51
i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE GENERATION THROUGHOUT CONSTRUCTION PROJECT LIFE CYCLE NOR SOLEHAH BINTI MD AKHIR A thesis submitted in fulfillment of the requirement for the award of the Degree of Master of Civil Engineering Faculty of Civil and Environmental Engineering Universiti Tun Hussein Onn Malaysia APRIL 2015

i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

  • Upload
    others

  • View
    13

  • Download
    0

Embed Size (px)

Citation preview

Page 1: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

i

RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE

GENERATION THROUGHOUT CONSTRUCTION PROJECT LIFE CYCLE

NOR SOLEHAH BINTI MD AKHIR

A thesis submitted in

fulfillment of the requirement for the award of the

Degree of Master of Civil Engineering

Faculty of Civil and Environmental Engineering

Universiti Tun Hussein Onn Malaysia

APRIL 2015

Page 2: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

v

ABSTRACT

The construction industry has an adverse impact on the environment from the wastes

generated during construction work. The amount of wastes generated increases

yearly due to rapid economic growth worldwide which includes Malaysia. Due to

waste generation, one of the major issues faced is the increase of illegal dumpsites.

The illegal dumping may caused a risk to human health and environment. Thus, it

calls for serious measures to regulate wastes generation. The waste is generated due

to various factors throughout construction project life cycle (CPLC). For controlling

purpose, it is very important to identify the generation factors and also to determine

the level of risk from each factor. Hence, this study focuses on assessing the risk

level of factors causing wastes generation throughout CPLC. Besides, it also

proposes mitigation measures for the high risk factors. For assessing the risk level, a

total of 33 factors that causes construction wastes generation that have been

identified from literature review were considered. The assessment involved 15

experts who are experienced in handling construction projects. This investigation

adopted two rounds of Delphi method in determining level of occurrence and

severity of each factor in relation with different phases of CPLC. The experts were

required to fill out the questionnaire set and the analysis on the gathered data from

the questionnaire work was done using risk matrix. The result indicated that in the

construction phase, majority of the identified factors occurred in this phase are

critical due to having high risk level and most of them are categorised in Human

Resource/Manpower (HRM) group. It is followed by finishing phase, design phase,

and planning phase. However, in planning phase, the chances of wastes generation

are minimal with no high risk factors. In order to control the construction wastes

generation problem, mitigation measures for high risk factors were proposed. The

findings of this study can be a useful guide for the practitioners in controlling

construction wastes generation.

Page 3: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

vi

ABSTRAK

Industri pembinaan telah menyumbang kesan buruk terhadap persekitaran akibat

daripada penjanaan sisa semasa kerja pembinaan. Jumlah penjanaan sisa kian

meningkat setiap tahun disebabkan pertumbuhan ekonomi yang semakin pesat di

seluruh dunia termasuk di Malaysia. Hal ini menyebabkan jumlah tapak pelupusan

sampah secara haram semakin meningkat. Tapak pelupusan sampah yang berleluasa

boleh mendatangkan risiko kepada kesihatan manusia dan alam sekitar. Oleh yang

demikian, perhatian yang serius diperlukan bagi mengawal masalah ini. Penjanaan

sisa boleh berlaku disebabkan pelbagai faktor di sepanjang kitaran hayat projek

pembinaan (CPLC). Bagi tujuan pengawalan, ia adalah penting untuk mengenalpasti

faktor-faktor penyebab penjanaan sisa dan juga menentukan tahap risiko bagi setiap

faktor. Oleh itu, kajian ini fokus kepada menilai tahap risiko bagi faktor-faktor

penyebab penjanaan sisa di sepanjang CPLC. Di samping itu, kajian ini juga

mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang berisiko tinggi.

Untuk menilai tahap risiko, sebanyak 33 faktor penyebab penjanaan sisa pembinaan

yang telah dikenalpasti daripada kajian literatur dipertimbangkan. Penilaian ini

melibatkan 15 orang pakar yang berpengalaman dalam mengendalikan projek-projek

pembinaan. Dua pusingan kaedah Delphi digunakan bagi menentukan tahap berlaku

dan tahap impak setiap faktor bagi setiap fasa di sepanjang CPLC. Pakar-pakar

diminta untuk mengisi borang soal selidik dan analisis yang dilakukan ke atas data

yang diperolehi adalah dengan menggunakan matrik risiko. Keputusan mendapati

bahawa dalam fasa pembinaan, sebahagian besar faktor-faktor yang dikenal pasti

berlaku dalam fasa ini adalah kritikal kerana mempunyai tahap risiko yang tinggi dan

kebanyakan faktor yang berisiko tinggi adalah dari kategori Sumber Manusia/Tenaga

Kerja (HRM). Ia diikuti dengan fasa kemasan, fasa reka bentuk, dan fasa

perancangan. Walau bagaimanapun, dalam fasa perancangan kemungkinan

penjanaan sisa adalah minimum dan tiada faktor yang berisiko tinggi dalam fasa ini.

Page 4: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

vii

Dalam usaha untuk mengawal masalah penjanaan sisa pembinaan, langkah-langkah

mengatasi bagi faktor yang berisiko tinggi telah dicadangkan. Hasil kajian ini dapat

menjadi panduan kepada pihak industri dalam mengawal penjanaan sisa binaan.

Page 5: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

viii

CONTENTS

TITLE i

DECLARATION ii

DEDICATION iii

ACKNOWLEDGEMENT iv

ABSTRACT v

CONTENTS vii

LIST OF TABLES xi

LIST OF FIGURES xiii

LIST OF SYMBOLS AND ABBREVIATIONS xiv

LIST OF APPENDICES xv

CHAPTER 1: INTRODUCTION

1.1 Research Background 1

1.2 Problem Statement 2

1.3 Aim and Objectives 4

1.4 Scope of Study 4

1.5 Research Methodology 4

1.6 Thesis Organization 5

CHAPTER 2: LITERATURE REVIEW

2.1 Introduction 6

2.2 Risk Management in Construction Project 6

2.3 Construction Wastes 9

2.3.1 Definition 9

2.3.2 Construction Wastes Generated 11

2.3.3 Waste Management 13

2.3.4 Impacts of the Waste 17

Page 6: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

ix

2.4 Causative Factors of Construction Waste

Generation

19

2.5 Causative Factors in Construction Project

Life Cycle

25

2.5.1 Construction Project Life Cycle

(CPLC)

25

2.5.2 Incorporation of Causative Factors

in CPLC

28

2.6 Mitigation Measures of Construction

Wastes Generation

32

2.7 Summary 34

CHAPTER 3: METHODOLOGY

3.1 Introduction 35

3.2 Flow of the Research 35

3.3 Questionnaire Development 36

3.4 Data Collection 38

3.4.1 Pilot Study 38

3.4.2 The Delphi Method 38

3.5 Analysis Method 41

3.5.1 Reliability Test 41

3.5.2 Descriptive Analysis 41

3.5.3 Risk Matrix 42

CHAPTER 4: ANALYSIS AND DISCUSSION

4.1 Introduction 44

4.2 The Pilot Study Analysis 44

4.2.1 Experts‟ Demography 45

4.2.2 Reliability Test 45

4.2.3 Analysis of Factors 46

Page 7: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

x

4.3 Analysis of Delphi Survey 52

4.3.1 Respondents‟ Demography 52

4.3.2 Identification of Risk Level 55

4.3.3 Agreeability on Identified Risk

Level

60

4.4 Proposed Mitigations for Risk Factor 65

4.5 Summary 68

CHAPTER 5: CONCLUSION AND RECOMMENDATION

5.1 Introduction 70

5.2 Significant Findings 70

5.3 Limitations of the Study 74

5.4 Recommendations for Future Work 75

REFERENCES 76

APPENDIX 91

Page 8: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

xi

LIST OF TABLES

2.1 Wastes definition 11

2.2 Construction wastes generated 13

2.3 Mapping of impact of construction waste 19

2.4 Mapping of factors contributing construction

wastes generation

23

2.5 Comparison between proposed CPLC with others

CPLC based on literature review

26

2.6 Factors of construction wastes according to CPLC 29

3.1 Scale represents the probability of occurrence and

level of severity

37

3.2 Applied Delphi method by researchers in

construction research

39

3.3 Suggested Delphi method for this study 41

4.1 Expert‟s demography in pilot study 45

4.2 Reliability test results 46

4.3 AI value of factors in each phase 47

4.4 Significant factors in each phase 48

4.5 Risk level of causative factor in the planning

phase

56

4.6 Risk level of causative factors in the design phase 56

4.7 Risk level of causative factors in the construction

phase

58

4.8 Risk level of causative factors in the finishing

phase

59

Page 9: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

xii

4.9 Percentage of agreeability for the risk level of

causative factors in the planning phase and the

design phase

61

4.10 Percentage of agreeability for the risk level of

causative factors in the construction phase

62

4.11 Percentage of agreeability from panels for the risk

level of causative factors in the finishing phase

64

4.12 Proposed mitigation measures of high risk factors 65

Page 10: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

xiii

LIST OF FIGURES

2.1 Six stage of waste management hierarchy 14

2.2 Construction project life cycle diagram 27

3.1 Research methodology flowchart 36

3.2 Process of the Delphi method 40

3.3 Risk matrix 43

4.1 Highest educational qualification of

respondents

51

4.2 Respondents‟ working experiences 53

4.3 Respondents‟ position 53

4.4 Type of organization of respondents 54

4.5 Category of organization of respondents 54

4.6 Highest contract amount of projects that

respondents have dealt with

55

4.7 Risk level of causative factor in the planning

phase

56

4.8 Risk level of causative factors in the design

phase

57

4.9 Risk level of causative factors in the

construction phase

59

4.10 Risk level of causative factors in the finishing

phase

60

5.1 Factors causing construction waste generation 71

5.2 Risk level of the factors throughout CPLC 73

Page 11: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

xiv

LIST OF SYMBOLS AND ABBREVIATIONS

AI - Average Index

CPLC - Construction Project Life Cycle

CWDCS - Construction Wastes Disposal Charging Scheme

C&D - Construction and Demolition

DEL - Delivery/Procurement

EQP - Equipments

EXT - External/Unpredictable

GHG - Green House Gas

HRM - Human Resource/Manpower

IBS - Industrialized Building System

ICT - Information, Communication, and Technology

MAT - Material

PCM - Project and Contract Management

RIBA - Royal Institute of British Architects

SPSS - Statistical Package for the Social Sciences

WGR - Wastes Generation Rate

WMP - Wastes Management Plan

- Cronbach‟s Alpha Coefficient

Page 12: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

xv

LIST OF APPENDICES

A Questionnaire Form: Pilot Study 91

B Questionnaire Form: Delphi Round 1 94

C Questionnaire Form: Delphi Round 2 97

D Description of the Factors 99

Page 13: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

CHAPTER 1

INTRODUCTION

1.1 Research Background

Construction is an imperative industry that plays a vital role in the socio-economic

growth of a country. It provides necessary infrastructure and physical structure for

activities such as commerce, services, and utilities (Khan, Liew, & Ghazali, 2014).

Besides that, it also generates employment opportunities and enhances the nation‟s

economy by creating foreign and local investment opportunities (Wibiwo, 2003).

However, the industry is facing the problem of construction wastes generation. As

reported by Kartam et al. (2004), based on statistics and assumptions, a total of

Construction and Demolition (C&D) wastes production was estimated to be 1.6

million ton/year. According to Ferguson et al. (1995), over 50% of the wastes in a

typical United Kingdom landfill is contributed by construction wastes. Bossink &

Brouwers (1996) indicated that9% of the totally purchased materials ended up as

wastes. Furthermore, Masudi et al. (2011) stated that wastage level for major

materials in some projects in Malaysia may reach up to 10%.

This generation of wastes has negative impact to the environment, cost,

productivity, time, social, and economy of the industry (Kozlovská & Spišáková,

2013; Marzouk & Azab, 2014; Osmani, 2012; Wang, Kang, & Tam, 2008). In

addition, production of wastes may weaken the efficiency, effectiveness, value, and

profitability of construction activities (Augustine, 2011). Thus, the risk of generation

of construction wastes needs to be proactively managed.

Page 14: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

2

There are various factors that contribute to generation of construction wastes.

These factors pose different levels of risk in wastes generation. Various researchers

have identified factors that contribute to wastes generation. As an example: A study

conducted in Sri Lanka revealed that the domestic construction industry workforce is

ignorant of the flow of activities that generated wastes (Senaratne & Wijesiri, 2008).

In Malaysia, it was found that there were five significant factors that caused

generation of construction wastes in this country. The factors are poor site

management or supervision, lack of experience, inadequate planning and scheduling,

mistakes and errors in design, and mistakes during construction (Nagapan, Rahman,

& Asmi, 2012a). In addition, contractors and consultants agreed that three most

important factors that contribute to generation of material wastes at construction site

are rework contrary to drawings and specification, design changes and revision, and

wastes from uneconomical shapes (Adeweyu & Otali, 2013).

A number of study highlighted that construction wastes are effectively

generated during the whole Construction Project Life Cycle (CPLC) from start until

completion of construction work (Kozlovská & Spišáková, 2013; Osmani, Glass, &

Price, 2008). It may be generated during planning, design, procurement, and

construction phase (Bossink & Brouwers, 1996; Ekanayake & Ofori, 2004; Wahab &

Lawal, 2011). While, several studies highlighted that construction wastes is

commonly generated during design and construction phase (Osmani, Glass, & Price,

2006; Panos & Danai, 2012).

Therefore, it can be concluded that construction wastes may be generated by

various factors and it may occur in the whole of CPLC. It also contributes to a lot of

negative impacts either to the project, environment or life. Thus, reducing wastes at

the source is the most effective measure in wastes management (Masudi et al., 2011).

By identifying the risk level of the factors and proposing the mitigations of the risky

factors, it may help the practitioners to figure out the best way to control this

problem.

1.2 Problem Statement

Production of construction wastes is directly related with the increasing demand of

infrastructure projects, residential development projects, and other facilities which

are required to improve the level of Malaysians‟ living conditions (Begum, Satari, &

Page 15: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

3

Pereira, 2010; Nasaruddin & Ravana, 2008). Out of these projects, the construction

of residential building contributes the largest amount of construction wastes (Begum

& Pereira, 2011; Foo et al., 2013).

According to Oh (2014) in The Star daily publication in March 2014, Solid

Wastes Management and Public Cleansing Corporation highlighted that in 2007,

Kuala Lumpur generated 1.04 million metric tonnes of construction wastes per year

and this amount is expected to increase to 1.34 million metric tonnes a year by 2020.

However, these wastes were not properly handled by the construction parties

involved. Research studies have indicated that dumping of construction wastes in

landfill is a common practice in Malaysia (Foo et al., 2013; Nagapan et al., 2012a).In

2007, a study conducted by Rahmat & Ibrahim (2007) showed that 42% of the

wastes were dumped illegally in the district of Johor Bahru Tengah, Johor. The study

also found 46 illegal dumping sites in the district and most of them were located near

the road side. A study in the Klang Valley found only 20% of C&D wastes were

disposed at legal landfills while others were disposed at illegal landfills or private

lands (Begum & Pereira, 2011). There are also a number of contractors that disposed

material wastes through open burning especially timber and packaging wastes, and

also by burying concrete wastes (Masudi et al., 2011).

The wastes then pose a threat to the environment and society if they are not

handled properly. Thus, it is important to control the source of construction wastes

generation. Before it can be controlled, it is vital to identify the factors that

contribute to wastes generation. Previous studies had identified factors that caused

construction wastes generation (Ikau, Tawie, & Joseph, 2013; Masudi et al., 2011;

Nagapan, Rahman, & Asmi, 2012b). However, not much emphasis was given in

assessing the relative risk level of these factors towards construction wastes

generation, which is very important for proper planning and development of

strategies in controlling the factors. This has motivated the author to conduct this

research in identifying the risk level of various causative factors that occurs in CPLC

phases and propose mitigations of risky factors, which can serve as a useful guide for

the practitioners in controlling the construction wastes generation.

Page 16: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

4

1.3 Aim and Objectives

The aim of this research is to assess the risk level of factors causing construction

wastes generation throughout CPLC. In order to achieve this aim, three objectives

have been established namely:

1) Identifying major factors causing construction wastes along the CPLC.

2) Determining the risk level of factor causing construction wastes along the

CPLC.

3) Proposing mitigation of the risky factors.

1.4 Scope of Study

The scope of this research is limited to construction-related companies in Peninsular

Malaysia. Data collection involves questionnaire survey using the Delphi method.

The survey is start conducted in the early of 2014. The targeted respondents are the

clients, consultants, and contractors whom are registered with CIDB between Grade

5 and 7. Respondents are selected among those who have more than ten years of

working experience in the construction industry. Construction wastes are limited to

material wastes only.

1.5 Research Methodology

This study is carried out based on the qualitative and quantitative mode of research.

It involves a comprehensive literature review from past researches to identify the

factors causing construction wastes generation. Based on that, a questionnaire is

developed to determine the factors occurrence and severity with respect to the

various phases of a construction project. The investigation for the developed

questionnaire is carried out using the Delphi method to assess the level of occurrence

and severity of the factors causing wastes generation for the construction industry in

Malaysia. The data are then analyzed using the average index and risk matrix to

identify the risk level of each factor. Mitigations of the risky factors are proposed

based on literature review.

Page 17: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

5

1.6 Thesis Organization

This thesis is divided into five chapters as follows:

Chapter 1: This chapter describes the need of this study. It contains study

background, problem statements, objectives, scope of study, research methodology,

and thesis organization.

Chapter 2: This chapter elaborates on related literature through the published

research work. It includes the definition, wastes generation scenarios, handling the

wastes, and factors causing construction wastes generation. Besides that, the phases

in CPLC are discussed.

Chapter 3: This chapter describes how this research is carried out. It explains

the technique of data collection and the way to analyze them.

Chapter 4: The survey results will be illustrated in this chapter. It includes the

factors of wastes generation throughout CPLC, level of occurrence, severity, and risk

of the factors causing generation construction wastes throughout the CPLC. At the

end of this chapter, the mitigation measures of high risk factors are presented.

Chapter 5: This chapter presents the conclusion of the study. It also presents

some recommendations for future study and limitations that arise while this study

was conducted.

Page 18: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

CHAPTER 2

LITERATURE REVIEW

2.1 Introduction

This chapter provides literature reviews that are related to this study. It is to

gain an overview of the current study and to provide a theoretical basis in refining

the research methodology and also the analysis approach for the current work. In this

chapter, risk management in construction projects, the definitions of construction

wastes, issues related to wastes generation, wastes management, impacts, and factors

causing construction wastes generations are reviewed. In addition, the concept of

four phases of CPLC is also discussed.

2.2 Risk Management in Construction Project

Project success can be defined by fulfilling the project objectives on the cost, time

and quality. However, to achieve project success, it is subjected to various risks due

to the unique features of construction activities, such as long period, complicated

processes, abominable environment, financial intensity, and dynamic organizational

structures (Zou, Zhang, & Wang, 2007; Akintoye & MacLeod, 1997). In addition,

Husin, Ismail, & Memon (2013) stated that the construction industry is always faced

with chronic problems such as time overrun, cost overrun, wastes generation,

imposing negative impacts to the environment, and excessive resource consumption.

Thus, risks in construction project have to be given serious attention so that the

project is successfully accomplished.

Page 19: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

7

Risk can be defined as a combination of the probability and the severity, and

also the exposure of all hazards in the construction activity (Jannadi & Almishari,

2003). In managing risk, a systematic way is required to look into the areas of risk

and consciously determining how to treat the risk. It is a management tool that aims

at identifying sources of risk and uncertainty, determining their impact, and

developing appropriate management responses (Uher, 2003). A process of risk

management has been divided into three consecutive stages as stated by Perera et al.

(2014) and KarimiAzari et al. (2011) which are;

i. risk identification,

ii. risk analysis and

iii. risk response, where risk response has been further divided into four actions,

i.e. retention, reduction, transfer, and avoidance

For risk identification and risk analysis, it specifies and predicts the likelihood and

adverse impacts of risks; whereas for risk response, it is concerns on the measures

taken by project management to reduce the probability and effects of risks (Perera et

al., 2014).

Risk identification is a significant step in the risk management process, as it

attempts to identify the various risks affecting a construction project. In this stage,

risk factors that influence the project are detected, classified and documented (Gohar,

Khandazi & Farmani, 2012). Source of the knowledge for risk identification phase is

vital to the success of this stage and should elicit the viewpoints of experts with

extensive experience in directly dealing with similar construction projects

(Ruthankoon & Ogunlana, 2003). In this study, risk identification was accomplished

through literature review and pilot study. A total of 33 factors causing construction

waste generation were identified through literature review. Then, the identified

factors were classified into four phase of CPLC through pilot study. From that, it

presented one factor in planning phase, five factors in design phase, 32 factors in

construction phase and nine factors in finishing phase.

Risk analysis is important as it estimate risk by identifying the undesired

event, the likelihood of occurrence of the unwanted event, and the consequence of

such event. It involves measures which produce the estimation of significance level

of the individual risk factors to the project, so as to produce the estimation of the risk

of the potential factors to project success (KarimiAzari et al., 2011).

Page 20: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

8

There are two approaches used in risk analysis, which are quantitative risk analysis

and qualitative risk analysis (Ehsan et al., 2010). Quantitative analysis involves more

sophisticated techniques and methods to investigate and analyze construction project

risks. Additionally, this analysis represents risks in mathematical form to quantify

them in terms of performance in quality, time and cost (Morledge, Smith, &

Kashiwagi, 2006). Quantitative risk analysis attempts to estimate the frequency of

risks and the magnitude of their consequences by different methods such as the

sensitivity analysis, decision tree analysis, the cost risk analysis, and Monte Carlo

simulation (Mahendra, Pitroda, & Bhavsar, 2013; Ehsan et al., 2010; Modarres,

2006)

Qualitative risk analysis assesses the impact and likelihood of the identified

risks and develops prioritized lists of the risks for further analysis or direct

mitigation. A common qualitative approach is the precedence diagramming method,

which uses ordinal numbers to determine priorities and outcomes. Another way of

employing qualitative approach is to make a list of the processes of a project in

descending order, calculate the risks associated with each process and list the

controls that may exist for each risk (Ehsan et al., 2010). A risk matrix (or a

probability/impact matrix) also is a tool commonly used in qualitative risk analysis

(Mahendra et al., 2013; Zhou & Leung, 2012; Modarres, 2006). It is a table that

contains several regions that indicate risk level based on the scale of probability and

scale of impact or severity. Risks are qualitatively assessed according to the region it

mapped. In this study, the risk levels for the factors that have been identified were

assessed by using risk matrix which has been explained in section 3.5.3.

Once the risks of a project have been identified and analyzed, appropriate risk

response strategies must be adopted to cope with the risks in the project

implementation. The treatment measures on each risk are based on the nature and

impact of the risk (Zou et al., 2007). As mentioned by Mahendra et al. (2013), risk

response can be done by several methods including risk avoidance, risk transfer, risk

mitigation/reduction, risk exploit, risk share, risk enhance, risk acceptance, and

contingency plan. In this study, to response the risk, mitigation measures for the

risky factor were proposed. The mitigation measure may reduce the probability

and/or impact of an adverse risk event to an acceptable level of risk. Taking early

action to reduce the probability and/or impact of a risk is often more effective than

attempting to repair the damage after the risk has passed (Mahendra et al., 2013).

Page 21: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

9

Basically, eliminating construction risks seems hardly doable (Siew & Abdul-

Rahman, 2013). However, risk management should be applied into any construction

project at the initial stage of the project to get maximum benefit in managing the risk.

This is because, the awareness of the risks and appropriate strategies for dealing with

the risks are imperative and contributes to the success of the projects (Zou et al.,

2007).

2.3 Construction Wastes

There are a lot of researches in construction wastes generation that have been carried

out in various countries. It includes the types of construction wastes, factors causing

construction wastes, the impacts, and the way of handling the wastes. This subtopic

comprises the definition of construction wastes, construction wastes generation in

other countries, wastes management, and the impact of the wastes.

2.3.1 Definition

Construction wastes have been defined in various ways. Skoyles & Skoyles (1987)

stated that construction wastes is „a material which needed to be transported

elsewhere from the construction site or used on the site itself other than the intended

purpose of the project due to damage, excess or non-use or which cannot be used due

to non-compliance with the specifications, or which is a by-product of the

construction process‟. In Hong Kong, the definition of construction wastes was

established by Hong Kong Polytechnic (1993) as „by-product generated and removed

from construction, renovation, and demolition work places or sites of building and

civil engineering structures‟. In another research, construction wastes was defined as

„any material apart from earth materials, which needed to be transported elsewhere

from the construction site or used on the site itself other than the intended specific

purpose of the project due to damage, excess or non-use or which cannot be used due

to non-compliance with the specifications, or which is a by-product of the

construction process‟ (Ekanayake & Ofori, 2004). Based on the Solid Wastes and

Public Cleaning Management Act 2007 (Act 672), construction solid wastes are „any

type of solid wastes that is produced from any construction activities or demolition or

including accomplishment, arrangement, renovation or modification‟.

Page 22: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

10

According to Poon et al. (2013), construction waste is a mixture of inert and non-

inert materials arising from various construction activities like excavation,

demolition, construction, renovation, and roadwork. Based on all highlighted

definitions, it should be understood that construction wastes is in the form of

materials losses while the construction project was being carried out.

However, according to new production philosophy, Koskela (1992) stated

that construction wastes „includes both the incidence of material losses and the

execution of unnecessary work, which generates additional costs but does not add

value to the product. This was then was supported by Formoso, Isatto, & Hirota

(1999) whom defined construction wastes as „any inefficiency that results in the use

of equipment, materials, labour, or capital in larger quantities than those considered

as necessary in the production of a building‟. This means that, besides material

wastes; time, cost, and process wastes also can be described as wastes. It can be

generated due to any inefficiency of activities such as waiting time, over production,

and processing but do not add any value to the project. However, this research only

focuses on construction material wastes. Although construction wastes generation

contributes to high economic losses than material wastes (Formoso et al., 1999), the

most important thing that we have to be concerned with is the adverse impact on the

environment (Masudi et al., 2011) which is contributed by material wastes. Table 2.1

summarizes the various definitions given for construction waste.

Page 23: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

11

Table 2.1: Wastes definition

No. References Wastes definition

1 Skoyles & Skoyles

(1987)

A material which needs to be transported elsewhere from the

construction site or used on the site itself other than the intended purpose

of the project due to damage, excess or non-use or which cannot be used

due to non-compliance with the specifications, or which is a by-product

of the construction process.

2 Koskela (1992) Includes both the incidence of material losses and the execution of

unnecessary work, which generate additional costs but does not add

value to the product.

3 Hong Kong

Polytechnic (1993)

By-product generated and removed from construction, renovation, and

demolition work place or sites of building and civil engineering

structures.

4 Formoso et al.

(1999)

Any inefficiency that results in the use of equipment, materials, labour,

or capital in larger quantities than those considered as necessary in the

production of a building.

5 Ekanayake & Ofori

(2004).

Any material apart from earth materials, which needed to be transported

elsewhere from the construction site or used on the site itself other than

the intended specific purpose of the project due to damage, excess or

non-use or which cannot be used due to non-compliance with the

specifications, or which is a by-product of the construction process.

6 Solid Wastes and

Public Cleaning

Management Act

2007 (Act 672)

(2007)

Any type of solid waste that is produced from any construction activities

or demolition or including accomplishment, arrangement, renovation or

modification.

7 Poon et al. (2013) Construction waste is a mixture of inert and noninert materials arising

from various construction activities like excavation, demolition,

construction, renovation, and roadwork.

2.3.2 Construction Wastes Generated

The construction wastes become serious environmental problems in many countries

and are becoming more critical recently. Through literature review, issues related to

the construction wastes generation in various countries are discussed below.

Malaysia: Rahmat & Ibrahim (2007) conducted a study in the district of Johor Bharu

Tengah, Johor and reported that a total of 46 illegal dumping were found in the

investigation, with most of them discovered near the road side corridor. Forty two

percent of the wastes are actually wastes from construction. A research conducted by

Begum & Pereira (2011) found that in the Klang Valley the majority of C&D wastes

were dumped into private land or illegal dumpsites while only 20% of them were

actually disposed in legal landfills. The results also showed that 88% of the C&D

wastes generated is from residential buildings while 9% from commercial, and 3%

from government buildings, all resulting from increased demand for housing and

commercial buildings. The largest components of C&D wastes are concrete,

Page 24: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

12

aggregate, and rubbles followed by soil, wood, metals, and roofing materials. In

2013, a research that was conducted in three construction sites found that timber

wastes was the dominant waste produced, followed by bricks, packaging wastes, and

concrete (Nagapan et al., 2013).

While, in another research, the total wastes generated at two housing project

sites was 154.31 m3 and the major wastes consists of timber (49%) (Foo et al., 2013).

Besides that, Masudi et al. (2011) conducted a study intending to quantify the

wastage level of several types of material wastes such as timber, concrete,

reinforcement bar, tiles, screeds, and plaster. The results showed that the wastage

level for major material is up to 10%. They also concluded that awareness among

construction players in Malaysia on wastes minimization is still lacking.

Thailand: As reported by a research in 2009, the construction industry generated an

average of 1.1 million tonnes of construction wastes per year between 2002 – 2005

(Kofoworola & Gheewala, 2009).

Indonesia: A research was conducted to determine quantities of construction wastes

material. The study indicated that brick and sand wastes were the most wastes on the

site which is 12.51% and 11.39% respectively. The cost modelling showed that the

range of material wastes cost was between 3.33% to 4.67% of the total material cost

(Intan, Alifen, & Arijanto, 2005).

Kuwait: Kartam et al. (2004) conducted a research to study the environmental

management of C&D wastes. The results indicated that C&D wastes in Kuwait

consist of concrete (30%), bricks (30%), sand (25%), wood (8%), steel (5%), and

others (2%). According to statistics and assumptions, the total C&D wastes

production was estimated to be 1.6 million ton/year (excluding solely earth and

sand).

China: In Shenzhen, a research was carried out to investigate the source of

construction wastes generation. According to the survey results, concrete, cement,

brick, timber, tile, steel, and aluminium wastes are the main wastes source produced

at construction sites (Wang et al., 2008). Another research found that Wastes

Generation Rate (WGR) ranged from 3.275 to 8.791 kg/m2 while miscellaneous

Page 25: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

13

wastes, timber for formwork and false work, and concrete were the three largest

components amongst the generated wastes (Lu et al., 2011).

Based on literature review, it can be seen that construction waste generation

problem not only occur in Malaysia but also in other countries. It also can be

concluded that construction waste is commonly contributed by timber, brick,

concrete, sand, steel, and others, with majority of the wastes disposed into landfills.

However, the amount of waste generated varies in each country. Table 2.2

summarizes the construction waste generated for the countries mentioned above.

Table 2.2: Construction wastes generated

Origin Reference Findings

Malaysia Rahmat & Ibrahim,

2007 A total of 46 sites of illegal dumping were found in the District

of Johor Bahru Tengah, Johor.

Most of illegal dumping sites were located near the road side

corridor.

42% of the wastes originated from the construction industry.

Begum & Pereira,

2011 Only 20% of C&D wastes were disposed in legal landsites

88% C&D wastes were generated from residential buildings,

9% from commercial buildings, and 3% from government

buildings.

Masudi et al., 2011 Wastage level for major material is up to 10%.

Awareness among construction players in Malaysia on wastes

minimization is still lacking.

Foo et al., 2013 Total waste generated at two sites was 154.31 m3 and 49%

were timber wastes.

Thailand Kofoworola &

Gheewala, 2009 1.1 million tonnes of construction wastes were generated per

year between2002-2005.

Indonesia Intan et al., 2005 Brick and sand were the dominant wastes (12.51% and

11.39%)

Wastes generated in the range of 3.33% to 4.67% of the total

material cost.

Kuwait Kartam et al., 2004 Wastes in Kuwait consist of concrete (30%), bricks (30%),

sand (25%), wood (8%), steel (5%), and others (2%).

1.6 million ton/year construction wastes generated.

China Wang et al., 2008 Concrete, cement, brick, timber, tile, steel, and aluminium

wastes are the main wastes sources produced at construction

sites.

Lu et al., 2011 Wastes Generation Rate (WGR) ranged from 3.275 to 8.791

kg/m2.

2.3.3 Waste Management

Construction waste issues are one of the prevailing global problems that require

serious attention. The implementation of construction waste management hierarchy

can help to handle and manage construction waste generation. Nagapan et al. (2012d)

Page 26: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

14

suggested that this adoption can be integrated into a six stage of waste management

hierarchy which includes prevention, minimization, reuse, recycling, recovery, and

disposal, as shown in Figure 2.1.

Figure 2.1: Six stage of waste management hierarchy

(Adapted from Nagapan et al., 2012d)

Figure 2.1 shows the six stages of waste management hierarchy that can be

adopted to handle the wastes. The stage of the waste management option is ranked

based on what is best for the environment. The most preferred way is by preventing

or reducing the generation of waste. However, if the waste generation cannot be

prevented or reduced, it is recommended to recycle, reuse or recover the wastes as

much as possible. But, if wastes are still being produced, then the last option is by

disposing the wastes. However, the disposal method is not a preferred option because

the role of waste management is to reduce the amount of waste that is discharged into

the environment (Nagapan et al., 2012d). Below is the description for each stage of

waste management hierarchy.

Prevention& Minimization: It refers to avoid or reduce producing waste, which is

the best way to reduce the impact of waste on the environment (Egan, 1998;

Ekanayake & Ofori, 2004; Esin & Cosgun, 2007) and for better economic savings

(Al-Hajj & Hamani, 2011). Besides that, avoiding or minimizing from the source in

construction project may reduce the amount of waste generation (Kozlovská &

Minimization

Reuse

Recycling

Recovery

Disposal

Prevention

Most preferable

Page 27: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

15

Spišáková, 2013), raw material usage, and lessen transportation works (Nagapan et

al., 2012d).

In order to prevent or minimize the generation of construction waste, a proper

construction waste management approach should be planned before site operations

begin. As stated by Lu & Tam (2013), contractors have to prepare a waste

management plan as part of the overall environmental management plan, and set out

waste reduction targets and programs. They also are advised to set up a good house-

keeping practice and a waste management monitoring and audit program, throughout

the whole construction processes (Lu & Tam, 2013). Al Hajj & Hamani (2011) have

suggested four measures for efficient prevention of construction waste on site which

are logistics management, supply chain management, modern construction method,

and training and incentivizing.

In China, the government has taken various actions to tackle the issue of the

increasing amount of construction waste generation. These actions include the

alteration of the Waste Disposal Ordinance, issuance of a policy paper for a

comprehensive 10 year plan to reduce construction waste, launching of a green

manager scheme on construction sites, promulgation of a waste reduction framework

plan, issuance of a practice note promoting the use of recycled aggregate,

implementation of the policy of Waste Management Plan (WMP) at construction

sites, commissioning of a pilot concrete recycling plant, and introduction of a

charging scheme for the disposal of construction waste (Esin & Cosgun, 2007).In

Malaysia, the implementation of prefabrication and Industrialized Building System

(IBS) method in the construction industry was encouraged by the government as a

solution to reduce the amount of waste generation (Abdullah & Malik, 2012). The

adoption of this method can reduce construction waste generated by as much as 41%

to 50%, which is a large amount of reduction (Hassan et al., 2012; Begum, et al.,

2010). Though preventing waste production on site is not possible, we can, however,

reduce its amount.

Reuse: It can be defined as using the same material in construction more than once,

including using the material again for the same function (e.g., timber formwork in

construction). Various countries use this approach to reduce the amount of waste

generated before it gets disposed in landfill. In China, the government implements

the Construction Waste Disposal Charging Scheme (CWDCS) to encourage

Page 28: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

16

contractors to recycle and reuse their construction waste and this scheme has shown a

significant reduction even after three years of implementation (Yu et al., 2013).

In Germany, a technology of drying distillation and burning is used to handle

waste which will separate every kind of material that can be reprocessed cleanly

from waste and reused again (Wang & Li, 2011).Besides that, some materials such as

timber can be reused in the site for several times to avoid the cost of collection and

disposal, and the extra cost of virgin material. Broken bricks and concrete can still be

reused as a sub-grade of access road to the construction site (Nagapan et al., 2012d).

This approach could help to reduce construction waste at site before it gets disposed.

Recycling: Recycling means separating, collecting, processing, marketing and

ultimately using a material that would otherwise have been thrown away (Yeheyis et

al., 2012). A study has shown that recycling reduces the amount of waste, Green

House Gas (GHG) emission, saves energy, and reduces the use of virgin raw material

(Pimenteira et al., 2005). Various countries have practised recycling very well in

order to reduce the amount of waste. In Denmark, Estonia, Germany, Ireland, and the

Netherlands the percentage of recycling rate is more than 80% while in France and

Luxembourg the recycling rate percentage is between 40% to 50% (Calvo et al.,

2014).

In Finland, the recycling rate of the C&D wasteincreasedto70% as the

government imposed garbage tax to 30 euro per tonne in 2005 and planned on

increasing the tax further more recently (Yunpeng, 2011). In Holland, the

government had set up a series of laws of restricting dumping of waste and quality-

control system of forcing recycling. The government also motivated contractors to

recycle their waste by granting reward bonus if they used recycled materials in their

project. However, the recycling rate of construction waste in Malaysia is still low at

10.5% (Solid Waste and Public Cleansing Management Corporation (PPSPPA),

2013), due to the lack of awareness among construction players (Goh et al., 2013;

Masudi et al., 2011).

Recovery: It can be defined as the removal of materials or components from the

waste stream in a manner to keeps in original form for reuse in the similar form as it

was produced. In Germany, the incineration technology has assisted the recovery of

metal waste. This recovery tool will cut off until two to three kilograms of harmful

Page 29: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

17

heavy metal in one tonne wastes after distillation and burning process. Thus, this

method resolves the problem effectively from taking up space at the landfill.

Moreover, the gas produced during the handling process is used to generate

electricity.

Disposal: The most common disposal of material waste is by landfill (Nagapan et al.,

2012d). This is the final option used for construction waste disposal. However, it is

advised to dispose properly at a landfill to alleviate pollution to the surrounding. In

Malaysia, the practice of construction waste management is still low as compared to

other countries. Most of the waste ends up at landfills. It can be seen in Malaysia that

about 261 to 291 landfill sites are in existence (Hamatschek, Tee, & Faulstich, 2010).

Also in Thailand, most of construction waste are buried on site, disposed at landfill

or illegally dumped. Reuse and recycle are less frequently practiced since the

processing cost exceeds the cost of buying raw material (Manowong, 2012).

As a conclusion, it is seen that a waste management hierarchy offer a

systematic and efficient waste management strategy which would minimize the

generation of waste at different level. A waste management hierarchy should be

applied in any construction project. The construction parties involved should try to

prevent, reduce, reuse, and recycle the construction waste before it dispose to

landfills. The approach will helps to reduce negative issues related to environment,

social and economy.

2.3.4 Impacts of the Waste

Some amount of the material used in the construction project generally will end up as

waste (Hasan et al., 2013). Various researches have revealed that the impacts of

construction waste generation are not only on the environment, but also on the

economic and social aspects (Marzouk & Azab, 2014; Nagapan et al., 2012d; Yuan,

2012). Wastes are usually disposed in landfills and this disposal significantly impacts

the environment. There are many types of environmental impacts associated with

construction waste generation, including the pollution of air, water, noise, and land;

ecology damage; loss of raw materials; and increased illegal dumping.

Page 30: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

18

According to Marzouk & Azab (2014), the environmental problems due to

waste generation include diminishing landfill space due to incremental quantities of

these disposed wastes in it, depleted building materials, increase in contamination

from landfills that leads to serious negative health effects, damage to the

environment, and increase in energy consumption for transportation, and

manufacturing new materials instead of those materials dumped and which require

energy production. Another study revealed that the effects of construction waste on

the environment are clear (Spies, 2009). It can cause water and soil pollution, air

pollution, climate change, and adverse effects on flora and fauna. As mentioned by

Laquatra (2004), the negative effects of construction waste on the environment

includes landfill space becoming limited, faulty landfills polluting the air, earth, and

water, and increase in illegal dumping of C&D waste. This shows that the majority

of researchers have a consensus that the significant impact on the environment due to

improper waste disposal is environmental pollution.

Production of waste can also affect the cost of project. As much as wastes are

generated, the more the cost is needed to dispose them. According to Marzouk &

Azab (2014), due to the production of construction waste, large amount of money is

needed to be spent for dumping wastes in landfills, and for controlling the effect of

dumping to the environment. Sometimes, the contractors would have to pay twice for

the material cost and landfill fees. Then, they would pass the cost to homebuyers in

the form of increased house price (Laquatra, 2004). On the other hand, as

construction waste impacts the environment, it can also spoil the public health. Air

pollution may cause various respiratory diseases such as asthma, heart cancer, and

lung cancer especially to the children and senior citizen (Marzouk & Azab, 2014).

Table 2.3 shows the mapping of impacts of construction waste generation which is

constructed based on literature review.

Page 31: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

19

Table 2.3: Mapping of impact of construction waste

Category Impact of Construction Waste

Reference

Fre

qu

ency

1 2 3 4 5

Na

ga

pa

n e

t a

l. (

201

2)

Ma

rzo

uk

& A

za

b (

20

14

)

La

qu

atr

a (

20

04

)

Sp

ies

(20

09

)

Lu

et

al.

(2

011

)

Environment

Environmental pollutions / / / / / 5

Shortage of land / / /

3

Increasing of illegal dumping /

/

2

Severe ecological damage / /

/

3

Increase contaminant in landfill

/

1

Climate change

/

1

Loss of raw materials

/

1

Economic

Increase in transportation charges of CW /

/

2

Increase cost of project /

/

2

Increase in landfill fee /

1

Increase price of raw materials /

1

Delay of projects /

1

Economic losses / /

2

Social Dangerous to the people's health / /

2

Negative effect to the society /

1

2.4 Causative Factors of Construction Waste Generation

As waste impairs the efficiency, effectiveness, value, and profitability of construction

activities, there is a need to identify the causes of wastes generation and to control

them within reasonable limits. Wastes in construction projects can occur due to many

reasons. The comprehensive literature reviews on causative risk factors regarding

construction wastes generation are carried out to understand these issues.

Malaysia: According to Hassan et al. (2012) which conducted a study in the

Northern Region of Malaysia regarding the factor causing construction wastes

generation has found that the factors that have the highest mean responses through

the questionnaires survey are „Traditional construction method‟, „Poor

workmanship‟, „Poor storage‟, „Poor handling‟, „Untidy construction site‟, and „Lack

of management techniques to minimize waste‟. Another study which was also

conducted in Malaysia has found that five significant factors causing construction

Page 32: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

20

wastes generation are „Poor site management or supervision‟, „Lack of experience‟,

„Inadequate planning and scheduling‟, „Mistakes and errors in design‟, and „Mistakes

during construction‟ (Nagapan et al., 2012c).

China: Yunpeng (2011) investigated the main causes of the generation of

construction wastes and they are „Unimplemented wastes management measures and

weak consciousness of material saving and environmental protection‟, „Low

performance of building materials and backward construction technologies‟, „Lack of

communication and coordination between building contractors‟, and „No irritation of

market benefit and short of supervision‟.

Singapore: Ekanayake & Ofori (2004) have carried out a survey to determine the

attributes according to their potential contributions to the generation of waste on site.

The finding shows that under Design-related waste sources, four of the attributes

have most significant impacts on construction wastes generation on site were „Lack

of attention paid to dimensional coordination of products‟, „Design changes while

construction is in progress‟, „Designer‟s inexperience in method and sequence of

construction‟, and „Lack of knowledge about standard sizes available on the market‟.

Under the Operational sector, the three attributes that had most significant impact on

construction wastes generation at site are: „Errors by trades persons or labourers‟,

„Damage to work done due to subsequent trades‟, and „Required quantity unclear due

to improper planning‟. Six attributes under Material handling related waste sources

and only one is the most significant impact which is „Inappropriate site storage‟.

There were three attributes under Procurement and none of the attributes

significantly contribute to construction wastes generation.

United Kingdom: Osmani et al. (2008) carried out a study to investigate the

architects‟ perspectives on construction wastes reduction by design. The findings

reveal that waste management is not a priority in the design process. Additionally,

the architects seem to take the view that wastes are mainly produced during site

operations and are rarely generated during the design stages; however, about one-

third of construction wastes could essentially arise from design decisions.

Page 33: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

21

India: A research conducted by Kulatunga et al. (2006) using questionnaires survey

to study the attitudes and perceptions of construction workforce on construction

wastes in Sri Lanka. The findings indicated positive perceptions and attitudes of the

construction workforce towards minimizing wastes and conserving natural resources.

However, a lack of effort in practicing these positive attitudes and perceptions

towards waste minimisation was identified.

Indonesia: Nazech, Zaldi, & Trigunarsyah (2008) also discussed the results of the

study on the identification of construction wastes in road and highway construction

projects in the greater Jakarta area. The study indicates that Work Execution has

been identified as the most important group of causes of the construction wastes

which „Inadequate proper construction equipment‟ has been suggested as the main

contributor to this condition. The other dominant sources of wastes are Materials and

Manpower. The study also shows that „Lack of management capability‟ as the main

factor of the construction wastes, which indicates the correlation between the waste

produced and management aspects related to project duration and labours.

Egypt: Garas, Anis, & Gammal (2001) whom conducted a research to address the

incidence of material waste in the Egyptian Construction Industry has found that the

most dominant causes are late information, uncompleted design, inadequate

information, poor control, unnecessary people‟s moves, untrained labour, work not

done, poor technology of equipment, changes to design, and damage during

transportation.

Botswana: Urio & Brent (2006) investigated construction waste in the Francistown

area of Botswana as a case study. The identified causes of construction wastes on the

sites are „Lack of onsite WMP‟, „Wastes from application process‟, „Overmixing of

material due to the lack of knowledge of requirements‟, „Error by tradesperson or

labourer‟, „Cutting uneconomical shapes/length‟, „Damage caused by subsequent

trades‟, „Change to design‟, „Use of incorrect material‟, „Damage during

transportation on site‟, „Inclement weather‟, „Order error‟, „Contract document

incomplete at time of construction commencement‟, „Error in contract document‟,

„Over-ordering‟, „Inappropriate storage on site‟, „Damage during transportation to

Page 34: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

22

site‟, „Accident, supplier error‟, „Criminal wastes due to damage or theft and

equipment malfunction‟.

Turkey: A research was conducted by Polat & Ballard (2004) to study the main

waste causes in the Turkish construction industry. The significant causes of material

waste that were found are „Ordering of materials that do not fulfil project

requirements defined on design documents‟, „Imperfect planning of construction‟,

and „Workers mistakes during operation‟.

Nigeria: Wahab & Lawal (2011) have conducted a research to assess the forms,

causes, and factors incidental to wastes. The result shows that among the factors

incidental to wastes, „Last minute client requirement‟ was ranked highest as the

factor that leads to design variation.

Based on past researches, it can be seen that there are various factors that

contribute to generation of construction wastes. The factors also vary in each

country. As such, a mapping of various factors causing construction wastes

generation was constructed. In order to adopt these factors in accordance to the

Malaysian construction industry, a total of 33 factors are chosen as the causative

factors in this research. The factors are classified into seven groups which are

Information and Communication (ICT), Equipment (EQP), Project and Contract

Management (PCM), Material (MAT), Delivery/Procurement (DEL),

External/Unpredictable (EXT), and Human Resources/Manpower (HRM). The

mapping of the 33 factors causing construction wastes generation according to

previous study is shown in Table 2.4. The description for each factor can be referred

in Appendix D.

Page 35: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

23

Table 2.4: Mapping of factors contributing construction wastes generation

No

COUNTRY

REFERENCES

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

MA

L

MA

L

MA

L

MA

L

CH

N

CH

N

CH

N

CH

N

CH

N

CH

N

CH

N

CH

N

SN

G

UK

UK

INS

IND

EG

P

BS

W

TK

Y

NIG

NIG

NIG

NIG

GH

N

GR

C

AS

D

BR

Z

TH

D

FACTORS CONTRIBUTING TO

CONSTRUCTION WASTES

Ha

ssa

n e

t a

l. (

20

12)

Na

ga

pa

n e

t a

l. (

201

2b

)

Ika

u e

t a

l. (

201

3)

Ma

sud

i et

al.

(2

01

1)

Lu

et

al.

(2

011

)

Wa

ng

et

al.

(2

008

)

Ta

m e

t a

l. (

200

7a)

Ta

m e

t a

l. (

200

7b

)

Wa

n e

t a

l. (

20

09)

Yu

np

en

g (

20

11)

Sh

en e

t a

l. (

20

02

)

Po

on

et

al.

(2

00

4)

Ek

an

ay

ak

e &

Ofo

ri.

(200

4)

Osm

an

i et

al.

(2

008

)

Do

min

go

et

al.

(2

008

)

Na

zech

et

al.

(20

08)

Su

rve

& K

ulk

arn

i (2

01

3)

Ga

ras

et a

l. (

200

1)

Uri

o &

Bre

nt

(20

06

)

Po

lat

& B

all

ard

(2

00

4)

Wa

ha

b &

La

wa

l (2

01

1)

Ola

dir

an

& J

ose

ph

(2

00

9)

Ad

ewey

u &

Ota

li (

20

13)

Jo

hn

& I

tod

o (

20

13

)

Ag

yek

um

et

al.

(2

01

2)

Pa

no

s &

Da

na

i (2

012

)

Al

Ha

jj &

Ha

ma

ni

(20

11)

Fo

rmo

so e

t a

l. (

200

3)

Ko

fow

oro

lo &

Gh

eew

al

(20

09

)

Information and Communication (ICT)

1 Poor coordination between parties / / / / / / / /

2 Poor quality of information / / / / / / /

3 Delay in information flow among parties / / /

Equipment (EQP)

4 Equipment failure / / / / / / /

5 Shortage of equipment / /

6 Unsuitable tools used / /

Project and Contract Management (PCM)

7 Lack of wastes management plans / / / / / / / / /

8 Rework / / / / / / / / /

9 Error in contract documentation / / / / / /

10 Mistakes in quantity surveys / / / / /

11 Last minute client requirements / / / / /

Page 36: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

24

Table 2.4 (continued) 12 Inexperience designer / / /

13 Lack of legal enforcement / /

Material (MAT)

14 Ordering errors / / / / / / / / / / / / / / /

15 Items not in compliance with specification / / / / / / /

16 Poor quality of materials / / / / / /

17 Inappropriate use of materials / / / / /

18 Inventory of materials not well

documented / / /

19 Vandalism at site / / / /

Delivery/Procurement (DEL)

20 Damage during transportation / / / / / / / / / / / / / / /

21 Wrong material delivery procedures / / / /

22 Supplier errors / /

External/Unpredictable (EXT)

23 Effect of weather / / / / / / / / / / /

24 Accident at site / / / / / / /

25 Damage caused by workers / / / / / /

26 Damages caused by third parties / /

27 Unforeseen ground conditions /

Human Resource/Manpower (HRM)

28 Poor attitudes of workers / / / / / / / / /

29 Insufficient training for workers / / / / / /

30 Poor workmanship / / / / / /

31 Lack of experience / / /

32 Lack of enthusiasm among workers / /

33 Lack of knowledge about construction / / /

*Note: MAL: Malaysia; CHN: China; SNG: Singapore; UK: United Kingdom; INS: Indonesia; IND: India; EGP: Egypt; BSW: Botswana; TKY: Turkey; GHN:

Ghana; ASD: Arab Saudi; BRZ: Brazil; THD: Thailand

Page 37: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

76

REFERENCES

Abdullah, A. M., & Malik, S. A. (2012). Key indicators of SWOT analysis between

Bumiputera and Non-bumiputera Industrialized Building System (IBS)

contractors in Selangor. 2012 International Conference on Statistics in Science,

Business and Engineering (ICSSBE) (pp. 1–6). IEEE.

Adeweyu, T. O., & Otali, M. (2013). Evaluation of causes of construction material

wastes - Case of Rivers State, Nigeria. Ethiopian Journal of Environmental

Studies and Management, 6(6), 746–753.

Agyekum, K., Ayarkwa, J., & Adinyira, E. (2012). Consultants‟ perspectives on

materials wastes reduction in Ghana. Engineering Management Research, 1(1),

138–150.

Akintoye, A. S., & Macleod, M. J. (1997). Risk analysis and management in

construction. International Journal of Project Management, 15(1), 31–38.

Al-Hajj, A., & Hamani, K. (2011). Material wastes in the UAE construction

industry : Main causes and minimisation practices. Architectural Engineering

and Design Management, 7(4), 221–235.

Alshubbak, A., Pellicer, E., & Catalá, J. (2009). A collaborative approach to project

life cycle definition based on the Spanish construction industry. 3RD

Conference on Engineering Work in Palestine November 3-5, 2009 (pp. 1–19).

Alwi, S., Hampson, K., & Mohamed, S. (2001). Effect of quality supervision on

rework in the Indonesian context. Asia Pacific Building and Construction

Management Journal, 1–9.

Alwi, S., Hampson, K., & Mohamed, S. (2002a). Wastes in the Indonesian

construction project. Proceedings of the 1st International Conferences of CIB

W107 – Creating a Sustainable Construction Industry in Developing Countries

(pp. 305–315).

Page 38: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

77

Abdullah, A. M., & Malik, S. A. (2012). Key indicators of SWOT analysis between

Bumiputera and Non-bumiputera Industrialized Building System (IBS)

contractors in Selangor. 2012 International Conference on Statistics in Science,

Business and Engineering (ICSSBE) (pp. 1–6). IEEE.

Adeweyu, T. O., & Otali, M. (2013). Evaluation of causes of construction material

wastes - Case of Rivers State, Nigeria. Ethiopian Journal of Environmental

Studies and Management, 6(6), 746–753.

Agyekum, K., Ayarkwa, J., & Adinyira, E. (2012). Consultants‟ perspectives on

materials wastes reduction in Ghana. Engineering Management Research, 1(1),

138–150.

Akintoye, A. S., & Macleod, M. J. (1997). Risk analysis and management in

construction. International Journal of Project Management, 15(1), 31–38.

Al-Hajj, A., & Hamani, K. (2011). Material wastes in the UAE construction

industry : Main causes and minimisation practices. Architectural Engineering

and Design Management, 7(4), 221–235.

Alshubbak, A., Pellicer, E., & Catalá, J. (2009). A collaborative approach to project

life cycle definition based on the Spanish construction industry. 3RD

Conference on Engineering Work in Palestine November 3-5, 2009 (pp. 1–19).

Alwi, S., Hampson, K., & Mohamed, S. (2001). Effect of quality supervision on

rework in the Indonesian context. Asia Pacific Building and Construction

Management Journal, 1–9.

Alwi, S., Hampson, K., & Mohamed, S. (2002a). Wastes in the Indonesian

construction project. Proceedings of the 1st International Conferences of CIB

W107 – Creating a Sustainable Construction Industry in Developing Countries

(pp. 305–315).

Page 39: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

78

Alwi, S., Hampson, K., & Mohamed, S. (2002b). Non value-adding activities in

Australian construction projects. Proceedings International Conference on

Advancement in Design, Construction, Construction Management and

Maintenance of Building Structure (pp. 270–278).

Alwi, S., Hampson, K., & Mohamed, S. (2002c). Non value-adding activities: A

comparative study of Indonesian and Australian construction projects.

Proceedings 10th of the International Group of Lean Construction Conference

(pp. 627–638).

Arnold, P., & Javernick-will, A. (2013). Projectwide Access : Key to effective

implementation of construction project management software systems. Journal

of Construction Engineering and Management, 139(5), 510–518.

Augustine, S. (2011). Managing wastes and cost in the construction industry : a case

study of the road construction. Kwame Nkrumah University of Science and

Technology: Master's Thesis.

Barron, M., & Barron, A. R., (2013). Project management. Rice University,

Houston, Texas: Connexions.

Bennet, F. L. (2007). The management of construction: a project lifecycle approach.

Alaska: Routledge.

Begum, R. A., & Pereira, J. J. (2011). C&D waste profile of the Malaysian

construction industry: Need a centralized database. Sustainable Technologies

(WCST), 2011 World Congress on (pp. 73-76). IEEE.

Begum, R. A., Satari, S. K., & Pereira, J. J. (2010). Wastes generation and recycling :

Comparison of Conventional and Industrialized Building Systems. American

Journal of Environmental Sciences, 6(4), 383–388.

Begum, R. A., Siwar, C., Pereira, J. J., & Jaafar, A. H. (2009). Attitude and

behavioral factors in wastes management in the construction industry of

Malaysia. Resources, Conservation and Recycling, 53(6), 321–328.

Berg, R., & Hinze, J. (2005). Theft and vandalism on construction sites. Journal of

Construction Engineering and Management, 131(7), 826–833.

Bossink, B. A. G., & Brouwers, H. J. H. (1996). Construction wastes: Quantification

and source evaluation. Journal of Construction Engineering and Management,

122(1), 55–60.

Calvo, N., Varela-Candamio, L., & Novo-Corti, I. (2014). A dynamic model for

construction and demolition (C&D) waste management in Spain: Driving

Page 40: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

79

policies based on economic incentives and tax penalties. Sustainability, 6(1),

416-435.

Chandrakanthi, M., & Ruwanpura, J. Y. (2002). Optimization of the wastes

management for construction projects using simulation. Proceedings of the

2002 Winter Simulation Conference (pp. 1771–1777). IEEE.

Chan, D. W., & Kumaraswamy, M. M. (1997). A comparative study of causes of

time overruns in Hong Kong construction projects. International Journal of

Project Management, 15(1), 55-63.

Chan, A. P. C., Yung, E. H. K., Lam, P. T. I., Tam, C. M. & Cheung, S. O. (2001).

Application of Delphi method in selection of procurement systems for

construction projects. Construction Management and Economics, 19 (7), 699 -

718.

Dainty, A. R., & Brooke, R. J. (2004). Towards improved construction wastes

minimisation: a need for improved supply chain integration? Structural Survey,

22(1), 20-29.

Domingo, N., Osmani, M., & Price, A. D. F. (2008). Reducing construction wastes in

healthcare facilities : A project lifecycle approach. Association of Researches in

ConstructionManagement, Cardiff, Wales.

Egan, J. (1998). Rethinking Construction. The Report of the Construction Task Force

to the Deputy Prime Minister, John Prescott. United Kingdom.

Ehsan, N., Mirza, E., Alam, M., Ishaque, A. (2010). Risk management in

construction industry. Computer Science and Information Technology

(ICCSIT), 2010 3rd IEEE International Conference, 9, 16-21.

Ekanayake, L. L., & Ofori, G. (2004). Building wastes assessment score: Design-

Based Tool. Building and Environment, 39(7), 851–861.

Engert, P. A., & Lansdowne, Z. F. (1999). Risk Matrix User‟s Guide. Bedford, MA:

The MITRE Corporation.

Esin, T., & Cosgun, N. (2007). A study conducted to reduce construction wastes

generation in Turkey. Building and Environment, 42(4), 1667–1674.

Enshassi, A., Mohamed, S., & Abushaban, S. (2009). Factors affecting the

performance of construction projects in the Gaza strip. Journal of Civil

Engineering and Management, 15(3), 269-280.

Page 41: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

80

Ferguson, J., Kermode, N., Nash, C. L., Sketch,W. A. J., & Huxford, R. P. (1995).

Managing and minimizing construction wastes - A practical guide. London:

Institution of Civil Engineers.

Foo, L. C., Rahman, I. A., Asmi, A., Nagapan, S., & Khalid, K. I. (2013).

Classification and quantification of construction wastes at housing project site.

International Journal of Zero Wastes Generation, 1(1), 1–4.

Formoso, C. T., Soibelman, L., Cesare, C. D., & Isatto, E. L. (2003). Material wastes

in building industry : Main causes and prevention. Journal of Construction

Engineering and Management, 128(4), 316–325.

Formoso, C. T., Isatto, E. L., & Hirota, E. H. (1999). Method for wastes control in

the building industry. Proceedings of the 7th Annual Conference of the

International Group for Lean Construction (1999) (pp. 325–334).

Frame, J. D. (2003). Managing Risk in Organizations: A Guide for Managers. 1st ed.

Jossey-Bass: A Wiley Imprint, San Francisco.

Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost

overruns in construction of groundwater projects in a developing countries;

Ghana as a case study. International Journal of Project Management, 21(5),

321-326.

Gannet Flaming Inc. (2009). Construction Project Management Handbook.

Washington DC: Federal Transit Administration.

Garas, G. L., Anis, A. R., & Gammal A. (2001). Materials wastes in the Egyptian

construction industry (pp. 1-8).

Garas, G. L. (2003). Estimating material wastes in the building construction industry

using Artificial Intelligence. Cairo University: Ph.D. Proceeding.

Gavilan, R. M., & Bernold, L. E. (1995). Source evaluation of solid wastes in

building construction. Journal of Construction Engineering and Management,

120(3), 536–552.

Gharaibeh, H. M. (2013). Cost control in mega projects using the Delphi Method.

Journal of Management in Engineering, 30(5),1-24.

Goh, K. C., Tey, J. S., Seow, T. W., & Goh, H. H. (2013). Importance of

sustainability and engineering economics in wastes infrastructure projects,

International Conference on Sustainable Building Asia (SB13 SEOUL). Seoul,

Korea: International Sustainability Council and Architectural Institute of Korea.

pp. 352–358.

Page 42: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

81

Gohar, A. S., Khanzadi, M., & Farmani, M. (2012). Identifying and evaluating risks

of construction projects in fuzzy environment: a case study in Iranian

construction industry. Indian Journal of Science and Technology, 5(11), 3593-

3602.

Gündüz, M., Nielsen, Y., & Özdemir, M. (2013). Quantification of delay factors

using the relative importance index method for construction projects in

Turkey. Journal of Management in Engineering, 29(2), 133-139.

Hallowell, M. R., & Gambatese, J. A. (2010). Qualitative research : application of the

Delphi method to CEM Research. Journal of Construction Engineering

Management, 136(1), 99–107.

Hamatschek, E., Tee, S. S., & Faulstich, M. (2010). Current practice of municipal

solid wastes management in Malaysia and the potential for Wastes-to-Energy

implementation. The International Solid Waste Association (ISWA) World

Congress, Hamburg, Germany.

Hasan, A. B. C., Ridzuan, A. R. B. M., Yusof, Z. B., Noordin, B. B., Atan, I. B., &

Ghani, A. H. B. A. (2013). Estimation model of construction waste materials in

Malaysia: Steel. In Business Engineering and Industrial Applications

Colloquium (BEIAC), 2013 IEEE (pp. 709-713). IEEE.

Hassan, S. H., Ahzahar, N., Fauzi, M. A., & Eman, J. (2012). Wastes management

issues in the Northern Region of Malaysia. Procedia - Social and Behavioral

Sciences, 42, 175–181.

Hong Kong Polytechnic. (1993). Reduction of Construction wastes: final report.

Hong Kong: The Hong Kong Construction Association Limited.

Hussin, J. M., Rahman, I. A., & Memon, A. H. (2013). The way forward in

sustainable construction: issues and challenges. International Journal of

Advances in Applied Sciences, 2(1), 15-24.

Ikau, R., Tawie, R., & Joseph, C. (2013). Initial findings on perspectives of local

contractors on wastes minimization barriers and incentives on construction sites.

2013 IEEE Business Engineering and Industrial Applications Colloquium

(BEIAC) (pp. 506–509). IEEE.

Intan, S., Alifen, R. S., & Arijanto, L. (2005). Analisa dan evaluasi sisa material

konstruksi. Civil Engineering Dimension, 7(1), 36–45.

Jannadi, O. A., & Almishari, S. (2003). Risk assessment in construction. Journal of

Construction Engineering and Management, 129(5), 492–500.

Page 43: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

82

Jiu-yan, W., Yi-kun, S., & Jin-xin, T. (2009). Study on the construction project life-

cycle Integrated Management System. 2009 International Conference on

Management Science & Engineering (16th) (pp. 1976–1981).

John, A. O., & Itodo, D. E., (2013). Professionals‟ views of material wastage on

construction sites and cost overruns. Organization, Technology & Management

in Construction: An International Journal. 5(1). (pp. 747-757).

Jordan, E., & Javernick-Will, A. (2013). Indicators of community recovery: content

analysis and Delphi approach. Natural hazards review, 14(1), 21-28.

KarimiAzari, A., Mousavi, N., Mousavi, S. F., & Hosseini, S. (2011). Risk

assessment model selection in construction industry. Expert Systems with

Applications, 38(8), 9105-9111.

Kartam, N. A. (1996). Making effective use of construction lessons learned in project

life cycle. Journal of Construction Engineering and Management, 122(5913),

14–21.

Kartam, N., Al-Mutairi, N., Al-Ghusain, I., & Al-Humoud, J. (2004). Environmental

management of construction and demolition wastes in Kuwait. Wastes

management (New York, N.Y.), 24(10), 1049–59.

Katz, A., & Baum, H. (2011). A novel methodology to estimate the evolution of

construction wastes in construction sites. Wastes management (New York, N.Y.),

31(2), 353–8.

Khan, R. A., Liew, M. S., & Ghazali, Z. (2014). Malaysian construction sector and

Malaysia Vision 2020 : Developed Nation Status. 2nd World Conference On

Business, Economics And Management - WCBEM 2013 (Vol. 109, pp. 507–

513). Elsevier B.V.

Kofoworola, O. F., & Gheewala, S. H. (2009). Estimation of construction wastes

generation and management in Thailand. Wastes management (New York, N.Y.),

29(2), 731–8.

Koskela, L. (1992). Application of the new production philosophy to

construction (No. 72). (Technical Report No. 72, Center for Integrated Facility

Engineering, Department of Civil Engineering). Stanford, CA: Stanford

University.

Kozlovská, M., & Spišáková, M. (2013). Construction wastes generation across

construction project life-cycle. Organization, Technology and Management in

Construction an International Journal, 5(1), 687–695.

Page 44: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

83

Kulatunga, U., Amaratunga, D., Haigh, R., & Rameezdeen, R. (2006). Attitudes and

perceptions of construction workforce on construction wastes in Sri Lanka.

Management of Environmental Quality: An International Journal, 17(1), 57–72.

Laquatra, J. (2004). Wastes management at the construction site. Proceedings of the

NSF Housing Research Agenda Workshop, Feb. 12-14, 2004, Orlando, FL. Vol.

2, pp. 45 - 50.

Lester, A. (2007). Project Management - Planning and Control. 5th ed. New York:

Elsevier Ltd.

Ling, F. Y. Y., & Nguyen, D. S. A. (2013). Strategies for construction wastes

management In Ho Chi Minh City, Vietnam. Emerald Group Publishing

Limited.

Linstone, H. A., & Turoff, M. (Eds.). (1975). The Delphi method: Techniques and

applications (Vol. 29). Reading, MA: Addison-Wesley.

Liu, Z., Osmani, M., Demian, P., & Baldwin, A. N. (2011). The potential use of BIM

to aid construction wastes minimisation. Proceedings of the CIB W78-W102

2011: International Conference –Sophia Antipolis, France, 26-28 October.

Lu, W., & Tam, V. W. Y. (2013). Construction wastes management policies and

their effectiveness in Hong Kong : A longitudinal review. Renewable and

Sustainable Energy Reviews, 23, 214–223.

Lu, W., & Yuan, H. (2011). A framework for understanding wastes management

studies in construction. Wastes management (New York, N.Y.), 31(6), 1252–60.

Lu, W., Yuan, H., Li, J., Hao, J. J. L., Mi, X., & Ding, Z. (2011). An empirical

investigation of construction and demolition wastes generation rates in

Shenzhen city, South China. Wastes management (New York, N.Y.), 31(4), 680–

687.

Mahamid, I. (2011). Risk matrix for factors affecting time delay in road construction

projects: owners‟ perspective. Engineering, Construction and Architectural

Management, 18(6), 609–617.

Mahendra, P. A., Pitroda, J. R., & Bhavsar, J. J. (2013). A Study of Risk

Management Techniques for Construction Projects in Developing

Countries.International Journal of Innovative Technology and Exploring

Engineering. Vol3, (5), 139-142.

Page 45: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

84

Manoliadis, O., Tsolas, I., & Nakou, A. (2006). Sustainable construction and drivers

of change in Greece: a Delphi study. Construction Management and Economics,

24(2), 113–120.

Manowong, E. (2012). Investigating factors influencing construction wastes

management efforts in developing countries: an experience from Thailand.

Wastes Management & Research : The Journal of the International Solid

Wastess and Public Cleansing Association, ISWA, 30(1), 56–71.

Marzouk, M. M., & El-Rasas, T. I. (2014). Analyzing delay causes in Egyptian

construction projects. Journal of Advanced Research, 5(1), 49-55.

Marzouk, M., & Azab, S. (2014). Environmental and economic impact assessment of

construction and demolition wastes disposal using System Dynamics.

Resources, Conservation and Recycling, 82, 41–49.

Masudi, A. F., Hassan, C. R. C., Mahmood, N. Z., Mokhtar, S. N., & Sulaiman, N.

M. (2011). Construction wastes quantification and benchmarking: A study in

Klang Valley, Malaysia. Journal of Chemistry and Chemical

Engineering, 5(10), 909-916.

Memon, A. H., Rahman, I. A., Asmi, A., & Azis, A. (2011). Preliminary study on

causative factors leading to construction cost overrun. International Journal of

Sustainable Construction Engineering & Technology, 2(1), 57–71.

Memon, A. H., Rahman, I. A., &Azis, A. A. A. (2012). Time and cost performance

in construction projects in Southern and Central Regions of Peninsular

Malaysia. International Journal of Advances in Applied Sciences, 1(1), 45-52.

Modarres, M. (2006). Risk analysis in engineering: techniques, tools, and trends. 1st

ed. Boka Raton: CRC Press.

Morledge, R., Smith, A. & Kashiwagi, D. T. (2006). Risk. in building procurement.

Oxford: Blackwell.

Nagapan, S., Rahman, I. A., & Asmi, A. (2011). A review of construction wastes

cause factors. Proceedings of the Asian Conference of Real Estate: Sustainable

Growth Managing Challenges (ACRE), Johor, Malaysia.

Nagapan, S., Rahman, I. A., & Asmi, A. (2012a). Construction wastes management :

Malaysian perspective. International Conference on Civil and Environmental

Engineering Sustainability (IConCEES), Malaysia (Vol. 2, pp. 299–309).

Page 46: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

85

Nagapan, S., Rahman, I. A., & Asmi, A. (2012b). Factors contributing to physical

and non-physical wastes generation in construction industry. International

Journal of Advances in Applied Sciences (IJAAS), 1(1), 1–10.

Nagapan, S., Rahman, I. A., Asmi, A., Hameed, A., & Zin, R. M. (2012c).

Identifying causes of construction wastes - case of Central Region of Peninsula

Malaysia. International Journal of Integrated Engineering, 4(2), 22–28.

Nagapan, S., Rahman, I. A., Asmi, A., Memon, A. H., & Latif, I. (2012d). Issues on

construction wastes: The need for sustainable wastes management. 2012 IEEE

Colloquium on Humanities, Science and Engineering (CHUSER) (pp. 325–330).

IEEE.

Nagapan, S., Rahman, I. A., Asmi, A., & Adnan, N. F. (2013). Study of site‟s

construction wastes in Batu Pahat, Johor. Malaysian Technical Universities

Conference on Engineering & Technology 2012, MUCET 2012 Part 3 - Civil

and Chemical Engineering (Vol. 53, pp. 99–103).

Nasaruddin, F. H., & Ravana, S. D. (2008). E-Construction wastes exchange in

Malaysia : A preliminary study issues in Malaysia management. Information

Technology, 2008. ITSim 2008. International Symposium on, 4, 1–7.

Nazech, E. M., Zaldi, D., & Trigunarsyah, B. (2008). Identification of construction

wastes in road & highway construction projects. Proceedings Eleventh East

Asia-Pacific Conference on Structural Engineering and Construction (EASEC-

11) (pp. 1–7).

Oladiran, & Joseph, O. (2009). Causes And minimization techniques of materials

wastes in Nigerian construction process. Fifth International Conference on

Construction in the 21st Century (CITC-V) “Collaboration and Integration in

Engineering, Management and Technology” May 20-22, 2009, Istanbul,

Turkey.

Official Portal Solid Wastes and Public Cleansing Management Corporation

(PPSPPA), (2013).

http://www.sisa.my/sisamy/index.php?option=com_content&view=article&id

=201&Itemid=41 [retrieved on 19 March 2014]

Oh, I. Y. (2014). Dispose of wastes at appointed site. The Star online,

http://www.thestar.com.my/News/Community/2014/03/07/Dispose-of-

wastes-at-appointed-sites-Ministry-planning-a-more-organised-construction-

debris-disposal/ [accessed on 24 March 2014].

Page 47: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

86

Olawale, Y. A., & Sun, M. (2010). Cost and time control of construction projects:

inhibiting factors and mitigating measures in practice. Construction

Management and Economics, 28(5), 509-526.

Osmani, M. (2012). Construction wastes minimization in the UK: Current pressures

for change and approaches. Procedia - Social and Behavioral Sciences, 40, 37–

40.

Osmani, M., Glass, J., & Price, A. (2006). Architect and contractor attitudes to

wastes minimisation. Proceeding of Institution of Civil Engineering, Wastes and

Resource Management 159 Issue WR2 (pp. 65–72).

Osmani, M., Glass, J., & Price, A. D. F. (2008). Architects‟ perspectives on

construction wastes reduction by design. Wastes Management, 28(7), 1147–

1158.

Panos, K., & Danai, G. I. (2012). Survey regarding control and reduction of

construction wastes. PLEA2012 - 28th Conference, Opportunities, Limits &

Needs Towards an environmentally responsible architecture Lima, Perú.

Perera, B. A. K. S., Rameezdeen, R., Chileshe, N., & Hosseini, M. R. (2014).

Enhancing the effectiveness of risk management practices in Sri Lankan road

construction projects: A Delphi approach. International Journal of Construction

Management, 14(1), 1-19.

Pimenteira, C. P., Carpio, L. G. T., Rosa, L. P., & Tolmansquim, M. T. (2005). Solid

wastess integrated management in Rio de Janeiro: input-output analysis. Wastes

Management (New York, N.Y.), 25(5), 539–53.

Polat, G., & Ballard, G. (2004). Wastes in Turkish construction. Proceedings of the

12th Annual Conference of the International Group for Lean Construction

IGLC-12, August, Denmark (pp. 488–501).

Poon, C S. (2007). Reducing construction wastes. Wastes Management, 27(12),

1715–1716.

Poon, C. S., Yu, A. T. W., & Jaillon, L. (2004). Reducing building wastes at

construction sites in Hong Kong. Construction Management and Economics,

22(5), 461–470.

Rahmat, N. R., & Ibrahim, A. H. (2007). Illegal dumping site : Case study in the

district of Johor Bahru Tengah, Johor. ICoSM (pp. 89–91).

RIBA Plan of Work 2013: Consultation document. (2013). (pp. 1–6).

Page 48: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

87

Rowe, G., & Wright, G. (1999). The Delphi technique as a forecasting tool : Issues

and analysis. International Journal of Forecasting, 15(4), 353–375.

Ruthankoon, R., & Ogunlana, S. O. (2003). Testing Herzberg‟s two-factor theory in

the Thai construction industry. Engineering, Construction and Architectural

Management, 10(5), 333-341.

Saad A. (2011). Factors impacting the project's life cycle. E-Leader Vietnam 2011.

(pp. 1-30)

Seagle, E. D., & Iverson, M. (2001). Characteristics of the turfgrass industry in 2020:

A Delphi study with implications for agricultural education programs. Journal

of Southern Agricultural Education Research, 52(1), 1-13.

Senaratne, S., & Wijesiri, D. (2008). Lean construction as a strategic option: Testing

its suitability and acceptability in Sri Lanka. Lean Construction Journal,4(1),

34-48.

Shen, L. Y., Tam, V. W. Y., Tam, C. M., & Ho, S. (2002). Material wastage in

construction activities - A Hong Kong survey. CIB W107: Creating a

Sustainable Construction Industry in Developing Countries.

Siew G. C., & Abdul-Rahman, H. (2013). The identification and management of

major risks in the Malaysian construction industry. Journal of Construction in

Developing Countries, 18(1), 19–32.

Skoyles, E.R. & Skoyles, J.R. (1987). Wastes prevention on site. Mitchell: London.

Skulmoski, G., Hartman, F., & Krahn, J. (2007). The Delphi method for graduate

research. Journal of Information Technology Education: Research,6(1), 1-21.

Spies, S. (2009). 3R in construction and demolition wastes ( CDW ) – potentials and

constraints. GTZ – German Technical Cooperation Division for Environment,

Resource Efficiency and Wastes Management.

Surve, R. B., & Kuljarni, S. S. (2013). “Construction wastes reduction – A case

study”. International Journal of Engineering Research & Technology (IJERT).

2(8). (pp. 870 - 875).

Tam, V. W. Y., & Le, K. N. (2009). On implementation of wastes management

systems in the Hong Kong construction industry using spectral methods. 2009

IEEE International Conference on Industrial Engineering and Engineering

Management (pp. 573–577). IEEE.

Page 49: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

88

Tam, V. W. Y., Shen, L. Y., Fung, I. W. H., & Wang, J. Y. (2007a). Controlling

construction wastes by implementing governmental ordinances in Hong Kong.

Construction Innovation: Information, Process, Management, 7(2), 149–166.

Tam, V. W. Y., Shen, L. Y., & Tam, C. M. (2007b). Assessing the levels of material

wastage affected by sub-contracting relationships and projects types with their

correlations. Building and Environment, 42(3), 1471–1477.

Uher, T. (2003) Programming and Scheduling techniques, UNSW Press, Sydney.

Urio, A. F., & Brent, A. C. (2006). Solid wastes management strategy in Botswana :

The reduction of construction wastes. Journal of the South African Institition of

Civil Engineering, 48(2), 18–22.

Van Teijlingen, E. R., & Hundley, V. (2010). The importance of pilot studies. Social

Research Update, 34, 1-4.

Wahab, A. B., & Lawal, A. F. (2011). An evaluation of wastes control measures in

construction industry in Nigeria. African Journal of Environmental Science and

Technology, 5(3), 246–254.

Wan, S. K., Kumaraswamy, M. M., & Liu, D. T. (2009). Contributors to construction

debris from electrical and mechanical work in Hong Kong infrastructure

projects. Journal of Construction Engineering and Management, 135(7), 637–

646.

Wang, J., Li, Z., & Tam, V. W. Y. (2014). Critical factors in effective construction

wastes minimization at the design stage: a Shenzhen case study, China.

Resources, Conservation and Recycling, 82, 1–7.

Wang, J.-Y., Kang, X.-P., & Tam, V. W.-Y. (2008). An investigation of construction

wastess: an empirical study in Shenzhen. Journal of Engineering, Design and

Technology, 6(3), 227–236.

Wang, R., & Li, S. (2011). Talking about the production and disposing of

construction wastes from the view of sustainable development. Power and

Energy Engineering Conference (APPEEC), 2011 Asia-Pacific, IEEE (pp. 1–4).

Wastes & Resources Action Programme (WRAP) (2009). Achieving good practice

wastes minimisation and management. Oxon: Wastes & Resauces Action

Programme.

Westland, J. (2006). The project management life cycle. United Kingdom: Kongan

Page.

Page 50: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

89

Wibiwo, M. A. (2003). The contribution of the construction industry to the economy

of Indonesia: a systemic approach. Civil Engineering Department, Diponegoro

University, Indonesia.

Xia, B., & Chan, A. P. C. (2010). Key competences of design-build clients in China.

Journal of Facilities Management, 8(2), 114–129.

Yang, Y. B., & Ou, S. F. (2008). Using structural equation modeling to analyze

relationships among key causes of delay in construction. Canadian Journal of

Civil Engineering. (35), 321–332.

Yeheyis, M., Hewage, K., Alam, M. S., Eskicioglu, C., & Sadiq, R. (2012). An

overview of construction and demolition wastes management in Canada: a

lifecycle analysis approach to sustainability. Clean Technologies and

Environmental Policy, 15(1), 81–91.

Yeung, J. F. Y., Chan, A. P. C., & Chan, D. W. M. (2009). Developing a

performance index for relationship-based construction projects in Australia :

Delphi Study. Journal of Management in Engineering, 25(2), 59–68.

Yu, A. T. W., Poon, C. S., Wong, A., Yip, R., & Jaillon, L. (2013). Impact of

construction wastes disposal charging scheme on work practices at construction

sites in Hong Kong. Wastes Management (New York, N.Y.), 33(1), 138–46.

Yuan, H. (2012). A model for evaluating the social performance of construction

wastes management. Wastes management (New York, N.Y.), 32(6), 1218–28.

Yunpeng, H. (2011). Minimization management of construction wastes. 2011

International Symposium on Water Resource and Environmental Protection

(ISWREP), China (pp. 2769–2772). IEEE.

Zhao, Y., & Chua, D. K. H. (2003). Relationship between productivity and non

value-adding activity. 11th Annual Conference of the International Group for

Lean Construction.

Zhou, H., & Zhang, H. (2011). Risk assessment methodology for a deep foundation

pit construction project in Shanghai, China. Journal of Construction

Engineering and Management, 137(12), 1185–1194.

Zhou, P., & Leung, H. K. (2012). An integrated risk analysis method using spatial

interpolation. In Software Engineering Conference (APSEC), 2012 19th Asia-

Pacific (Vol. 1, pp. 452-461). IEEE.

Page 51: i RISK LEVEL OF FACTORS CAUSING CONSTRUCTION WASTE ...eprints.uthm.edu.my/id/eprint/7025/1/NOR_SOLEHAH_MD_AKHIR.pdf · mencadangkan langkah-langkah mengatasi untuk faktor-faktor yang

90

Zou, P. X., Zhang, G., & Wang, J. (2007). Understanding the key risks in

construction projects in China. International Journal of Project Management,

25(6), 601-614.