Hossein Ghara 6 per page.pdf

  • Upload
    abimana

  • View
    220

  • Download
    0

Embed Size (px)

Citation preview

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    1/66

    Overview of Post Katrina Eventsand Accelerated ConstructionChallenges in Louisiana and

    More

    Hossein Ghara, P.E., M.B.A.State Bridge Engineer

    Louisiana Department of Transportation

    Monday, March 1, 2010

    I-10 ATCHAFALYA SPILLWAYBRIDGE CONSTRUCTION

     An Example of Accelerated

    Construction of the Distant Past

     Accelerated Bridge Construction is

    not a New Concept

    DREDGING OPERATIONS

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    2/66

    54” DIAMETERCYLINDER PILES

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    3/66

    DOUBLE ROWPRECAST CONCRETE CAPS

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    4/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    5/66

    PRECAST PRESTRESSEDCONCRETE GIRDER SPANS

    MONOLITHIC CONSTRUCTION

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    6/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    7/66

    PRECAST CONCRETEBENT CONSTRUCTION

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    8/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    9/66

    PRECAST CONCRETESPAN CONSTRUCTION

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    10/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    11/66

    CONVENTIONALCONSTRUCTION METHODS

    NON-REPETATIVE

    CONSTRUCTION

    PROJECT COMPLETIONPHOTOGRAPHS

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    12/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    13/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    14/66

    Examples of Modern Projects

     Accelerated Construction

    Rayne, Louisiana

    I-10 and La. 35 Overpass

    The I-10 bridge was struck by an over height

    vehicle travelling on La. 35 damaging both

    east and west bound spans on I-10. The

    existing spans were shored up and new

    spans constructed off site and moved into

    position during two-12 hour closures. Traffic

    was maintained on the ramps of the

    interchange during the exchange of the

    spans.

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    15/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    16/66

    New Iberia, Louisiana

    Lewis Street Vertical Li ftBridge

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    17/66

    The Lewis Street vertical lift bridge was

    constructed over the footprint of the existing

    swing span bridge. The main lift span was

    constructed off site and move onto a bargeby SPMT and barged into place for final

    erection.

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    18/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    19/66

    Shreveport, Louisiana

    I-49 over La. 526

    Fabricate an new steel box girder 

    Close I-49 and La. 526

    Remove damaged girder and concrete deck

    utilizing SPMT

    Erect new steel box girder with cranes

    Reopen I-49 to one lane of traffic and La. 526

    Cast deck and barrier 

    Sequence of Construction

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    20/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    21/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    22/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    23/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    24/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    25/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    26/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    27/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    28/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    29/66

    New Orleans, Louisiana

    Florida Avenue BridgeFlorida Avenue Bridge

    To reduce disruption to navigation the main

    span for this vertical lift bridge was

    constructed near site, transported by barge

    and then erected.

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    30/66

    HURRICANES KATRINA &

    RITALOUISIANA’SRESPONSE AND RECOVERY

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    31/66

    TWO MAJOR HURRICANES HITTWO MAJOR HURRICANES HIT

    THE LOUISIANA COAST IN 2005THE LOUISIANA COAST IN 2005

    •• KATRINAKATRINA--Category 4 at landfallCategory 4 at landfallMorning of August 29, 2005Morning of August 29, 2005

    •• RITARITA – – Category 3 at landfallCategory 3 at landfallMorning of September 24, 2005Morning of September 24, 2005

    HURRICANE DAMAGEHURRICANE DAMAGE

    •• STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION – – MAJOR INFRASTRUCTURE DAMAGEMAJOR INFRASTRUCTURE DAMAGE

    •• FLOODINGFLOODING – – LOSS OF LIFE AND PROPERTYLOSS OF LIFE AND PROPERTY

    •• SCOURSCOUR – – BRIDGE AND ROADWAY INFRASTRUCTUREBRIDGE AND ROADWAY INFRASTRUCTURE

    •• WINDWIND – – COMMUNICATION, TRANSPORTATIONCOMMUNICATION, TRANSPORTATION

    INFRASTRUTURE & PROPERTYINFRASTRUTURE & PROPERTY

    STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION

    LAKE PONTCHARTRAIN I-10 TWIN SPANS

    STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION

    LAKE PONTCHARTRAIN - SLIDELL

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    32/66

    STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION

    WEST PEARL RIVER MOVABLE BRIDGE

    STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION

    HOLLY BEACHHOLLY BEACH – – CAMERON PARISHCAMERON PARISH

    STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION

    SOUTH WEST LOUISIANA

    STORM SURGE & WAVE ACTIONSTORM SURGE & WAVE ACTION

    NOTHING IS SACRED OR PROTECTED

    FLOODINGFLOODING

    NEW ORLEANS

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    33/66

    FLOODINGFLOODING

    CLAIBORNE BRIDGE – IHNC

    FLOODINGFLOODING

    INNER HARBOR NAVIGATIONAL CANAL

    FLOODINGFLOODING

    ST. BERNARD PARISH

    FLOODINGFLOODING

    FLOODINGFLOODING

    NEW ORLEANS AREA

    FLOODINGFLOODING

    I-10 / I-610 NEW ORLEANS

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    34/66

    FLOODINGFLOODING

    NEW ORLEANS

    FLOODINGFLOODING

    I-510 NEAR SIX FLAGS

    FLOODINGFLOODING FLOODINGFLOODING

    CAMERON PARISH

    FLOODINGFLOODING

    CAMERON PARISH

    FLOODINGFLOODING

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    35/66

    FLOODINGFLOODING SCOURSCOUR

    NEW ORLEANS AREA

    SCOURSCOUR SCOURSCOUR

    SCOURSCOUR

    CHEF MENTEUR PASS – PIER SCOUR

    WINDWIND

    ELECTRICAL POWER LINES

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    36/66

    WINDWIND

    ELECTRICAL SUBSTATION

    WINDWIND

    VERTICAL LIFT BRIDGE – POWER, GREASE

    WINDWIND

    COMMUNICATION TOWER

    WINDWIND

    NEW ORLEANS SUPERDOME

    WINDWIND

    LAKE CHARLES – CALCASIEU RIVER BRIDGE

    WINDWIND

    I-10 TWIN SPANS

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    37/66

    WINDWIND

    Huey P. Long Bridg e – Paint Failure

    MOVABLE BRIDGE DAMAGEMOVABLE BRIDGE DAMAGE

    •• 152 Movable bridges on & off system152 Movable bridges on & off system

    •• 142 affected142 affected

    •• 52 damaged52 damaged

    BRIDGE DAMAGE EVALUATIONBRIDGE DAMAGE EVALUATION

    •• Formed Damage Assessment TeamsFormed Damage Assessment TeamsLA DOTD/FHWA Engineers (major bridges,LA DOTD/FHWA Engineers (major bridges,movable bridges, major highways, parishmovable bridges, major highways, parishand port movable bridges and roadways)and port movable bridges and roadways)

    •• Emergency Relief or FEMA Funding.Emergency Relief or FEMA Funding.

    •• Bridge Assessment Teams delayedBridge Assessment Teams delayed(access and security issues)(access and security issues)

    DAMAGE OF MAJORDAMAGE OF MAJORBRIDGESBRIDGES

     ALMONASTER ALMONASTER – – INNER HARBOR INNER HARBOR DanzigerDanziger – – Inner HarborInner Harbor  Almonaster Almonaster – – Inner HarborInner Harbor

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    38/66

    EmpireEmpireEmpireEmpire EmpireEmpire

    EmpireEmpire EmpireEmpire

    RigoletRigolet’ ’ ss Pass BridgePass Bridge – – US 90US 90

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    39/66

    Historic Fort PikeHistoric Fort Pike Fort Pike (Post Hurricane)Fort Pike (Post Hurricane)

    NewNew RigoletRigolet’ ’ ss Pass BridgePass Bridge – – US 90US 90

    CamindaCaminda Bay at Grand IsleBay at Grand Isle

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    40/66

    CamindaCaminda Bay at Grand IsleBay at Grand Isle ICWWICWW – – Black Bayou PontoonBlack Bayou Pontoon

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    41/66

    MAJOR BRIDGES IN LAKEMAJOR BRIDGES IN LAKE

    PONTCHARTRAINPONTCHARTRAIN

    •• US 11 BridgeUS 11 Bridge

    •• Pontchartrain Causeway BridgePontchartrain Causeway Bridge

    •• II--10 Twin Span Bridges10 Twin Span Bridges

                      P             o              n

                      t             c                   h

                  a              r                  t              r              a

                       i              n                 C

                  a              u             s             e              w              a              y    

                      P             o              n

                      t             c                   h

                  a              r                  t              r              a                   i              n

                     C              a              u             s             e              w              a              y                      (                       2

                      0                  (                       2                  0                   ’                   ’                   )                        )     

       I   I  -  -   1   0

        1   0

        (    1  4

       (    1  4   ’   ’    )     ) 

          U      S      1      1

     

          U      S      1      1

           (        1      1

          (        1      1      ’      ’       )        ) 

        U   S    9   0

     

        U   S    9   0

        (    1    7   (    1    7    ’    ’    )     ) 

       R    i  g 

      o   l  e   t

       R    i  g 

      o   l  e   t   ’   ’  s  s

       P  a  s

      s

       P  a  s

      s

     C  h e f 

     C  h e f   M e

     n t e u r  M e

     n t e u r  P a

     s s  P a

     s s

    Fetch

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    42/66

    http://hurricane.lsu.edu/floodprediction/katrina22/

    CausewayCauseway – – Lake PontchartrainLake Pontchartrain

    Turnaround RampsTurnaround Ramps

    US 11 over Lake PontchartrainUS 11 over Lake Pontchartrain

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    43/66

    DAMAGE OF IDAMAGE OF I--1010

    TWIN SPANS &TWIN SPANS & ACCELERATED ACCELERATED

    REPAIR PROJECTREPAIR PROJECT

    II--10 TWIN SPANS10 TWIN SPANS

    5.4 MILES5.4 MILES

    Low level 65Low level 65’ ’ 

    monolithic simplemonolithic simple

    prestressprestress girdergirder

    spans on 54spans on 54” ” ppcppc

    cylinder piles.cylinder piles.

    High rise on shortHigh rise on short

    section of bridgesection of bridge

    DESCRIPTION OF DAMAGEDESCRIPTION OF DAMAGE

    •• Eastbound BridgeEastbound Bridge --lost 38 spans and 170lost 38 spans and 170spans shifted alignment.spans shifted alignment.

    •• Westbound BridgeWestbound Bridge -- lost 26 spans and 303lost 26 spans and 303spans shifted alignment. Approximately 14,000spans shifted alignment. Approximately 14,000’ ’ of bridge railing damaged.of bridge railing damaged.

    •• Bridge BearingsBridge Bearings --Major bearing replacementMajor bearing replacementon both bridges, roadway crossovers for traffic,on both bridges, roadway crossovers for traffic,debris removaldebris removal

    WATER HAMMER WATER HAMMER 

    SURGE LEVEL

    NORMAL BAY LEVEL

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    44/66

    WATER HAMMER WATER HAMMER 

    Connection fails,

    decks lift off 

    Upward pressure

    WATER HAMMER WATER HAMMER 

    Other sections

    removed entirely,

    thrown in bay

    Fender System Causeway Bri dge

    Note missing bent in center ofNote missing bent in center of

    photo.photo.

    Two spans missing, 12 clearlyTwo spans missing, 12 clearly

    misaligned, 4 rails missing.misaligned, 4 rails missing.

    8 spans each off of one cap, one8 spans each off of one cap, one

    additional span submerged.additional span submerged.

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    45/66

    1 span leaning, 1 span missing, rails1 span leaning, 1 span missing, rails

    missing, spans misalignedmissing, spans misaligned

    4 spans leaning, 2 spans missing,4 spans leaning, 2 spans missing,

    rails missing, spans misalignedrails missing, spans misaligned

     View looking towards North end. View looking towards North end.

    North end of bridge. Note spanNorth end of bridge. Note span

    off to side.off to side.

    Looking Southwest from NorthLooking Southwest from North

    end.end. Two leaning spans, note signTwo leaning spans, note sign

    truss in place.truss in place.

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    46/66

    Good view of diaphragms.Good view of diaphragms.

    Spans missing, bearing baseSpans missing, bearing base

    plates in place.plates in place.

    Note how movement was arrestedNote how movement was arrested

    by the risers. This caused theby the risers. This caused the

    cracks noted at girders 2 & 5.cracks noted at girders 2 & 5.

     View looking to South end of View looking to South end of

    bridge. Spans on the left are offbridge. Spans on the left are off

    at least one cap. Spans on theat least one cap. Spans on the

    right are shifted.right are shifted.

    Two spans wedged against oneTwo spans wedged against one

    cap.cap.

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    47/66

    SpallingSpalling at girder ends of twoat girder ends of two

    spans.spans.

    II--10 Twin Spans10 Twin SpansDisplacements (by one riserDisplacements (by one riser

    spacing) and debris at northspacing) and debris at north

    shore. Note uniformly exposedshore. Note uniformly exposed

    portion of caps.portion of caps.

    •• Hurricane Katrina hit Monday, August 29, 2005Hurricane Katrina hit Monday, August 29, 2005

    •• LaDOTDLaDOTD met with FDOT andmet with FDOT and VolkertVolkert andand Associates performed in Associates per formed in--depth inspection within adepth inspection within a

    weekweek

    •• PrePre--bid, proposal developed, question / answerbid, proposal developed, question / answersession held and low bidder announced onsession held and low bidder announced onWednesday, September 7, 2005Wednesday, September 7, 2005

    •• BohBoh Brothers Construction went to work onBrothers Construction went to work onMonday, September 12, 2005, Fourteen days afterMonday, September 12, 2005, Fourteen days afterthe hurricane made land fallthe hurricane made land fall

    II--10 REPAIR PROJECT10 REPAIR PROJECT II--10 REPAIR PHASES10 REPAIR PHASES

    PHASE 1: REPAIR EASTBOUND ROADWAYPHASE 1: REPAIR EASTBOUND ROADWAY

    •• Move spans from WB to fill gaps on EBMove spans from WB to f ill gaps on EB

    •• Realign and repair missing spans on EBRealign and repair missing spans on EB

    •• 45 days, completed in 34 days and $1.1 milli on45 days, completed in 34 days and $1.1 milli onincenti ve (Opened October 14, 2005)]incent ive (Opened October 14, 2005)]

    •• Construct crossovers & Open EB two way trafficConstruct crossovers & Open EB two way traffic

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    48/66

    II--10 REPAIR PHASES10 REPAIR PHASES

    PHASE 2: REPAIR WESTBOUND ROADWAYPHASE 2: REPAIR WESTBOUND ROADWAY

    •• Replace WB spans with approximately 1 mile ofReplace WB spans with approximately 1 mile of

     ACROW 700 Series bridg ing, & realign spans ACROW 700 Series bridging, & realign spans

    •• Opened WB lanes to one way traffic onOpened WB lanes to one way traffic onJanuary 6, 2006.January 6, 2006.

    •• Converted EB lanes to one way trafficConverted EB lanes to one way traffic

    II--10 REPAIR PHASES10 REPAIR PHASES

    PHASE 3:PHASE 3: MAINTENANCE FOR ACROWMAINTENANCE FOR ACROWBRIDGE FOR 3 YEARS.BRIDGE FOR 3 YEARS.

    PERMENANT SOLUTION:PERMENANT SOLUTION:•• Develop plans for new 6Develop plans for new 6 – – lane bridge at alane bridge at a

    higher elevationhigher elevation

    •• Coastal Engineering Firm to perform study toCoastal Engineering Firm to perform study todetermine elevation fo r the new br idgedetermine elevation for the new br idge

    Jack and Slide MethodJack and Slide MethodMoving SpansMoving Spans -- MammoetMammoet

    MammoetMammoet -- Jack and Slide MethodJack and Slide Method

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    49/66

    Span SupportsSpan Supports

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    50/66

    TRAFFIC IS BACK ON ITRAFFIC IS BACK ON I--1010

    No Permit Loads AllowedNo Permit Loads Allowed

    II--10 NEW BRIDGE10 NEW BRIDGE

    CRITICAL FEATURES:CRITICAL FEATURES:

    •• Six lane facilitySix lane facility

    •• Storm protectionStorm protection

    •• Enhanced ship collision resistanceEnhanced ship collision resistance

    •• 75 year service life75 year service life

    •• Design alternates where possibleDesign alternates where possible

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    51/66

    GENERALGENERAL FACTSFACTS

    •• TotalTotal Bridge Length = 58,388Bridge Length = 58,388’ ’ 

     – – 260,000 LF 36260,000 LF 36” ” Piles or 200,000 LF ShaftsPiles or 200,000 LF Shafts – – 257,000 LF BT 78 or 44,000 LF Segmental257,000 LF BT 78 or 44,000 LF Segmental

    •• Surface area = 3.75 million ftSurface area = 3.75 million ft22

    •• Total Roadway Length =1.2 milesTotal Roadway Length =1.2 miles

    GENERAL FACTSGENERAL FACTS

    CONTRACT #1CONTRACT #1

    •• Transition spans, mid level spans and roadwayTransition spans, mid level spans and roadway

    •• Expected Letting Date: Spring 2006Expected Letting Date: Spring 2006

    CONTRACT #2CONTRACT #2

    •• High level and remaining roadwayHigh level and remaining roadway

    •• Expected Letting Date: Summer 2006Expected Letting Date: Summer 2006

    BRIDGEBRIDGE LOW LEVELLOW LEVEL -- TRANSITIONTRANSITION

    •• SuperstructureSuperstructure (no alternates)(no alternates)1 mile long Type III and flat slab1 mile long Type III and flat slab

    •• SubstructureSubstructureConcrete bents with 36Concrete bents with 36” ” concreteconcrete

    piles or 66piles or 66” ” drilled shaftsdrilled shafts

    TYPICAL SECTION (Type III)TYPICAL SECTION (Type III)

    BRIDGE MID LEVEL PORTIONBRIDGE MID LEVEL PORTION

    •• SuperstructureSuperstructure

    8 miles8 miles of Segmental Construction orof Segmental Construction or7878” ” BT Girders, span range 135BT Girders, span range 135’ ’ to 155to 155’ ’ 

    •• SubstructureSubstructureConcrete bents with 36Concrete bents with 36” ” concreteconcrete pilespiles

    or 66or 66” ” drilled shaftsdrilled shafts

    If you needIf you needto addto add

    anythinganything

     Al ternate ABT-78”

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    52/66

     Alternate A  Alternate A --1: 361: 36” ” Concrete PilesConcrete Piles  Alternate A-2 : Typical Section66” Diameter Drilled Shafts Alternate A  Alternate A --2 : Typical Section2 : Typical Section

    6666” ” Diameter Drilled ShaftsDiameter Drilled Shafts

     Al ternate B:Segmental

    Typical Span LayoutTypical Span Layout

    Typical SectionTypical SectionSpan by Span ErectionSpan by Span Erection

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    53/66

    Superstructure Erection SchemeSuperstructure Erection Scheme

    If you needIf you needto addto add

    anythinganything

    ConstructionPhasing

    CONSTRUCTION PHASINGCONSTRUCTION PHASING

    •• Phase IPhase I – – Low & midLow & mid--level approach bridgeslevel approach bridges

    •• Phase IIPhase II – – Main span unit and approachesMain span unit and approaches

    •• Phase IIIPhase III – – Demolition of existing bridge at connectionsDemolition of existing bridge at connections

    and completion of bridge structuresand completion of bridge structures

    Critical PathCritical Path – – 1 complete bridge open in 301 complete bridge open in 30

    mos.mos.

    CONSTRUCTION PHASINGCONSTRUCTION PHASING

    OBJECTIVESOBJECTIVES

    •• Complete one useable bridge in one directionComplete one useable bridge in one direction

    •• Improve Level of Service for the motorist atImprove Level of Service for the motorist ateach stage of constructioneach stage of construction

    •• Provide maximum access for the contractorProvide maximum access for the contractorduring constructionduring construction

    •• Maintain at least two lanes of traffic in eachMaintain at least two lanes of traffic in eachdirection throughout constructiondirection throughout construction

    Top Down ConstructionMethods

    I-310 & La. 1 Construction

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    54/66

    Top Down Construction

    MethodsEnd On Construction - build the new

    bridge from the previously constructed

    portion of the new bridge.

    Forward Construction – building the new

    bridge from a temporary construction

    bridge forward of the new bridge

    construction.

    Top Down ConstructionMethods

    Construction by the forward constructionmethod allows for a gradual application ofpermanent loads to be applied to the newstructure, therefore allowing time for pileset up and the construction to advance ata quicker rate. However, the cost of thework bridge should be considered in thedecision of construction methods.

    Interstate I-310

    End On Construction Method

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    55/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    56/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    57/66

    La. 1 Project

    Forward Construction Method Utilizing a Work

    Bridge

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    58/66

    Cone Tip Resistance, qc

          S      l    e    e    v    e      F    r      i    c     t      i    o    n  ,

          f    s

    Penetration Rate: 2 cm/sec

    Cone Penetration Test (CPT)

    Base area = 10 cm2

    Sleeve area = 150 cm2 

    Cone angle = 60o

    Equipment used to obtain CPT Data andEquipment used to obtain CPT Data andBoringsBorings

    Repeatability of CPT

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

       D  e  p   t   h   (  m   )

    0 10 20 30 40 50

    Tip Resistance (MPa)

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    0.0 0.1 0.2 0.3 0.4 0.5

    Sleeve Friction (MPa)

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    0 2 4 6 8 10

    Rf (%)

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    0 .0 0 .5 1 .0 1 .5

    Pore Pressure (MPa)

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    0 20 40 60 80 100

    Probability of soil type (%)

    Clayey

    Sandy

    U1

    Silty

    Qt/Q0 = 0.4271Log(t/t0) + 1R2 = 0.9509

    Qs/Q0 = 0.4435Log(t/t0) + 1R2 = 0.9924

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    1.4

    1.6

    0.001 0.01 0.1 1 10

       R  e   l  a   t   i  v  e   R  e  s   i  s   t  a  n  c  e   (   t   0

      =   1   d  a  y   )

    Elapsed Time (days)

    T-2 16-inch 109 Feet Penetrati on

    Total Resistance

    Skin Friction Only

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    59/66

    520’ Forward ConstructionZone

    Drive Steel Temp. Piles & Set Trestle

    Drive Permanent P.C.C. Piles

    Set Pre-Cast Conc. Caps

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    60/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    61/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    62/66

    520’ Cure Form & Pour Zone

    Set Precast Conc. Voided Slabs or Girders

    Set Deck Side Forms w/Rail for Screed

    Set Deck Reinforcing Steel

    Pour & Cure Concrete Decks

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    63/66

    520’ Rear Construction Zone

    Remove Steel Temp. Piles &Temp.

    Crane/Tread Rails

    Transport and Off Load Materials/Supplies

    Forward

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    64/66

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    65/66

    THE END

    US 90

    HUEY P. LONG BRIDGEWIDENING

    In order to determine the existing condition

    of the main piers prior to construction, the

    Department in cooperation with the NewOrleans Public Belt Railroad utilized

    acoustical imaging to acquire a global image

    of the piers in the muddy water of the

    Mississippi.

    If damage was uncovered, a more detailed

    investigation would have been initiated.

  • 8/20/2019 Hossein Ghara 6 per page.pdf

    66/66

    THE END

    QUESTIONS:1. What was the primary reason for dredging a channel in

    the ground prior to the construction of the I-10 bridge

    going through Louisiana?2. What were the reasons why dredging was not allowed inlater years?

    3 A th f l id li ifi ti d t d

     ANSWERS:1. Dredging in wetlands would allow ease of construction by giving the contractor direct access to

    the construction site through various navigable waterways. This made construction moreconvenient and faster. It also allowed ease of shipping construction elements such as piles andgirders to the job site.

    2. Dredging in wetland often interfered with the natural echo system and resulted in theenvironmental damage. Wetlands are very different than lakes or deeper waterways and theirconversion into other types of waterways is no longer allowed.

    3. In some instances dredging also allowed for salt water intrusion and thereby convertingfreshwater into Brackish water which is harmful to the freshwater natural habitat.