FM 2252 September 27, 2017
FM 2252 FROM: EVANS RD TO: FM 3009 BEXAR & COMAL COUNTIES
OPEN HOUSE PUBLIC MEETING
September 27, 2017
5:00 pm – 7:00 pm
Veterans Memorial High School (Cafeteria)
7618 Evans Rd
San Antonio, Texas 78266
FM 2252 September 27, 2017
General Project Information
PROJECT LENGTH – Approximately 2.8 miles
FM 2252 Proposed Improvements:
– Expand the existing 2 lane road to 4 lanes with a continuous two way left
turn lane and raised medians, bike lanes, curb, sidewalk, and drainage
improvements
– Intersection improvements at Evans Road
– Replace existing bridge over Cibolo Creek and construct new bridge
– New grade separation over the railroad at Bracken
4
FM 2252 September 27, 2017
Level Of Service (with Delay in time)
7
2016 EXISTING 2041 NO BUILD 2041 PROPOSED PROJECT
Delay
(sec
/vehicle)
LOS Delay
(sec /vehicle) LOS
Delay
(sec /vehicle) LOS
* Evans Road 46.40 D 207.00 F 41.10 D
** Marbach Lane 15.41 C 407.00 F 13.70 B
** Goll St. 22.90 C 425.84 F 76.82 F
** Tonkawa Pass 11.66 B 315.15 F 9.20 A
** Bat Cave Road 12.82 B 265.48 F 13.90 B
** Hickory Bend 7.17 A 260.90 F 13.00 B
* FM 3009 56.40 E 113.30 F 91.10 F
Note:
* Signalized currently.
** Unsignalized currently.
Analysis assumes Marbach Lane, Tonkawa Pass, Bat Cave Road, and Hickory Bend must be signalized by 2041 or queing will be excessive. Signals will
not be installed until warranted.
FM 2252 September 27, 2017
YEARLY AADT COUNTS
TRAFFIC PROJECTION
8
0.00
5,000.00
10,000.00
15,000.00
20,000.00
25,000.00
30,000.00
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2021 2041 2051
AN
NU
AL A
VE
RA
GE
DA
ILY
TR
AF
FIC
(
AA
DT )
12
,60
0
23
,05
0
25
,70
0
PR
OJE
CTE
D
PR
OJE
CTE
D
Year
16
,00
0
PR
OJE
CTE
D
FM 2252 September 27, 2017
ENVIRONMENTAL
CONSIDERATIONS
– Approximately 2 Acres ROW needed
– Traffic Noise Analysis will be studied
– Karst study will be performed
– Historical and Archeological resources will be evaluated
– Water resources will be studied
– Portions of the proposed project are within a Federal Emergency
Management Agency (FEMA) designated 100 yr floodplain.
9
FM 2252 September 27, 2017
PROJECT TIMELINE
10
EARLIEST ANTICIPATED CONSTRUCTION
CONSTRUCTION DURATION
CONSTRUCTION COST
APPROX 2.5 yrs
APPROX $30 M
* FALL 2020
ENVIRONMENTAL CLEARANCE
Estimated SUMMER 2018
* Depending upon funding
availability, utility, and ROW
coordination
FM 2252 September 27, 2017
ENVIRONMENTAL STATEMENT
The environmental review, consultation, and other actions required by
applicable Federal environmental laws for this project are being, or have been,
carried-out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of
Understanding dated December 16, 2014, and executed by FHWA and TxDOT.
La revisión ambiental, consultas y otras acciones requeridas por las leyes
ambientales federales aplicables para este proyecto están siendo o han sido,
llevado a cabo por TxDOT ‐ en virtud de 23 USC 327 y un Memorando de
Entendimiento fechado el 16 de Diciembre del 2014, y ejecutado por la FHWA
y el TxDOT.
11
FM 2252 September 27, 2017
COMMENTS
12
Deadline for Comments: Thursday, October 12, 2017
For more information visit www.txdot.gov
and search “FM 2252 Evans Rd to FM 3009”
Options for Commenting
1. Complete a written comment card at the meeting tonight.
2. E-mail comments to: [email protected]
3. Provide verbal comments to the onsite court reporter.
4. Mail comments to: TxDOT Attn: Ricardo Flores
4615 NW Loop 410
San Antonio, Tx 78229