42
Human Environment Chapter 12: Socio-Economics, Tourism, Land Use and Recreation

Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

HumanEnvironmentChapter 12: Socio-Economics, Tourism, Land Use and Recreation

Page 2: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36
Page 3: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

i

Contents  

Contents  .........................................................................................................................................  i  

List  of  Tables  ..................................................................................................................................  iii  

List  of  Figures  .................................................................................................................................  iii  

Abbreviations  and  Acronyms  .........................................................................................................  iv  

Glossary  .........................................................................................................................................  iv  

12.1   Introduction  ...................................................................................................................  1  

12.2   Consultation  ...................................................................................................................  1  

12.3   Policy  and  Legislation  .....................................................................................................  4  

12.4   Baseline  Environment  .....................................................................................................  4  

12.4.1   Data  Sources  ..........................................................................................................................  4  

12.4.2   Study  Area  .............................................................................................................................  5  

12.4.3   Population  .............................................................................................................................  6  

12.4.4   Economic  Activity  and  Employment  ......................................................................................  7  

12.4.5   Land  Use  ................................................................................................................................  7  

12.4.6   Tourism  and  Recreation  ........................................................................................................  9  

12.4.7   Public  Access  .......................................................................................................................  12  

12.4.8   Baseline  Without  the  Project  ..............................................................................................  14  

12.5   Assessment  Methodology  .............................................................................................  15  

12.5.1   Methodology  .......................................................................................................................  15  

12.6   Embedded  Mitigation  ....................................................................................................  17  

12.7   Impact  Assessment  –  Onshore  Transmission  Works  .......................................................  18  

12.7.1   Impacts  of  Construction  ......................................................................................................  18  

12.7.2   Impacts  of  Operation  and  Maintenance  .............................................................................  23  

12.7.3   Impacts  of  Decommissioning  ..............................................................................................  26  

12.8   Impact  Interactions  .......................................................................................................  26  

12.9   Additional  Mitigation  ....................................................................................................  26  

12.10   Conclusions  and  Assessment  Summary  ..........................................................................  26  

12.11   Cumulative  Impacts  –  Onshore  Transmission  Works  and  Offshore  Wind  Farm  ...............  28  

12.11.1   Impacts  of  Construction  ......................................................................................................  28  

12.11.2   Impacts  of  Operation  and  Maintenance  .............................................................................  29  

12.11.3   Impacts  of  Decommissioning  ..............................................................................................  29  

12.12   Cumulative  Impacts  –  Onshore  Transmission  Works  and  Other  Projects  ........................  30  

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

i

Page 4: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

ii

12.12.1   Impacts  of  Construction  ......................................................................................................  30  

12.12.2   Impacts  of  Operation  and  Maintenance  .............................................................................  33  

12.13   Cumulative  Impacts  Conclusions  ....................................................................................  34  

References  ....................................................................................................................................  36  

   

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

ii

Page 5: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

iii

List  of  Tables  

Table  12.1:  EIA  Scoping  Comment  and  Actions  .....................................................................................  2  Table  12.2:  Key  Data  Sources  ................................................................................................................  4  Table  12.3:  Determining  Magnitude  of  Predicted  Impacts  ..................................................................  15  Table  12.4:  Determining  Sensitivity  of  Receptors  ................................................................................  16  Table  12.5:  Determining  the  Significance  of  Effect  ..............................................................................  17  Table  12.6:  Summary  of  Residual  Effects  .............................................................................................  26  

 

List  of  Figures  

Figure  12.1:  Preston/Seton/Gosford  Ward  2007  ...................................................................................  6  Figure  12.2:  Land  Use  Allocations  in  the  East  Lothian  Local  Plan  ..........................................................  8  Figure  12.3:  Key  Tourism  and  Recreation  Attractions  with  5  km  of  the  Application  Site  ....................  12  Figure  12.4:  Core  Paths  and  Rights  of  Way  ..........................................................................................  13  

 

   

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

iii

Page 6: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

iv

Abbreviations  and  Acronyms    

CCGT  

EIA  

ES  

FTE  

GROS  

HDD  

ICOL  

NCR  

OfTW  

OnTW  

PPP  

SIMD  

Denotes  the  Cockenzie  Combined  Cycle  Gas  Turbine  Power  Station  

Environmental  Impact  Assessment  

Environmental  Statement  

Denotes  full  time  equivalent  jobs  

General  Register  of  Scotland  

Horizontal  Directional  Drilling  

Inch  Cape  Offshore  Limited  

National  Cycle  Route  

Offshore  Transmission  Works  

Onshore  Transmission  Works  

Planning  Permission  in  Principle  

Scottish  Index  of  Multiple  Deprivation    

ELC     East  Lothian  Council    

SLVIA   Seascape,  Landscape  and  Visual  Impact  Assessment  

STEAM   Scottish  Tourism  Economic  Activity  Monitor    

 

Glossary  

Right  of  Way     A   Right   of   Way   is   a   route   over   which   the   public   has   been   able   to   pass  unhindered   for   at   least   20   years.   The   route  must   link   two   “public  places”,  such  as  villages,  churches  or  roads  and  must  follow  a  more  or   less  defined  route.  

Core  Path   Core   Paths   are   paths   or   routes,   including   waterways,   to   facilitate   the  exercise   of   access   rights   under   the   Land   Reform   (Scotland)   Act   2003.   The  purpose  of  Core  Paths  is  to  provide  the  basic  framework  of  routes  sufficient  for   the   purpose   of   giving   the   public   reasonable   access   throughout   their  area.  

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

iv

Page 7: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

1 of 36

12 Socio-­‐Economics,  Tourism,  Land  Use  and  Recreation  

12.1 Introduction  

1 This   chapter  presents  an  assessment  of   the  potential   socio-­‐economic,   land  use,   recreation  and  tourism  effects  of  the  construction,  operation  and  decommissioning  phases  of  the  Inch  Cape  Onshore  Transmission  Works  (OnTW).    

2 In  particular,  this  chapter  considers  the  following  effects:  

• Direct,   indirect   and   induced   effects   on   employment   and   the   economy   through   job  creation  and  expenditure;  

• Effects   on   land   use,   including   consideration   of   the   implications   of   changes   to   existing  land  uses;  

• Effects  on  public  access  and  recreation,   including  consideration  of  Rights  of  Way,  Core  Paths  and  other  promoted  outdoor  access  routes;  and  

• Effects  on  tourism.  

3 Effects   on   tourism   will   be   indirect   and   will   be   primarily   related   to   visual   effects   and   the  impact   of   these   visual   effects   on   visitor   numbers   and   the   local   tourism   economy.  Consequently   this   chapter   shares   direct   linkages  with  Chapter   8:   Landscape   and   Visual  of  this  Environmental  Statement  (ES)  and  makes  reference  to  its  content  where  relevant.  Other  indirect  impacts  such  as  noise,  traffic  and  transport  and  air  quality  resulting  from  the  OnTW  may   also   have   an   indirect   effect   upon   visitor   numbers.   Such   effects   are   not   generally  considered   within   this   chapter   given   they   are   not   considered   to   have   the   potential   for  significant  effects  but  are  discussed   in  Chapter  10:  Noise  and  Vibration,  Chapter  11:  Traffic  and  Transport  and  Chapter  13:  Air  Quality  respectively.    

12.2 Consultation  

4 Comments   from   the   East   Lothian   Council   (ELC)   Environmental   Impact   Assessment   (EIA)  Scoping   Opinion   dated   14   May   2014   related   to   socio-­‐economics,   tourism,   land   use   and  recreation   are   summarised   in   Table   12.1   below,   along   with   a   summary   of   how   these  comments  have  been  addressed.  

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

1 of 36

Page 8: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

2 of 36

Table  12.1:  EIA  Scoping  Comment  and  Actions  

Consultee   Scoping/Consultation  Response   Project  Response  

East  Lothian  Council  

The   Scoping   Report   identifies   Core   Paths  crossing   the   site,   as   well   as   the   nearby  Ghost  Trail.  The  John  Muir  Way  crosses  the  site.   The   Scoping   Report   identifies   direct  and   indirect   impacts   on   recreation   and  tourism.   Impacts   from   the   construction  phase  are  scoped  in,  but  scoped  out  of  the  operational   phase.   Given   the   size   of   the  structure   and   the   re-­‐routing   of   the   Core  Path   running   through   the   site,   the   impact  on   this   route  will   be   continuing.   This   is   an  important   route   linking   Tranent   to   the  coast   (as   well   as   Cockenzie)   and   ongoing  impacts  should  be  examined.  

Impacts  on  traffic  and  transport  are  considered   in   Chapter   11:   Traffic  and  Transport.    

This   assessment   considers   the  potential   effects   of   the   OnTW   on  specifically   on   the   Core   Paths  during   both   the   construction   and  operational   phase   which   can   be  found  in  Section  12.5  to  12.9  

Mitigation  has   also  been   identified  to  minimise  the  potential  effects  on  the  Core  Path   running   through   the  Application  Site  (Core  Path  144).  

East  Lothian  Council/  Historic  Scotland    

There  is  the  potential  for  direct   impacts  on  the  Prestonpans  Battlefield,  as  a  significant  portion   of   the   development   is   within   this  site.  

There   are   also   a   number   of   assets   in   the  vicinity   of   the   proposal   which   should   be  assessed   for   their   potential   impact   on  setting,  namely:  

• Seton  West  Mains,  enclosures  (Index  no.  5687)  Scheduled  Monument    

• Seton   Castle   (formerly   Seton   House)  with   retaining   terrace   and  walls   (HB  no  19080)    

• Cockenzie   House,   with   Great   Custom,  Gates,   Walls   and   garden   features   (HB  no.  23026)    

• Cockenzie   House   (on   the   Inventory   of  Gardens  and  Designed  Landscapes)    

• Seton   House   (on   the   Inventory   of  Gardens  and  Designed  Landscapes)    

• Prestonpans  (Inventory  Battlefields    

Impacts   on   the   Prestonpans  Battlefield   site   in   addition   to  another   of   cultural   heritage   assets  are   considered   in   Chapter   9:  Cultural  Heritage  and  Archaeology.  Mitigation   appropriate   to   reduce  impacts   to   an   acceptable   level   are  detailed  in  this  chapter.    

Setting   impacts   are   detailed   in  Chapter  8:  Landscape  and  Visual.  

Any   indirect   impacts  on   tourism  or  recreation   are   assessed   in   Section  12.5  to  12.9.    

East  Lothian  Council  

The  site   is   located  on  an  area   identified  on  the   John   Hutton   Institute   maps   as   prime  quality  agricultural  land.  The  impact  on  this  should  be  briefly  stated.  The  area  may  also  contain   mineral   reserves   and   this   again  should   be   briefly   explored   and   any  sterilisation  of  these  noted.  

Land   use   considerations   are  included   in   the   Chapter   6:  Hydrology,   Hydrogeology   and  Geology   in   Baseline   Environment  Section   6.4   and   assessed   in   the  impact   assessment   Sections   6.5   to  6.9.  These  are  further  considered  in  Section  12.5  to  12.9.    

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

2 of 36

Page 9: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

3 of 36

Consultee   Scoping/Consultation  Response   Project  Response  

East  Lothian  Council/  SEPA  

Any   application   involving   large   scale  beach  replenishment   and/or   dredging   works  should  be  cross  checked  as  to  whether  the  proposals  lie  within  or  close  to  a  designated  bathing   water   or   shellfish   growing   water.  Ideally   all   physical   works   should   be   done  outwith   the   Bathing  Water   Season   (1   June  to   15   September)   and   spatfall   (oyster  spawning)  periods.  Further  guidance  on  the  Bathing   Waters   Directive   (2006/7/EC)   can  be   obtained   from  www.sepa.org.uk/data/bathingwaters.  

In   Section   6.4.3,   it   has   been  identified   that   the   Application   Site  is   not   within   designated   bathing  waters   of   shellfish   growing   water.  As  such  no  seasonal  restrictions  are  proposed   in   the   mitigation   in  Section  6.5.2  and  6.7.  

The  effects  on   leisure  beaches  and  recreation   associated   with   the  Project   are   further   considered   in  the   Inch  Cape  Offshore  ES  Chapter  10  Metocean  and  Coastal  Processes  and   Chapter   22   Socio   Economics  and  tourism  

East  Lothian  Council  

Any   impacts   on   the   consented   Cockenzie  Gas   Pipeline   should   be   examined,  whether  it   is   constructed   or   not   (provided   the  consent   is   still   valid   at   the   time   of  application).   If   the   route   of   this   Pipeline  would  have  to  be  altered  as  a  result  of  this  project   the   impacts   of   this   should   be  examined  as  an  indirect  impact.  

Potential   effects   on   prime   quality  agricultural  land,  the  Cockenzie  Gas  Pipeline   and   Core   Paths   are  assessed  in  Sections  12.5  to  12.9  of  this  chapter.  

East  Lothian  Council    

Scottish   Water   has   assets   in   the   area.   A  map   of   these   can   be   obtained   from   Site  Investigation   Services   (UK)   Ltd,   Tel   0333  123   1223   email   [email protected],   or  National  One-­‐Call,  Tel  0844  800  9957,  email  swplans@national-­‐one-­‐call.co.uk   ,   which  will   charge,   or   by   calling   at   Scottish  Water  area   offices.   Precautions  will   require   to   be  taken   to   avoid   damage   to   these   assets.  Scottish  Water   requests   that   the   applicant  contacts   their   Service   Relocation   team   via  [email protected]  regarding   this.   Measures,   which   may  include   an   offset   distance   from   the   asset,  requirements   for   excavation,   pumping   or  piling,   and   maintenance   of   access   to   the  asset   for   SW   staff.   This   should   be   very  briefly  summarised  in  the  ES.  

Potential  effects  on  Scottish  Water  assets   are   assessed   in   Chapter   6:  Hydrology,   Hydrogeology   and  Geology.  

SNH   While   we   support   the   proposed  methodology   and   scope   of   the   impact  assessment,  we  also  strongly  encourage  the  applicant   to   consider   opportunities   for  mitigation   and   positive   enhancement   of  local   landscape   and   visual   amenity   and  green  networks.  

Landscape   and   Visual   impacts   are  detailed   in   Chapter   8   Landscape  and  Visual.  

These   are   further   considered   for  indirect   impacts   on   socio-­‐economics,   tourism,   land   use   and  recreation  in  Sections  12.5  to  12.9.  

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

3 of 36

Page 10: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

4 of 36

5 The  information  received  through  scoping  has  informed  the  methodology  and  scope  for  the  assessment  of  the  socio-­‐economic,  tourism,  land  use  and  recreation  effects  presented  in  this  chapter.    

12.3 Policy  and  Legislation  

6 Relevant   policies   and   legislation   are   introduced   in   Chapter   2:   Policy   and   Legislation.   An  overview  of  policy  and  legislation  relevant  to  this  chapter  are  provided  below:    

• The  Land  Reform  (Scotland  )  Act  2003  sets  out  where  and  when  access  rights  apply  and  how  land  should  be  managed  with  regard  to  access.  The  Act  also  places  a  duty  on  local  authorities   to   draw   up   a   Core   Paths   plan.   This   is   a   plan   sufficient   to   give   the   public  reasonable  non-­‐motorised  access  throughout  their  area;    

• The   Scottish   Outdoor   Access   Code   defines   how   access   rights   should   be   exercised   and  gives   detailed   guidance   on   the   responsibilities   of   those   exercising   access   rights   and  those  managing  land  and  water;  

• Policy  DC1:  Development  in  the  Countryside  (part  5)  of  the  East  Lothian  Local  Plan,  (See  Section  12.4.5  and  Chapter  2  for  further  details);  

• Policy  NRG1:  Electricity  Generating  Stations  of   the  East  Lothian  Local  Plan,  See  Section  12.4.5  and  Chapter  2  for  further  details);  and  

• Policy  C3:  Protection  of  Open  Space  See  Section  12.4.5  and  Chapter  2  for  further  details).  

12.4 Baseline  Environment    

12.4.1 Data  Sources  

7 Information  on  the  baseline  environment  was  established  through  a  desk  based  assessment  and  a  visit  to  the  Study  Areas.  Key  data  sources  for  the  desk  based  assessment  are  identified  in  Table  12.2  below.  

Table  12.2:  Key  Data  Sources  

Data  Source   Area  of  Research  

Existing  Data  

Scotland’s  Census  2011  

(http://www.scotlandscensus.gov.uk/)  

Population,  employment,  economic  activity.  

Scottish  Neighbourhood  Statistics  

(http://www.sns.gov.uk/)    

Education  and  employment.  

Nomis  Official  Labour  Market  Statistics   Employment  

Scottish  Index  of  Multiple  Deprivation  2012  

(http://simd.scotland.gov.uk/publication-­‐2012/)    

Deprivation  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

4 of 36

Page 11: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

5 of 36

Data  Source   Area  of  Research  

VisitScotland  

(www.visitscotland.org)    

Tourism  

Visit  East  Lothian  

(http://www.visiteastlothian.org/home.asp)  

Tourism  

East  Lothian  Council  

(http://www.eastlothian.gov.uk/)  

Tourism  and  Recreation  

Sustrans  

(http://www.sustrans.org.uk/)    

Recreation  

East  Lothian  Local  Plan  2008   Land  Use  

Land  Capability  for  Agricultural  Map  Sheet  66  (Macaulay  Institute,  2010).    

Land  Use  

Site  Surveys  

Site  visit  to  Study  Areas   Land  use,  tourism  and  recreation.  

 

12.4.2 Study  Area  

8 The   Study   Area   used   in   this   assessment   varies   depending   upon   the   potential   effect   being  considered   and   the   sources   of   information   used.   In   general   the   Study   Areas   below   were  used:  

• Economic  Study  Area  –  the  Preston/Seton/Gosford  Electoral  Ward  2007  (see  Figure  12.1:  Preston/Seton/Gosford   Electoral   Ward   2007)   was   used   to   define   the   population,  employment  and  economic  baseline  for  the  Application  Site  and  the  local  area.  This  was  compared  with  data  from  the  2011  Census  for  ELC  and  Scotland-­‐wide  data;    

• Land  Use  Study  Area  –  the  Study  Area  was  confined  to  the   land  within  the  Application  Site;    

• Public   Access   and   Recreation   Study   Area   –   the   Study   Area   was   confined   to   the   land  within  the  Application  Site;  and  

• Tourism   Study   Area   –   a   5   km   radius   around   the   Application   Site   was   chosen   to  determine   tourism   routes   and   attractions  with   the  potential   to   experience   an   indirect  impact  upon  their  use  as  a  result  of  visual  impacts.  This  reflects  the  Study  Area  used  in  the   landscape  and  visual   impact   assessment   (see  Chapter  8),   the   conclusions  of  which  informed   this   assessment.   Beyond   this   distance   it   is   not   anticipated   that   there  will   be  any  significant  indirect  impacts  upon  tourist  visitor  numbers  as  a  result  of  the  OnTW.  

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

5 of 36

Page 12: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

6 of 36

Figure  12.1:  Preston/Seton/Gosford  Ward  2007  

 

 

12.4.3 Population  

9 According   to   the   2001   census,   the   Preston/Seton/Gosford  ward   had   a   total   population   of  17,540  people,  making  it  the  ward  with  the  second  highest  population  in  East  Lothian.  

10 The  Preston/Seton/Gosford  ward  includes  the  main  settlements  of:  

• Prestonpans  –  9,140  people  (52  per  cent  of  the  population  of  the  ward);  

• Port  Seton/Cockenzie  –  5,551  people  (32  per  cent  of  the  population  of  the  ward);  and  

• Longniddry  –  2,488  people  (14  per  cent  of  the  population  of  the  ward).  

11 Across   the   ward   the   population   has   grown   at   a   faster   rate   than   across   East   Lothian   as   a  whole,  with   a  population   increase  of   11.4  per   cent   since  2001   compared   to  10.7  per   cent  across  the  district.  

12 The  age  structure  of  the  ward  is  very  similar  to  East  Lothian.  Compared  to  Scotland  there  are  proportionally  more  children  and  fewer  people  of  working  age.  

13 Further   details   on   the   population   structure   of   the   Preston/Seton/Gosford   ward,   including  comparison   with   that   of   East   Lothian   and   Scotland,   is   contained   in  Appendix   12.A:   Socio-­‐Economics  Baseline.  

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

6 of 36

Page 13: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

7 of 36

12.4.4 Economic  Activity  and  Employment  

14 Although  East  Lothian  is  considered  to  be  an  area  of  high  employment  and  general  affluence  there   is   a   considerable   variation   in   economic   activity,   unemployment   and   the   financial  position   of   households   within   East   Lothian.   According   to   the   Scottish   Index   of   Multiple  Deprivation  2012,  Prestonpans   (the  nearest   settlement   to   the  Application   site)   falls  within  the  20  per  cent  most  income  deprived  areas  in  Scotland.  

15 According   to   the   2001   census,   the   greatest   industry   of   employment   sector   in   the  Preston/Seton/Gosford  ward  was  wholesale  and  retail,  which  employed  15.2  per  cent  of  all  persons  of  working  age  in  employment  compared  to  14.1  per  cent  across  East  Lothian.  The  next  most  popular  sectors  were  human  health  and  social  work  (14.1  per  cent  compared  to  15.2  per  across  East  Lothian)  and  construction  (9.1  per  cent  compared  to  8.4  per  cent  across  East  Lothian).    

16 Further   details   of   economic   activity   and   employment   within   the   Preston/Seton/Gosford  ward,  including  comparison  with  that  of  East  Lothian  and  Scotland,  is  contained  in  Appendix  12.A:  Socio-­‐Economics  Baseline.  

12.4.5 Land  Use  

17 The  majority  of  the  Application  site  (approximately  13  ha)   lies  within  countryside  (land  use  allocation  DC1:  Development   in   the  Countryside)  as  defined   in   the  East   Lothian  Local  Plan  (see   Figure   12.2).   The   remainder   of   the   Application   Site   lies   within   land   defined   as   open  space  (Policy  C3:  Protection  of  Open  Space)  (approximately  4  ha),  and  land  safeguarded  for  use  as  or  in  association  with  a  power  generating  station  (Policy  NRG1:  Electricity  Generating  Stations)  (approximately  6  ha).    

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

7 of 36

Page 14: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

8 of 36

Figure  12.2:  Land  Use  Allocations  in  the  East  Lothian  Local  Plan  

 

 

18 Prime  Quality  Agricultural  Land  is  defined  by  the  Macaulay  Land  Use  Research  Institute  (now  the  James  Hutton  Institute)  as  land  which  is:  

• Class  1:  Land  capable  of  producing  a  very  wide  range  of  crops;  

• Class  2:  Land  capable  of  producing  a  wider  range  of  crops;  and  

• Class  3.1:  Land  capable  of  producing  consistently  high  yields  of  a  narrow  range  of  crops  and/or  moderate  yields  of  a  wider  range  of  crops.  

19 Most   of   East   Lothian   aside   from   the   upland   areas   is   defined   as   prime   quality   agricultural  land.  All   of   the   land  within   the  Application  Site  defined  as   countryside   in   the  East   Lothian  Local  Plan  (13  ha)  is  classified  as  Class  1  agricultural  land  according  to  the  Land  Capability  for  Agricultural  Map  Sheet  66   (Macaulay   Institute,  2010).  However   field  visits  and  a   review  of  aerial   photography   identify   that   the   majority   of   the   land   is   rough   grassland   which   is   no  longer  in  agricultural  use.  

20 A   number   of   Scottish   Water   utilities   have   been   identified   beneath   the   Application   Site.  These   include   a   water   distribution   main   and   combined   sewer   beneath   the   Onshore  Substation   Site   and   a   water   distribution   main,   combined   sewer   and   combined   sewer  overflow  intersecting  the  Onshore  Export  Cable  Corridor.  Further  details  on  these  utilities  is  discussed  in  Chapter  6:  Hydrology,  Hydrogeology  and  Geology,  with  their  locations  shown  on  Figure  6.2.  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

8 of 36

Page 15: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

9 of 36

21 Part  of  the  Application  Site  also  lies  within  a  Coal  Authority  Referral  Area  which  means  that  the  area  has  been  defined  by  the  Coal  Authority  as  containing  potential  hazards  from  former  coal  mining  activity.  Potential  hazards  identified  include  a  historical  coal  mine  and  a  number  of  mine  shafts  at  Preston  Links,  one  of  which  is  identified  as  lying  within  the  Onshore  Export  Cable  Corridor.  Further  details  on  these  mining  hazards  is  discussed  in  Chapter  6,  with  their  location  shown  on  Figure  6.7.  

22 Other   land   uses   within   the   Application   Site   include   a   railway   line   which   runs   from  Prestonpans  through  the  Onshore  Substation  Site  to  the  Cockenzie  coal  store.  A  Certificate  of   Lawfulness   for   the   demolition,   dismantlement   and   removal   of   infrastructure   at   the  Cockenzie   coal   store   was   issued   by   ELC   to   Scottish   Power   Generation   on   14   April   2014  reference  14/00212/CLD.  The  railway  line  is  not  publicly  accessible.  

23 The  B1348  (Edinburgh  Road)  crosses  through  the  Onshore  Export  Cable  Corridor.  The  B1348  provides  an  important  link  between  Cockenzie  and  Prestonpans  and  is  also  a  promoted  long  distance   cycle   route  and   tourist   route  as  discussed   in   the   sections  below.  Other   footpaths  and   recreational   land   uses   within   the   Application   Site,   including   a   number   of   Core   Paths  which  cross  through  the  Application  Site,  are  also  discussed  in  detail  Section  12.4.7.  Details  on  traffic  flows  along  the  B1348  are  discussed  in  Chapter  11.  

24 Outwith   the   Application   Site,   the   land   uses   in   the   vicinity   of   the   Application   Site   include  residential   development   along   the   eastern   edge   of   Prestonpans   along   the   length   of   the  Application  Site,  further  agricultural   land  to  the  south  and  east  of  the  Application  Site,  and  the  former  Cockenzie  coal  store  and  Cockenzie  Power  Station  to  the  north  and  east  of   the  Application  Site.  A  full  description  of  these  land  uses  is  contained  in  Chapter  6.  

12.4.6  Tourism  and  Recreation  

25 According   to   the   East   Lothian   District   Council   Scottish   Tourism   Economic   Activity  Monitor  (STEAM)   Report   2012   (Global   Tourism   Solutions,   2013),   the   total   revenue   generated   by  tourism   in   East   Lothian   in   2012  was   estimated   to   be   £195.88  million,   comprising   £148.60  million   spent   directly   and   £47.28  million   spent   indirectly.   Visitors   spent   their  money   on   a  variety  of  things,  with  £36.63  million  spent  on  transport,  £34.48  million  spent  on  food  and  drink,   £21.15   million   spent   on   accommodation,   £16.16   million   spent   on   recreation   and  £15.42   million   spent   on   shopping.   This   revenue   accounted   for   3,736   full   time   equivalent  (FTE)  jobs.  

26 The  East  Lothian  Visitor  Survey  2011  (East  Lothian  Council,  2012)  is  a  comprehensive  survey  of  542  visitors  to  East  Lothian  between  April  to  October  2011.  The  survey  identifies  that:  

• The  majority  of  visitors  to  East  Lothian  were  from  the  UK  (92  per  cent),  with  74  per  cent  of  those  coming  from  elsewhere  in  Scotland.  Most  day  trip  visitors  were  from  Scotland  (66   per   cent)  with   the  main   areas   represented   being   Edinburgh,   Strathclyde,   Borders,  West  Lothian  and  Midlothian;  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

9 of 36

Page 16: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

10 of 36

• More  than  half  of  visitors  to  East  Lothian  were  on  a  day  trip  from  home  (52  per  cent).  For  those  on  holiday,  the  majority  of  visitors  (56  per  cent)  were  on  a  short  break  booked  or  arranged  by  themselves;  

• More  than  four  out  of  five  visitors  to  East  Lothian  were  on  a  repeat  visit  to  the  area  (84  per  cent),  whilst  16  per  cent  were  on  their  first  ever  visit  to  East  Lothian;  

• The  main  type  of  accommodation  used  by  overnight  visitors  to  East  Lothian  was  staying  with   friends   and   relatives   (29   per   cent).   Other   visitors   stayed   in   static   caravans   and  mobile   homes   (25  per   cent),   hotels   (16  per   cent),   self   catering   accommodation   (8   per  cent)  and  bed  and  breakfasts  (8  per  cent);  and  

• Visitors   spent   on   average   £49.08   per   person   per   day   in   2011   if   the   costs   for  accommodation  are  included.    

27 Tourists  are  drawn  to  East  Lothian  for  a  variety  of  reasons.  With  over  40  miles  of  coastline,  East   Lothian   is   a   popular   destination   for   those   who   enjoy   the   outdoors.   It   is   a   popular  destination   for   walkers,   water   sports   and   bird   watchers.   It   is   also   a   leading   golf   tourism  location;   home   to   a  number  of   high  quality   golf   courses   including  Muirfield,   host  of  Open  championships.   Food   and   drink   is   also   gaining   prominence   as   a   driver   for   tourism   in   East  Lothian,   with   a   number   of   farmers   markets   and   popular   restaurants   present   across   the  district.  

28 According   to   the   East   Lothian   Visitor   Survey   2011,   the   most   common   general   activities  undertaken  by  the  majority  of  visitors  to  East  Lothian  in  2011  were  general  sightseeing  and  touring   (68   per   cent)   and   visits   to   the  beach/viewing   coastal   scenery   (64   per   cent).  Other  popular   activities  were   visiting   cafes/tearooms  and   coffee   shops   (60  per   cent)   and  visiting  restaurants   and   pubs   (24   per   cent).   Other   common   activities   amongst   tourists   in   East  Lothian   were   visits   to   museums/galleries   and   arts   exhibits   (43   per   cent),   visits   to   the  countryside   (34   per   cent)   and   visits   to   historical   buildings/churches/other   heritage  attractions  (31  per  cent).  

29 According   to   the   East   Lothian   Visitor   Survey   2011,   the   most   common   sporting   activities  undertaken   were   golfing   (eight   per   cent),   indoor   swimming   (eight   per   cent),   horse  riding/pony  trekking  (six  per  cent),  outdoor  water  sports   (four  per  cent),  cycling  (three  per  cent),  walking  (three  per  cent)  and  bird  watching  (three  per  cent).  

30 The   top   five   visitor   attractions   within   East   Lothian,   based   upon   visitor   numbers,   are   the  National  Museum  of  Flight  near  East  Fortune   (approximately  15.7  km   to   the  north  east  of  the   Application   Site),   the   Seabird   Centre   in   North   Berwick   (approximately   19.3   km   to   the  north-­‐east  of  the  Application  Site),  Tantallon  Castle  near  North  Berwick  (approximately  22.3  km   to   the   north   east   of   the   Application   Site),   Newhailes   House   in   Musselburgh  (approximately   7.1   km   to   the  west   of   the  Application   Site)   and  Glenkinchie  Distillery   near  Pencaitland  (approximately  8.5  km  to  the  south  east  of  the  Application  Site).    

31 The  key  tourist  and  recreation  resources  within  the  Tourism  Study  Area  are  shown  on  Figure  12.3  and  include  (but  are  not  limited  to):  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

10 of 36

Page 17: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

11 of 36

• Meadowmill   Sports   Centre   which   lies   approximately   602  m   to   the   south  west   of   the  Application   Site.   As   well   as   an   indoor   sports   hall,   the   centre   also   contains   outdoor  football,  rugby  and  hockey  pitches  and  an  athletics  track;  

• Seton   Sands   Holiday   Park   which   is   located   approximately   1.4   km   to   the   east   of   the  Application  Site  at   its  closest  point.  The  caravan  park  is  a  popular  destination  for  many  visitors  in  the  summer  months;    

• The  Royal  Musselburgh  Golf  Course  which  is  located  approximately  1.6  km  to  the  west  of  the  Application  Site  at  its  closest  point.  This  18  hole  golf  course  was  built  in  1926,  with  the  club  established  in  1774;  

• Prestongrange   Industrial   Heritage   Museum  which   is   located   approximately   2.4   km   to  the  west  of  the  Application  Site  at  its  closest  point.  The  museum,  which  is  run  by  ELC,  is  situated   on   a   former   colliery   site   near   Prestonpans   and   has   extensive   displays   and  special  exhibitions,  the  centrepiece  of  which  is  its  rare  Cornish  beam  engine;    

• Longniddry   Golf   Course   which   is   located   approximately   2.8   km   to   the   east   of   the  Application  Site.  This  18  hole  golf  course  was  founded  in  1921;  

• Musselburgh   Race   Course   which   lies   approximately   4.5   km   to   the   west   of   the  Application  Site  at  its  closest  point.  The  racecourse  is  a  VisitScotland  five  star  attraction  and  provides  an  extensive  programme  of  horse  racing  throughout  the  year;  

• Musselburgh  Links,  The  Old  Golf  Course  which   is   located  approximately  4.5  km  to  the  west  of  the  Application  Site.  The  nine  hole  course  is  the  oldest  continually  played  course  in  the  world,  dating  back  to  1672;  

• Longniddry  Bents  which  lie  approximately  3  km  to  the  north-­‐east  of  the  Application  Site  at   its   closest   point.   This   4.5   km   stretch   of   coastline   is   popular   for   walkers   and   bird  watchers;  

• The  Battle  of  Prestonpans  Memorial  which  is  located  approximately  191  m  to  the  south  west  of  the  Application  Site  at  its  closest  point.  The  memorial  is  in  memory  to  the  site  at  which  Prince  Charlie’s  Highland  army  defeated  Hanoverian  redcoats  under  General  John  Cope  during  the  1745  Jacobite  Rebellion;  and    

• The  Battle  of  Prestonpans  Viewpoint  which  lies  approximately  389  m  to  the  south  west  of  the  Application  Site  at   its  closest  point.  The  pyramidal  viewpoint  provides  a  vantage  point   for   visitors   of   the   battlefield,   with   a   series   of   display   panels   positioned   on   the  summit.  

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

11 of 36

Page 18: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

12 of 36

Figure  12.3:  Key  Tourism  and  Recreation  Attractions  with  5  km  of  the  Application  Site  

 

 

32 With   specific   regard   to   the   Battle   of   Prestonpans   Memorial   and   Viewpoint,   no   visitor  numbers  are  available.  It  is  understood  that  a  study  has  been  undertaken  by  Richard  Gerald  Associates  Ltd  (2007)  on  behalf  of  The  Battle  of  Prestonpans  (1745)  Heritage  Trust  to  explore  the  feasibility  of  developing  a  visitor  centre  at  Meadowmill.  At  the  time  of  writing  of  this  ES  chapter  no  firm  proposals  for  the  development  of  this  facility  or  another  similar  facility  were  available.    

33 The  B1348   crosses   the  Application  Site  and   forms  part  of   Scotland’s  Golf  Coast  Road.   This  promoted   tourism   route   stretches   from   Musselburgh   to   Dunbar   and   incorporates   22   golf  courses  along  its  length.  The  road  was  re-­‐branded  in  June  2013  to  reflect  East  Lothian’s  title  of  Scotland’s  Golf  Coast.  

34 The  East   Lothian  Tourism  Strategy  2010-­‐13   (East   Lothian  Council,   2010a)  outlines   ELC  and  partner  commitment  to  supporting  the  continued  development  of  the  tourism  economy  in  East  Lothian.  It  details  how  ELC,  in  partnership  with  both  the  private  sector  and  other  public  bodies,  will  work  together  towards  activities  which  contribute  toward  the  national  ambition  for  50  per  cent  tourism  growth  by  2015.  

12.4.7 Public  Access  

35 The  Land  Reform  (Scotland)  Act  2003  took  effect  in  February  2005  and  placed  a  duty  on  local  authorities   to   draw   up   a   Core   Paths   plan.   This   is   a   plan   sufficient   to   give   the   public  reasonable  non-­‐motorised  access  throughout  their  area.  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

12 of 36

Page 19: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

13 of 36

36 The   East   Lothian   Core   Path   Plan   (East   Lothian   Council,   2010b)   identifies   five   Core   Paths  which  cross  through  the  Application  Site  (see  Figure  12.4).  These  are  Core  Path  144  (which  runs  from  the  B6371  to  the  B1361),  Core  Paths  145  and  146  (which  skirt  around  the  eastern  periphery  of  Prestonpans),  Core  Path  284   (which   runs   immediately   south  of   the  Cockenzie  Gas  Holder)  and  Core  Path  276  (which  runs  along  Preston  Links).  

Figure  12.4:  Core  Paths  and  Rights  of  Way  

 

37 Core  Path  276  forms  part  of  The  John  Muir  Way,  a  long  distance  promoted  footpath  which  extends   along   the   coastline   of   East   Lothian   from   Dunbar   to   Musselburgh   and   has   been  recently   extended   through   to   Helensburgh   on   the   west   coast   of   Scotland.   The   newly  extended   John   Muir   Way   officially   opened   in   April   2014,   with   the   Scottish   Government  anticipating  that  the  route  will  bring  about  £40  million  in  economic  benefits  to  communities  along  the  route.  

38 Core   Path   144   forms   part   of   the   Tranent   to   Cockenzie   Waggonway,   a   public   footpath  between  Cockenzie  and  Prestonpans  which  runs  along  the  route  of   the   first   railway   line   in  Scotland  and  is  well  used  by  walkers,  cyclists  and  horse  riders.  Chapter  9:  Cultural  Heritage  and   Archaeology   considers   the   historical   significance   of   the   Tranent   to   Cockenzie  Waggonway.    

39 As   shown   on   Figure   12.4,   sections   of   Core   Paths   144,   145,   146   ,   276   and   284   are   also  designated  as  Rights  of  Way.  In  addition,  there  is  also  a  designated  Right  of  Way  which  runs  under   the   conveyor   belt   from   the   coal   store   to   Cockenzie   Power   Station   through   the  Application  Site.  Whilst  the  conveyor  belt  currently  obstructs  access  on  this  Right  of  Way  and  there  is  no  evidence  of  the  route  being  diverted.  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

13 of 36

Page 20: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

14 of 36

40 The  B1348  road  crosses  the  Application  Site.  The  B1348  forms  part  of  National  Cycle  Route  (NCR)  76  of   the  National  Cycle  Network  and  runs   from  Berwick  upon  Tweed  to  Edinburgh,  Stirling  and  St  Andrews.    

41 The   Land   Reform   (Scotland)   Act   2003   also   gives   the   public   the   right   of   responsible   non-­‐motorised  access  to  most  land  and  inland  water  in  Scotland  for  recreation  such  as  walking,  cycling,  horse  riding  or  canoeing.  

42 The  Application  Site  crosses  Preston  Links,  an  area  of  open  amenity  space  which  is  popular  with  walkers  and  dog  walkers.  Outwith  Preston  Links  and   the  Core  Paths   identified  above,  the   remainder   of   the  Application   Site   comprises   areas   of   rough   grassland   that   is   less  well  used  for  public  access.  There  is  no  inland  water  within  the  Application  Site.  

12.4.8 Baseline  Without  the  Project    

43 The   above   information   describes   the   baseline   conditions   at   the   time   of   undertaking   the  assessment.  There  is  the  likelihood  that  these  baseline  conditions  will  change  in  the  future,  regardless  of  whether  or  not  the  OnTW  is  developed.  However  prediction  of  many  of  these  aspects   is   very  uncertain  and   is   considered  unlikely   to   impact  upon   the  conclusions  of   the  assessment.  

44 Many  social  and  economic   factors   influence  population  change.  The  relationships  between  the  various  factors  are  complex  and  involve  inherent  uncertainty.  However,  on  the  basis  of  the  population  trends   identified  above   it   is  anticipated  that   the  population  of  East  Lothian  will  continue  to  grow.    

45 Employment  and  economic  activity   is  very  difficult   to  predict.  However   in   terms  of  energy  developments   it   seems   likely   that   the   Scottish  Government   energy   targets   (as   outlined   in  Chapter  2)  and  commitment  to  investment  in  renewable  energy  that  there  will  be  continued  growth   associated   with   renewable   energy   developments.   In   particular,   it   is   noted   the  emerging   National   Planning   Framework   3   identifies   that   there   may   be   significant  opportunities   for   renewable   energy-­‐related   investment   at   Cockenzie.   Consequently   the  proportion  of  the  local  economy  benefitting  from  renewables  related  developments  is  likely  to  increase  in  the  future.  

46 Tourism  activity  is  likely  to  depend  on  the  overall  state  of  the  economy  and  is  therefore  also  difficult  to  predict.  VisitScotland  Consumer  Review  2012  (VisitScotland,  2012)  has  identified  that   the   current   economic   climate   has   led   to   consumers   becoming   more   cautious.   The  experience  of  the  holiday  is  now  seen  as  the  most  important  factor  when  booking  a  trip,  as  consumers   look   to   gain   an   unforgettable   experience   that   allows   them   to   gain   a   sense   of  achievement  and  authenticity  from  their  holiday.  

47 Public  access   is  expected  to  remain  as  present  or   increase  slightly  as  the  population   in  the  Study  Area  increases.    

48 Without  development  of  the  OnTW,  it  is  not  predicted  that  land  uses  within  the  Application  Site   will   change   significantly.   Outwith   the   Application   Site,   there   are   a   number   of  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

14 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 21: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

15 of 36

development  proposals  which  may  have  a  significant  change  on   land  use   in  the   immediate  vicinity  of  the  Application  Site.  These  development  proposal  are  discussed  in  Chapter  3  and  are  assessed  in  Section  12.12  of  this  Chapter.  

12.5 Assessment  Methodology  

12.5.1 Methodology  

49 There  is  no  prescribed  methodology  or  standard  guidance  for  assessing  the  socio-­‐economic  and  related  effects  in  EIA.  The  method  adopted  is  therefore  one  of  determining  the  existing  circumstances  (the  baseline  conditions)  through  desk  based  analysis.  The  potential   impacts  of   the   OnTW   on   this   baseline   are   then   identified,   taking   into   account   the   embedded  mitigation  measures  (see  Section  12.6  Mitigation  Measures  below).  Professional  judgement  is  then  applied  to  determine  the  significance  of  any  predicted  residual  effects.  

50 As  detailed  in  Chapter  3,  determining  the  significance  of  predicted  effects  is  a  function  of  the  magnitude   of   the   predicted   impact   and   the   sensitivity   of   the   receptor.   Whether   the  predicted  effect  is  considered  to  be  positive  or  negative  and  temporary  or  permanent  is  also  influential  in  determining  the  significance  of  effects.  

Magnitude  of  Impacts  

51 Criteria  for  determining  the  magnitude  of  impact  are  presented  in  Table  12.3.  

Table  12.3:  Determining  Magnitude  of  Predicted  Impacts  

Receptor  Criteria  for  Magnitude  of  Impacts  

High   Moderate   Low    

Employment  and  the  economy  

A   fundamental   change  to   baseline   business/  employment/  economic  conditions.    

A   detectable   but   not  fundamental   change   to  baseline   business/  employment/   economic  conditions.  

Little   change   to  baseline   business/  employment/  economic  conditions.  

Land  Use   A   fundamental   change  to   current   land   uses  and   compatibility   with  other   existing   land  uses   within   the   Study  Area.  

A   detectable   but   not  fundamental   change   to  current   land   uses   and  compatibility   with   other  existing  land  uses  within  the  Study  Area.  

Little   change   to  current   land   uses  and   compatibility  with   other   existing  land   uses   within   the  Study  Area.  

Tourism   A   fundamental   change  in   visitor   numbers   to  the   local   tourism  economy.  

A   detectable   but   not  fundamental   change   in  visitor   numbers   to   the  local  tourism  economy.  

Little   change   to  visitor   numbers   to  the   local   tourism  economy.  

Recreation   Permanent   or   long  term   effects   on   the  access/   recreation  resource.  

Longer   term   but  temporary   effects   on  the   access/   recreation  resource.  

Short   term  temporary  effects  on  the   access/  recreation  resource.  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

15 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 22: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

16 of 36

Sensitivity  of  Receptor  

52 Criteria  for  determining  the  sensitivity  of  receptors  are  presented  in  Table  12.4.  

Table  12.4:  Determining  Sensitivity  of  Receptors    

Receptor  Sensitivity  Criteria  

High   Moderate   Low    

Employment  and  the  economy  

The   business/  employment/  economic   conditions  would   have   a   low  capacity   to  accommodate   the  predicted  change.  

The   business/  employment/   economic  conditions   would   have  some   tolerance   to  accommodate   the  predicted  change.  

The   business/  employment/  economic   conditions  would   be   generally  tolerant   of   the  predicted  change.  

Land  Use   Nationally   important/  rare  land  use.  The  land  use   would   have   a   low  capacity   to  accommodate   the  predicted  change.  

Regionally   important/  rare   land   use.   The   land  use   would   have   some  tolerance   to  accommodate   the  predicted  change.  

Locally   important   land  use.   The   land   use  would   be   generally  tolerant   of   the  predicted  change.  

Tourism   Nationally   important  tourism   resource.   The  local  tourism  economy  would   have   a   low  capacity   to  accommodate   the  predicted  change.  

Regionally   important  tourism   resource.   The  local   tourism   economy  would   have   some  tolerance   to  accommodate   the  predicted  change.  

Locally   important  tourism   resource.   The  local   tourism  economy  would   be   generally  tolerant   of   the  predicted  change.  

Recreation   Nationally   important  access/   recreational  resource.   The   access/  recreation   resource  would   have   a   low  capacity   to  accommodate   the  predicted  change.  

Regionally   important  access/   recreational  resource.   The   access/  recreation   resource  would   have   some  tolerance   to  accommodate   the  predicted  change.  

Locally   important  access/   recreational  resource.   The   access/  recreation   resource  would   be   generally  tolerant   of   the  predicted  change.  

 

Assessment  of  Effect  Significance  

53 Using  the  above  criteria,  the  significance  of  predicted  effects  is  determined  using  the  matrix  in  Table  12.5  below.  Effects  that  are  predicted  to  be  major  and  moderate/major  are  deemed  to  be  significant  in  terms  of  the  EIA  Regulations.  

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

16 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 23: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

17 of 36

Table  12.5:  Determining  the  Significance  of  Effect  

Magnitude  of  Impact  

Sensitivity  of  Receptor  

High   Moderate   Low    

High   Major   Moderate/Major   Moderate  

Moderate     Moderate/Major   Moderate   Minor/Moderate  

Low   Moderate   Minor/Moderate   Minor  

Negligible   Minor/Moderate   Minor   Negligible  

 

12.6 Embedded  Mitigation  

54 The   assessment   of   effects   on   socio-­‐economic,   land   use,   recreation   and   tourism   receptors  has  taken  account  of  the  following  embedded  measures  to  minimise  environmental  effects:    

• The  Onshore  Substation  will  be   located   to  avoid  any  closure  of   the   route  of  Core  Path  144  and  the  Right  of  Way  during  all  phases  of  development;  

• Where  public  access  will  be  temporarily  disrupted  during  construction,  maintenance  or  decommissioning   activities,   a   suitable   diversion   which   minimises   the   length   of   path  affected  will  be  put   in  place  along  with  the  display  of  signage  at  each  end  of  the  route  where   the   route   is   diverted.   The   signage   will   detail   the   path   which   is   closed,   the  proposed  alternative   route   and   the  duration  of   the   closure.  All   signage  will   be   agreed  with   the   Access   Officer   for   ELC   prior   to   the   commencement   of   construction,  maintenance  or  decommissioning  activities.  Sustrans  will  also  be  notified  of  any  planned  closures  or  diversions  to  the  National  Cycle  Network,  with  information  disseminated  to  the  public  prior  to  and  during  the  route  diversion.  The  duration  of  all  temporary  closures  and   diversion  will   also   be  minimised   by   Inch   Cape  Offshore   Limited   (ICOL)   as   far   as   a  possible;  

• Where  technically  feasible,  ICOL  will  seek  to  use  Horizontal  Directional  Drilling  (HDD)  to  lay   the   Onshore   Export   Cables   under   the   B1348.   This   will   avoid   the   need   for   any  potential  closure  of  this  road.  However   in  the  event  that  HDD  is  not  feasible  and  open  cut  trenching  is  required  to  install  the  Onshore  Export  Cables,  as  detailed  in  Chapter  11,  a   local   traffic   management   scheme   will   be   put   in   place   to   minimise   any   potential  disruption  to  road  users  during  the  construction  works.  The  scheme  will  be  designed  in  consultation   with   the   local   community,   local   businesses,   ELC   and   Transport   Scotland.  During  these  works  ICOL  commit  to  maintaining  access  to  the  Prestonpans  Yachting  and  Boating  Club,  located  adjacent  to  the  Landfall,  at  all  times;  and  

• The   Onshore   Export   Cable   will   be   routed   to   avoid   any   interaction   or   other   potential  indirect  effects  on   the  proposed  Cockenzie  Gas  Pipeline  and  minimise   interaction  with  any  other  utilities  infrastructure.  In  the  event  that  the  proposed  site  access  track  crosses  the  proposed  Cockenzie  Gas  Pipeline  post  construction,   the   track  will  be   strengthened  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

17 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 24: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

18 of 36

and  best  practice  construction  methods  will  be  put  in  place  to  protect  the  pipeline.  The  method  of  track  strengthening  will  be  confirmed  at  the  detailed  design  stage.  

55 These  measures  will  be  delivered  as  part  of  the  OnTW  (see  Section  5.6).  

56 All  of   the  above  mitigation  measures  have  been  taken   into  account  when  determining   the  significance  of  effects  in  this  assessment.  

12.7 Impact  Assessment  –  Onshore  Transmission  Works    

12.7.1 Impacts  of  Construction  

Expenditure  

57 Development   projects   may   have   a   positive   effect   on   the   local   economy   as   a   result   of  financial  investment  for  a  number  of  businesses  who  may  supply  services  and  goods  during  construction.   The   significance   of   potential   effects   arising   from   expenditure   during   the  construction  of  the  OnTW  are  considered  below.  

58 The  total  capital  expenditure  for  the  OnTW  is  estimated  to  be  in  the  region  of  £60.5  million.  The   greatest   element   of   this   expenditure   will   be   for   the   Onshore   Substation,   the   cost   of  which  is  anticipated  to  cost  in  the  region  of  £50  million.  

59 Given   the   current   levels   of   employment   in   the   construction,   manufacturing   and  transportation   and   storage   sectors,   the   structure   of   the   local   economy   is   such   that   it   is  considered  to  have  the  capacity  to  benefit  from  expenditure  associated  with  the  OnTW.  The  sensitivity   of   the   receptor   is   therefore   considered   to   be   moderate.   Site   preparation   and  building  works  will   provide   opportunities   for  materials   and   construction   equipment   to   be  sourced   locally.   Although   these   will   represent   modest   proportions   of   the   total   capital  expenditure,  this  direct  expenditure  would  be  likely  to  re-­‐circulate  and  bring  some  benefits  to  the  local  economy.  However,  given  that  the  majority  of  the  capital  expenditure  will  be  for  specialist  equipment  that  is  likely  to  be  sourced  outwith  the  local  area,  the  magnitude  of  this  impact   is  considered  to  be   low.  Overall  a  positive  temporary  effect  of  minor  significance   is  therefore  anticipated  to  the  local  economy  from  project  expenditure  during  the  construction  phase.  

Employment  and  Economic  Activity  

60 All  development  projects  will  result  in  direct  employment  opportunities  as  well  as  potential  indirect  and  induced  employment  opportunities.  The  significance  of  potential  direct,  indirect  and  induced  employment  and  economic  activity  arising  from  the  construction  of  the  OnTW  are  considered  below.  

61 The  construction  of  the  OnTW  would  directly  support  around  40  FTE  jobs  for  a  period  of  up  to   24   months.   The   construction   of   the   OnTW   will   require   both   specialist   and   general  construction  labour  capabilities.  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

18 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 25: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

19 of 36

62 It   is   estimated   that   the   total   civil   construction   value   of   the   OnTW   will   be   approximately  £10.7  million.  The  majority  of  this  civil  construction  value  relates  to  the  Onshore  Substation,  the  value  of  which  will  be  approximately  £7.5  million.  

63 Given  the  current  levels  of  employment  in  the  construction  sector,  the  structure  of  the  local  economy   is   such   that   it   is   considered   to   have   the   capacity   to   benefit   from   construction  contracts  (in  particular  for  general  labour)  associated  with  the  OnTW.  The  sensitivity  of  this  receptor   is   therefore   considered   to   be   moderate.   However,   due   to   the   greater   level   of  specialist   construction   labour   which   will   be   required   there   will   be   a   greater   competitive  advantage  for  experienced  contractors  who  are  likely  to  be  located  outwith  the  local  area  in  Edinburgh  or  further  afield.  The  magnitude  of  this  impact  is  therefore  considered  to  be  low.  Overall   a   positive   temporary   effect   of  minor   significance   is   therefore   anticipated   to   direct  local  employment  during  the  construction  phase.    

64 Indirectly,   the  OnTW  may   also   create   further   employment   opportunities   down   the   supply  chain   for   those  companies  providing  services   to   the  contractors  during  the  construction  of  the  OnTW.  In  addition,  there  will  be  further  induced  economic  benefit  to  the  local  economy  relating   to   expenditure   from   workers   spending   their   income   in   local   businesses   such   as  shops,  pubs,  cafes  and  takeaways.  There  may  also  be  some  benefit  to  businesses  providing  accommodation  to  specialist  construction  workers,  albeit   it   is  anticipated  that  the  majority  of   workers   will   live   within   the   Central   Belt   of   Scotland   and   will   consequently   not   require  accommodation.  

65 The   capacity   of   the   local   economy   is   such   that   it   is   considered   to   have   the   capability   to  provide   such   services   to   contractors.   Consequently   the   sensitivity   of   this   receptor   can   be  assessed   as   moderate.   However,   given   the   anticipated   scale   of   additional   indirect   and  induced   employment,   the   magnitude   of   this   impact   is   considered   to   be   low.   Overall   a  positive  temporary  effect  of  minor  significance  is  therefore  anticipated  to  the  local  economy  from  indirect  and  induced  employment  and  economic  output  during  the  construction  phase.    

Land  Use  

66 As  discussed  in  Chapter  5  the  Onshore  Export  Cable  Corridor  will  be  approximately  1.3  km  in  length  from  Transition  Pits  to  the  Onshore  Substation  and  1  km  in  length  from  the  Onshore  Substation   to   the   grid   connection   point.   For   the   purposes   of   the   application   for   Planning  Permission   in   Principle   (PPP),   an   indicative   60  m   wide   area   has   been   identified   for  assessment.  The  exact  location  of  the  Onshore  Export  Cables  within  this  indicative  area  will  be  determined  based  on  site  investigation  and  the  conclusions  of  EIA.  All  construction  works  for  the  installation  of  the  Onshore  Export  Cables,  including  access  for  plant  and  vehicles,  will  take   place   within   this   Onshore   Export   Cable   Corridor.   A   maximum   total   area   of  approximately  9  ha  is  therefore  required  for  installation  of  the  Onshore  Export  Cables.  

67 In   addition   to   the   temporary   land   take   for   the   installation   of   the   Onshore   Export   Cables,  formation  of  the  temporary  construction  compound  next  to  the  Onshore  Substation  Site  will  also   require   occupation   of   an   area   of   approximately   1.7   ha   for   the   duration   of   the  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

19 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 26: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

20 of 36

construction  activities.  Permanent  land  take  effects  associated  with  the  Onshore  Substation  and  site  access  track  are  assessed  in  Section  12.7.2.  

68 The  construction  of  the  OnTW  (both  the  Onshore  Substation  and  the  Onshore  Export  Cable  and   associated   infrastructure)   will   therefore   require   the   direct   temporary   disturbance   of  approximately  10.7  ha  of   land  defined  as  countryside/agricultural.  However  given  that   this  land  is  not  currently  in  agricultural  use  it  is  considered  to  be  generally  tolerant  to  potential  disturbance.   The   sensitivity  of   this   receptor   is   therefore   considered   to  be   low.   Taking   into  account  that  outwith  the  Onshore  Substation  Site  that  construction  activities  will  only  take  place  within  a  small  part  of  the  Application  Site  at  any  one  point  in  time,  and  given  that  the  land  will  be  fully  restored  once  these  construction  activities  have  ceased,  the  magnitude  of  this  impact  is  considered  to  be  low.  Overall  a  temporary  negative  effect  of  minor  significance  is  therefore  predicted  on  countryside/agricultural  land  during  construction  of  the  OnTW.  

69 Potential   construction   effects   on   open   space   at   Preston   Links   and   on   public   access   and  recreation  are  considered  in  the  section  below.  

70 Potential   construction   effects   on   utilities   and   on   potential   hazards   from   former   mining  activities   are   considered   in  Chapter  6.   Potential   construction  effects  on   local   and   strategic  road   network,   including   traffic   disruption   and   accessibility,   are   considered   in   Chapter   11.  Potential  construction  effects  upon  the  residential  amenity  of  nearby  residential  properties  as  a  result  of  visual   impacts,  noise,  and  air  quality  are  considered  in  Chapters  8,  10  and  13  respectively.  

Public  Access  and  Recreation  

71 The   construction   phase   of   the   OnTW   has   the   potential   to   directly   disrupt   the   following  public  access  and  recreational  facilities  which  cross  through  or  lie  within  the  Application  Site:  

• The  John  Muir  Way;  

• NCR  76;  

• Core  Paths  144,  145,  146,  276  and  284  (and  associated  Rights  of  Way);  and  

• Preston  Links  open  space.  

72 The   John   Muir   Way   and   NCR   76   are   considered   to   be   the   most   sensitive   of   the   above  receptors  given  that  they  are  long  distance  promoted  routes  recognised  as  being  of  national  importance.   The   sensitivity   of   both   these   receptors   are   considered   to   be   high.  Given   that  Core   Path   276   forms   part   of   the   John   Muir   Way,   the   sensitivity   of   this   receptor   is   also  considered  to  be  high.  

73 Core  Paths  144,  145,  146  and  284  are  considered  to  be  of  no  more  than  regional  importance  and   consequently   the   sensitivity   of   these   receptors   are   assessed   as   being   moderate.  Assessment   of   the   sensitivity   of   the   Tranent   to   Cockenzie  Waggonway   (Core   Path   144)   in  cultural  heritage  terms  is  detailed  in  Chapter  9.  Preston  Links  is  considered  to  be  of  no  more  than  local  importance  and  consequently  the  sensitivity  of  this  receptor  is  assessed  as  being  low.  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

20 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 27: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

21 of 36

74 As   discussed   in   Chapter   5,   the   Onshore   Export   Cables   between   Landfall   and   the   Onshore  Substation  will  be  laid  in  up  to  four  separate  trenches  which  will  each  be  approximately  one  metre  wide.  It  is  anticipated  that  the  majority  of  the  Onshore  Export  Cables  will  be  installed  using   surface   cut   trenching.  However,   if   technically   feasible   some   sections  of   the  Onshore  Export  Cable  Corridor,  such  as  the  crossing  of  the  B1348,  may  be  undertaken  by  HDD.    

75 The   laying   of   the   Onshore   Export   Cable   will   result   in   the   temporary   diversion   of   a   short  section  of  the  John  Muir  Way  (and  Core  Path  276)  for  a  maximum  period  of  up  to  7  weeks.  Given  the  short  term  nature  of  the  diversion  and  the  very  slight  diversion  to  the  route  that  will  be  required,  the  magnitude  of  this  impact  is  considered  to  be  low.  Overall  a  temporary  negative  effect  of  moderate  significance  on  users  of  the  John  Muir  Way  and  Core  Path  276  is  therefore  anticipated  during  construction.  

76 In  the  event  that  HDD  is  not  technically  feasible  to  install  the  Onshore  Export  Cables  under  NCR76   and   open   cut   trenching   requires   to   be   undertaken,   a   local   traffic   management  scheme   will   be   put   in   place   to   minimise   any   potential   disruption   to   road   users   during  construction.  The  installation  of  the  Onshore  Export  Cables  under  this  route  is  anticipated  to  take   up   to   4   to   12   weeks.   With   this   mitigation   measure   in   place,   it   is   considered   that  potential  delays   to  cyclists  using  this   route  will  be  negligible.  Overall  a   temporary  negative  effect  of  minor  significance  at  worst  is  predicted  on  cyclists  using  NCR76  during  construction  of  the  OnTW.  

77 The  Onshore   Export   Cable  will   also   cross   Core   Path   284.   This  will   result   in   the   temporary  diversion  of  a  short  section  of  the  route  for  a  maximum  period  of  up  to  7  weeks.  Given  the  short  term  nature  of  the  diversion  and  the  slight  diversion  to  the  route  that  will  be  required,  the  magnitude  of  this  impact  is  considered  to  be  low.  Overall  a  temporary  negative  effect  of  minor  significance  on  users  of  Core  Path  284  is  therefore  anticipated  during  construction.  

78 Core   Paths   145   and   146   both   run   along   the  western   boundary   of   the   Application   Site.   As  outlined  in  Chapter  5,  the  exact  location  of  the  Onshore  Export  Cables  within  the  Application  Site  will  be  determined  following  site  investigation.  If  the  Onshore  Export  Cables  were  to  be  located  along  or  near   these   footpaths,   there  may  be   the  requirement   for  slight   temporary  diversions   to  both   these   routes   to  minimise  disruption   from   construction   activities   due   to  their  proximity  to  the  Onshore  Export  Cables.  The  magnitude  of  this  impact  is  considered  to  be  low.  Overall  a  temporary  negative  effect  of  minor  significance  on  users  of  Core  Paths  145  and  146  is  therefore  anticipated  during  construction  of  the  OnTW.  

79 The  Onshore  Substation  will  be  located  to  avoid  any  direct  effects  on  the  route  of  Core  Path  144  which  crosses  through  the  Application  Site,  both  during  construction  and  operation.  

80 There  will  be  a  requirement  for  temporary  closure  of  a  small  area  of  Preston  Links  during  the  construction  of   the  OnTW   to   facilitate   the   laying  of   the  Onshore  Export  Cables.  Given   the  remainder   of   the   open   space   at   Preston   Links   which   will   remain   accessible   during  construction  and  the  extent  of  other  amenity  open  space  in  the  local  area,  the  magnitude  of  this  impact  is  considered  to  be  low.  Overall  a  temporary  negative  effect  of  minor  significance  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

21 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 28: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

22 of 36

on   recreational   users   of   Preston   Links   is   therefore   anticipated   during   construction   of   the  OnTW.  

81 With  regard  to  public  access   in  general,  as   identified   in  Section  12.4  Baseline  Environment,  the   remainder   of   the   Onshore   Export   Cable   Corridor   and   the   Onshore   Substation   Site  outwith  Preston  Links  and  the  path  networks  assessed  above  is  less  well  used  for  access  and  recreational  use  but  is  considered  to  be  of  local  importance.  The  sensitivity  of  this  receptor  is   therefore   considered   to  be   low.  Construction  activities  will   result   in  a   temporary   loss  of  public  access  to  parts  of  the  Onshore  Export  Cable  Corridor  and  the  Onshore  Substation  Site  where   the   infrastructure   is   being   installed   and  materials   and   equipment   stored.   However  given   that   construction   works   will   progress   sequentially   throughout   the   Onshore   Export  Cable   Corridor   and   will   therefore   only   affect   public   access   to   a   small   part   of   the   overall  Application   Site   at   any   one   point   in   time,   the   magnitude   of   this   impact   is   therefore  considered   to   be   low.  Overall   a   temporary   negative   effect   of  minor   significance   on   public  access  to  the  Application  Site   in  general   is  therefore  anticipated  during  construction  of  the  OnTW.    

Tourism  

82 The  construction  phase  of  the  OnTW  has  the  potential  to  directly  disrupt  tourists  using  the  Golf  Coast  Road  which  crosses  through  the  Application  Site.  Given  the  importance  of  golf  to  the  economy  of  the   local  area,  East  Lothian  and  Scotland,  the  sensitivity  of  this  receptor   is  considered  to  be  high.  

83 Similar   to   the   effects   discussed   above  on   cyclists   using   the  NCR76  which   shares   the   same  route   as   the   Golf   Coast   Road,   in   the   event   that   open   cut   trenching   is   utilised   to   lay   the  Onshore  Export  Cables  under   the  B1348  a   local   traffic  management   scheme  will  be  put   in  place   to   minimise   any   potential   disruption   to   visitors   using   this   road   during   construction.  With   this   mitigation   in   place   it   is   considered   that   potential   delays   to   visitors   using   this  section   of   the   Golf   Coast   Road   will   be   negligible.   Overall   a   temporary   negative   effect   of  minor  significance  on  the  local  tourism  economy  is  therefore  predicted  at  worst  as  a  result  of   a   decrease   in   visitors   numbers   using   the   Golf   Coast   Road   during   construction   of   the  OnTW.    

84 The  construction  phase  of  the  OnTW  also  has  the  potential  to  indirectly  impact  upon  visitor  numbers  to  the  Battle  of  Prestonpans  Memorial  and  the  Battle  of  Prestonpans  Viewpoint  if  their   appreciation   of   the   current   view   were   to   be   notably   affected.   Both   these   tourism  attractions   are   considered   to   be   of   local   importance   to   tourism   and   consequently   are  assessed  as  being  of   low  sensitivity   in   this   regard.  This   judgement   reflects   the  current   low  visitor  numbers  observed  to  both  these  attractions.  

85 The  landscape  and  visual  impact  assessment  in  Chapter  8  identifies  that  visitors  to  the  Battle  of  Prestonpans  Viewpoint  are  predicted  to  experience  temporary  effects  of  major/moderate  significance  on  their  view  as  a  result  of  the  construction  works  and  associated  machinery  at  the   Onshore   Substation   Site.   Although   it   should   be   recognised   that   the   view   may   be  regarded  by  some  visitors  as  an   important  reason  for  visiting  the  site,   it   is  considered  that  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

22 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 29: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

23 of 36

the  cultural  heritage  value  of  the  battlefield  and  gaining  an  understanding  of  how  the  battle  was   fought   are   likely   to   be   the   primary   reason   for   the  majority   of   visitors   to   the   site.   As  detailed   in   Chapter   9,   these   values   will   not   be   significantly   affected   by   the   proposed  construction  works.   Consequently   it   is   concluded   that   the  number  of   visitors  who  may  be  deterred   by   the   visual   impact   of   the  OnTW  will   be   small   at  worst.   The  magnitude   of   this  impact  is  therefore  considered  to  be  moderate.  Overall  a  temporary  negative  effect  of  minor  significance  is  therefore  predicted  at  worst  on  the  local  tourism  economy  as  a  result  of  any  decrease  in  visitor  numbers  to  the  Battle  of  Prestonpans  site.    

No   potential   for   any   other   direct   or   indirect   effects   upon   visitor   numbers   to   any   other  tourism  routes  or  attractions  within  the  Tourism  Study  Area  during  the  construction  of  the  OnTW  is  predicted  to  occur.  

12.7.2 Impacts  of  Operation  and  Maintenance  

Employment  and  Economic  Activity  

86 The  Onshore  Substation  will   not  normally  be  manned  and   staff  will   only  be  on   site  during  maintenance  or   for  repair  work.  Typically,   these  activities  will   require  up  to  a  maximum  of  five   staff   for   five   days,   once  or   twice   a   year   over   the   lifetime  of   the  OnTW.   There  will   be  opportunities   for  suitable  qualified   locally  based  contractors   to  carry  out   this  maintenance  work.  ICOL  will  implement  a  protocol  to  enable  suitably  qualified  locally  based  contractors  to  tender  for  work  in  relation  to  the  construction  and  operation  of  the  OfTW.  

87 The   structure   of   the   local   economy   is   such   that   it   is   considered   to   have   the   capacity   to  benefit   from   these  operational   employment  opportunities.   Consequently   the   sensitivity   of  this   receptor   can   be   assessed   as   moderate.   However,   given   the   very   small   scale   of  employment   opportunities   associated  with   the   operation   of   the  OnTW,   the  magnitude   of  this  impact  is  considered  to  be  negligible.  Overall  a  positive  effect  of  negligible  significance  is  therefore  predicted  to  direct  local  employment  during  the  operational  phase.  

Land  Use  

88 During  the  operational  phase,  all  of  the   land  within  the  Onshore  Export  Cable  Corridor  will  have  been   fully   restored  to   its   former  use.  Following  this   restoration,   the  operation  of   the  Onshore   Export   Cables   is   not   predicted   to   have   any   potentially   significant   effects   upon  countryside/agricultural  land  use.  

89 The   footprint     of   the   Onshore   Substation   Site   will   be   approximately   2.7   ha   (including  screening).  

90 Given   that   the   land   upon   which   the   Onshore   Substation   will   be   located   comprises   rough  grassland  which  is  not  currently  in  agricultural  use,  the  sensitivity  of  this  receptor  is  consider  to  be  low.  Taking  into  account  the  small  magnitude  of  the  landtake,  and  the  fact  that  it  will  not  result   in   loss  or  severance  of  access  to  other  surrounding   land  for  agricultural  use,  the  magnitude   of   this   impact   is   considered   to   be   low.   Overall   a   negative   effect   of   minor  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

23 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 30: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

24 of 36

significance   is   therefore  predicted  on  countryside/agricultural   land  during  operation  of   the  OnTW.  

91 Potential   effects   on   open   space   at   Preston   Links   and   on   public   access   and   recreation   are  considered  in  the  section  below.  

92 Potential   operational   and   maintenance   effects   on   utilities   and   on   potential   hazards   from  former  mining  activities  are  considered  in  Chapter  6.  Potential  operational  and  maintenance  effects   on   traffic   on   the   local   and   strategic   road   network   are   considered   in   Chapter   11.  Potential   operational   and   maintenance   effects   upon   the   residential   amenity   of   nearby  residential  properties  as  a   result  of   visual   impacts,  noise,  and  air  quality  are  considered   in  Chapters  8,  10  and  13  respectively.  

Public  Access  and  Recreation  

93 As  detailed   in  Section   12.6,   it   is   confirmed   that   the  Onshore   Substation  will   be   located   to  avoid  any  direct  effects  on  the  route  of  Core  Path  144.  Consequently  there  is  no  potential  for  direct  effects  on  Core  Path  144.  

94 Given  the  land  for  the  Onshore  Export  Cable  Corridor  will  be  fully  restored  to  its  former  use  during  the  operational  phase  of  the  OnTW,  there  is  no  potential  for  direct  impacts  upon  any  other  public  access  and  recreational  facilities  that  cross  or  lie  within  the  Application  Site.  The  only   exception   to   this  would   be   for   infrequent  maintenance   activities   (approximately   one  day  per  year)  or  in  the  unlikely  event  that  a  fault  occurs  on  a  section  of  the  Onshore  Export  Cable  and  requires  to  be  repaired  and/or  replaced.  

95 In   the   event   that   a   fault   does   occur   along   a   section   of   the   Onshore   Export   Cable,   the  potential   direct   effects   on   public   access   and   recreation   with   the   Application   Site   is  considered   to  be  equivalent   to  and  potentially   lower   than   the  effects  anticipated   to  occur  during   the   construction   phase.   Overall,   at   worst,   a   temporary   negative   direct   effect   of  moderate   significance   is   therefore   predicted   to   public   access   and   recreational   resources  within   the   Application   Site   in   the   unlikely   event   that   a   fault   occurs   on   a   section   of   the  Onshore  Export  Cable.  

Tourism  

96 Once   operational,   the   landscape   and   visual   impact   of   the   Onshore   Substation   has   the  potential  to  indirectly  impact  upon  visitor  numbers  to  tourism  routes  and  attractions  within  the  Tourism  Study  Area.  

97 The  actual  impacts  on  visitors  is  difficult  to  assess  given  that  people’s  views  on  the  landscape  and   visual   effects   of   developments   are   entirely   subjective.   For   example,   even   at   locations  where  the  Onshore  Substation  is  a  feature  in  the  landscape,  for  some  visitors  this  may  have  no   effect   on   their   enjoyment   and   their   future   propensity   to   visit,   whilst   for   others   the  presence  of  the  Onshore  Substation  may  decrease  their  enjoyment  and  propensity  to  revisit.    

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

24 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 31: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

25 of 36

98 As   identified   in   the  baseline  Section  12.4  of   this   chapter,   it   is   important   to   note   the  most  popular  tourist  attractions  within  East  Lothian  are  located  outwith  the  Tourism  Study  Area  at  distances  of  approximately  7  to  23  km  from  the  Application  Site  where  there  is  no  potential  for  any  adverse   indirect   impact  upon   their  use  as  a   result  of   visual  effects  of   the  Onshore  Substation.    

99 Figure   12.4   identifies   those   tourism   routes   and   attractions  within   the   Tourism   Study  Area  that   have   theoretical   visibility   of   the   Onshore   Substation.   However,   as   discussed   in   the  landscape   and   visual   impact   assessment   in   Section   8.4.3,   the   zone   of   theoretical   visibility  illustrates   the   bare   earth   situation,   not   taking   into   account   the   screening   impacts   of  vegetation,  buildings,  or  other   local   features  that  may  prevent  or  reduce  visibility.  The  ZTV  therefore   illustrates   a   maximum   theoretical   visibility   scenario.   Field   surveys   have  demonstrated  that  actual  visibility  of   the  Onshore  Substation  within   the  Study  Area  would  be  much  reduced  as  a  result  of  existing  vegetation  as  well  as  local  landforms  (not  captured  by  the  Ordnance  Survey  data)  and  buildings.  

100 On   the   basis   of   the   conclusions   of   the   landscape   and   visual   impact   assessment,   it   is  considered   that   the   only   visitor   attraction   within   the   Tourism   Study   Area   that   has   the  potential  to  experience  a  decrease  in  visitor  numbers  due  to  the  landscape  and  visual  impact  of   the   Onshore   Substation   will   be   the   Battle   of   Prestonpans   Viewpoint.   The   potential  impacts  upon  this  tourist  attraction  are  discussed  below.  

101 The   landscape   and   visual   impact   assessment   identifies   that   visitors   to   the   Battle   of  Prestonpans  Viewpoint  are  predicted  to  experience  landscape  and  visual  impacts  which  will  be  major   and   of   significant   effect   at   Year   1.   At   year   15   of   operation  with   the   established  vegetation  of  the  Landscape  Mitigation  (see  Section  8.5.2)   the  magnitude  of  change  would  be  slight  and  the  overall  impact  moderate.    

102 Although   it   should  be   recognised   that   the  view  may  be   regarded  by   some  visitors  as   their  primary   reason   for   visiting   the   site,   it   is   considered   that   the   cultural   heritage   value  of   the  battlefield  and  gaining  an  understanding  of  how  the  battle  was   fought  are   likely   to  be   the  primary   reason   for   the  majority   of   visitors   to   the   viewpoint.   As   detailed   in  Chapter   9,   the  setting   of   the   Battle   of   Prestonpans   battlefield   was   assessed   from   a   variety   of   locations  including   the   coal   bing   viewpoint   (The   Battle   of   Prestonpans   viewpoint).   Buildings,  topography  and  dense  mature  trees  and  vegetation  between  this  viewpoint  and  Cockenzie  coal  store  suggests  the  Onshore  Substation  would  be  slightly  visible  from  the  bing  viewpoint  but   would   appear   below   the   horizon   in   an   area   already   dominated   by   trees   in   the  foreground  and  by  the  industrial  structures  of  the  Cockenzie  coal  store  below  the  horizon.  In  views   from   this   location   the  Onshore   Substation  will   appear  below   the  horizon   in   an   area  already  characterised  by  modern  industrial  development.  

103 Consequently  it  is  concluded  that  the  number  of  visitors  who  may  be  deterred  from  visiting  the   viewpoint   will   be   small.   The   magnitude   of   this   impact   is   therefore   considered   to   be  minor  at  worst.  Overall  a  negative  effect  of  minor  significance  is  therefore  predicted  at  worst  on   the   local   tourism  economy  as  a   result  of  a  decrease   in  visitor  numbers   to   the  Battle  of  Prestonpans  site.  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

25 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 32: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

26 of 36

12.7.3 Impacts  of  Decommissioning    

104 The   potential   impacts   of   decommissioning   are   considered   to   be   equivalent   to   and  potentially   lower   than   the   worst   case   impacts   assessed   for   the   construction   phase.   The  assessment  findings  are  therefore  presented  for  construction  and  operational  phases  of  the  OnTW   only,   assuming   that   the   impacts   during   the   construction   will   apply   to   the   impacts  during  decommissioning.  The  approach  to  decommissioning  is  described  in  Chapter  5.    

12.8 Impact  Interactions  

105 The   potential   for   individual   impacts   identified   through   the   impact   assessment   above   to  interact  and  create   significant  effects  on   the   identified   receptors  has  been  considered.  No  such  potential  interactions  have  been  identified.  

12.9 Additional  Mitigation    

106 On   the   basis   of   the   findings   that   there   will   be   no   significant   socio-­‐economic,   land-­‐use,  recreation   and   tourism   effects   as   a   result   of   the   construction,   operational   and  decommissioning  phases  of  the  OnTW  following  implementation  of  the  embedded  measures  identified   in   Section   12.6   of   this   chapter,   no   requirement   for   any   additional   additional  mitigation  has  been  identified.  

12.10 Conclusions  and  Assessment  Summary  

107 This  assessment  of  the  OnTW  has  considered  effects  on  socio-­‐economic,  land  use,  recreation  and   tourism.   The   key   findings   of   the   assessment   are   summarised   in   Table   12.6   below.  Overall,  no  significant  adverse  effects  are  predicted  for  socio-­‐economic,  land  use,  recreation  and  tourism.    

Table  12.6:  Summary  of  Residual  Effects    

Receptor   Effect   Nature  of  Effect   Significance  of  Effect  

Construction  and  Decommissioning  

Employment  and  the  economy  

Temporary  direct,  indirect  and  induced  employment  

Positive   Minor  (not  significant)  

Land  Use   Temporary  loss  of  countryside/agricultural  land  

Negative   Minor  (not  significant)  

Public  Access  and  Recreation  

Temporary  diversion  of  the  John  Muir  Way  and  Core  Path  276  (and  associated  Right  of  Way)  

Negative   Moderate  (not  significant)  

Public  Access  and  Recreation  

Temporary  disruption  to  cyclists  using  NCR76  

Negative   Minor  (not  significant)  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

26 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 33: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

27 of 36

Receptor   Effect   Nature  of  Effect   Significance  of  Effect  

Public  Access  and  recreation  

Temporary  diversion  to  users  of  Core  Paths  144,  145,  146  and  284  (and  associated  Rights  of  Way).  

Negative   Minor  (not  significant)  

Public  Access  and  Recreation  

Temporary  loss  of  recreational  open  space  at  Preston  Links.  

Negative   Minor  (not  significant)  

Public  Access  and  Recreation  

Temporary  loss  of  public  access  to  the  Application  Site.  

Negative   Minor  (not  significant)  

Tourism  Economy   Temporary  traffic  disruption  to  visitors  using  the  Golf  Coast  Road  resulting  in  a  decrease  in  visitor  numbers.  

Negative   Minor  (not  significant)  

Tourism  Economy   Temporary  adverse  visual  effects  on  the  Battle  of  Prestonpans  Viewpoint  resulting  in  a  decrease  in  visitor  numbers.  

Negative   Minor  (not  significant)  

Operation  and  Maintenance  

Employment  and  the  Economy  

Direct,  indirect  and  induced  employment.  

Positive   Negligible  (not  significant)  

Land  Use   Loss  of  countryside/  agricultural  land  due  to  the  Onshore  Substation.  

Negative   Minor  (not  significant)  

Public  Access  and  Recreation  

No  direct  effects  are  predicted  as  a  result  of  the  operation  of  the  OnTW  given  the  Onshore  Export  Cable  Corridor  will  be  fully  restored  once  constructed  and  the  Onshore  substation  will  be  located  to  avoid  any  closure  of  Core  Path  144.    

N/A   N/A  

Tourism  economy  

Adverse  visual  effects  on  the  Battle  of  Prestonpans  Viewpoint  resulting  in  a  decrease  in  visitor  numbers.  

Negative  

 

Minor  (not  significant)  

 

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

27 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 34: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

28 of 36

12.11 Cumulative  Impacts  –  Onshore  Transmission  Works  and  Offshore  Wind  Farm  

108 This  section  considers  the  potential  cumulative  effects  upon  employment,  economic  activity  and   tourism   that   are   predicted   to   arise   during   the   construction,   operational   and  decommissioning   phases   of   the   OnTW   in   combination   with   the   Inch   Cape   Offshore   Wind  Farm  and  associated  Offshore  Transmission  Works  (OfTW).  Potential  effects  upon   land  use  and  potential  direct  effects  upon  public  access  and  recreation  are  not  considered  given  there  is   no   potential   for   cumulative   effects   with   regard   to   either   of   these   topics   due   to   their  geographical  separation.  

12.11.1 Impacts  of  Construction  

Employment  and  Economic  Activity  

109 The   Socio-­‐Economic   Assessment   within   the   Inch   Cape   Offshore   Wind   Farm   ES   (Section  22.7.2)   (ICOL,   2013)  estimates   that   a   total   of   2,244  FTE   jobs  will   be   created   in   association  with   the   construction   of   the   OfTW   and   the   Inch   Cape   Offshore   Wind   Farm.   However   the  majority   of   these   jobs   will   be   for   specialist   skilled   labour   that   will   most   likely   be   located  outwith   the   local   area,   for   example   in   Edinburgh   (Leith),   Rosyth   (Fife),   Dundee   and   the  Cromarty  Firth  (Highland)  and  further  afield.   It   is   therefore  considered  that  the  addition  of  the  employment  associated  with  the  OfTW  and  the  Inch  Cape  Offshore  Wind  Farm  will  not  result   in  a   significantly  greater  effect  upon  employment  and  economic  activity   in   the   local  area  than  that  predicted  to  occur  during  the  construction  of  the  OnTW  in  isolation.  

110 Although   the  construction  of   the  OnTW   in  combination  with   the   Inch  Cape  Offshore  Wind  Farm   and  OfTW  will   not   result   in   a   significant   effect   on   the   local   economy,   it   is   however  important  to  note  that  the  significant  employment  and  economic  opportunities  presented  to  the  East  Coast  of  Scotland  and  further  afield  by  the  development  of  the  Inch  Cape  Offshore  Wind  Farm  are  entirely  dependent  upon  the  development  of  the  OnTW.  These  opportunities  include  the  development  of  business  and  industry  networks,  infrastructural  strengthening  of  various   ports,   skills   and   training   initiatives   and   attracting   major   international   energy  investors   and  manufacturing   businesses.   The   importance   of   these   economic   opportunities  should  consequently  not  be  ignored  when  considering  the  economic  effects  of  the  OnTW.  

Tourism  

111 The  effects  of  both  the  OnTW  and  the  OfTW  on  tourism  will  be  indirect  and  will  be  related  to  the  impacts  of  visual  effects  on  visitor  numbers.  

112 There  will  be  construction  activity  related  to  both  the  OnTW  and  the  OfTW  occurring  at  the  same  time  in  the   intertidal  area.  However,   it   is  considered  that  members  of  the  public  will  perceive   these   activities   as   part   of   the   same   project   and   that   consequently   the   predicted  effects  on  tourism  will  be  no  greater  than  those  predicted  to  occur  during  the  construction  of  the  OnTW  in  isolation.  

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

28 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 35: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

29 of 36

12.11.2 Impacts  of  Operation  and  Maintenance  

Employment  and  Economic  Activity  

113 The   Socio-­‐Economic   Impact   Assessment   within   the   Inch   Cape   Offshore   Wind   Farm   ES  (Section   22.7.3)   (ICOL,   2013)   identifies   that   there  would   be   between   72   and   104   onshore  based  FTE  jobs  created  as  a  result  of  operational  and  maintenance  activities.  However,  the  majority   of   these   jobs   will   again   be   for   specialist   skilled   labour   that   will   most   likely   be  located   outwith   the   local   area.   It   is   therefore   considered   that   the   addition   of   the  employment  associated  with  the  Inch  Cape  Offshore  Wind  Farm  and  OfTW  will  not  result  in  a  significantly  greater  effect  upon  employment  and  economic  activity  in  the  local  area  than  that  predicted  to  occur  during  the  construction  of  the  OnTW  in  isolation.  

114 As  with  construction  employment  effects,  it  is  important  again  to  note  that  the  employment  and  economic  opportunities  to  the  East  Coast  of  Scotland  and  further  afield  as  a  result  of  the  development   of   the   Inch   Cape   Offshore   Wind   Farm   are   entirely   dependent   upon   the  development   of   the   OnTW   and   its   continued   maintenance.   The   importance   of   this   effect  should  consequently  not  be  ignored  when  considering  the  economic  effects  of  the  OnTW.    

Tourism  

115 The  effects  of  both  the  OnTW  and  the  OfTW  on  tourism  will  be  indirect  and  will  be  related  to  the  impacts  of  visual  effects  on  visitor  numbers.  

116 The   Seascape,   Landscape   and   Visual   Impact   Assessment   (SLVIA)   within   the   Inch   Cape  Offshore  Wind   Farm   ES   (Section   16.16)   identifies   that   significant   effects   are   predicted   for  tourism  visitors  at  distances  of  up  to  approximately  35  km  with  open  sea  views  towards  the  Inch  Cape  Offshore  Wind  Farm.    

117 The   Inch   Cape   Offshore   Wind   Farm   will   be   over   50   km   away   from   any   of   the   tourist  attractions  in  the  Tourism  Study  Area.  Consequently  it  is  concluded  that  the  visual  impact  of  the   Inch  Cape  Offshore  Wind  Farm  will  have  no  significant   impact  upon  visitor  numbers  to  the   tourist   routes   and   attractions   in   the   Tourism   Study   Area.   No   significant   cumulative  effects   are   therefore   predicted   on   tourism   as   a   result   of   the   operation   of   the   Inch   Cape  Offshore  Wind  Farm  and  the  OnTW  in  combination.  

12.11.3 Impacts  of  Decommissioning    

118 The  potential  cumulative  impacts  of  decommissioning  of  the  OnTW  in  combination  with  the  decommissioning   of   the   Inch   Cape   Offshore   Wind   Farm   and   OfTW   are   considered   to   be  equivalent   to   and   potentially   lower   than   the   worst   case   impacts   assessed   for   the  construction  phase.   The  assessment   findings  are   therefore  presented   for   construction  and  operational   phases   of   the   OnTW   only,   assuming   that   the   cumulative   impacts   during   the  construction  will  apply  to  the  impacts  during  decommissioning.  

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

29 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 36: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

30 of 36

12.12 Cumulative  Impacts  –  Onshore  Transmission  Works  and  Other  Projects  

119 This  section  considers  the  potential  cumulative  effects  that  are  predicted  to  arise  during  the  construction,  operation  and  decommissioning  phases  of   the  OnTW  in  conjunction  with  the  following  other  development  proposals:  

• The  proposed  Cockenzie  Combined  Cycle  Gas  Turbine  (CCGT)  Power  Station;  

• The  proposed  Cockenzie  Gas  Pipeline;  and    

• The  proposed  Blindwells  New  Settlement.  

120 Further  details  on  each  of  the  above  development  proposals  is  contained  in  Chapter  3.  

121 An   Environmental   Scoping   Report   was   submitted   in   April   2014   for   an   Energy   Park   at  Cockenzie  by  Scottish  Enterprise.  The  detail  of  the  scale,  location  and  composition  of  future  development   is   not   yet   known   and   will   evolve   over   time   as   consultation   with   key  stakeholders  progresses.  

122 The  timescales  for  taking  forward  the  Cockenzie  Energy  Park  are  not  known  at  this  time.  It  is  expected  that  an  application  for  Planning  Permission  in  Principle  will  be  submitted  in  2015.  For   this   reason   and   given   the   uncertainty   regarding   the   scale   and   composition   of   future  development,  it  has  not  been  considered  in  the  cumulative  assessment  in  this  ES  because  it  is  only  at  the  scoping  stage  and  there  is  currently  insufficient  information  on  which  to  base  an  assessment  of  the  impacts  of  this  development  (see  Section  3.6.2  for  more  information).  

12.12.1 Impacts  of  Construction  

Employment  and  Economic  Activity  

123 In  the  absence  of  detailed  construction  programmes  for  the  other  development  proposals,  it  is   difficult   to   predict   which   of   the   above   development   proposals   might   be   constructed   in  parallel  or   in  close  sequence  with  the  OnTW.  This  will  have   implications  for  the  number  of  construction  workers  required  at  any  one  time  in  the  local  area  and  may  result  in  increased  local  employment  opportunities  and/or  the  import  of  construction  labour  into  the  local  area  during   peak   periods   of   construction   activity.   The   import   of   construction   workers   into   the  local   area   will   provide   a   short   term   economic   benefit   as   a   result   of   the   need   to  accommodate  these  workers  however  may  also  have  other  effects  such  as  reducing  tourist  bed  availability.  

124 The   ES   for   the   proposed   CCGT   power   station   (Scottish   Power,   2009)   identifies   that   its  construction  will   create  between  564  and  627  FTE   jobs  within   the   local  area  and  a   further  243  to  270  FTE  jobs  in  the  regional  area  during  its  83  month  construction.  This  is  deemed  to  be  a  temporary  positive  effect  of  major  significance  in  the  ES.  Indirect  and  induced  effects  on  the  local  economy  are  not  assessed  in  the  ES  but  are  also  likely  to  be  significant.  

125 The   ES   for   the   proposed  Cockenzie  Gas   Pipeline   (Scottish   Power,   2010)   identifies   that   the  total  construction  labour  workforce  is  expected  to  total  approximately  200.  The  construction  period   for   the   proposed   Cockenzie   Gas   Pipeline   is   expected   to   last   for   nine   to   twelve  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

30 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 37: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

31 of 36

months.   The   ES   for   the   proposal   considers   that   its   construction   will   have   a   temporary  positive  effect  of  minor  significance  in  terms  of  local  employment,  and  a  temporary  positive  effect   of   moderate   significance   in   terms   of   indirect   and   induced   effects   on   the   local  economy.  

126 The   ES   for   the   proposed   Blindwells   New   Settlement   (SRG   Estates,   March   2011)   does   not  identify   the   direct,   indirect   or   induced   effects   on   employment   and   the   local   economy.  However,  given  the  scale  of  the  development  it  is  anticipated  that  it  would  have  a  significant  temporary  benefit  to  employment  and  the  local  economy  during  its  construction.    

127 On  the  basis  of  the  above  it  is  considered  that  the  construction  of  the  cumulative  projects,  if  more   than   one   are   built   in   parallel   or   overlapping   each   other,   will   have   a   significant  temporary  effect  on  direct   local  employment  and  on  the   local  and  regional  economy  from  indirect  and  induced  employment  and  economic  activity.  However  it   is  not  considered  that  the   addition   of   the   OnTW   to   this   potential   cumulative   baseline   will   result   in   a   further  significant   effect   due   to   the   small   levels   of   direct   employment   and   indirect   and   induced  benefits  that  the  construction  of  the  OnTW  will  generate.    

Land  Use  

128 The   CCGT   proposals   will   be   on   brownfield   land,   whilst   the   proposed   Blindwells   New  Settlement   will   be   on   land   which   the   ES   for   the   Blindwells   proposal   (SRG   Estates,   March  2011)  acknowledges  has  not  been  reused  since  its  return  to  agricultural  status  after  previous  mining  activity.  

129 Although  the  proposed  Cockenzie  Gas  Pipeline  will  result  in  temporary  loss  of  approximately  175   ha   of   predominantly   Class   1   and   Class   2   agricultural   land,   given   the   extent   of   such  agricultural   land  in  East  Lothian  and  the  fact  this   loss  will  only  be  temporary  the  ES  for  the  proposed  Cockenzie  Gas  Pipeline  (Scottish  Power,  2010)  considers  that  this   loss  will  not  be  significant.   It   is   not   considered   that   the   addition   of   the   loss   of   a   further   10.7   ha   of   land  defined   as   countryside/agricultural   as   a   result   of   the   construction   of   the   OnTW   in  combination  with  the  proposed  CCGT  would  have  the  potential  for  a  significant  cumulative  effect  on  agricultural  land  use.  

130 The   consented   Cockenzie   Gas   Pipeline   corridor   includes   parts   of   the   Application   Site  however  the  consent  for  the  gas  pipeline  includes  a  degree  of  flexibility  in  terms  of  allowing  the  final  routing  of  the  gas  pipeline  within  the  geographic  area  which,  in  accordance  with  the  EIA  Regulations,   has  been   subject   to   full   EIA.   This   flexibility   allows   the   final   routing  of   the  pipeline  approximately  250  m  either  side  of  the  proposed  pipeline  route  along  the  majority  of   its   length,   although   it   is   acknowledged   that   where   the   proposed   Pipeline   route   enters  more  urban  areas  at  its  western  end,  the  potential  for  flexibility  is  reduced.  The  gas  pipeline  would  not  be  located  within  the  Onshore  Substation  Site.  

131 Potential   cumulative   construction   effects   on   open   space   at   Preston   Links   and   on   public  access  and  recreation  are  considered  in  the  section  below.  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

31 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 38: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

32 of 36

132 Potential   cumulative   construction   effects   on   Scottish   Water   Utilities   and   on   potential  hazards   from   former   mining   activities   are   considered   in   Chapter   6   Potential   cumulative  construction   effects   on   traffic   on   the   B1348   and   the   local   and   strategic   road   network   are  considered   in   Chapter   11.   Potential   cumulative   construction   effects   upon   the   residential  amenity  of  nearby  residential  properties  as  a  result  of  visual   impacts,  noise,  and  air  quality  are  considered  in  Chapters  8,  10  and  13  respectively.  

Public  Access  and  Recreation  

133 The  ES  for  the  proposed  Cockenzie  Gas  Pipeline  (Scottish  Power,  2010)  identifies  that  a  safe  means  of  crossing  the  working  width  of  the  cable  will  be  provided  at  all  footpaths  that  cross  through  the  site  during  construction  activities.  On  this  basis  it  is  considered  that  there  is  no  potential   for   significant   direct   cumulative   effects   upon   public   access   and   recreation   as   a  result  of  its  construction  in  parallel  or  close  succession  with  the  construction  of  the  OnTW.  

134 The   proposed   CCGT   power   station   will   be   constructed   mainly   within   the   footprint   of   the  existing   Cockenzie   Power   Station.   However   the   ES   for   this   proposed   CCGT   power   station  (Scottish  Power,  2009)  identifies  that  there  will  be  a  temporary  loss  of  a  small  area  of  open  space  at  Preston  Links   (as  well   as  at  Whin  Park  Playing  Fields)  during  construction.  The  ES  concludes   that   this   will   result   in   temporary   adverse   effect   on   recreational   open   space  provision   of  minor   significance.  Given   the   equally   small   extent   of   recreational   open   space  that  will   require  to  be  temporarily  closed  as  a  result  of  the  construction  of  the  OnTW,   it   is  not   considered   that   there   is   potential   for   significant   direct   cumulative   effects   upon  recreation  in  the  local  area  as  a  result  of  the  construction  of  the  consented  CCGT  proposals  in  parallel  or  close  succession  with  the  construction  of  the  OnTW.  

135 No  potential   for  significant  direct  cumulative  effects  upon  public  access  and  recreation  are  predicted  to  occur  as  result  of  the  construction  of  the  proposed  Blindwells  New  Settlement  in  parallel  or  close  succession  with  the  construction  of  the  OnTW.  This  conclusion  is  made  on  the  basis  that  public  access  to  the  site  at  present  is  actively  discouraged  for  safety  reasons.  

Tourism  

136 The  ES   for   the  proposed  CCGT  power   station   (Scottish  Power,  2009)  does  not   identify  any  potential   for   adverse   impacts   upon   tourism   as   a   result   of   the   construction   of   the  development.   Likewise   the   ES   for   the   proposed   Cockenzie   Gas   Pipeline   (Scottish   Power,  2010)  did  not   identify   the  potential   for  any  adverse   impact  upon   tourism  as  a   result  of   its  construction.   Consequently   it   is   not   considered   that   there   is   the   potential   for   significant  effects   upon   the   local   tourism   economy   as   a   result   of   the   construction   of   the   OnTW   in  combination  with  either  or  both  of  these  development  proposals.  

137 The   ES   for   the   proposed   Blindwells   new   settlement   (Scottish   Resources   Group,   2011)  identifies  that  the  construction  of  the  development  will  result  in  disruption  to  visitors  using  the   A198   between   the   between   the   Bankton   and   Meadowmill   roundabouts.   The   ES  concludes   that   this   will   result   in   temporary   adverse   effect   on   tourist   visitor   numbers   of  minor  significance.  As  detailed  in  Chapter  11  of  this  ES,  although  this  route  will  also  be  used  for   traffic   for   the   construction   of   the   OnTW,   the   percentage   increase   in   cumulative   total  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

32 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 39: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

33 of 36

construction  vehicles  along  the  A198  should  construction  of  both  development  occur  at  the  same   time   would   not   be   significant.   Consequently   it   is   not   considered   that   there   is   the  potential  for  significant  cumulative  effects  on  tourists  visitor  numbers  and  associated  effects  on   the   local   tourism   economy   due   to   traffic   disruption   should   both   developments   be  constructed  at  the  same  time.  No  potential  for  any  other  adverse  effects  upon  tourism  are  identified  in  the  ES  for  the  proposed  Blindwells  new  settlement.  

12.12.2 Impacts  of  Operation  and  Maintenance  

Employment  and  Economic  Activity  

138 The   ES   for   the   proposed   CCGT   power   station   (Scottish   Power,   2009)   and   the   ES   for   the  proposed   Cockenzie   Gas   Pipeline   (Scottish   Power,   2010)   both   conclude   that,   once  operational,  that  these  development  will  result  in  a  negligible  effect  on  the  local  economy  in  term   of   employment   and   economic   activity.   Given   the   very   small   scale   of   employment  opportunities   associated   with   the   operation   and   maintenance   of   the   OnTW,   it   is   not  considered  that  the  addition  of  the  OnTW  to  this  cumulative  scenario  has  the  potential  for  a  significant  positive  effect  on  the  local  economy.  

139 The  ES   for   the  proposed  Blindwells  new  settlement   (Scottish  Resources  Group,  2011)  does  not   discuss   the   economic   benefits   to   the   local   area   once   operational.   However,   it   is  considered   on   the   basis   of   the   extent   of   employment   land   to   be   provided   that   there  will  likely  be  a  significant  beneficial  effect  on  the  local  economy  in  terms  of  direct  employment.  It  is  not  considered  that  the  addition  of  the  OnTW  will  result  in  a  further  significant  positive  effect  given  the  very  small  scale  of  employment  opportunities  associated  with  the  operation  and  maintenance  of  the  OnTW.  

Land  Use  

140 The  ES   for   the  proposed  CCGT  power   station   (Scottish  Power,   2009)  does  not   identify   the  potential  for  any  significant  effects  on  land  use  given  that  its  use  will  remain  the  same  as  the  current   land   use.   Neither   does   the   ES   for   the   proposed   Cockenzie   Gas   Pipeline   (Scottish  Power,  2010)  identify  the  potential  for  any  significant  effects  on  land  use  given  the  site  will  be   fully   restored   once   the   Pipeline   has   been   installed.   Consequently   no   significant  cumulative  effects  are  predicted  as  a  result.    

141 The   ES   for   the   proposed   Blindwells   new   settlement   (Scottish   Resources   Group,   2011)  concludes  that  the  development  of  a  new  settlement  at  Blindwells  would  have  a  significant  permanent  effect  on  the  current  land  use  of  the  site  by  virtue  of  the  land  use  changing  from  its   current   rural   agricultural   status   to   a   new  urban   settlement.   The   amount   of   permanent  land  take  of  agricultural  land  at  Blindwells  will  be  circa  127  ha.    

142 It   is   not   considered   that   the   addition   of   the   OnTW   in   combination   with   the   proposed  Blindwells  New  Settlement  will   result   in  a   further  significant  negative  effect  on  agricultural  land  given  the  small   landtake  of  the  Onshore  Substation.  Although  the  Onshore  Substation  will   be   a   further   industrial   development,   it   is   not   considered   that   its   addition   to   the  Blindwells  New  Settlement  proposals  will  result   in  an  increased  urbanisation  of  this  part  of  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

33 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 40: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

34 of 36

East  Lothian  given  its  small  footprint  and  limited  visibility  outwith  the  immediate  locality  of  the  site  as  discussed  in  Chapter  8.  

143 Additional  cumulative  effects  relating  to  land  use  including  landscape  and  visual  effects  and  effects   on   transport   and   landscape   and   visual   are   discussed   in   Chapters   8   and   11  respectively.  

Public  Access  and  Recreation  

144 There  will  be  no  direct  effects  upon  public  access  and  recreation  once   the  proposed  CCGT  power   station   and   the  proposed  Cockenzie  Gas  Pipeline   are   operational.   Consequently   no  significant   direct   cumulative   effects   are   predicted   in   the   ES   for   both   these   proposals   as   a  result.  

145 The   ES   for   the   proposed   Blindwells   new   settlement   (Scottish   Resources   Group,   2011)  identifies   that,   as  a   result  of   the  provision  of  a  path  network   through  and  around   the   site  and  the  creation  of  new  areas  of  open  space  as  part  of  the  development  proposals,  that  the  development  will  result  in  a  permanent  beneficial  effect  of  moderate  significance  on  public  access  and  recreation.  

146 The  construction  of  the  OnTW  would  not  result  in  any  beneficial  effects  upon  public  access  and  recreation  and  consequently  no  significant  effects  upon  public  access  and  recreation  in  combination  with  the  proposed  Blindwells  new  settlement  are  predicted.  

Tourism  

147 The  ES  for  the  proposed  CCGT  power  station  (Scottish  Power,  2009),  the  proposed  Cockenzie  Gas  Pipeline   (Scottish  Power,  2010)   and   the  proposed  Blindwells  new  settlement   (Scottish  Resources  Group,  2011)  do  not  identify  the  potential  for  adverse  impacts  upon  tourism  as  a  result   of   these   developments.   Consequently   no   significant   direct   cumulative   effects   upon  the  local  tourism  economy  are  predicted  as  a  result.  

12.13 Cumulative  Impacts  Conclusions  

148 The  above  assessment   considered   the  potential   for   cumulative   effects   on   socio-­‐economic,  land   use,   recreation   and   tourism   as   a   result   of   both   the   development   of   the   Inch   Cape  Offshore  Wind  Farm  and  OfTW  and  other  development  proposals   in  combination  with   the  OnTW.  

149 Overall   the   cumulative   impact   assessment   concludes   that   the   addition   of   the   Inch   Cape  Offshore  Wind  Farm  and  OfTW  will  result  in  no  greater  effects  on  socio-­‐economic,  land  use,  recreation  and  tourism  than  those  predicted  to  occur  during  the  construction,  operation  and  decommissioning  of  the  OnTW  in  isolation.  

150 With  regards  to  other  cumulative  development  proposals,  including  the  proposed  CCGT,  the  proposed   Cockenzie   Gas   Pipeline   and   the   proposed   Blindwells   New   Settlement,   the  assessment  concludes  that  should  all  of  these  developments  be  constructed  in  parallel  or  in  

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

34 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 41: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

35 of 36

close   succession   that   there   may   be   a   significant   temporary   positive   effect   on   local  employment   and   the   economy.   No   other   significant   cumulative   effects   on   land   use,  recreation  and  tourism  are  predicted.  

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

35 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12

Page 42: Human Environment - inchcapewind.com · 12.4.7 Public Access ..... 12 12.4.8 Baseline Without the Project ... Multiple Deprivation ELC East ... Human Environment Chapter 12 2 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

 

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

Chapter

12

36 of 36

References  

East  Lothian  Council  (2008).  East  Lothian  Local  Plan  2008.  Available  at:  http://www.eastlothian.gov.uk/info/204/statutory_development_plans/231/statutory_development_plans/3    

East  Lothian  Council  (2010a).  East  Lothian  Tourism  Strategy.  East  Lothian  Council,  Economic  Development  Division.  

East  Lothian  Council  (2010b).  East  Lothian  Core  Path  Plan.  Available  at:  http://www.eastlothian.gov.uk/info/379/countryside_and_wildlife/1264/core_paths    

East  Lothian  Council  (2012).  East  Lothian  Visitor  Survey  2011.  Prepared  for  East  Lothian  Council  by  Leithal  Thinking,  Edinburgh.  

Global  Tourism  Solutions  (2013),  East  Lothian  District  Council  STEAM  Report  2012.  Global  Tourism  Solutions  (UK)  Ltd,  23  April  2013.  

GROS  (2012).  Population  Projections  for  Scottish  Areas  (2010-­‐based).  General  Register  Office  for  Scotland,  February  2012.  Available  at:  http://www.gro-­‐scotland.gov.uk/files2/stats/population-­‐projections/scottish-­‐areas-­‐2010-­‐based/population-­‐projections-­‐scottish-­‐areas-­‐2010-­‐based.pdf    

ICOL  (2013).  Inch  Cape  Offshore  Wind  Farm  Environmental  Statement.  Inch  Cape  Offshore  Limited,  May  2013.  

Macaulay  Institute  (2010).  Land  Capability  for  Agriculture  Sheet  66  Edinburgh.  The  Macaulay  Institute  for  Soil  Research,  Aberdeen.  

Richard  Gerald  Associates  (2007).  Feasibility  Study  for  a  New  Visitor  Experience  at  Prestonpans,  East  Lothian.  Richard  Gerald  Associates  Ltd,  Edinburgh.  

Scottish  Power  (2009).  Cockenzie  Combined  Cycle  Gas  Turbine  Power  Station  Environmental  Statement.  Scottish  Power,  December  2009.  

Scottish  Power  (2010).  Cockenzie  Gas  Pipeline  Environmental  Statement.  Scottish  Power,  December  2010.  

Scottish  Resources  Group  (2011).  Blindwells  New  Settlement  Environmental  Statement.  Scottish  Resources  Group,  March  2011.  

VisitScotland  (2012).  Consumer  Review  2012.  Available  at:  http://www.visitscotland.org/pdf/Consumer%20Review%20-­‐%202012.pdf    

   

INCH CAPE OFFSHORE LIMITED ONSHORE ENVIRONMENTAL STATEMENT

36 of 36

Human Environment SOCIO-ECONOMICS, TOURISM, LAND USE AND RECREATION

Chapter

12