Upload
phunghanh
View
223
Download
1
Embed Size (px)
Citation preview
Heat networks:
Code of Practice
for the UK
Rehau Seminar
4th November 2015
Paul Woods Concessions Director Cofely Energy Services [email protected]
• Leicester District Energy • Birmingham District Energy • Coventry District Energy
• Olympic Park & Stratford
City
• Bloomsbury Heat & Power
• ExCeL Exhibition Centre
• Southampton Geothermal
• Eastleigh
£3.1bn revenue stream over the concessions
77,000 tonnes CO2 saved per annum 270 GWh energy sales per annum
London
Midlands
South coast
Cofely’s Heat Network Projects
www.cibse.org/CP1
Why use heat networks/district heating?
• Lower CO2 emissions – limiting climate change
• Lower running costs – combating fuel poverty
• Delivers high reliability from diverse heat supplies
• Above has led to:
• Requirements for heat networks from local planning policies
• Development of Government policy to support Heat Networks
• EU Energy Efficiency Directive encourages heat networks
www.cibse.org/CP1
The need for standards
• Heat networks not always delivering on promises
• ADE market research and anecdotal evidence revealed the following
problem areas:
• High heat losses from • Poor pipework specification
• Lack of insulation continuity
• High operating temperatures
• Poor pipework layout
• High capital costs • Oversizing of network and plant
• CHPs not operating well
• High operating and maintenance costs
• Poor commissioning
• A threat to the sector’s future – main weaknesses in the areas of design
and commissioning
www.cibse.org/CP1
A fragmented supply chain
Feasibility Outline design Detailed design Construction
and Commissioning
Operation
Suppliers
Energy services company (ESCo)
www.cibse.org/CP1
www.cibse.org/CP1
• Require CoP to be followed in briefs and specifications
• Ensure any deviations from CoP are documented
• Monitor project against the minimum requirements
• Manage handover between stages
• Ensure project team is experienced and qualified in heat network
• Provide feedback to CIBSE on the experience of using the Code to enable progressive improvement
• Best Practice – employ an independent auditor to check compliance with the Code
Objective 1.1 – Aimed at Clients
www.cibse.org/CP1
Key goals that run across all stages of
the plan of work
A. Correct sizing of plant
and network
B. Low heat losses
C. Low return temperatures
D. Use of variable volume
control
E. Use low carbon heat
supply
F. Safe, high quality, low
environmental impact
systems
But these goals are linked!
www.cibse.org/CP1
Correct sizing of plant and network
1. Main concern was diversity
factor for instantaneous
domestic hot water heating
2. Typical peak seen in practice
is <5kW per dwelling for new
flats
3. CHP heat capacity typically
one third of peak
4. For the majority of time
systems operate at 10% to
25% of peak
5. Oversizing of network leads
to higher heat losses
www.cibse.org/CP1
Achieving low heat losses from network
1. Code requires calculation on heat
losses and economic evaluation – no
fixed maximum loss
2. Avoid oversizing
3. Minimise length of network
4. Insulation type and thickness
5. Low mean network temperature
• But is a 90/40 system worse than a 65/40
system? – use of variable network
temperatures
6. How important is it?
• A typical CHP-based system with 30% heat
losses has 10% higher emissions than one
with a 10% heat loss – as the low carbon
CHP will supply the extra heat loss
www.cibse.org/CP1
Low return temperatures (and low flow
temperatures)
1. Low return temperatures result in:
• Less volume of water
• Smaller pipes – lower cost
• Lower heat losses
• More efficient central plant
• More cost-effective thermal storage
Requirement for new radiator circuit is a return temperature < 40°C – achieved with pre-settable TRV designed for low flow rates
The building services design governs return temperatures!
2. Lower flow temperatures
result in:
• More efficient central plant
• Lower heat losses
• But larger pipes offset this
benefit and add to cost –
need to consider impact of
smaller delta T (Tflow-
Treturn)
3. Minimise bypasses,
minimise no. of heat
exchangers, and use
variable volume control
www.cibse.org/CP1
Variable volume control
1. Variable volume control using two-port control valves results in:
• Falling return temperatures under part-load
• Lower pumping energy*
• Lower heat losses
• Better use of low carbon plant
2. Need controlled bypass flow to maintain temperatures in the network and meet minimum pump flow requirements
*For a 50% drop in demand pump energy drops to 12.5%
0.00
5.00
10.00
15.00
20.00
25.00
30.00
0 500 1000 1500 2000 2500 3000 3500 4000
Ave
rage
dT
MWh/year
www.cibse.org/CP1
Use of low carbon heat sources
1. Optimal sizing
• 60% to 80% from low carbon plant
• Delivered CO2 content <150g/kWh
2. Use of thermal store
3. Maintain low return temperatures
4. Location of peak boilers
www.cibse.org/CP1
Safety, quality and environment
1. Safety
• Trenching work remains a high risk area
2. Quality
• Inspections of heat network installations
• Commissioning of buildings
3. Environment
• Visual impact
• Air quality
• Noise
• Construction impact
Page 14
www.cibse.org/CP1
www.cibse.org/CP1
• Clear and transparent statement on heat tariffs and charges and how these may be indexed over time – compliance with the Heat Trust scheme
• Choice of paper or electronic bills
• Pre-payment option
• Annual statement showing comparison of costs with an individual heating system
• Annual statement on heat sources used, CO2 emissions, heat losses, pumping energy
Objective 7.1 – Billing of customers
www.cibse.org/CP1
• Information pack for residents when they move in
especially around controls and metering
• Annual newsletter about the scheme
• Provide advance notice of any planned shutdowns
• Vulnerable customers
• Helpline and emergency calls
• Complaints procedure
• Best Practice – customer representative committee
Objective 7.2 – Communications to customers
www.cibse.org/CP1
The Code of Practice – training and certification
One day course – aimed at developers, clients, Local Authorities etc.
Next date:
• 11 November 2015 (London)
Two day course – detailed technical content and exam/certification
Next dates:
• 18-19 November 2015 (Birmingham)
• 30 Nov-01 December 2015 (London)
IN HOUSE TRAINING AVAILABLE – 6 or more people
www.cibse.org/CP1
Purchase or download the Code (free pdf for
CIBSE members) at www.cibse.org/CP1