18
High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace Castings for Improved Defense Readiness NADCA DMC February 2008 Chicago, IL

High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

  • Upload
    donkor

  • View
    26

  • Download
    2

Embed Size (px)

DESCRIPTION

High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace. Castings for Improved Defense Readiness NADCA DMC February 2008 Chicago, IL. Objectives. - PowerPoint PPT Presentation

Citation preview

Page 1: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

High Production Rate ToolingCase Western Reserve University

David SchwamJohn F. Wallace

Castings for Improved Defense Readiness

NADCA DMC February 2008

Chicago, IL

Page 2: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Objectives

• Production rate determines profitability of metal mold processes. Increasing production rate is therefore a high priority, boosting profits and competitiveness.

• A key aspect of increased production rate is shorter cycle times by faster removal of heat from the casting.

• Advances in modern die steels should allow more aggressive use of cooling line size and distance from the cavity.

• The project will evaluate effectiveness of new cooling line design and provide guidelines that account for higher strength and toughness of advanced die steels.

Page 3: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Needs & Benefits

Benefits to:

• DoD– Shorter production lead times and lower cost

parts for DoD weapon systems

• Industry– Increased profitability and competitiveness

of metal mold casting industry

Page 4: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Process Specifications

IN SIMULATION THIS OCCURS AT THE SAME TIME.

Spray time is:

(5) Seconds on large inserts

(3) seconds on cores

Some additional time:

(5) seconds blow off

(2) seconds wait

Page 5: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Cover Side Cooling Lines – V4

Cover Cores

Green shows cooling line bubblers in cores. Material Water

Cover cooling lines. Material - Oil

Oil lines 157 ºC (300 –325 ºF)

Flow rate of 0.34 m3/hr (1.5 gal/min)

HTC of 500 W/m2K

Water line run at 20 ºC

Flow rate of 0.7 m3/hr. (3.0 gal / min)

HTC of 5500 W/m2K

Shot tip - HTC of 10000 W/m2K

Shot Tip cooling Material – Water Not shown

Die Steel initial temp 300 ºC (600 º F)

Page 6: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Ejector Side Cooling Lines V4

Green shows cooling line bubbler in ejector inserts. Material Water

Ejector cooling lines. Material - Oil

Ejector Runner block cooling lines. Material - Water

Oil lines 157 ºC (300 –325 ºF)

Flow rate of 0.34 m3/hr (1.5 gal/min)

HTC of 500 W/m2K

Water line run at 20 ºC

Flow rate of 0.7 m3/hr. (3.0 gal / min)

HTC of 5500 W/m2KDie Steel initial temp 300 ºC (600 º F)

Page 7: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Section Though Die

Cover die cooling lines

Ejector die bubbler lines.

Ejector die bubbler lines.

COVER SIDE

EJECTOR SIDE

Cover core bubbler lines.

Thermocouple placed in center of the part spaced ½ way between the cores (length wise).

A

B

0.30”

0.50”

Current Design

A= 0.87”

B= 0.69”

Page 8: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Part during solidification V4 (open die at 30 sec.)Click on image

Page 9: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Section though the die steel during solidification V04Click on image

Page 10: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Thermocouple Result During Cycle V04

At 30 seconds thermocouple is 545.6 C

Page 11: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Cover Side Cooling Lines – V5 Cover Cores

Green shows cooling line bubblers in cores. Material Water

Cover cooling lines. Material - Water

Oil lines NONE

Water line run at 20 ºC

Flow rate of 0.7 m3/hr. (3.0 gal / min)

HTC of 5500 W/m2K

Shot tip - HTC of 10000 W/m2K

Shot Tip cooling Material – Water Not shown

Die Steel initial temp 150 ºC (300 º F)

Page 12: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Ejector Side Cooling Lines - V5

Green shows cooling line bubbler in ejector inserts. Material Water

Ejector cooling lines. Material - Water

Ejector Runner block cooling lines. Material - Water

Oil lines NONE

Water line run at 20 ºC

Flow rate of 0.7 m3/hr. (3.0 gal / min)

HTC of 5500 W/m2K

Die Steel initial temp 150 ºC (300 º F)

Page 13: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Section Though Die

Cover die cooling lines

Ejector die bubbler lines.

Ejector die bubbler lines.

COVER SIDE

EJECTOR SIDE

Cover core bubbler lines.

Thermocouple placed in center of the part spaced ½ way between the cores (length wise).

A

B

0.30”

0.50”

Modified Design

A= 0.50”

B= 0.50”

Page 14: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Thermocouple Result During V05

•V5 was run with these conditions.

•Initial Die Steel initial temp 150 ºC (300 º F)

•A and B dimensions changed to 0.500

•A & B lines run with water.23.9 sec

Page 15: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Oil (V04) vs. Water (V05) Comparison

V05 with waterV04 with Oil

TC = 545.6 C @ 30 sec TC = 545.6 C @23.9 sec

Predicted cycle time reduction: 6.1/30=20%

Page 16: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Project and Implementation Plan

• Fabricate and test die casting inserts with larger cooling lines and/or closer to the casting.

• Monitor production of parts and determine new cycle time.

• Evaluate effect of modified cooling line system on die life.

• A good baseline for the study is available from extensive database of previous production.

• Results will be disseminated through NADCA meetings, NADCA publications for industry, and the Metalcasting Congress

Page 17: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

Acknowledgements

• AMC’s Castings for Improved Defense Readiness program is sponsored the Armaments Research and Development Engineering Center, Picatinny, NJ and Benet Laboratories, Watervliet, NY.

• The support of St. Clair Die Casting is gratefully acknowledged.

Page 18: High Production Rate Tooling Case Western Reserve University David Schwam John F. Wallace

High Production Rate ToolingDLA - POC: Dan Gearing ([email protected], 703-767-1418)

Warfighter Relevance: Increased productivity of metal mold components for weapon systems

• Problem: High cycle times in the production of metal mold castings

• Objective: Evaluate advanced cooling techniques for casting dies in order to reduce cycle times for metal mold castings

• Benefits: 10% reduction in cycle time associated with the production of a die casting

• Reduced production lead time

• Improved productivity

• Reduced operating costs

• Milestones / Deliverables– Revised guideline for cooling line placement

• Transition Plan– The revised guidelines will be added to the NADCA Die

Cooling Systems Engineering Course and accompanying text

Partners:– Case Western Reserve University,

NADCA, St. Clair Die Casting, Premier Tool & Die Casting