23
I-49 North Shreveport to the Arkansas State Line Project Update: History and Current Status January 2011 La. Transportation Conference Joe Umeozulu

I-49 North Shreveport to the Arkansas State LineI-49 North Shreveport to the Arkansas State Line Project Update: History and Current Status January 2011 La. Transportation Conference

Embed Size (px)

Citation preview

I-49 NorthShreveport to the Arkansas State Line

Project Update:History and Current Status

January 2011 La. Transportation Conference

Joe Umeozulu

Outline• Brief General I-49 History• I-49 North Funding

• Funds received• Where spent

• Completion Cost Summary• Preconstruction Challenges• What Next ?

I-49 History

• Designated by US Congress in 1984 – Interstate entirely within Louisiana– Connect Shreveport and Lafayette– Completed in 1996– 208 miles in length

I-49 History (continued)

• 1991, ISTEA– High Priority Corridor 1– Kansas City to Shreveport– $28.8 million in DEMO to LA

I-49 History (continued)

• 1996, TEA-21– High Priority Corridor 37 – U.S Route 90 from Lafayette to

New Orleans– $4.3 million DEMO to LA

• HPC 1 and 37 commonly known as proposed:

I-49 in Louisiana

(~ 405 miles)

I-49 Corridor

• Completed I-49 will connect New Orleans to Kansas City

• 900 miles from New Orleans to Kansas City

• Will connect ports of Louisiana to middle America and Canada

I-49 US Corridor

I-49 NorthCorridor

• 36 Miles• 11 Construction

Segments

(I-220 to Arkansas State Line)

Funding I-49

• FEDERAL FUNDS– SAFETEA-LU $200M– ISTEA , TEA-21 & Other Earmarks $ 43M

Total Earmarks $243M

Fed. Earmark Funds after Reduction $226MEconomic Stimulus (DOTD) $ 42MEconomic Stimulus (MPO) $ 4.5M

Total Federal Funds $272.5M

Funding I-49

• STATE FUNDS– General Fund Surplus $109M– Unclaimed Property Fund $ 30M– GO Bonds $50.3M

Total State Funds $189.3M

Total Available Fed. & State Funds $461.5M

(continued)

Funded Activities Segment A (La 168 – Arkansas State Line)

- Engineering $ 0.3M- Right-0f-Way $ 1.0M- Utility $ 0.4M- Construction $34.4M

Segment B (Mira-Myrtis Road To La 168)-Engineering $ 1.2M- Right-0f-Way $ 1.3M- Utility $ 0.1M- Construction $51.4M

Segment C (La 2 – To Mira-Myrtis Road)-Engineering $ 0.4M- Right-0f-Way $ 0.5M- Utility $ 0.3M- Construction $23.5M

Funded Activities Segment D (US 71 – La 2)

- Engineering $ 0.8M- Right-0f-Way $ 1.7M- Utility $ 1.2M- Construction $49.3M

Segment E (La 170 – US 71)-Engineering $ 1.0M- Right-0f-Way $ 3.7M- Utility $ 2.4M- Construction $46.7M

Segment F (La 530 – La 170)-Engineering $ 1.4M- Right-0f-Way $11.1M- Utility $ 0.6M- Construction $30.8M

Funded Activities Segment G (La 169 – La 530)

- Engineering $ 0.7M- Right-0f-Way $ 6.1M- Utility $ 2.4M- Construction $43.7M

Segment H (La 173 – La 169)- Engineering $ 0.03M- Right-0f-Way $ 1.3M- Utility $ 1.0M- Construction $12.2M

Segment I (La 1 – La 173)- Engineering $ 1.9M- Right-0f-Way $ 6.7M- Utility $ 2.9M- Construction $ 69.2M

Funded Activities

Segment J (MLK Blvd. – La 1)- Engineering $ 1.5M- Right-0f-Way $10.7M- Utility $ 1.0M- Construction Unfunded

(Estimated $60.5M)

Segment K (I-220 To MLK Blvd)- Engineering $ 2.5M- Right-0f-Way $14.0M- Utility $ 1.2M- Construction Unfunded

(Estimated $96.8M)

Status SummaryStatus Summary

• Segments Under Construction or Have been Let (~31 miles)

• Unfunded Construction Segments

• Segments Under Construction or Have been Let (~31 miles)

• Unfunded Construction Segments

Completion Cost SummaryPhase Total

Engineering $ 11.8 million

Right-of-Way $ 57.9 million

Utility Relocation $ 13.5 million

Construction $ 523.4 million EIS & Feasibility $ 2.4 million Geotechnical Borings $ 3.3 millionWetland Mitigation $ 6.6 million

Total Estimated Project Cost $618.9 million

Updated: January 7, 2011

Preconstruction Challenges• ROW acquisition due to high concentration of oil

wells in segments E, F & G. • Our records show a total of 95 out of 102 oils wells

in these 3 segments with 57 in segment F alone.• These wells needed to be evaluated for their

reserve content, appraised, compensated for, plugged and abandoned.

Preconstruction Challenges• The hard work of our Real Estate section, along

with their consultant (P.E.C.) made these acquisition possible on time for authorization and bid letting.

• Future challenge will be dealing with high number of relocations during the acquisition of segments J & K.

What Next?• About additional $160M needed to complete I-49

North (segments J & K).• It is likely some segments of I-49N could be open

to traffic, possibly within 2 years or less.• If opened, a detour via La 168 is needed to

continue north until Arkansas joins to Louisiana.

What Next?• With completion of the segments from Arkansas to

I-220, continuous I-49 traffic south will be via I-220 and La 3132 (Inner Loop Expy).

• A feasibility study for direct southern connection of I-49 (I-220 to I-20) has recently been completed.

• It is estimated that the “Inner City Connection” (I-220 to I-20) will cost about $350M to complete.

I-49 North Team• DOTD Prime Consultants

Road Design Aucoin & AssociatesBridge Design Coyle EngineeringReal Estate Alliance Inc.Utility Balar EngineersConstruction NTB AssociatesPavement & Geotechnical AFJM, Ic.Traffic Engineering Huval & AssociatesContract Services TRC EngineersProject Finance PECChief Engineer LaPAC

OthersFHWALouisiana I-49 Coalition

Project Manager Contact

Joe Umeozulu225-379-1386

[email protected]