Upload
pppnews
View
214
Download
0
Embed Size (px)
Citation preview
8/9/2019 Infrastructure Projects Financing.
1/11
HM Trsr
Financing PFI projects in the creditcrisis and the Treasurys response
RepoRT by THeCoMpTRolleR andaudiToR GeneRal
HC 287
SeSSion 20102011
27 july 2010
8/9/2019 Infrastructure Projects Financing.
2/11
4 Smmr Financing PFI projects in the credit crisis and the Treasurys response
Summary
Introduction
Economic and social inrastructure orms the backbone o economic activity1
in the United Kingdom, and enables the delivery o public services across thecountry. The term inrastructure encompasses social and economic sectors such as
communications, education, energy, health, transport, waste and water.
In the ve years to April 2010 approximately 30 billion per year was invested in2
UK inrastructure. Future investment is orecast in the range o 40-50 billion per annum
until 2030. Investment is nanced in a range o ways:
Finance can be provided by private companies, but with some orm o explicit
public regulation or implicit public support. Examples include the water and energy
sectors, which are largely privately owned and nanced.
Finance can be provided by public resources only, or or large one-o projects
such as the Olympics, with a mixture o public and private resources.
Finance can also be provided under the Private Finance Initiative (PFI) or other
orms o Public Private Partnership (PPP). Sectors o economic and social
inrastructure provided in this way include, or example, new hospitals and
some roads.
PFI projects are long-term contractual arrangements between public authorities3
and private sector companies with project nancing raised by private companies.
Project nance means that the nancing is provided or a sole project, through a special
company set up or the purpose. Departments generally conclude that the contract
oers value or money when the benets associated with the transer o project risk
outweigh any additional PFI nancing cost.
PFI projects typically use around 90 per cent debt nance and 10 per cent equity4
nance. The debt portion o this nancing can be provided by bank loans and/or bonds.
The banks and bond holders receive interest on their loans related to risks. Interest
charged on a bank loan is usually a combination o two parts, the reerence rate (usually
the interbank rate) and the loan margin (Fgr 1). The interbank rate refects general
market risks, while the loan margin refects project specic risks. Variable rate bank loans
are swapped to xed rates to provide stable monthly payments over the project lie.
8/9/2019 Infrastructure Projects Financing.
3/11
Financing PFI projects in the credit crisis and the Treasurys response Smmr 5
Bond nance is where a loan is split up into many identical bonds which saving5
institutions can trade in public markets known as capital markets. Credit Rating
Agencies analyse individual project and nance structure risks and publish a rating as
a guide to investors. Beore the credit crisis, the purchase o credit insurance could
improve the rating o the bond, thus making the risks acceptable to non-specialised
lenders such as pension unds.
In late 2007, market condence in the providers o this credit insurance collapsed,6
leaving PFI projects in the United Kingdom without access to capital markets.
The bank loan market, however, continued to unction. Banks can make loans7
while they have sucient reserve capital (see Glossary) to allocate against them. To keep
making new loans banks must ree up reserve capital by selling existing loans, in whole
or in part, to other banks or raise new capital. This process is known as syndication.
The collapse o Lehman Brothers in September 2008 led to a halt in loan syndication,continuing throughout 2009. This limited the ability o banks to make new PFI loans.
The equity nance is provided by a projects contractors and nancial institutions.8
It typically comprises a mixture o shares and shareholder loans. Equity nance is known
as risk capital because, generally, the equity will be lost rst i the project company
ails. The shareholder loans are higher risk as their repayment in a ailure is junior to the
external debt, known as senior debt, which is repaid rst.
Figure 1
This shows how a variable rate loan is converted to a fixed rate and the
composition of loan interest costs
NOTES
1 LIBOR means the London Inter Bank Offered Rate (see Glossary) which is similar to base rate, but usually higher to
reflect risk of bank failure.
2 A swap fee is payable to convert a variable rate loan to a fixed rate loan. Short-term rates can often exceed long-term
rates during the life of a project.
Source: National Audit Office
Reflects
Project Risks
Reflects
Market Risks
Cushion for changes
in Market Risks
Swap Fee
Margin
Index Rate
(LIBOR) Variable
Swapped Rate
(LIBOR)
Fixed Long Term
Margin
8/9/2019 Infrastructure Projects Financing.
4/11
6 Smmr Financing PFI projects in the credit crisis and the Treasurys response
Sc
This report examines the eects o the credit crisis on privately nanced9
government inrastructure projects and the Treasurys response. Although unable
to control conditions in the nancial markets, the Treasury sets guidance on how
departments assess value or money and approves signicant projects. It thereore
was responsible or coordinating the Governments response to the nancial crisis and
mitigating its impact on inrastructure procurement. In particular, the report sets out:
how the Treasury responded to the impact o the credit crisis on the availability
and terms o nance or PFI contracts;
the impact o the credit crisis on the cost o nance or PFI contracts; and
the challenges ahead.
The report does not consider the value or money o individual projects, nor does it
address the remit o Inrastructure UK, the new body established to coordinate the
Governments approach to the inrastructure challenge. The report does, however, make
recommendations on issues that Inrastructure UK should address.
Figure 2
Average international project finance loan margins compared to PFI
Margin (%)Credit Crisis
Year
No of PFI deals
NOTES
1 The margins are averages based on monthly data.
2 Numbers in bold are the number of PFI projects financed in that year.
Source: National Audit Office and project finance chart based on data from the Infrastructure Project Finance Benchmarking Report 1995-2009 further
description at http://infrastructureeconomics.org/2010/02/09/project-finance-benchmarking-report/
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
1998 1999 2000 2001 2002 20031995
1 15 24 46 54 68 52 54 51 61 50 57 57 31 35
1996 1997 2004 2005 2006 2007 2008 2009
All PFI
8/9/2019 Infrastructure Projects Financing.
5/11
Financing PFI projects in the credit crisis and the Treasurys response Smmr 7
K fgs
The Treasurys response to lower availability o nance
The Treasurys role in establishing the PFI market contributed to reductions10
in the risk margin o private debt nance between 1999 and 2007. Over this period,
the establishment o the PFI market and the availability o bank nance lowered nancing
costs as bank competition increased. Departments took advantage by letting around
300 contracts with relatively low nancing charges. The part o the interest cost relating
to project risk, the PFI loan margin, averaged around one per cent, or less. These rates
were lower than intern ational project loan margins which averaged 1.7 per cent rom
1994 to 2008 (Fgr 2).
As the credit crisis took hold in autumn 2008, debt nance became11
increasingly unavailable. As a result o market conditions, largely outside the
Treasurys control, rst bond nance, and then bank nance, became severely restricted.
But as the UK economy entered recession, the Government had a signicant pipeline o
inrastructure projects, with an investment value exceeding 13 billion (Fgr 3).
Figure 3
The investment value of UK infrastructure projects notified in the Official Journal of the European
Union as at March 2009
billion
NOTES
1 Building Schools for the Future (BSF) is a secondary schools investment programme.
2 Local Improvement Finance Trusts (LIFT) finance primary medical care projects.
Source: HM Treasury
Capital value of pipeline by sector
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
Housing Health Street
lighting
Emergency
Services
Libraries Education
(other)
Waste Educat ion
(BSF)
Transport Leisure Prisons NHS
LIFT
Joint-service
centres
Courts
8/9/2019 Infrastructure Projects Financing.
6/11
8 Smmr Financing PFI projects in the credit crisis and the Treasurys response
The Treasury was concerned about the macroeconomic impact o the12withdrawal o debt nance. With debt nance increasingly unavailable, individual
contracts became harder to nalise. The Treasury eared that, as a result o this potential
slowdown in new PFI contracts, the opportunity to stimulate the economy through
new inrastructure would be lost. In addition, important benets, or example, improved
school acilities and dealing with road congestion, depended on the completion o
planned PFI projects.
The Treasury thereore sought to maintain a fow o signed PFI contracts.13
The overarching Government policy in late 2008 was that the pipeline o PFI deals
should reach nancial close promptly, to stimulate national and local economies, and
create jobs. The Treasury ollowed this policy whilst continuing to apply standard PFIvalue or money tests.
Bank lending was so restricted in late 2008 that, despite Treasury14
encouragement, no sizeable contracts could be let. In September 2008, the
Treasury asked the European Investment Bank to step up its lending to inrastructure
projects which the Bank did. The Treasury, however, did not set PFI lending targets or
UK banks when they received government support during that winter. The Treasury
initiated internal discussions about such targets but did not pursue them because the
banks concerned were a sub-set o the PFI lending market and because PFI lending
was only a small part o the issues acing the Treasury in relation to its banking support.
In early 2009, there continued to be insucient bank debt or larger projects becausebanks did not resume lending as expected.
The Treasury helped to reactivate the lending market or inrastructure15
projects by setting up its own nance unit. In March 2009, the Government rapidly
set up The Inrastructure Finance Unit to address the scarcity o debt nance. The
units role was to be available to provide government loans to inrastructure projects, on
commercial terms, so shortalls in the amount o available bank nance could be met.
In April 2009, The Inrastructure Finance Unit helped to nalise a large waste16
treatment and power generation project. The unit provided a 120 million loan to
complete a 582 million nancing package or a waste treatment and power generation
project in Greater Manchester. The Treasurys participation in this loan, on the same
terms as commercial banks, is intended to be temporary and reversible.
The Treasurys willingness to lend improved market condence and17
subsequently around 35 government inrastructure projects have been agreed
without any urther public lending. The Inrastructure Finance Unit has not made any
urther loans. But since its establishment, around 35 projects have been agreed. There
is thereore some evidence that the unit improved market condence. In addition, the
availability o government loans provided some competitive tension to the banks in a
market which, since 2008, had lacked competition on loan nancing terms.
8/9/2019 Infrastructure Projects Financing.
7/11
Financing PFI projects in the credit crisis and the Treasurys response Smmr 9
Th cst fc
We ound that as a result o the credit crisis, the total interest cost o bank18
nance increased by one-th to one-third. In the 35 projects agreed ater the
establishment o The Inrastructure Finance Unit, we ound that the part o the cost
relating to loan margins on PFI deals, which had been 1 per cent or less, widened
signicantly to around 2.5 per cent on average (Fgr 4). Some, or example, the
complex Greater Manchester Waste project, will rise to more than 3 per cent in stages
over the project lie. The increased loan margins resulted in substantial increases to the
cost o nance (Figure 4).
These increases occurred despite the all in short-term borrowing rates and19
little change in the intrinsic risk prole o projects. The all in the underlying short-
term bank lending rate (the base rate) to 0.5 per cent only had a slight impact on PFI
deals. This is because the private sector xes the interest cost on their long-term PFI
borrowings. This xed interest rate, currently around 4 per cent, refects the risk o uture
changes in interest rates and is a market actor that is not specic to PFI.
In line with policy on acting to stimulate the economy, the Treasury gave20
priority to closing deals at the prevailing market rates, even i this meant paying
more and banks carrying less risk. In addition to charging higher margins, the
banks have sought to de-risk their lending to projects ollowing the credit crisis. They
renegotiated their lending terms with preerred bidders, through: lowering the proportion
o debt in projects; increasing cover ratios (see Glossary); requiring the private sector
to inject risk capital earlier; and placing more onerous conditions on when the private
investors can withdraw cash rom the project.
Figure 4
Comparison o interest costs on PFI projects
Str ds lrg ds
pr crss pst crss pr crss pst crss
K csts Sm rcts(2007)
Sch sm(2009)
FSTa(Mrch 2008)
GMW(ar 2009)
M25(M 2009)
Level o project risk Various Low High/medium High Medium
Interest rate margin (%) 0.79 2.51 1-1.15 3.25-4.50 2.5-3.5
Total interest cost (%) 5.9 6.9 5.9-6.1 7.7-8.91 6.9-7.9
Increase post crisis
(minimum) (%)
+18 +31 +17
noTeS
1 The indicative level o project risk shown above illustrates the act that the projects are not directly comparable. The change in interest margin
percentages partly reflects this.
2 The Future Strategic Tanker Aircrat (FSTA) project raised unding o 2.5 billion. Greater Manchester Waste (GMW) borrowed 582 million.
3 The increase post crisis will rise with stepped increases in the interest rate margin i refnancing (see Glossary) does not take place.
Source: KPMG and National Audit Office
8/9/2019 Infrastructure Projects Financing.
8/11
10 Smmr Financing PFI projects in the credit crisis and the Treasurys response
Our analysis shows that the higher nancing costs increased the annual21charge o typical PFI projects by 6 to 7 per cent (Appendix Two). Riskier PFI
projects experienced a larger increase. For example, we estimate that the increase in
the nancing charges o the Greater Manchester Waste project added 12 per cent to
its annual contract price (Figure 11 on page 25). To address this, in October 2008 the
Treasury increased the public sector share o any uture reductions in debt costs rom
50 per cent to 70 per cent.
We estimate that between 500 million and 1 billion o higher cost has been22
locked in, partly oset by the increased public sector share o renancing gains.
The higher end o this range refects the dierence between current PFI bank rates and
low rates prior to the credit crisis. Although departments can now press investors torenance, any renancing requires careul judgement and will depend on uture market
conditions. We doubt whether more than hal o the current higher nancing costs might
be recovered.
Higher nancing costs eroded the value or money advantage that23
departments attribute to PFI. Departments initially seek assurance on the value
or money o PFI procurement by comparing alternative ways o providing the same
results. Although we have oten expressed concern about these calculations, the
typical estimate o the PFI cost advantage lay in the range o 5 to 10 per cent (and
some cases we have audited showed smaller savings). We estimate that nancing rate
changes increased the annual contract charge by around 6 to 7 per cent. This ndingsuggests an increased risk to value or money resulting rom the credit crisis. Given the
Governments policy objectives or stimulating the economy, we accept, however, that
delays rom resubmission o individual business cases might have put the policy at risk.
Although the Treasury and departments took steps to assess the impact24
on the value or money o projects, there were limitations to their assessment.
Despite the higher nancing costs the Treasury and departments considered that all
35 contracts let in 2009 continued to represent value or money. The Treasury relied
on the normal review processes or PFI projects and a review by Partnerships UK o
the expected eect o higher bank risk margins on a sample o projects. There were,
however, limitations to this approach, as:
although the Partnerships UK review, commissioned by the Treasury, was useul
analysis, it did not cover all projects let or all aspects o nancing costs. In addition,
the Treasury monitored actual nancing terms, but did not have a ull analysis o the
impact o the higher rates on the cost o projects that closed in 2009;
some schools projects did not ully reassess their business cases, using out o date
guidance which had said an updated quantitative analysis was only necessary i
costs increased by 25 per cent; and
the value or money assessments or the M25 and Greater Manchester Waste
projects continued to rely on assumptions, rom earlier business cases,that high savings in uture whole lie costs would not be available under
conventional procurement.
8/9/2019 Infrastructure Projects Financing.
9/11
Financing PFI projects in the credit crisis and the Treasurys response Smmr 11
Challenges
The Treasury, through Inrastructure UK, aces a number o challenges to25
identiy the best unding models or projects now being developed. The Treasury
has ormed Inrastructure UK to oversee inrastructure investment in the UK, including
aspects o Government capital spending. It will ace important challenges regarding the
prioritisation o projects and procurement methods given the large decit in the public
nances and the increased cost o using private nance.
There are alternative nancing options to PFI.26 Projects such as the Olympics
and Crossrail have relied on, or will be using, a greater input o public money. There were
other nancing options, and although these would not have been likely to achieve the
Governments policy objectives in 2009, they could be relevant in uture:
The French government guarantees 80 per cent o the debt, once a project
is operating successully, to reduce the use o bank risk capital and thereore
nancing costs. The disadvantage is that this approach is not a temporary or
reversible intervention and retains some operating project risk or the public sector.
The not-or-prot European Investment Bank (EIB) is generally able to make unding
available on more avourable terms (such as margins and ees) than commercial
banks. Some European countries have used public loans in a similar manner.
Ccs v r m
We have assessed how the Treasury managed the risks to value or money,27
rather than examining individual projects. Departments ability to nance the existing
programme was in doubt until the Treasury set up The Inrastructure Finance Unit and
reactivated the lending market. Our value or money conclusion relates to projects
actually nanced in 2009. However, we accompany that conclusion with a warning on
value or money or subsequent projects.
On projects nanced in 2009:28 It is our opinion that in the circumstances the extra
nance costs o projects nanced during 2009 were value or money. We take this view
because the overarching policy priority to provide economic stimulus severely limited thescope or the Treasury to do more than they did to protect public value while ensuring
that the programme o PFI projects was moved orward. In reaching this view we
considered the act that the nancing margin being paid had widened signicantly, and
that banks renegotiated lending terms which resulted in an increased cost o risk or the
public sector. We regard this as having been oset to some extent, and as ar as was
reasonably achievable in all the circumstances, by the increased renancing gain share
terms obtained by the Treasury.
8/9/2019 Infrastructure Projects Financing.
10/11
12 Smmr Financing PFI projects in the credit crisis and the Treasurys response
We also considered whether the PFI deals could have been required to29submit individual revised business cases, which might have led to some o the least
advantageous projects being postponed or discontinued with the eect o improving
overall value or money. We concluded that this requirement would have imposed urther
delay that might have put the policy objectives at risk, and would not thereore be a
reasonable yardstick to assess the protection o value or money in the programme.
However, having concluded thus positively on projects nanced at the height o the
crisis, we would expect more exacting criteria to be applied subsequently.
On projects which have yet to be ully developed:30 There should be no
presumption, based on earlier business case analysis, that continuing the use o private
nance at current rates will be value or money. We now expect a thorough projectby project review o the orward programme to apply more exacting and narrower
criteria than applied to projects nanced at the height o the crisis. PFI is less likely to
be value or money unless there are substantial and credible savings to oset higher
nancing costs. The Treasurys ormation o Inrastructure UK gives a platorm or wider
consideration o risks, other unding options and alternative procurement models.
Rcmmts
To the Treasury
Market disruption, causing a lower availability o nance, has interrupted
the Governments inrastructure programme.The Treasury should analyse
the lessons rom the past two years. It should use these lessons to prepare a
contingency plan or how departments should handle uture market disruption
aecting procurement plans.
There is limited evidence that projects undamentally re-evaluated their
business cases in light o the credit crisis. Where there are material changes,
such as project costs increasing by 15 per cent, the Treasury should require that
the department re-evaluate the project. This re-evaluation should assess all the
benets, and potential loss o benets, o continuing the project in its current orm,
compared to other available options, including other orms o procurement.
Increased reliance on a single type o nance, with reduced competition,c
promotes ineciency. The Treasury should continue to consider how a greater
mix o nance sources, with less emphasis on the use o commercial bank loans,
can be used to nance inrastructure projects.
8/9/2019 Infrastructure Projects Financing.
11/11
Financing PFI projects in the credit crisis and the Treasurys response Smmr 13
To the Treasury and departments
Allowing individual projects to negotiate renancing will lead to variable and
overall sub-optimal outcomes. The Treasury should adopt a portolio approach
to renancing, with input rom the relevant departmental team, so that individual
authorities do not exercise any right to a renancing on a piecemeal basis. During
the operating phase o a number o projects, taking a portolio approach will
enhance the public sector bargaining position, reduce transaction costs and
increase potential gains. The Treasury should also consider whether the returns to
equity investors are aligned with the changed risk allocation in deals that has arisen
ollowing the credit crisis.
The increase in nance costs, including some reduction in risk borne by
banks, makes PFI less likely to be a value or money solution. In line with
Treasury guidance, departments should not presume that a wholly privately
nanced project oers a solution likely to secure good value or money. During
procurement, and in drating notices or the Ocial Journal o the European Union,
departments should assess a range o nancing options, including all public
nance or part public and part private nance.
The public sector gave greater priority to securing agreed contracts than
to negotiating better outcomes. In such situations, departments should
nevertheless make greater use o sensitivity analysis to inorm decision-making
over negotiation on possible small changes in nancing rates and on each request
to take on additional project risk.