INDEX
S. NO. CONTENTS PAGE NO.
1.0 Executive Summary 1
2.0 Introduction of the Project / Background Information 3
(i) Identification of Project & Project Proponent 3
(ii) Brief Description of Nature of the Project 3
(iii) Need for the Project & Its Importance to the Country and or Region 3
(iv) Demand-Supply Gap 3
(v) Import Vs. Indigenous Production 4
(vi) Export Possibility 4
(vii) Domestic / Export Markets 4
(viii) Employment Generation (Direct and Indirect) due to the Project 4
3. Project Description 5
(i) Type of Project including Interlinked and Independent Projects, if any 5
(ii) Location (Map showing General Location, Specific Location, and Project Boundary & Project Site Layout) with
coordinates 6
(iii) Key Plan 7
(iv) Details of Alternative Sites Consideration and Basis of Selecting the Project Site, Particularly the Environmental
Considerations gone into should be highlighted 8
(v) Size or Magnitude of Operation 8
(vi) Project Description with Process Details 8
(vii) Raw Material Required along with Estimated Quantity, Likely Source, Marketing Area of Final Products, Mode
of Transport of Raw Material and Finished Product 17
(viii) Resources Optimization/ Recycling and Reuse Envisaged in the Project, If any, should be briefly outlined 17
(ix) Availability of Water its Source, Energy /Power Requirement and Source should be given 18
(x) Quantity of Waste to be Generated (Liquid and Solid) and Scheme for their Management/ Disposal 18
4. Site Analysis 19
(i) Connectivity 19
(ii) Land Form, Land Use and Land Ownership 19
(iii) Topography 19
(iv)
Existing Land Use Pattern {Agriculture, Non-Agriculture, Forest, Water Bodies (including area under CRZ)},
Shortest Distances from the Periphery of the Project to Periphery of the Forests, National Park, Wild Life
Sanctuary, Eco Sensitive Areas, Water Bodies (Distance from the HFL of the river), CRZ. In Case of Notified
Industrial area, a copy of the Gazette Notification
19
(v) Existing Infrastructure 20
(vi) Climatic Data from Secondary Sources 20
(vii) Social Infrastructure Available 20
5. Planning Brief 21
(i) Planning Concept (Type of Industries, Facilities, and Transportation etc.) Town and Country Planning/
Development Authority Classification 21
(ii) Population Projection 21
(iii) Land Use Planning (Break Up along with Green Belt Etc.) 21
(iv) Assessment of Infrastructure Demand (Physical & Social) 21
ii
S. NO. CONTENTS PAGE NO.
(v) Amenities/ Facilities 21
6.0 Proposed Infrastructure 21
(i) Industrial Area (Processing Area) 21
(ii) Residential Area (Non Processing Area) 22
(iii) Green Belt 22
(iv) Social Infrastructure 22
(v) Connectivity 22
(vi) Drinking Water 22
(vii) Sewerage System 23
(viii) Industrial Waste Management 23
(ix) Solid Waste Management 23
(x) Power Requirement & Source 23
7. Rehabilitation and Resettlement (R & R) Plan 23
(i) Policy to be adopted (Central/ State) in respect of the Project affected persons including Home Oustees, Land
Oustees and Landless Laborers (Brief Outline to be given) 23
8. Project Schedule & Cost Estimates 23
(i) Likely Date of Start of Construction and Likely Date of Completion (Time Schedule for the Project to be given) 23
(ii) Estimated Project Cost 24
9. Analysis of Proposal 24
(i) Financial and Social Benefits with special emphasis on the benefit to the local people including tribal,
population, if any in the area 24
iii
ABBREVIATIONS
APCE’s : Air Pollution Control Equipments
AP : Andhra Pradesh
AQC : After Quenching Chamber
CPP : Captive Power Plant
CPCB : Central Pollution Control Board
CRZ : Central Regulation Zone
CFBC : Circulating Fluidized Bed Combustion
DG : Diesel Generator
ESP : Electrostatic Precipitator
ESE : East of South East
ECL : Emami Cement Limited
EIA : Environmental Impact Assessment
FY : Financial Year
Ha. : Hector
HAG : Hot Air Generator
IS : Indian Standard
ILC : An Incline Calciner
KVA : Kilo-Volt-Ampere
KLD : Kilo Littre Per Day
Kg : Kilogram
MW : Mega Watt
MTPA : Million Tonnes Per Annam
ML : Mining Lease
MoEF & CC : Ministry of Environment, Forest & Climate Change
NW : North West
NE : North East
OPC : Ordinary Portland Cement
PF : Protected Forest
PPC : Portland Pozzolana Cement
PH : Pre-Heater
PSC : Portland Slag Cement
RCC : Reinforced Cement Concrete
RF : Reserved Forest
R&R : Rehabilitation and Resettlement
SW : South West
SE : South East
SH : State Highway
SSW : South of South West
ToR : Terms of Reference
TPA : Tonnes Per Annum
TAD : Tertiary Air Duct
VRM : Vertical Roller Mill
WHRS : West Heat Recovery Boiler
WNW : West of North West
WSW : West of South West
WTP : Water Treatment Plant
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Limited 1
PRE - FEASIBILITY REPORT
1.0 EXECUTIVE SUMMARY
M/s. Emami Cement Ltd. (ECL) is proposing Integrated Cement Project - Clinker (3.2 MTPA),
Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit (100
TPH) & DG Sets (2325 KVA) near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra
Pradesh).
Salient Features of the project are given in Table - 1.
Table - 1Salient Features of the Project
S. NO. PARTICULARS DETAILS
A. Nature & Size of the Project Units Proposed Capacity
Clinker 3.2 MTPA
Cement 4.25 MTPA
Captive Power Plant 30 MW
WHRS 15 MW
Synthetic Gypsum Unit 100 TPH
DG Sets 2325 KVA
B. Category of the Project As per EIA Notification dated 14th Sept., 2006 as amended fromtime to time, this project falls under S. No. 3 (Material Production),Project Activity ‘3 (b)’ Cement Plants.
C. Location Details
Villages Tangeda
Tehsil Dachepalli
District Guntur
State Andhra Pradesh
Latitude 16° 38' 7.09" N to 16° 39' 59.96 "N
Longitude 79° 48' 0.31" E to 79° 48' 52.60" E
Toposheet No. 56 P/10 & 56 P/14
Location Map has been shown in Figure - 1.
D. Area Details
Total Project Area 254.34 ha
Greenbelt Area / Plantation Area (ha) ~84 ha (i.e. 33% of the total project area) will be covered undergreenbelt / plantation.
E. Environmental Setting Details (with approximate aerial distance & direction from proposed project site)
1. Nearest Town / City Dachepalli (8.5 km in SW direction)
2. Nearest National Highway / StateHighway
SH - 2 (7.5 km in SSW direction)
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Limited 2
S. NO. PARTICULARS DETAILS
3. Nearest Railway station Nadikudi (9.5 km in SW direction)
4. Nearest Airport Vijayawada (106 km in ESE direction)
5. National Parks, Wildlife Sanctuaries,Biosphere Reserves, Tiger/ ElephantReserves within 10 km radius.
No National Park, Wildlife Sanctuary, Biosphere Reserve, Tiger/Elephant Reserve falls within 10 km radius of the proposed projectsite.
6. Reserved Forests (RF) / ProtectedForests (PF) within 10 km radius
o Tangeda RF (~2.0 km in NE direction)
o Regulagadda RF (~4.5 km in ENE direction)
o Vemavaram RF (~5.0 km in SE direction)
o Madinapadu RF (~5.0 km in West direction)
o Sultanpur RF (~6.5 km in North direction)
o Madinapadu Extension RF (~7.0 km in West direction)
o Govindpuram RF (~7.5 km in ESE direction)
o Reserved Forest (~7.5 km in NE direction)
o Pittalsarikota RF (~8.0 km in ENE direction)
o Gurrambodu RF (~8.5 km in North direction)
o Dranam RF (~9.0 km in East direction)
o Gamalapadu RF (~9.0 km in WNW direction)
o Vajralgani RF (~9.0 km in NNW direction)
o Ravipahad RF (~9.5 in NW direction)
7. Water Bodies (within 10 km radius) o Berimeda Vagu (~0.02 km in East direction)
o Nendra Vagu (~0.5 Km in NW direction)
o Tangeda Major Canal (~2.5 km in SSW direction)
o Krishna River (~3.0 km in North direction)
o Vemuleru River (~8.0 km in NNW direction)
o Naguleru Vagu (~8.0 km in WSW direction)
8. Seismic Zone Zone - II [as per IS 1893 (Part-I): 2002]
9. Archaeological site None within 10 km radius study area
F. Cost Details
1. Total Cost of the Project Rs. 1950 Crores
2. Cost for Environment Management Plan Capital Cost - Rs. 97.5 Crores
Recurring Cost - Rs. 4.8 Crores / annum
G. Basic Requirements for the project
Water Requirement 3500 KLD
Source: Ground Water & Krishna River
Power Requirement 45 MW
Source: Proposed Captive Power Plant, WHRS, DG Sets & State Grid(in case of Emergency)
Man Power Requirement During Implementation phase - 1050 Persons
During Operation phase - 538 persons
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Limited 3
2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
(i) Identification of Project and Project Proponent
Emami Group was founded by Mr. R. S. Agarwal and Mr. R. S. Goenka. It is 4th Largest listed Indian
FMCG company. Emami Cement Limited (ECL) is an incorporated Company under Company’s Act
1956 and is a unit of Emami Group. The company’s Head quarter is in Kolkata, it has a Pan-India
presence and footprints in various countries across the world.
Emami group is a well-diversified, professionally managed group of company in Eastern India,
having interest in FMCG, news print, writing instruments, Health care and Hospitals, Retail
pharmacies, Departmental stores, Bio diesel, Edible Oil, Real estate, construction and planning for
diversifying in manufacturing of Cement.
ECL is proposing an Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive
Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit (100 TPH) & DG Sets (2325 KVA)
near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh).
(ii) Brief description of nature of the project
M/s. Emami Cement Ltd. (ECL) is proposing Integrated Cement Project - Clinker (3.2 MTPA),
Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit (100
TPH) & DG Sets (2325 KVA) near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra
Pradesh).
As per EIA Notification dated 14th Sept., 2006 as amended from time to time, this project falls
under S. No. 3 (Material Production), Project Activity ‘3 (b)’ Cement Plants.
(iii) Need for the project and its importance to the country and or region
Cement is an essential ingredient for the modern building construction. The new generation
cement plant in India now employs the latest technology for better efficiency, energy
conservation and economics of large capacity production. The improved market conditions
witnessed recently, after a grip of recession over a long period, are expected to continue due to
high priority being given by the Government to housing and infrastructure and also in view of the
massive investment proposed in industry and rural sectors. Therefore, there is an urgent need to
increase the cement production capacity in the country in spite of severe resource constraints.
(iv) Demand- Supply Gap
Cement demand in India is expected to increase due to government’s push for large infrastructure
projects, leading to 45 million tonnes of cement needed in the next three to four years. In the
view of large limestone deposits in Guntur district, manufacture of cement utilizing these deposits
will be a profitable venture for Emami Cement Limited. The cement demand and supply is
estimated based on the following assumptions:
The cement market has growth due to Central government liberization policies and
development of housing, road and infrastructure projects.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Limited 4
A cement deficit situation is envisaged in the coming years but the situation may change
depending upon the infrastructure growth in the coming years.
Cement plant utilisation trend in southern states is expected to pick up in the current fiscal as
compared with the previous year, and overall demand in the region should go up by 5 -7 % in FY
2014 - 15, as against 1 % year-on-year growth a year ago. This along with limited capacity expansion
in south should boost plant utilisation in the region.
Among southern states, Andhra Pradesh market demand is 21 million tonnes per annum and it is
expected to grow at 10 - 12 % this fiscal, as against 6 % in the previous financial year.
The demand in Tamil Nadu is 20 million tonnes per annum and is expected to grow at 4-5 per cent
in FY 2014 - 15, as compared to 4 % decline in the previous year.
Karnataka's demand stands at 16 million tonnes per annum and is likely to increase by 3-5 % in FY
2014 - 15. The cement demand in Kerala is 10 million tonnes per annum and expected to grow at 8-
10 % in the current financial year, as compared with 5 % growth a year ago.
The expert highlighted that demand recovery in the southern region initially will be from
infrastructure projects as political stability has set in the Andhra Pradesh region.
Both pending and new infrastructure projects in AP (combined) should boost double digit demand
growth in the state. Post the bifurcation of the AP, Vizag, Vijayawada and Tirupati would emerge
as key cities.
(v) Import vs. Indigenous Production
The proposed project will utilize locally available raw material. However, some imports will be
required for Coal / Petcoke.
(vi) Export Possibility
No export feasibility.
(vi) Domestic / Export Markets
The proposed cement production will cater to the cement demands in southern states like Andhra
Pradesh, Telangana, Tamil Nadu, Karnataka, Kerala etc.
(vii) Employment Generation (Direct and Indirect) due to the project
Direct and indirect employment will be generated due to the proposed project. The total
manpower requirement during implementation phase will be around 1050 persons and during
operation phase will be around 538 persons. Unskilled / semi - skilled manpower can be sourced
from the local area and skilled manpower will be sourced from outside/ local.
Particulars Nos.Skilled 133
Semi - Skilled 105
Unskilled 300
Total 538
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Limited 5
3.0 PROJECT DESCRIPTION
(i) Type of Project including interlinked and independent projects, if any.
M/s. Emami Cement Ltd. is proposing Integrated Cement Project - Clinker (3.2 MTPA), Cement
(4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit (100 TPH) &
DG Sets (2325 KVA) near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh).
Interlinked Projects:
Proposed Tangeda Limestone Mine (Applied ML Area: 521.691 ha) with limestone production
capacity of 4.5 MTPA at Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh).
Application for the same has been submitted to MoEFCC, New Delhi for obtaining Environmental
Clearance on 09th April 2014. ToR letter for the same has been issued vide MoEFCC letter no J-
11015/139/2014-IA.II (M) dated 12th August, 2014. Final EIA / EMP Report, after conduction of Public
Hearing, has been uploaded on 27th Aug., 2016 on MoEFCC portal.
Independent Projects: There is no independent project.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Limited 6
(ii) Location (map showing general location, specific location, and project boundary & project site
layout) with coordinates
Figure - 1: Location Map
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit (100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Limited. 7
(iii) Key Plan
Figure - 2: Key Plan
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 8
(iv) Details of alternative sites consideration and basis of selecting the proposed site, particularly the
environmental considerations gone into should be highlighted.
Proposed project site has been considered near to the Captive Limestone Mine Site, for which LOI
has been granted by Industries & Commerce (M-IV) Department, Govt. of Andhra Pradesh vide
letter no. 15011/M.IV(2)/2013-1 dated 03rd December, 2013.
In addition to above, following are the criteria, considered for locating an Integrated Cement
Project:
Proximity to source of water
Availability of adequate & reliable power supply
Availability of sufficient land
Availability of transport facility
No National Park, Wildlife Sanctuary, Biosphere Reserve falls within 10 km radius of the
proposed site.
Vicinity to the social infrastructural facilities, market centre, educational institutions, local
transport, medical facilities and township etc.
From the above considerations, the proposed site falling near the Village Tangeda of Tehsil
Dachepalli, District Guntur (Andhra Pradesh) has been found suitable for setting up the proposed
Cement plant subject to environmental clearance.
(v) Size or magnitude of operation
M/s. Emami Cement Ltd. (ECL) is proposing Integrated Cement Project - Clinker (3.2 MTPA),
Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit (100
TPH) & DG Sets (2325 KVA) near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra
Pradesh).
As per EIA Notification dated 14th Sept., 2006 as amended from time to time, this project falls
under S. No. 3 (Material Production), Project Activity ‘3 (b)’ Cement Plants.
(vi) Project Description with Process Details
Project Description
Units Proposed Capacity
Clinker (MTPA) 3.2
Cement (MTPA) 4.25
CPP (MW) 30
WHRS (MW) 15
Synthetic Gypsum Unit (TPH) 100
DG Sets (KVA) 2325
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 9
Process Description
A. Cement Manufacturing
The cement manufacturing process largely comprises of the following steps:
Transport of crushed limestone from Captive Limestone mine
Grinding of raw material
Raw Mix Preparation & Homogenization
Preheating and Calcination
Clinker cooling
Clinker storage and transport
Fly ash unloading and storage
Cement Production
Cement Packing and dispatch.
The type of cement manufactured will be PPC, OPC & PSC.
Product Mix for PPC
S. No. Component Proportion, % by weight1. Clinker 652. Fly ash 303. Gypsum (Mineral and Synthetic) 5
Product Mix for OPC
S. No. Component Proportion, % by weight1. Clinker 952. Gypsum (Mineral and Synthetic) 5
Product Mix for PSC
S. No. Component Proportion, % by weight1. Clinker 35-452. Slag 50 - 603. Gypsum (Mineral and Synthetic) 5
The detailed cement manufacturing process has been described below:
(a) Transport of excavated limestone from Captive mine site
Limestone will be transported from captive mines to the plant by covered conveyor belt.
(b) Grinding of raw material
Crusher of capacity 1500 TPH will be located within the mining area. A common crusher of capacity
100 TPH is envisaged for correctives and additives i.e. Iron Ore, Bauxite and Gypsum within the
plant.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 10
Raw Material Reclaiming and Transport
Two nos. Chevron type, longitudinal stockpiles have been proposed for storages and
homogenization of the crushed limestone. The limestone received from crushing plant is fed to a
1000 Tonne surge hopper by way of belt conveyer system and will be stacked with the help of a
stacker of capacity 1500 TPH. For extraction, a bridge type reclaimer of capacity 800 TPH has been
considered.
While stacking of raw materials will be done in one pile, material reclaiming will be done from the
other. Reclaimed material will be transported to the raw material hoper in the raw mill
department through a series of belt conveyors.
Dry process of cement manufacturing offers more advantages, particularly in fuel consumption
and is the most rational and logical choice. The proposed plant will adopt dry process to
manufacture Portland Pozzolana Cement (PPC), Portland Slag Cement (PSC) & Ordinary Portland
Cement (OPC) using rotary kiln, pre-heater and pre-calciner.
(c) Raw Mix Preparation & Homogenization
Raw material drying and grinding
The installation of a VRM of capacity 750 TPH has been considered for drying and grinding of the
raw materials.
Raw meal blending and kiln feed
Blending will be performed to minimize the variations in raw meal chemistry. For homogenization
of the raw meal, a continuous, controlled flow type-blending silo with a minimum-blending ratio of
7 is recommended. The proposed capacity of the raw meal silo will be 25,000 tonnes. Provision
will be made for the recirculation of material from silo discharge to silo feeding.
A kiln feed system, comprising of a steel bin will be installed beneath the blending silo. The system
will use gravimetric feed control by solid flow meters. A system having Bucket elevators and air
slides has been considered for feeding the material to PH.
(d) Pyro-processing & Clinkerisation
A dry- process kiln installation has been envisaged. With higher number of cyclones stages in the
PH, the specific heat consumption and the PH exit gas temperature would be lower. On the other
hand, the total pressure drops across the PH and hence, the specific power consumption of the
PH fan increases with the increasing number of PH stages. A double string 6 stage PH consisting of
high efficiency and low-pressure drop cyclones has been recommended. An Incline Calciner (ILC) is
envisaged to be installed. The kiln feed material from storage silo will be introduced into the PH by
means of a system having bucket elevator and air slides. The material will be preheated in the PH
before entering the PC. Fuel firing in the PC will be controlled to achieve about 90-95% calcinations
of the material at its discharge. A separate tertiary air duct (TAD) will be installed to transport the
preheated air from the clinker cooler to PC.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 11
For the PH strings, high efficiency, suitably designed variable speed drive PH fans will be installed
for handling the gases.
The pre-heater fans (ID fan) will be designed suiting the arrangement required for waste heat
recovery system (WHRS).
Kiln burner
A modern multi channel, multi fuel type burner with low primary air consumption will be installed
for fuel firing in the kiln; kiln burner will be suitable for using multiple fuels.
(e) Clinker cooling, transport & storage
Clinker Cooler
A new generation, high heat recuperation efficiency (minimum 75%), modular type pit-less clinker
cooler will be provided. The clinker cooler will be equipped with an intermediate clinker roll
crusher to maximise the heat recuperation through WHR. The clinker cooler shall be designed for
clinker outlet temperature of max 65°C above ambient. The clinker cooler waste gas can be de-
dusted through ESP. Cleaned gas from clinker cooler shall be vented through stack. On-line dust
monitoring equipment will be provided at the cooler stack. Dust from cooler ESP will be
transported to the clinker pan conveyor to clinker silo.
Clinker transport & storage
Clinker transport from cooler to clinker silo has been considered to be with the help of pan
conveyor. Pan conveyor will be sized with a nominal capacity of 500 TPH. Clinker storage is
envisaged in an RCC silo of capacity, 1,00,000 tonne live capacity equivalent to about 7 days
storage. Clinker will be extracted from the bottom of the clinker silos through a set of Deep Pan
Conveyors and unloaded on to two set of belt conveyors. One common belt conveyor for clinker
transport up to hopper building in the cement grinding section.
(f) Fly ash unloading & Storage
Fly ash will be transported to the plant from its source by bulk carriers and pumped into a RCC silo.
From the silo, fly ash will be transported to the cement mill through a set of air slides and bucket
elevator and controlled by a solid flow meter dozing value combination.
(g) Cement Production
Cement Grinding
The installation of two 2 VRM of 335 TPH of capacity will be preferred.
Cement Storage
Cement from the cement grinding section will be transported to the storage silo by a system of air
slides and bucket elevator / belt conveyor 6 x 10,000 tonnes for PPC, OPC & PSC cement storage
silos of RCC construction have been considered for the project. From the silos, cement will be
transported to the packer with the help of a set of air slides and bucket elevators.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 12
(h) Cement Packing and Dispatch
3 x 240 TPH, 16 spouts, double discharge packing machines and 1 x 90 TPH 6 spouts, single
discharge packing machines have been considered. 11 no’s semi automatic truck loaders for
loading of bags to road trucks have been considered. The rotary packer outlet up to loading of the
packed bags, suitable system with flat transport belts and diverters has been considered.
Cement manufacturing process is shown in Figure - 3.
Figure - 3: Cement Manufacturing Process
Technical Concept
o Emphasis
State of The Art Technology
Energy efficient clinkerisation system
Environment friendly plant concept.
Manufacturing Process: Calcination by state of the art 6 stage Pre heater with Pre-
calciner, Rotary Kiln Grate Cooler & High Efficiency Bag House.
Gypsum
Cement Mill
Limestone
Laterite, otheradditives and
correctivematerials
Raw MillGrindingto Fine
Powder
Raw MealStorage
HeaterPre
Pre
Calciner Kiln
ClinkerFine Coalstorage
Coal MillCoal
CementStorage
Silo
Clinker to GrindingUnit
Dispatch (Bags & Bulk)and Transport (Road &
Rail)
Fly ash
Alternate Fuels
AlternateFuels
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 13
o Main Equipment
Stacker
Reclaimer
Raw Mill (VRM)
HAG (Hot Air Generator)
Pyro-processing
Coal Crusher
Coal Mill
Cement Mill
Packers
Synthetic Gypsum Unit
o Storages
Pre-blending stockpile
Corrective storage
Blending Silo
Clinker Silo
Coal stock pile
Gypsum (Mineral & Synthetic)
Slag
Bauxite
Pet Coke
o Process Control
Distributed control system comprising of microprocessor based controls and field
instrumentation. Plant operation shall be controlled from central control room.
B. Captive Power Plant
M/s. Emami Cement Limited is intending to install a Coal / Petcoke based thermal power plant
having capacity of 30 MW within the plant premises.
The generating unit will consist of Circulating Fluidized Bed Combustion (CFBC) boiler using coal/
pet coke as primary fuel, one condensing steam turbine and generator, one air cooled condenser
and other necessary auxiliary equipment including balance of plant equipment.
The generating station will be designed to operate with high efficiency and availability at various
modes throughout the lifetime of the project considering the nature of cement plant loading.
There are various sections of the power plant described as below:
1) Fuel Storage and Handling
This section will include all the necessary equipments like coal crusher, conveyor and drives. Coal
from the source will be crushed into required size and taken to the fuel bunkers feed hopper of
the boiler. Coal yard will have separate arrangements for incoming coal and crushed coal to be
sent to the bunker.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 14
2) Boiler and other Auxiliary equipments
The boiler house will have the main boiler as mentioned above along with ID and FD fans, ducts,
Pollution control equipment (ESP/ Bag House), and other necessary valves, piping and fittings.
Fuel from the conveyor will be put into the main bunker from where it will be fed to the boiler
furnace.
3) Water Treatment Plant:
In order to have smooth operation and long life of the boiler system, it requires suitable water
treatment plant. Depending upon the test results of the water sample, appropriate treatment
methods and equipment will be decided upon.
4) Turbine and Control Room:
Turbine and control room will be housed in the separate building other than boiler house. This will
also house other turbine auxiliary equipment, cable cellar, switchgear room, central control room
and other administrative facilities. The steam from the boiler will be expanded and condensed in
the turbine to generate electricity.
5) Condenser / De-aerator Tank:
At the exit of the turbine, the low-pressure steam will be condensed in air cool condenser and
condensed water will be fed to de-aerator through condensate circuit.
6) Fly ash disposal:
After combustion of coal/ pet coke inside the boiler furnace, it liberates heat that is used for steam
generation. At the same time it generates ash that is a by-product of combustion process. This ash
travels along with flue gases through various parts of the system like Economiser, Air Preheater
and pollution control equipment and finally through ducts. There is also some collection at the
bottom of the furnace. In the end, flue gases are fed into the chimney/stack through ID fan and
vented out in the atmosphere. Ash will be collected at different points and moved by using
suitable material handling systems and collected into the silos (dry fly ash).
All the equipment including valves, pumps, standby pumps & valves etc. will be operated,
monitored and controlled from central control room. In this way, generated power and fly ash will
be sent to the cement plant for their respective usages.
The project will include the complete civil construction of the buildings, reservoirs, pump house,
MCC room, WTP plant area building, cooling tower including ash silos, covered fuel shed, site
infrastructure, supply and installation of all mechanical equipment, piping, instrumentation,
power evacuation system and other necessary equipment for the completion and satisfactory
operation of the generating unit.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 15
Figure - 4: Process Flow Chart of Captive Power Plant
C. Waste Heat Recovery System
ECL is proposing installation of Waste Heat Recovery System (WHRS) of 15 MW for re-utilization of
the exhaust gases from the Pre-heater/ Cooler to generate electric power and consequently
reduce consumption of grid power through fossil fuel. The project will contribute to the more
efficient use of energy and will reduce reliance on exhaustible fossil fuel.
The PH boiler will be a vertical configuration single drum boiler. AQC boiler will be vertical single
drum boiler. Both the boilers are top supported, outdoor Unit suitable for the specified Pre-heater
and clinker Cooler exhaust of cement plant.
The Waste Heat coming out of Pre-heater and cooler from present kilns and proposed kiln will be
used in Waste Heat Recovery Boiler to produce low pressure steam which is fed to turbine to
produce power of 15 MW. One number waste heat recovery boiler of 15 MW capacity in existing
line I and new line II will be installed. WHR boiler will be based on steam rankine cycle and
envisaging recovery of heat from exhaust gases at two points viz. pre-heater and clinker cooler
(tapping at exhaust or mid-cooler). Steam generated in the boiler will be used in the turbine to
generate electricity in the generator.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 16
FLOW CHART OF THE WHRS
D. DG Sets
ECL is proposing installation of DG sets of 2325 KVA for use in case of shutdown of Captive Power
Plant and in case of emergency.
Storage of Raw Material
S. No. Raw Material / Finished product Type of Storage Storage Capacity (Tonnes)
1. Limestone Covered Stockpile 1,50,000
2. Raw Meal Silo 25,000
3. Clinker Silo 1,00,000
4. Fly Ash Silo 10000
5. Slag Covered Stockpile 15,000
6. Mineral Gypsum Covered Stockpile 15,000
7. Synthetic Gypsum Covered Stockpile 15,000
8. Cement Silo 6 x 10,000 (OPC, PSC, PPC)
9. Bauxite Covered shed 10,000
10. Iron Ore Covered shed 10,000
11. Coal Covered Stockpile 60,000
12. Pet Coke Covered Stockpile 60,000
Details of Pollution Control Equipment
S. No. Locations Proposed
1. Crusher Bag Filter
2. Raw Mill + Kiln Bag House
3. Coal Mill Bag Filter
4. Clinker Cooler ESP
5. Cement Mill Bag Filter
6. Various Transfer Points Bag Filters
7. Captive Power Plant ESP
PreHeate
r
ClinkerCooler
Boiler
Boiler
SteamTurbine
Generator
ESP
Hotgas Steam
To Stack
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 17
(vii) Raw material required along with estimated quantity, likely source, marketing area of final
products, mode of transport of raw material and finished product.
(a) Raw Material Requirement
S. No. Name of Raw Material Quantity (MTPA) Source Mode of Transportation
1. Limestone 4.8 Captive Mine / OutsourceCovered Conveyor Belt /
Road / Rail
2. Bauxite 0.09East Godavari & Vishakhapatnam
(AP) / Local MarketRoad / Rail
3. Iron Ore 0.09Cuddaph District (AP) / Local
MarketRoad / Rail
4.Gypsum (Mineral /Synthetic)
0.22Captive Synthetic Gypsum Unit /
Near-by Fertilizer Plants at Vizag /Vishakhapatnam
Road / Rail
5. Fly ash 0.7CPP / Thermal Power Plants at
Korba / Near-by Power Plants ofAndhra Pradesh
Road
6. Slag 0.32Vishakhapatnam and Steel plantsin southern part of country / Local
MarketRoad / Rail
(b) Fuel Requirement
Fuel Quantity (MTPA) Source Mode of Transportation
Coal (Indigenous /Imported) / Petcoke
0.488
Coal Indian - Preferably SECL / OpenmarketImported Coal - Indonesia, South Africa,Australia etc.Petcoke - Indian / Oversees Suppliers
Rail / Road / Waterway
(c) Marketing Area and Mode of transportation of Final Product
Marketing area will be in major states of South India like Andhra Pradesh, Telangana, Tamil Nadu,
Karnataka, Kerala etc.
Mode of transportation of Final Product
Cement will be transported by Rail / Road / Waterway.
(viii) Resources optimization/ recycling and reuse envisaged in the project, if any, should be briefly
outlined.
Dust collected from air pollution control equipment like ESP, Bag house / Bag filters will be
totally recycled into the process.
Fly ash generated from CPP will be utilized in manufacturing of PPC grade cement.
Sludge generated from STP will be used as manure in greenbelt development/ plantation.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 18
In cement plant, water used for cooling at various stages will be totally absorbed in the
process or will be subjected to evaporation & recycling and hence, no waste water will be
discharged from the cement plant.
Waste water generated from CPP will be recycled into the process and used for dust
suppression after proper neutralization.
The domestic wastewater generated from plant & colony will be treated in STP and the
treated water will be utilized for greenbelt development / plantation within ECL premises.
(ix) Availability of water it’s source, energy /power requirement and source should be given.
(a) Water Requirement and Source
The total water requirement for the proposed project will be 3500 KLD which will be sourced from
the Ground Water & Krishna River. Break-up of water requirement is given in table below:
Table - 2
Water Requirement Break-Up
Purpose Requirement (KLD) Source
Cement Plant 2000
Ground Water & KrishnaRiver
Captive Power Plant 500
WHRS 200
Green Belt Development/ Plantation 300
Drinking, Sanitation & Colony 500
TOTAL 3500
(b) Power Requirement and Source
Total power requirement for the proposed project will be 45 MW.
Source: Proposed CPP, WHRS, State Grid & DG Sets (in case of emergency).
(x) Quantity of waste to be generated (liquid and solid) and scheme for their management/disposal
In cement plant, water used for cooling at various stages will be totally absorbed in the
process or will be subjected to evaporation & recycling and hence, no waste water will be
discharged from the cement plant.
Waste water generated from CPP will be recycled into the process and used for dust
suppression after proper neutralization.
The domestic wastewater generated from plant & colony will be treated in STP and the
treated water will be utilized for greenbelt development / plantation within ECL premises.
No solid waste will be generated from the cement manufacturing process.
Dust collected from air pollution control equipment like ESP, Bag house / Bag filters will be
totally recycled into the process.
Fly ash generated from CPP will be utilized in manufacturing of PPC grade cement.
Sludge generated from STP will be used as manure in greenbelt development/ plantation.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 19
4.0 SITE ANALYSIS
(i) Connectivity
The project site is well connected to SH - 2 (~7.5 km in SSW direction). Nearest town to the
proposed project site is Dachepalli (~8.5 km in SW direction). Nearest Railway Station is Nadikudi
Railway Station, which is approx. 9.5 km in SW direction from the proposed project site and
nearest Airport is Vijayawada (~ 106 km in ESE direction) from the proposed project site.
All communication facilities such as telephone, telefax, STD, ISD & internet are available in the
vicinity of the project site.
(ii) Land from Land use and Land ownership
Total land requirement for the proposed project will be 254.34 ha; out of which, 34.16 ha is Govt.
waste land and remaining 220.18 ha is Private dry land.
(iii) Topography
The Topography of the core zone is flat with minor undulations having some trees & bushes.
(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area
under CRZ)), shortest distances from the periphery of the project to periphery of the forests,
national park, wild life sanctuary, eco sensitive areas, water bodies (distance from the HFL of the
river), CRZ. In case of notified industrial area, a copy of the Gazette notification should be given
Table - 3
Environmental Settings of the Area
S. NO. PARTICULARSDETAILS
(with approximate aerial distance & direction from proposed project site)
1. Nearest Town / City Dachepalli (8.5 km in SW direction)
2. Nearest National Highway / StateHighway
SH - 2 (7.5 km in SSW direction)
3. Nearest Railway station Nadikudi (9.5 km in SW direction)
4. Nearest Airport Vijayawada (106 km in ESE direction)
5. National Parks, Wildlife Sanctuaries,Biosphere Reserves, Tiger/ ElephantReserves within 10 km radius.
No National Park, Wildlife Sanctuary, Biosphere Reserve, Tiger/Elephant Reserve falls within 10 km radius of the proposed projectsite.
6. Reserved Forests (RF) / ProtectedForests (PF) within 10 km radius
o Tangeda RF (~2.0 km in NE direction)
o Regulagadda RF (~4.5 km in ENE direction)
o Vemavaram RF (~5.0 km in SE direction)
o Madinapadu RF (~5.0 km in West direction)
o Sultanpur RF (~6.5 km in North direction)
o Madinapadu Extension RF (~7.0 km in West direction)
o Govindpuram RF (~7.5 km in ESE direction)
o Reserved Forest (~7.5 km in NE direction)
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 20
S. NO. PARTICULARSDETAILS
(with approximate aerial distance & direction from proposed project site)
o Pittalsarikota RF (~8.0 km in ENE direction)
o Gurrambodu RF (~8.5 km in North direction)
o Dranam RF (~9.0 km in East direction)
o Gamalapadu RF (~9.0 km in WNW direction)
o Vajralgani RF (~9.0 km in NNW direction)
o Ravipahad RF (~9.5 in NW direction)
7. Water Bodies (within 10 km radius) o Berimeda Vagu (~0.02 km in East direction)
o Nendra Vagu (~0.5 Km in NW direction)
o Tangeda Major Canal (~2.5 km in SSW direction)
o Krishna River (~3.0 km in North direction)
o Vemuleru River (~8.0 km in NNW direction)
o Naguleru Vagu (~8.0 km in WSW direction)
8. Seismic Zone Zone - II [as per IS 1893 (Part-I): 2002]
9. Archaeological site None within 10 km radius study area
10. Soil Type Black Cotton Soils, Red Loamy Soils and Sandy Loam
(v) Existing Infrastructure
There is no existing infrastructure within the proposed project site, as it is a Greenfield project.
(vi) Climatic data from secondary sources
Climate in Guntur is tropical (Aw). The average temperature is warm to hot year round. The
summer season (especially during May/June) has the highest temperatures, but these are usually
followed by summer monsoon rains. The winter season (from October to February) is the most
enjoyable with a pleasant climate. Winter months may feature more rainfall than summer but
there are dry spells during the winter season. The wettest month is July. The average annual
temperature is 28.5 C and annual rain fall is about 905 mm.
Rain storms and hurricanes are common in the region during the rainy season, which starts with
the monsoons in early June. Hurricanes may occur any time of the year, but occur more
commonly between May and November.
(vii) Social Infrastructure available
All basic amenities such as school, hospital, market etc. are available in the nearby towns.
Adequate infrastructural facilities will be developed by ECL at their proposed cement plant
premises which include residential colony for staff and workers having facilities like dispensary /
hospital, shopping complex, community centre, guesthouse, school, temple, club etc.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 21
5.0 PLANNING BRIEF
(i) Planning Concept (type of industries, facilities, transportation etc.) Town and country Planning/
Development authority classification.
Proposed industry is Cement industry (Red Category). Transportation of raw material and final
product will be done via existing Road network / Rail / Water ways and cement concrete road will
be developed within the proposed project area.
(ii) Population Projection
Temporary influx of people will be there as the managerial and supervisory staff will generally be
outsider.
(iii) Land use planning (breakup along with green belt etc.)
Total area requirement for the proposed project will be 254.34 ha; out of which, 34.16 ha is Govt.
waste land and remaining 220.18 ha is Private dry land. Approx. 84 ha (i.e. 33% of the total project
area) will be developed under greenbelt / plantation.
(iv) Assessment of infrastructure demand (Physical & Social)
M/s. Emami Cement Ltd. has assessed the demand of infrastructure (Physical & Social) in nearby
area of the plant site and development activities are being undertaken under corporate social
responsibilities program for rural development initiatives for the upliftment of the nearby
communities from time to time.
(v) Amenities/Facilities
M/s. Emami Cement Ltd. will develop the amenities/ facilities in nearby area of the proposed
project site as per requirement of local people of the nearby area under Corporate Social
Responsibilities program.
6.0 PROPOSED INFRASTRUCTURE
(i) Industrial Area (Processing Area)
Following infrastructure will be provided as following:
Workshop
Adequately equipped workshops have been envisaged for all disciplines i.e. mechanical,
electrical, electronic computer maintenance etc. at proposed cement plant.
Warehouse and Spare Parts Store
A store building will be constructed as warehouse or spare parts store. Fenced open-air
yard with sheds will be built for storing heavy machinery parts.
Elevators, Cranes, Hoists and Maintenance Tools
Elevators, maintenance cranes/ hoists and all required specially designed maintenance tools
for equipment and plant will be provided.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 22
Technical & Administrative office
A suitable technical office & administrative office will be constructed for the project
activities and operation phase.
Time and Security office
At the entrance of the main plant, a time office and a security office will be constructed.
Dispensary / Hospital
A dispensary with first aid facilities will be provided in the plant premises.
Weighbridge
Two Electronic weighbridges will be provided to take care of the incoming and outgoing
materials at the plant.
Bags go down
Space will be provided in the packing plant area for the storage of bags.
Parking
Adequate parking space will be provided in the plant premises for the parking of vehicles.
(ii) Residential area (Non Processing area)
A residential colony to accommodate management staff has been proposed with all latest
recreational & communication facilities for plant employees.
(iii) Green Belt
Total project area will be 254.34 ha; out of which, ~84 ha (i.e. 33% of the total project area) will
be developed under greenbelt / plantation.
(iv) Social Infrastructure
Proposed project will result in growth of the surrounding areas by increased direct and indirect
employment opportunities in the region including ancillary development and supporting
infrastructure.
(v) Connectivity
The project site is well connected to SH - 2 (~7.5 km in SSW direction). Nearest town to the
proposed project site is Dachepalli (~8.5 km in SW direction). Nearest Railway Station is
Nadikudi Railway Station, which is approx. 9.5 km in SW direction from the proposed project
site and nearest Airport is Vijayawada (~ 106 km in ESE direction) from the proposed project
site.
(vi) Drinking Water
500 KLD of water will be required for drinking & domestic purpose in the proposed project for
both colony and plant which will be sourced from Ground Water & Krishna River.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 23
(vii) Sewage Treatment System
Domestic effluent generated from plant office, canteen and colony will be treated in STP and
treated water will be used for greenbelt development/ plantation. The sludge will be used as
manure in greenbelt development/ plantation.
(viii) Industrial Waste Management
No waste water will be generated from cement manufacturing process, as it is based on dry
process technology.
In cement plant, water used for cooling at various stages will be totally absorbed in the
process or will be subjected to evaporation & recycling and hence, no waste water will be
discharged from the cement plant.
Waste water generated from CPP will be recycled into the process and used for dust
suppression after proper neutralization.
The domestic wastewater generated from plant & colony will be treated in STP and the
treated water will be utilized for greenbelt development / plantation within ECL premises.
(ix) Solid Waste Management
No solid waste will be generated from the cement manufacturing process.
Dust collected from air pollution control equipment like ESP, Bag house / Bag filters will be
totally recycled into the process.
Fly ash generated from CPP will be utilized in manufacturing of PPC grade cement.
Sludge generated from STP will be used as manure in greenbelt development/ plantation.
Used oil & grease will be generated from plant machinery/ Gear boxes as hazardous waste
will be sold out to the CPCB authorized recycler.
(x) Power requirement and source
Total power requirement for the proposed project will be 45 MW.
Source: Proposed CPP, WHRS, State Grid & DG Sets (in case of emergency).
7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN
(i) Policy to be adopted (Central/State) in respect of the project affected persons including home
oustees, land oustees and landless labourers (a brief outline to be given).
Company will purchase land directly from the land holders; if needed, then, R&R policy of AP State
and Central Government will be followed.
8.0 PROJECT SCHEDULE AND COST ESTIMATES
(i) Likely date of start of construction and likely date of completion (time schedule for the project
to be given).
The project will start only after obtaining Environmental Clearance and other statutory
permissions from concerned authorities.
Proposed Integrated Cement Project - Clinker (3.2 MTPA), Cement (4.25 MTPA), Captive Power Plant (30 MW), WHRS (15 MW), Synthetic Gypsum Unit(100 TPH) & DG Sets (2325 KVA)Near Village: Tangeda, Tehsil: Dachepalli, District: Guntur (Andhra Pradesh)
Pre - feasibility Report
M/s. Emami Cement Ltd. 24
(ii) Estimated project cost along with analysis in term of economic viability of the project.
Total cost of the Project: Rs. 1950 Crores.
Cost for Environment Protection Measures:
Capital Cost: Rs. 97.5 Crores
Recurring Cost/annum: Rs. 4.8 Crores.
9.0 ANALYSIS OF PROPOSAL (final recommendations)
(i) Financial and social benefits with special emphasis on the benefit to the local people including
tribal population, if any, in the area.
Proposed project will result in growth of the surrounding areas by increasing direct and indirect
employment opportunities in the region including ancillary development and supporting
infrastructure. Special emphasis on Financial and social benefits will be given to the local people
including tribal population, if any, in the area.
Development of social amenities will be in the form of medical facilities, education to
underprivileged and creation of self-help groups.
Andhra Pradesh state will get revenues in terms of taxes and local people will get direct & indirect
employment. Business opportunities for local community will be available like transport of cement
to market, fly ash transport from power plant, maintenance & house-keeping contract work etc.