INFRASTRUCTURE PROJECTS
OCTOBER 2009
Prepared By: Sura Al Shami
WET UTILITIES DESIGN WORK STAGES
HIP – Sharjah / Water & Power Business Group
Infrastructure Project – Wet Utilities Work
CONTENTS
• Brief Introduction
• Stages of the Design Work
• Open Discussion and Questions
Infrastructure Project – Wet Utilities Work
INTRODUCTION
• Infrastructure development projects refer to development of new or upgrading the existing development projects comprising of one or more of the land use types like residential, commercial, recreational and industrial etc.
Infrastructure Project – Wet Utilities Work
Airport Plot Development – Abu Dhabi
Infrastructure Project – Wet Utilities Work
Land Development
Survey & Investigation
Master Planning
Grading Plans &
Earth Work Design
Roads Design
Design of Utilities
Dry Utilities
Wet Utilities
Power Telecom Street Lighting
Water Supply Foul Drainage Storm Water Irrigation Fire Fighting
Infrastructure Project – Wet Utilities Work
Master Planning Support & Data Collection
Concept Design
Preliminary Design
Detail Design
Tender
Construction, Supervision, Commissioning and Handing over (not covered)
Review & Approval from Client and related
Authorities
Infrastructure development project comprise of the following stages
Infrastructure Project – Wet Utilities Work
STAGE 1: Master Planning Support and Data Collection
• Collection and review of all the available data including topographic maps, geological maps, existing land use, climatic data and existing utilities etc.
• Preparation of existing utilities inventory including (data collection, review and site appraisal, utility authority liaison - RFI’s)
• Assessment for the condition and loads on the existing facilities and identify requirements for upgrade, diversion, protection…etc
• Demands assessment for the new development under consideration.
• Preparation and submission of an Inception Report for client review and approval
Infrastructure Project – Wet Utilities Work
Survey Data
Land Use Layout
Infrastructure Project – Wet Utilities Work
Infrastructure Project – Wet Utilities Work
Land Use Summery Tables
Infrastructure Project – Wet Utilities Work
Existing Irrigation System from Agriculture Dept
Infrastructure Project – Wet Utilities Work
STAGE 2: Concept Design
• Development of design strategy and options.
• Evaluation of alternatives and cost estimate analysis.
• Setting up the Utilities Design Standards and Criteria.
• Fixing of the utility corridors for different ROWs of roads as per the services authorities requirements.
• Preparation of utilities concept design drawings including the preliminary size and locations of the primary infrastructure (reservoirs, pumping stations, RO and STP plants, sub stations etc) and concept network layouts
• Preparation and submission of Concept Design Report
Infrastructure Project – Wet Utilities Work
Utilities Corridors
Infrastructure Project – Wet Utilities Work
Concept Layout for SW Network
Infrastructure Project – Wet Utilities Work
STAGE 3: Preliminary Design
• Firming up the systems layout plans.
• Hydraulic design and sizing of systems (usually by means computer programs for hydraulic design and analysis).
• Preliminary civil, M&E and structural design of primary structures like reservoirs, pumping stations etc and setting up the design parameters for RO plants and STP.
• Preparation of preliminary drawings (Layouts and Details)
• Quantity survey and preliminary cost estimates.
• Preparation of Preliminary Design Report
Infrastructure Project – Wet Utilities Work
Preliminary Layout for Foul Network
Infrastructure Project – Wet Utilities Work
STAGE 4: Detail Design
• Finalization of the layout in exact corridor
• Conflict resolution with other services
• Final hydraulic design and systems sizing
• Preparation of manhole schedules and profiles
• Detailed civil, M&E and structural designs for LS, PS, tanks and Reservoir.
• Preparation of final detailed drawings
• Preparation of a Detailed Design Report
Infrastructure Project – Wet Utilities Work
Manhole Schedule
Infrastructure Project – Wet Utilities Work
Longitude Profile
Infrastructure Project – Wet Utilities Work
STAGE 5: Tender
• Quantity surveys and preparation of Bill of Quantities.
• Preparation of technical specifications.
• Specialty equipments or items, such as packaged STP or RO plants
• Preparation of Tender Documents.
• Invitation for Tenders
Infrastructure Project – Wet Utilities Work
BOQs Example
Infrastructure Project – Wet Utilities Work
Invitation to Tenderers Example
Infrastructure Project – Wet Utilities Work
Open Discussion and Questions