Upload
della-white
View
229
Download
0
Tags:
Embed Size (px)
Citation preview
How to Perform Project Risk Management for Oil
and Gas Projects
Intaver Institute Inc.303, 6707, Elbow Drive S.W, Calgary, AB, CanadaTel: +1(403)692-2252Fax: +1(403)459-4533www.intaver.com
Introduction
• Intaver Institute Timeline– 2002: Established
– 2004: V.1 RiskyProject
– 2009: v 3 Integrated Risk Register
– 2012: v 5
• RiskyProject– Full Project Risk Management
Lifecycle
– Integrated Risk Register
– Risk Matrix, Risk Planning
+– Quantitative Monte Carlo Cost and
Schedule Risk Analysis
04/20/23 2013 Intaver Institute 2
Clients
Gorgon Natural Gas Project
04/20/23 2013 Intaver Institute 3
Project Cost Estimate in Billions A$
Date of cost estimate
A three-train liquefied natural gas (LNG) facility on Barrow Island (Australia) that will produce 15.6 million metric tons of LNG per year.
Corporate Portfolio Management Process
04/20/23 2013 Intaver Institute 4
Project Cost and Schedule risks and
uncertainties
Geological and other Uncertainties affecting
production
Price Uncertainties
Other Risks and Uncertainties:
-Political risks-Uncertainties in Royalties regimes-….
Economic Analysis of the
Projects
Corporate Portfolio
Management
Strategic Decision
Quantitative cost and schedule risk analysis is an important component of portfolio management
Risk Management Affects Project Profitability
04/20/23 2013 Intaver Institute 5
Full circle cost of gas$/Mcf
Quantitative risk analysis provides realistic risk adjusted and risk mitigated cost estimates
Identifying and Managing Critical Risks is Key
04/20/23 2013 Intaver Institute 6
Risk
Quantitative risk analysis identifies and prioritizes critical risks
Which risks are critical?
04/20/23 2013 Intaver Institute 7
Risk 3Risk 3
Risk 4Risk 4
Risk 1Risk 1
Risk 5Risk 5
Risk 2Risk 2
Risk 1Risk 1
Risk 2Risk 2
Risk 3Risk 3
Risk 4Risk 4
Risk 5Risk 5
Sche
dule
ris
k
Cost
Ris
k
Safe
ty R
isk
Lega
l Ris
k
Qua
lity
Risk
……
……
…..
Risk
Envi
rom
enta
l Ris
k
Time Dependent C
osts
Cost
Ris
k
Time is Money: Cost and Schedule Risks
04/20/23 2013 Intaver Institute 8
• Schedule risk drives Costs due to time dependent resource costs
• 40% -70% cost risk is schedule driven
Sche
dule
ris
k
Input 1: Project Schedule
Input 2: List of Risks (Risk Register)
Assign Risks to Project Tasks and Resources
Perform Analysis
Risk Events Approach
Schedule
04/20/23 2013 Intaver Institute 10
Import project schedule from project management tool (Primavera, MS Project, etc..
Costs
04/20/23 2013 Intaver Institute 11
Schedules can include cost data for quantitative risk analysis of fixed costs
Resources
04/20/23 2013 Intaver Institute 12
Resources with rates are loaded with the project schedule to allow for risk analysis of time dependent costs
Risk Register
04/20/23 2013 Intaver Institute 13
Project risk register is integrated to the project schedule and cost
Risk Assignment
04/20/23 2013 Intaver Institute 14
Task R1 R2 R3 R4 R5 R6
Installing Microsoft Seismic monitoring
x x
Deliver frac fleet and install equipment
x
Deliver rig and equipment x
Well 1,2,3 (share common risks) x
Rig Mobilization x
Drilling x x x x
Installing Service Rig x
Completion (8 stages fracing) x x
Risks are assigned to project activities
Risk Assignment Interface
04/20/23 2013 Intaver Institute 15
30 % chance that risk causes a delay and
increase in cost of drillingRisk Assigned to task
‘Drilling’
Risk probability and cost and schedule impact are assigned to activities
Run Monte Carlo Simulation
04/20/23 2013 Intaver Institute 16
Monte Carlo simulation prioritizes risk based on impact on cost, schedule or other parameters
Results of Analysis
04/20/23 2013 Intaver Institute 17
Monte Carlo simulation results for cost and schedule can be viewed as histograms or cumulative probability
Risk Adjusted Project Schedule
04/20/23 2013 Intaver Institute 18
Schedule with risks
Schedule without risks
Arrows show risk assignments
Project Cost
04/20/23 2013 Intaver Institute 19
Schedule with risks
Schedule without risks
Results of quantitative cost risk analysis are shown on the Cost view
Risk Planning – Mitigation Plan
04/20/23 2013 Intaver Institute 20
Risk response plans can be plotted on a Risk Mitigation Waterfall chart
Pre and Post Mitigation Risk Scores
04/20/23 2013 Intaver Institute 21
Pre-mitigation
Post-mitigation
Risk Planning
Risk: Mechanical Problem with instrument
04/20/23 2013 Intaver Institute 22
Post Mitigation $16, 734, 906Pre-Mitigation Cost 17, 178, 397
Risk response plans can reduce the expected cost of the project
RiskyProject Enterprise
04/20/23 2013 Intaver Institute 23
Enterprise Risk Database:Schedules,
Risks,Mitigation Plans
RiskyProject Professional
RiskyProject Lite
RiskyProject Web
Future Reading
• Virine, L. and M. Trumper. 2007 Project Decisions: The Art and Science. VA: Management Concepts
• Virine, L. and M. Trumper. 2013. Project Think: Why Good Managers Make Poor Project Choices. England: Gower Publishing
• P. Leach. 2005. Late and Over Budget: Why Projects Always Seem to Take Longer and Cost More Than Planned. Projects & Profits, Vol. V Issue - XI, November 2005
• http://www.project decisions.org
• http://www.intaver.com/index-whitepapers.html
• http://www.risk-doctor.com/
• http://www.projectrisk.com
Contact Michael [email protected] Institute Inc.www.intaver.com
04/20/23 2013 Intaver Institute 24