Upload
abimana
View
220
Download
0
Embed Size (px)
Citation preview
8/20/2019 Hossein Ghara 6 per page.pdf
1/66
Overview of Post Katrina Eventsand Accelerated ConstructionChallenges in Louisiana and
More
Hossein Ghara, P.E., M.B.A.State Bridge Engineer
Louisiana Department of Transportation
Monday, March 1, 2010
I-10 ATCHAFALYA SPILLWAYBRIDGE CONSTRUCTION
An Example of Accelerated
Construction of the Distant Past
Accelerated Bridge Construction is
not a New Concept
DREDGING OPERATIONS
8/20/2019 Hossein Ghara 6 per page.pdf
2/66
54” DIAMETERCYLINDER PILES
8/20/2019 Hossein Ghara 6 per page.pdf
3/66
DOUBLE ROWPRECAST CONCRETE CAPS
8/20/2019 Hossein Ghara 6 per page.pdf
4/66
8/20/2019 Hossein Ghara 6 per page.pdf
5/66
PRECAST PRESTRESSEDCONCRETE GIRDER SPANS
MONOLITHIC CONSTRUCTION
8/20/2019 Hossein Ghara 6 per page.pdf
6/66
8/20/2019 Hossein Ghara 6 per page.pdf
7/66
PRECAST CONCRETEBENT CONSTRUCTION
8/20/2019 Hossein Ghara 6 per page.pdf
8/66
8/20/2019 Hossein Ghara 6 per page.pdf
9/66
PRECAST CONCRETESPAN CONSTRUCTION
8/20/2019 Hossein Ghara 6 per page.pdf
10/66
8/20/2019 Hossein Ghara 6 per page.pdf
11/66
CONVENTIONALCONSTRUCTION METHODS
NON-REPETATIVE
CONSTRUCTION
PROJECT COMPLETIONPHOTOGRAPHS
8/20/2019 Hossein Ghara 6 per page.pdf
12/66
8/20/2019 Hossein Ghara 6 per page.pdf
13/66
8/20/2019 Hossein Ghara 6 per page.pdf
14/66
Examples of Modern Projects
Accelerated Construction
Rayne, Louisiana
I-10 and La. 35 Overpass
The I-10 bridge was struck by an over height
vehicle travelling on La. 35 damaging both
east and west bound spans on I-10. The
existing spans were shored up and new
spans constructed off site and moved into
position during two-12 hour closures. Traffic
was maintained on the ramps of the
interchange during the exchange of the
spans.
8/20/2019 Hossein Ghara 6 per page.pdf
15/66
8/20/2019 Hossein Ghara 6 per page.pdf
16/66
New Iberia, Louisiana
Lewis Street Vertical Li ftBridge
8/20/2019 Hossein Ghara 6 per page.pdf
17/66
The Lewis Street vertical lift bridge was
constructed over the footprint of the existing
swing span bridge. The main lift span was
constructed off site and move onto a bargeby SPMT and barged into place for final
erection.
8/20/2019 Hossein Ghara 6 per page.pdf
18/66
8/20/2019 Hossein Ghara 6 per page.pdf
19/66
Shreveport, Louisiana
I-49 over La. 526
Fabricate an new steel box girder
Close I-49 and La. 526
Remove damaged girder and concrete deck
utilizing SPMT
Erect new steel box girder with cranes
Reopen I-49 to one lane of traffic and La. 526
Cast deck and barrier
Sequence of Construction
8/20/2019 Hossein Ghara 6 per page.pdf
20/66
8/20/2019 Hossein Ghara 6 per page.pdf
21/66
8/20/2019 Hossein Ghara 6 per page.pdf
22/66
8/20/2019 Hossein Ghara 6 per page.pdf
23/66
8/20/2019 Hossein Ghara 6 per page.pdf
24/66
8/20/2019 Hossein Ghara 6 per page.pdf
25/66
8/20/2019 Hossein Ghara 6 per page.pdf
26/66
8/20/2019 Hossein Ghara 6 per page.pdf
27/66
8/20/2019 Hossein Ghara 6 per page.pdf
28/66
8/20/2019 Hossein Ghara 6 per page.pdf
29/66
New Orleans, Louisiana
Florida Avenue BridgeFlorida Avenue Bridge
To reduce disruption to navigation the main
span for this vertical lift bridge was
constructed near site, transported by barge
and then erected.
8/20/2019 Hossein Ghara 6 per page.pdf
30/66
HURRICANES KATRINA &
RITALOUISIANA’SRESPONSE AND RECOVERY
8/20/2019 Hossein Ghara 6 per page.pdf
31/66
TWO MAJOR HURRICANES HITTWO MAJOR HURRICANES HIT
THE LOUISIANA COAST IN 2005THE LOUISIANA COAST IN 2005
•• KATRINAKATRINA--Category 4 at landfallCategory 4 at landfallMorning of August 29, 2005Morning of August 29, 2005
•• RITARITA – – Category 3 at landfallCategory 3 at landfallMorning of September 24, 2005Morning of September 24, 2005
HURRICANE DAMAGEHURRICANE DAMAGE
•• STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION – – MAJOR INFRASTRUCTURE DAMAGEMAJOR INFRASTRUCTURE DAMAGE
•• FLOODINGFLOODING – – LOSS OF LIFE AND PROPERTYLOSS OF LIFE AND PROPERTY
•• SCOURSCOUR – – BRIDGE AND ROADWAY INFRASTRUCTUREBRIDGE AND ROADWAY INFRASTRUCTURE
•• WINDWIND – – COMMUNICATION, TRANSPORTATIONCOMMUNICATION, TRANSPORTATION
INFRASTRUTURE & PROPERTYINFRASTRUTURE & PROPERTY
STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION
LAKE PONTCHARTRAIN I-10 TWIN SPANS
STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION
LAKE PONTCHARTRAIN - SLIDELL
8/20/2019 Hossein Ghara 6 per page.pdf
32/66
STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION
WEST PEARL RIVER MOVABLE BRIDGE
STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION
HOLLY BEACHHOLLY BEACH – – CAMERON PARISHCAMERON PARISH
STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION
SOUTH WEST LOUISIANA
STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION
NOTHING IS SACRED OR PROTECTED
FLOODINGFLOODING
NEW ORLEANS
8/20/2019 Hossein Ghara 6 per page.pdf
33/66
FLOODINGFLOODING
CLAIBORNE BRIDGE – IHNC
FLOODINGFLOODING
INNER HARBOR NAVIGATIONAL CANAL
FLOODINGFLOODING
ST. BERNARD PARISH
FLOODINGFLOODING
FLOODINGFLOODING
NEW ORLEANS AREA
FLOODINGFLOODING
I-10 / I-610 NEW ORLEANS
8/20/2019 Hossein Ghara 6 per page.pdf
34/66
FLOODINGFLOODING
NEW ORLEANS
FLOODINGFLOODING
I-510 NEAR SIX FLAGS
FLOODINGFLOODING FLOODINGFLOODING
CAMERON PARISH
FLOODINGFLOODING
CAMERON PARISH
FLOODINGFLOODING
8/20/2019 Hossein Ghara 6 per page.pdf
35/66
FLOODINGFLOODING SCOURSCOUR
NEW ORLEANS AREA
SCOURSCOUR SCOURSCOUR
SCOURSCOUR
CHEF MENTEUR PASS – PIER SCOUR
WINDWIND
ELECTRICAL POWER LINES
8/20/2019 Hossein Ghara 6 per page.pdf
36/66
WINDWIND
ELECTRICAL SUBSTATION
WINDWIND
VERTICAL LIFT BRIDGE – POWER, GREASE
WINDWIND
COMMUNICATION TOWER
WINDWIND
NEW ORLEANS SUPERDOME
WINDWIND
LAKE CHARLES – CALCASIEU RIVER BRIDGE
WINDWIND
I-10 TWIN SPANS
8/20/2019 Hossein Ghara 6 per page.pdf
37/66
WINDWIND
Huey P. Long Bridg e – Paint Failure
MOVABLE BRIDGE DAMAGEMOVABLE BRIDGE DAMAGE
•• 152 Movable bridges on & off system152 Movable bridges on & off system
•• 142 affected142 affected
•• 52 damaged52 damaged
BRIDGE DAMAGE EVALUATIONBRIDGE DAMAGE EVALUATION
•• Formed Damage Assessment TeamsFormed Damage Assessment TeamsLA DOTD/FHWA Engineers (major bridges,LA DOTD/FHWA Engineers (major bridges,movable bridges, major highways, parishmovable bridges, major highways, parishand port movable bridges and roadways)and port movable bridges and roadways)
•• Emergency Relief or FEMA Funding.Emergency Relief or FEMA Funding.
•• Bridge Assessment Teams delayedBridge Assessment Teams delayed(access and security issues)(access and security issues)
DAMAGE OF MAJORDAMAGE OF MAJORBRIDGESBRIDGES
ALMONASTER ALMONASTER – – INNER HARBOR INNER HARBOR DanzigerDanziger – – Inner HarborInner Harbor Almonaster Almonaster – – Inner HarborInner Harbor
8/20/2019 Hossein Ghara 6 per page.pdf
38/66
EmpireEmpireEmpireEmpire EmpireEmpire
EmpireEmpire EmpireEmpire
RigoletRigolet’ ’ ss Pass BridgePass Bridge – – US 90US 90
8/20/2019 Hossein Ghara 6 per page.pdf
39/66
Historic Fort PikeHistoric Fort Pike Fort Pike (Post Hurricane)Fort Pike (Post Hurricane)
NewNew RigoletRigolet’ ’ ss Pass BridgePass Bridge – – US 90US 90
CamindaCaminda Bay at Grand IsleBay at Grand Isle
8/20/2019 Hossein Ghara 6 per page.pdf
40/66
CamindaCaminda Bay at Grand IsleBay at Grand Isle ICWWICWW – – Black Bayou PontoonBlack Bayou Pontoon
8/20/2019 Hossein Ghara 6 per page.pdf
41/66
MAJOR BRIDGES IN LAKEMAJOR BRIDGES IN LAKE
PONTCHARTRAINPONTCHARTRAIN
•• US 11 BridgeUS 11 Bridge
•• Pontchartrain Causeway BridgePontchartrain Causeway Bridge
•• II--10 Twin Span Bridges10 Twin Span Bridges
P o n
t c h
a r t r a
i n C
a u s e w a y
P o n
t c h
a r t r a i n
C a u s e w a y ( 2
0 ( 2 0 ’ ’ ) )
I I - - 1 0
1 0
( 1 4
( 1 4 ’ ’ ) )
U S 1 1
U S 1 1
( 1 1
( 1 1 ’ ’ ) )
U S 9 0
U S 9 0
( 1 7 ( 1 7 ’ ’ ) )
R i g
o l e t
R i g
o l e t ’ ’ s s
P a s
s
P a s
s
C h e f
C h e f M e
n t e u r M e
n t e u r P a
s s P a
s s
Fetch
8/20/2019 Hossein Ghara 6 per page.pdf
42/66
http://hurricane.lsu.edu/floodprediction/katrina22/
CausewayCauseway – – Lake PontchartrainLake Pontchartrain
Turnaround RampsTurnaround Ramps
US 11 over Lake PontchartrainUS 11 over Lake Pontchartrain
8/20/2019 Hossein Ghara 6 per page.pdf
43/66
DAMAGE OF IDAMAGE OF I--1010
TWIN SPANS &TWIN SPANS & ACCELERATED ACCELERATED
REPAIR PROJECTREPAIR PROJECT
II--10 TWIN SPANS10 TWIN SPANS
5.4 MILES5.4 MILES
Low level 65Low level 65’ ’
monolithic simplemonolithic simple
prestressprestress girdergirder
spans on 54spans on 54” ” ppcppc
cylinder piles.cylinder piles.
High rise on shortHigh rise on short
section of bridgesection of bridge
DESCRIPTION OF DAMAGEDESCRIPTION OF DAMAGE
•• Eastbound BridgeEastbound Bridge --lost 38 spans and 170lost 38 spans and 170spans shifted alignment.spans shifted alignment.
•• Westbound BridgeWestbound Bridge -- lost 26 spans and 303lost 26 spans and 303spans shifted alignment. Approximately 14,000spans shifted alignment. Approximately 14,000’ ’ of bridge railing damaged.of bridge railing damaged.
•• Bridge BearingsBridge Bearings --Major bearing replacementMajor bearing replacementon both bridges, roadway crossovers for traffic,on both bridges, roadway crossovers for traffic,debris removaldebris removal
WATER HAMMER WATER HAMMER
SURGE LEVEL
NORMAL BAY LEVEL
8/20/2019 Hossein Ghara 6 per page.pdf
44/66
WATER HAMMER WATER HAMMER
Connection fails,
decks lift off
Upward pressure
WATER HAMMER WATER HAMMER
Other sections
removed entirely,
thrown in bay
Fender System Causeway Bri dge
Note missing bent in center ofNote missing bent in center of
photo.photo.
Two spans missing, 12 clearlyTwo spans missing, 12 clearly
misaligned, 4 rails missing.misaligned, 4 rails missing.
8 spans each off of one cap, one8 spans each off of one cap, one
additional span submerged.additional span submerged.
8/20/2019 Hossein Ghara 6 per page.pdf
45/66
1 span leaning, 1 span missing, rails1 span leaning, 1 span missing, rails
missing, spans misalignedmissing, spans misaligned
4 spans leaning, 2 spans missing,4 spans leaning, 2 spans missing,
rails missing, spans misalignedrails missing, spans misaligned
View looking towards North end. View looking towards North end.
North end of bridge. Note spanNorth end of bridge. Note span
off to side.off to side.
Looking Southwest from NorthLooking Southwest from North
end.end. Two leaning spans, note signTwo leaning spans, note sign
truss in place.truss in place.
8/20/2019 Hossein Ghara 6 per page.pdf
46/66
Good view of diaphragms.Good view of diaphragms.
Spans missing, bearing baseSpans missing, bearing base
plates in place.plates in place.
Note how movement was arrestedNote how movement was arrested
by the risers. This caused theby the risers. This caused the
cracks noted at girders 2 & 5.cracks noted at girders 2 & 5.
View looking to South end of View looking to South end of
bridge. Spans on the left are offbridge. Spans on the left are off
at least one cap. Spans on theat least one cap. Spans on the
right are shifted.right are shifted.
Two spans wedged against oneTwo spans wedged against one
cap.cap.
8/20/2019 Hossein Ghara 6 per page.pdf
47/66
SpallingSpalling at girder ends of twoat girder ends of two
spans.spans.
II--10 Twin Spans10 Twin SpansDisplacements (by one riserDisplacements (by one riser
spacing) and debris at northspacing) and debris at north
shore. Note uniformly exposedshore. Note uniformly exposed
portion of caps.portion of caps.
•• Hurricane Katrina hit Monday, August 29, 2005Hurricane Katrina hit Monday, August 29, 2005
•• LaDOTDLaDOTD met with FDOT andmet with FDOT and VolkertVolkert andand Associates performed in Associates per formed in--depth inspection within adepth inspection within a
weekweek
•• PrePre--bid, proposal developed, question / answerbid, proposal developed, question / answersession held and low bidder announced onsession held and low bidder announced onWednesday, September 7, 2005Wednesday, September 7, 2005
•• BohBoh Brothers Construction went to work onBrothers Construction went to work onMonday, September 12, 2005, Fourteen days afterMonday, September 12, 2005, Fourteen days afterthe hurricane made land fallthe hurricane made land fall
II--10 REPAIR PROJECT10 REPAIR PROJECT II--10 REPAIR PHASES10 REPAIR PHASES
PHASE 1: REPAIR EASTBOUND ROADWAYPHASE 1: REPAIR EASTBOUND ROADWAY
•• Move spans from WB to fill gaps on EBMove spans from WB to f ill gaps on EB
•• Realign and repair missing spans on EBRealign and repair missing spans on EB
•• 45 days, completed in 34 days and $1.1 milli on45 days, completed in 34 days and $1.1 milli onincenti ve (Opened October 14, 2005)]incent ive (Opened October 14, 2005)]
•• Construct crossovers & Open EB two way trafficConstruct crossovers & Open EB two way traffic
8/20/2019 Hossein Ghara 6 per page.pdf
48/66
II--10 REPAIR PHASES10 REPAIR PHASES
PHASE 2: REPAIR WESTBOUND ROADWAYPHASE 2: REPAIR WESTBOUND ROADWAY
•• Replace WB spans with approximately 1 mile ofReplace WB spans with approximately 1 mile of
ACROW 700 Series bridg ing, & realign spans ACROW 700 Series bridging, & realign spans
•• Opened WB lanes to one way traffic onOpened WB lanes to one way traffic onJanuary 6, 2006.January 6, 2006.
•• Converted EB lanes to one way trafficConverted EB lanes to one way traffic
II--10 REPAIR PHASES10 REPAIR PHASES
PHASE 3:PHASE 3: MAINTENANCE FOR ACROWMAINTENANCE FOR ACROWBRIDGE FOR 3 YEARS.BRIDGE FOR 3 YEARS.
PERMENANT SOLUTION:PERMENANT SOLUTION:•• Develop plans for new 6Develop plans for new 6 – – lane bridge at alane bridge at a
higher elevationhigher elevation
•• Coastal Engineering Firm to perform study toCoastal Engineering Firm to perform study todetermine elevation fo r the new br idgedetermine elevation for the new br idge
Jack and Slide MethodJack and Slide MethodMoving SpansMoving Spans -- MammoetMammoet
MammoetMammoet -- Jack and Slide MethodJack and Slide Method
8/20/2019 Hossein Ghara 6 per page.pdf
49/66
Span SupportsSpan Supports
8/20/2019 Hossein Ghara 6 per page.pdf
50/66
TRAFFIC IS BACK ON ITRAFFIC IS BACK ON I--1010
No Permit Loads AllowedNo Permit Loads Allowed
II--10 NEW BRIDGE10 NEW BRIDGE
CRITICAL FEATURES:CRITICAL FEATURES:
•• Six lane facilitySix lane facility
•• Storm protectionStorm protection
•• Enhanced ship collision resistanceEnhanced ship collision resistance
•• 75 year service life75 year service life
•• Design alternates where possibleDesign alternates where possible
8/20/2019 Hossein Ghara 6 per page.pdf
51/66
GENERALGENERAL FACTSFACTS
•• TotalTotal Bridge Length = 58,388Bridge Length = 58,388’ ’
– – 260,000 LF 36260,000 LF 36” ” Piles or 200,000 LF ShaftsPiles or 200,000 LF Shafts – – 257,000 LF BT 78 or 44,000 LF Segmental257,000 LF BT 78 or 44,000 LF Segmental
•• Surface area = 3.75 million ftSurface area = 3.75 million ft22
•• Total Roadway Length =1.2 milesTotal Roadway Length =1.2 miles
GENERAL FACTSGENERAL FACTS
CONTRACT #1CONTRACT #1
•• Transition spans, mid level spans and roadwayTransition spans, mid level spans and roadway
•• Expected Letting Date: Spring 2006Expected Letting Date: Spring 2006
CONTRACT #2CONTRACT #2
•• High level and remaining roadwayHigh level and remaining roadway
•• Expected Letting Date: Summer 2006Expected Letting Date: Summer 2006
BRIDGEBRIDGE LOW LEVELLOW LEVEL -- TRANSITIONTRANSITION
•• SuperstructureSuperstructure (no alternates)(no alternates)1 mile long Type III and flat slab1 mile long Type III and flat slab
•• SubstructureSubstructureConcrete bents with 36Concrete bents with 36” ” concreteconcrete
piles or 66piles or 66” ” drilled shaftsdrilled shafts
TYPICAL SECTION (Type III)TYPICAL SECTION (Type III)
BRIDGE MID LEVEL PORTIONBRIDGE MID LEVEL PORTION
•• SuperstructureSuperstructure
8 miles8 miles of Segmental Construction orof Segmental Construction or7878” ” BT Girders, span range 135BT Girders, span range 135’ ’ to 155to 155’ ’
•• SubstructureSubstructureConcrete bents with 36Concrete bents with 36” ” concreteconcrete pilespiles
or 66or 66” ” drilled shaftsdrilled shafts
If you needIf you needto addto add
anythinganything
Al ternate ABT-78”
8/20/2019 Hossein Ghara 6 per page.pdf
52/66
Alternate A Alternate A --1: 361: 36” ” Concrete PilesConcrete Piles Alternate A-2 : Typical Section66” Diameter Drilled Shafts Alternate A Alternate A --2 : Typical Section2 : Typical Section
6666” ” Diameter Drilled ShaftsDiameter Drilled Shafts
Al ternate B:Segmental
Typical Span LayoutTypical Span Layout
Typical SectionTypical SectionSpan by Span ErectionSpan by Span Erection
8/20/2019 Hossein Ghara 6 per page.pdf
53/66
Superstructure Erection SchemeSuperstructure Erection Scheme
If you needIf you needto addto add
anythinganything
ConstructionPhasing
CONSTRUCTION PHASINGCONSTRUCTION PHASING
•• Phase IPhase I – – Low & midLow & mid--level approach bridgeslevel approach bridges
•• Phase IIPhase II – – Main span unit and approachesMain span unit and approaches
•• Phase IIIPhase III – – Demolition of existing bridge at connectionsDemolition of existing bridge at connections
and completion of bridge structuresand completion of bridge structures
Critical PathCritical Path – – 1 complete bridge open in 301 complete bridge open in 30
mos.mos.
CONSTRUCTION PHASINGCONSTRUCTION PHASING
OBJECTIVESOBJECTIVES
•• Complete one useable bridge in one directionComplete one useable bridge in one direction
•• Improve Level of Service for the motorist atImprove Level of Service for the motorist ateach stage of constructioneach stage of construction
•• Provide maximum access for the contractorProvide maximum access for the contractorduring constructionduring construction
•• Maintain at least two lanes of traffic in eachMaintain at least two lanes of traffic in eachdirection throughout constructiondirection throughout construction
Top Down ConstructionMethods
I-310 & La. 1 Construction
8/20/2019 Hossein Ghara 6 per page.pdf
54/66
Top Down Construction
MethodsEnd On Construction - build the new
bridge from the previously constructed
portion of the new bridge.
Forward Construction – building the new
bridge from a temporary construction
bridge forward of the new bridge
construction.
Top Down ConstructionMethods
Construction by the forward constructionmethod allows for a gradual application ofpermanent loads to be applied to the newstructure, therefore allowing time for pileset up and the construction to advance ata quicker rate. However, the cost of thework bridge should be considered in thedecision of construction methods.
Interstate I-310
End On Construction Method
8/20/2019 Hossein Ghara 6 per page.pdf
55/66
8/20/2019 Hossein Ghara 6 per page.pdf
56/66
8/20/2019 Hossein Ghara 6 per page.pdf
57/66
La. 1 Project
Forward Construction Method Utilizing a Work
Bridge
8/20/2019 Hossein Ghara 6 per page.pdf
58/66
Cone Tip Resistance, qc
S l e e v e F r i c t i o n ,
f s
Penetration Rate: 2 cm/sec
Cone Penetration Test (CPT)
Base area = 10 cm2
Sleeve area = 150 cm2
Cone angle = 60o
Equipment used to obtain CPT Data andEquipment used to obtain CPT Data andBoringsBorings
Repeatability of CPT
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
D e p t h ( m )
0 10 20 30 40 50
Tip Resistance (MPa)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0.0 0.1 0.2 0.3 0.4 0.5
Sleeve Friction (MPa)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0 2 4 6 8 10
Rf (%)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0 .0 0 .5 1 .0 1 .5
Pore Pressure (MPa)
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
0 20 40 60 80 100
Probability of soil type (%)
Clayey
Sandy
U1
Silty
Qt/Q0 = 0.4271Log(t/t0) + 1R2 = 0.9509
Qs/Q0 = 0.4435Log(t/t0) + 1R2 = 0.9924
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0.001 0.01 0.1 1 10
R e l a t i v e R e s i s t a n c e ( t 0
= 1 d a y )
Elapsed Time (days)
T-2 16-inch 109 Feet Penetrati on
Total Resistance
Skin Friction Only
8/20/2019 Hossein Ghara 6 per page.pdf
59/66
520’ Forward ConstructionZone
Drive Steel Temp. Piles & Set Trestle
Drive Permanent P.C.C. Piles
Set Pre-Cast Conc. Caps
8/20/2019 Hossein Ghara 6 per page.pdf
60/66
8/20/2019 Hossein Ghara 6 per page.pdf
61/66
8/20/2019 Hossein Ghara 6 per page.pdf
62/66
520’ Cure Form & Pour Zone
Set Precast Conc. Voided Slabs or Girders
Set Deck Side Forms w/Rail for Screed
Set Deck Reinforcing Steel
Pour & Cure Concrete Decks
8/20/2019 Hossein Ghara 6 per page.pdf
63/66
520’ Rear Construction Zone
Remove Steel Temp. Piles &Temp.
Crane/Tread Rails
Transport and Off Load Materials/Supplies
Forward
8/20/2019 Hossein Ghara 6 per page.pdf
64/66
8/20/2019 Hossein Ghara 6 per page.pdf
65/66
THE END
US 90
HUEY P. LONG BRIDGEWIDENING
In order to determine the existing condition
of the main piers prior to construction, the
Department in cooperation with the NewOrleans Public Belt Railroad utilized
acoustical imaging to acquire a global image
of the piers in the muddy water of the
Mississippi.
If damage was uncovered, a more detailed
investigation would have been initiated.
8/20/2019 Hossein Ghara 6 per page.pdf
66/66
THE END
QUESTIONS:1. What was the primary reason for dredging a channel in
the ground prior to the construction of the I-10 bridge
going through Louisiana?2. What were the reasons why dredging was not allowed inlater years?
3 A th f l id li ifi ti d t d
ANSWERS:1. Dredging in wetlands would allow ease of construction by giving the contractor direct access to
the construction site through various navigable waterways. This made construction moreconvenient and faster. It also allowed ease of shipping construction elements such as piles andgirders to the job site.
2. Dredging in wetland often interfered with the natural echo system and resulted in theenvironmental damage. Wetlands are very different than lakes or deeper waterways and theirconversion into other types of waterways is no longer allowed.
3. In some instances dredging also allowed for salt water intrusion and thereby convertingfreshwater into Brackish water which is harmful to the freshwater natural habitat.