31
HITACHI GE Hitachi Nuclear Energy James C. Kinsey Vice President, ESBWR Licensing PO Box 780 M/C A-55 Wilmington, NC 28402-0780 USA T 910 675 5057 F 910 362 5057 MFN 08-341 Docket No. 52-010 April 25, 2008 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001 Subject: Response to Portion of NRC Request for Additional Information Letter No. 110 Related to ESBWR Design Certification Application - Containment Systems - RAI Number 6.2-180 Enclosure 1 contains the GE Hitachi Nuclear Energy (GEH) response to the subject NRC RAI transmitted via the Reference 1 letter. DCD Markups related to this response are provided in Enclosure 2. Verified DCD changes associated with this RAI response are identified in the enclosed DCD markups by enclosing the text within a black box. The marked-up pages may contain unverified changes in addition to the verified changes resulting from this RAI response. Other changes shown in the markup(s) may not be fully developed and approved for inclusion in DCD Revision 5. If you have any questions or require additional information, please contact me. Sincerely, James C. Kinsey Vice President, ESBWR Licensing

HITACHI GE Energy

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: HITACHI GE Energy

HITACHI GE Hitachi Nuclear Energy

James C. KinseyVice President, ESBWR Licensing

PO Box 780 M/C A-55Wilmington, NC 28402-0780USA

T 910 675 5057F 910 362 5057

MFN 08-341 Docket No. 52-010

April 25, 2008

U.S. Nuclear Regulatory CommissionDocument Control DeskWashington, D.C. 20555-0001

Subject: Response to Portion of NRC Request for AdditionalInformation Letter No. 110 Related to ESBWR DesignCertification Application - Containment Systems -RAI Number 6.2-180

Enclosure 1 contains the GE Hitachi Nuclear Energy (GEH) response to thesubject NRC RAI transmitted via the Reference 1 letter. DCD Markups related tothis response are provided in Enclosure 2.

Verified DCD changes associated with this RAI response are identified in theenclosed DCD markups by enclosing the text within a black box. The marked-uppages may contain unverified changes in addition to the verified changesresulting from this RAI response. Other changes shown in the markup(s) maynot be fully developed and approved for inclusion in DCD Revision 5.

If you have any questions or require additional information, please contact me.

Sincerely,

James C. KinseyVice President, ESBWR Licensing

Page 2: HITACHI GE Energy

MFN 08-341Page 2 of 2

Reference:

1. MFN 07-510, Letter from U.S. Nuclear Regulatory Commission to RobertE. Brown, Request for Additional Information Letter No. 110 Related toESBWR Design Certification Application, September 19, 2007

Enclosures:

1. MFN 08-341 - Response to Portion of NRC Request for AdditionalInformation Letter No. 110 Related to ESBWR Design CertificationApplication - Containment Systems - RAI Number 6.2-180

2. MFN 08-341 - Response to Portion of NRC Request for AdditionalInformation Letter No. 110 Related to ESBWR Design CertificationApplication - Containment Systems - RAI Number 6.2-180 - DCD Markups

cc: AE CubbageDH HindsGB StrambackRE BrowneDRF

USNRC (with enclosures)GEH/Wilmington (with enclosures)GEH/San Jose (with enclosures)GEH/Wilmington (with enclosures)0000-0078-3785

Page 3: HITACHI GE Energy

Enclosure I

MFN 08-341

Response to Portion of NRC Request forAdditional Information Letter No. 110

Related to ESBWR Design Certification Application

Containment Systems

RAI Number 6.2-180

Page 4: HITACHI GE Energy

MFN 08-341Enclosure 1 Page 1 of 2

NRC RAI 6.2-180:

DCD, Tier 2, Revision 3, Section 6.2.1.1.2 states that "[flor a postulated DBA, thecalculated maximum DW temperature and absolute pressure remain below their designvalues, shown in Table 6.2-1." However, DCD Table 6.2-5 shows that the "short-term"drywell temperature exceeding the design value for the following accidents: (1) mainsteam line break and bottom head drain line based on standard TRACG evaluationmodel and (2) feedwater line break for based on both standard TRACG evaluationmodel and bounding values model. This table also shows that the short-term peakdrywell temperature predicted for the main steam line break based on the standardTRACG evaluation model (174. 70C (346. 80F)) is more limiting than that based on thebounding values model (170. 8°C (339.6°F)).

A. Please correct or explain this apparent discrepancy in the DCD. Also, pleaseexplain why it is acceptable for the drywell temperature to exceed its design value.

B. Please explain why the short-term peak drywell temperature for the main steam linebreak predicted by the standard TRACG evaluation model is more limiting than thatbased on the bounding values model.

GEH Response:

A. The temperatures shown on DCD Tier 2, Revision 3, Table 6.2-5 represent thetemperature at a single location in the TRACG evaluation. The selected location isnot representative of the bulk drywell temperature used in the structural analysis. Asa result, local temperatures near the break location can exceed the bulk designtemperature used to determine the global structural response. DCD Tier 2,Subsection 6.2.1.1.2 will be revised to state that the bulk temperature remains belowthe design value. DCD Tier 2, Table 6.2-5 and Table 3H-8 values will be replacedwith the bulk temperature rather than those of a single location, because thisrepresents the temperature that is used in the structural analysis.

For some cases, at about 1000 seconds into the transient, the drywell bulktemperature is much lower than the peak design temperature but slightly higher thanthe temperature transient profile considered in the structural analysis. The highertemperatures last for no more than 800 seconds. No impact on structural design isexpected, and the effect on the structural analysis documented in DCD Tier 2,Appendix 3G will be taken into account in the detailed design stage.

B. The bounding main steam line break analysis is that which produces the greatestpressure within the containment, not necessarily the highest temperature. In theESBWR, the peak containment pressure is obtained after several hours, but thepeak containment temperature occurs within the first 5 seconds due to heating fromthe steam discharge. The initial conditions leading to the higher long-termcontainment pressure increase result in lower initial flow out the break, and thuslower initial increase in containment pressure and temperature.

Page 5: HITACHI GE Energy

MFN 08-341Enclosure 1 Page 2 of 2

DCD Impact:

DCD Tier 2, Appendix 3G; Table 3H-8; Subsection 6.2.1.1.2; Figures 6.2-9bl, 6.2-9b2,6.2-9b3, 6.2-1Obl, 6.2-10b2, 6.2-10b3, 6.2-1 lbl, 6.2-11 b2, 6.2-11 b3, 6.2-12bl,6.2-12b2, 6.2-12b3, 6.2-13bl, 6.2-13b2, 6.2-13b3, 6.2-14bl, 6.2-14b2, and 6.2-14b3;and Appendix 6E will be revised as shown in the attached markup.

Page 6: HITACHI GE Energy

Enclosure 2

MFN 08-341

Response to Portion of NRC Request forAdditional Information Letter No. 110

Related'to ESBWR Design Certification Application

Containment Systems

RAI Number 6.2-180

DCD Markups

Verified DCD changes associated with this RAI response are identified in the enclosedDCD markups by enclosing the text within a black box. The marked-up pages maycontain unverified changes in addition to the verified changes resulting from this RAIresponse. Other changes shown in the markup(s) may not be fully developed andapproved for inclusion in DCD Revision 5.

Page 7: HITACHI GE Energy

26A6642AN Rev. 05ESBWR Design Control Document/Tier 2

3G. DESIGN DETAILS AND EVALUATION RESULTS OF SEISMICCATEGORY I STRUCTURES

This appendix presents the structural design and analysis for the Reactor Building, ControlBuilding, Fuel Building and Fire Water Service Complex of the ESBWR Standard Plant. Itaddresses all applicable items included in Appendix C to United States Nuclear RegulatoryCommision (USNRC) Standard Review Plan, NUREG-0800, Subsection 3.8.4. Drawingsdepicted in the Design Control Document (DCD) are not used for construction. Constructiondrawings meet the technical licensing commitments made in the DCD but are issued underdifferent contractual/industrial rules than the DCD drawings; and reflect detailed designconfiguration. The final design details, and hence final component stresses may be differentfrom those reported here but they will meet the structural acceptance criteria presented inSection 3.8.

3G.1 REACTOR BUILDING

The Reactor Building (RB) encloses the concrete containment and its internal systems,structures, and components. In addition, the RB contains the Isolation Condenser/PassiveContainment Cooling (IC/PCC) pools and the services pools for storage of Dryer/Separator onthe top of the concrete containment.

3G.1.1 Objective and Scope

The objective of this subsection is to document the structural design details, inputs and analyticalresults from the analysis of the ESBWR main building structures encased in the ReactorBuilding. The scope includes the design and analysis of the structure for normal, severeenvironmental, extreme environmental, and abnormal loads.

3G.1.2 Conclusions

The following are the major summary conclusions on the design and analysis of the ReactorBuilding, the concrete containment and the containment internal structures.

* Based on the results of finite element analyses performed in accordance with the designconditions identified in Subsections 3G.1.3 and 3G.1.5, stresses and/or strains inconcrete, reinforcement, liner and containment internal structures are less than theallowable stresses and/or strains per the applicable regulations, codes or standards listedin Section 3.8.

* The factors of safety against floatation, sliding, and overturning of the structure undervarious loading combinations are higher than the required minimum.

* The thickness of the roof slabs and exterior walls are more than the minimum required topreclude penetration, perforation or spalling resulting from impact of design basistornado missiles.

3G-1

Page 8: HITACHI GE Energy

26A6642AN Rev. 05ESBWR Design Control Document/Tier 2

Table 311-8

Thermodynamic Environment Conditions Inside Containment Vessel for Accident

Conditions

Plant Zone

(a-I & a-2) Upper and lower drywell (1) Time (2) 0 h - 72 h.(Figure 6.2-1) Bulk Tern. 0C(F) 178 (352) Max.

Press. kPag (psig) 310 (45) Max.Humidity % Steam

(a-3) Wetwell Time (2) 0 h - 72 h(Figure 6.2-1) Bulk Temp. °C (°F) 135 (275) Max.

Press. kPag (psig) 310 (45) Max.Humidity % 100

Notes:

(1) For a pipe failure inside the containment vessel, water accumulates in the lower drywell.The amount depends upon the break location.

(2) Time denotes the time after the occurrence of LOCA.

3H-13

Page 9: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

* The containment structure shall withstand coincident fluid jet forces associated with theflow from the postulated rupture of any pipe within the containment.

* The containment structure shall accommodate flooding to a sufficient depth above theactive fuel to maintain core cooling and to permit safe removal of the fuel assembliesfrom the reactor core after the postulated DBA.

* The containment structure shall be protected from or designed to withstand hypotheticalmissiles from internal sources and uncontrolled motion of broken pipes, which couldendanger the integrity of the containment.

" The containment structure shall direct the high energy blowdown fluids from postulatedLOCA pipe ruptures in the DW to the pressure suppression pool and to the PassiveContainment Cooling System (PCCS).

* The containment system shall allow for periodic tests at the calculated peak or reducedtest pressure to measure the leakage from individual penetrations, isolation valves and theintegrated leakage rate from the containment structure to confirm the leak-tight integrityof the containment.

* The Containment Inerting System establishes and maintains the containment atmosphereto *• 3% by volume oxygen during normal operating conditions to ensure inertatmosphere operation.

* PCCS shall remove post-LOCA decay heat from the containment for a minimum of72 hours, without operator action, to maintain containment pressure and temperaturewithin design limits.

6.2.1.1.2 Design Features

The containment structure is a reinforced concrete cylindrical structure, which encloses theReactor Pressure Vessel (RPV) and its related systems and components. Key containmentcomponents and design features are exhibited in Figures 6.2-1 through 6.2-5. The containmentstructure has an internal steel liner providing the leak-tight containment boundary. Thecontainment is divided into a DW region and a WW region with interconnecting vent system.The functions of these regionsare as follows:

* The DW region is a leak-tight gas space, surrounding the RPV and reactor coolantpressure boundary, which provides containment of radioactive fission products, steam,and water released by a LOCA, prior to directing them to the suppression pool via theDW/WW Vent System. A relatively small quantity of DW steam is also directed to thePCCS during the LOCA blowdown.

" The WW region consists of the suppression pool and the gas space above it. Thesuppression pool is a large body of water to absorb energy by condensing steam fromSRV discharges and pipe break accidents. The pool is an additional source of reactorwater makeup and serves as a reactor heat sink. The flow path to the WW is designed toentrain radioactive materials by routing fluids through the suppression pool during andfollowing a LOCA. The gas space above the suppression pool is leak-tight and sized tocollect and retain the DW gases following a pipe break in the DW, without exceeding thecontainment design pressure.

6.2-2

Page 10: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

The DW/WW Vent System directs LOCA blowdown flow from the DW into the suppressionpool.

The containment structure consists of the following major structural components: RPV supportstructure (pedestal), diaphragm floor separating DW and WW, suppression pool floor slab,containment cylindrical outer wall, cylindrical vent wall, containment top slab, and DW head.The containment cylindrical outer wall extends below the suppression pool floor slab to thecommon basemat. This extension is not part of containment boundary, however, it supports theupper containment cylinder. The reinforced concrete basemat foundation supports the entirecontainment system and extends to support the RB surrounding the containment. The refuelingbellows seal extends from the lower flange of the reactor vessel to the interior of the reactorcavity. This extension is also not part of the containment boundary, however, it provides aSeismic Category I seal between the upper drywell and reactor well during a refueling outage.

The design parameters of the containment and the major components of the containment systemare given in Tables 6.2-1 through 6.2-4. A detailed discussion of their structural design bases isgiven in Section 3.8.

Drywell

The DW (Figure 6.2-1) comprises two volumes: (1) an upper DW volume surrounding the upperportion of the RPV and housing the main steam and feedwater piping, GDCS pools and piping,PCCS piping, ICS piping, SRVs and piping, Depressurization Valves (DPVs) and piping, DWcoolers and piping, and other miscellaneous systems; and (2) a lower DW volume below theRPV support structure housing the lower portion of the RPV, fine motion control rod drives,other miscellaneous systems and equipment below the RPV, and vessel bottom drain piping.

The upper DW is a cylindrical, reinforced concrete structure with a removable steel head and adiaphragm floor constructed of steel girders with concrete fill. The RPV support structureseparates the lower DW from the upper DW. There is an open communication path between thetwo DW volumes via upper DW to lower DW connecting vents, built into the RPV supportstructure. Penetrations through the liner for the DW head, equipment hatches, personnel locks,piping, electrical and instrumentation lines are provided with seals and leak-tight connections.

The DW is designed to withstand the pressure and temperature transients associated with therupture of any primary system pipe inside the DW, and also the negative differential pressuresassociated with containment depressurization events, when the steam in the DW is condensed bythe PCCS, the GDCS, the FAPCS, and cold water cascading from the break following post-LOCA flooding of the RPV.

For a postulated DBA, the calculated maximum bulk DW temperature and absolute pressure inTable 6.2-5 remain below their design values, shown in Table 6.2-1.

Three -vacuum breakers are provided between the DW and WW. The vacuum breaker is aprocess-actuated valve, similar to a check valve, see Figure 6.2-28. The purpose of the DW-to-WW vacuum breaker system is to protect the integrity of the diaphragm floor slab and vent wallbetween the DW and the WW, and the DW structure and liner, and to prevent back-flooding ofthe suppression pool water into the DW. The vacuum breaker is provided with redundantproximity sensors to detect its closed position. One out of the three vacuum breakers arerequired to perform vacuum relief function. The third vacuum breaker provides redundancy

6.2-3

Page 11: HITACHI GE Energy

26A6642AT Rev. 05ESBWR

W JJEcanmilIMaTEM PORARYX:WL4A 1DPV-72.GRF

8r2212007 6 10 33

Design Control Document/Tier 2

120-

100-

E9

72

Time (sec)

W:\JJEscamilla\TEMPORARY\FWL4AIDPV-72.GRF8/2212007 6010:33

36

Time (hr)

Figure 6.2-9bl. Feedwater Line Break (Nominal Case) -Containment Temperatures (72hrs)

6.2-103

Page 12: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W:MJE-cnam4l\TEMPORARYkFWL4A DOPV-72 GRF

802212007: 6:1033

120

100

Ea" .,

100 200 300 400 500

Time (eec)

W JJEscamifla\TEMPORARYIFWL4A_1DPV-72.GRF8/22W2007:6:10:33

50 100 150 200 250 300 350 400 450

Time (.)

Figure 6.2-9b2. Feedwater Line Break (Nominal Case) -Containment Temperatures (500 s)

6.2-104

Page 13: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W:UJE.scaill\TE0MPORARY'FWL4A_1DPV-72 GRF

8r222007 6:10:33

200,

180. ____

160,

140.

120

' 100

E

Time (sec)

W: JJEscamiIla\TEMPORARY\FWL4A_1 DPV-72.GRF

8/22/2007: 6:10:33

200 400 600 800 1000 1200 1400 1600 1800 2"00

Time (s)

Figure 6.2-9b3. Feedwater Line Break (Nominal Case) -Containment Temperatures (2000 s)

6.2-105

Page 14: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W:\JJEscmmillaCO4MSL FWL\MSL4A1OPV-72 GRF

8/19/2007 0:23:10

U

E 100

E8O

A-so

72

Time (see)

W:\JJEscamilla\DCD4MSLFWL\MSL4A 1 DPV-72.GRF8/19/2007 0:23:10

6 12 18 24 30 36 42 48 54 60 66

Time (hr)

Figure 6.2-10bl. Main Steam Line Break (Nominal Case) -Containment Temperatures (72 hrs)

72

6.2-112

Page 15: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W UJEaca.rrIIa/DCD4MSL_FWL\MSL4A 1DPV-72.GRF

8a19i2007 023:10

DW Gas Temperature

500

Time (sec)

WAJJEscamilla\DCD4MSLFWL\MSL4A_1 DPV-72.GRF8/19/2007 0:23:10

Tim (a)

Figure 6.2-10b2. Main Steam Line Break (Nominal Case) -Containment Temperatures (500 s)

6.2-113

Page 16: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W UJEwcamlla\DCD4MSL FWLXMSL4A lDPV-72 GRF

8d19i2007 0 23:10

200

180.

160-

140

120-

100

E12 -

2000

Time (see)

W:UJJEscamilla\DCD4MSLFWL\MSL4A 1 DPV-72.GRF8/19/2007:0:23:10

1000

Time (.)

Figure 6.2-10b3. Main Steam Line Break (Nominal Case) -Containment Temperatures (2000 s)

6.2-114

Page 17: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

N:1kw nC ONT4A\GDL4_I DPV-72.\GDL4alDPV-72a GRF

8/ 3M2007:17 1945

200

U

E126

72

Time (sec)

N:\Hwang\CONT4a\GDL4a 1DPV-72a\GDL4alDPV-72a.GRF8/3/2007:17:19:45

8 12 18 24 30 36 42 48 54 60 6 72

Time (hr)

Figure 6.2-11bl. GDCS Line Break (Nominal Case) -Containment Temperatures (72 hrs)

6.2-121

Page 18: HITACHI GE Energy

26A6642AT Rev. 05ESBWR

N:•wang\CONT4a\GDL4a_1DPV-72a\GDL4a_ 1DPV-72a.GRF8/3/2007:17:19:45

20 1

180 : -_ -Dryell Gas Temp (Level 34, Ring 5)

--Wewell Gas Temp (Level 31, Ring 7)160

-Sup. Pool Temp (level 29, Ring 7)140 -

120- -_____

S00

E

Design Control Document/Tier 2

0 50 100 150 200 250 300 350 400 450 500

Ttme Is)

N:\Hw-ag\CONT4aGDL4aI DPV-72a\GDL4a_1DPV-72aGRF

8/1/2007:17:19:45

Time (sec)

Figure 6.2-11b2. GDCS Line Break (Nominal Case) -Containment Temperatures (500 s)

6.2-122

Page 19: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

Nl•H-wrXCONT4a\GOL4a1DPVJ72a8GDL4a IDPV.72, 0GRF

813/2007.171945

200

180.

160 /

140

120 .....................

i 100

&-^

0 200 400 600 800 1000 1200 1400 1600 1800 2000

Time (sec)

N:\Hwang\CONT4a\GDL4a_1DPV-72a\GDL4a_1DPV-72a.GRF8/3/2007:17:19:45

0 200 400 600 800 1000 1200 1400 1600 1800 2000

Time i)

Figure 6.2-11b3. GDCS Line Break (Nominal Case) -Containment Temperatures (2000 s)

6.2-123

Page 20: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

M :w.ngCONT4a\BDL4aI DPV-72a\BDL4a_,DPV-72aGRF

8/5Q2W7: 6:12:26

120

100

Ea. -

72

Time (see)

M:\Hwang\CONT4a\BDL4a_1DPV-72a\BDL4a_1 DPV-72a.GRF8/5/2007: 6:12:26

Time (hI)

Figure 6.2-12bl. Bottom Drain Line Break (Nominal Case) -Containment Temperatures (72 hrs)

6.2-129

Page 21: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

M :w4gCONT4alBDL4a.1DPV-72.lBDL4aIDPV-72aGRF

8/5/2007: 61226

200-Avg (1.22 34)

180

i-Supp Pool T-9

160 _ _ _ _

140 _

120

1/5/2007:61226

Time (s)

Figure 6.2-12b2. Bottom Drain Line Break (Nominal Case) -Containment Temperatures (500 s)

6.2-130

Page 22: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

M:AHw-Mg/CONT4a/BDOL4a_lOPV-72a\BDL4 1 DPV-72a.GRF

8/5/2007:6:12:26

120-

100-

E

80-

Time (sec)

MA\Hwang\CONT4a\IBDL4a_1 DPV-72a\BDL4a_1 DPV-72a.GRF8/5/2007:6:12:26

200 400 600 800 1000 1200 1400 1600 1800 2000

Time is)

Figure 6.2-12b3. Bottom Drain Line Break (Nominal Case) -Containment Temperatures (2000 s)

6.2-131

Page 23: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W:J JEsca miIaDCDLOCA04FWL4A_ 1DPVCB-72 GRF

W=222007 454,52

200,

180 _

160,

140

,.120

100

E

6 12 18 24 30 36 42 48 54 60 66 72

Time (sec)

W:\JJEscamilla\DCDLOCAO4\FWL4A_1 DPVCB-72.GRF8/22/2007: 4:54:52

0 6 12 18 24 30 36 42 48 54 60 66 72

Time (hr)

Figure 6.2-13bl. Feedwater Line Break (Bounding Case) -Containment Temperatures (72 hrs)

6.2-137

Page 24: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W: J5JE4c.IIaDCDLOCA04FWL4A 1DPVCB-72 GRF

822r2007 454 52

100

500

Time (sec)

W:IJJEscamilla\DCDLOCA04\FWL4A 1 DPVCB-72.GRF8/22/2007: 4:54:52

Time 1)

Figure 6.2-13b2. Feedwater Line Break (Bounding Case) -Containment Temperatures (500 s)

6.2-138

Page 25: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W UJEnIlla\DCDLOCAO4\FWL4A_1 DPVCB-72.GRF

8122r2007: 4:5452

200

180.

160._ _

140 •

120•

100.

0 200 400 600 800 1000 1200 1400 1600 1800 2000

Time (see)

W:UJJEscamilla\DCDLOCAO4\FWL4A1IDPVCB-72.GRF8/22/2007: 4:54:52

0 200 400 600 800 1000 1200 1400 1600 1800 2000

Time (.)

Figure 6.2-13b3. Feedwater Line Break (Bounding Case) -Containment Temperatures (2000 s)

6.2-139

Page 26: HITACHI GE Energy

26A6642AT Rev. 05ESBWR Design Control Document/Tier 2

W.UJEscamieaDCD4MSL_FWL\MSL4A_1DPVCB-72 GRF

82/2r007 6:1021

2001 1 -

180

160

120.

a 100 ..........

E

80--

60 - - __

40

20 1

12 18 24 30 36 42 48 54 60 66 72

Time (sec)

W:\JJEscamilla\DCD4MSL FWLMISL4A_I DPVC8-72.GRF8/22/2007: 6:10:21

6 12 18 24 30 36 42 48 54 60 66 72

Time (hr)

Figure 6.2-14bl. Main Steam Line Break (Bounding Case) -Containment Temperatures (72 hrs)

6.2-145

Page 27: HITACHI GE Energy

26A6642AT Rev. 05ESBWR

W UJEsrn,.alXDCD4MSLFWLWV SL4AIDPVCa-72,GRF

&122r2007 6:10:21

Design Control Document/Tier 2

120

£8 100-

500

Time (sec)

W:\JJEscamilla\DCD4MSLFWL\MSL4A_1 DPVCB-72.GRF8/22/2007: 6:10:21

Time 1.)

Figure 6.2-14b2. Main Steam Line Break (Bounding Case) -Containment Temperatures (500 s)

6.2-146

Page 28: HITACHI GE Energy

26A6642AT Rev. 05ESBWR

W:UJEscnam~ilaDCD4MSL_FWLVMSL4AIDPVCB-72 GRF

8(2212007 6:1021

Design Control Document/Tier 2

120U

E

80

TIme (sec)

WMJJEscamifla\DCD4MSLFWL\OSL4A_1 DPVCB-72.GRF8/22/2007: 6:10:21

200 400 600 800 1000 1200 1400 1600 1800 2000

Ti-(.))

Figure 6.2-14b3. Main Steam Line Break (Bounding Case) -Containment Temperatures (2000 s)

6.2-147

Page 29: HITACHI GE Energy

26A6642BP Rev. 05ESBWR Design Control Document/Tier 2

6E. TRACG LOCA CONTAINMENT RESPONSE ANALYSIS

The chronology of progressions of Feedwater Line Break (FWLB) LOCA (Bounding Case) andMain Steam Line Break (MSLB) LOCA (Bounding Case) containment responses are discussedin detail in this appendix.

6E.1 Feedwater Line Break LOCA (Bounding Case)

Following the postulated FWLB LOCA, the Drywell pressure increases rapidly leading to theclearing of the Passive Containment Cooling System (PCCS) and main vents. The Drywellpressure increase is terminated at around 70 seconds (Figure 6.2-13a2), when most of thenon-condensable (NC) gases in the Drywell annulus have been purged into the Wetwell(Figure 6.2-13d3).

As shown in Figure 6.2-13a2, the peak Drywell pressure is approximately 318 kPa (46.1 psia) at347 seconds prior to the Gravity-Driven Cooling System (GDCS) flow initiation, shortly afterthe opening of the depressurization valves (DPVs) (Table 6.2-7d). This peak pressure is belowthe design pressure of 413.7 kPa (60 psia) with a large margin. The GDCS flow initiates atapproximately 513 seconds. The subcooled GDCS water continues flowing into the vessel,reduces the steaming from the reactor pressure vessel (RPV) and the Drywell pressure. Atapproximately 800 seconds, the Drywell pressure drops below the Wetwell pressure, causing theopening of the vacuum breakers and allowing some NC gases to flow back into the Drywell.Consequently, the system pressures drop to a value of approximately 260 kPa (Figure 6.2-13a3).

Figures 6.2-13dl through 6.2-13d3 show the NC gas pressures in the Drywell annulus, theDrywell head gas space, and the GDCS pool gas space. Figure 6.2-13d3 shows that most of theNC gases in the Drywell annulus are purged into the Wetwell within 100 seconds. At around800 seconds, some NC gases flows back to the Drywell annulus (Figure 6.2-13d3) after theopening of the vacuum breakers.

Subsequently, decay heat overcomes the subcooling in the GDCS water and steaming resumes(at -1800 seconds, Figure 6.2-13a3). The resumption of RPV steaming causes the Drywellpressure to increase again starting from 1800 seconds. The Drywell pressure reaches thelong-term peak of 339 kPa (49 psia) at 72 hours (Figure 6.2-13al).

After 1800 seconds, the Drywell pressure is higher than the Wetwell pressure. The PCCS movesthe steam and NC gas mixture from the Drywell and purges the NC gases into the Wetwell.Most of the NC gases that returned to the Drywell annulus because of vacuum breaker openingsare purged back into the Wetwell in approximately 3 hours (Figure 6.2-13dl).

Figure 6.2-13cl compares the total heat removal by the PCCS with the decay heat. After thefirst 6 hours, the PCCS is able to remove all the decay heat with some margin to spare. Fromthis point on, all the decay heat generated by the core is transferred to the Isolation Condenser(IC)/Passive Containment Cooling (PCC) pools, which are located outside of the containment.

Page 30: HITACHI GE Energy

26A6642BP Rev. 05ESBWR Design Control Document/Tier 2

Figures 6.2-13b] through 6.2-13b3 show the Drywell gas temperature, Wetwell gas temperature,and suppression pool surface temperature. As shown in Figure 6.2-13b2, the bulk Dry welltemperature reaches a maximum of 1l66.3°C at approximately 350 seconds. By the end of72 hours, the Drywell temperature is maintained at 138.7°C, well below the Drywell designtemperature of 171°C (340'F). While the Wetwell gas temberature remains below the Wetwelltemperature design limit of 121.P°C (250'F) in 72 hours.

Figure 6E-1 compares the water levels in the Drywell annulus and suppression pool. TheDrywell annulus water level rises due to the break flow discharges from the RPV and the brokenfeedwater piping. In approximately 10 hours, the Drywell annulus water level reaches thequasi-equilibrium elevation of 9 meters. At this elevation, the Drywell annulus water level isapproximately 3 meters below the spillover holes. The hot water in the Drywell annulus willremain in the Drywell and not enter into the bottom of the suppression pool via the spilloverholes.

Figure 6E-2 shows the GDCS pool levels. The water level drops below L33 (Figure 6.2-7) inapproximately 4 hours, after the initiation of GDCS flow. This creates a bottom layer of NC gasspace, which is approximately 6 meters below the connection pipes. The NC gas masses storedin the top two levels (L34 and L35) are purged to minimal values in a few hours, through theconnection pipes.

6E.2 Main Steam Line Break LOCA (Boundiniz Case)

Following the postulated LOCA, the Drywell pressure increased rapidly leading to clearing ofthe PCCS and main vents. The containment pressure responses of the Drywell, Wetwell, andRPV are shown in Figures 6.2-14al through 6.2-14a3. During the initial blowdown phase, theNC gases in the upper regions of the Drywell are cleared rapidly to the Wetwell through themain vents, as shown by the Drywell and GDCS gas pressures in Figures 6.2-14d2 and 6.2-14d3.The Drywell pressure starts to turn around and decrease at approximately 930 seconds after theGDCS flow initiates, as shown in Figure 6.2-14a3. The GDCS flow fills the reactor vessel to theelevation of the break, and then spills into the Drywell. The heat transfer process during theGDCS cooling period is characterized by condensation of steam in the vessel and Drywell. Ataround 550 seconds, vacuum breaker openings occur as the steam production drops off, returningsome of NC gases back to the Drywell. Subsequently, decay heat overcomes the subcooling ofthe GDCS water and steaming resumes. The Drywell pressure rises until flow is establishedthrough the PCCS, where condensate from the PCCS is recycled back into the vessel through theGDCS pool in the Drywell. It takes approximately 18 hours for the NC gases to be cleared fromthe GDCS gas space and 23 hours from the Drywell as shown in Figure 6.2-14dI. The long-term(72 hours) response of the containment pressure is shown in Figure 6.2-14al. The Drywellpressure levels off at around 4 hours and increases in a gradual pace. The peak Drywell pressurereaches 384 kPa (55.8 psia) at the end of 72 hours, but remains below the design pressure of414 kPa (60 psia).

Due to the presence NC gases, the effectiveness of condensation heat transfer in the PCCS isimpaired for the first 28 hours, as shown by the PCCS heat removal versus decay heat inFigure 6.2-14cI. The spike in the heat removal for the time between 17 and 28 hours indicate

Page 31: HITACHI GE Energy

26A6642BP Rev. 05ESBWR Design Control Document/Tier 2

the period where the PCCS heat removal temporarily exceeds the decay heat, resulting in a dropin the Drywell pressure below the Wetwell pressure. This leads to a temporary cessation ofsteam flow to the PCCS. Subsequently the vacuum breakers open, some NC gases are returnedto the Drywell, and the PCCS heat removal rate increases as the steam flow from the Drywellresumes. For the first 28 hours, the decay heat exceeds the PCCS heat removal capacity. Thenafter the NC gases are purged from the GDCS and Drywell gas spaces, the PCCS heat removalcapacity matches the decay heat. However, it still cannot remove radiation heating generated inthe core. Hence, both the Drywell and Wetwell pressures continue to increase continually overthe 72-hour period.

Figures 6.2-14b] through 6.2-14b3 show the Drywell, Wetwell and suppression pool gas spacetemperature responses at various elevations. Initially, all elevations heat up due to the main ventand break discharge. After the main vents close, only the upper levels are impacted by the PCCSvent discharge. The-bulk'Drywell gas temperature peaks at 156.2°C immediately following theblowdown, which is slightly below the Drywell design temperature of 171°C (340'F), due toadiabatic compression by the steam discharging from the break. In the long term (72 hours), thetemperature remains below 171'C. While the Wetwell gas temperature remains below theWetwell temperature design limit of 121.1°C (250TF) in 72 hours.

Figure 6E-3 compares the water levels in the Drywell annulus and suppression pool. TheDrywell annulus water level rises due to the break flow discharges from the main steam linebroken piping. The Drywell annulus water level will remain in the lower Drywell and not enterinto the bottom of the suppression pool via the spillover holes.

For MSLB, the GDCS pool level (Figure 6E-4) drops to the elevation of the DPVs and staysabove L33 (Figure 6.2-7). As no gas mass is stored below L33, gas masses stored in the top twolevels (L34 and L35) are purged to minimal values in a few hours through the connection pipes.Approximately 60% (or 1200 mi3) of the initial GDCS cold water 46.1C (1 15'F) remains insidethe GDCS pools. The hot PCCS condensate mixes with the cold GDCS pool water. Thetemperature of the GDCS water injected into the RPV is lower than that of the FWLB. A portionof the decay heat is used to heat up the incoming colder GDCS water, which is shown inFigure 6.2-14c3 as the difference between the decay heat and the total PCCS condensationpower. It takes approximately 60 hours to bring the mixture temperature to approximately 95°C.

Both the initial blowdown and the ensuing suppression pool heat up are larger in the MSLB thanthe FWLB, which leads to higher pool water temperature and higher suppression pool waterlevel and smaller Wetwell gas space volume. All these effects result in higher Drywell pressurein the MSLB than FWLB.