HOUSING & DEVELOPMENT BOARDBUILDING QUALITY DEPARTMENTUPGRADING CONSTRUCTION MANAGEMENT SECTIONUPGRADING CONSTRUCTION MAMAGEMENT UNIT 3
SITE OBSERVATION REPORT Ref No: 452-21-11-0163A
PrecinctChai Chee / Chin SweeBlk 1,2, 50 to 54 / Blk 53
Contract HIP & LUP C64ARecord Ref No.
UCM / 002 / 11
Name of Main Contractor
Logistics Construction Pte Ltd Contract No. D/076/09Date of Visit
13 Jan 2011
Status of Works 63.0% Overall Work Done as at Dec 10
Works Within Flat
Stage 1 : In Progress Project Manager IC
AVP Chow Yew Keong
Original Contract Period
26 May 09 to 04 Nov 11Works Outside Flat
In progressSite Supervisor
SSS Ong Ting Hock
Recorded By: PD Ong Toon Lian (Lead)PDA Wong Woon Meng
AUDIT FINDINGS
S/N GOOD WORK PRACTICES REMARKS
Overhead shelter provided at edge of hoarding to prevent falling object.
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
B SAFETY / SECURITY PROVISIONS
1.0 Electrical trucking
We found the electrical trucking and wires hanging at ceiling not properly installed. @ Blk 52 #02-324 half landing
These will posed safety hazard, to instate immediately.
Electrical trucking and wire not properly instated The affected electrical trunking and wires have been properly reinstated.
Page 2 of 10TMPU – Technical Compliance & Project Management Audit - 020606
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
2.0 Toe-board
We noticed the new lift lobby “Toe-boards” not provided.
This will posed falling object hazard. @ Blk 52
To rectify immediately.
Site staff and safety officer must carry out daily inspection to ensure all safety measures apply on site.
Toe-boards not provided
The affected lift lobby has been provided with toe boards.
3.0 Gondola
We found the gondola winches not symmetrically installed on cradle.
This will caused unbalance when the gondola in operation.
To adjust immediately.
Gondola winches not symmetrically installed The affected Gondola winches have been symmetrically installed on cradle.
Page 3 of 10TMPU – Technical Compliance & Project Management Audit - 020606
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
C WORKSITE HOUSEKEEPING MEASURES
1.0 Housekeeping
We found poor housekeeping around lift lobby and drain. @ Blk 52 & 53
Debris collected around lift lobby
Debris and water stagnant at drain
The debris have been removed.
The debris and stagnant water at drain have been cleared.
Page 4 of 10TMPU – Technical Compliance & Project Management Audit - 020606
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
1.0 Housekeeping(Con’t)
We found unwanted materials such as steel bars and mesh not cleared off. @ Blk 53
Unwanted materials not cleared off The unwanted materials have been cleared.
The unwanted timber has been cleared.
Page 5 of 10TMPU – Technical Compliance & Project Management Audit - 020606
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
1.0 Casting work
We found lift lobby slab badly casted with honeycomb. @Blk 53 #04- 336
Contractor to propose repair method to Resident Engineer for approval.
Site staffs to tighten the casting work and to check and ensure all defects are rectify.
Slab casted badly
Steel bar exposed
The affected lift lobby slabs have rectified according to RE’s recommendation and site staff will step up their checks and supervisions on this aspect of casting works..
The affected steel bar and slab with the honeycomb have been rectified
Page 6 of 10TMPU – Technical Compliance & Project Management Audit - 020606
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
1.0 Casting work(Con’t)
We found lift lobby slab badly casted with honeycomb. @Blk 52 # 02-324
Slab not properly castedThe affected slab with honeycomb has been rectified.
Page 7 of 10TMPU – Technical Compliance & Project Management Audit - 020606
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
Page 8 of 10TMPU – Technical Compliance & Project Management Audit - 020606
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
1.0 Casting work(Con’t)
We found lift lobby column not properly casted. @ Blk 53 #02-336
Column not properly casted
The affected column has been properly rectified.
Page 9 of 10TMPU – Technical Compliance & Project Management Audit - 020606
Precinct Work findings and clarifications (Consultants to Complete)
S/N OBSERVATIONS / NON-COMPLIANCES REMARKSCONSULTANTS COMMENTS / CLARIFICATIONS
E OTHERS OBSERVATION
1.0 Rain water down pipe
We found rain water down pipe at staircase half landing not reinstated after remove for clearing choke.@ Blk 53 #02-336
To rectify immediately to prevent rain water stagnant at lift lobby caused mosquito breeding hazard.
Rain water down pipe not reinstatedThe affected rainwater down pipe has been reinstated.
Page 10 of 10TMPU – Technical Compliance & Project Management Audit - 020606