution) Act, 1974: This provides for the

prevention and control of water pollution and the maintaining and restoring of

wholesomeness of water.

• The Air (Prevention and Control of Pollution) Act, 1981: This provides for

prevention, control and abatement of air pollution. 'Air Pollution' means the

presence in the atmosphere of any 'air pollutant', which means any solid, liquid or

gaseous substance (including noise) present in the atmosphere in such

concentration as may be or tend to be injurious to human beings or other living

creatures or plants or property or environment.

• The Environment (Protection) Act, 1986: This provides for the protection and

improvement of environment and for matters connected therewith, and the

prevention of hazards to human beings, other living creatures, plants and property.

'Environment' includes water, air and land and the interrelationship which exists

among and between water, air and land, and human beings, other living creatures,

plants, micro-organism and property.

• The Public Liability Insurance Act, 1991: This provides for public liability

insurance for the purpose of providing immediate relief to the persons affected by

accident occurring while handling hazardous substances and for matters connected

herewith or incidental thereto. Hazardous substance means any substance or

preparation which is defined as hazardous substance under the Environment

(Protection) Act 1986, and exceeding such quantity as may be specified by

notification by the Central Government.

� Labour Enactments:

• The Contractor and his Sub-contractors shall abide at all times by all existing

labour enactments and rules made there under, regulations, notifications and bye

laws of State or Central Government or local authority and any other labour law

(including rules), regulations, bye laws that may be passed or notification that may

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 91

be issued under any labour law in future either by the State or the Central

Government or the local authority.

• The Contractor shall, if required by the Engineer, provide a return in detail of the

employment of labour, in such form and at such intervals as the Engineer may

prescribe, showing the staff and the numbers of the several classes of labour,

employed by the Contractor on the Site, from time to time.

(i) Workmen Compensation Act, 1923

The Act provides for compensation in case of injury by accident arising out of and during

the course of employment.

(ii) Payment of Gratuity Act, 1972

Gratuity is payable to an employee under the Act on satisfaction of certain conditions on

separation if an employee has completed 5 years service or more or on death at the rate of

15 days wages for every completed year of service. The Act is applicable to all

establishments employing 10 or more employees.

(iii) Employees’ PF and Miscellaneous Provisions Act, 1952

The Act provides for monthly contributions by the employer plus workers@10% or

8.33%

The benefits payable under the Act are:

• Pension or family pension on retirement or death as the case may be.

• Deposit linked insurance on the death in harness of the worker.

• Payment of PF accumulation on retirement/death etc.

(iv) Maternity Benefit Act, 1951

The Act provides for leave and some other benefits to women employees in case of

confinement or miscarriage etc.

(v) Contract Labour (Regulation and Abolition) Act, 1970

The Act provides for certain welfare measures to be provided by the Contractor to

contract labour and in case the Contractor fails to provide, the same are required to be

provided by the Principal Employer by Law. The principal employer is required to take

Certificate of Registration and the Contractor is required to take a License from the

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 92

designated Officer. The Act is applicable to the establishments or Contractor of principal

employer if they employ 20 or more contract labour.

(vi) Minimum Wages Act, 1948

The employer is supposed to pay not less than the Minimum Wages fixed by appropriate

Government as per provisions of the Act if the employment is a scheduled employment.

Construction of Buildings, Roads, and Runways are scheduled employment.

(vii) Payment of Wages Act, 1936

It lays down as to by what date the wages are to be paid, when it will be paid and what

deductions can be made from the wages of the workers.

(viii) Equal Remuneration Act, 1979

The Act provides for payment of equal wages for work of equal nature to Male and

Female workers and not for making discrimination against Female employees in the

matters of transfers, training and promotions etc.

(ix) Payment of Bonus Act, 1965

The Act is applicable to all establishments employing 20 or more workmen. The Act

provides for payments of annual bonus subject to a minimum of 8.33 % of wages and

maximum of 20 % of wages to employees drawing Rs. 3,500/- per month or less. The

bonus to be paid to employees getting Rs. 2,500/- per month or above up to Rs.3, 500/-

per month shall be worked out by taking wages as Rs.2,500/- per month only. The Act

does not apply to certain establishments. The newly set up establishments are exempted

for five years in certain circumstances. Some of the State Governments have reduced the

employment size from 20 to 10 for the purpose of applicability of the Act.

(x) Industrial Disputes Act, 1947

The Act lays down the machinery and procedure for resolution of industrial disputes, in

what situations a strike or lock-out becomes illegal and what are the requirements for

laying off or retrenching the employees or closing down the establishment.

(xi) Industrial Employment (Standing Orders) Act, 1946

It is applicable to all establishments employing 100 or more workmen (employment size

reduced by some of the States and Central Government to 50). The Act provides for

laying down rules governing the conditions of employment by the employer on matters

provided in the Act and get the same certified by the designated Authority.

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 93

(xii) Trade Unions Act, 1926

The Act lays down the procedure for registration of trade unions of workmen and

employees. The trade unions registered under the Act have been given certain immunities

from civil and criminal liabilities.

(xiii) Child Labour (Prohibition and Regulation) Act, 1986

The Act prohibits employment of children below 14 years of age in certain occupations

and processes and provides for regulation of employment of children in all other

occupations and processes. Employment of child labour is prohibited in Building and

Construction Industry.

(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of

Service) Act, 1979

The Act is applicable to an establishment which employs 5 or more interstate migrant

workmen through an intermediary (who has recruited workmen in one state for

employment in the establishment situated in another state). The inter-state migrant

workmen, in an establishment to which this Act becomes applicable, are required to be

provided certain facilities such as housing, medical aid, travelling expenses from home up

to the establishment and back, etc.

(xv) The Building and Other Construction Workers (Regulation of Employment and

Conditions of Service) Act, 1996 and the Cess Act of 1996

All the establishments who carry on any building or other construction work and employ

10 or more workers are covered under this Act. All such establishments are required to

pay Cess at rate not exceeding 2% of the cost of construction as may be notified by the

Government. The employer of the establishment is required to provide safety measures at

the Building or Construction work and other welfare measures, such as Canteens, First-

aid facilities, Ambulance, Housing accommodation for Workers near the workplace etc.

The employer to whom the Act applies has to obtain a registration certificate from the

Registering Officer appointed by the Government.

(xvi) The Factories Act, 1948

The Act lays down the procedure for approval of plans before setting up a factory, health

and safety provisions, welfare provisions, working hours, annual earned leave and

rendering information regarding accidents or dangerous occurrences to designated

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 94

authorities. It is applicable to premises employing 10 persons or more with aid of power

or 20 or more persons without the aid of power engaged in manufacturing process.

(xvii) The Apprentices Act, 1961

The Contractor shall duly comply with the provisions of the Apprentices Act, 1961, the

rules made there under and the orders that may be issued from time to time under the said

Act and the said Rules and on his failure or neglect to do so, he shall be subject to all

liabilities and penalties provided by the said Act and the said Rules. ‘The Contractor

shall, if required by the Engineer, provide a return in detail of the employment of labour,

in such form and at such intervals as the Engineer may prescribe, showing the staff and

the numbers of the several classes of labour, employed by the Contractor on the Site,

from time to time.’ Safety & Welfare Provisions for labour to be employed by the

Contractor

All necessary personal safety equipment as considered adequate by the Engineer shall be

available for use of persons employed on the Site and maintained in a condition suitable

for immediate use; and the Contractor shall take adequate steps to ensure proper use of

such equipment by those concerned All workmen at site shall be provided with safety

helmets and yellow/orange jackets. Workmen required on site during night hours shall be

provided with fluorescent yellow jackets with reflective lopes.

The Contractor shall provide all necessary fencing and lights to protect the public from

accidents and shall be bound to bear the expenses of defending every suit, action or other

proceedings at law that may be brought by any person for injury sustained owing to

neglect of the above precautions and to pay any damages and costs which may be

awarded in any such suit, action or proceedings to any such person or which may with the

consent of the Contractor be paid to compromise any claim by any such person.

I) First Aid-At every workplace, there shall be maintained, in a readily accessible place,

first aid appliances including an adequate supply of sterilized dressings and sterilised

cotton wool as prescribed in the Factory Rules of the State in which the work is

carried on. The appliances shall be kept in good order and, in large work places;

these shall be placed under the charge of a responsible person who shall be readily

available during working hours.

II) Accommodation for Labour: The Contractor shall during the progress of the work

provide, erect and maintain necessary temporary living accommodation (in rented

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 95

premises) and ancillary facilities for labour at his own expense to standards and

scales approved by the Engineer.

III) Drinking Water: In every workplace, there shall be provided and maintained at

suitable places easily accessible to labour, a sufficient supply of cold water fit for

drinking. Where drinking water is obtained from an intermittent public water supply

each workplace shall be provided with storage tanks where drinking water shall be

stored.

(The Environment Management Plan is an integral part of the contract and the contractor has

the responsibility to implement it under the supervision of the Environmental officer of the

Supervision Consultant. All actions taken by the Environmental officer shall be deemed to

have the concurrence of the “Engineer” as defined in the contract data. All management

measures of the Environment and Management plan are deemed to be incidental to work

unless otherwise provided in the BOQ. No separate payments shall be made for implementing

these measures.)

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 96

APPENDIX 2 RAPID ENVIRONMENTAL ASSESSMENT (REA) CHECKLIST

URBAN DEVELOPMENT

Instructions:

(i) The project team completes this checklist to support the environmental classification of a

project. It is to be attached to the environmental categorization form and submitted to the

Environment and Safeguards Division (RSES) for endorsement by Director, RSES and for

approval by the Chief Compliance Officer.

(ii) This checklist focuses on environmental issues and concerns. To ensure that social dimensions

are adequately considered, refer also to ADB's (a) checklists on involuntary resettlement and

Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and

participation; and (d) gender checklists.

(iii) Answer the questions assuming the “without mitigation” case. The purpose is to identify

potential Impacts. Use the “remarks” section to discuss any anticipated mitigation measures.

1. Country/Project Title: IDIPT – Tamil Nadu – Infrastructure Development at

Tharangambadi Town Panchayat, Nagappattinam District - Construction of sanitary

complexes for the floating population, placement of gravity entailed deep earth bins

for garbage collection (2.5 cubic meters), Placement of energy efficient heritage street

lighting, Placement of tourism friendly uniform signage’s for convenience of the

tourists and Placement of street furniture such as litter bins & benches

Sector Division:

SCREENING QUESTIONS Yes No REMARKS

A. Project Siting

Is the Project area adjacent to or within

any of the following environmentally

sensitive areas?

• Cultural heritage site √ The sites have been located away

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 97

from heritage structures and being

small facilities , pose no threat to the

heritage structures/places of cultural

importance

• Protected Area √

• Wetland √

• Mangrove √

• Estuarine √

• Buffer zone of protected area √

• Special area for protecting biodiversity

• Bay √

B. Potential Environmental Impacts

Will the Project cause…

• Ecological disturbances arising from

the establishment of a plant or facility

complex in or near sensitive habitats?

• Eventual degradation of water bodies

due to discharge of wastes and other

effluents from plant or facility

complex?

• Serious contamination of soil and

groundwater?

• Aggravation of solid waste problems

in the area?

• Public health risks from discharge of

wastes and poor air quality; noise and

foul odour from plant emissions?

• Short-term construction impacts

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 98

• Soil erosion √

• Deterioration of water quality

The proposed works will not result

in pollution of surface and ground

water or cause overflows to and

flooding of surroundings

• Deterioration of air quality √

• Noise and vibration from construction equipment

Minor impact as structures are

proposed

• dislocation or involuntary resettlement of people

Rehabilitation and resettlement do

not arise since in the case of

signages, Garbage bins, and road

furniture, they are to be constructed

within the right of way of the

existing roads. Further, in the case of

Sanitary complexes, the sites are

owned by the ULB and free of all

encumbrances.

• Social conflicts arising from the

influx of construction labourers from

other areas?

No significant emigrant labour is

required

• Environmental degradation (e.g.

erosion, soil and water contamination,

loss of soil fertility, disruption of

wildlife habitat) from intensification

of agricultural land use to supply raw

materials for plant operation; and

modification of natural species

diversity as a result of the

transformation to monoculture

practices?

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 99

• Water pollution from discharge of liquid effluents?

The proposed works will not result

in pollution of surface and ground

water or cause overflows to and

flooding of surroundings

• Air pollution from all plant operations?

• Gaseous and odour emissions to the

atmosphere from processing

operations?

• Accidental release of potentially

hazardous solvents, acidic and

alkaline materials?

• Uncontrolled in-migration with

opening of roads to forest area and

overloading of social infrastructure?

• Occupational health hazards due to

fugitive dust, materials handling,

noise, or other process operations?

• Disruption of transit patterns, creation of noise and congestion, and pedestrian hazards aggravated by heavy trucks?

• Disease transmission from inadequate waste disposal?

NB: Taking into consideration of various selection criteria indicated in the above checklist,

the project sub-components proposed can be classified as Category B, as it is likely to have

minimal or no adverse environmental impacts and therefore does not require conducting EIA

or IEE.

2. Country/Project Title: IDIPT – Tamil Nadu – Infrastructure Development at

Tharangambadi Town Panchayat, Nagappattinam District - Conservation &

Restoration of Dansborg Fort

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 100

The project Components confined in a single location Tranquebar Fort (Dansborg).,

The proposed works shall not result in pollution of surface and ground water or cause

overflows to and flooding of surroundings, especially the tourist attraction.

An assessment of the Project Sub-components has been carried out as per the Rapid

Environmental Assessment REA screening Checklist as given below:

REA SCREENING CHECKLIST

SCREENING QUESTIONS Yes No REMARKS

A. Project Siting

Is the Project area adjacent to or within

any of the following environmentally

sensitive areas?

• Cultural heritage site

The sites have been located away

from heritage structures and being

small facilities , pose no threat to the

heritage structures/places of cultural

importance

• Protected Area √

• Wetland √

• Mangrove √

• Estuarine √

• Buffer zone of protected area √

• Special area for protecting biodiversity

• Bay √

B. Potential Environmental Impacts

Will the Project cause…

• Ecological disturbances arising from

the establishment of a plant or facility

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 101

complex in or near sensitive habitats?

• Eventual degradation of water bodies

due to discharge of wastes and other

effluents from plant or facility

complex?

• Serious contamination of soil and

groundwater?

• Aggravation of solid waste problems

in the area?

• Public health risks from discharge of

wastes and poor air quality; noise and

foul odour from plant emissions?

• Short-term construction impacts

• Soil erosion √

• Deterioration of water quality

The proposed works will not result

in pollution of surface and ground

water or cause overflows to and

flooding of surroundings

• Deterioration of air quality √

• Noise and vibration from construction equipment √

Minor impact as structures are

proposed

• dislocation or involuntary resettlement of people

Rehabilitation and resettlement do

not arise

• Social conflicts arising from the

influx of construction labourers from

other areas?

No significant emigrant labour is

required

• Environmental degradation (e.g.

erosion, soil and water contamination,

loss of soil fertility, disruption of

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 102

wildlife habitat) from intensification

of agricultural land use to supply raw

materials for plant operation; and

modification of natural species

diversity as a result of the

transformation to monoculture

practices?

• Water pollution from discharge of liquid effluents?

• Air pollution from all plant operations?

• Gaseous and odour emissions to the

atmosphere from processing

operations?

• Accidental release of potentially

hazardous solvents, acidic and

alkaline materials?

• Uncontrolled in-migration with

opening of roads to forest area and

overloading of social infrastructure?

• Occupational health hazards due to

fugitive dust, materials handling,

noise, or other process operations?

• Disruption of transit patterns, creation of noise and congestion, and pedestrian hazards aggravated by heavy trucks?

• Disease transmission from inadequate waste disposal?

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 103

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 104

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 105

APPENDIX 4

ENVIRONMENTAL MONITORING FORMAT

1) Work Details

Table 1: Work Details and Risks

Loc

atio

ns

Sub-

proj

ects

Com

pone

nts

(Pac

kage

No.

)

Nam

e of

the

cont

ract

Lis

ting

of w

orks

und

er th

e

pack

age

Star

ting

Dat

e (l

and

clea

ranc

e)

and

sche

dule

dat

e of

com

plet

ion

Wha

t typ

e of

wor

ks c

ontin

ued

at

pres

ent

Prog

ress

Per

cent

age

Exp

ecte

d ch

ange

s fr

om

appr

oved

sco

pe

Fulf

illm

ent o

f ob

ject

ives

- T

ype

of r

emed

ial m

easu

re n

eede

d

Key

ass

umpt

ions

and

ris

ks th

at

affe

ct a

ttai

nmen

t of

the

obje

ctiv

e

2) Implementation of Environmental Management Plan

Table 2: Status of Environment, Forest and Other Clearances

City / Town Work (Package No.) Applicable Legislation /

Type of Clearance

Clearance given by and

date Subject / Issue Remarks / Action needed

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 106

Table 3: Compliance with Environmental Management Plan

Des

crip

tion

of

Impa

ct

Miti

gatio

n M

easu

res

Prop

osed

Impl

anta

tion

Sta

tus

Det

ail /

Rem

arks

on

Impl

emen

tati

on

Mon

itori

ng m

etho

ds a

nd

freq

uenc

y

Mon

itori

ng c

ondu

cted

by

Mon

itori

ng R

emar

ks

(Exc

elle

nt /

Satis

fact

ory

/

Part

ially

Sat

isfa

ctor

y /

Bel

ow S

atis

fact

ion

/ Poo

r /

Ver

y Po

or)

Rem

arks

and

act

ions

take

n to

impr

ove

impl

emen

tati

on

Detailed Design

Pre- construction

Construction

Table 4: Measurement of Pollutants

Components Package/ Location Period of monitoring Parameters /Pollutants Standard Base line status

Monitoring result

during project

Implementation

Remarks

Noise

Air Quality

Water Quality

Soil Quality

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 107

APPENDIX 5

SAMPLE GRIEVANCE REGISTRATION FORM

(To be available in Local Language)

The Project welcomes complaints suggestions, queries and comments regarding project

implementation. We encourage persons with grievance to provide their name and contact

information to enable us to get in touch with you for clarification and feedback.

Should you choose to include your personal details but prefer to keep the information’s remain

confidential, please inform us by typing *(CONFIDENTIAL)* above your name. Thank you.

Date Place of registration

Contact Information / Personal Details

Name Gender: _Male _Female Age:

Home Address

Village / Town

District

Phone no.

E-mail

Complaint / Suggestion / Comment / Question Please provide the details (who, what,

where and how) of your grievance below :

If included as attachment/note/letter, please tick here:

How do you want us to reach you for feedback or update on your comment/grievance?

Infrastructure development Investment Program for Tourism, Tamil Nadu (IDIPT-TN) ( Project – 2)

IEE-Tharangambadi

Department of Tourism, GoTN 108

FOR OFFICIAL USE ONLY

Registered by : (Name of official registering grievance)

Verified thru :

Note/Letter

_E-mail

Reviewed by : (Names/Positions of Official(s) reviewing grievance)

Action taken :

Whether Action Taken

Disclosed: Yes No

Means of Disclosure:

Appendix – 3

Position Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun JulHom

e

Fiel

dTotal

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

1 DR.ANUP KUMAR ADITYA Team Leader

Home 8

Field 26 34

2 DR.R.PARAMASIVAMSafeguards Specialist

Environment & Social

Home 3

Field 7 10

1 K1- Mr. M. Devanathan Team Leader

Home 0 0

Field 30 30

2 K9- Mr. Anilkumar PandaSafeguards Specialist

Environment & Social

Home 0

Field 20 20

LEGENDS:

Note: The Strategy have been prepared with reference to available data and however since the volume and nature of balance project work under Tranche - 1 and the new projects to be identified under Tranche -2 is unknown and have not been finalized till now,

hence the above mentioned schedule is tentative and shall be revised at the later stage based on the Contractor's work Programme.

KEY EXPERTS - PMC

FULL TIME INPUT PART TIME / INTERMITTENT INPUT - Would be engaged with reference to Departmant of Tourism Requirement

KEY EXPERTS - DSC

Implementation Sequence of the Key Experts

No.2013 2014 2015 2016

Total Time -

Input