44
IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN CONTRACTOR AND SUBCONTRACTOR FOR SUCCESSFUL CONSTRUCTION PROJECT IMPLEMENTATION SYAHIDAH BINTI LAGIMAN A thesis submitted in fulfillment of the requirement for the award of the Degree of Master of Science in Construction Technology Management Faculty of Technology Management and Business Universiti Tun Hussein Onn Malaysia JANUARY 2017

IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN CONTRACTOR AND

SUBCONTRACTOR FOR SUCCESSFUL CONSTRUCTION PROJECT

IMPLEMENTATION

SYAHIDAH BINTI LAGIMAN

A thesis submitted in

fulfillment of the requirement for the award of the

Degree of Master of Science in Construction Technology Management

Faculty of Technology Management and Business

Universiti Tun Hussein Onn Malaysia

JANUARY 2017

Page 2: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

iii

ACKNOWLEDGEMENT

First and foremost, I would like to express my deepest thanks to my supervisor

Dr.Norliana Binti Sarpin and co-supervisor Dr. Kamalludin Bin Bilal, who have been

much more than just advisors since my beginning of this research. They also been

generous in time, guidance and their support. Without their interest and

encouragement, this study would never have been completed.

I am deeply grateful to Universiti Tun Hussein Onn Malaysia because give me

platform to continue my study with providing a scholarship.

I would also like to thank all the construction practitioners who involved in this study

for providing me a lot information about construction industry. Their co-operation and

support have made my data collection going smoothly and easy process.

Big thanks also extended to my lovely husband, mother, my sister and my brother, and

my daughter for their encouragement, love and support.

Finally, I convey my sincere thanks to all my friends for their support, advice and help

throughout the journey of my study. Last but not least, I would like to thank everyone

who has directly and indirectly contributed to the successful completion of this study.

Page 3: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

iv

ABSTRACT

Cooperation between the main contractor and subcontractor to deliver the construction

project within the time, quality and cost are important in the construction industry. The

success of the construction project depends on the subcontractors because they are the

party that execute the technical and the operation of the works. The main contractor

needs to possess the ability to effectively coordinate and manages the sub-contractors.

Despite to this importance, there are relationship issues between the main contractor

and the subcontractor that required to be reviewed. The objectives of this research

were to determine the factors leading to relationship problems between the main

contractors and subcontractors in a construction project and to propose

recommendations to improve the main contractor and subcontractor relationship for a

successful project implementation. A qualitative method was chosen and face to face

semi-structure interview was conducted by having the discussion with six respondents

from both main contractors and subcontractors. The scope of this research is the

housing development project in Johor Bahru. The data collected was analysed using

content analysis. The outcome of this research concluded the relatives to this issues,

the factors leading to relationship problems between the main contractor and

subcontractor are time and cost overrun factor, delay, trust, lack of quality, lack of

communication, lack of safety, shortage of construction material and shortage of skill

labors. On the other hand, the recommendation to improve the relationship between

both parties are skill, integrity, trust, responsibility and communication application

which is mutual in a contractual relationship between both parties. In conclusion, the

finding can assist in the improvement of the main contractor and subcontractor

relationship for successful construction project implementation.

Page 4: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

v

ABSTRAK

Kerjasama di antara kontraktor utama dan subkontraktor dalam menyiapkan sesebuah

projek di dalam masa, kualiti dan kos yang ditetapkan adalah penting dalam industri

pembinaan. Kejayaan sesebuah projek pembinaan bergantung kepada subkontraktor

disebabkan mereka melaksanakan secara teknikal dan operasi kerja pembinaan.

Kontraktor utama memerlukan keupayaan yang efektif dalam menyelaras dan

menguruskan subkontraktor. Disebalik kepentingan ini, terdapat beberapa isu

berkaitan hubungan di antara kontraktor utama dan subkontraktor yang perlu dikaji.

Objektif kajian ini adalah untuk mengenal pasti faktor-faktor yang membawa kepada

permasalahan hubungan di antara kontraktor utama dan subkontraktor di dalam projek

pembinaan dan untuk mengkaji cadangan memperbaiki hubungan di antara kontraktor

utama dan subkontraktor untuk tujuan pelaksanaan sesebuah projek dengan jayanya.

Pendekatan kualitatif dipilih dan temu bual semi-struktur diadakan dengan

perbincangan dengan enam orang responden yang terdiri daripada kontraktor utama

dan subkontraktor. Skop kajian adalah projek pembangunan perumahan yang terletak

di Johor Bahru. Data yang diperolehi dianalisis dengan menggunakan analisis

kandungan. Hasil daripada kajian ini dicapai dan kesimpulan dapat dibuat menerusi

isu dan permasalahan ini iaitu faktor-faktor yang boleh membawa kepada masalah

perhubungan iaitu lebihan masa dan kos, kelewatan, kepercayaan, kekurangan kualiti,

kekurangan komunikasi, kekurangan keselamatan, kekurangan bahan pembinaan dan

kekurangan pekerja mahir. Selain itu, cadangan untuk membaiki perhubungan di

antara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab,

dan komunikasi di mana boleh digunakan untuk perhubungan kontrak bersama di

antara kedua pihak. Kesimpulannya, dapatan ini dapat membantu di dalam menambah

baik hubungan kontraktor utama dan subkontraktor untuk kejayaan pelaksanaan

projek pembinaan.

Page 5: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

vi

TABLE OF CONTENT

TITLE i

DECLARATION ii

ACKNOWLEDGEMENT iii

ABSTRACT iv

ABSTRAK v

TABLE OF CONTENT vi

LIST OF TABLES xi

LIST OF FIGURES xiv

LIST OF APPENDIX xv

CHAPTER 1 INTRODUCTION

1.1 Introduction 1

1.2 Background of research 2

1.3 Problem Statement 2

1.4 Research Questions 4

1.5 Research Objectives 4

1.6 Research Scope 4

1.7 Significance of research 5

1.8 Research Methodology 6

1.9 Outline of Thesis 7

1.10 Summary 8

CHAPTER 2 LITERATURE REVIEW

2.1 Introduction 9

2.2 Current Scenario of Construction Industry 9

2.2.1 Challenges in Construction industry 10

2.2.2 The importance of time, quality and cost in

construction 11

2.3 Concept of Relationship Between Parties Involved in

Construction Industry 12

Page 6: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

vii

2.4 Parties involves in Construction project 13

2.4.1 Client/Owner 13

2.4.2 Consultant 14

2.4.3 Main contractor 15

2.4.4 Sub-contractor 16

2.4.4.1 Types of sub-contractor 17

a) Domestic subcontractor 17

b) Nominated subcontractor 17

2.5 Successful project implementation in construction

Industry 18

2.6 Relationship issues between main contractor and sub-

contractor 18

2.6.1 Contractual issues 19

2.6.2 Time and cost overrun 19

2.6.3 Delay in project completion 20

2.6.4 Trust issues 21

2.6.5 Poor construction of quality 21

2.6.6 Lack of communication 22

2.6.7 Contractor financial problem 23

2.6.8 Changes in material and labor cost 23

2.6.9 Conflict of scheduling and planning 24

2.6.10 Lack of safety 25

2.6.11 Incomplete working drawing 25

2.6.12 Shortage of construction materials 26

2.6.13 Shortage of skilled labors 26

2.6.14 Termination of works 26

2.6.15 Incorrect pricing 27

2.6.16 Acts of God factor 27

2.7 Recommendation to minimize issues between

main contractor and subcontractor at

construction industry 28

2.8 Summary 29

Page 7: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

viii

CHAPTER 3 RESEARCH METHODOLOGY

3.1 Introduction 30

3.2 Research Process 30

3.2.1 Problem definition 31

3.2.2 Research Approach 32

3.2.2.1 Qualitative Approach 33

3.2.3 Respondents Selection 33

3.2.4 Research Instrument 34

3.2.4.1 Face to face Interview 34

3.2.5 Data Collection 35

3.2.5.1 Primary data 35

3.2.5.2 Secondary data 36

3.2.6 Data Analysis 36

3.3 Summary 37

CHAPTER 4 DATA ANALYSIS

4.1 Introduction 38

4.2 Data Analysis Overview 38

4.3 Respondent Background 39

4.3.1 Demographic data of the Main contractors 39

4.3.2 Demographic data of the Subcontractors 40

4.4 Data Analysis 40

4.5 The factors that lead to relationship problems

between main contractors and subcontractors in

a construction project. 41

4.5.1 Relationship scenario in construction industry 41

4.5.2 Relationship of people involved in the

construction industry 43

4.5.3 Contractual Issues 46

4.5.4 Time and cost overrun 48

4.5.5 Delay in project completion 50

4.5.6 Trust issues 52

Page 8: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

ix

4.5.7 Poor construction of quality 54

4.5.8 Lack of communication 56

4.5.9 Contractor financial problem 58

4.5.10 Changes in materials and labor cost 60

4.5.11 Conflict of scheduling and planning 62

4.5.12 Lack of safety features 65

4.5.13 Incomplete working drawing 66

4.5.14 Shortage of construction material 68

4.5.15 Shortage of skilled labors 70

4.5.16 Termination of works 73

4.5.17 Incorrect pricing 74

4.5.18 Acts of God factor 76

4.6 Ways to improve the relationship between the

main contractor and subcontractor 80

4.7 Ways to ensure long-term relationship between the main

contractor and subcontractor 83

4.8 Discussion 85

4.8.1 Factors that lead to relationship problems

between the main contractor and

subcontractor 85

4.8.2 Ways to improve the relationship between

the main contractor and subcontractors 86

4.9 Main finding of interviews 88

4.10 Summary 88

CHAPTER 5 CONCLUSION AND RECOMMENDATION

5.1 Introduction 90

5.2 Conclusion 90

5.2.1 To determine the factor that lead to relationship

problems between main contractor and

subcontractor in a construction project. 91

5.2.2 To propose recommendations to improve the main

contractor and subcontractor relationship

Page 9: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

x

for a successful project implementation. 92

5.3 Limitation of Study 93

5.4 Recommendation 93

5.4.1 Recommendation for future industry 93

5.4.2 Recommendation for future study 95

5.6 Closure 96

REFERENCES 97

APPENDIX 103

Page 10: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

xi

LIST OF TABLES

Table 4.1 Respondents’ (Main contractor) Background Information 39

Table 4.2 Respondents’ (Subcontractor) Background Information 40

Table 4.3 Respondents’ responses (main contractor) in term of relationship

scenario in construction industry 41

Table 4.4 Respondents’ responses (subcontractor) in term of relationship

scenario in construction industry 42

Table 4.5 Respondents’ responses (main contractor) in term of relationship

all people involved in construction industry 44

Table 4.6 Respondents’ responses (subcontractor) in term of relationship

all people involved in construction industry 45

Table 4.7 Respondents’ responses (Main contractor) in term of

Contractual issues 46

Table 4.8 Respondents’ responses (Subcontractor) in term of

Contractual issues 47

Table 4.9 Respondents’ responses (Main contractor) in term of time

and cost overrun 48

Table 4.10 Respondents’ responses (Subcontractor) in term of time

and cost overrun 49

Table 4.11 Respondents’ response (main contractor) for the of delay in

construction project 50

Table 4.12 Respondents’ responses (subcontractor) for the issue of delay in

construction project 51

Table 4.13 Respondents’ responses (Main contractor) in term of trust 52

Table 4.14 Respondents’ responses (subcontractor) in term of trust 53

Table 4.15 Respondents’ responses (main contractor) in term of

lack of quality 54

Table 4.16 Respondents’ responses (subcontractor) in term of

lack of quality 55

Table 4.17 Respondents’ responses (main contractor) in term conflict

of Lack of communication 56

Table 4.18 Respondents’ responses (subcontractor) in term conflict

Page 11: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

xii

of lack of communication 57

Table 4.19 Respondents’ responses (main contractor) in term conflict

of contractor financial problems 58

Table 4.20 Respondents’ responses (subcontractor) in term conflict

of contractor financial problems 59

Table 4.21 Respondents’ responses (main contractor) in term of changes

in material and labor cost. 60

Table 4.22 Respondents’ responses (subcontractor) in term of changes

in material and labor cost. 61

Table 4.23 Respondents’ responses (main contractor) in term conflict

of scheduling planning. 63

Table 4.24 Respondents’ responses (subcontractor) in term conflict of

scheduling planning. 64

Table 4.25 Respondents’ responses (main contractor) in term of lack

of safety. 65

Table 4.26 Respondents’ responses (subcontractor) in term of lack

of safety. 66

Table 4.27 Respondents’ responses (main contractor) in term of

incomplete working drawing. 67

Table 4.28 Respondents’ responses (subcontractor) in term of

incomplete working drawing. 67

Table 4.29 Respondents’ responses (main contractor) in term of shortage

of construction materials. 68

Table 4.30 Respondents’ responses (subcontractor) in term of shortage of

construction materials. 70

Table 4.31 Respondents’ responses (main contractor) in term of shortage of

skill labors. 71

Table 4.32 Respondents’ responses (subcontractor) in term of shortage

of skill labors. 72

Table 4.33 Respondents’ responses (main contractor) in term of

termination of works. 73

Table 4.34 Respondents’ responses (subcontractor) in term of

termination of works. 74

Table 4.35 Respondents’ responses (main contractor) in term of

Page 12: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

xiii

Incorrect pricing. 75

Table 4.36 Respondents’ responses (subcontractor) in term of

Incorrect pricing. 76

Table 4.37 Respondents’ responses (main contractor) in term of

‘Acts of God factor’. 76

Table 4.38 Respondents’ responses (subcontractor) in term of

‘Acts of God factor’. 78

Table 4.39 Summary of factors that lead to relationship problems

between main contractor and subcontractor (according to

main contractor) 79

Table 4.40 Summary of factors that lead to relationship problems

between main contractor and subcontractor (according to

subcontractor) 79

Table 4.41 Respondents’ responses (main contractor) on recommendation

towards a better relationship between the two parties 81

Table 4.42 Respondents’ recommendation (subcontractors) towards

relationship between the subcontractor and main contractor 82

Table 4.43 Respondents’ responses (main contractor) on ways to ensure

long term relationship between the main contractor and

subcontractor 83

Table 4.44 Respondents’ responses (subcontractor) on ways to ensure

long term relationship between the main contractor and

subcontractor 84

Page 13: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

xiv

LIST OF FIGURES

Figure 1.1 Value of construction work done by location of project for

Q3 2016 (Department of Statistics Malaysia, 2016) 5

Figure 1.2 The steps of the research methodology 6

Figure 3.1 Flow chart of research design process 31

Page 14: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

xv

LIST OF APPENDIX

APPENDIX TITLE PAGE

A Interview Question Form 103

B Summary Objective 1 111

C Summary Objective 2 117

Page 15: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

CHAPTER 1

INTRODUCTION

1.1 Introduction

The construction industry is an important industry, which plays a vital role in the

socioeconomic growth of a country. Economically, it contributes in significant

improvement in the overall GDP of a country. In Malaysia, the GDP for construction

industry was the fastest ranking to be compared with other industry with 7.4 % rate in

quarter 2015 (Department Statistic Malaysia, 2016). It totally improves the better

quality of human life as construction industry supply for the infrastructure such as

hospitals, roads, schools and other facilities for necessary purpose (Wong et al., 2007).

Hence, it cannot be denied that construction industry has been propelled by demand

for the projects (Endut, 2008).

There are so many parties involves in the construction project starting from

professionals until the labors such as clients, consultants, main contractor,

subcontractor, supplier and labors which can cause problems between them, for

example, the lack of trust, delay, lack of communication that can cause conflict leading

to relationship problems among all this project stakeholder during the implementation

of construction project (Huang et al., 2008).

With the rapid development in technology and increasing in many type of

construction technology, the involves parties required to pay more attention in any

interface problems that will occur during construction process and need to be resolved

accordingly.

Page 16: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

2

1.2 Background of Research

According to Rashid et al. (2006), the factors that influence the overall productivity is

the quality-related, time-related and also cost-related that give significant challenges

to the development of construction industry in Malaysia nowadays. As demand for

construction continues to grow, the main contractor facing lots of challenges in terms

of the ‘relationship’ between the main contractor and subcontractor.

The relationship between main contractor and subcontractor is very crucial as

they are the persons who will make the project complete into reality. The management

in construction projects involves a great deal of managing risks to be apply and to be

practice. Managing risks involves: planning, identifying, analyzing, developing risk

handling strategies, monitoring and control. Consequently, the factors that lead the

relationship problems between the main contractor and subcontractor are seem to be

ignore since the main contractor only focus on the organizational client need (Huang,

2008).

Thus, all related issues and factors must be resolved between both parties

which involves in a development of construction site. Therefore, it is essential to

rigorously categorize the relationship problems between the main contractor and

subcontractor to accurately study their factors and recommendation can be made

during process for successful implementation projects in order to improve the quality

and productivity of the construction projects.

1.3 Problem Statement

Within the construction projects, where the concept of relationship is being tried to be

improved, all the project participants are realising that the sharing of knowledge and

information is the one of the key elements of success in a construction project. Main

contractors played a significant role in the most projects in construction field, also

commonly referred to subcontractors as the execution of construction works.

However, the relationship between them is slightly poor (Andreas et al., 2009).

According to Thomas (2011), main contractors are responsible for the

construction of projects, but they rely on subcontractors and/or specialist contractors

Page 17: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

3

and suppliers to execute the works. The main contractor does this to reduce their

overhead and operating costs, improve efficiency, and achieve a more economic

delivery of projects (Al Turkey, 2011).

Hola et al. (2014) also identify that there is poor level of information sharing

between main contractors and subcontractors. They reveal subcontractors’

unhappiness with main contractors was due to the insensitivity of their need for prompt

and correct information. Costs that run beyond estimates can result in losses for

construction company. Some of the largest construction contractors have significant

numbers of projects based on fixed price contracts, in which they bear the risk for cost

overruns. Factors such as raw material costs, economic conditions, and weather-

related delays could lead to losses for construction company. The longer the term of

the contract, the greater the potential deviation from original estimates (Huang, 2008).

According to Arditi and Chotibhongs (2005), many problems arise between

main contractor and subcontractor concerning on the management, quality,

workmanship and other related problem that will influence the relationship between

the main contractor and subcontractor. The subcontractor scope of works and

responsibilities are always misunderstood when there is some confusing information

by the main contractor and subcontractors.

The main contractors, on the other hand, complain that subcontractors have a

habit of bringing in adequate workmen to site, a practice which hampers the works

and fuel conflicts (Hook, 2012). Hook (2012) added that, common risks main

contractors face include weather, unexpected job conditions, personnel problems,

errors in cost estimating and scheduling, delays, financial difficulties, strikes, faulty

materials, faulty workmanship, operational problems, inadequate plans and

specifications, and disaster. Contractors can respond to the price of risk before a

construction project or after. All the situation stated had leading relationship problems

between the main contractor and subcontractors.

With the problem stated above, therefore this research is undertaken to look

into the factors that lead to relationship problems between the main contractor and

subcontractor that always occur in construction industry. The main contractor and

subcontractor relationship needs to be maintained throughout procurement process and

construction to enable a strong interface within the project team, which signifies a

positive move away from the traditional adverse relationships.

Page 18: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

4

1.4 Research Questions

Based on the problem statement outlined above, the research questions for this study

are as follows:

1. What are the factors leading to relationship problem between main contractor

and subcontractor in a construction project implementation?

2. How to improve the relationship between main contractor and subcontractor

for a successful construction project implementation?

1.5 Research Objectives

The aim of this research is improvement of relationship between the main contractor

and subcontractor for successful construction project implementation. Following are

the objectives in order to achieve this aim:

1. To determine the factors that lead to relationship problems between main

contractor and subcontractor in a construction project.

2. To propose recommendations to improve the main contractor and

subcontractor relationship for a successful project implementation.

1.6 Research Scope

This study focuses on housing project which involve of respondents from the main

contractor and subcontractor who practice in the construction industry in Johor Bahru,

Johor. There are many individuals and companies owner are grown very fast to

expanding their demand on the market such as residential housing construction,

commercial construction and many types of development especially in Johor Bahru.

Johor Bahru was chosen because many developments are in rapid progress if compared

to other states in Malaysia as statistic shown in Figure 1.1.

Page 19: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

5

In order to make the project into reality, many parties needed to be involved to

implement the structures and this is include main contractor and subcontractor.

Therefore, the study is to find out the factor that lead to relationship problems between

main contractor and subcontractor at construction site for successful project

implementation. This research, focuses on two groups of respondents, the main

contractors and also the subcontractor, consist of the selected sample represented all

classification categories of the main contractors from Grade 5 and above. For the

second population of subcontractors, the selected subcontractors represented did all

specialties of works such as shuttering, building, plastering, tiling, painting, mechanic,

and electrical, aluminum, carpentry and ironmongery.

1.7 Significance of Research

To complete the project, the main contractor and subcontractor are the most important

team in construction site to ensure all the project are completed on time, provide good

quality and also follow the time schedule.

Figure 1.1: Value of construction work done by location of project for Q3 2016 (Department of

Statistics Malaysia, 2016)

Page 20: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

6

This research will provide many information in the construction industry

especially who are practicing in construction site which involvement of main

contractor and subcontractor in many specialists. Among of the issues which arise are

the relationship between main contractor and subcontractor. In addition, this research

list all the relationship problems between the main contractor and subcontractor.

Therefore, this research discover the factor that lead to the problems of relationship

between main contractor and subcontractor in a construction project. This research is

also hope can solve the problems that arise between the main contractor and the

subcontractor through the recommendation given by the main contractor and

subcontractor based on their perspectives.

1.8 Research Methodology

Research process and method of approach were used as guidelines to meet the

objectives of the study. Every step has been organized to make sure all the data and

information could be done in systematic ways. The steps of the research methodology

are shown in Figure 1.1;

Figure 1.2 The stage of research methodology

Page 21: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

7

Figure 1.2 shows, when the topic has been selected, the problems were identified at

the beginning of the research. At the same time, the objectives of the research were

establishing. Then data collection was divided into primary data and secondary data.

The primary data was collected from the qualitative method which is interview

session. Interview with the practitioners of the construction (main contractors and

subcontractors) was conducted face to face and the question was given by the

researcher to gain more information from the respondents. The sources of the

secondary data basically come from the literature review, thesis, journal, electronic

media and books. Then the data were analysed using the content analysis, table and

paragraph to get the result. Conclusions were given after data analysis finish analysed

and the recommendations were made to end of this research.

1.9 Outline of Thesis

The outline of this thesis has five chapters which was covered in this research study.

In general, this study focused on improvement of relationship between main contractor

and subcontractor for successful construction project implementation.

The chapter 1 was present about the introduction, background of research,

problem statement, research questions, research objectives, research scope,

significance of research and research methodology. In this chapter, the researcher want

to explain what the research is all about and the description of the research.

In chapter 2, the focused more on literature review. Literature review involves

the systematic identification, location, and analysis of documents containing

information related to the research problem. The term is also used to describe the

written component of a research plan or report that discusses the reviewed documents.

These documents can include articles, abstracts, reviews, monographs, dissertations,

other research reports, books and electronic media. Besides, the purposes of the

literature reviews are act as benchmark for comparing the results of research study to

other findings.

In chapter 3, research methodology was explained about introduction, research

process, problem definition, research approach, respondent selection, research

instrument that suitable for this research study, data collection which is divided into

primary data and secondary data and data analysis to get the result.

Page 22: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

8

In chapter 4, the results of the data analysis are presented. The data were

collected and then processed in response to the problems posed in chapter 1 of this

research. The findings from the qualitative data was presented in this chapter

demonstrate the potential for merging theory and practice by using content analysis.

In chapter 5, the conclusions and recommendations was suggested in this

chapter. This chapter consist of conclusion, limitation of study, recommendation and

closure. This chapter was highlighted any interesting, new or unexpected findings

which did not discover in conducting the literature review.

In conclusions, the outline of thesis is a road map list in order to provide a good

process and important element in writing of research study. An outline of thesis also

helps to target the research areas, always keep within the scope without going off-

track, and it can also help to keep the argument in good order when writing the essay.

1.10 Summary

Construction nowadays create too many problems especially at the site between the

main contractor and subcontractor. Normally it will involve the practitioners on site

construction. In this chapter, the introduction of the research explained about the factor

and issues in the industry, followed by research background, statement of problems,

objectives of the study, the scope, significant of study, research methodology and

outline of the thesis in this research study.

Page 23: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

CHAPTER 2

LITERATURE REVIEW

2.1 Introduction

This chapter aims to provide an overview of the literature review related to this

research. This chapter also briefs with the scenario in our construction industry, the

challenges in the construction industry and the importance of time, cost and quality.

This chapter will also review on the concept of relationship between all parties which

involved in a construction project and most importantly the relationship between the

main contractor and their subcontractor. The issues between main contractor and

subcontractor create many conflict among them. The problems mostly faced in the

construction industry are usually from the design process and the construction process.

Both problems can give bad impact to the productivity of the construction industry

later. Lastly, this chapter will explain the recommendation to improve the relationship

between the main contractor and the subcontractor for successful project

implementation in the future.

2.2 Current scenario in construction industry

Construction industry is one of the major contributors that motivate and expand

Malaysia’s national economy. Nowadays, the construction industry acts as the engine

of the country economic growth (Memon et al., 2013) where buildings and structures

have enabled mankind to meet their special needs for shelter, economic to feed the

nation’s investment needs, as well as in satisfying corporate objectives.

Activities in the construction industry play an important role in achieving the

national socio-economic development, such as providing shelter upgrading and

improving the infrastructure system and providing employment opportunities

Page 24: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

10

especially for the locals. In accordance to the literature review, the construction

industry activities give tremendous impacts in every aspect of the economy; which is

why it is one of the industries that has been categorized as economic driver,

particularly in developing countries (Rangelova, 2015).

The results from the construction investment that gives effects through the

local and national economy, is from the appropriate planning that involved many

parties whom connected with many available construction resources (Teplicka et al.,

2012)

2.2.1 Challenges in construction industry

Construction industry is one of the industry that contributes the most to the ecological

problem especially to our environment as compared to other sectors. However,

according to Johnston (2007), most construction project nowadays has already

practiced the sustainability to the environment when doing the construction work.

Plessis (2007), in her studies has mentioned that Malaysia’s continuous growth to

achieve the vision 2020 has caused most developers to exert more priorities on the

economic issues as compared to the sustainable agenda of the country.

The labor crisis is not a new issue, in fact it has been reported years ago, To

date, the issue regarding labor crisis such as lack of skills and low number of local

labors in the construction industry are still a big concern to the industry. Nevertheless,

most experts predicted that it will continue to be better in 2016 and beyond, as talent

deficit requires multiple years to fill up again (Menk, 2016).

Volkov (2013) had explained about Building Information Modeling

(BIM) where according to him, BIM has been a growing trend for years, as it is no

longer relegated to large firms. Experts have also stated that BIM is capable in

providing tangible business benefits. Many organizations agreed with BIM's ability to

provide consistent, accurate and less time-consuming project documentation.

Moreover, BIM users can also expect a better collaboration and coordination among

the different parties such as consultants and contractors that are involved in that

particular project.

The opportunities in construction are growing, but so is project complexity.

With companies already operating under razor-thin profit margins, a single production

Page 25: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

11

surprise can wipe out profits for the whole company. Design complexity compounds

this problem. As designs become larger and require greater efficiency, construction

companies struggle to keep up. The lack of on-time and on-budget projects is is on of

the challenges in the construction industry today (Idrus et al., 2011).

According to Othman (2012), relationship between contractors and

subcontractors are often overloaded and expose to dispute due to a poor sense of

fairness and misunderstanding of each other’s need. As stated by Olawale and Sun

(2010) a construction project involves so many parties such as owners, designers,

construction main contractor, subcontractor, maintenance contractor, and material

suppliers that some relationship problems cannot but arise, e.g. lack of cooperation,

inefficient communication, interruptions and lack of identification of responsibilities

and proper record of work carried out by subcontractor may cause confusion on site

leading to relationship problems between project stakeholders.

In conclusion, the challenges in the construction industry are varies in all

aspect and angle. Thus, all project stakeholders need to ensure that all the challenges

in the construction industry are facing together for successful project implementation.

2.2.2 The importance of time, quality and cost in construction industry

Nowadays, most construction organizations still taking it lightly when it comes to

evaluating the total cost of their project management performance. Normally, they will

emphasize more in getting the work completed within the given time, and cost and

also in complying with all the quality specifications required for the projects (Qureshi

et al., 2009).

The rapid and smooth growth of Malaysia’s construction industry has managed

to attract many new and potential investor to invest in this country such as investors

from China. However, Abu Mansor (2010) in his study has stated that although

RM230 billion has been allocated in the 10th Malaysian Plan, the construction industry

was found to be unable to complete their project within the given time and under the

estimated cost.

According to Pheng et al., (2006), time is an intangible resource in project

management especially in construction industry and it is considered as a unique integer

due to its finite element. Time availability of a project is defined as the availability of

Page 26: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

12

time needed to complete the designated work. Meanwhile, when a project is unable to

finish within the planned duration and require an extension of time, it indicates that

the project has a time overrun.

In a rapidly growing construction market, there is a vital need to ensure that

the project is done with approved quality as explained by Huang (2008). A good

quality product is not only to meet the customer requirements, but also to do it at the

lowest cost. Sharma (2006) has suggested that a timely help from the top management

in getting the resources or making a decision for critical issue that often arise during

the construction work can leave a big implication on overall cost performance. This is

significant especially when dealing with short duration projects where with each day

of delay, there will be large detrimental effect on cost.

For a construction project to be categorized as a successful project, its main

focus will be on the construction processes and the ability to accomplish project cost

and time objectives. Productivity success deals with the quality of the project’s final

product and the quality objectives of the project (Pheng and Chuan, 2006). Sharma

(2006) has pointed out that a successful commercialization of quality products requires

due attention to the complete supply chain (both suppliers and distributors).

Time, cost and quality is the triangle that connects the three major elements in

the construction industry. Their impact on each other will be just as unique to a

construction project’s circumstances. Hence, it can be concluded that the key to a

successful project is when the project has the right balance of quality, time and cost

that may vary according to the particular requirements of the project.

2.3 Concept of relationship between parties involved in construction industry

Relationship as explained by Mouzas and Ford (2007) is a social exchange process

that includes personal bonds between two persons or more, and plays an important

role during their development. Meanwhile, trust can be reacted as inter organizational

as well as interpersonal.

The systematic study shows that interpersonal relationship and their impact

especially in human behavior and development was developed with years in the

concept of relationship (Hinde, 1979). The relationship is also shaped by various

geographical sizes and natural resources of different economies. Thus, relationship

Page 27: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

13

and trust can be interdependence factor for both people and organization. In

conclusion, relationship is one of the indicators used in achieving the strategy goals

and indirectly can improve the performance of a project.

2.4 Parties involves in construction project

A construction project normally involves many parties in order to provide good

productivity of a construction project. The involvement of the client as owner,

consultant, main contractor and subcontractor continuously are essential to make sure

the project is in track and is able to be completed as demanded by the owner.

A highly effective team can gain a great outcome, by establishing good

working relationship and conducive environment while minimizing conflict in the

project team. With reference to this working concept, collaboration between parties as

a team will ensure all the knowledge and experiences can meet the needs in today’s

world and also in future.

2.4.1 Client/Owner

Client is the party that has the authority in making decision especially on goals,

objectives, and parameters as well as the time that the project can start to commence

since they are the owner of the project. Every project is unique since every client has

different perspective and idea that will later be elaborated by a team of consultants led

by an architect. The client is the initiator and financer to all the construction project

(Al turkey, 2011) and Kelly (2015) also agreed with it by stating that different owner

(client) will think from different perspectives. They will always put the value of

management as their main priority to ensure their investment worth every cent.

Kelly (2015) has also mentioned that client can be categorized into a few categories

as listed below:

a) Commercial

A commercial client is comprised of company, factory or any that need to do

construction works to aid their business process or production. The strict legal in

Page 28: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

14

today’s world make it clear that regulations have to be followed strictly

especially in safety and environmental regulation pertaining to planning and

construction of any particular building.

b) Private

Private clients comprised of person like sole trader or local people who need a

group of professional team to handle the construction, alteration and also

maintenance of their private properties.

c) Government

Government based project normally involved three levels ; local council, state

and territory government and central (federal) government. The division of this

level shows that the government client does all the works. For instance, the local

council will handle small maintaining services, the state government will instruct

to do a public building or significant infrastructure changes. The central

government will only manage the infrastructure projects.

d) Public Limited Companies

Public limited companies consist of companies that are listed in stock exchange

such as banks, developer and also retailer in which these companies have public

shares and normally there will be -a tender or a contract before construction work

can proceed.

Construction rarely will has the same design since different type of clients has

different and variety of ideas that is usually unique. This resulting in different expert

and professional team required for each project due to the unique characteristics of the

project in terms of planning and execution of works.

2.4.2 Consultant

Consultants- normally involved in the initial stage of a construction project and their

presence at the early stage is usually beneficial to the client. Consultant will be in

charge in project budgeting and management, to advice the client and give solutions

Page 29: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

15

for any issue that may arise with regards to their design, to prepare feasibility study

before construction work starts and to take care of space relationship (Locke, 2013).

Consultants consist of a team that was appointed by the client to perform the given

task for the construction project. According to Tai et al. (2008), consultant should

work as a team with architect, engineer, quantity surveyor and other related consultant

to discuss and work together in order to resolve any issue pertaining the project.

Therefore, communication and trust is a vital factor to all consultants in ensuring the

success of the project, by allowing a smooth planning of the project and getting the

project to complete within the given timeline.

2.4.3 Main Contractor

Rahman (2013) mentioned in his studies that a collaboration is necessary in

construction project to ensure the success of a project, especially to the main contractor

that holds the greatest responsibilities towards the development of the project. Their

scope of works includes planning, coordinating and supervising their subcontractor

when delivering the construction project. According to Schaufelberger (2009) the

main contractor undertakes the project based on the client needs. They need to

proactively seek for new projects and any available opportunities, in order to build

new networks and creating a long-term relationship with other industry’s player.

Contractor also will be involved in training owner’s personnel about the operation of

the building systems and may be required to provide maintenance during post-

construction.

Main contractor has their own field of specialization such as building industry,

commercial, industrial and for mega project. The main contractor would prepare

budget and planning schedule right from the design phase until the completion

inspection of the project. The main contractor normally will liaise with all the

consultants when there is issue aroused. This is to ensure the project can complete

within the given time, under designated cost and following all the required specs for a

good quality end product.

Page 30: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

16

2.4.4 Sub-Contractor

Malaysian can witness the booming in our nation’s construction industry when

numerous projects can be seen ongoing including mega project such as Mass Rapid

Transit (MRT) project. Most major construction works at site are performed by the

subcontractor and the main contractor roles has become limited in the execution of

work at site (Andreas et. al., 2009).

Blomback and Axelsson (2007) have explained that main contractor would

select the subcontractor through bidding process. Awarding a project to the right

subcontractor is critically important as it may affect the overall project performance.

The main contractor will need to do a background study on their financial status,

technical ability and gather other information that may be helpful about their

subcontractor.

The common practice when selecting a subcontractor is through the ‘lowest

bidding’, (Singh and Tiong, 2006) although when the main contractor is very well

aware about problems that may arise later, particularly on issue regarding poor quality

of workmanship and low productivity. This also can avoid claims and disputes. Thus,

the main contractor has to do a list of supplementary selection criteria such as looking

at its past performance, financial status and team working capacity that will give more

impact on the final output performance of the main contractor.

According to Aslan et al. (2008), there are some factors that need to be taken

into consideration before selecting subcontractor that includes:

a. Subcontractor’s capacity of resources

b. Their past performance records

c. Company reputation and,

d. the ability to complete the work on time.

A good integration between the subcontractor and the main contractor could

assist in many aspects like timely completion, improved quality and at the same time

can help in improving environmental issues, health and safety.

Page 31: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

17

2.4.4.1 Types of sub-contractor

There are two types of subcontractor:

a) Domestic subcontractor

A domestic sub-contractor is any sub-contractor, other than a nominated-sub

contractor, that the main contractor sub-contracts to carry out part of the works. The

work of the sub-contractor is the responsibility of the main contractor as far as the

contract between the main contractor and the client is concerned (Cheng Ying, 2010).

Cartlidge (2009) had explained that most domestic subcontractors are normally

appointed directly by the main contractor. Domestic subcontractor will carry out the

works on behalf of the main contractor and basically, they will do all the general

works. Hence, the scope of works of a domestic subcontractor includes all the works

stated in the subcontract in accordance with order from the main contractor.

b) Nominated subcontractor

Definition of nominated subcontractor according to Cheng Ying (2010) is any

merchant tradesman specialist or other person, firm or company that is nominated in

accordance with the Contract to be employed by the Contractor for the execution of

work or supply of goods materials or services for which Prime Cost has been inserted

in the Contract or ordered by the Engineer to be employed by the Contractor to execute

work or supply goods materials or services under a Provisional Sum.

The nominated subcontractor is normally appointed by the project stakeholder

or directly through client, unlike the domestic subcontractor. Nominated subcontractor

does not need to report progress to the main contractor since they do not have a formal

contract with the main contractor and their payment is paid directly by client

(Cartlidge, 2009).

Page 32: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

18

2.5 Successful project implementation

A successful Project general definition is meeting the goals and objectives as stated in

the initial project plan. A project is considered success when the project had

successfully accomplished its technical performance, maintained its schedule, and

remained within budgetary costs. The success of a project also can be defined from

several factors such as the competencies of the project leaders, characteristic, skills,

leadership concept and their personalities in order to produce great outcome

(Ogunlana, 2011).

According to Kerzner (2009), a success project has always been defined as the

ability to complete the project within the time constraints, cost and performance for

overall outcome productivity. However, the cliché definition has been modified to

fulfill the requirements in order to be considered as successful as listed below:

a. Within the allocated time period

b. Within the budgeted cost

c. At the proper performance or specification level

d. With acceptance by the customer/user

e. With minimum or mutually agreed upon scope changes

f. Without disturbing the main work flow of the organization

g. Without changing the corporate culture

According to Muller and Turner (2007), every project has different criteria

and the public judgment on the successful of a project is merely depending on its

personal objectives. To one person, the project may be considered as success.

However, another person may have a different perspective that considered the project

as a failure.

2.6 Relationship issues between main contractor and sub-contractor

Metri (2005) in his study mentioned that every project is different in situation and

condition for example; personnel characteristics, construction productivity, types of

material use, weather condition as well as difference in terms of required time and

Page 33: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

19

project cost. Furthermore, the uniqueness in construction industry has always been

related to its nature of uncertainty. Most problems that are commonly found in

construction projects are contractual issues, time and cost overrun, project delay, trust

issue, lack of quality, lack of communication, contractor’s financial problems, changes

in material and labor cost, conflict of scheduling and planning, lack of safety,

incomplete working drawing, shortage of construction materials, shortage of skilled

labors, termination of work, incorrect pricing and act of God factor (force majeure).

2.6.1 Contractual issues

Subcontracts are often used in most construction works so as to meet the target and

demand from the owner of the project. According to Huang et al. (2008), most of the

contracts awarded to the subcontractor contains several contracting issues that will

cause problems between the main contractor and the subcontractor when executed on

the site later. Improper project management either by the main contractor or the

subcontractor may lead to the interface problem between both parties. The issues will

get worse if the contract letter is incomplete.

Most awarded subcontracts do not have formal discussion between the

contractor and the subcontractor. The problem normally happens when the involved

parties make or execute the contracts. Volkov et al. (2008) in his studies stated that

there are several contracting problems that are commonly emerged in the contract

execution such as unclear/missing details in the drawing, incomplete contract, changes

in design and so forth. This may increase the probability of a conflict after construction

work has begun.

2.6.2 Time overrun and cost overrun

One of the most significant issues and often occurred in most construction project is

time overrun. According to Sweis et al. (2008) time overrun occurs when a project

exceeded the original completion time as per contract or the project execution is

beyond the actual deadline as agreed by other involved parties due to unavoidable or

reasonable excuse (Endut et al., 2006; Marzouk and El-Rasas, 2014). The issues with

time and cost overrun will give an immediate effect to the owner and the stakeholder

Page 34: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

20

of construction project (Moura et al; 2007). The five main reasons that lead to this

problem as listed by project owner are incomplete drawings, poor planning process,

poor leadership that lead to late decision, increase in the materials cost and excessive

change orders (Cox, 2007).

According to Endut (2008), when there is a time overrun, it will lead to cost

overrun as well since these two are interrelated factors. Ramanathan et al. (2012)

mentioned in his studies, the parties that suffered the most when the project

encountered time and cost overrun is the owner/stakeholder of the project. Clients and

stakeholder will keep facing the same issues every time since this problem seems to

be unavoidable in most construction project. This will lead to more problems that is

not favorable to the clients/stakeholder such as continuous financial waste, project

completion delayed, trust issue, and most importantly low quality and productivity of

the product (Ramanathan et al., 2012). The low productivity leads to relationship

problem between main contractor and subcontractor.

2.6.3 Delay in project completion

Another common problem that can be found in construction industry is project delay

(Enshassi et al., 2009). Delays in completing a construction project can be categorized

as a global issue as it happens across the world and leaves a significant financial impact

on the owner and the contractor. Some are able to resolve the disputes that arise out of

delays, but in often cases, it may fall to the courts or arbitrators to determine which

party or parties, if any, are responsible for the delay and which party or parties, if any,

must bear the increased costs caused by the delay.

Delay in payment as explained by Ye and Abdul Rahman (2010) normally

comes from the delay in issuing certification by involved parties in the construction

project. The client or owner might hold the approving of payment issues due to certain

reason that arises by the parties that are involved in the project. As an example, a delay

in payment by the clients to the contractor will cause in late payment issues to the

subcontractor by the main contractor. The low productivity leads to relationship

problem between main contractor and subcontractor.

Page 35: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

21

2.6.4 Trust issues

Trust is extremely difficult to elaborate, especially on behavior of trust in a

construction project relationship from a holistic view. According to Mouzas et al.

(2007), trust is necessary in every relationship management concept. According to

Ha’kansson et al. (2008) trust is a necessary requirement that needs to be built in every

relationship since not all aspects can be controlled by contract. Trust has to be built

slowly between parties that will gradually develop and mature as time goes by.

The main contractor has to put trust on the subcontractor that will execute the

work mainly on task that involves expertise or required specific skills (Ogunlana et

al., 2007). The success of the project will depend upon the productivity and the

selection of subcontractor with good attitude to execute their portion of works. The

relationship between the subcontractor and the main contractor will also prosper for

the better. The low productivity leads to relationship problem between main contractor

and subcontractor.

2.6.5 Poor construction work quality

Quality is a set coordinated to control all the activities in construction industries to

provide the effectiveness and the efficiency of the construction performance.

According to Wei (2012), there is a difference in the definition of quality control

between manufacturing sector and construction sector. Quality output is fundamental

for all sectors particularly in the construction industry as it is hard to achieve and

requires a special quality control technique. t A good plan and systematic management

by the construction company will improve the construction quality to meet the client

requirement (SIRIM, 2007).

Huang et al. (2008) mentioned that most construction problems are due to the

lack of experience that will eventually lead to poor flexibility and quality from the

adaption of the new environment. When the main contractor is awarded with the

construction contract, they will perform their construction work portion while

specialist required work will be done by the subcontractor (Pheng et al., 2005). In

normal practice, experienced main contractor will make less mistakes when

performing the construction works. Whenever either the main contractor or the

Page 36: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

22

subcontractor makes a mistake while constructing the project, it will affect the work

of the other party especially when the scope of works is related to quality factor.

However, most poor construction quality occurs due to the lack of proper

communication. The low productivity leads to relationship problem between main

contractor and subcontractor.

2.6.6 Lack of communication

Communication is defined as getting the receiver and the sender tuned together for a

particular message (Imtiaz and Ibrahim, 2005). Communication happens when one

party transfers some understandable data to the other party. According to Huang et al.

(2005) communication usually includes the exchange of thoughts, opinions,

sentiments, facts, and information between two or more persons. Receiving a feedback

is very important as it assures that the message has been properly conveyed to the

receiver.

Most construction project that experiences lack of communication issue will

lead to poor project scheduling and planning. This will result in lack of project

management and can cause a critical problem to the quality of end product. According

to Briscoe et al. (2007), for a smooth flow of information exchange, an effective

communication system is required as it can help to clear any misunderstanding or

integrity of message conveyed, to receive proper response and feedback from the other

party. Good communication with proper coordination are critical in construction to

avoid any possible problems that may arise in any construction project. The need for

communication and coordination drives many of the contract terms to acquire notice

of claims and complete information on the cost and time impact at an early stage.

Communication is critical during this three stages namely, the bidding process,

in preparations to proceed with the project and also during commencement of the

construction work. Communication about problematic construction work has to

involve various parties and the flow comes from all directions between the owner and

the architect. Information received from them will be delivered to the main contractor

and shared to both subcontractors and suppliers, and to or from third party participants.

Any problems on site must be reported once it appears by the contractors and the

suppliers to the architect and the project owner. Information that received afterward

needs to flow back through the main contractor to the owner and architect to minimize

Page 37: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

23

possible delays in work completion. It is also important for both suppliers and

subcontractors to have a two-way communication through the main contractor.

However, some relationship problems in the construction industry stem from

the lack of trust and ineffective communication between the project participants

especially when subcontractor is not integrated into the main alliance (Huang et al.,

2008). A prompt and clear communication can reduce any potential future problems

that may arise, and this is only possible when there is a proper coordination among all

parties that include contractors, subcontractors, and suppliers. The lack of

communication can lead to relationship problem between the main contractor and

subcontractor.

2.6.7 Contractor financial problem

Construction project will always be linked to payment problems. An issue that is not

new, in fact has been reported in most construction projects. According to Morton

(2008), a deteriorating in world economy has worsen the issue and has caused the main

contractor to delay the payment to their subcontractor. The main reason would be to

protect the main contractor’s cash flow on expenses of subcontractor.

Furthermore, the client also tends to hold payment from the contractor’s claim.

In most cases, late payment is normally due to the lack of adequate supporting

documentation, different specifications from original plan and on site, as well as

payment rules clauses that allow the main contractor to delay the subcontractor

payment (Bassam, 2007). These are among the tricks that the main contractor always

use to hold back the subcontractor’s payment. Consequently, a conflict may occur

between the contractor and his subcontractors that can lead to relationship problem

between the main contractor and subcontractor.

2.6.8 Changes in materials and labor cost

Changes in material and labor cost represent the largest element of any construction

project (Ogunlana, 2007). Efficient utilization of labor, material and equipment are the

examples of good project management in construction. Improvement of labor

productivity should be a major and continual concern of those who are responsible for

Page 38: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

24

cost control of constructed facilities. Activities in material handling require special

attention to allow cost reduction including procurement, inventory, shop fabrication

and field servicing. According to Bramble (2011), he main contractor or subcontractor

will experience loss instead of making profit if both parties make a mistake during the

cost estimation and pricing, in particular for material and labor cost. The low

productivity leads to relationship problem between main contractor and subcontractor.

2.6.9 Conflict of scheduling and planning

Planning includes what type of activities involved and how to conduct the activities,

while scheduling focuses on when will the activities take place and who will be in

charge. The purpose of scheduling and planning is to ensure a smooth project flow and

at the same time, it also serves other purposes. Scheduling and planning started with

the owner and the architect, and later expanded with the contractor, the subcontractors

and the material suppliers. Coordination between the team is crucial in conducting all

the activities (Huang et al. 2008). Bragadin et al. (2015) in his studies stated that a

good construction planning and scheduling does not guarantee the success of the

project but it can be a good guideline for everyone. A successful project planning can

save client from overspending their money and reducing the total project cost as well

as capable to meet the quality as required by clients.

Poor project scheduling can also cause a conflict between the main contractor

and the subcontractor during the project construction. The same issue is also found

among the subcontractors. In this case, the main contractor roles will interface into

this aroused issue with the subcontractor so that it will resolve as soon as possible

before any other issue like delay arises that will affect the relationship (Bassam, 2007).

Idrus et al. (2011) have explained that most of the delays in schedule occur because of

the main contractor does not make thorough inspection and recognized with their

subcontractor progress of works. Hence, a two-way communication between the main

contractors and the subcontractors need to be done and a discussion is required in order

to identify the roots of the problems.

Page 39: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

REFERENCES

Addison R. (1999). The grounded hermeneutic approach: editing style. In: Crabtree B,

Miller W, eds. Doing Qualitative Research. Thousand Oaks, California:

Sage 145–61.

Akintoye, A., and Main, J. (2007). Collaborative relationships in construction: the UK

contractors’ perception, Engineering, Construction and Architectural

Management Journal, vol. 14 No.6, pp. 597- 617.

Al Turkey (2011). The reality of projects in terms of organization and structure, and

the reasons for success and failure In Saudi Arabia. Alwatan Newspaper.

(online) accessed on 19 April 2015 available from

http://www.alwatan.com.sa/Local/News_Detail.aspx?ArticleID=49126&

CategoryID=5.

Andreas, H., Florence, Y. Y. L., and Jane, S. H. T. (2009). Relative Importance of

Subcontractor Selection Criteria: Evidence from Singapore. Journal of

Construction Engineering and Management, 135(9), 826-832.

Idrus A, Sodangi M and Husin M.H (2011). Prioritizing Project Performance Criteria

within Client Perspective.

Arditi D. and Chotibhongs R., (2005). “Issues in subcontracting practice,” Journal of

Construction Engineering and Management, vol. 131, p. 866.

Arslan G., Kivrak, S., Birgonul, M.T. and Dikmen, I. (2008). Improving subcontractor

selection process in construction projects: Web-based subcontractor

evaluation system (WEBSES), Automation in Construction, Vol. 17, pp.

480-488.

Bassam A. Tayeh. (2007). The Relationship Between Contractors and Their

Subcontractors in The Gaza Strip.

Bramble BB. (2011). Callahan MT. Construction delay claims. 4th ed. US: Aspen

Publishers.

Bryman, A., and Bell, E. (2007). Business research methods. New York: Oxford

University Press.

Cantarelli, C.C., (2009). Cost overruns in Dutch transportation infrastructure projects.

http://www.cvs-congres.nVcvspdfdocs Icvs09-156.pdf.

Page 40: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

98

Chen Ying (2010). “Sustainable Performance Criteria for Construction Method

Selection in Concrete Buildings”, journal of Automation in Construction,

vol 19, issue 2, pp. 235-244.

Creswell J. (1999). Qualitative Inquiry and Research Design: Choosing among Five

Traditions. Thousand Oaks, California:Sage 118–20.

Construction Industry Master Plan 2006-2015 (CIMP 2006-2015) (2006).

Construction Industry Development Board (CIDB) Malaysia, December

2006, Kuala Lumpur

Dejus T. (2013). Typical Solutions for the Construction Site Employees’ Safety.

Dėjus,T. (2009). Dangerous actions while installing building constructions and means

to decrease their undesirable influence.

Denzin, N.K. and Lincoln, Y.S. (2000). Handbook of Qualitative Research, 2nd

edition, Thousand Oaks, CA: Sage

Endut, I.R., (2008). Framework for Minimising Time Overruns Of Malaysian

Construction Projects. Unpublished PhD Thesis, School of Engineering

andBuilt Environment, Glasgow Caledonian University, UK.

Enshassi, A., Mohamed, S., Abu Mustafa, Z. and Mayer,P.E. (2007). Factors affecting

labour productivity in building projects in the gaza strip, Journal of Civil

Engineering and Management, Vol. XIII, No. 4, pp. 245-254.

Erickson, F., and Gutierrez, K. (2002). Culture, rigor, and science in educational

research. Educational Researcher, 31(8), 21–24.

Fah, C. (2006). A study on domestic subcontractor, www.efka.utm. retrieved on 15-

06- 2008

Fellows, R. and Liu, A. (2008). Research methods for construction, 3rd ed, Chichester,

WileyBlackwell.

FMI/CMAA (2004). Survey of Construction Industry Ethical Practices and Issues,

Management Consultant for the Construction Industry and Construction

Management Association of America, 1-18.

Glaser B. (1992). Strauss A. The Discovery of Grounded Theory. New York: Aldine

Hamzah, H. (2003).”Future Prospects for Project Management in the Malaysian

Construction.” Industry, Universiti Malaya, Kuala Lumpur.

Hashim, M., Li, M.C.Y., Yin, N.S, Heng., S.M, Yong, T.L. (2006). Factors

Influencing the Selection of Procurement Systems by Clients, Conference

on Construction Industry, Padang, Indonesia.

Page 41: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

99

Hoła. B, and Sawicki. M. (2014). Knowledge assets about construction enterprise

collected in the knowledge map, Technical Transactions, Krakow.

Hook. J. (2012). “Industry issues. PWC,” http://www.pwc.co.uk/engineering-

construction/issues/index.jhtml.

Huang, R.Y., Huang, C.T., Lin, H. and Ku, W.H., (2008). Factor analysis of interface

problems among construction parties a case study of MRT, Journal of

Marine

Science and Technology, Vol. 16, No. 1, pp. 52-63.

Imtiaz, G. and Ibrahim, A.R. (2005). Lean production system in project delivery: the

way forward for Malaysian construction industry, Proceedings of Kuala

Lumpur Quantity Surveyor Convention, Kuala Lumpur.

Kelly, J., Male, S., and Graham, D. (2015). Value management of construction

projects. Chichester, England: Wiley Blackwell.

Kuzel A. (1999). Sampling in qualitative inquiry. In: Crabtree B, Miller W, eds. Doing

Qualitative Research. 2nd edn. Thousand Oaks, California: Sage 33–45.

Khle, S. and Arditi, D. (2001), General contractors’ relationships with subcontractors:

a strategic asset, Construction Management and Economics, Vol. 19, pp.

541–549. Kish L. 1965, Survey sampling. New York, NY: Wiley.

Liaudanskiene, R. (2010). Modelling the application of workplace safety and health

act in Lithuania construction sector. Technological and economic

development of economy, Baltic Journal on Sustainability 16 (2) pp. 233–

253.

Marco A. Bragadina, and Kalle Kahkonenb (2015). Safety, space and structure quality

requirements in construction scheduling

Maxcy, S. J. (2003). Pragmatic threads in mixed methods research in the social

sciences: The search for multiple modes of inquiry and the end of the

philosophy of formalism. In A.Tashakkori & C. Teddlie (Eds.), Handbook

of mixed methods in social and behavioral research (pp. 51-89). Thousand

Oaks, CA: Sage.

Mayring, Ph. (2000). Qualitative Inhaltsanalyse. Grundlagen und Techniken (7th

edition, first edition 1983). Weinheim: Deutscher Studien Verlag.

Miller W, and Crabtree B. (2005). Clinical research. In: Denzin N, Lincoln Y, eds.

Handbook of Qualitative Research. 3rd edn. Thousand Oaks, California:

Sage 605–39.

Page 42: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

100

Mbachu, J.; Nkando, R. (2007). Factors constraining successful building project

implementation in South Africa, Construction Management and

Economics 25(1): 39–54.

Mbachu, J.; (2008). “Conceptual framework for the assessment of subcontractors'

eligibility and performance in the construction industry,” Construction

Management and Economics, vol. 26, pp. 471–484,

Muller, R., and Turner. R., (2007). Matching the project manager’s leadership style to

project type, International Journal of Project Management, Vol. 25, No. 1,

pp. 21–32.

Myers, D. (2013). Construction Economics: A new approach (3rd ed.). New York:

Routledg

Odeyinka, H. and Kelly, S. (2009). An evaluation of the budgetary reliability of bills

of quantities in building procurement. RICS COBRA Research

Conference, University of Cape Town, 435-446.

Okunlola, O. S. and Johnson, I. I. (2013). Determining the Performance of

Procurement Methods against Selection Criteria using Outranking -

Satisfying Methodology. Journal of Engineering, Project, and Production

Management, 3(2), 74-84.

Ogunlana, S., (2011). Factors and procedures in large construction projects in

Vietnam, Engineering, Construction and Architectural Management, Vol.

11 No.6.

Olawale, Y.A. and Sun.M, (2010). Cost and time control of construction projects:

Inhibiting factors and mitigating measures in practice. Comtr. Manage.

Econ., 28: 509-526.

Othman, M. R. (2012), Forging Main and Subcontractor Relationship for Successful

Projects. Available at:

http://rakan1.jkr.gov.my/csfj/editor/files/Files/Projek/Lessions

Learned/MAINandSUB_2.pdf (assessed January, 2017)

Pheng Y.H, Chen S. J., and Lu H. J.(2005). “Potential benefits for collaborating

formwork subcontractors based on co-operative game theory,” Building

and Environment, vol. 40, pp. 239–244,

Pheng L. S. and Chuan Q. T., (2006) "Environmental factors and workperformance

of project managers in the construction industry," International Journal of

Project Management, vol. 24, no. 1, pp.24–37.

Page 43: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

101

Phillips, D. C. (2004). Is mixed methods research an epistemological oxymoron?

Paper presented at the annual meeting of the American Educational

Research Association, San Diego, CA.

Polit D.F, and Hungler B.P (1999). Nursing Research: Principles and

Methods. Sixth edition. Philadelphia, Lippincott Williams and Wilkins.

Project Management Institute, Inc. (2013): A Guide to Project Management Body of

Knowledge, (PMBOK) Fifth Edition, Project Management Institute,

Inc.Pennsylvania 19073-3299

Rahman S.H. (2013), The Importance of Collaboration in Construction Industry from

Contractors’ Perspectives. International Conference on Innovation,

Management and Technology Research, Malaysia, 22 – 23 September,

2013

Rahman, H.A., Wang, C. & Yap, X.W. (2010). ‘How professional ethics impact

construction quality: Perception and evidence in a fast-developing

economy’, Scientific Research and Essays, 5 (23), 3742-3749

Robert A.Hinde. (1979). Towards understanding relationships. London: Academic, pp

xii + 367

Schaufelberger J (2009), Construction Business Management: Prentice-Hall.

Seng,N.W. and Yusof,A.M. (2006). “The success factors of design and build

procurement method: A literature visit”. Proceedings of the 6th Asia-

Pacific Structural Engineering and Construction Conference (APSEC

2006), 5 – 6 September 2006, Kuala Lumpur, Malaysia

Sharma.A (2006). "Innovation and new product introductions in emerging markets:

Strategic recommendations for the Indian market," Industrial Marketing

Management, vol. 35, no., pp. 373-382, 2006.

Silverman, D. (2001). Doing qualitative research: A practical handbook. Thousand

Oaks, CA: Sage.

Tai, S., Wang, Y., and Anumba, C. J. (2008). A survey on communications in large-

scale construction project in China. Engineering Construction and

Architecture Management.

Teo, E. A. L., Ling, F. Y. Y., Ong D. S. Y., (2005). Fostering safe work behaviour in

workers at construction sites. Engineering, Construction and Architectural

Management 12(4), pp. 410−422.

Page 44: IMPROVEMENT OF RELATIONSHIP BETWEEN MAIN …eprints.uthm.edu.my/9557/1/SYAHIDAH_LAGIMAN.pdfantara dua pihak adalah aplikasi kemahiran, integriti, kepercayaan, tanggungjawab, dan komunikasi

102

Thomas H.R and Flynn C. J (2011) . “Fundamental principles of subcontractor

management,” Practice Periodical on Structural Design and Construction,

vol. 16, no. 3, pp. 106–111,

Toor, S.R and Ogunlana, S. O. (2008). Critical COMs of success in large-scale

construction projects: Evidence from Thailand construction industry.

International Journal of Project Management, 26(4): 420–430.

Volkov A., Chelyshkov P., Sedov A (2013). Application of computer simulation to

ensure comprehensive security of buildings. Applied Mechanics and

Materials Vols. 409-410 (2013) pp 630-633 © Trans Tech Publications,

Switzerland doi:10.4028/www.scientific.net/AMM.409-410.630"

Wolcott, H.F. (2001). Writing Up Qualitative Research, 2nd edition, Newbury Park,

CA: Sage

Wong S.P, and Cheung S.O (2007). Structural equation model on trust and partnering

success. J Manage Eng 2005;21(2):70–80.