HiRadMat : report from WG2 – WANF dismantling January 08, 2010 S. Evrard 1 Activities carried out in Week 1 Planning for Week 2 WANF cleaning : preparation T1 dismantling : news. Agenda

HiRadMat : report from WG2 – WANF dismantling

  • Upload
    kioshi

  • View
    32

  • Download
    0

Embed Size (px)

DESCRIPTION

HiRadMat : report from WG2 – WANF dismantling . Agenda. Activities carried out in Week 1 Planning for Week 2 WANF cleaning : preparation T1 dismantling : news. Activities carried out in Week 1. MCA and TCX blocks. January 08, 2010. Forklift shielding in progress. - PowerPoint PPT Presentation

Citation preview

Page 1: HiRadMat : report from WG2 – WANF dismantling

HiRadMat : report from WG2 – WANF dismantling

January 08, 2010S. Evrard

1

• Activities carried out in Week 1• Planning for Week 2• WANF cleaning : preparation• T1 dismantling : news.

Agenda

Page 2: HiRadMat : report from WG2 – WANF dismantling

Activities carried out in Week 1

S. Evrard

2 MCA and TCX blocks

• Forklift shielding in progress

January 08, 2010

Page 3: HiRadMat : report from WG2 – WANF dismantling

Activities carried out in Week 1

S. Evrard

3 B846 pit reconnaissance

• Two doors opened by Fire Brigade• Crinoline ladder seems to be OK

January 08, 2010

Page 4: HiRadMat : report from WG2 – WANF dismantling

Activities carried out in Week 1

S. Evrard

4 Cabling

• 3 cables pulled for door interlocks and patrol box• Red telephone cable still missing• Lighting power cable already available : additional TL’s in late January

January 08, 2010

Page 5: HiRadMat : report from WG2 – WANF dismantling

Activities carried out in Week 1

S. Evrard

5 Furet dismantling and electrical cupboard refurbishment

• Work in progress• FURET on the floor• Cerap will clean it on Monday

January 08, 2010

Page 6: HiRadMat : report from WG2 – WANF dismantling

Co-activities in January 2010 6 Planning in week 2

EN-HE

EN-HE

EN-CVContractor

EN-HE

GS-ASE, IT

-CS

EN-HE: T1 : MCA + Tax blocksEN-HE: furet removalEN-HE: Electrical cabinet refurbish.

January 08, 2010

Page 7: HiRadMat : report from WG2 – WANF dismantling

WANF cleaning

S. Evrard

7

• ENDEL SCTN best offer out of 4 companies enquired (all contacted):• Work procedure transmitted today by Endel• Analysis in progress with DG-SCR• Work preparation (safety courses, access requests, equipment on site,…)

on Thursday 14 and Friday 15• Work in Week 3 (18 22 January)

January 08, 2010

Page 8: HiRadMat : report from WG2 – WANF dismantling

T1 dismantling : news

S. Evrard

8

• Location of remaining beam pipe defined (Thanks to V. De Jesus)

January 08, 2010