Integrated Project Delivery Getting Under the Hood

1

Does Project Delivery Matter?

2

Is Normal Normal? (or Dysfunctional)

3

If You Could Start from a Clean Slate

4

An IPD Example: SMC Castro Valley

5

6

Overview @ 70% Completion Expected Cost $255 Mill ion Authorized Cost $225 Million 30% Schedule Compression (and 6 weeks ahead) $5.8 Million Contingency (only $2.2 used) 26 Owner Originated Changes (