modelo para informes de soldadura
Citation preview
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 11/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI BR109-DN50-HCY 5 2 SW 40 304L W2 W2 11-Nov-14
2 C DEMI BR109-DN50-HCY 11 2 SW 40 304L W2 W2 11-Nov-14
3 C DEMI BR109-DN50-HCY 12 2 SW 40 304L W2 W2 11-Nov-14
4 C DEMI BR109-DN50-HCY 13 2 SW 40 304L W2 W2 11-Nov-14
5 C DEMI BR109-DN50-HCY 14 2 SW 40 304L W2 W2 11-Nov-14
6 C DEMI BR109-DN50-HCY 15 2 SW 40 304L W2 W2 11-Nov-14
7 C DEMI BR109-DN50-HCY 16 2 SW 40 304L W2 W2 11-Nov-14
8 C DEMI BR109-DN50-HCY 17 2 SW 40 304L W2 W2 11-Nov-14
9 C DEMI BR109-DN50-HCY 18 2 SW 40 304L W2 W2 11-Nov-14
10 C DEMI BR109-DN50-HCY 20 2 SW 40 304L W2 W2 11-Nov-14
11 C DEMI BR109-DN50-HCY 21 2 SW 40 304L W2 W2 11-Nov-14
12 C DEMI BR109-DN50-HCY 22 2 SW 40 304L W2 W2 11-Nov-14
13 C DEMI BR109-DN50-HCY 25 2 SW 40 304L W2 W2 11-Nov-14
14 C DEMI BR109-DN50-HCY 26 2 SW 40 304L W2 W2 11-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 12/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI BR109-DN50-HCY 29 2 SW 40 304L W2 W2 12-Nov-14
2 C DEMI BR109-DN50-HCY 28 2 SW 40 304L W2 W2 12-Nov-14
3 C DEMI BR109-DN50-HCY 66 2 SW 40 304L W2 W2 12-Nov-14
4 C DEMI BR109-DN50-HCY 29 2 SW 40 304L W2 W2 12-Nov-14
5 C DEMI BR109-DN50-HCY 65 2 SW 40 304L W2 W2 12-Nov-14
6 C DEMI BR109-DN50-HCY 64 2 SW 40 304L W2 W2 12-Nov-14
7 C DEMI BR109-DN50-HCY 63 2 SW 40 304L W2 W2 12-Nov-14
8 C DEMI BR109-DN50-HCY 60 2 SW 40 304L W2 W2 12-Nov-14
9 C DEMI BR109-DN50-HCY 59 2 SW 40 304L W2 W2 12-Nov-14
10 C DEMI BR109-DN50-HCY 58 2 SW 40 304L W2 W2 12-Nov-14
11 C DEMI BR109-DN50-HCY 57 2 SW 40 304L W2 W2 12-Nov-14
12 C DEMI BR109-DN50-HCY 49 2 SW 40 304L W2 W2 12-Nov-14
13 C DEMI BR109-DN50-HCY 48 2 SW 40 304L W2 W2 12-Nov-14
14 C DEMI BR109-DN50-HCY 47 2 SW 40 304L W2 W2 12-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 13/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI BR109-DN50-HCY 1 1.1/2 SW 40 304L W2 W2 13-Nov-14
2 C DEMI BR109-DN50-HCY 3 1.1/2 SW 40 304L W2 W2 13-Nov-14
3 C DEMI BR109-DN50-HCY 2 1.1/2 SW 40 304L W2 W2 13-Nov-14
4 C DEMI BR109-DN50-HCY 36 2 SW 40 304L W2 W2 13-Nov-14
5 C DEMI BR109-DN50-HCY 34 1.1/2 SW 40 304L W2 W2 13-Nov-14
6 C DEMI BR109-DN50-HCY 33 1.1/2 SW 40 304L W2 W2 13-Nov-14
7 C DEMI BR109-DN50-HCY 6 .1/2 SW 40 304L W2 W2 13-Nov-14
8 C DEMI BR109-DN50-HCY 7 .1/2 SW 40 304L W2 W2 13-Nov-14
9 C DEMI BR109-DN50-HCY 8 .1/2 SW 40 304L W2 W2 13-Nov-14
10 C DEMI BR109-DN50-HCY 37 .1/2 SW 40 304L W2 W2 13-Nov-14
11 C DEMI BR109-DN50-HCY 38 .1/2 SW 40 304L W2 W2 13-Nov-14
12 C DEMI BR109-DN50-HCY 39 .1/2 SW 40 304L W2 W2 13-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 14/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI BR109-DN50-HCY 46 2 SW 40 304L W2 W2 14-Nov-14
2 C DEMI BR109-DN50-HCY 45 2 SW 40 304L W2 W2 14-Nov-14
3 C DEMI BR109-DN50-HCY 44 2 SW 40 304L W2 W2 14-Nov-14
4 C DEMI BR109-DN50-HCY 43 2 SW 40 304L W2 W2 14-Nov-14
5 C DEMI BR109-DN50-HCY 42 2 SW 40 304L W2 W2 14-Nov-14
6 C DEMI BR109-DN50-HCY 69 .3/4 SW 40 304L W2 W2 14-Nov-14
7 C DEMI BR109-DN50-HCY 70 .3/4 SW 40 304L W2 W2 14-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 15/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI BR109-DN50-HCY 71 .3/4 SW 40 304L W2 W2 15-Nov-14
2 C DEMI BR109-DN50-HCY 72 .3/4 SW 40 304L W2 W2 15-Nov-14
3 C DEMI BR109-DN50-HCY 51 .3/4 SW 40 304L W2 W2 15-Nov-14
4 C DEMI BR109-DN50-HCY 52 .3/4 SW 40 304L W2 W2 15-Nov-14
5 C DEMI BR109-DN50-HCY 53 .3/4 SW 40 304L W2 W2 15-Nov-14
6 C DEMI BR109-DN50-HCY 55 .3/4 SW 40 304L W2 W2 15-Nov-14
7 C DEMI BR109-DN50-HCY 54 .3/4 SW 40 304L W2 W2 15-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 16/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBSENSAYOS
FECHA VTPT RT UT MT A R
1 C DEMI BR108-DN25-HCY 1 1 SW 40 304L W2 W2 16-Nov-14
2 C DEMI BR108-DN25-HCY 2 1 SW 40 304L W2 W2 16-Nov-14
3 C DEMI BR108-DN25-HCY 3 1 SW 40 304L W2 W2 16-Nov-14
4 C DEMI BR108-DN25-HCY 4 1 SW 40 304L W2 W2 16-Nov-14
5 C DEMI BR108-DN25-HCY 5 1 SW 40 304L W2 W2 16-Nov-14
6 C DEMI BR108-DN25-HCY 6 1 SW 40 304L W2 W2 16-Nov-14
7 C DEMI BR108-DN25-HCY 7 1 SW 40 304L W2 W2 16-Nov-14
8 C DEMI BR108-DN25-HCY 8 1 SW 40 304L W2 W2 16-Nov-14
9 C DEMI BR108-DN25-HCY 9 1 SW 40 304L W2 W2 16-Nov-14
10 C DEMI BR108-DN25-HCY 10 1 SW 40 304L W2 W2 16-Nov-14
11 C DEMI BR108-DN25-HCY 11 1 SW 40 304L W2 W2 16-Nov-14
12 C DEMI BR108-DN25-HCY 12 1 SW 40 304L W2 W2 16-Nov-14
13 C DEMI BR108-DN25-HCY 13 1 SW 40 304L W2 W2 16-Nov-14
14 C DEMI BR108-DN25-HCY 14 1 SW 40 304L W2 W2 16-Nov-14
15 C DEMI BR108-DN25-HCY 15 1 SW 40 304L W2 W2 16-Nov-14
16 C DEMI BR108-DN25-HCY 16 1 SW 40 304L W2 W2 16-Nov-14
17 C DEMI BR108-DN25-HCY 17 1 SW 40 304L W2 W2 16-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 17/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI BR108-DN25-HCY 18 1 SW 40 304L W2 W2 17-Nov-14
2 C DEMI BR108-DN25-HCY 19 1 SW 40 304L W2 W2 17-Nov-14
3 C DEMI BR108-DN25-HCY 21 1 SW 40 304L W2 W2 17-Nov-14
4 C DEMI BR108-DN25-HCY 22 1 SW 40 304L W2 W2 17-Nov-14
5 C DEMI BR108-DN25-HCY 23 1 SW 40 304L W2 W2 17-Nov-14
6 C DEMI BR108-DN25-HCY 25 1 SW 40 304L W2 W2 17-Nov-14
7 C DEMI BR108-DN25-HCY 26 1 SW 40 304L W2 W2 17-Nov-14
8 C DEMI BR108-DN25-HCY 27 1 SW 40 304L W2 W2 17-Nov-14
9 C DEMI BR108-DN25-HCY 28 1 SW 40 304L W2 W2 17-Nov-14
10 C DEMI BR108-DN25-HCY 29 1 SW 40 304L W2 W2 17-Nov-14
11 C DEMI BR108-DN25-HCY 30 1 SW 40 304L W2 W2 17-Nov-14
12 C DEMI BR108-DN25-HCY 31 1 SW 40 304L W2 W2 17-Nov-14
13 C DEMI BR108-DN25-HCY 32 1 SW 40 304L W2 W2 17-Nov-14
14 C DEMI BR108-DN25-HCY 33 1 SW 40 304L W2 W2 17-Nov-14
15 C DEMI BR108-DN25-HCY 34 1 SW 40 304L W2 W2 17-Nov-14
16 C DEMI BR108-DN25-HCY 35 1 SW 40 304L W2 W2 17-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 21/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI BR308 DN25HCY 21 1 SW 40 304L W6 W6 21-Nov-14
2 C DEMI BR308 DN25HCY 19 1 SW 40 304L W6 W6 21-Nov-14
3 C DEMI BR308 DN25HCY 8 1 SW 40 304L W6 W6 21-Nov-14
4 C DEMI BR308 DN25HCY 29 1 SW 40 304L W6 W6 21-Nov-14
5 C DEMI BR309 DN50HCY 29 2 SW 40 304L W16 W16 21-Nov-14
6 C DEMI BR309 DN50HCY 30 2 SW 40 304L W16 W16 21-Nov-14
7 C DEMI BR309 DN50HCY 18 2 SW 40 304L W16 W16 21-Nov-14
8 C DEMI BR309 DN50HCY 26 2 SW 40 304L W16 W16 21-Nov-14
9 C DEMI BR309 DN50HCY 19 .1/2 SW 40 304L W16 W16 21-Nov-14
10 C DEMI BR309 DN50HCY 1 1.1/2 SW 40 304L W16 W16 21-Nov-14
11 C DEMI BR309 DN50HCY 2 1.1/2 SW 40 304L W16 W16 21-Nov-14
12 C DEMI BR309 DN50HCY 44 1.1/2 SW 40 304L W16 W16 21-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 19/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI 05GCK01 BR309 DN50-HCY 2 1.1/2 SW 40 304L W15 W15 19-Nov-14
2 C DEMI 05GCK01 BR309 DN50-HCY 3 1.1/2 SW 40 304L W15 W15 19-Nov-14
3 C DEMI 05GCK01 BR309 DN50-HCY 4 2 SW 40 304L W15 W15 19-Nov-14
4 C DEMI 05GCK01 BR309 DN50-HCY 5 2 SW 40 304L W15 W15 19-Nov-14
5 C DEMI 05GCK01 BR309 DN50-HCY 11 2 SW 40 304L W15 W15 19-Nov-14
6 C DEMI 05GCK01 BR309 DN50-HCY 12 2 SW 40 304L W15 W15 19-Nov-14
7 C DEMI 05GCK01 BR309 DN50-HCY 17 2 SW 40 304L W15 W15 19-Nov-14
8 C DEMI 05GCK01 BR309 DN50-HCY 18 2 SW 40 304L W15 W15 19-Nov-14
9 C DEMI 05GCK01 BR309 DN50-HCY 19 .1/2 SW 40 304L W15 W15 19-Nov-14
10 C DEMI 05GCK01 BR309 DN50-HCY 26 2 SW 40 304L W15 W15 19-Nov-14
11 C DEMI 05GCK01 BR309 DN50-HCY 27 2 SW 40 304L W15 W15 19-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 20/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBS ENSAYOS FECHA VTPT RT UT MT A R
1 C DEMI 05GCK01BR309DN50-HCY 20 .3/4 SW 40 304L W16 W16 20-Nov-14
2 C DEMI 05GCK01BR309DN50-HCY 21 .3/4 SW 40 304L W16 W16 20-Nov-14
3 C DEMI 05GCK01BR309DN50-HCY 22 .3/4 SW 40 304L W16 W16 20-Nov-14
4 C DEMI 05GCK01BR309DN50-HCY 23 .3/4 SW 40 304L W16 W16 20-Nov-14
5 C DEMI 05GCK01BR309DN50-HCY 24 .3/4 SW 40 304L W16 W16 20-Nov-14
6 C DEMI 05GCK01BR309DN50-HCY 25 .3/4 SW 40 304L W16 W16 20-Nov-14
7 C DEMI 05GCK01BR309DN50-HCY 62 .3/4 SW 40 304L W16 W16 20-Nov-14
8 C DEMI 05GCK01BR309DN50-HCY 63 .3/4 SW 40 304L W16 W16 20-Nov-14
9 C DEMI 05GCK01BR309DN50-HCY 64 .3/4 SW 40 304L W16 W16 20-Nov-14
10 C DEMI 05GCK01BR309DN50-HCY 65 .3/4 SW 40 304L W16 W16 20-Nov-14
11 C DEMI 05GCK01BR309DN50-HCY 66 .3/4 SW 40 304L W16 W16 20-Nov-14
12 C DEMI 05GCK01BR309DN50-HCY 67 .3/4 SW 40 304L W16 W16 20-Nov-14
13 C DEMI 05GCK01BR309DN50-HCY 68 .3/4 SW 40 304L W16 W16 20-Nov-14
14 C DEMI 05GCK01BR309DN50-HCY 49 .3/4 SW 40 304L W16 W16 20-Nov-14
15 C DEMI 05GCK01BR309DN50-HCY 50 .3/4 SW 40 304L W16 W16 20-Nov-14
16 C DEMI 05GCK01BR309DN50-HCY 51 .3/4 SW 40 304L W16 W16 20-Nov-14
17 C DEMI 05GCK01BR309DN50-HCY 6 .3/4 SW 40 304L W16 W16 20-Nov-14
18 C DEMI 05GCK01BR309DN50-HCY 7 .3/4 SW 40 304L W16 W16 20-Nov-14
19 C DEMI 05GCK01BR309DN50-HCY 8 .3/4 SW 40 304L W16 W16 20-Nov-14
20 C DEMI 05GCK01BR309DN50-HCY 1 .3/4 SW 40 304L W16 W16 20-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC. (T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
FO.E
IM-P
OS-
04-0
2 INFORME ISC Nº :
INSP. VISUAL Nº :
Nº CONTRATO : GUACOLDA U5
(ISC) Nº OBRA : 298
Rev. 0 FECHA : 21/Nov/14
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. OBSENSAYOS
FECHA VTPT RT UT MT A R
1 C DEMI BR309 DN50 HCY 32 2 SW 40 304L W6 W6 21-Nov-14
2 C DEMI BR309 DN50 HCY 33 2 SW 40 304L W6 W6 21-Nov-14
3 C DEMI BR309 DN50 HCY 74 2 SW 40 304L W6 W6 21-Nov-14
4 C DEMI BR309 DN50 HCY 41 2 SW 40 304L W6 W6 21-Nov-14
5 C DEMI BR309 DN50 HCY 40 2 SW 40 304L W6 W6 21-Nov-14
6 C DEMI BR309 DN50 HCY 42 2 SW 40 304L W6 W6 21-Nov-14
7 C DEMI BR309 DN50 HCY 43 2 SW 40 304L W6 W6 21-Nov-14
8 C DEMI BR308 DN25 HCY 11 1 SW 40 304L W6 W6 21-Nov-14
9 C DEMI BR308 DN25 HCY 12 1 SW 40 304L W6 W6 21-Nov-14
10 C DEMI BR308 DN25 HCY 13 1 SW 40 304L W6 W6 21-Nov-14
11 C DEMI BR308 DN25 HCY 14 1 SW 40 304L W6 W6 21-Nov-14
12 C DEMI BR308 DN25 HCY 15 1 SW 40 304L W6 W6 21-Nov-14
13 C DEMI BR308 DN25 HCY 32 1 SW 40 304L W6 W6 21-Nov-14
14 C DEMI BR308 DN25 HCY 34 1 SW 40 304L W6 W6 21-Nov-14
15 C DEMI BR308 DN25 HCY 36 1 SW 40 304L W6 W6 21-Nov-14
16 C DEMI BR308 DN25 HCY 17 1 SW 40 304L W6 W6 21-Nov-14
17 C DEMI BR308 DN25 HCY 21 1 SW 40 304L W6 W6 21-Nov-14
18 C DEMI BR308 DN25 HCY 19 1 SW 40 304L W6 W6 21-Nov-14
DETALLE TIPO DE OBSERVACIONES (ATRIB) Inspector de Calidad / EIMISA Jefe de Gestion Toma de Conocimiento Cliente C = UNIÓN CREADA de Calidad en Obra / EIMISAIF = UNIÓN INTERVENIDA POR FABRIC.
IC = UNIÓN INTERVENIDA POR CLIENTE Nombre : Nombre : Nombre :E = UNIÓN ELIMINADA NO EJECUTADA
EE = UNIÓN ELIMINADA EJECUTADA Firma : Firma : Firma :A = 1a REPARACIÓN
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
UBIC.
(T/C)
N° UNION
N° MODIF.
SOLD. 1
SOLD. 2
RESUL. VT
B = 2a REPARACIÓN Fecha : Fecha : Fecha :
FO.E
IM-P
OS-
04-0
2
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
(ISC)
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. SOLD. 1 SOLD. 2 OBS
FO.E
IM-P
OS-
04-0
2
INFORME DE UNIONES SOLDADURAS DE CAÑERÍAS
(ISC)
ITEM AREA N° ISOMETRICO ATRIB. Ø TIPO SCH. MAT. SOLD. 1 SOLD. 2 OBS
UBIC. (T/C)
N° UNION
N° MODIF.
UBIC. (T/C)
N° UNION
N° MODIF.