Hayden, Thomas (CFM)
From: Tracy.Abdouch [[email protected]]Sent: Friday, August 12, 2011 6:04 PMTo: Hayden, Thomas (CFM)Cc: Pogany, Tim (CFM); Willoughby, Thaddeus (CFM); Meranda, Mark E - (MIA); Klebba, A. J.
(KIEWIT-Turner); Whitham, Michael G - (DEN); Carmelita Thorndike; Josh Schaefer; Fatur, Eugene P - (DEN); Wayne.Given; Matt.Koenen
Subject: FTP Schedule Attachments: DVFTP Schedule Assumptions 08 12 11 rev 12 .pdf; 2222 - FTP SCHEDULE
REPORTS.pdf
Tom,
Please find attached pdf copies of the FTP schedule reports and assumptions.
The schedule reports file includes the following:
• Overall schedule by WBS
• Critical Path
• Total Float
• Hot List
• 4 Week Look Ahead
• Network Diagrams
Due to the file sizes, we will deliver the P6 xer file and schedule key plans (on discs) to you first thing this Monday.
Thank you,
Tracy Abdouch
Kiewit - Turner
303-917-7717
Page 001
Schedule Reports
Schedule File – DVFTP-04-8.12.11 VA Medical Campus
TABLE of CONTENTS
1. Overall Schedule by WBS
2. Summary schedule
3. Critical Paths
4. Total Float Report
5. Hot List
6. 4 Week Look Ahead
7. Network Diagrams
VA Milestones Off-site Infrastructure CON DAT ENC PVS PVN PSN IBS IBN CBN CBC RES
Page 003
Activity ID Activity Name OrigDur
Start Finish
DENVER VA MDENVER VA MEDICAL CENTER - FTP SCHEDULEDENVER VA MEDICAL CENTER - FTP SCHEDULEDENVER VA MEDICAL CENTER - FTP SCHEDULEDENVER VA MEDICAL CENTER - FTP SCHEDULEPROJECT MILEPROJECT MILESTONESPROJECT MILESTONESPROJECT MILESTONESPROJECT MILESTONESAAAA-1010 NTP FOR CONSTRUCTION 0 06-Sep-11*
AAAA-1040 NTP FOR POTHOLING FOR SHORING TIE-BACKS (start milestone) 0 07-Sep-11
AAAA-1030 NTP FOR POTHOLING FOR WHEELING WATERLINE (start milestone) 0 12-Sep-11
ZZZZWS-9999 NEW WATERLINE COMPLETE @ WHEELING ST (finish milestone) 0 30-Jan-12
AAAAPVS-0100 START PVS CONSTRUCTION (start milestone) 0 06-Feb-12
CBSMIMI-3610 DOD/VA ACCEPT LEVELS 1,3 & 4 - CBS MILESTONE 0 08-Feb-12*
AAAADAT-0100 START DAT CONSTRUCTION (start milestone) 0 10-Feb-12
AAAAIBS-0100 START IBS CONSTRUCTION (start milestone) 0 14-Mar-12
AAAAENC-0100 START ENC CONSTRUCTION (start milestone) 0 05-Apr-12
AAAACON-0100 START CON CONSTRUCTION (start milestone) 0 24-Apr-12
AAAAIBT-0100 START IBN CONSTRUCTION (start milestone) 0 27-Apr-12
AAAACBN-0100 START CBN CONSTRUCTION (start milestone) 0 12-Jun-12
AAAAPSN-0100 START PSN CONSTRUCTION (start milestone) 0 14-Jun-12
AAAACBC-0100 START CBC CONSTRUCTION (start milestone) 0 10-Jul-12
AAAACLC-100 START CLC CONSTRUCTION (start milestone) 0 22-Aug-12
AAAAPVN-0100 START PVN CONSTRUCTION (start milestone) 0 23-Sep-13
ZZZZPVS-9999 FINISH PVS CONSTRUCTION (finish milestone) 0 30-Jan-14
AAAARES-0100 START RES CONSTRUCTION (start milestone) 0 31-Jan-14
ZZZZENC-9999 FINISH ENC CONSTRUCTION (finish milestone) 0 28-Feb-14
ZZZZPSN-9999 FINISH PSN CONSTRUCTION (finish milestone) 0 14-Mar-14
ZZZZCLC-10009 FINISH CLC CONSTRUCTION (finish milestone) 0 06-Apr-14
ZZZZOFF-10019 FINISH OFF-SITE IMPROVEMENTS (finish milestone) 0 22-May-14
ZZZZIBT-9999 FINISH IBN CONSTRUCTION (finish milestone) 0 19-Oct-14
ZZZZSIT-9999 FINISH SITEWORK (finish milestone) 0 04-Nov-14
ZZZZIBS-9999 FINISH IBS CONSTRUCTION (finish milestone) 0 06-Nov-14
ZZZZCBN-9999 FINISH CBN CONSTRUCTION (finish milestone) 0 20-Jan-15
ZZZZPVN-9999 FINISH PVN CONSTRUCTION (finish milestone) 0 24-Feb-15
ZZZZDAT-9999 FINISH DAT CONSTRUCTION (finish milestone) 0 26-Feb-15
ZZZZCBC-9999 FINISH CBC CONSTRUCTION (finish milestone) 0 26-Feb-15
ZZZZCON-9999 FINISH CON CONSTRUCTION (finish milestone) 0 23-Mar-15
ZZZZZZZ-10009 CAMPUS SUBSTANTIAL COMPLETION LESS THE RESEARCH BUILDING (finish milestone) 0 28-Mar-15*
ZZZZCBS-9999 FINISH CBS CONSTRUCTION (finish milestone) 0 30-Sep-15
ZZZZRES-9999 FINISH RES CONSTRUCTION (finish milestone) 0 03-Oct-15
ZZZZZZZ-10019 CAMPUS FINAL COMPLETION (finish milestone) 0 03-Oct-15*
BUILDINGS AVABUILDINGS AVAILABLE TO ENERGIZEBUILDINGS AVAILABLE TO ENERGIZEBUILDINGS AVAILABLE TO ENERGIZEBUILDINGS AVAILABLE TO ENERGIZEEEEEENC-0990 ENC BLDG AVAILABLE FOR ENERGIZE 0 29-Aug-13
EEEEPVS-0000 PVS BLDG AVAILABLE FOR ENERGIZE 0 17-Oct-13
EEEEDAT-0000 DAT BLDG AVAILABLE FOR ENERGIZE 0 23-Oct-13
EEEEPSN-0000 PSN BLDG AVAILABLE FOR ENERGIZE 0 07-Nov-13
EEEEIBN-0000 IBN BLDG AVAILABLE FOR ENERGIZE 0 04-Feb-14
EEEEIBS-0000 IBS BLDG AVAILABLE FOR ENERGIZE 0 13-Feb-14
EEEECBN-0000 CBN BLDG AVAILABLE FOR ENERGIZE 0 26-Jun-14
EEEECBC-0000 CBC BLDG AVAILABLE FOR ENERGIZE 0 07-Jul-14
EEEEPVN-0000 PVN BLDG AVAILABLE FOR ENERGIZE 0 07-Oct-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 1 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 004
Activity ID Activity Name OrigDur
Start Finish
EEEECON-0000 CON BLDG AVAILABLE FOR ENERGIZE 0 10-Oct-14
EEEERES-0000 RES BLDG AVAILABLE FOR ENERGIZE 0 27-May-15
OVERALL BUILDOVERALL BUILDING DURATIONSOVERALL BUILDING DURATIONSOVERALL BUILDING DURATIONSOVERALL BUILDING DURATIONSXXXXCBS-0500 CBS OVERALL DURATION 936 09-May-11 A 30-Sep-15
XXXXSIT-0510 INITIAL SITEWORK DURATION 958 11-Jan-12 25-Aug-14
XXXXPVS-0500 PVS OVERALL DURATION 724 06-Feb-12 30-Jan-14
XXXXDAT-0500 DAT OVERALL DURATION 1113 10-Feb-12 26-Feb-15
XXXXIBS-0500 IBS OVERALL DURATION 968 14-Mar-12 06-Nov-14
XXXXENC-0500 ENC OVERALL DURATION 695 05-Apr-12 28-Feb-14
XXXXCON-0500 CON OVERALL DURATION 1064 24-Apr-12 23-Mar-15
XXXXIBN-0500 IBN OVERALL DURATION 906 27-Apr-12 19-Oct-14
XXXXCBN-0500 CBN OVERALL DURATION 953 12-Jun-12 20-Jan-15
XXXXPSN-0500 PSN OVERALL DURATION 639 14-Jun-12 14-Mar-14
XXXXCBC-0500 CBC OVERALL DURATION 961 10-Jul-12 26-Feb-15
XXXXCLC-0500 CLC OVERALL DURATION 480 13-Dec-12 06-Apr-14
XXXXPVN-0500 PVN OVERALL DURATION 520 23-Sep-13 24-Feb-15
XXXCAMP-1600 COMMISSION - FULL CAMPUS 315 24-Dec-13 27-Mar-15
XXXXRES-0500 RES OVERALL DURATION 611 31-Jan-14 03-Oct-15
VA MILESTONEVA MILESTONESVA MILESTONESVA MILESTONESVA MILESTONESAAAA-4630 VA PROVIDES CONSENT TO SUBCONTRACT - DESIGN ASSIST SUBCONTRACTORS 0 06-Sep-11
AAAA-5580 VA APPROVE LOW VOLTAGE CONTRACTOR DESIGN ASSIST 0 07-Sep-11
AAAA-4800 VA APPROVE MECHANICAL AND PLUMBING CONTRACTOR DESIGN ASSIST 0 07-Sep-11
AAAA-4810 VA APPROVE ELECTRICAL CONTRACTOR DESIGN ASSIST 0 07-Sep-11
P-CD3-3660 VA APPROVE CURTAIN WALL CONTRACTOR DESIGN ASSIST 0 07-Sep-11
AAAA-5520 VA REVIEW BID TABS - TEMP REDIRECTION OF STORMWATER 2 12-Oct-11 13-Oct-11
SITSWTP-5720 VA REVIEW BID TABS - TEMP PARKING CBS 5 13-Oct-11 19-Oct-11
AAAA-5630 VA PROVIDES CONSENT TO SUBCONTRACT - TEMP REDIRECTION OF STORMWATER 0 13-Oct-11
SITSWTP-5620 VA PROVIDES CONSENT TO SUBCONTRACT - TEMP PARKING CBS 0 19-Oct-11
AAAA-5570 VA REVIEW/APPROVE TEMP REDIRECTION OF STORMWATER 5 09-Nov-11 16-Nov-11
SITSWTP-7800 JVT DESIGN COMPLETE - TEMP PARKING 0 28-Nov-11
SITSWTP1-5530 VA REVIEW/APPROVE TEMP PARKING 15 29-Nov-11 19-Dec-11
RFP3-0100 VACATE CREDIT UNION 10 01-Feb-12* 11-Feb-12
XXXXRES-500 RES TEMPORARY PARKING OVERALL DURATION 722 09-Feb-12 30-Jan-14
AAAA-5640 VA FINAL APPROVAL OF CONSTRUCTION SCHEDULE 0 24-Sep-12
XXXXPVS-510 PVS (UNDERGROUND) TEMPORARY PARKING OVERALL DURATION 422 31-Jan-14 28-Mar-15
CBS-0100 KT AND VA VACATE CBS LEVEL 2 10 24-Mar-15 02-Apr-15
CBS-1 PRECON MCBS-1 PRECON MILESTONESCBS-1 PRECON MILESTONESCBS-1 PRECON MILESTONESCBS-1 PRECON MILESTONESP-CBS-4100 VA APPROVES FIRM FIXED PRICE 100% AND ISSUES MOD - CBS-1 0 15-Aug-11
RFP-3 PRECON MRFP-3 PRECON MILESTONESRFP-3 PRECON MILESTONESRFP-3 PRECON MILESTONESRFP-3 PRECON MILESTONESC-RF3-1408 VA APPROVAL OF ABATEMENT PLAN - RFP 3 30 12-Jul-11 A 16-Aug-11
OFS PRECON MIOFS PRECON MILESTONESOFS PRECON MILESTONESOFS PRECON MILESTONESOFS PRECON MILESTONESOSI-4810 CITY OF AURORA PLAN REVIEW AND APPROVAL - OSI-1 129 10-Feb-11 A 23-Nov-11
OSI-4850 CITY OF AURORA WHEELING WATER LINE REVIEW AND AP - OSI-1 62 10-Feb-11 A 23-Nov-11
OSI-4410 VA REVIEWS/SIGN-OFF ON BID TABS- OSI-1 5 09-Sep-11 15-Sep-11
OSI-5620 VA PROVDES CONSENT TO SUBCONTRACT - OSI-1 0 15-Sep-11
OSI-250 VA LICENSE AGREEMENTS WITH FRA/COA/UCD 0 23-Nov-11*
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 2 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 005
Activity ID Activity Name OrigDur
Start Finish
STR-1 PRECON MSTR-1 PRECON MILESTONESSTR-1 PRECON MILESTONESSTR-1 PRECON MILESTONESSTR-1 PRECON MILESTONESAAAA-5590 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1 0 06-Sep-11
STR1-5710 VA REVIEW BID TABS (earthwork) - STR-1 5 21-Sep-11 27-Sep-11
AAAA-5610 VA PROVIDES CONSENT TO SUBCONTRACT (earthwork) - STR-1 0 27-Sep-11
STR1-5610 VA REVIEW/APPROVE SHOP DRAWINGS - CBS ROOF DRAIN 20 03-Nov-11 05-Dec-11
STR1-0000 VA OBTAIN APPROVAL FOR TIE-BACKS UNDER ROADWAYS 0 23-Nov-11
STR-1A/IFO-2 PSTR-1A/IFO-2 PRECON MILESTONESSTR-1A/IFO-2 PRECON MILESTONESSTR-1A/IFO-2 PRECON MILESTONESSTR-1A/IFO-2 PRECON MILESTONESAAAA-5600 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1A 0 06-Sep-11
CREDIT UNION PCREDIT UNION PRECON MILESTONESCREDIT UNION PRECON MILESTONESCREDIT UNION PRECON MILESTONESCREDIT UNION PRECON MILESTONESCREDIT-1458 VA REVIEWS/APPROVES DEMOLITION PLAN FOR CREDIT UNION 20 13-Dec-11 11-Jan-12
STR-2 PRECON MSTR-2 PRECON MILESTONESSTR-2 PRECON MILESTONESSTR-2 PRECON MILESTONESSTR-2 PRECON MILESTONESSTR2-4630 VA REVIEWS BID TABS - STR-2 5 19-Oct-11 25-Oct-11
STR2-3700 VA PROVIDES CONSENT TO SUBCONTRACT - STR-2 0 25-Oct-11
STR2-5030 VA REVIEWS/COMMENTS ON CONSTRUCTION SCHEDULE (90-days cost only)- STR-2 30 06-Nov-11 05-Dec-11
STR2-5040 VA REVIEWS/APPROVES COST/RESOURCE LOADED CONSTRUCTION SCHEDULE- STR-2 30 05-Jan-12 03-Feb-12
CS-1/IFO-3 PRECS-1/IFO-3 PRECON MILESTONESCS-1/IFO-3 PRECON MILESTONESCS-1/IFO-3 PRECON MILESTONESCS-1/IFO-3 PRECON MILESTONESCS1-5030 VA REVIEWS/COMMENTS ON CONSTRUCTION SCHEDULE (90-days cost only)- CS-1/IFO-3 30 26-Dec-11 24-Jan-12
CS1-4920 VA REVIEW BID TABS - CS-1/IFO-3 5 28-Dec-11 04-Jan-12
CS1-3650 VA PROVIDES CONSENT TO SUBCONTRACT - CS-1/IFO-3 0 04-Jan-12
CS1-5040 VA REVIEWS/APPROVES COST/RESOURCE LOADED CONSTRUCTION SCHEDULE- CS-1/IFO-3 30 05-Mar-12 03-Apr-12
IFO-1 PRECON MIFO-1 PRECON MILESTONESIFO-1 PRECON MILESTONESIFO-1 PRECON MILESTONESIFO-1 PRECON MILESTONESIFO-4920 VA REVIEW BID TABS (GROUP #1) - IFO-1 5 29-Mar-12 04-Apr-12
IFO-5031 VA REVIEWS/COMMENTS ON CONSTRUCTION SCHEDULE (90-days cost only)- IFO-1 30 01-Apr-12 30-Apr-12
IFO-3790 VA PROVIDES CONSENT TO SUBCONTRACT (GROUP #1) - IFO-1 0 04-Apr-12
IFO-4960 VA REVIEW BID TABS (GROUP #2) - IFO-1 5 26-Apr-12 02-May-12
IFO-4970 VA PROVIDES CONSENT TO SUBCONTRACT (GROUP #2) - IFO-1 0 02-May-12
IFO-4980 VA REVIEW BID TABS (GROUP #3) - IFO-1 5 24-May-12 31-May-12
IFO-4990 VA PROVIDES CONSENT TO SUBCONTRACT (GROUP #3) - IFO-1 0 31-May-12
IFO-5041 VA REVIEWS/APPROVES COST/RESOURCE LOADED CONSTRUCTION SCHEDULE- IFO-1 30 31-Jul-12 29-Aug-12
IFO-1999 VA APPROVAL OF FINAL COST/RESOURCE LOADED CONSTRUCTION SCHEDULE - IFO-1 0 29-Aug-12
CLC PRECON MICLC PRECON MILESTONESCLC PRECON MILESTONESCLC PRECON MILESTONESCLC PRECON MILESTONESCLC-5030 VA REVIEWS/COMMENTS ON CONSTRUCTION SCHEDULE (90-days cost only)- CLC 30 27-Jun-12 26-Jul-12
CLC-4920 VA REVIEW BID TABS - CLC 5 18-Jul-12 24-Jul-12
CLC-3650 VA PROVIDES CONSENT TO SUBCONTRACT - CLC 0 24-Jul-12
CLC-5040 VA REVIEWS/APPROVES COST/RESOURCE LOADED CONSTRUCTION SCHEDULE- CLC 30 26-Aug-12 24-Sep-12
OWNER PROVIDOWNER PROVIDED SHOP DRAWINGSOWNER PROVIDED SHOP DRAWINGSOWNER PROVIDED SHOP DRAWINGSOWNER PROVIDED SHOP DRAWINGSDVAPOPO-4950 VA PROVIDE MED EQUIP COORDINATED CDS (pharmacy) - DAT 60 04-Oct-12 03-Jan-13
DVAPOPO-1500 VA PROVIDE FIXED FF&E SHOP DRAWINGS - IBS/IBN 30 09-Nov-12 26-Dec-12
DVAPOPO-3960 VA PROVIDE MED EQUIP COORDINATED CDS(gen imaging) - DAT 60 04-Jan-13 01-Apr-13
DVAPOPO-4990 VA PROVIDE MED EQUIP COORDINATED CDS (MRI/CT) - DAT 60 05-Mar-13 28-May-13
DVAPOPO-4870 VA PROVIDE MED EQUIP COORDINATED CDS (dental) - DAT 60 14-May-13 07-Aug-13
DVAPOPO-5010 VA PROVIDE FIXED FF&E SHOP DRAWINGS - CBN 30 12-Jun-13 24-Jul-13
DVAPOPO-4910 VA PROVIDE MED EQUIP COORDINATED CDS (surgery) - DAT 60 06-Sep-13 03-Dec-13
DVAPOPO-5000 VA PROVIDE FIXED FF&E SHOP DRAWINGS - CBC 30 04-Oct-13 18-Nov-13
DVAPOPO-5020 VA PROVIDE FIXED FF&E SHOP DRAWINGS - RES 30 06-Aug-14 17-Sep-14
XCEL POWER TOXCEL POWER TO ENCXCEL POWER TO ENCXCEL POWER TO ENCXCEL POWER TO ENCZZZCAMP-1000 XCEL PROVIDE ENERGY TO ENC 0 29-Aug-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 3 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 006
Activity ID Activity Name OrigDur
Start Finish
PRECONSTRUCPRECONSTRUCTION ACTIVITIESPRECONSTRUCTION ACTIVITIESPRECONSTRUCTION ACTIVITIESPRECONSTRUCTION ACTIVITIESOFS-1 100% COOFS-1 100% CONSTRUCTION DOCUMENTSOFS-1 100% CONSTRUCTION DOCUMENTSOFS-1 100% CONSTRUCTION DOCUMENTSOFS-1 100% CONSTRUCTION DOCUMENTSOSI-4400 PREPARE/SUBMIT BID TABS TO VA - OSI-1 25 18-Apr-11 A 08-Sep-11
TEMP PARKING TEMP PARKING PRECONSTRUCTIONTEMP PARKING PRECONSTRUCTIONTEMP PARKING PRECONSTRUCTIONTEMP PARKING PRECONSTRUCTIONSITSWTP-5230 SUBCONTRACTOR PRICING - TEMP PARKING CBS 15 07-Sep-11 27-Sep-11
SITSWTP-5700 PREPARE BID TABS - TEMP PARKING CBS 10 28-Sep-11 12-Oct-11
SITSWTP-4440 AWARD SUBCONTRACTS -TEMP PARKING CBS 10 20-Oct-11 02-Nov-11
SITSWTP-5550 KT DESIGN TEMP PARKING CBS 15 03-Nov-11 28-Nov-11
SITSWTP-4450 PREPARE/SUBMIT SHOP DRAWINGS - TEMP PARKING CBS 14 29-Nov-11 16-Dec-11
SITSWTP-4880 KT REVIEWS SHOP DRAWINGS - TEMP PARKING CBS 10 19-Dec-11 03-Jan-12
SITSWTP-4470 MATERIAL PROCUREMENT - TEMP PARKING CBS 8 04-Jan-12 13-Jan-12
WHEELING STREWHEELING STREET WATER LINE PRECONSTRUCTIONWHEELING STREET WATER LINE PRECONSTRUCTIONWHEELING STREET WATER LINE PRECONSTRUCTIONWHEELING STREET WATER LINE PRECONSTRUCTIONW-OSI-5310 AWARD CONTRACT - WHEELING WATERLINE 20 07-Sep-11 04-Oct-11
W-OSI-4450 PREPARE/SUBMIT SHOP DRAWINGS - WHEELING WATER 10 05-Oct-11 19-Oct-11
W-OSI-5320 SUB SUBMIT WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 10 05-Oct-11 19-Oct-11
W-OSI-4490 KT REVIEWS SHOP DRAWINGS - WHEELING WATER 10 20-Oct-11 02-Nov-11
W-OSI-5390 VA APPROVE WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 20 20-Oct-11 17-Nov-11
W-OSI-4460 VA SUBMITTAL REVIEW - WHEELING WATER 20 03-Nov-11 05-Dec-11
W-OSI-5610 FRA/COA APPROVE WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 20 28-Nov-11 23-Dec-11
W-OSI-4470 MATERIAL PROCUREMENT - WHEELING WATER 10 06-Dec-11 19-Dec-11
W-OSI-4480 MATERIALS ARRIVE - WHEELING WATER 0 19-Dec-11
OFS-1 PROCUREOFS-1 PROCUREMENTOFS-1 PROCUREMENTOFS-1 PROCUREMENTOFS-1 PROCUREMENTOSI-4440 AWARD SUBCONTRACTS -OFS-1 20 16-Sep-11 14-Oct-11
OSI-4450 PREPARE/SUBMIT SHOP DRAWINGS - OSI-1 20 17-Oct-11 14-Nov-11
OSI-5320 SUBMIT WORK/TRAFFIC CONTROL PLAN - OSI-1 10 17-Oct-11 28-Oct-11
OSI-5390 VA APPROVE WORK/TRAFFIC CONTROL PLAN - OSI-1 20 31-Oct-11 30-Nov-11
OSI-4880 KT REVIEWS SHOP DRAWINGS - OSI-1 10 15-Nov-11 30-Nov-11
OSI-5610 FRA/COA APPROVE WORK/TRAFFIC CONTROL PLAN - OSI-1 0 23-Nov-11
OSI-4460 VA SUBMITTAL REVIEW - OSI-1 20 01-Dec-11 29-Dec-11
OSI-4470 MATERIAL PROCUREMENT - OSI-1 15 30-Dec-11 23-Jan-12
OSI-4480 MATERIALS ARRIVE - OSI-1 0 23-Jan-12
CBS-1 (buildout)CBS-1 (buildout) PRECONSTRUCTIONCBS-1 (buildout) PRECONSTRUCTIONCBS-1 (buildout) PRECONSTRUCTIONCBS-1 (buildout) PRECONSTRUCTIONCBS-1 (buildoutCBS-1 (buildout) CONSTRUCTION DOCUMENTSCBS-1 (buildout) CONSTRUCTION DOCUMENTSCBS-1 (buildout) CONSTRUCTION DOCUMENTSCBS-1 (buildout) CONSTRUCTION DOCUMENTSCBS-1 100% (builCBS-1 100% (buildout) CONSTRUCTION DOCUMENTSCBS-1 100% (buildout) CONSTRUCTION DOCUMENTSCBS-1 100% (buildout) CONSTRUCTION DOCUMENTSCBS-1 100% (buildout) CONSTRUCTION DOCUMENTS
P-CBS-4090 VA REVIEWS FIRM FIXED PRICE 100% CD - CBS-1 15 26-Jul-11 15-Aug-11
CBS-1 PROCURCBS-1 PROCUREMENTCBS-1 PROCUREMENTCBS-1 PROCUREMENTCBS-1 PROCUREMENTCBS-1 MECHANICACBS-1 MECHANICAL PROCUREMENTCBS-1 MECHANICAL PROCUREMENTCBS-1 MECHANICAL PROCUREMENTCBS-1 MECHANICAL PROCUREMENT
P-CBS-4220 SUBMITTAL DEVELOPMENT BALANCE OF MATERIAL (mechanical) - CBS-1 20 12-Jul-11 A 05-Aug-11
P-CBS-4820 KT REVIEW INITIAL MATERIAL SUBMITTAL (mechanical) - CBS-1 10 26-Jul-11 08-Aug-11
P-CBS-4230 KT REVIEW BALANCE OF MATERIAL SUBMITTALS (mechanical) - CBS-1 10 08-Aug-11 19-Aug-11
P-CBS-4480 VA/JVT REVIEW INITIAL MATERIAL SUBMITTAL (mechanical) - CBS-1 15 09-Aug-11 29-Aug-11
P-CBS-4830 VA/JVT REVIEW BALANCE OF MATERIAL SUBMITTALS (mechanical) - CBS-1 15 22-Aug-11 12-Sep-11
P-CBS-4240 INITIAL MATERIAL PROCUREMENT (mechanical) - CBS-1 15 30-Aug-11 20-Sep-11
P-CBS-4410 BALANCE OF MATERIAL PROCUREMENT (mechanical) - CBS-1 25 21-Sep-11 26-Oct-11
P-CBS-4250 ALL MATERIALS ARRIVE (mechanical) - CBS-1 0 26-Oct-11
CBS-1 ELECTRICACBS-1 ELECTRICAL PROCUREMENTCBS-1 ELECTRICAL PROCUREMENTCBS-1 ELECTRICAL PROCUREMENTCBS-1 ELECTRICAL PROCUREMENT
P-CBS-4270 SUBMITTAL DEVELOPMENT (electrical) - CBS-1 20 24-Jun-11 A 16-Aug-11
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 4 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 007
Activity ID Activity Name OrigDur
Start Finish
P-CBS-4280 SUBMITTAL VA REVIEW (electrical) - CBS-1 30 17-Aug-11 28-Sep-11
P-CBS-4290 INITIAL MATERIAL PROCUREMENT (electrical) - CBS-1 15 29-Sep-11 20-Oct-11
P-CBS-4420 REMAINING MATERIAL PROCUREMENT (electrical) - CBS-1 25 21-Oct-11 29-Nov-11
P-CBS-4300 ALL MATERIALS ARRIVE (electrical) - CBS-1 0 29-Nov-11
CBS-1 STRUCTURACBS-1 STRUCTURAL PROCUREMENTCBS-1 STRUCTURAL PROCUREMENTCBS-1 STRUCTURAL PROCUREMENTCBS-1 STRUCTURAL PROCUREMENT
P-CBS-4370 SUBMITTAL DEVELOPMENT (structural steel) - CBS-1 20 14-Jun-11 A 02-Aug-11
P-CBS-4440 SUBMITTAL REVIEW (interior steel) - CBS-1 30 27-Jun-11 A 09-Aug-11
P-CBS-4380 SUBMITTAL REVIEW (structural steel) - CBS-1 20 03-Aug-11 30-Aug-11
P-CBS-4450 MATERIAL PROCUREMENT (interior steel) - CBS-1 20 10-Aug-11 07-Sep-11
P-CBS-4390 MATERIAL PROCUREMENT (structural steel) - CBS-1 25 31-Aug-11 05-Oct-11
P-CBS-4460 MATERIALS ARRIVE (interior steel) - CBS-1 0 07-Sep-11
P-CBS-4400 MATERIALS ARRIVE (structural steel) - CBS-1 0 05-Oct-11
CBS-1 CBS CURTACBS-1 CBS CURTAIN WALL PROCUREMENT (WITH CS-1/IFO-3 PKG)CBS-1 CBS CURTAIN WALL PROCUREMENT (WITH CS-1/IFO-3 PKG)CBS-1 CBS CURTAIN WALL PROCUREMENT (WITH CS-1/IFO-3 PKG)CBS-1 CBS CURTAIN WALL PROCUREMENT (WITH CS-1/IFO-3 PKG)
P-CD3-4740 AWARD CURTAINWALL - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 20 07-Sep-11 04-Oct-11
P-CD3-4750 PAINT/FINISH/GLASS SAMPLES - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 30 05-Jan-12 17-Feb-12
P-CD3-4860 DETAIL CBS CURTAINWALL SHOP DRAWINGS - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 30 05-Jan-12 17-Feb-12
P-CD3-4760 KT APPROVE CURTAINWALL SHOP DRAWINGS - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 10 20-Feb-12 02-Mar-12
P-CD3-4850 VA/JVT APPROVE CURTAINWALL SHOP DRAWINGS - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 20 20-Feb-12 16-Mar-12
P-CD3-4870 VA/JVT APPROVE PAINT/FINISH/GLASS SAMPLES - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 20 20-Feb-12 16-Mar-12
P-CD3-4810 EXTRUDE CURTAINWALL MULLIONS - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 30 19-Mar-12 27-Apr-12
P-CD3-4820 CURTAINWALL SHOP ASSEMBLY - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 25 30-Apr-12 04-Jun-12
P-CD3-4840 DELIVER CURTAINWALL - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 0 04-Jun-12
STR-1 (mass ex/STR-1 (mass ex/shoring/CBS site/erosion ctrl) PRECONSTR-1 (mass ex/shoring/CBS site/erosion ctrl) PRECONSTR-1 (mass ex/shoring/CBS site/erosion ctrl) PRECONSTR-1 (mass ex/shoring/CBS site/erosion ctrl) PRECONSTR-1 PROCURSTR-1 PROCUREMENTSTR-1 PROCUREMENTSTR-1 PROCUREMENTSTR-1 PROCUREMENTSTR1-5230 SUBCONTRACTOR PRICING (earthwork) - STR-1 25 26-Jul-11 29-Aug-11
STR1-5700 PREPARE BID TABS (earthwork) - STR-1 15 30-Aug-11 20-Sep-11
STR1-5200 AWARD ROOF DRAIN CONTRACT - CBS ROOF DRAIN 20 07-Sep-11 04-Oct-11
STR1-5650 AWARD CONTRACT - DEWATERING 20 07-Sep-11 04-Oct-11
STR1-4250 AWARD EXCAVATION CONTRACT STR-1 20 28-Sep-11 26-Oct-11
STR1-4260 MOBILIZE EXCAVATOR STR-1 10 27-Dec-11 10-Jan-12
STR-1 SHORING PSTR-1 SHORING PROCUREMENTSTR-1 SHORING PROCUREMENTSTR-1 SHORING PROCUREMENTSTR-1 SHORING PROCUREMENT
STR-1 SHORINSTR-1 SHORING PROCUREMENTSTR-1 SHORING PROCUREMENTSTR-1 SHORING PROCUREMENTSTR-1 SHORING PROCUREMENT
STR1-5420 AWARD SHORING CONTRACT 20 07-Sep-11 04-Oct-11
STR1-5490 PROCURE SHORING MATERIALS STR-1 50 05-Oct-11 19-Dec-11
STR1-5430 PREPARE/SUBMIT SHOP DRAWINGS FOR SHORING STR-1 20 12-Oct-11 08-Nov-11
STR1-5410 KT APPROVE SHOP DRAWINGS FOR SHORING STR-1 30 09-Nov-11 23-Dec-11
STR1-5450 FABRICATE SHORING MATERIALS STR-1 10 27-Dec-11 10-Jan-12
STR1-5440 MATERIALS ARRIVE ON SITE STR-1 0 10-Jan-12
DEWATERING PRDEWATERING PRECONSTRUCTIONDEWATERING PRECONSTRUCTIONDEWATERING PRECONSTRUCTIONDEWATERING PRECONSTRUCTIONSTR1-5660 PREPARE SHOP DRAWINGS - DEWATERING 20 05-Oct-11 02-Nov-11
STR1-5670 REVIEW/APPROVE SHOP DRAWINGS - DEWATERING 10 03-Nov-11 17-Nov-11
STR1-5680 PROCURE DEWATERING EQUIPMENT 20 18-Nov-11 19-Dec-11
CBS ROOF DRAICBS ROOF DRAIN RELOCATION PRECONSTRUCTIONCBS ROOF DRAIN RELOCATION PRECONSTRUCTIONCBS ROOF DRAIN RELOCATION PRECONSTRUCTIONCBS ROOF DRAIN RELOCATION PRECONSTRUCTIONSTR1-5210 PREPARE PERMIT/APPROVAL - CBS ROOF DRAIN 20 05-Oct-11 02-Nov-11
STR1-5220 AURORA PERMIT APPROVAL - CBS ROOF DRAIN 20 03-Nov-11 05-Dec-11
STR1-5620 PROCURE MATERIALS - CBS ROOF DRAIN 20 06-Dec-11 04-Jan-12
SWPPP PRECONSWPPP PRECONSTRUCTIONSWPPP PRECONSTRUCTIONSWPPP PRECONSTRUCTIONSWPPP PRECONSTRUCTION
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 5 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 008
Activity ID Activity Name OrigDur
Start Finish
STR1-5240 KT PREPARES EROSION CONTROL PLAN - FILE FOR NOI 15 07-Sep-11 27-Sep-11
STR1-5260 EPA PERMIT - SWPPP 10 21-Sep-11 04-Oct-11
TEMP REDIRECTTEMP REDIRECTION OF DENTAL CLINIC STORMWATERTEMP REDIRECTION OF DENTAL CLINIC STORMWATERTEMP REDIRECTION OF DENTAL CLINIC STORMWATERTEMP REDIRECTION OF DENTAL CLINIC STORMWATERSTR1-5560 SUBCONTRACTOR PRICING - TEMP REDIRECTION OF STORMWATER 15 06-Sep-11 26-Sep-11
STR1-5570 PREPARE BID TABS - TEMP REDIRECTION OF STORMWATER 10 27-Sep-11 11-Oct-11
STR1-5540 AWARD DESIGN CONTRACTOR FOR TEMP REDIRECTION OF STORMWATER 10 14-Oct-11 27-Oct-11
STR1-5550 KT DESIGN TEMP REDIRECTION OF STORMWATER 8 28-Oct-11 08-Nov-11
STR1-5580 PROCURE VAULT/PUMP FOR TEMP REDIRECTION OF STORMWATER 11 17-Nov-11 05-Dec-11
STR1-5730 INSTALL TEMP/TEMP REDIRECTION OF STORMWATER 20 06-Dec-11 04-Jan-12
TEMPORARY ELETEMPORARY ELECTRIC PRECONSTRUCTIONTEMPORARY ELECTRIC PRECONSTRUCTIONTEMPORARY ELECTRIC PRECONSTRUCTIONTEMPORARY ELECTRIC PRECONSTRUCTIONSTR1-5330 AWARD CONTRACT TO SUBCONTRACTOR - TEMP ELEC 20 07-Sep-11 04-Oct-11
STR1-5360 XCEL DESIGN & INSTALL - TEMP ELEC 40 21-Sep-11 17-Nov-11
STR1-5340 PREPARE/SUBMIT DESIGN & SHOP DRAWINGS - TEMP ELEC 15 05-Oct-11 26-Oct-11
STR1-5350 KT REVIEW/APPROVE DESIGN & SHOP DRAWINGS - TEMP ELEC 10 27-Oct-11 09-Nov-11
STR1-5690 PROCURE TEMP MATERIALS & EQUIPMENT - TEMP ELEC 15 10-Nov-11 05-Dec-11
STR1-5370 KT INSTALLS PHASE 1 - TEMP ELEC 20 06-Dec-11 04-Jan-12
STR-1A/IFO-2 (mSTR-1A/IFO-2 (major piers/CON ductbank) PRECONSTUCTIONSTR-1A/IFO-2 (major piers/CON ductbank) PRECONSTUCTIONSTR-1A/IFO-2 (major piers/CON ductbank) PRECONSTUCTIONSTR-1A/IFO-2 (major piers/CON ductbank) PRECONSTUCTIONSTR-1A/IFO-2 PSTR-1A/IFO-2 PROCUREMENTSTR-1A/IFO-2 PROCUREMENTSTR-1A/IFO-2 PROCUREMENTSTR-1A/IFO-2 PROCUREMENTSTR1A-5020 AWARD DRILLED PIERS CONTRACT - STR-1A/IFO-2 20 07-Sep-11 04-Oct-11
STR1A/IFO-2 DRISTR1A/IFO-2 DRILLED PIERS PROCUREMENTSTR1A/IFO-2 DRILLED PIERS PROCUREMENTSTR1A/IFO-2 DRILLED PIERS PROCUREMENTSTR1A/IFO-2 DRILLED PIERS PROCUREMENT
STR1A-5110 PREPARE DRILLED PIER SHOP DRAWINGS - STR-1A/IFO-2 15 21-Sep-11 12-Oct-11
STR1A-5120 KT APPROVE DRILLED PIER SHOP DRAWINGS - STR-1A/IFO-2 10 13-Oct-11 26-Oct-11
STR1A-5130 VA APPROVE DRILLED PIER SHOP DRAWINGS - STR-1A/IFO-2 20 13-Oct-11 09-Nov-11
STR1A-5030 MOBILIZE DRILLED PIER CONTRACTOR - STR-1A/IFO-2 10 10-Nov-11 28-Nov-11
STR1A/IFO-2 (COSTR1A/IFO-2 (CON) DUCTBANK & DRAINAGE PROCUREMENTSTR1A/IFO-2 (CON) DUCTBANK & DRAINAGE PROCUREMENTSTR1A/IFO-2 (CON) DUCTBANK & DRAINAGE PROCUREMENTSTR1A/IFO-2 (CON) DUCTBANK & DRAINAGE PROCUREMENT
STR1A-4930 PREPARE/SUBMIT DUCTBANK/VAULT SHOP/DRAINAGE DRAWINGS (CON) - STR-1A/IFO-2 20 07-Sep-11 04-Oct-11
STR1A-5080 KT APPROVE DUCTBANK/VAULT/DRAINAGE SHOP DRAWINGS (CON) - STR-1A/IFO-2 10 05-Oct-11 19-Oct-11
STR1A-4940 VA APPROVE DUCTBANK/VAULT/DRAINAGE SHOP DRAWINGS (CON) - STR-1A/IFO-2 20 20-Oct-11 17-Nov-11
STR1A-4950 FABRICATE DUCTBANK/VAULT (CON) - STR-1A/IFO-2 25 18-Nov-11 27-Dec-11
STR1A-5010 FIRST DUCTBANK/VAULT DELIVERY (CON) - STR-1A/IFO-2 0 27-Dec-11
STR-2 (minor pieSTR-2 (minor piers/substructure/superstructure/perm drain) PRECONSTR-2 (minor piers/substructure/superstructure/perm drain) PRECONSTR-2 (minor piers/substructure/superstructure/perm drain) PRECONSTR-2 (minor piers/substructure/superstructure/perm drain) PRECONSTR-2 95% CONSTR-2 95% CONSTRUCTION DOCUMENTSSTR-2 95% CONSTRUCTION DOCUMENTSSTR-2 95% CONSTRUCTION DOCUMENTSSTR-2 95% CONSTRUCTION DOCUMENTSSTR2-3660 KT PROVIDES RED LINE COMMENTS 95% CD - STR-2 5 26-Jul-11 01-Aug-11
STR2-3670 PAGE FLIP 95% CD - STR-2 5 02-Aug-11 08-Aug-11
STR2-3680 JVT REVISE DOCUMENTS 95% CD - STR-2 15 09-Aug-11 29-Aug-11
STR2-3690 JVT QA/QC DOCUMENTS 95% CD - STR-2 5 30-Aug-11 06-Sep-11
STR-2 100% COSTR-2 100% CONSTRUCTION DOCUMENTSSTR-2 100% CONSTRUCTION DOCUMENTSSTR-2 100% CONSTRUCTION DOCUMENTSSTR-2 100% CONSTRUCTION DOCUMENTSSTR2-3610 100% CD DESIGN COMPLETION - STR-2 0 06-Sep-11
STR2-4830 SUBCONTRACTOR PRICING - STR-2 14 07-Sep-11 26-Sep-11
STR2-3710 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - STR-2 60 07-Sep-11 05-Nov-11
STR2-4800 PREPARE/SUBMIT BID TABS - STR-2 15 27-Sep-11 18-Oct-11
STR2-5020 COST/RESOURCE LOAD BALANCE OF SCHEDULE - STR-2 60 06-Nov-11 04-Jan-12
STR-2 PROCURSTR-2 PROCUREMENTSTR-2 PROCUREMENTSTR-2 PROCUREMENTSTR-2 PROCUREMENTSTR2-4810 AWARD STEEL CONTRACT 20 26-Oct-11 23-Nov-11
STR2-4820 AWARD CAST-IN-PLACE GARAGES (PVN/PSN) CONTRACT 20 26-Oct-11 23-Nov-11
STR-2 STEEL PROCSTR-2 STEEL PROCUREMENTSTR-2 STEEL PROCUREMENTSTR-2 STEEL PROCUREMENTSTR-2 STEEL PROCUREMENT
STR2-3580 EVALUATE AND RELEASE MILL ORDER - STR-2 10 28-Nov-11 09-Dec-11
STR-2 DAT STSTR-2 DAT STEEL PROCUREMENTSTR-2 DAT STEEL PROCUREMENTSTR-2 DAT STEEL PROCUREMENTSTR-2 DAT STEEL PROCUREMENT
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 6 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 009
Activity ID Activity Name OrigDur
Start Finish
DATPOPO-3590 PREPARE/SUBMIT INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (DAT) 30 12-Dec-11 25-Jan-12
DATPOPO-5030 KT APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (DAT) 25 26-Jan-12 01-Mar-12
DATPOPO-3600 VA APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (DAT) 20 02-Mar-12 29-Mar-12
DATPOPO-3610 FABRICATE/DELIVER INTERSTITIAL STEEL - STR-2 (DAT) 40 30-Mar-12 24-May-12
DATPOPO-3620 FIRST DELIVERY OF INTERSTITIAL STEEL - STR-2 (DAT) 0 24-May-12
STR-2 IBN STESTR-2 IBN STEEL PROCUREMENTSTR-2 IBN STEEL PROCUREMENTSTR-2 IBN STEEL PROCUREMENTSTR-2 IBN STEEL PROCUREMENT
IBNPOPO-3591 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (IBN) 30 27-Dec-11 08-Feb-12
IBNPOPO-3590 PREPARE/SUBMIT INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBN) 30 11-Jan-12 23-Feb-12
IBNPOPO-3631 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (IBN) 25 09-Feb-12 15-Mar-12
IBNPOPO-3641 KT APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBN) 25 24-Feb-12 29-Mar-12
IBNPOPO-3601 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (IBN) 20 16-Mar-12 12-Apr-12
IBNPOPO-3600 VA APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBN) 20 30-Mar-12 26-Apr-12
IBNPOPO-3611 FABRICATE/DELIVER STRUCT STEEL - STR-2 (IBN) 65 13-Apr-12 16-Jul-12
IBNPOPO-3610 FABRICATE/DELIVER INTERSTITIAL STEEL - STR-2 (IBN) 40 27-Apr-12 22-Jun-12
IBNPOPO-3620 FIRST DELIVERY OF INTERSTITIAL STEEL - STR-2 (IBN) 0 22-Jun-12
IBNPOPO-3621 FIRST DELIVERY OF STRUCT STEEL - STR-2 (IBN) 0 16-Jul-12
STR-2 IBS STESTR-2 IBS STEEL PROCUREMENTSTR-2 IBS STEEL PROCUREMENTSTR-2 IBS STEEL PROCUREMENTSTR-2 IBS STEEL PROCUREMENT
IBSPOPO-4860 PREPARE/SUBMIT INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBS) 30 27-Dec-11 08-Feb-12
IBSPOPO-4660 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (IBS) 30 11-Jan-12 23-Feb-12
IBSPOPO-4910 KT APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBS) 25 09-Feb-12 15-Mar-12
IBSPOPO-4900 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (IBS) 25 24-Feb-12 29-Mar-12
IBSPOPO-4870 VA APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBS) 20 16-Mar-12 12-Apr-12
IBSPOPO-4670 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (IBS) 20 30-Mar-12 26-Apr-12
IBSPOPO-4880 FABRICATE/DELIVER INTERSTITIAL STEEL - STR-2 (IBS) 40 13-Apr-12 08-Jun-12
IBSPOPO-4680 FABRICATE/DELIVER STRUCT STEEL - STR-2 (IBS) 65 27-Apr-12 30-Jul-12
IBSPOPO-4890 FIRST DELIVERY OF INTERSTITIAL STEEL - STR-2 (IBS) 0 08-Jun-12
IBSPOPO-4690 FIRST DELIVERY OF STRUCT STEEL - STR-2 (IBS) 0 30-Jul-12
STR-2 ENC STSTR-2 ENC STEEL PROCUREMENTSTR-2 ENC STEEL PROCUREMENTSTR-2 ENC STEEL PROCUREMENTSTR-2 ENC STEEL PROCUREMENT
ENCPOPO-4660 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (ENC) 50 12-Dec-11 23-Feb-12
ENCPOPO-5459 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (ENC) 25 24-Feb-12 29-Mar-12
ENCPOPO-4711 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (ENC) 20 30-Mar-12 26-Apr-12
ENCPOPO-4721 FABRICATE/DELIVER STRUCT STEEL - STR-2 (ENC) 50 27-Apr-12 09-Jul-12
ENCPOPO-4731 FIRST DELIVERY OF STRUCT STEEL - STR-2 (ENC) 0 09-Jul-12
STR-2 CBN STSTR-2 CBN STEEL PROCUREMENTSTR-2 CBN STEEL PROCUREMENTSTR-2 CBN STEEL PROCUREMENTSTR-2 CBN STEEL PROCUREMENT
CBNPOPO-4740 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (CBN) 30 26-Jan-12 08-Mar-12
CBNPOPO-4780 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CBN) 25 09-Mar-12 12-Apr-12
CBNPOPO-4750 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CBN) 20 13-Apr-12 10-May-12
CBNPOPO-4760 FABRICATE/DELIVER STRUCT STEEL - STR-2 (CBN) 65 11-May-12 13-Aug-12
CBNPOPO-4770 FIRST DELIVERY OF STRUCT STEEL - STR-2 (CBN) 0 13-Aug-12
STR-2 CBC STSTR-2 CBC STEEL PROCUREMENTSTR-2 CBC STEEL PROCUREMENTSTR-2 CBC STEEL PROCUREMENTSTR-2 CBC STEEL PROCUREMENT
CBCPOPO-4780 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (CBC) 30 24-Feb-12 05-Apr-12
CBCPOPO-4820 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CBC) 25 06-Apr-12 10-May-12
CBCPOPO-4790 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CBC) 20 11-May-12 08-Jun-12
CBCPOPO-4800 FABRICATE/DELIVER STRUCT STEEL - STR-2 (CBC) 65 11-Jun-12 11-Sep-12
CBCPOPO-4810 FIRST DELIVERY OF STRUCT STEEL - STR-2 (CBC) 0 11-Sep-12
STR-2 CON STSTR-2 CON STEEL PROCUREMENTSTR-2 CON STEEL PROCUREMENTSTR-2 CON STEEL PROCUREMENTSTR-2 CON STEEL PROCUREMENT
CONPOPO-4820 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (CON) 50 09-Feb-12 19-Apr-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 7 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 010
Activity ID Activity Name OrigDur
Start Finish
CONPOPO-4910 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CON) 25 20-Apr-12 24-May-12
CONPOPO-4830 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CON) 20 25-May-12 22-Jun-12
CONPOPO-4840 FABRICATE/DELIVER STRUCT STEEL - STR-2 (CON) 65 25-Jun-12 25-Sep-12
CONPOPO-4844 FIRST DELIVERY OF STRUCT STEEL - STR-2 (CON) 0 25-Sep-12
STR-2 CAST-IN-PLSTR-2 CAST-IN-PLACE GARAGE PROCUREMENTSTR-2 CAST-IN-PLACE GARAGE PROCUREMENTSTR-2 CAST-IN-PLACE GARAGE PROCUREMENTSTR-2 CAST-IN-PLACE GARAGE PROCUREMENT
STR-2 PVN CASTR-2 PVN CAST-IN-PLACE GARAGE PROCUREMENTSTR-2 PVN CAST-IN-PLACE GARAGE PROCUREMENTSTR-2 PVN CAST-IN-PLACE GARAGE PROCUREMENTSTR-2 PVN CAST-IN-PLACE GARAGE PROCUREMENT
PVNPOPO-4820 PREPARE/SUBMIT GARAGE SHOP DRAWINGS - STR-2 (PVN) 30 27-Dec-11 08-Feb-12
PVNPOPO-4880 KT APPROVE GARAGE SHOP DRAWINGS - STR-2 (PVN) 25 09-Feb-12 15-Mar-12
PVNPOPO-4830 VA APPROVE GARAGE SHOP DRAWINGS - STR-2 (PVN) 20 16-Mar-12 12-Apr-12
PVNPOPO-4840 FABRICATE/DELIVER STRUCTURAL MATERIALS - STR-2 (PVN) 20 13-Apr-12 10-May-12
PVNPOPO-4850 FIRST DELIVERY OF STRUCTURAL MATERIALS - STR-2 (PVN) 0 10-May-12
STR-2 PSN CASTR-2 PSN CAST-IN-PLACE GARAGE PROCURMENTSTR-2 PSN CAST-IN-PLACE GARAGE PROCURMENTSTR-2 PSN CAST-IN-PLACE GARAGE PROCURMENTSTR-2 PSN CAST-IN-PLACE GARAGE PROCURMENT
PSNPOPO-4820 PREPARE/SUBMIT GARAGE SHOP DRAWINGS - STR-2 (PSN) 30 28-Nov-11 10-Jan-12
PSNPOPO-4880 KT APPROVE GARAGE SHOP DRAWINGS - STR-2 (PSN) 25 11-Jan-12 16-Feb-12
PSNPOPO-4830 VA APPROVE GARAGE SHOP DRAWINGS - STR-2 (PSN) 20 17-Feb-12 15-Mar-12
PSNPOPO-4840 FABRICATE/DELIVER STRUCTURAL MATERIALS - STR-2 (PSN) 20 16-Mar-12 12-Apr-12
PSNPOPO-4850 FIRST DELIVERY OF STRUCTUAL MATERIALS - STR-2 (PSN) 0 12-Apr-12
CS-1/IFO-3 (CBSCS-1/IFO-3 (CBS skin/ext envelope/underslab utilities/onsite utilities/final site) PRECONCS-1/IFO-3 (CBS skin/ext envelope/underslab utilities/onsite utilities/final site) PRECONCS-1/IFO-3 (CBS skin/ext envelope/underslab utilities/onsite utilities/final site) PRECONCS-1/IFO-3 (CBS skin/ext envelope/underslab utilities/onsite utilities/final site) PRECONCS-1/IFO-3 95%CS-1/IFO-3 95% CONSTRUCTION DOCUMENTSCS-1/IFO-3 95% CONSTRUCTION DOCUMENTSCS-1/IFO-3 95% CONSTRUCTION DOCUMENTSCS-1/IFO-3 95% CONSTRUCTION DOCUMENTSCS1-3040 95% DESIGN - CS-1/IFO-3 78 18-Apr-11 A 29-Aug-11
CS1-3510 95% CD DESIGN COMPLETE - CS-1/IFO-3 0 29-Aug-11
CS1-3660 KT PROVIDES RED LINE COMMENTS 95% CD - CS-1/IFO-3 15 30-Aug-11 20-Sep-11
CS1-3670 PAGE FLIP 95% CD - CS-1/IFO-3 5 21-Sep-11 27-Sep-11
CS1-3680 JVT REVISE DOCUMENTS 95% CD - CS-1/IFO-3 15 28-Sep-11 19-Oct-11
CS1-3690 JVT QA/QC DOCUMENTS 95% CD - CS-1/IFO-3 5 20-Oct-11 26-Oct-11
CS-1/IFO-3 100CS-1/IFO-3 100% CONSTRUCTION DOCUMENTSCS-1/IFO-3 100% CONSTRUCTION DOCUMENTSCS-1/IFO-3 100% CONSTRUCTION DOCUMENTSCS-1/IFO-3 100% CONSTRUCTION DOCUMENTSCS1-3610 100% CD DESIGN COMPLETION - CS-1/IFO-3 0 26-Oct-11
CS1-3630 SUBCONTRACTOR PRICING - CS-1/IFO-3 25 27-Oct-11 05-Dec-11
CS1-3710 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - CS-1/IFO-3 60 27-Oct-11 25-Dec-11
CS1-4930 PREPARE BID TABS - CS-1/IFO-3 15 06-Dec-11 27-Dec-11
CS1-5020 COST/RESOURCE LOAD BALANCE OF SCHEDULE - CS-1/IFO-3 60 05-Jan-12 04-Mar-12
CS-1/IFO-3 PROCS-1/IFO-3 PROCUREMENTCS-1/IFO-3 PROCUREMENTCS-1/IFO-3 PROCUREMENTCS-1/IFO-3 PROCUREMENTCS1-4820 AWARD ELEVATOR CONTRACT 20 05-Jan-12 02-Feb-12
CS1-4940 AWARD ROOFING CONTRACT 20 05-Jan-12 02-Feb-12
CS1-4950 AWARD ON-SITE UTILITIES CONTRACT 20 05-Jan-12 02-Feb-12
CS1-4960 AWARD MISC METAL CONTRACT 20 05-Jan-12 02-Feb-12
CS-1 STAIR PROCUCS-1 STAIR PROCUREMENTCS-1 STAIR PROCUREMENTCS-1 STAIR PROCUREMENTCS-1 STAIR PROCUREMENT
CS-1/IFO-3 PVCS-1/IFO-3 PVS STAIRSCS-1/IFO-3 PVS STAIRSCS-1/IFO-3 PVS STAIRSCS-1/IFO-3 PVS STAIRS
PVSPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 20 03-Feb-12 02-Mar-12
PVSPOPO-4820 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 15 05-Mar-12 23-Mar-12
PVSPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 20 26-Mar-12 20-Apr-12
PVSPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (PVS) 55 23-Apr-12 10-Jul-12
CS-1/IFO-3 DACS-1/IFO-3 DAT STAIRSCS-1/IFO-3 DAT STAIRSCS-1/IFO-3 DAT STAIRSCS-1/IFO-3 DAT STAIRS
DATPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 20 02-Apr-12 27-Apr-12
DATPOPO-5040 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 15 30-Apr-12 18-May-12
DATPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 20 21-May-12 18-Jun-12
DATPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (DAT) 55 19-Jun-12 05-Sep-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 8 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 011
Activity ID Activity Name OrigDur
Start Finish
CS-1/IFO-3 ENCS-1/IFO-3 ENC STAIRSCS-1/IFO-3 ENC STAIRSCS-1/IFO-3 ENC STAIRSCS-1/IFO-3 ENC STAIRS
ENCPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 20 30-Apr-12 25-May-12
ENCPOPO-5469 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 15 29-May-12 18-Jun-12
ENCPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 20 19-Jun-12 17-Jul-12
ENCPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (ENC) 55 18-Jul-12 03-Oct-12
CS-1/IFO-3 IBSCS-1/IFO-3 IBS/IBN STAIRSCS-1/IFO-3 IBS/IBN STAIRSCS-1/IFO-3 IBS/IBN STAIRSCS-1/IFO-3 IBS/IBN STAIRS
IBPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 20 03-Feb-12 02-Mar-12
IBPOPO-5680 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 15 05-Mar-12 23-Mar-12
IBPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 20 26-Mar-12 20-Apr-12
IBPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (IBS/IBN) 55 23-Apr-12 10-Jul-12
CS-1/IFO-3 CBCS-1/IFO-3 CBC/CBN STAIRSCS-1/IFO-3 CBC/CBN STAIRSCS-1/IFO-3 CBC/CBN STAIRSCS-1/IFO-3 CBC/CBN STAIRS
CBPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 20 05-Mar-12 30-Mar-12
CBPOPO-4870 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 15 02-Apr-12 20-Apr-12
CBPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 20 23-Apr-12 18-May-12
CBPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (CBS/CBN) 55 21-May-12 07-Aug-12
CS-1/IFO-3 PVCS-1/IFO-3 PVN STAIRSCS-1/IFO-3 PVN STAIRSCS-1/IFO-3 PVN STAIRSCS-1/IFO-3 PVN STAIRS
PVNPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 20 26-Jun-12 24-Jul-12
PVNPOPO-4890 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 15 25-Jul-12 14-Aug-12
PVNPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 20 15-Aug-12 12-Sep-12
PVNPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (PVN) 55 13-Sep-12 04-Dec-12
CS-1/IFO-3 PSCS-1/IFO-3 PSN STAIRSCS-1/IFO-3 PSN STAIRSCS-1/IFO-3 PSN STAIRSCS-1/IFO-3 PSN STAIRS
PSNPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 20 29-May-12 25-Jun-12
PSNPOPO-4890 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 15 26-Jun-12 17-Jul-12
PSNPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 20 18-Jul-12 14-Aug-12
PSNPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (PSN) 55 15-Aug-12 01-Nov-12
CS-1 ROOF PROCUCS-1 ROOF PROCUREMENTCS-1 ROOF PROCUREMENTCS-1 ROOF PROCUREMENTCS-1 ROOF PROCUREMENT
ALLPOPO-3690 GREEN ROOF MOCK-UP SHOP DRAWINGS - CS-1/IFO-3 30 03-Feb-12 16-Mar-12
ALLPOPO-4740 KT APPROVE GREEN ROOF MOCK- UP DESIGN - CS-1/IFO-3 15 19-Mar-12 06-Apr-12
ALLPOPO-4710 VA APPROVE GREEN ROOF MOCK- UP DESIGN - CS-1/IFO-3 20 09-Apr-12 04-May-12
ALLPOPO-4720 GREEN ROOF MOCK- UP MATERIAL PROCURMENT AND FAB - CS-1/IFO-3 40 07-May-12 02-Jul-12
ALLPOPO-4730 GREEN ROOF MOCK- UP INSTALL AND TEST - CS-1/IFO-3 15 03-Jul-12 24-Jul-12
ALLPOPO-3720 GREEN ROOF ARCH APPROVALS - SHOPS - CS-1/IFO-3 14 25-Jul-12 13-Aug-12
ALLPOPO-3730 GREEN ROOF MATERIALS PROCUREMENT (dry-in material only) - CS-1/IFO-3 30 14-Aug-12 25-Sep-12
ALLPOPO-3760 GREEN ROOF (dry-in material only) 1ST DELIVERY - CS-1/IFO-3 0 25-Sep-12
CS-1 CURTAIN WACS-1 CURTAIN WALL PROCUREMENTCS-1 CURTAIN WALL PROCUREMENTCS-1 CURTAIN WALL PROCUREMENTCS-1 CURTAIN WALL PROCUREMENT
CS-1 DAT CURCS-1 DAT CURTAIN WALL PROCUREMENTCS-1 DAT CURTAIN WALL PROCUREMENTCS-1 DAT CURTAIN WALL PROCUREMENTCS-1 DAT CURTAIN WALL PROCUREMENT
DATPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (DAT) 30 10-Nov-11 27-Dec-11
DATPOPO-3700 KT/VA APPROVE BLAST ANALYSIS - SHOPS/BLAST - CS-1/IFO-3 (DAT) 20 28-Dec-11 26-Jan-12
DATPOPO-4710 DETAIL CURTAINWALL SHOP DRAWINGS - CS-1/IFO-3 (DAT) 30 27-Feb-12 06-Apr-12
DATPOPO-3710 KT APPROVE CURTAINWALL SHOPS - CS-1/IFO-3 (DAT) 30 09-Apr-12 18-May-12
DATPOPO-3720 ORDER CUSTOM DIES - CS-1/IFO-3 (DAT) 30 21-May-12 02-Jul-12
DATPOPO-4720 VA APPROVE CURTIANWALL SHOPS - CS-1/IFO-3 (DAT) 20 21-May-12 18-Jun-12
DATPOPO-4730 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (DAT) 60 03-Jul-12 26-Sep-12
DATPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (DAT) 30 27-Sep-12 08-Nov-12
DATPOPO-3740 FABRICATE/DELIVER - CS-1/IFO-3 (DAT) 25 09-Nov-12 18-Dec-12
DATPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (DAT) 0 18-Dec-12
CS-1 ENC CURCS-1 ENC CURTAIN WALL PROCUREMENTCS-1 ENC CURTAIN WALL PROCUREMENTCS-1 ENC CURTAIN WALL PROCUREMENTCS-1 ENC CURTAIN WALL PROCUREMENT
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 9 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 012
Activity ID Activity Name OrigDur
Start Finish
ENCPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (ENC) 30 12-Jan-12 24-Feb-12
ENCPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (ENC) 20 27-Feb-12 23-Mar-12
ENCPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (ENC) 30 15-Aug-12 26-Sep-12
ENCPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (ENC) 30 27-Sep-12 08-Nov-12
ENCPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (ENC) 30 09-Nov-12 26-Dec-12
ENCPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (ENC) 20 09-Nov-12 11-Dec-12
ENCPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (ENC) 60 27-Dec-12 25-Mar-13
ENCPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (ENC) 30 26-Mar-13 06-May-13
ENCPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (ENC) 25 07-May-13 11-Jun-13
ENCPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (ENC) 0 11-Jun-13
CS-1 CON CURCS-1 CON CURTAIN WALL PROCUREMENTCS-1 CON CURTAIN WALL PROCUREMENTCS-1 CON CURTAIN WALL PROCUREMENTCS-1 CON CURTAIN WALL PROCUREMENT
CONPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (CON) 30 27-Oct-11 12-Dec-11
CONPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (CON) 20 13-Dec-11 11-Jan-12
CONPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (CON) 30 12-Jan-12 24-Feb-12
CONPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (CON) 30 27-Feb-12 06-Apr-12
CONPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (CON) 20 09-Apr-12 04-May-12
CONPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (CON) 30 09-Apr-12 18-May-12
CONPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (CON) 60 21-May-12 14-Aug-12
CONPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (CON) 30 15-Aug-12 26-Sep-12
CONPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (CON) 25 27-Sep-12 01-Nov-12
CONPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (CON) 0 01-Nov-12
CS-1 IBS/IBN CCS-1 IBS/IBN CURTAIN WALL PROCUREMENTCS-1 IBS/IBN CURTAIN WALL PROCUREMENTCS-1 IBS/IBN CURTAIN WALL PROCUREMENTCS-1 IBS/IBN CURTAIN WALL PROCUREMENT
IBPPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (IBS/IBN) 30 29-Nov-11 11-Jan-12
IBPPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (IBS/IBN) 20 12-Jan-12 09-Feb-12
IBPPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 30 09-Apr-12 18-May-12
IBPPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (IBS/IBN) 30 21-May-12 02-Jul-12
IBPPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (IBS/IBN) 20 03-Jul-12 31-Jul-12
IBPPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (IBS/IBN) 30 03-Jul-12 14-Aug-12
IBPPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (IBS/IBN) 60 15-Aug-12 08-Nov-12
IBPPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (IBS/IBN) 30 09-Nov-12 26-Dec-12
IBPPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (IBS/IBN) 25 27-Dec-12 01-Feb-13
IBPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (IBS/IBN) 0 01-Feb-13
CS-1 CBS/CBNCS-1 CBS/CBN CURTAIN WALL PROCUREMENTCS-1 CBS/CBN CURTAIN WALL PROCUREMENTCS-1 CBS/CBN CURTAIN WALL PROCUREMENTCS-1 CBS/CBN CURTAIN WALL PROCUREMENT
CBPPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (CBC/CBN) 30 13-Dec-11 26-Jan-12
CBPPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (CBC/CBN) 20 27-Jan-12 24-Feb-12
CBPPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (CBC/CBN) 30 21-May-12 02-Jul-12
CBPPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (CBC/CBN) 30 03-Jul-12 14-Aug-12
CBPPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (CBC/CBN) 20 15-Aug-12 12-Sep-12
CBPPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (CBC/CBN) 30 15-Aug-12 26-Sep-12
CBPPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (CBC/CBN) 60 27-Sep-12 26-Dec-12
CBPPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (CBC/CBN) 30 27-Dec-12 08-Feb-13
CBPPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (CBC/CBN) 25 12-Feb-13 18-Mar-13
CBPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (CBC/CBN) 0 18-Mar-13
CS-1 RES CURCS-1 RES CURTAIN WALL PROCUREMENTCS-1 RES CURTAIN WALL PROCUREMENTCS-1 RES CURTAIN WALL PROCUREMENTCS-1 RES CURTAIN WALL PROCUREMENT
RESPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (RES) 30 28-Dec-11 09-Feb-12
RESPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (RES) 20 10-Feb-12 09-Mar-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 10 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 013
Activity ID Activity Name OrigDur
Start Finish
RESPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (RES) 30 03-Jul-12 14-Aug-12
RESPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (RES) 30 15-Aug-12 26-Sep-12
RESPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (RES) 20 27-Sep-12 25-Oct-12
RESPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (RES) 30 27-Sep-12 08-Nov-12
RESPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (RES) 60 09-Nov-12 08-Feb-13
RESPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (RES) 30 12-Feb-13 25-Mar-13
RESPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (RES) 25 26-Mar-13 29-Apr-13
RESPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (RES) 0 29-Apr-13
CS-1 FORCE WALLCS-1 FORCE WALL PROCUREMENTCS-1 FORCE WALL PROCUREMENTCS-1 FORCE WALL PROCUREMENTCS-1 FORCE WALL PROCUREMENT
P-CD3-3780 SUBMIT FORCE PROTECTION - CS-1/IFO-3 40 05-Jan-12 02-Mar-12
P-CD3-4900 KT APPROVE FORCE PROTECTION - CS-1/IFO-3 30 05-Mar-12 13-Apr-12
P-CD3-3790 VA PPROVE FORCE PROTECTION - CS-1/IFO-3 20 16-Apr-12 11-May-12
P-CD3-3800 FABRICATE FORCE PROTECTION - CS-1/IFO-3 100 14-May-12 03-Oct-12
P-CD3-3810 FORCE PROTECTION MATERIALS ARRIVE - CS-1/IFO-3 0 03-Oct-12
CS-1/IFO-3 ELEVACS-1/IFO-3 ELEVATOR PROCUREMENTCS-1/IFO-3 ELEVATOR PROCUREMENTCS-1/IFO-3 ELEVATOR PROCUREMENTCS-1/IFO-3 ELEVATOR PROCUREMENT
CS-1/IFO-3 COCS-1/IFO-3 CON ELEVATOR PROCUREMENTCS-1/IFO-3 CON ELEVATOR PROCUREMENTCS-1/IFO-3 CON ELEVATOR PROCUREMENTCS-1/IFO-3 CON ELEVATOR PROCUREMENT
CONPOPO-4850 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CON) 60 29-May-12 21-Aug-12
CONPOPO-4920 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CON) 15 22-Aug-12 12-Sep-12
CONPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CON) 45 13-Sep-12 16-Nov-12
CONPOPO-4860 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (CON) 90 19-Nov-12 01-Apr-13
CS-1/IFO-3 ENCS-1/IFO-3 ENC ELEVATOR PROCUREMENTCS-1/IFO-3 ENC ELEVATOR PROCUREMENTCS-1/IFO-3 ENC ELEVATOR PROCUREMENTCS-1/IFO-3 ENC ELEVATOR PROCUREMENT
ENCPOPO-5409 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 40 26-Jun-12 21-Aug-12
ENCPOPO-5479 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 15 22-Aug-12 12-Sep-12
ENCPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 45 13-Sep-12 16-Nov-12
ENCPOPO-5419 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (ENC) 90 19-Nov-12 01-Apr-13
CS-1/IFO-3 PVCS-1/IFO-3 PVS ELEVATOR PROCUREMENTCS-1/IFO-3 PVS ELEVATOR PROCUREMENTCS-1/IFO-3 PVS ELEVATOR PROCUREMENTCS-1/IFO-3 PVS ELEVATOR PROCUREMENT
PVSPOPO-4800 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 40 03-Feb-12 30-Mar-12
PVSPOPO-4830 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 15 02-Apr-12 20-Apr-12
PVSPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 45 23-Apr-12 25-Jun-12
PVSPOPO-4810 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (PVS) 90 26-Jun-12 01-Nov-12
CS-1/IFO-3 DACS-1/IFO-3 DAT ELEVATOR PROCUREMENTCS-1/IFO-3 DAT ELEVATOR PROCUREMENTCS-1/IFO-3 DAT ELEVATOR PROCUREMENTCS-1/IFO-3 DAT ELEVATOR PROCUREMENT
DATPOPO-4850 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 40 05-Mar-12 27-Apr-12
DATPOPO-5050 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 15 30-Apr-12 18-May-12
DATPOPO-1400 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 45 21-May-12 24-Jul-12
DATPOPO-4860 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (DAT) 90 25-Jul-12 04-Dec-12
CS-1/IFO-3 IBSCS-1/IFO-3 IBS/IBN ELEVATOR PROCUREMENTCS-1/IFO-3 IBS/IBN ELEVATOR PROCUREMENTCS-1/IFO-3 IBS/IBN ELEVATOR PROCUREMENTCS-1/IFO-3 IBS/IBN ELEVATOR PROCUREMENT
IBPOPO-4850 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 40 30-Apr-12 25-Jun-12
IBPOPO-5690 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 15 26-Jun-12 17-Jul-12
IBPOPO-5670 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 45 18-Jul-12 19-Sep-12
IBPOPO-4860 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (IBS/IBN) 90 20-Sep-12 01-Feb-13
CS-1/IFO-3 CBCS-1/IFO-3 CBC/CBN ELEVATOR PROCUREMENTCS-1/IFO-3 CBC/CBN ELEVATOR PROCUREMENTCS-1/IFO-3 CBC/CBN ELEVATOR PROCUREMENTCS-1/IFO-3 CBC/CBN ELEVATOR PROCUREMENT
CBPOPO-4850 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 40 02-Apr-12 25-May-12
CBPOPO-4880 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 15 29-May-12 18-Jun-12
CBPOPO-4832 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 45 19-Jun-12 21-Aug-12
CBPOPO-4860 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (CBS/CBN) 90 22-Aug-12 03-Jan-13
CS-1/IFO-3 PVCS-1/IFO-3 PVN ELEVATOR PROCUREMENTCS-1/IFO-3 PVN ELEVATOR PROCUREMENTCS-1/IFO-3 PVN ELEVATOR PROCUREMENTCS-1/IFO-3 PVN ELEVATOR PROCUREMENT
PVNPOPO-4860 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 40 22-Aug-12 18-Oct-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 11 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 014
Activity ID Activity Name OrigDur
Start Finish
PVNPOPO-4900 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 15 19-Oct-12 08-Nov-12
PVNPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 45 09-Nov-12 17-Jan-13
PVNPOPO-4870 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (PVN) 90 18-Jan-13 28-May-13
CS-1/IFO-3 PSCS-1/IFO-3 PSN ELEVATOR PROCUREMENTCS-1/IFO-3 PSN ELEVATOR PROCUREMENTCS-1/IFO-3 PSN ELEVATOR PROCUREMENTCS-1/IFO-3 PSN ELEVATOR PROCUREMENT
PSNPOPO-4860 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 40 25-Jul-12 19-Sep-12
PSNPOPO-4900 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 15 20-Sep-12 10-Oct-12
PSNPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 45 11-Oct-12 18-Dec-12
PSNPOPO-4870 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (PSN) 90 19-Dec-12 29-Apr-13
CS-1/IFO-3 UTILICS-1/IFO-3 UTILITY PROCUREMENTCS-1/IFO-3 UTILITY PROCUREMENTCS-1/IFO-3 UTILITY PROCUREMENTCS-1/IFO-3 UTILITY PROCUREMENT
UTIPOPO-4850 PREPARE/SUBMIT ON-SITE UTILITIES SHOP DRAWINGS - CS-1/IFO-3 50 03-Feb-12 13-Apr-12
UTIPOPO-4870 KT APPROVE ON SITE UTILITIES SHOP DRAWINGS - CS-1/IFO-3 25 16-Apr-12 18-May-12
UTIPOPO-556 VA APPROVE ON SITE UTILITIES SHOP DRAWINGS - CS-1/IFO-3 20 21-May-12 18-Jun-12
UTIPOPO-4860 FAB/DELIVER ON SITE UTILITY MATERIALS - CS-1/IFO-3 65 19-Jun-12 19-Sep-12
CS-1/IFO-3 SELECCS-1/IFO-3 SELECTIVE UNDERGROUND MEP (incl ductbank balance)CS-1/IFO-3 SELECTIVE UNDERGROUND MEP (incl ductbank balance)CS-1/IFO-3 SELECTIVE UNDERGROUND MEP (incl ductbank balance)CS-1/IFO-3 SELECTIVE UNDERGROUND MEP (incl ductbank balance)
CS-1/IFO-3 PVCS-1/IFO-3 PVS UNDERGROUND MEPCS-1/IFO-3 PVS UNDERGROUND MEPCS-1/IFO-3 PVS UNDERGROUND MEPCS-1/IFO-3 PVS UNDERGROUND MEP
PVSPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVS) 20 27-Jan-12 24-Feb-12
PVSPOPO-4840 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVS) 15 27-Feb-12 16-Mar-12
PVSPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVS) 20 19-Mar-12 13-Apr-12
PVSPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (PVS) 20 16-Apr-12 11-May-12
CS-1/IFO-3 COCS-1/IFO-3 CON UNDERGROUND MEPCS-1/IFO-3 CON UNDERGROUND MEPCS-1/IFO-3 CON UNDERGROUND MEPCS-1/IFO-3 CON UNDERGROUND MEP
CONPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CON) 20 28-Dec-11 26-Jan-12
CONPOPO-4930 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CON) 15 27-Jan-12 17-Feb-12
CONPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CON) 20 20-Feb-12 16-Mar-12
CONPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (CON) 20 19-Mar-12 13-Apr-12
CS-1/IFO-3 DACS-1/IFO-3 DAT (no pharmacy) UNDERGROUND MEPCS-1/IFO-3 DAT (no pharmacy) UNDERGROUND MEPCS-1/IFO-3 DAT (no pharmacy) UNDERGROUND MEPCS-1/IFO-3 DAT (no pharmacy) UNDERGROUND MEP
DATPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 40 27-Oct-11 27-Dec-11
DATPOPO-5060 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 15 28-Dec-11 19-Jan-12
DATPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 20 20-Jan-12 17-Feb-12
DATPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (DAT) 15 20-Feb-12 09-Mar-12
CS-1/IFO-3 ENCS-1/IFO-3 ENC UNDERGROUND MEPCS-1/IFO-3 ENC UNDERGROUND MEPCS-1/IFO-3 ENC UNDERGROUND MEPCS-1/IFO-3 ENC UNDERGROUND MEP
ENCPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (ENC) 40 27-Feb-12 20-Apr-12
ENCPOPO-5489 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (ENC) 15 23-Apr-12 11-May-12
ENCPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (ENC) 20 14-May-12 11-Jun-12
ENCPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (ENC) 20 12-Jun-12 10-Jul-12
CS-1/IFO-3 IBSCS-1/IFO-3 IBS/IBN UNDERGROUND MEPCS-1/IFO-3 IBS/IBN UNDERGROUND MEPCS-1/IFO-3 IBS/IBN UNDERGROUND MEPCS-1/IFO-3 IBS/IBN UNDERGROUND MEP
IBPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 35 23-Apr-12 11-Jun-12
IBPOPO-5700 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 15 12-Jun-12 02-Jul-12
IBPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 20 03-Jul-12 31-Jul-12
IBPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (IBS/IBN) 20 01-Aug-12 28-Aug-12
CS-1/IFO-3 CBCS-1/IFO-3 CBC/CBN UNDERGROUND MEPCS-1/IFO-3 CBC/CBN UNDERGROUND MEPCS-1/IFO-3 CBC/CBN UNDERGROUND MEPCS-1/IFO-3 CBC/CBN UNDERGROUND MEP
CBPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CBC/CBN) 30 12-Jun-12 24-Jul-12
CBPOPO-4890 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CBC/CBN) 15 25-Jul-12 14-Aug-12
CBPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CBC/CBN) 20 15-Aug-12 12-Sep-12
CBPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (CBC/CBN) 20 13-Sep-12 10-Oct-12
CS-1/IFO-3 PVCS-1/IFO-3 PVN UNDERGROUND MEPCS-1/IFO-3 PVN UNDERGROUND MEPCS-1/IFO-3 PVN UNDERGROUND MEPCS-1/IFO-3 PVN UNDERGROUND MEP
PVNPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVN) 32 22-Aug-12 05-Oct-12
PVNPOPO-4910 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVN) 15 08-Oct-12 29-Oct-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 12 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 015
Activity ID Activity Name OrigDur
Start Finish
PVNPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVN) 20 30-Oct-12 29-Nov-12
PVNPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (PVN) 20 30-Nov-12 28-Dec-12
CS-1/IFO-3 PSCS-1/IFO-3 PSN UNDERGROUND MEPCS-1/IFO-3 PSN UNDERGROUND MEPCS-1/IFO-3 PSN UNDERGROUND MEPCS-1/IFO-3 PSN UNDERGROUND MEP
PSNPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PSN) 20 25-Jul-12 21-Aug-12
PSNPOPO-4910 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PSN) 15 22-Aug-12 12-Sep-12
PSNPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PSN) 20 13-Sep-12 10-Oct-12
PSNPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (PSN) 20 11-Oct-12 08-Nov-12
ENC MEP EQUIPMENC MEP EQUIPMENTENC MEP EQUIPMENTENC MEP EQUIPMENTENC MEP EQUIPMENT
ENC ELECTRICENC ELECTRICAL EQUIPMENT PROCUREMENTENC ELECTRICAL EQUIPMENT PROCUREMENTENC ELECTRICAL EQUIPMENT PROCUREMENTENC ELECTRICAL EQUIPMENT PROCUREMENT
ENCPOPO-5609 PREPARE/SUBMIT TRANSFORMER SHOP DRAWINGS- ENC EQUIPMENT 50 27-Oct-11 11-Jan-12
ENCPOPO-5639 PREPARE/SUBMIT SWITCHGEAR SHOP DRAWINGS- ENC EQUIPMENT 50 27-Oct-11 11-Jan-12
ENCPOPO-5669 PREPARE/SUBMIT GENERATOR SHOP DRAWINGS- ENC EQUIPMENT 50 27-Oct-11 11-Jan-12
ENCPOPO-5699 PREPARE/SUBMIT SUBSTATION SHOP DRAWINGS- ENC EQUIPMENT 50 27-Oct-11 11-Jan-12
ENCPOPO-5569 KT APPROVE TRANSFORMER SHOP DRAWINGS- ENC EQUIPMENT 20 12-Jan-12 09-Feb-12
ENCPOPO-5589 KT APPROVE GENERATOR SHOP DRAWINGS- ENC EQUIPMENT 20 12-Jan-12 09-Feb-12
ENCPOPO-5599 KT APPROVE SUBSTATION SHOP DRAWINGS- ENC EQUIPMENT 20 12-Jan-12 09-Feb-12
ENCPOPO-5649 KT APPROVE SWITCHGEAR SHOP DRAWINGS- ENC EQUIPMENT 20 12-Jan-12 09-Feb-12
ENCPOPO-5579 VA APPROVE SWITCHGEAR SHOP DRAWINGS - ENC EQUIPMENT 25 10-Feb-12 16-Mar-12
ENCPOPO-5619 VA APPROVE TRANSFORMER SHOP DRAWINGS - ENC EQUIPMENT 25 10-Feb-12 16-Mar-12
ENCPOPO-5679 VA APPROVE GENERATOR SHOP DRAWINGS - ENC EQUIPMENT 25 10-Feb-12 16-Mar-12
ENCPOPO-5709 VA APPROVE SUBSTATION SHOP DRAWINGS - ENC EQUIPMENT 25 10-Feb-12 16-Mar-12
ENCPOPO-5629 FABRICATE/DELIVER TRANSFORMERS - ENC EQUIPMENT 100 19-Mar-12 07-Aug-12
ENCPOPO-5659 FABRICATE/DELIVER SWITCHGEAR - ENC EQUIPMENT 115 19-Mar-12 28-Aug-12
ENCPOPO-5689 FABRICATE/DELIVER GENERATORS - ENC EQUIPMENT 125 19-Mar-12 12-Sep-12
ENCPOPO-5719 FABRICATE/DELIVER SUBSTATIONS - ENC EQUIPMENT 125 19-Mar-12 12-Sep-12
ENC MECHANENC MECHANICAL EQUIPMENT PROCUREMENTENC MECHANICAL EQUIPMENT PROCUREMENTENC MECHANICAL EQUIPMENT PROCUREMENTENC MECHANICAL EQUIPMENT PROCUREMENT
ENCPOPO-5759 PREPARE/SUBMIT CHILLER SHOP DRAWINGS- ENC EQUIPMENT 40 27-Oct-11 27-Dec-11
ENCPOPO-5789 PREPARE/SUBMIT BOILER SHOP DRAWINGS- ENC EQUIPMENT 40 27-Oct-11 27-Dec-11
ENCPOPO-5819 PREPARE/SUBMIT COOLING TOWER SHOP DRAWINGS- ENC EQUIPMENT 40 27-Oct-11 27-Dec-11
ENCPOPO-5729 KT APPROVE CHILLER SHOP DRAWINGS- ENC EQUIPMENT 20 28-Dec-11 26-Jan-12
ENCPOPO-5739 KT APPROVE BOILER SHOP DRAWINGS- ENC EQUIPMENT 20 28-Dec-11 26-Jan-12
ENCPOPO-5749 KT APPROVE COOLING TOWER SHOP DRAWINGS- ENC EQUIPMENT 20 28-Dec-11 26-Jan-12
ENCPOPO-5769 VA APPROVE CHILLER SHOP DRAWINGS- ENC EQUIPMENT 35 27-Jan-12 16-Mar-12
ENCPOPO-5799 VA APPROVE BOILER SHOP DRAWINGS- ENC EQUIPMENT 35 27-Jan-12 16-Mar-12
ENCPOPO-5829 VA APPROVE COOLING TOWER SHOP DRAWINGS- ENC EQUIPMENT 35 27-Jan-12 16-Mar-12
ENCPOPO-5779 FABRICATE/DELIVER CHILLERS- ENC EQUIPMENT 80 19-Mar-12 10-Jul-12
ENCPOPO-5809 FABRICATE/DELIVER BOILERS- ENC EQUIPMENT 80 19-Mar-12 10-Jul-12
ENCPOPO-5839 FABRICATE/DELIVER COOLING TOWERS- ENC EQUIPMENT 80 19-Mar-12 10-Jul-12
IFO-1(balance oIFO-1(balance of interior fit out/MEP Equip/ENC utilities) PRECONIFO-1(balance of interior fit out/MEP Equip/ENC utilities) PRECONIFO-1(balance of interior fit out/MEP Equip/ENC utilities) PRECONIFO-1(balance of interior fit out/MEP Equip/ENC utilities) PRECONIFO-1 95% CONIFO-1 95% CONSTRUCTION DOCUMENTSIFO-1 95% CONSTRUCTION DOCUMENTSIFO-1 95% CONSTRUCTION DOCUMENTSIFO-1 95% CONSTRUCTION DOCUMENTSIFO-3040 95% DESIGN - IFO-1 87 26-Jul-11 30-Nov-11
IFO-3510 95% CD TO KT - IFO-1 1 01-Dec-11 01-Dec-11
IFO-3660 KT PROVIDES RED LINE COMMENTS 95% CD - IFO-1 15 02-Dec-11 22-Dec-11
IFO-3670 PAGE FLIP 95% CD - IFO-1 5 23-Dec-11 30-Dec-11
IFO-3680 JVT REVISE DOCUMENTS 95% CD - IFO-1 15 03-Jan-12 24-Jan-12
IFO-3690 JVT QA/QC DOCUMENTS 95% CD - IFO-1 5 25-Jan-12 31-Jan-12
IFO-1 100% COIFO-1 100% CONSTRUCTION DOCUMENTSIFO-1 100% CONSTRUCTION DOCUMENTSIFO-1 100% CONSTRUCTION DOCUMENTSIFO-1 100% CONSTRUCTION DOCUMENTS
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 13 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 016
Activity ID Activity Name OrigDur
Start Finish
IFO-3700 100% CD DOCUMENTS COMPLETE - IFO-1 0 31-Jan-12
IFO-3630 SUBCONTRACTOR PRICING (GROUP #1)- IFO-1 25 01-Feb-12 07-Mar-12
IFO-3710 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - IFO-1 60 01-Feb-12 31-Mar-12
IFO-4940 SUBCONTRACTOR PRICING (GROUP #2)- IFO-1 25 01-Mar-12 04-Apr-12
IFO-4930 PREPARE BID TABS (GROUP #1) - IFO-1 15 08-Mar-12 28-Mar-12
IFO-5000 SUBCONTRACTOR PRICING (GROUP #3)- IFO-1 25 29-Mar-12 02-May-12
IFO-4950 PREPARE BID TABS (GROUP #2) - IFO-1 15 05-Apr-12 25-Apr-12
IFO-5020 COST/RESOURCE LOAD SCHEDULE (GROUP #1) - IFO-1 60 05-Apr-12 03-Jun-12
IFO-5010 PREPARE BID TABS (GROUP #3) - IFO-1 15 03-May-12 23-May-12
IFO-5030 COST/RESOURCE LOAD SCHEDULE (GROUP #2) - IFO-1 60 03-May-12 01-Jul-12
IFO-5040 COST/RESOURCE LOAD SCHEDULE (GROUP #3) - IFO-1 60 01-Jun-12 30-Jul-12
IFO-1 PROCUREIFO-1 PROCUREMENT (GROUP #1)IFO-1 PROCUREMENT (GROUP #1)IFO-1 PROCUREMENT (GROUP #1)IFO-1 PROCUREMENT (GROUP #1)P-CD4-3950 AWARD MEDICAL EQUIPMENT CONTRACT 20 05-Apr-12 02-May-12
P-CD4-4920 AWARD PNEUMATIC TUBE CONTRACT 20 05-Apr-12 02-May-12
P-CD4-4930 AWARD LAB CASEWORK CONTRACT 20 05-Apr-12 02-May-12
IFO-1 MECHANICAIFO-1 MECHANICAL PROCUREMENTIFO-1 MECHANICAL PROCUREMENTIFO-1 MECHANICAL PROCUREMENTIFO-1 MECHANICAL PROCUREMENT
IFO-1 DAT MECIFO-1 DAT MECHANICAL EQUIPMENT PROCUREMENTIFO-1 DAT MECHANICAL EQUIPMENT PROCUREMENTIFO-1 DAT MECHANICAL EQUIPMENT PROCUREMENTIFO-1 DAT MECHANICAL EQUIPMENT PROCUREMENT
DATPOPO-4800 PREPARE/SUBMIT AHU SHOP DRAWINGS - IFO-1 (DAT) 40 05-Apr-12 31-May-12
DATPOPO-5070 KT APPROVE AHU SHOP DRAWINGS - IFO-1 (DAT) 20 01-Jun-12 28-Jun-12
DATPOPO-556 VA APPROVE AHU SHOP DRAWINGS - IFO-1 (DAT) 20 29-Jun-12 27-Jul-12
DATPOPO-4810 FAB/DELIVER AHUS - IFO-1 (DAT) 65 30-Jul-12 30-Oct-12
IFO-1 IBS/IBN IFO-1 IBS/IBN MECHANICAL EQUIPMENT PROCUREMENTIFO-1 IBS/IBN MECHANICAL EQUIPMENT PROCUREMENTIFO-1 IBS/IBN MECHANICAL EQUIPMENT PROCUREMENTIFO-1 IBS/IBN MECHANICAL EQUIPMENT PROCUREMENT
IBPOPO-4800 PREPARE/SUBMIT AHU SHOP DRAWINGS - IFO-1 (IBS/IBN) 40 05-Apr-12 31-May-12
IBPOPO-5710 KT APPROVE AHU SHOP DRAWINGS - IFO-1 (IBS/IBN) 20 01-Jun-12 28-Jun-12
IBPOPO-556 VA APPROVE AHU SHOP DRAWINGS - IFO-1 (IBS/IBN) 20 29-Jun-12 27-Jul-12
IBPOPO-4810 FAB/DELIVER AHUS - IFO-1 (IBS/IBN) 80 30-Jul-12 21-Nov-12
IFO-1 CBC/CBIFO-1 CBC/CBN MECHANICAL EQUIPMENT PROCUREMENTIFO-1 CBC/CBN MECHANICAL EQUIPMENT PROCUREMENTIFO-1 CBC/CBN MECHANICAL EQUIPMENT PROCUREMENTIFO-1 CBC/CBN MECHANICAL EQUIPMENT PROCUREMENT
CBPOPO-4800 PREPARE/SUBMIT AHU SHOP DRAWINGS - IFO-1 (CBS/CBN) 40 05-Apr-12 31-May-12
CBPOPO-4900 KT APPROVE AHU SHOP DRAWINGS - IFO-1 (CBS/CBN) 20 01-Jun-12 28-Jun-12
CBPOPO-556 VA APPROVE AHU SHOP DRAWINGS - IFO-1 (CBS/CBN) 20 29-Jun-12 27-Jul-12
CBPOPO-4810 FAB/DELIVER AHUS - IFO-1 (CBS/CBN) 80 30-Jul-12 21-Nov-12
IFO-1 WATER TREIFO-1 WATER TREATMENT PROCUREMENTIFO-1 WATER TREATMENT PROCUREMENTIFO-1 WATER TREATMENT PROCUREMENTIFO-1 WATER TREATMENT PROCUREMENT
IFO-3860 SUBMIT WATER TREATMENT EQUIPMENT - IFO-1 60 05-Apr-12 28-Jun-12
IFO-4900 KT APPROVE WATER TREATMENT EQUIPMENT - IFO-1 15 29-Jun-12 20-Jul-12
IFO-3870 VA APPROVE WATER TREATMENT EQUIPMENT - IFO-1 20 23-Jul-12 17-Aug-12
IFO-3880 FABRICATE WATER TREATMENT EQUIPMENT - IFO-1 120 20-Aug-12 14-Feb-13
IFO-3890 WATER TREATMENT EQUIPMENT ARRIVES 0 14-Feb-13
IFO-1 ELECTRICALIFO-1 ELECTRICAL PROCUREMENTIFO-1 ELECTRICAL PROCUREMENTIFO-1 ELECTRICAL PROCUREMENTIFO-1 ELECTRICAL PROCUREMENT
IFO-4010 SUBMIT SOLARVOLTAIC EQUIPMENT - IFO-1 50 05-Apr-12 14-Jun-12
IFO-4910 KT APPROVE SOLARVOLTAIC EQUIPMENT - IFO-1 25 15-Jun-12 20-Jul-12
IFO-4020 VA APPROVE SOLARVOLTAIC EQUIPMENT - IFO-1 20 23-Jul-12 17-Aug-12
IFO-4030 FABRICATE SOLARVOLTAIC EQUIPMENT - IFO-1 140 20-Aug-12 14-Mar-13
IFO-4040 SOLARVOLTAIC EQUIPMENT ARRIVES - IFO-1 0 14-Mar-13
IFO-1 DAT ELEIFO-1 DAT ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 DAT ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 DAT ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 DAT ELECTRICAL EQUIPMENT PROCUREMENT
DATPOPO-4820 PREPARE/SUBMIT ELEC EQUIP SHOP DRAWINGS - IFO-1 (DAT) 50 19-Apr-12 28-Jun-12
DATPOPO-5080 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (DAT) 15 29-Jun-12 20-Jul-12
DATPOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (DAT) 25 23-Jul-12 24-Aug-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 14 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 017
Activity ID Activity Name OrigDur
Start Finish
DATPOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (DAT) 65 27-Aug-12 30-Nov-12
IFO-1 IBS/IBN IFO-1 IBS/IBN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 IBS/IBN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 IBS/IBN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 IBS/IBN ELECTRICAL EQUIPMENT PROCUREMENT
IBPOPO-4820 PREPARE/SUBMIT ELEC SHOP DRAWINGS - IFO-1 (IBS/IBN) 50 17-May-12 27-Jul-12
IBPOPO-5720 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (IBS/IBN) 15 30-Jul-12 17-Aug-12
IBPOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (IBS/IBN) 25 20-Aug-12 24-Sep-12
IBPOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (IBS/IBN) 65 25-Sep-12 31-Dec-12
IFO-1 PVN ELEIFO-1 PVN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 PVN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 PVN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 PVN ELECTRICAL EQUIPMENT PROCUREMENT
PVNOPO-4820 PREPARE/SUBMIT ELEC SHOP DRAWINGS - IFO-1 (PVN) 50 01-Jun-12 10-Aug-12
PVNOPO-4850 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (PVN) 15 13-Aug-12 31-Aug-12
PVNOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (PVN) 25 04-Sep-12 08-Oct-12
PVNOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (PVN) 65 09-Oct-12 15-Jan-13
IFO-1 PVS ELEIFO-1 PVS ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 PVS ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 PVS ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 PVS ELECTRICAL EQUIPMENT PROCUREMENT
PVSOPO-4820 PREPARE/SUBMIT ELEC SHOP DRAWINGS - IFO-1 (PVS) 50 05-Apr-12 14-Jun-12
PVSOPO-4850 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (PVS) 15 15-Jun-12 06-Jul-12
PVSOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (PVS) 25 09-Jul-12 10-Aug-12
PVSOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (PVS) 65 13-Aug-12 14-Nov-12
IFO-1 CBC/CBIFO-1 CBC/CBN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 CBC/CBN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 CBC/CBN ELECTRICAL EQUIPMENT PROCUREMENTIFO-1 CBC/CBN ELECTRICAL EQUIPMENT PROCUREMENT
CBPOPO-4820 PREPARE/SUBMIT ELEC SHOP DRAWINGS - IFO-1 (CBS/CBN) 50 03-May-12 13-Jul-12
CBPOPO-4910 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (CBS/CBN) 15 16-Jul-12 03-Aug-12
CBPOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (CBS/CBN) 25 06-Aug-12 10-Sep-12
CBPOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (CBS/CBN) 65 11-Sep-12 14-Dec-12
IFO-1 MEDICAL EQIFO-1 MEDICAL EQUIPMENT PROCUREMENTIFO-1 MEDICAL EQUIPMENT PROCUREMENTIFO-1 MEDICAL EQUIPMENT PROCUREMENTIFO-1 MEDICAL EQUIPMENT PROCUREMENT
IFO-1 DAT MEIFO-1 DAT MEDICAL EQUIPMENT PROCUREMENTIFO-1 DAT MEDICAL EQUIPMENT PROCUREMENTIFO-1 DAT MEDICAL EQUIPMENT PROCUREMENTIFO-1 DAT MEDICAL EQUIPMENT PROCUREMENT
DATPOPO-4950 SUBMIT MEDICAL EQUIPMENT SHOPS (pharmacy) - IFO-1 (DAT) 60 03-May-12 27-Jul-12
DATPOPO-3960 SUBMIT MEDICAL EQUIPMENT SHOPS (gen imaging) - IFO-1 (DAT) 60 17-May-12 10-Aug-12
DATPOPO-4990 SUBMIT MEDICAL EQUIPMENTSHOPS (MRI/CT) - IFO-1 (DAT) 60 01-Jun-12 24-Aug-12
DATPOPO-4870 SUBMIT MEDICAL EQUIPMENTSHOPS (dental) - IFO-1 (DAT) 60 15-Jun-12 10-Sep-12
DATPOPO-4910 SUBMIT MEDICAL EQUIPMENT SHOPS (surgery) - IFO-1 (DAT) 60 29-Jun-12 24-Sep-12
DATPOPO-5120 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(pharmacy) INFO - IFO-1 (DAT) 15 30-Jul-12 17-Aug-12
DATPOPO-5090 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(gen imaging) INFO- IFO-1 (DAT) 15 13-Aug-12 31-Aug-12
DATPOPO-4960 VA APPROVE MEDICAL EQUIPMENT(pharmacy) - IFO-1 (DAT) 20 20-Aug-12 17-Sep-12
DATPOPO-5130 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(MRI/CT) INFO- IFO-1 (DAT) 15 27-Aug-12 17-Sep-12
DATPOPO-3970 VA APPROVE MEDICAL EQUIPMENT(gen imaging) - IFO-1 (DAT) 20 04-Sep-12 01-Oct-12
DATPOPO-5100 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(dental) INFO - IFO-1 (DAT) 15 11-Sep-12 01-Oct-12
DATPOPO-4970 FABRICATE MEDICAL EQUIPMENT (pharmacy) - IFO-1 (DAT) 140 18-Sep-12 11-Apr-13
DATPOPO-5000 VA APPROVE MEDICAL EQUIPMENT(MRI/CT) - IFO-1 (DAT) 20 18-Sep-12 16-Oct-12
DATPOPO-5110 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(surgery) INFO - IFO-1 (DAT) 15 25-Sep-12 16-Oct-12
DATPOPO-4880 VA APPROVE MEDICAL EQUIPMENT(dental) - IFO-1 (DAT) 20 02-Oct-12 30-Oct-12
DATPOPO-3980 FABRICATE MEDICAL EQUIPMENT (gen imaging) - IFO-1 (DAT) 140 02-Oct-12 25-Apr-13
DATPOPO-4920 VA APPROVE MEDICAL EQUIPMENT(surgery) - IFO-1 (DAT) 20 17-Oct-12 14-Nov-12
DATPOPO-5010 FABRICATE MEDICAL EQUIPMENT (MRI/CT) - IFO-1 (DAT) 160 17-Oct-12 07-Jun-13
DATPOPO-4890 FABRICATE MEDICAL EQUIPMENT (dental) - IFO-1 (DAT) 140 31-Oct-12 23-May-13
DATPOPO-4930 FABRICATE MEDICAL EQUIPMENT (surgery) - IFO-1 (DAT) 140 15-Nov-12 07-Jun-13
DATPOPO-4980 MEDICAL EQUIPMENT ARRIVES (pharmacy) - IFO-1 (DAT) 0 11-Apr-13
DATPOPO-3990 MEDICAL EQUIPMENT ARRIVES (gen imaging) - IFO-1 (DAT) 0 25-Apr-13
DATPOPO-4900 MEDICAL EQUIPMENT ARRIVES (dental) - IFO-1 (DAT) 0 23-May-13
DATPOPO-4940 MEDICAL EQUIPMENT ARRIVES (surgery) - IFO-1 (DAT) 0 07-Jun-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 15 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 018
Activity ID Activity Name OrigDur
Start Finish
DATPOPO-5020 MEDICAL EQUIPMENT ARRIVES (MRI/CT) - IFO-1 (DAT) 0 07-Jun-13
IFO-1 IBS/IBN IFO-1 IBS/IBN HEAD WALL PROCUREMENTIFO-1 IBS/IBN HEAD WALL PROCUREMENTIFO-1 IBS/IBN HEAD WALL PROCUREMENTIFO-1 IBS/IBN HEAD WALL PROCUREMENT
IBPOPO-1500 HEADWALL MOCK-UP SHOP DRAWINGS - IFO-1 (IBS/IBN) 30 05-Apr-12 16-May-12
IBPOPO-5730 KT REVIEW HEADWALL MOCK- UP DESIGN - IFO-1 (IBS/IBN) 10 17-May-12 31-May-12
IBPOPO-1501 VA APPROVE HEADWALL MOCK- UP DESIGN - IFO-1 (IBS/IBN) 20 01-Jun-12 28-Jun-12
IBPOPO-1052 HEADWALL MOCK- UP MATERIAL PROCURMENT AND FAB - IFO-1 (IBS/IBN) 40 29-Jun-12 24-Aug-12
IBPOPO-5740 KT REVIEW HEADWALL MOCK-UP - IFO-1 (IBS/IBN) 15 27-Aug-12 17-Sep-12
IBPOPO-4880 VA APPROVE HEADWALL MOCK-UP - IFO-1 (IBS/IBN) 20 18-Sep-12 16-Oct-12
IBPOPO-4890 FABRICATE/DELIVER HEADWALLS - IFO-1 (IBS/IBN) 120 17-Oct-12 11-Apr-13
IBPOPO-5750 HEADWALLS ARRIVE - IFO-1 (IBS/IBN) 0 11-Apr-13
IFO-1 LAB CASEWIFO-1 LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 LAB CASEWORK/EQUIPMENT PROCUREMENT
IFO-1 DAT LABIFO-1 DAT LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 DAT LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 DAT LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 DAT LAB CASEWORK/EQUIPMENT PROCUREMENT
DATPOPO-1500 LAB CASEWORK MOCK-UP SHOP DRAWINGS - IFO-1 (DAT) 30 03-May-12 14-Jun-12
DATPOPO-4901 KT REVIEW LAB CASEWORK MOCK- UP DESIGN - IFO-1 (DAT) 20 15-Jun-12 13-Jul-12
DATPOPO-1501 VA APPROVE LAB CASEWORK MOCK- UP DESIGN - IFO-1 (DAT) 20 16-Jul-12 10-Aug-12
DATPOPO-1052 LAB CASEWORK MOCK- UP MATERIAL PROCURMENT AND FAB - IFO-1 (DAT) 40 13-Aug-12 08-Oct-12
DATPOPO-4911 KT REVIEW LAB CASEWORK MOCK-UP - IFO-1 (DAT) 20 09-Oct-12 06-Nov-12
DATPOPO-4881 VA APPROVE LAB CASEWORK MOCK-UP - IFO-1 (DAT) 20 07-Nov-12 07-Dec-12
DATPOPO-4891 FABRICATE/DELIVER LAB CASEWORK - IFO-1 (DAT) 65 10-Dec-12 14-Mar-13
IFO-1 RES LABIFO-1 RES LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 RES LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 RES LAB CASEWORK/EQUIPMENT PROCUREMENTIFO-1 RES LAB CASEWORK/EQUIPMENT PROCUREMENT
RESPOPO-1500 LAB CASEWORK MOCK-UP SHOP DRAWINGS - IFO-1 (RES) 30 15-Jun-12 27-Jul-12
RESPOPO-4901 KT REVIEW LAB CASEWORK MOCK- UP DESIGN - IFO-1 (RES) 20 30-Jul-12 24-Aug-12
RESPOPO-1501 VA APPROVE LAB CASEWORK MOCK- UP DESIGN - IFO-1 (RES) 20 27-Aug-12 24-Sep-12
RESPOPO-1052 LAB CASEWORK MOCK- UP MATERIAL PROCURMENT AND FAB - IFO-1 (RES) 40 25-Sep-12 21-Nov-12
RESPOPO-4911 KT REVIEW LAB CASEWORK MOCK-UP - IFO-1 (RES) 20 26-Nov-12 21-Dec-12
RESPOPO-4881 VA APPROVE LAB CASEWORK MOCK-UP - IFO-1 (RES) 20 24-Dec-12 23-Jan-13
RESPOPO-4891 FABRICATE/DELIVER LAB CASEWORK - IFO-1 (RES) 65 24-Jan-13 25-Apr-13
IFO-1 PNEUMATICIFO-1 PNEUMATIC TUBE PROCUREMENTIFO-1 PNEUMATIC TUBE PROCUREMENTIFO-1 PNEUMATIC TUBE PROCUREMENTIFO-1 PNEUMATIC TUBE PROCUREMENT
ALLPOPO-4820 PREPARE/SUBMIT PNEU TUBE SHOP DRAWINGS - IFO-1 60 03-May-12 27-Jul-12
ALLPOPO-4850 KT APPROVE PNEUB TUBE SHOP DRAWINGS - IFO-1 20 30-Jul-12 24-Aug-12
ALLPOPO-4830 VA APPROVE PNEUB TUBE SHOP DRAWINGS - IFO-1 20 27-Aug-12 24-Sep-12
ALLPOPO-4840 FAB/DELIVER PNEUMATIC TUBE - IFO-1 45 25-Sep-12 30-Nov-12
IFO-1 GROUP #IFO-1 GROUP #2 PROCUREMENTIFO-1 GROUP #2 PROCUREMENTIFO-1 GROUP #2 PROCUREMENTIFO-1 GROUP #2 PROCUREMENTALLPOPO-4870 PREPARE/SUBMIT SHOP DRAWINGS - IFO-1 GROUP #2 50 03-May-12 13-Jul-12
ALLPOPO-4860 KT APPROVE SHOP DRAWINGS - IFO-1 GROUP #2 15 16-Jul-12 03-Aug-12
ALLPOPO-4880 VA APPROVE SHOP DRAWINGS - IFO-1 GROUP #2 20 06-Aug-12 31-Aug-12
ALLPOPO-4890 FAB/DELIVER MATERIALS & EQUIPMENT - IFO-1 GROUP #2 45 04-Sep-12 06-Nov-12
IFO-1 GROUP #IFO-1 GROUP #3 PROCUREMENTIFO-1 GROUP #3 PROCUREMENTIFO-1 GROUP #3 PROCUREMENTIFO-1 GROUP #3 PROCUREMENTALLPOPO-4910 PREPARE/SUBMIT SHOP DRAWINGS - IFO-1 GROUP #3 50 01-Jun-12 10-Aug-12
ALLPOPO-4900 KT APPROVE SHOP DRAWINGS - IFO-1 GROUP #3 15 13-Aug-12 31-Aug-12
ALLPOPO-4920 VA APPROVE SHOP DRAWINGS - IFO-1 GROUP #3 20 04-Sep-12 01-Oct-12
ALLPOPO-4930 FAB/DELIVER MATERIALS & EQUIPMENT - IFO-1 GROUP #3 45 02-Oct-12 07-Dec-12
CREDIT UNION PCREDIT UNION PRECONSTRUCTIONCREDIT UNION PRECONSTRUCTIONCREDIT UNION PRECONSTRUCTIONCREDIT UNION PRECONSTRUCTIONCREDIT-1418 SUBCONTRACTOR PRICING FOR CREDIT UNION DEMO 25 26-Jul-11 29-Aug-11
CREDIT-1468 PREPARE BID TABS - CREDIT UNION DEMO 15 30-Aug-11 20-Sep-11
CREDIT-1428 AWARD CREDIT UNION DEMO CONTRACT 20 28-Sep-11 26-Oct-11
CREDIT-1438 PREPARE DEMOLITION PLAN FOR CREDIT UNION 20 27-Oct-11 28-Nov-11
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 16 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 019
Activity ID Activity Name OrigDur
Start Finish
CREDIT-1448 KT REVIEW/APPROVE DEMOLITION PLAN FOR CREDIT UNION 10 29-Nov-11 12-Dec-11
CLC PRECONSTRCLC PRECONSTRUCTIONCLC PRECONSTRUCTIONCLC PRECONSTRUCTIONCLC PRECONSTRUCTIONCLC-5310 AWARD CONTRACT - CLC 20 25-Jul-12 21-Aug-12
CLC 100% CONCLC 100% CONSTRUCTION DOCUMENTSCLC 100% CONSTRUCTION DOCUMENTSCLC 100% CONSTRUCTION DOCUMENTSCLC 100% CONSTRUCTION DOCUMENTSCLC-3610 100% CD DESIGN COMPLETION - CLC 0 27-Apr-12*
CLC-3710 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - CLC 60 28-Apr-12 26-Jun-12
CLC-3630 SUBCONTRACTOR PRICING - CLC 40 30-Apr-12 25-Jun-12
CLC-4930 PREPARE BID TABS - CLC 15 26-Jun-12 17-Jul-12
CLC-5020 COST/RESOURCE LOAD BALANCE OF SCHEDULE - CLC 60 27-Jun-12 25-Aug-12
CLC PROCUREMCLC PROCUREMENTCLC PROCUREMENTCLC PROCUREMENTCLC PROCUREMENTCS-1/IFO-3 CBC/CCS-1/IFO-3 CBC/CBN UNDERGROUND MEPCS-1/IFO-3 CBC/CBN UNDERGROUND MEPCS-1/IFO-3 CBC/CBN UNDERGROUND MEPCS-1/IFO-3 CBC/CBN UNDERGROUND MEP
CLCOPO-4770 PREPARE/SUBMIT CRITICAL PROCUREMENT - CLC 30 22-Aug-12 03-Oct-12
CLCOPO-4890 KT APPROVE CRITICAL PROCUREMENT - CLC 15 04-Oct-12 25-Oct-12
CLCOPO-4780 VA APPROVE CRITICAL PROCUREMENT - CLC 20 26-Oct-12 27-Nov-12
CLCOPO-4790 DELIVER CRITICAL PROCUREMENT - CLC 20 28-Nov-12 26-Dec-12
HOISTING REQHOISTING REQUIREMENTSHOISTING REQUIREMENTSHOISTING REQUIREMENTSHOISTING REQUIREMENTSTOWER CRANESTOWER CRANESTOWER CRANESTOWER CRANESTOWER CRANESHOITCTC-0110 ERECT TOWER CRANE #1 (DAT & CON C/D) 10 07-Apr-12 16-Apr-12
HOITCTC-0100 MAINTAIN TOWER CRANE #1 (DAT & CON C/D) 487 17-Apr-12 16-Aug-13
HOITCTC-0103 ERECT TOWER CRANE #3 (IBS/IBN CON B) 10 16-May-12 25-May-12
HOITCTC-0300 MAINTAIN TOWER CRANE #3 (IBS/IBN, CON B) 524 16-May-12 21-Oct-13
HOITCTC-0102 ERECT TOWER CRANE #2 (PVS) 10 23-Oct-12 03-Nov-12
HOITCTC-0200 MAINTAIN TOWER CRANE #2 (PVS) 153 03-Nov-12 05-Apr-13
MAN/MATERIALMAN/MATERIAL HOISTSMAN/MATERIAL HOISTSMAN/MATERIAL HOISTSMAN/MATERIAL HOISTSDATESAC-0530 INSTALL/MAINTAIN MAN/MATERIAL HOIST - ALL ELEVS AR-C (DAT) 499 16-Apr-13 27-Aug-14
DATESAF-0530 INSTALL/MAINTAIN MAN/MATERIAL HOIST - ALL ELEVS AR-F (DAT) 499 16-Apr-13 27-Aug-14
HOIMHMH-0300 INSTALL/MAINTAIN MAN MATERIAL HOIST (IBN) 256 12-Jul-13 24-Mar-14
HOIMHMH-0200 INSTALL/MAINTAIN MAN/MATERIAL HOIST (IBS) 249 20-Jul-13 25-Mar-14
HOIMHMH-0100 INSTALL/MAINTAIN MAN/MATERIAL HOIST (RES) 240 04-Sep-14 01-May-15
INITIAL SITEWINITIAL SITEWORKINITIAL SITEWORKINITIAL SITEWORKINITIAL SITEWORKINITIAL SITEWOINITIAL SITEWORKINITIAL SITEWORKINITIAL SITEWORKINITIAL SITEWORKSITSWSW-0100 MOBILIZE INITIAL CONSTRUCTION RESOURCES - FULL CAMPUS 5 23-Sep-11 30-Sep-11
SITSWSW-0220 SURVEY- FULL CAMPUS 20 03-Oct-11 03-Nov-11
SITSWSW-0230 PLACE EROSION CONTROL - FULL CAMPUS 20 05-Oct-11 07-Nov-11
SITSWSW-260 OVERLOT GRADING - FULL CAMPUS 15 08-Nov-11 26-Nov-11
NORTH PARCELNORTH PARCELNORTH PARCELNORTH PARCELNORTH PARCELRFP #3RFP #3RFP #3RFP #3RFP #3C-DEM-1409 MOBILIZE ABATEMENT 10 18-Aug-11 02-Sep-11
C-DEM-1400 APARTMENT COMPLEX ABATEMENT 20 06-Sep-11 06-Oct-11
C-DEM-1411 UTILITY DISCONNECTS 5 06-Sep-11 12-Sep-11
C-DEM-1401 POOL BUILDING ABATEMENT 20 07-Oct-11 09-Nov-11
C-DEM-1412 APARTMENT COMPLEX POST ABATEMENT AIR QUALITY REV 10 07-Oct-11 24-Oct-11
SITSWNP-0100 MOBILIZE RFP 3 CONSTRUCTION RESOURCES - NORTH PARCEL 5 14-Oct-11 20-Oct-11
C-DEM-1403 APARTMENT COMPLEX DEMOLITION & EXCAVATION/FILL 25 25-Oct-11 05-Dec-11
SITSWNP-0280 RFP 3 ABOVE GROUND DEMOLITION - NORTH PARCEL 25 27-Oct-11 06-Dec-11
SITSWNP-0200 RFP 3 UNDERGROUND DEMOLITION/ABATEMENT - NORTH PARCEL 30 04-Nov-11 22-Dec-11
C-DEM-1414 POOL BUILDING POST ABATEMENT AIR QUALITY REVIEW 10 10-Nov-11 28-Nov-11
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 17 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 020
Activity ID Activity Name OrigDur
Start Finish
C-DEM-1404 POOL BUILDING DEMOLITION & EXCAVATION/FILL 25 06-Dec-11 17-Jan-12
C-DEM-1413 COMPLETE RFP 3 APT AND POOL COMPLEX DEMO 0 17-Jan-12
CREDIT UNIONCREDIT UNION DEMOLITIONCREDIT UNION DEMOLITIONCREDIT UNION DEMOLITIONCREDIT UNION DEMOLITIONCREDIT-1424 MOBILIZE CONTRACTOR - CREDIT UNION 10 13-Feb-12 28-Feb-12
CREDIT-1434 INSTALL FENCE AND EROSION CONTROL - CREDIT UNION 20 29-Feb-12 30-Mar-12
CREDIT-1405 DEMOLITION & EXCAVATION/FILL - CREDIT UNION 30 02-Apr-12 25-May-12
SOUTH PARCELSOUTH PARCELSOUTH PARCELSOUTH PARCELSOUTH PARCELSITSWSP-0100 MOBILIZE CONSTRUCTION RESOURCES - SOUTH PARCEL 5 14-Oct-11 20-Oct-11
SITSWSP-0280 ABOVE GROUND DEMOLITION - SOUTH PARCEL 25 27-Oct-11 06-Dec-11
SITSWSP-0200 UNDERGROUND DEMOLITION - SOUTH PARCEL 30 08-Nov-11 27-Dec-11
TEMPORARY PARTEMPORARY PARKINGTEMPORARY PARKINGTEMPORARY PARKINGTEMPORARY PARKINGRESEARCH TEMRESEARCH TEMP PARKINGRESEARCH TEMP PARKINGRESEARCH TEMP PARKINGRESEARCH TEMP PARKINGSITSWTP-18 GRADING - TEMP PARKING 10 20-Dec-11 05-Jan-12
SITSWTP-20 INSTALL UTILITIES - TEMP PARKING 10 17-Jan-12 30-Jan-12
SITSWTP-07800 PLACE CURB/GUTTER/SIDEWALK/PARKING LOT - TEMP PARKING 7 26-Jan-12 03-Feb-12
SITSWTP-28 STRIPE PARKING LOT & INSTALL FINISHES- TEMP PARKING 3 06-Feb-12 08-Feb-12
OFF-SITE INFROFF-SITE INFRASTRUCTUREOFF-SITE INFRASTRUCTUREOFF-SITE INFRASTRUCTUREOFF-SITE INFRASTRUCTUREPOTHOLING FORPOTHOLING FOR SOE TIE-BACK COORDINATION ACTIVITIESPOTHOLING FOR SOE TIE-BACK COORDINATION ACTIVITIESPOTHOLING FOR SOE TIE-BACK COORDINATION ACTIVITIESPOTHOLING FOR SOE TIE-BACK COORDINATION ACTIVITIESSITWSSW-0288 SURVEYOR MAP/PROVIDE AS-BUILTS - POTHOLING 15 12-Sep-11 05-Oct-11
SITSWSW-0150 LOCATE ALL UTILITIES - POTHOLING 10 12-Sep-11 27-Sep-11
SITSWSW-0102 SHORING SUB COORDINATE WITH DESIGN - POTHOLING 5 05-Oct-11 11-Oct-11
SITSWSW-0001 KT ATTAIN APPROVAL FOR TIE-BACKS UNDER ROADWAYS - POTHOLING 20 12-Oct-11 08-Nov-11
WHEELING WATWHEELING WATERLINE ACTIVITIESWHEELING WATERLINE ACTIVITIESWHEELING WATERLINE ACTIVITIESWHEELING WATERLINE ACTIVITIESSITWSSW-328 PLACE EROSION PROTECTION/TRAFFIC CONTROL - WHEELING ST. 2 23-Dec-11 28-Dec-11
SITWSSW-288 DEMO/GRADING - WHEELING ST. 5 28-Dec-11 05-Jan-12
SITWSSW-0205 INSTALL/TEST NEW WATERLINE - WHEELING ST. 15 05-Jan-12 30-Jan-12
SITWSSW-298 CONSTRUCT ROADWAY - WHEELING ST. 8 30-Jan-12 09-Feb-12
SITWSSW-308 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - WHEELING ST. 10 16-Apr-12 30-Apr-12
BALANCE OF WHBALANCE OF WHEELING STREET ACTIVITIESBALANCE OF WHEELING STREET ACTIVITIESBALANCE OF WHEELING STREET ACTIVITIESBALANCE OF WHEELING STREET ACTIVITIESNORTH WHEELINORTH WHEELING STREET ACTIVITIESNORTH WHEELING STREET ACTIVITIESNORTH WHEELING STREET ACTIVITIESNORTH WHEELING STREET ACTIVITIESSITSWBW-0215 PLACE EROSION PROTECTION/TRAFFIC CONTROL - NORTH WHEELING ST. 4 01-May-12 07-May-12
SITSWBW-0218 DEMO/GRADING - NORTH WHEELING ST. 15 08-May-12 01-Jun-12
SITSWBW-0205 INSTALL REMAINING UTILITIES - NORTH WHEELING ST. 25 04-Jun-12 16-Jul-12
SITSWBW-0228 CONSTRUCT ROADWAY - NORTH WHEELING ST. 25 17-Jul-12 28-Aug-12
SITSWBW-0238 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - NORTH WHEELING ST. 25 30-Aug-12 09-Oct-12
INTERSECTIONINTERSECTION WHEELING STREET ACTIVITIESINTERSECTION WHEELING STREET ACTIVITIESINTERSECTION WHEELING STREET ACTIVITIESINTERSECTION WHEELING STREET ACTIVITIESSITSWBW-238 PLACE EROSION PROTECTION/TRAFFIC CONTROL - INTERSEC WHEELING ST. 4 10-Oct-12 16-Oct-12
SITSWBW-248 DEMO/GRADING - INTERSEC WHEELING ST.. 10 18-Oct-12 01-Nov-12
SITSWBW-258 INSTALL REMAINING UTILITIES - INTERSEC WHEELING ST. 17 02-Nov-12 30-Nov-12
SITSWBW-268 CONSTRUCT ROADWAY - INTERSEC WHEELING ST. 15 03-Dec-12 26-Dec-12
SITSWBW-278 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - INTERSEC WHEELING ST. 20 15-Apr-13 14-May-13
SOUTH WHEELISOUTH WHEELING STREET ACTIVITIESSOUTH WHEELING STREET ACTIVITIESSOUTH WHEELING STREET ACTIVITIESSOUTH WHEELING STREET ACTIVITIESSITSWBW-288 PLACE EROSION PROTECTION/TRAFFIC CONTROL - SOUTH WHEELING ST. 4 16-May-13 21-May-13
SITSWBW-298 DEMO/GRADING - SOUTH WHEELING ST. 15 23-May-13 17-Jun-13
SITSWBW-308 INSTALL REMAINING UTILITIES - SOUTH WHEELING ST. 25 18-Jun-13 30-Jul-13
SITSWBW-318 CONSTRUCT ROADWAY - SOUTH WHEELING ST. 25 01-Aug-13 12-Sep-13
SITSWBW-328 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - SOUTH WHEELING ST. 25 13-Sep-13 23-Oct-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 18 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 021
Activity ID Activity Name OrigDur
Start Finish
19TH PLACE ACT19TH PLACE ACTIVITIES19TH PLACE ACTIVITIES19TH PLACE ACTIVITIES19TH PLACE ACTIVITIES19SW-0215 PLACE EROSION PROTECTION/TRAFFIC CONTROL - 19TH PLACE 4 01-May-12 07-May-12
19SW-0218 DEMO/GRADING - 19TH PLACE 12 08-May-12 29-May-12
19SW-0220 INSTALL UTILITIES - 19TH PLACE 15 30-May-12 22-Jun-12
19SW-0228 CONSTRUCT ROADWAY - 19TH PLACE 15 25-Jun-12 19-Jul-12
19SW-0238 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - 19TH PLACE 10 20-Jul-12 06-Aug-12
17TH PLACE ACT17TH PLACE ACTIVITIES17TH PLACE ACTIVITIES17TH PLACE ACTIVITIES17TH PLACE ACTIVITIESPLSW-0215 PLACE EROSION PROTECTION/TRAFFIC CONTROL - 17TH PLACE 4 16-May-13 21-May-13
PLSW-0218 DEMO/GRADING - 17TH PLACE 12 23-May-13 11-Jun-13
PLSW-0220 INSTALL UTILITIES - 17TH PLACE 25 13-Jun-13 25-Jul-13
PLSW-238 INSTALL UTILIDOR - 17TH PLACE 15 21-Jun-13 16-Jul-13
PLSW-0228 CONSTRUCT ROADWAY - 17TH PLACE 25 26-Jul-13 06-Sep-13
PLSW-0238 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - 17TH PLACE 15 09-Sep-13 02-Oct-13
17TH AVENUE AC17TH AVENUE ACTIVITIES17TH AVENUE ACTIVITIES17TH AVENUE ACTIVITIES17TH AVENUE ACTIVITIES17SW-0215 PLACE EROSION PROTECTION/TRAFFIC CONTROL - 17TH AVE 2 16-May-13 17-May-13
17SW-0218 DEMO/GRADING - 17TH AVE 5 20-May-13 28-May-13
17SW-0220 INSTALL UTILITIES - 17TH AVE 15 29-May-13 21-Jun-13
17SW-0228 CONSTRUCT ROADWAY - 17TH AVE 15 24-Jun-13 18-Jul-13
17SW-0238 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - 17TH AVE 5 19-Jul-13 25-Jul-13
MONTVIEW BLVMONTVIEW BLVD. ACTIVITIESMONTVIEW BLVD. ACTIVITIESMONTVIEW BLVD. ACTIVITIESMONTVIEW BLVD. ACTIVITIESMBSW-238 PLACE EROSION PROTECTION/TRAFFIC CONTROL - MONTVIEW BLVD. 4 24-Oct-13 29-Oct-13
MBSW-248 DEMO/GRADING - MONTVIEW BLVD. 15 31-Oct-13 25-Nov-13
MBSW-258 INSTALL UTILITIES - MONTVIEW BLVD. 15 26-Nov-13 19-Dec-13
MBSW-268 CONSTRUCT ROADWAY - MONTVIEW BLVD. 25 20-Dec-13 29-Jan-14
MBSW-278 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - MONTVIEW BLVD. 25 14-Apr-14 22-May-14
CONCOURSE (CCONCOURSE (CON)CONCOURSE (CON)CONCOURSE (CON)CONCOURSE (CON)CONCOURSE (COCONCOURSE (CON) - STRUCTURECONCOURSE (CON) - STRUCTURECONCOURSE (CON) - STRUCTURECONCOURSE (CON) - STRUCTURECON - AREA ACON - AREA ACON - AREA ACON - AREA ACON - AREA ACON - LEVEL 1 ARECON - LEVEL 1 AREA ACON - LEVEL 1 AREA ACON - LEVEL 1 AREA ACON - LEVEL 1 AREA A
CONAAL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-A CON 12 04-Oct-12 23-Oct-12
CONAASL-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS - SERV LVL AR-A CON 8 08-Oct-12 19-Oct-12
CONAAL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-A CON 5 24-Oct-12 30-Oct-12
CONAAL1-0320 DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-A CON 8 08-Jan-13 18-Jan-13
CONAAL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-A CON 6 22-Jan-13 29-Jan-13
CONAAL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-A CON 8 30-Jan-13 08-Feb-13
CON - SUPER STRUCON - SUPER STRUCTURE AREA ACON - SUPER STRUCTURE AREA ACON - SUPER STRUCTURE AREA ACON - SUPER STRUCTURE AREA A
CONAASS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-A CON 23 11-Feb-13 19-Mar-13
CONAASS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-A CON 5 20-Mar-13 26-Mar-13
CON - SERVICE LECON - SERVICE LEVEL AREA ACON - SERVICE LEVEL AREA ACON - SERVICE LEVEL AREA ACON - SERVICE LEVEL AREA A
CONAASL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-A CON 8 27-Feb-12 06-Mar-12
CONAASL-3210 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-A CON 7 08-Mar-12 16-Mar-12
CONAASL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-A CON 15 05-Apr-12 03-May-12
CONAASL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-A CON 18 11-May-12 11-Jun-12
CONAASL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-A CON 40 12-Jun-12 20-Aug-12
CONAASL-3200 UNDERSLAB UTILITIES - SERV LVL AR-A CON 17 21-Aug-12 18-Sep-12
CONAASL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-A CON 11 20-Sep-12 05-Oct-12
CONAASL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-A CON 40 01-Nov-12 07-Jan-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 19 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 022
Activity ID Activity Name OrigDur
Start Finish
CON - LOW ROOFSCON - LOW ROOFS AREA ACON - LOW ROOFS AREA ACON - LOW ROOFS AREA ACON - LOW ROOFS AREA A
CONAALR-0710 PARAPET/BLOCKING/ROOFING - LOW ROOF AR-A CON 12 23-Apr-13 14-May-13
CONAALR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF AR-A CON 12 16-May-13 04-Jun-13
CONAALR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF AR-A CON 10 06-Jun-13 21-Jun-13
CON - HIGH ROOFCON - HIGH ROOF AREA ACON - HIGH ROOF AREA ACON - HIGH ROOF AREA ACON - HIGH ROOF AREA A
CONAAHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- LOW ROOF AR-A CON 12 29-Aug-13 17-Sep-13
CONAAHR-0755 INSTALL STANDING SEAM ROOF - LOW ROOF AR-A CON 25 19-Sep-13 28-Oct-13
CON - AREA BCON - AREA BCON - AREA BCON - AREA BCON - AREA BCON - SERVICE LECON - SERVICE LEVEL AREA BCON - SERVICE LEVEL AREA BCON - SERVICE LEVEL AREA BCON - SERVICE LEVEL AREA B
CONABSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-B CON 8 06-Mar-12 14-Mar-12
CONABSL-3210 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-B CON 7 15-Mar-12 26-Mar-12
CONABSL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-B CON 15 27-Mar-12 23-Apr-12
CONABSL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-B CON 9 24-Apr-12 10-May-12
CONABSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-B CON 30 11-May-12 02-Jul-12
CONABSL-3200 UNDERSLAB UTILITIES - SERV LVL AR-B CON 14 03-Jul-12 26-Jul-12
CONABSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-B CON 9 27-Jul-12 10-Aug-12
CONABSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-B CON 18 10-Sep-12 08-Oct-12
CON - LEVEL 1 ARECON - LEVEL 1 AREA BCON - LEVEL 1 AREA BCON - LEVEL 1 AREA BCON - LEVEL 1 AREA B
CONABL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-B CON 10 13-Aug-12 28-Aug-12
CONABSL-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-B CON 8 13-Aug-12 24-Aug-12
CONABL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-B CON 6 30-Aug-12 07-Sep-12
CONABL1-0330 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-B CON 30 19-Mar-13 09-May-13
CONABL1-0320 DRILL/PLACE CAISSONS (EAST BALANCE) - LVL-1 AR-B CON 9 05-Apr-13 19-Apr-13
CONABL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-B CON 9 10-May-13 24-May-13
CONABL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-B CON 9 28-May-13 10-Jun-13
CON - SUPER STRUCON - SUPER STRUCTURE AREA BCON - SUPER STRUCTURE AREA BCON - SUPER STRUCTURE AREA BCON - SUPER STRUCTURE AREA B
CONABSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-B CON 26 11-Jun-13 25-Jul-13
CONABSS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-B CON 10 26-Jul-13 12-Aug-13
CON - LOW ROOFSCON - LOW ROOFS AREA BCON - LOW ROOFS AREA BCON - LOW ROOFS AREA BCON - LOW ROOFS AREA B
CONABLR-0710 PARAPET/BLOCKING/ROOFING - LOW ROOF AR-B CON 15 09-Sep-13 02-Oct-13
CONABLR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF AR-B CON 12 03-Oct-13 22-Oct-13
CONABLR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF AR-B CON 10 23-Oct-13 07-Nov-13
CON - HIGH ROOFCON - HIGH ROOF AREA BCON - HIGH ROOF AREA BCON - HIGH ROOF AREA BCON - HIGH ROOF AREA B
CONABHR-0510 FRAMING @ CLEARSTORY - HIGH ROOF AR-B CON 9 13-Aug-13 27-Aug-13
CONABHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- HIGH ROOF AR-B CON 14 29-Aug-13 20-Sep-13
CONABHR-0755 INSTALL STANDING SEAM ROOF - HIGH ROOF AR-B CON 30 23-Sep-13 08-Nov-13
CONABHR-0888 INSTALL GLAZING @ CLEARSTORY - HIGH ROOF AR-B CON 12 23-Sep-13 09-Oct-13
CON - AREA CCON - AREA CCON - AREA CCON - AREA CCON - AREA CCON - SERVICE LECON - SERVICE LEVEL AREA CCON - SERVICE LEVEL AREA CCON - SERVICE LEVEL AREA CCON - SERVICE LEVEL AREA C
CONACSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-C CON 8 12-Mar-12 20-Mar-12
CONACSL-3210 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-C CON 7 22-Mar-12 02-Apr-12
CONACSL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-C CON 15 16-Apr-12 11-May-12
CONACSL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-C CON 12 12-Jun-12 02-Jul-12
CONACSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-C CON 30 09-Jul-12 28-Aug-12
CONACSL-3200 UNDERSLAB UTILITIES - SERV LVL AR-C CON 11 30-Aug-12 17-Sep-12
CONACSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-C CON 12 18-Sep-12 05-Oct-12
CONACSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-C CON 19 06-Nov-12 07-Dec-12
CON - LEVEL 1 ARECON - LEVEL 1 AREA CCON - LEVEL 1 AREA CCON - LEVEL 1 AREA CCON - LEVEL 1 AREA C
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 20 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 023
Activity ID Activity Name OrigDur
Start Finish
CONACL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-C CON 15 01-Oct-12 23-Oct-12
CONACSL-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-C CON 8 08-Oct-12 19-Oct-12
CONACL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-C CON 8 24-Oct-12 05-Nov-12
CONACL1-0320 DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-C CON 6 10-Dec-12 17-Dec-12
CONACL1-0330 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-C CON 9 18-Dec-12 02-Jan-13
CONACL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-C CON 7 03-Jan-13 11-Jan-13
CONACL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-C CON 7 14-Jan-13 24-Jan-13
CON - SUPER STRUCON - SUPER STRUCTURE AREA CCON - SUPER STRUCTURE AREA CCON - SUPER STRUCTURE AREA CCON - SUPER STRUCTURE AREA C
CONACSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-C CON 24 25-Jan-13 01-Mar-13
CONACSS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-C CON 15 04-Mar-13 26-Mar-13
CON - HIGH ROOFCON - HIGH ROOF AREA CCON - HIGH ROOF AREA CCON - HIGH ROOF AREA CCON - HIGH ROOF AREA C
CONACHR-0510 FRAMING @ CLEARSTORY - HIGH ROOF AR-C CON 12 28-Mar-13 16-Apr-13
CONACHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- LOW ROOF AR-C CON 18 18-Apr-13 20-May-13
CONACHR-0755 INSTALL STANDING SEAM ROOF - LOW ROOF AR-C CON 42 21-May-13 01-Aug-13
CONACHR-0888 INSTALL GLAZING @ CLEARSTORY - LOW ROOF AR-C CON 15 02-Aug-13 27-Aug-13
CON - AREA DCON - AREA DCON - AREA DCON - AREA DCON - AREA DCON - SERVICE LECON - SERVICE LEVEL AREA DCON - SERVICE LEVEL AREA DCON - SERVICE LEVEL AREA DCON - SERVICE LEVEL AREA D
CONADSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-D CON 8 21-Mar-12 29-Mar-12
CONADSL-3210 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-D CON 7 30-Mar-12 10-Apr-12
CONADSL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-D CON 15 24-Apr-12 21-May-12
CONADSL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-D CON 7 03-Jul-12 13-Jul-12
CONADSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-D CON 28 06-Aug-12 20-Sep-12
CONADSL-3200 UNDERSLAB UTILITIES - SERV LVL AR-D CON 12 21-Sep-12 09-Oct-12
CONADSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-D CON 10 10-Oct-12 25-Oct-12
CONADSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-D CON 17 03-Dec-12 28-Dec-12
CON - LEVEL 1 ARECON - LEVEL 1 AREA DCON - LEVEL 1 AREA DCON - LEVEL 1 AREA DCON - LEVEL 1 AREA D
CONADL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-D CON 15 24-Oct-12 16-Nov-12
CONADL1-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-D CON 8 26-Oct-12 08-Nov-12
CONADL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-D CON 8 19-Nov-12 30-Nov-12
CONADL1-0320 DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-D CON 6 31-Dec-12 08-Jan-13
CONADL1-0330 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-D CON 9 09-Jan-13 23-Jan-13
CONADL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-D CON 7 24-Jan-13 01-Feb-13
CONADL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-D CON 8 04-Feb-13 14-Feb-13
CON - SUPER STRUCON - SUPER STRUCTURE AREA DCON - SUPER STRUCTURE AREA DCON - SUPER STRUCTURE AREA DCON - SUPER STRUCTURE AREA D
CONADSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-D CON 23 04-Mar-13 09-Apr-13
CONADSS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-D CON 11 11-Apr-13 29-Apr-13
CON - LOW ROOFSCON - LOW ROOFS AREA DCON - LOW ROOFS AREA DCON - LOW ROOFS AREA DCON - LOW ROOFS AREA D
CONADLR-0710 PARAPET/BLOCKING/ROOFING - LOW ROOF AR-D CON 12 29-May-13 17-Jun-13
CONADLR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF AR-D CON 12 18-Jun-13 08-Jul-13
CONADLR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF AR-D CON 10 09-Jul-13 25-Jul-13
CON - HIGH ROOFCON - HIGH ROOF AREA DCON - HIGH ROOF AREA DCON - HIGH ROOF AREA DCON - HIGH ROOF AREA D
CONADHR-0510 FRAMING @ CLEARSTORY - HIGH ROOF AR-D CON 11 02-May-13 20-May-13
CONADHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- HIGH ROOF AR-D CON 11 21-May-13 07-Jun-13
CONADHR-0755 INSTALL STANDING SEAM ROOF - LOW ROOF AR-D CON 31 10-Jun-13 01-Aug-13
CONADHR-0888 INSTALL GLAZING @ CLEARSTORY - LOW ROOF AR-D CON 13 02-Aug-13 23-Aug-13
CON - AREA ECON - AREA ECON - AREA ECON - AREA ECON - AREA ECON - SUPER STRUCON - SUPER STRUCTURE AREA ECON - SUPER STRUCTURE AREA ECON - SUPER STRUCTURE AREA ECON - SUPER STRUCTURE AREA E
CONAESS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-E CON 25 14-Mar-13 23-Apr-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 21 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 024
Activity ID Activity Name OrigDur
Start Finish
CONAESS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-E CON 6 25-Apr-13 06-May-13
CON - SERVICE LECON - SERVICE LEVEL AREA ECON - SERVICE LEVEL AREA ECON - SERVICE LEVEL AREA ECON - SERVICE LEVEL AREA E
CONAESL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-E CON 8 30-Mar-12 07-Apr-12
CONAESL-3211 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-E CON 7 09-Apr-12 20-Apr-12
CONAESL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-E CON 15 02-Jul-12 27-Jul-12
CONAESL-3210 INSTALL GREASE TRAP AND SANITARY - SERV LVL AR-E CON 10 19-Jul-12 07-Aug-12
CONAESL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-E CON 11 07-Aug-12 24-Aug-12
CONAESL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-E CON 25 30-Aug-12 09-Oct-12
CONAESL-3200 UNDERSLAB UTILITIES - SERV LVL AR-E CON 18 10-Oct-12 08-Nov-12
CONAESL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-E CON 11 09-Nov-12 27-Nov-12
CONAESL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-E CON 19 27-Dec-12 25-Jan-13
CON - LEVEL 1 ARECON - LEVEL 1 AREA ECON - LEVEL 1 AREA ECON - LEVEL 1 AREA ECON - LEVEL 1 AREA E
CONAEL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-E CON 19 14-Nov-12 13-Dec-12
CONAESL-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-E CON 8 29-Nov-12 11-Dec-12
CONAEL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-E CON 7 14-Dec-12 26-Dec-12
CONAEL1-0320 DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-E CON 4 28-Jan-13 31-Jan-13
CONAEL1-0330 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-E CON 8 01-Feb-13 12-Feb-13
CONAEL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-E CON 3 14-Feb-13 19-Feb-13
CONAEL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-E CON 3 20-Feb-13 22-Feb-13
CON - LOW ROOFSCON - LOW ROOFS AREA ECON - LOW ROOFS AREA ECON - LOW ROOFS AREA ECON - LOW ROOFS AREA E
CONAELR-0710 PARAPET/BLOCKING/ROOFING - LOW ROOF AR-E CON 12 03-Jun-13 21-Jun-13
CONAELR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF AR-E CON 12 24-Jun-13 12-Jul-13
CONAELR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF AR-E CON 10 15-Jul-13 30-Jul-13
CON - HIGH ROOFCON - HIGH ROOF AREA ECON - HIGH ROOF AREA ECON - HIGH ROOF AREA ECON - HIGH ROOF AREA E
CONAEHR-0510 FRAMING @ CLEARSTORY - HIGH ROOF AR-E CON 9 07-May-13 21-May-13
CONAEHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- LOW ROOF AR-E CON 5 23-May-13 30-May-13
CONAEHR-0755 INSTALL STANDING SEAM ROOF - LOW ROOF AR-E CON 17 31-May-13 28-Jun-13
CONAEHR-0888 INSTALL GLAZING @ CLEARSTORY - LOW ROOF AR-E CON 11 01-Jul-13 18-Jul-13
CONCOURSE (COCONCOURSE (CON) - EXTERIOR SKINCONCOURSE (CON) - EXTERIOR SKINCONCOURSE (CON) - EXTERIOR SKINCONCOURSE (CON) - EXTERIOR SKINCON - AREA ACON - AREA ACON - AREA ACON - AREA ACON - AREA ACONESAA-0540 ERECT EXTERIOR STUDS/SHEATHING - AR-A CON 15 28-Mar-13 22-Apr-13
CONESAA-0855 INSTALL BLAST PROOF PANELS @ LVL-1 (NORTH ELEV) - AR-A CON 12 28-Mar-13 16-Apr-13
CONESAA-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR-A CON 12 28-Mar-13 16-Apr-13
CONESAA-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-A CON 12 28-Mar-13 16-Apr-13
CONESAA-890 INSTALL EXTERIOR FINISHES (LVL-1 BUMP OUTS) - AR-A CON 15 23-Apr-13 20-May-13
CONESAA-0870 INSTALL CURTAIN WALL (NORTH ELEV) - AR-A CON 20 06-Jun-13 09-Jul-13
CONESAA-870 INSTALL CURTAIN WALL (WEST ELEV) - AR-A CON 20 06-Jun-13 09-Jul-13
CONESAA-880 INSTALL CURTAIN WALL (EAST ELEV) - AR-A CON 20 06-Jun-13 09-Jul-13
CON - AREA BCON - AREA BCON - AREA BCON - AREA BCON - AREA BCONESAB-0540 ERECT EXTERIOR STUDS/SHEATHING - AR-B CON 15 13-Aug-13 06-Sep-13
CONESAB-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR B CON 12 13-Aug-13 03-Sep-13
CONESAB-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-B CON 12 13-Aug-13 03-Sep-13
CONESAB-890 INSTALL EXTERIOR FINISHES (LVL-1 BUMP OUTS) - AR-B CON 15 09-Sep-13 02-Oct-13
CONESAB-0870 INSTALL CURTAIN WALL (WEST ELEV) - AR-B CON 20 19-Sep-13 21-Oct-13
CONESAB-880 INSTALL CURTAIN WALL (EAST ELEV) - AR-B CON 20 19-Sep-13 21-Oct-13
CON - AREA CCON - AREA CCON - AREA CCON - AREA CCON - AREA CCONESAC-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR-C CON 12 18-Apr-13 09-May-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 22 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 025
Activity ID Activity Name OrigDur
Start Finish
CONESAC-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-C CON 12 18-Apr-13 09-May-13
CONESAC-880 INSTALL CURTAIN WALL (EAST ELEV) - AR-C CON 15 10-May-13 04-Jun-13
CONESAC-0870 INSTALL CURTAIN WALL (WEST ELEV) - AR-C CON 15 10-May-13 04-Jun-13
CON - AREA DCON - AREA DCON - AREA DCON - AREA DCON - AREA DCONESAD-0540 ERECT EXTERIOR STUDS/SHEATHING - AR-D CON 15 02-May-13 28-May-13
CONESAD-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR-D CON 12 10-May-13 30-May-13
CONESAD-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-D CON 12 10-May-13 30-May-13
CONESAD-890 INSTALL EXTERIOR FINISHES (LVL-1 BUMP OUTS) - AR-D CON 15 29-May-13 21-Jun-13
CONESAD-900 INSTALL PVS TO CON ENTRY - AR-D CON 35 04-Jun-13 02-Aug-13
CONESAD-0870 INSTALL CURTAIN WALL (WEST ELEV) - AR-D CON 20 11-Jul-13 13-Aug-13
CONESAD-880 INSTALL CURTAIN WALL (EAST ELEV) - AR-D CON 20 11-Jul-13 13-Aug-13
CON - AREA ECON - AREA ECON - AREA ECON - AREA ECON - AREA ECONESAE-0540 ERECT EXTERIOR STUDS/SHEATHING - AR-E CON 15 07-May-13 31-May-13
CONESAE-0855 INSTALL BLAST PROOF PANELS @ LVL-1 (SOUTH ELEV) - AR-E CON 12 31-May-13 20-Jun-13
CONESAE-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR-E CON 12 31-May-13 20-Jun-13
CONESAE-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-E CON 12 31-May-13 20-Jun-13
CONESAE-890 INSTALL EXTERIOR FINISHES (LVL-1 BUMP OUTS) - AR-E CON 20 03-Jun-13 05-Jul-13
CONESAE-0870 INSTALL CURTAIN WALL (SOUTH ELEV) - AR-E CON 20 15-Aug-13 17-Sep-13
CONESAE-870 INSTALL CURTAIN WALL (EAST ELEV) - AR-E CON 20 15-Aug-13 17-Sep-13
CONESAE-880 INSTALL CURTAIN WALL (WEST ELEV) - AR-E CON 20 15-Aug-13 17-Sep-13
CONCOURSE (COCONCOURSE (CON) - INTERIOR BUILDOUTCONCOURSE (CON) - INTERIOR BUILDOUTCONCOURSE (CON) - INTERIOR BUILDOUTCONCOURSE (CON) - INTERIOR BUILDOUTCON - SERVICE CON - SERVICE LEVELCON - SERVICE LEVELCON - SERVICE LEVELCON - SERVICE LEVELCON - SERVICE LECON - SERVICE LEVEL AREA ACON - SERVICE LEVEL AREA ACON - SERVICE LEVEL AREA ACON - SERVICE LEVEL AREA A
CONSLAA-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-A CON 60 31-Oct-12 30-Jan-13
CONSLAA-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-A CON 30 31-Jan-13 14-Mar-13
CONSLAA-8900 PULL 13.2 KVA WIRE - SERV LVL AR-A CON 5 31-Jan-13 06-Feb-13
CONSLAA-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-A CON 31 15-Mar-13 26-Apr-13
CONSLAA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-A CON 15 10-Jul-13 30-Jul-13
CONSLAA-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-A CON 5 31-Jul-13 06-Aug-13
CON - SERVICE LECON - SERVICE LEVEL AREA BCON - SERVICE LEVEL AREA BCON - SERVICE LEVEL AREA BCON - SERVICE LEVEL AREA B
CONSLAB-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-B CON 50 31-Jan-13 11-Apr-13
CONSLAB-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-B CON 30 12-Apr-13 23-May-13
CONSLAB-8900 PULL 13.2 KVA WIRE - SERV LVL AR-B CON 5 12-Apr-13 18-Apr-13
CONSLAB-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-B CON 14 24-May-13 13-Jun-13
CONSLAB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-B CON 15 22-Oct-13 12-Nov-13
CONSLAB-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-B CON 5 13-Nov-13 19-Nov-13
CON - SERVICE LECON - SERVICE LEVEL AREA CCON - SERVICE LEVEL AREA CCON - SERVICE LEVEL AREA CCON - SERVICE LEVEL AREA C
CONSLAC-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-C CON 55 12-Apr-13 28-Jun-13
CONSLAC-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-C CON 30 01-Jul-13 12-Aug-13
CONSLAC-8900 PULL 13.2 KVAWIRE - SERV LVL AR-C CON 5 01-Jul-13 08-Jul-13
CONSLAC-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-C CON 18 13-Aug-13 06-Sep-13
CONSLAC-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-C CON 5 09-Sep-13 13-Sep-13
CONSLAC-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-C CON 5 16-Sep-13 20-Sep-13
CON - SERVICE LECON - SERVICE LEVEL AREA DCON - SERVICE LEVEL AREA DCON - SERVICE LEVEL AREA DCON - SERVICE LEVEL AREA D
CONSLAD-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-D CON 47 01-Jul-13 05-Sep-13
CONSLAD-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-D CON 30 06-Sep-13 17-Oct-13
CONSLAD-8900 PULL 13.2 KVAWIRE - SERV LVL AR-D CON 5 06-Sep-13 12-Sep-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 23 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 026
Activity ID Activity Name OrigDur
Start Finish
CONSLAD-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-D CON 14 18-Oct-13 07-Nov-13
CONSLAD-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-D CON 15 08-Nov-13 02-Dec-13
CONSLAD-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-D CON 5 03-Dec-13 09-Dec-13
CON - SERVICE LECON - SERVICE LEVEL AREA ECON - SERVICE LEVEL AREA ECON - SERVICE LEVEL AREA ECON - SERVICE LEVEL AREA E
CONSLAE-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-E CON 68 06-Sep-13 13-Dec-13
CONSLAE-8900 PULL 13.2 KVA WIRE - SERV LVL AR-E CON 5 16-Dec-13 20-Dec-13
CONSLAE-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-E CON 30 16-Dec-13 29-Jan-14
CONSLAE-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-E CON 23 30-Jan-14 04-Mar-14
CONSLAE-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-E CON 15 05-Mar-14 25-Mar-14
CONSLAE-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-E CON 5 26-Mar-14 01-Apr-14
CON - SERVICCON - SERVICE LEVEL AREA E - KITCHENCON - SERVICE LEVEL AREA E - KITCHENCON - SERVICE LEVEL AREA E - KITCHENCON - SERVICE LEVEL AREA E - KITCHEN
CONSLKI-1516 R-I OVERHEAD MEP/FIRE PRO/HOODS - SERV LVL KITCHEN AR-E CON 35 30-Jan-14 20-Mar-14
CONSLKI-0910 FRAMING/INWALL ROUGH - SERV LVL KITCHEN AR-E CON 15 21-Mar-14 10-Apr-14
CONSLKI-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL KITCHEN AR-E CON 15 11-Apr-14 01-May-14
CONSLKI-0990 INSTALL INTERIOR FINISHES - SERV LVL KITCHEN AR-E CON 20 02-May-14 30-May-14
CONSLKI-1120 INSTALL WALK-IN COOLERS/FREEZERS- SERV LVL KITCHEN AR-E CON 10 02-May-14 15-May-14
CONSLKI-1110 SET/CONNECT/TEST/INSP KITCHEN EQUIP- SERV LVL KITCHEN AR-E CON 20 02-Jun-14 27-Jun-14
CONSLKI-8880 CLEAN-UP/PRE PUNCH - SERV LVL KITCHEN AR-E CON 15 30-Jun-14 21-Jul-14
CON - CONCOUCON - CONCOURSE BUMPOUT AREASCON - CONCOURSE BUMPOUT AREASCON - CONCOURSE BUMPOUT AREASCON - CONCOURSE BUMPOUT AREASCON - DININGCON - DININGCON - DININGCON - DININGCON - DINING
CONL1DI-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 DINING CON 18 19-Aug-14 12-Sep-14
CONL1DI-0910 FRAMING/INWALL ROUGH - LVL-1 AR-D DINING CON 17 15-Sep-14 07-Oct-14
CONL1DI-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D DINING CON 17 08-Oct-14 31-Oct-14
CONL1DI-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D DINING CON 35 03-Nov-14 23-Dec-14
CONL1DI-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-D DINING CON 15 24-Dec-14 15-Jan-15
CON - AUDITORIUCON - AUDITORIUMCON - AUDITORIUMCON - AUDITORIUMCON - AUDITORIUM
CONL1AU-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AUDITRM CON 25 19-Aug-14 23-Sep-14
CONL1AU-0910 FRAMING/INWALL ROUGH - LVL-1 AUDITRM CON 17 17-Sep-14 09-Oct-14
CONL1AU-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AUDITRM CON 17 01-Oct-14 24-Oct-14
CONL1AU-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AUDITRM CON 30 27-Oct-14 09-Dec-14
CONL1AU-8880 CLEAN-UP/PRE PUNCH - LVL-1 AUDITRM CON 10 10-Dec-14 23-Dec-14
CON - CHAPELCON - CHAPELCON - CHAPELCON - CHAPELCON - CHAPEL
CONL1CH-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B CHAPEL CON 20 04-Feb-14 04-Mar-14
CONL1CH-0910 FRAMING/INWALL ROUGH - LVL-1 AR-B CHAPEL CON 15 05-Mar-14 25-Mar-14
CONL1CH-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-B CHAPEL CON 15 26-Mar-14 15-Apr-14
CONL1CH-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-B CHAPEL CON 25 16-Apr-14 20-May-14
CONL1CH-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-B CHAPEL CON 10 21-May-14 04-Jun-14
CON - AREA D RESCON - AREA D RESTROOMSCON - AREA D RESTROOMSCON - AREA D RESTROOMSCON - AREA D RESTROOMS
CONL1DR-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-D RESTRMS CON 20 24-Jun-14 22-Jul-14
CONL1DR-0910 FRAMING/INWALL ROUGH - LVL-1 AR-D RESTRMS CON 15 23-Jul-14 12-Aug-14
CONL1DR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D RESTRMS CON 12 13-Aug-14 28-Aug-14
CONL1DR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D RESTRMS CON 30 29-Aug-14 10-Oct-14
CONL1DR-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-D RESTRMS CON 10 13-Oct-14 27-Oct-14
CON - COFFEE SHOCON - COFFEE SHOPCON - COFFEE SHOPCON - COFFEE SHOPCON - COFFEE SHOP
CONL1CS-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 COFFEE SHOP CON 20 06-Jan-14 03-Feb-14
CONL1CS-0910 FRAMING/INWALL ROUGH - LVL-1 COFFEE SHOP CON 12 04-Feb-14 20-Feb-14
CONL1CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 COFFEE SHOP CON 12 21-Feb-14 10-Mar-14
CONL1CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 COFFEE SHOP CON 30 11-Mar-14 21-Apr-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 24 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 027
Activity ID Activity Name OrigDur
Start Finish
CONL1CS-8880 CLEAN-UP/PRE PUNCH - LVL-1 COFFEE SHOP CON 15 22-Apr-14 12-May-14
CON - SOUTH LOBCON - SOUTH LOBBYCON - SOUTH LOBBYCON - SOUTH LOBBYCON - SOUTH LOBBY
CONL1SL-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 SOUTH LOBBY CON 22 19-Aug-14 18-Sep-14
CONL1SL-0910 FRAMING/INWALL ROUGH - LVL-1 SOUTH LOBBY CON 18 17-Sep-14 10-Oct-14
CONL1SL-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SOUTH LOBBY CON 16 01-Oct-14 23-Oct-14
CONL1SL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SOUTH LOBBY CON 40 13-Oct-14 10-Dec-14
CONL1SL-8880 CLEAN-UP/PRE PUNCH - LVL-1 SOUTH LOBBY CON 15 11-Dec-14 02-Jan-15
CON - NORTH LOBCON - NORTH LOBBYCON - NORTH LOBBYCON - NORTH LOBBYCON - NORTH LOBBY
CONL1NL-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 NORTH LOBBY CON 25 06-Jan-14 11-Feb-14
CONL1NL-0910 FRAMING/INWALL ROUGH - LVL-1 NORTH LOBBY CON 20 04-Feb-14 04-Mar-14
CONL1NL-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 NORTH LOBBY CON 5 05-Mar-14 11-Mar-14
CONL1NL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NORTH LOBBY CON 32 10-Mar-14 22-Apr-14
CONL1NL-8880 CLEAN-UP/PRE PUNCH - LVL-1 NORTH LOBBY CON 5 23-Apr-14 29-Apr-14
CON - AREA A RESCON - AREA A RESTROOMSCON - AREA A RESTROOMSCON - AREA A RESTROOMSCON - AREA A RESTROOMS
CONL1AR-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-A RESTRMS CON 20 06-Jan-14 03-Feb-14
CONL1AR-0910 FRAMING/INWALL ROUGH - LVL-1 AR-A RESTRMS CON 15 04-Feb-14 25-Feb-14
CONL1AR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-A RESTRMS CON 12 26-Feb-14 13-Mar-14
CONL1AR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-A RESTRMS CON 30 14-Mar-14 24-Apr-14
CONL1AR-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-A RESTRMS CON 10 25-Apr-14 08-May-14
CON - SERVINGCON - SERVINGCON - SERVINGCON - SERVINGCON - SERVING
CONL1SE-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 SERVING CON 25 19-Aug-14 23-Sep-14
CONL1SE-0910 FRAMING/INWALL ROUGH - LVL-1 SERVING CON 6 30-Sep-14 07-Oct-14
CONL1SE-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SERVING CON 18 14-Oct-14 07-Nov-14
CONL1SE-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SERVING CON 30 10-Nov-14 23-Dec-14
CONL1SE-8880 CLEAN-UP/PRE PUNCH - LVL-1 SERVING CON 10 24-Dec-14 08-Jan-15
CON - AREA B RESCON - AREA B RESTROOMSCON - AREA B RESTROOMSCON - AREA B RESTROOMSCON - AREA B RESTROOMS
CONL1BR-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B RESTRMS CON 20 04-Feb-14 04-Mar-14
CONL1BR-0910 FRAMING/INWALL ROUGH - LVL-1 AR-B RESTRMS CON 15 05-Mar-14 25-Mar-14
CONL1BR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-B RESTRMS CON 12 26-Mar-14 10-Apr-14
CONL1BR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-B RESTRMS CON 30 11-Apr-14 22-May-14
CONL1BR-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-B RESTRMS CON 10 23-May-14 06-Jun-14
CON - AREA E RESCON - AREA E RESTROOMSCON - AREA E RESTROOMSCON - AREA E RESTROOMSCON - AREA E RESTROOMS
CONL1ER-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-E RESTRMS CON 20 19-Aug-14 16-Sep-14
CONL1ER-0910 FRAMING/INWALL ROUGH - LVL-1 AR-E RESTRMS CON 15 17-Sep-14 07-Oct-14
CONL1ER-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D AR-E RESTRMS CON 12 08-Oct-14 24-Oct-14
CONL1ER-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D AR-E RESTRMS CON 30 27-Oct-14 09-Dec-14
CONL1ER-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-D AR-E RESTRMS CON 10 10-Dec-14 23-Dec-14
CON - CONCOUCON - CONCOURSE (general seating)CON - CONCOURSE (general seating)CON - CONCOURSE (general seating)CON - CONCOURSE (general seating)CON - CONCOURSCON - CONCOURSE HIGH BAY WORK-1CON - CONCOURSE HIGH BAY WORK-1CON - CONCOURSE HIGH BAY WORK-1CON - CONCOURSE HIGH BAY WORK-1
CON - CONCOCON - CONCOURSE AREA A - HIGH BAYCON - CONCOURSE AREA A - HIGH BAYCON - CONCOURSE AREA A - HIGH BAYCON - CONCOURSE AREA A - HIGH BAY
CONHBAA-15 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-A CON 15 23-Sep-13 11-Oct-13
CONHBAA-09 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-A CON 15 14-Oct-13 04-Nov-13
CONHBAA-092 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-A CON 15 05-Nov-13 27-Nov-13
CONHBAA-099 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-A CON 15 28-Nov-13 18-Dec-13
CONHBAA-888 CLEAN-UP/PRE PUNCH/FINAL PUNCH- HIGH BAY AR-A CON 10 19-Dec-13 03-Jan-14
CONHBAA-889 TEAR DOWN STAGE - HIGH BAY AR-A CON 7 06-Jan-14 14-Jan-14
CON - CONCOCON - CONCOURSE AREA B - HIGH BAYCON - CONCOURSE AREA B - HIGH BAYCON - CONCOURSE AREA B - HIGH BAYCON - CONCOURSE AREA B - HIGH BAY
CONHBAB-151 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-B CON 15 03-Oct-13 24-Oct-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 25 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 028
Activity ID Activity Name OrigDur
Start Finish
CONHBAB-091 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-B CON 15 25-Oct-13 15-Nov-13
CONHBAB-092 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-B CON 15 18-Nov-13 09-Dec-13
CONHBAB-099 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-B CON 15 10-Dec-13 31-Dec-13
CONHBAB-888 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-B CON 10 02-Jan-14 15-Jan-14
CONHBAB-889 TEAR DOWN STAGE - HIGH BAY AR-B CON 7 16-Jan-14 27-Jan-14
CON - CONCOCON - CONCOURSE AREA C - HIGH BAYCON - CONCOURSE AREA C - HIGH BAYCON - CONCOURSE AREA C - HIGH BAYCON - CONCOURSE AREA C - HIGH BAY
CONHBAC-151 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-C CON 15 15-Jan-14 05-Feb-14
CONHBAC-091 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-C CON 15 06-Feb-14 27-Feb-14
CONHBAC-092 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-C CON 18 28-Feb-14 25-Mar-14
CONHBAC-099 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-C CON 15 26-Mar-14 15-Apr-14
CONHBAC-888 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-C CON 10 16-Apr-14 29-Apr-14
CONHBAC-889 TEAR DOWN STAGE - HIGH BAY AR-C CON 7 30-Apr-14 08-May-14
CON - CONCOCON - CONCOURSE AREA D - HIGH BAYCON - CONCOURSE AREA D - HIGH BAYCON - CONCOURSE AREA D - HIGH BAYCON - CONCOURSE AREA D - HIGH BAY
CONHBAD-15 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-D CON 15 28-Jan-14 18-Feb-14
CONHBAD-09 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-D CON 15 19-Feb-14 11-Mar-14
CONHBAD-092 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-D CON 16 12-Mar-14 02-Apr-14
CONHBAD-099 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-D CON 15 03-Apr-14 23-Apr-14
CONHBAD-888 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-D CON 10 24-Apr-14 07-May-14
CONHBAD-889 TEAR DOWN STAGE - HIGH BAY AR-D CON 7 08-May-14 16-May-14
CON - CONCOCON - CONCOURSE AREA E - HIGH BAYCON - CONCOURSE AREA E - HIGH BAYCON - CONCOURSE AREA E - HIGH BAYCON - CONCOURSE AREA E - HIGH BAY
CONHBAE-151 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-E CON 15 09-May-14 30-May-14
CONHBAE-091 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-E CON 15 02-Jun-14 20-Jun-14
CONHBAE-092 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-E CON 15 23-Jun-14 14-Jul-14
CONHBAE-099 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-E CON 15 15-Jul-14 04-Aug-14
CONHBAE-888 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-E CON 10 05-Aug-14 18-Aug-14
CONHBAE-889 TEAR DOWN STAGE - HIGH BAY AR-E CON 7 19-Aug-14 27-Aug-14
CON - CONCOURSCON - CONCOURSE LEVEL 1CON - CONCOURSE LEVEL 1CON - CONCOURSE LEVEL 1CON - CONCOURSE LEVEL 1
CON - CONCOCON - CONCOURSE AREA A - LEVEL 1CON - CONCOURSE AREA A - LEVEL 1CON - CONCOURSE AREA A - LEVEL 1CON - CONCOURSE AREA A - LEVEL 1
CONL1AA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-A CON 20 06-Jan-14 03-Feb-14
CONL1AA-0910 FRAMING/ ROUGH-IN - LVL-1 AR-A CON 18 04-Feb-14 28-Feb-14
CONL1AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-A CON 12 03-Mar-14 18-Mar-14
CONL1AA-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-A CON 60 19-Mar-14 11-Jun-14
CONL1AA-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH- LVL-1 AR-A CON 10 12-Jun-14 25-Jun-14
CON - CONCOCON - CONCOURSE AREA B - LEVEL 1CON - CONCOURSE AREA B - LEVEL 1CON - CONCOURSE AREA B - LEVEL 1CON - CONCOURSE AREA B - LEVEL 1
CONL1AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B CON 20 04-Feb-14 04-Mar-14
CONL1AB-0910 FRAMING/ ROUGH-IN - LVL-1 AR-B CON 18 05-Mar-14 28-Mar-14
CONL1AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-B CON 12 31-Mar-14 15-Apr-14
CONL1AB-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-B CON 60 16-Apr-14 10-Jul-14
CONL1AB-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-B CON 10 11-Jul-14 24-Jul-14
CON - CONCOCON - CONCOURSE AREA C - LEVEL 1CON - CONCOURSE AREA C - LEVEL 1CON - CONCOURSE AREA C - LEVEL 1CON - CONCOURSE AREA C - LEVEL 1
CONL1AC-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-C CON 25 19-May-14 23-Jun-14
CONL1AC-0910 FRAMING/ ROUGH-IN - LVL-1 AR-C CON 20 24-Jun-14 22-Jul-14
CONL1AC-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-C CON 15 23-Jul-14 12-Aug-14
CONL1AC-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-C CON 65 13-Aug-14 14-Nov-14
CONL1AC-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-C CON 10 17-Nov-14 01-Dec-14
CON - CONCOCON - CONCOURSE AREA D - LEVEL 1CON - CONCOURSE AREA D - LEVEL 1CON - CONCOURSE AREA D - LEVEL 1CON - CONCOURSE AREA D - LEVEL 1
CONL1AD-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-D CON 20 24-Jun-14 22-Jul-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 26 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 029
Activity ID Activity Name OrigDur
Start Finish
CONL1AD-0910 FRAMING/ ROUGH-IN - LVL-1 AR-D CON 18 23-Jul-14 15-Aug-14
CONL1AD-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D CON 12 18-Aug-14 03-Sep-14
CONL1AD-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-D CON 60 04-Sep-14 01-Dec-14
CONL1AD-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-D CON 10 02-Dec-14 15-Dec-14
CON - CONCOCON - CONCOURSE AREA E - LEVEL 1CON - CONCOURSE AREA E - LEVEL 1CON - CONCOURSE AREA E - LEVEL 1CON - CONCOURSE AREA E - LEVEL 1
CONL1AE-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-E CON 20 19-Aug-14 16-Sep-14
CONL1AE-0910 FRAMING/ ROUGH-IN - LVL-1 AR-E CON 18 17-Sep-14 10-Oct-14
CONL1AE-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-E CON 12 13-Oct-14 29-Oct-14
CONL1AE-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-E CON 35 30-Oct-14 19-Dec-14
CONL1AE-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-E CON 10 22-Dec-14 06-Jan-15
CON - CONCOURSCON - CONCOURSE LEVEL 2CON - CONCOURSE LEVEL 2CON - CONCOURSE LEVEL 2CON - CONCOURSE LEVEL 2
CON - CONCOCON - CONCOURSE AREA A - LEVEL 2CON - CONCOURSE AREA A - LEVEL 2CON - CONCOURSE AREA A - LEVEL 2CON - CONCOURSE AREA A - LEVEL 2
CONL2AA-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-A CON 512 10-Dec-12 23-Dec-14
CONL2AA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-A CON 25 18-Sep-13 23-Oct-13
CONL2AA-0910 FRAMING/ ROUGH-IN - LVL-2 AR-A CON 25 24-Oct-13 29-Nov-13
CONL2AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-A CON 30 02-Dec-13 14-Jan-14
CONL2AA-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-A CON 5 15-Jan-14 22-Jan-14
CON - CONCOCON - CONCOURSE AREA B - LEVEL 2CON - CONCOURSE AREA B - LEVEL 2CON - CONCOURSE AREA B - LEVEL 2CON - CONCOURSE AREA B - LEVEL 2
CONL2AB-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-B CON 512 10-Dec-12 23-Dec-14
CONL2AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-B CON 20 24-Oct-13 22-Nov-13
CONL2AB-0910 FRAMING/ ROUGH-IN - LVL-2 AR-B CON 20 25-Nov-13 20-Dec-13
CONL2AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-B CON 25 23-Dec-13 29-Jan-14
CONL2AB-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-B CON 5 30-Jan-14 05-Feb-14
CON - CONCOCON - CONCOURSE AREA C - LEVEL 2CON - CONCOURSE AREA C - LEVEL 2CON - CONCOURSE AREA C - LEVEL 2CON - CONCOURSE AREA C - LEVEL 2
CONL2AC-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-C CON 512 10-Dec-12 23-Dec-14
CONL2AC-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-C CON 20 25-Nov-13 20-Dec-13
CONL2AC-0910 FRAMING/ ROUGH-IN - LVL-2 AR-C CON 20 23-Dec-13 22-Jan-14
CONL2AC-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-C CON 25 23-Jan-14 27-Feb-14
CONL2AC-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-C CON 5 28-Feb-14 06-Mar-14
CON - CONCOCON - CONCOURSE AREA D - LEVEL 2CON - CONCOURSE AREA D - LEVEL 2CON - CONCOURSE AREA D - LEVEL 2CON - CONCOURSE AREA D - LEVEL 2
CONL2AD-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-D CON 512 10-Dec-12 23-Dec-14
CONL2AD-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-D CON 20 23-Dec-13 22-Jan-14
CONL2AD-0910 FRAMING/ ROUGH-IN - LVL-2 AR-D CON 20 23-Jan-14 20-Feb-14
CONL2AD-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-D CON 25 21-Feb-14 27-Mar-14
CONL2AD-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-D CON 5 28-Mar-14 03-Apr-14
CON - CONCOCON - CONCOURSE AREA E - LEVEL 2CON - CONCOURSE AREA E - LEVEL 2CON - CONCOURSE AREA E - LEVEL 2CON - CONCOURSE AREA E - LEVEL 2
CONL2AE-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-E CON 20 23-Jan-14 20-Feb-14
CONL2AE-0910 FRAMING/ ROUGH-IN - LVL-2 AR-E CON 20 21-Feb-14 20-Mar-14
CONL2AE-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-E CON 25 21-Mar-14 24-Apr-14
CONL2AE-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-E CON 20 11-Apr-14 08-May-14
CONL2AE-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-E CON 5 09-May-14 15-May-14
CON - CONCOURSCON - CONCOURSE LEVEL 3CON - CONCOURSE LEVEL 3CON - CONCOURSE LEVEL 3CON - CONCOURSE LEVEL 3
CON - CONCOCON - CONCOURSE AREA A - LEVEL 3CON - CONCOURSE AREA A - LEVEL 3CON - CONCOURSE AREA A - LEVEL 3CON - CONCOURSE AREA A - LEVEL 3
CONL3AA-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-A CON 512 10-Dec-12 23-Dec-14
CONL3AA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-A CON 20 18-Sep-13 15-Oct-13
CONL3AA-0910 FRAMING/ ROUGH-IN - LVL-3 AR-A CON 20 16-Oct-13 14-Nov-13
CONL3AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-A CON 25 15-Nov-13 20-Dec-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 27 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 030
Activity ID Activity Name OrigDur
Start Finish
CONL3AA-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-A CON 5 23-Dec-13 30-Dec-13
CON - CONCOCON - CONCOURSE AREA B - LEVEL 3CON - CONCOURSE AREA B - LEVEL 3CON - CONCOURSE AREA B - LEVEL 3CON - CONCOURSE AREA B - LEVEL 3
CONL3AB-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-B CON 512 10-Dec-12 23-Dec-14
CONL3AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-B CON 20 16-Oct-13 14-Nov-13
CONL3AB-0910 FRAMING/ ROUGH-IN - LVL-3 AR-B CON 20 15-Nov-13 13-Dec-13
CONL3AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-B CON 25 16-Dec-13 22-Jan-14
CONL3AB-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-B CON 5 23-Jan-14 29-Jan-14
CON - CONCOCON - CONCOURSE AREA C - LEVEL 3CON - CONCOURSE AREA C - LEVEL 3CON - CONCOURSE AREA C - LEVEL 3CON - CONCOURSE AREA C - LEVEL 3
CONL3AC-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-C CON 512 10-Dec-12 23-Dec-14
CONL3AC-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-C CON 20 15-Nov-13 13-Dec-13
CONL3AC-0910 FRAMING/ ROUGH-IN - LVL-3 AR-C CON 20 16-Dec-13 14-Jan-14
CONL3AC-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-C CON 25 15-Jan-14 20-Feb-14
CONL3AC-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-C CON 5 21-Feb-14 27-Feb-14
CON - CONCOCON - CONCOURSE AREA D - LEVEL 3CON - CONCOURSE AREA D - LEVEL 3CON - CONCOURSE AREA D - LEVEL 3CON - CONCOURSE AREA D - LEVEL 3
CONL3AD-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-D CON 512 10-Dec-12 23-Dec-14
CONL3AD-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-D CON 20 16-Dec-13 14-Jan-14
CONL3AD-0910 FRAMING/ ROUGH-IN - LVL-3 AR-D CON 20 15-Jan-14 13-Feb-14
CONL3AD-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-D CON 25 14-Feb-14 20-Mar-14
CONL3AD-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-D CON 5 21-Mar-14 27-Mar-14
CON - CONCOCON - CONCOURSE AREA E - LEVEL 3CON - CONCOURSE AREA E - LEVEL 3CON - CONCOURSE AREA E - LEVEL 3CON - CONCOURSE AREA E - LEVEL 3
CONL3AE-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-E CON 20 15-Jan-14 13-Feb-14
CONL3AE-0910 FRAMING/ ROUGH-IN - LVL-3 AR-E CON 20 14-Feb-14 13-Mar-14
CONL3AE-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-E CON 25 14-Mar-14 17-Apr-14
CONL3AE-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-E CON 20 11-Apr-14 08-May-14
CONL3AE-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-E CON 5 09-May-14 15-May-14
CON - CONCOURSCON - CONCOURSE ALL LEVELSCON - CONCOURSE ALL LEVELSCON - CONCOURSE ALL LEVELSCON - CONCOURSE ALL LEVELS
CONALAL-1402 INSTALL SERVICE ELEVATOR - AREA A CON 60 28-Nov-13 25-Feb-14
CONALAL-1401 INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 6-7) - AREA A CON 25 15-Jan-14 20-Feb-14
CONALAL-1403 INSTALL ELEVATORS SHAFT WALLS (GRIDLINE 15-16) - AREA B CON 25 21-Feb-14 27-Mar-14
CONALAL-1425 INSTALL ELEVATOR CAR (GRIDLINE 6-7) - AREA A CON 60 23-Apr-14 17-Jul-14
CONALAL-1404 INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 20-21) - AREA C CON 25 09-May-14 13-Jun-14
CONALAL-1435 INSTALL ELEVATORS CAR (GRIDLINE 15-16) - AREA B CON 60 29-May-14 21-Aug-14
CONALAL-1405 INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 25-26) - AREA C CON 25 16-Jun-14 21-Jul-14
CONALAL-1415 INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 28-29)- AREA D CON 25 22-Jul-14 25-Aug-14
CONALAL-1455 INSTALL ELEVATOR CAR (GRIDLINE 25-26) - AREA C CON 60 18-Sep-14 15-Dec-14
CONALAL-1445 INSTALL ELEVATOR CAR (GRIDLINE 20-21) - AREA C CON 60 24-Oct-14 22-Jan-15
CONALAL-1465 INSTALL ELEVATOR CAR (GRIDLINE 28-29)- AREA D CON 60 02-Dec-14 27-Feb-15
CON - COMMISSCON - COMMISSIONINGCON - COMMISSIONINGCON - COMMISSIONINGCON - COMMISSIONINGCONALCO-1592 TEST & BALANCE - CON 20 24-Dec-14 23-Jan-15
CONALCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - CON 15 24-Dec-14 15-Jan-15
CONALCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - CON 20 16-Jan-15 16-Feb-15
CONALCO-1596 FUNCTIONAL TESTING/CORRECTIONS - CON 15 16-Jan-15 06-Feb-15
CONALCO-1599 BUILDING FLUSH - ALL LVLS CON 35 17-Feb-15 23-Mar-15
ENERGY CENTENERGY CENTER & WAREHOUSE (ENC)ENERGY CENTER & WAREHOUSE (ENC)ENERGY CENTER & WAREHOUSE (ENC)ENERGY CENTER & WAREHOUSE (ENC)ENERGY CENTERENERGY CENTER & WAREHOUSE (ENC) - STRUCTUREENERGY CENTER & WAREHOUSE (ENC) - STRUCTUREENERGY CENTER & WAREHOUSE (ENC) - STRUCTUREENERGY CENTER & WAREHOUSE (ENC) - STRUCTUREENC - PIPE GALENC - PIPE GALLERYENC - PIPE GALLERYENC - PIPE GALLERYENC - PIPE GALLERYENCPGPG-3100 MASS EXCAVATION/RECONDITIONING - PIPE GALLERY ENC 25 07-Mar-12 04-Apr-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 28 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 031
Activity ID Activity Name OrigDur
Start Finish
ENCPGPG-0320 DRILL/PLACE CAISSONS - PIPE GALLERY ENC 6 05-Apr-12 16-Apr-12
ENCPGPG-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY ENC 15 17-Apr-12 14-May-12
ENCPGPG-3200 UNDERSLAB UTILITIES - PIPE GALLERY ENC 8 15-May-12 29-May-12
ENCPGPG-0380 FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY ENC 5 30-May-12 05-Jun-12
ENCPGPG-3210 PERM DRAINS/BACKFILL FOUNDATION WALLS - PIPE GALLERY ENC 3 30-Jul-12 03-Aug-12
ENC - SERVICE ENC - SERVICE LEVELENC - SERVICE LEVELENC - SERVICE LEVELENC - SERVICE LEVELENCSLSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL ENC 25 07-Mar-12 04-Apr-12
ENCSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL ENC 20 17-Apr-12 22-May-12
ENCSLSL-0330 FORM/PLACE PIER CAPS/CORES/ WALLS/COLUMNS - SERV LVL ENC 60 26-Apr-12 09-Aug-12
ENCSLSL-0510 ERECT STRUCTURAL STEEL/DECK (PIPE BSMT LID)- SERV LVL ENC 8 10-Jul-12 23-Jul-12
ENCSLSL-3200 UNDERSLAB UTILITIES - SERV LVL ENC 28 12-Jul-12 28-Aug-12
ENCSLSL-0322 FORM/REIN/R-I/PLACE TOPPING SLAB (PIPE BSMT LID) - SERV LVL ENC 3 24-Jul-12 27-Jul-12
ENCSLSL-0720 SPRAY ON FIREPROOFING - SERV LVL ENC 5 30-Jul-12 07-Aug-12
ENCSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL ENC 12 17-Aug-12 06-Sep-12
ENCSLSL-0540 ERECT EXTERIOR STUDS/SHEATHING - SERV LVL ENC 15 02-Oct-12 24-Oct-12
ENCSLSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL ENC 15 02-Oct-12 24-Oct-12
ENC - ALL LEVEENC - ALL LEVELSENC - ALL LEVELSENC - ALL LEVELSENC - ALL LEVELSENCALAL-0510 ERECT STRUCTURAL STEEL/DECK (LEVEL 1(incl. deck) - PH ROOF) - ALL LEVELS ENC 20 10-Aug-12 13-Sep-12
ENCALAL-1426 ERECT/DETAIL METAL DECK (LEVEL 2 - PH ROOF) - LVLS 2 - PH ROOF) ENC 10 14-Sep-12 01-Oct-12
ENC - LEVEL 1ENC - LEVEL 1ENC - LEVEL 1ENC - LEVEL 1ENC - LEVEL 1ENCL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 ENC 10 14-Sep-12 01-Oct-12
ENCL1L1-1660 FORM/REINFORCE/PLACE EQUIPMENT PADS - LVL-1 ENC 5 27-Sep-12 03-Oct-12
ENCL1L1-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-1 ENC 15 02-Oct-12 24-Oct-12
ENCL1L1-0720 SPRAY ON FIREPROOFING - LVL-1 ENC 7 18-Oct-12 26-Oct-12
ENC - LOW ROOENC - LOW ROOFENC - LOW ROOFENC - LOW ROOFENC - LOW ROOFENCLRLR-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LOW ROOF ENC 10 02-Oct-12 16-Oct-12
ENCLRLR-3210 SET COOLING TOWERS - LOW ROOF ENC 5 17-Oct-12 23-Oct-12
ENCLRLR-0750 APPLY WATERPROOFING - LOW ROOF ENC 7 01-Nov-12 13-Nov-12
ENCLRLR-0720 SPRAY ON FIREPROOFING - LOW ROOF ENC 5 01-Nov-12 08-Nov-12
ENCLRLR-2600 INSTALL GREEN ROOF SYSTEM - LOW ROOF ENC 15 26-Jul-13 20-Aug-13
ENC - HIGH ROENC - HIGH ROOFENC - HIGH ROOFENC - HIGH ROOFENC - HIGH ROOFENCHRHR-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - HIGH ROOF ENC 5 24-Oct-12 30-Oct-12
ENCHRHR-0720 SPRAY ON FIREPROOFING - HIGH ROOF ENC 3 09-Nov-12 14-Nov-12
ENCHRHR-0750 APPLY ROOFING - HIGH ROOF ENC 10 15-Nov-12 30-Nov-12
ENCHRHR-2600 SET/CONNECT PHOTOVOLTAIC PANELS - HIGH ROOF ENC 50 15-Mar-13 10-Jun-13
ENC - WATER TAENC - WATER TANK STORAGEENC - WATER TANK STORAGEENC - WATER TANK STORAGEENC - WATER TANK STORAGEENCTSTS-3100 MASS EXCAVATION/RECONDITIONING - WATER TANK ENC 5 07-May-13 11-May-13
ENCTSTS-3200 UNDERSLAB UTILITIES- WATER TANK ENC 15 30-May-13 24-Jun-13
ENCTSTS-0380 FORM/PLACE/FINISH/TENSION SLAB ON GRADE - WATER TANK ENC 7 25-Jun-13 05-Jul-13
ENCTSTS-0390 FORM/PLACE/FINISH WALLS/COLUMNS/CURBS - WATER TANK ENC 20 08-Jul-13 09-Aug-13
ENCTSTS-3220 FORM/PLACE/FINISH/TENSION LID - WATER TANK ENC 53 12-Aug-13 07-Nov-13
ENCTRTR-0750 APPLY WATERPROOFING - WATER TANK ENC 20 08-Nov-13 11-Dec-13
ENC - FUEL TANENC - FUEL TANKSENC - FUEL TANKSENC - FUEL TANKSENC - FUEL TANKSENCFTFT-3100 MASS EXCAVATION/PREP GRADE - FUEL TANK ENC 13 12-Dec-13 27-Dec-13
ENCFTFT-0378 FORM/PLACE/FINISH/TENSION SLAB ON GRADE - FUEL TANK ENC 18 30-Dec-13 27-Jan-14
ENCFTFT-0380 SET TANKS- FUEL TANK ENC 3 28-Jan-14 30-Jan-14
ENCFTFT-3200 INSTALL FUEL TANK PIPING - FUEL TANK ENC 25 31-Jan-14 10-Mar-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 29 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 032
Activity ID Activity Name OrigDur
Start Finish
ENCFTFT-0390 TEST FUEL TANKS - FUEL TANK ENC 5 11-Mar-14 18-Mar-14
ENCFTFT-3220 BACKFILL - FUEL TANK ENC 20 20-Mar-14 22-Apr-14
ENERGY CENTERENERGY CENTER & WAREHOUSE (ENC) - EXTERIOR SKINENERGY CENTER & WAREHOUSE (ENC) - EXTERIOR SKINENERGY CENTER & WAREHOUSE (ENC) - EXTERIOR SKINENERGY CENTER & WAREHOUSE (ENC) - EXTERIOR SKINENC - NORTH EENC - NORTH ELEVATIONENC - NORTH ELEVATIONENC - NORTH ELEVATIONENC - NORTH ELEVATIONENCESNE-0440 LAY STACKED STONE - NORTH ELEV ENC 25 25-Oct-12 06-Dec-12
ENCESNE-870 INSTALL CURTAINWALL - NORTH ELEV ENC 10 18-Jul-13 02-Aug-13
ENCESNE-0870 INSTALL METAL PANELS - NORTH ELEV ENC 15 05-Aug-13 29-Aug-13
ENC - EAST ELEENC - EAST ELEVATIONENC - EAST ELEVATIONENC - EAST ELEVATIONENC - EAST ELEVATIONENCESEE-0440 LAY STACKED STONE - EAST ELEV ENC 25 14-Dec-12 24-Jan-13
ENCESEE-870 INSTALL GLASS - EAST ELEV ENC 5 14-Dec-12 21-Dec-12
ENCESEE-0870 INSTALL METAL PANELS/LOUVERS - EAST ELEV ENC 15 30-Aug-13 24-Sep-13
ENC - SOUTH ELENC - SOUTH ELEVATIONENC - SOUTH ELEVATIONENC - SOUTH ELEVATIONENC - SOUTH ELEVATIONENCESSE-0440 LAY STACKED STONE - SOUTH ELEV ENC 25 20-Nov-12 31-Dec-12
ENCESSE-880 INSTALL CURTAINWALL - SOUTH ELEV ENC 10 13-Jun-13 28-Jun-13
ENCESSE-0870 INSTALL METAL PANELS - SOUTH ELEV ENC 15 01-Jul-13 25-Jul-13
ENCESSE-0880 SET/CONNECT SOLAR TUBES - SOUTH ELEV ENC 40 26-Jul-13 02-Oct-13
ENC - WEST ELEENC - WEST ELEVATIONENC - WEST ELEVATIONENC - WEST ELEVATIONENC - WEST ELEVATIONENCESWE-0870 TIE-INS @ CONCOURSE - WEST ELEV ENC 20 01-Nov-12 04-Dec-12
ENCESWE-870 INSTALL CURTAINWALL - WEST ELEV ENC 10 01-Jul-13 16-Jul-13
ENCESWE-0777 INSTALL SCREEN WALL - WEST ELEV ENC 15 18-Jul-13 12-Aug-13
ENC - PENTHOUENC - PENTHOUSE ELEVATIONSENC - PENTHOUSE ELEVATIONSENC - PENTHOUSE ELEVATIONSENC - PENTHOUSE ELEVATIONSENCESPH-0870 INSTALL CURTAIN WALL - PENTHOUSE ENC 10 13-Jun-13 28-Jun-13
ENCESPH-0777 INSTALL LOUVERS - WEST ELEV ENC 15 01-Jul-13 25-Jul-13
ENERGY CENTERENERGY CENTER & WAREHOUSE (ENC) - INTERIOR BUILDOUTENERGY CENTER & WAREHOUSE (ENC) - INTERIOR BUILDOUTENERGY CENTER & WAREHOUSE (ENC) - INTERIOR BUILDOUTENERGY CENTER & WAREHOUSE (ENC) - INTERIOR BUILDOUTENC - PIPE BASENC - PIPE BASEMENTENC - PIPE BASEMENTENC - PIPE BASEMENTENC - PIPE BASEMENTENCPBPB-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - SERV LVL MECH RMS ENC 15 02-Oct-12 23-Oct-12
ENCPBPB-1520 SET/CONNECT/PIPE-UP PUMPS - SERV LVL MECH RMS ENC 90 24-Oct-12 07-Mar-13
ENC - SERVICE ENC - SERVICE LEVELENC - SERVICE LEVELENC - SERVICE LEVELENC - SERVICE LEVELENC - SERVICE LEVENC - SERVICE LEVEL SHOP AREAENC - SERVICE LEVEL SHOP AREAENC - SERVICE LEVEL SHOP AREAENC - SERVICE LEVEL SHOP AREA
ENCSLSH-1516 R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHOP ENC 20 03-Jan-13 31-Jan-13
ENCSLSH-0910 FRAMING/INWALL ROUGH - SERV LVL SHOP ENC 30 15-Jan-13 27-Feb-13
ENCSLSH-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL SHOP ENC 15 14-Feb-13 06-Mar-13
ENCSLSH-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHOP ENC 22 07-Mar-13 05-Apr-13
ENCSLSH-8880 CLEAN-UP/PRE PUNCH - SERV LVL SHOP ENC 8 08-Apr-13 17-Apr-13
ENC - SERVICE LEVENC - SERVICE LEVEL MECH ROOMSENC - SERVICE LEVEL MECH ROOMSENC - SERVICE LEVEL MECH ROOMSENC - SERVICE LEVEL MECH ROOMS
ENCSLSL-1520 SET BOILERS - SERV LVL MECH RMS ENC 5 07-Sep-12 13-Sep-12
ENCSLSL-3210 SET CHILLERS - SERV LVL MECH RMS ENC 5 07-Sep-12 13-Sep-12
ENCSLME-0420 LAY CMU WALLS - SERV LVL MECH RMS ENC 20 25-Oct-12 26-Nov-12
ENCSLME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - SERV LVL MECH RMS ENC 30 01-Feb-13 15-Mar-13
ENCSLME-1520 CONNECT/PIPE-UP BOILERS - SERV LVL MECH RMS ENC 60 18-Mar-13 10-Jun-13
ENCSLME-1525 CONNECT/PIPE-UP CHILLERS - SERV LVL MECH RMS ENC 20 18-Mar-13 12-Apr-13
ENCSLME-1600 SET/CONNECT/PIPE-UP MECH EQUIP (BALANCE) - SERV LVL MECH RMS ENC 60 18-Mar-13 10-Jun-13
ENC - SERVICE LEVENC - SERVICE LEVEL ELEC ROOMSENC - SERVICE LEVEL ELEC ROOMSENC - SERVICE LEVEL ELEC ROOMSENC - SERVICE LEVEL ELEC ROOMS
ENCSLEL-0420 LAY CMU WALLS - SERV LVL ELEC RMS ENC 10 25-Oct-12 07-Nov-12
ENCSLEL-0910 FRAMING/INWALL ROUGH - SERV LVL ELEC RMS ENC 10 25-Feb-13 08-Mar-13
ENCSLEL-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL ELEC RMS ENC 15 11-Mar-13 29-Mar-13
ENCSLEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP - SERV LVL ELEC RMS ENC 30 01-Apr-13 10-May-13
ENC - LEVEL 1ENC - LEVEL 1ENC - LEVEL 1ENC - LEVEL 1ENC - LEVEL 1
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 30 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 033
Activity ID Activity Name OrigDur
Start Finish
ENC - LEVEL 1 MEENC - LEVEL 1 MECH ROOMSENC - LEVEL 1 MECH ROOMSENC - LEVEL 1 MECH ROOMSENC - LEVEL 1 MECH ROOMS
ENCL1ME-0420 LAY CMU WALLS - LVL-1 MECH RMS ENC 10 25-Oct-12 07-Nov-12
ENCL1ME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - LVL-1 MECH RMS ENC 15 08-Nov-12 03-Dec-12
ENCL1ME-1520 SET/CONNECT AHU - 1 - LVL-1 MECH RMS ENC 25 04-Dec-12 09-Jan-13
ENCL1ME-1590 START-UP MECH EQUIP - LVL-1 MECH RMS ENC 10 05-Dec-13 18-Dec-13
ENC - LEVEL 1 ELEENC - LEVEL 1 ELEC ROOMSENC - LEVEL 1 ELEC ROOMSENC - LEVEL 1 ELEC ROOMSENC - LEVEL 1 ELEC ROOMS
ENCL1EL-0420 LAY CMU WALLS - LVL-1 ELEC RMS ENC 15 25-Oct-12 15-Nov-12
ENCL1EL-1650 ROUGH-IN/CONNECT TRANSFORMERS - LVL-1 ELEC RMS ENC 210 29-Oct-12 29-Aug-13
ENCL1EL-1660 ROUGH-IN/CONNECT SUBSTATION - LVL-1 ELEC RMS ENC 210 29-Oct-12 29-Aug-13
ENCL1EL-1620 ROUGH-IN/CONNECT SWITCHGEAR - LVL-1 ELEC RMS ENC 210 29-Oct-12 29-Aug-13
ENCL1EL-1640 ROUGH-IN/CONNECT GENERATORS - LVL-1 ELEC RMS ENC 210 29-Oct-12 29-Aug-13
ENCL1EL-0910 FRAMING/INWALL ROUGH - LVL-1 ELEC RMS ENC 10 27-Nov-12 10-Dec-12
ENCL1EL-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 ELEC RMS ENC 15 11-Dec-12 02-Jan-13
ENCL1L1-1620 SET SWITCHGEAR - LVL-1 ENC 5 12-Feb-13 18-Feb-13
ENCL1L1-1630 SET TRANFORMERS - LVL-1 ENC 3 12-Feb-13 14-Feb-13
ENCL1L1-1640 SET SUBSTATION - LVL-1 ENC 5 12-Feb-13 18-Feb-13
ENCL1L1-1650 SET GENERATORS - LVL-1 ENC 3 12-Feb-13 14-Feb-13
ENC - LEVEL 1 OFFENC - LEVEL 1 OFFICESENC - LEVEL 1 OFFICESENC - LEVEL 1 OFFICESENC - LEVEL 1 OFFICES
ENCL1OF-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 OFFICES ENC 20 04-Dec-12 02-Jan-13
ENCL1OF-0910 FRAMING/INWALL ROUGH - LVL-1 OFFICES ENC 15 18-Dec-12 09-Jan-13
ENCL1OF-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 OFFICES ENC 12 10-Jan-13 28-Jan-13
ENCL1OF-0990 INSTALL INTERIOR FINISHES & SPECIALTIES- LVL-1 OFFICES ENC 35 29-Jan-13 19-Mar-13
ENCL1OF-8880 CLEAN-UP/PRE PUNCH - LVL-1 OFFICES ENC 10 20-Mar-13 02-Apr-13
ENC - PENTHOUENC - PENTHOUSEENC - PENTHOUSEENC - PENTHOUSEENC - PENTHOUSEENCPHPH-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE ENC 30 31-Oct-12 14-Dec-12
ENCPHPH-1525 CONNECT/PIPE-UP AHUS - PENTHOUSE ENC 30 17-Dec-12 30-Jan-13
ENCPHPH-1600 SET/CONNECT/PIPE-UP MECH EQUIP (BALANCE) - PENTHOUSE ENC 20 17-Dec-12 15-Jan-13
ENCPHPH-1520 CONNECT/PIPE-UP COOLING TOWERS - PENTHOUSE ENC 60 15-Apr-13 09-Jul-13
ENC - ALL LEVEENC - ALL LEVELSENC - ALL LEVELSENC - ALL LEVELSENC - ALL LEVELSENCALAL-0551 ERECT STAIR (ST1) - ALL LVLS ENC 15 04-Oct-12 26-Oct-12
ENCALAL-0552 ERECT STAIR (ST2) - ALL LVLS ENC 15 22-Oct-12 14-Nov-12
ENCALAL-0553 ERECT STAIR (ST3) - ALL LVLS ENC 15 06-Nov-12 30-Nov-12
ENCALAL-0561 STAIR CORE FINISHES (ST1) - ALL LVLS ENC 30 08-Apr-13 17-May-13
ENCALAL-0562 STAIR CORE FINISHES (ST2) - ALL LVLS ENC 30 20-May-13 01-Jul-13
ENCALAL-0563 STAIR CORE FINISHES (ST3) - ALL LVLS ENC 30 02-Jul-13 13-Aug-13
ENCALAL-1416 INSTALL ELEVATOR (SE14) - ALL LVLS ENC 60 08-Aug-13 15-Nov-13
ENERGY CENTERENERGY CENTER & WAREHOUSE (ENC) - COMMISSIONINGENERGY CENTER & WAREHOUSE (ENC) - COMMISSIONINGENERGY CENTER & WAREHOUSE (ENC) - COMMISSIONINGENERGY CENTER & WAREHOUSE (ENC) - COMMISSIONINGENCALCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - ALL LVLS ENC 20 18-Nov-13 16-Dec-13
ENCALCO-10009 TEST & BALANCE - ALL LVLS ENC 15 19-Dec-13 10-Jan-14
ENCALCO-10019 PRE FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS ENC 20 19-Dec-13 17-Jan-14
ENCALCO-1592 FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS ENC 20 21-Jan-14 18-Feb-14
ENCALCO-1599 BUILDING FLUSH - ALL LVLS ENC 10 19-Feb-14 28-Feb-14
D&T BUILDINGD&T BUILDING (DAT)D&T BUILDING (DAT)D&T BUILDING (DAT)D&T BUILDING (DAT)D&T BUILDING (D&T BUILDING (DAT) - STRUCTURED&T BUILDING (DAT) - STRUCTURED&T BUILDING (DAT) - STRUCTURED&T BUILDING (DAT) - STRUCTUREDAT - PIPE GALDAT - PIPE GALLERYDAT - PIPE GALLERYDAT - PIPE GALLERYDAT - PIPE GALLERYDATPGPG-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PIPE GALLERY DAT 25 11-Jan-12 09-Feb-12
DATPGPG-0320 DRILL/PLACE CAISSONS - PIPE GALLERY DAT 15 10-Feb-12 05-Mar-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 31 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 034
Activity ID Activity Name OrigDur
Start Finish
DATPGPG-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY DAT 27 21-Feb-12 02-Apr-12
DATPGPG-3110 SET/BACKFILL DUCTBANKS - PIPE GALLERY DAT 7 03-Apr-12 16-Apr-12
DATPGPG-3200 UNDERSLAB UTILITIES - PIPE GALLERY DAT 7 03-Apr-12 16-Apr-12
DATPGPG-0380 FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY DAT 5 17-Apr-12 24-Apr-12
DATPGPG-3210 BACKFILL FOUNDATION WALLS (INTERIOR) - PIPE GALLERY DAT 5 24-May-12 31-May-12
DATPGPG-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - PIPE GALLERY DAT 8 11-Jun-12 22-Jun-12
DAT - SERVICE DAT - SERVICE LEVELDAT - SERVICE LEVELDAT - SERVICE LEVELDAT - SERVICE LEVELDATSLSL-0340 FORM/PLACE TOWER CRANE #1 BASE (DAT & CON C/D) 35 10-Feb-12 06-Apr-12
DATSLSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL DAT 33 10-Feb-12 20-Mar-12
DATSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL DAT 25 06-Mar-12 17-Apr-12
DATSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL DAT 30 14-Mar-12 07-May-12
DATSLSL-3200 UNDERSLAB UTILITIES - SERV LVL DAT 30 22-Mar-12 15-May-12
DATSLSL-0322 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - SERV LVL DAT 15 26-Apr-12 22-May-12
DATSLSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL DAT 15 08-May-12 01-Jun-12
DATSLSL-0382 FORM/PLACE/FINISH SLAB ON GRADE (AREA E) - SERV LVL DAT 10 08-May-12 24-May-12
DATSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE (AREA C) - SERV LVL DAT 15 15-May-12 08-Jun-12
DATSLSL-3210 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - SERV LVL DAT 10 24-May-12 08-Jun-12
DATSLSL-0381 FORM/PLACE/FINISH SLAB ON GRADE (AREA D) - SERV LVL DAT 10 24-May-12 08-Jun-12
DATSLSL-0383 FORM/PLACE/FINISH SLAB ON GRADE (AREA F) - SERV LVL DAT 10 01-Jun-12 18-Jun-12
DATSLSL-0388 FORM/PLACE/FINISH SLAB ON GRADE (AREA A) - SERV LVL DAT 10 19-Jun-12 05-Jul-12
DATPGPG-3220 BACKFILL FOUNDATION WALLS - SERV LVL DAT 5 23-Aug-12 30-Aug-12
DAT SERVICE LEVEDAT SERVICE LEVEL - INTERSTITIALDAT SERVICE LEVEL - INTERSTITIALDAT SERVICE LEVEL - INTERSTITIALDAT SERVICE LEVEL - INTERSTITIAL
DATSLIL-1537 ERECT INTER STEEL/TOPPING (AREA C) - SERV LVL INTER LVL DAT 15 20-Nov-12 13-Dec-12
DATSLIL-1547 ERECT INTER STEEL/TOPPING (AREA D) - SERV LVL INTER LVL DAT 15 07-Dec-12 31-Dec-12
DATSLIL-1557 ERECT INTER STEEL/TOPPING (AREA E) - SERV LVL INTER LVL DAT 15 24-Dec-12 15-Jan-13
DATSLIL-1567 ERECT INTER STEEL/TOPPING (AREA F) - SERV LVL INTER LVL DAT 15 09-Jan-13 31-Jan-13
DATSLIL-0510 ERECT INTER STEEL/TOPPING (AREA A) - SERV LVL INTER LVL DAT 15 25-Jan-13 15-Feb-13
DATSLIL-1527 ERECT INTER STEEL/TOPPING (AREA B) - SERV LVL INTER LVL DAT 15 08-Feb-13 04-Mar-13
DAT - LEVEL 1DAT - LEVEL 1DAT - LEVEL 1DAT - LEVEL 1DAT - LEVEL 1DATL1L1-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-1 DAT 15 11-Jun-12 05-Jul-12
DATL1L1-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-1 DAT 5 06-Jul-12 13-Jul-12
DATL1L1-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-1 DAT 5 16-Jul-12 23-Jul-12
DATL1L1-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-1 DAT 10 24-Jul-12 09-Aug-12
DATL1L1-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-1 DAT 5 10-Aug-12 17-Aug-12
DATL1L1-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-1 DAT 5 20-Aug-12 27-Aug-12
DAT LEVEL 1 - INTDAT LEVEL 1 - INTERSTITIALDAT LEVEL 1 - INTERSTITIALDAT LEVEL 1 - INTERSTITIALDAT LEVEL 1 - INTERSTITIAL
DATL1IL-1537 ERECT INTER STEEL/TOPPING (AREA C) - LVL-1 INTER LVL DAT 15 17-Jan-13 07-Feb-13
DATL1IL-1547 ERECT INTER STEEL/TOPPING (AREA D) - LVL-1 INTER LVL DAT 15 01-Feb-13 25-Feb-13
DATL1IL-1557 ERECT INTER STEEL/TOPPING (AREA E) - LVL-1 INTER LVL DAT 15 19-Feb-13 12-Mar-13
DATL1IL-1567 ERECT INTER STEEL/TOPPING (AREA F) - LVL-1 INTER LVL DAT 15 05-Mar-13 28-Mar-13
DATL1IL-0510 ERECT INTER STEEL/TOPPING (AREA A) - LVL-1 INTER LVL DAT 15 21-Mar-13 15-Apr-13
DATL1IL-1527 ERECT INTER STEEL/TOPPING (AREA B) - LVL-1 INTER LVL DAT 15 08-Apr-13 03-May-13
DAT - LEVEL 2DAT - LEVEL 2DAT - LEVEL 2DAT - LEVEL 2DAT - LEVEL 2DATL2L2-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-2 DAT 5 28-Aug-12 05-Sep-12
DATL2L2-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-2 DAT 5 28-Aug-12 05-Sep-12
DATL2L2-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-2 DAT 5 06-Sep-12 13-Sep-12
DATL2L2-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-2 DAT 5 06-Sep-12 13-Sep-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 32 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 035
Activity ID Activity Name OrigDur
Start Finish
DATL2L2-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-2 DAT 5 14-Sep-12 21-Sep-12
DATL2L2-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-2 DAT 5 14-Sep-12 21-Sep-12
DAT LEVEL 2 - INTDAT LEVEL 2 - INTERSTITIALDAT LEVEL 2 - INTERSTITIALDAT LEVEL 2 - INTERSTITIALDAT LEVEL 2 - INTERSTITIAL
DATL2IL-1537 ERECT INTER STEEL/TOPPING (AREA C) - LVL-2 INTER LVL DAT 15 20-Nov-12 13-Dec-12
DATL2IL-1547 ERECT INTER STEEL/TOPPING (AREA D) - LVL-2 INTER LVL DAT 15 07-Dec-12 31-Dec-12
DATL2IL-1557 ERECT INTER STEEL/TOPPING (AREA E) - LVL-2 INTER LVL DAT 15 24-Dec-12 15-Jan-13
DATL2IL-1567 ERECT INTER STEEL/TOPPING (AREA F) - LVL-2 INTER LVL DAT 15 02-Jan-13 24-Jan-13
DATL2IL-0510 ERECT INTER STEEL/TOPPING (AREA A) - LVL-2 INTER LVL DAT 15 17-Jan-13 07-Feb-13
DATL2IL-1527 ERECT INTER STEEL/TOPPING (AREA B) - LVL-2 INTER LVL DAT 15 01-Feb-13 25-Feb-13
DAT - LEVEL 3DAT - LEVEL 3DAT - LEVEL 3DAT - LEVEL 3DAT - LEVEL 3DATL3L3-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-3 DAT 5 24-Sep-12 01-Oct-12
DATL3L3-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-3 DAT 5 02-Oct-12 08-Oct-12
DATL3L3-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-3 DAT 5 09-Oct-12 16-Oct-12
DATL3L3-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-3 DAT 5 18-Oct-12 24-Oct-12
DATL3L3-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-3 DAT 5 25-Oct-12 01-Nov-12
DATL3L3-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-3 DAT 5 02-Nov-12 09-Nov-12
DAT LEVEL 3 - INTDAT LEVEL 3 - INTERSTITIALDAT LEVEL 3 - INTERSTITIALDAT LEVEL 3 - INTERSTITIALDAT LEVEL 3 - INTERSTITIAL
DATL3IL-1537 ERECT INTER STEEL/TOPPING (AREA C) - LVL-3 INTER LVL DAT 15 17-Jan-13 07-Feb-13
DATL3IL-1547 ERECT INTER STEEL/TOPPING (AREA D) - LVL-3 INTER LVL DAT 15 01-Feb-13 25-Feb-13
DATL3IL-1557 ERECT INTER STEEL/TOPPING (AREA E) - LVL-3 INTER LVL DAT 15 19-Feb-13 12-Mar-13
DATL3IL-1567 ERECT INTER STEEL/TOPPING (AREA F) - LVL-3 INTER LVL DAT 15 05-Mar-13 28-Mar-13
DATL3IL-0510 ERECT INTER STEEL/TOPPING (AREA A) - LVL-3 INTER LVL DAT 15 21-Mar-13 15-Apr-13
DATL3IL-1527 ERECT INTER STEEL/TOPPING (AREA B) - LVL-3 INTER LVL DAT 15 08-Apr-13 03-May-13
DAT - PENTHOUDAT - PENTHOUSE LEVELDAT - PENTHOUSE LEVELDAT - PENTHOUSE LEVELDAT - PENTHOUSE LEVELDATPHPH-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - PENT DAT 5 13-Nov-12 19-Nov-12
DATPHPH-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - PENT DAT 5 20-Nov-12 27-Nov-12
DATPHPH-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - PENT DAT 5 29-Nov-12 06-Dec-12
DATPHPH-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - PENT DAT 5 07-Dec-12 13-Dec-12
DATPHPH-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - PENT DAT 5 14-Dec-12 21-Dec-12
DATPHPH-0322 FORM/REINFORCE/PLACE EQUIPMENT PADS (south penthouse) - PENT DAT 7 14-Dec-12 26-Dec-12
DATPHPH-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - PENT DAT 5 24-Dec-12 31-Dec-12
DATPHPH-0370 FORM/REINFORCE/PLACE/FINISH EQUIPMENT PADS (north penthouse) - PENT DAT 7 02-Jan-13 10-Jan-13
DAT - SOUTH PENTDAT - SOUTH PENTHOUSEDAT - SOUTH PENTHOUSEDAT - SOUTH PENTHOUSEDAT - SOUTH PENTHOUSE
DATPHSP-1500 SET MECH EQUIPMENT - SOUTH PENT DAT 2 27-Dec-12 28-Dec-12
DATPHSP-1600 SET ELECTRICAL EQUIPMENT - SOUTH PENT DAT 10 27-Dec-12 10-Jan-13
DATPHSP-0510 ERECT PENTHOUSE STEEL/METAL DECK/TOPPING- SOUTH PENT DAT 18 11-Jan-13 07-Feb-13
DATPHSP-0750 BLOCKING/ROOFING- SOUTH PENT DAT 15 08-Feb-13 04-Mar-13
DATPHSP-1690 SET/CONNECT PHOTOVOLTAIC PANELS- SOUTH PENT DAT 50 15-Mar-13 10-Jun-13
DAT - NORTH PENDAT - NORTH PENTHOUSEDAT - NORTH PENTHOUSEDAT - NORTH PENTHOUSEDAT - NORTH PENTHOUSE
DATPHNP-1610 SET MECH EQUIPMENT- NORTH PENT DAT 2 11-Jan-13 14-Jan-13
DATPHNP-1621 SET ELECTRICAL EQUIPMENT - NORTH PENT DAT 10 11-Jan-13 25-Jan-13
DATPHNP-1631 ERECT PENTHOUSE STEEL/METAL DECK/TOPPING- NORTH PENT DAT 18 28-Jan-13 22-Feb-13
DATPHNP-0750 BLOCKING/ROOFING- NORTH PENT DAT 15 25-Feb-13 19-Mar-13
DATPHNP-1623 SET/CONNECT PHOTOVOLTAIC PANELS- NORTH PENT DAT 50 20-Mar-13 14-Jun-13
DAT - LOW SOUTHDAT - LOW SOUTH ROOFDAT - LOW SOUTH ROOFDAT - LOW SOUTH ROOFDAT - LOW SOUTH ROOF
DATRLNR-1640 PARAPET/BLOCKING/WATERPROOFING - SOUTH LOW ROOF DAT 15 08-Feb-13 04-Mar-13
DATRLNR-1670 INSTALL GREEN ROOF SYSTEM - SOUTH LOW ROOF DAT 18 25-Apr-13 28-May-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 33 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 036
Activity ID Activity Name OrigDur
Start Finish
DATRLNR-1680 INSTALL ROOF ACCESSORIES - SOUTH LOW ROOF DAT 10 29-May-13 13-Jun-13
DAT - LOW NORTHDAT - LOW NORTH ROOFDAT - LOW NORTH ROOFDAT - LOW NORTH ROOFDAT - LOW NORTH ROOF
DATRLRL-1610 PARAPET/BLOCKING/WATERPROOFING - NORTH LOW ROOF DAT 15 25-Feb-13 19-Mar-13
DATRLRL-1650 INSTALL GREEN ROOF SYSTEM - NORTH LOW ROOF DAT 18 13-May-13 11-Jun-13
DATRLRL-1660 INSTALL ROOF ACCESSORIES - NORTH LOW ROOF DAT 10 13-Jun-13 28-Jun-13
D&T BUILDING (D&T BUILDING (DAT)- EXTERIOR SKIND&T BUILDING (DAT)- EXTERIOR SKIND&T BUILDING (DAT)- EXTERIOR SKIND&T BUILDING (DAT)- EXTERIOR SKINDAT - ALL ELEVDAT - ALL ELEVATIONS AREA - CDAT - ALL ELEVATIONS AREA - CDAT - ALL ELEVATIONS AREA - CDAT - ALL ELEVATIONS AREA - CDATESAC-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-C DAT 15 08-Feb-13 04-Mar-13
DATESAC-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-C DAT 15 05-Mar-13 28-Mar-13
DATESAC-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-C DAT 20 29-Mar-13 03-May-13
DATESAC-0780 INSTALL METAL PANEL - ALL ELEVS AR-C DAT 15 29-Mar-13 23-Apr-13
DATESAC-0550 HOIST INFILL - ALL ELEVS AR-C DAT 10 29-May-14 13-Jun-14
DAT - ALL ELEVDAT - ALL ELEVATIONS AREA - DDAT - ALL ELEVATIONS AREA - DDAT - ALL ELEVATIONS AREA - DDAT - ALL ELEVATIONS AREA - DDATESAD-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-D DAT 15 26-Feb-13 20-Mar-13
DATESAD-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-D DAT 15 21-Mar-13 15-Apr-13
DATESAD-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-D DAT 20 23-May-13 25-Jun-13
DATESAD-0780 INSTALL METAL PANEL - ALL ELEVS AR-D DAT 5 23-May-13 30-May-13
DAT - ALL ELEVDAT - ALL ELEVATIONS AREA - EDAT - ALL ELEVATIONS AREA - EDAT - ALL ELEVATIONS AREA - EDAT - ALL ELEVATIONS AREA - EDATESAE-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-E DAT 15 14-Mar-13 05-Apr-13
DATESAE-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-E DAT 15 08-Apr-13 03-May-13
DATESAE-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-E DAT 30 06-May-13 25-Jun-13
DATESAE-0440 LAY STACKED STONE - ALL ELEVS AR-E DAT 20 06-May-13 07-Jun-13
DATESAE-0780 INSTALL METAL PANEL - ALL ELEVS AR-E DAT 19 31-May-13 02-Jul-13
DATESAF-0890 INFILL FOR MRI EQUIPMENT INSTALL - ALL ELEVS AR-E DAT 5 10-Jul-14 17-Jul-14
DAT - ALL ELEVDAT - ALL ELEVATIONS AREA - FDAT - ALL ELEVATIONS AREA - FDAT - ALL ELEVATIONS AREA - FDAT - ALL ELEVATIONS AREA - FDATESAF-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-F DAT 15 29-Mar-13 23-Apr-13
DATESAF-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-F DAT 15 25-Apr-13 21-May-13
DATESAF-0780 INSTALL METAL PANEL - ALL ELEVS AR-F DAT 20 23-May-13 25-Jun-13
DATESAF-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-F DAT 25 23-May-13 03-Jul-13
DATESAF-0550 HOIST INFILL - ALL ELEVS AR-F DAT 10 29-May-14 13-Jun-14
DAT - ALL ELEVDAT - ALL ELEVATIONS AREA - ADAT - ALL ELEVATIONS AREA - ADAT - ALL ELEVATIONS AREA - ADAT - ALL ELEVATIONS AREA - ADATESAA-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-A DAT 15 16-Apr-13 13-May-13
DATESAA-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-A DAT 15 14-May-13 07-Jun-13
DATESAA-0440 LAY STACKED STONE - ALL ELEVS AR-A DAT 20 10-Jun-13 12-Jul-13
DATESAA-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-A DAT 20 15-Jul-13 16-Aug-13
DATESAA-0780 INSTALL METAL PANEL - ALL ELEVS AR-A DAT 15 15-Jul-13 08-Aug-13
DAT - ALL ELEVDAT - ALL ELEVATIONS AREA - BDAT - ALL ELEVATIONS AREA - BDAT - ALL ELEVATIONS AREA - BDAT - ALL ELEVATIONS AREA - BDATESAB-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-B DAT 15 06-May-13 30-May-13
DATESAB-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-B DAT 15 31-May-13 25-Jun-13
DATESAB-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-B DAT 25 27-Jun-13 08-Aug-13
DATESAB-0440 LAY STACKED STONE - ALL ELEVS AR-B DAT 20 27-Jun-13 30-Jul-13
DATESAB-0780 INSTALL METAL PANEL - ALL ELEVS AR-B DAT 20 09-Aug-13 12-Sep-13
DAT - ALL ELEVDAT - ALL ELEVATIONS NORTH PENTHOUSEDAT - ALL ELEVATIONS NORTH PENTHOUSEDAT - ALL ELEVATIONS NORTH PENTHOUSEDAT - ALL ELEVATIONS NORTH PENTHOUSEDATESNP-0520 ERECT STUDS/SHEATHING/VAPOR BARRIER - ALL ELEVS NORTH PNTHSE DAT 15 25-Feb-13 19-Mar-13
DATESNP-0555 ERECT TRELLIS - ALL ELEVS NORTH PNTHSE DAT 10 20-Mar-13 04-Apr-13
DATESNP-780 INSTALL LOUVERS - ALL ELEVS NORTH PNTHSE DAT 10 20-Mar-13 04-Apr-13
DATESNP-0780 INSTALL METAL PANEL - ALL ELEVS NORTH PNTHSE DAT 20 05-Apr-13 10-May-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 34 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 037
Activity ID Activity Name OrigDur
Start Finish
DAT - ALL ELEVDAT - ALL ELEVATIONS SOUTH PENTHOUSEDAT - ALL ELEVATIONS SOUTH PENTHOUSEDAT - ALL ELEVATIONS SOUTH PENTHOUSEDAT - ALL ELEVATIONS SOUTH PENTHOUSEDATESSP-0520 STUDS/SHEATHING/VAPOR BARRIER - ALL ELEVS SOUTH PNTHSE DAT 15 08-Feb-13 04-Mar-13
DATESSP-0555 ERECT TRELLIS - ALL ELEVS SOUTH PNTHSE DAT 10 05-Mar-13 20-Mar-13
DATESSP-780 INSTALL LOUVERS - ALL ELEVS SOUTH PNTHSE DAT 10 05-Mar-13 20-Mar-13
DATESSP-0780 INSTALL METAL PANEL - ALL ELEVS SOUTH PNTHSE DAT 20 21-Mar-13 23-Apr-13
D&T BUILDING (D&T BUILDING (DAT) - INTERIOR BUILDOUTD&T BUILDING (DAT) - INTERIOR BUILDOUTD&T BUILDING (DAT) - INTERIOR BUILDOUTD&T BUILDING (DAT) - INTERIOR BUILDOUTDAT - PIPE GALDAT - PIPE GALLERYDAT - PIPE GALLERYDAT - PIPE GALLERYDAT - PIPE GALLERYDATPGPG-1516 R-I OVERHEAD MEP/FIRE PROT - PIPE GALLERY DAT 15 02-Jan-13 23-Jan-13
DAT - SERVICE DAT - SERVICE LEVELDAT - SERVICE LEVELDAT - SERVICE LEVELDAT - SERVICE LEVELDAT - SERVICE LEVDAT - SERVICE LEVEL - INTERSTITIALDAT - SERVICE LEVEL - INTERSTITIALDAT - SERVICE LEVEL - INTERSTITIALDAT - SERVICE LEVEL - INTERSTITIAL
DATSLIL-1800 ROUGH-IN MEP/FIRE PROTECTION (EMER MGMNT) (AHU18) - SERV LVL INTER LVL DAT 45 05-Mar-13 06-May-13
DATSLIL-0200 ROUGH-IN MEP/FIRE PROTECTION (PHARMACY) (AHU2) - SERV LVL INTER LVL DAT 45 02-Apr-13 04-Jun-13
DATSLIL-0700 ROUGH-IN MEP/FIRE PROTECTION (STERILIZATION) (AHU7) - SERV LVL INTER LVL DAT 45 30-Apr-13 02-Jul-13
DATSLIL-1900 ROUGH-IN MEP/FIRE PROTECTION (SHELL) (AHU19) - SERV LVL INTER LVL DAT 45 29-May-13 31-Jul-13
DATSLIL-1901 TRIM-OUT MEP (SHELL) (AHU19) - SERV LVL INTER LVL DAT 5 01-Aug-13 07-Aug-13
DATSLIL-0201 TRIM-OUT MEP (PHARMACY) (AHU2) - SERV LVL INTER LVL DAT 5 29-Aug-13 05-Sep-13
DATSLIL-0701 TRIM-OUT MEP (STERILIZATION) (AHU7) - SERV LVL INTER LVL DAT 5 02-Oct-13 08-Oct-13
DATSLIL-1801 TRIM-OUT MEP (EMER MGMNT) (AHU18) - SERV LVL INTER LVL DAT 5 27-Nov-13 03-Dec-13
DAT - SERVICE LEVDAT - SERVICE LEVEL - PHARMACYDAT - SERVICE LEVEL - PHARMACYDAT - SERVICE LEVEL - PHARMACYDAT - SERVICE LEVEL - PHARMACY
DATSLPY-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL PHARMACY DAT 20 05-Jun-13 02-Jul-13
DATSLPY-0910 FRAMING/INWALL ROUGH - SERV LVL PHARMACY DAT 35 05-Jun-13 24-Jul-13
DATSLPY-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL PHARMACY DAT 20 03-Jul-13 31-Jul-13
DATSLPY-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL PHARMACY DAT 55 25-Jul-13 10-Oct-13
DATSLPY-0977 INSTALL OWNER FIXED FF&E - SERV LVL PHARMACY DAT 20 13-Sep-13 10-Oct-13
DATSLPY-8880 CLEAN-UP/PRE PUNCH - SERV LVL PHARMACY DAT 10 11-Oct-13 25-Oct-13
DAT - SERVICDAT - SERVICE LEVEL - PHARMACY CORRIDORDAT - SERVICE LEVEL - PHARMACY CORRIDORDAT - SERVICE LEVEL - PHARMACY CORRIDORDAT - SERVICE LEVEL - PHARMACY CORRIDOR
DATSLPC-0990 INSTALL INTERIOR FINISHES - SERV LVL PHARMACY CORR DAT 20 11-Oct-13 08-Nov-13
DAT - SERVICE LEVDAT - SERVICE LEVEL - STERILIZATIONDAT - SERVICE LEVEL - STERILIZATIONDAT - SERVICE LEVEL - STERILIZATIONDAT - SERVICE LEVEL - STERILIZATION
DATSLST-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL STER DAT 25 03-Jul-13 07-Aug-13
DATSLST-0910 FRAMING/INWALL ROUGH - SERV LVL STER DAT 35 03-Jul-13 21-Aug-13
DATSLST-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL STER DAT 15 08-Aug-13 28-Aug-13
DATSLST-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL STER DAT 45 22-Aug-13 25-Oct-13
DATSLST-0977 INSTALL OWNER FIXED FF&E - SERV LVL STER DAT 20 27-Sep-13 25-Oct-13
DATSLST-8880 CLEAN-UP/PRE PUNCH - SERV LVL STER DAT 10 28-Oct-13 08-Nov-13
DAT - SERVICDAT - SERVICE LEVEL - STERILIZATION SUPPORT RMSDAT - SERVICE LEVEL - STERILIZATION SUPPORT RMSDAT - SERVICE LEVEL - STERILIZATION SUPPORT RMSDAT - SERVICE LEVEL - STERILIZATION SUPPORT RMS
DATSLSS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL STER SUPP DAT 15 22-Aug-13 12-Sep-13
DATSLSS-0910 FRAMING/INWALL ROUGH - SERV LVL STER SUPP DAT 15 29-Aug-13 19-Sep-13
DATSLSS-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL STER SUPP DAT 8 20-Sep-13 01-Oct-13
DATSLSS-0977 INSTALL OWNER FIXED FF&E - SERV LVL STER DAT 20 02-Oct-13 30-Oct-13
DATSLSS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL STER SUPP DAT 20 02-Oct-13 30-Oct-13
DATSLSS-8880 CLEAN-UP/PRE PUNCH - SERV LVL STER SUPP DAT 10 31-Oct-13 14-Nov-13
DAT - SERVICE LEVDAT - SERVICE LEVEL - EMERGENCY MANAGEMENTDAT - SERVICE LEVEL - EMERGENCY MANAGEMENTDAT - SERVICE LEVEL - EMERGENCY MANAGEMENTDAT - SERVICE LEVEL - EMERGENCY MANAGEMENT
DATSLEM-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL EMER MGMT DAT 25 07-May-13 11-Jun-13
DATSLEM-0910 FRAMING/INWALL ROUGH - SERV LVL EMER MGMT DAT 20 21-May-13 18-Jun-13
DATSLEM-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL EMER MGMT DAT 20 27-Sep-13 25-Oct-13
DATSLEM-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL EMER MGMT DAT 55 28-Oct-13 16-Jan-14
DATSLEM-0977 INSTALL OWNER FIXED FF&E - SERV LVL EMER MGMT DAT 20 18-Dec-13 16-Jan-14
DATSLEM-8880 CLEAN-UP/PRE PUNCH - SERV LVL EMER MGMT DAT 10 17-Jan-14 31-Jan-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 35 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 038
Activity ID Activity Name OrigDur
Start Finish
DAT - SERVICE LEVDAT - SERVICE LEVEL - SHELL SPACEDAT - SERVICE LEVEL - SHELL SPACEDAT - SERVICE LEVEL - SHELL SPACEDAT - SERVICE LEVEL - SHELL SPACE
DATSLSH-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL SHELL DAT 15 08-Aug-13 28-Aug-13
DAT - LEVEL 1DAT - LEVEL 1DAT - LEVEL 1DAT - LEVEL 1DAT - LEVEL 1DAT - LEVEL 1 - INDAT - LEVEL 1 - INTERSTITIALDAT - LEVEL 1 - INTERSTITIALDAT - LEVEL 1 - INTERSTITIALDAT - LEVEL 1 - INTERSTITIAL
DATL1IL-0400 ROUGH-IN MEP/FIRE PROTECTION (GEN RADIOLOGY) (AHU4) - LVL-1 INTER LVL DAT 55 26-Jun-13 12-Sep-13
DATL1IL-0100 ROUGH-IN MEP/FIRE PROTECTION (PRE ADMIN) (AHU1) - LVL-1 INTER LVL DAT 50 25-Jul-13 03-Oct-13
DATL1IL-1500 ROUGH-IN MEP/FIRE PROTECTION (SPECIAL RADIOLOGY) (AHU15) - LVL-1 INTER LVL DAT 65 22-Aug-13 26-Nov-13
DATL1IL-0500 ROUGH-IN MEP/FIRE PROTECTION (NUC MED) (AHU5) - LVL-1 INTER LVL DAT 50 22-Aug-13 01-Nov-13
DATL1IL-1600 ROUGH-IN MEP/FIRE PROTECTION (ER) (AHU16) - LVL-1 INTER LVL DAT 65 20-Sep-13 24-Dec-13
DATL1IL-0800 ROUGH-IN MEP/FIRE PROTECTION (OFFICES) (AHU8) - LVL-1 INTER LVL DAT 50 20-Sep-13 03-Dec-13
DATL1IL-0401 TRIM-OUT MEP (GEN RADIOLOGY) (AHU4) - LVL-1 INTER LVL DAT 15 18-Dec-13 09-Jan-14
DATL1IL-0501 TRIM-OUT MEP (NUC MED) (AHU5) - LVL-1 INTER LVL DAT 20 25-Feb-14 24-Mar-14
DATL1IL-0101 TRIM-OUT MEP (PRE ADMIN) (AHU1) - LVL-1 INTER LVL DAT 15 08-Apr-14 28-Apr-14
DATL1IL-1501 TRIM-OUT MEP (SPECIAL RADIOLOGY) (AHU15) - LVL-1 INTER LVL DAT 20 22-Apr-14 19-May-14
DATL1IL-0801 TRIM-OUT MEP (OFFICE) (AHU8) - LVL-1 INTER LVL DAT 15 06-May-14 27-May-14
DATL1IL-1601 TRIM-OUT MEP (ER) (AHU16) - LVL-1 INTER LVL DAT 15 20-May-14 10-Jun-14
DAT - LEVEL 1 - PRDAT - LEVEL 1 - PRE ADMIT/PHARMACY/WAITINGDAT - LEVEL 1 - PRE ADMIT/PHARMACY/WAITINGDAT - LEVEL 1 - PRE ADMIT/PHARMACY/WAITINGDAT - LEVEL 1 - PRE ADMIT/PHARMACY/WAITING
DATL1PA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 PRE-ADMIT DAT 30 04-Oct-13 18-Nov-13
DATL1PA-0910 FRAMING/INWALL ROUGH - LVL-1 PRE-ADMIT DAT 25 26-Dec-13 31-Jan-14
DATL1PA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 PRE-ADMIT DAT 20 17-Jan-14 17-Feb-14
DATL1PA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PRE-ADMIT DAT 55 25-Feb-14 12-May-14
DATL1PA-0977 INSTALL OWNER FIXED FF&E - LVL-1 PRE-ADMIT DAT 20 15-Apr-14 12-May-14
DATL1PA-8880 CLEAN-UP/PRE PUNCH - LVL-1 PRE-ADMIT DAT 10 13-May-14 27-May-14
DAT - LEVEL 1 - NUDAT - LEVEL 1 - NUCLEAR MEDICINEDAT - LEVEL 1 - NUCLEAR MEDICINEDAT - LEVEL 1 - NUCLEAR MEDICINEDAT - LEVEL 1 - NUCLEAR MEDICINE
DATL1NM-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 NUC MED DAT 20 19-Nov-13 17-Dec-13
DATL1NM-0910 FRAMING/INWALL ROUGH - LVL-1 NUC MED DAT 25 27-Nov-13 02-Jan-14
DATL1NM-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 NUC MED DAT 20 18-Dec-13 16-Jan-14
DATL1NM-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NUC MED DAT 65 10-Jan-14 14-Apr-14
DATL1NM-0977 INSTALL OWNER FIXED FF&E - LVL-1 NUC MED DAT 20 18-Mar-14 14-Apr-14
DATL1NM-8880 CLEAN-UP/PRE PUNCH - LVL-1 NUC MED DAT 10 15-Apr-14 28-Apr-14
DAT - LEVEL 1 - FLDAT - LEVEL 1 - FLUOROSCOPY/ULTRASOUNDDAT - LEVEL 1 - FLUOROSCOPY/ULTRASOUNDDAT - LEVEL 1 - FLUOROSCOPY/ULTRASOUNDDAT - LEVEL 1 - FLUOROSCOPY/ULTRASOUND
DATL1FL-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 FLURO/UTLSND DAT 25 27-Nov-13 02-Jan-14
DATL1FL-0910 FRAMING/INWALL ROUGH - LVL-1 FLURO/UTLSND DAT 30 17-Jan-14 03-Mar-14
DATL1FL-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 FLURO/UTLSND DAT 25 11-Feb-14 17-Mar-14
DATL1FL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 FLURO/UTLSND DAT 65 25-Feb-14 27-May-14
DATL1FL-0977 INSTALL OWNER FIXED FF&E - LVL-1 FLURO.UTLSND DAT 20 29-Apr-14 27-May-14
DATL1FL-8880 CLEAN-UP/PRE PUNCH - LVL-1 FLURO/UTLSND DAT 10 28-May-14 10-Jun-14
DAT - LEVEL 1DAT - LEVEL 1 - MRI AND CT ROOMSDAT - LEVEL 1 - MRI AND CT ROOMSDAT - LEVEL 1 - MRI AND CT ROOMSDAT - LEVEL 1 - MRI AND CT ROOMS
DATL1MR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 MRI/CT DAT 20 03-Jan-14 31-Jan-14
DATL1MR-0910 FRAMING/INWALL ROUGH - LVL-1 MRI/CT DAT 40 17-Jan-14 17-Mar-14
DATL1MR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 MRI/CT DAT 25 18-Mar-14 21-Apr-14
DATL1MR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 MRI/CT DAT 55 22-Apr-14 09-Jul-14
DATL1MR-0977 INSTALL OWNER FIXED FF&E - LVL-1 MRI/CT DAT 20 11-Jun-14 09-Jul-14
DATL1MR-8880 CLEAN-UP/PRE PUNCH - LVL-1 MRI/CT DAT 10 10-Jul-14 23-Jul-14
DAT - LEVEL 1 - SODAT - LEVEL 1 - SOUTH CORRIDORDAT - LEVEL 1 - SOUTH CORRIDORDAT - LEVEL 1 - SOUTH CORRIDORDAT - LEVEL 1 - SOUTH CORRIDOR
DATL1SC-0990 INSTALL INTERIOR FINISHES - LVL-1 SOUTH CORR DAT 55 10-Jul-14 25-Sep-14
DAT - LEVEL 1 - GEDAT - LEVEL 1 - GENERAL RADIOLOGYDAT - LEVEL 1 - GENERAL RADIOLOGYDAT - LEVEL 1 - GENERAL RADIOLOGYDAT - LEVEL 1 - GENERAL RADIOLOGY
DATL1GR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 GEN RADIOLOGY DAT 35 13-Sep-13 01-Nov-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 36 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 039
Activity ID Activity Name OrigDur
Start Finish
DATL1GR-0910 FRAMING/INWALL ROUGH - LVL-1 GEN RADIOLGY DAT 25 04-Oct-13 08-Nov-13
DATL1GR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 GEN RADIOLGY DAT 30 18-Oct-13 03-Dec-13
DATL1GR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 GEN RADIOLOGY DAT 65 04-Nov-13 07-Feb-14
DATL1GR-0977 INSTALL OWNER FIXED FF&E - LVL-1 GEN RADIOLOGY DAT 20 10-Jan-14 07-Feb-14
DATL1GR-8880 CLEAN-UP/PRE PUNCH - LVL-1 GEN RADIOLGY DAT 10 11-Feb-14 24-Feb-14
DAT - LEVEL 1 EMEDAT - LEVEL 1 EMERGENCYDAT - LEVEL 1 EMERGENCYDAT - LEVEL 1 EMERGENCYDAT - LEVEL 1 EMERGENCY
DATL1ER-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 ER DAT 35 26-Dec-13 17-Feb-14
DATL1ER-0910 FRAMING/INWALL ROUGH - LVL-1 ER DAT 30 10-Jan-14 24-Feb-14
DATL1ER-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 ER DAT 25 27-Jan-14 03-Mar-14
DATL1ER-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 ER DAT 65 08-Apr-14 09-Jul-14
DATL1ER-0977 INSTALL OWNER FIXED FF&E - LVL-1 ER DAT 20 11-Jun-14 09-Jul-14
DATL1ER-8880 CLEAN-UP/PRE PUNCH - LVL-1 ER DAT 10 10-Jul-14 23-Jul-14
DAT - LEVEL 1 - RADAT - LEVEL 1 - RADIOLOGISTS OFFICESDAT - LEVEL 1 - RADIOLOGISTS OFFICESDAT - LEVEL 1 - RADIOLOGISTS OFFICESDAT - LEVEL 1 - RADIOLOGISTS OFFICES
DATL1RO-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 RAD OFFICES DAT 20 18-Dec-13 16-Jan-14
DATL1RO-0910 FRAMING/INWALL ROUGH - LVL-1 RAD OFFICES DAT 20 27-Jan-14 24-Feb-14
DATL1RO-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 RAD OFFICES DAT 15 18-Feb-14 10-Mar-14
DATL1RO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 RAD OFFICES DAT 40 08-Apr-14 03-Jun-14
DATL1RO-0977 INSTALL OWNER FIXED FF&E - LVL-1 RAD OFFICES DAT 20 06-May-14 03-Jun-14
DATL1RO-8880 CLEAN-UP/PRE PUNCH - LVL-1 RAD OFFICES DAT 10 04-Jun-14 17-Jun-14
DAT - LEVEL 2DAT - LEVEL 2DAT - LEVEL 2DAT - LEVEL 2DAT - LEVEL 2DAT - LEVEL 2 - INDAT - LEVEL 2 - INTERSTITIALDAT - LEVEL 2 - INTERSTITIALDAT - LEVEL 2 - INTERSTITIALDAT - LEVEL 2 - INTERSTITIAL
DATL2IL-1700 ROUGH-IN MEP/FIRE PROTECTION (LABS) (AHU17) - LVL-2 INTER LVL DAT 45 01-Aug-13 03-Oct-13
DATL2IL-0300 ROUGH-IN MEP/FIRE PROTECTION (CARDIO) (AHU3) - LVL-2 INTER LVL DAT 60 04-Nov-13 31-Jan-14
DATL2IL-1400 ROUGH-IN MEP/FIRE PROTECTION (DENTAL) (AHU14) - LVL-2 INTER LVL DAT 65 04-Nov-13 07-Feb-14
DATL2IL-0800 ROUGH-IN MEP/FIRE PROTECTION (SLEEP LABS) (AHU8) - LVL-2 INTER LVL DAT 65 18-Dec-13 24-Mar-14
DATL2IL-1701 TRIM-OUT MEP (LABS) (AHU17) - LVL-2 INTER LVL DAT 5 03-Feb-14 07-Feb-14
DATL2IL-0301 TRIM-OUT MEP (CARDIO) (AHU3) - LVL-2 INTER LVL DAT 5 18-Jun-14 24-Jun-14
DATL2IL-1401 TRIM-OUT MEP (DENTAL) (AHU14) - LVL-2 INTER LVL DAT 5 18-Jun-14 24-Jun-14
DATL2IL-0801 TRIM-OUT MEP (SLEEP LABS) (AHU8) - LVL-2 INTER LVL DAT 5 31-Jul-14 06-Aug-14
DAT - LEVEL 2 - LADAT - LEVEL 2 - LABSDAT - LEVEL 2 - LABSDAT - LEVEL 2 - LABSDAT - LEVEL 2 - LABS
DATL2LA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 LABS DAT 35 04-Nov-13 24-Dec-13
DATL2LA-0910 FRAMING/INWALL ROUGH - LVL-2 LABS DAT 30 19-Nov-13 02-Jan-14
DATL2LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 LABS DAT 35 04-Dec-13 24-Jan-14
DATL2LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 LABS DAT 65 18-Dec-13 24-Mar-14
DATL2LA-0977 INSTALL OWNER FIXED FF&E - LVL-2 LABS DAT 20 25-Feb-14 24-Mar-14
DATL2LA-8880 CLEAN-UP/PRE PUNCH - LVL-2 LABS DAT 10 25-Mar-14 07-Apr-14
DAT - LEVEL 2 - SLDAT - LEVEL 2 - SLEEP LAB/OFFICESDAT - LEVEL 2 - SLEEP LAB/OFFICESDAT - LEVEL 2 - SLEEP LAB/OFFICESDAT - LEVEL 2 - SLEEP LAB/OFFICES
DATL2SL-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 SLEEP DAT 20 10-Jan-14 07-Feb-14
DATL2SL-0910 FRAMING/INWALL ROUGH - LVL-2 SLEEP DAT 30 25-Mar-14 05-May-14
DATL2SL-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SLEEP DAT 25 22-Apr-14 27-May-14
DATL2SL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SLEEP DAT 45 02-Jul-14 04-Sep-14
DATL2SL-0977 INSTALL OWNER FIXED FF&E - LVL-2 LABS DAT 20 07-Aug-14 04-Sep-14
DATL2SL-8880 CLEAN-UP/PRE PUNCH - LVL-2 SLEEP DAT 10 05-Sep-14 18-Sep-14
DAT - LEVEL 2 - DEDAT - LEVEL 2 - DENTALDAT - LEVEL 2 - DENTALDAT - LEVEL 2 - DENTALDAT - LEVEL 2 - DENTAL
DATL2DE-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 DENTAL DAT 45 18-Feb-14 21-Apr-14
DATL2DE-0910 FRAMING/INWALL ROUGH - LVL-2 DENTAL DAT 45 25-Feb-14 28-Apr-14
DATL2DE-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 DENTAL DAT 25 01-Apr-14 05-May-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 37 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 040
Activity ID Activity Name OrigDur
Start Finish
DATL2DE-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 DENTAL DAT 55 20-May-14 06-Aug-14
DATL2DE-0977 INSTALL OWNER FIXED FF&E - LVL-2 DENTAL DAT 20 10-Jul-14 06-Aug-14
DATL2DE-8880 CLEAN-UP/PRE PUNCH - LVL-2 DENTAL DAT 10 07-Aug-14 20-Aug-14
DAT - LEVEL 2 SOUDAT - LEVEL 2 SOUTH CORRIDORDAT - LEVEL 2 SOUTH CORRIDORDAT - LEVEL 2 SOUTH CORRIDORDAT - LEVEL 2 SOUTH CORRIDOR
DATL2SC-0990 INSTALL INTERIOR FINISHES - LVL-2 SOUTH CORR DAT 55 07-Aug-14 24-Oct-14
DAT - LEVEL 2 - CADAT - LEVEL 2 - CARDIOLOGYDAT - LEVEL 2 - CARDIOLOGYDAT - LEVEL 2 - CARDIOLOGYDAT - LEVEL 2 - CARDIOLOGY
DATL2CA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 CARDIO DAT 35 19-Nov-13 09-Jan-14
DATL2CA-0910 FRAMING/INWALL ROUGH - LVL-2 CARDIO DAT 35 25-Feb-14 14-Apr-14
DATL2CA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 CARDIO DAT 25 18-Mar-14 21-Apr-14
DATL2CA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CARDIO DAT 55 20-May-14 06-Aug-14
DATL2CA-0977 INSTALL OWNER FIXED FF&E - LVL-2 CARDIO DAT 20 10-Jul-14 06-Aug-14
DATL2CA-8880 CLEAN-UP/PRE PUNCH - LVL-2 CARDIO DAT 10 07-Aug-14 20-Aug-14
DAT - LEVEL 3DAT - LEVEL 3DAT - LEVEL 3DAT - LEVEL 3DAT - LEVEL 3DAT - LEVEL 3 - INDAT - LEVEL 3 - INTERSTITIALDAT - LEVEL 3 - INTERSTITIALDAT - LEVEL 3 - INTERSTITIALDAT - LEVEL 3 - INTERSTITIAL
DATL3IL-0600 ROUGH-IN MEP/FIRE PROTECTION (PACU) (AHU6) - LVL-3 INTER LVL DAT 55 29-Aug-13 18-Nov-13
DATL3IL-1300 ROUGH-IN MEP/FIRE PROTECTION (OFFICES) (AHU13) - LVL-3 INTER LVL DAT 65 04-Dec-13 10-Mar-14
DATL3IL-0300 ROUGH-IN MEP/FIRE PROTECTION (CATH) (AHU3) - LVL-3 INTER LVL DAT 55 17-Jan-14 07-Apr-14
DATL3IL-0900 ROUGH-IN MEP/FIRE PROTECTION (ORS) (AHU9) - LVL-3 INTER LVL DAT 50 04-Mar-14 12-May-14
DATL3IL-0601 TRIM-OUT MEP (PACU) (AHU6) - LVL-3 INTER LVL DAT 5 08-Apr-14 14-Apr-14
DATL3IL-1301 TRIM-OUT MEP (OFFICES) (AHU13) - LVL-3 INTER LVL DAT 5 31-Jul-14 06-Aug-14
DATL3IL-0301 TRIM-OUT MEP (CATH) (AHU3) - LVL-3 INTER LVL DAT 5 26-Sep-14 02-Oct-14
DATL3IL-0901 TRIM-OUT MEP (ORS) (AHU9) - LVL-3 INTER LVL DAT 5 27-Oct-14 31-Oct-14
DAT - LEVEL 3 - CADAT - LEVEL 3 - CATH LABSDAT - LEVEL 3 - CATH LABSDAT - LEVEL 3 - CATH LABSDAT - LEVEL 3 - CATH LABS
DATL3CA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 CATH LABS DAT 20 08-Apr-14 05-May-14
DATL3CA-0910 FRAMING/INWALL ROUGH - LVL-3 CATH LABS DAT 35 22-Apr-14 10-Jun-14
DATL3CA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 CATH LABS DAT 25 28-May-14 01-Jul-14
DATL3CA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CATH LABS DAT 65 14-Aug-14 17-Nov-14
DATL3CA-0977 INSTALL OWNER FIXED FF&E - LVL-3 CATH LABS DAT 20 17-Oct-14 17-Nov-14
DATL3CA-8880 CLEAN-UP/PRE PUNCH - LVL-3 CATH LABS DAT 10 18-Nov-14 02-Dec-14
DAT - LEVEL 3 - OPDAT - LEVEL 3 - OPERATING ROOMSDAT - LEVEL 3 - OPERATING ROOMSDAT - LEVEL 3 - OPERATING ROOMSDAT - LEVEL 3 - OPERATING ROOMS
DATL3OR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 ORS DAT 45 13-May-14 16-Jul-14
DATL3OR-0910 FRAMING/INWALL ROUGH - LVL-3 ORS DAT 55 20-May-14 06-Aug-14
DATL3OR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 ORS DAT 35 02-Jul-14 20-Aug-14
DATL3OR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 ORS DAT 75 12-Sep-14 31-Dec-14
DATL3OR-0977 INSTALL OWNER FIXED FF&E - LVL-3 CATH LABS DAT 20 03-Dec-14 31-Dec-14
DATL3OR-8880 CLEAN-UP/PRE PUNCH - LVL-3 ORS DAT 10 02-Jan-15 15-Jan-15
DAT - LEVEL 3DAT - LEVEL 3 - HYBRID CVORDAT - LEVEL 3 - HYBRID CVORDAT - LEVEL 3 - HYBRID CVORDAT - LEVEL 3 - HYBRID CVOR
DATL3HY-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 HYBRID CVOR DAT 5 17-Jul-14 23-Jul-14
DATL3HY-0910 FRAMING/INWALL ROUGH - LVL-3 HYBRID CVOR DAT 20 17-Jul-14 13-Aug-14
DATL3HY-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 HYBRID CVOR DAT 10 14-Aug-14 27-Aug-14
DATL3HY-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 HYBRID CVOR DAT 30 12-Sep-14 24-Oct-14
DATL3HY-0977 INSTALL OWNER FIXED FF&E - LVL-3 HYBRID CVOR DAT 20 26-Sep-14 24-Oct-14
DATL3HY-8880 CLEAN-UP/PRE PUNCH - LVL-3 HYBRID CVOR DAT 5 27-Oct-14 31-Oct-14
DAT - LEVEL 3 - PADAT - LEVEL 3 - PACUDAT - LEVEL 3 - PACUDAT - LEVEL 3 - PACUDAT - LEVEL 3 - PACU
DATL3PA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 PACU DAT 35 26-Dec-13 17-Feb-14
DATL3PA-0910 FRAMING/INWALL ROUGH - LVL-3 PACU DAT 45 26-Dec-13 03-Mar-14
DATL3PA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 PACU DAT 25 03-Feb-14 10-Mar-14
DATL3PA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PACU DAT 65 04-Mar-14 03-Jun-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 38 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 041
Activity ID Activity Name OrigDur
Start Finish
DATL3PA-0977 INSTALL OWNER FIXED FF&E - LVL-3 PACU LABS DAT 20 06-May-14 03-Jun-14
DATL3PA-8880 CLEAN-UP/PRE PUNCH - LVL-3 PACU DAT 10 04-Jun-14 17-Jun-14
DAT - LEVEL 3 - DIDAT - LEVEL 3 - DIGESTIVE DISEASESDAT - LEVEL 3 - DIGESTIVE DISEASESDAT - LEVEL 3 - DIGESTIVE DISEASESDAT - LEVEL 3 - DIGESTIVE DISEASES
DATL3DI-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 DIGEST DIS DAT 20 22-Apr-14 19-May-14
DATL3DI-0910 FRAMING/INWALL ROUGH - LVL-3 DIGEST DIS DAT 30 22-Apr-14 03-Jun-14
DATL3DI-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 DIGEST DIS DAT 25 06-May-14 10-Jun-14
DATL3DI-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 DIGEST DIS DAT 45 02-Jul-14 04-Sep-14
DATL3DI-0977 INSTALL OWNER FIXED FF&E - LVL-3 DIGEST DIS DAT 20 07-Aug-14 04-Sep-14
DATL3DI-8880 CLEAN-UP/PRE PUNCH - LVL-3 DIGEST DIS DAT 10 05-Sep-14 18-Sep-14
DAT - LEVEL 3 - SUDAT - LEVEL 3 - SURGERY OFFICESDAT - LEVEL 3 - SURGERY OFFICESDAT - LEVEL 3 - SURGERY OFFICESDAT - LEVEL 3 - SURGERY OFFICES
DATL3OF-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 OFFICES DAT 20 20-May-14 17-Jun-14
DATL3OF-0910 FRAMING/INWALL ROUGH - LVL-3 OFFICES DAT 25 20-May-14 24-Jun-14
DATL3OF-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 OFFICES DAT 20 04-Jun-14 01-Jul-14
DATL3OF-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 OFFICES DAT 40 18-Jun-14 13-Aug-14
DATL3OF-0977 INSTALL OWNER FIXED FF&E - LVL-3 CATH OFFICES DAT 20 17-Jul-14 13-Aug-14
DATL3OF-8880 CLEAN-UP/PRE PUNCH - LVL-3 OFFICES DAT 10 14-Aug-14 27-Aug-14
DAT - LEVEL 3 - SODAT - LEVEL 3 - SOUTH CORRIDORDAT - LEVEL 3 - SOUTH CORRIDORDAT - LEVEL 3 - SOUTH CORRIDORDAT - LEVEL 3 - SOUTH CORRIDOR
DATL3SC-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 SOUTH CORR DAT 7 02-Jul-14 11-Jul-14
DATL3SC-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SOUTH CORR DAT 20 14-Jul-14 08-Aug-14
DATL3SC-8880 CLEAN-UP/PRE PUNCH - LVL-3 SOUTH CORR DAT 5 11-Aug-14 15-Aug-14
DAT - NORTH PDAT - NORTH PENTHOUSEDAT - NORTH PENTHOUSEDAT - NORTH PENTHOUSEDAT - NORTH PENTHOUSEDAT - NORTH PENDAT - NORTH PENTHOUSE - MECHANICAL ROOMSDAT - NORTH PENTHOUSE - MECHANICAL ROOMSDAT - NORTH PENTHOUSE - MECHANICAL ROOMSDAT - NORTH PENTHOUSE - MECHANICAL ROOMS
DATPHNP-0420 LAY CMU WALLS - NORTH PENT MECH DAT 15 25-Feb-13 15-Mar-13
DATPHNP-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - NORTH PENT MECH DAT 45 20-Mar-13 21-May-13
DATPHNP-1520 CONNECT/PIPE-UP MECH EQUIP - NORTH PENT MECH DAT 60 22-May-13 15-Aug-13
DATPHNP-1641 START-UP ELECTRICAL SYSTEMS - NORTH PENT MECH DAT 30 24-Oct-13 06-Dec-13
DATPHNP-1590 START-UP MECH EQUIP - NORTH PENT MECH DAT 30 19-Sep-14 31-Oct-14
DAT - NORTH PENDAT - NORTH PENTHOUSE - ELECTRICAL ROOMSDAT - NORTH PENTHOUSE - ELECTRICAL ROOMSDAT - NORTH PENTHOUSE - ELECTRICAL ROOMSDAT - NORTH PENTHOUSE - ELECTRICAL ROOMS
DATPHNP-0910 FRAMING/INWALL ROUGH - NORTH PENT ELEC DAT 25 10-Apr-13 14-May-13
DATPHNP-0920 HANG/TAPE/FINISH DRYWALL - NORTH PENT ELEC DAT 15 15-May-13 05-Jun-13
DATPHNP-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - NORTH PENT ELEC DAT 75 06-Jun-13 20-Sep-13
DAT - SOUTH PEDAT - SOUTH PENTHOUSEDAT - SOUTH PENTHOUSEDAT - SOUTH PENTHOUSEDAT - SOUTH PENTHOUSEDAT - SOUTH PENTDAT - SOUTH PENTHOUSE - ELECTRICAL ROOMSDAT - SOUTH PENTHOUSE - ELECTRICAL ROOMSDAT - SOUTH PENTHOUSE - ELECTRICAL ROOMSDAT - SOUTH PENTHOUSE - ELECTRICAL ROOMS
DATPHSP-0910 FRAMING/INWALL ROUGH - SOUTH PENT ELEC DAT 25 26-Mar-13 29-Apr-13
DATPHSP-0920 HANG/TAPE/FINISH DRYWALL - SOUTH PENT ELEC DAT 15 30-Apr-13 20-May-13
DATPHSP-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - SOUTH PENT ELEC DAT 75 09-Jul-13 23-Oct-13
DAT - SOUTH PENTDAT - SOUTH PENTHOUSE - MECHANICAL ROOMSDAT - SOUTH PENTHOUSE - MECHANICAL ROOMSDAT - SOUTH PENTHOUSE - MECHANICAL ROOMSDAT - SOUTH PENTHOUSE - MECHANICAL ROOMS
DATPHSP-0420 LAY CMU WALLS - SOUTH PENT DAT 15 08-Feb-13 01-Mar-13
DATPHSP-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - SOUTH PENT MECH DAT 50 05-Mar-13 13-May-13
DATPHSP-1520 CONNECT/PIPE-UP MECH EQUIP - SOUTH PENT MECH DAT 60 14-May-13 07-Aug-13
DATPHSP-1641 START-UP ELECTRICAL SYSTEMS - SOUTH PENT MECH DAT 30 24-Oct-13 06-Dec-13
DATPHSP-1590 START-UP MECH EQUIP - SOUTH PENT MECH DAT 30 03-Oct-14 17-Nov-14
DAT - ALL LEVEDAT - ALL LEVELSDAT - ALL LEVELSDAT - ALL LEVELSDAT - ALL LEVELSDATALAL-0502 ERECT STAIRS (ST2)- ALL LVLS DAT 15 24-Dec-12 15-Jan-13
DATALAL-0501 ERECT STAIRS (ST1) - ALL LVLS DAT 15 09-Jan-13 31-Jan-13
DATALAL-0503 ERECT STAIRS (ST3) - ALL LVLS DAT 15 25-Jan-13 15-Feb-13
DATALAL-0505 ERECT STAIRS (ST5) - ALL LVLS DAT 15 08-Feb-13 04-Mar-13
DATALAL-1456 INSTALL ELEVATORS (PE5/6) - ALL LVLS DAT 120 20-Jun-13 08-Jan-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 39 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 042
Activity ID Activity Name OrigDur
Start Finish
DATALAL-1467 INSTALL ELEVATORS (SE6/7) - ALL LVLS DAT 120 20-Jun-13 08-Jan-14
DATALAL-1410 INSTALL ELEVATOR (SE10) - ALL LVLS DAT 60 02-Oct-13 08-Jan-14
DATALAL-1409 INSTALL ELEVATOR (SE9) - ALL LVLS DAT 60 02-Oct-13 08-Jan-14
DATALAL-0992 FINISH STAIR CORE (ST2) - ALL LVLS DAT 30 18-Nov-14 31-Dec-14
DATALAL-0991 FINISH STAIR CORE (ST1) - ALL LVLS DAT 30 18-Nov-14 31-Dec-14
DATALAL-0993 FINISH STAIR CORE (ST3) - ALL LVLS DAT 30 10-Dec-14 23-Jan-15
DATALAL-0995 FINISH STAIR CORE (ST5) - ALL LVLS DAT 30 10-Dec-14 23-Jan-15
D&T BUILDING (D&T BUILDING (DAT) - COMMISSIONINGD&T BUILDING (DAT) - COMMISSIONINGD&T BUILDING (DAT) - COMMISSIONINGD&T BUILDING (DAT) - COMMISSIONINGDATALCL-1592 TEST & BALANCE - DAT 60 17-Oct-14 15-Jan-15
DATALCL-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - DAT 45 17-Oct-14 23-Dec-14
DATALCL-1596 FUNCTIONAL TESTING/CORRECTIONS - DAT 45 03-Dec-14 06-Feb-15
DATALCL-9999 CREATE/COMPLETE FINAL PUNCHLIST - DAT 30 17-Dec-14 30-Jan-15
DATALCL-1599 BUILDING FLUSH - DAT 20 07-Feb-15 26-Feb-15
PARKING VISIPARKING VISITOR SOUTH (PVS)PARKING VISITOR SOUTH (PVS)PARKING VISITOR SOUTH (PVS)PARKING VISITOR SOUTH (PVS)PVS - SITEWORKPVS - SITEWORK - ALL AREASPVS - SITEWORK - ALL AREASPVS - SITEWORK - ALL AREASPVS - SITEWORK - ALL AREASPVSSWSW-3220 INSTALL DEWATERING SYSTEM - PVS SITEWORK 20 13-Jan-12 13-Feb-12
PVSSWSW-3210 RELOCATE CBS ROOF DRAIN - PVS SITEWORK 10 23-Jan-12 06-Feb-12
PVSSWSW-3130 DRIVE SOLDIER PILES - PVS SITEWORK 10 23-Jan-12 06-Feb-12
PVSSWSW-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PVS SITEWORK 115 06-Feb-12 21-Jun-12
PVSSWSW-3230 DRIVE SOLDIER PILES (REMAINING EAST SIDE) - PVS SITEWORK 10 29-May-12 14-Jun-12
PVSSWSW-3250 BACKFILL RAMP (EAST SIDE) - PVS SITEWORK 5 01-Jun-12 11-Jun-12
PVSSWSW-3240 SHORING(REMAINING EAST SIDE) - PVS SITEWORK 15 14-Jun-12 02-Jul-12
PARKING VISITOPARKING VISITOR SOUTH (PVS) - STRUCTUREPARKING VISITOR SOUTH (PVS) - STRUCTUREPARKING VISITOR SOUTH (PVS) - STRUCTUREPARKING VISITOR SOUTH (PVS) - STRUCTUREPVS - PARKINGPVS - PARKING LEVEL 3PVS - PARKING LEVEL 3PVS - PARKING LEVEL 3PVS - PARKING LEVEL 3PVS - PARKING LEPVS - PARKING LEVEL 3 - AREA APVS - PARKING LEVEL 3 - AREA APVS - PARKING LEVEL 3 - AREA APVS - PARKING LEVEL 3 - AREA A
PVSP3AA-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA A PVS 14 21-Jun-12 16-Jul-12
PVSP3AA-0355 WATERPROOF/REINFORCE/SHOTCRETE SOUTH WALL - PKG LVL-3 AREA A PVS 30 29-Jun-12 21-Aug-12
PVSP3AA-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA A PVS 4 13-Jul-12 20-Jul-12
PVSP3AA-0332 FORM/PLACE FTGS/COLUMNS - PKG LVL-3 AREA A PVS 15 16-Jul-12 10-Aug-12
PVSP3AA-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA A PVS 5 21-Aug-12 30-Aug-12
PVSP3AA-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA A PVS 10 30-Aug-12 17-Sep-12
PVS - PARKING LEPVS - PARKING LEVEL 3 - AREA BPVS - PARKING LEVEL 3 - AREA BPVS - PARKING LEVEL 3 - AREA BPVS - PARKING LEVEL 3 - AREA B
PVSP3AB-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA B PVS 14 16-Jul-12 09-Aug-12
PVSP3AB-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA B PVS 4 08-Aug-12 14-Aug-12
PVSP3AB-0332 FORM/PLACE FTGS/WALLS/COLUMNS - PKG LVL-3 AREA B PVS 20 09-Aug-12 13-Sep-12
PVSP3AB-0335 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA B PVS 20 09-Aug-12 13-Sep-12
PVSP3AB-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA B PVS 5 13-Sep-12 21-Sep-12
PVSP3AB-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA B PVS 10 21-Sep-12 08-Oct-12
PVS - PARKING LEPVS - PARKING LEVEL 3 - AREA CPVS - PARKING LEVEL 3 - AREA CPVS - PARKING LEVEL 3 - AREA CPVS - PARKING LEVEL 3 - AREA C
PVSP3AC-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA C PVS 14 09-Aug-12 04-Sep-12
PVSP3AC-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA C PVS 4 31-Aug-12 07-Sep-12
PVSP3AC-0332 FORM/PLACE FTGS/COLUMNS - PKG LVL-3 AREA C PVS 15 04-Sep-12 28-Sep-12
PVSP3AC-0335 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA D PVS 12 04-Sep-12 24-Sep-12
PVSP3AC-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA C PVS 5 28-Sep-12 05-Oct-12
PVSP3AC-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA C PVS 10 05-Oct-12 23-Oct-12
PVS - PARKING LEPVS - PARKING LEVEL 3 - AREA DPVS - PARKING LEVEL 3 - AREA DPVS - PARKING LEVEL 3 - AREA DPVS - PARKING LEVEL 3 - AREA D
PVSP3AD-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA D PVS 14 21-Jun-12 16-Jul-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 40 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 043
Activity ID Activity Name OrigDur
Start Finish
PVSP3AD-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA D PVS 4 13-Jul-12 20-Jul-12
PVSP3AD-0332 FORM/PLACE FTGS/WALLS/COLUMNS - PKG LVL-3 AREA D PVS 15 20-Jul-12 16-Aug-12
FL2P3AD-0355 WATERPROOF/REINFORCE/SHOTCRETE EAST WALL - PKG LVL-3 AREA D PVS 12 21-Aug-12 11-Sep-12
PVSP3AD-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA D PVS 5 11-Sep-12 20-Sep-12
PVSP3AD-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA D PVS 10 20-Sep-12 05-Oct-12
PVS - PARKING LEPVS - PARKING LEVEL 3 - AREA EPVS - PARKING LEVEL 3 - AREA EPVS - PARKING LEVEL 3 - AREA EPVS - PARKING LEVEL 3 - AREA E
PVSP3AE-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA E PVS 14 16-Jul-12 09-Aug-12
PVSP3AE-0335 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA E PVS 21 09-Aug-12 14-Sep-12
PVSP3AE-3220 FORM/PLACE PIER CAPS - PKG LVL-3 AREA E PVS 4 09-Aug-12 16-Aug-12
PVSP3AE-0332 FORM/PLACE FTGS/ COLUMNS - PKG LVL-3 AREA E PVS 15 09-Aug-12 05-Sep-12
PVSP3AE-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA E PVS 5 14-Sep-12 24-Sep-12
PVSP3AE-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA E PVS 10 03-Oct-12 19-Oct-12
PVS - PARKING LEPVS - PARKING LEVEL 3 - AREA FPVS - PARKING LEVEL 3 - AREA FPVS - PARKING LEVEL 3 - AREA FPVS - PARKING LEVEL 3 - AREA F
PVSP3AF-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA F PVS 14 09-Aug-12 04-Sep-12
PVSP3AF-0330 FORM/PLACE TOWER CRANE #2 BASE - (PVS) 35 24-Aug-12 23-Oct-12
PVSP3AF-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA F PVS 4 31-Aug-12 07-Sep-12
PVSP3AF-0332 FORM/PLACE ELEV PITS/ FTGS/WALLS/COLUMNS - PKG LVL-3 AREA F PVS 15 04-Sep-12 28-Sep-12
PVSP3AF-0335 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA F PVS 25 04-Sep-12 12-Oct-12
PVSP3AF-3220 REMOVE ACCESS RAMP/INFILL WALL - PKG LVL-3 AREA F PVS 20 28-Sep-12 30-Oct-12
PVSP3AF-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA F PVS 5 12-Oct-12 23-Oct-12
PVSP3AF-3230 BACKFILL RAMP - PKG LVL-3 AREA F PVS 5 23-Oct-12 30-Oct-12
PVSP3AF-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA F PVS 10 30-Oct-12 16-Nov-12
PVSP3AF-3240 FORM/PLACE/FINISH RAMP - PKG LVL-3 AREA F PVS 10 30-Oct-12 16-Nov-12
PVS - PARKINGPVS - PARKING LEVEL 2PVS - PARKING LEVEL 2PVS - PARKING LEVEL 2PVS - PARKING LEVEL 2PVS - PARKING LEPVS - PARKING LEVEL 2 - AREA APVS - PARKING LEVEL 2 - AREA APVS - PARKING LEVEL 2 - AREA APVS - PARKING LEVEL 2 - AREA A
PVSP2AA-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA A PVS 12 05-Nov-12 23-Nov-12
PVSP2AA-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA A PVS 12 26-Nov-12 13-Dec-12
PVS - PARKING LEPVS - PARKING LEVEL 2 - AREA BPVS - PARKING LEVEL 2 - AREA BPVS - PARKING LEVEL 2 - AREA BPVS - PARKING LEVEL 2 - AREA B
PVSP2AB-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA B PVS 10 14-Nov-12 29-Nov-12
PVSP2AB-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA B PVS 12 30-Nov-12 18-Dec-12
PVS - PARKING LEPVS - PARKING LEVEL 2 - AREA CPVS - PARKING LEVEL 2 - AREA CPVS - PARKING LEVEL 2 - AREA CPVS - PARKING LEVEL 2 - AREA C
PVSP2AC-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA C PVS 10 21-Nov-12 07-Dec-12
PVSP2AC-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA C PVS 12 10-Dec-12 27-Dec-12
PVS - PARKING LEPVS - PARKING LEVEL 2 - AREA DPVS - PARKING LEVEL 2 - AREA DPVS - PARKING LEVEL 2 - AREA DPVS - PARKING LEVEL 2 - AREA D
PVSP2AD-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA D PVS 10 30-Nov-12 14-Dec-12
PVSP2AD-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA D PVS 12 17-Dec-12 04-Jan-13
PVS - PARKING LEPVS - PARKING LEVEL 2 - AREA EPVS - PARKING LEVEL 2 - AREA EPVS - PARKING LEVEL 2 - AREA EPVS - PARKING LEVEL 2 - AREA E
PVSP2AE-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA E PVS 10 10-Dec-12 24-Dec-12
PVSP2AE-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA E PVS 12 26-Dec-12 11-Jan-13
PVS - PARKING LEPVS - PARKING LEVEL 2 - AREA FPVS - PARKING LEVEL 2 - AREA FPVS - PARKING LEVEL 2 - AREA FPVS - PARKING LEVEL 2 - AREA F
PVSP2AF-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA F PVS 10 17-Dec-12 02-Jan-13
PVSP2AF-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA F PVS 12 03-Jan-13 22-Jan-13
PVSP2AF-0325 FORM/PLACE FINISH RAMP - PKG LVL-2 AREA F PVS 15 24-Jan-13 14-Feb-13
PVS - PARKINGPVS - PARKING LEVEL 1PVS - PARKING LEVEL 1PVS - PARKING LEVEL 1PVS - PARKING LEVEL 1PVS - PARKING LEPVS - PARKING LEVEL 1 - AREA APVS - PARKING LEVEL 1 - AREA APVS - PARKING LEVEL 1 - AREA APVS - PARKING LEVEL 1 - AREA A
PVSP1AA-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA A PVS 10 10-Dec-12 24-Dec-12
PVSP1AA-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA A PVS 12 26-Dec-12 11-Jan-13
PVSP1AA-1620 ROUGH-IN/INSTALL SUBSTATION - PKG LVL-1 AREA A PVS 10 01-Feb-13 18-Feb-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 41 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 044
Activity ID Activity Name OrigDur
Start Finish
PVSP1AA-1666 PULL WIRE FROM CON - PKG LVL-1 AREA A PVS 5 18-Feb-13 25-Feb-13
PVSP1AA-1641 START-UP ELECTRICAL SYSTEMS (pvs/con) - PKG LVL-1 AREA A PVS 30 18-Oct-13 03-Dec-13
PVS - PARKING LEPVS - PARKING LEVEL 1 - AREA BPVS - PARKING LEVEL 1 - AREA BPVS - PARKING LEVEL 1 - AREA BPVS - PARKING LEVEL 1 - AREA B
PVSP1AB-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA B PVS 10 17-Dec-12 02-Jan-13
PVSP1AB-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA B PVS 12 03-Jan-13 22-Jan-13
PVS - PARKING LEPVS - PARKING LEVEL 1 - AREA CPVS - PARKING LEVEL 1 - AREA CPVS - PARKING LEVEL 1 - AREA CPVS - PARKING LEVEL 1 - AREA C
PVSP1AC-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA C PVS 10 26-Dec-12 09-Jan-13
PVSP1AC-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA C PVS 12 10-Jan-13 29-Jan-13
PVS - PARKING LEPVS - PARKING LEVEL 1 - AREA DPVS - PARKING LEVEL 1 - AREA DPVS - PARKING LEVEL 1 - AREA DPVS - PARKING LEVEL 1 - AREA D
PVSP1AD-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA D PVS 10 03-Jan-13 17-Jan-13
PVSP1AD-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA D PVS 12 18-Jan-13 05-Feb-13
PVS - PARKING LEPVS - PARKING LEVEL 1 - AREA EPVS - PARKING LEVEL 1 - AREA EPVS - PARKING LEVEL 1 - AREA EPVS - PARKING LEVEL 1 - AREA E
PVSP1AE-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA E PVS 10 10-Jan-13 25-Jan-13
PVSP1AE-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA E PVS 12 28-Jan-13 12-Feb-13
PVSP1AE-1620 ROUGH-IN/INSTALL SUBSTATION - PKG LVL-1 AREA E PVS 10 26-Mar-13 08-Apr-13
PVSP1AE-1666 PULL WIRE FROM CON - PKG LVL-1 AREA E PVS 5 09-Apr-13 15-Apr-13
PVSP1AE-1641 START-UP ELECTRICAL SYSTEMS (pvs/con) - PKG LVL-1 AREA E PVS 20 18-Oct-13 18-Nov-13
PVS - PARKING LEPVS - PARKING LEVEL 1 - AREA FPVS - PARKING LEVEL 1 - AREA FPVS - PARKING LEVEL 1 - AREA FPVS - PARKING LEVEL 1 - AREA F
PVSP1AF-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA F PVS 10 18-Jan-13 01-Feb-13
PVSP1AF-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA F PVS 12 04-Feb-13 21-Feb-13
PVSP1AF-0332 FORM/PLACE FINISH RAMP - PKG LVL-1 AREA F PVS 15 25-Feb-13 19-Mar-13
PVS - PARKINGPVS - PARKING LEVEL 0PVS - PARKING LEVEL 0PVS - PARKING LEVEL 0PVS - PARKING LEVEL 0PVS - LEVEL 0 - ARPVS - LEVEL 0 - AREA APVS - LEVEL 0 - AREA APVS - LEVEL 0 - AREA APVS - LEVEL 0 - AREA A
PVSP0AA-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA A PVS 10 18-Jan-13 01-Feb-13
PVS - LEVEL 0 - ARPVS - LEVEL 0 - AREA BPVS - LEVEL 0 - AREA BPVS - LEVEL 0 - AREA BPVS - LEVEL 0 - AREA B
PVSP0AB-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA B PVS 10 31-Jan-13 14-Feb-13
PVS - LEVEL 0 - ARPVS - LEVEL 0 - AREA CPVS - LEVEL 0 - AREA CPVS - LEVEL 0 - AREA CPVS - LEVEL 0 - AREA C
PVSP0AC-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA C PVS 10 12-Feb-13 27-Feb-13
PVS - LEVEL 0 - ARPVS - LEVEL 0 - AREA DPVS - LEVEL 0 - AREA DPVS - LEVEL 0 - AREA DPVS - LEVEL 0 - AREA D
PVSP0AD-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA D PVS 10 26-Feb-13 12-Mar-13
PVS - LEVEL 0 - ARPVS - LEVEL 0 - AREA EPVS - LEVEL 0 - AREA EPVS - LEVEL 0 - AREA EPVS - LEVEL 0 - AREA E
PVSP0AE-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA E PVS 10 11-Mar-13 25-Mar-13
PVS - LEVEL 0 - ARPVS - LEVEL 0 - AREA FPVS - LEVEL 0 - AREA FPVS - LEVEL 0 - AREA FPVS - LEVEL 0 - AREA F
PVSP0AF-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA F PVS 10 21-Mar-13 05-Apr-13
PARKING VISITOPARKING VISITOR SOUTH (PVS) - INTERIOR BUILDOUTPARKING VISITOR SOUTH (PVS) - INTERIOR BUILDOUTPARKING VISITOR SOUTH (PVS) - INTERIOR BUILDOUTPARKING VISITOR SOUTH (PVS) - INTERIOR BUILDOUTPVS - PARKINGPVS - PARKING LEVEL 1PVS - PARKING LEVEL 1PVS - PARKING LEVEL 1PVS - PARKING LEVEL 1PVSINP1-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-3 PVS 30 29-May-13 10-Jul-13
PVSINP1-0990 GARAGE FINISHES - - PKG LVL-3 PVS 30 11-Jul-13 21-Aug-13
PVSINP1-8880 CLEAN-UP/PRE PUNCH - PKG LVL-3 PVS 10 22-Aug-13 05-Sep-13
PVS - PARKINGPVS - PARKING LEVEL 2PVS - PARKING LEVEL 2PVS - PARKING LEVEL 2PVS - PARKING LEVEL 2PVSINP2-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-2 PVS 30 26-Jun-13 07-Aug-13
PVSINP2-0990 GARAGE FINISHES - PKG LVL-2 PVS 30 08-Aug-13 19-Sep-13
PVSINP2-8880 CLEAN-UP/PRE PUNCH - PKG LVL-2 PVS 10 20-Sep-13 03-Oct-13
PVS - PARKINGPVS - PARKING LEVEL 3PVS - PARKING LEVEL 3PVS - PARKING LEVEL 3PVS - PARKING LEVEL 3PVSINP3-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-1 PVS 30 25-Jul-13 05-Sep-13
PVSINP3-0990 GARAGE FINISHES - PKG LVL-1 PVS 30 06-Sep-13 17-Oct-13
PVSINP3-8880 CLEAN-UP/PRE PUNCH - PKG LVL-1 PVS 10 18-Oct-13 01-Nov-13
PVS - LEVEL 0PVS - LEVEL 0PVS - LEVEL 0PVS - LEVEL 0PVS - LEVEL 0PVSINL0-0750 APPLY WATERPROOFING- PKG LVL-0 PVS 30 08-Apr-13 17-May-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 42 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 045
Activity ID Activity Name OrigDur
Start Finish
PVSINL0-0320 INSTALL RIDGID INSULATION/PLACE TOPPING SLAB - PKG LVL-0 PVS 15 13-May-13 03-Jun-13
PVS - ALL LEVEPVS - ALL LEVELSPVS - ALL LEVELSPVS - ALL LEVELSPVS - ALL LEVELSPVSALAL-0555 ERECT STAIRS ST1 - ALL LVLS PVS 20 08-Apr-13 03-May-13
PVSALAL-0556 ERECT STAIRS ST2 - ALL LVLS PVS 20 18-Apr-13 15-May-13
PVSALAL-0557 ERECT STAIRS ST3 - ALL LVLS PVS 20 30-Apr-13 28-May-13
PVSALAL-0990 FINISH STAIR CORES ST1/ST2/ST3 - ALL LVLS PVS 25 07-May-13 11-Jun-13
PVSALAL-1400 INSTALL ELEVATOR PGE15/PGE16X - ALL LVLS PVS 60 04-Oct-13 02-Jan-14
PARKING VISITOPARKING VISITOR SOUTH (PVS) - COMMISSIONINGPARKING VISITOR SOUTH (PVS) - COMMISSIONINGPARKING VISITOR SOUTH (PVS) - COMMISSIONINGPARKING VISITOR SOUTH (PVS) - COMMISSIONINGPVSALCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - ALL LVLS PVS 30 04-Dec-13 16-Jan-14
PVSALCO-1592 TEST & BALANCE - ALL LVLS PVS 20 24-Dec-13 12-Jan-14
PVSALCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS PVS 10 24-Dec-13 08-Jan-14
PVSALCO-1596 FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS PVS 15 09-Jan-14 30-Jan-14
PARKING VISIPARKING VISITOR NORTH (PVN)PARKING VISITOR NORTH (PVN)PARKING VISITOR NORTH (PVN)PARKING VISITOR NORTH (PVN)PARKING VISITOPARKING VISITOR NORTH (PVN) - STRUCTUREPARKING VISITOR NORTH (PVN) - STRUCTUREPARKING VISITOR NORTH (PVN) - STRUCTUREPARKING VISITOR NORTH (PVN) - STRUCTUREPVNSLSL-3130 DRIVE SOLDIER PILES - SERV LVL PVN 10 01-Aug-13 16-Aug-13
PVNSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL PVN 30 17-Aug-13 21-Sep-13
PVN - LOADINGPVN - LOADING DOCK/SERVICE LEVELPVN - LOADING DOCK/SERVICE LEVELPVN - LOADING DOCK/SERVICE LEVELPVN - LOADING DOCK/SERVICE LEVELPVN - DOCK SIDEPVN - DOCK SIDEPVN - DOCK SIDEPVN - DOCK SIDEPVN - DOCK SIDE
PVNSLDO-0320 DRILL/PLACE CAISSONS - SERV LVL DOCK PVN 10 23-Sep-13 07-Oct-13
PVNSLDO-0322 FORM/PLACE FOUNDATION WALLS/ELEVATOR PITS - SERV LVL DOCK PVN 45 08-Oct-13 20-Dec-13
PVNSLDO-0350 POUR PIER CAPS - SERV LVL DOCK PVN 10 12-Nov-13 26-Nov-13
PVNSLDO-0390 FORM/PLACE COLUMNS - SERV LVL DOCK PVN 10 15-Nov-13 02-Dec-13
PVNSLDO-0352 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL DOCK PVN 5 03-Dec-13 10-Dec-13
PVNSLDO-0288 BACKFILL DOCK WALLS - SERV LVL DOCK PVN 5 13-Dec-13 20-Dec-13
PVN - PARKING SIPVN - PARKING SIDEPVN - PARKING SIDEPVN - PARKING SIDEPVN - PARKING SIDE
PVNSLPK-0350 POUR PIER CAPS - SERV LVL PVN - SERV LVL PARK PVN 10 04-Oct-13 21-Oct-13
PVNSLPK-0320 DRILL/PLACE CAISSONS - SERV LVL PARK PVN 10 04-Oct-13 21-Oct-13
PVNSLPK-0322 FORM/PLACE FOUNDATION WALLS - SERV LVL PARK PVN 30 11-Oct-13 02-Dec-13
PVNSLPK-0323 FORM/PLACE RAMP WALLS - SERV LVL PARK PVN 30 29-Oct-13 17-Dec-13
PVNSLPK-0244 BACKFILL FOUNDATION WALLS - SERV LVL PARK PVN 10 25-Nov-13 10-Dec-13
PVNSLPK-0266 BELOW GRADE UTILITY ROUGH-IN - SERV LVL PARK PVN 10 11-Dec-13 26-Dec-13
PVNSLPK-0245 BACKFILL DOCK FOUNDATION WALLS - SERV LVL PARK PVN 10 07-Jan-14 22-Jan-14
PVNSLPK-0344 FORM/PLACE SOG/EQUIPMENT PADS - SERV LVL PARK PVN 20 23-Jan-14 20-Feb-14
PVNSLPK-1676 DRILL/PLACE BALANCE OF CAISSONS - SERV LVL PARK PVN 5 23-Jan-14 29-Jan-14
PVNSLPK-1620 ROUGH-IN/INSTALL SUBSTATION - SERV LVL PARK PVN 10 21-Feb-14 06-Mar-14
PVNSLPK-1641 START-UP ELECTRICAL SYSTEMS (pvn/con) - SERV LVL PARK PVN 30 13-Aug-14 24-Sep-14
PVNSLPK-1666 PULL WIRE FROM CON - SER LVL PARK PVN 5 25-Sep-14 01-Oct-14
PVN - DOCK SIDPVN - DOCK SIDE LEVEL 1PVN - DOCK SIDE LEVEL 1PVN - DOCK SIDE LEVEL 1PVN - DOCK SIDE LEVEL 1PVNSLDO-0366 FORM/PLACE/TENSION DOCK LID - SERV LVL DOCK PVN 21 03-Dec-13 06-Jan-14
PVNSLDO-0730 WATERPROOFING/FINISH DOCK LID - SERV LVL DOCK PVN 20 07-Jan-14 05-Feb-14
PVNSLDO-0560 ERECT STRUCTURAL STEEL/CORES/ROOF - SERV LVL DOCK PVN 25 14-Aug-14 25-Sep-14
PVNSLDO-0370 FORM/REINFORCE/PLACE COMD - SERV LVL DOCK PVN 5 05-Sep-14 12-Sep-14
PVN - PARKINGPVN - PARKING SIDE LEVELS 1 - 5PVN - PARKING SIDE LEVELS 1 - 5PVN - PARKING SIDE LEVELS 1 - 5PVN - PARKING SIDE LEVELS 1 - 5PVNALAL-0310 FORM/PLACE/TENSION DECKS - LVLS 1-5 PVN 100 21-Feb-14 12-Aug-14
PARKING VISITOPARKING VISITOR NORTH (PVN) - EXTERIOR SKINSPARKING VISITOR NORTH (PVN) - EXTERIOR SKINSPARKING VISITOR NORTH (PVN) - EXTERIOR SKINSPARKING VISITOR NORTH (PVN) - EXTERIOR SKINSPVNESES-0750 INSTALL EXTERIOR SKIN FINISHES @ GARAGE - ALL ELEVATIONS PVN 50 14-Aug-14 04-Nov-14
PVNESES-750 INSTALL CURTAIN WALL @ ELEVATOR/STAIR CORE - ALL ELEVATIONS PVN 25 26-Sep-14 04-Nov-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 43 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 046
Activity ID Activity Name OrigDur
Start Finish
PVN - ROOF LEVPVN - ROOF LEVELPVN - ROOF LEVELPVN - ROOF LEVELPVN - ROOF LEVELPVNESRL-1600 INSTALL ROOF TRELLIS SYSTEM - ROOF LVL PVN 20 14-Aug-14 16-Sep-14
PVNESRL-1610 INSTALL GLASS ROOFING SYSTEM - ROOF LVL PVN 40 18-Sep-14 21-Nov-14
PVNESRL-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - ROOF LVL PVN 10 24-Nov-14 09-Dec-14
PARKING VISITOPARKING VISITOR NORTH (PVN) - INTERIOR BUILDOUTPARKING VISITOR NORTH (PVN) - INTERIOR BUILDOUTPARKING VISITOR NORTH (PVN) - INTERIOR BUILDOUTPARKING VISITOR NORTH (PVN) - INTERIOR BUILDOUTPVN - SERVICE PVN - SERVICE LEVELPVN - SERVICE LEVELPVN - SERVICE LEVELPVN - SERVICE LEVELPVN - DOCK SIDE PVN - DOCK SIDE - LOADING DOCK/MAINTENANCEPVN - DOCK SIDE - LOADING DOCK/MAINTENANCEPVN - DOCK SIDE - LOADING DOCK/MAINTENANCEPVN - DOCK SIDE - LOADING DOCK/MAINTENANCE
PVNSLLM-0412 LAY CMU WALLS - SERV LVL DOCK/MAINTENANCE PVN 10 22-Jan-14 04-Feb-14
PVNSLLM-1560 ROUGH-IN MEP/FIRE PROTECTION - SERV LVL DOCK/MAINTENANCE PVN 40 06-Feb-14 03-Apr-14
PVNSLLM-1570 GARAGE FINISHES - SERV LVL DOCK/MAINTENANCE PVN 25 04-Apr-14 08-May-14
PVNSLLM-8890 CLEAN-UP/PRE PUNCH/FINAL PUNCH - SERV LVL DOCK/MAINTENANCE PVN 10 09-May-14 22-May-14
PVN - PARKING SIPVN - PARKING SIDE - STORAGE ROOMSPVN - PARKING SIDE - STORAGE ROOMSPVN - PARKING SIDE - STORAGE ROOMSPVN - PARKING SIDE - STORAGE ROOMS
PVNSLST-0315 FORM/PLACE FINISH EQUIPMENT PADS - SERV LVL DOCK PVN 5 11-Dec-13 17-Dec-13
PVNSLST-0910 FRAMING/IN-WALL ROUGH IN - SERV LVL DOCK PVN 10 18-Dec-13 02-Jan-14
PVNSLST-1620 CONNECT/PIPE-UP EQUIPMENT - SERV LVL DOCK PVN 25 18-Dec-13 24-Jan-14
PVNSLST-8890 CLEAN-UP/PRE PUNCH/FINAL PUNCH - SERV LVL DOCK PVN 5 27-Jan-14 31-Jan-14
PVN - PARKINGPVN - PARKING SIDE - LEVEL 1PVN - PARKING SIDE - LEVEL 1PVN - PARKING SIDE - LEVEL 1PVN - PARKING SIDE - LEVEL 1PVNL1L1-1560 ROUGH-IN MEP/FIRE PROTECTION - LVL-1 PVN 25 08-Jul-14 11-Aug-14
PVNL1L1-1570 GARAGE FINISHES - LVL-1 PVN 25 27-Oct-14 02-Dec-14
PVNL1L1-8890 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 PVN 10 03-Dec-14 16-Dec-14
PVN - PARKINGPVN - PARKING SIDE - LEVEL 2PVN - PARKING SIDE - LEVEL 2PVN - PARKING SIDE - LEVEL 2PVN - PARKING SIDE - LEVEL 2PVNL2L2-1580 ROUGH-IN MEP/FIRE PROTECTION - LVL-2 PVN 25 22-Jul-14 25-Aug-14
PVNL2L2-1590 GARAGE FINISHES - LVL -2 PVN 25 27-Oct-14 02-Dec-14
PVNL2L2-8900 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 PVN 10 03-Dec-14 16-Dec-14
PVN - PARKINGPVN - PARKING SIDE - LEVEL 3PVN - PARKING SIDE - LEVEL 3PVN - PARKING SIDE - LEVEL 3PVN - PARKING SIDE - LEVEL 3PVNL3L3-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-3 PVN 25 05-Aug-14 09-Sep-14
PVNL3L3-1610 GARAGE FINISHES - LVL-3 PVN 25 27-Oct-14 02-Dec-14
PVNL3L3-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 PVN 10 03-Dec-14 16-Dec-14
PVN - PARKINGPVN - PARKING SIDE - LEVEL 4PVN - PARKING SIDE - LEVEL 4PVN - PARKING SIDE - LEVEL 4PVN - PARKING SIDE - LEVEL 4PVNL4L4-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-4 PVN 25 19-Aug-14 23-Sep-14
PVNL4L4-1610 GARAGE FINISHES - LVL-4 PVN 25 27-Oct-14 02-Dec-14
PVNL4L4-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-4 PVN 10 03-Dec-14 16-Dec-14
PVN - PARKINGPVN - PARKING SIDE - LEVEL 5PVN - PARKING SIDE - LEVEL 5PVN - PARKING SIDE - LEVEL 5PVN - PARKING SIDE - LEVEL 5PVNL5L5-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-5 PVN 25 03-Sep-14 07-Oct-14
PVNL5L5-1610 GARAGE FINISHES - LVL-5 PVN 25 27-Oct-14 02-Dec-14
PVNL5L5-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-5 PVN 10 03-Dec-14 16-Dec-14
PVN - ALL LEVELSPVN - ALL LEVELSPVN - ALL LEVELSPVN - ALL LEVELSPVN - ALL LEVELSPVNALAL-3120 ERECT STAIR 1 - ALL LVLS PVN 20 16-Jul-14 12-Aug-14
PVNALAL-3130 ERECT STAIR 2 - ALL LVLS PVN 20 30-Jul-14 26-Aug-14
PVNALAL-0555 ERECT STAIR 3A - ALL LVLS PVN 20 26-Sep-14 24-Oct-14
PVNALAL-0991 FINISH STAIR CORES - ALL LVLS PVN 44 05-Nov-14 09-Jan-15
PVNALAL-1400 INSTALL ELEVATOR - ALL LVLS PVN 44 05-Nov-14 09-Jan-15
PVN - COMMISSPVN - COMMISSIONINGPVN - COMMISSIONINGPVN - COMMISSIONINGPVN - COMMISSIONINGPVNCOCO-1592 TEST & BALANCE - PVN 20 12-Jan-15 10-Feb-15
PVNCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - PVN 20 12-Jan-15 10-Feb-15
PVNCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - PVN 15 12-Jan-15 02-Feb-15
PVNCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - PVN 15 03-Feb-15 24-Feb-15
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 44 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 047
Activity ID Activity Name OrigDur
Start Finish
PARKING STAFPARKING STAFF NORTH (PSN)PARKING STAFF NORTH (PSN)PARKING STAFF NORTH (PSN)PARKING STAFF NORTH (PSN)PARKING STAFFPARKING STAFF NORTH (PSN) - STRUCTUREPARKING STAFF NORTH (PSN) - STRUCTUREPARKING STAFF NORTH (PSN) - STRUCTUREPARKING STAFF NORTH (PSN) - STRUCTUREPSNSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL PSN 15 26-May-12 13-Jun-12
PSNSLSL-3150 DRILL/PLACE CAISSONS - SERV LVL PSN 30 14-Jun-12 06-Aug-12
PSN - ALL LEVEPSN - ALL LEVELSPSN - ALL LEVELSPSN - ALL LEVELSPSN - ALL LEVELSPSNALAL-0290 FORM/PLACE/PIER CAPS/FTGS/ELEV PITS/ WALLS/ COLUMNS - ALL LVLS PSN 45 07-Aug-12 19-Oct-12
PSNALAL-0300 UNDERSLAB UTILITIES/PLACE SLAB ON GRADE - ALL LVLS PSN 35 09-Nov-12 07-Jan-13
PSNALAL-0310 FORM/PLACE/POST TENSION DECKS - ALL LVLS PSN 125 08-Jan-13 06-Aug-13
PARKING VISITOPARKING VISITOR NORTH (PSN) - EXTERIOR SKINSPARKING VISITOR NORTH (PSN) - EXTERIOR SKINSPARKING VISITOR NORTH (PSN) - EXTERIOR SKINSPARKING VISITOR NORTH (PSN) - EXTERIOR SKINSPSNESES-0320 INSTALL EXTERIOR SKIN FINISHES - ALL ELEVATIONS PSN 40 08-Aug-13 11-Oct-13
PSN - ROOF LEVPSN - ROOF LEVELPSN - ROOF LEVELPSN - ROOF LEVELPSN - ROOF LEVELPSNESRL-1600 INSTALL ROOF TRELLIS SYSTEM - ROOF LVL PSN 20 08-Aug-13 10-Sep-13
PSNESRL-1610 INSTALL GLASS ROOFING SYSTEM - ROOF LVL PSN 40 12-Sep-13 15-Nov-13
PSNESRL-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - ROOF LVL PSN 10 18-Nov-13 03-Dec-13
PARKING STAFFPARKING STAFF NORTH (PSN) - INTERIOR BUILDOUTPARKING STAFF NORTH (PSN) - INTERIOR BUILDOUTPARKING STAFF NORTH (PSN) - INTERIOR BUILDOUTPARKING STAFF NORTH (PSN) - INTERIOR BUILDOUTPSN - LEVEL 1PSN - LEVEL 1PSN - LEVEL 1PSN - LEVEL 1PSN - LEVEL 1PSNL1L1-1560 ROUGH-IN MEP/FIRE PROTECTION - LVL-1 PSN 25 08-Jul-13 09-Aug-13
PSNL1L1-1570 GARAGE FINISHES - LVL-1 PSN 25 12-Aug-13 16-Sep-13
PSNL1L1-8890 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 PSN 10 17-Sep-13 30-Sep-13
PSN - LEVEL 2PSN - LEVEL 2PSN - LEVEL 2PSN - LEVEL 2PSN - LEVEL 2PSNL2L2-1580 ROUGH-IN MEP/FIRE PROTECTION - LVL-2 PSN 25 07-Aug-13 11-Sep-13
PSNL2L2-1590 GARAGE FINISHES - LVL -2 PSN 25 12-Sep-13 16-Oct-13
PSNL2L2-8900 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 PSN 10 17-Oct-13 31-Oct-13
PSN - LEVEL 3PSN - LEVEL 3PSN - LEVEL 3PSN - LEVEL 3PSN - LEVEL 3PSNL3L3-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-3 PSN 25 21-Aug-13 25-Sep-13
PSNL3L3-1610 GARAGE FINISHES - LVL-3 PSN 25 26-Sep-13 31-Oct-13
PSNL3L3-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 PSN 10 01-Nov-13 15-Nov-13
PSN - LEVEL 4PSN - LEVEL 4PSN - LEVEL 4PSN - LEVEL 4PSN - LEVEL 4PSNL4L4-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-4 PSN 25 05-Sep-13 09-Oct-13
PSNL4L4-1610 GARAGE FINISHES - LVL-4 PSN 25 10-Oct-13 15-Nov-13
PSNL4L4-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-4 PSN 10 18-Nov-13 02-Dec-13
PSN - LEVEL 5PSN - LEVEL 5PSN - LEVEL 5PSN - LEVEL 5PSN - LEVEL 5PSNL5L5-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-5 PSN 25 19-Sep-13 24-Oct-13
PSNL5L5-1610 GARAGE FINISHES - LVL-5 PSN 25 25-Oct-13 02-Dec-13
PSNL5L5-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-5 PSN 10 03-Dec-13 16-Dec-13
PSN - LEVEL 6PSN - LEVEL 6PSN - LEVEL 6PSN - LEVEL 6PSN - LEVEL 6PSNL6L6-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-6 PSN 25 03-Oct-13 07-Nov-13
PSNL6L6-1610 GARAGE FINISHES - LVL-6 PSN 25 08-Nov-13 16-Dec-13
PSNL6L6-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-6 PSN 10 17-Dec-13 31-Dec-13
PSN - ALL LEVELSPSN - ALL LEVELSPSN - ALL LEVELSPSN - ALL LEVELSPSN - ALL LEVELSPSNALAL-0555 ERECT STAIRS - ALL LVLS PSN 20 10-Jul-13 06-Aug-13
PSNALAL-1400 INSTALL ELEVATOR - ALL LVLS PSN 60 07-Aug-13 31-Oct-13
PSNALAL-0991 FINISH STAIR CORES - ALL LVLS PSN 20 07-Aug-13 04-Sep-13
PSN - PEDESTRIPSN - PEDESTRIAN BRIDGEPSN - PEDESTRIAN BRIDGEPSN - PEDESTRIAN BRIDGEPSN - PEDESTRIAN BRIDGEPSNCOCO-0520 PEDESTRIAN BRIDGE CONSTRUCTION - PSN 120 20-Mar-13 11-Oct-13
PSN - COMMISSPSN - COMMISSIONINGPSN - COMMISSIONINGPSN - COMMISSIONINGPSN - COMMISSIONINGPSNCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - PSN 20 02-Jan-14 30-Jan-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 45 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 048
Activity ID Activity Name OrigDur
Start Finish
PSNCOCO-1592 TEST & BALANCE - PSN 20 31-Jan-14 28-Feb-14
PSNCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - PSN 15 31-Jan-14 21-Feb-14
PSNCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - PSN 15 24-Feb-14 14-Mar-14
INPATIENT BEINPATIENT BED TOWER SOUTH (IBS)INPATIENT BED TOWER SOUTH (IBS)INPATIENT BED TOWER SOUTH (IBS)INPATIENT BED TOWER SOUTH (IBS)INPATIENT BED INPATIENT BED TOWERS SOUTH (IBS) - STRUCTUREINPATIENT BED TOWERS SOUTH (IBS) - STRUCTUREINPATIENT BED TOWERS SOUTH (IBS) - STRUCTUREINPATIENT BED TOWERS SOUTH (IBS) - STRUCTUREIBS - PIPE BASEIBS - PIPE BASEMENTIBS - PIPE BASEMENTIBS - PIPE BASEMENTIBS - PIPE BASEMENTIBSPBPB-3130 DRIVE SOLDIER PILES - PIPE BSMT IBS 10 12-Jan-12 26-Jan-12
IBSPBPB-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PIPE BSMT IBS 28 27-Jan-12 29-Feb-12
IBSPBPB-0320 DRILL/PLACE CAISSONS - PIPE BSMT IBS 25 14-Mar-12 26-Apr-12
IBSPBPB-0103 FORM/PLACE TOWER CRANE #3 BASE (IBS/IBN CON B) 35 14-Mar-12 15-May-12
IBSPBPB-0330 FORM/PLACE/PIER CAPS/TIE BEAMS/ELEV PITS/ WALLS/ COLUMNS/CORES - PIPE BSMT IBS 125 27-Apr-12 29-Nov-12
IBSPBPB-3110 SET/BACKFILL DUCTBANKS - PIPE BSMT IBS 5 13-Aug-12 20-Aug-12
IBSPBPB-3200 UNDERSLAB UTILITIES - PIPE BSMT IBS 15 30-Aug-12 24-Sep-12
IBSPBPB-0380 FORM/PLACE/FINISH SLAB ON GRADE - PIPE BSMT IBS 5 25-Sep-12 02-Oct-12
IBSPBPB-0390 PERM DRAINS/BACKFILL - PIPE BSMT IBS 14 26-Feb-13 19-Mar-13
IBS - SERVICE LIBS - SERVICE LEVELIBS - SERVICE LEVELIBS - SERVICE LEVELIBS - SERVICE LEVELIBSSLSL-0510 ERECT STRUCTURAL STEEL/DECK - SERVICE LEVEL IBS 15 30-Nov-12 24-Dec-12
IBSSLSL-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - SERVICE LEVEL IBS 9 11-Feb-13 25-Feb-13
IBSSLSL-0725 SPRAY-ON FIREPROOFING - SERVICE LEVEL IBS 8 20-Feb-13 01-Mar-13
IBS SERVICE LEVEIBS SERVICE LEVEL - INTERSTITIALIBS SERVICE LEVEL - INTERSTITIALIBS SERVICE LEVEL - INTERSTITIALIBS SERVICE LEVEL - INTERSTITIAL
IBSSLIL-0510 ERECT INTERSTITIAL STEEL/TOPPING - SERVICE LEVEL INTERSTITIAL LVL IBS 35 28-Mar-13 29-May-13
IBS - LEVEL 1IBS - LEVEL 1IBS - LEVEL 1IBS - LEVEL 1IBS - LEVEL 1IBSL1L1-0510 ERECT STRUCTURAL STEEL/DECK - LVL-1 IBS 15 26-Dec-12 17-Jan-13
IBSL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 IBS 9 07-Mar-13 20-Mar-13
IBSL1L1-0725 SPRAY-ON FIREPROOFING - LVL-1 IBS 8 15-Mar-13 26-Mar-13
IBSL1L1-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-1 IBS 20 28-Mar-13 02-May-13
IBS LEVEL 1 - INTIBS LEVEL 1 - INTERSTITIALIBS LEVEL 1 - INTERSTITIALIBS LEVEL 1 - INTERSTITIALIBS LEVEL 1 - INTERSTITIAL
IBSL1IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-1 INTERSTITIAL LVL IBS 35 23-Apr-13 24-Jun-13
IBS - LEVEL 2IBS - LEVEL 2IBS - LEVEL 2IBS - LEVEL 2IBS - LEVEL 2IBSL2L2-0510 ERECT STRUCTURAL STEEL/DECK - LVL-2 IBS 15 18-Jan-13 08-Feb-13
IBSL2L2-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 IBS 9 01-Apr-13 15-Apr-13
IBSL2L2-0725 SPRAY-ON FIREPROOFING - LVL-2 IBS 8 05-Apr-13 18-Apr-13
IBSL2L2-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-2 IBS 20 19-Apr-13 24-May-13
IBS LEVEL 2 - INTIBS LEVEL 2 - INTERSTITIALIBS LEVEL 2 - INTERSTITIALIBS LEVEL 2 - INTERSTITIALIBS LEVEL 2 - INTERSTITIAL
IBSL2IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-2 INTERSTITIAL LVL IBS 35 10-May-13 09-Jul-13
IBS - LEVEL 3IBS - LEVEL 3IBS - LEVEL 3IBS - LEVEL 3IBS - LEVEL 3IBSL3L3-0510 ERECT STRUCTURAL STEEL/DECK - LVL-3 IBS 15 11-Feb-13 05-Mar-13
IBSL3L3-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 IBS 9 16-Apr-13 02-May-13
IBSL3L3-0725 SPRAY-ON FIREPROOFING - LVL-3 IBS 8 22-Apr-13 06-May-13
IBSL3L3-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-3 IBS 20 07-May-13 10-Jun-13
IBS LEVEL 3 - INTIBS LEVEL 3 - INTERSTITIALIBS LEVEL 3 - INTERSTITIALIBS LEVEL 3 - INTERSTITIALIBS LEVEL 3 - INTERSTITIAL
IBSL3IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-3 INTERSTITIAL LVL IBS 35 21-May-13 19-Jul-13
IBS - PENTHOUIBS - PENTHOUSEIBS - PENTHOUSEIBS - PENTHOUSEIBS - PENTHOUSEIBSPHPH-0510 ERECT STRUCTURAL STEEL/DECK - PENT IBS 15 07-Mar-13 29-Mar-13
IBSPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT IBS 9 26-Apr-13 13-May-13
IBSPHPH-0725 SPRAY-ON FIREPROOFING - PENT IBS 8 14-May-13 28-May-13
IBSPHPH-1610 FORM/PLACE EQUIPMENT PADS - PENT IBS 5 14-May-13 21-May-13
IBSPHPH-1500 SET MECH EQUIPMENT - PENT IBS 15 29-May-13 18-Jun-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 46 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 049
Activity ID Activity Name OrigDur
Start Finish
IBSPHPH-1600 SET ELECTRICAL EQUIPMENT - PENT IBS 10 19-Jun-13 02-Jul-13
IBSPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENT IBS 15 03-Jul-13 29-Jul-13
IBSPHPH-0710 INSTALL LOUVERS - PENT IBS 10 30-Jul-13 15-Aug-13
IBSPHPH-0777 INSTALL METAL PANEL - PENT IBS 10 16-Aug-13 03-Sep-13
IBS - ROOFIBS - ROOFIBS - ROOFIBS - ROOFIBS - ROOFIBSRLRL-0510 ERECT STRUCTURAL STEEL/DECK - ROOF IBS 15 01-Apr-13 25-Apr-13
IBSRLRL-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ROOF IBS 9 14-May-13 29-May-13
IBSRLRL-0750 INSTALL ROOFING - ROOF IBS 20 30-May-13 02-Jul-13
IBSRLRL-2610 INSTALL GREEN ROOF SYSTEM - ROOF IBS 15 03-Jul-13 29-Jul-13
IBSRLRL-2600 SET/CONNECT PHOTOVOLTAIC PANELS - ROOF IBS 40 03-Jul-13 10-Sep-13
INPATIENT BED INPATIENT BED TOWERS SOUTH (IBS) - EXTERIOR SKININPATIENT BED TOWERS SOUTH (IBS) - EXTERIOR SKININPATIENT BED TOWERS SOUTH (IBS) - EXTERIOR SKININPATIENT BED TOWERS SOUTH (IBS) - EXTERIOR SKINIBS - NORTH ELIBS - NORTH ELEVATIONIBS - NORTH ELEVATIONIBS - NORTH ELEVATIONIBS - NORTH ELEVATIONIBSESNE-0870 INSTALL PRECAST PANELS - NORTH ELEV IBS 10 07-Mar-13 21-Mar-13
IBSESNE-0820 INSTALL STRIP WINDOWS - NORTH ELEV IBS 15 22-Mar-13 16-Apr-13
IBSESNE-890 INSTALL METAL PANELS - NORTH ELEV IBN 15 18-Apr-13 14-May-13
IBS - EAST ELEVIBS - EAST ELEVATIONIBS - EAST ELEVATIONIBS - EAST ELEVATIONIBS - EAST ELEVATIONIBSESEE-0870 INSTALL PRECAST PANELS - EAST ELEV IBS 10 22-Mar-13 08-Apr-13
IBSESEE-870 INSTALL STRIP WINDOWS - EAST ELEV IBS 5 09-Apr-13 16-Apr-13
IBSESEE-0880 INSTALL METAL PANELS - EAST ELEV IBS 12 18-Apr-13 09-May-13
IBS - SOUTH ELIBS - SOUTH ELEVATIONIBS - SOUTH ELEVATIONIBS - SOUTH ELEVATIONIBS - SOUTH ELEVATIONIBSESSE-0580 ERECT/CONNECT PEDESTRIAN BRIDGE - SOUTH ELEV IBS 22 11-Feb-13 18-Mar-13
IBSESSE-0877 INSTALL PRECAST PANELS - SOUTH ELEV IBS 5 09-Apr-13 16-Apr-13
IBSESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV IBS 50 18-Apr-13 15-Jul-13
IBSESSE-0880 INSTALL METAL PANELS - SOUTH ELEV IBS 15 16-Jul-13 09-Aug-13
IBS - WEST ELEIBS - WEST ELEVATIONIBS - WEST ELEVATIONIBS - WEST ELEVATIONIBS - WEST ELEVATIONIBSESWE-0870 INSTALL STOREFRONT - WEST ELEV IBS 10 12-Aug-13 27-Aug-13
IBSESWE-0880 INSTALL STRIP WINDOWS - WEST ELEV IBS 5 29-Aug-13 05-Sep-13
INPATIENT BED INPATIENT BED TOWERS SOUTH (IBS) - INTERIOR BUILDOUTINPATIENT BED TOWERS SOUTH (IBS) - INTERIOR BUILDOUTINPATIENT BED TOWERS SOUTH (IBS) - INTERIOR BUILDOUTINPATIENT BED TOWERS SOUTH (IBS) - INTERIOR BUILDOUTIBS - PIPE BASEIBS - PIPE BASEMENTIBS - PIPE BASEMENTIBS - PIPE BASEMENTIBS - PIPE BASEMENTIBSPBPB-1516 R-I OVERHEAD MEP/FIRE PRO - PIPE BSMT IBS 15 26-Feb-13 18-Mar-13
IBSPBPB-0910 FRAMING/INWALL ROUGH - PIPE BSMT IBS 10 26-Mar-13 08-Apr-13
IBSPBPB-0920 HANG/TAPE/FINISH DRYWALL - PIPE BSMT IBS 15 12-Aug-13 30-Aug-13
IBSPBPB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - PIPE BSMT IBS 10 03-Sep-13 16-Sep-13
IBSPBPB-8880 CLEAN-UP/PRE PUNCH - PIPE BSMT IBS 15 17-Sep-13 07-Oct-13
IBS - SERVICE LIBS - SERVICE LEVELIBS - SERVICE LEVELIBS - SERVICE LEVELIBS - SERVICE LEVELIBS - SERVICE LEVIBS - SERVICE LEVEL - INTERSTITIALIBS - SERVICE LEVEL - INTERSTITIALIBS - SERVICE LEVEL - INTERSTITIALIBS - SERVICE LEVEL - INTERSTITIAL
IBSSLIL-1516 ROUGH-IN MEP/FIRE PROTECTION - SERV LVL INTER LVL IBS 60 30-May-13 22-Aug-13
IBSSLIL-1517 TRIM-OUT MEP/FIRE PROTECTION - SERV LVL INTER LVL IBS 25 23-Aug-13 27-Sep-13
IBS - SERVICE LEVIBS - SERVICE LEVEL - ENVIRONMENTAL SERVICESIBS - SERVICE LEVEL - ENVIRONMENTAL SERVICESIBS - SERVICE LEVEL - ENVIRONMENTAL SERVICESIBS - SERVICE LEVEL - ENVIRONMENTAL SERVICES
IBSSLES-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL ENVIRO IBS 15 30-May-13 19-Jun-13
IBSSLES-0910 FRAMING/INWALL ROUGH - SERV LVL ENVIRO IBS 55 30-May-13 15-Aug-13
IBSSLES-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL ENVIRO IBS 20 12-Aug-13 09-Sep-13
IBSSLES-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL ENVIRO IBS 35 03-Sep-13 22-Oct-13
IBSSLES-0977 INSTALL OWNER FIXED FF&E - SERV LVL ENVIRO IBS 20 24-Sep-13 22-Oct-13
IBSSLES-1190 INSTALL MEDICAL HEADWALLS - SERV LVL ENVIRO IBS 35 23-Oct-13 12-Dec-13
IBSSLES-8890 INTERFACE TESTS/INSPECTIONS- SERV LVL ENVIRO IBS 10 13-Dec-13 27-Dec-13
IBSSLES-8880 CLEAN-UP/PRE PUNCH - SERV LVL ENVIRO IBS 15 30-Dec-13 21-Jan-14
IBS - SERVICE LEVIBS - SERVICE LEVEL - CANTEENIBS - SERVICE LEVEL - CANTEENIBS - SERVICE LEVEL - CANTEENIBS - SERVICE LEVEL - CANTEEN
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 47 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 050
Activity ID Activity Name OrigDur
Start Finish
IBSSLCA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 CANTEEN IBS 15 20-Jun-13 11-Jul-13
IBSSLCA-0910 FRAMING/INWALL ROUGH - SERV LVL CANTEEN IBS 45 20-Jun-13 22-Aug-13
IBSSLCA-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL CANTEEN IBS 20 06-Sep-13 03-Oct-13
IBSSLCA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CANTEEN IBS 30 27-Sep-13 08-Nov-13
IBSSLCA-0977 INSTALL OWNER FIXED FF&E - SERV LVL CANTEEN IBS 20 11-Oct-13 08-Nov-13
IBSSLCA-8880 CLEAN-UP/PRE PUNCH - SERV LVL CANTEEN IBS 15 12-Nov-13 03-Dec-13
IBS - SERVICE LEVIBS - SERVICE LEVEL - PATHOLOGYIBS - SERVICE LEVEL - PATHOLOGYIBS - SERVICE LEVEL - PATHOLOGYIBS - SERVICE LEVEL - PATHOLOGY
IBSSLPA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL PATH IBS 15 12-Jul-13 01-Aug-13
IBSSLPA-0910 FRAMING/INWALL ROUGH - SERV LVL PATH IBS 55 12-Jul-13 27-Sep-13
IBSSLPA-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL PATH IBS 20 18-Sep-13 15-Oct-13
IBSSLPA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL PATH IBS 35 09-Oct-13 29-Nov-13
IBSSLPA-0977 INSTALL OWNER FIXED FF&E - SERV LVL PATH IBS 20 31-Oct-13 29-Nov-13
IBSSLPA-1190 INSTALL MEDICAL HEADWALLS - SERV LVL PATH IBS 35 02-Dec-13 22-Jan-14
IBSSLPA-8890 INTERFACE TESTS/INSPECTIONS- SERV LVL PATH IBS 10 23-Jan-14 05-Feb-14
IBSSLPA-8880 CLEAN-UP/PRE PUNCH - SERV LVL PATH IBS 15 06-Feb-14 27-Feb-14
IBS - SERVICE LEVIBS - SERVICE LEVEL - BIOMEDIBS - SERVICE LEVEL - BIOMEDIBS - SERVICE LEVEL - BIOMEDIBS - SERVICE LEVEL - BIOMED
IBSSLBM-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL BIO IBS 15 02-Aug-13 22-Aug-13
IBSSLBM-0910 FRAMING/INWALL ROUGH - SERV LVL BIO IBS 55 02-Aug-13 18-Oct-13
IBSSLBM-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL BIO IBS 20 30-Sep-13 28-Oct-13
IBSSLBM-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL BIO IBS 30 22-Oct-13 04-Dec-13
IBSSLBM-0977 INSTALL OWNER FIXED FF&E - SERV LVL BIO IBS 20 05-Nov-13 04-Dec-13
IBSSLBM-1190 INSTALL MEDICAL HEADWALLS - SERV LVL BIO IBS 35 05-Dec-13 27-Jan-14
IBSSLBM-8890 INTERFACE TESTS/INSPECTIONS- SERV LVL BIO IBS 10 28-Jan-14 11-Feb-14
IBSSLBM-8880 CLEAN-UP/PRE PUNCH - SERV LVL BIO IBS 15 12-Feb-14 04-Mar-14
IBS - SERVICE LEVIBS - SERVICE LEVEL - CORE/SHELLIBS - SERVICE LEVEL - CORE/SHELLIBS - SERVICE LEVEL - CORE/SHELLIBS - SERVICE LEVEL - CORE/SHELL
IBSSLCS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHELL IBS 10 23-Aug-13 06-Sep-13
IBSSLCS-0910 FRAMING/INWALL ROUGH - SERV LVL SHELL IBS 55 23-Aug-13 12-Nov-13
IBSSLCS-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL SHELL IBS 20 22-Oct-13 19-Nov-13
IBSSLCS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHELL IBS 30 13-Nov-13 26-Dec-13
IBSSLCS-0977 INSTALL OWNER FIXED FF&E - SERV LVL SHELL IBS 15 05-Dec-13 26-Dec-13
IBSSLCS-1190 INSTALL MEDICAL HEADWALLS - SERV LVL SHELL IBS 35 27-Dec-13 18-Feb-14
IBSSLCS-8890 INTERFACE TESTS/INSPECTIONS- SERV LVL SHELL IBS 10 19-Feb-14 04-Mar-14
IBSSLCS-8880 CLEAN-UP/PRE PUNCH - SERV LVL SHELL IBS 15 05-Mar-14 25-Mar-14
IBS - SERVICE LEVIBS - SERVICE LEVEL - CORRIDORIBS - SERVICE LEVEL - CORRIDORIBS - SERVICE LEVEL - CORRIDORIBS - SERVICE LEVEL - CORRIDOR
IBSSLCO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CORR IBS 25 19-Feb-14 25-Mar-14
IBSSLCO-8880 CLEAN-UP/PRE PUNCH - SERV LVL CORR IBS 15 26-Mar-14 15-Apr-14
IBS - LEVEL 1IBS - LEVEL 1IBS - LEVEL 1IBS - LEVEL 1IBS - LEVEL 1IBS - LEVEL 1 - INIBS - LEVEL 1 - INTERSTITIALIBS - LEVEL 1 - INTERSTITIALIBS - LEVEL 1 - INTERSTITIALIBS - LEVEL 1 - INTERSTITIAL
IBSL1IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-1 INTER IBS 100 05-Jul-13 27-Nov-13
IBSL1IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-1 INTER IBS 25 28-Nov-13 03-Jan-14
IBS - LEVEL 1 - PAIBS - LEVEL 1 - PATIENT ROOMSIBS - LEVEL 1 - PATIENT ROOMSIBS - LEVEL 1 - PATIENT ROOMSIBS - LEVEL 1 - PATIENT ROOMS
IBSL1PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-1 PATIENT IBS 20 05-Jul-13 01-Aug-13
IBSL1PR-0910 FRAMING/INWALL ROUGH - LVL-1 PATIENT IBS 55 05-Jul-13 20-Sep-13
IBSL1PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 PATIENT IBS 35 06-Sep-13 25-Oct-13
IBSL1PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PATIENT IBS 30 11-Oct-13 26-Nov-13
IBSL1PR-0977 INSTALL OWNER FIXED FF&E - LVL-1 PATIENT IBS 20 28-Oct-13 26-Nov-13
IBSL1PR-1190 INSTALL MEDICAL HEADWALLS - LVL-1 PATIENT IBS 35 27-Nov-13 16-Jan-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 48 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 051
Activity ID Activity Name OrigDur
Start Finish
IBSL1PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 PATIENT IBS 10 17-Jan-14 31-Jan-14
IBSL1PR-8880 CLEAN-UP/PRE PUNCH - LVL-1 PATIENT IBS 15 03-Feb-14 24-Feb-14
IBS - LEVEL 1 - NUIBS - LEVEL 1 - NURSINGIBS - LEVEL 1 - NURSINGIBS - LEVEL 1 - NURSINGIBS - LEVEL 1 - NURSING
IBSL1NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 NURSING IBS 20 02-Aug-13 29-Aug-13
IBSL1NR-0910 FRAMING/INWALL ROUGH - LVL-1 NURSING IBS 55 02-Aug-13 18-Oct-13
IBSL1NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 NURSING IBS 35 04-Oct-13 26-Nov-13
IBSL1NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NURSING IBS 30 12-Nov-13 24-Dec-13
IBSL1NR-0977 INSTALL OWNER FIXED FF&E - LVL-1 NURSING IBS 20 27-Nov-13 24-Dec-13
IBSL1NR-1190 INSTALL MEDICAL HEADWALLS - LVL-1 NURSING IBS 35 26-Dec-13 17-Feb-14
IBSL1NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 NURSING IBS 10 18-Feb-14 03-Mar-14
IBSL1NR-8880 CLEAN-UP/PRE PUNCH - LVL-1 NURSING IBS 15 04-Mar-14 24-Mar-14
IBS - LEVEL 1 - COIBS - LEVEL 1 - CORE/SHELLIBS - LEVEL 1 - CORE/SHELLIBS - LEVEL 1 - CORE/SHELLIBS - LEVEL 1 - CORE/SHELL
IBSL1CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 SHELL IBS 10 30-Aug-13 13-Sep-13
IBSL1CS-0910 FRAMING/INWALL ROUGH - LVL-1 SHELL IBS 55 30-Aug-13 19-Nov-13
IBSL1CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SHELL IBS 25 04-Nov-13 10-Dec-13
IBSL1CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SHELL IBS 20 11-Dec-13 09-Jan-14
IBSL1CS-0977 INSTALL OWNER FIXED FF&E - LVL-1 SHELL IBS 15 18-Dec-13 09-Jan-14
IBSL1CS-1190 INSTALL MEDICAL HEADWALLS - LVL-1 SHELL IBS 35 10-Jan-14 03-Mar-14
IBSL1CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 SHELL IBS 10 04-Mar-14 17-Mar-14
IBSL1CS-8880 CLEAN-UP/PRE PUNCH - LVL-1 SHELL IBS 15 18-Mar-14 07-Apr-14
IBS - LEVEL 1 - COIBS - LEVEL 1 - CORRIDORIBS - LEVEL 1 - CORRIDORIBS - LEVEL 1 - CORRIDORIBS - LEVEL 1 - CORRIDOR
IBSL1CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 CORR IBS 20 04-Mar-14 31-Mar-14
IBSL1CO-8880 CLEAN-UP/PRE PUNCH - LVL-1 CORR IBS 10 01-Apr-14 14-Apr-14
IBS - LEVEL 2IBS - LEVEL 2IBS - LEVEL 2IBS - LEVEL 2IBS - LEVEL 2IBS - LEVEL 2 - INIBS - LEVEL 2 - INTERSTITIALIBS - LEVEL 2 - INTERSTITIALIBS - LEVEL 2 - INTERSTITIALIBS - LEVEL 2 - INTERSTITIAL
IBSL2IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-2 INTER IBS 100 16-Aug-13 10-Jan-14
IBSL2IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-2I NTER IBS 25 13-Jan-14 18-Feb-14
IBS - LEVEL 2 - PAIBS - LEVEL 2 - PATIENT ROOMSIBS - LEVEL 2 - PATIENT ROOMSIBS - LEVEL 2 - PATIENT ROOMSIBS - LEVEL 2 - PATIENT ROOMS
IBSL2PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-2 PATIENT IBS 20 16-Aug-13 13-Sep-13
IBSL2PR-0910 FRAMING/INWALL ROUGH - LVL-2 PATIENT IBS 55 16-Aug-13 04-Nov-13
IBSL2PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 PATIENT IBS 35 22-Oct-13 11-Dec-13
IBSL2PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 PATIENT IBS 30 05-Dec-13 17-Jan-14
IBSL2PR-0977 INSTALL OWNER FIXED FF&E - LVL-2 PATIENT IBS 20 19-Dec-13 17-Jan-14
IBSL2PR-1190 INSTALL MEDICAL HEADWALLS - LVL-2 PATIENT IBS 35 21-Jan-14 11-Mar-14
IBSL2PR-8880 CLEAN-UP/PRE PUNCH - LVL-2 PATIENT IBS 15 12-Mar-14 01-Apr-14
IBSL2PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 PATIENT IBS 10 12-Mar-14 25-Mar-14
IBS - LEVEL 2 - NUIBS - LEVEL 2 - NURSINGIBS - LEVEL 2 - NURSINGIBS - LEVEL 2 - NURSINGIBS - LEVEL 2 - NURSING
IBSL2NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 NURSING IBS 20 16-Sep-13 11-Oct-13
IBSL2NR-0910 FRAMING/INWALL ROUGH - LVL-2 NURSING IBS 55 16-Sep-13 04-Dec-13
IBSL2NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 NURSING IBS 35 20-Nov-13 10-Jan-14
IBSL2NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 NURSING IBS 30 06-Jan-14 18-Feb-14
IBSL2NR-0977 INSTALL OWNER FIXED FF&E - LVL-2 NURSING IBS 20 21-Jan-14 18-Feb-14
IBSL2NR-1190 INSTALL MEDICAL HEADWALLS - LVL-2 NURSING IBS 35 19-Feb-14 08-Apr-14
IBSL2NR-8880 CLEAN-UP/PRE PUNCH - LVL-2 NURSING IBS 15 09-Apr-14 29-Apr-14
IBSL2NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 NURSING IBS 10 09-Apr-14 22-Apr-14
IBS - LEVEL 2 - COIBS - LEVEL 2 - CORE/SHELLIBS - LEVEL 2 - CORE/SHELLIBS - LEVEL 2 - CORE/SHELLIBS - LEVEL 2 - CORE/SHELL
IBSL2CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SHELL IBS 15 14-Oct-13 04-Nov-13
IBSL2CS-0910 FRAMING/INWALL ROUGH - LVL-2 SHELL IBS 55 14-Oct-13 03-Jan-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 49 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 052
Activity ID Activity Name OrigDur
Start Finish
IBSL2CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SHELL IBS 25 19-Dec-13 27-Jan-14
IBSL2CS-0977 INSTALL OWNER FIXED FF&E - LVL-2 SHELL IBS 20 21-Jan-14 18-Feb-14
IBSL2CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SHELL IBS 15 28-Jan-14 18-Feb-14
IBSL2CS-1190 INSTALL MEDICAL HEADWALLS - LVL-2 SHELL IBS 35 19-Feb-14 08-Apr-14
IBSL2CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 SHELL IBS 10 09-Apr-14 22-Apr-14
IBSL2CS-8880 CLEAN-UP/PRE PUNCH - LVL-2 SHELL IBS 15 23-Apr-14 13-May-14
IBS - LEVEL 2 - COIBS - LEVEL 2 - CORRIDORIBS - LEVEL 2 - CORRIDORIBS - LEVEL 2 - CORRIDORIBS - LEVEL 2 - CORRIDOR
IBSL2CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CORR IBS 20 09-Apr-14 06-May-14
IBSL2CO-8880 CLEAN-UP/PRE PUNCH - LVL-2 CORR IBS 10 07-May-14 20-May-14
IBS - LEVEL 3IBS - LEVEL 3IBS - LEVEL 3IBS - LEVEL 3IBS - LEVEL 3IBS - LEVEL 3 - INIBS - LEVEL 3 - INTERSTITIALIBS - LEVEL 3 - INTERSTITIALIBS - LEVEL 3 - INTERSTITIALIBS - LEVEL 3 - INTERSTITIAL
IBSL3IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-3 INTER IBS 100 30-Sep-13 25-Feb-14
IBSL3IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-3 INTER IBS 25 26-Feb-14 01-Apr-14
IBS - LEVEL 3 - PAIBS - LEVEL 3 - PATIENT ROOMSIBS - LEVEL 3 - PATIENT ROOMSIBS - LEVEL 3 - PATIENT ROOMSIBS - LEVEL 3 - PATIENT ROOMS
IBSL3PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-3 PATIENT IBS 20 30-Sep-13 28-Oct-13
IBSL3PR-0910 FRAMING/INWALL ROUGH - LVL-3 PATIENT IBS 55 30-Sep-13 18-Dec-13
IBSL3PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 PATIENT IBS 40 05-Dec-13 03-Feb-14
IBSL3PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PATIENT IBS 30 28-Jan-14 11-Mar-14
IBSL3PR-0977 INSTALL OWNER FIXED FF&E - LVL-3 PATIENT IBS 20 12-Feb-14 11-Mar-14
IBSL3PR-1190 INSTALL MEDICAL HEADWALLS - LVL-3 PATIENT IBS 35 12-Mar-14 29-Apr-14
IBSL3PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 PATIENT IBS 10 30-Apr-14 13-May-14
IBSL3PR-8880 CLEAN-UP/PRE PUNCH - LVL-3 PATIENT IBS 15 14-May-14 04-Jun-14
IBS - LEVEL 3 - NUIBS - LEVEL 3 - NURSINGIBS - LEVEL 3 - NURSINGIBS - LEVEL 3 - NURSINGIBS - LEVEL 3 - NURSING
IBSL3NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 NURSING IBS 20 29-Oct-13 27-Nov-13
IBSL3NR-0910 FRAMING/INWALL ROUGH - LVL-3 NURSING IBS 55 29-Oct-13 17-Jan-14
IBSL3NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 NURSING IBS 45 13-Jan-14 18-Mar-14
IBSL3NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 NURSING IBS 30 12-Mar-14 22-Apr-14
IBSL3NR-0977 INSTALL OWNER FIXED FF&E - LVL-3 NURSING IBS 20 26-Mar-14 22-Apr-14
IBSL3NR-1190 INSTALL MEDICAL HEADWALLS - LVL-3 NURSING IBS 35 23-Apr-14 11-Jun-14
IBSL3NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 NURSING IBS 10 12-Jun-14 25-Jun-14
IBSL3NR-8880 CLEAN-UP/PRE PUNCH - LVL-3 NURSING IBS 15 26-Jun-14 17-Jul-14
IBS - LEVEL 3 - COIBS - LEVEL 3 - CORE/SHELLIBS - LEVEL 3 - CORE/SHELLIBS - LEVEL 3 - CORE/SHELLIBS - LEVEL 3 - CORE/SHELL
IBSL3CS-0910 FRAMING/INWALL ROUGH - LVL-3 SHELL IBS 55 28-Nov-13 18-Feb-14
IBSL3CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 SHELL IBS 15 28-Nov-13 18-Dec-13
IBSL3CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 SHELL IBS 25 19-Feb-14 25-Mar-14
IBSL3CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SHELL IBS 25 26-Mar-14 29-Apr-14
IBSL3CS-0977 INSTALL OWNER FIXED FF&E - LVL-3 SHELL IBS 20 02-Apr-14 29-Apr-14
IBSL3CS-1190 INSTALL MEDICAL HEADWALLS - LVL-3 SHELL IBS 35 30-Apr-14 18-Jun-14
IBSL3CS-8880 CLEAN-UP/PRE PUNCH - LVL-3 SHELL IBS 15 05-Jun-14 25-Jun-14
IBSL3CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 SHELL IBS 10 12-Jun-14 25-Jun-14
IBS - LEVEL 3 - COIBS - LEVEL 3 - CORRIDORIBS - LEVEL 3 - CORRIDORIBS - LEVEL 3 - CORRIDORIBS - LEVEL 3 - CORRIDOR
IBSL3CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CORR IBS 20 21-May-14 18-Jun-14
IBSL3CO-8880 CLEAN-UP/PRE PUNCH - LVL-3 CORR IBS 10 12-Jun-14 25-Jun-14
IBS - PENTHOUIBS - PENTHOUSEIBS - PENTHOUSEIBS - PENTHOUSEIBS - PENTHOUSEIBS - PENTHOUSE IBS - PENTHOUSE - MECHANICALIBS - PENTHOUSE - MECHANICALIBS - PENTHOUSE - MECHANICALIBS - PENTHOUSE - MECHANICAL
IBSPHME-0420 LAY CMU WALLS - PENT MECH IBS 15 04-Sep-13 24-Sep-13
IBSPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENT MECH IBS 45 25-Sep-13 29-Nov-13
IBSPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENT MECH IBS 60 02-Dec-13 27-Feb-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 50 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 053
Activity ID Activity Name OrigDur
Start Finish
IBSPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH IBS 30 14-Feb-14 27-Mar-14
IBSPHME-1590 START-UP MECH EQUIP - PENT MECH IBS 20 28-Mar-14 24-Apr-14
IBS - PENTHOUSE IBS - PENTHOUSE - ELECTRICALIBS - PENTHOUSE - ELECTRICALIBS - PENTHOUSE - ELECTRICALIBS - PENTHOUSE - ELECTRICAL
IBSPHEL-0910 FRAMING/INWALL ROUGH - PENT ELEC IBS 10 16-Oct-13 30-Oct-13
IBSPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENT ELEC IBS 10 31-Oct-13 14-Nov-13
IBSPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC IBS 70 31-Oct-13 13-Feb-14
IBS - ALL LEVELIBS - ALL LEVELSIBS - ALL LEVELSIBS - ALL LEVELSIBS - ALL LEVELSIBSALAL-0555 ERECT STAIRS ST1 - ALL LVLS IBS 15 01-Apr-13 19-Apr-13
IBSALAL-0556 ERECT STAIRS ST2 - ALL LVLS IBS 15 15-Apr-13 03-May-13
IBSALAL-1400 INSTALL ELEVATOR SE04 - ALL LVLS IBS 60 30-Jan-14 24-Apr-14
IBSALAL-1401 INSTALL ELEVATOR PE3/PE4 - ALL LVLS IBS 60 30-Jan-14 24-Apr-14
IBSALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS IBS 15 29-May-14 18-Jun-14
IBSALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS IBS 15 19-Jun-14 10-Jul-14
IBS - COMMISSIIBS - COMMISSIONINGIBS - COMMISSIONINGIBS - COMMISSIONINGIBS - COMMISSIONINGIBSCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - IBS 30 18-Jul-14 28-Aug-14
IBSCOCO-1592 TEST & BALANCE - IBS 25 29-Aug-14 03-Oct-14
IBSCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - IBS 20 29-Aug-14 26-Sep-14
IBSCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - IBS 20 29-Sep-14 27-Oct-14
IBSCOCO-1599 BUILDING FLUSH - IBS 10 28-Oct-14 06-Nov-14
INPATIENT BEINPATIENT BED TOWER NORTH (IBN)INPATIENT BED TOWER NORTH (IBN)INPATIENT BED TOWER NORTH (IBN)INPATIENT BED TOWER NORTH (IBN)INPATIENT BED INPATIENT BED TOWERS NORTH (IBN) - STRUCTUREINPATIENT BED TOWERS NORTH (IBN) - STRUCTUREINPATIENT BED TOWERS NORTH (IBN) - STRUCTUREINPATIENT BED TOWERS NORTH (IBN) - STRUCTUREIBN - SERVICE IBN - SERVICE LEVELIBN - SERVICE LEVELIBN - SERVICE LEVELIBN - SERVICE LEVELIBNSLSL-3130 DRIVE SOLDIER PILES - SERV LVL IBN 10 27-Jan-12 09-Feb-12
IBNSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL IBN 20 21-Feb-12 14-Mar-12
IBNSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL IBN 25 27-Apr-12 11-Jun-12
IBNSLSL-0330 FORM/PLACE/PIER CAPS/TIE BEAMS/ELEV/ WALLS/CORES - SERV LVL IBN 110 12-Jun-12 14-Dec-12
IBNSLSL-3200 UNDERSLAB UTILITIES - SERV LVL IBN 15 30-Aug-12 24-Sep-12
IBNSLSL-3110 SET/BACKFILL DUCTBANKS - SERV LVL IBN 5 25-Sep-12 02-Oct-12
IBNSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL IBN 5 03-Oct-12 09-Oct-12
IBNSLSL-0390 PERM DRAINS/BACKFILL - SERV LVL IBN 14 14-Mar-13 04-Apr-13
IBN SERVICE LEVEIBN SERVICE LEVEL - INTERSTITIALIBN SERVICE LEVEL - INTERSTITIALIBN SERVICE LEVEL - INTERSTITIALIBN SERVICE LEVEL - INTERSTITIAL
IBNSLIL-0510 ERECT INTERSTITIAL STEEL/TOPPING - SERVICE LEVEL INTERSTITIAL LVL IBN 35 20-Mar-13 20-May-13
IBN - LEVEL 1IBN - LEVEL 1IBN - LEVEL 1IBN - LEVEL 1IBN - LEVEL 1IBNL1L1-0510 ERECT STRUCTURAL STEEL/DECK - LVL-1 IBN 15 17-Dec-12 09-Jan-13
IBNL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 IBN 9 27-Feb-13 12-Mar-13
IBNL1L1-0725 SPRAY-ON FIREPROOFING - LVL-1 IBN 8 04-Mar-13 15-Mar-13
IBNL1L1-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-1 IBN 20 05-Apr-13 10-May-13
IBN LEVEL 1 - INTIBN LEVEL 1 - INTERSTITIALIBN LEVEL 1 - INTERSTITIALIBN LEVEL 1 - INTERSTITIALIBN LEVEL 1 - INTERSTITIAL
IBNL1IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-1 INTERSTITIAL LVL IBN 35 15-Apr-13 14-Jun-13
IBN - LEVEL 2IBN - LEVEL 2IBN - LEVEL 2IBN - LEVEL 2IBN - LEVEL 2IBNL2L2-0510 ERECT STRUCTURAL STEEL/DECK - LVL-2 IBN 15 10-Jan-13 01-Feb-13
IBNL2L2-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 IBN 9 22-Mar-13 05-Apr-13
IBNL2L2-0725 SPRAY-ON FIREPROOFING - LVL-2 IBN 8 28-Mar-13 09-Apr-13
IBNL2L2-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-2 IBN 20 11-Apr-13 16-May-13
IBN LEVEL 2 - INTIBN LEVEL 2 - INTERSTITIALIBN LEVEL 2 - INTERSTITIALIBN LEVEL 2 - INTERSTITIALIBN LEVEL 2 - INTERSTITIAL
IBNL2IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-2 INTERSTITIAL LVL IBN 35 02-May-13 01-Jul-13
IBN - LEVEL 3IBN - LEVEL 3IBN - LEVEL 3IBN - LEVEL 3IBN - LEVEL 3IBNL3L3-0510 ERECT STRUCTURAL STEEL/DECK - LVL-3 IBN 15 04-Feb-13 26-Feb-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 51 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 054
Activity ID Activity Name OrigDur
Start Finish
IBNL3L3-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 IBN 9 08-Apr-13 22-Apr-13
IBNL3L3-0725 SPRAY-ON FIREPROOFING - LVL-3 IBN 8 12-Apr-13 25-Apr-13
IBNL3L3-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-3 IBN 20 26-Apr-13 31-May-13
IBN LEVEL 3 - INTIBN LEVEL 3 - INTERSTITIALIBN LEVEL 3 - INTERSTITIALIBN LEVEL 3 - INTERSTITIALIBN LEVEL 3 - INTERSTITIAL
IBNL3IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-3 INTERSTITIAL LVL IBN 35 13-May-13 11-Jul-13
IBN - PENTHOUIBN - PENTHOUSEIBN - PENTHOUSEIBN - PENTHOUSEIBN - PENTHOUSEIBNPHPH-0510 ERECT STRUCTURAL STEEL/DECK - PENT IBN 15 27-Feb-13 21-Mar-13
IBNPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT IBN 9 18-Apr-13 03-May-13
IBNPHPH-0725 SPRAY-ON FIREPROOFING - PENT IBN 8 06-May-13 17-May-13
IBNPHPH-1610 FORM/PLACE FINISH EQUIPMENT PADS - PENT IBN 5 06-May-13 13-May-13
IBNPHPH-1500 SET MECH EQUIPMENT - PENT IBN 15 20-May-13 10-Jun-13
IBNPHPH-1600 SET ELECTRICAL EQUIPMENT - PENT IBN 10 11-Jun-13 24-Jun-13
IBNPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENT IBN 15 25-Jun-13 19-Jul-13
IBNPHPH-0710 INSTALL LOUVERS - PENT IBN 10 22-Jul-13 06-Aug-13
IBNPHPH-0777 INSTALL METAL PANELS - PENT IBN 10 08-Aug-13 23-Aug-13
IBN - ROOFIBN - ROOFIBN - ROOFIBN - ROOFIBN - ROOFIBNRLRL-0510 ERECT STRUCTURAL STEEL/DECK - ROOF IBN 15 22-Mar-13 16-Apr-13
IBNRLRL-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ROOF IBN 9 06-May-13 20-May-13
IBNRLRL-0750 INSTALL ROOFING - ROOF IBN 20 21-May-13 24-Jun-13
IBNRLRL-2600 SET/CONNECT PHOTOVOLTAIC PANELS - ROOF IBN 40 25-Jun-13 03-Sep-13
IBNRLRL-2610 INSTALL GREEN ROOFING SYSTEM - ROOF IBN 15 25-Jun-13 19-Jul-13
INPATIENT BED INPATIENT BED TOWERS NORTH (IBN) - EXTERIOR SKININPATIENT BED TOWERS NORTH (IBN) - EXTERIOR SKININPATIENT BED TOWERS NORTH (IBN) - EXTERIOR SKININPATIENT BED TOWERS NORTH (IBN) - EXTERIOR SKINIBN - NORTH ELIBN - NORTH ELEVATIONIBN - NORTH ELEVATIONIBN - NORTH ELEVATIONIBN - NORTH ELEVATIONIBNESNE-0870 INSTALL PRECAST PANELS - NORTH ELEV IBN 10 27-Feb-13 14-Mar-13
IBNESNE-870 INSTALL STRIP WINDOWS - NORTH ELEV IBN 15 15-Mar-13 08-Apr-13
IBNESNE-880 INSTALL METAL PANELS - NORTH ELEV IBN 15 09-Apr-13 06-May-13
IBN - EAST ELEVIBN - EAST ELEVATIONIBN - EAST ELEVATIONIBN - EAST ELEVATIONIBN - EAST ELEVATIONIBNESEE-0870 INSTALL PRECAST PANELS - EAST ELEV IBN 10 15-Mar-13 29-Mar-13
IBNESEE-870 INSTALL CURTAIN WALL - EAST ELEV IBN 15 01-Apr-13 25-Apr-13
IBNESEE-880 INSTALL METAL PANELS - EAST ELEV IBN 12 26-Apr-13 17-May-13
IBN - SOUTH ELIBN - SOUTH ELEVATIONIBN - SOUTH ELEVATIONIBN - SOUTH ELEVATIONIBN - SOUTH ELEVATIONIBNESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV IBN 20 26-Apr-13 31-May-13
IBNESSE-870 INSTALL METAL PANELS - SOUTH ELEV IBN 20 03-Jun-13 05-Jul-13
IBN - WEST ELEIBN - WEST ELEVATIONIBN - WEST ELEVATIONIBN - WEST ELEVATIONIBN - WEST ELEVATIONIBNESWE-0870 INSTALL METAL PANELS - WEST ELEV IBN 15 08-Jul-13 01-Aug-13
INPATIENT BED INPATIENT BED TOWERS NORTH (IBN) - INTERIOR BUILDOUTINPATIENT BED TOWERS NORTH (IBN) - INTERIOR BUILDOUTINPATIENT BED TOWERS NORTH (IBN) - INTERIOR BUILDOUTINPATIENT BED TOWERS NORTH (IBN) - INTERIOR BUILDOUTIBN - SERVICE IBN - SERVICE LEVELIBN - SERVICE LEVELIBN - SERVICE LEVELIBN - SERVICE LEVELIBN - SERVICE LEVIBN - SERVICE LEVEL - INTERSTITIALIBN - SERVICE LEVEL - INTERSTITIALIBN - SERVICE LEVEL - INTERSTITIALIBN - SERVICE LEVEL - INTERSTITIAL
IBNSLIL-1516 ROUGH-IN MEP/FIRE PROTECTION - SERV LVL INTER LVL IBN 60 21-May-13 14-Aug-13
IBNSLIL-1517 TRIM-OUT MEP/FIRE PROTECTION - SERV LVL INTER LVL IBN 25 15-Aug-13 19-Sep-13
IBN - SERVICE LEVIBN - SERVICE LEVEL - WAREHOUSE/RECEIVINGIBN - SERVICE LEVEL - WAREHOUSE/RECEIVINGIBN - SERVICE LEVEL - WAREHOUSE/RECEIVINGIBN - SERVICE LEVEL - WAREHOUSE/RECEIVING
IBNSLWH-0910 FRAMING/INWALL ROUGH - SERV LVL WAREHOUSE IBN 55 21-May-13 07-Aug-13
IBNSLWH-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL WAREHOUSE IBN 20 21-May-13 18-Jun-13
IBNSLWH-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL WAREHOUSE IBN 35 02-Aug-13 20-Sep-13
IBNSLWH-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL WAREHOUSE IBN 30 16-Sep-13 28-Oct-13
IBNSLWH-8880 CLEAN-UP/PRE PUNCH - SERV LVL WAREHOUSE IBN 15 29-Oct-13 19-Nov-13
IBN - SERVICE LEVIBN - SERVICE LEVEL - MAILIBN - SERVICE LEVEL - MAILIBN - SERVICE LEVEL - MAILIBN - SERVICE LEVEL - MAIL
IBNSLMR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 MAIL IBN 20 19-Jun-13 17-Jul-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 52 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 055
Activity ID Activity Name OrigDur
Start Finish
IBNSLMR-0910 FRAMING/INWALL ROUGH - SERV LVL MAIL IBN 55 19-Jun-13 05-Sep-13
IBNSLMR-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL MAIL IBN 30 30-Aug-13 11-Oct-13
IBNSLMR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL MAIL IBN 30 14-Oct-13 27-Nov-13
IBNSLMR-8880 CLEAN-UP/PRE PUNCH - SERV LVL MAIL IBN 15 28-Nov-13 18-Dec-13
IBN - SERVICE LEVIBN - SERVICE LEVEL - CORE/SHELLIBN - SERVICE LEVEL - CORE/SHELLIBN - SERVICE LEVEL - CORE/SHELLIBN - SERVICE LEVEL - CORE/SHELL
IBNSLCS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHELL IBN 15 18-Jul-13 07-Aug-13
IBNSLCS-0910 FRAMING/INWALL ROUGH - SERV LVL SHELL IBN 55 18-Jul-13 03-Oct-13
IBNSLCS-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL SHELL IBN 20 30-Sep-13 28-Oct-13
IBNSLCS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHELL IBN 15 29-Oct-13 19-Nov-13
IBNSLCS-8880 CLEAN-UP/PRE PUNCH - SERV LVL SHELL IBN 15 20-Nov-13 11-Dec-13
IBN - SERVICE LEVIBN - SERVICE LEVEL - CORRIDORIBN - SERVICE LEVEL - CORRIDORIBN - SERVICE LEVEL - CORRIDORIBN - SERVICE LEVEL - CORRIDOR
IBNSLCO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CORR IBN 20 20-Nov-13 18-Dec-13
IBNSLCO-8880 CLEAN-UP/PRE PUNCH - SERV LVL CORR IBN 15 19-Dec-13 10-Jan-14
IBN - LEVEL 1IBN - LEVEL 1IBN - LEVEL 1IBN - LEVEL 1IBN - LEVEL 1IBN - LEVEL 1 - INIBN - LEVEL 1 - INTERSTITIALIBN - LEVEL 1 - INTERSTITIALIBN - LEVEL 1 - INTERSTITIALIBN - LEVEL 1 - INTERSTITIAL
IBNL1IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-1 INTER IBN 100 26-Jun-13 18-Nov-13
IBNL1IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-1 INTER IBN 25 19-Nov-13 24-Dec-13
IBN - LEVEL 1 - PHIBN - LEVEL 1 - PHYSICAL/OCCUPATIONAL THERAPYIBN - LEVEL 1 - PHYSICAL/OCCUPATIONAL THERAPYIBN - LEVEL 1 - PHYSICAL/OCCUPATIONAL THERAPYIBN - LEVEL 1 - PHYSICAL/OCCUPATIONAL THERAPY
IBNL1PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-1 PT/OT IBN 20 26-Jun-13 24-Jul-13
IBNL1PR-0910 FRAMING/INWALL ROUGH - LVL-1 PT/OT IBN 55 26-Jun-13 12-Sep-13
IBNL1PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 PT/OT IBN 35 22-Aug-13 10-Oct-13
IBNL1PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PT/OT IBN 25 04-Oct-13 08-Nov-13
IBNL1PR-0977 INSTALL OWNER FIXED FF&E - LVL-1 PT/OT IBN 20 11-Oct-13 08-Nov-13
IBNL1PR-1190 INSTALL MEDICAL HEADWALLS - LVL-1 PT/OT IBN 35 12-Nov-13 02-Jan-14
IBNL1PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 PT/OT IBN 10 03-Jan-14 16-Jan-14
IBNL1PR-8880 CLEAN-UP/PRE PUNCH - LVL-1 PT/OT IBN 15 17-Jan-14 07-Feb-14
IBN - LEVEL 1 - URIBN - LEVEL 1 - UROLOGYIBN - LEVEL 1 - UROLOGYIBN - LEVEL 1 - UROLOGYIBN - LEVEL 1 - UROLOGY
IBNL1UR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 UROLOGY IBN 20 25-Jul-13 21-Aug-13
IBNL1UR-0910 FRAMING/INWALL ROUGH - LVL-1 UROLOGY IBN 55 25-Jul-13 10-Oct-13
IBNL1UR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 UROLOGY IBN 25 13-Sep-13 17-Oct-13
IBNL1UR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 UROLOGY IBN 30 11-Oct-13 26-Nov-13
IBNL1UR-0977 INSTALL OWNER FIXED FF&E - LVL-1 UROLOGY IBN 20 28-Oct-13 26-Nov-13
IBNL1UR-1190 INSTALL MEDICAL HEADWALLS - LVL-1 UROLOGY IBN 35 27-Nov-13 16-Jan-14
IBNL1UR-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 UROLOGY IBN 10 17-Jan-14 31-Jan-14
IBNL1UR-8880 CLEAN-UP/PRE PUNCH - LVL-1 UROLOGY IBN 15 03-Feb-14 24-Feb-14
IBN - LEVEL 1 - PHIBN - LEVEL 1 - PHARMACYIBN - LEVEL 1 - PHARMACYIBN - LEVEL 1 - PHARMACYIBN - LEVEL 1 - PHARMACY
IBNL1PY-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 PHARMACY IBN 20 22-Aug-13 19-Sep-13
IBNL1PY-0910 FRAMING/INWALL ROUGH - LVL-1 PHARMACY IBN 55 22-Aug-13 08-Nov-13
IBNL1PY-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 PHARMACY IBN 25 11-Oct-13 18-Nov-13
IBNL1PY-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PHARMACY IBN 25 12-Nov-13 17-Dec-13
IBNL1PY-0977 INSTALL OWNER FIXED FF&E - LVL-1 PHARMACY IBN 20 19-Nov-13 17-Dec-13
IBNL1PY-1190 INSTALL MEDICAL HEADWALLS - LVL-1 PHARMACY IBN 35 18-Dec-13 07-Feb-14
IBNL1PY-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 PHARMACY IBN 10 11-Feb-14 24-Feb-14
IBNL1PY-8880 CLEAN-UP/PRE PUNCH - LVL-1 PHARMACY IBN 15 25-Feb-14 17-Mar-14
IBN - LEVEL 1 - OFIBN - LEVEL 1 - OFFICES/ADMINISTRATIONIBN - LEVEL 1 - OFFICES/ADMINISTRATIONIBN - LEVEL 1 - OFFICES/ADMINISTRATIONIBN - LEVEL 1 - OFFICES/ADMINISTRATION
IBNL1OF-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 OFFICE IBN 20 20-Sep-13 17-Oct-13
IBNL1OF-0910 FRAMING/INWALL ROUGH - LVL-1 OFFICE IBN 55 20-Sep-13 10-Dec-13
IBNL1OF-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 OFFICE IBN 25 12-Nov-13 17-Dec-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 53 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 056
Activity ID Activity Name OrigDur
Start Finish
IBNL1OF-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 OFFICE IBN 30 11-Dec-13 24-Jan-14
IBNL1OF-0977 INSTALL OWNER FIXED FF&E - LVL-1 PT/OT IBN 20 26-Dec-13 24-Jan-14
IBNL1OF-1190 INSTALL MEDICAL HEADWALLS - LVL-1 OFFICE IBN 35 27-Jan-14 17-Mar-14
IBNL1OF-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 OFFICE IBN 10 18-Mar-14 31-Mar-14
IBNL1OF-8880 CLEAN-UP/PRE PUNCH - LVL-1 OFFICE IBN 15 01-Apr-14 21-Apr-14
IBN - LEVEL 1 - COIBN - LEVEL 1 - CORE/SHELLIBN - LEVEL 1 - CORE/SHELLIBN - LEVEL 1 - CORE/SHELLIBN - LEVEL 1 - CORE/SHELL
IBNL1CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 SHELL IBN 15 18-Oct-13 08-Nov-13
IBNL1CS-0910 FRAMING/INWALL ROUGH - LVL-1 SHELL IBN 55 18-Oct-13 09-Jan-14
IBNL1CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SHELL IBN 15 26-Dec-13 16-Jan-14
IBNL1CS-0977 INSTALL OWNER FIXED FF&E - LVL-1 PT/OT IBN 20 10-Jan-14 07-Feb-14
IBNL1CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SHELL IBN 15 17-Jan-14 07-Feb-14
IBNL1CS-8880 CLEAN-UP/PRE PUNCH - LVL-1 SHELL IBN 15 11-Feb-14 03-Mar-14
IBN - LEVEL 1 - COIBN - LEVEL 1 - CORRIDORIBN - LEVEL 1 - CORRIDORIBN - LEVEL 1 - CORRIDORIBN - LEVEL 1 - CORRIDOR
IBNL1CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 CORR IBN 20 11-Feb-14 10-Mar-14
IBNL1CO-8880 CLEAN-UP/PRE PUNCH - LVL-1 CORR IBN 10 11-Mar-14 24-Mar-14
IBN - LEVEL 2IBN - LEVEL 2IBN - LEVEL 2IBN - LEVEL 2IBN - LEVEL 2IBN - LEVEL 2 - INIBN - LEVEL 2 - INTERSTITIALIBN - LEVEL 2 - INTERSTITIALIBN - LEVEL 2 - INTERSTITIALIBN - LEVEL 2 - INTERSTITIAL
IBNL2IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-2 INTER IBN 100 15-Aug-13 09-Jan-14
IBNL2IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-2 INTER IBN 25 10-Jan-14 17-Feb-14
IBN - LEVEL 2 - PAIBN - LEVEL 2 - PATIENT ROOMSIBN - LEVEL 2 - PATIENT ROOMSIBN - LEVEL 2 - PATIENT ROOMSIBN - LEVEL 2 - PATIENT ROOMS
IBNL2PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-2 PATIENT IBN 20 15-Aug-13 12-Sep-13
IBNL2PR-0910 FRAMING/INWALL ROUGH - LVL-2 PATIENT IBN 55 15-Aug-13 01-Nov-13
IBNL2PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 PATIENT IBN 35 04-Oct-13 26-Nov-13
IBNL2PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 PATIENT IBN 35 12-Nov-13 02-Jan-14
IBNL2PR-0977 INSTALL OWNER FIXED FF&E - LVL-2 PATIENT IBN 20 04-Dec-13 02-Jan-14
IBNL2PR-1190 INSTALL MEDICAL HEADWALLS - LVL-2 PATIENT IBN 35 03-Jan-14 24-Feb-14
IBNL2PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 PATIENT IBN 10 25-Feb-14 10-Mar-14
IBNL2PR-8880 CLEAN-UP/PRE PUNCH - LVL-1 PATIENT IBN 15 11-Mar-14 31-Mar-14
IBN - LEVEL 2 - NUIBN - LEVEL 2 - NURSINGIBN - LEVEL 2 - NURSINGIBN - LEVEL 2 - NURSINGIBN - LEVEL 2 - NURSING
IBNL2NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 NURSING IBN 20 13-Sep-13 10-Oct-13
IBNL2NR-0910 FRAMING/INWALL ROUGH - LVL-2 NURSING IBN 55 13-Sep-13 03-Dec-13
IBNL2NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 NURSING IBN 35 04-Nov-13 24-Dec-13
IBNL2NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 NURSING IBN 35 11-Dec-13 31-Jan-14
IBNL2NR-0977 INSTALL OWNER FIXED FF&E - LVL-2 NURSING IBN 20 03-Jan-14 31-Jan-14
IBNL2NR-1190 INSTALL MEDICAL HEADWALLS - LVL-2 NURSING IBN 35 03-Feb-14 24-Mar-14
IBNL2NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 NURSING IBN 10 25-Mar-14 07-Apr-14
IBNL2NR-8880 CLEAN-UP/PRE PUNCH - LVL-2 NURSING IBN 15 08-Apr-14 28-Apr-14
IBN - LEVEL 2 - STIBN - LEVEL 2 - STAFF SUPPORT/SLEEPIBN - LEVEL 2 - STAFF SUPPORT/SLEEPIBN - LEVEL 2 - STAFF SUPPORT/SLEEPIBN - LEVEL 2 - STAFF SUPPORT/SLEEP
IBNL2SS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SUPPORT IBN 20 11-Oct-13 08-Nov-13
IBNL2SS-0910 FRAMING/INWALL ROUGH - LVL-2 SUPPORT IBN 55 11-Oct-13 02-Jan-14
IBNL2SS-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SUPPORT IBN 45 27-Nov-13 31-Jan-14
IBNL2SS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SUPPORT IBN 25 27-Jan-14 03-Mar-14
IBNL2SS-0977 INSTALL OWNER FIXED FF&E - LVL-2 SUPPORT IBN 20 03-Feb-14 03-Mar-14
IBNL2SS-1190 INSTALL MEDICAL HEADWALLS - LVL-2 SUPPORT IBN 35 04-Mar-14 21-Apr-14
IBNL2SS-8880 CLEAN-UP/PRE PUNCH - LVL-2 SUPPORT IBN 15 22-Apr-14 12-May-14
IBNL2SS-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 SUPPORT IBN 10 22-Apr-14 05-May-14
IBN - LEVEL 2 - COIBN - LEVEL 2 - CORE/SHELLIBN - LEVEL 2 - CORE/SHELLIBN - LEVEL 2 - CORE/SHELLIBN - LEVEL 2 - CORE/SHELL
IBNL2CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SHELL IBN 15 28-Oct-13 18-Nov-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 54 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 057
Activity ID Activity Name OrigDur
Start Finish
IBNL2CS-0910 FRAMING/INWALL ROUGH - LVL-2 SHELL IBN 15 28-Oct-13 18-Nov-13
IBNL2CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SHELL IBN 20 18-Dec-13 16-Jan-14
IBNL2CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SHELL IBN 20 10-Jan-14 07-Feb-14
IBNL2CS-0977 INSTALL OWNER FIXED FF&E - LVL-2 SHELL IBN 15 17-Jan-14 07-Feb-14
IBNL2CS-1190 INSTALL MEDICAL HEADWALLS - LVL-2 SHELL IBN 35 11-Feb-14 31-Mar-14
IBNL2CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 SHELL IBN 10 01-Apr-14 14-Apr-14
IBNL2CS-8880 CLEAN-UP/PRE PUNCH - LVL-2 SHELL IBN 15 15-Apr-14 05-May-14
IBN - LEVEL 2 - COIBN - LEVEL 2 - CORRIDORIBN - LEVEL 2 - CORRIDORIBN - LEVEL 2 - CORRIDORIBN - LEVEL 2 - CORRIDOR
IBNL2CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CORR IBN 15 01-Apr-14 21-Apr-14
IBNL2CO-8880 CLEAN-UP/PRE PUNCH - LVL-2 CORR IBN 10 22-Apr-14 05-May-14
IBN - LEVEL 3IBN - LEVEL 3IBN - LEVEL 3IBN - LEVEL 3IBN - LEVEL 3IBN - LEVEL 3 - INIBN - LEVEL 3 - INTERSTITIALIBN - LEVEL 3 - INTERSTITIALIBN - LEVEL 3 - INTERSTITIALIBN - LEVEL 3 - INTERSTITIAL
IBNL3IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-3 INTER IBN 100 06-Sep-13 31-Jan-14
IBNL3IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-3 INTER IBN 25 03-Feb-14 10-Mar-14
IBN - LEVEL 3 - PAIBN - LEVEL 3 - PATIENT ROOMSIBN - LEVEL 3 - PATIENT ROOMSIBN - LEVEL 3 - PATIENT ROOMSIBN - LEVEL 3 - PATIENT ROOMS
IBNL3PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-3 PATIENT IBN 20 06-Sep-13 03-Oct-13
IBNL3PR-0910 FRAMING/INWALL ROUGH - LVL-3 PATIENT IBN 55 06-Sep-13 26-Nov-13
IBNL3PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 PATIENT IBN 35 28-Oct-13 17-Dec-13
IBNL3PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PATIENT IBN 35 04-Dec-13 24-Jan-14
IBNL3PR-0977 INSTALL OWNER FIXED FF&E - LVL-3 PATIENT IBN 25 18-Dec-13 24-Jan-14
IBNL3PR-1190 INSTALL MEDICAL HEADWALLS - LVL-3 PATIENT IBN 35 27-Jan-14 17-Mar-14
IBNL3PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 PATIENT IBN 10 18-Mar-14 31-Mar-14
IBNL3PR-8880 CLEAN-UP/PRE PUNCH - LVL-3 PATIENT IBN 15 01-Apr-14 21-Apr-14
IBN - LEVEL 3 - NUIBN - LEVEL 3 - NURSINGIBN - LEVEL 3 - NURSINGIBN - LEVEL 3 - NURSINGIBN - LEVEL 3 - NURSING
IBNL3NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 NURSING IBN 25 04-Oct-13 08-Nov-13
IBNL3NR-0910 FRAMING/INWALL ROUGH - LVL-3 NURSING IBN 55 04-Oct-13 24-Dec-13
IBNL3NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 NURSING IBN 35 27-Nov-13 16-Jan-14
IBNL3NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 NURSING IBN 30 10-Jan-14 24-Feb-14
IBNL3NR-0977 INSTALL OWNER FIXED FF&E - LVL-3 PATIENT IBN 20 27-Jan-14 24-Feb-14
IBNL3NR-1190 INSTALL MEDICAL HEADWALLS - LVL-3 NURSING IBN 35 25-Feb-14 14-Apr-14
IBNL3NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 NURSING IBN 10 15-Apr-14 28-Apr-14
IBNL3NR-8880 CLEAN-UP/PRE PUNCH - LVL-3 NURSING IBN 15 29-Apr-14 19-May-14
IBN - LEVEL 3 - INIBN - LEVEL 3 - INPATIENT REHAB/THERAPYIBN - LEVEL 3 - INPATIENT REHAB/THERAPYIBN - LEVEL 3 - INPATIENT REHAB/THERAPYIBN - LEVEL 3 - INPATIENT REHAB/THERAPY
IBNL3RH-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 REHAB IBN 20 12-Nov-13 10-Dec-13
IBNL3RH-0910 FRAMING/INWALL ROUGH - LVL-3 REHAB IBN 60 12-Nov-13 07-Feb-14
IBNL3RH-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 REHAB IBN 35 10-Jan-14 03-Mar-14
IBNL3RH-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 REHAB IBN 25 25-Feb-14 31-Mar-14
IBNL3RH-0977 INSTALL OWNER FIXED FF&E - LVL-3 REHAB IBN 20 04-Mar-14 31-Mar-14
IBNL3RH-1190 INSTALL MEDICAL HEADWALLS - LVL-3 REHAB IBN 35 01-Apr-14 19-May-14
IBNL3RH-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 REHAB IBN 10 20-May-14 03-Jun-14
IBNL3RH-8880 CLEAN-UP/PRE PUNCH - LVL-3 REHAB IBN 15 20-May-14 10-Jun-14
IBN - LEVEL 3 - COIBN - LEVEL 3 - CORE/SHELLIBN - LEVEL 3 - CORE/SHELLIBN - LEVEL 3 - CORE/SHELLIBN - LEVEL 3 - CORE/SHELL
IBNL3CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 SHELL IBN 15 11-Dec-13 02-Jan-14
IBNL3CS-0910 FRAMING/INWALL ROUGH - LVL-3 SHELL IBN 35 11-Dec-13 31-Jan-14
IBNL3CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 SHELL IBN 35 03-Feb-14 24-Mar-14
IBNL3CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SHELL IBN 30 04-Mar-14 14-Apr-14
IBNL3CS-0977 INSTALL OWNER FIXED FF&E - LVL-3 SHELL IBN 20 18-Mar-14 14-Apr-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 55 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 058
Activity ID Activity Name OrigDur
Start Finish
IBNL3CS-1190 INSTALL MEDICAL HEADWALLS - LVL-3 SHELL IBN 35 15-Apr-14 03-Jun-14
IBNL3CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 SHELL IBN 10 04-Jun-14 17-Jun-14
IBNL3CS-8880 CLEAN-UP/PRE PUNCH - LVL-3 SHELL IBN 15 18-Jun-14 09-Jul-14
IBN - LEVEL 3 - COIBN - LEVEL 3 - CORRIDORIBN - LEVEL 3 - CORRIDORIBN - LEVEL 3 - CORRIDORIBN - LEVEL 3 - CORRIDOR
IBNL3CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CORR IBN 20 20-May-14 17-Jun-14
IBNL3CO-8880 CLEAN-UP/PRE PUNCH - LVL-3 CORR IBN 10 18-Jun-14 01-Jul-14
IBN - PENTHOUIBN - PENTHOUSEIBN - PENTHOUSEIBN - PENTHOUSEIBN - PENTHOUSEIBN - PENTHOUSEIBN - PENTHOUSE - MECHANICALIBN - PENTHOUSE - MECHANICALIBN - PENTHOUSE - MECHANICALIBN - PENTHOUSE - MECHANICAL
IBNPHME-0420 LAY CMU WALLS - PENT MECH IBN 15 26-Aug-13 16-Sep-13
IBNPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENT MECH IBN 45 17-Sep-13 20-Nov-13
IBNPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENT MECH IBN 60 22-Nov-13 19-Feb-14
IBNPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH IBN 30 05-Feb-14 19-Mar-14
IBNPHME-1590 START-UP MECH EQUIP - PENT MECH IBN 20 20-Mar-14 16-Apr-14
IBN - PENTHOUSEIBN - PENTHOUSE - ELECTRICALIBN - PENTHOUSE - ELECTRICALIBN - PENTHOUSE - ELECTRICALIBN - PENTHOUSE - ELECTRICAL
IBNPHEL-0910 FRAMING/INWALL ROUGH - PENT ELEC IBN 10 08-Oct-13 22-Oct-13
IBNPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENT ELEC IBN 10 23-Oct-13 05-Nov-13
IBNPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC IBN 70 23-Oct-13 04-Feb-14
IBN - ALL LEVELIBN - ALL LEVELSIBN - ALL LEVELSIBN - ALL LEVELSIBN - ALL LEVELSIBNALAL-0556 ERECT STAIRS ST2 - ALL LVLS IBN 15 22-Mar-13 16-Apr-13
IBNALAL-0555 ERECT STAIRS ST1 - ALL LVLS IBN 15 09-Apr-13 06-May-13
IBNALAL-1400 INSTALL ELEVATOR SE1/SE2 - ALL LVLS IBN 60 16-Jan-14 22-Apr-14
IBNALAL-1401 INSTALL ELEVATOR PE1/PE2 - ALL LVLS IBN 60 16-Jan-14 22-Apr-14
IBNALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS IBN 15 28-May-14 17-Jun-14
IBNALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS IBN 15 18-Jun-14 09-Jul-14
IBN - COMMISSIIBN - COMMISSIONINGIBN - COMMISSIONINGIBN - COMMISSIONINGIBN - COMMISSIONINGIBNCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - IBN 30 02-Jul-14 13-Aug-14
IBNCOCO-1592 TEST & BALANCE - IBN 25 14-Aug-14 18-Sep-14
IBNCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - IBN 20 14-Aug-14 11-Sep-14
IBNCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - IBN 20 12-Sep-14 09-Oct-14
IBNCOCO-1599 BUILDING FLUSH - IBN 10 10-Oct-14 19-Oct-14
CLINIC BUILDCLINIC BUILDINGS (CBN)CLINIC BUILDINGS (CBN)CLINIC BUILDINGS (CBN)CLINIC BUILDINGS (CBN)CLINIC BUILDINCLINIC BUILDING NORTH (CBN) - STRUCTURECLINIC BUILDING NORTH (CBN) - STRUCTURECLINIC BUILDING NORTH (CBN) - STRUCTURECLINIC BUILDING NORTH (CBN) - STRUCTURECBN - SERVICE CBN - SERVICE LEVELCBN - SERVICE LEVELCBN - SERVICE LEVELCBN - SERVICE LEVELCBNSLSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL CBN 15 30-Mar-12 16-Apr-12
CBNSLSL-8890 DRILL/PLACE CAISSONS (with concourse) - SERV LVL CBN 15 12-Jun-12 06-Jul-12
CBNSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/WALLS/GRD BEAMS - SERV LVL CBN 35 09-Jul-12 06-Sep-12
CBNSLSL-0390 PERIMETER DRAINS/BACKFILL PIERCAPS/GRADE BEAMS - SERV LVL CBN 14 07-Sep-12 01-Oct-12
CBNSLSL-3110 SET/BACKFILL DUCTBANKS - SERV LVL CBN 5 02-Oct-12 08-Oct-12
CBNSLSL-3200 UNDERSLAB UTILITIES - SERV LVL CBN 15 11-Oct-12 05-Nov-12
CBNSLSL-0380 FINE GRADE/FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL CBN 8 21-Nov-12 04-Dec-12
CBNSLSL-0320 DRILL/PLACE CAISSONS (balance @ bench) - SERV LVL CBN 5 10-Dec-12 14-Dec-12
CBN - SUPER STCBN - SUPER STRUCTURECBN - SUPER STRUCTURECBN - SUPER STRUCTURECBN - SUPER STRUCTURECBNSLSL-0352 FORM/PLACE/STRIP SHEAR WALLS - SERV LVL CBN 45 07-Sep-12 20-Nov-12
CBNSSSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBN 35 17-Dec-12 08-Feb-13
CBN - PENTHOUSECBN - PENTHOUSECBN - PENTHOUSECBN - PENTHOUSECBN - PENTHOUSE
CBNPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT LVL CBN 19 11-Feb-13 12-Mar-13
CBNPHPH-0725 SPRAY-ON FIREPROOFING - PENTLVL CBN 10 14-Mar-13 28-Mar-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 56 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 059
Activity ID Activity Name OrigDur
Start Finish
CBNPHPH-0310 FORM/REINFORCE/FINISH HOUSEKEEPING PADS - PENT LVL CBN 7 14-Mar-13 22-Mar-13
CBNPHPH-1500 SET MECH EQUIPMENT - PENTLVL CBN 5 25-Mar-13 29-Mar-13
CBNPHPH-1600 SET ELECTRICAL EQUIPMENT - PENTLVL CBN 10 01-Apr-13 12-Apr-13
CBNPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTLVL CBN 15 15-Apr-13 10-May-13
CBNPHPH-0710 INSTALL LOUVERS - PENTLVL CBN 10 13-May-13 29-May-13
CBNPHPH-0777 INSTALL METAL PANEL - PENTLVL CBN 10 30-May-13 14-Jun-13
CBN - PENTHOCBN - PENTHOUSE ROOFCBN - PENTHOUSE ROOFCBN - PENTHOUSE ROOFCBN - PENTHOUSE ROOF
CBNPHPR-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT ROOF CBN 11 14-Mar-13 29-Mar-13
CBNHRPR-0788 APPLY ROOFING SYSTEM - PENT ROOF CBN 15 01-Apr-13 25-Apr-13
CBNHRPR-0750 BLOCKING/ICE WATER SHIELD- PENT ROOF CBN 20 26-Apr-13 31-May-13
CBNHRPR-0740 INSTALL/CONNECT PV PANELS - PENT ROOF CBN 20 03-Jun-13 05-Jul-13
CBN - LEVEL 3CBN - LEVEL 3CBN - LEVEL 3CBN - LEVEL 3CBN - LEVEL 3
CBNL3L3-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 CBN 11 26-Mar-13 12-Apr-13
CBNL3L3-0725 SPRAY-ON FIREPROOFING - LVL-3 CBN 10 15-Apr-13 02-May-13
CBNL3L3-0540 ERECT EXTERIOR STUDS - LVL-3 CBN 15 03-May-13 29-May-13
CBN - LEVEL 2CBN - LEVEL 2CBN - LEVEL 2CBN - LEVEL 2CBN - LEVEL 2
CBNL2L2-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 CBN 11 12-Apr-13 02-May-13
CBNL2L2-0725 SPRAY-ON FIREPROOFING - LVL-2 CBN 10 03-May-13 20-May-13
CBNL2L2-0540 ERECT EXTERIOR STUDS - LVL-2 CBN 15 21-May-13 14-Jun-13
CBN - LEVEL 1CBN - LEVEL 1CBN - LEVEL 1CBN - LEVEL 1CBN - LEVEL 1
CBNL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 CBN 11 06-May-13 23-May-13
CBNL1L1-0725 SPRAY-ON FIREPROOFING - LVL-1 CBN 10 24-May-13 10-Jun-13
CBNL1L1-0540 ERECT EXTERIOR STUDS - LVL-1 CBN 15 11-Jun-13 05-Jul-13
CBN - LOW ROOCBN - LOW ROOF (elevation = 160')CBN - LOW ROOF (elevation = 160')CBN - LOW ROOF (elevation = 160')CBN - LOW ROOF (elevation = 160')CBNLRLR-0710 PARAPET/BLOCKING/WATERPROOFING - LOW ROOF CBN 10 17-Jun-13 02-Jul-13
CBNLRLR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF CBN 15 03-Jul-13 29-Jul-13
CBNLRLR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF CBN 3 30-Jul-13 02-Aug-13
CLINIC BUILDINCLINIC BUILDING NORTH (CBN) - EXTERIOR SKINCLINIC BUILDING NORTH (CBN) - EXTERIOR SKINCLINIC BUILDING NORTH (CBN) - EXTERIOR SKINCLINIC BUILDING NORTH (CBN) - EXTERIOR SKINCBN - NORTH ECBN - NORTH ELEVATIONCBN - NORTH ELEVATIONCBN - NORTH ELEVATIONCBN - NORTH ELEVATIONCBNESNE-0520 SHEATHING/VAPOR BARRIER - NORTH ELEV CBN 10 08-Jul-13 23-Jul-13
CBNESNE-0440 INSTALL PRECAST PANELS - NORTH ELEV CBN 8 25-Jul-13 06-Aug-13
CBNESSE-877 INSTALL CURTAIN WALL - NORTH ELEV CBN 35 08-Aug-13 04-Oct-13
CBN - WEST ELECBN - WEST ELEVATIONCBN - WEST ELEVATIONCBN - WEST ELEVATIONCBN - WEST ELEVATIONCBNESWE-0520 SHEATHING/VAPOR BARRIER - WEST ELEV CBN 5 25-Jul-13 01-Aug-13
CBNESWE-0440 INSTALL PRECAST PANELS - WEST ELEV CBN 4 02-Aug-13 08-Aug-13
CBNESSE-887 INSTALL CURTAIN WALL - WEST ELEV CBN 20 09-Aug-13 12-Sep-13
CBN - SOUTH ECBN - SOUTH ELEVATIONCBN - SOUTH ELEVATIONCBN - SOUTH ELEVATIONCBN - SOUTH ELEVATIONCBNESSE-0520 SHEATHING/VAPOR BARRIER - SOUTH ELEV CBN 10 02-Aug-13 19-Aug-13
CBNESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV CBN 35 20-Aug-13 17-Oct-13
CBN - EAST ELECBN - EAST ELEVATIONCBN - EAST ELEVATIONCBN - EAST ELEVATIONCBN - EAST ELEVATIONCBNESEE-0520 SHEATHING/VAPOR BARRIER - EAST ELEV CBN 5 20-Aug-13 27-Aug-13
CBNESEE-0440 INSTALL METAL PANELS - EAST ELEV CBN 5 29-Aug-13 05-Sep-13
CLINIC BUILDINCLINIC BUILDING NORTH (CBN) - INTERIOR BUILDOUTCLINIC BUILDING NORTH (CBN) - INTERIOR BUILDOUTCLINIC BUILDING NORTH (CBN) - INTERIOR BUILDOUTCLINIC BUILDING NORTH (CBN) - INTERIOR BUILDOUTCBN - PENTHOUCBN - PENTHOUSECBN - PENTHOUSECBN - PENTHOUSECBN - PENTHOUSECBN - PENTHOUSECBN - PENTHOUSE - MECHANICALCBN - PENTHOUSE - MECHANICALCBN - PENTHOUSE - MECHANICALCBN - PENTHOUSE - MECHANICAL
CBNPHME-0420 LAY CMU WALLS - PENTHOUSE MECH CBN 15 17-Jun-13 08-Jul-13
CBNPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECH CBN 30 09-Jul-13 19-Aug-13
CBNPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENTHOUSE MECH CBN 25 20-Aug-13 24-Sep-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 57 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 060
Activity ID Activity Name OrigDur
Start Finish
CBNPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH CBN 30 27-Jun-14 08-Aug-14
CBNPHME-1590 START-UP MECH EQUIP - PENT MECH CBN 20 11-Aug-14 08-Sep-14
CBN - PENTHOUSECBN - PENTHOUSE - ELECTRICALCBN - PENTHOUSE - ELECTRICALCBN - PENTHOUSE - ELECTRICALCBN - PENTHOUSE - ELECTRICAL
CBNPHEL-0910 FRAMING/INWALL ROUGH - PENT ELEC CBN 10 18-Oct-13 01-Nov-13
CBNPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENT ELEC CBN 15 20-Feb-14 12-Mar-14
CBNPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC CBN 75 13-Mar-14 26-Jun-14
CBNPHEL-1630 INTERIOR FINISHES - PENT ELEC CBN 30 13-Jun-14 25-Jul-14
CBN - LEVEL 3CBN - LEVEL 3CBN - LEVEL 3CBN - LEVEL 3CBN - LEVEL 3CBN - LEVEL 3 - ARCBN - LEVEL 3 - AREA ACBN - LEVEL 3 - AREA ACBN - LEVEL 3 - AREA ACBN - LEVEL 3 - AREA A
CBNL3AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-3 AREA A CBN 20 28-Aug-13 25-Sep-13
CBNL3AA-0910 FRAMING/INWALL ROUGH - LVL-3 AREA A CBN 14 22-Jan-14 11-Feb-14
CBNL3AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA A CBN 13 05-Feb-14 24-Feb-14
CBNL3AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA A CBN 23 20-Feb-14 24-Mar-14
CBNL3AA-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBN 15 04-Mar-14 24-Mar-14
CBNL3AA-8880 CLEAN-UP/PRE PUNCH - LVL-3 AREA A CBN 8 25-Mar-14 03-Apr-14
CBN - LEVEL 3 - ARCBN - LEVEL 3 - AREA BCBN - LEVEL 3 - AREA BCBN - LEVEL 3 - AREA BCBN - LEVEL 3 - AREA B
CBNL3AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AREA B CBN 20 12-Sep-13 09-Oct-13
CBNL3AB-0910 FRAMING/INWALL ROUGH - LVL-3 AREA B CBN 14 09-Jan-14 29-Jan-14
CBNL3AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA B CBN 12 13-Feb-14 28-Feb-14
CBNL3AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA B CBN 22 27-Feb-14 28-Mar-14
CBNL3AB-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBN 15 10-Mar-14 28-Mar-14
CBNL3AB-8880 CLEAN-UP/PRE PUNCH - LVL-3 AREA B CBN 8 31-Mar-14 09-Apr-14
CBN - LEVEL 2CBN - LEVEL 2CBN - LEVEL 2CBN - LEVEL 2CBN - LEVEL 2CBN - LEVEL 2 - ARCBN - LEVEL 2 - AREA ACBN - LEVEL 2 - AREA ACBN - LEVEL 2 - AREA ACBN - LEVEL 2 - AREA A
CBNL2AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-2 AREA A CBN 18 26-Sep-13 22-Oct-13
CBNL2AA-0910 FRAMING/INWALL ROUGH - LVL-2 AREA A CBN 14 27-Dec-13 16-Jan-14
CBNL2AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA A CBN 13 13-Jan-14 30-Jan-14
CBNL2AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA A CBN 23 28-Jan-14 28-Feb-14
CBNL2AA-0977 INSTALL OWNER FIXED FF&E - LVL-2 AREA-A CBN 15 07-Feb-14 28-Feb-14
CBNL2AA-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBN 8 03-Mar-14 12-Mar-14
CBN - LEVEL 2 - ARCBN - LEVEL 2 - AREA BCBN - LEVEL 2 - AREA BCBN - LEVEL 2 - AREA BCBN - LEVEL 2 - AREA B
CBNL2AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AREA B CBN 17 10-Oct-13 04-Nov-13
CBNL2AB-0910 FRAMING/INWALL ROUGH - LVL-2 AREA B CBN 14 16-Dec-13 06-Jan-14
CBNL2AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA B CBN 12 21-Jan-14 05-Feb-14
CBNL2AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA B CBN 22 04-Feb-14 06-Mar-14
CBNL2AB-0977 INSTALL OWNER FIXED FF&E - LVL-2 AREA-B CBN 15 14-Feb-14 06-Mar-14
CBNL2AB-8880 CLEAN-UP/PRE PUNCH - LVL-2 AREA B CBN 8 07-Mar-14 18-Mar-14
CBN - LEVEL 1CBN - LEVEL 1CBN - LEVEL 1CBN - LEVEL 1CBN - LEVEL 1CBN - LEVEL 1 - ARCBN - LEVEL 1 - AREA ACBN - LEVEL 1 - AREA ACBN - LEVEL 1 - AREA ACBN - LEVEL 1 - AREA A
CBNL1AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-1 AREA A CBN 18 25-Oct-13 20-Nov-13
CBNL1AA-0910 FRAMING/INWALL ROUGH - LVL-1 AREA A CBN 14 04-Dec-13 23-Dec-13
CBNL1AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA A CBN 13 18-Dec-13 07-Jan-14
CBNL1AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA A CBN 23 03-Jan-14 05-Feb-14
CBNL1AA-0977 INSTALL OWNER FIXED FF&E - LVL-1 AREA-A CBN 15 15-Jan-14 05-Feb-14
CBNL1AA-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBN 8 06-Feb-14 18-Feb-14
CBN - LEVEL 1 - ARCBN - LEVEL 1 - AREA BCBN - LEVEL 1 - AREA BCBN - LEVEL 1 - AREA BCBN - LEVEL 1 - AREA B
CBNL1AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AREA B CBN 17 08-Nov-13 04-Dec-13
CBNL1AB-0910 FRAMING/INWALL ROUGH - LVL-1 AREA B CBN 14 22-Nov-13 11-Dec-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 58 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 061
Activity ID Activity Name OrigDur
Start Finish
CBNL1AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA B CBN 12 26-Dec-13 13-Jan-14
CBNL1AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA B CBN 22 10-Jan-14 12-Feb-14
CBNL1AB-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBN 15 22-Jan-14 12-Feb-14
CBNL1AB-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA B CBN 8 13-Feb-14 24-Feb-14
CBN - SERVICE CBN - SERVICE LEVELCBN - SERVICE LEVELCBN - SERVICE LEVELCBN - SERVICE LEVELCBN - SERVICE LECBN - SERVICE LEVEL - ELEVATOR LOBBYCBN - SERVICE LEVEL - ELEVATOR LOBBYCBN - SERVICE LEVEL - ELEVATOR LOBBYCBN - SERVICE LEVEL - ELEVATOR LOBBY
CBNSLSL-0910 FRAMING/INWALL ROUGH - SERV LVL CBN 5 13-Feb-14 19-Feb-14
CBNSLSL-0990 HANG/TAPE/FINISH/PAINT - SERV LVL CORR CBN 10 20-Feb-14 05-Mar-14
CBNSLSL-8880 CLEAN-UP/PRE PUNCH - SERV LVL CORR CBN 5 06-Mar-14 12-Mar-14
CBN - ALL LEVECBN - ALL LEVELSCBN - ALL LEVELSCBN - ALL LEVELSCBN - ALL LEVELSCBNALAL-0555 ERECT STAIRS ST1 - ALL LVLS CBN 15 12-Feb-13 04-Mar-13
CBNALAL-0556 ERECT STAIRS ST2 - ALL LVLS CBN 15 05-Mar-13 25-Mar-13
CBNALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS CBN 15 20-Feb-14 12-Mar-14
CBNALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS CBN 15 13-Mar-14 02-Apr-14
CBNALAL-1400 INSTALL ELEVATOR SE5 - ALL LVLS CBN 60 13-Jun-14 08-Sep-14
CLINIC BUILDINCLINIC BUILDINGS COMMISSIONING - CBNCLINIC BUILDINGS COMMISSIONING - CBNCLINIC BUILDINGS COMMISSIONING - CBNCLINIC BUILDINGS COMMISSIONING - CBNCBNCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - CBN 33 09-Sep-14 24-Oct-14
CBNCOCO-1620 TEST & BALANCE - CBN 30 27-Oct-14 09-Dec-14
CBNCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS 20 27-Oct-14 25-Nov-14
CBNCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - CBN 25 26-Nov-14 31-Dec-14
CBNCOCO-1599 BUILDING FLUSH - CBN 20 31-Dec-14 20-Jan-15
CLINIC BUILDCLINIC BUILDING CENTRAL (CBC)CLINIC BUILDING CENTRAL (CBC)CLINIC BUILDING CENTRAL (CBC)CLINIC BUILDING CENTRAL (CBC)CLINIC BUILDINCLINIC BUILDING CENTRAL (CBC) - STRUCTURECLINIC BUILDING CENTRAL (CBC) - STRUCTURECLINIC BUILDING CENTRAL (CBC) - STRUCTURECLINIC BUILDING CENTRAL (CBC) - STRUCTURECBC - SERVICE CBC - SERVICE LEVELCBC - SERVICE LEVELCBC - SERVICE LEVELCBC - SERVICE LEVELCBCSLSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL CBC 15 21-Jun-12 10-Jul-12
CBCSLSL-3210 DRILL/PLACE CAISSONS (with concourse) - SERV LVL CBC 5 10-Jul-12 19-Jul-12
CBCSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ GRD BEAMS/WALLS/COLUMNS - SERV LVL CBC 35 19-Jul-12 18-Sep-12
CBCSLSL-3110 SET/BACKFILL DUCTBANKS - SER LVL CBC 5 18-Sep-12 27-Sep-12
CBCSLSL-0390 PERIMETER DRAINS/BACKFILL PIERCAPS/GRADE BEAMS - SERV LVL CBC 14 27-Sep-12 19-Oct-12
CBCSLSL-3200 UNDERSLAB UTILITIES - SERV LVL CBC 15 11-Oct-12 05-Nov-12
CBCSLSL-0380 FINE GRADE FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL CBC 8 03-Dec-12 14-Dec-12
CBCSLSL-0320 DRILL/PLACE CAISSONS (balance @ bench) - SERV LVL CBC 15 29-Mar-13 23-Apr-13
CBC - SUPER STCBC - SUPER STRUCTURECBC - SUPER STRUCTURECBC - SUPER STRUCTURECBC - SUPER STRUCTURECBCSSSS-0352 FORM/PLACE/STRIP SHEAR WALLS - ALL LVLS CBC 45 18-Sep-12 03-Dec-12
CBCSSSS-510 FORM/PLACE/STRIP SHEAR WALLS (southwest corner) - ALL LVLS CBC 45 16-Apr-13 03-Jul-13
CBCSSSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBC 33 05-Jul-13 30-Aug-13
CBC - PENTHOUSECBC - PENTHOUSECBC - PENTHOUSECBC - PENTHOUSECBC - PENTHOUSE
CBCPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT LVL CBC 19 03-Sep-13 02-Oct-13
CBCPHPH-0310 FORM/REINFORCE/FINISH HOUSEKEEPING PADS - PENT LVL CBC 7 03-Oct-13 11-Oct-13
CBCPHPH-0725 SPRAY-ON FIREPROOFING - PENTLVL CBC 10 03-Oct-13 18-Oct-13
CBCPHPH-1500 SET MECH EQUIPMENT - PENTLVL CBC 5 14-Oct-13 18-Oct-13
CBCPHPH-1600 SET ELECTRICAL EQUIPMENT - PENTLVL CBC 10 22-Oct-13 04-Nov-13
CBCPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTLVL CBC 15 05-Nov-13 29-Nov-13
CBCPHPH-0710 INSTALL LOUVERS - PENTLVL CBC 10 02-Dec-13 16-Dec-13
CBCPHPH-0777 INSTALL METAL PANEL - PENTLVL CBC 10 17-Dec-13 02-Jan-14
CBC - PENTHOCBC - PENTHOUSE ROOFCBC - PENTHOUSE ROOFCBC - PENTHOUSE ROOFCBC - PENTHOUSE ROOF
CBCPHPR-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT ROOF CBC 11 03-Oct-13 21-Oct-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 59 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 062
Activity ID Activity Name OrigDur
Start Finish
CBCHRPR-0755 INSTALL ROOFING SYSTEM- PENT ROOF CBC 15 22-Oct-13 14-Nov-13
CBCHRPR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- PENT ROOF CBC 20 15-Nov-13 17-Dec-13
CBCHRPR-755 INSTALL PV PANELS - PENT ROOF CBC 20 19-Dec-13 21-Jan-14
CBC - LEVEL 3CBC - LEVEL 3CBC - LEVEL 3CBC - LEVEL 3CBC - LEVEL 3
CBCL3L3-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 CBC 11 10-Oct-13 28-Oct-13
CBCL3L3-0725 SPRAY-ON FIREPROOFING - LVL-3 CBC 10 29-Oct-13 14-Nov-13
CBCL3L3-0540 ERECT EXTERIOR STUDS - LVL-3 CBC 15 02-Dec-13 24-Dec-13
CBC - LEVEL 2CBC - LEVEL 2CBC - LEVEL 2CBC - LEVEL 2CBC - LEVEL 2
CBCL2L2-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 CBC 11 28-Oct-13 14-Nov-13
CBCL2L2-0725 SPRAY-ON FIREPROOFING - LVL-2 CBC 10 15-Nov-13 02-Dec-13
CBCL2L2-0540 ERECT EXTERIOR STUDS - LVL-2 CBC 15 26-Dec-13 17-Jan-14
CBC - LEVEL 1CBC - LEVEL 1CBC - LEVEL 1CBC - LEVEL 1CBC - LEVEL 1
CBCL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 CBC 11 18-Nov-13 05-Dec-13
CBCL1L1-0725 SPRAY-ON FIREPROOFING - LVL-1 CBC 10 06-Dec-13 20-Dec-13
CBCL1L1-0540 ERECT EXTERIOR STUDS - LVL-1 CBC 7 21-Jan-14 29-Jan-14
CBC - LOW ROOCBC - LOW ROOF (elevation = 160')CBC - LOW ROOF (elevation = 160')CBC - LOW ROOF (elevation = 160')CBC - LOW ROOF (elevation = 160')CBCLRLR-0710 PARAPET/BLOCKING/WATERPROOFING - LOW ROOF CBC 10 03-Jan-14 17-Jan-14
CBCLRLR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF CBC 15 21-Jan-14 11-Feb-14
CBCLRLR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF CBC 3 13-Feb-14 17-Feb-14
CLINIC BUILDINCLINIC BUILDING CENTRAL (CBC) - EXTERIOR SKINCLINIC BUILDING CENTRAL (CBC) - EXTERIOR SKINCLINIC BUILDING CENTRAL (CBC) - EXTERIOR SKINCLINIC BUILDING CENTRAL (CBC) - EXTERIOR SKINCBC - NORTH ECBC - NORTH ELEVATIONCBC - NORTH ELEVATIONCBC - NORTH ELEVATIONCBC - NORTH ELEVATIONCBCESNE-0520 SHEATHING/VAPOR BARRIER - NORTH ELEV CBC 10 30-Jan-14 14-Feb-14
CBCESNE-0440 INSTALL PRECAST PANELS - NORTH ELEV CBC 8 17-Feb-14 26-Feb-14
CBCESNE-0870 INSTALL CURTAIN WALL - NORTH ELEV CBC 40 27-Feb-14 05-May-14
CBC - WEST ELECBC - WEST ELEVATIONCBC - WEST ELEVATIONCBC - WEST ELEVATIONCBC - WEST ELEVATIONCBCESWE-0520 SHEATHING/VAPOR BARRIER - WEST ELEV CBC 5 17-Feb-14 21-Feb-14
CBCESWE-0440 INSTALL PRECAST PANELS - WEST ELEV CBC 4 24-Feb-14 27-Feb-14
CBCESWE-0870 INSTALL CURTAIN WALL - WEST ELEV CBC 20 28-Feb-14 01-Apr-14
CBC - SOUTH ELCBC - SOUTH ELEVATIONCBC - SOUTH ELEVATIONCBC - SOUTH ELEVATIONCBC - SOUTH ELEVATIONCBCESSE-0520 SHEATHING/VAPOR BARRIER - SOUTH ELEV CBC 10 24-Feb-14 07-Mar-14
CBCESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV CBC 40 10-Mar-14 16-May-14
CBC - EAST ELECBC - EAST ELEVATIONCBC - EAST ELEVATIONCBC - EAST ELEVATIONCBC - EAST ELEVATIONCBCESEE-0520 SHEATHING/VAPOR BARRIER - EAST ELEV CBC 5 10-Mar-14 17-Mar-14
CBCESEE-0440 INSTALL METAL PANELS - EAST ELEV CBC 5 18-Mar-14 25-Mar-14
CLINIC BUILDINCLINIC BUILDING CENTRAL (CBC) - INTERIOR BUILDOUTCLINIC BUILDING CENTRAL (CBC) - INTERIOR BUILDOUTCLINIC BUILDING CENTRAL (CBC) - INTERIOR BUILDOUTCLINIC BUILDING CENTRAL (CBC) - INTERIOR BUILDOUTCBC - PENTHOUCBC - PENTHOUSECBC - PENTHOUSECBC - PENTHOUSECBC - PENTHOUSECBC - PENTHOUSECBC - PENTHOUSE - MECHANICALCBC - PENTHOUSE - MECHANICALCBC - PENTHOUSE - MECHANICALCBC - PENTHOUSE - MECHANICAL
CBCPHME-0420 LAY CMU WALLS - PENTHOUSE MECH CBC 15 03-Jan-14 24-Jan-14
CBCPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECH CBC 30 27-Jan-14 10-Mar-14
CBCPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENTHOUSE MECH CBC 25 11-Mar-14 14-Apr-14
CBCPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH CBC 30 08-Jul-14 18-Aug-14
CBCPHME-1590 START-UP MECH EQUIP - PENT MECH CBC 20 19-Aug-14 16-Sep-14
CBC - PENTHOUSECBC - PENTHOUSE - ELECTRICALCBC - PENTHOUSE - ELECTRICALCBC - PENTHOUSE - ELECTRICALCBC - PENTHOUSE - ELECTRICAL
CBCPHEL-0910 FRAMING/INWALL ROUGH - PENT ELEC CBC 8 18-Feb-14 27-Feb-14
CBCPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENT ELEC CBC 15 28-Feb-14 20-Mar-14
CBCPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC CBC 75 21-Mar-14 07-Jul-14
CBCPHEL-1630 INTERIOR FINISHES - PENT ELEC CBC 30 23-Jun-14 04-Aug-14
CBC - LEVEL 3CBC - LEVEL 3CBC - LEVEL 3CBC - LEVEL 3CBC - LEVEL 3
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 60 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 063
Activity ID Activity Name OrigDur
Start Finish
CBC - LEVEL 3 - ARCBC - LEVEL 3 - AREA ACBC - LEVEL 3 - AREA ACBC - LEVEL 3 - AREA ACBC - LEVEL 3 - AREA A
CBCL3AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-3 AREA A CBC 20 18-Mar-14 14-Apr-14
CBCL3AA-0910 FRAMING/INWALL ROUGH - LVL-3 AREA A CBC 14 15-Jul-14 01-Aug-14
CBCL3AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA A CBC 13 29-Jul-14 14-Aug-14
CBCL3AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA A CBC 23 12-Aug-14 12-Sep-14
CBCL3AA-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBC 15 22-Aug-14 12-Sep-14
CBCL3AA-8880 CLEAN-UP/PRE PUNCH - LVL-3 AREA A CBC 8 15-Sep-14 24-Sep-14
CBC - LEVEL 3 - ARCBC - LEVEL 3 - AREA BCBC - LEVEL 3 - AREA BCBC - LEVEL 3 - AREA BCBC - LEVEL 3 - AREA B
CBCL3AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AREA B CBC 20 01-Apr-14 28-Apr-14
CBCL3AB-0910 FRAMING/INWALL ROUGH - LVL-3 AREA B CBC 14 08-Jul-14 25-Jul-14
CBCL3AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA B CBC 12 05-Aug-14 20-Aug-14
CBCL3AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA B CBC 22 19-Aug-14 18-Sep-14
CBCL3AB-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-B CBC 15 28-Aug-14 18-Sep-14
CBCL3AB-8880 CLEAN-UP/PRE PUNCH - LVL-3 AREA B CBC 8 19-Sep-14 30-Sep-14
CBC - LEVEL 2CBC - LEVEL 2CBC - LEVEL 2CBC - LEVEL 2CBC - LEVEL 2CBC - LEVEL 2 - ARCBC - LEVEL 2 - AREA ACBC - LEVEL 2 - AREA ACBC - LEVEL 2 - AREA ACBC - LEVEL 2 - AREA A
CBCL2AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-2 AREA A CBC 18 15-Apr-14 08-May-14
CBCL2AA-0910 FRAMING/INWALL ROUGH - LVL-2 AREA A CBC 14 30-Jun-14 18-Jul-14
CBCL2AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA A CBC 13 15-Jul-14 31-Jul-14
CBCL2AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA A CBC 23 29-Jul-14 28-Aug-14
CBCL2AA-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBC 15 08-Aug-14 28-Aug-14
CBCL2AA-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBC 8 29-Aug-14 10-Sep-14
CBC - LEVEL 2 - ARCBC - LEVEL 2 - AREA BCBC - LEVEL 2 - AREA BCBC - LEVEL 2 - AREA BCBC - LEVEL 2 - AREA B
CBCL2AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AREA B CBC 17 29-Apr-14 21-May-14
CBCL2AB-0910 FRAMING/INWALL ROUGH - LVL-2 AREA B CBC 14 23-Jun-14 11-Jul-14
CBCL2AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA B CBC 12 22-Jul-14 06-Aug-14
CBCL2AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA B CBC 22 05-Aug-14 04-Sep-14
CBCL2AB-0977 INSTALL OWNER FIXED FF&E - LVL-2 AREA-B CBC 15 14-Aug-14 04-Sep-14
CBCL2AB-8880 CLEAN-UP/PRE PUNCH - LVL-2 AREA B CBC 8 05-Sep-14 16-Sep-14
CBC - LEVEL 1CBC - LEVEL 1CBC - LEVEL 1CBC - LEVEL 1CBC - LEVEL 1CBC - LEVEL 1 - ARCBC - LEVEL 1 - AREA ACBC - LEVEL 1 - AREA ACBC - LEVEL 1 - AREA ACBC - LEVEL 1 - AREA A
CBCL1AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-1 AREA A CBC 18 13-May-14 06-Jun-14
CBCL1AA-0910 FRAMING/INWALL ROUGH - LVL-1 AREA A CBC 14 16-Jun-14 03-Jul-14
CBCL1AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA A CBC 13 30-Jun-14 17-Jul-14
CBCL1AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA A CBC 23 15-Jul-14 14-Aug-14
CBCL1AA-0977 INSTALL OWNER FIXED FF&E - LVL-31AREA-A CBC 15 25-Jul-14 14-Aug-14
CBCL1AA-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBC 8 15-Aug-14 26-Aug-14
CBC - LEVEL 1 - ARCBC - LEVEL 1 - AREA BCBC - LEVEL 1 - AREA BCBC - LEVEL 1 - AREA BCBC - LEVEL 1 - AREA B
CBCL1AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AREA B CBC 17 28-May-14 19-Jun-14
CBCL1AB-0910 FRAMING/INWALL ROUGH - LVL-1 AREA B CBC 14 09-Jun-14 26-Jun-14
CBCL1AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA B CBC 12 08-Jul-14 23-Jul-14
CBCL1AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA B CBC 22 22-Jul-14 20-Aug-14
CBCL1AB-0977 INSTALL OWNER FIXED FF&E - LVL-31AREA-A CBC 15 31-Jul-14 20-Aug-14
CBCL1AB-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA B CBC 8 21-Aug-14 02-Sep-14
CBC - SERVICE CBC - SERVICE LEVELCBC - SERVICE LEVELCBC - SERVICE LEVELCBC - SERVICE LEVELCBC - SERVICE LEVCBC - SERVICE LEVEL - ELEVATOR LOBBYCBC - SERVICE LEVEL - ELEVATOR LOBBYCBC - SERVICE LEVEL - ELEVATOR LOBBYCBC - SERVICE LEVEL - ELEVATOR LOBBY
CBCSLEL-0910 FRAMING/INWALL ROUGH - SERV LVL CORR CBC 5 21-Aug-14 27-Aug-14
CBCSLEL-0990 HANG/TAPE/FINISH/PAINT - SERV LVL CORR CBC 10 28-Aug-14 11-Sep-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 61 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 064
Activity ID Activity Name OrigDur
Start Finish
CBCSLEL-8880 CLEAN-UP/PRE PUNCH - SERV LVL CORR CBC 5 12-Sep-14 18-Sep-14
CBC - ALL LEVECBC - ALL LEVELSCBC - ALL LEVELSCBC - ALL LEVELSCBC - ALL LEVELSCBCALAL-0555 ERECT STAIRS ST1 - ALL LVLS CBC 15 03-Sep-13 23-Sep-13
CBCALAL-0556 ERECT STAIRS ST2 - ALL LVLS CBC 15 17-Sep-13 07-Oct-13
CBCALAL-1400 INSTALL ELEVATOR SE5 - ALL LVLS CBC 60 23-Jun-14 16-Sep-14
CBCALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS CBC 15 21-Aug-14 11-Sep-14
CBCALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS CBC 20 12-Sep-14 09-Oct-14
CLINIC BUILDINCLINIC BUILDINGS COMMISSIONING - CBCCLINIC BUILDINGS COMMISSIONING - CBCCLINIC BUILDINGS COMMISSIONING - CBCCLINIC BUILDINGS COMMISSIONING - CBCCBCCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - CBC 35 10-Oct-14 02-Dec-14
CBCCOCO-1620 TEST & BALANCE - CBC 30 03-Dec-14 15-Jan-15
CBCCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - CBC 20 03-Dec-14 31-Dec-14
CBCCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - CBC 25 02-Jan-15 06-Feb-15
CBCCOCO-1599 BUILDING FLUSH - CBC 20 07-Feb-15 26-Feb-15
RESEARCH BURESEARCH BUILDING (RES)RESEARCH BUILDING (RES)RESEARCH BUILDING (RES)RESEARCH BUILDING (RES)RESEARCH BUILRESEARCH BUILDING (RES) - STRUCTURERESEARCH BUILDING (RES) - STRUCTURERESEARCH BUILDING (RES) - STRUCTURERESEARCH BUILDING (RES) - STRUCTURERES - SERVICE RES - SERVICE LEVELRES - SERVICE LEVELRES - SERVICE LEVELRES - SERVICE LEVELRESSLSL-3130 DRIVE SOLDIER PILES - SERV LVL RES 10 31-Jan-14 17-Feb-14
RESSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL RES 18 18-Feb-14 10-Mar-14
RESSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL RES 26 11-Mar-14 24-Apr-14
RESSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL RES 30 07-Apr-14 29-May-14
RESSLSL-3200 UNDERSLAB UTILITIES (DUCTBANKS/VAULTS/PLUMBING) - SERV LVL RES 15 02-May-14 29-May-14
RESSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL RES 10 30-May-14 16-Jun-14
RESSLSL-0390 PERM DRAINS/WATERPROOFING/BACKFILL FOUNDATION WALLS - SERV LVL RES 25 14-Jul-14 25-Aug-14
RES - INTERSTIRES - INTERSTITIAL LEVELRES - INTERSTITIAL LEVELRES - INTERSTITIAL LEVELRES - INTERSTITIAL LEVELRESSLIL-0320 ERECT INTERSTITIAL STEEL/TOPPING (INCL CURE)- INTERSTITIAL LVL RES 15 30-Oct-14 24-Nov-14
RES - LEVEL 1RES - LEVEL 1RES - LEVEL 1RES - LEVEL 1RES - LEVEL 1RESL1L1-0320 FORM/REINFORCE/PLACE/FINISH - LVL-1 RES 15 17-Jun-14 11-Jul-14
RES - LEVEL 2RES - LEVEL 2RES - LEVEL 2RES - LEVEL 2RES - LEVEL 2RESL2L2-0320 FORM/REINFORCE/PLACE/FINISH - LVL-2 RES 15 14-Jul-14 07-Aug-14
RESL2L2-0520 ERECT STRUCTURAL STEEL FOR LOW ROOF - LVL-2 RES 6 17-Nov-14 25-Nov-14
RES - LEVEL 3RES - LEVEL 3RES - LEVEL 3RES - LEVEL 3RES - LEVEL 3RESL3L3-0320 FORM/REINFORCE/PLACE/FINISH - LVL-3 RES 15 08-Aug-14 03-Sep-14
RES - PENTHOURES - PENTHOUSERES - PENTHOUSERES - PENTHOUSERES - PENTHOUSERESPHPH-0320 FORM/REINFORCE/PLACE/FINISH (INCL CORE COMP)- PENTHOUSE RES 30 04-Sep-14 22-Oct-14
RESPHPH-1600 SET ELECTRICAL EQUIPMENT - ROOF RES 7 23-Oct-14 31-Oct-14
RESPHPH-1500 SET MECH EQUIPMENT - ROOF RES 2 10-Nov-14 12-Nov-14
RESPHPH-0510 ERECT PENTHOUSE STEEL/METAL DECK - ROOF RES 20 13-Nov-14 15-Dec-14
RES - ROOFRES - ROOFRES - ROOFRES - ROOFRES - ROOFRESRLRL-0520 INSTALL ROOF CANOPY STRUCTURE - ROOF RES 15 04-Nov-14 28-Nov-14
RESRLRL-0750 PARAPET/BLOCKING/ROOFING - ROOF RES 20 16-Dec-14 16-Jan-15
RESRLRL-1600 SET/CONNECT PHOTOVOLTAIC PANELS - ROOF RES 40 20-Jan-15 23-Mar-15
RES - LOADINGRES - LOADING DOCKRES - LOADING DOCKRES - LOADING DOCKRES - LOADING DOCKRESLDLD-0320 FORM/PLACE RAMP & STAIRS - LOADING DOCK RES 12 23-Oct-14 12-Nov-14
RESEARCH BUILRESEARCH BUILDING (RES) - EXTERIOR SKINRESEARCH BUILDING (RES) - EXTERIOR SKINRESEARCH BUILDING (RES) - EXTERIOR SKINRESEARCH BUILDING (RES) - EXTERIOR SKINRES - NORTH ELRES - NORTH ELEVATIONRES - NORTH ELEVATIONRES - NORTH ELEVATIONRES - NORTH ELEVATIONRESESNE-0520 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - NORTH ELE... 15 04-Sep-14 29-Sep-14
RESESNE-0870 INSTALL CURTAIN WALL- NORTH ELEV RES 15 07-Oct-14 30-Oct-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 62 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 065
Activity ID Activity Name OrigDur
Start Finish
RESESNE-0780 INSTALL METAL PANEL - NORTH ELEV RES 10 31-Oct-14 17-Nov-14
RES - SOUTH ELRES - SOUTH ELEVATIONRES - SOUTH ELEVATIONRES - SOUTH ELEVATIONRES - SOUTH ELEVATIONRESESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV RES 20 04-Sep-14 06-Oct-14
RESESSE-1610 INSTALL STRUCTURAL STEEL FRAME FOR SOLAR TUBES - SOUTH ELEV RES 15 07-Oct-14 30-Oct-14
RESESSE-1600 INSTALL SOLAR TUBES - SOUTH ELEV RES 50 31-Oct-14 22-Jan-15
RES - EAST ELEVRES - EAST ELEVATIONRES - EAST ELEVATIONRES - EAST ELEVATIONRES - EAST ELEVATIONRESESEE-0520 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - EAST ELEV ... 15 16-Sep-14 08-Oct-14
RESESEE-0870 INSTALL CURTAIN WALL - EAST ELEV RES 10 31-Oct-14 17-Nov-14
RESESEE-0780 INSTALL METAL PANEL - EAST ELEV RES 5 18-Nov-14 25-Nov-14
RESESEE-1600 INSTALL SOLAR TUBES - EAST ELEV RES 30 27-Nov-14 13-Jan-15
RES - WEST ELERES - WEST ELEVATIONRES - WEST ELEVATIONRES - WEST ELEVATIONRES - WEST ELEVATIONRESESWE-0520 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - WEST ELEV ... 15 09-Oct-14 03-Nov-14
RESESWE-0530 EXTERIOR SKIN TIE INTO CONCOURSE - WEST ELEV RES 15 04-Nov-14 28-Nov-14
RESESWE-0870 INSTALL CURTAIN WALL - WEST ELEV RES 15 27-Nov-14 19-Dec-14
RESESWE-0780 INSTALL METAL PANEL - WEST ELEV RES 5 22-Dec-14 29-Dec-14
RES - PENTHOURES - PENTHOUSE ELEVATIONRES - PENTHOUSE ELEVATIONRES - PENTHOUSE ELEVATIONRES - PENTHOUSE ELEVATIONRESESPH-0520 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTHOUSE ELEV RES 15 16-Dec-14 08-Jan-15
RESESPH-0710 INSTALL LOUVERS - PENTHOUSE ELEV RES 5 09-Jan-15 16-Jan-15
RESESPH-0777 INSTALL METAL PANELS - PENTHOUSE ELEV RES 7 20-Jan-15 28-Jan-15
RESEARCH BUILRESEARCH BUILDING (RES) - INTERIOR BUILDOUTRESEARCH BUILDING (RES) - INTERIOR BUILDOUTRESEARCH BUILDING (RES) - INTERIOR BUILDOUTRESEARCH BUILDING (RES) - INTERIOR BUILDOUTRES - SERVICE RES - SERVICE LEVELRES - SERVICE LEVELRES - SERVICE LEVELRES - SERVICE LEVELRESSLSL-0420 LAY CMU WALLS - SERV LVL RES 10 25-Nov-14 08-Dec-14
RESSLSL-1516 ROUGH-IN OVERHEAD PIPING (PROCESS/MED GAS/FIRE PROT) - SERV LVL RES 20 23-Dec-14 22-Jan-15
RESSLSL-0910 FRAMING/INWALL ROUGH - SERV LVL RES 30 23-Dec-14 05-Feb-15
RESSLSL-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL RES 30 28-Jan-15 12-Mar-15
RESSLSL-0990 INTERIOR FINISHES (GENERAL) - SERV LVL RES 45 19-Feb-15 23-Apr-15
RESSLSL-0992 INTERIOR FINISHES (CART WASH) - SERV LVL RES 30 12-Mar-15 23-Apr-15
RESSLSL-0994 INTERIOR FINISHES (SURGURY) - SERV LVL RES 30 12-Mar-15 23-Apr-15
RESSLSL-8880 CLEAN-UP/PRE PUNCH - SERV LVL RES 15 23-Apr-15 14-May-15
RES - INTERSTIRES - INTERSTITIAL LEVELRES - INTERSTITIAL LEVELRES - INTERSTITIAL LEVELRES - INTERSTITIAL LEVELRESSLIL-1516 ROUGH-IN MEP/FIRE PROTECTION - INTER LVL RES 110 25-Nov-14 01-May-15
RESSLIL-1517 TRIM-OUT MEP/FIRE PROTECTION - INTER LVL RES 25 04-May-15 08-Jun-15
RES - LEVEL 1RES - LEVEL 1RES - LEVEL 1RES - LEVEL 1RES - LEVEL 1RES - LEVEL 1 - SURES - LEVEL 1 - SUPPORT/OFFICERES - LEVEL 1 - SUPPORT/OFFICERES - LEVEL 1 - SUPPORT/OFFICERES - LEVEL 1 - SUPPORT/OFFICE
RESL1SO-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 SUPP RES 25 16-Dec-14 22-Jan-15
RESL1SO-0910 FRAMING/INWALL ROUGH - LVL-1 SUPP RES 20 08-Jan-15 05-Feb-15
RESL1SO-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SUPP RES 15 28-Jan-15 19-Feb-15
RESL1SO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SUPP RES 45 06-Feb-15 10-Apr-15
RESL1SO-8880 CLEAN-UP/PRE PUNCH - LVL-1 SUPP RES 10 13-Apr-15 24-Apr-15
RES - LEVEL 1 - BIRES - LEVEL 1 - BIOMEDICAL LABRES - LEVEL 1 - BIOMEDICAL LABRES - LEVEL 1 - BIOMEDICAL LABRES - LEVEL 1 - BIOMEDICAL LAB
RESL1LA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 LAB RES 25 09-Dec-14 14-Jan-15
RESL1LA-0910 FRAMING/INWALL ROUGH - LVL-1 LAB RES 20 16-Dec-14 14-Jan-15
RESL1LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 LAB RES 15 20-Jan-15 10-Feb-15
RESL1LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 LAB RES 45 27-Jan-15 31-Mar-15
RESL1LA-0977 INSTALL OWNER FIXED FF&E - LVL-1 LAB RES 20 04-Mar-15 31-Mar-15
RESL1LA-8880 CLEAN-UP/PRE PUNCH - LVL-1 LAB RES 10 01-Apr-15 14-Apr-15
RES - LEVEL 2RES - LEVEL 2RES - LEVEL 2RES - LEVEL 2RES - LEVEL 2RES - LEVEL 2 - BIRES - LEVEL 2 - BIOMEDICAL LABRES - LEVEL 2 - BIOMEDICAL LABRES - LEVEL 2 - BIOMEDICAL LABRES - LEVEL 2 - BIOMEDICAL LAB
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 63 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 066
Activity ID Activity Name OrigDur
Start Finish
RESL2LA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 LAB RES 25 15-Jan-15 20-Feb-15
RESL2LA-0910 FRAMING/INWALL ROUGH - LVL-2 LAB RES 20 16-Feb-15 13-Mar-15
RESL2LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 LAB RES 15 02-Mar-15 20-Mar-15
RESL2LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 LAB RES 45 01-Apr-15 03-Jun-15
RESL2LA-0977 INSTALL OWNER FIXED FF&E - LVL-2 LAB RES 20 06-May-15 03-Jun-15
RESL2LA-8880 CLEAN-UP/PRE PUNCH - LVL-2 LAB RES 10 04-Jun-15 17-Jun-15
RES - LEVEL 2 - SURES - LEVEL 2 - SUPPORT/OFFICERES - LEVEL 2 - SUPPORT/OFFICERES - LEVEL 2 - SUPPORT/OFFICERES - LEVEL 2 - SUPPORT/OFFICE
RESL2SO-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 SUPP RES 25 23-Jan-15 27-Feb-15
RESL2SO-0910 FRAMING/INWALL ROUGH - LVL-2 SUPP RES 20 16-Feb-15 13-Mar-15
RESL2SO-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SUPP RES 15 02-Mar-15 20-Mar-15
RESL2SO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SUPP RES 45 16-Mar-15 15-May-15
RESL2SO-8880 CLEAN-UP/PRE PUNCH - LVL-2 SUPP RES 10 18-May-15 01-Jun-15
RES - LEVEL 3RES - LEVEL 3RES - LEVEL 3RES - LEVEL 3RES - LEVEL 3RES - LEVEL 3 - BIRES - LEVEL 3 - BIOMEDICAL LABRES - LEVEL 3 - BIOMEDICAL LABRES - LEVEL 3 - BIOMEDICAL LABRES - LEVEL 3 - BIOMEDICAL LAB
RESL3LA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 LAB RES 35 23-Feb-15 10-Apr-15
RESL3LA-0910 FRAMING/INWALL ROUGH - LVL-3 LAB RES 20 30-Mar-15 24-Apr-15
RESL3LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 LAB RES 15 13-Apr-15 01-May-15
RESL3LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 LAB RES 45 04-Jun-15 06-Aug-15
RESL3LA-0977 INSTALL OWNER FIXED FF&E - LVL-3 LAB RES 20 10-Jul-15 06-Aug-15
RESL3LA-8880 CLEAN-UP/PRE PUNCH - LVL-3 LAB RES 10 07-Aug-15 20-Aug-15
RES - LEVEL 3 - SURES - LEVEL 3 - SUPPORT/OFFICERES - LEVEL 3 - SUPPORT/OFFICERES - LEVEL 3 - SUPPORT/OFFICERES - LEVEL 3 - SUPPORT/OFFICE
RESL3SO-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 SUPP RES 25 02-Mar-15 03-Apr-15
RESL3SO-0910 FRAMING/INWALL ROUGH - LVL-3 SUPP RES 20 23-Mar-15 17-Apr-15
RESL3SO-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 SUPP RES 15 13-Apr-15 01-May-15
RESL3SO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SUPP RES 45 20-Apr-15 22-Jun-15
RESL3SO-8880 CLEAN-UP/PRE PUNCH - LVL-3 SUPP RES 10 23-Jun-15 07-Jul-15
RES - PENTHOURES - PENTHOUSERES - PENTHOUSERES - PENTHOUSERES - PENTHOUSERES - PENTHOUSERES - PENTHOUSE - ELECTRICALRES - PENTHOUSE - ELECTRICALRES - PENTHOUSE - ELECTRICALRES - PENTHOUSE - ELECTRICAL
RESPHEL-0910 FRAMING/INWALL ROUGH - PENTHOUSE ELEC RES 10 27-Jan-15 10-Feb-15
RESPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENTHOUSE ELEC RES 10 11-Feb-15 24-Feb-15
RESPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENTHOUSE ELEC RES 65 25-Feb-15 27-May-15
RES - PENTHOUSERES - PENTHOUSE - MECHANICALRES - PENTHOUSE - MECHANICALRES - PENTHOUSE - MECHANICALRES - PENTHOUSE - MECHANICAL
RESPHME-0420 LAY CMU WALLS - PENTHOUSE MECH RES 15 16-Dec-14 07-Jan-15
RESPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECH RES 45 09-Jan-15 16-Mar-15
RESPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENTHOUSE MECH RES 60 17-Mar-15 09-Jun-15
RESPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH RES 20 28-May-15 24-Jun-15
RESPHME-1590 START-UP MECH EQUIP - PENT MECH RES 15 25-Jun-15 16-Jul-15
RES - ALL LEVERES - ALL LEVELSRES - ALL LEVELSRES - ALL LEVELSRES - ALL LEVELSRESALAL-0555 ERECT STAIRS ST1 - ALL LVLS RES 15 16-Dec-14 07-Jan-15
RESALAL-0556 ERECT STAIRS ST2 - ALL LVLS RES 15 31-Dec-14 22-Jan-15
RESALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS RES 15 13-Apr-15 01-May-15
RESALAL-1400 INSTALL ELEVATOR SE13 - ALL LVLS RES 60 29-Apr-15 23-Jul-15
RESALAL-1401 INSTALL ELEVATOR SE12- ALL LVLS RES 60 29-Apr-15 23-Jul-15
RESALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS RES 20 04-May-15 01-Jun-15
RESEARCH BUILRESEARCH BUILDING (RES) - COMMISSIONINGRESEARCH BUILDING (RES) - COMMISSIONINGRESEARCH BUILDING (RES) - COMMISSIONINGRESEARCH BUILDING (RES) - COMMISSIONINGRESCOCL-1592 TEST & BALANCE - RES 20 24-Jul-15 20-Aug-15
RESCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - RES 15 24-Jul-15 13-Aug-15
RESCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - RES 20 14-Aug-15 11-Sep-15
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 64 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 067
Activity ID Activity Name OrigDur
Start Finish
RESCOCL-9999 CREATE/COMPLETE FINAL PUNCHLIST - RES 20 21-Aug-15 18-Sep-15
RESCOCL-1599 BUILDING FLUSH - RES 15 19-Sep-15 03-Oct-15
CBS - CLINIC BCBS - CLINIC BUILDING SOUTHCBS - CLINIC BUILDING SOUTHCBS - CLINIC BUILDING SOUTHCBS - CLINIC BUILDING SOUTHCBS - SITEWORKCBS - SITEWORK/STRUCTURECBS - SITEWORK/STRUCTURECBS - SITEWORK/STRUCTURECBS - SITEWORK/STRUCTURECBS - SITEWORCBS - SITEWORKCBS - SITEWORKCBS - SITEWORKCBS - SITEWORKCBSSWSW-4140 RELOCATE FIRE DEPARTMENT CONNECTION - SITEWORK CBS 7 26-Jul-11 03-Aug-11
CBSSWSW-2310 GROUND RING - SITEWORK CBS 10 07-Nov-11 21-Nov-11
CBS - STRUCTUCBS - STRUCTURECBS - STRUCTURECBS - STRUCTURECBS - STRUCTURECBSSTST-2400 INTERIOR STEEL FRAMING LEVEL 1,2,3,4 - STRUCTURE CBS 15 26-Jul-11 11-Aug-11
CBSSTST-4040 DRILLED PIERS - CANOPY - STRUCTURE CBS 5 26-Jul-11 30-Jul-11
CBSSTST-3760 EXCAVATION AND SHORING - STRUCTURE CBS 15 01-Aug-11 17-Aug-11
CBSSTST-2330 CANOPY FOUNDATION - STRUCTURE CBS 15 01-Aug-11 17-Aug-11
CBSSTST-2380 CANOPY FRAMING - STRUCTURE CBS 5 18-Aug-11 23-Aug-11
CBSSTST-4050 DRILLED PIERS - BUILDING ADDITION - STRUCTURE CBS 5 18-Aug-11 23-Aug-11
CBSSTST-2340 STAIR CORE AND ELEVATOR FOUNDATION - STRUCTURE CBS 16 24-Aug-11 12-Sep-11
CBSSTST-2350 STAIR CORE WALLS - STRUCTURE CBS 40 13-Sep-11 29-Oct-11
CBSSTST-2360 ELEVATOR CORE WALLS - STRUCTURE CBS 40 13-Sep-11 29-Oct-11
CBSSTST-4160 ERECT STRUCTURAL STEEL AT ADDITION - CBS - STRUCTURE CBS 10 31-Oct-11 10-Nov-11
CBSSTST-4060 SLAB ON GRADE - STRUCTURE CBS 5 31-Oct-11 04-Nov-11
CBSSTST-4170 PLACE/FINISH COMD AT ADDITION - CBS - STRUCTURE CBS 8 19-Nov-11 29-Nov-11
CBSSTST-4180 APPLY FIREPROOFING - CBS - STRUCTURE CBS 6 30-Nov-11 06-Dec-11
CBS - ROOFCBS - ROOFCBS - ROOFCBS - ROOFCBS - ROOF
CBSRLRL-3550 CANOPY ROOFING - ROOF CBS 5 24-Aug-11 30-Aug-11
CBSRLRL-3540 NEW ADDITION ROOFING - ROOF CBS 10 06-Jan-12 20-Jan-12
CBSRLRL-3560 LIGHTNING PROTECTION - ROOF CBS 5 23-Jan-12 27-Jan-12
CBSRLRL-3570 NEW EXHAUST FANS - ROOF CBS 5 23-Jan-12 27-Jan-12
CLINIC BUILDINCLINIC BUILDING SOUTH (CBS) - EXTERIOR SKINSCLINIC BUILDING SOUTH (CBS) - EXTERIOR SKINSCLINIC BUILDING SOUTH (CBS) - EXTERIOR SKINSCLINIC BUILDING SOUTH (CBS) - EXTERIOR SKINSCBS - EXTERIORCBS - EXTERIOR SKINCBS - EXTERIOR SKINCBS - EXTERIOR SKINCBS - EXTERIOR SKINCBSESES-3580 INSTALL TEMPORARY EXTERIOR SKIN @ NEW ADITION - SKINS CBS 20 07-Dec-11 05-Jan-12
CBSESES-4140 INSTALL EXTERIOR SKIN @ NEW ADITION - SKINS CBS 20 07-Dec-11 05-Jan-12
CBSESES-4130 REMOVE TEMP BUILDING ENCLOSURE - SKINS CBS 10 06-Jan-12 20-Jan-12
CBSESES-3590 CANOPY GLAZING - SKINS CBS 10 05-Jun-12 18-Jun-12
CLINICH BUILDICLINICH BUILDING SOUTH (CBS) - DEMOCLINICH BUILDING SOUTH (CBS) - DEMOCLINICH BUILDING SOUTH (CBS) - DEMOCLINICH BUILDING SOUTH (CBS) - DEMOCBS - INTERIORCBS - INTERIOR DEMOCBS - INTERIOR DEMOCBS - INTERIOR DEMOCBS - INTERIOR DEMOCBSDEIN-4100 LEVEL 2 SALVAGE - INT DEMO CBS 2 03-Apr-15 06-Apr-15
CBSDEIN-2470 LEVEL 2 DEMOLITION - INT DEMO CBS 3 10-Apr-15 14-Apr-15
CBS - SKIN DEMCBS - SKIN DEMOCBS - SKIN DEMOCBS - SKIN DEMOCBS - SKIN DEMOCBSDEES-2440 SKIN PENETRATIONS FOR TRELLIS ATTACHMENT - EXT DEMO CBS 10 26-Jul-11 08-Aug-11
CLINIC BUILDINCLINIC BUILDING SOUTH (CBS) - ADDITIONCLINIC BUILDING SOUTH (CBS) - ADDITIONCLINIC BUILDING SOUTH (CBS) - ADDITIONCLINIC BUILDING SOUTH (CBS) - ADDITIONCBS - LEVEL 4 ACBS - LEVEL 4 ADDITIONCBS - LEVEL 4 ADDITIONCBS - LEVEL 4 ADDITIONCBS - LEVEL 4 ADDITIONCBSADL4-2630 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL 4 ADD CBS 5 07-Dec-11 12-Dec-11
CBSADL4-2640 FIRE SPRINKLER ROUGH-IN - LVL-4 ADD CBS 4 13-Dec-11 16-Dec-11
CBSADL4-2650 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-4 ADD CBS 4 17-Dec-11 21-Dec-11
CBSADL4-2660 FRAMING - LVL-4 ADD CBS 4 22-Dec-11 27-Dec-11
CBSADL4-2670 WALL ROUGH-IN - LVL-4 ADD CBS 4 28-Dec-11 31-Dec-11
CBSADL4-2680 DRYWALL / FINISH - LVL-4 ADD CBS 5 06-Jan-12 11-Jan-12
CBSADL4-2690 INTERIOR PAINT - LVL-4 ADD CBS 3 12-Jan-12 14-Jan-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 65 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 068
Activity ID Activity Name OrigDur
Start Finish
CBSADL4-2700 CEILING - LVL-4 ADD CBS 5 17-Jan-12 21-Jan-12
CBSADL4-2720 FLOORING - LVL-4 ADD CBS 5 23-Jan-12 27-Jan-12
CBSADL4-2730 MEP TRIMOUT - LVL-4 ADD CBS 5 23-Jan-12 27-Jan-12
CBSADL4-2740 HANDRAIL - LVL-4 ADD CBS 2 23-Jan-12 24-Jan-12
CBSADL4-3950 TEST AND BALANCE - LVL-4 ADD CBS 1 28-Jan-12 28-Jan-12
CBSADL4-2750 PUNCHLIST - LVL-4 ADD CBS 5 30-Jan-12 03-Feb-12
CBS - LEVEL 3 ACBS - LEVEL 3 ADDITIONCBS - LEVEL 3 ADDITIONCBS - LEVEL 3 ADDITIONCBS - LEVEL 3 ADDITIONCBSADL3-2900 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-3 ADD CBS 4 07-Dec-11 10-Dec-11
CBSADL3-2910 FIRE SPRINKLER ROUGH-IN - LVL-3 ADD CBS 2 17-Dec-11 19-Dec-11
CBSADL3-2920 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-3 ADD CBS 4 22-Dec-11 27-Dec-11
CBSADL3-2930 FRAMING - LVL-3 ADD CBS 4 28-Dec-11 31-Dec-11
CBSADL3-2940 WALL ROUGH-IN - LVL-3 ADD CBS 2 03-Jan-12 04-Jan-12
CBSADL3-2950 DRYWALL / FINISH - LVL-3 ADD CBS 5 10-Jan-12 14-Jan-12
CBSADL3-2960 INTERIOR PAINT - LVL-3 ADD CBS 2 17-Jan-12 18-Jan-12
CBSADL3-2970 CEILING - LVL-3 ADD CBS 4 19-Jan-12 23-Jan-12
CBSADL3-2980 FLOORING - LVL-3 ADD CBS 2 28-Jan-12 30-Jan-12
CBSADL3-2990 MEP TRIMOUT - LVL-3 ADD CBS 2 31-Jan-12 01-Feb-12
CBSADL3-3000 HANDRAIL - LVL-3 ADD CBS 2 31-Jan-12 01-Feb-12
CBSADL3-3970 TEST AND BALANCE - LVL-3 ADD CBS 1 02-Feb-12 02-Feb-12
CBSADL3-3010 PUNCHLIST - LVL-3 ADD CBS 2 03-Feb-12 04-Feb-12
CBS - LEVEL 2 ACBS - LEVEL 2 ADDITIONCBS - LEVEL 2 ADDITIONCBS - LEVEL 2 ADDITIONCBS - LEVEL 2 ADDITIONCBSADL2-3160 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-2 ADD CBS 4 07-Dec-11 10-Dec-11
CBSADL2-3170 FIRE SPRINKLER ROUGH-IN - LVL-2 ADD CBS 2 17-Dec-11 19-Dec-11
CBSADL2-3180 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-2 ADD CBS 4 22-Dec-11 27-Dec-11
CBSADL2-3190 FRAMING - LVL-2 ADD CBS 4 28-Dec-11 31-Dec-11
CBSADL2-3200 WALL ROUGH-IN - LVL-2 ADD CBS 2 05-Jan-12 06-Jan-12
CBSADL2-3210 DRYWALL / FINISH - LVL-2 ADD CBS 5 13-Jan-12 19-Jan-12
CBSADL2-3220 INTERIOR PAINT - LVL-2 ADD CBS 2 20-Jan-12 21-Jan-12
CBSADL2-3230 CEILING - LVL-2 ADD CBS 3 23-Jan-12 25-Jan-12
CBSADL2-3240 FLOORING - LVL-2 ADD CBS 2 28-Jan-12 30-Jan-12
CBSADL2-3250 MEP TRIMOUT - LVL-2 ADD CBS 2 31-Jan-12 01-Feb-12
CBSADL2-3990 TEST AND BALANCE - LVL-2 ADD CBS 1 02-Feb-12 02-Feb-12
CBSADL2-3260 HANDRAIL - LVL-2 ADD CBS 2 02-Feb-12 03-Feb-12
CBSADL2-3270 PUNCHLIST - LVL-2 ADD CBS 2 03-Feb-12 04-Feb-12
CBS - LEVEL 1 ACBS - LEVEL 1 ADDITIONCBS - LEVEL 1 ADDITIONCBS - LEVEL 1 ADDITIONCBS - LEVEL 1 ADDITIONCBSADL1-3420 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-1 ADD CBS 5 07-Dec-11 12-Dec-11
CBSADL1-3430 FIRE SPRINKLER ROUGH-IN - LVL-1 ADD CBS 2 17-Dec-11 19-Dec-11
CBSADL1-3440 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-1 ADD CBS 3 22-Dec-11 24-Dec-11
CBSADL1-3450 FRAMING - LVL-1 ADD CBS 3 28-Dec-11 30-Dec-11
CBSADL1-3460 WALL ROUGH-IN - LVL-1 ADD CBS 2 05-Jan-12 06-Jan-12
CBSADL1-3470 DRYWALL / FINISH - LVL-1 ADD CBS 5 07-Jan-12 12-Jan-12
CBSADL1-3480 INTERIOR PAINT - LVL-1 ADD CBS 2 20-Jan-12 21-Jan-12
CBSADL1-3490 CEILING - LVL-1 ADD CBS 2 23-Jan-12 24-Jan-12
CBSADL1-3500 FLOORING - LVL-1 ADD CBS 2 28-Jan-12 30-Jan-12
CBSADL1-3510 MEP TRIMOUT - LVL-1 ADD CBS 2 31-Jan-12 01-Feb-12
CBSADL1-3530 PUNCHLIST - LVL-1 ADD CBS 3 02-Feb-12 04-Feb-12
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 66 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 069
Activity ID Activity Name OrigDur
Start Finish
CBSADL1-4010 TEST AND BALANCE - LVL-1 ADD CBS 1 02-Feb-12 02-Feb-12
CBSADL1-3520 HANDRAIL - LVL-1 ADD CBS 1 02-Feb-12 02-Feb-12
CBS - ALL LEVECBS - ALL LEVELS @ ADDITIONCBS - ALL LEVELS @ ADDITIONCBS - ALL LEVELS @ ADDITIONCBS - ALL LEVELS @ ADDITIONCBSADAL-2410 STEEL STAIRS - ALL LVLS ADD CBS 10 14-Nov-11 29-Nov-11
CBSADAL-3600 NEW ELEVATOR - ALL LVLS ADD CBS 15 04-Jan-13 25-Jan-13
CLINIC BUILDINCLINIC BUILDIN GSOUTH (CBS) - INTERIOR ACTIVITIESCLINIC BUILDIN GSOUTH (CBS) - INTERIOR ACTIVITIESCLINIC BUILDIN GSOUTH (CBS) - INTERIOR ACTIVITIESCLINIC BUILDIN GSOUTH (CBS) - INTERIOR ACTIVITIESCBS - LEVEL 4CBS - LEVEL 4CBS - LEVEL 4CBS - LEVEL 4CBS - LEVEL 4CBSINL4-2490 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-4 CBS 15 04-Aug-11 20-Aug-11
CBSINL4-2500 FIRE SPRINKLER ROUGH-IN - LVL-4 CBS 10 22-Aug-11 01-Sep-11
CBSINL4-2510 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-4 CBS 10 02-Sep-11 14-Sep-11
CBSINL4-2520 FRAMING - LVL-4 CBS 10 15-Sep-11 26-Sep-11
CBSINL4-2530 WALL ROUGH-IN - LVL-4 CBS 20 27-Sep-11 20-Oct-11
CBSINL4-2540 DRYWALL / FINISH - LVL-4 CBS 15 21-Oct-11 07-Nov-11
CBSINL4-2550 INTERIOR PAINT - LVL-4 CBS 10 08-Nov-11 19-Nov-11
CBSINL4-2560 CEILING - LVL-4 CBS 12 21-Nov-11 05-Dec-11
CBSINL4-2570 MILLWORK - LVL-4 CBS 10 06-Dec-11 16-Dec-11
CBSINL4-2580 FLOORING - LVL-4 CBS 10 17-Dec-11 29-Dec-11
CBSINL4-2590 MEP TRIMOUT - LVL-4 CBS 12 30-Dec-11 13-Jan-12
CBSINL4-2600 HANDRAIL - LVL-4 CBS 10 14-Jan-12 26-Jan-12
CBSINL4-3940 TEST AND BALANCE - LVL-4 CBS 5 14-Jan-12 20-Jan-12
CBSSTST-2610 PUNCHLIST - LVL-4 CBS 10 27-Jan-12 07-Feb-12
CBS - LEVEL 3CBS - LEVEL 3CBS - LEVEL 3CBS - LEVEL 3CBS - LEVEL 3CBSL3L3-2760 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-3 CBS 15 04-Aug-11 20-Aug-11
CBSL3L3-2770 FIRE SPRINKLER ROUGH-IN - LVL-3 CBS 5 22-Aug-11 26-Aug-11
CBSL3L3-4030 NEW EXHAUST FANS - LVL-3 CBS 10 22-Aug-11 01-Sep-11
CBSL3L3-2780 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-3 CBS 5 15-Sep-11 20-Sep-11
CBSL3L3-2790 FRAMING - LVL-3 CBS 5 27-Sep-11 01-Oct-11
CBSL3L3-2800 WALL ROUGH-IN - LVL-3 CBS 5 21-Oct-11 26-Oct-11
CBSL3L3-2810 DRYWALL / FINISH - LVL-3 CBS 5 08-Nov-11 14-Nov-11
CBSL3L3-2820 INTERIOR PAINT - LVL-3 CBS 10 21-Nov-11 02-Dec-11
CBSL3L3-2830 CEILING - LVL-3 CBS 5 06-Dec-11 10-Dec-11
CBSL3L3-2840 MILLWORK - LVL-3 CBS 5 17-Dec-11 22-Dec-11
CBSL3L3-2850 FLOORING - LVL-3 CBS 10 30-Dec-11 11-Jan-12
CBSL3L3-2860 MEP TRIMOUT - LVL-3 CBS 10 14-Jan-12 26-Jan-12
CBSL3L3-3960 TEST AND BALANCE - LVL-3 CBS 3 27-Jan-12 30-Jan-12
CBSL3L3-2880 PUNCHLIST - LVL-3 CBS 5 02-Feb-12 07-Feb-12
CBS - LEVEL 2CBS - LEVEL 2CBS - LEVEL 2CBS - LEVEL 2CBS - LEVEL 2CBSL2L2-3020 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-2 CBS 10 15-Apr-15 28-Apr-15
CBSL2L2-3030 FIRE SPRINKLER ROUGH-IN - LVL-2 CBS 5 29-Apr-15 05-May-15
CBSL2L2-3040 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-2 CBS 5 06-May-15 12-May-15
CBSL2L2-3050 FRAMING - LVL-2 CBS 12 13-May-15 29-May-15
CBSL2L2-3060 WALL ROUGH-IN - LVL-2 CBS 10 22-May-15 05-Jun-15
CBSL2L2-3070 DRYWALL / FINISH - LVL-2 CBS 15 08-Jun-15 26-Jun-15
CBSL2L2-3080 INTERIOR PAINT - LVL-2 CBS 6 29-Jun-15 07-Jul-15
CBSL2L2-3090 CEILING GRID- LVL-2 CBS 7 08-Jul-15 16-Jul-15
CBSL2L2-3110 FLOORING - LVL-2 CBS 13 13-Jul-15 29-Jul-15
CBSL2L2-3100 MILLWORK - LVL-2 CBS 5 17-Jul-15 23-Jul-15
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 67 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 070
Activity ID Activity Name OrigDur
Start Finish
CBSL2L2-3120 MEP TRIMOUT - LVL-2 CBS 6 30-Jul-15 06-Aug-15
CBSL2L2-3980 TEST AND BALANCE - LVL-2 CBS 3 07-Aug-15 11-Aug-15
CBSL2L2-3140 PUNCHLIST - LVL-2 CBS 5 12-Aug-15 18-Aug-15
CBS - LEVEL 1CBS - LEVEL 1CBS - LEVEL 1CBS - LEVEL 1CBS - LEVEL 1CBSL1L1-3285 BELOW GRADE PLUMBING ROUGH-IN - LVL-1 CBS 10 26-Jul-11 05-Aug-11
CBSL1L1-3280 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-1 CBS 15 06-Aug-11 23-Aug-11
CBSL1L1-3290 FIRE SPRINKLER ROUGH-IN - LVL-1 CBS 5 22-Aug-11 26-Aug-11
CBSL1L1-3300 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-1 CBS 10 27-Aug-11 08-Sep-11
CBSL1L1-3303 NEW ELECTRICAL ROOM ROUGH-IN - LVL-1 CBS 20 09-Sep-11 01-Oct-11
CBSL1L1-3307 NEW ELECTRICAL ROOM FIT-OUT - LVL-1 CBS 20 03-Oct-11 26-Oct-11
CBSL1L1-3310 FRAMING - LVL-1 CBS 10 27-Oct-11 07-Nov-11
CBSL1L1-3320 WALL ROUGH-IN - LVL-1 CBS 5 05-Nov-11 10-Nov-11
CBSL1L1-3330 DRYWALL / FINISH - LVL-1 CBS 15 12-Nov-11 30-Nov-11
CBSL1L1-3340 INTERIOR PAINT - LVL-1 CBS 8 01-Dec-11 09-Dec-11
CBSL1L1-3350 CEILING - LVL-1 CBS 10 10-Dec-11 21-Dec-11
CBSL1L1-3360 MILLWORK - LVL-1 CBS 10 22-Dec-11 04-Jan-12
CBSL1L1-3370 FLOORING - LVL-1 CBS 10 05-Jan-12 17-Jan-12
CBSL1L1-3380 MEP TRIMOUT - LVL-1 CBS 10 18-Jan-12 28-Jan-12
CBSL1L1-3390 HANDRAIL - LVL-1 CBS 10 18-Jan-12 28-Jan-12
CBSL1L1-3400 PUNCHLIST - LVL-1 CBS 8 30-Jan-12 07-Feb-12
CBSL1L1-4000 TEST AND BALANCE - LVL-1 CBS 5 30-Jan-12 03-Feb-12
CBS - COMMISSICBS - COMMISSIONINGCBS - COMMISSIONINGCBS - COMMISSIONINGCBS - COMMISSIONINGCBSCOCO-4020 WHOLE BUILDING TEST AND BALANCE - ALL LVLS CBS 10 19-Aug-15 01-Sep-15
CBSCOCO-2120 COMMISSIONING - ALL LVLS CBS 20 02-Sep-15 30-Sep-15
CBS - TEMPORARCBS - TEMPORARY UTILITIES AND BUILDING MAINTENANCECBS - TEMPORARY UTILITIES AND BUILDING MAINTENANCECBS - TEMPORARY UTILITIES AND BUILDING MAINTENANCECBS - TEMPORARY UTILITIES AND BUILDING MAINTENANCECBSTUTU-3850 MAINTAIN TEMPERARY NATURAL GAS - TEMP UTILITIES CBS 514 20-May-11 A 22-Jan-14
CBSTUTU-3840 MAINTAIN TEMPERARY ELECTRICAL / COMMS - TEMP UTILITIES CBS 557 01-Jul-11 A 31-Dec-13
CBSTUTU-3790 INSTALL TEMPERARY BOILER - TEMP UTILITIES CBS 5 24-Aug-11 30-Aug-11
CBSTUTU-3830 MAINTAIN TEMPERARY BOILER - TEMP UTILITIES CBS 585 31-Aug-11 03-Jan-14
CBSTUTU-3870 MAINTAIN TEMPERARY HVAC - TEMP UTILITIES CBS 617 31-Aug-11 20-Feb-14
CBSTUTU-3890 DISCONNECT TEMPERARY BOILER - TEMP UTILITIES CBS 5 27-Dec-13 03-Jan-14
CBSTUTU-3900 DISCONNECT TEMPERARY ELECTRICAL / COMMS - TEMP UTILITIES CBS 1 31-Dec-13 31-Dec-13
CBSTUTU-3910 DISCONNECT TEMPERARY NATURAL GAS - TEMP UTILITIES CBS 5 15-Jan-14 22-Jan-14
CBSTUTU-3930 DISCONNECT TEMPERARY HVAC - TEMP UTILITIES CBS 15 30-Jan-14 20-Feb-14
CBS - SYSTEM TRCBS - SYSTEM TRANSITION (after ENC operational)CBS - SYSTEM TRANSITION (after ENC operational)CBS - SYSTEM TRANSITION (after ENC operational)CBS - SYSTEM TRANSITION (after ENC operational)CBSSTST-3640 FIRE SPRINKLER - SYSTEM TRANSFER CBS 5 28-Nov-13 04-Dec-13
CBSSTST-3650 WATER - SYSTEM TRANSFER CBS 5 05-Dec-13 11-Dec-13
CBSSTST-3660 DOMESTIC HOT WATER - SYSTEM TRANSFER CBS 10 12-Dec-13 26-Dec-13
CBSSTST-3680 ELECTRICAL POWER - SYSTEM TRANSFER CBS 10 16-Dec-13 30-Dec-13
CBSSTST-3670 STEAM - SYSTEM TRANSFER CBS 10 27-Dec-13 10-Jan-14
CBSSTST-3690 PHONE, SECURITY, FIRE ALARM - SYSTEM TRANSFER CBS 5 31-Dec-13 07-Jan-14
CBSSTST-3700 NATURAL GAS - SYSTEM TRANSFER CBS 5 08-Jan-14 14-Jan-14
CBSSTST-3710 DEMO EXISTING ROOF TOP DX SYSTEM - SYSTEM TRANSFER CBS 10 15-Jan-14 29-Jan-14
CBSSTST-3720 PATCH ROOF - SYSTEM TRANSFER CBS 5 30-Jan-14 05-Feb-14
CLC CONSTRUCCLC CONSTRUCTIONCLC CONSTRUCTIONCLC CONSTRUCTIONCLC CONSTRUCTIONCLC-0100 CLC CONSTRUCTION (16 months) 480 13-Dec-12 06-Apr-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 68 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 071
Activity ID Activity Name OrigDur
Start Finish
HARDSCAPE &HARDSCAPE & LANDSCAPEHARDSCAPE & LANDSCAPEHARDSCAPE & LANDSCAPEHARDSCAPE & LANDSCAPEDEMOBILIZEDEMOBILIZEDEMOBILIZEDEMOBILIZEDEMOBILIZESWSW-0100 KT DEMOBILIZE LESS RESEARCH AND CBS LVL-2 BUILDOUT 40 30-Jan-15 30-Mar-15
HARDSCAPE & LHARDSCAPE & LANDSCAPE - CBNHARDSCAPE & LANDSCAPE - CBNHARDSCAPE & LANDSCAPE - CBNHARDSCAPE & LANDSCAPE - CBNCBNSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK CBN 12 18-Oct-13 05-Nov-13
CBNSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK CBN 10 25-Oct-13 12-Nov-13
CBNSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK CBN 25 13-Nov-13 16-May-14
CBNSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK CBN 30 19-May-14 10-Jul-14
HARDSCAPE & LHARDSCAPE & LANDSCAPE - CBCHARDSCAPE & LANDSCAPE - CBCHARDSCAPE & LANDSCAPE - CBCHARDSCAPE & LANDSCAPE - CBCCBCSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK CBC 6 19-May-14 29-May-14
CBCSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK CBC 10 29-May-14 13-Jun-14
CBCSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK CBC 25 16-Jun-14 28-Jul-14
CBCSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK CBC 30 29-Jul-14 18-Sep-14
HARDSCAPE & LHARDSCAPE & LANDSCAPE - DAT BUILDINGHARDSCAPE & LANDSCAPE - DAT BUILDINGHARDSCAPE & LANDSCAPE - DAT BUILDINGHARDSCAPE & LANDSCAPE - DAT BUILDINGDATSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK DAT 45 13-May-14 31-Jul-14
DATSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK DAT 16 05-Jun-14 01-Jul-14
DATSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK DAT 20 19-Jun-14 22-Jul-14
DATSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK DAT 55 02-Jul-14 03-Oct-14
HARDSCAPE & LHARDSCAPE & LANDSCAPE - IBSHARDSCAPE & LANDSCAPE - IBSHARDSCAPE & LANDSCAPE - IBSHARDSCAPE & LANDSCAPE - IBSIBSSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK IBS 16 06-Sep-13 02-Oct-13
IBSSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK IBS 16 20-Sep-13 15-Oct-13
IBSSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK IBS 25 17-Oct-13 22-Apr-14
IBSSWHL-0290 LANDSCAPING/SITE FURNISHINGS - IBS 20 23-Apr-14 23-May-14
HARDSCAPE & LHARDSCAPE & LANDSCAPE - IBNHARDSCAPE & LANDSCAPE - IBNHARDSCAPE & LANDSCAPE - IBNHARDSCAPE & LANDSCAPE - IBNIBNSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK IBN 20 02-Aug-13 05-Sep-13
IBNSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK IBN 16 16-Aug-13 12-Sep-13
IBNSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK IBN 40 13-Sep-13 14-Apr-14
IBNSWHL-0290 LANDSCAPING/SITE FURNISHINGS - IBN 35 15-Apr-14 12-Jun-14
HARDSCAPE & LHARDSCAPE & LANDSCAPE - PVSHARDSCAPE & LANDSCAPE - PVSHARDSCAPE & LANDSCAPE - PVSHARDSCAPE & LANDSCAPE - PVSPVSSWHL-0210 INSTALL UNDERGROUND UTILITIES @ SOUTH ENTRY - SITEWORK PVS 8 20-Sep-12 02-Oct-12
PVSSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK PVS 20 28-Sep-12 29-Oct-12
PVSSWHL-0280 HARDSCAPE - SITEWORK PVS 60 14-Apr-14 24-Jul-14
PVSSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK PVS 25 25-Jul-14 05-Sep-14
HARDSCAPE & LHARDSCAPE & LANDSCAPE - ENCHARDSCAPE & LANDSCAPE - ENCHARDSCAPE & LANDSCAPE - ENCHARDSCAPE & LANDSCAPE - ENCENCSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK ENC 15 24-Apr-14 19-May-14
ENCSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK ENC 20 08-May-14 12-Jun-14
ENCSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK ENC 40 13-Jun-14 21-Aug-14
ENCSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK ENC 45 22-Aug-14 04-Nov-14
HARDSCAPE & LHARDSCAPE & LANDSCAPE - RESHARDSCAPE & LANDSCAPE - RESHARDSCAPE & LANDSCAPE - RESHARDSCAPE & LANDSCAPE - RESRESSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK RES 30 29-Jan-15 17-Mar-15
RESSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK RES 16 12-Feb-15 06-Mar-15
RESSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK RES 45 13-Apr-15 22-Jun-15
RESSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK RES 45 14-May-15 24-Jul-15
HARDSCAPE & LHARDSCAPE & LANDSCAPE - PVNHARDSCAPE & LANDSCAPE - PVNHARDSCAPE & LANDSCAPE - PVNHARDSCAPE & LANDSCAPE - PVNPVNSWHL-0210 INSTALL UNDERGROUND UTILITIES @ NORTH ENTRY- SITEWORK PVN 25 31-Dec-12 06-Feb-13
PVNSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK PVN 20 11-Jan-13 11-Feb-13
PVNSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK PVN 10 15-Apr-13 29-Apr-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 69 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 072
Activity ID Activity Name OrigDur
Start Finish
PVNSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK PVN 8 30-Apr-13 10-May-13
HARDSCAPE & LHARDSCAPE & LANDSCAPE - PSNHARDSCAPE & LANDSCAPE - PSNHARDSCAPE & LANDSCAPE - PSNHARDSCAPE & LANDSCAPE - PSNPSNSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK PSN 34 20-Sep-12 14-Nov-12
PSNSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK PSN 30 03-Oct-12 20-Nov-12
PSNSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK PSN 30 15-Apr-13 03-Jun-13
PSNSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK PSN 20 04-Jun-13 01-Jul-13
FULL CAMPUS FULL CAMPUS COMMISSIONINGFULL CAMPUS COMMISSIONINGFULL CAMPUS COMMISSIONINGFULL CAMPUS COMMISSIONINGFULL CAMPUS COFULL CAMPUS COMMISSIONINGFULL CAMPUS COMMISSIONINGFULL CAMPUS COMMISSIONINGFULL CAMPUS COMMISSIONINGENCPBPB-1606 START UP CAMPUS ELEC EQUIPMENT - FULL CAMPUS 30 30-Aug-13 11-Oct-13
ENCPBPB-1590 START-UP CAMPUS PUMPS- SERV LVL MECH RMS ENC 30 14-Oct-13 27-Nov-13
ENCSLME-1590 START-UP CAMPUS BOILERS/CHILLERS - SERV LVL MECH RMS ENC 30 14-Oct-13 27-Nov-13
ENCPHPH-1590 START-UP CAMPUS COOLING TOWERS - PENTHOUSE ENC 30 14-Oct-13 27-Nov-13
COMMISS-1616 SYSTEM CONTROLS/STABILIZATION - FULL CAMPUS 30 14-Oct-13 27-Nov-13
COMMISS-1626 LOAD TEST - FULL CAMPUS 5 28-Nov-13 04-Dec-13
COMMISS-1596 INTEGRATED SYSTEMS TEST - FULL CAMPUS 45 12-Feb-15 28-Mar-15
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SCHEDULE
Page 70 of 70
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 073
Activity ID Activity Name OrigDur
Start Finish
DENVER VA MDENVER VA MEDICAL CENTER - FTP SCHEDULEDENVER VA MEDICAL CENTER - FTP SCHEDULEDENVER VA MEDICAL CENTER - FTP SCHEDULEDENVER VA MEDICAL CENTER - FTP SCHEDULEPROJECT MILEPROJECT MILESTONESPROJECT MILESTONESPROJECT MILESTONESPROJECT MILESTONESAAAA-1020 DESIGN KICKOFF 0 01-Nov-10 A
AAAACBS-0100 START CBS CONSTRUCTION (start milestone) 0 09-May-11 A
AAAA-1010 NTP FOR CONSTRUCTION 0 06-Sep-11*
AAAA-1040 NTP FOR POTHOLING FOR SHORING TIE-BACKS (start milestone) 0 07-Sep-11
AAAA-1030 NTP FOR POTHOLING FOR WHEELING WATERLINE (start milestone) 0 12-Sep-11
ZZZZWS-9999 NEW WATERLINE COMPLETE @ WHEELING ST (finish milestone) 0 30-Jan-12
AAAAPVS-0100 START PVS CONSTRUCTION (start milestone) 0 06-Feb-12
CBSMIMI-3610 DOD/VA ACCEPT LEVELS 1,3 & 4 - CBS MILESTONE 0 08-Feb-12*
AAAADAT-0100 START DAT CONSTRUCTION (start milestone) 0 10-Feb-12
AAAAIBS-0100 START IBS CONSTRUCTION (start milestone) 0 14-Mar-12
AAAAENC-0100 START ENC CONSTRUCTION (start milestone) 0 05-Apr-12
AAAACON-0100 START CON CONSTRUCTION (start milestone) 0 24-Apr-12
AAAAIBT-0100 START IBN CONSTRUCTION (start milestone) 0 27-Apr-12
AAAACBN-0100 START CBN CONSTRUCTION (start milestone) 0 12-Jun-12
AAAAPSN-0100 START PSN CONSTRUCTION (start milestone) 0 14-Jun-12
AAAACBC-0100 START CBC CONSTRUCTION (start milestone) 0 10-Jul-12
AAAACLC-100 START CLC CONSTRUCTION (start milestone) 0 22-Aug-12
AAAAPVN-0100 START PVN CONSTRUCTION (start milestone) 0 23-Sep-13
ZZZZPVS-9999 FINISH PVS CONSTRUCTION (finish milestone) 0 30-Jan-14
AAAARES-0100 START RES CONSTRUCTION (start milestone) 0 31-Jan-14
ZZZZENC-9999 FINISH ENC CONSTRUCTION (finish milestone) 0 28-Feb-14
ZZZZPSN-9999 FINISH PSN CONSTRUCTION (finish milestone) 0 14-Mar-14
ZZZZCLC-10009 FINISH CLC CONSTRUCTION (finish milestone) 0 06-Apr-14
ZZZZOFF-10019 FINISH OFF-SITE IMPROVEMENTS (finish milestone) 0 22-May-14
ZZZZIBT-9999 FINISH IBN CONSTRUCTION (finish milestone) 0 19-Oct-14
ZZZZSIT-9999 FINISH SITEWORK (finish milestone) 0 04-Nov-14
ZZZZIBS-9999 FINISH IBS CONSTRUCTION (finish milestone) 0 06-Nov-14
ZZZZCBN-9999 FINISH CBN CONSTRUCTION (finish milestone) 0 20-Jan-15
ZZZZPVN-9999 FINISH PVN CONSTRUCTION (finish milestone) 0 24-Feb-15
ZZZZDAT-9999 FINISH DAT CONSTRUCTION (finish milestone) 0 26-Feb-15
ZZZZCBC-9999 FINISH CBC CONSTRUCTION (finish milestone) 0 26-Feb-15
ZZZZCON-9999 FINISH CON CONSTRUCTION (finish milestone) 0 23-Mar-15
ZZZZZZZ-10009 CAMPUS SUBSTANTIAL COMPLETION LESS THE RESEARCH BUILDING (finish milestone) 0 28-Mar-15*
ZZZZCBS-9999 FINISH CBS CONSTRUCTION (finish milestone) 0 30-Sep-15
ZZZZRES-9999 FINISH RES CONSTRUCTION (finish milestone) 0 03-Oct-15
ZZZZZZZ-10019 CAMPUS FINAL COMPLETION (finish milestone) 0 03-Oct-15*
BUILDINGS AVABUILDINGS AVAILABLE TO ENERGIZEBUILDINGS AVAILABLE TO ENERGIZEBUILDINGS AVAILABLE TO ENERGIZEBUILDINGS AVAILABLE TO ENERGIZEEEEEENC-0990 ENC BLDG AVAILABLE FOR ENERGIZE 0 29-Aug-13
EEEEPVS-0000 PVS BLDG AVAILABLE FOR ENERGIZE 0 17-Oct-13
EEEEDAT-0000 DAT BLDG AVAILABLE FOR ENERGIZE 0 23-Oct-13
EEEEPSN-0000 PSN BLDG AVAILABLE FOR ENERGIZE 0 07-Nov-13
EEEEIBN-0000 IBN BLDG AVAILABLE FOR ENERGIZE 0 04-Feb-14
EEEEIBS-0000 IBS BLDG AVAILABLE FOR ENERGIZE 0 13-Feb-14
EEEECBN-0000 CBN BLDG AVAILABLE FOR ENERGIZE 0 26-Jun-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SUMMARY SCHEDULE
Page 1 of 2
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 074
Activity ID Activity Name OrigDur
Start Finish
EEEECBC-0000 CBC BLDG AVAILABLE FOR ENERGIZE 0 07-Jul-14
EEEEPVN-0000 PVN BLDG AVAILABLE FOR ENERGIZE 0 07-Oct-14
EEEECON-0000 CON BLDG AVAILABLE FOR ENERGIZE 0 10-Oct-14
EEEERES-0000 RES BLDG AVAILABLE FOR ENERGIZE 0 27-May-15
OVERALL BUILDOVERALL BUILDING DURATIONSOVERALL BUILDING DURATIONSOVERALL BUILDING DURATIONSOVERALL BUILDING DURATIONSXXXXCBS-0500 CBS OVERALL DURATION 936 09-May-11 A 30-Sep-15
XXXXSIT-0510 INITIAL SITEWORK DURATION 958 11-Jan-12 25-Aug-14
XXXXPVS-0500 PVS OVERALL DURATION 724 06-Feb-12 30-Jan-14
XXXXDAT-0500 DAT OVERALL DURATION 1113 10-Feb-12 26-Feb-15
XXXXIBS-0500 IBS OVERALL DURATION 968 14-Mar-12 06-Nov-14
XXXXENC-0500 ENC OVERALL DURATION 695 05-Apr-12 28-Feb-14
XXXXCON-0500 CON OVERALL DURATION 1064 24-Apr-12 23-Mar-15
XXXXIBN-0500 IBN OVERALL DURATION 906 27-Apr-12 19-Oct-14
XXXXCBN-0500 CBN OVERALL DURATION 953 12-Jun-12 20-Jan-15
XXXXPSN-0500 PSN OVERALL DURATION 639 14-Jun-12 14-Mar-14
XXXXCBC-0500 CBC OVERALL DURATION 961 10-Jul-12 26-Feb-15
XXXXCLC-0500 CLC OVERALL DURATION 480 13-Dec-12 06-Apr-14
XXXXPVN-0500 PVN OVERALL DURATION 520 23-Sep-13 24-Feb-15
XXXCAMP-1600 COMMISSION - FULL CAMPUS 315 24-Dec-13 27-Mar-15
XXXXRES-0500 RES OVERALL DURATION 611 31-Jan-14 03-Oct-15
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - FTP SUMMARY SCHEDULE
Page 2 of 2
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 075
Activity ID Activity Name OrigDur
Start Finish
AAAA-1010 NTP FOR CONSTRUCTION 0 06-Sep-11*
AAAA-5590 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1 0 06-Sep-11
STR1-5420 AWARD SHORING CONTRACT 20 07-Sep-11 04-Oct-11
SITSWSW-0102 SHORING SUB COORDINATE WITH DESIGN - POTHOLING 5 05-Oct-11 11-Oct-11
STR1-5430 PREPARE/SUBMIT SHOP DRAWINGS FOR SHORING STR-1 20 12-Oct-11 08-Nov-11
STR1-5410 KT APPROVE SHOP DRAWINGS FOR SHORING STR-1 30 09-Nov-11 23-Dec-11
STR1-5450 FABRICATE SHORING MATERIALS STR-1 10 27-Dec-11 10-Jan-12
STR1-5440 MATERIALS ARRIVE ON SITE STR-1 0 10-Jan-12
DATPGPG-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PIPE GALLERY DAT 25 11-Jan-12 09-Feb-12
DATPGPG-0320 DRILL/PLACE CAISSONS - PIPE GALLERY DAT 15 10-Feb-12 05-Mar-12
DATPGPG-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY DAT 27 21-Feb-12 02-Apr-12
DATPGPG-3110 SET/BACKFILL DUCTBANKS - PIPE GALLERY DAT 7 03-Apr-12 16-Apr-12
DATPGPG-3200 UNDERSLAB UTILITIES - PIPE GALLERY DAT 7 03-Apr-12 16-Apr-12
DATPGPG-0380 FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY DAT 5 17-Apr-12 24-Apr-12
DATSLSL-0322 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - SERV LVL DAT 15 26-Apr-12 22-May-12
DATSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE (AREA C) - SERV LVL DAT 15 15-May-12 08-Jun-12
DATPGPG-3210 BACKFILL FOUNDATION WALLS (INTERIOR) - PIPE GALLERY DAT 5 24-May-12 31-May-12
DATSLSL-3210 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - SERV LVL DAT 10 24-May-12 08-Jun-12
DATL1L1-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-1 DAT 15 11-Jun-12 05-Jul-12
DATL1L1-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-1 DAT 5 06-Jul-12 13-Jul-12
DATL1L1-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-1 DAT 5 16-Jul-12 23-Jul-12
DATL1L1-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-1 DAT 10 24-Jul-12 09-Aug-12
DATL1L1-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-1 DAT 5 10-Aug-12 17-Aug-12
DATL1L1-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-1 DAT 5 20-Aug-12 27-Aug-12
DATL2L2-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-2 DAT 5 28-Aug-12 05-Sep-12
DATL2L2-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-2 DAT 5 28-Aug-12 05-Sep-12
DATL2L2-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-2 DAT 5 06-Sep-12 13-Sep-12
DATL2L2-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-2 DAT 5 06-Sep-12 13-Sep-12
DATL2L2-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-2 DAT 5 14-Sep-12 21-Sep-12
DATL2L2-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-2 DAT 5 14-Sep-12 21-Sep-12
DATL3L3-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-3 DAT 5 24-Sep-12 01-Oct-12
DATL3L3-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-3 DAT 5 02-Oct-12 08-Oct-12
DATL3L3-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-3 DAT 5 09-Oct-12 16-Oct-12
DATL3L3-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-3 DAT 5 18-Oct-12 24-Oct-12
DATL3L3-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-3 DAT 5 25-Oct-12 01-Nov-12
DATL3L3-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-3 DAT 5 02-Nov-12 09-Nov-12
DATPHPH-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - PENT DAT 5 13-Nov-12 19-Nov-12
DATSLIL-1537 ERECT INTER STEEL/TOPPING (AREA C) - SERV LVL INTER LVL DAT 15 20-Nov-12 13-Dec-12
DATSLIL-1547 ERECT INTER STEEL/TOPPING (AREA D) - SERV LVL INTER LVL DAT 15 07-Dec-12 31-Dec-12
DATSLIL-1557 ERECT INTER STEEL/TOPPING (AREA E) - SERV LVL INTER LVL DAT 15 24-Dec-12 15-Jan-13
DATSLIL-1567 ERECT INTER STEEL/TOPPING (AREA F) - SERV LVL INTER LVL DAT 15 09-Jan-13 31-Jan-13
DATSLIL-0510 ERECT INTER STEEL/TOPPING (AREA A) - SERV LVL INTER LVL DAT 15 25-Jan-13 15-Feb-13
DATSLIL-1527 ERECT INTER STEEL/TOPPING (AREA B) - SERV LVL INTER LVL DAT 15 08-Feb-13 04-Mar-13
DATSLIL-1800 ROUGH-IN MEP/FIRE PROTECTION (EMER MGMNT) (AHU18) - SERV LVL INTER LVL DAT 45 05-Mar-13 06-May-13
DATSLIL-0200 ROUGH-IN MEP/FIRE PROTECTION (PHARMACY) (AHU2) - SERV LVL INTER LVL DAT 45 02-Apr-13 04-Jun-13
DATSLIL-0700 ROUGH-IN MEP/FIRE PROTECTION (STERILIZATION) (AHU7) - SERV LVL INTER LVL DAT 45 30-Apr-13 02-Jul-13
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - CRITICAL PATH TO SUBSTANTIAL COMPLETION (DAT)
Page 1 of 2
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 076
Activity ID Activity Name OrigDur
Start Finish
DATSLIL-1900 ROUGH-IN MEP/FIRE PROTECTION (SHELL) (AHU19) - SERV LVL INTER LVL DAT 45 29-May-13 31-Jul-13
DATL1IL-0400 ROUGH-IN MEP/FIRE PROTECTION (GEN RADIOLOGY) (AHU4) - LVL-1 INTER LVL DAT 55 26-Jun-13 12-Sep-13
DATL1IL-0100 ROUGH-IN MEP/FIRE PROTECTION (PRE ADMIN) (AHU1) - LVL-1 INTER LVL DAT 50 25-Jul-13 03-Oct-13
DATL1PA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 PRE-ADMIT DAT 30 04-Oct-13 18-Nov-13
DATL1NM-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 NUC MED DAT 20 19-Nov-13 17-Dec-13
DATL1NM-0910 FRAMING/INWALL ROUGH - LVL-1 NUC MED DAT 25 27-Nov-13 02-Jan-14
DATL1NM-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 NUC MED DAT 20 18-Dec-13 16-Jan-14
DATL1NM-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NUC MED DAT 65 10-Jan-14 14-Apr-14
DATL1PA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PRE-ADMIT DAT 55 25-Feb-14 12-May-14
DATL1RO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 RAD OFFICES DAT 40 08-Apr-14 03-Jun-14
DATL2CA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CARDIO DAT 55 20-May-14 06-Aug-14
DATL2SL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SLEEP DAT 45 02-Jul-14 04-Sep-14
DATL3CA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CATH LABS DAT 65 14-Aug-14 17-Nov-14
DATL3OR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 ORS DAT 75 12-Sep-14 31-Dec-14
DATALCL-1592 TEST & BALANCE - DAT 60 17-Oct-14 15-Jan-15
DATALCL-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - DAT 45 17-Oct-14 23-Dec-14
DATALCL-1596 FUNCTIONAL TESTING/CORRECTIONS - DAT 45 03-Dec-14 06-Feb-15
DATALCL-1599 BUILDING FLUSH - DAT 20 07-Feb-15 26-Feb-15
COMMISS-1596 INTEGRATED SYSTEMS TEST - FULL CAMPUS 45 12-Feb-15 28-Mar-15
ZZZZZZZ-10009 CAMPUS SUBSTANTIAL COMPLETION LESS THE RESEARCH BUILDING (finish milestone) 0 28-Mar-15*
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - CRITICAL PATH TO SUBSTANTIAL COMPLETION (DAT)
Page 2 of 2
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 077
Activity ID Activity Name OrigDur
Start Finish
OSI-250 VA LICENSE AGREEMENTS WITH FRA/COA/UCD 0 23-Nov-11*
W-OSI-5610 FRA/COA APPROVE WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 20 28-Nov-11 23-Dec-11
SITWSSW-328 PLACE EROSION PROTECTION/TRAFFIC CONTROL - WHEELING ST. 2 23-Dec-11 28-Dec-11
SITWSSW-288 DEMO/GRADING - WHEELING ST. 5 28-Dec-11 05-Jan-12
SITWSSW-0205 INSTALL/TEST NEW WATERLINE - WHEELING ST. 15 05-Jan-12 30-Jan-12
PVSSWSW-3130 DRIVE SOLDIER PILES - PVS SITEWORK 10 23-Jan-12 06-Feb-12
ZZZZWS-9999 NEW WATERLINE COMPLETE @ WHEELING ST (finish milestone) 0 30-Jan-12
PVSSWSW-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PVS SITEWORK 115 06-Feb-12 21-Jun-12
PVSP3AA-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA A PVS 14 21-Jun-12 16-Jul-12
PVSP3AD-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA D PVS 14 21-Jun-12 16-Jul-12
PVSP3AE-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA E PVS 14 16-Jul-12 09-Aug-12
PVSP3AF-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA F PVS 14 09-Aug-12 04-Sep-12
PVSP3AF-0330 FORM/PLACE TOWER CRANE #2 BASE - (PVS) 35 24-Aug-12 23-Oct-12
HOITCTC-0102 ERECT TOWER CRANE #2 (PVS) 10 23-Oct-12 03-Nov-12
PVSP2AA-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA A PVS 12 05-Nov-12 23-Nov-12
PVSP2AB-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA B PVS 10 14-Nov-12 29-Nov-12
PVSP2AC-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA C PVS 10 21-Nov-12 07-Dec-12
PVSP2AD-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA D PVS 10 30-Nov-12 14-Dec-12
PVSP1AA-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA A PVS 10 10-Dec-12 24-Dec-12
PVSP2AE-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA E PVS 10 10-Dec-12 24-Dec-12
PVSP1AB-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA B PVS 10 17-Dec-12 02-Jan-13
PVSP1AC-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA C PVS 10 26-Dec-12 09-Jan-13
PVSP1AD-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA D PVS 10 03-Jan-13 17-Jan-13
PVSP0AA-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA A PVS 10 18-Jan-13 01-Feb-13
PVSP0AB-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA B PVS 10 31-Jan-13 14-Feb-13
PVSP0AC-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA C PVS 10 12-Feb-13 27-Feb-13
PVSP0AD-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA D PVS 10 26-Feb-13 12-Mar-13
PVSP0AE-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA E PVS 10 11-Mar-13 25-Mar-13
PVSP0AF-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA F PVS 10 21-Mar-13 05-Apr-13
CBCSLSL-0320 DRILL/PLACE CAISSONS (balance @ bench) - SERV LVL CBC 15 29-Mar-13 23-Apr-13
CBCSSSS-510 FORM/PLACE/STRIP SHEAR WALLS (southwest corner) - ALL LVLS CBC 45 16-Apr-13 03-Jul-13
CBCSSSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBC 33 05-Jul-13 30-Aug-13
CBCPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT LVL CBC 19 03-Sep-13 02-Oct-13
CBCPHPH-0310 FORM/REINFORCE/FINISH HOUSEKEEPING PADS - PENT LVL CBC 7 03-Oct-13 11-Oct-13
CBCPHPH-1500 SET MECH EQUIPMENT - PENTLVL CBC 5 14-Oct-13 18-Oct-13
CBCPHPH-1600 SET ELECTRICAL EQUIPMENT - PENTLVL CBC 10 22-Oct-13 04-Nov-13
CBCPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTLVL CBC 15 05-Nov-13 29-Nov-13
CBCL3L3-0540 ERECT EXTERIOR STUDS - LVL-3 CBC 15 02-Dec-13 24-Dec-13
CBCL2L2-0540 ERECT EXTERIOR STUDS - LVL-2 CBC 15 26-Dec-13 17-Jan-14
CBCL1L1-0540 ERECT EXTERIOR STUDS - LVL-1 CBC 7 21-Jan-14 29-Jan-14
CBCESNE-0520 SHEATHING/VAPOR BARRIER - NORTH ELEV CBC 10 30-Jan-14 14-Feb-14
CBCESWE-0520 SHEATHING/VAPOR BARRIER - WEST ELEV CBC 5 17-Feb-14 21-Feb-14
CBCESSE-0520 SHEATHING/VAPOR BARRIER - SOUTH ELEV CBC 10 24-Feb-14 07-Mar-14
CBCESEE-0520 SHEATHING/VAPOR BARRIER - EAST ELEV CBC 5 10-Mar-14 17-Mar-14
CBCL3AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-3 AREA A CBC 20 18-Mar-14 14-Apr-14
CBCL3AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AREA B CBC 20 01-Apr-14 28-Apr-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - CRITICAL PATH TO SUBSTANTIAL COMPLETION (PVS-CBC)
Page 1 of 2
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 078
Activity ID Activity Name OrigDur
Start Finish
CBCL2AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-2 AREA A CBC 18 15-Apr-14 08-May-14
CBCL2AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AREA B CBC 17 29-Apr-14 21-May-14
CBCL1AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-1 AREA A CBC 18 13-May-14 06-Jun-14
CBCL1AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AREA B CBC 17 28-May-14 19-Jun-14
CBCL1AB-0910 FRAMING/INWALL ROUGH - LVL-1 AREA B CBC 14 09-Jun-14 26-Jun-14
CBCL1AA-0910 FRAMING/INWALL ROUGH - LVL-1 AREA A CBC 14 16-Jun-14 03-Jul-14
CBCL1AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA A CBC 13 30-Jun-14 17-Jul-14
CBCL1AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA B CBC 12 08-Jul-14 23-Jul-14
CBCL1AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA B CBC 22 22-Jul-14 20-Aug-14
CBCSLEL-0910 FRAMING/INWALL ROUGH - SERV LVL CORR CBC 5 21-Aug-14 27-Aug-14
CBCALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS CBC 15 21-Aug-14 11-Sep-14
CBCSLEL-0990 HANG/TAPE/FINISH/PAINT - SERV LVL CORR CBC 10 28-Aug-14 11-Sep-14
CBCALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS CBC 20 12-Sep-14 09-Oct-14
CBCCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - CBC 35 10-Oct-14 02-Dec-14
CBCCOCO-1620 TEST & BALANCE - CBC 30 03-Dec-14 15-Jan-15
CBCCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - CBC 20 03-Dec-14 31-Dec-14
CBCCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - CBC 25 02-Jan-15 06-Feb-15
CBCCOCO-1599 BUILDING FLUSH - CBC 20 07-Feb-15 26-Feb-15
COMMISS-1596 INTEGRATED SYSTEMS TEST - FULL CAMPUS 45 12-Feb-15 28-Mar-15
ZZZZZZZ-10009 CAMPUS SUBSTANTIAL COMPLETION LESS THE RESEARCH BUILDING (finish milestone) 0 28-Mar-15*
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - CRITICAL PATH TO SUBSTANTIAL COMPLETION (PVS-CBC)
Page 2 of 2
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 079
Activity ID Activity Name OrigDur
Start Finish
OSI-250 VA LICENSE AGREEMENTS WITH FRA/COA/UCD 0 23-Nov-11*
W-OSI-5610 FRA/COA APPROVE WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 20 28-Nov-11 23-Dec-11
SITWSSW-328 PLACE EROSION PROTECTION/TRAFFIC CONTROL - WHEELING ST. 2 23-Dec-11 28-Dec-11
SITWSSW-288 DEMO/GRADING - WHEELING ST. 5 28-Dec-11 05-Jan-12
SITWSSW-0205 INSTALL/TEST NEW WATERLINE - WHEELING ST. 15 05-Jan-12 30-Jan-12
PVSSWSW-3130 DRIVE SOLDIER PILES - PVS SITEWORK 10 23-Jan-12 06-Feb-12
ZZZZWS-9999 NEW WATERLINE COMPLETE @ WHEELING ST (finish milestone) 0 30-Jan-12
PVSSWSW-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PVS SITEWORK 115 06-Feb-12 21-Jun-12
PVSP3AA-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA A PVS 14 21-Jun-12 16-Jul-12
PVSP3AD-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA D PVS 14 21-Jun-12 16-Jul-12
PVSP3AE-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA E PVS 14 16-Jul-12 09-Aug-12
PVSP3AF-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA F PVS 14 09-Aug-12 04-Sep-12
PVSP3AF-0330 FORM/PLACE TOWER CRANE #2 BASE - (PVS) 35 24-Aug-12 23-Oct-12
HOITCTC-0102 ERECT TOWER CRANE #2 (PVS) 10 23-Oct-12 03-Nov-12
PVSP2AA-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA A PVS 12 05-Nov-12 23-Nov-12
PVSP2AB-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA B PVS 10 14-Nov-12 29-Nov-12
PVSP2AC-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA C PVS 10 21-Nov-12 07-Dec-12
PVSP2AD-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA D PVS 10 30-Nov-12 14-Dec-12
PVSP1AA-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA A PVS 10 10-Dec-12 24-Dec-12
PVSP2AE-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA E PVS 10 10-Dec-12 24-Dec-12
PVSP1AB-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA B PVS 10 17-Dec-12 02-Jan-13
PVSP1AC-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA C PVS 10 26-Dec-12 09-Jan-13
PVSP1AD-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA D PVS 10 03-Jan-13 17-Jan-13
PVSP0AA-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA A PVS 10 18-Jan-13 01-Feb-13
PVSP0AB-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA B PVS 10 31-Jan-13 14-Feb-13
PVSP0AC-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA C PVS 10 12-Feb-13 27-Feb-13
PVSP0AD-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA D PVS 10 26-Feb-13 12-Mar-13
PVSP0AE-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA E PVS 10 11-Mar-13 25-Mar-13
PVSP0AF-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA F PVS 10 21-Mar-13 05-Apr-13
PVSALAL-0555 ERECT STAIRS ST1 - ALL LVLS PVS 20 08-Apr-13 03-May-13
PVSALAL-0556 ERECT STAIRS ST2 - ALL LVLS PVS 20 18-Apr-13 15-May-13
PVSALAL-0557 ERECT STAIRS ST3 - ALL LVLS PVS 20 30-Apr-13 28-May-13
PVSINP1-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-3 PVS 30 29-May-13 10-Jul-13
PVSINP2-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-2 PVS 30 26-Jun-13 07-Aug-13
PVSINP3-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-1 PVS 30 25-Jul-13 05-Sep-13
PVSINP3-0990 GARAGE FINISHES - PKG LVL-1 PVS 30 06-Sep-13 17-Oct-13
PVSALAL-1400 INSTALL ELEVATOR PGE15/PGE16X - ALL LVLS PVS 60 04-Oct-13 02-Jan-14
EEEEPVS-0000 PVS BLDG AVAILABLE FOR ENERGIZE 0 17-Oct-13
PVSP1AA-1641 START-UP ELECTRICAL SYSTEMS (pvs/con) - PKG LVL-1 AREA A PVS 30 18-Oct-13 03-Dec-13
PVSALCO-1592 TEST & BALANCE - ALL LVLS PVS 20 24-Dec-13 12-Jan-14
PVSALCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS PVS 10 24-Dec-13 08-Jan-14
PVSALCO-1596 FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS PVS 15 09-Jan-14 30-Jan-14
RESSLSL-3130 DRIVE SOLDIER PILES - SERV LVL RES 10 31-Jan-14 17-Feb-14
RESSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL RES 18 18-Feb-14 10-Mar-14
RESSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL RES 26 11-Mar-14 24-Apr-14
RESSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL RES 30 07-Apr-14 29-May-14
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - CRITICAL PATH TO CAMPUS FINAL COMPLETION
Page 1 of 2
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 080
Activity ID Activity Name OrigDur
Start Finish
RESSLSL-3200 UNDERSLAB UTILITIES (DUCTBANKS/VAULTS/PLUMBING) - SERV LVL RES 15 02-May-14 29-May-14
RESSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL RES 10 30-May-14 16-Jun-14
RESL1L1-0320 FORM/REINFORCE/PLACE/FINISH - LVL-1 RES 15 17-Jun-14 11-Jul-14
RESL2L2-0320 FORM/REINFORCE/PLACE/FINISH - LVL-2 RES 15 14-Jul-14 07-Aug-14
RESL3L3-0320 FORM/REINFORCE/PLACE/FINISH - LVL-3 RES 15 08-Aug-14 03-Sep-14
RESPHPH-0320 FORM/REINFORCE/PLACE/FINISH (INCL CORE COMP)- PENTHOUSE RES 30 04-Sep-14 22-Oct-14
RESPHPH-1500 SET MECH EQUIPMENT - ROOF RES 2 10-Nov-14 12-Nov-14
RESPHPH-0510 ERECT PENTHOUSE STEEL/METAL DECK - ROOF RES 20 13-Nov-14 15-Dec-14
RESRLRL-0750 PARAPET/BLOCKING/ROOFING - ROOF RES 20 16-Dec-14 16-Jan-15
RESL1LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 LAB RES 15 20-Jan-15 10-Feb-15
RESL1LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 LAB RES 45 27-Jan-15 31-Mar-15
RESL2LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 LAB RES 45 01-Apr-15 03-Jun-15
RESL3LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 LAB RES 45 04-Jun-15 06-Aug-15
RESL3LA-8880 CLEAN-UP/PRE PUNCH - LVL-3 LAB RES 10 07-Aug-15 20-Aug-15
RESCOCL-9999 CREATE/COMPLETE FINAL PUNCHLIST - RES 20 21-Aug-15 18-Sep-15
RESCOCL-1599 BUILDING FLUSH - RES 15 19-Sep-15 03-Oct-15
ZZZZRES-9999 FINISH RES CONSTRUCTION (finish milestone) 0 03-Oct-15
ZZZZZZZ-10019 CAMPUS FINAL COMPLETION (finish milestone) 0 03-Oct-15*
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015
DENVER VA MEDICAL CENTER - FTP SCHEDULE
SCHEDULE FILE:DVFTP-04 8.12.11
DATA DATE:26-Jul-11
RUN DATE: 12-Aug-11
2222 - CRITICAL PATH TO CAMPUS FINAL COMPLETION
Page 2 of 2
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 081
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DVFTP-04 DVFTP-04 8.12.11 DENVER VA MEDICAL CENTER - FTP SCHEDULE 1262 1077 14.66% 01-Nov-10 A 03-Oct-15 09-May-11 03-Oct-15 0
RESCOCL-1599 BUILDING FLUSH - RES 15 15 0% 19-Sep-15 03-Oct-15 19-Sep-15 03-Oct-15 0
RESCOCL-9999 CREATE/COMPLETE FINAL PUNCHLIST - RES 20 20 0% 21-Aug-15 18-Sep-15 21-Aug-15 18-Sep-15 0
RESL1LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 LAB RES 15 15 0% 20-Jan-15 10-Feb-15 20-Jan-15 10-Feb-15 0
RESL1LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 LAB RES 45 45 0% 27-Jan-15 31-Mar-15 27-Jan-15 31-Mar-15 0
RESL2LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 LAB RES 45 45 0% 01-Apr-15 03-Jun-15 01-Apr-15 03-Jun-15 0
RESL3LA-0977 INSTALL OWNER FIXED FF&E - LVL-3 LAB RES 20 20 0% 10-Jul-15 06-Aug-15 10-Jul-15 06-Aug-15 0
RESL3LA-8880 CLEAN-UP/PRE PUNCH - LVL-3 LAB RES 10 10 0% 07-Aug-15 20-Aug-15 07-Aug-15 20-Aug-15 0
RESL3LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 LAB RES 45 45 0% 04-Jun-15 06-Aug-15 04-Jun-15 06-Aug-15 0
RESL2L2-0320 FORM/REINFORCE/PLACE/FINISH - LVL-2 RES 15 15 0% 14-Jul-14 07-Aug-14 14-Jul-14 07-Aug-14 0
RESSLSL-3200 UNDERSLAB UTILITIES (DUCTBANKS/VAULTS/PLUMBING) - SERV LVL RES 15 15 0% 02-May-14 29-May-14 02-May-... 29-May-14 0
RESSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL RES 18 18 0% 18-Feb-14 10-Mar-14 18-Feb-14 10-Mar-14 0
RESSLSL-3130 DRIVE SOLDIER PILES - SERV LVL RES 10 10 0% 31-Jan-14 17-Feb-14 31-Jan-14 17-Feb-14 0
RESSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL RES 26 26 0% 11-Mar-14 24-Apr-14 11-Mar-14 24-Apr-14 0
RESSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL RES 10 10 0% 30-May-14 16-Jun-14 30-May-... 16-Jun-14 0
RESSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL RES 30 30 0% 07-Apr-14 29-May-14 07-Apr-14 29-May-14 0
RESRLRL-0750 PARAPET/BLOCKING/ROOFING - ROOF RES 20 20 0% 16-Dec-14 16-Jan-15 16-Dec-14 16-Jan-15 0
RESL1L1-0320 FORM/REINFORCE/PLACE/FINISH - LVL-1 RES 15 15 0% 17-Jun-14 11-Jul-14 17-Jun-14 11-Jul-14 0
RESPHPH-1500 SET MECH EQUIPMENT - ROOF RES 2 2 0% 10-Nov-14 12-Nov-14 10-Nov-14 12-Nov-14 0
RESPHPH-0320 FORM/REINFORCE/PLACE/FINISH (INCL CORE COMP)- PENTHOUSE RES 30 30 0% 04-Sep-14 22-Oct-14 04-Sep-14 22-Oct-14 0
RESPHPH-0510 ERECT PENTHOUSE STEEL/METAL DECK - ROOF RES 20 20 0% 13-Nov-14 15-Dec-14 13-Nov-14 15-Dec-14 0
RESL3L3-0320 FORM/REINFORCE/PLACE/FINISH - LVL-3 RES 15 15 0% 08-Aug-14 03-Sep-14 08-Aug-14 03-Sep-14 0
PVNSLSL-3130 DRIVE SOLDIER PILES - SERV LVL PVN 10 10 0% 01-Aug-13 16-Aug-13 01-Aug-13 16-Aug-13 0
HOITCTC-0200 MAINTAIN TOWER CRANE #2 (PVS) 153 153 0% 03-Nov-12 05-Apr-13 03-Nov-12 05-Apr-13 0
CBCSSSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBC 33 33 0% 05-Jul-13 30-Aug-13 05-Jul-13 30-Aug-13 0
CBCSSSS-510 FORM/PLACE/STRIP SHEAR WALLS (southwest corner) - ALL LVLS CBC 45 45 0% 16-Apr-13 03-Jul-13 16-Apr-13 03-Jul-13 0
CBCL1L1-0540 ERECT EXTERIOR STUDS - LVL-1 CBC 7 7 0% 21-Jan-14 29-Jan-14 21-Jan-14 29-Jan-14 0
CBCL2L2-0540 ERECT EXTERIOR STUDS - LVL-2 CBC 15 15 0% 26-Dec-13 17-Jan-14 26-Dec-13 17-Jan-14 0
CBCPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT LVL CBC 19 19 0% 03-Sep-13 02-Oct-13 03-Sep-13 02-Oct-13 0
CBCPHPH-0310 FORM/REINFORCE/FINISH HOUSEKEEPING PADS - PENT LVL CBC 7 7 0% 03-Oct-13 11-Oct-13 03-Oct-13 11-Oct-13 0
CBCPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTLVL CBC 15 15 0% 05-Nov-13 29-Nov-13 05-Nov-13 29-Nov-13 0
CBCPHPH-1500 SET MECH EQUIPMENT - PENTLVL CBC 5 5 0% 14-Oct-13 18-Oct-13 14-Oct-13 18-Oct-13 0
CBCPHPH-1600 SET ELECTRICAL EQUIPMENT - PENTLVL CBC 10 10 0% 22-Oct-13 04-Nov-13 22-Oct-13 04-Nov-13 0
CBCL3L3-0540 ERECT EXTERIOR STUDS - LVL-3 CBC 15 15 0% 02-Dec-13 24-Dec-13 02-Dec-13 24-Dec-13 0
CBCSLSL-0320 DRILL/PLACE CAISSONS (balance @ bench) - SERV LVL CBC 15 15 0% 29-Mar-13 23-Apr-13 29-Mar-13 23-Apr-13 0
CBCESNE-0520 SHEATHING/VAPOR BARRIER - NORTH ELEV CBC 10 10 0% 30-Jan-14 14-Feb-14 30-Jan-14 14-Feb-14 0
CBCESEE-0520 SHEATHING/VAPOR BARRIER - EAST ELEV CBC 5 5 0% 10-Mar-14 17-Mar-14 10-Mar-14 17-Mar-14 0
CBCESWE-0520 SHEATHING/VAPOR BARRIER - WEST ELEV CBC 5 5 0% 17-Feb-14 21-Feb-14 17-Feb-14 21-Feb-14 0
CBCESSE-0520 SHEATHING/VAPOR BARRIER - SOUTH ELEV CBC 10 10 0% 24-Feb-14 07-Mar-14 24-Feb-14 07-Mar-14 0
CBCCOCO-1599 BUILDING FLUSH - CBC 20 20 0% 07-Feb-15 26-Feb-15 07-Feb-15 26-Feb-15 0
CBCCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - CBC 35 35 0% 10-Oct-14 02-Dec-14 10-Oct-14 02-Dec-14 0
CBCCOCO-1620 TEST & BALANCE - CBC 30 30 0% 03-Dec-14 15-Jan-15 03-Dec-14 15-Jan-15 0
CBCCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - CBC 20 20 0% 03-Dec-14 31-Dec-14 03-Dec-14 31-Dec-14 0
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
1 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 082
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBCCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - CBC 25 25 0% 02-Jan-15 06-Feb-15 02-Jan-15 06-Feb-15 0
CBCL1AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AREA B CBC 17 17 0% 28-May-14 19-Jun-14 28-May-... 19-Jun-14 0
CBCL1AB-0910 FRAMING/INWALL ROUGH - LVL-1 AREA B CBC 14 14 0% 09-Jun-14 26-Jun-14 09-Jun-14 26-Jun-14 0
CBCL1AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA B CBC 12 12 0% 08-Jul-14 23-Jul-14 08-Jul-14 23-Jul-14 0
CBCL1AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA B CBC 22 22 0% 22-Jul-14 20-Aug-14 22-Jul-14 20-Aug-14 0
CBCL1AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-1 AREA A CBC 18 18 0% 13-May-14 06-Jun-14 13-May-... 06-Jun-14 0
CBCL1AA-0910 FRAMING/INWALL ROUGH - LVL-1 AREA A CBC 14 14 0% 16-Jun-14 03-Jul-14 16-Jun-14 03-Jul-14 0
CBCL1AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA A CBC 13 13 0% 30-Jun-14 17-Jul-14 30-Jun-14 17-Jul-14 0
CBCL2AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-2 AREA A CBC 18 18 0% 15-Apr-14 08-May-14 15-Apr-14 08-May-14 0
CBCL2AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AREA B CBC 17 17 0% 29-Apr-14 21-May-14 29-Apr-14 21-May-14 0
CBCL3AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AREA B CBC 20 20 0% 01-Apr-14 28-Apr-14 01-Apr-14 28-Apr-14 0
CBCL3AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-3 AREA A CBC 20 20 0% 18-Mar-14 14-Apr-14 18-Mar-14 14-Apr-14 0
CBCSLEL-0910 FRAMING/INWALL ROUGH - SERV LVL CORR CBC 5 5 0% 21-Aug-14 27-Aug-14 21-Aug-14 27-Aug-14 0
CBCSLEL-0990 HANG/TAPE/FINISH/PAINT - SERV LVL CORR CBC 10 10 0% 28-Aug-14 11-Sep-14 28-Aug-14 11-Sep-14 0
CBCALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS CBC 15 15 0% 21-Aug-14 11-Sep-14 21-Aug-14 11-Sep-14 0
CBCALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS CBC 20 20 0% 12-Sep-14 09-Oct-14 12-Sep-14 09-Oct-14 0
SITSWTP-5620 VA PROVIDES CONSENT TO SUBCONTRACT - TEMP PARKING CBS 0 0 0% 19-Oct-11 19-Oct-11 0
SITSWTP-5720 VA REVIEW BID TABS - TEMP PARKING CBS 5 5 0% 13-Oct-11 19-Oct-11 13-Oct-11 19-Oct-11 0
AAAA-4630 VA PROVIDES CONSENT TO SUBCONTRACT - DESIGN ASSIST SUBCONTRACTORS 0 0 0% 06-Sep-11 06-Sep-11 0
RFP3-0100 VACATE CREDIT UNION 10 10 0% 01-Feb-12* 11-Feb-12 01-Feb-12 11-Feb-12 0
XXXXPVS-510 PVS (UNDERGROUND) TEMPORARY PARKING OVERALL DURATION 422 422 0% 31-Jan-14 28-Mar-15 31-Jan-14 28-Mar-15 0
DVAPOPO-3960 VA PROVIDE MED EQUIP COORDINATED CDS(gen imaging) - DAT 60 60 0% 04-Jan-13 01-Apr-13 04-Jan-13 01-Apr-13 0
DVAPOPO-4950 VA PROVIDE MED EQUIP COORDINATED CDS (pharmacy) - DAT 60 60 0% 04-Oct-12 03-Jan-13 04-Oct-12 03-Jan-13 0
AAAA-5600 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1A 0 0 0% 06-Sep-11 06-Sep-11 0
OSI-250 VA LICENSE AGREEMENTS WITH FRA/COA/UCD 0 0 0% 23-Nov-11* 23-Nov-11 0
AAAA-5590 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1 0 0 0% 06-Sep-11 06-Sep-11 0
COMMISS-1596 INTEGRATED SYSTEMS TEST - FULL CAMPUS 45 45 0% 12-Feb-15 28-Mar-15 12-Feb-15 28-Mar-15 0
CBSMIMI-3610 DOD/VA ACCEPT LEVELS 1,3 & 4 - CBS MILESTONE 0 0 0% 08-Feb-12* 08-Feb-12 0
ZZZZDAT-9999 FINISH DAT CONSTRUCTION (finish milestone) 0 0 0% 26-Feb-15 26-Feb-15 0
ZZZZRES-9999 FINISH RES CONSTRUCTION (finish milestone) 0 0 0% 03-Oct-15 03-Oct-15 0
ZZZZPVS-9999 FINISH PVS CONSTRUCTION (finish milestone) 0 0 0% 30-Jan-14 30-Jan-14 0
ZZZZZZZ-10009 CAMPUS SUBSTANTIAL COMPLETION LESS THE RESEARCH BUILDING (finish milestone) 0 0 0% 28-Mar-15* 28-Mar-15 0
AAAA-1010 NTP FOR CONSTRUCTION 0 0 0% 06-Sep-11* 06-Sep-11 0
ZZZZCBC-9999 FINISH CBC CONSTRUCTION (finish milestone) 0 0 0% 26-Feb-15 26-Feb-15 0
XXXXPVS-0500 PVS OVERALL DURATION 724 724 0% 06-Feb-12 30-Jan-14 22-Jun-12 30-Jan-14 0
XXXXDAT-0500 DAT OVERALL DURATION 1113 1113 0% 10-Feb-12 26-Feb-15 21-Feb-12 26-Feb-15 0
XXXXRES-0500 RES OVERALL DURATION 611 611 0% 31-Jan-14 03-Oct-15 07-Apr-14 03-Oct-15 0
XXXCAMP-1600 COMMISSION - FULL CAMPUS 315 315 0% 24-Dec-13 27-Mar-15 24-Dec-13 27-Mar-15 0
XXXXCBC-0500 CBC OVERALL DURATION 961 961 0% 10-Jul-12 26-Feb-15 19-Feb-13 26-Feb-15 0
XXXXRES-500 RES TEMPORARY PARKING OVERALL DURATION 722 722 0% 09-Feb-12 30-Jan-14 09-Feb-12 30-Jan-14 0
EEEEPVS-0000 PVS BLDG AVAILABLE FOR ENERGIZE 0 0 0% 17-Oct-13 17-Oct-13 0
STR1-4260 MOBILIZE EXCAVATOR STR-1 10 10 0% 27-Dec-11 10-Jan-12 27-Dec-11 10-Jan-12 0
STR1-5450 FABRICATE SHORING MATERIALS STR-1 10 10 0% 27-Dec-11 10-Jan-12 27-Dec-11 10-Jan-12 0
STR1-5410 KT APPROVE SHOP DRAWINGS FOR SHORING STR-1 30 30 0% 09-Nov-11 23-Dec-11 09-Nov-11 23-Dec-11 0
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
2 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 083
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
STR1-5420 AWARD SHORING CONTRACT 20 20 0% 07-Sep-11 04-Oct-11 07-Sep-11 04-Oct-11 0
STR1-5430 PREPARE/SUBMIT SHOP DRAWINGS FOR SHORING STR-1 20 20 0% 12-Oct-11 08-Nov-11 12-Oct-11 08-Nov-11 0
STR1-5440 MATERIALS ARRIVE ON SITE STR-1 0 0 0% 10-Jan-12 10-Jan-12 0
SITSWTP-5550 KT DESIGN TEMP PARKING CBS 15 15 0% 03-Nov-11 28-Nov-11 03-Nov-11 28-Nov-11 0
SITSWTP-4440 AWARD SUBCONTRACTS -TEMP PARKING CBS 10 10 0% 20-Oct-11 02-Nov-11 20-Oct-11 02-Nov-11 0
SITSWTP-4450 PREPARE/SUBMIT SHOP DRAWINGS - TEMP PARKING CBS 14 14 0% 29-Nov-11 16-Dec-11 29-Nov-11 16-Dec-11 0
SITSWTP-4470 MATERIAL PROCUREMENT - TEMP PARKING CBS 8 8 0% 04-Jan-12 13-Jan-12 04-Jan-12 13-Jan-12 0
SITSWTP-4880 KT REVIEWS SHOP DRAWINGS - TEMP PARKING CBS 10 10 0% 19-Dec-11 03-Jan-12 19-Dec-11 03-Jan-12 0
SITSWTP-5230 SUBCONTRACTOR PRICING - TEMP PARKING CBS 15 15 0% 07-Sep-11 27-Sep-11 07-Sep-11 27-Sep-11 0
SITSWTP-5700 PREPARE BID TABS - TEMP PARKING CBS 10 10 0% 28-Sep-11 12-Oct-11 28-Sep-11 12-Oct-11 0
W-OSI-5610 FRA/COA APPROVE WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 20 20 0% 28-Nov-11 23-Dec-11 28-Nov-11 23-Dec-11 0
CLC-3610 100% CD DESIGN COMPLETION - CLC 0 0 0% 27-Apr-12* 27-Apr-12 0
PVSALAL-0556 ERECT STAIRS ST2 - ALL LVLS PVS 20 20 0% 18-Apr-13 15-May-13 18-Apr-13 15-May-13 0
PVSALAL-0557 ERECT STAIRS ST3 - ALL LVLS PVS 20 20 0% 30-Apr-13 28-May-13 30-Apr-13 28-May-13 0
PVSALAL-1400 INSTALL ELEVATOR PGE15/PGE16X - ALL LVLS PVS 60 60 0% 04-Oct-13 02-Jan-14 04-Oct-13 02-Jan-14 0
PVSALAL-0555 ERECT STAIRS ST1 - ALL LVLS PVS 20 20 0% 08-Apr-13 03-May-13 08-Apr-13 03-May-13 0
PVSINP1-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-3 PVS 30 30 0% 29-May-13 10-Jul-13 29-May-... 10-Jul-13 0
PVSINP2-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-2 PVS 30 30 0% 26-Jun-13 07-Aug-13 26-Jun-13 07-Aug-13 0
PVSINP3-1620 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-1 PVS 30 30 0% 25-Jul-13 05-Sep-13 25-Jul-13 05-Sep-13 0
PVSINP3-0990 GARAGE FINISHES - PKG LVL-1 PVS 30 30 0% 06-Sep-13 17-Oct-13 06-Sep-13 17-Oct-13 0
PVSP1AA-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA A PVS 10 10 0% 10-Dec-12 24-Dec-12 10-Dec-12 24-Dec-12 0
PVSP1AA-1641 START-UP ELECTRICAL SYSTEMS (pvs/con) - PKG LVL-1 AREA A PVS 30 30 0% 18-Oct-13 03-Dec-13 18-Oct-13 03-Dec-13 0
PVSP1AD-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA D PVS 10 10 0% 03-Jan-13 17-Jan-13 03-Jan-13 17-Jan-13 0
PVSP1AB-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA B PVS 10 10 0% 17-Dec-12 02-Jan-13 17-Dec-12 02-Jan-13 0
PVSP1AC-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA C PVS 10 10 0% 26-Dec-12 09-Jan-13 26-Dec-12 09-Jan-13 0
PVSP0AE-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA E PVS 10 10 0% 11-Mar-13 25-Mar-13 11-Mar-13 25-Mar-13 0
PVSP0AA-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA A PVS 10 10 0% 18-Jan-13 01-Feb-13 18-Jan-13 01-Feb-13 0
PVSP0AF-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA F PVS 10 10 0% 21-Mar-13 05-Apr-13 21-Mar-13 05-Apr-13 0
PVSP0AC-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA C PVS 10 10 0% 12-Feb-13 27-Feb-13 12-Feb-13 27-Feb-13 0
PVSP0AD-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA D PVS 10 10 0% 26-Feb-13 12-Mar-13 26-Feb-13 12-Mar-13 0
PVSP0AB-0333 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA B PVS 10 10 0% 31-Jan-13 14-Feb-13 31-Jan-13 14-Feb-13 0
PVSP2AE-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA E PVS 10 10 0% 10-Dec-12 24-Dec-12 10-Dec-12 24-Dec-12 0
PVSP2AB-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA B PVS 10 10 0% 14-Nov-12 29-Nov-12 14-Nov-12 29-Nov-12 0
PVSP2AD-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA D PVS 10 10 0% 30-Nov-12 14-Dec-12 30-Nov-12 14-Dec-12 0
PVSP2AA-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA A PVS 12 12 0% 05-Nov-12 23-Nov-12 05-Nov-12 23-Nov-12 0
PVSP2AC-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA C PVS 10 10 0% 21-Nov-12 07-Dec-12 21-Nov-12 07-Dec-12 0
PVSALCO-1592 TEST & BALANCE - ALL LVLS PVS 20 20 0% 24-Dec-13 12-Jan-14 24-Dec-13 12-Jan-14 0
PVSALCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS PVS 10 10 0% 24-Dec-13 08-Jan-14 24-Dec-13 08-Jan-14 0
PVSALCO-1596 FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS PVS 15 15 0% 09-Jan-14 30-Jan-14 09-Jan-14 30-Jan-14 0
DATL1L1-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-1 DAT 5 5 0% 10-Aug-12 17-Aug-12 10-Aug-12 17-Aug-12 0
DATL1L1-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-1 DAT 5 5 0% 20-Aug-12 27-Aug-12 20-Aug-12 27-Aug-12 0
DATL1L1-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-1 DAT 15 15 0% 11-Jun-12 05-Jul-12 11-Jun-12 05-Jul-12 0
DATL1L1-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-1 DAT 5 5 0% 06-Jul-12 13-Jul-12 06-Jul-12 13-Jul-12 0
DATL1L1-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-1 DAT 5 5 0% 16-Jul-12 23-Jul-12 16-Jul-12 23-Jul-12 0
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
3 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 084
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL1L1-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-1 DAT 10 10 0% 24-Jul-12 09-Aug-12 24-Jul-12 09-Aug-12 0
DATPGPG-0320 DRILL/PLACE CAISSONS - PIPE GALLERY DAT 15 15 0% 10-Feb-12 05-Mar-12 10-Feb-12 05-Mar-12 0
DATPGPG-0380 FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY DAT 5 5 0% 17-Apr-12 24-Apr-12 17-Apr-12 24-Apr-12 0
DATPGPG-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PIPE GALLERY DAT 25 25 0% 11-Jan-12 09-Feb-12 11-Jan-12 09-Feb-12 0
DATPGPG-3110 SET/BACKFILL DUCTBANKS - PIPE GALLERY DAT 7 7 0% 03-Apr-12 16-Apr-12 03-Apr-12 16-Apr-12 0
DATPGPG-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY DAT 27 27 0% 21-Feb-12 02-Apr-12 21-Feb-12 02-Apr-12 0
DATPGPG-3200 UNDERSLAB UTILITIES - PIPE GALLERY DAT 7 7 0% 03-Apr-12 16-Apr-12 03-Apr-12 16-Apr-12 0
DATPGPG-3210 BACKFILL FOUNDATION WALLS (INTERIOR) - PIPE GALLERY DAT 5 5 0% 24-May-12 31-May-12 24-May-... 31-May-12 0
DATSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE (AREA C) - SERV LVL DAT 15 15 0% 15-May-12 08-Jun-12 15-May-... 08-Jun-12 0
DATSLSL-0322 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - SERV LVL DAT 15 15 0% 26-Apr-12 22-May-12 26-Apr-12 22-May-12 0
DATSLSL-3210 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - SERV LVL DAT 10 10 0% 24-May-12 08-Jun-12 24-May-... 08-Jun-12 0
DATSLIL-1567 ERECT INTER STEEL/TOPPING (AREA F) - SERV LVL INTER LVL DAT 15 15 0% 09-Jan-13 31-Jan-13 09-Jan-13 31-Jan-13 0
DATSLIL-0510 ERECT INTER STEEL/TOPPING (AREA A) - SERV LVL INTER LVL DAT 15 15 0% 25-Jan-13 15-Feb-13 25-Jan-13 15-Feb-13 0
DATSLIL-1527 ERECT INTER STEEL/TOPPING (AREA B) - SERV LVL INTER LVL DAT 15 15 0% 08-Feb-13 04-Mar-13 08-Feb-13 04-Mar-13 0
DATSLIL-1537 ERECT INTER STEEL/TOPPING (AREA C) - SERV LVL INTER LVL DAT 15 15 0% 20-Nov-12 13-Dec-12 20-Nov-12 13-Dec-12 0
DATSLIL-1547 ERECT INTER STEEL/TOPPING (AREA D) - SERV LVL INTER LVL DAT 15 15 0% 07-Dec-12 31-Dec-12 07-Dec-12 31-Dec-12 0
DATSLIL-1557 ERECT INTER STEEL/TOPPING (AREA E) - SERV LVL INTER LVL DAT 15 15 0% 24-Dec-12 15-Jan-13 24-Dec-12 15-Jan-13 0
DATPHPH-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - PENT DAT 5 5 0% 13-Nov-12 19-Nov-12 13-Nov-12 19-Nov-12 0
DATL3L3-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-3 DAT 5 5 0% 25-Oct-12 01-Nov-12 25-Oct-12 01-Nov-12 0
DATL3L3-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-3 DAT 5 5 0% 24-Sep-12 01-Oct-12 24-Sep-12 01-Oct-12 0
DATL3L3-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-3 DAT 5 5 0% 02-Oct-12 08-Oct-12 02-Oct-12 08-Oct-12 0
DATL3L3-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-3 DAT 5 5 0% 09-Oct-12 16-Oct-12 09-Oct-12 16-Oct-12 0
DATL3L3-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-3 DAT 5 5 0% 18-Oct-12 24-Oct-12 18-Oct-12 24-Oct-12 0
DATL3L3-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-3 DAT 5 5 0% 02-Nov-12 09-Nov-12 02-Nov-12 09-Nov-12 0
DATL2L2-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-2 DAT 5 5 0% 06-Sep-12 13-Sep-12 06-Sep-12 13-Sep-12 0
DATL2L2-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-2 DAT 5 5 0% 14-Sep-12 21-Sep-12 14-Sep-12 21-Sep-12 0
DATL2L2-0330 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-2 DAT 5 5 0% 28-Aug-12 05-Sep-12 28-Aug-12 05-Sep-12 0
DATL2L2-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-2 DAT 5 5 0% 06-Sep-12 13-Sep-12 06-Sep-12 13-Sep-12 0
DATL2L2-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-2 DAT 5 5 0% 14-Sep-12 21-Sep-12 14-Sep-12 21-Sep-12 0
DATL2L2-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-2 DAT 5 5 0% 28-Aug-12 05-Sep-12 28-Aug-12 05-Sep-12 0
DATALCL-1592 TEST & BALANCE - DAT 60 60 0% 17-Oct-14 15-Jan-15 17-Oct-14 15-Jan-15 0
DATALCL-1599 BUILDING FLUSH - DAT 20 20 0% 07-Feb-15 26-Feb-15 07-Feb-15 26-Feb-15 0
DATALCL-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - DAT 45 45 0% 17-Oct-14 23-Dec-14 17-Oct-14 23-Dec-14 0
DATALCL-1596 FUNCTIONAL TESTING/CORRECTIONS - DAT 45 45 0% 03-Dec-14 06-Feb-15 03-Dec-14 06-Feb-15 0
DATL1NM-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 NUC MED DAT 20 20 0% 19-Nov-13 17-Dec-13 19-Nov-13 17-Dec-13 0
DATL1NM-0910 FRAMING/INWALL ROUGH - LVL-1 NUC MED DAT 25 25 0% 27-Nov-13 02-Jan-14 27-Nov-13 02-Jan-14 0
DATL1NM-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 NUC MED DAT 20 20 0% 18-Dec-13 16-Jan-14 18-Dec-13 16-Jan-14 0
DATL1NM-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NUC MED DAT 65 65 0% 10-Jan-14 14-Apr-14 10-Jan-14 14-Apr-14 0
DATL1RO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 RAD OFFICES DAT 40 40 0% 08-Apr-14 03-Jun-14 08-Apr-14 03-Jun-14 0
DATL1PA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 PRE-ADMIT DAT 30 30 0% 04-Oct-13 18-Nov-13 04-Oct-13 18-Nov-13 0
DATL1PA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PRE-ADMIT DAT 55 55 0% 25-Feb-14 12-May-14 25-Feb-14 12-May-14 0
DATL1IL-0400 ROUGH-IN MEP/FIRE PROTECTION (GEN RADIOLOGY) (AHU4) - LVL-1 INTER LVL DAT 55 55 0% 26-Jun-13 12-Sep-13 26-Jun-13 12-Sep-13 0
DATL1IL-0100 ROUGH-IN MEP/FIRE PROTECTION (PRE ADMIN) (AHU1) - LVL-1 INTER LVL DAT 50 50 0% 25-Jul-13 03-Oct-13 25-Jul-13 03-Oct-13 0
DATL2CA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CARDIO DAT 55 55 0% 20-May-14 06-Aug-14 20-May-... 06-Aug-14 0
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
4 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 085
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL2SL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SLEEP DAT 45 45 0% 02-Jul-14 04-Sep-14 02-Jul-14 04-Sep-14 0
DATL3OR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 ORS DAT 75 75 0% 12-Sep-14 31-Dec-14 12-Sep-14 31-Dec-14 0
DATL3CA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CATH LABS DAT 65 65 0% 14-Aug-14 17-Nov-14 14-Aug-14 17-Nov-14 0
DATSLIL-0700 ROUGH-IN MEP/FIRE PROTECTION (STERILIZATION) (AHU7) - SERV LVL INTER LVL DAT 45 45 0% 30-Apr-13 02-Jul-13 30-Apr-13 02-Jul-13 0
DATSLIL-1800 ROUGH-IN MEP/FIRE PROTECTION (EMER MGMNT) (AHU18) - SERV LVL INTER LVL DAT 45 45 0% 05-Mar-13 06-May-13 05-Mar-13 06-May-13 0
DATSLIL-1900 ROUGH-IN MEP/FIRE PROTECTION (SHELL) (AHU19) - SERV LVL INTER LVL DAT 45 45 0% 29-May-13 31-Jul-13 29-May-... 31-Jul-13 0
DATSLIL-0200 ROUGH-IN MEP/FIRE PROTECTION (PHARMACY) (AHU2) - SERV LVL INTER LVL DAT 45 45 0% 02-Apr-13 04-Jun-13 02-Apr-13 04-Jun-13 0
SITSWTP-20 INSTALL UTILITIES - TEMP PARKING 10 10 0% 17-Jan-12 30-Jan-12 17-Jan-12 30-Jan-12 0
SITSWTP-28 STRIPE PARKING LOT & INSTALL FINISHES- TEMP PARKING 3 3 0% 06-Feb-12 08-Feb-12 06-Feb-12 08-Feb-12 0
SITSWTP-07800 PLACE CURB/GUTTER/SIDEWALK/PARKING LOT - TEMP PARKING 7 7 0% 26-Jan-12 03-Feb-12 26-Jan-12 03-Feb-12 0
SITSWSW-0102 SHORING SUB COORDINATE WITH DESIGN - POTHOLING 5 5 0% 05-Oct-11 11-Oct-11 05-Oct-11 11-Oct-11 0
SITSWBW-278 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - INTERSEC WHEELING ST. 20 20 0% 15-Apr-13 14-May-13 15-Apr-13 14-May-13 0
SITSWBW-298 DEMO/GRADING - SOUTH WHEELING ST. 15 15 0% 23-May-13 17-Jun-13 23-May-... 17-Jun-13 0
SITSWBW-308 INSTALL REMAINING UTILITIES - SOUTH WHEELING ST. 25 25 0% 18-Jun-13 30-Jul-13 18-Jun-13 30-Jul-13 0
SITSWBW-288 PLACE EROSION PROTECTION/TRAFFIC CONTROL - SOUTH WHEELING ST. 4 4 0% 16-May-13 21-May-13 16-May-... 21-May-13 0
ZZZZZZZ-10019 CAMPUS FINAL COMPLETION (finish milestone) 0 0 0% 03-Oct-15* 03-Oct-15 0
HOITCTC-0102 ERECT TOWER CRANE #2 (PVS) 10 10 0% 23-Oct-12 03-Nov-12 24-Oct-12 03-Nov-12 0
ZZZZWS-9999 NEW WATERLINE COMPLETE @ WHEELING ST (finish milestone) 0 0 0% 30-Jan-12 30-Jan-12 0
PVSSWSW-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PVS SITEWORK 115 115 0% 06-Feb-12 21-Jun-12 07-Feb-12 21-Jun-12 0
PVSSWSW-3210 RELOCATE CBS ROOF DRAIN - PVS SITEWORK 10 10 0% 23-Jan-12 06-Feb-12 24-Jan-12 06-Feb-12 0
PVSSWSW-3130 DRIVE SOLDIER PILES - PVS SITEWORK 10 10 0% 23-Jan-12 06-Feb-12 24-Jan-12 06-Feb-12 0
PVSP3AA-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA A PVS 14 14 0% 21-Jun-12 16-Jul-12 22-Jun-12 16-Jul-12 0
PVSP3AE-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA E PVS 14 14 0% 16-Jul-12 09-Aug-12 17-Jul-12 09-Aug-12 0
PVSP3AD-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA D PVS 14 14 0% 21-Jun-12 16-Jul-12 22-Jun-12 16-Jul-12 0
PVSP3AF-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA F PVS 14 14 0% 09-Aug-12 04-Sep-12 10-Aug-12 04-Sep-12 0
PVSP3AF-0330 FORM/PLACE TOWER CRANE #2 BASE - (PVS) 35 35 0% 24-Aug-12 23-Oct-12 27-Aug-12 23-Oct-12 0
SITWSSW-288 DEMO/GRADING - WHEELING ST. 5 5 0% 28-Dec-11 05-Jan-12 29-Dec-11 05-Jan-12 0
SITWSSW-328 PLACE EROSION PROTECTION/TRAFFIC CONTROL - WHEELING ST. 2 2 0% 23-Dec-11 28-Dec-11 27-Dec-11 28-Dec-11 0
SITWSSW-0205 INSTALL/TEST NEW WATERLINE - WHEELING ST. 15 15 0% 05-Jan-12 30-Jan-12 06-Jan-12 30-Jan-12 0
PVNSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL PVN 30 30 0% 17-Aug-13 21-Sep-13 19-Aug-13 23-Sep-13 1
PVNSLDO-0350 POUR PIER CAPS - SERV LVL DOCK PVN 10 10 0% 12-Nov-13 26-Nov-13 13-Nov-13 28-Nov-13 1
PVNSLDO-0390 FORM/PLACE COLUMNS - SERV LVL DOCK PVN 10 10 0% 15-Nov-13 02-Dec-13 18-Nov-13 03-Dec-13 1
PVNSLDO-0320 DRILL/PLACE CAISSONS - SERV LVL DOCK PVN 10 10 0% 23-Sep-13 07-Oct-13 24-Sep-13 08-Oct-13 1
PVNSLDO-0322 FORM/PLACE FOUNDATION WALLS/ELEVATOR PITS - SERV LVL DOCK PVN 45 45 0% 08-Oct-13 20-Dec-13 09-Oct-13 23-Dec-13 1
PVNSLPK-0344 FORM/PLACE SOG/EQUIPMENT PADS - SERV LVL PARK PVN 20 20 0% 23-Jan-14 20-Feb-14 24-Jan-14 21-Feb-14 1
PVNSLPK-1676 DRILL/PLACE BALANCE OF CAISSONS - SERV LVL PARK PVN 5 5 0% 23-Jan-14 29-Jan-14 24-Jan-14 30-Jan-14 1
PVNSLPK-0245 BACKFILL DOCK FOUNDATION WALLS - SERV LVL PARK PVN 10 10 0% 07-Jan-14 22-Jan-14 08-Jan-14 23-Jan-14 1
PVNSLDO-0560 ERECT STRUCTURAL STEEL/CORES/ROOF - SERV LVL DOCK PVN 25 25 0% 14-Aug-14 25-Sep-14 15-Aug-14 26-Sep-14 1
PVNSLDO-0366 FORM/PLACE/TENSION DOCK LID - SERV LVL DOCK PVN 21 21 0% 03-Dec-13 06-Jan-14 05-Dec-13 07-Jan-14 1
PVNALAL-0310 FORM/PLACE/TENSION DECKS - LVLS 1-5 PVN 100 100 0% 21-Feb-14 12-Aug-14 24-Feb-14 14-Aug-14 1
PVNESES-750 INSTALL CURTAIN WALL @ ELEVATOR/STAIR CORE - ALL ELEVATIONS PVN 25 25 0% 26-Sep-14 04-Nov-14 29-Sep-14 06-Nov-14 1
CBSADAL-2410 STEEL STAIRS - ALL LVLS ADD CBS 10 10 0% 14-Nov-11 29-Nov-11 15-Nov-11 30-Nov-11 1
CBSSWSW-4140 RELOCATE FIRE DEPARTMENT CONNECTION - SITEWORK CBS 7 7 0% 26-Jul-11 03-Aug-11 27-Jul-11 04-Aug-11 1
CBSSTST-4180 APPLY FIREPROOFING - CBS - STRUCTURE CBS 6 6 0% 30-Nov-11 06-Dec-11 01-Dec-11 07-Dec-11 1
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
5 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 086
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBSSTST-4170 PLACE/FINISH COMD AT ADDITION - CBS - STRUCTURE CBS 8 8 0% 19-Nov-11 29-Nov-11 21-Nov-11 30-Nov-11 1
CBSRLRL-3540 NEW ADDITION ROOFING - ROOF CBS 10 10 0% 06-Jan-12 20-Jan-12 09-Jan-12 23-Jan-12 1
CBSRLRL-3560 LIGHTNING PROTECTION - ROOF CBS 5 5 0% 23-Jan-12 27-Jan-12 24-Jan-12 30-Jan-12 1
CBSL1L1-3290 FIRE SPRINKLER ROUGH-IN - LVL-1 CBS 5 5 0% 22-Aug-11 26-Aug-11 23-Aug-11 27-Aug-11 1
CBSL1L1-3300 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-1 CBS 10 10 0% 27-Aug-11 08-Sep-11 29-Aug-11 09-Sep-11 1
CBSL1L1-3310 FRAMING - LVL-1 CBS 10 10 0% 27-Oct-11 07-Nov-11 28-Oct-11 08-Nov-11 1
CBSL1L1-3320 WALL ROUGH-IN - LVL-1 CBS 5 5 0% 05-Nov-11 10-Nov-11 07-Nov-11 12-Nov-11 1
CBSL1L1-3330 DRYWALL / FINISH - LVL-1 CBS 15 15 0% 12-Nov-11 30-Nov-11 14-Nov-11 01-Dec-11 1
CBSL1L1-3340 INTERIOR PAINT - LVL-1 CBS 8 8 0% 01-Dec-11 09-Dec-11 02-Dec-11 10-Dec-11 1
CBSL1L1-3350 CEILING - LVL-1 CBS 10 10 0% 10-Dec-11 21-Dec-11 12-Dec-11 22-Dec-11 1
CBSL1L1-3360 MILLWORK - LVL-1 CBS 10 10 0% 22-Dec-11 04-Jan-12 23-Dec-11 05-Jan-12 1
CBSL1L1-3370 FLOORING - LVL-1 CBS 10 10 0% 05-Jan-12 17-Jan-12 06-Jan-12 18-Jan-12 1
CBSL1L1-3380 MEP TRIMOUT - LVL-1 CBS 10 10 0% 18-Jan-12 28-Jan-12 19-Jan-12 30-Jan-12 1
CBSL1L1-3400 PUNCHLIST - LVL-1 CBS 8 8 0% 30-Jan-12 07-Feb-12 31-Jan-12 08-Feb-12 1
CBSL1L1-3303 NEW ELECTRICAL ROOM ROUGH-IN - LVL-1 CBS 20 20 0% 09-Sep-11 01-Oct-11 10-Sep-11 03-Oct-11 1
CBSL1L1-3307 NEW ELECTRICAL ROOM FIT-OUT - LVL-1 CBS 20 20 0% 03-Oct-11 26-Oct-11 04-Oct-11 27-Oct-11 1
CBSL1L1-4000 TEST AND BALANCE - LVL-1 CBS 5 5 0% 30-Jan-12 03-Feb-12 31-Jan-12 04-Feb-12 1
CBSINL4-2490 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-4 CBS 15 15 0% 04-Aug-11 20-Aug-11 05-Aug-11 22-Aug-11 1
CBSINL4-2500 FIRE SPRINKLER ROUGH-IN - LVL-4 CBS 10 10 0% 22-Aug-11 01-Sep-11 23-Aug-11 02-Sep-11 1
CBSINL4-2510 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-4 CBS 10 10 0% 02-Sep-11 14-Sep-11 03-Sep-11 15-Sep-11 1
CBSINL4-2520 FRAMING - LVL-4 CBS 10 10 0% 15-Sep-11 26-Sep-11 16-Sep-11 27-Sep-11 1
CBSINL4-2530 WALL ROUGH-IN - LVL-4 CBS 20 20 0% 27-Sep-11 20-Oct-11 28-Sep-11 21-Oct-11 1
CBSINL4-2540 DRYWALL / FINISH - LVL-4 CBS 15 15 0% 21-Oct-11 07-Nov-11 22-Oct-11 08-Nov-11 1
CBSINL4-2550 INTERIOR PAINT - LVL-4 CBS 10 10 0% 08-Nov-11 19-Nov-11 09-Nov-11 21-Nov-11 1
CBSINL4-2560 CEILING - LVL-4 CBS 12 12 0% 21-Nov-11 05-Dec-11 22-Nov-11 06-Dec-11 1
CBSINL4-2570 MILLWORK - LVL-4 CBS 10 10 0% 06-Dec-11 16-Dec-11 07-Dec-11 17-Dec-11 1
CBSINL4-2580 FLOORING - LVL-4 CBS 10 10 0% 17-Dec-11 29-Dec-11 19-Dec-11 30-Dec-11 1
CBSINL4-2590 MEP TRIMOUT - LVL-4 CBS 12 12 0% 30-Dec-11 13-Jan-12 31-Dec-11 14-Jan-12 1
CBSINL4-2600 HANDRAIL - LVL-4 CBS 10 10 0% 14-Jan-12 26-Jan-12 17-Jan-12 27-Jan-12 1
CBSSTST-2610 PUNCHLIST - LVL-4 CBS 10 10 0% 27-Jan-12 07-Feb-12 28-Jan-12 08-Feb-12 1
CBSL3L3-2770 FIRE SPRINKLER ROUGH-IN - LVL-3 CBS 5 5 0% 22-Aug-11 26-Aug-11 23-Aug-11 27-Aug-11 1
CBSL3L3-2880 PUNCHLIST - LVL-3 CBS 5 5 0% 02-Feb-12 07-Feb-12 03-Feb-12 08-Feb-12 1
CBSL3L3-2760 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-3 CBS 15 15 0% 04-Aug-11 20-Aug-11 05-Aug-11 22-Aug-11 1
CBSESES-3580 INSTALL TEMPORARY EXTERIOR SKIN @ NEW ADITION - SKINS CBS 20 20 0% 07-Dec-11 05-Jan-12 08-Dec-11 06-Jan-12 1
PVNALAL-1400 INSTALL ELEVATOR - ALL LVLS PVN 44 44 0% 05-Nov-14 09-Jan-15 07-Nov-14 13-Jan-15 2
PVNCOCO-1592 TEST & BALANCE - PVN 20 20 0% 12-Jan-15 10-Feb-15 14-Jan-15 12-Feb-15 2
PVNCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - PVN 15 15 0% 03-Feb-15 24-Feb-15 05-Feb-15 26-Feb-15 2
PVNCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - PVN 15 15 0% 12-Jan-15 02-Feb-15 14-Jan-15 04-Feb-15 2
CBSCOCO-4020 WHOLE BUILDING TEST AND BALANCE - ALL LVLS CBS 10 10 0% 19-Aug-15 01-Sep-15 21-Aug-15 03-Sep-15 2
CBSCOCO-2120 COMMISSIONING - ALL LVLS CBS 20 20 0% 02-Sep-15 30-Sep-15 04-Sep-15 02-Oct-15 2
CBSSTST-4160 ERECT STRUCTURAL STEEL AT ADDITION - CBS - STRUCTURE CBS 10 10 0% 31-Oct-11 10-Nov-11 02-Nov-11 14-Nov-11 2
CBSSTST-2350 STAIR CORE WALLS - STRUCTURE CBS 40 40 0% 13-Sep-11 29-Oct-11 15-Sep-11 01-Nov-11 2
CBSSTST-3760 EXCAVATION AND SHORING - STRUCTURE CBS 15 15 0% 01-Aug-11 17-Aug-11 03-Aug-11 19-Aug-11 2
CBSSTST-2340 STAIR CORE AND ELEVATOR FOUNDATION - STRUCTURE CBS 16 16 0% 24-Aug-11 12-Sep-11 26-Aug-11 14-Sep-11 2
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
6 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 087
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBSSTST-4040 DRILLED PIERS - CANOPY - STRUCTURE CBS 5 5 0% 26-Jul-11 30-Jul-11 28-Jul-11 02-Aug-11 2
CBSSTST-4050 DRILLED PIERS - BUILDING ADDITION - STRUCTURE CBS 5 5 0% 18-Aug-11 23-Aug-11 20-Aug-11 25-Aug-11 2
CBSSTST-2360 ELEVATOR CORE WALLS - STRUCTURE CBS 40 40 0% 13-Sep-11 29-Oct-11 15-Sep-11 01-Nov-11 2
CBSL2L2-3060 WALL ROUGH-IN - LVL-2 CBS 10 10 0% 22-May-15 05-Jun-15 27-May-... 09-Jun-15 2
CBSL2L2-3070 DRYWALL / FINISH - LVL-2 CBS 15 15 0% 08-Jun-15 26-Jun-15 10-Jun-15 30-Jun-15 2
CBSL2L2-3080 INTERIOR PAINT - LVL-2 CBS 6 6 0% 29-Jun-15 07-Jul-15 01-Jul-15 09-Jul-15 2
CBSL2L2-3090 CEILING GRID- LVL-2 CBS 7 7 0% 08-Jul-15 16-Jul-15 10-Jul-15 20-Jul-15 2
CBSL2L2-3100 MILLWORK - LVL-2 CBS 5 5 0% 17-Jul-15 23-Jul-15 21-Jul-15 27-Jul-15 2
CBSL2L2-3110 FLOORING - LVL-2 CBS 13 13 0% 13-Jul-15 29-Jul-15 15-Jul-15 31-Jul-15 2
CBSL2L2-3120 MEP TRIMOUT - LVL-2 CBS 6 6 0% 30-Jul-15 06-Aug-15 03-Aug-15 10-Aug-15 2
CBSL2L2-3140 PUNCHLIST - LVL-2 CBS 5 5 0% 12-Aug-15 18-Aug-15 14-Aug-15 20-Aug-15 2
CBSL2L2-3980 TEST AND BALANCE - LVL-2 CBS 3 3 0% 07-Aug-15 11-Aug-15 11-Aug-15 13-Aug-15 2
CBSL2L2-3020 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-2 CBS 10 10 0% 15-Apr-15 28-Apr-15 17-Apr-15 30-Apr-15 2
CBSL2L2-3030 FIRE SPRINKLER ROUGH-IN - LVL-2 CBS 5 5 0% 29-Apr-15 05-May-15 01-May-... 07-May-15 2
CBSL2L2-3040 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-2 CBS 5 5 0% 06-May-15 12-May-15 08-May-... 14-May-15 2
CBSL2L2-3050 FRAMING - LVL-2 CBS 12 12 0% 13-May-15 29-May-15 15-May-... 02-Jun-15 2
CBSDEIN-2470 LEVEL 2 DEMOLITION - INT DEMO CBS 3 3 0% 10-Apr-15 14-Apr-15 14-Apr-15 16-Apr-15 2
CBSDEIN-4100 LEVEL 2 SALVAGE - INT DEMO CBS 2 2 0% 03-Apr-15 06-Apr-15 07-Apr-15 08-Apr-15 2
CBSESES-4140 INSTALL EXTERIOR SKIN @ NEW ADITION - SKINS CBS 20 20 0% 07-Dec-11 05-Jan-12 09-Dec-11 09-Jan-12 2
ZZZZPVN-9999 FINISH PVN CONSTRUCTION (finish milestone) 0 0 0% 24-Feb-15 26-Feb-15 2
XXXXPVN-0500 PVN OVERALL DURATION 520 520 0% 23-Sep-13 24-Feb-15 09-Oct-13 26-Feb-15 2
SITWSSW-0288 SURVEYOR MAP/PROVIDE AS-BUILTS - POTHOLING 15 15 0% 12-Sep-11 05-Oct-11 15-Sep-11 07-Oct-11 2
SITSWSW-0150 LOCATE ALL UTILITIES - POTHOLING 10 10 0% 12-Sep-11 27-Sep-11 15-Sep-11 30-Sep-11 2
CONABHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- HIGH ROOF AR-B CON 14 14 0% 29-Aug-13 20-Sep-13 04-Sep-13 26-Sep-13 3
CONABHR-0510 FRAMING @ CLEARSTORY - HIGH ROOF AR-B CON 9 9 0% 13-Aug-13 27-Aug-13 19-Aug-13 03-Sep-13 3
CONABSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-B CON 26 26 0% 11-Jun-13 25-Jul-13 17-Jun-13 30-Jul-13 3
CONABSS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-B CON 10 10 0% 26-Jul-13 12-Aug-13 01-Aug-13 16-Aug-13 3
CONABL1-0330 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-B CON 30 30 0% 19-Mar-13 09-May-13 22-Mar-13 14-May-13 3
CONABL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-B CON 9 9 0% 10-May-13 24-May-13 16-May-... 30-May-13 3
CONABL1-0320 DRILL/PLACE CAISSONS (EAST BALANCE) - LVL-1 AR-B CON 9 9 0% 05-Apr-13 19-Apr-13 11-Apr-13 25-Apr-13 3
CONABL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-B CON 9 9 0% 28-May-13 10-Jun-13 31-May-... 14-Jun-13 3
CONABSL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-B CON 15 15 0% 27-Mar-12 23-Apr-12 02-Apr-12 27-Apr-12 3
CONABSL-3210 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-B CON 7 7 0% 15-Mar-12 26-Mar-12 20-Mar-12 30-Mar-12 3
IBNL3L3-0510 ERECT STRUCTURAL STEEL/DECK - LVL-3 IBN 15 15 0% 04-Feb-13 26-Feb-13 07-Feb-13 01-Mar-13 3
IBNL2L2-0510 ERECT STRUCTURAL STEEL/DECK - LVL-2 IBN 15 15 0% 10-Jan-13 01-Feb-13 15-Jan-13 06-Feb-13 3
IBNSLSL-0330 FORM/PLACE/PIER CAPS/TIE BEAMS/ELEV/ WALLS/CORES - SERV LVL IBN 110 110 0% 12-Jun-12 14-Dec-12 18-Jun-12 20-Dec-12 3
IBNSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL IBN 25 25 0% 27-Apr-12 11-Jun-12 04-May-... 15-Jun-12 3
IBNSLSL-0390 PERM DRAINS/BACKFILL - SERV LVL IBN 14 14 0% 14-Mar-13 04-Apr-13 19-Mar-13 09-Apr-13 3
IBNL1L1-0510 ERECT STRUCTURAL STEEL/DECK - LVL-1 IBN 15 15 0% 17-Dec-12 09-Jan-13 21-Dec-12 14-Jan-13 3
IBNL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 IBN 9 9 0% 27-Feb-13 12-Mar-13 04-Mar-13 18-Mar-13 3
CBSADL3-2980 FLOORING - LVL-3 ADD CBS 2 2 0% 28-Jan-12 30-Jan-12 01-Feb-12 02-Feb-12 3
CBSADL3-2990 MEP TRIMOUT - LVL-3 ADD CBS 2 2 0% 31-Jan-12 01-Feb-12 03-Feb-12 04-Feb-12 3
CBSADL3-3010 PUNCHLIST - LVL-3 ADD CBS 2 2 0% 03-Feb-12 04-Feb-12 07-Feb-12 08-Feb-12 3
CBSADL3-3970 TEST AND BALANCE - LVL-3 ADD CBS 1 1 0% 02-Feb-12 02-Feb-12 06-Feb-12 06-Feb-12 3
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
7 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 088
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBSADL2-3270 PUNCHLIST - LVL-2 ADD CBS 2 2 0% 03-Feb-12 04-Feb-12 07-Feb-12 08-Feb-12 3
CBSADL4-2680 DRYWALL / FINISH - LVL-4 ADD CBS 5 5 0% 06-Jan-12 11-Jan-12 10-Jan-12 14-Jan-12 3
CBSADL4-2690 INTERIOR PAINT - LVL-4 ADD CBS 3 3 0% 12-Jan-12 14-Jan-12 17-Jan-12 19-Jan-12 3
CBSADL4-2700 CEILING - LVL-4 ADD CBS 5 5 0% 17-Jan-12 21-Jan-12 20-Jan-12 25-Jan-12 3
CBSADL4-2720 FLOORING - LVL-4 ADD CBS 5 5 0% 23-Jan-12 27-Jan-12 26-Jan-12 31-Jan-12 3
CBSADL1-3530 PUNCHLIST - LVL-1 ADD CBS 3 3 0% 02-Feb-12 04-Feb-12 06-Feb-12 08-Feb-12 3
CBSRLRL-3570 NEW EXHAUST FANS - ROOF CBS 5 5 0% 23-Jan-12 27-Jan-12 26-Jan-12 01-Feb-12 3
CBSL3L3-2860 MEP TRIMOUT - LVL-3 CBS 10 10 0% 14-Jan-12 26-Jan-12 19-Jan-12 30-Jan-12 3
CBSL3L3-3960 TEST AND BALANCE - LVL-3 CBS 3 3 0% 27-Jan-12 30-Jan-12 31-Jan-12 02-Feb-12 3
ZZZZCBS-9999 FINISH CBS CONSTRUCTION (finish milestone) 0 0 0% 30-Sep-15 03-Oct-15 3
AAAA-1030 NTP FOR POTHOLING FOR WHEELING WATERLINE (start milestone) 0 0 0% 12-Sep-11 15-Sep-11 3
XXXXCBS-0500 CBS OVERALL DURATION 936 1528 0% 09-May-11A
30-Sep-15 09-May-... 03-Oct-15 3
ENCALAL-0510 ERECT STRUCTURAL STEEL/DECK (LEVEL 1(incl. deck) - PH ROOF) - ALL LEVELS ENC 20 20 0% 10-Aug-12 13-Sep-12 16-Aug-12 18-Sep-12 3
ENCALAL-1426 ERECT/DETAIL METAL DECK (LEVEL 2 - PH ROOF) - LVLS 2 - PH ROOF) ENC 10 10 0% 14-Sep-12 01-Oct-12 20-Sep-12 04-Oct-12 3
ENCPGPG-0320 DRILL/PLACE CAISSONS - PIPE GALLERY ENC 6 6 0% 05-Apr-12 16-Apr-12 10-Apr-12 20-Apr-12 3
ENCLRLR-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LOW ROOF ENC 10 10 0% 02-Oct-12 16-Oct-12 05-Oct-12 22-Oct-12 3
ENCL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 ENC 10 10 0% 14-Sep-12 01-Oct-12 20-Sep-12 04-Oct-12 3
ENCL1L1-0720 SPRAY ON FIREPROOFING - LVL-1 ENC 7 7 0% 18-Oct-12 26-Oct-12 23-Oct-12 01-Nov-12 3
ENCSLSL-0330 FORM/PLACE PIER CAPS/CORES/ WALLS/COLUMNS - SERV LVL ENC 60 60 0% 26-Apr-12 09-Aug-12 03-May-... 14-Aug-12 3
ENCSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL ENC 20 20 0% 17-Apr-12 22-May-12 23-Apr-12 29-May-12 3
DATSLSL-0340 FORM/PLACE TOWER CRANE #1 BASE (DAT & CON C/D) 35 35 0% 10-Feb-12 06-Apr-12 16-Feb-12 12-Apr-12 3
IBSPBPB-0320 DRILL/PLACE CAISSONS - PIPE BSMT IBS 25 25 0% 14-Mar-12 26-Apr-12 19-Mar-12 03-May-12 3
IBSPBPB-3130 DRIVE SOLDIER PILES - PIPE BSMT IBS 10 10 0% 12-Jan-12 26-Jan-12 18-Jan-12 31-Jan-12 3
CONAASL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-A CON 8 8 0% 27-Feb-12 06-Mar-12 02-Mar-12 10-Mar-12 4
CONABSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-B CON 8 8 0% 06-Mar-12 14-Mar-12 10-Mar-12 19-Mar-12 4
CONHBAC-1516 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-C CON 15 15 0% 15-Jan-14 05-Feb-14 22-Jan-14 12-Feb-14 4
CONHBAC-0910 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-C CON 15 15 0% 06-Feb-14 27-Feb-14 13-Feb-14 05-Mar-14 4
CONHBAC-0920 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-C CON 18 18 0% 28-Feb-14 25-Mar-14 06-Mar-14 31-Mar-14 4
CONHBAC-0990 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-C CON 15 15 0% 26-Mar-14 15-Apr-14 01-Apr-14 21-Apr-14 4
CONHBAC-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-C CON 10 10 0% 16-Apr-14 29-Apr-14 22-Apr-14 05-May-14 4
CONHBAC-8890 TEAR DOWN STAGE - HIGH BAY AR-C CON 7 7 0% 30-Apr-14 08-May-14 06-May-... 14-May-14 4
CONHBAE-0920 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-E CON 15 15 0% 23-Jun-14 14-Jul-14 27-Jun-14 18-Jul-14 4
CONHBAE-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-E CON 10 10 0% 05-Aug-14 18-Aug-14 11-Aug-14 22-Aug-14 4
CONHBAE-0990 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-E CON 15 15 0% 15-Jul-14 04-Aug-14 21-Jul-14 08-Aug-14 4
CONHBAE-1516 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-E CON 15 15 0% 09-May-14 30-May-14 15-May-... 05-Jun-14 4
CONHBAE-0910 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-E CON 15 15 0% 02-Jun-14 20-Jun-14 06-Jun-14 26-Jun-14 4
CONHBAA-1516 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-A CON 15 15 0% 23-Sep-13 11-Oct-13 27-Sep-13 17-Oct-13 4
CONHBAA-0910 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-A CON 15 15 0% 14-Oct-13 04-Nov-13 18-Oct-13 08-Nov-13 4
CONHBAA-0920 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-A CON 15 15 0% 05-Nov-13 27-Nov-13 12-Nov-13 03-Dec-13 4
CONHBAA-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH- HIGH BAY AR-A CON 10 10 0% 19-Dec-13 03-Jan-14 26-Dec-13 09-Jan-14 4
CONHBAA-0990 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-A CON 15 15 0% 28-Nov-13 18-Dec-13 04-Dec-13 24-Dec-13 4
CONHBAA-8890 TEAR DOWN STAGE - HIGH BAY AR-A CON 7 7 0% 06-Jan-14 14-Jan-14 10-Jan-14 21-Jan-14 4
CONL1AE-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-E CON 20 20 0% 19-Aug-14 16-Sep-14 25-Aug-14 22-Sep-14 4
CONL1DI-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D DINING CON 17 17 0% 08-Oct-14 31-Oct-14 14-Oct-14 06-Nov-14 4
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
8 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 089
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CONL1DI-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-D DINING CON 15 15 0% 24-Dec-14 15-Jan-15 31-Dec-14 22-Jan-15 4
CONL1DI-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D DINING CON 35 35 0% 03-Nov-14 23-Dec-14 07-Nov-14 30-Dec-14 4
CONL1DI-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 DINING CON 18 18 0% 19-Aug-14 12-Sep-14 25-Aug-14 18-Sep-14 4
CONL1DI-0910 FRAMING/INWALL ROUGH - LVL-1 AR-D DINING CON 17 17 0% 15-Sep-14 07-Oct-14 19-Sep-14 13-Oct-14 4
CONALCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - CON 20 20 0% 16-Jan-15 16-Feb-15 23-Jan-15 20-Feb-15 4
IBNSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL IBN 20 20 0% 21-Feb-12 14-Mar-12 25-Feb-12 19-Mar-12 4
CBSADL3-3000 HANDRAIL - LVL-3 ADD CBS 2 2 0% 31-Jan-12 01-Feb-12 04-Feb-12 06-Feb-12 4
CBSADL2-3240 FLOORING - LVL-2 ADD CBS 2 2 0% 28-Jan-12 30-Jan-12 02-Feb-12 03-Feb-12 4
CBSADL2-3250 MEP TRIMOUT - LVL-2 ADD CBS 2 2 0% 31-Jan-12 01-Feb-12 04-Feb-12 06-Feb-12 4
CBSADL2-3260 HANDRAIL - LVL-2 ADD CBS 2 2 0% 02-Feb-12 03-Feb-12 07-Feb-12 08-Feb-12 4
CBSADL4-3950 TEST AND BALANCE - LVL-4 ADD CBS 1 1 0% 28-Jan-12 28-Jan-12 02-Feb-12 02-Feb-12 4
CBSADL4-2750 PUNCHLIST - LVL-4 ADD CBS 5 5 0% 30-Jan-12 03-Feb-12 03-Feb-12 08-Feb-12 4
CBSADL4-2730 MEP TRIMOUT - LVL-4 ADD CBS 5 5 0% 23-Jan-12 27-Jan-12 27-Jan-12 01-Feb-12 4
CBS-0100 KT AND VA VACATE CBS LEVEL 2 10 10 0% 24-Mar-15 02-Apr-15 28-Mar-15 06-Apr-15 4
AAAA-5630 VA PROVIDES CONSENT TO SUBCONTRACT - TEMP REDIRECTION OF STORMWATER 0 0 0% 13-Oct-11 19-Oct-11 4
AAAA-5570 VA REVIEW/APPROVE TEMP REDIRECTION OF STORMWATER 5 5 0% 09-Nov-11 16-Nov-11 16-Nov-11 22-Nov-11 4
AAAA-5520 VA REVIEW BID TABS - TEMP REDIRECTION OF STORMWATER 2 2 0% 12-Oct-11 13-Oct-11 18-Oct-11 19-Oct-11 4
ZZZCAMP-1000 XCEL PROVIDE ENERGY TO ENC 0 0 0% 29-Aug-13 05-Sep-13 4
ENCPBPB-1606 START UP CAMPUS ELEC EQUIPMENT - FULL CAMPUS 30 30 0% 30-Aug-13 11-Oct-13 06-Sep-13 17-Oct-13 4
EEEEENC-0990 ENC BLDG AVAILABLE FOR ENERGIZE 0 0 0% 29-Aug-13 05-Sep-13 4
STR1-5490 PROCURE SHORING MATERIALS STR-1 50 50 0% 05-Oct-11 19-Dec-11 12-Oct-11 23-Dec-11 4
W-OSI-4450 PREPARE/SUBMIT SHOP DRAWINGS - WHEELING WATER 10 10 0% 05-Oct-11 19-Oct-11 12-Oct-11 25-Oct-11 4
W-OSI-4460 VA SUBMITTAL REVIEW - WHEELING WATER 20 20 0% 03-Nov-11 05-Dec-11 09-Nov-11 09-Dec-11 4
W-OSI-4470 MATERIAL PROCUREMENT - WHEELING WATER 10 10 0% 06-Dec-11 19-Dec-11 12-Dec-11 23-Dec-11 4
W-OSI-4480 MATERIALS ARRIVE - WHEELING WATER 0 0 0% 19-Dec-11 23-Dec-11 4
W-OSI-4490 KT REVIEWS SHOP DRAWINGS - WHEELING WATER 10 10 0% 20-Oct-11 02-Nov-11 26-Oct-11 08-Nov-11 4
W-OSI-5310 AWARD CONTRACT - WHEELING WATERLINE 20 20 0% 07-Sep-11 04-Oct-11 13-Sep-11 11-Oct-11 4
STR1-5730 INSTALL TEMP/TEMP REDIRECTION OF STORMWATER 20 20 0% 06-Dec-11 04-Jan-12 12-Dec-11 10-Jan-12 4
STR1-5560 SUBCONTRACTOR PRICING - TEMP REDIRECTION OF STORMWATER 15 15 0% 06-Sep-11 26-Sep-11 12-Sep-11 30-Sep-11 4
STR1-5580 PROCURE VAULT/PUMP FOR TEMP REDIRECTION OF STORMWATER 11 11 0% 17-Nov-11 05-Dec-11 23-Nov-11 09-Dec-11 4
STR1-5540 AWARD DESIGN CONTRACTOR FOR TEMP REDIRECTION OF STORMWATER 10 10 0% 14-Oct-11 27-Oct-11 20-Oct-11 02-Nov-11 4
STR1-5550 KT DESIGN TEMP REDIRECTION OF STORMWATER 8 8 0% 28-Oct-11 08-Nov-11 03-Nov-11 15-Nov-11 4
STR1-5570 PREPARE BID TABS - TEMP REDIRECTION OF STORMWATER 10 10 0% 27-Sep-11 11-Oct-11 03-Oct-11 17-Oct-11 4
ENCL1EL-1650 ROUGH-IN/CONNECT TRANSFORMERS - LVL-1 ELEC RMS ENC 210 210 0% 29-Oct-12 29-Aug-13 02-Nov-12 05-Sep-13 4
ENCL1EL-1660 ROUGH-IN/CONNECT SUBSTATION - LVL-1 ELEC RMS ENC 210 210 0% 29-Oct-12 29-Aug-13 02-Nov-12 05-Sep-13 4
ENCL1EL-1620 ROUGH-IN/CONNECT SWITCHGEAR - LVL-1 ELEC RMS ENC 210 210 0% 29-Oct-12 29-Aug-13 02-Nov-12 05-Sep-13 4
ENCL1EL-1640 ROUGH-IN/CONNECT GENERATORS - LVL-1 ELEC RMS ENC 210 210 0% 29-Oct-12 29-Aug-13 02-Nov-12 05-Sep-13 4
ENCPGPG-3100 MASS EXCAVATION/RECONDITIONING - PIPE GALLERY ENC 25 25 0% 07-Mar-12 04-Apr-12 12-Mar-12 09-Apr-12 4
PVSP2AA-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA A PVS 12 12 0% 26-Nov-12 13-Dec-12 03-Dec-12 20-Dec-12 4
IBSPBPB-3100 SHORING/MASS EXCAVATION/RECONDITIONING - PIPE BSMT IBS 28 28 0% 27-Jan-12 29-Feb-12 01-Feb-12 05-Mar-12 4
RESCOCL-1592 TEST & BALANCE - RES 20 20 0% 24-Jul-15 20-Aug-15 31-Jul-15 27-Aug-15 5
RESCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - RES 15 15 0% 24-Jul-15 13-Aug-15 31-Jul-15 20-Aug-15 5
RESCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - RES 20 20 0% 14-Aug-15 11-Sep-15 21-Aug-15 18-Sep-15 5
RESSLIL-0320 ERECT INTERSTITIAL STEEL/TOPPING (INCL CURE)- INTERSTITIAL LVL RES 15 15 0% 30-Oct-14 24-Nov-14 07-Nov-14 02-Dec-14 5
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
9 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 090
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CONALCO-1599 BUILDING FLUSH - ALL LVLS CON 35 35 0% 17-Feb-15 23-Mar-15 22-Feb-15 28-Mar-15 5
CBSADL2-3990 TEST AND BALANCE - LVL-2 ADD CBS 1 1 0% 02-Feb-12 02-Feb-12 08-Feb-12 08-Feb-12 5
CBSADL1-3510 MEP TRIMOUT - LVL-1 ADD CBS 2 2 0% 31-Jan-12 01-Feb-12 06-Feb-12 07-Feb-12 5
CBSADL1-3500 FLOORING - LVL-1 ADD CBS 2 2 0% 28-Jan-12 30-Jan-12 03-Feb-12 04-Feb-12 5
CBSADL1-4010 TEST AND BALANCE - LVL-1 ADD CBS 1 1 0% 02-Feb-12 02-Feb-12 08-Feb-12 08-Feb-12 5
CBSADL1-3520 HANDRAIL - LVL-1 ADD CBS 1 1 0% 02-Feb-12 02-Feb-12 08-Feb-12 08-Feb-12 5
CBSL3L3-2850 FLOORING - LVL-3 CBS 10 10 0% 30-Dec-11 11-Jan-12 06-Jan-12 18-Jan-12 5
ZZZZCON-9999 FINISH CON CONSTRUCTION (finish milestone) 0 0 0% 23-Mar-15 28-Mar-15 5
XXXXCON-0500 CON OVERALL DURATION 1064 1064 0% 24-Apr-12 23-Mar-15 22-Jun-12 28-Mar-15 5
DATPHPH-0340 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - PENT DAT 5 5 0% 20-Nov-12 27-Nov-12 29-Nov-12 06-Dec-12 5
DATALCL-9999 CREATE/COMPLETE FINAL PUNCHLIST - DAT 30 30 0% 17-Dec-14 30-Jan-15 24-Dec-14 06-Feb-15 5
DATALAL-0992 FINISH STAIR CORE (ST2) - ALL LVLS DAT 30 30 0% 18-Nov-14 31-Dec-14 26-Nov-14 08-Jan-15 5
DATALAL-0991 FINISH STAIR CORE (ST1) - ALL LVLS DAT 30 30 0% 18-Nov-14 31-Dec-14 26-Nov-14 08-Jan-15 5
DATALAL-0993 FINISH STAIR CORE (ST3) - ALL LVLS DAT 30 30 0% 10-Dec-14 23-Jan-15 17-Dec-14 30-Jan-15 5
DATALAL-0995 FINISH STAIR CORE (ST5) - ALL LVLS DAT 30 30 0% 10-Dec-14 23-Jan-15 17-Dec-14 30-Jan-15 5
SITSWTP-18 GRADING - TEMP PARKING 10 10 0% 20-Dec-11 05-Jan-12 29-Dec-11 13-Jan-12 5
IBNESNE-0870 INSTALL PRECAST PANELS - NORTH ELEV IBN 10 10 0% 27-Feb-13 14-Mar-13 08-Mar-13 22-Mar-13 6
IBNESNE-870 INSTALL STRIP WINDOWS - NORTH ELEV IBN 15 15 0% 15-Mar-13 08-Apr-13 25-Mar-13 18-Apr-13 6
IBNESNE-880 INSTALL METAL PANELS - NORTH ELEV IBN 15 15 0% 09-Apr-13 06-May-13 19-Apr-13 16-May-13 6
CBSADL3-2950 DRYWALL / FINISH - LVL-3 ADD CBS 5 5 0% 10-Jan-12 14-Jan-12 18-Jan-12 23-Jan-12 6
CBSADL2-3210 DRYWALL / FINISH - LVL-2 ADD CBS 5 5 0% 13-Jan-12 19-Jan-12 21-Jan-12 26-Jan-12 6
CBSADL2-3220 INTERIOR PAINT - LVL-2 ADD CBS 2 2 0% 20-Jan-12 21-Jan-12 27-Jan-12 28-Jan-12 6
CBSADL2-3230 CEILING - LVL-2 ADD CBS 3 3 0% 23-Jan-12 25-Jan-12 30-Jan-12 01-Feb-12 6
CBSADL4-2670 WALL ROUGH-IN - LVL-4 ADD CBS 4 4 0% 28-Dec-11 31-Dec-11 05-Jan-12 09-Jan-12 6
CBSADL4-2630 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL 4 ADD CBS 5 5 0% 07-Dec-11 12-Dec-11 14-Dec-11 19-Dec-11 6
CBSADL4-2640 FIRE SPRINKLER ROUGH-IN - LVL-4 ADD CBS 4 4 0% 13-Dec-11 16-Dec-11 20-Dec-11 23-Dec-11 6
CBSADL4-2650 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-4 ADD CBS 4 4 0% 17-Dec-11 21-Dec-11 24-Dec-11 29-Dec-11 6
CBSADL4-2660 FRAMING - LVL-4 ADD CBS 4 4 0% 22-Dec-11 27-Dec-11 30-Dec-11 04-Jan-12 6
CBSINL4-3940 TEST AND BALANCE - LVL-4 CBS 5 5 0% 14-Jan-12 20-Jan-12 23-Jan-12 27-Jan-12 6
SITSWTP-7800 JVT DESIGN COMPLETE - TEMP PARKING 0 0 0% 28-Nov-11 06-Dec-11 6
SITSWTP1-5530 VA REVIEW/APPROVE TEMP PARKING 15 15 0% 29-Nov-11 19-Dec-11 07-Dec-11 28-Dec-11 6
ENCSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK ENC 40 40 0% 13-Jun-14 21-Aug-14 24-Jun-14 02-Sep-14 6
ENCSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK ENC 45 45 0% 22-Aug-14 04-Nov-14 03-Sep-14 14-Nov-14 6
ENCSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK ENC 15 15 0% 24-Apr-14 19-May-14 05-May-... 30-May-14 6
ENCSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK ENC 20 20 0% 08-May-14 12-Jun-14 19-May-... 23-Jun-14 6
P-CBS-4440 SUBMITTAL REVIEW (interior steel) - CBS-1 30 11 63.33% 27-Jun-11 A 09-Aug-11 03-Aug-11 17-Aug-11 6
P-CBS-4450 MATERIAL PROCUREMENT (interior steel) - CBS-1 20 20 0% 10-Aug-11 07-Sep-11 18-Aug-11 15-Sep-11 6
P-CBS-4460 MATERIALS ARRIVE (interior steel) - CBS-1 0 0 0% 07-Sep-11 15-Sep-11 6
ENCTRTR-0750 APPLY WATERPROOFING - WATER TANK ENC 20 20 0% 08-Nov-13 11-Dec-13 19-Nov-13 20-Dec-13 6
ENCTSTS-3200 UNDERSLAB UTILITIES- WATER TANK ENC 15 15 0% 30-May-13 24-Jun-13 10-Jun-13 03-Jul-13 6
ENCTSTS-0380 FORM/PLACE/FINISH/TENSION SLAB ON GRADE - WATER TANK ENC 7 7 0% 25-Jun-13 05-Jul-13 05-Jul-13 16-Jul-13 6
ENCTSTS-3220 FORM/PLACE/FINISH/TENSION LID - WATER TANK ENC 53 53 0% 12-Aug-13 07-Nov-13 22-Aug-13 18-Nov-13 6
ENCTSTS-0390 FORM/PLACE/FINISH WALLS/COLUMNS/CURBS - WATER TANK ENC 20 20 0% 08-Jul-13 09-Aug-13 18-Jul-13 20-Aug-13 6
ENCFTFT-3200 INSTALL FUEL TANK PIPING - FUEL TANK ENC 25 25 0% 31-Jan-14 10-Mar-14 11-Feb-14 20-Mar-14 6
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
10 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 091
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ENCFTFT-0380 SET TANKS- FUEL TANK ENC 3 3 0% 28-Jan-14 30-Jan-14 05-Feb-14 07-Feb-14 6
ENCFTFT-0390 TEST FUEL TANKS - FUEL TANK ENC 5 5 0% 11-Mar-14 18-Mar-14 21-Mar-14 28-Mar-14 6
ENCFTFT-3220 BACKFILL - FUEL TANK ENC 20 20 0% 20-Mar-14 22-Apr-14 31-Mar-14 02-May-14 6
ENCFTFT-0378 FORM/PLACE/FINISH/TENSION SLAB ON GRADE - FUEL TANK ENC 18 18 0% 30-Dec-13 27-Jan-14 08-Jan-14 04-Feb-14 6
PVSP2AB-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA B PVS 12 12 0% 30-Nov-12 18-Dec-12 11-Dec-12 28-Dec-12 6
PVSP2AD-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA D PVS 12 12 0% 17-Dec-12 04-Jan-13 27-Dec-12 14-Jan-13 6
PVSP2AC-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA C PVS 12 12 0% 10-Dec-12 27-Dec-12 18-Dec-12 07-Jan-13 6
RESSLIL-1516 ROUGH-IN MEP/FIRE PROTECTION - INTER LVL RES 110 110 0% 25-Nov-14 01-May-15 04-Dec-14 12-May-15 7
RESL1LA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 LAB RES 25 25 0% 09-Dec-14 14-Jan-15 18-Dec-14 26-Jan-15 7
RESL1LA-0910 FRAMING/INWALL ROUGH - LVL-1 LAB RES 20 20 0% 16-Dec-14 14-Jan-15 26-Dec-14 26-Jan-15 7
RESPHPH-1600 SET ELECTRICAL EQUIPMENT - ROOF RES 7 7 0% 23-Oct-14 31-Oct-14 03-Nov-14 12-Nov-14 7
PVNSLPK-0320 DRILL/PLACE CAISSONS - SERV LVL PARK PVN 10 10 0% 04-Oct-13 21-Oct-13 17-Oct-13 31-Oct-13 7
PVNSLPK-0244 BACKFILL FOUNDATION WALLS - SERV LVL PARK PVN 10 10 0% 25-Nov-13 10-Dec-13 06-Dec-13 20-Dec-13 7
PVNSLPK-0322 FORM/PLACE FOUNDATION WALLS - SERV LVL PARK PVN 30 30 0% 11-Oct-13 02-Dec-13 24-Oct-13 12-Dec-13 7
PVNSLPK-0266 BELOW GRADE UTILITY ROUGH-IN - SERV LVL PARK PVN 10 10 0% 11-Dec-13 26-Dec-13 23-Dec-13 07-Jan-14 7
CBSADL3-2960 INTERIOR PAINT - LVL-3 ADD CBS 2 2 0% 17-Jan-12 18-Jan-12 25-Jan-12 26-Jan-12 7
CBSADL3-2970 CEILING - LVL-3 ADD CBS 4 4 0% 19-Jan-12 23-Jan-12 27-Jan-12 31-Jan-12 7
CBCL2AA-0910 FRAMING/INWALL ROUGH - LVL-2 AREA A CBC 14 14 0% 30-Jun-14 18-Jul-14 10-Jul-14 29-Jul-14 7
CBCL2AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA A CBC 13 13 0% 15-Jul-14 31-Jul-14 24-Jul-14 11-Aug-14 7
CBCL2AB-0910 FRAMING/INWALL ROUGH - LVL-2 AREA B CBC 14 14 0% 23-Jun-14 11-Jul-14 02-Jul-14 22-Jul-14 7
CBCL2AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA B CBC 12 12 0% 22-Jul-14 06-Aug-14 31-Jul-14 15-Aug-14 7
CBCL3AB-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-B CBC 15 15 0% 28-Aug-14 18-Sep-14 09-Sep-14 29-Sep-14 7
CBCL3AB-0910 FRAMING/INWALL ROUGH - LVL-3 AREA B CBC 14 14 0% 08-Jul-14 25-Jul-14 17-Jul-14 05-Aug-14 7
CBCL3AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA B CBC 12 12 0% 05-Aug-14 20-Aug-14 14-Aug-14 29-Aug-14 7
CBCL3AB-8880 CLEAN-UP/PRE PUNCH - LVL-3 AREA B CBC 8 8 0% 19-Sep-14 30-Sep-14 30-Sep-14 09-Oct-14 7
CBCL3AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA B CBC 22 22 0% 19-Aug-14 18-Sep-14 28-Aug-14 29-Sep-14 7
CBCL3AA-0910 FRAMING/INWALL ROUGH - LVL-3 AREA A CBC 14 14 0% 15-Jul-14 01-Aug-14 24-Jul-14 12-Aug-14 7
CBCL3AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA A CBC 13 13 0% 29-Jul-14 14-Aug-14 07-Aug-14 25-Aug-14 7
DVAPOPO-5020 VA PROVIDE FIXED FF&E SHOP DRAWINGS - RES 30 30 0% 06-Aug-14 17-Sep-14 15-Aug-14 26-Sep-14 7
PVNSLDO-0370 FORM/REINFORCE/PLACE COMD - SERV LVL DOCK PVN 5 5 0% 05-Sep-14 12-Sep-14 19-Sep-14 26-Sep-14 8
CBSADL4-2740 HANDRAIL - LVL-4 ADD CBS 2 2 0% 23-Jan-12 24-Jan-12 01-Feb-12 02-Feb-12 8
CBSADL1-3480 INTERIOR PAINT - LVL-1 ADD CBS 2 2 0% 20-Jan-12 21-Jan-12 30-Jan-12 31-Jan-12 8
CBSADL1-3490 CEILING - LVL-1 ADD CBS 2 2 0% 23-Jan-12 24-Jan-12 01-Feb-12 02-Feb-12 8
AAAA-1040 NTP FOR POTHOLING FOR SHORING TIE-BACKS (start milestone) 0 0 0% 07-Sep-11 15-Sep-11 8
ENCFTFT-3100 MASS EXCAVATION/PREP GRADE - FUEL TANK ENC 13 13 0% 12-Dec-13 27-Dec-13 21-Dec-13 07-Jan-14 8
RESESPH-0520 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTHOUSE ELEV RES 15 15 0% 16-Dec-14 08-Jan-15 31-Dec-14 23-Jan-15 9
CONL2AB-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-B CON 512 512 0% 10-Dec-12 23-Dec-14 04-Dec-13 07-Jan-15 9
CONL1SE-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 SERVING CON 25 25 0% 19-Aug-14 23-Sep-14 02-Sep-14 06-Oct-14 9
CONL1SE-0910 FRAMING/INWALL ROUGH - LVL-1 SERVING CON 6 6 0% 30-Sep-14 07-Oct-14 13-Oct-14 21-Oct-14 9
CONL1SE-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SERVING CON 18 18 0% 14-Oct-14 07-Nov-14 28-Oct-14 24-Nov-14 9
CONL1SE-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SERVING CON 30 30 0% 10-Nov-14 23-Dec-14 25-Nov-14 07-Jan-15 9
CONL1SE-8880 CLEAN-UP/PRE PUNCH - LVL-1 SERVING CON 10 10 0% 24-Dec-14 08-Jan-15 08-Jan-15 22-Jan-15 9
CONALCO-1592 TEST & BALANCE - CON 20 20 0% 24-Dec-14 23-Jan-15 08-Jan-15 05-Feb-15 9
CONALCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - CON 15 15 0% 24-Dec-14 15-Jan-15 08-Jan-15 29-Jan-15 9
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
11 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 092
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CONALCO-1596 FUNCTIONAL TESTING/CORRECTIONS - CON 15 15 0% 16-Jan-15 06-Feb-15 30-Jan-15 20-Feb-15 9
IBNSLSL-3130 DRIVE SOLDIER PILES - SERV LVL IBN 10 10 0% 27-Jan-12 09-Feb-12 09-Feb-12 24-Feb-12 9
HOITCTC-0110 ERECT TOWER CRANE #1 (DAT & CON C/D) 10 10 0% 07-Apr-12 16-Apr-12 16-Apr-12 25-Apr-12 9
CBCPHPR-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT ROOF CBC 11 11 0% 03-Oct-13 21-Oct-13 18-Oct-13 04-Nov-13 9
CBCL3L3-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 CBC 11 11 0% 10-Oct-13 28-Oct-13 25-Oct-13 13-Nov-13 9
CBCL3L3-0725 SPRAY-ON FIREPROOFING - LVL-3 CBC 10 10 0% 29-Oct-13 14-Nov-13 14-Nov-13 29-Nov-13 9
ENCTSTS-3100 MASS EXCAVATION/RECONDITIONING - WATER TANK ENC 5 5 0% 07-May-13 11-May-13 17-May-... 22-May-13 9
PVSALCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - ALL LVLS PVS 30 30 0% 04-Dec-13 16-Jan-14 17-Dec-13 30-Jan-14 9
RESESEE-0520 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - EAST ELEV RES 15 15 0% 16-Sep-14 08-Oct-14 02-Oct-14 24-Oct-14 10
RESESWE-0520 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - WEST ELEV RES 15 15 0% 09-Oct-14 03-Nov-14 27-Oct-14 19-Nov-14 10
RESESNE-0520 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - NORTH ELEV RES 15 15 0% 04-Sep-14 29-Sep-14 22-Sep-14 14-Oct-14 10
RESPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECH RES 45 45 0% 09-Jan-15 16-Mar-15 26-Jan-15 30-Mar-15 10
RESPHME-1590 START-UP MECH EQUIP - PENT MECH RES 15 15 0% 25-Jun-15 16-Jul-15 10-Jul-15 30-Jul-15 10
RESPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH RES 20 20 0% 28-May-15 24-Jun-15 11-Jun-15 09-Jul-15 10
RESPHEL-0910 FRAMING/INWALL ROUGH - PENTHOUSE ELEC RES 10 10 0% 27-Jan-15 10-Feb-15 11-Feb-15 24-Feb-15 10
RESPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENTHOUSE ELEC RES 10 10 0% 11-Feb-15 24-Feb-15 25-Feb-15 10-Mar-15 10
RESPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENTHOUSE ELEC RES 65 65 0% 25-Feb-15 27-May-15 11-Mar-15 10-Jun-15 10
RESRLRL-0520 INSTALL ROOF CANOPY STRUCTURE - ROOF RES 15 15 0% 04-Nov-14 28-Nov-14 21-Nov-14 15-Dec-14 10
CBSADL3-2920 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-3 ADD CBS 4 4 0% 22-Dec-11 27-Dec-11 05-Jan-12 09-Jan-12 10
CBSADL3-2930 FRAMING - LVL-3 ADD CBS 4 4 0% 28-Dec-11 31-Dec-11 10-Jan-12 13-Jan-12 10
CBSADL3-2940 WALL ROUGH-IN - LVL-3 ADD CBS 2 2 0% 03-Jan-12 04-Jan-12 14-Jan-12 17-Jan-12 10
CBSL3L3-2840 MILLWORK - LVL-3 CBS 5 5 0% 17-Dec-11 22-Dec-11 30-Dec-11 05-Jan-12 10
CBCPHPH-0725 SPRAY-ON FIREPROOFING - PENTLVL CBC 10 10 0% 03-Oct-13 18-Oct-13 21-Oct-13 04-Nov-13 10
EEEERES-0000 RES BLDG AVAILABLE FOR ENERGIZE 0 0 0% 27-May-15 10-Jun-15 10
DATPHPH-0350 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - PENT DAT 5 5 0% 29-Nov-12 06-Dec-12 14-Dec-12 21-Dec-12 10
DATL1IL-0500 ROUGH-IN MEP/FIRE PROTECTION (NUC MED) (AHU5) - LVL-1 INTER LVL DAT 50 50 0% 22-Aug-13 01-Nov-13 06-Sep-13 18-Nov-13 10
DATL3OR-0977 INSTALL OWNER FIXED FF&E - LVL-3 CATH LABS DAT 20 20 0% 03-Dec-14 31-Dec-14 17-Dec-14 15-Jan-15 10
DATL3OR-8880 CLEAN-UP/PRE PUNCH - LVL-3 ORS DAT 10 10 0% 02-Jan-15 15-Jan-15 16-Jan-15 30-Jan-15 10
RESPHME-0420 LAY CMU WALLS - PENTHOUSE MECH RES 15 15 0% 16-Dec-14 07-Jan-15 02-Jan-15 23-Jan-15 11
CONL1AE-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-E CON 10 10 0% 22-Dec-14 06-Jan-15 08-Jan-15 22-Jan-15 11
CONL1AE-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-E CON 35 35 0% 30-Oct-14 19-Dec-14 17-Nov-14 07-Jan-15 11
CONL1AE-0910 FRAMING/ ROUGH-IN - LVL-1 AR-E CON 18 18 0% 17-Sep-14 10-Oct-14 02-Oct-14 28-Oct-14 11
CONL1AE-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-E CON 12 12 0% 13-Oct-14 29-Oct-14 29-Oct-14 14-Nov-14 11
CBSADL2-3200 WALL ROUGH-IN - LVL-2 ADD CBS 2 2 0% 05-Jan-12 06-Jan-12 19-Jan-12 20-Jan-12 11
CBSL1L1-3390 HANDRAIL - LVL-1 CBS 10 10 0% 18-Jan-12 28-Jan-12 31-Jan-12 10-Feb-12 11
CBCL3AA-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBC 15 15 0% 22-Aug-14 12-Sep-14 09-Sep-14 29-Sep-14 11
CBCL3AA-8880 CLEAN-UP/PRE PUNCH - LVL-3 AREA A CBC 8 8 0% 15-Sep-14 24-Sep-14 30-Sep-14 09-Oct-14 11
CBCL3AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA A CBC 23 23 0% 12-Aug-14 12-Sep-14 27-Aug-14 29-Sep-14 11
AAAADAT-0100 START DAT CONSTRUCTION (start milestone) 0 0 0% 10-Feb-12 21-Feb-12 11
PVSP1AA-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA A PVS 12 12 0% 26-Dec-12 11-Jan-13 11-Jan-13 30-Jan-13 11
RESESEE-0870 INSTALL CURTAIN WALL - EAST ELEV RES 10 10 0% 31-Oct-14 17-Nov-14 21-Nov-14 08-Dec-14 12
RESESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV RES 20 20 0% 04-Sep-14 06-Oct-14 25-Sep-14 24-Oct-14 12
RESESWE-0870 INSTALL CURTAIN WALL - WEST ELEV RES 15 15 0% 27-Nov-14 19-Dec-14 16-Dec-14 08-Jan-15 12
RESESWE-0780 INSTALL METAL PANEL - WEST ELEV RES 5 5 0% 22-Dec-14 29-Dec-14 09-Jan-15 16-Jan-15 12
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
12 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 093
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
RESESNE-0870 INSTALL CURTAIN WALL- NORTH ELEV RES 15 15 0% 07-Oct-14 30-Oct-14 27-Oct-14 19-Nov-14 12
RESL2LA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 LAB RES 25 25 0% 15-Jan-15 20-Feb-15 03-Feb-15 10-Mar-15 12
RESL2LA-0910 FRAMING/INWALL ROUGH - LVL-2 LAB RES 20 20 0% 16-Feb-15 13-Mar-15 04-Mar-15 31-Mar-15 12
RESL2L2-0520 ERECT STRUCTURAL STEEL FOR LOW ROOF - LVL-2 RES 6 6 0% 17-Nov-14 25-Nov-14 08-Dec-14 15-Dec-14 12
PVNALAL-0991 FINISH STAIR CORES - ALL LVLS PVN 44 44 0% 05-Nov-14 09-Jan-15 25-Nov-14 28-Jan-15 12
PVNCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - PVN 20 20 0% 12-Jan-15 10-Feb-15 29-Jan-15 26-Feb-15 12
CBSADL3-2910 FIRE SPRINKLER ROUGH-IN - LVL-3 ADD CBS 2 2 0% 17-Dec-11 19-Dec-11 03-Jan-12 04-Jan-12 12
STR1-5610 VA REVIEW/APPROVE SHOP DRAWINGS - CBS ROOF DRAIN 20 20 0% 03-Nov-11 05-Dec-11 22-Nov-11 21-Dec-11 12
STR1-5200 AWARD ROOF DRAIN CONTRACT - CBS ROOF DRAIN 20 20 0% 07-Sep-11 04-Oct-11 23-Sep-11 21-Oct-11 12
STR1-5210 PREPARE PERMIT/APPROVAL - CBS ROOF DRAIN 20 20 0% 05-Oct-11 02-Nov-11 24-Oct-11 21-Nov-11 12
STR1-5620 PROCURE MATERIALS - CBS ROOF DRAIN 20 20 0% 06-Dec-11 04-Jan-12 22-Dec-11 23-Jan-12 12
CONL1SL-0910 FRAMING/INWALL ROUGH - LVL-1 SOUTH LOBBY CON 18 18 0% 17-Sep-14 10-Oct-14 06-Oct-14 30-Oct-14 13
CONL1SL-8880 CLEAN-UP/PRE PUNCH - LVL-1 SOUTH LOBBY CON 15 15 0% 11-Dec-14 02-Jan-15 31-Dec-14 22-Jan-15 13
CONL1SL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SOUTH LOBBY CON 40 40 0% 13-Oct-14 10-Dec-14 31-Oct-14 30-Dec-14 13
CBSADL2-3180 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-2 ADD CBS 4 4 0% 22-Dec-11 27-Dec-11 09-Jan-12 12-Jan-12 13
CBSADL2-3190 FRAMING - LVL-2 ADD CBS 4 4 0% 28-Dec-11 31-Dec-11 13-Jan-12 18-Jan-12 13
CBSADL1-3460 WALL ROUGH-IN - LVL-1 ADD CBS 2 2 0% 05-Jan-12 06-Jan-12 21-Jan-12 23-Jan-12 13
CBSADL1-3470 DRYWALL / FINISH - LVL-1 ADD CBS 5 5 0% 07-Jan-12 12-Jan-12 24-Jan-12 28-Jan-12 13
ENCPBPB-1590 START-UP CAMPUS PUMPS- SERV LVL MECH RMS ENC 30 30 0% 14-Oct-13 27-Nov-13 01-Nov-13 16-Dec-13 13
ENCSLME-1590 START-UP CAMPUS BOILERS/CHILLERS - SERV LVL MECH RMS ENC 30 30 0% 14-Oct-13 27-Nov-13 01-Nov-13 16-Dec-13 13
ENCPHPH-1590 START-UP CAMPUS COOLING TOWERS - PENTHOUSE ENC 30 30 0% 14-Oct-13 27-Nov-13 01-Nov-13 16-Dec-13 13
COMMISS-1626 LOAD TEST - FULL CAMPUS 5 5 0% 28-Nov-13 04-Dec-13 17-Dec-13 23-Dec-13 13
CONL3AA-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-A CON 512 512 0% 10-Dec-12 23-Dec-14 27-Sep-13 14-Jan-15 14
CONL3AD-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-D CON 512 512 0% 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL3AB-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-B CON 512 512 0% 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL3AC-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-C CON 512 512 0% 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL2AC-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-C CON 512 512 0% 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL2AD-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-D CON 512 512 0% 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL2AA-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-A CON 512 512 0% 10-Dec-12 23-Dec-14 27-Sep-13 14-Jan-15 14
CBSL1L1-3285 BELOW GRADE PLUMBING ROUGH-IN - LVL-1 CBS 10 10 0% 26-Jul-11 05-Aug-11 11-Aug-11 22-Aug-11 14
CBCL2L2-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 CBC 11 11 0% 28-Oct-13 14-Nov-13 20-Nov-13 09-Dec-13 14
CBCL2L2-0725 SPRAY-ON FIREPROOFING - LVL-2 CBC 10 10 0% 15-Nov-13 02-Dec-13 10-Dec-13 24-Dec-13 14
W-OSI-5320 SUB SUBMIT WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 10 10 0% 05-Oct-11 19-Oct-11 26-Oct-11 08-Nov-11 14
W-OSI-5390 VA APPROVE WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 20 20 0% 20-Oct-11 17-Nov-11 09-Nov-11 09-Dec-11 14
PVSP1AB-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA B PVS 12 12 0% 03-Jan-13 22-Jan-13 25-Jan-13 11-Feb-13 14
CONL1SL-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SOUTH LOBBY CON 16 16 0% 01-Oct-14 23-Oct-14 23-Oct-14 14-Nov-14 15
CBSADL2-3170 FIRE SPRINKLER ROUGH-IN - LVL-2 ADD CBS 2 2 0% 17-Dec-11 19-Dec-11 06-Jan-12 07-Jan-12 15
CBSL3L3-2830 CEILING - LVL-3 CBS 5 5 0% 06-Dec-11 10-Dec-11 23-Dec-11 29-Dec-11 15
CBCSLEL-8880 CLEAN-UP/PRE PUNCH - SERV LVL CORR CBC 5 5 0% 12-Sep-14 18-Sep-14 03-Oct-14 09-Oct-14 15
ENCSLSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL ENC 25 25 0% 07-Mar-12 04-Apr-12 24-Mar-12 21-Apr-12 15
PVSP1AE-1641 START-UP ELECTRICAL SYSTEMS (pvs/con) - PKG LVL-1 AREA E PVS 20 20 0% 18-Oct-13 18-Nov-13 12-Nov-13 10-Dec-13 15
DATSLSL-0381 FORM/PLACE/FINISH SLAB ON GRADE (AREA D) - SERV LVL DAT 10 10 0% 24-May-12 08-Jun-12 19-Jun-12 05-Jul-12 15
DATPHPH-0360 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - PENT DAT 5 5 0% 07-Dec-12 13-Dec-12 02-Jan-13 08-Jan-13 15
DATL1PA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 PRE-ADMIT DAT 20 20 0% 17-Jan-14 17-Feb-14 11-Feb-14 10-Mar-14 15
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
13 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 094
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL3CA-0977 INSTALL OWNER FIXED FF&E - LVL-3 CATH LABS DAT 20 20 0% 17-Oct-14 17-Nov-14 10-Nov-14 09-Dec-14 15
DATL3CA-8880 CLEAN-UP/PRE PUNCH - LVL-3 CATH LABS DAT 10 10 0% 18-Nov-14 02-Dec-14 10-Dec-14 23-Dec-14 15
CBSADL1-3450 FRAMING - LVL-1 ADD CBS 3 3 0% 28-Dec-11 30-Dec-11 18-Jan-12 20-Jan-12 16
CBCPHPH-0710 INSTALL LOUVERS - PENTLVL CBC 10 10 0% 02-Dec-13 16-Dec-13 27-Dec-13 10-Jan-14 16
CBCPHPH-0777 INSTALL METAL PANEL - PENTLVL CBC 10 10 0% 17-Dec-13 02-Jan-14 13-Jan-14 28-Jan-14 16
CBCESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV CBC 40 40 0% 10-Mar-14 16-May-14 07-Apr-14 16-Jun-14 16
AAAAPVN-0100 START PVN CONSTRUCTION (start milestone) 0 0 0% 23-Sep-13 09-Oct-13 16
CS1-3610 100% CD DESIGN COMPLETION - CS-1/IFO-3 0 0 0% 26-Oct-11 18-Nov-11 16
DATPOPO-5060 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 15 15 0% 28-Dec-11 19-Jan-12 23-Jan-12 10-Feb-12 16
DATPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 40 40 0% 27-Oct-11 27-Dec-11 21-Nov-11 20-Jan-12 16
DATPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 20 20 0% 20-Jan-12 17-Feb-12 14-Feb-12 12-Mar-12 16
DATPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (DAT) 15 15 0% 20-Feb-12 09-Mar-12 13-Mar-12 02-Apr-12 16
CS1-3040 95% DESIGN - CS-1/IFO-3 78 25 67.95% 18-Apr-11 A 29-Aug-11 17-Aug-11 21-Sep-11 16
CS1-3510 95% CD DESIGN COMPLETE - CS-1/IFO-3 0 0 0% 29-Aug-11 21-Sep-11 16
CS1-3660 KT PROVIDES RED LINE COMMENTS 95% CD - CS-1/IFO-3 15 15 0% 30-Aug-11 20-Sep-11 22-Sep-11 13-Oct-11 16
CS1-3670 PAGE FLIP 95% CD - CS-1/IFO-3 5 5 0% 21-Sep-11 27-Sep-11 14-Oct-11 20-Oct-11 16
CS1-3680 JVT REVISE DOCUMENTS 95% CD - CS-1/IFO-3 15 15 0% 28-Sep-11 19-Oct-11 21-Oct-11 10-Nov-11 16
CS1-3690 JVT QA/QC DOCUMENTS 95% CD - CS-1/IFO-3 5 5 0% 20-Oct-11 26-Oct-11 14-Nov-11 18-Nov-11 16
RESESPH-0710 INSTALL LOUVERS - PENTHOUSE ELEV RES 5 5 0% 09-Jan-15 16-Jan-15 05-Feb-15 13-Feb-15 17
RESESPH-0777 INSTALL METAL PANELS - PENTHOUSE ELEV RES 7 7 0% 20-Jan-15 28-Jan-15 16-Feb-15 24-Feb-15 17
RESSLSL-0390 PERM DRAINS/WATERPROOFING/BACKFILL FOUNDATION WALLS - SERV LVL RES 25 25 0% 14-Jul-14 25-Aug-14 12-Aug-14 23-Sep-14 17
CBSADL3-2900 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-3 ADD CBS 4 4 0% 07-Dec-11 10-Dec-11 28-Dec-11 31-Dec-11 17
CBSADL1-3440 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-1 ADD CBS 3 3 0% 22-Dec-11 24-Dec-11 13-Jan-12 17-Jan-12 17
CBSL3L3-2820 INTERIOR PAINT - LVL-3 CBS 10 10 0% 21-Nov-11 02-Dec-11 12-Dec-11 22-Dec-11 17
CBCL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 CBC 11 11 0% 18-Nov-13 05-Dec-13 16-Dec-13 02-Jan-14 17
CBCL1L1-0725 SPRAY-ON FIREPROOFING - LVL-1 CBC 10 10 0% 06-Dec-13 20-Dec-13 03-Jan-14 17-Jan-14 17
CBCL2AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA B CBC 22 22 0% 05-Aug-14 04-Sep-14 28-Aug-14 29-Sep-14 17
CBCL2AB-8880 CLEAN-UP/PRE PUNCH - LVL-2 AREA B CBC 8 8 0% 05-Sep-14 16-Sep-14 30-Sep-14 09-Oct-14 17
CBCL2AB-0977 INSTALL OWNER FIXED FF&E - LVL-2 AREA-B CBC 15 15 0% 14-Aug-14 04-Sep-14 09-Sep-14 29-Sep-14 17
CBCPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECH CBC 30 30 0% 27-Jan-14 10-Mar-14 20-Feb-14 02-Apr-14 17
CBCPHME-0420 LAY CMU WALLS - PENTHOUSE MECH CBC 15 15 0% 03-Jan-14 24-Jan-14 29-Jan-14 19-Feb-14 17
CBCPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH CBC 30 30 0% 08-Jul-14 18-Aug-14 31-Jul-14 11-Sep-14 17
CBCPHEL-0910 FRAMING/INWALL ROUGH - PENT ELEC CBC 8 8 0% 18-Feb-14 27-Feb-14 13-Mar-14 24-Mar-14 17
CBCPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENT ELEC CBC 15 15 0% 28-Feb-14 20-Mar-14 25-Mar-14 14-Apr-14 17
CBCPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC CBC 75 75 0% 21-Mar-14 07-Jul-14 15-Apr-14 30-Jul-14 17
CBCALAL-1400 INSTALL ELEVATOR SE5 - ALL LVLS CBC 60 60 0% 23-Jun-14 16-Sep-14 17-Jul-14 09-Oct-14 17
DVAPOPO-5000 VA PROVIDE FIXED FF&E SHOP DRAWINGS - CBC 30 30 0% 04-Oct-13 18-Nov-13 30-Oct-13 12-Dec-13 17
EEEECBC-0000 CBC BLDG AVAILABLE FOR ENERGIZE 0 0 0% 07-Jul-14 30-Jul-14 17
PVSP1AF-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA F PVS 12 12 0% 04-Feb-13 21-Feb-13 01-Mar-13 20-Mar-13 17
PVSP1AF-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA F PVS 10 10 0% 18-Jan-13 01-Feb-13 14-Feb-13 28-Feb-13 17
PVSP1AE-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA E PVS 10 10 0% 10-Jan-13 25-Jan-13 06-Feb-13 21-Feb-13 17
PVSP1AC-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA C PVS 12 12 0% 10-Jan-13 29-Jan-13 06-Feb-13 25-Feb-13 17
PVSP3AB-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA B PVS 14 14 0% 16-Jul-12 09-Aug-12 16-Aug-12 07-Sep-12 17
PVSP3AC-0332 FORM/PLACE FTGS/COLUMNS - PKG LVL-3 AREA C PVS 15 15 0% 04-Sep-12 28-Sep-12 03-Oct-12 25-Oct-12 17
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
14 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 095
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
PVSP3AC-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA C PVS 5 5 0% 28-Sep-12 05-Oct-12 26-Oct-12 02-Nov-12 17
PVSP3AC-0320 DRILL/PLACE CAISSONS - PKG LVL-3 AREA C PVS 14 14 0% 09-Aug-12 04-Sep-12 10-Sep-12 02-Oct-12 17
PVSP3AC-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA C PVS 10 10 0% 05-Oct-12 23-Oct-12 05-Nov-12 20-Nov-12 17
CONABHR-0888 INSTALL GLAZING @ CLEARSTORY - HIGH ROOF AR-B CON 12 12 0% 23-Sep-13 09-Oct-13 22-Oct-13 08-Nov-13 18
CONL1SL-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 SOUTH LOBBY CON 22 22 0% 19-Aug-14 18-Sep-14 15-Sep-14 14-Oct-14 18
COMMISS-1616 SYSTEM CONTROLS/STABILIZATION - FULL CAMPUS 30 30 0% 14-Oct-13 27-Nov-13 08-Nov-13 23-Dec-13 18
P-CBS-4370 SUBMITTAL DEVELOPMENT (structural steel) - CBS-1 20 6 70% 14-Jun-11 A 02-Aug-11 19-Aug-11 26-Aug-11 18
P-CBS-4380 SUBMITTAL REVIEW (structural steel) - CBS-1 20 20 0% 03-Aug-11 30-Aug-11 29-Aug-11 26-Sep-11 18
P-CBS-4390 MATERIAL PROCUREMENT (structural steel) - CBS-1 25 25 0% 31-Aug-11 05-Oct-11 27-Sep-11 01-Nov-11 18
P-CBS-4400 MATERIALS ARRIVE (structural steel) - CBS-1 0 0 0% 05-Oct-11 01-Nov-11 18
P-CBS-4280 SUBMITTAL VA REVIEW (electrical) - CBS-1 30 30 0% 17-Aug-11 28-Sep-11 13-Sep-11 25-Oct-11 18
P-CBS-4290 INITIAL MATERIAL PROCUREMENT (electrical) - CBS-1 15 15 0% 29-Sep-11 20-Oct-11 26-Oct-11 16-Nov-11 18
P-CBS-4300 ALL MATERIALS ARRIVE (electrical) - CBS-1 0 0 0% 29-Nov-11 23-Dec-11 18
P-CBS-4420 REMAINING MATERIAL PROCUREMENT (electrical) - CBS-1 25 25 0% 21-Oct-11 29-Nov-11 17-Nov-11 23-Dec-11 18
P-CBS-4270 SUBMITTAL DEVELOPMENT (electrical) - CBS-1 20 16 20% 24-Jun-11 A 16-Aug-11 19-Aug-11 12-Sep-11 18
CONL1ER-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-E RESTRMS CON 20 20 0% 19-Aug-14 16-Sep-14 16-Sep-14 13-Oct-14 19
CONL1ER-0910 FRAMING/INWALL ROUGH - LVL-1 AR-E RESTRMS CON 15 15 0% 17-Sep-14 07-Oct-14 14-Oct-14 04-Nov-14 19
CONL1ER-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D AR-E RESTRMS CON 12 12 0% 08-Oct-14 24-Oct-14 05-Nov-14 24-Nov-14 19
CONL1ER-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-D AR-E RESTRMS CON 10 10 0% 10-Dec-14 23-Dec-14 08-Jan-15 22-Jan-15 19
CONL1ER-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D AR-E RESTRMS CON 30 30 0% 27-Oct-14 09-Dec-14 25-Nov-14 07-Jan-15 19
CONL1AU-0910 FRAMING/INWALL ROUGH - LVL-1 AUDITRM CON 17 17 0% 17-Sep-14 09-Oct-14 14-Oct-14 06-Nov-14 19
CONL1AU-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AUDITRM CON 17 17 0% 01-Oct-14 24-Oct-14 29-Oct-14 24-Nov-14 19
CONL1AU-8880 CLEAN-UP/PRE PUNCH - LVL-1 AUDITRM CON 10 10 0% 10-Dec-14 23-Dec-14 08-Jan-15 22-Jan-15 19
CONL1AU-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AUDITRM CON 30 30 0% 27-Oct-14 09-Dec-14 25-Nov-14 07-Jan-15 19
PVNALAL-0555 ERECT STAIR 3A - ALL LVLS PVN 20 20 0% 26-Sep-14 24-Oct-14 24-Oct-14 24-Nov-14 19
CBSADL1-3430 FIRE SPRINKLER ROUGH-IN - LVL-1 ADD CBS 2 2 0% 17-Dec-11 19-Dec-11 11-Jan-12 12-Jan-12 19
PVSP3AB-0332 FORM/PLACE FTGS/WALLS/COLUMNS - PKG LVL-3 AREA B PVS 20 20 0% 09-Aug-12 13-Sep-12 13-Sep-12 12-Oct-12 19
RESALAL-1400 INSTALL ELEVATOR SE13 - ALL LVLS RES 60 60 0% 29-Apr-15 23-Jul-15 28-May-... 20-Aug-15 20
RESALAL-1401 INSTALL ELEVATOR SE12- ALL LVLS RES 60 60 0% 29-Apr-15 23-Jul-15 28-May-... 20-Aug-15 20
CONL1AC-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-C CON 25 25 0% 19-May-14 23-Jun-14 17-Jun-14 22-Jul-14 20
CONL1AC-0910 FRAMING/ ROUGH-IN - LVL-1 AR-C CON 20 20 0% 24-Jun-14 22-Jul-14 23-Jul-14 19-Aug-14 20
CONL1AC-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-C CON 15 15 0% 23-Jul-14 12-Aug-14 20-Aug-14 10-Sep-14 20
CONL1AC-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-C CON 65 65 0% 13-Aug-14 14-Nov-14 11-Sep-14 15-Dec-14 20
CONALAL-1455 INSTALL ELEVATOR CAR (GRIDLINE 25-26) - AREA C CON 60 60 0% 18-Sep-14 15-Dec-14 16-Oct-14 14-Jan-15 20
CONALAL-1445 INSTALL ELEVATOR CAR (GRIDLINE 20-21) - AREA C CON 60 60 0% 24-Oct-14 22-Jan-15 25-Nov-14 20-Feb-15 20
CONALAL-1465 INSTALL ELEVATOR CAR (GRIDLINE 28-29)- AREA D CON 60 60 0% 02-Dec-14 27-Feb-15 31-Dec-14 27-Mar-15 20
CBSADL2-3160 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-2 ADD CBS 4 4 0% 07-Dec-11 10-Dec-11 31-Dec-11 05-Jan-12 20
DVAPOPO-4990 VA PROVIDE MED EQUIP COORDINATED CDS (MRI/CT) - DAT 60 60 0% 05-Mar-13 28-May-13 02-Apr-13 25-Jun-13 20
OSI-4850 CITY OF AURORA WHEELING WATER LINE REVIEW AND AP - OSI-1 62 84 0% 10-Feb-11 A 23-Nov-11 23-Aug-11 23-Dec-11 20
PVSINP2-0990 GARAGE FINISHES - PKG LVL-2 PVS 30 30 0% 08-Aug-13 19-Sep-13 06-Sep-13 17-Oct-13 20
PVSP1AD-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA D PVS 12 12 0% 18-Jan-13 05-Feb-13 20-Feb-13 08-Mar-13 20
DATSLSL-0388 FORM/PLACE/FINISH SLAB ON GRADE (AREA A) - SERV LVL DAT 10 10 0% 19-Jun-12 05-Jul-12 24-Jul-12 09-Aug-12 20
DATSLSL-0383 FORM/PLACE/FINISH SLAB ON GRADE (AREA F) - SERV LVL DAT 10 10 0% 01-Jun-12 18-Jun-12 06-Jul-12 23-Jul-12 20
DATPHPH-0320 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - PENT DAT 5 5 0% 14-Dec-12 21-Dec-12 17-Jan-13 24-Jan-13 20
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
15 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 096
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL1ER-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 ER DAT 35 35 0% 26-Dec-13 17-Feb-14 27-Jan-14 17-Mar-14 20
DATL1ER-0910 FRAMING/INWALL ROUGH - LVL-1 ER DAT 30 30 0% 10-Jan-14 24-Feb-14 11-Feb-14 24-Mar-14 20
DATL1ER-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 ER DAT 25 25 0% 27-Jan-14 03-Mar-14 25-Feb-14 31-Mar-14 20
DATL1ER-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 ER DAT 65 65 0% 08-Apr-14 09-Jul-14 06-May-... 06-Aug-14 20
DATL1FL-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 FLURO/UTLSND DAT 25 25 0% 11-Feb-14 17-Mar-14 11-Mar-14 14-Apr-14 20
DATL1FL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 FLURO/UTLSND DAT 65 65 0% 25-Feb-14 27-May-14 25-Mar-14 24-Jun-14 20
DATL1PA-0910 FRAMING/INWALL ROUGH - LVL-1 PRE-ADMIT DAT 25 25 0% 26-Dec-13 31-Jan-14 27-Jan-14 03-Mar-14 20
DATL1IL-1600 ROUGH-IN MEP/FIRE PROTECTION (ER) (AHU16) - LVL-1 INTER LVL DAT 65 65 0% 20-Sep-13 24-Dec-13 18-Oct-13 24-Jan-14 20
DATL1IL-1500 ROUGH-IN MEP/FIRE PROTECTION (SPECIAL RADIOLOGY) (AHU15) - LVL-1 INTER LVL DAT 65 65 0% 22-Aug-13 26-Nov-13 20-Sep-13 24-Dec-13 20
DATL2DE-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 DENTAL DAT 55 55 0% 20-May-14 06-Aug-14 18-Jun-14 04-Sep-14 20
DATL2SC-0990 INSTALL INTERIOR FINISHES - LVL-2 SOUTH CORR DAT 55 55 0% 07-Aug-14 24-Oct-14 05-Sep-14 25-Nov-14 20
DATL3HY-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 HYBRID CVOR DAT 30 30 0% 12-Sep-14 24-Oct-14 10-Oct-14 25-Nov-14 20
PVSP3AC-0335 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA D PVS 12 12 0% 04-Sep-12 24-Sep-12 08-Oct-12 25-Oct-12 20
RESPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENTHOUSE MECH RES 60 60 0% 17-Mar-15 09-Jun-15 15-Apr-15 09-Jul-15 21
CONAASL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-A CON 40 40 0% 12-Jun-12 20-Aug-12 19-Jul-12 25-Sep-12 21
CONAASL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-A CON 18 18 0% 11-May-12 11-Jun-12 18-Jun-12 17-Jul-12 21
CONABSL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-B CON 9 9 0% 24-Apr-12 10-May-12 01-Jun-12 15-Jun-12 21
CONACSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-C CON 30 30 0% 09-Jul-12 28-Aug-12 14-Aug-12 03-Oct-12 21
CONACSL-3200 UNDERSLAB UTILITIES - SERV LVL AR-C CON 11 11 0% 30-Aug-12 17-Sep-12 04-Oct-12 22-Oct-12 21
CONACSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-C CON 12 12 0% 18-Sep-12 05-Oct-12 23-Oct-12 09-Nov-12 21
CONACSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-C CON 19 19 0% 06-Nov-12 07-Dec-12 12-Dec-12 10-Jan-13 21
CONACSL-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-C CON 8 8 0% 08-Oct-12 19-Oct-12 13-Nov-12 23-Nov-12 21
CONACL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-C CON 15 15 0% 01-Oct-12 23-Oct-12 02-Nov-12 27-Nov-12 21
CONACL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-C CON 8 8 0% 24-Oct-12 05-Nov-12 29-Nov-12 11-Dec-12 21
CONL1AU-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AUDITRM CON 25 25 0% 19-Aug-14 23-Sep-14 18-Sep-14 23-Oct-14 21
CBCL2AA-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBC 15 15 0% 08-Aug-14 28-Aug-14 09-Sep-14 29-Sep-14 21
CBCL2AA-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBC 8 8 0% 29-Aug-14 10-Sep-14 30-Sep-14 09-Oct-14 21
CBCL2AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA A CBC 23 23 0% 29-Jul-14 28-Aug-14 27-Aug-14 29-Sep-14 21
CBNESEE-0520 SHEATHING/VAPOR BARRIER - EAST ELEV CBN 5 5 0% 20-Aug-13 27-Aug-13 26-Sep-13 02-Oct-13 21
CBNESWE-0520 SHEATHING/VAPOR BARRIER - WEST ELEV CBN 5 5 0% 25-Jul-13 01-Aug-13 30-Aug-13 06-Sep-13 21
CBNESSE-0520 SHEATHING/VAPOR BARRIER - SOUTH ELEV CBN 10 10 0% 02-Aug-13 19-Aug-13 09-Sep-13 24-Sep-13 21
CBNESNE-0520 SHEATHING/VAPOR BARRIER - NORTH ELEV CBN 10 10 0% 08-Jul-13 23-Jul-13 13-Aug-13 29-Aug-13 21
CBNSSSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBN 35 35 0% 17-Dec-12 08-Feb-13 22-Jan-13 15-Mar-13 21
CBNPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT LVL CBN 19 19 0% 11-Feb-13 12-Mar-13 18-Mar-13 16-Apr-13 21
CBNPHPR-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT ROOF CBN 11 11 0% 14-Mar-13 29-Mar-13 18-Apr-13 07-May-13 21
CBNL1L1-0540 ERECT EXTERIOR STUDS - LVL-1 CBN 15 15 0% 11-Jun-13 05-Jul-13 18-Jul-13 12-Aug-13 21
CBNL1L1-0725 SPRAY-ON FIREPROOFING - LVL-1 CBN 10 10 0% 24-May-13 10-Jun-13 01-Jul-13 16-Jul-13 21
CBNL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 CBN 11 11 0% 06-May-13 23-May-13 11-Jun-13 28-Jun-13 21
CBNL2L2-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 CBN 11 11 0% 12-Apr-13 02-May-13 21-May-... 07-Jun-13 21
CBNL3L3-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 CBN 11 11 0% 26-Mar-13 12-Apr-13 03-May-... 21-May-13 21
CBNSLSL-0320 DRILL/PLACE CAISSONS (balance @ bench) - SERV LVL CBN 5 5 0% 10-Dec-12 14-Dec-12 11-Jan-13 18-Jan-13 21
PVSP3AB-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA B PVS 5 5 0% 13-Sep-12 21-Sep-12 19-Oct-12 25-Oct-12 21
PVSP3AB-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA B PVS 10 10 0% 21-Sep-12 08-Oct-12 26-Oct-12 13-Nov-12 21
PVSP3AB-0335 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA B PVS 20 20 0% 09-Aug-12 13-Sep-12 17-Sep-12 18-Oct-12 21
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
16 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 097
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
RESL2LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 LAB RES 15 15 0% 02-Mar-15 20-Mar-15 01-Apr-15 21-Apr-15 22
CBSL3L3-2810 DRYWALL / FINISH - LVL-3 CBS 5 5 0% 08-Nov-11 14-Nov-11 06-Dec-11 10-Dec-11 22
CONL1AD-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-D CON 20 20 0% 24-Jun-14 22-Jul-14 28-Jul-14 22-Aug-14 23
CBSADL1-3420 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-1 ADD CBS 5 5 0% 07-Dec-11 12-Dec-11 05-Jan-12 10-Jan-12 23
CBCESNE-0440 INSTALL PRECAST PANELS - NORTH ELEV CBC 8 8 0% 17-Feb-14 26-Feb-14 24-Mar-14 04-Apr-14 23
CBCESNE-0870 INSTALL CURTAIN WALL - NORTH ELEV CBC 40 40 0% 27-Feb-14 05-May-14 07-Apr-14 16-Jun-14 23
PVSP1AE-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA E PVS 12 12 0% 28-Jan-13 12-Feb-13 04-Mar-13 21-Mar-13 23
PVSP2AE-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA E PVS 12 12 0% 26-Dec-12 11-Jan-13 31-Jan-13 19-Feb-13 23
PVSP2AF-0335 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA F PVS 12 12 0% 03-Jan-13 22-Jan-13 07-Feb-13 26-Feb-13 23
PVSP2AF-0330 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA F PVS 10 10 0% 17-Dec-12 02-Jan-13 24-Jan-13 06-Feb-13 23
SITWSSW-308 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - WHEELING ST. 10 10 0% 16-Apr-12 30-Apr-12 24-May-... 08-Jun-12 23
SITSWBW-0218 DEMO/GRADING - NORTH WHEELING ST. 15 15 0% 08-May-12 01-Jun-12 18-Jun-12 12-Jul-12 23
SITSWBW-0228 CONSTRUCT ROADWAY - NORTH WHEELING ST. 25 25 0% 17-Jul-12 28-Aug-12 27-Aug-12 05-Oct-12 23
SITSWBW-0238 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - NORTH WHEELING ST. 25 25 0% 30-Aug-12 09-Oct-12 08-Oct-12 16-Nov-12 23
SITSWBW-0205 INSTALL REMAINING UTILITIES - NORTH WHEELING ST. 25 25 0% 04-Jun-12 16-Jul-12 13-Jul-12 24-Aug-12 23
SITSWBW-0215 PLACE EROSION PROTECTION/TRAFFIC CONTROL - NORTH WHEELING ST. 4 4 0% 01-May-12 07-May-12 11-Jun-12 15-Jun-12 23
PVSP3AA-0332 FORM/PLACE FTGS/COLUMNS - PKG LVL-3 AREA A PVS 15 15 0% 16-Jul-12 10-Aug-12 27-Aug-12 20-Sep-12 23
CONABSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-B CON 30 30 0% 11-May-12 02-Jul-12 22-Jun-12 13-Aug-12 24
CONACSL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-C CON 12 12 0% 12-Jun-12 02-Jul-12 24-Jul-12 13-Aug-12 24
DATSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL DAT 30 30 0% 14-Mar-12 07-May-12 26-Apr-12 18-Jun-12 24
DATSLSL-3200 UNDERSLAB UTILITIES - SERV LVL DAT 30 30 0% 22-Mar-12 15-May-12 07-May-... 26-Jun-12 24
DATSLSL-0320 DRILL/PLACE CAISSONS - SERV LVL DAT 25 25 0% 06-Mar-12 17-Apr-12 17-Apr-12 31-May-12 24
CONAASL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-A CON 15 15 0% 05-Apr-12 03-May-12 22-May-... 15-Jun-12 25
CONL1AD-0910 FRAMING/ ROUGH-IN - LVL-1 AR-D CON 18 18 0% 23-Jul-14 15-Aug-14 27-Aug-14 22-Sep-14 25
CONL1AD-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D CON 12 12 0% 18-Aug-14 03-Sep-14 23-Sep-14 08-Oct-14 25
CONL1AD-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-D CON 10 10 0% 02-Dec-14 15-Dec-14 08-Jan-15 22-Jan-15 25
CONL1AD-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-D CON 60 60 0% 04-Sep-14 01-Dec-14 09-Oct-14 07-Jan-15 25
DATSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK DAT 55 55 0% 02-Jul-14 03-Oct-14 15-Aug-14 14-Nov-14 25
DATSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK DAT 16 16 0% 05-Jun-14 01-Jul-14 18-Jul-14 14-Aug-14 25
EEEECBN-0000 CBN BLDG AVAILABLE FOR ENERGIZE 0 0 0% 26-Jun-14 01-Aug-14 25
CBNCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - CBN 25 25 0% 26-Nov-14 31-Dec-14 02-Jan-15 06-Feb-15 25
CBNCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - CBN 33 33 0% 09-Sep-14 24-Oct-14 14-Oct-14 02-Dec-14 25
CBNCOCO-1620 TEST & BALANCE - CBN 30 30 0% 27-Oct-14 09-Dec-14 03-Dec-14 15-Jan-15 25
CBNCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS 20 20 0% 27-Oct-14 25-Nov-14 03-Dec-14 31-Dec-14 25
CBNL3AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-3 AREA A CBN 20 20 0% 28-Aug-13 25-Sep-13 03-Oct-13 31-Oct-13 25
CBNL3AA-0910 FRAMING/INWALL ROUGH - LVL-3 AREA A CBN 14 14 0% 22-Jan-14 11-Feb-14 27-Feb-14 18-Mar-14 25
CBNL3AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA A CBN 13 13 0% 05-Feb-14 24-Feb-14 13-Mar-14 31-Mar-14 25
CBNL3AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA B CBN 12 12 0% 13-Feb-14 28-Feb-14 20-Mar-14 04-Apr-14 25
CBNL3AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AREA B CBN 20 20 0% 12-Sep-13 09-Oct-13 17-Oct-13 15-Nov-13 25
CBNL3AB-0910 FRAMING/INWALL ROUGH - LVL-3 AREA B CBN 14 14 0% 09-Jan-14 29-Jan-14 17-Feb-14 06-Mar-14 25
CBNALAL-1400 INSTALL ELEVATOR SE5 - ALL LVLS CBN 60 60 0% 13-Jun-14 08-Sep-14 21-Jul-14 13-Oct-14 25
CBNL1AB-0910 FRAMING/INWALL ROUGH - LVL-1 AREA B CBN 14 14 0% 22-Nov-13 11-Dec-13 30-Dec-13 17-Jan-14 25
CBNL1AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AREA B CBN 17 17 0% 08-Nov-13 04-Dec-13 17-Dec-13 10-Jan-14 25
CBNL1AA-0910 FRAMING/INWALL ROUGH - LVL-1 AREA A CBN 14 14 0% 04-Dec-13 23-Dec-13 10-Jan-14 30-Jan-14 25
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
17 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 098
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBNL1AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-1 AREA A CBN 18 18 0% 25-Oct-13 20-Nov-13 03-Dec-13 27-Dec-13 25
CBNL2AA-1516 R-I OVERHEAD MEP/FIRE PRO- LVL-2 AREA A CBN 18 18 0% 26-Sep-13 22-Oct-13 01-Nov-13 28-Nov-13 25
CBNL2AA-0910 FRAMING/INWALL ROUGH - LVL-2 AREA A CBN 14 14 0% 27-Dec-13 16-Jan-14 04-Feb-14 24-Feb-14 25
CBNL2AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AREA B CBN 17 17 0% 10-Oct-13 04-Nov-13 18-Nov-13 11-Dec-13 25
CBNL2AB-0910 FRAMING/INWALL ROUGH - LVL-2 AREA B CBN 14 14 0% 16-Dec-13 06-Jan-14 23-Jan-14 12-Feb-14 25
CBNPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENT ELEC CBN 15 15 0% 20-Feb-14 12-Mar-14 27-Mar-14 16-Apr-14 25
CBNPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC CBN 75 75 0% 13-Mar-14 26-Jun-14 17-Apr-14 01-Aug-14 25
CBNPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH CBN 30 30 0% 27-Jun-14 08-Aug-14 04-Aug-14 15-Sep-14 25
DATPHPH-0321 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - PENT DAT 5 5 0% 24-Dec-12 31-Dec-12 01-Feb-13 07-Feb-13 25
DATL1FL-0910 FRAMING/INWALL ROUGH - LVL-1 FLURO/UTLSND DAT 30 30 0% 17-Jan-14 03-Mar-14 25-Feb-14 07-Apr-14 25
DATL1RO-0910 FRAMING/INWALL ROUGH - LVL-1 RAD OFFICES DAT 20 20 0% 27-Jan-14 24-Feb-14 04-Mar-14 31-Mar-14 25
DATL2CA-0910 FRAMING/INWALL ROUGH - LVL-2 CARDIO DAT 35 35 0% 25-Feb-14 14-Apr-14 01-Apr-14 19-May-14 25
DATL2CA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 CARDIO DAT 25 25 0% 18-Mar-14 21-Apr-14 22-Apr-14 27-May-14 25
DATESAF-0550 HOIST INFILL - ALL ELEVS AR-F DAT 10 10 0% 29-May-14 13-Jun-14 11-Jul-14 28-Jul-14 25
DATESAC-0550 HOIST INFILL - ALL ELEVS AR-C DAT 10 10 0% 29-May-14 13-Jun-14 11-Jul-14 28-Jul-14 25
PVSSWSW-3220 INSTALL DEWATERING SYSTEM - PVS SITEWORK 20 20 0% 13-Jan-12 13-Feb-12 23-Feb-12 23-Mar-12 25
PVSP3AA-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA A PVS 10 10 0% 30-Aug-12 17-Sep-12 12-Oct-12 29-Oct-12 26
PVSP3AA-0355 WATERPROOF/REINFORCE/SHOTCRETE SOUTH WALL - PKG LVL-3 AREA A PVS 30 30 0% 29-Jun-12 21-Aug-12 16-Aug-12 04-Oct-12 26
PVSP3AA-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA A PVS 5 5 0% 21-Aug-12 30-Aug-12 05-Oct-12 11-Oct-12 26
RESL1SO-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 SUPP RES 25 25 0% 16-Dec-14 22-Jan-15 27-Jan-15 03-Mar-15 27
RESL2SO-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 SUPP RES 25 25 0% 23-Jan-15 27-Feb-15 04-Mar-15 07-Apr-15 27
RESL3LA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 LAB RES 35 35 0% 23-Feb-15 10-Apr-15 01-Apr-15 19-May-15 27
RESL3LA-0910 FRAMING/INWALL ROUGH - LVL-3 LAB RES 20 20 0% 30-Mar-15 24-Apr-15 06-May-... 03-Jun-15 27
RESL3SO-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 SUPP RES 25 25 0% 02-Mar-15 03-Apr-15 08-Apr-15 12-May-15 27
RESL3SO-0910 FRAMING/INWALL ROUGH - LVL-3 SUPP RES 20 20 0% 23-Mar-15 17-Apr-15 29-Apr-15 27-May-15 27
RESL3SO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SUPP RES 45 45 0% 20-Apr-15 22-Jun-15 28-May-... 30-Jul-15 27
CONAASL-3200 UNDERSLAB UTILITIES - SERV LVL AR-A CON 17 17 0% 21-Aug-12 18-Sep-12 05-Oct-12 01-Nov-12 27
CONAASL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-A CON 11 11 0% 20-Sep-12 05-Oct-12 02-Nov-12 20-Nov-12 27
CONAASL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-A CON 40 40 0% 01-Nov-12 07-Jan-13 17-Dec-12 19-Feb-13 27
CONAASL-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS - SERV LVL AR-A CON 8 8 0% 08-Oct-12 19-Oct-12 21-Nov-12 04-Dec-12 27
CONAAL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-A CON 6 6 0% 22-Jan-13 29-Jan-13 04-Mar-13 12-Mar-13 27
CONAAL1-0320 DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-A CON 8 8 0% 08-Jan-13 18-Jan-13 20-Feb-13 01-Mar-13 27
CONAAL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-A CON 8 8 0% 30-Jan-13 08-Feb-13 14-Mar-13 25-Mar-13 27
CONAAL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-A CON 12 12 0% 04-Oct-12 23-Oct-12 19-Nov-12 07-Dec-12 27
CONAAL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-A CON 5 5 0% 24-Oct-12 30-Oct-12 10-Dec-12 14-Dec-12 27
CBCL1AB-0977 INSTALL OWNER FIXED FF&E - LVL-31AREA-A CBC 15 15 0% 31-Jul-14 20-Aug-14 09-Sep-14 29-Sep-14 27
CBCL1AB-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA B CBC 8 8 0% 21-Aug-14 02-Sep-14 30-Sep-14 09-Oct-14 27
STR2-4630 VA REVIEWS BID TABS - STR-2 5 5 0% 19-Oct-11 25-Oct-11 30-Nov-11 06-Dec-11 27
STR2-3700 VA PROVIDES CONSENT TO SUBCONTRACT - STR-2 0 0 0% 25-Oct-11 06-Dec-11 27
STR2-3610 100% CD DESIGN COMPLETION - STR-2 0 0 0% 06-Sep-11 14-Oct-11 27
STR2-4800 PREPARE/SUBMIT BID TABS - STR-2 15 15 0% 27-Sep-11 18-Oct-11 04-Nov-11 29-Nov-11 27
STR2-4830 SUBCONTRACTOR PRICING - STR-2 14 14 0% 07-Sep-11 26-Sep-11 17-Oct-11 03-Nov-11 27
STR2-3660 KT PROVIDES RED LINE COMMENTS 95% CD - STR-2 5 5 0% 26-Jul-11 01-Aug-11 01-Sep-11 08-Sep-11 27
STR2-3670 PAGE FLIP 95% CD - STR-2 5 5 0% 02-Aug-11 08-Aug-11 09-Sep-11 15-Sep-11 27
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
18 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 099
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
STR2-3680 JVT REVISE DOCUMENTS 95% CD - STR-2 15 15 0% 09-Aug-11 29-Aug-11 16-Sep-11 06-Oct-11 27
STR2-3690 JVT QA/QC DOCUMENTS 95% CD - STR-2 5 5 0% 30-Aug-11 06-Sep-11 07-Oct-11 14-Oct-11 27
STR2-4810 AWARD STEEL CONTRACT 20 20 0% 26-Oct-11 23-Nov-11 07-Dec-11 05-Jan-12 27
STR2-3580 EVALUATE AND RELEASE MILL ORDER - STR-2 10 10 0% 28-Nov-11 09-Dec-11 06-Jan-12 20-Jan-12 27
ENCPOPO-5459 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (ENC) 25 25 0% 24-Feb-12 29-Mar-12 03-Apr-12 07-May-12 27
ENCPOPO-4711 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (ENC) 20 20 0% 30-Mar-12 26-Apr-12 08-May-... 05-Jun-12 27
ENCPOPO-4721 FABRICATE/DELIVER STRUCT STEEL - STR-2 (ENC) 50 50 0% 27-Apr-12 09-Jul-12 06-Jun-12 15-Aug-12 27
ENCPOPO-4731 FIRST DELIVERY OF STRUCT STEEL - STR-2 (ENC) 0 0 0% 09-Jul-12 15-Aug-12 27
ENCPOPO-4660 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (ENC) 50 50 0% 12-Dec-11 23-Feb-12 23-Jan-12 02-Apr-12 27
SITSWSW-0230 PLACE EROSION CONTROL - FULL CAMPUS 20 20 0% 05-Oct-11 07-Nov-11 21-Nov-11 20-Dec-11 27
PVNL1L1-1570 GARAGE FINISHES - LVL-1 PVN 25 25 0% 27-Oct-14 02-Dec-14 08-Dec-14 13-Jan-15 28
PVNL1L1-8890 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 PVN 10 10 0% 03-Dec-14 16-Dec-14 14-Jan-15 28-Jan-15 28
PVNL2L2-1590 GARAGE FINISHES - LVL -2 PVN 25 25 0% 27-Oct-14 02-Dec-14 08-Dec-14 13-Jan-15 28
PVNL2L2-8900 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 PVN 10 10 0% 03-Dec-14 16-Dec-14 14-Jan-15 28-Jan-15 28
PVNL3L3-1610 GARAGE FINISHES - LVL-3 PVN 25 25 0% 27-Oct-14 02-Dec-14 08-Dec-14 13-Jan-15 28
PVNL3L3-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 PVN 10 10 0% 03-Dec-14 16-Dec-14 14-Jan-15 28-Jan-15 28
PVNL4L4-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-4 PVN 10 10 0% 03-Dec-14 16-Dec-14 14-Jan-15 28-Jan-15 28
PVNL4L4-1610 GARAGE FINISHES - LVL-4 PVN 25 25 0% 27-Oct-14 02-Dec-14 08-Dec-14 13-Jan-15 28
PVNL5L5-1610 GARAGE FINISHES - LVL-5 PVN 25 25 0% 27-Oct-14 02-Dec-14 08-Dec-14 13-Jan-15 28
PVNL5L5-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-5 PVN 10 10 0% 03-Dec-14 16-Dec-14 14-Jan-15 28-Jan-15 28
CBNSLSL-0352 FORM/PLACE/STRIP SHEAR WALLS - SERV LVL CBN 45 45 0% 07-Sep-12 20-Nov-12 24-Oct-12 07-Jan-13 28
CBNSLSL-0380 FINE GRADE/FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL CBN 8 8 0% 21-Nov-12 04-Dec-12 08-Jan-13 18-Jan-13 28
CBNSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/WALLS/GRD BEAMS - SERV LVL CBN 35 35 0% 09-Jul-12 06-Sep-12 27-Aug-12 23-Oct-12 28
RESL1SO-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SUPP RES 15 15 0% 28-Jan-15 19-Feb-15 11-Mar-15 31-Mar-15 28
XXXXSIT-0510 INITIAL SITEWORK DURATION 958 958 0% 11-Jan-12 25-Aug-14 11-Jan-12 23-Sep-14 29
PVSINP3-8880 CLEAN-UP/PRE PUNCH - PKG LVL-1 PVS 10 10 0% 18-Oct-13 01-Nov-13 03-Dec-13 16-Dec-13 29
DATSLSL-0382 FORM/PLACE/FINISH SLAB ON GRADE (AREA E) - SERV LVL DAT 10 10 0% 08-May-12 24-May-12 28-Jun-12 13-Jul-12 29
SITSWSW-0220 SURVEY- FULL CAMPUS 20 20 0% 03-Oct-11 03-Nov-11 21-Nov-11 20-Dec-11 29
SITSWSW-0100 MOBILIZE INITIAL CONSTRUCTION RESOURCES - FULL CAMPUS 5 5 0% 23-Sep-11 30-Sep-11 10-Nov-11 18-Nov-11 29
PVSP3AE-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA E PVS 10 10 0% 03-Oct-12 19-Oct-12 21-Nov-12 07-Dec-12 29
PVSP3AD-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA D PVS 5 5 0% 11-Sep-12 20-Sep-12 30-Oct-12 06-Nov-12 29
PVSP3AD-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA D PVS 10 10 0% 20-Sep-12 05-Oct-12 08-Nov-12 23-Nov-12 29
FL2P3AD-0355 WATERPROOF/REINFORCE/SHOTCRETE EAST WALL - PKG LVL-3 AREA D PVS 12 12 0% 21-Aug-12 11-Sep-12 10-Oct-12 29-Oct-12 29
PVNSLPK-1641 START-UP ELECTRICAL SYSTEMS (pvn/con) - SERV LVL PARK PVN 30 30 0% 13-Aug-14 24-Sep-14 25-Sep-14 06-Nov-14 30
DVAPOPO-4910 VA PROVIDE MED EQUIP COORDINATED CDS (surgery) - DAT 60 60 0% 06-Sep-13 03-Dec-13 18-Oct-13 16-Jan-14 30
STR1-0000 VA OBTAIN APPROVAL FOR TIE-BACKS UNDER ROADWAYS 0 0 0% 23-Nov-11 10-Jan-12 30
ENCL1L1-1620 SET SWITCHGEAR - LVL-1 ENC 5 5 0% 12-Feb-13 18-Feb-13 26-Mar-13 01-Apr-13 30
ENCL1L1-1640 SET SUBSTATION - LVL-1 ENC 5 5 0% 12-Feb-13 18-Feb-13 26-Mar-13 01-Apr-13 30
DATL1IL-0510 ERECT INTER STEEL/TOPPING (AREA A) - LVL-1 INTER LVL DAT 15 15 0% 21-Mar-13 15-Apr-13 14-May-... 07-Jun-13 30
DATL1IL-1527 ERECT INTER STEEL/TOPPING (AREA B) - LVL-1 INTER LVL DAT 15 15 0% 08-Apr-13 03-May-13 31-May-... 25-Jun-13 30
DATL1IL-1537 ERECT INTER STEEL/TOPPING (AREA C) - LVL-1 INTER LVL DAT 15 15 0% 17-Jan-13 07-Feb-13 05-Mar-13 28-Mar-13 30
DATL1IL-1547 ERECT INTER STEEL/TOPPING (AREA D) - LVL-1 INTER LVL DAT 15 15 0% 01-Feb-13 25-Feb-13 21-Mar-13 15-Apr-13 30
DATL1IL-1557 ERECT INTER STEEL/TOPPING (AREA E) - LVL-1 INTER LVL DAT 15 15 0% 19-Feb-13 12-Mar-13 08-Apr-13 03-May-13 30
DATL1IL-1567 ERECT INTER STEEL/TOPPING (AREA F) - LVL-1 INTER LVL DAT 15 15 0% 05-Mar-13 28-Mar-13 25-Apr-13 21-May-13 30
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
19 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 100
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL1RO-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 RAD OFFICES DAT 15 15 0% 18-Feb-14 10-Mar-14 01-Apr-14 21-Apr-14 30
DATL1IL-0800 ROUGH-IN MEP/FIRE PROTECTION (OFFICES) (AHU8) - LVL-1 INTER LVL DAT 50 50 0% 20-Sep-13 03-Dec-13 04-Nov-13 16-Jan-14 30
DATL2IL-0300 ROUGH-IN MEP/FIRE PROTECTION (CARDIO) (AHU3) - LVL-2 INTER LVL DAT 60 60 0% 04-Nov-13 31-Jan-14 18-Dec-13 17-Mar-14 30
DATL2IL-0800 ROUGH-IN MEP/FIRE PROTECTION (SLEEP LABS) (AHU8) - LVL-2 INTER LVL DAT 65 65 0% 18-Dec-13 24-Mar-14 03-Feb-14 05-May-14 30
DATL2SL-0910 FRAMING/INWALL ROUGH - LVL-2 SLEEP DAT 30 30 0% 25-Mar-14 05-May-14 06-May-... 17-Jun-14 30
DATL2SL-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SLEEP DAT 25 25 0% 22-Apr-14 27-May-14 04-Jun-14 09-Jul-14 30
DATPHSP-1590 START-UP MECH EQUIP - SOUTH PENT MECH DAT 30 30 0% 03-Oct-14 17-Nov-14 18-Nov-14 31-Dec-14 30
DATL3IL-0300 ROUGH-IN MEP/FIRE PROTECTION (CATH) (AHU3) - LVL-3 INTER LVL DAT 55 55 0% 17-Jan-14 07-Apr-14 04-Mar-14 19-May-14 30
DATL3IL-0301 TRIM-OUT MEP (CATH) (AHU3) - LVL-3 INTER LVL DAT 5 5 0% 26-Sep-14 02-Oct-14 10-Nov-14 17-Nov-14 30
DATL3IL-0900 ROUGH-IN MEP/FIRE PROTECTION (ORS) (AHU9) - LVL-3 INTER LVL DAT 50 50 0% 04-Mar-14 12-May-14 15-Apr-14 24-Jun-14 30
DATL3OR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 ORS DAT 45 45 0% 13-May-14 16-Jul-14 25-Jun-14 27-Aug-14 30
DATL3OR-0910 FRAMING/INWALL ROUGH - LVL-3 ORS DAT 55 55 0% 20-May-14 06-Aug-14 02-Jul-14 18-Sep-14 30
DATL3OR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 ORS DAT 35 35 0% 02-Jul-14 20-Aug-14 14-Aug-14 02-Oct-14 30
DATL3HY-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 HYBRID CVOR DAT 5 5 0% 17-Jul-14 23-Jul-14 28-Aug-14 04-Sep-14 30
DATL3HY-0910 FRAMING/INWALL ROUGH - LVL-3 HYBRID CVOR DAT 20 20 0% 17-Jul-14 13-Aug-14 28-Aug-14 25-Sep-14 30
DATL3HY-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 HYBRID CVOR DAT 10 10 0% 14-Aug-14 27-Aug-14 26-Sep-14 09-Oct-14 30
DATL3CA-0910 FRAMING/INWALL ROUGH - LVL-3 CATH LABS DAT 35 35 0% 22-Apr-14 10-Jun-14 04-Jun-14 23-Jul-14 30
DATL3CA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 CATH LABS DAT 25 25 0% 28-May-14 01-Jul-14 10-Jul-14 13-Aug-14 30
CONALAL-1404 INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 20-21) - AREA C CON 25 25 0% 09-May-14 13-Jun-14 24-Jun-14 29-Jul-14 31
CONALAL-1405 INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 25-26) - AREA C CON 25 25 0% 16-Jun-14 21-Jul-14 30-Jul-14 03-Sep-14 31
CONALAL-1415 INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 28-29)- AREA D CON 25 25 0% 22-Jul-14 25-Aug-14 04-Sep-14 08-Oct-14 31
PVNESRL-1600 INSTALL ROOF TRELLIS SYSTEM - ROOF LVL PVN 20 20 0% 14-Aug-14 16-Sep-14 06-Oct-14 06-Nov-14 31
PVNESRL-1610 INSTALL GLASS ROOFING SYSTEM - ROOF LVL PVN 40 40 0% 18-Sep-14 21-Nov-14 07-Nov-14 12-Jan-15 31
PVNESRL-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - ROOF LVL PVN 10 10 0% 24-Nov-14 09-Dec-14 13-Jan-15 28-Jan-15 31
CBCL1AA-0977 INSTALL OWNER FIXED FF&E - LVL-31AREA-A CBC 15 15 0% 25-Jul-14 14-Aug-14 09-Sep-14 29-Sep-14 31
CBCL1AA-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBC 8 8 0% 15-Aug-14 26-Aug-14 30-Sep-14 09-Oct-14 31
CBCL1AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA A CBC 23 23 0% 15-Jul-14 14-Aug-14 27-Aug-14 29-Sep-14 31
P-CBS-4240 INITIAL MATERIAL PROCUREMENT (mechanical) - CBS-1 15 15 0% 30-Aug-11 20-Sep-11 14-Oct-11 03-Nov-11 31
P-CBS-4250 ALL MATERIALS ARRIVE (mechanical) - CBS-1 0 0 0% 26-Oct-11 13-Dec-11 31
P-CBS-4410 BALANCE OF MATERIAL PROCUREMENT (mechanical) - CBS-1 25 25 0% 21-Sep-11 26-Oct-11 04-Nov-11 13-Dec-11 31
P-CBS-4480 VA/JVT REVIEW INITIAL MATERIAL SUBMITTAL (mechanical) - CBS-1 15 15 0% 09-Aug-11 29-Aug-11 22-Sep-11 13-Oct-11 31
P-CBS-4820 KT REVIEW INITIAL MATERIAL SUBMITTAL (mechanical) - CBS-1 10 10 0% 26-Jul-11 08-Aug-11 08-Sep-11 21-Sep-11 31
STR1-5240 KT PREPARES EROSION CONTROL PLAN - FILE FOR NOI 15 15 0% 07-Sep-11 27-Sep-11 21-Oct-11 10-Nov-11 31
STR1-5260 EPA PERMIT - SWPPP 10 10 0% 21-Sep-11 04-Oct-11 04-Nov-11 18-Nov-11 31
CBNL2AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA A CBN 13 13 0% 13-Jan-14 30-Jan-14 27-Feb-14 17-Mar-14 31
CBNL2AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA B CBN 12 12 0% 21-Jan-14 05-Feb-14 06-Mar-14 21-Mar-14 31
SITSWSP-0200 UNDERGROUND DEMOLITION - SOUTH PARCEL 30 30 0% 08-Nov-11 27-Dec-11 29-Dec-11 13-Feb-12 31
RESL1SO-0910 FRAMING/INWALL ROUGH - LVL-1 SUPP RES 20 20 0% 08-Jan-15 05-Feb-15 25-Feb-15 24-Mar-15 32
RESL3LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 LAB RES 15 15 0% 13-Apr-15 01-May-15 28-May-... 17-Jun-15 32
RESL3SO-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 SUPP RES 15 15 0% 13-Apr-15 01-May-15 28-May-... 17-Jun-15 32
RESL3SO-8880 CLEAN-UP/PRE PUNCH - LVL-3 SUPP RES 10 10 0% 23-Jun-15 07-Jul-15 07-Aug-15 20-Aug-15 32
CBSL3L3-2800 WALL ROUGH-IN - LVL-3 CBS 5 5 0% 21-Oct-11 26-Oct-11 30-Nov-11 05-Dec-11 32
STR1-5220 AURORA PERMIT APPROVAL - CBS ROOF DRAIN 20 20 0% 03-Nov-11 05-Dec-11 22-Dec-11 23-Jan-12 32
ENCL1L1-1630 SET TRANFORMERS - LVL-1 ENC 3 3 0% 12-Feb-13 14-Feb-13 28-Mar-13 01-Apr-13 32
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
20 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 101
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ENCL1L1-1650 SET GENERATORS - LVL-1 ENC 3 3 0% 12-Feb-13 14-Feb-13 28-Mar-13 01-Apr-13 32
DATSLSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL DAT 33 33 0% 10-Feb-12 20-Mar-12 20-Mar-12 26-Apr-12 32
CBNL2L2-0540 ERECT EXTERIOR STUDS - LVL-2 CBN 15 15 0% 21-May-13 14-Jun-13 18-Jul-13 12-Aug-13 33
CBNL2L2-0725 SPRAY-ON FIREPROOFING - LVL-2 CBN 10 10 0% 03-May-13 20-May-13 01-Jul-13 16-Jul-13 33
SITSWSP-0280 ABOVE GROUND DEMOLITION - SOUTH PARCEL 25 25 0% 27-Oct-11 06-Dec-11 20-Dec-11 30-Jan-12 33
PVSP3AC-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA C PVS 4 4 0% 31-Aug-12 07-Sep-12 29-Oct-12 02-Nov-12 34
CONAASL-3210 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-A CON 7 7 0% 08-Mar-12 16-Mar-12 10-May-... 21-May-12 35
CONL1AC-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-C CON 10 10 0% 17-Nov-14 01-Dec-14 08-Jan-15 22-Jan-15 35
AAAA-5610 VA PROVIDES CONSENT TO SUBCONTRACT (earthwork) - STR-1 0 0 0% 27-Sep-11 17-Nov-11 35
STR1-5710 VA REVIEW BID TABS (earthwork) - STR-1 5 5 0% 21-Sep-11 27-Sep-11 10-Nov-11 17-Nov-11 35
CBCSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK CBC 25 25 0% 16-Jun-14 28-Jul-14 15-Aug-14 26-Sep-14 35
CBCSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK CBC 30 30 0% 29-Jul-14 18-Sep-14 29-Sep-14 14-Nov-14 35
CBCSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK CBC 6 6 0% 19-May-14 29-May-14 21-Jul-14 29-Jul-14 35
CBCSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK CBC 10 10 0% 29-May-14 13-Jun-14 29-Jul-14 14-Aug-14 35
STR1-4250 AWARD EXCAVATION CONTRACT STR-1 20 20 0% 28-Sep-11 26-Oct-11 18-Nov-11 19-Dec-11 35
STR1-5230 SUBCONTRACTOR PRICING (earthwork) - STR-1 25 25 0% 26-Jul-11 29-Aug-11 14-Sep-11 19-Oct-11 35
STR1-5700 PREPARE BID TABS (earthwork) - STR-1 15 15 0% 30-Aug-11 20-Sep-11 20-Oct-11 09-Nov-11 35
CREDIT-1418 SUBCONTRACTOR PRICING FOR CREDIT UNION DEMO 25 25 0% 26-Jul-11 29-Aug-11 14-Sep-11 19-Oct-11 35
CREDIT-1468 PREPARE BID TABS - CREDIT UNION DEMO 15 15 0% 30-Aug-11 20-Sep-11 20-Oct-11 09-Nov-11 35
DATL2DE-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 DENTAL DAT 45 45 0% 18-Feb-14 21-Apr-14 08-Apr-14 10-Jun-14 35
DATL2DE-0910 FRAMING/INWALL ROUGH - LVL-2 DENTAL DAT 45 45 0% 25-Feb-14 28-Apr-14 15-Apr-14 17-Jun-14 35
DATL2DE-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 DENTAL DAT 25 25 0% 01-Apr-14 05-May-14 20-May-... 24-Jun-14 35
DATL3IL-0901 TRIM-OUT MEP (ORS) (AHU9) - LVL-3 INTER LVL DAT 5 5 0% 27-Oct-14 31-Oct-14 17-Dec-14 23-Dec-14 35
DATL3HY-0977 INSTALL OWNER FIXED FF&E - LVL-3 HYBRID CVOR DAT 20 20 0% 26-Sep-14 24-Oct-14 18-Nov-14 16-Dec-14 35
DATL3HY-8880 CLEAN-UP/PRE PUNCH - LVL-3 HYBRID CVOR DAT 5 5 0% 27-Oct-14 31-Oct-14 17-Dec-14 23-Dec-14 35
DATL3CA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 CATH LABS DAT 20 20 0% 08-Apr-14 05-May-14 28-May-... 24-Jun-14 35
PVSP3AE-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA E PVS 5 5 0% 14-Sep-12 24-Sep-12 14-Nov-12 20-Nov-12 35
PVSP3AE-0335 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA E PVS 21 21 0% 09-Aug-12 14-Sep-12 09-Oct-12 13-Nov-12 35
PVSP3AE-0332 FORM/PLACE FTGS/ COLUMNS - PKG LVL-3 AREA E PVS 15 15 0% 09-Aug-12 05-Sep-12 09-Oct-12 01-Nov-12 35
SITSWSW-260 OVERLOT GRADING - FULL CAMPUS 15 15 0% 08-Nov-11 26-Nov-11 22-Dec-11 10-Jan-12 36
PVSP3AD-0332 FORM/PLACE FTGS/WALLS/COLUMNS - PKG LVL-3 AREA D PVS 15 15 0% 20-Jul-12 16-Aug-12 24-Sep-12 16-Oct-12 36
PVSP3AD-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA D PVS 4 4 0% 13-Jul-12 20-Jul-12 17-Sep-12 21-Sep-12 36
RESSLIL-1517 TRIM-OUT MEP/FIRE PROTECTION - INTER LVL RES 25 25 0% 04-May-15 08-Jun-15 25-Jun-15 30-Jul-15 37
CBCESWE-0440 INSTALL PRECAST PANELS - WEST ELEV CBC 4 4 0% 24-Feb-14 27-Feb-14 25-Apr-14 01-May-14 37
CBCESWE-0870 INSTALL CURTAIN WALL - WEST ELEV CBC 20 20 0% 28-Feb-14 01-Apr-14 02-May-... 06-Jun-14 37
P-CBS-4220 SUBMITTAL DEVELOPMENT BALANCE OF MATERIAL (mechanical) - CBS-1 20 9 55% 12-Jul-11 A 05-Aug-11 16-Sep-11 28-Sep-11 37
P-CBS-4830 VA/JVT REVIEW BALANCE OF MATERIAL SUBMITTALS (mechanical) - CBS-1 15 15 0% 22-Aug-11 12-Sep-11 14-Oct-11 03-Nov-11 37
P-CBS-4230 KT REVIEW BALANCE OF MATERIAL SUBMITTALS (mechanical) - CBS-1 10 10 0% 08-Aug-11 19-Aug-11 29-Sep-11 13-Oct-11 37
CBNL1AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA B CBN 12 12 0% 26-Dec-13 13-Jan-14 20-Feb-14 07-Mar-14 37
CBNL1AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA A CBN 13 13 0% 18-Dec-13 07-Jan-14 13-Feb-14 03-Mar-14 37
CBNSLSL-3200 UNDERSLAB UTILITIES - SERV LVL CBN 15 15 0% 11-Oct-12 05-Nov-12 13-Dec-12 07-Jan-13 37
ZZZZCBN-9999 FINISH CBN CONSTRUCTION (finish milestone) 0 0 0% 20-Jan-15 26-Feb-15 37
XXXXCBN-0500 CBN OVERALL DURATION 953 953 0% 12-Jun-12 20-Jan-15 27-Aug-12 26-Feb-15 37
CBNCOCO-1599 BUILDING FLUSH - CBN 20 20 0% 31-Dec-14 20-Jan-15 07-Feb-15 26-Feb-15 37
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
21 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 102
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBNSLSL-8890 DRILL/PLACE CAISSONS (with concourse) - SERV LVL CBN 15 15 0% 12-Jun-12 06-Jul-12 17-Aug-12 11-Sep-12 38
PVNL1L1-1560 ROUGH-IN MEP/FIRE PROTECTION - LVL-1 PVN 25 25 0% 08-Jul-14 11-Aug-14 03-Sep-14 07-Oct-14 40
PVNL2L2-1580 ROUGH-IN MEP/FIRE PROTECTION - LVL-2 PVN 25 25 0% 22-Jul-14 25-Aug-14 17-Sep-14 22-Oct-14 40
PVNL3L3-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-3 PVN 25 25 0% 05-Aug-14 09-Sep-14 01-Oct-14 05-Nov-14 40
PVNL4L4-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-4 PVN 25 25 0% 19-Aug-14 23-Sep-14 15-Oct-14 21-Nov-14 40
PVNL5L5-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-5 PVN 25 25 0% 03-Sep-14 07-Oct-14 30-Oct-14 05-Dec-14 40
CBSSWSW-2310 GROUND RING - SITEWORK CBS 10 10 0% 07-Nov-11 21-Nov-11 09-Jan-12 23-Jan-12 40
DVAPOPO-4870 VA PROVIDE MED EQUIP COORDINATED CDS (dental) - DAT 60 60 0% 14-May-13 07-Aug-13 11-Jul-13 03-Oct-13 40
PVSINP1-0990 GARAGE FINISHES - - PKG LVL-3 PVS 30 30 0% 11-Jul-13 21-Aug-13 06-Sep-13 17-Oct-13 40
DATL1MR-0910 FRAMING/INWALL ROUGH - LVL-1 MRI/CT DAT 40 40 0% 17-Jan-14 17-Mar-14 18-Mar-14 12-May-14 40
DATL1MR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 MRI/CT DAT 25 25 0% 18-Mar-14 21-Apr-14 13-May-... 17-Jun-14 40
DATL1MR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 MRI/CT DAT 55 55 0% 22-Apr-14 09-Jul-14 18-Jun-14 04-Sep-14 40
DATL1SC-0990 INSTALL INTERIOR FINISHES - LVL-1 SOUTH CORR DAT 55 55 0% 10-Jul-14 25-Sep-14 05-Sep-14 25-Nov-14 40
DATL2IL-1400 ROUGH-IN MEP/FIRE PROTECTION (DENTAL) (AHU14) - LVL-2 INTER LVL DAT 65 65 0% 04-Nov-13 07-Feb-14 03-Jan-14 07-Apr-14 40
DATPHNP-1590 START-UP MECH EQUIP - NORTH PENT MECH DAT 30 30 0% 19-Sep-14 31-Oct-14 18-Nov-14 31-Dec-14 40
SITSWSW-0001 KT ATTAIN APPROVAL FOR TIE-BACKS UNDER ROADWAYS - POTHOLING 20 20 0% 12-Oct-11 08-Nov-11 12-Dec-11 10-Jan-12 40
PVSP3AF-0332 FORM/PLACE ELEV PITS/ FTGS/WALLS/COLUMNS - PKG LVL-3 AREA F PVS 15 15 0% 04-Sep-12 28-Sep-12 09-Nov-12 04-Dec-12 40
PVSP3AF-0380 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA F PVS 10 10 0% 30-Oct-12 16-Nov-12 08-Jan-13 23-Jan-13 40
PVSP3AF-3220 REMOVE ACCESS RAMP/INFILL WALL - PKG LVL-3 AREA F PVS 20 20 0% 28-Sep-12 30-Oct-12 06-Dec-12 07-Jan-13 40
CONACSL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-C CON 15 15 0% 16-Apr-12 11-May-12 28-Jun-12 23-Jul-12 41
PVNSLPK-0323 FORM/PLACE RAMP WALLS - SERV LVL PARK PVN 30 30 0% 29-Oct-13 17-Dec-13 07-Jan-14 21-Feb-14 41
CBCESEE-0440 INSTALL METAL PANELS - EAST ELEV CBC 5 5 0% 18-Mar-14 25-Mar-14 30-May-... 06-Jun-14 41
RESSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK RES 45 45 0% 13-Apr-15 22-Jun-15 17-Jun-15 31-Aug-15 41
RESSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK RES 45 45 0% 14-May-15 24-Jul-15 20-Jul-15 02-Oct-15 41
PVSPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVS) 20 20 0% 27-Jan-12 24-Feb-12 27-Mar-12 23-Apr-12 41
CONPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CON) 20 20 0% 28-Dec-11 26-Jan-12 28-Feb-12 26-Mar-12 41
IBPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 35 35 0% 23-Apr-12 11-Jun-12 20-Jun-12 08-Aug-12 41
ENCPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (ENC) 40 40 0% 27-Feb-12 20-Apr-12 24-Apr-12 19-Jun-12 41
CBPOPO-4890 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CBC/CBN) 15 15 0% 25-Jul-12 14-Aug-12 21-Sep-12 11-Oct-12 41
CBPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CBC/CBN) 30 30 0% 12-Jun-12 24-Jul-12 09-Aug-12 20-Sep-12 41
CBPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CBC/CBN) 20 20 0% 15-Aug-12 12-Sep-12 12-Oct-12 09-Nov-12 41
CBPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (CBC/CBN) 20 20 0% 13-Sep-12 10-Oct-12 13-Nov-12 12-Dec-12 41
SITSWSP-0100 MOBILIZE CONSTRUCTION RESOURCES - SOUTH PARCEL 5 5 0% 14-Oct-11 20-Oct-11 20-Dec-11 28-Dec-11 41
PVSSWHL-0280 HARDSCAPE - SITEWORK PVS 60 60 0% 14-Apr-14 24-Jul-14 24-Jun-14 03-Oct-14 42
PVSSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK PVS 25 25 0% 25-Jul-14 05-Sep-14 06-Oct-14 14-Nov-14 42
IBNSLSL-3110 SET/BACKFILL DUCTBANKS - SERV LVL IBN 5 5 0% 25-Sep-12 02-Oct-12 06-Dec-12 12-Dec-12 43
IBNSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL IBN 5 5 0% 03-Oct-12 09-Oct-12 13-Dec-12 20-Dec-12 43
DATESAC-0530 INSTALL/MAINTAIN MAN/MATERIAL HOIST - ALL ELEVS AR-C (DAT) 499 499 0% 16-Apr-13 27-Aug-14 24-Jul-13 09-Oct-14 43
DATESAF-0530 INSTALL/MAINTAIN MAN/MATERIAL HOIST - ALL ELEVS AR-F (DAT) 499 499 0% 16-Apr-13 27-Aug-14 24-Jul-13 09-Oct-14 43
STR1-5650 AWARD CONTRACT - DEWATERING 20 20 0% 07-Sep-11 04-Oct-11 08-Nov-11 08-Dec-11 43
STR1-5660 PREPARE SHOP DRAWINGS - DEWATERING 20 20 0% 05-Oct-11 02-Nov-11 09-Dec-11 09-Jan-12 43
STR1-5670 REVIEW/APPROVE SHOP DRAWINGS - DEWATERING 10 10 0% 03-Nov-11 17-Nov-11 10-Jan-12 24-Jan-12 43
STR1-5680 PROCURE DEWATERING EQUIPMENT 20 20 0% 18-Nov-11 19-Dec-11 25-Jan-12 22-Feb-12 43
CBNESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV CBN 35 35 0% 20-Aug-13 17-Oct-13 31-Oct-13 27-Dec-13 43
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
22 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 103
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBNL3L3-0540 ERECT EXTERIOR STUDS - LVL-3 CBN 15 15 0% 03-May-13 29-May-13 18-Jul-13 12-Aug-13 43
CBNL3L3-0725 SPRAY-ON FIREPROOFING - LVL-3 CBN 10 10 0% 15-Apr-13 02-May-13 01-Jul-13 16-Jul-13 43
PVSP3AB-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA B PVS 4 4 0% 08-Aug-12 14-Aug-12 22-Oct-12 25-Oct-12 43
PVSP3AF-3200 UNDERSLAB UTILITIES - PKG LVL-3 AREA F PVS 5 5 0% 12-Oct-12 23-Oct-12 27-Dec-12 03-Jan-13 43
PVSP3AF-0335 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA F PVS 25 25 0% 04-Sep-12 12-Oct-12 15-Nov-12 26-Dec-12 43
PVSP3AF-3230 BACKFILL RAMP - PKG LVL-3 AREA F PVS 5 5 0% 23-Oct-12 30-Oct-12 04-Jan-13 10-Jan-13 43
CBSSTST-2400 INTERIOR STEEL FRAMING LEVEL 1,2,3,4 - STRUCTURE CBS 15 15 0% 26-Jul-11 11-Aug-11 16-Sep-11 03-Oct-11 44
RESL2LA-0977 INSTALL OWNER FIXED FF&E - LVL-2 LAB RES 20 20 0% 06-May-15 03-Jun-15 10-Jul-15 06-Aug-15 45
RESL2LA-8880 CLEAN-UP/PRE PUNCH - LVL-2 LAB RES 10 10 0% 04-Jun-15 17-Jun-15 07-Aug-15 20-Aug-15 45
ENCSLSL-0510 ERECT STRUCTURAL STEEL/DECK (PIPE BSMT LID)- SERV LVL ENC 8 8 0% 10-Jul-12 23-Jul-12 27-Sep-12 08-Oct-12 45
ENCSLSL-0322 FORM/REIN/R-I/PLACE TOPPING SLAB (PIPE BSMT LID) - SERV LVL ENC 3 3 0% 24-Jul-12 27-Jul-12 09-Oct-12 11-Oct-12 45
ENCSLSL-0720 SPRAY ON FIREPROOFING - SERV LVL ENC 5 5 0% 30-Jul-12 07-Aug-12 12-Oct-12 22-Oct-12 45
DATL1RO-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 RAD OFFICES DAT 20 20 0% 18-Dec-13 16-Jan-14 25-Feb-14 24-Mar-14 45
RESALAL-0555 ERECT STAIRS ST1 - ALL LVLS RES 15 15 0% 16-Dec-14 07-Jan-15 25-Feb-15 17-Mar-15 47
RESALAL-0556 ERECT STAIRS ST2 - ALL LVLS RES 15 15 0% 31-Dec-14 22-Jan-15 11-Mar-15 31-Mar-15 47
RESL2SO-0910 FRAMING/INWALL ROUGH - LVL-2 SUPP RES 20 20 0% 16-Feb-15 13-Mar-15 22-Apr-15 19-May-15 47
RESL2SO-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SUPP RES 15 15 0% 02-Mar-15 20-Mar-15 06-May-... 27-May-15 47
CONACSL-3210 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-C CON 7 7 0% 22-Mar-12 02-Apr-12 15-Jun-12 26-Jun-12 47
CBSL3L3-2790 FRAMING - LVL-3 CBS 5 5 0% 27-Sep-11 01-Oct-11 23-Nov-11 29-Nov-11 47
HOIMHMH-0100 INSTALL/MAINTAIN MAN/MATERIAL HOIST (RES) 240 240 0% 04-Sep-14 01-May-15 04-Sep-14 17-Jun-15 47
CBCPHEL-1630 INTERIOR FINISHES - PENT ELEC CBC 30 30 0% 23-Jun-14 04-Aug-14 28-Aug-14 09-Oct-14 47
DVAPOPO-5010 VA PROVIDE FIXED FF&E SHOP DRAWINGS - CBN 30 30 0% 12-Jun-13 24-Jul-13 19-Aug-13 30-Sep-13 47
DATPGPG-1516 R-I OVERHEAD MEP/FIRE PROT - PIPE GALLERY DAT 15 15 0% 02-Jan-13 23-Jan-13 12-Mar-13 01-Apr-13 47
IBNSLSL-3200 UNDERSLAB UTILITIES - SERV LVL IBN 15 15 0% 30-Aug-12 24-Sep-12 19-Nov-12 12-Dec-12 48
DATSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK DAT 45 45 0% 13-May-14 31-Jul-14 07-Aug-14 21-Oct-14 48
DATSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK DAT 20 20 0% 19-Jun-14 22-Jul-14 11-Sep-14 10-Oct-14 48
PVSINP2-8880 CLEAN-UP/PRE PUNCH - PKG LVL-2 PVS 10 10 0% 20-Sep-13 03-Oct-13 03-Dec-13 16-Dec-13 49
PVSP3AA-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA A PVS 4 4 0% 13-Jul-12 20-Jul-12 08-Oct-12 11-Oct-12 49
STR1A-5020 AWARD DRILLED PIERS CONTRACT - STR-1A/IFO-2 20 20 0% 07-Sep-11 04-Oct-11 18-Nov-11 19-Dec-11 50
STR1A-5030 MOBILIZE DRILLED PIER CONTRACTOR - STR-1A/IFO-2 10 10 0% 10-Nov-11 28-Nov-11 27-Jan-12 09-Feb-12 50
STR1A-5110 PREPARE DRILLED PIER SHOP DRAWINGS - STR-1A/IFO-2 15 15 0% 21-Sep-11 12-Oct-11 06-Dec-11 27-Dec-11 50
STR1A-5120 KT APPROVE DRILLED PIER SHOP DRAWINGS - STR-1A/IFO-2 10 10 0% 13-Oct-11 26-Oct-11 28-Dec-11 11-Jan-12 50
STR1A-5130 VA APPROVE DRILLED PIER SHOP DRAWINGS - STR-1A/IFO-2 20 20 0% 13-Oct-11 09-Nov-11 28-Dec-11 26-Jan-12 50
CBNESSE-877 INSTALL CURTAIN WALL - NORTH ELEV CBN 35 35 0% 08-Aug-13 04-Oct-13 31-Oct-13 27-Dec-13 50
CBNESNE-0440 INSTALL PRECAST PANELS - NORTH ELEV CBN 8 8 0% 25-Jul-13 06-Aug-13 18-Oct-13 29-Oct-13 50
DATL1FL-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 FLURO/UTLSND DAT 25 25 0% 27-Nov-13 02-Jan-14 11-Feb-14 17-Mar-14 50
DATL1MR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 MRI/CT DAT 20 20 0% 03-Jan-14 31-Jan-14 18-Mar-14 14-Apr-14 50
PVNESES-0750 INSTALL EXTERIOR SKIN FINISHES @ GARAGE - ALL ELEVATIONS PVN 50 50 0% 14-Aug-14 04-Nov-14 07-Nov-14 28-Jan-15 51
CBSSTST-4060 SLAB ON GRADE - STRUCTURE CBS 5 5 0% 31-Oct-11 04-Nov-11 03-Jan-12 07-Jan-12 51
AAAA-5580 VA APPROVE LOW VOLTAGE CONTRACTOR DESIGN ASSIST 0 0 0% 07-Sep-11 21-Nov-11 51
RESSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK RES 30 30 0% 29-Jan-15 17-Mar-15 24-Apr-15 16-Jun-15 51
DATL3IL-1547 ERECT INTER STEEL/TOPPING (AREA D) - LVL-3 INTER LVL DAT 15 15 0% 01-Feb-13 25-Feb-13 26-Apr-13 23-May-13 51
DATL3IL-1557 ERECT INTER STEEL/TOPPING (AREA E) - LVL-3 INTER LVL DAT 15 15 0% 19-Feb-13 12-Mar-13 16-May-... 10-Jun-13 51
DATL3IL-1567 ERECT INTER STEEL/TOPPING (AREA F) - LVL-3 INTER LVL DAT 15 15 0% 05-Mar-13 28-Mar-13 03-Jun-13 27-Jun-13 51
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
23 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 104
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL3IL-1537 ERECT INTER STEEL/TOPPING (AREA C) - LVL-3 INTER LVL DAT 15 15 0% 17-Jan-13 07-Feb-13 09-Apr-13 06-May-13 51
DATL2IL-1537 ERECT INTER STEEL/TOPPING (AREA C) - LVL-2 INTER LVL DAT 15 15 0% 20-Nov-12 13-Dec-12 11-Feb-13 05-Mar-13 51
DATL2IL-1557 ERECT INTER STEEL/TOPPING (AREA E) - LVL-2 INTER LVL DAT 15 15 0% 24-Dec-12 15-Jan-13 15-Mar-13 08-Apr-13 51
DATL2IL-1547 ERECT INTER STEEL/TOPPING (AREA D) - LVL-2 INTER LVL DAT 15 15 0% 07-Dec-12 31-Dec-12 27-Feb-13 21-Mar-13 51
DATESAF-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-F DAT 15 15 0% 29-Mar-13 23-Apr-13 28-Jun-13 23-Jul-13 51
RESL2SO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SUPP RES 45 45 0% 16-Mar-15 15-May-15 28-May-... 30-Jul-15 52
CONAASS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-A CON 23 23 0% 11-Feb-13 19-Mar-13 10-May-... 18-Jun-13 52
CONAASS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-A CON 5 5 0% 20-Mar-13 26-Mar-13 20-Jun-13 27-Jun-13 52
CONESAA-0870 INSTALL CURTAIN WALL (NORTH ELEV) - AR-A CON 20 20 0% 06-Jun-13 09-Jul-13 05-Sep-13 07-Oct-13 52
CONESAA-870 INSTALL CURTAIN WALL (WEST ELEV) - AR-A CON 20 20 0% 06-Jun-13 09-Jul-13 05-Sep-13 07-Oct-13 52
CONESAA-880 INSTALL CURTAIN WALL (EAST ELEV) - AR-A CON 20 20 0% 06-Jun-13 09-Jul-13 05-Sep-13 07-Oct-13 52
CONESAA-0855 INSTALL BLAST PROOF PANELS @ LVL-1 (NORTH ELEV) - AR-A CON 12 12 0% 28-Mar-13 16-Apr-13 28-Jun-13 18-Jul-13 52
CONESAC-880 INSTALL CURTAIN WALL (EAST ELEV) - AR-C CON 15 15 0% 10-May-13 04-Jun-13 09-Aug-13 04-Sep-13 52
CONESAC-0870 INSTALL CURTAIN WALL (WEST ELEV) - AR-C CON 15 15 0% 10-May-13 04-Jun-13 09-Aug-13 04-Sep-13 52
CONESAC-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR-C CON 12 12 0% 18-Apr-13 09-May-13 19-Jul-13 08-Aug-13 52
CONESAC-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-C CON 12 12 0% 18-Apr-13 09-May-13 19-Jul-13 08-Aug-13 52
CONESAE-0870 INSTALL CURTAIN WALL (SOUTH ELEV) - AR-E CON 20 20 0% 15-Aug-13 17-Sep-13 12-Nov-13 12-Dec-13 52
CONESAE-870 INSTALL CURTAIN WALL (EAST ELEV) - AR-E CON 20 20 0% 15-Aug-13 17-Sep-13 12-Nov-13 12-Dec-13 52
CONESAE-880 INSTALL CURTAIN WALL (WEST ELEV) - AR-E CON 20 20 0% 15-Aug-13 17-Sep-13 12-Nov-13 12-Dec-13 52
CONESAD-0870 INSTALL CURTAIN WALL (WEST ELEV) - AR-D CON 20 20 0% 11-Jul-13 13-Aug-13 08-Oct-13 08-Nov-13 52
CONESAD-880 INSTALL CURTAIN WALL (EAST ELEV) - AR-D CON 20 20 0% 11-Jul-13 13-Aug-13 08-Oct-13 08-Nov-13 52
CONESAB-0870 INSTALL CURTAIN WALL (WEST ELEV) - AR-B CON 20 20 0% 19-Sep-13 21-Oct-13 13-Dec-13 14-Jan-14 52
CONESAB-880 INSTALL CURTAIN WALL (EAST ELEV) - AR-B CON 20 20 0% 19-Sep-13 21-Oct-13 13-Dec-13 14-Jan-14 52
CBSL3L3-2780 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-3 CBS 5 5 0% 15-Sep-11 20-Sep-11 17-Nov-11 22-Nov-11 52
CBCPHME-1590 START-UP MECH EQUIP - PENT MECH CBC 20 20 0% 19-Aug-14 16-Sep-14 03-Nov-14 02-Dec-14 52
AAAAIBT-0100 START IBN CONSTRUCTION (start milestone) 0 0 0% 27-Apr-12 18-Jun-12 52
CONHBAE-8890 TEAR DOWN STAGE - HIGH BAY AR-E CON 7 7 0% 19-Aug-14 27-Aug-14 05-Nov-14 14-Nov-14 54
CBNSLSL-0390 PERIMETER DRAINS/BACKFILL PIERCAPS/GRADE BEAMS - SERV LVL CBN 14 14 0% 07-Sep-12 01-Oct-12 07-Dec-12 28-Dec-12 54
CBNSLSL-3110 SET/BACKFILL DUCTBANKS - SERV LVL CBN 5 5 0% 02-Oct-12 08-Oct-12 31-Dec-12 07-Jan-13 54
CONHBAB-0910 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-B CON 15 15 0% 25-Oct-13 15-Nov-13 16-Jan-14 06-Feb-14 55
CONHBAB-0920 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-B CON 15 15 0% 18-Nov-13 09-Dec-13 07-Feb-14 28-Feb-14 55
CONHBAB-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-B CON 10 10 0% 02-Jan-14 15-Jan-14 24-Mar-14 04-Apr-14 55
CONHBAB-0990 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-B CON 15 15 0% 10-Dec-13 31-Dec-13 03-Mar-14 21-Mar-14 55
CONHBAB-8890 TEAR DOWN STAGE - HIGH BAY AR-B CON 7 7 0% 16-Jan-14 27-Jan-14 07-Apr-14 15-Apr-14 55
CONHBAB-1516 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-B CON 15 15 0% 03-Oct-13 24-Oct-13 24-Dec-13 15-Jan-14 55
CONHBAD-0910 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-D CON 15 15 0% 19-Feb-14 11-Mar-14 07-May-... 28-May-14 55
CONHBAD-0920 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-D CON 16 16 0% 12-Mar-14 02-Apr-14 29-May-... 19-Jun-14 55
CONHBAD-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-D CON 10 10 0% 24-Apr-14 07-May-14 14-Jul-14 25-Jul-14 55
CONHBAD-0990 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-D CON 15 15 0% 03-Apr-14 23-Apr-14 20-Jun-14 11-Jul-14 55
CONHBAD-1516 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-D CON 15 15 0% 28-Jan-14 18-Feb-14 16-Apr-14 06-May-14 55
IBPOPO-5700 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 15 15 0% 12-Jun-12 02-Jul-12 29-Aug-12 19-Sep-12 55
IBPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 20 20 0% 03-Jul-12 31-Jul-12 20-Sep-12 18-Oct-12 55
IBPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (IBS/IBN) 20 20 0% 01-Aug-12 28-Aug-12 19-Oct-12 16-Nov-12 55
CBNPHEL-1630 INTERIOR FINISHES - PENT ELEC CBN 30 30 0% 13-Jun-14 25-Jul-14 02-Sep-14 13-Oct-14 55
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
24 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 105
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL3DI-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 DIGEST DIS DAT 45 45 0% 02-Jul-14 04-Sep-14 19-Sep-14 25-Nov-14 55
DATL3IL-0510 ERECT INTER STEEL/TOPPING (AREA A) - LVL-3 INTER LVL DAT 15 15 0% 21-Mar-13 15-Apr-13 28-Jun-13 23-Jul-13 56
DATL3IL-1527 ERECT INTER STEEL/TOPPING (AREA B) - LVL-3 INTER LVL DAT 15 15 0% 08-Apr-13 03-May-13 16-Jul-13 09-Aug-13 56
DATL2IL-0510 ERECT INTER STEEL/TOPPING (AREA A) - LVL-2 INTER LVL DAT 15 15 0% 17-Jan-13 07-Feb-13 18-Apr-13 14-May-13 56
DATL2IL-1527 ERECT INTER STEEL/TOPPING (AREA B) - LVL-2 INTER LVL DAT 15 15 0% 01-Feb-13 25-Feb-13 07-May-... 31-May-13 56
DATL2IL-1567 ERECT INTER STEEL/TOPPING (AREA F) - LVL-2 INTER LVL DAT 15 15 0% 02-Jan-13 24-Jan-13 01-Apr-13 25-Apr-13 56
DATESAB-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-B DAT 15 15 0% 06-May-13 30-May-13 12-Aug-13 05-Sep-13 56
RESALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS RES 15 15 0% 13-Apr-15 01-May-15 02-Jul-15 23-Jul-15 57
RESALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS RES 20 20 0% 04-May-15 01-Jun-15 24-Jul-15 20-Aug-15 57
RESL2SO-8880 CLEAN-UP/PRE PUNCH - LVL-2 SUPP RES 10 10 0% 18-May-15 01-Jun-15 07-Aug-15 20-Aug-15 57
RESSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK RES 16 16 0% 12-Feb-15 06-Mar-15 19-May-... 16-Jun-15 57
SITSWBW-328 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - SOUTH WHEELING ST. 25 25 0% 13-Sep-13 23-Oct-13 12-May-... 24-Jun-14 57
PVSP3AE-3220 FORM/PLACE PIER CAPS - PKG LVL-3 AREA E PVS 4 4 0% 09-Aug-12 16-Aug-12 15-Nov-12 20-Nov-12 57
CONL1DR-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-D RESTRMS CON 20 20 0% 24-Jun-14 22-Jul-14 16-Sep-14 13-Oct-14 58
CONL1DR-0910 FRAMING/INWALL ROUGH - LVL-1 AR-D RESTRMS CON 15 15 0% 23-Jul-14 12-Aug-14 14-Oct-14 04-Nov-14 58
CONL1DR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D RESTRMS CON 12 12 0% 13-Aug-14 28-Aug-14 05-Nov-14 24-Nov-14 58
CONL1DR-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-D RESTRMS CON 10 10 0% 13-Oct-14 27-Oct-14 08-Jan-15 22-Jan-15 58
CONL1DR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D RESTRMS CON 30 30 0% 29-Aug-14 10-Oct-14 25-Nov-14 07-Jan-15 58
CBNPHME-1590 START-UP MECH EQUIP - PENT MECH CBN 20 20 0% 11-Aug-14 08-Sep-14 03-Nov-14 02-Dec-14 58
AAAACON-0100 START CON CONSTRUCTION (start milestone) 0 0 0% 24-Apr-12 22-Jun-12 59
SITWSSW-298 CONSTRUCT ROADWAY - WHEELING ST. 8 8 0% 30-Jan-12 09-Feb-12 10-May-... 22-May-12 59
PVNALAL-3120 ERECT STAIR 1 - ALL LVLS PVN 20 20 0% 16-Jul-14 12-Aug-14 09-Oct-14 06-Nov-14 60
PVNALAL-3130 ERECT STAIR 2 - ALL LVLS PVN 20 20 0% 30-Jul-14 26-Aug-14 24-Oct-14 24-Nov-14 60
DATL2SL-0977 INSTALL OWNER FIXED FF&E - LVL-2 LABS DAT 20 20 0% 07-Aug-14 04-Sep-14 03-Nov-14 02-Dec-14 60
DATL2SL-8880 CLEAN-UP/PRE PUNCH - LVL-2 SLEEP DAT 10 10 0% 05-Sep-14 18-Sep-14 03-Dec-14 16-Dec-14 60
CONESAB-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR B CON 12 12 0% 13-Aug-13 03-Sep-13 25-Nov-13 12-Dec-13 61
CONESAB-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-B CON 12 12 0% 13-Aug-13 03-Sep-13 25-Nov-13 12-Dec-13 61
CONALAL-1401 INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 6-7) - AREA A CON 25 25 0% 15-Jan-14 20-Feb-14 14-Apr-14 16-May-14 61
CONALAL-1403 INSTALL ELEVATORS SHAFT WALLS (GRIDLINE 15-16) - AREA B CON 25 25 0% 21-Feb-14 27-Mar-14 19-May-... 23-Jun-14 61
IBSSLSL-0510 ERECT STRUCTURAL STEEL/DECK - SERVICE LEVEL IBS 15 15 0% 30-Nov-12 24-Dec-12 08-Mar-13 01-Apr-13 61
IBSSLIL-0510 ERECT INTERSTITIAL STEEL/TOPPING - SERVICE LEVEL INTERSTITIAL LVL IBS 35 35 0% 28-Mar-13 29-May-13 15-Jul-13 12-Sep-13 61
IBSL1L1-0510 ERECT STRUCTURAL STEEL/DECK - LVL-1 IBS 15 15 0% 26-Dec-12 17-Jan-13 02-Apr-13 26-Apr-13 61
IBSL1L1-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 IBS 9 9 0% 07-Mar-13 20-Mar-13 21-Jun-13 05-Jul-13 61
IBSL3L3-0510 ERECT STRUCTURAL STEEL/DECK - LVL-3 IBS 15 15 0% 11-Feb-13 05-Mar-13 28-May-... 20-Jun-13 61
IBSL2L2-0510 ERECT STRUCTURAL STEEL/DECK - LVL-2 IBS 15 15 0% 18-Jan-13 08-Feb-13 29-Apr-13 24-May-13 61
IBSPBPB-0330 FORM/PLACE/PIER CAPS/TIE BEAMS/ELEV PITS/ WALLS/ COLUMNS/CORES - PIPE BSMT IBS 125 125 0% 27-Apr-12 29-Nov-12 14-Aug-12 07-Mar-13 61
STR1-5360 XCEL DESIGN & INSTALL - TEMP ELEC 40 40 0% 21-Sep-11 17-Nov-11 23-Dec-11 22-Feb-12 63
CONACL1-0330 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-C CON 9 9 0% 18-Dec-12 02-Jan-13 01-Apr-13 15-Apr-13 64
CONACL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-C CON 7 7 0% 03-Jan-13 11-Jan-13 16-Apr-13 26-Apr-13 64
CONACL1-0320 DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-C CON 6 6 0% 10-Dec-12 17-Dec-12 21-Mar-13 29-Mar-13 64
CONACL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-C CON 7 7 0% 14-Jan-13 24-Jan-13 29-Apr-13 10-May-13 64
CONACSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-C CON 24 24 0% 25-Jan-13 01-Mar-13 13-May-... 21-Jun-13 64
CONACSS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-C CON 15 15 0% 04-Mar-13 26-Mar-13 24-Jun-13 18-Jul-13 64
ENCPGPG-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY ENC 15 15 0% 17-Apr-12 14-May-12 09-Aug-12 04-Sep-12 64
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
25 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 106
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ENCPGPG-3200 UNDERSLAB UTILITIES - PIPE GALLERY ENC 8 8 0% 15-May-12 29-May-12 05-Sep-12 17-Sep-12 64
ENCPGPG-0380 FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY ENC 5 5 0% 30-May-12 05-Jun-12 18-Sep-12 25-Sep-12 64
CBNESWE-0440 INSTALL PRECAST PANELS - WEST ELEV CBN 4 4 0% 02-Aug-13 08-Aug-13 19-Nov-13 25-Nov-13 64
CBNESSE-887 INSTALL CURTAIN WALL - WEST ELEV CBN 20 20 0% 09-Aug-13 12-Sep-13 26-Nov-13 27-Dec-13 64
AAAA-4800 VA APPROVE MECHANICAL AND PLUMBING CONTRACTOR DESIGN ASSIST 0 0 0% 07-Sep-11 13-Dec-11 65
EEEEPVN-0000 PVN BLDG AVAILABLE FOR ENERGIZE 0 0 0% 07-Oct-14 13-Jan-15 65
STR1A-5080 KT APPROVE DUCTBANK/VAULT/DRAINAGE SHOP DRAWINGS (CON) - STR-1A/IFO-2 10 10 0% 05-Oct-11 19-Oct-11 12-Jan-12 26-Jan-12 65
STR1A-4930 PREPARE/SUBMIT DUCTBANK/VAULT SHOP/DRAINAGE DRAWINGS (CON) - STR-1A/IFO-2 20 20 0% 07-Sep-11 04-Oct-11 13-Dec-11 11-Jan-12 65
STR1A-4940 VA APPROVE DUCTBANK/VAULT/DRAINAGE SHOP DRAWINGS (CON) - STR-1A/IFO-2 20 20 0% 20-Oct-11 17-Nov-11 27-Jan-12 24-Feb-12 65
STR1A-4950 FABRICATE DUCTBANK/VAULT (CON) - STR-1A/IFO-2 25 25 0% 18-Nov-11 27-Dec-11 27-Feb-12 30-Mar-12 65
STR1A-5010 FIRST DUCTBANK/VAULT DELIVERY (CON) - STR-1A/IFO-2 0 0 0% 27-Dec-11 30-Mar-12 65
DATL3DI-0977 INSTALL OWNER FIXED FF&E - LVL-3 DIGEST DIS DAT 20 20 0% 07-Aug-14 04-Sep-14 10-Nov-14 09-Dec-14 65
DATL3DI-8880 CLEAN-UP/PRE PUNCH - LVL-3 DIGEST DIS DAT 10 10 0% 05-Sep-14 18-Sep-14 10-Dec-14 23-Dec-14 65
AAAARES-0100 START RES CONSTRUCTION (start milestone) 0 0 0% 31-Jan-14 07-Apr-14 66
DATESAA-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-A DAT 15 15 0% 16-Apr-13 13-May-13 12-Aug-13 05-Sep-13 66
PVSSWSW-3230 DRIVE SOLDIER PILES (REMAINING EAST SIDE) - PVS SITEWORK 10 10 0% 29-May-12 14-Jun-12 21-Sep-12 05-Oct-12 66
CBSL1L1-3280 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-1 CBS 15 15 0% 06-Aug-11 23-Aug-11 26-Oct-11 12-Nov-11 67
SITSWBW-248 DEMO/GRADING - INTERSEC WHEELING ST.. 10 10 0% 18-Oct-12 01-Nov-12 05-Feb-13 20-Feb-13 67
SITSWBW-268 CONSTRUCT ROADWAY - INTERSEC WHEELING ST. 15 15 0% 03-Dec-12 26-Dec-12 20-Mar-13 12-Apr-13 67
SITSWBW-258 INSTALL REMAINING UTILITIES - INTERSEC WHEELING ST. 17 17 0% 02-Nov-12 30-Nov-12 21-Feb-13 19-Mar-13 67
SITSWBW-238 PLACE EROSION PROTECTION/TRAFFIC CONTROL - INTERSEC WHEELING ST. 4 4 0% 10-Oct-12 16-Oct-12 30-Jan-13 04-Feb-13 67
IBSL1IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-1 INTERSTITIAL LVL IBS 35 35 0% 23-Apr-13 24-Jun-13 20-Aug-13 17-Oct-13 67
IBSL2L2-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 IBS 9 9 0% 01-Apr-13 15-Apr-13 29-Jul-13 12-Aug-13 67
IBSPHPH-0510 ERECT STRUCTURAL STEEL/DECK - PENT IBS 15 15 0% 07-Mar-13 29-Mar-13 02-Jul-13 26-Jul-13 67
CBNESEE-0440 INSTALL METAL PANELS - EAST ELEV CBN 5 5 0% 29-Aug-13 05-Sep-13 20-Dec-13 27-Dec-13 68
RESSLSL-0990 INTERIOR FINISHES (GENERAL) - SERV LVL RES 45 45 0% 19-Feb-15 23-Apr-15 28-May-... 30-Jul-15 68
RESSLSL-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL RES 30 30 0% 28-Jan-15 12-Mar-15 06-May-... 17-Jun-15 68
RESSLSL-8880 CLEAN-UP/PRE PUNCH - SERV LVL RES 15 15 0% 23-Apr-15 14-May-15 31-Jul-15 20-Aug-15 68
RESSLSL-0992 INTERIOR FINISHES (CART WASH) - SERV LVL RES 30 30 0% 12-Mar-15 23-Apr-15 18-Jun-15 30-Jul-15 68
RESSLSL-0994 INTERIOR FINISHES (SURGURY) - SERV LVL RES 30 30 0% 12-Mar-15 23-Apr-15 18-Jun-15 30-Jul-15 68
PVSSWSW-3250 BACKFILL RAMP (EAST SIDE) - PVS SITEWORK 5 5 0% 01-Jun-12 11-Jun-12 01-Oct-12 05-Oct-12 68
PVNSLPK-1666 PULL WIRE FROM CON - SER LVL PARK PVN 5 5 0% 25-Sep-14 01-Oct-14 07-Jan-15 13-Jan-15 69
PVSINP1-8880 CLEAN-UP/PRE PUNCH - PKG LVL-3 PVS 10 10 0% 22-Aug-13 05-Sep-13 03-Dec-13 16-Dec-13 69
IBNSLIL-0510 ERECT INTERSTITIAL STEEL/TOPPING - SERVICE LEVEL INTERSTITIAL LVL IBN 35 35 0% 20-Mar-13 20-May-13 22-Jul-13 19-Sep-13 70
STR1-5330 AWARD CONTRACT TO SUBCONTRACTOR - TEMP ELEC 20 20 0% 07-Sep-11 04-Oct-11 20-Dec-11 19-Jan-12 70
STR1-5340 PREPARE/SUBMIT DESIGN & SHOP DRAWINGS - TEMP ELEC 15 15 0% 05-Oct-11 26-Oct-11 20-Jan-12 09-Feb-12 70
STR1-5350 KT REVIEW/APPROVE DESIGN & SHOP DRAWINGS - TEMP ELEC 10 10 0% 27-Oct-11 09-Nov-11 10-Feb-12 24-Feb-12 70
STR1-5370 KT INSTALLS PHASE 1 - TEMP ELEC 20 20 0% 06-Dec-11 04-Jan-12 19-Mar-12 13-Apr-12 70
STR1-5690 PROCURE TEMP MATERIALS & EQUIPMENT - TEMP ELEC 15 15 0% 10-Nov-11 05-Dec-11 27-Feb-12 16-Mar-12 70
DATL2IL-0801 TRIM-OUT MEP (SLEEP LABS) (AHU8) - LVL-2 INTER LVL DAT 5 5 0% 31-Jul-14 06-Aug-14 10-Nov-14 17-Nov-14 70
DATL3DI-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 DIGEST DIS DAT 20 20 0% 22-Apr-14 19-May-14 31-Jul-14 27-Aug-14 70
DATL3OF-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 OFFICES DAT 20 20 0% 04-Jun-14 01-Jul-14 12-Sep-14 09-Oct-14 70
DATL3OF-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 OFFICES DAT 40 40 0% 18-Jun-14 13-Aug-14 26-Sep-14 25-Nov-14 70
DATL3OF-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 OFFICES DAT 20 20 0% 20-May-14 17-Jun-14 28-Aug-14 25-Sep-14 70
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
26 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 107
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL3OF-0910 FRAMING/INWALL ROUGH - LVL-3 OFFICES DAT 25 25 0% 20-May-14 24-Jun-14 28-Aug-14 02-Oct-14 70
PVSP3AF-3210 FORM/PLACE PIER CAPS - PKG LVL-3 AREA F PVS 4 4 0% 31-Aug-12 07-Sep-12 02-Jan-13 07-Jan-13 72
RESRLRL-1600 SET/CONNECT PHOTOVOLTAIC PANELS - ROOF RES 40 40 0% 20-Jan-15 23-Mar-15 21-May-... 30-Jul-15 73
CONACSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-C CON 8 8 0% 12-Mar-12 20-Mar-12 06-Jun-12 14-Jun-12 73
CONL1AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B CON 20 20 0% 04-Feb-14 04-Mar-14 19-May-... 16-Jun-14 73
CONL1AA-0910 FRAMING/ ROUGH-IN - LVL-1 AR-A CON 18 18 0% 04-Feb-14 28-Feb-14 19-May-... 12-Jun-14 73
CONL1AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-A CON 12 12 0% 03-Mar-14 18-Mar-14 13-Jun-14 30-Jun-14 73
CONL1AA-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-A CON 60 60 0% 19-Mar-14 11-Jun-14 01-Jul-14 24-Sep-14 73
CONL1AA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-A CON 20 20 0% 06-Jan-14 03-Feb-14 21-Apr-14 16-May-14 73
CONALAL-1425 INSTALL ELEVATOR CAR (GRIDLINE 6-7) - AREA A CON 60 60 0% 23-Apr-14 17-Jul-14 06-Aug-14 30-Oct-14 73
CONALAL-1435 INSTALL ELEVATORS CAR (GRIDLINE 15-16) - AREA B CON 60 60 0% 29-May-14 21-Aug-14 11-Sep-14 08-Dec-14 73
DATL3SC-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 SOUTH CORR DAT 7 7 0% 02-Jul-14 11-Jul-14 15-Oct-14 24-Oct-14 73
DATL3SC-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SOUTH CORR DAT 20 20 0% 14-Jul-14 08-Aug-14 27-Oct-14 25-Nov-14 73
DATESAB-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-B DAT 15 15 0% 31-May-13 25-Jun-13 04-Oct-13 28-Oct-13 73
DATESAB-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-B DAT 25 25 0% 27-Jun-13 08-Aug-13 29-Oct-13 10-Dec-13 73
DATESAA-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-A DAT 20 20 0% 15-Jul-13 16-Aug-13 15-Nov-13 17-Dec-13 73
ENCL1L1-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-1 ENC 15 15 0% 02-Oct-12 24-Oct-12 31-Jan-13 22-Feb-13 74
ENCSLSL-0540 ERECT EXTERIOR STUDS/SHEATHING - SERV LVL ENC 15 15 0% 02-Oct-12 24-Oct-12 31-Jan-13 22-Feb-13 74
IBSCOCO-1592 TEST & BALANCE - IBS 25 25 0% 29-Aug-14 03-Oct-14 17-Dec-14 23-Jan-15 74
IBSCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - IBS 30 30 0% 18-Jul-14 28-Aug-14 03-Nov-14 16-Dec-14 74
IBSCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - IBS 20 20 0% 29-Aug-14 26-Sep-14 17-Dec-14 15-Jan-15 74
IBSCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - IBS 20 20 0% 29-Sep-14 27-Oct-14 16-Jan-15 16-Feb-15 74
IBSL3NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 NURSING IBS 45 45 0% 13-Jan-14 18-Mar-14 29-Apr-14 01-Jul-14 74
IBSL3NR-8880 CLEAN-UP/PRE PUNCH - LVL-3 NURSING IBS 15 15 0% 26-Jun-14 17-Jul-14 10-Oct-14 31-Oct-14 74
IBSL3NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 NURSING IBS 30 30 0% 12-Mar-14 22-Apr-14 25-Jun-14 06-Aug-14 74
IBSL3NR-1190 INSTALL MEDICAL HEADWALLS - LVL-3 NURSING IBS 35 35 0% 23-Apr-14 11-Jun-14 07-Aug-14 25-Sep-14 74
IBSL3NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 NURSING IBS 10 10 0% 12-Jun-14 25-Jun-14 26-Sep-14 09-Oct-14 74
IBSL3IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-3 INTER IBS 100 100 0% 30-Sep-13 25-Feb-14 17-Jan-14 10-Jun-14 74
IBSL3PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 PATIENT IBS 40 40 0% 05-Dec-13 03-Feb-14 25-Mar-14 19-May-14 74
IBSL3PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-3 PATIENT IBS 20 20 0% 30-Sep-13 28-Oct-13 17-Jan-14 17-Feb-14 74
IBSL3PR-0910 FRAMING/INWALL ROUGH - LVL-3 PATIENT IBS 55 55 0% 30-Sep-13 18-Dec-13 17-Jan-14 07-Apr-14 74
IBSL2IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-2 INTER IBS 100 100 0% 16-Aug-13 10-Jan-14 04-Dec-13 28-Apr-14 74
IBSL1IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-1 INTER IBS 100 100 0% 05-Jul-13 27-Nov-13 18-Oct-13 17-Mar-14 74
IBSSLIL-1516 ROUGH-IN MEP/FIRE PROTECTION - SERV LVL INTER LVL IBS 60 60 0% 30-May-13 22-Aug-13 13-Sep-13 10-Dec-13 74
CONESAD-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR-D CON 12 12 0% 10-May-13 30-May-13 19-Sep-13 07-Oct-13 75
CONESAD-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-D CON 12 12 0% 10-May-13 30-May-13 19-Sep-13 07-Oct-13 75
CONHBAD-8890 TEAR DOWN STAGE - HIGH BAY AR-D CON 7 7 0% 08-May-14 16-May-14 25-Aug-14 03-Sep-14 75
CBNSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK CBN 25 25 0% 13-Nov-13 16-May-14 15-Aug-14 26-Sep-14 75
CBNSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK CBN 30 30 0% 19-May-14 10-Jul-14 29-Sep-14 14-Nov-14 75
DATL2CA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 CARDIO DAT 35 35 0% 19-Nov-13 09-Jan-14 11-Mar-14 28-Apr-14 75
DATL2SL-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 SLEEP DAT 20 20 0% 10-Jan-14 07-Feb-14 29-Apr-14 27-May-14 75
DATL3DI-0910 FRAMING/INWALL ROUGH - LVL-3 DIGEST DIS DAT 30 30 0% 22-Apr-14 03-Jun-14 07-Aug-14 18-Sep-14 75
DATL3DI-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 DIGEST DIS DAT 25 25 0% 06-May-14 10-Jun-14 21-Aug-14 25-Sep-14 75
PVNSLPK-0350 POUR PIER CAPS - SERV LVL PVN - SERV LVL PARK PVN 10 10 0% 04-Oct-13 21-Oct-13 06-Feb-14 21-Feb-14 76
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
27 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 108
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
AAAACBN-0100 START CBN CONSTRUCTION (start milestone) 0 0 0% 12-Jun-12 27-Aug-12 76
RESL1SO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SUPP RES 45 45 0% 06-Feb-15 10-Apr-15 28-May-... 30-Jul-15 77
RESSLSL-1516 ROUGH-IN OVERHEAD PIPING (PROCESS/MED GAS/FIRE PROT) - SERV LVL RES 20 20 0% 23-Dec-14 22-Jan-15 15-Apr-15 12-May-15 77
RESSLSL-0910 FRAMING/INWALL ROUGH - SERV LVL RES 30 30 0% 23-Dec-14 05-Feb-15 15-Apr-15 27-May-15 77
CONL1AB-0910 FRAMING/ ROUGH-IN - LVL-1 AR-B CON 18 18 0% 05-Mar-14 28-Mar-14 24-Jun-14 18-Jul-14 78
CONL1AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-B CON 12 12 0% 31-Mar-14 15-Apr-14 21-Jul-14 05-Aug-14 78
CONL1AB-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-B CON 60 60 0% 16-Apr-14 10-Jul-14 06-Aug-14 30-Oct-14 78
IBNPHPH-0510 ERECT STRUCTURAL STEEL/DECK - PENT IBN 15 15 0% 27-Feb-13 21-Mar-13 12-Jul-13 06-Aug-13 78
IBNL2L2-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 IBN 9 9 0% 22-Mar-13 05-Apr-13 08-Aug-13 22-Aug-13 78
IBNL1IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-1 INTERSTITIAL LVL IBN 35 35 0% 15-Apr-13 14-Jun-13 30-Aug-13 25-Oct-13 78
CONESAA-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR-A CON 12 12 0% 28-Mar-13 16-Apr-13 15-Aug-13 04-Sep-13 79
CONESAA-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-A CON 12 12 0% 28-Mar-13 16-Apr-13 15-Aug-13 04-Sep-13 79
CONADSS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-D CON 23 23 0% 04-Mar-13 09-Apr-13 22-Jul-13 29-Aug-13 80
CONADSS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-D CON 11 11 0% 11-Apr-13 29-Apr-13 30-Aug-13 17-Sep-13 80
ENCL1ME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - LVL-1 MECH RMS ENC 15 15 0% 08-Nov-12 03-Dec-12 11-Mar-13 29-Mar-13 80
ENCL1ME-0420 LAY CMU WALLS - LVL-1 MECH RMS ENC 10 10 0% 25-Oct-12 07-Nov-12 25-Feb-13 08-Mar-13 80
ENCL1OF-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 OFFICES ENC 20 20 0% 04-Dec-12 02-Jan-13 01-Apr-13 26-Apr-13 80
ENCPHPH-1520 CONNECT/PIPE-UP COOLING TOWERS - PENTHOUSE ENC 60 60 0% 15-Apr-13 09-Jul-13 07-Aug-13 31-Oct-13 80
ENCSLSH-1516 R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHOP ENC 20 20 0% 03-Jan-13 31-Jan-13 29-Apr-13 24-May-13 80
ENCSLME-1520 CONNECT/PIPE-UP BOILERS - SERV LVL MECH RMS ENC 60 60 0% 18-Mar-13 10-Jun-13 10-Jul-13 02-Oct-13 80
ENCSLME-1525 CONNECT/PIPE-UP CHILLERS - SERV LVL MECH RMS ENC 20 20 0% 18-Mar-13 12-Apr-13 10-Jul-13 06-Aug-13 80
ENCSLME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - SERV LVL MECH RMS ENC 30 30 0% 01-Feb-13 15-Mar-13 28-May-... 09-Jul-13 80
DATL3OF-8880 CLEAN-UP/PRE PUNCH - LVL-3 OFFICES DAT 10 10 0% 14-Aug-14 27-Aug-14 10-Dec-14 23-Dec-14 80
DATL3OF-0977 INSTALL OWNER FIXED FF&E - LVL-3 CATH OFFICES DAT 20 20 0% 17-Jul-14 13-Aug-14 10-Nov-14 09-Dec-14 80
EEEECON-0000 CON BLDG AVAILABLE FOR ENERGIZE 0 0 0% 10-Oct-14 11-Feb-15 81
ENCSLEL-0910 FRAMING/INWALL ROUGH - SERV LVL ELEC RMS ENC 10 10 0% 25-Feb-13 08-Mar-13 19-Jun-13 02-Jul-13 81
ENCSLEL-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL ELEC RMS ENC 15 15 0% 11-Mar-13 29-Mar-13 03-Jul-13 24-Jul-13 81
ENCSLEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP - SERV LVL ELEC RMS ENC 30 30 0% 01-Apr-13 10-May-13 25-Jul-13 05-Sep-13 81
RESL1SO-8880 CLEAN-UP/PRE PUNCH - LVL-1 SUPP RES 10 10 0% 13-Apr-15 24-Apr-15 07-Aug-15 20-Aug-15 82
CONESAE-0855 INSTALL BLAST PROOF PANELS @ LVL-1 (SOUTH ELEV) - AR-E CON 12 12 0% 31-May-13 20-Jun-13 22-Oct-13 08-Nov-13 83
CONESAE-0866 INSTALL BLAST PROOF PANELS @ LVL 1 (EAST ELEV) - AR-E CON 12 12 0% 31-May-13 20-Jun-13 22-Oct-13 08-Nov-13 83
CONESAE-0867 INSTALL BLAST PROOF PANELS @ LVL 1 (WEST ELEV) - AR-E CON 12 12 0% 31-May-13 20-Jun-13 22-Oct-13 08-Nov-13 83
IBNSLIL-1516 ROUGH-IN MEP/FIRE PROTECTION - SERV LVL INTER LVL IBN 60 60 0% 21-May-13 14-Aug-13 20-Sep-13 17-Dec-13 85
IBNL1IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-1 INTER IBN 100 100 0% 26-Jun-13 18-Nov-13 28-Oct-13 24-Mar-14 85
IBNL2IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-2 INTER IBN 100 100 0% 15-Aug-13 09-Jan-14 18-Dec-13 12-May-14 85
IBNL3CS-8880 CLEAN-UP/PRE PUNCH - LVL-3 SHELL IBN 15 15 0% 18-Jun-14 09-Jul-14 17-Oct-14 07-Nov-14 85
IBNL3CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SHELL IBN 30 30 0% 04-Mar-14 14-Apr-14 02-Jul-14 13-Aug-14 85
IBNL3CS-1190 INSTALL MEDICAL HEADWALLS - LVL-3 SHELL IBN 35 35 0% 15-Apr-14 03-Jun-14 14-Aug-14 02-Oct-14 85
IBNL3CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 SHELL IBN 10 10 0% 04-Jun-14 17-Jun-14 03-Oct-14 16-Oct-14 85
IBNL3CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 SHELL IBN 35 35 0% 03-Feb-14 24-Mar-14 04-Jun-14 23-Jul-14 85
IBNL3NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 NURSING IBN 25 25 0% 04-Oct-13 08-Nov-13 11-Feb-14 17-Mar-14 85
IBNL3IL-1516 ROUGH-IN MEP/FIRE PROTECTION - LVL-3 INTER IBN 100 100 0% 06-Sep-13 31-Jan-14 10-Jan-14 03-Jun-14 85
IBNL3RH-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 REHAB IBN 20 20 0% 12-Nov-13 10-Dec-13 18-Mar-14 14-Apr-14 85
IBNL3RH-0910 FRAMING/INWALL ROUGH - LVL-3 REHAB IBN 60 60 0% 12-Nov-13 07-Feb-14 18-Mar-14 10-Jun-14 85
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
28 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 109
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
IBNL3RH-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 REHAB IBN 35 35 0% 10-Jan-14 03-Mar-14 13-May-... 01-Jul-14 85
IBNL3PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-3 PATIENT IBN 20 20 0% 06-Sep-13 03-Oct-13 10-Jan-14 07-Feb-14 85
IBNCOCO-1592 TEST & BALANCE - IBN 25 25 0% 14-Aug-14 18-Sep-14 17-Dec-14 23-Jan-15 85
IBNCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - IBN 30 30 0% 02-Jul-14 13-Aug-14 03-Nov-14 16-Dec-14 85
IBNCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - IBN 20 20 0% 14-Aug-14 11-Sep-14 17-Dec-14 15-Jan-15 85
IBNCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - IBN 20 20 0% 12-Sep-14 09-Oct-14 16-Jan-15 16-Feb-15 85
DATL2DE-0977 INSTALL OWNER FIXED FF&E - LVL-2 DENTAL DAT 20 20 0% 10-Jul-14 06-Aug-14 10-Nov-14 09-Dec-14 85
DATL2DE-8880 CLEAN-UP/PRE PUNCH - LVL-2 DENTAL DAT 10 10 0% 07-Aug-14 20-Aug-14 10-Dec-14 23-Dec-14 85
DATL2CA-0977 INSTALL OWNER FIXED FF&E - LVL-2 CARDIO DAT 20 20 0% 10-Jul-14 06-Aug-14 10-Nov-14 09-Dec-14 85
DATL2CA-8880 CLEAN-UP/PRE PUNCH - LVL-2 CARDIO DAT 10 10 0% 07-Aug-14 20-Aug-14 10-Dec-14 23-Dec-14 85
IBSL3L3-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 IBS 9 9 0% 16-Apr-13 02-May-13 16-Sep-13 30-Sep-13 86
IBSL2IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-2 INTERSTITIAL LVL IBS 35 35 0% 10-May-13 09-Jul-13 07-Oct-13 03-Dec-13 86
RESSLSL-0420 LAY CMU WALLS - SERV LVL RES 10 10 0% 25-Nov-14 08-Dec-14 01-Apr-15 14-Apr-15 87
ENCSLSL-3200 UNDERSLAB UTILITIES - SERV LVL ENC 28 28 0% 12-Jul-12 28-Aug-12 10-Dec-12 23-Jan-13 88
ENCSLSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL ENC 12 12 0% 17-Aug-12 06-Sep-12 11-Jan-13 30-Jan-13 88
DATL3SC-8880 CLEAN-UP/PRE PUNCH - LVL-3 SOUTH CORR DAT 5 5 0% 11-Aug-14 15-Aug-14 17-Dec-14 23-Dec-14 88
RESESEE-0780 INSTALL METAL PANEL - EAST ELEV RES 5 5 0% 18-Nov-14 25-Nov-14 16-Apr-15 23-Apr-15 90
RESL1LA-0977 INSTALL OWNER FIXED FF&E - LVL-1 LAB RES 20 20 0% 04-Mar-15 31-Mar-15 10-Jul-15 06-Aug-15 90
RESL1LA-8880 CLEAN-UP/PRE PUNCH - LVL-1 LAB RES 10 10 0% 01-Apr-15 14-Apr-15 07-Aug-15 20-Aug-15 90
CONADL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-D CON 8 8 0% 19-Nov-12 30-Nov-12 15-Apr-13 26-Apr-13 90
CONADL1-0330 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-D CON 9 9 0% 09-Jan-13 23-Jan-13 10-Jun-13 24-Jun-13 90
CONADL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-D CON 7 7 0% 24-Jan-13 01-Feb-13 25-Jun-13 05-Jul-13 90
CONADL1-0320 DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-D CON 6 6 0% 31-Dec-12 08-Jan-13 30-May-... 07-Jun-13 90
CONADL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-D CON 8 8 0% 04-Feb-13 14-Feb-13 08-Jul-13 19-Jul-13 90
CONADL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-D CON 15 15 0% 24-Oct-12 16-Nov-12 20-Mar-13 12-Apr-13 90
CONADSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-D CON 17 17 0% 03-Dec-12 28-Dec-12 29-Apr-13 29-May-13 90
IBNSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK IBN 40 40 0% 13-Sep-13 14-Apr-14 11-Jul-14 18-Sep-14 91
IBNSWHL-0290 LANDSCAPING/SITE FURNISHINGS - IBN 35 35 0% 15-Apr-14 12-Jun-14 19-Sep-14 14-Nov-14 91
CBCHRPR-0755 INSTALL ROOFING SYSTEM- PENT ROOF CBC 15 15 0% 22-Oct-13 14-Nov-13 20-Mar-14 14-Apr-14 92
CONADL1-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-D CON 8 8 0% 26-Oct-12 08-Nov-12 28-Mar-13 09-Apr-13 93
CONADSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-D CON 28 28 0% 06-Aug-12 20-Sep-12 08-Jan-13 20-Feb-13 93
CONADSL-3200 UNDERSLAB UTILITIES - SERV LVL AR-D CON 12 12 0% 21-Sep-12 09-Oct-12 21-Feb-13 11-Mar-13 93
CONADSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-D CON 10 10 0% 10-Oct-12 25-Oct-12 12-Mar-13 26-Mar-13 93
DATESAF-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-F DAT 15 15 0% 25-Apr-13 21-May-13 04-Oct-13 28-Oct-13 93
DATESAF-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-F DAT 25 25 0% 23-May-13 03-Jul-13 29-Oct-13 10-Dec-13 93
DATESAA-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-A DAT 15 15 0% 14-May-13 07-Jun-13 22-Oct-13 14-Nov-13 93
DATESAF-0890 INFILL FOR MRI EQUIPMENT INSTALL - ALL ELEVS AR-E DAT 5 5 0% 10-Jul-14 17-Jul-14 16-Dec-14 23-Dec-14 94
DATESAE-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-E DAT 15 15 0% 14-Mar-13 05-Apr-13 26-Aug-13 19-Sep-13 94
IBSL3CO-8880 CLEAN-UP/PRE PUNCH - LVL-3 CORR IBS 10 10 0% 12-Jun-14 25-Jun-14 27-Oct-14 07-Nov-14 94
IBSL3CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CORR IBS 20 20 0% 21-May-14 18-Jun-14 03-Oct-14 31-Oct-14 94
IBSL3CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 SHELL IBS 25 25 0% 19-Feb-14 25-Mar-14 02-Jul-14 06-Aug-14 94
IBSL3CS-8880 CLEAN-UP/PRE PUNCH - LVL-3 SHELL IBS 15 15 0% 05-Jun-14 25-Jun-14 17-Oct-14 07-Nov-14 94
IBSL3CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SHELL IBS 25 25 0% 26-Mar-14 29-Apr-14 07-Aug-14 11-Sep-14 94
IBSL3CS-1190 INSTALL MEDICAL HEADWALLS - LVL-3 SHELL IBS 35 35 0% 30-Apr-14 18-Jun-14 12-Sep-14 31-Oct-14 94
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
29 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 110
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
IBSL3CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 SHELL IBS 10 10 0% 12-Jun-14 25-Jun-14 27-Oct-14 07-Nov-14 94
RESESNE-0780 INSTALL METAL PANEL - NORTH ELEV RES 10 10 0% 31-Oct-14 17-Nov-14 07-Apr-15 23-Apr-15 95
IBNL3CO-8880 CLEAN-UP/PRE PUNCH - LVL-3 CORR IBN 10 10 0% 18-Jun-14 01-Jul-14 03-Nov-14 17-Nov-14 95
IBNL3CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CORR IBN 20 20 0% 20-May-14 17-Jun-14 03-Oct-14 31-Oct-14 95
CBSTUTU-3790 INSTALL TEMPERARY BOILER - TEMP UTILITIES CBS 5 5 0% 24-Aug-11 30-Aug-11 13-Jan-12 20-Jan-12 95
DATL1ER-0977 INSTALL OWNER FIXED FF&E - LVL-1 ER DAT 20 20 0% 11-Jun-14 09-Jul-14 27-Oct-14 25-Nov-14 95
DATL1ER-8880 CLEAN-UP/PRE PUNCH - LVL-1 ER DAT 10 10 0% 10-Jul-14 23-Jul-14 26-Nov-14 09-Dec-14 95
DATL3IL-1301 TRIM-OUT MEP (OFFICES) (AHU13) - LVL-3 INTER LVL DAT 5 5 0% 31-Jul-14 06-Aug-14 17-Dec-14 23-Dec-14 95
IBSPBPB-0380 FORM/PLACE/FINISH SLAB ON GRADE - PIPE BSMT IBS 5 5 0% 25-Sep-12 02-Oct-12 28-Feb-13 07-Mar-13 96
IBSPBPB-3200 UNDERSLAB UTILITIES - PIPE BSMT IBS 15 15 0% 30-Aug-12 24-Sep-12 05-Feb-13 27-Feb-13 96
PVSSWSW-3240 SHORING(REMAINING EAST SIDE) - PVS SITEWORK 15 15 0% 14-Jun-12 02-Jul-12 08-Oct-12 25-Oct-12 96
CONAESS-0510 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-E CON 25 25 0% 14-Mar-13 23-Apr-13 30-Aug-13 09-Oct-13 97
CONAESS-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-E CON 6 6 0% 25-Apr-13 06-May-13 10-Oct-13 21-Oct-13 97
CBNPHEL-0910 FRAMING/INWALL ROUGH - PENT ELEC CBN 10 10 0% 18-Oct-13 01-Nov-13 13-Mar-14 26-Mar-14 97
IBNL3NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 NURSING IBN 35 35 0% 27-Nov-13 16-Jan-14 22-Apr-14 10-Jun-14 100
IBNL3NR-0910 FRAMING/INWALL ROUGH - LVL-3 NURSING IBN 55 55 0% 04-Oct-13 24-Dec-13 04-Mar-14 19-May-14 100
IBNL3RH-1190 INSTALL MEDICAL HEADWALLS - LVL-3 REHAB IBN 35 35 0% 01-Apr-14 19-May-14 21-Aug-14 09-Oct-14 100
IBNL3RH-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 REHAB IBN 10 10 0% 20-May-14 03-Jun-14 10-Oct-14 24-Oct-14 100
IBNL3RH-8880 CLEAN-UP/PRE PUNCH - LVL-3 REHAB IBN 15 15 0% 20-May-14 10-Jun-14 10-Oct-14 31-Oct-14 100
IBNL3RH-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 REHAB IBN 25 25 0% 25-Feb-14 31-Mar-14 17-Jul-14 20-Aug-14 100
IBNL3PR-0910 FRAMING/INWALL ROUGH - LVL-3 PATIENT IBN 55 55 0% 06-Sep-13 26-Nov-13 03-Feb-14 21-Apr-14 100
IBNL3PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 PATIENT IBN 35 35 0% 28-Oct-13 17-Dec-13 25-Mar-14 12-May-14 100
IBNL3L3-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 IBN 9 9 0% 08-Apr-13 22-Apr-13 01-Oct-13 11-Oct-13 100
IBNL2IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-2 INTERSTITIAL LVL IBN 35 35 0% 02-May-13 01-Jul-13 22-Oct-13 17-Dec-13 100
ENCSLME-1600 SET/CONNECT/PIPE-UP MECH EQUIP (BALANCE) - SERV LVL MECH RMS ENC 60 60 0% 18-Mar-13 10-Jun-13 07-Aug-13 31-Oct-13 100
DATL2IL-0301 TRIM-OUT MEP (CARDIO) (AHU3) - LVL-2 INTER LVL DAT 5 5 0% 18-Jun-14 24-Jun-14 10-Nov-14 17-Nov-14 100
DATL2IL-1401 TRIM-OUT MEP (DENTAL) (AHU14) - LVL-2 INTER LVL DAT 5 5 0% 18-Jun-14 24-Jun-14 10-Nov-14 17-Nov-14 100
DATL3IL-1300 ROUGH-IN MEP/FIRE PROTECTION (OFFICES) (AHU13) - LVL-3 INTER LVL DAT 65 65 0% 04-Dec-13 10-Mar-14 29-Apr-14 30-Jul-14 100
CONABL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-B CON 10 10 0% 13-Aug-12 28-Aug-12 29-Jan-13 11-Feb-13 101
CONABL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-B CON 6 6 0% 30-Aug-12 07-Sep-12 12-Feb-13 21-Feb-13 101
CONABSL-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-B CON 8 8 0% 13-Aug-12 24-Aug-12 29-Jan-13 07-Feb-13 101
CONABSL-3200 UNDERSLAB UTILITIES - SERV LVL AR-B CON 14 14 0% 03-Jul-12 26-Jul-12 21-Dec-12 11-Jan-13 101
CONABSL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-B CON 9 9 0% 27-Jul-12 10-Aug-12 14-Jan-13 28-Jan-13 101
CONABSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-B CON 18 18 0% 10-Sep-12 08-Oct-12 22-Feb-13 21-Mar-13 101
IBSSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK IBS 25 25 0% 17-Oct-13 22-Apr-14 03-Sep-14 10-Oct-14 101
IBSSWHL-0290 LANDSCAPING/SITE FURNISHINGS - IBS 20 20 0% 23-Apr-14 23-May-14 14-Oct-14 14-Nov-14 101
PVSPOPO-4840 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVS) 15 15 0% 27-Feb-12 16-Mar-12 19-Jul-12 08-Aug-12 101
PVSPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVS) 20 20 0% 19-Mar-12 13-Apr-12 09-Aug-12 06-Sep-12 101
PVSPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (PVS) 20 20 0% 16-Apr-12 11-May-12 07-Sep-12 04-Oct-12 101
MBSW-278 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - MONTVIEW BLVD. 25 25 0% 14-Apr-14 22-May-14 06-Oct-14 14-Nov-14 102
ENCPOPO-5489 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (ENC) 15 15 0% 23-Apr-12 11-May-12 18-Sep-12 08-Oct-12 103
ENCPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (ENC) 20 20 0% 14-May-12 11-Jun-12 09-Oct-12 06-Nov-12 103
ENCPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (ENC) 20 20 0% 12-Jun-12 10-Jul-12 07-Nov-12 07-Dec-12 103
ENCPGPG-3210 PERM DRAINS/BACKFILL FOUNDATION WALLS - PIPE GALLERY ENC 3 3 0% 30-Jul-12 03-Aug-12 18-Jan-13 23-Jan-13 103
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
30 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 111
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CONADSL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-D CON 7 7 0% 03-Jul-12 13-Jul-12 27-Dec-12 07-Jan-13 104
DATESAD-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-D DAT 15 15 0% 26-Feb-13 20-Mar-13 26-Aug-13 19-Sep-13 104
IBSL3NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 NURSING IBS 20 20 0% 29-Oct-13 27-Nov-13 01-Apr-14 28-Apr-14 104
IBSL3NR-0910 FRAMING/INWALL ROUGH - LVL-3 NURSING IBS 55 55 0% 29-Oct-13 17-Jan-14 01-Apr-14 17-Jun-14 104
IBSL3PR-8880 CLEAN-UP/PRE PUNCH - LVL-3 PATIENT IBS 15 15 0% 14-May-14 04-Jun-14 10-Oct-14 31-Oct-14 104
IBSL3PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PATIENT IBS 30 30 0% 28-Jan-14 11-Mar-14 25-Jun-14 06-Aug-14 104
IBSL3PR-1190 INSTALL MEDICAL HEADWALLS - LVL-3 PATIENT IBS 35 35 0% 12-Mar-14 29-Apr-14 07-Aug-14 25-Sep-14 104
IBSL3PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 PATIENT IBS 10 10 0% 30-Apr-14 13-May-14 26-Sep-14 09-Oct-14 104
IBNL3CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 SHELL IBN 15 15 0% 11-Dec-13 02-Jan-14 13-May-... 03-Jun-14 105
IBNL3CS-0910 FRAMING/INWALL ROUGH - LVL-3 SHELL IBN 35 35 0% 11-Dec-13 31-Jan-14 13-May-... 01-Jul-14 105
CBCLRLR-0710 PARAPET/BLOCKING/WATERPROOFING - LOW ROOF CBC 10 10 0% 03-Jan-14 17-Jan-14 30-Jun-14 15-Jul-14 105
ENCSLME-0420 LAY CMU WALLS - SERV LVL MECH RMS ENC 20 20 0% 25-Oct-12 26-Nov-12 01-Apr-13 26-Apr-13 105
DATL1MR-0977 INSTALL OWNER FIXED FF&E - LVL-1 MRI/CT DAT 20 20 0% 11-Jun-14 09-Jul-14 10-Nov-14 09-Dec-14 105
DATL1MR-8880 CLEAN-UP/PRE PUNCH - LVL-1 MRI/CT DAT 10 10 0% 10-Jul-14 23-Jul-14 10-Dec-14 23-Dec-14 105
ENCL1L1-1660 FORM/REINFORCE/PLACE EQUIPMENT PADS - LVL-1 ENC 5 5 0% 27-Sep-12 03-Oct-12 19-Mar-13 25-Mar-13 106
IBSSLSL-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - SERVICE LEVEL IBS 9 9 0% 11-Feb-13 25-Feb-13 13-Aug-13 27-Aug-13 106
IFO-4920 VA REVIEW BID TABS (GROUP #1) - IFO-1 5 5 0% 29-Mar-12 04-Apr-12 29-Aug-12 05-Sep-12 107
IFO-3790 VA PROVIDES CONSENT TO SUBCONTRACT (GROUP #1) - IFO-1 0 0 0% 04-Apr-12 05-Sep-12 107
CBNPOPO-4780 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CBN) 25 25 0% 09-Mar-12 12-Apr-12 09-Aug-12 13-Sep-12 107
CBNPOPO-4740 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (CBN) 30 30 0% 26-Jan-12 08-Mar-12 27-Jun-12 08-Aug-12 107
CBNPOPO-4750 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CBN) 20 20 0% 13-Apr-12 10-May-12 14-Sep-12 11-Oct-12 107
CBNPOPO-4760 FABRICATE/DELIVER STRUCT STEEL - STR-2 (CBN) 65 65 0% 11-May-12 13-Aug-12 12-Oct-12 18-Jan-13 107
CBNPOPO-4770 FIRST DELIVERY OF STRUCT STEEL - STR-2 (CBN) 0 0 0% 13-Aug-12 18-Jan-13 107
IBNPOPO-3591 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (IBN) 30 30 0% 27-Dec-11 08-Feb-12 30-May-... 11-Jul-12 107
IBSPOPO-4660 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (IBS) 30 30 0% 11-Jan-12 23-Feb-12 13-Jun-12 25-Jul-12 107
IFO-3630 SUBCONTRACTOR PRICING (GROUP #1)- IFO-1 25 25 0% 01-Feb-12 07-Mar-12 03-Jul-12 07-Aug-12 107
IFO-4930 PREPARE BID TABS (GROUP #1) - IFO-1 15 15 0% 08-Mar-12 28-Mar-12 08-Aug-12 28-Aug-12 107
P-CD4-3950 AWARD MEDICAL EQUIPMENT CONTRACT 20 20 0% 05-Apr-12 02-May-12 06-Sep-12 03-Oct-12 107
DATPOPO-4950 SUBMIT MEDICAL EQUIPMENT SHOPS (pharmacy) - IFO-1 (DAT) 60 60 0% 03-May-12 27-Jul-12 04-Oct-12 03-Jan-13 107
IFO-3040 95% DESIGN - IFO-1 87 87 0% 26-Jul-11 30-Nov-11 30-Dec-11 03-May-12 107
IFO-3510 95% CD TO KT - IFO-1 1 1 0% 01-Dec-11 01-Dec-11 04-May-... 04-May-12 107
IFO-3660 KT PROVIDES RED LINE COMMENTS 95% CD - IFO-1 15 15 0% 02-Dec-11 22-Dec-11 07-May-... 25-May-12 107
IFO-3670 PAGE FLIP 95% CD - IFO-1 5 5 0% 23-Dec-11 30-Dec-11 29-May-... 04-Jun-12 107
IFO-3680 JVT REVISE DOCUMENTS 95% CD - IFO-1 15 15 0% 03-Jan-12 24-Jan-12 05-Jun-12 25-Jun-12 107
IFO-3690 JVT QA/QC DOCUMENTS 95% CD - IFO-1 5 5 0% 25-Jan-12 31-Jan-12 26-Jun-12 02-Jul-12 107
IBSL3IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-3 INTERSTITIAL LVL IBS 35 35 0% 21-May-13 19-Jul-13 20-Nov-13 16-Jan-14 107
IBSRLRL-0510 ERECT STRUCTURAL STEEL/DECK - ROOF IBS 15 15 0% 01-Apr-13 25-Apr-13 04-Oct-13 28-Oct-13 107
IBSPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT IBS 9 9 0% 26-Apr-13 13-May-13 29-Oct-13 13-Nov-13 107
CONAESL-0322 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-E CON 8 8 0% 29-Nov-12 11-Dec-12 29-May-... 10-Jun-13 108
CONAEL1-0330 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-E CON 8 8 0% 01-Feb-13 12-Feb-13 06-Aug-13 19-Aug-13 108
CONAEL1-3200 UNDERSLAB UTILITIES - LVL-1 AR-E CON 3 3 0% 14-Feb-13 19-Feb-13 20-Aug-13 23-Aug-13 108
CONAEL1-0320 DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-E CON 4 4 0% 28-Jan-13 31-Jan-13 30-Jul-13 05-Aug-13 108
CONAEL1-0380 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-E CON 3 3 0% 20-Feb-13 22-Feb-13 26-Aug-13 29-Aug-13 108
CONAEL1-1527 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-E CON 19 19 0% 14-Nov-12 13-Dec-12 13-May-... 13-Jun-13 108
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
31 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 112
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CONAEL1-0390 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-E CON 7 7 0% 14-Dec-12 26-Dec-12 14-Jun-13 25-Jun-13 108
CONAESL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-E CON 25 25 0% 30-Aug-12 09-Oct-12 25-Feb-13 04-Apr-13 108
CONAESL-3200 UNDERSLAB UTILITIES - SERV LVL AR-E CON 18 18 0% 10-Oct-12 08-Nov-12 05-Apr-13 07-May-13 108
CONAESL-0380 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-E CON 11 11 0% 09-Nov-12 27-Nov-12 09-May-... 28-May-13 108
CONAESL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-E CON 19 19 0% 27-Dec-12 25-Jan-13 27-Jun-13 29-Jul-13 108
IBNPHPH-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT IBN 9 9 0% 18-Apr-13 03-May-13 23-Oct-13 05-Nov-13 108
IBNL3IL-0510 ERECT INTERSTITIAL STEEL/TOPPING - LVL-3 INTERSTITIAL LVL IBN 35 35 0% 13-May-13 11-Jul-13 14-Nov-13 09-Jan-14 108
IBNRLRL-0510 ERECT STRUCTURAL STEEL/DECK - ROOF IBN 15 15 0% 22-Mar-13 16-Apr-13 30-Sep-13 22-Oct-13 108
IBNPOPO-3631 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (IBN) 25 25 0% 09-Feb-12 15-Mar-12 13-Jul-12 16-Aug-12 108
IBNPOPO-3601 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (IBN) 20 20 0% 16-Mar-12 12-Apr-12 17-Aug-12 14-Sep-12 108
IBNPOPO-3611 FABRICATE/DELIVER STRUCT STEEL - STR-2 (IBN) 65 65 0% 13-Apr-12 16-Jul-12 17-Sep-12 20-Dec-12 108
IBNPOPO-3621 FIRST DELIVERY OF STRUCT STEEL - STR-2 (IBN) 0 0 0% 16-Jul-12 20-Dec-12 108
DATALAL-1467 INSTALL ELEVATORS (SE6/7) - ALL LVLS DAT 120 120 0% 20-Jun-13 08-Jan-14 20-Dec-13 10-Jul-14 108
IBSALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS IBS 15 15 0% 29-May-14 18-Jun-14 03-Nov-14 25-Nov-14 109
IBSALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS IBS 15 15 0% 19-Jun-14 10-Jul-14 26-Nov-14 16-Dec-14 109
RESESSE-1610 INSTALL STRUCTURAL STEEL FRAME FOR SOLAR TUBES - SOUTH ELEV RES 15 15 0% 07-Oct-14 30-Oct-14 07-Apr-15 01-May-15 110
RESESSE-1600 INSTALL SOLAR TUBES - SOUTH ELEV RES 50 50 0% 31-Oct-14 22-Jan-15 04-May-... 30-Jul-15 110
CONADSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-D CON 8 8 0% 21-Mar-12 29-Mar-12 30-Jul-12 07-Aug-12 110
IBNALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS IBN 15 15 0% 18-Jun-14 09-Jul-14 26-Nov-14 16-Dec-14 110
IBNALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS IBN 15 15 0% 28-May-14 17-Jun-14 03-Nov-14 25-Nov-14 110
CBNPHPH-0310 FORM/REINFORCE/FINISH HOUSEKEEPING PADS - PENT LVL CBN 7 7 0% 14-Mar-13 22-Mar-13 23-Sep-13 02-Oct-13 110
CBNSLSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL CBN 15 15 0% 30-Mar-12 16-Apr-12 08-Aug-12 24-Aug-12 110
DATL1IL-1601 TRIM-OUT MEP (ER) (AHU16) - LVL-1 INTER LVL DAT 15 15 0% 20-May-14 10-Jun-14 27-Oct-14 17-Nov-14 110
DATSLPY-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL PHARMACY DAT 20 20 0% 05-Jun-13 02-Jul-13 12-Nov-13 10-Dec-13 110
DATSLST-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL STER DAT 25 25 0% 03-Jul-13 07-Aug-13 11-Dec-13 16-Jan-14 110
DATSLSH-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL SHELL DAT 15 15 0% 08-Aug-13 28-Aug-13 17-Jan-14 07-Feb-14 110
CONAESL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-E CON 15 15 0% 02-Jul-12 27-Jul-12 07-Jan-13 29-Jan-13 110
CONAESL-0320 DRILL/PLACE CAISSONS - SERV LVL AR-E CON 11 11 0% 07-Aug-12 24-Aug-12 06-Feb-13 22-Feb-13 110
CONAESL-3210 INSTALL GREASE TRAP AND SANITARY - SERV LVL AR-E CON 10 10 0% 19-Jul-12 07-Aug-12 23-Jan-13 05-Feb-13 110
IBNALAL-1400 INSTALL ELEVATOR SE1/SE2 - ALL LVLS IBN 60 60 0% 16-Jan-14 22-Apr-14 24-Jul-14 31-Oct-14 111
IBNALAL-1401 INSTALL ELEVATOR PE1/PE2 - ALL LVLS IBN 60 60 0% 16-Jan-14 22-Apr-14 24-Jul-14 31-Oct-14 111
PVNSLDO-0730 WATERPROOFING/FINISH DOCK LID - SERV LVL DOCK PVN 20 20 0% 07-Jan-14 05-Feb-14 15-Jul-14 18-Aug-14 112
CBSL3L3-4030 NEW EXHAUST FANS - LVL-3 CBS 10 10 0% 22-Aug-11 01-Sep-11 06-Jan-12 18-Jan-12 112
ZZZZIBS-9999 FINISH IBS CONSTRUCTION (finish milestone) 0 0 0% 06-Nov-14 26-Feb-15 112
XXXXIBS-0500 IBS OVERALL DURATION 968 968 0% 14-Mar-12 06-Nov-14 14-Aug-12 26-Feb-15 112
IBSCOCO-1599 BUILDING FLUSH - IBS 10 10 0% 28-Oct-14 06-Nov-14 17-Feb-15 26-Feb-15 112
IBSL3CS-0910 FRAMING/INWALL ROUGH - LVL-3 SHELL IBS 55 55 0% 28-Nov-13 18-Feb-14 13-May-... 30-Jul-14 114
IBSL3CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 SHELL IBS 15 15 0% 28-Nov-13 18-Dec-13 13-May-... 03-Jun-14 114
IBNL3NR-8880 CLEAN-UP/PRE PUNCH - LVL-3 NURSING IBN 15 15 0% 29-Apr-14 19-May-14 10-Oct-14 31-Oct-14 115
IBNL3NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 NURSING IBN 30 30 0% 10-Jan-14 24-Feb-14 25-Jun-14 06-Aug-14 115
IBNL3NR-1190 INSTALL MEDICAL HEADWALLS - LVL-3 NURSING IBN 35 35 0% 25-Feb-14 14-Apr-14 07-Aug-14 25-Sep-14 115
IBNL3NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 NURSING IBN 10 10 0% 15-Apr-14 28-Apr-14 26-Sep-14 09-Oct-14 115
DATL1GR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 GEN RADIOLOGY DAT 35 35 0% 13-Sep-13 01-Nov-13 04-Mar-14 21-Apr-14 115
DATL2LA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 LABS DAT 35 35 0% 04-Nov-13 24-Dec-13 22-Apr-14 10-Jun-14 115
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
32 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 113
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL2LA-0910 FRAMING/INWALL ROUGH - LVL-2 LABS DAT 30 30 0% 19-Nov-13 02-Jan-14 06-May-... 17-Jun-14 115
DATL2LA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 LABS DAT 35 35 0% 04-Dec-13 24-Jan-14 20-May-... 09-Jul-14 115
DATL2LA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 LABS DAT 65 65 0% 18-Dec-13 24-Mar-14 04-Jun-14 04-Sep-14 115
IBSPBPB-3110 SET/BACKFILL DUCTBANKS - PIPE BSMT IBS 5 5 0% 13-Aug-12 20-Aug-12 21-Feb-13 27-Feb-13 116
IBSPHPH-0725 SPRAY-ON FIREPROOFING - PENT IBS 8 8 0% 14-May-13 28-May-13 03-Dec-13 13-Dec-13 118
P-CBS-4100 VA APPROVES FIRM FIXED PRICE 100% AND ISSUES MOD - CBS-1 0 0 0% 15-Aug-11 08-Feb-12 119
P-CBS-4090 VA REVIEWS FIRM FIXED PRICE 100% CD - CBS-1 15 15 0% 26-Jul-11 15-Aug-11 19-Jan-12 08-Feb-12 119
IBSL3NR-0977 INSTALL OWNER FIXED FF&E - LVL-3 NURSING IBS 20 20 0% 26-Mar-14 22-Apr-14 12-Sep-14 09-Oct-14 119
IBSL3CS-0977 INSTALL OWNER FIXED FF&E - LVL-3 SHELL IBS 20 20 0% 02-Apr-14 29-Apr-14 19-Sep-14 16-Oct-14 119
IBSL2NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 NURSING IBS 35 35 0% 20-Nov-13 10-Jan-14 13-May-... 01-Jul-14 119
IBSL2PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-2 PATIENT IBS 20 20 0% 16-Aug-13 13-Sep-13 11-Feb-14 10-Mar-14 119
IBSL2PR-0910 FRAMING/INWALL ROUGH - LVL-2 PATIENT IBS 55 55 0% 16-Aug-13 04-Nov-13 11-Feb-14 28-Apr-14 119
IBSL2PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 PATIENT IBS 35 35 0% 22-Oct-13 11-Dec-13 15-Apr-14 03-Jun-14 119
IBSL2CO-8880 CLEAN-UP/PRE PUNCH - LVL-2 CORR IBS 10 10 0% 07-May-14 20-May-14 27-Oct-14 07-Nov-14 119
IBSL2CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CORR IBS 20 20 0% 09-Apr-14 06-May-14 26-Sep-14 24-Oct-14 119
IBSL2CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SHELL IBS 25 25 0% 19-Dec-13 27-Jan-14 11-Jun-14 16-Jul-14 119
IBSL2CS-8880 CLEAN-UP/PRE PUNCH - LVL-2 SHELL IBS 15 15 0% 23-Apr-14 13-May-14 10-Oct-14 31-Oct-14 119
IBSL2CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SHELL IBS 15 15 0% 28-Jan-14 18-Feb-14 17-Jul-14 06-Aug-14 119
IBSL2CS-1190 INSTALL MEDICAL HEADWALLS - LVL-2 SHELL IBS 35 35 0% 19-Feb-14 08-Apr-14 07-Aug-14 25-Sep-14 119
IBSL2CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 SHELL IBS 10 10 0% 09-Apr-14 22-Apr-14 26-Sep-14 09-Oct-14 119
IBNL2SS-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SUPPORT IBN 45 45 0% 27-Nov-13 31-Jan-14 20-May-... 23-Jul-14 120
IBNL2SS-8880 CLEAN-UP/PRE PUNCH - LVL-2 SUPPORT IBN 15 15 0% 22-Apr-14 12-May-14 10-Oct-14 31-Oct-14 120
IBNL2SS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SUPPORT IBN 25 25 0% 27-Jan-14 03-Mar-14 17-Jul-14 20-Aug-14 120
IBNL2SS-1190 INSTALL MEDICAL HEADWALLS - LVL-2 SUPPORT IBN 35 35 0% 04-Mar-14 21-Apr-14 21-Aug-14 09-Oct-14 120
IBNL2SS-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 SUPPORT IBN 10 10 0% 22-Apr-14 05-May-14 10-Oct-14 24-Oct-14 120
IBNL2PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-2 PATIENT IBN 20 20 0% 15-Aug-13 12-Sep-13 11-Feb-14 10-Mar-14 120
IBNL2PR-0910 FRAMING/INWALL ROUGH - LVL-2 PATIENT IBN 55 55 0% 15-Aug-13 01-Nov-13 11-Feb-14 28-Apr-14 120
IBNL2PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 PATIENT IBN 35 35 0% 04-Oct-13 26-Nov-13 01-Apr-14 19-May-14 120
IBNL2NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 NURSING IBN 35 35 0% 04-Nov-13 24-Dec-13 29-Apr-14 17-Jun-14 120
CONPOPO-4930 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CON) 15 15 0% 27-Jan-12 17-Feb-12 18-Jul-12 07-Aug-12 120
CONPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (CON) 20 20 0% 20-Feb-12 16-Mar-12 08-Aug-12 05-Sep-12 120
CONPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (CON) 20 20 0% 19-Mar-12 13-Apr-12 06-Sep-12 03-Oct-12 120
DATPHNP-1631 ERECT PENTHOUSE STEEL/METAL DECK/TOPPING- NORTH PENT DAT 18 18 0% 28-Jan-13 22-Feb-13 20-Aug-13 19-Sep-13 120
DATPHNP-0750 BLOCKING/ROOFING- NORTH PENT DAT 15 15 0% 25-Feb-13 19-Mar-13 20-Sep-13 11-Oct-13 120
DATL1RO-0977 INSTALL OWNER FIXED FF&E - LVL-1 RAD OFFICES DAT 20 20 0% 06-May-14 03-Jun-14 27-Oct-14 25-Nov-14 120
DATL1RO-8880 CLEAN-UP/PRE PUNCH - LVL-1 RAD OFFICES DAT 10 10 0% 04-Jun-14 17-Jun-14 26-Nov-14 09-Dec-14 120
DATL1IL-0801 TRIM-OUT MEP (OFFICE) (AHU8) - LVL-1 INTER LVL DAT 15 15 0% 06-May-14 27-May-14 27-Oct-14 17-Nov-14 120
DATL3PA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 PACU DAT 35 35 0% 26-Dec-13 17-Feb-14 18-Jun-14 06-Aug-14 120
DATL3PA-0910 FRAMING/INWALL ROUGH - LVL-3 PACU DAT 45 45 0% 26-Dec-13 03-Mar-14 18-Jun-14 20-Aug-14 120
DATL3PA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 PACU DAT 25 25 0% 03-Feb-14 10-Mar-14 24-Jul-14 27-Aug-14 120
DATL3PA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PACU DAT 65 65 0% 04-Mar-14 03-Jun-14 21-Aug-14 25-Nov-14 120
IBSPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENT IBS 15 15 0% 03-Jul-13 29-Jul-13 23-Jan-14 14-Feb-14 120
IBSPHPH-0710 INSTALL LOUVERS - PENT IBS 10 10 0% 30-Jul-13 15-Aug-13 17-Feb-14 28-Feb-14 120
IBSPHPH-0777 INSTALL METAL PANEL - PENT IBS 10 10 0% 16-Aug-13 03-Sep-13 03-Mar-14 17-Mar-14 120
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
33 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 114
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
IBNPHPH-0725 SPRAY-ON FIREPROOFING - PENT IBN 8 8 0% 06-May-13 17-May-13 29-Nov-13 11-Dec-13 121
HOIMHMH-0300 INSTALL/MAINTAIN MAN MATERIAL HOIST (IBN) 256 256 0% 12-Jul-13 24-Mar-14 10-Jan-14 23-Jul-14 121
IFO-4900 KT APPROVE WATER TREATMENT EQUIPMENT - IFO-1 15 15 0% 29-Jun-12 20-Jul-12 26-Dec-12 16-Jan-13 121
IFO-3860 SUBMIT WATER TREATMENT EQUIPMENT - IFO-1 60 60 0% 05-Apr-12 28-Jun-12 26-Sep-12 24-Dec-12 121
IFO-3870 VA APPROVE WATER TREATMENT EQUIPMENT - IFO-1 20 20 0% 23-Jul-12 17-Aug-12 17-Jan-13 15-Feb-13 121
IFO-3880 FABRICATE WATER TREATMENT EQUIPMENT - IFO-1 120 120 0% 20-Aug-12 14-Feb-13 18-Feb-13 06-Aug-13 121
IFO-3890 WATER TREATMENT EQUIPMENT ARRIVES 0 0 0% 14-Feb-13 06-Aug-13 121
DATPHPH-0370 FORM/REINFORCE/PLACE/FINISH EQUIPMENT PADS (north penthouse) - PENT DAT 7 7 0% 02-Jan-13 10-Jan-13 25-Jul-13 05-Aug-13 121
IBSPHPH-1610 FORM/PLACE EQUIPMENT PADS - PENT IBS 5 5 0% 14-May-13 21-May-13 09-Dec-13 13-Dec-13 121
IBSPBPB-0103 FORM/PLACE TOWER CRANE #3 BASE (IBS/IBN CON B) 35 35 0% 14-Mar-12 15-May-12 11-Oct-12 10-Dec-12 121
DATPOPO-5030 KT APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (DAT) 25 25 0% 26-Jan-12 01-Mar-12 19-Jul-12 22-Aug-12 122
DATPOPO-3590 PREPARE/SUBMIT INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (DAT) 30 30 0% 12-Dec-11 25-Jan-12 06-Jun-12 18-Jul-12 122
DATPOPO-3600 VA APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (DAT) 20 20 0% 02-Mar-12 29-Mar-12 23-Aug-12 20-Sep-12 122
DATPOPO-3610 FABRICATE/DELIVER INTERSTITIAL STEEL - STR-2 (DAT) 40 40 0% 30-Mar-12 24-May-12 21-Sep-12 19-Nov-12 122
DATPOPO-3620 FIRST DELIVERY OF INTERSTITIAL STEEL - STR-2 (DAT) 0 0 0% 24-May-12 19-Nov-12 122
IBSESEE-0870 INSTALL PRECAST PANELS - EAST ELEV IBS 10 10 0% 22-Mar-13 08-Apr-13 22-Oct-13 05-Nov-13 122
IBSESSE-0877 INSTALL PRECAST PANELS - SOUTH ELEV IBS 5 5 0% 09-Apr-13 16-Apr-13 07-Nov-13 14-Nov-13 122
IBSESSE-0880 INSTALL METAL PANELS - SOUTH ELEV IBS 15 15 0% 16-Jul-13 09-Aug-13 05-Feb-14 27-Feb-14 122
IBSESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV IBS 50 50 0% 18-Apr-13 15-Jul-13 15-Nov-13 04-Feb-14 122
IBSESWE-0870 INSTALL STOREFRONT - WEST ELEV IBS 10 10 0% 12-Aug-13 27-Aug-13 28-Feb-14 14-Mar-14 122
IBSESWE-0880 INSTALL STRIP WINDOWS - WEST ELEV IBS 5 5 0% 29-Aug-13 05-Sep-13 17-Mar-14 24-Mar-14 122
IBSESNE-0870 INSTALL PRECAST PANELS - NORTH ELEV IBS 10 10 0% 07-Mar-13 21-Mar-13 04-Oct-13 21-Oct-13 122
CONL1AB-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-B CON 10 10 0% 11-Jul-14 24-Jul-14 08-Jan-15 22-Jan-15 123
IBNPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENT IBN 15 15 0% 25-Jun-13 19-Jul-13 21-Jan-14 11-Feb-14 123
IBNPHPH-0710 INSTALL LOUVERS - PENT IBN 10 10 0% 22-Jul-13 06-Aug-13 13-Feb-14 26-Feb-14 123
IBNPHPH-0777 INSTALL METAL PANELS - PENT IBN 10 10 0% 08-Aug-13 23-Aug-13 27-Feb-14 13-Mar-14 123
CONSLAB-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-B CON 50 50 0% 31-Jan-13 11-Apr-13 29-Jul-13 07-Oct-13 124
CONSLAA-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-A CON 60 60 0% 31-Oct-12 30-Jan-13 02-May-... 26-Jul-13 124
CONSLAC-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-C CON 55 55 0% 12-Apr-13 28-Jun-13 08-Oct-13 27-Dec-13 124
CONSLAC-8900 PULL 13.2 KVAWIRE - SERV LVL AR-C CON 5 5 0% 01-Jul-13 08-Jul-13 30-Dec-13 06-Jan-14 124
IBNPHPH-1610 FORM/PLACE FINISH EQUIPMENT PADS - PENT IBN 5 5 0% 06-May-13 13-May-13 05-Dec-13 11-Dec-13 124
EEEEDAT-0000 DAT BLDG AVAILABLE FOR ENERGIZE 0 0 0% 23-Oct-13 23-Apr-14 124
DATPHNP-1641 START-UP ELECTRICAL SYSTEMS - NORTH PENT MECH DAT 30 30 0% 24-Oct-13 06-Dec-13 24-Apr-14 05-Jun-14 124
DATPHSP-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - SOUTH PENT ELEC DAT 75 75 0% 09-Jul-13 23-Oct-13 07-Jan-14 23-Apr-14 124
DATPHSP-1641 START-UP ELECTRICAL SYSTEMS - SOUTH PENT MECH DAT 30 30 0% 24-Oct-13 06-Dec-13 24-Apr-14 05-Jun-14 124
IBNL2CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CORR IBN 15 15 0% 01-Apr-14 21-Apr-14 26-Sep-14 16-Oct-14 125
IBNL2CO-8880 CLEAN-UP/PRE PUNCH - LVL-2 CORR IBN 10 10 0% 22-Apr-14 05-May-14 17-Oct-14 31-Oct-14 125
IBNL2CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 SHELL IBN 20 20 0% 18-Dec-13 16-Jan-14 18-Jun-14 16-Jul-14 125
IBNL2CS-8880 CLEAN-UP/PRE PUNCH - LVL-2 SHELL IBN 15 15 0% 15-Apr-14 05-May-14 10-Oct-14 31-Oct-14 125
IBNL2CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SHELL IBN 20 20 0% 10-Jan-14 07-Feb-14 10-Jul-14 06-Aug-14 125
IBNL2CS-1190 INSTALL MEDICAL HEADWALLS - LVL-2 SHELL IBN 35 35 0% 11-Feb-14 31-Mar-14 07-Aug-14 25-Sep-14 125
IBNL2CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 SHELL IBN 10 10 0% 01-Apr-14 14-Apr-14 26-Sep-14 09-Oct-14 125
DATL1IL-1501 TRIM-OUT MEP (SPECIAL RADIOLOGY) (AHU15) - LVL-1 INTER LVL DAT 20 20 0% 22-Apr-14 19-May-14 17-Oct-14 17-Nov-14 125
CONSLAD-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-D CON 47 47 0% 01-Jul-13 05-Sep-13 02-Jan-14 11-Mar-14 126
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
34 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 115
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CONSLAE-8890 R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-E CON 68 68 0% 06-Sep-13 13-Dec-13 12-Mar-14 16-Jun-14 126
CONSLAE-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-E CON 30 30 0% 16-Dec-13 29-Jan-14 17-Jun-14 29-Jul-14 126
CONSLKI-8880 CLEAN-UP/PRE PUNCH - SERV LVL KITCHEN AR-E CON 15 15 0% 30-Jun-14 21-Jul-14 31-Dec-14 22-Jan-15 126
CONSLKI-0990 INSTALL INTERIOR FINISHES - SERV LVL KITCHEN AR-E CON 20 20 0% 02-May-14 30-May-14 31-Oct-14 01-Dec-14 126
CONSLKI-1110 SET/CONNECT/TEST/INSP KITCHEN EQUIP- SERV LVL KITCHEN AR-E CON 20 20 0% 02-Jun-14 27-Jun-14 02-Dec-14 30-Dec-14 126
CONSLKI-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL KITCHEN AR-E CON 15 15 0% 11-Apr-14 01-May-14 09-Oct-14 30-Oct-14 126
CONSLKI-1516 R-I OVERHEAD MEP/FIRE PRO/HOODS - SERV LVL KITCHEN AR-E CON 35 35 0% 30-Jan-14 20-Mar-14 30-Jul-14 17-Sep-14 126
CONSLKI-0910 FRAMING/INWALL ROUGH - SERV LVL KITCHEN AR-E CON 15 15 0% 21-Mar-14 10-Apr-14 18-Sep-14 08-Oct-14 126
AAAAENC-0100 START ENC CONSTRUCTION (start milestone) 0 0 0% 05-Apr-12 09-Aug-12 126
ENCALAL-0553 ERECT STAIR (ST3) - ALL LVLS ENC 15 15 0% 06-Nov-12 30-Nov-12 07-Jun-13 02-Jul-13 127
ENCALAL-0551 ERECT STAIR (ST1) - ALL LVLS ENC 15 15 0% 04-Oct-12 26-Oct-12 03-May-... 29-May-13 127
ENCALAL-0552 ERECT STAIR (ST2) - ALL LVLS ENC 15 15 0% 22-Oct-12 14-Nov-12 21-May-... 14-Jun-13 127
ENCLRLR-0720 SPRAY ON FIREPROOFING - LOW ROOF ENC 5 5 0% 01-Nov-12 08-Nov-12 03-Jun-13 10-Jun-13 127
ENCHRHR-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - HIGH ROOF ENC 5 5 0% 24-Oct-12 30-Oct-12 24-May-... 31-May-13 127
ENCHRHR-0750 APPLY ROOFING - HIGH ROOF ENC 10 10 0% 15-Nov-12 30-Nov-12 17-Jun-13 02-Jul-13 127
ENCHRHR-0720 SPRAY ON FIREPROOFING - HIGH ROOF ENC 3 3 0% 09-Nov-12 14-Nov-12 11-Jun-13 14-Jun-13 127
CBCSSSS-0352 FORM/PLACE/STRIP SHEAR WALLS - ALL LVLS CBC 45 45 0% 18-Sep-12 03-Dec-12 16-Apr-13 03-Jul-13 127
CBCSLSL-3210 DRILL/PLACE CAISSONS (with concourse) - SERV LVL CBC 5 5 0% 10-Jul-12 19-Jul-12 08-Feb-13 15-Feb-13 127
CBCSLSL-0330 FORM/PLACE PIER CAPS/ELEV PITS/ GRD BEAMS/WALLS/COLUMNS - SERV LVL CBC 35 35 0% 19-Jul-12 18-Sep-12 19-Feb-13 15-Apr-13 127
CONADSL-3110 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-D CON 15 15 0% 24-Apr-12 21-May-12 03-Dec-12 26-Dec-12 128
PVSALAL-0990 FINISH STAIR CORES ST1/ST2/ST3 - ALL LVLS PVS 25 25 0% 07-May-13 11-Jun-13 08-Nov-13 16-Dec-13 129
DATPHSP-0510 ERECT PENTHOUSE STEEL/METAL DECK/TOPPING- SOUTH PENT DAT 18 18 0% 11-Jan-13 07-Feb-13 20-Aug-13 19-Sep-13 129
DATPHSP-0750 BLOCKING/ROOFING- SOUTH PENT DAT 15 15 0% 08-Feb-13 04-Mar-13 20-Sep-13 11-Oct-13 129
IBSL2NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 NURSING IBS 20 20 0% 16-Sep-13 11-Oct-13 25-Mar-14 21-Apr-14 129
IBSL2NR-8880 CLEAN-UP/PRE PUNCH - LVL-2 NURSING IBS 15 15 0% 09-Apr-14 29-Apr-14 10-Oct-14 31-Oct-14 129
IBSL2NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 NURSING IBS 30 30 0% 06-Jan-14 18-Feb-14 10-Jul-14 20-Aug-14 129
IBSL2NR-1190 INSTALL MEDICAL HEADWALLS - LVL-2 NURSING IBS 35 35 0% 19-Feb-14 08-Apr-14 21-Aug-14 09-Oct-14 129
IBSL2NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 NURSING IBS 10 10 0% 09-Apr-14 22-Apr-14 10-Oct-14 24-Oct-14 129
IBSL2CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SHELL IBS 15 15 0% 14-Oct-13 04-Nov-13 22-Apr-14 12-May-14 129
IBSL2CS-0910 FRAMING/INWALL ROUGH - LVL-2 SHELL IBS 55 55 0% 14-Oct-13 03-Jan-14 22-Apr-14 09-Jul-14 129
IBNL2SS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SUPPORT IBN 20 20 0% 11-Oct-13 08-Nov-13 22-Apr-14 19-May-14 130
IBNL2SS-0910 FRAMING/INWALL ROUGH - LVL-2 SUPPORT IBN 55 55 0% 11-Oct-13 02-Jan-14 22-Apr-14 09-Jul-14 130
IBNL2NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 NURSING IBN 20 20 0% 13-Sep-13 10-Oct-13 25-Mar-14 21-Apr-14 130
IBNL2NR-0910 FRAMING/INWALL ROUGH - LVL-2 NURSING IBN 55 55 0% 13-Sep-13 03-Dec-13 25-Mar-14 10-Jun-14 130
IBNL2NR-8880 CLEAN-UP/PRE PUNCH - LVL-2 NURSING IBN 15 15 0% 08-Apr-14 28-Apr-14 10-Oct-14 31-Oct-14 130
IBNL2NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 NURSING IBN 35 35 0% 11-Dec-13 31-Jan-14 18-Jun-14 06-Aug-14 130
IBNL2NR-1190 INSTALL MEDICAL HEADWALLS - LVL-2 NURSING IBN 35 35 0% 03-Feb-14 24-Mar-14 07-Aug-14 25-Sep-14 130
IBNL2NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 NURSING IBN 10 10 0% 25-Mar-14 07-Apr-14 26-Sep-14 09-Oct-14 130
IBNL3CS-0977 INSTALL OWNER FIXED FF&E - LVL-3 SHELL IBN 20 20 0% 18-Mar-14 14-Apr-14 19-Sep-14 16-Oct-14 130
IBNCOCO-1599 BUILDING FLUSH - IBN 10 10 0% 10-Oct-14 19-Oct-14 17-Feb-15 26-Feb-15 130
ZZZZIBT-9999 FINISH IBN CONSTRUCTION (finish milestone) 0 0 0% 19-Oct-14 26-Feb-15 130
XXXXIBN-0500 IBN OVERALL DURATION 906 906 0% 27-Apr-12 19-Oct-14 18-Jun-12 26-Feb-15 130
ENCPOPO-5599 KT APPROVE SUBSTATION SHOP DRAWINGS- ENC EQUIPMENT 20 20 0% 12-Jan-12 09-Feb-12 18-Jul-12 14-Aug-12 130
ENCPOPO-5699 PREPARE/SUBMIT SUBSTATION SHOP DRAWINGS- ENC EQUIPMENT 50 50 0% 27-Oct-11 11-Jan-12 07-May-... 17-Jul-12 130
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
35 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 116
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ENCPOPO-5709 VA APPROVE SUBSTATION SHOP DRAWINGS - ENC EQUIPMENT 25 25 0% 10-Feb-12 16-Mar-12 15-Aug-12 19-Sep-12 130
ENCPOPO-5719 FABRICATE/DELIVER SUBSTATIONS - ENC EQUIPMENT 125 125 0% 19-Mar-12 12-Sep-12 20-Sep-12 25-Mar-13 130
CBNL3AB-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBN 15 15 0% 10-Mar-14 28-Mar-14 11-Sep-14 01-Oct-14 130
CBNL3AB-8880 CLEAN-UP/PRE PUNCH - LVL-3 AREA B CBN 8 8 0% 31-Mar-14 09-Apr-14 02-Oct-14 13-Oct-14 130
CBNL3AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA B CBN 22 22 0% 27-Feb-14 28-Mar-14 02-Sep-14 01-Oct-14 130
DATL1GR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 GEN RADIOLOGY DAT 65 65 0% 04-Nov-13 07-Feb-14 13-May-... 13-Aug-14 130
DATL1GR-0910 FRAMING/INWALL ROUGH - LVL-1 GEN RADIOLGY DAT 25 25 0% 04-Oct-13 08-Nov-13 15-Apr-14 19-May-14 130
DATL1GR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 GEN RADIOLGY DAT 30 30 0% 18-Oct-13 03-Dec-13 29-Apr-14 10-Jun-14 130
DATL3PA-0977 INSTALL OWNER FIXED FF&E - LVL-3 PACU LABS DAT 20 20 0% 06-May-14 03-Jun-14 10-Nov-14 09-Dec-14 130
DATL3PA-8880 CLEAN-UP/PRE PUNCH - LVL-3 PACU DAT 10 10 0% 04-Jun-14 17-Jun-14 10-Dec-14 23-Dec-14 130
IBSL3L3-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-3 IBS 20 20 0% 07-May-13 10-Jun-13 16-Dec-13 16-Jan-14 130
IBSL3L3-0725 SPRAY-ON FIREPROOFING - LVL-3 IBS 8 8 0% 22-Apr-13 06-May-13 03-Dec-13 13-Dec-13 130
IBSPBPB-1516 R-I OVERHEAD MEP/FIRE PRO - PIPE BSMT IBS 15 15 0% 26-Feb-13 18-Mar-13 29-Aug-13 19-Sep-13 130
RESESEE-1600 INSTALL SOLAR TUBES - EAST ELEV RES 30 30 0% 27-Nov-14 13-Jan-15 07-Jul-15 27-Aug-15 131
DATPHPH-0322 FORM/REINFORCE/PLACE EQUIPMENT PADS (south penthouse) - PENT DAT 7 7 0% 14-Dec-12 26-Dec-12 25-Jul-13 05-Aug-13 131
DATESAC-0540 ERECT EXTERIOR STUDS - ALL ELEVS AR-C DAT 15 15 0% 08-Feb-13 04-Mar-13 24-Sep-13 17-Oct-13 131
IBSL2L2-0725 SPRAY-ON FIREPROOFING - LVL-2 IBS 8 8 0% 05-Apr-13 18-Apr-13 19-Nov-13 02-Dec-13 131
SWSW-0100 KT DEMOBILIZE LESS RESEARCH AND CBS LVL-2 BUILDOUT 40 40 0% 30-Jan-15 30-Mar-15 07-Aug-15 02-Oct-15 132
EEEEIBS-0000 IBS BLDG AVAILABLE FOR ENERGIZE 0 0 0% 13-Feb-14 20-Aug-14 132
ENCPOPO-5589 KT APPROVE GENERATOR SHOP DRAWINGS- ENC EQUIPMENT 20 20 0% 12-Jan-12 09-Feb-12 20-Jul-12 16-Aug-12 132
ENCPOPO-5669 PREPARE/SUBMIT GENERATOR SHOP DRAWINGS- ENC EQUIPMENT 50 50 0% 27-Oct-11 11-Jan-12 09-May-... 19-Jul-12 132
ENCPOPO-5679 VA APPROVE GENERATOR SHOP DRAWINGS - ENC EQUIPMENT 25 25 0% 10-Feb-12 16-Mar-12 17-Aug-12 21-Sep-12 132
ENCPOPO-5689 FABRICATE/DELIVER GENERATORS - ENC EQUIPMENT 125 125 0% 19-Mar-12 12-Sep-12 24-Sep-12 27-Mar-13 132
IBSALAL-1400 INSTALL ELEVATOR SE04 - ALL LVLS IBS 60 60 0% 30-Jan-14 24-Apr-14 07-Aug-14 31-Oct-14 132
IBSALAL-1401 INSTALL ELEVATOR PE3/PE4 - ALL LVLS IBS 60 60 0% 30-Jan-14 24-Apr-14 07-Aug-14 31-Oct-14 132
IBSPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENT MECH IBS 45 45 0% 25-Sep-13 29-Nov-13 08-Apr-14 10-Jun-14 132
IBSPHME-0420 LAY CMU WALLS - PENT MECH IBS 15 15 0% 04-Sep-13 24-Sep-13 18-Mar-14 07-Apr-14 132
IBSPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH IBS 30 30 0% 14-Feb-14 27-Mar-14 21-Aug-14 02-Oct-14 132
IBSPHEL-0910 FRAMING/INWALL ROUGH - PENT ELEC IBS 10 10 0% 16-Oct-13 30-Oct-13 29-Apr-14 12-May-14 132
IBSPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC IBS 70 70 0% 31-Oct-13 13-Feb-14 13-May-... 20-Aug-14 132
CONADSL-3210 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-D CON 7 7 0% 30-Mar-12 10-Apr-12 20-Nov-12 30-Nov-12 134
HOIMHMH-0200 INSTALL/MAINTAIN MAN/MATERIAL HOIST (IBS) 249 249 0% 20-Jul-13 25-Mar-14 17-Jan-14 06-Aug-14 134
ENCESNE-0870 INSTALL METAL PANELS - NORTH ELEV ENC 15 15 0% 05-Aug-13 29-Aug-13 13-Mar-14 07-Apr-14 134
ENCESNE-870 INSTALL CURTAINWALL - NORTH ELEV ENC 10 10 0% 18-Jul-13 02-Aug-13 26-Feb-14 11-Mar-14 134
ENCESSE-880 INSTALL CURTAINWALL - SOUTH ELEV ENC 10 10 0% 13-Jun-13 28-Jun-13 27-Jan-14 07-Feb-14 134
ENCESWE-870 INSTALL CURTAINWALL - WEST ELEV ENC 10 10 0% 01-Jul-13 16-Jul-13 11-Feb-14 25-Feb-14 134
ENCESEE-0870 INSTALL METAL PANELS/LOUVERS - EAST ELEV ENC 15 15 0% 30-Aug-13 24-Sep-13 08-Apr-14 02-May-14 134
CBNL3AA-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBN 15 15 0% 04-Mar-14 24-Mar-14 11-Sep-14 01-Oct-14 134
CBNL3AA-8880 CLEAN-UP/PRE PUNCH - LVL-3 AREA A CBN 8 8 0% 25-Mar-14 03-Apr-14 02-Oct-14 13-Oct-14 134
CBNL3AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA A CBN 23 23 0% 20-Feb-14 24-Mar-14 29-Aug-14 01-Oct-14 134
CBNPHPH-0540 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTLVL CBN 15 15 0% 15-Apr-13 10-May-13 03-Dec-13 26-Dec-13 134
CBNPHPH-0710 INSTALL LOUVERS - PENTLVL CBN 10 10 0% 13-May-13 29-May-13 27-Dec-13 10-Jan-14 134
CBNPHPH-0777 INSTALL METAL PANEL - PENTLVL CBN 10 10 0% 30-May-13 14-Jun-13 13-Jan-14 28-Jan-14 134
PVNSLLM-1560 ROUGH-IN MEP/FIRE PROTECTION - SERV LVL DOCK/MAINTENANCE PVN 40 40 0% 06-Feb-14 03-Apr-14 19-Aug-14 14-Oct-14 135
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
36 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 117
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
IBNL1UR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 UROLOGY IBN 20 20 0% 25-Jul-13 21-Aug-13 11-Feb-14 10-Mar-14 135
IBNL1PY-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 PHARMACY IBN 20 20 0% 22-Aug-13 19-Sep-13 11-Mar-14 07-Apr-14 135
IBNL1PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-1 PT/OT IBN 20 20 0% 26-Jun-13 24-Jul-13 10-Jan-14 07-Feb-14 135
IBNL1OF-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 OFFICE IBN 20 20 0% 20-Sep-13 17-Oct-13 08-Apr-14 05-May-14 135
IBNL1OF-0910 FRAMING/INWALL ROUGH - LVL-1 OFFICE IBN 55 55 0% 20-Sep-13 10-Dec-13 08-Apr-14 24-Jun-14 135
IBNL1OF-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 OFFICE IBN 25 25 0% 12-Nov-13 17-Dec-13 28-May-... 01-Jul-14 135
IBNL1OF-8880 CLEAN-UP/PRE PUNCH - LVL-1 OFFICE IBN 15 15 0% 01-Apr-14 21-Apr-14 10-Oct-14 31-Oct-14 135
IBNL1OF-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 OFFICE IBN 30 30 0% 11-Dec-13 24-Jan-14 25-Jun-14 06-Aug-14 135
IBNL1OF-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 OFFICE IBN 10 10 0% 18-Mar-14 31-Mar-14 26-Sep-14 09-Oct-14 135
IBNL1OF-1190 INSTALL MEDICAL HEADWALLS - LVL-1 OFFICE IBN 35 35 0% 27-Jan-14 17-Mar-14 07-Aug-14 25-Sep-14 135
IBNL3RH-0977 INSTALL OWNER FIXED FF&E - LVL-3 REHAB IBN 20 20 0% 04-Mar-14 31-Mar-14 12-Sep-14 09-Oct-14 135
IBNL3PR-8880 CLEAN-UP/PRE PUNCH - LVL-3 PATIENT IBN 15 15 0% 01-Apr-14 21-Apr-14 10-Oct-14 31-Oct-14 135
IBNL3PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PATIENT IBN 35 35 0% 04-Dec-13 24-Jan-14 18-Jun-14 06-Aug-14 135
IBNL3PR-1190 INSTALL MEDICAL HEADWALLS - LVL-3 PATIENT IBN 35 35 0% 27-Jan-14 17-Mar-14 07-Aug-14 25-Sep-14 135
IBNL3PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-3 PATIENT IBN 10 10 0% 18-Mar-14 31-Mar-14 26-Sep-14 09-Oct-14 135
OSI-5610 FRA/COA APPROVE WORK/TRAFFIC CONTROL PLAN - OSI-1 0 0 0% 23-Nov-11 08-Jun-12 135
CBNALAL-0990 FINISH STAIR CORE ST1 - ALL LVLS CBN 15 15 0% 20-Feb-14 12-Mar-14 02-Sep-14 22-Sep-14 135
CBNALAL-0991 FINISH STAIR CORE ST2 - ALL LVLS CBN 15 15 0% 13-Mar-14 02-Apr-14 23-Sep-14 13-Oct-14 135
CBNPHPH-1500 SET MECH EQUIPMENT - PENTLVL CBN 5 5 0% 25-Mar-13 29-Mar-13 03-Oct-13 09-Oct-13 135
CBNPHPH-1600 SET ELECTRICAL EQUIPMENT - PENTLVL CBN 10 10 0% 01-Apr-13 12-Apr-13 10-Oct-13 24-Oct-13 135
DATL1FL-0977 INSTALL OWNER FIXED FF&E - LVL-1 FLURO.UTLSND DAT 20 20 0% 29-Apr-14 27-May-14 10-Nov-14 09-Dec-14 135
DATL1FL-8880 CLEAN-UP/PRE PUNCH - LVL-1 FLURO/UTLSND DAT 10 10 0% 28-May-14 10-Jun-14 10-Dec-14 23-Dec-14 135
DATL2IL-1700 ROUGH-IN MEP/FIRE PROTECTION (LABS) (AHU17) - LVL-2 INTER LVL DAT 45 45 0% 01-Aug-13 03-Oct-13 18-Feb-14 21-Apr-14 135
CONSLKI-1120 INSTALL WALK-IN COOLERS/FREEZERS- SERV LVL KITCHEN AR-E CON 10 10 0% 02-May-14 15-May-14 17-Nov-14 01-Dec-14 136
IBNPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENT MECH IBN 45 45 0% 17-Sep-13 20-Nov-13 04-Apr-14 06-Jun-14 136
IBNPHME-0420 LAY CMU WALLS - PENT MECH IBN 15 15 0% 26-Aug-13 16-Sep-13 14-Mar-14 03-Apr-14 136
IBNPHME-1641 START-UP ELECTRICAL SYSTEMS - PENT MECH IBN 30 30 0% 05-Feb-14 19-Mar-14 19-Aug-14 30-Sep-14 136
IBNPHEL-0910 FRAMING/INWALL ROUGH - PENT ELEC IBN 10 10 0% 08-Oct-13 22-Oct-13 25-Apr-14 08-May-14 136
IBNPHEL-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC IBN 70 70 0% 23-Oct-13 04-Feb-14 09-May-... 18-Aug-14 136
EEEEIBN-0000 IBN BLDG AVAILABLE FOR ENERGIZE 0 0 0% 04-Feb-14 18-Aug-14 136
IBSL1L1-0725 SPRAY-ON FIREPROOFING - LVL-1 IBS 8 8 0% 15-Mar-13 26-Mar-13 05-Nov-13 18-Nov-13 136
AAAAPVS-0100 START PVS CONSTRUCTION (start milestone) 0 0 0% 06-Feb-12 22-Jun-12 136
CBCLRLR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF CBC 3 3 0% 13-Feb-14 17-Feb-14 07-Oct-14 09-Oct-14 138
CBCLRLR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF CBC 15 15 0% 21-Jan-14 11-Feb-14 12-Sep-14 06-Oct-14 138
IBSPHPH-1500 SET MECH EQUIPMENT - PENT IBS 15 15 0% 29-May-13 18-Jun-13 16-Dec-13 07-Jan-14 138
IBSPHPH-1600 SET ELECTRICAL EQUIPMENT - PENT IBS 10 10 0% 19-Jun-13 02-Jul-13 08-Jan-14 22-Jan-14 138
PVNSLDO-0288 BACKFILL DOCK WALLS - SERV LVL DOCK PVN 5 5 0% 13-Dec-13 20-Dec-13 07-Aug-14 14-Aug-14 139
IBSL2NR-0910 FRAMING/INWALL ROUGH - LVL-2 NURSING IBS 55 55 0% 16-Sep-13 04-Dec-13 08-Apr-14 24-Jun-14 139
IBSSLCS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHELL IBS 10 10 0% 23-Aug-13 06-Sep-13 18-Mar-14 31-Mar-14 139
IBSSLCS-0910 FRAMING/INWALL ROUGH - SERV LVL SHELL IBS 55 55 0% 23-Aug-13 12-Nov-13 18-Mar-14 03-Jun-14 139
IBSSLCS-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL SHELL IBS 20 20 0% 22-Oct-13 19-Nov-13 13-May-... 10-Jun-14 139
IBSSLCS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHELL IBS 30 30 0% 13-Nov-13 26-Dec-13 04-Jun-14 16-Jul-14 139
IBSSLCS-1190 INSTALL MEDICAL HEADWALLS - SERV LVL SHELL IBS 35 35 0% 27-Dec-13 18-Feb-14 17-Jul-14 04-Sep-14 139
IBSSLCA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 CANTEEN IBS 15 15 0% 20-Jun-13 11-Jul-13 10-Jan-14 31-Jan-14 139
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
37 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 118
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
IBSSLPA-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL PATH IBS 15 15 0% 12-Jul-13 01-Aug-13 03-Feb-14 24-Feb-14 139
IBSSLES-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL ENVIRO IBS 15 15 0% 30-May-13 19-Jun-13 18-Dec-13 09-Jan-14 139
IBSSLCO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CORR IBS 25 25 0% 19-Feb-14 25-Mar-14 05-Sep-14 09-Oct-14 139
IBSSLCO-8880 CLEAN-UP/PRE PUNCH - SERV LVL CORR IBS 15 15 0% 26-Mar-14 15-Apr-14 10-Oct-14 31-Oct-14 139
IBSSLBM-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL BIO IBS 15 15 0% 02-Aug-13 22-Aug-13 25-Feb-14 17-Mar-14 139
CBCPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENTHOUSE MECH CBC 25 25 0% 11-Mar-14 14-Apr-14 26-Sep-14 31-Oct-14 140
ENCPOPO-5579 VA APPROVE SWITCHGEAR SHOP DRAWINGS - ENC EQUIPMENT 25 25 0% 10-Feb-12 16-Mar-12 29-Aug-12 03-Oct-12 140
ENCPOPO-5639 PREPARE/SUBMIT SWITCHGEAR SHOP DRAWINGS- ENC EQUIPMENT 50 50 0% 27-Oct-11 11-Jan-12 21-May-... 31-Jul-12 140
ENCPOPO-5649 KT APPROVE SWITCHGEAR SHOP DRAWINGS- ENC EQUIPMENT 20 20 0% 12-Jan-12 09-Feb-12 01-Aug-12 28-Aug-12 140
ENCPOPO-5659 FABRICATE/DELIVER SWITCHGEAR - ENC EQUIPMENT 115 115 0% 19-Mar-12 28-Aug-12 04-Oct-12 25-Mar-13 140
CBNSLSL-0990 HANG/TAPE/FINISH/PAINT - SERV LVL CORR CBN 10 10 0% 20-Feb-14 05-Mar-14 09-Sep-14 22-Sep-14 140
CBNSLSL-0910 FRAMING/INWALL ROUGH - SERV LVL CBN 5 5 0% 13-Feb-14 19-Feb-14 02-Sep-14 08-Sep-14 140
CBNL1AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA B CBN 22 22 0% 10-Jan-14 12-Feb-14 31-Jul-14 29-Aug-14 140
DATL1IL-0101 TRIM-OUT MEP (PRE ADMIN) (AHU1) - LVL-1 INTER LVL DAT 15 15 0% 08-Apr-14 28-Apr-14 27-Oct-14 17-Nov-14 140
IBSESSE-0580 ERECT/CONNECT PEDESTRIAN BRIDGE - SOUTH ELEV IBS 22 22 0% 11-Feb-13 18-Mar-13 09-Oct-13 14-Nov-13 140
IBSL1CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SHELL IBS 25 25 0% 04-Nov-13 10-Dec-13 28-May-... 01-Jul-14 140
IBSL1CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SHELL IBS 20 20 0% 11-Dec-13 09-Jan-14 02-Jul-14 30-Jul-14 140
IBSL1CS-1190 INSTALL MEDICAL HEADWALLS - LVL-1 SHELL IBS 35 35 0% 10-Jan-14 03-Mar-14 31-Jul-14 18-Sep-14 140
IBSL1PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 PATIENT IBS 35 35 0% 06-Sep-13 25-Oct-13 01-Apr-14 19-May-14 140
IBSL1CO-8880 CLEAN-UP/PRE PUNCH - LVL-1 CORR IBS 10 10 0% 01-Apr-14 14-Apr-14 17-Oct-14 31-Oct-14 140
IBSL1CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 CORR IBS 20 20 0% 04-Mar-14 31-Mar-14 19-Sep-14 16-Oct-14 140
IBSL1NR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 NURSING IBS 35 35 0% 04-Oct-13 26-Nov-13 29-Apr-14 17-Jun-14 140
PVNSLPK-1620 ROUGH-IN/INSTALL SUBSTATION - SERV LVL PARK PVN 10 10 0% 21-Feb-14 06-Mar-14 11-Sep-14 24-Sep-14 141
CONADHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- HIGH ROOF AR-D CON 11 11 0% 21-May-13 07-Jun-13 17-Jan-14 03-Feb-14 142
CONADHR-0755 INSTALL STANDING SEAM ROOF - LOW ROOF AR-D CON 31 31 0% 10-Jun-13 01-Aug-13 04-Feb-14 24-Mar-14 142
CONADHR-0888 INSTALL GLAZING @ CLEARSTORY - LOW ROOF AR-D CON 13 13 0% 02-Aug-13 23-Aug-13 25-Mar-14 15-Apr-14 142
CONADHR-0510 FRAMING @ CLEARSTORY - HIGH ROOF AR-D CON 11 11 0% 02-May-13 20-May-13 31-Dec-13 16-Jan-14 142
IBNESWE-0870 INSTALL METAL PANELS - WEST ELEV IBN 15 15 0% 08-Jul-13 01-Aug-13 28-Feb-14 24-Mar-14 142
IBNESEE-0870 INSTALL PRECAST PANELS - EAST ELEV IBN 10 10 0% 15-Mar-13 29-Mar-13 15-Nov-13 02-Dec-13 142
IBNESEE-870 INSTALL CURTAIN WALL - EAST ELEV IBN 15 15 0% 01-Apr-13 25-Apr-13 03-Dec-13 26-Dec-13 142
IBNESSE-870 INSTALL METAL PANELS - SOUTH ELEV IBN 20 20 0% 03-Jun-13 05-Jul-13 29-Jan-14 27-Feb-14 142
IBNESSE-0870 INSTALL CURTAIN WALL - SOUTH ELEV IBN 20 20 0% 26-Apr-13 31-May-13 27-Dec-13 28-Jan-14 142
IBNPHPH-1500 SET MECH EQUIPMENT - PENT IBN 15 15 0% 20-May-13 10-Jun-13 12-Dec-13 03-Jan-14 142
IBNPHPH-1600 SET ELECTRICAL EQUIPMENT - PENT IBN 10 10 0% 11-Jun-13 24-Jun-13 06-Jan-14 17-Jan-14 142
OSI-4410 VA REVIEWS/SIGN-OFF ON BID TABS- OSI-1 5 5 0% 09-Sep-11 15-Sep-11 06-Apr-12 12-Apr-12 142
OSI-5620 VA PROVDES CONSENT TO SUBCONTRACT - OSI-1 0 0 0% 15-Sep-11 12-Apr-12 142
OSI-4440 AWARD SUBCONTRACTS -OFS-1 20 20 0% 16-Sep-11 14-Oct-11 13-Apr-12 10-May-12 142
OSI-5320 SUBMIT WORK/TRAFFIC CONTROL PLAN - OSI-1 10 10 0% 17-Oct-11 28-Oct-11 11-May-... 24-May-12 142
OSI-5390 VA APPROVE WORK/TRAFFIC CONTROL PLAN - OSI-1 20 20 0% 31-Oct-11 30-Nov-11 25-May-... 22-Jun-12 142
OSI-4400 PREPARE/SUBMIT BID TABS TO VA - OSI-1 25 2 92% 18-Apr-11 A 08-Sep-11 04-Apr-12 05-Apr-12 142
P-CD4-4920 AWARD PNEUMATIC TUBE CONTRACT 20 20 0% 05-Apr-12 02-May-12 26-Oct-12 27-Nov-12 142
ALLPOPO-4850 KT APPROVE PNEUB TUBE SHOP DRAWINGS - IFO-1 20 20 0% 30-Jul-12 24-Aug-12 26-Feb-13 25-Mar-13 142
ALLPOPO-4820 PREPARE/SUBMIT PNEU TUBE SHOP DRAWINGS - IFO-1 60 60 0% 03-May-12 27-Jul-12 28-Nov-12 25-Feb-13 142
ALLPOPO-4830 VA APPROVE PNEUB TUBE SHOP DRAWINGS - IFO-1 20 20 0% 27-Aug-12 24-Sep-12 26-Mar-13 22-Apr-13 142
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
38 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 119
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ALLPOPO-4840 FAB/DELIVER PNEUMATIC TUBE - IFO-1 45 45 0% 25-Sep-12 30-Nov-12 23-Apr-13 25-Jun-13 142
ENCLRLR-0750 APPLY WATERPROOFING - LOW ROOF ENC 7 7 0% 01-Nov-12 13-Nov-12 28-Jun-13 09-Jul-13 142
CONL1AA-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH- LVL-1 AR-A CON 10 10 0% 12-Jun-14 25-Jun-14 08-Jan-15 22-Jan-15 143
CS1-4920 VA REVIEW BID TABS - CS-1/IFO-3 5 5 0% 28-Dec-11 04-Jan-12 23-Jul-12 27-Jul-12 143
CS1-3650 VA PROVIDES CONSENT TO SUBCONTRACT - CS-1/IFO-3 0 0 0% 04-Jan-12 27-Jul-12 143
CS1-3630 SUBCONTRACTOR PRICING - CS-1/IFO-3 25 25 0% 27-Oct-11 05-Dec-11 24-May-... 28-Jun-12 143
CS1-4930 PREPARE BID TABS - CS-1/IFO-3 15 15 0% 06-Dec-11 27-Dec-11 29-Jun-12 20-Jul-12 143
CS1-4960 AWARD MISC METAL CONTRACT 20 20 0% 05-Jan-12 02-Feb-12 30-Jul-12 24-Aug-12 143
CBPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 20 20 0% 05-Mar-12 30-Mar-12 25-Sep-12 23-Oct-12 143
DATPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 20 20 0% 02-Apr-12 27-Apr-12 24-Oct-12 21-Nov-12 143
IBPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 20 20 0% 03-Feb-12 02-Mar-12 27-Aug-12 24-Sep-12 143
ENCPOPO-5469 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 15 15 0% 29-May-12 18-Jun-12 24-Dec-12 15-Jan-13 143
ENCPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 20 20 0% 30-Apr-12 25-May-12 26-Nov-12 21-Dec-12 143
ENCPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 20 20 0% 19-Jun-12 17-Jul-12 16-Jan-13 14-Feb-13 143
ENCPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (ENC) 55 55 0% 18-Jul-12 03-Oct-12 15-Feb-13 02-May-13 143
CBNPHPH-0725 SPRAY-ON FIREPROOFING - PENTLVL CBN 10 10 0% 14-Mar-13 28-Mar-13 15-Nov-13 02-Dec-13 143
DATPHNP-1621 SET ELECTRICAL EQUIPMENT - NORTH PENT DAT 10 10 0% 11-Jan-13 25-Jan-13 06-Aug-13 19-Aug-13 143
DATALAL-0502 ERECT STAIRS (ST2)- ALL LVLS DAT 15 15 0% 24-Dec-12 15-Jan-13 23-Aug-13 17-Sep-13 143
DATALAL-0501 ERECT STAIRS (ST1) - ALL LVLS DAT 15 15 0% 09-Jan-13 31-Jan-13 10-Sep-13 03-Oct-13 143
DATALAL-0503 ERECT STAIRS (ST3) - ALL LVLS DAT 15 15 0% 25-Jan-13 15-Feb-13 27-Sep-13 21-Oct-13 143
DATALAL-0505 ERECT STAIRS (ST5) - ALL LVLS DAT 15 15 0% 08-Feb-13 04-Mar-13 11-Oct-13 05-Nov-13 143
IBSSLSL-0725 SPRAY-ON FIREPROOFING - SERVICE LEVEL IBS 8 8 0% 20-Feb-13 01-Mar-13 23-Oct-13 04-Nov-13 143
CONACHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- LOW ROOF AR-C CON 18 18 0% 18-Apr-13 20-May-13 23-Dec-13 21-Jan-14 144
CONACHR-0510 FRAMING @ CLEARSTORY - HIGH ROOF AR-C CON 12 12 0% 28-Mar-13 16-Apr-13 03-Dec-13 20-Dec-13 144
ZZZZSIT-9999 FINISH SITEWORK (finish milestone) 0 0 0% 04-Nov-14 28-Mar-15 144
IBSL1PR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-1 PATIENT IBS 20 20 0% 05-Jul-13 01-Aug-13 03-Feb-14 03-Mar-14 144
IBSL1PR-0910 FRAMING/INWALL ROUGH - LVL-1 PATIENT IBS 55 55 0% 05-Jul-13 20-Sep-13 03-Feb-14 21-Apr-14 144
IBSSLCA-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL CANTEEN IBS 20 20 0% 06-Sep-13 03-Oct-13 07-Apr-14 02-May-14 144
IBSSLPA-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL PATH IBS 20 20 0% 18-Sep-13 15-Oct-13 17-Apr-14 14-May-14 144
IBSSLBM-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL BIO IBS 20 20 0% 30-Sep-13 28-Oct-13 29-Apr-14 27-May-14 144
IBSSLBM-0910 FRAMING/INWALL ROUGH - SERV LVL BIO IBS 55 55 0% 02-Aug-13 18-Oct-13 04-Mar-14 19-May-14 144
IBNL1PY-0910 FRAMING/INWALL ROUGH - LVL-1 PHARMACY IBN 55 55 0% 22-Aug-13 08-Nov-13 25-Mar-14 10-Jun-14 145
IBNL1PY-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 PHARMACY IBN 25 25 0% 11-Oct-13 18-Nov-13 13-May-... 17-Jun-14 145
IBNL3L3-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-3 IBN 20 20 0% 26-Apr-13 31-May-13 02-Jan-14 31-Jan-14 145
IBNL3L3-0725 SPRAY-ON FIREPROOFING - LVL-3 IBN 8 8 0% 12-Apr-13 25-Apr-13 19-Dec-13 31-Dec-13 145
ENCLRLR-3210 SET COOLING TOWERS - LOW ROOF ENC 5 5 0% 17-Oct-12 23-Oct-12 17-May-... 23-May-13 145
PVSP1AE-1620 ROUGH-IN/INSTALL SUBSTATION - PKG LVL-1 AREA E PVS 10 10 0% 26-Mar-13 08-Apr-13 18-Oct-13 01-Nov-13 145
PVSP1AE-1666 PULL WIRE FROM CON - PKG LVL-1 AREA E PVS 5 5 0% 09-Apr-13 15-Apr-13 04-Nov-13 08-Nov-13 145
DATL1PA-0977 INSTALL OWNER FIXED FF&E - LVL-1 PRE-ADMIT DAT 20 20 0% 15-Apr-14 12-May-14 10-Nov-14 09-Dec-14 145
DATL1PA-8880 CLEAN-UP/PRE PUNCH - LVL-1 PRE-ADMIT DAT 10 10 0% 13-May-14 27-May-14 10-Dec-14 23-Dec-14 145
DATL3IL-0600 ROUGH-IN MEP/FIRE PROTECTION (PACU) (AHU6) - LVL-3 INTER LVL DAT 55 55 0% 29-Aug-13 18-Nov-13 01-Apr-14 17-Jun-14 145
MBSW-238 PLACE EROSION PROTECTION/TRAFFIC CONTROL - MONTVIEW BLVD. 4 4 0% 24-Oct-13 29-Oct-13 26-Jun-14 01-Jul-14 145
MBSW-248 DEMO/GRADING - MONTVIEW BLVD. 15 15 0% 31-Oct-13 25-Nov-13 02-Jul-14 28-Jul-14 145
MBSW-258 INSTALL UTILITIES - MONTVIEW BLVD. 15 15 0% 26-Nov-13 19-Dec-13 29-Jul-14 22-Aug-14 145
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
39 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 120
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
MBSW-268 CONSTRUCT ROADWAY - MONTVIEW BLVD. 25 25 0% 20-Dec-13 29-Jan-14 25-Aug-14 03-Oct-14 145
SITSWBW-318 CONSTRUCT ROADWAY - SOUTH WHEELING ST. 25 25 0% 01-Aug-13 12-Sep-13 28-Mar-14 09-May-14 145
IBSL1CS-8880 CLEAN-UP/PRE PUNCH - LVL-1 SHELL IBS 15 15 0% 18-Mar-14 07-Apr-14 10-Oct-14 31-Oct-14 145
IBSL1CS-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 SHELL IBS 10 10 0% 04-Mar-14 17-Mar-14 26-Sep-14 09-Oct-14 145
CONAAHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- LOW ROOF AR-A CON 12 12 0% 29-Aug-13 17-Sep-13 28-Apr-14 16-May-14 146
IBNL2L2-0725 SPRAY-ON FIREPROOFING - LVL-2 IBN 8 8 0% 28-Mar-13 09-Apr-13 06-Dec-13 17-Dec-13 146
CBNL2AB-0977 INSTALL OWNER FIXED FF&E - LVL-2 AREA-B CBN 15 15 0% 14-Feb-14 06-Mar-14 11-Sep-14 01-Oct-14 146
CBNL2AB-8880 CLEAN-UP/PRE PUNCH - LVL-2 AREA B CBN 8 8 0% 07-Mar-14 18-Mar-14 02-Oct-14 13-Oct-14 146
CBNL2AB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA B CBN 22 22 0% 04-Feb-14 06-Mar-14 02-Sep-14 01-Oct-14 146
DATPHNP-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - NORTH PENT MECH DAT 45 45 0% 20-Mar-13 21-May-13 15-Oct-13 19-Dec-13 146
DATPHNP-0910 FRAMING/INWALL ROUGH - NORTH PENT ELEC DAT 25 25 0% 10-Apr-13 14-May-13 06-Nov-13 12-Dec-13 146
DATPHNP-0920 HANG/TAPE/FINISH DRYWALL - NORTH PENT ELEC DAT 15 15 0% 15-May-13 05-Jun-13 13-Dec-13 06-Jan-14 146
DATPHNP-1620 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - NORTH PENT ELEC DAT 75 75 0% 06-Jun-13 20-Sep-13 07-Jan-14 23-Apr-14 146
IBNL2CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SHELL IBN 15 15 0% 28-Oct-13 18-Nov-13 02-Jun-14 20-Jun-14 148
IBNL2CS-0910 FRAMING/INWALL ROUGH - LVL-2 SHELL IBN 15 15 0% 28-Oct-13 18-Nov-13 02-Jun-14 20-Jun-14 148
DATPHNP-0420 LAY CMU WALLS - NORTH PENT MECH DAT 15 15 0% 25-Feb-13 15-Mar-13 24-Sep-13 14-Oct-13 148
CONSLAB-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-B CON 30 30 0% 12-Apr-13 23-May-13 14-Nov-13 27-Dec-13 149
IBSPOPO-4900 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (IBS) 25 25 0% 24-Feb-12 29-Mar-12 25-Sep-12 30-Oct-12 149
IBSPOPO-4670 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (IBS) 20 20 0% 30-Mar-12 26-Apr-12 31-Oct-12 30-Nov-12 149
IBSPOPO-4680 FABRICATE/DELIVER STRUCT STEEL - STR-2 (IBS) 65 65 0% 27-Apr-12 30-Jul-12 03-Dec-12 07-Mar-13 149
IBSPOPO-4690 FIRST DELIVERY OF STRUCT STEEL - STR-2 (IBS) 0 0 0% 30-Jul-12 07-Mar-13 149
IBSL3PR-0977 INSTALL OWNER FIXED FF&E - LVL-3 PATIENT IBS 20 20 0% 12-Feb-14 11-Mar-14 12-Sep-14 09-Oct-14 149
IBSL2PR-8880 CLEAN-UP/PRE PUNCH - LVL-2 PATIENT IBS 15 15 0% 12-Mar-14 01-Apr-14 10-Oct-14 31-Oct-14 149
IBSL2PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 PATIENT IBS 30 30 0% 05-Dec-13 17-Jan-14 10-Jul-14 20-Aug-14 149
IBSL2PR-1190 INSTALL MEDICAL HEADWALLS - LVL-2 PATIENT IBS 35 35 0% 21-Jan-14 11-Mar-14 21-Aug-14 09-Oct-14 149
IBSL2PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 PATIENT IBS 10 10 0% 12-Mar-14 25-Mar-14 10-Oct-14 24-Oct-14 149
IBSL1CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 SHELL IBS 10 10 0% 30-Aug-13 13-Sep-13 08-Apr-14 21-Apr-14 149
IBSL1CS-0910 FRAMING/INWALL ROUGH - LVL-1 SHELL IBS 55 55 0% 30-Aug-13 19-Nov-13 08-Apr-14 24-Jun-14 149
IBSL1NR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 NURSING IBS 20 20 0% 02-Aug-13 29-Aug-13 11-Mar-14 07-Apr-14 149
CONAESL-3211 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-E CON 7 7 0% 09-Apr-12 20-Apr-12 26-Dec-12 04-Jan-13 150
IBNL2PR-8880 CLEAN-UP/PRE PUNCH - LVL-1 PATIENT IBN 15 15 0% 11-Mar-14 31-Mar-14 10-Oct-14 31-Oct-14 150
IBNL2PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 PATIENT IBN 35 35 0% 12-Nov-13 02-Jan-14 18-Jun-14 06-Aug-14 150
IBNL2PR-1190 INSTALL MEDICAL HEADWALLS - LVL-2 PATIENT IBN 35 35 0% 03-Jan-14 24-Feb-14 07-Aug-14 25-Sep-14 150
IBNL2PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-2 PATIENT IBN 10 10 0% 25-Feb-14 10-Mar-14 26-Sep-14 09-Oct-14 150
IBNESEE-880 INSTALL METAL PANELS - EAST ELEV IBN 12 12 0% 26-Apr-13 17-May-13 09-Jan-14 28-Jan-14 150
CBNSLSL-8880 CLEAN-UP/PRE PUNCH - SERV LVL CORR CBN 5 5 0% 06-Mar-14 12-Mar-14 07-Oct-14 13-Oct-14 150
CBNL2AA-0977 INSTALL OWNER FIXED FF&E - LVL-2 AREA-A CBN 15 15 0% 07-Feb-14 28-Feb-14 11-Sep-14 01-Oct-14 150
CBNL2AA-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBN 8 8 0% 03-Mar-14 12-Mar-14 02-Oct-14 13-Oct-14 150
CBNL2AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA A CBN 23 23 0% 28-Jan-14 28-Feb-14 29-Aug-14 01-Oct-14 150
DATL3IL-0601 TRIM-OUT MEP (PACU) (AHU6) - LVL-3 INTER LVL DAT 5 5 0% 08-Apr-14 14-Apr-14 10-Nov-14 17-Nov-14 150
CONSLAE-8900 PULL 13.2 KVA WIRE - SERV LVL AR-E CON 5 5 0% 16-Dec-13 20-Dec-13 23-Jul-14 29-Jul-14 151
ENCSLEL-0420 LAY CMU WALLS - SERV LVL ELEC RMS ENC 10 10 0% 25-Oct-12 07-Nov-12 05-Jun-13 18-Jun-13 151
DATPHNP-1610 SET MECH EQUIPMENT- NORTH PENT DAT 2 2 0% 11-Jan-13 14-Jan-13 16-Aug-13 19-Aug-13 151
IBSSLPA-0910 FRAMING/INWALL ROUGH - SERV LVL PATH IBS 55 55 0% 12-Jul-13 27-Sep-13 20-Feb-14 07-May-14 151
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
40 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 121
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
AAAAIBS-0100 START IBS CONSTRUCTION (start milestone) 0 0 0% 14-Mar-12 14-Aug-12 153
IFO-3700 100% CD DOCUMENTS COMPLETE - IFO-1 0 0 0% 31-Jan-12 02-Jul-12 153
DATPHSP-1600 SET ELECTRICAL EQUIPMENT - SOUTH PENT DAT 10 10 0% 27-Dec-12 10-Jan-13 06-Aug-13 19-Aug-13 153
HOITCTC-0300 MAINTAIN TOWER CRANE #3 (IBS/IBN, CON B) 524 524 0% 16-May-12 21-Oct-13 11-Dec-12 24-Mar-14 154
CONPOPO-4844 FIRST DELIVERY OF STRUCT STEEL - STR-2 (CON) 0 0 0% 25-Sep-12 09-May-13 154
CONPOPO-4910 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CON) 25 25 0% 20-Apr-12 24-May-12 03-Dec-12 08-Jan-13 154
CONPOPO-4820 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (CON) 50 50 0% 09-Feb-12 19-Apr-12 18-Sep-12 30-Nov-12 154
CONPOPO-4830 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CON) 20 20 0% 25-May-12 22-Jun-12 09-Jan-13 06-Feb-13 154
CONPOPO-4840 FABRICATE/DELIVER STRUCT STEEL - STR-2 (CON) 65 65 0% 25-Jun-12 25-Sep-12 07-Feb-13 09-May-13 154
CBNPHME-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECH CBN 30 30 0% 09-Jul-13 19-Aug-13 20-Feb-14 02-Apr-14 154
CBNPHME-0420 LAY CMU WALLS - PENTHOUSE MECH CBN 15 15 0% 17-Jun-13 08-Jul-13 29-Jan-14 19-Feb-14 154
PLSW-0238 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - 17TH PLACE 15 15 0% 09-Sep-13 02-Oct-13 22-Oct-14 14-Nov-14 154
IBSL2L2-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-2 IBS 20 20 0% 19-Apr-13 24-May-13 09-Jan-14 07-Feb-14 154
IBSSLCS-8890 INTERFACE TESTS/INSPECTIONS- SERV LVL SHELL IBS 10 10 0% 19-Feb-14 04-Mar-14 26-Sep-14 09-Oct-14 154
IBSSLCS-8880 CLEAN-UP/PRE PUNCH - SERV LVL SHELL IBS 15 15 0% 05-Mar-14 25-Mar-14 10-Oct-14 31-Oct-14 154
IBSSLES-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL ENVIRO IBS 20 20 0% 12-Aug-13 09-Sep-13 26-Mar-14 22-Apr-14 154
RESESWE-0530 EXTERIOR SKIN TIE INTO CONCOURSE - WEST ELEV RES 15 15 0% 04-Nov-14 28-Nov-14 27-Jul-15 20-Aug-15 155
IBNL1UR-0910 FRAMING/INWALL ROUGH - LVL-1 UROLOGY IBN 55 55 0% 25-Jul-13 10-Oct-13 11-Mar-14 27-May-14 155
IBNL1UR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 UROLOGY IBN 25 25 0% 13-Sep-13 17-Oct-13 29-Apr-14 03-Jun-14 155
IBNL1PR-0910 FRAMING/INWALL ROUGH - LVL-1 PT/OT IBN 55 55 0% 26-Jun-13 12-Sep-13 11-Feb-14 28-Apr-14 155
IBNL1PR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 PT/OT IBN 35 35 0% 22-Aug-13 10-Oct-13 08-Apr-14 27-May-14 155
IBNL1CS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 SHELL IBN 15 15 0% 18-Oct-13 08-Nov-13 04-Jun-14 24-Jun-14 155
IBNL1CS-0910 FRAMING/INWALL ROUGH - LVL-1 SHELL IBN 55 55 0% 18-Oct-13 09-Jan-14 04-Jun-14 20-Aug-14 155
IBNL1CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 SHELL IBN 15 15 0% 26-Dec-13 16-Jan-14 07-Aug-14 27-Aug-14 155
IBNL1CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SHELL IBN 15 15 0% 17-Jan-14 07-Feb-14 28-Aug-14 18-Sep-14 155
IBNL1CO-8880 CLEAN-UP/PRE PUNCH - LVL-1 CORR IBN 10 10 0% 11-Mar-14 24-Mar-14 17-Oct-14 31-Oct-14 155
IBNL1CO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 CORR IBN 20 20 0% 11-Feb-14 10-Mar-14 19-Sep-14 16-Oct-14 155
IBNL2SS-0977 INSTALL OWNER FIXED FF&E - LVL-2 SUPPORT IBN 20 20 0% 03-Feb-14 03-Mar-14 12-Sep-14 09-Oct-14 155
CBCHRPR-755 INSTALL PV PANELS - PENT ROOF CBC 20 20 0% 19-Dec-13 21-Jan-14 09-Sep-14 09-Oct-14 155
CBCHRPR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- PENT ROOF CBC 20 20 0% 15-Nov-13 17-Dec-13 05-Aug-14 08-Sep-14 155
CONPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (CON) 30 30 0% 27-Oct-11 12-Dec-11 12-Jun-12 24-Jul-12 155
CONPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (CON) 20 20 0% 13-Dec-11 11-Jan-12 25-Jul-12 21-Aug-12 155
CONPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (CON) 30 30 0% 12-Jan-12 24-Feb-12 22-Aug-12 03-Oct-12 155
ENCPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (ENC) 60 60 0% 27-Dec-12 25-Mar-13 08-Aug-13 01-Nov-13 155
ENCPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (ENC) 30 30 0% 15-Aug-12 26-Sep-12 02-Apr-13 13-May-13 155
ENCPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (ENC) 30 30 0% 27-Sep-12 08-Nov-12 14-May-... 25-Jun-13 155
ENCPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (ENC) 30 30 0% 09-Nov-12 26-Dec-12 26-Jun-13 07-Aug-13 155
ENCPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (ENC) 0 0 0% 11-Jun-13 24-Jan-14 155
ENCPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (ENC) 30 30 0% 26-Mar-13 06-May-13 04-Nov-13 17-Dec-13 155
ENCPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (ENC) 25 25 0% 07-May-13 11-Jun-13 18-Dec-13 24-Jan-14 155
DATPOPO-4710 DETAIL CURTAINWALL SHOP DRAWINGS - CS-1/IFO-3 (DAT) 30 30 0% 27-Feb-12 06-Apr-12 04-Oct-12 16-Nov-12 155
IBPPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 30 30 0% 09-Apr-12 18-May-12 19-Nov-12 03-Jan-13 155
RESPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (RES) 30 30 0% 03-Jul-12 14-Aug-12 19-Feb-13 01-Apr-13 155
CBPPOPO-4880 DETAIL CURTAIN WALL SHOP DRAWINGS - CS-1/IFO-3 (CBC/CBN) 30 30 0% 21-May-12 02-Jul-12 04-Jan-13 18-Feb-13 155
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
41 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 122
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATL1NM-0977 INSTALL OWNER FIXED FF&E - LVL-1 NUC MED DAT 20 20 0% 18-Mar-14 14-Apr-14 27-Oct-14 25-Nov-14 155
DATL1NM-8880 CLEAN-UP/PRE PUNCH - LVL-1 NUC MED DAT 10 10 0% 15-Apr-14 28-Apr-14 26-Nov-14 09-Dec-14 155
DATESAE-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-E DAT 15 15 0% 08-Apr-13 03-May-13 31-Dec-13 23-Jan-14 155
DATESAE-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-E DAT 30 30 0% 06-May-13 25-Jun-13 24-Jan-14 10-Mar-14 155
DATESAD-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-D DAT 20 20 0% 23-May-13 25-Jun-13 07-Feb-14 10-Mar-14 155
IBSL1NR-8880 CLEAN-UP/PRE PUNCH - LVL-1 NURSING IBS 15 15 0% 04-Mar-14 24-Mar-14 10-Oct-14 31-Oct-14 155
IBSL1NR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NURSING IBS 30 30 0% 12-Nov-13 24-Dec-13 25-Jun-14 06-Aug-14 155
IBSL1NR-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 NURSING IBS 10 10 0% 18-Feb-14 03-Mar-14 26-Sep-14 09-Oct-14 155
IBSL1NR-1190 INSTALL MEDICAL HEADWALLS - LVL-1 NURSING IBS 35 35 0% 26-Dec-13 17-Feb-14 07-Aug-14 25-Sep-14 155
CONL1BR-0910 FRAMING/INWALL ROUGH - LVL-1 AR-B RESTRMS CON 15 15 0% 05-Mar-14 25-Mar-14 14-Oct-14 04-Nov-14 156
CONL1BR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-B RESTRMS CON 12 12 0% 26-Mar-14 10-Apr-14 05-Nov-14 24-Nov-14 156
CONL1BR-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-B RESTRMS CON 10 10 0% 23-May-14 06-Jun-14 08-Jan-15 22-Jan-15 156
CONL1BR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-B RESTRMS CON 30 30 0% 11-Apr-14 22-May-14 25-Nov-14 07-Jan-15 156
CONL1BR-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B RESTRMS CON 20 20 0% 04-Feb-14 04-Mar-14 16-Sep-14 13-Oct-14 156
DATRLRL-1610 PARAPET/BLOCKING/WATERPROOFING - NORTH LOW ROOF DAT 15 15 0% 25-Feb-13 19-Mar-13 19-Nov-13 12-Dec-13 156
ENCPOPO-5569 KT APPROVE TRANSFORMER SHOP DRAWINGS- ENC EQUIPMENT 20 20 0% 12-Jan-12 09-Feb-12 24-Aug-12 21-Sep-12 157
ENCPOPO-5609 PREPARE/SUBMIT TRANSFORMER SHOP DRAWINGS- ENC EQUIPMENT 50 50 0% 27-Oct-11 11-Jan-12 14-Jun-12 23-Aug-12 157
ENCPOPO-5619 VA APPROVE TRANSFORMER SHOP DRAWINGS - ENC EQUIPMENT 25 25 0% 10-Feb-12 16-Mar-12 24-Sep-12 29-Oct-12 157
ENCPOPO-5629 FABRICATE/DELIVER TRANSFORMERS - ENC EQUIPMENT 100 100 0% 19-Mar-12 07-Aug-12 30-Oct-12 27-Mar-13 157
DATPOPO-3960 SUBMIT MEDICAL EQUIPMENT SHOPS (gen imaging) - IFO-1 (DAT) 60 60 0% 17-May-12 10-Aug-12 04-Jan-13 01-Apr-13 157
DATPHSP-0910 FRAMING/INWALL ROUGH - SOUTH PENT ELEC DAT 25 25 0% 26-Mar-13 29-Apr-13 06-Nov-13 12-Dec-13 157
DATPHSP-0920 HANG/TAPE/FINISH DRYWALL - SOUTH PENT ELEC DAT 15 15 0% 30-Apr-13 20-May-13 13-Dec-13 06-Jan-14 157
DATPHSP-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - SOUTH PENT MECH DAT 50 50 0% 05-Mar-13 13-May-13 15-Oct-13 27-Dec-13 157
CONL1CH-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B CHAPEL CON 20 20 0% 04-Feb-14 04-Mar-14 18-Sep-14 15-Oct-14 158
CONL1CH-0910 FRAMING/INWALL ROUGH - LVL-1 AR-B CHAPEL CON 15 15 0% 05-Mar-14 25-Mar-14 16-Oct-14 06-Nov-14 158
CONL1CH-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-B CHAPEL CON 15 15 0% 26-Mar-14 15-Apr-14 07-Nov-14 01-Dec-14 158
CONL1CH-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-B CHAPEL CON 10 10 0% 21-May-14 04-Jun-14 08-Jan-15 22-Jan-15 158
CONL1CH-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-B CHAPEL CON 25 25 0% 16-Apr-14 20-May-14 02-Dec-14 07-Jan-15 158
CBPPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (CBC/CBN) 30 30 0% 03-Jul-12 14-Aug-12 22-Feb-13 04-Apr-13 158
CBPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (CBC/CBN) 0 0 0% 18-Mar-13 30-Oct-13 158
CBPPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (CBC/CBN) 30 30 0% 27-Dec-12 08-Feb-13 13-Aug-13 24-Sep-13 158
CBPPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (CBC/CBN) 25 25 0% 12-Feb-13 18-Mar-13 25-Sep-13 30-Oct-13 158
CBPPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (CBC/CBN) 60 60 0% 27-Sep-12 26-Dec-12 17-May-... 12-Aug-13 158
CBPPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (CBC/CBN) 30 30 0% 15-Aug-12 26-Sep-12 05-Apr-13 16-May-13 158
DATPHSP-0420 LAY CMU WALLS - SOUTH PENT DAT 15 15 0% 08-Feb-13 01-Mar-13 24-Sep-13 14-Oct-13 158
IBNL2L2-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-2 IBN 20 20 0% 11-Apr-13 16-May-13 09-Jan-14 07-Feb-14 159
IBSRLRL-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ROOF IBS 9 9 0% 14-May-13 29-May-13 06-Feb-14 20-Feb-14 159
IBSRLRL-0750 INSTALL ROOFING - ROOF IBS 20 20 0% 30-May-13 02-Jul-13 21-Feb-14 24-Mar-14 159
IBSL1NR-0910 FRAMING/INWALL ROUGH - LVL-1 NURSING IBS 55 55 0% 02-Aug-13 18-Oct-13 25-Mar-14 10-Jun-14 159
IBNL1PY-8880 CLEAN-UP/PRE PUNCH - LVL-1 PHARMACY IBN 15 15 0% 25-Feb-14 17-Mar-14 10-Oct-14 31-Oct-14 160
IBNL1PY-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PHARMACY IBN 25 25 0% 12-Nov-13 17-Dec-13 02-Jul-14 06-Aug-14 160
IBNL1PY-1190 INSTALL MEDICAL HEADWALLS - LVL-1 PHARMACY IBN 35 35 0% 18-Dec-13 07-Feb-14 07-Aug-14 25-Sep-14 160
IBNL1PY-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 PHARMACY IBN 10 10 0% 11-Feb-14 24-Feb-14 26-Sep-14 09-Oct-14 160
IBNL3NR-0977 INSTALL OWNER FIXED FF&E - LVL-3 PATIENT IBN 20 20 0% 27-Jan-14 24-Feb-14 12-Sep-14 09-Oct-14 160
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
42 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 123
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ENCPHPH-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE ENC 30 30 0% 31-Oct-12 14-Dec-12 25-Jun-13 06-Aug-13 161
DATPHSP-1500 SET MECH EQUIPMENT - SOUTH PENT DAT 2 2 0% 27-Dec-12 28-Dec-12 16-Aug-13 19-Aug-13 161
IBNL1L1-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-1 IBN 20 20 0% 05-Apr-13 10-May-13 09-Jan-14 07-Feb-14 162
IFO-4960 VA REVIEW BID TABS (GROUP #2) - IFO-1 5 5 0% 26-Apr-12 02-May-12 19-Dec-12 26-Dec-12 162
IFO-4970 VA PROVIDES CONSENT TO SUBCONTRACT (GROUP #2) - IFO-1 0 0 0% 02-May-12 26-Dec-12 162
ALLPOPO-4860 KT APPROVE SHOP DRAWINGS - IFO-1 GROUP #2 15 15 0% 16-Jul-12 03-Aug-12 12-Mar-13 01-Apr-13 162
ALLPOPO-4870 PREPARE/SUBMIT SHOP DRAWINGS - IFO-1 GROUP #2 50 50 0% 03-May-12 13-Jul-12 27-Dec-12 11-Mar-13 162
ALLPOPO-4880 VA APPROVE SHOP DRAWINGS - IFO-1 GROUP #2 20 20 0% 06-Aug-12 31-Aug-12 02-Apr-13 29-Apr-13 162
ALLPOPO-4890 FAB/DELIVER MATERIALS & EQUIPMENT - IFO-1 GROUP #2 45 45 0% 04-Sep-12 06-Nov-12 30-Apr-13 02-Jul-13 162
IFO-4940 SUBCONTRACTOR PRICING (GROUP #2)- IFO-1 25 25 0% 01-Mar-12 04-Apr-12 19-Oct-12 27-Nov-12 162
IFO-4950 PREPARE BID TABS (GROUP #2) - IFO-1 15 15 0% 05-Apr-12 25-Apr-12 28-Nov-12 18-Dec-12 162
CBNL1AB-0977 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBN 15 15 0% 22-Jan-14 12-Feb-14 11-Sep-14 01-Oct-14 162
CBNL1AB-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA B CBN 8 8 0% 13-Feb-14 24-Feb-14 02-Oct-14 13-Oct-14 162
IBSL1L1-0540 ERECT EXTERIOR STUDS/SHEATHING - LVL-1 IBS 20 20 0% 28-Mar-13 02-May-13 02-Jan-14 31-Jan-14 162
IBSPHME-1590 START-UP MECH EQUIP - PENT MECH IBS 20 20 0% 28-Mar-14 24-Apr-14 18-Nov-14 16-Dec-14 162
CBNSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK CBN 12 12 0% 18-Oct-13 05-Nov-13 21-Jul-14 08-Aug-14 163
CBNSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK CBN 10 10 0% 25-Oct-13 12-Nov-13 29-Jul-14 14-Aug-14 163
CONSLAD-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-D CON 30 30 0% 06-Sep-13 17-Oct-13 05-May-... 16-Jun-14 164
IBSL2NR-0977 INSTALL OWNER FIXED FF&E - LVL-2 NURSING IBS 20 20 0% 21-Jan-14 18-Feb-14 12-Sep-14 09-Oct-14 164
IBSL2CS-0977 INSTALL OWNER FIXED FF&E - LVL-2 SHELL IBS 20 20 0% 21-Jan-14 18-Feb-14 12-Sep-14 09-Oct-14 164
RESLDLD-0320 FORM/PLACE RAMP & STAIRS - LOADING DOCK RES 12 12 0% 23-Oct-14 12-Nov-14 31-Jul-15 20-Aug-15 165
AAAA-4810 VA APPROVE ELECTRICAL CONTRACTOR DESIGN ASSIST 0 0 0% 07-Sep-11 07-May-... 165
DATRLNR-1640 PARAPET/BLOCKING/WATERPROOFING - SOUTH LOW ROOF DAT 15 15 0% 08-Feb-13 04-Mar-13 19-Nov-13 12-Dec-13 165
DATL1IL-0501 TRIM-OUT MEP (NUC MED) (AHU5) - LVL-1 INTER LVL DAT 20 20 0% 25-Feb-14 24-Mar-14 17-Oct-14 17-Nov-14 165
IBSSLES-0910 FRAMING/INWALL ROUGH - SERV LVL ENVIRO IBS 55 55 0% 30-May-13 15-Aug-13 28-Jan-14 15-Apr-14 165
PVSP1AA-1666 PULL WIRE FROM CON - PKG LVL-1 AREA A PVS 5 5 0% 18-Feb-13 25-Feb-13 11-Oct-13 17-Oct-13 165
PVSP1AA-1620 ROUGH-IN/INSTALL SUBSTATION - PKG LVL-1 AREA A PVS 10 10 0% 01-Feb-13 18-Feb-13 27-Sep-13 10-Oct-13 165
CONL3AA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-A CON 20 20 0% 18-Sep-13 15-Oct-13 19-May-... 16-Jun-14 166
CONL3AD-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-D CON 20 20 0% 16-Dec-13 14-Jan-14 13-Aug-14 10-Sep-14 166
CONL3AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-B CON 20 20 0% 16-Oct-13 14-Nov-13 17-Jun-14 15-Jul-14 166
CONL3AC-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-C CON 20 20 0% 15-Nov-13 13-Dec-13 16-Jul-14 12-Aug-14 166
CONL3AE-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-E CON 20 20 0% 15-Jan-14 13-Feb-14 11-Sep-14 08-Oct-14 166
CONL3AE-0910 FRAMING/ ROUGH-IN - LVL-3 AR-E CON 20 20 0% 14-Feb-14 13-Mar-14 09-Oct-14 06-Nov-14 166
CONL3AE-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-E CON 25 25 0% 14-Mar-14 17-Apr-14 07-Nov-14 15-Dec-14 166
CONL3AE-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-E CON 20 20 0% 11-Apr-14 08-May-14 09-Dec-14 07-Jan-15 166
CONL2AC-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-C CON 20 20 0% 25-Nov-13 20-Dec-13 23-Jul-14 19-Aug-14 166
CONL2AB-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-B CON 20 20 0% 24-Oct-13 22-Nov-13 24-Jun-14 22-Jul-14 166
CONL2AD-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-D CON 20 20 0% 23-Dec-13 22-Jan-14 20-Aug-14 17-Sep-14 166
CONL2AE-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-E CON 20 20 0% 23-Jan-14 20-Feb-14 18-Sep-14 15-Oct-14 166
CONL2AE-0910 FRAMING/ ROUGH-IN - LVL-2 AR-E CON 20 20 0% 21-Feb-14 20-Mar-14 16-Oct-14 14-Nov-14 166
CONL2AE-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-E CON 25 25 0% 21-Mar-14 24-Apr-14 17-Nov-14 22-Dec-14 166
CONL2AE-0990 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-E CON 20 20 0% 11-Apr-14 08-May-14 09-Dec-14 07-Jan-15 166
CONL2AA-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-A CON 25 25 0% 18-Sep-13 23-Oct-13 19-May-... 23-Jun-14 166
ENCPBPB-1520 SET/CONNECT/PIPE-UP PUMPS - SERV LVL MECH RMS ENC 90 90 0% 24-Oct-12 07-Mar-13 25-Jun-13 31-Oct-13 166
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
43 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 124
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ENCPBPB-1516 ROUGH-IN OVERHEAD MEP (NOT UNITS) - SERV LVL MECH RMS ENC 15 15 0% 02-Oct-12 23-Oct-12 04-Jun-13 24-Jun-13 166
CBNL1AA-0977 INSTALL OWNER FIXED FF&E - LVL-1 AREA-A CBN 15 15 0% 15-Jan-14 05-Feb-14 11-Sep-14 01-Oct-14 166
CBNL1AA-8880 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBN 8 8 0% 06-Feb-14 18-Feb-14 02-Oct-14 13-Oct-14 166
CBNL1AA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA A CBN 23 23 0% 03-Jan-14 05-Feb-14 29-Aug-14 01-Oct-14 166
IBSPBPB-0390 PERM DRAINS/BACKFILL - PIPE BSMT IBS 14 14 0% 26-Feb-13 19-Mar-13 10-Dec-13 31-Dec-13 167
IBNPHME-1590 START-UP MECH EQUIP - PENT MECH IBN 20 20 0% 20-Mar-14 16-Apr-14 18-Nov-14 16-Dec-14 168
IBSSLCA-0910 FRAMING/INWALL ROUGH - SERV LVL CANTEEN IBS 45 45 0% 20-Jun-13 22-Aug-13 24-Feb-14 25-Apr-14 168
CONSLAA-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-A CON 30 30 0% 31-Jan-13 14-Mar-13 01-Oct-13 13-Nov-13 169
ENCESSE-0870 INSTALL METAL PANELS - SOUTH ELEV ENC 15 15 0% 01-Jul-13 25-Jul-13 08-Apr-14 02-May-14 169
IBSSLBM-8880 CLEAN-UP/PRE PUNCH - SERV LVL BIO IBS 15 15 0% 12-Feb-14 04-Mar-14 10-Oct-14 31-Oct-14 169
IBSSLBM-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL BIO IBS 30 30 0% 22-Oct-13 04-Dec-13 25-Jun-14 06-Aug-14 169
IBSSLBM-1190 INSTALL MEDICAL HEADWALLS - SERV LVL BIO IBS 35 35 0% 05-Dec-13 27-Jan-14 07-Aug-14 25-Sep-14 169
IBSSLBM-8890 INTERFACE TESTS/INSPECTIONS- SERV LVL BIO IBS 10 10 0% 28-Jan-14 11-Feb-14 26-Sep-14 09-Oct-14 169
PVNSLLM-1570 GARAGE FINISHES - SERV LVL DOCK/MAINTENANCE PVN 25 25 0% 04-Apr-14 08-May-14 08-Dec-14 13-Jan-15 170
PVNSLLM-8890 CLEAN-UP/PRE PUNCH/FINAL PUNCH - SERV LVL DOCK/MAINTENANCE PVN 10 10 0% 09-May-14 22-May-14 14-Jan-15 28-Jan-15 170
IBNL1CS-0977 INSTALL OWNER FIXED FF&E - LVL-1 PT/OT IBN 20 20 0% 10-Jan-14 07-Feb-14 12-Sep-14 09-Oct-14 170
IBNL1CS-8880 CLEAN-UP/PRE PUNCH - LVL-1 SHELL IBN 15 15 0% 11-Feb-14 03-Mar-14 10-Oct-14 31-Oct-14 170
IBNL2CS-0977 INSTALL OWNER FIXED FF&E - LVL-2 SHELL IBN 15 15 0% 17-Jan-14 07-Feb-14 19-Sep-14 09-Oct-14 170
DATPOPO-5080 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (DAT) 15 15 0% 29-Jun-12 20-Jul-12 08-Mar-13 28-Mar-13 170
DATPOPO-4820 PREPARE/SUBMIT ELEC EQUIP SHOP DRAWINGS - IFO-1 (DAT) 50 50 0% 19-Apr-12 28-Jun-12 24-Dec-12 07-Mar-13 170
DATPOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (DAT) 25 25 0% 23-Jul-12 24-Aug-12 29-Mar-13 02-May-13 170
DATPOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (DAT) 65 65 0% 27-Aug-12 30-Nov-12 03-May-... 05-Aug-13 170
PVSOPO-4820 PREPARE/SUBMIT ELEC SHOP DRAWINGS - IFO-1 (PVS) 50 50 0% 05-Apr-12 14-Jun-12 10-Dec-12 21-Feb-13 170
CONL3AE-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-E CON 5 5 0% 09-May-14 15-May-14 15-Jan-15 22-Jan-15 171
CONL2AE-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-E CON 5 5 0% 09-May-14 15-May-14 15-Jan-15 22-Jan-15 171
IBSSLPA-8890 INTERFACE TESTS/INSPECTIONS- SERV LVL PATH IBS 10 10 0% 23-Jan-14 05-Feb-14 26-Sep-14 09-Oct-14 172
IBSSLPA-8880 CLEAN-UP/PRE PUNCH - SERV LVL PATH IBS 15 15 0% 06-Feb-14 27-Feb-14 10-Oct-14 31-Oct-14 172
IBSSLPA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL PATH IBS 35 35 0% 09-Oct-13 29-Nov-13 18-Jun-14 06-Aug-14 172
IBSSLPA-1190 INSTALL MEDICAL HEADWALLS - SERV LVL PATH IBS 35 35 0% 02-Dec-13 22-Jan-14 07-Aug-14 25-Sep-14 172
CONACHR-0755 INSTALL STANDING SEAM ROOF - LOW ROOF AR-C CON 42 42 0% 21-May-13 01-Aug-13 07-Mar-14 19-May-14 174
CONACHR-0888 INSTALL GLAZING @ CLEARSTORY - LOW ROOF AR-C CON 15 15 0% 02-Aug-13 27-Aug-13 20-May-... 16-Jun-14 174
CONL1CS-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 COFFEE SHOP CON 20 20 0% 06-Jan-14 03-Feb-14 12-Sep-14 09-Oct-14 174
CONL1CS-0910 FRAMING/INWALL ROUGH - LVL-1 COFFEE SHOP CON 12 12 0% 04-Feb-14 20-Feb-14 10-Oct-14 28-Oct-14 174
CONL1CS-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 COFFEE SHOP CON 12 12 0% 21-Feb-14 10-Mar-14 29-Oct-14 14-Nov-14 174
CONL1CS-8880 CLEAN-UP/PRE PUNCH - LVL-1 COFFEE SHOP CON 15 15 0% 22-Apr-14 12-May-14 31-Dec-14 22-Jan-15 174
CONL1CS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 COFFEE SHOP CON 30 30 0% 11-Mar-14 21-Apr-14 17-Nov-14 30-Dec-14 174
CONSLAB-8900 PULL 13.2 KVA WIRE - SERV LVL AR-B CON 5 5 0% 12-Apr-13 18-Apr-13 20-Dec-13 27-Dec-13 174
IBNL1L1-0725 SPRAY-ON FIREPROOFING - LVL-1 IBN 8 8 0% 04-Mar-13 15-Mar-13 27-Dec-13 08-Jan-14 174
IBNL1UR-8880 CLEAN-UP/PRE PUNCH - LVL-1 UROLOGY IBN 15 15 0% 03-Feb-14 24-Feb-14 10-Oct-14 31-Oct-14 175
IBNL1UR-1190 INSTALL MEDICAL HEADWALLS - LVL-1 UROLOGY IBN 35 35 0% 27-Nov-13 16-Jan-14 07-Aug-14 25-Sep-14 175
IBNL1UR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 UROLOGY IBN 30 30 0% 11-Oct-13 26-Nov-13 25-Jun-14 06-Aug-14 175
IBNL1UR-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 UROLOGY IBN 10 10 0% 17-Jan-14 31-Jan-14 26-Sep-14 09-Oct-14 175
IBNL2NR-0977 INSTALL OWNER FIXED FF&E - LVL-2 NURSING IBN 20 20 0% 03-Jan-14 31-Jan-14 12-Sep-14 09-Oct-14 175
DATPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (DAT) 30 30 0% 10-Nov-11 27-Dec-11 25-Jul-12 05-Sep-12 175
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
44 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 125
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATPOPO-3700 KT/VA APPROVE BLAST ANALYSIS - SHOPS/BLAST - CS-1/IFO-3 (DAT) 20 20 0% 28-Dec-11 26-Jan-12 06-Sep-12 03-Oct-12 175
DATESAC-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-C DAT 15 15 0% 05-Mar-13 28-Mar-13 31-Dec-13 23-Jan-14 175
DATESAC-0870 INSTALL CURTAIN WALL - ALL ELEVS AR-C DAT 20 20 0% 29-Mar-13 03-May-13 24-Jan-14 24-Feb-14 175
DATESAD-0520 SHEATHING/VAPOR BARRIER - ALL ELEVS AR-D DAT 15 15 0% 21-Mar-13 15-Apr-13 16-Jan-14 06-Feb-14 175
IBSL1PR-8880 CLEAN-UP/PRE PUNCH - LVL-1 PATIENT IBS 15 15 0% 03-Feb-14 24-Feb-14 10-Oct-14 31-Oct-14 175
IBSL1PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PATIENT IBS 30 30 0% 11-Oct-13 26-Nov-13 25-Jun-14 06-Aug-14 175
IBSL1PR-1190 INSTALL MEDICAL HEADWALLS - LVL-1 PATIENT IBS 35 35 0% 27-Nov-13 16-Jan-14 07-Aug-14 25-Sep-14 175
IBSL1PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 PATIENT IBS 10 10 0% 17-Jan-14 31-Jan-14 26-Sep-14 09-Oct-14 175
CBCSLSL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL CBC 15 15 0% 21-Jun-12 10-Jul-12 22-Jan-13 07-Feb-13 175
CONL1AR-8880 CLEAN-UP/PRE PUNCH - LVL-1 AR-A RESTRMS CON 10 10 0% 25-Apr-14 08-May-14 08-Jan-15 22-Jan-15 176
CONL1AR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-A RESTRMS CON 30 30 0% 14-Mar-14 24-Apr-14 25-Nov-14 07-Jan-15 176
CONL1AR-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-A RESTRMS CON 12 12 0% 26-Feb-14 13-Mar-14 05-Nov-14 24-Nov-14 176
CONL1AR-0910 FRAMING/INWALL ROUGH - LVL-1 AR-A RESTRMS CON 15 15 0% 04-Feb-14 25-Feb-14 14-Oct-14 04-Nov-14 176
CONL1AR-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-A RESTRMS CON 20 20 0% 06-Jan-14 03-Feb-14 16-Sep-14 13-Oct-14 176
DATPOPO-5120 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(pharmacy) INFO - IFO-1 (DAT) 15 15 0% 30-Jul-12 17-Aug-12 16-Apr-13 06-May-13 177
DATPOPO-4960 VA APPROVE MEDICAL EQUIPMENT(pharmacy) - IFO-1 (DAT) 20 20 0% 20-Aug-12 17-Sep-12 07-May-... 04-Jun-13 177
CONL1NL-0910 FRAMING/INWALL ROUGH - LVL-1 NORTH LOBBY CON 20 20 0% 04-Feb-14 04-Mar-14 16-Oct-14 14-Nov-14 178
CONL1NL-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 NORTH LOBBY CON 5 5 0% 05-Mar-14 11-Mar-14 17-Nov-14 24-Nov-14 178
CONL1NL-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NORTH LOBBY CON 32 32 0% 10-Mar-14 22-Apr-14 21-Nov-14 07-Jan-15 178
CONAEHR-0750 PARAPET/BLOCKING/ICE WATER SHIELD- LOW ROOF AR-E CON 5 5 0% 23-May-13 30-May-13 18-Mar-14 25-Mar-14 179
CONAEHR-0755 INSTALL STANDING SEAM ROOF - LOW ROOF AR-E CON 17 17 0% 31-May-13 28-Jun-13 27-Mar-14 24-Apr-14 179
CONAEHR-0888 INSTALL GLAZING @ CLEARSTORY - LOW ROOF AR-E CON 11 11 0% 01-Jul-13 18-Jul-13 25-Apr-14 13-May-14 179
CONAEHR-0510 FRAMING @ CLEARSTORY - HIGH ROOF AR-E CON 9 9 0% 07-May-13 21-May-13 04-Mar-14 17-Mar-14 179
IBNSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK IBN 16 16 0% 16-Aug-13 12-Sep-13 13-Jun-14 10-Jul-14 179
IBNSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK IBN 20 20 0% 02-Aug-13 05-Sep-13 30-May-... 02-Jul-14 179
IBSL3IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-3 INTER IBS 25 25 0% 26-Feb-14 01-Apr-14 10-Nov-14 16-Dec-14 179
IBNL1OF-0977 INSTALL OWNER FIXED FF&E - LVL-1 PT/OT IBN 20 20 0% 26-Dec-13 24-Jan-14 12-Sep-14 09-Oct-14 180
IBNL3PR-0977 INSTALL OWNER FIXED FF&E - LVL-3 PATIENT IBN 25 25 0% 18-Dec-13 24-Jan-14 05-Sep-14 09-Oct-14 180
DATL2LA-0977 INSTALL OWNER FIXED FF&E - LVL-2 LABS DAT 20 20 0% 25-Feb-14 24-Mar-14 10-Nov-14 09-Dec-14 180
DATL2LA-8880 CLEAN-UP/PRE PUNCH - LVL-2 LABS DAT 10 10 0% 25-Mar-14 07-Apr-14 10-Dec-14 23-Dec-14 180
CONSLAC-1516 R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVL AR-C CON 30 30 0% 01-Jul-13 12-Aug-13 24-Mar-14 02-May-14 181
IBSPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENT MECH IBS 60 60 0% 02-Dec-13 27-Feb-14 21-Aug-14 17-Nov-14 182
CONL1NL-1516 R-I OVERHEAD MEP/FIRE PRO - LVL-1 NORTH LOBBY CON 25 25 0% 06-Jan-14 11-Feb-14 25-Sep-14 30-Oct-14 183
CONL1NL-8880 CLEAN-UP/PRE PUNCH - LVL-1 NORTH LOBBY CON 5 5 0% 23-Apr-14 29-Apr-14 15-Jan-15 22-Jan-15 183
DATESAB-0780 INSTALL METAL PANEL - ALL ELEVS AR-B DAT 20 20 0% 09-Aug-13 12-Sep-13 13-Jun-14 17-Jul-14 183
DATESAA-0780 INSTALL METAL PANEL - ALL ELEVS AR-A DAT 15 15 0% 15-Jul-13 08-Aug-13 16-May-... 12-Jun-14 183
PVSPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 20 20 0% 03-Feb-12 02-Mar-12 25-Oct-12 26-Nov-12 184
PVSPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 20 20 0% 26-Mar-12 20-Apr-12 18-Dec-12 16-Jan-13 184
PVSPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (PVS) 55 55 0% 23-Apr-12 10-Jul-12 17-Jan-13 05-Apr-13 184
PVSPOPO-4820 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 15 15 0% 05-Mar-12 23-Mar-12 27-Nov-12 17-Dec-12 184
IBSL2PR-0977 INSTALL OWNER FIXED FF&E - LVL-2 PATIENT IBS 20 20 0% 19-Dec-13 17-Jan-14 12-Sep-14 09-Oct-14 184
IBNL1PR-8880 CLEAN-UP/PRE PUNCH - LVL-1 PT/OT IBN 15 15 0% 17-Jan-14 07-Feb-14 10-Oct-14 31-Oct-14 185
IBNL1PR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PT/OT IBN 25 25 0% 04-Oct-13 08-Nov-13 02-Jul-14 06-Aug-14 185
IBNL1PR-1190 INSTALL MEDICAL HEADWALLS - LVL-1 PT/OT IBN 35 35 0% 12-Nov-13 02-Jan-14 07-Aug-14 25-Sep-14 185
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
45 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 126
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
IBNL1PR-8890 INTERFACE TESTS/INSPECTIONS - LVL-1 PT/OT IBN 10 10 0% 03-Jan-14 16-Jan-14 26-Sep-14 09-Oct-14 185
ENCL1EL-0910 FRAMING/INWALL ROUGH - LVL-1 ELEC RMS ENC 10 10 0% 27-Nov-12 10-Dec-12 22-Aug-13 05-Sep-13 186
PVSP1AF-0332 FORM/PLACE FINISH RAMP - PKG LVL-1 AREA F PVS 15 15 0% 25-Feb-13 19-Mar-13 08-Jan-14 30-Jan-14 186
IBSESNE-0820 INSTALL STRIP WINDOWS - NORTH ELEV IBS 15 15 0% 22-Mar-13 16-Apr-13 05-Feb-14 27-Feb-14 187
IBSESNE-890 INSTALL METAL PANELS - NORTH ELEV IBN 15 15 0% 18-Apr-13 14-May-13 28-Feb-14 24-Mar-14 187
IBNPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENT MECH IBN 60 60 0% 22-Nov-13 19-Feb-14 21-Aug-14 17-Nov-14 188
CONSLAD-8900 PULL 13.2 KVAWIRE - SERV LVL AR-D CON 5 5 0% 06-Sep-13 12-Sep-13 10-Jun-14 16-Jun-14 189
IBSSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK IBS 16 16 0% 06-Sep-13 02-Oct-13 22-Jul-14 18-Aug-14 189
IBSSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK IBS 16 16 0% 20-Sep-13 15-Oct-13 05-Aug-14 02-Sep-14 189
P-CD3-3660 VA APPROVE CURTAIN WALL CONTRACTOR DESIGN ASSIST 0 0 0% 07-Sep-11 12-Jun-12 190
DATSLSS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL STER SUPP DAT 15 15 0% 22-Aug-13 12-Sep-13 28-May-... 17-Jun-14 190
DATSLSS-0910 FRAMING/INWALL ROUGH - SERV LVL STER SUPP DAT 15 15 0% 29-Aug-13 19-Sep-13 04-Jun-14 24-Jun-14 190
DATSLSS-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL STER SUPP DAT 8 8 0% 20-Sep-13 01-Oct-13 25-Jun-14 07-Jul-14 190
DATSLEM-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL EMER MGMT DAT 55 55 0% 28-Oct-13 16-Jan-14 31-Jul-14 16-Oct-14 190
DATSLEM-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL EMER MGMT DAT 20 20 0% 27-Sep-13 25-Oct-13 02-Jul-14 30-Jul-14 190
IBSESEE-870 INSTALL STRIP WINDOWS - EAST ELEV IBS 5 5 0% 09-Apr-13 16-Apr-13 26-Feb-14 04-Mar-14 190
IBSESEE-0880 INSTALL METAL PANELS - EAST ELEV IBS 12 12 0% 18-Apr-13 09-May-13 05-Mar-14 24-Mar-14 190
IBSL1CS-0977 INSTALL OWNER FIXED FF&E - LVL-1 SHELL IBS 15 15 0% 18-Dec-13 09-Jan-14 19-Sep-14 09-Oct-14 190
CONPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (CON) 30 30 0% 15-Aug-12 26-Sep-12 22-May-... 03-Jul-13 191
CONPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (CON) 25 25 0% 27-Sep-12 01-Nov-12 05-Jul-13 08-Aug-13 191
CONPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (CON) 0 0 0% 01-Nov-12 08-Aug-13 191
CONPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (CON) 60 60 0% 21-May-12 14-Aug-12 27-Feb-13 21-May-13 191
CONPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (CON) 30 30 0% 27-Feb-12 06-Apr-12 29-Nov-12 11-Jan-13 191
CONPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (CON) 30 30 0% 09-Apr-12 18-May-12 14-Jan-13 26-Feb-13 191
ENCL1EL-0420 LAY CMU WALLS - LVL-1 ELEC RMS ENC 15 15 0% 25-Oct-12 15-Nov-12 01-Aug-13 21-Aug-13 191
ENCPHPH-1525 CONNECT/PIPE-UP AHUS - PENTHOUSE ENC 30 30 0% 17-Dec-12 30-Jan-13 19-Sep-13 31-Oct-13 191
PVSP2AF-0325 FORM/PLACE FINISH RAMP - PKG LVL-2 AREA F PVS 15 15 0% 24-Jan-13 14-Feb-13 13-Dec-13 07-Jan-14 191
IBNALAL-0556 ERECT STAIRS ST2 - ALL LVLS IBN 15 15 0% 22-Mar-13 16-Apr-13 14-Feb-14 06-Mar-14 192
IBNALAL-0555 ERECT STAIRS ST1 - ALL LVLS IBN 15 15 0% 09-Apr-13 06-May-13 28-Feb-14 24-Mar-14 192
DATESAF-0780 INSTALL METAL PANEL - ALL ELEVS AR-F DAT 20 20 0% 23-May-13 25-Jun-13 11-Apr-14 15-May-14 193
CONSLAA-8900 PULL 13.2 KVA WIRE - SERV LVL AR-A CON 5 5 0% 31-Jan-13 06-Feb-13 06-Nov-13 13-Nov-13 194
IBNL2PR-0977 INSTALL OWNER FIXED FF&E - LVL-2 PATIENT IBN 20 20 0% 04-Dec-13 02-Jan-14 12-Sep-14 09-Oct-14 195
IBNL3IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-3 INTER IBN 25 25 0% 03-Feb-14 10-Mar-14 10-Nov-14 16-Dec-14 195
IBPPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (IBS/IBN) 30 30 0% 29-Nov-11 11-Jan-12 06-Sep-12 18-Oct-12 195
IBPPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (IBS/IBN) 20 20 0% 12-Jan-12 09-Feb-12 19-Oct-12 16-Nov-12 195
DATL2IL-1701 TRIM-OUT MEP (LABS) (AHU17) - LVL-2 INTER LVL DAT 5 5 0% 03-Feb-14 07-Feb-14 10-Nov-14 17-Nov-14 195
17SW-0238 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - 17TH AVE 5 5 0% 19-Jul-13 25-Jul-13 07-Nov-14 14-Nov-14 195
CONSLAE-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-E CON 23 23 0% 30-Jan-14 04-Mar-14 12-Nov-14 15-Dec-14 198
CONSLAE-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-E CON 15 15 0% 05-Mar-14 25-Mar-14 16-Dec-14 07-Jan-15 198
CBCALAL-0556 ERECT STAIRS ST2 - ALL LVLS CBC 15 15 0% 17-Sep-13 07-Oct-13 02-Jul-14 23-Jul-14 198
CBCALAL-0555 ERECT STAIRS ST1 - ALL LVLS CBC 15 15 0% 03-Sep-13 23-Sep-13 18-Jun-14 09-Jul-14 198
IBPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (IBS/IBN) 0 0 0% 01-Feb-13 14-Nov-13 198
IBPPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (IBS/IBN) 30 30 0% 09-Nov-12 26-Dec-12 27-Aug-13 08-Oct-13 198
IBPPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (IBS/IBN) 25 25 0% 27-Dec-12 01-Feb-13 09-Oct-13 14-Nov-13 198
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
46 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 127
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
IBPPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (IBS/IBN) 60 60 0% 15-Aug-12 08-Nov-12 03-Jun-13 26-Aug-13 198
IBPPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (IBS/IBN) 30 30 0% 21-May-12 02-Jul-12 08-Mar-13 18-Apr-13 198
IBPPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (IBS/IBN) 30 30 0% 03-Jul-12 14-Aug-12 19-Apr-13 31-May-13 198
DATPOPO-5070 KT APPROVE AHU SHOP DRAWINGS - IFO-1 (DAT) 20 20 0% 01-Jun-12 28-Jun-12 20-Mar-13 16-Apr-13 198
DATPOPO-4800 PREPARE/SUBMIT AHU SHOP DRAWINGS - IFO-1 (DAT) 40 40 0% 05-Apr-12 31-May-12 22-Jan-13 19-Mar-13 198
DATPOPO-556 VA APPROVE AHU SHOP DRAWINGS - IFO-1 (DAT) 20 20 0% 29-Jun-12 27-Jul-12 17-Apr-13 14-May-13 198
DATPOPO-4810 FAB/DELIVER AHUS - IFO-1 (DAT) 65 65 0% 30-Jul-12 30-Oct-12 15-May-... 15-Aug-13 198
IBSSLES-8880 CLEAN-UP/PRE PUNCH - SERV LVL ENVIRO IBS 15 15 0% 30-Dec-13 21-Jan-14 10-Oct-14 31-Oct-14 198
IBSSLES-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL ENVIRO IBS 35 35 0% 03-Sep-13 22-Oct-13 18-Jun-14 06-Aug-14 198
IBSSLES-1190 INSTALL MEDICAL HEADWALLS - SERV LVL ENVIRO IBS 35 35 0% 23-Oct-13 12-Dec-13 07-Aug-14 25-Sep-14 198
IBSSLES-8890 INTERFACE TESTS/INSPECTIONS- SERV LVL ENVIRO IBS 10 10 0% 13-Dec-13 27-Dec-13 26-Sep-14 09-Oct-14 198
IBSSLCS-0977 INSTALL OWNER FIXED FF&E - SERV LVL SHELL IBS 15 15 0% 05-Dec-13 26-Dec-13 19-Sep-14 09-Oct-14 199
DATL1GR-0977 INSTALL OWNER FIXED FF&E - LVL-1 GEN RADIOLOGY DAT 20 20 0% 10-Jan-14 07-Feb-14 27-Oct-14 25-Nov-14 200
DATL1GR-8880 CLEAN-UP/PRE PUNCH - LVL-1 GEN RADIOLGY DAT 10 10 0% 11-Feb-14 24-Feb-14 26-Nov-14 09-Dec-14 200
IBSL1NR-0977 INSTALL OWNER FIXED FF&E - LVL-1 NURSING IBS 20 20 0% 27-Nov-13 24-Dec-13 12-Sep-14 09-Oct-14 200
CONL2AD-0910 FRAMING/ ROUGH-IN - LVL-2 AR-D CON 20 20 0% 23-Jan-14 20-Feb-14 07-Nov-14 08-Dec-14 201
CONL2AD-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-D CON 25 25 0% 21-Feb-14 27-Mar-14 09-Dec-14 14-Jan-15 201
CONL2AD-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-D CON 5 5 0% 28-Mar-14 03-Apr-14 15-Jan-15 22-Jan-15 201
ENCPHPH-1600 SET/CONNECT/PIPE-UP MECH EQUIP (BALANCE) - PENTHOUSE ENC 20 20 0% 17-Dec-12 15-Jan-13 03-Oct-13 31-Oct-13 201
CBCPOPO-4820 KT APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CBC) 25 25 0% 06-Apr-12 10-May-12 29-Jan-13 05-Mar-13 202
CBCPOPO-4780 PREPARE/SUBMIT STRUCT STEEL SHOP DRAWINGS - STR-2 (CBC) 30 30 0% 24-Feb-12 05-Apr-12 13-Dec-12 28-Jan-13 202
CBCPOPO-4790 VA APPROVE STRUCT STEEL SHOP DRAWINGS - STR-2 (CBC) 20 20 0% 11-May-12 08-Jun-12 06-Mar-13 02-Apr-13 202
CBCPOPO-4800 FABRICATE/DELIVER STRUCT STEEL - STR-2 (CBC) 65 65 0% 11-Jun-12 11-Sep-12 03-Apr-13 03-Jul-13 202
CBCPOPO-4810 FIRST DELIVERY OF STRUCT STEEL - STR-2 (CBC) 0 0 0% 11-Sep-12 03-Jul-13 202
CONSLAE-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-E CON 5 5 0% 26-Mar-14 01-Apr-14 15-Jan-15 22-Jan-15 203
ENCSLSL-1520 SET BOILERS - SERV LVL MECH RMS ENC 5 5 0% 07-Sep-12 13-Sep-12 02-Jul-13 09-Jul-13 203
ENCSLSL-3210 SET CHILLERS - SERV LVL MECH RMS ENC 5 5 0% 07-Sep-12 13-Sep-12 02-Jul-13 09-Jul-13 203
IBNSLWH-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL WAREHOUSE IBN 35 35 0% 02-Aug-13 20-Sep-13 28-May-... 16-Jul-14 204
IBNSLCS-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL SHELL IBN 20 20 0% 30-Sep-13 28-Oct-13 24-Jul-14 20-Aug-14 204
IBNSLCS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHELL IBN 15 15 0% 29-Oct-13 19-Nov-13 21-Aug-14 11-Sep-14 204
IBNSLMR-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL MAIL IBN 30 30 0% 30-Aug-13 11-Oct-13 25-Jun-14 06-Aug-14 204
IBNSLCO-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CORR IBN 20 20 0% 20-Nov-13 18-Dec-13 12-Sep-14 09-Oct-14 204
IBNSLCO-8880 CLEAN-UP/PRE PUNCH - SERV LVL CORR IBN 15 15 0% 19-Dec-13 10-Jan-14 10-Oct-14 31-Oct-14 204
PVNSLDO-0352 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL DOCK PVN 5 5 0% 03-Dec-13 10-Dec-13 14-Nov-14 21-Nov-14 205
IBNL1PY-0977 INSTALL OWNER FIXED FF&E - LVL-1 PHARMACY IBN 20 20 0% 19-Nov-13 17-Dec-13 12-Sep-14 09-Oct-14 205
DVAPOPO-1500 VA PROVIDE FIXED FF&E SHOP DRAWINGS - IBS/IBN 30 30 0% 09-Nov-12 26-Dec-12 06-Sep-13 17-Oct-13 205
CONL3AD-0910 FRAMING/ ROUGH-IN - LVL-3 AR-D CON 20 20 0% 15-Jan-14 13-Feb-14 07-Nov-14 08-Dec-14 206
CONL3AD-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-D CON 25 25 0% 14-Feb-14 20-Mar-14 09-Dec-14 14-Jan-15 206
CONL3AD-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-D CON 5 5 0% 21-Mar-14 27-Mar-14 15-Jan-15 22-Jan-15 206
PSNALAL-0310 FORM/PLACE/POST TENSION DECKS - ALL LVLS PSN 125 125 0% 08-Jan-13 06-Aug-13 23-Dec-13 21-Jul-14 206
PSNALAL-0300 UNDERSLAB UTILITIES/PLACE SLAB ON GRADE - ALL LVLS PSN 35 35 0% 09-Nov-12 07-Jan-13 24-Oct-13 20-Dec-13 206
HOITCTC-0100 MAINTAIN TOWER CRANE #1 (DAT & CON C/D) 487 487 0% 17-Apr-12 16-Aug-13 26-Apr-12 10-Mar-14 206
CBPOPO-4910 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (CBS/CBN) 15 15 0% 16-Jul-12 03-Aug-12 13-May-... 03-Jun-13 206
CBPOPO-4820 PREPARE/SUBMIT ELEC SHOP DRAWINGS - IFO-1 (CBS/CBN) 50 50 0% 03-May-12 13-Jul-12 04-Mar-13 10-May-13 206
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
47 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 128
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBPOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (CBS/CBN) 25 25 0% 06-Aug-12 10-Sep-12 04-Jun-13 09-Jul-13 206
CBPOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (CBS/CBN) 65 65 0% 11-Sep-12 14-Dec-12 10-Jul-13 09-Oct-13 206
DATALAL-1410 INSTALL ELEVATOR (SE10) - ALL LVLS DAT 60 60 0% 02-Oct-13 08-Jan-14 16-Sep-14 23-Dec-14 206
DATALAL-1456 INSTALL ELEVATORS (PE5/6) - ALL LVLS DAT 120 120 0% 20-Jun-13 08-Jan-14 03-Jun-14 23-Dec-14 206
DATALAL-1409 INSTALL ELEVATOR (SE9) - ALL LVLS DAT 60 60 0% 02-Oct-13 08-Jan-14 16-Sep-14 23-Dec-14 206
DATPOPO-4990 SUBMIT MEDICAL EQUIPMENTSHOPS (MRI/CT) - IFO-1 (DAT) 60 60 0% 01-Jun-12 24-Aug-12 02-Apr-13 25-Jun-13 207
HOITCTC-0103 ERECT TOWER CRANE #3 (IBS/IBN CON B) 10 10 0% 16-May-12 25-May-12 11-Dec-12 20-Dec-12 209
IBSL2IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-2I NTER IBS 25 25 0% 13-Jan-14 18-Feb-14 10-Nov-14 16-Dec-14 209
IBNSLWH-0910 FRAMING/INWALL ROUGH - SERV LVL WAREHOUSE IBN 55 55 0% 21-May-13 07-Aug-13 25-Mar-14 10-Jun-14 210
IBNSLWH-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL WAREHOUSE IBN 20 20 0% 21-May-13 18-Jun-13 25-Mar-14 21-Apr-14 210
IBNL2IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-2 INTER IBN 25 25 0% 10-Jan-14 17-Feb-14 10-Nov-14 16-Dec-14 210
PVNSLLM-0412 LAY CMU WALLS - SERV LVL DOCK/MAINTENANCE PVN 10 10 0% 22-Jan-14 04-Feb-14 24-Nov-14 05-Dec-14 211
PSNSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK PSN 30 30 0% 15-Apr-13 03-Jun-13 25-Aug-14 10-Oct-14 212
PSNSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK PSN 20 20 0% 04-Jun-13 01-Jul-13 14-Oct-14 14-Nov-14 212
ENCPOPO-5749 KT APPROVE COOLING TOWER SHOP DRAWINGS- ENC EQUIPMENT 20 20 0% 28-Dec-11 26-Jan-12 31-Oct-12 30-Nov-12 213
ENCPOPO-5819 PREPARE/SUBMIT COOLING TOWER SHOP DRAWINGS- ENC EQUIPMENT 40 40 0% 27-Oct-11 27-Dec-11 04-Sep-12 30-Oct-12 213
ENCPOPO-5829 VA APPROVE COOLING TOWER SHOP DRAWINGS- ENC EQUIPMENT 35 35 0% 27-Jan-12 16-Mar-12 03-Dec-12 23-Jan-13 213
ENCPOPO-5839 FABRICATE/DELIVER COOLING TOWERS- ENC EQUIPMENT 80 80 0% 19-Mar-12 10-Jul-12 24-Jan-13 16-May-13 213
IBSSLBM-0977 INSTALL OWNER FIXED FF&E - SERV LVL BIO IBS 20 20 0% 05-Nov-13 04-Dec-13 12-Sep-14 09-Oct-14 214
IBNSLCS-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHELL IBN 15 15 0% 18-Jul-13 07-Aug-13 28-May-... 17-Jun-14 215
IBNSLCS-0910 FRAMING/INWALL ROUGH - SERV LVL SHELL IBN 55 55 0% 18-Jul-13 03-Oct-13 28-May-... 13-Aug-14 215
IBNSLMR-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 MAIL IBN 20 20 0% 19-Jun-13 17-Jul-13 29-Apr-14 27-May-14 215
CBPPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (CBC/CBN) 20 20 0% 27-Jan-12 24-Feb-12 05-Dec-12 03-Jan-13 215
CBPPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (CBC/CBN) 30 30 0% 13-Dec-11 26-Jan-12 19-Oct-12 04-Dec-12 215
DATL1IL-0401 TRIM-OUT MEP (GEN RADIOLOGY) (AHU4) - LVL-1 INTER LVL DAT 15 15 0% 18-Dec-13 09-Jan-14 27-Oct-14 17-Nov-14 215
DATSLST-0910 FRAMING/INWALL ROUGH - SERV LVL STER DAT 35 35 0% 03-Jul-13 21-Aug-13 13-May-... 01-Jul-14 215
AAAA-5640 VA FINAL APPROVAL OF CONSTRUCTION SCHEDULE 0 0 0% 24-Sep-12 06-Aug-13 216
DATPOPO-3710 KT APPROVE CURTAINWALL SHOPS - CS-1/IFO-3 (DAT) 30 30 0% 09-Apr-12 18-May-12 20-Feb-13 02-Apr-13 216
DATPOPO-3720 ORDER CUSTOM DIES - CS-1/IFO-3 (DAT) 30 30 0% 21-May-12 02-Jul-12 03-Apr-13 14-May-13 216
DATPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (DAT) 30 30 0% 27-Sep-12 08-Nov-12 09-Aug-13 20-Sep-13 216
DATPOPO-3740 FABRICATE/DELIVER - CS-1/IFO-3 (DAT) 25 25 0% 09-Nov-12 18-Dec-12 23-Sep-13 28-Oct-13 216
DATPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (DAT) 0 0 0% 18-Dec-12 28-Oct-13 216
DATPOPO-4730 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (DAT) 60 60 0% 03-Jul-12 26-Sep-12 15-May-... 08-Aug-13 216
CBPOPO-4900 KT APPROVE AHU SHOP DRAWINGS - IFO-1 (CBS/CBN) 20 20 0% 01-Jun-12 28-Jun-12 15-Apr-13 10-May-13 216
CBPOPO-4800 PREPARE/SUBMIT AHU SHOP DRAWINGS - IFO-1 (CBS/CBN) 40 40 0% 05-Apr-12 31-May-12 18-Feb-13 12-Apr-13 216
CBPOPO-556 VA APPROVE AHU SHOP DRAWINGS - IFO-1 (CBS/CBN) 20 20 0% 29-Jun-12 27-Jul-12 13-May-... 10-Jun-13 216
CBPOPO-4810 FAB/DELIVER AHUS - IFO-1 (CBS/CBN) 80 80 0% 30-Jul-12 21-Nov-12 11-Jun-13 02-Oct-13 216
CONAESL-3100 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-E CON 8 8 0% 30-Mar-12 07-Apr-12 15-Dec-12 24-Dec-12 217
PVSOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (PVS) 25 25 0% 09-Jul-12 10-Aug-12 21-May-... 25-Jun-13 217
PVSOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (PVS) 65 65 0% 13-Aug-12 14-Nov-12 26-Jun-13 26-Sep-13 217
PVSOPO-4850 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (PVS) 15 15 0% 15-Jun-12 06-Jul-12 30-Apr-13 20-May-13 217
CLC-3630 SUBCONTRACTOR PRICING - CLC 40 40 0% 30-Apr-12 25-Jun-12 14-Mar-13 08-May-13 217
IBSSLPA-0977 INSTALL OWNER FIXED FF&E - SERV LVL PATH IBS 20 20 0% 31-Oct-13 29-Nov-13 12-Sep-14 09-Oct-14 217
PSNSLSL-3150 DRILL/PLACE CAISSONS - SERV LVL PSN 30 30 0% 14-Jun-12 06-Aug-12 18-Jun-13 08-Aug-13 218
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
48 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 129
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
PSNALAL-0290 FORM/PLACE/PIER CAPS/FTGS/ELEV PITS/ WALLS/ COLUMNS - ALL LVLS PSN 45 45 0% 07-Aug-12 19-Oct-12 09-Aug-13 23-Oct-13 218
DATPGPG-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - PIPE GALLERY DAT 8 8 0% 11-Jun-12 22-Jun-12 14-Jun-13 27-Jun-13 218
CREDIT-1405 DEMOLITION & EXCAVATION/FILL - CREDIT UNION 30 30 0% 02-Apr-12 25-May-12 08-Apr-13 30-May-13 218
CREDIT-1424 MOBILIZE CONTRACTOR - CREDIT UNION 10 10 0% 13-Feb-12 28-Feb-12 19-Feb-13 04-Mar-13 218
CREDIT-1434 INSTALL FENCE AND EROSION CONTROL - CREDIT UNION 20 20 0% 29-Feb-12 30-Mar-12 05-Mar-13 05-Apr-13 218
IBNSLMR-8880 CLEAN-UP/PRE PUNCH - SERV LVL MAIL IBN 15 15 0% 28-Nov-13 18-Dec-13 10-Oct-14 31-Oct-14 219
IBNSLMR-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL MAIL IBN 30 30 0% 14-Oct-13 27-Nov-13 28-Aug-14 09-Oct-14 219
CONESAB-0540 ERECT EXTERIOR STUDS/SHEATHING - AR-B CON 15 15 0% 13-Aug-13 06-Sep-13 21-Aug-14 15-Sep-14 220
IBNL1UR-0977 INSTALL OWNER FIXED FF&E - LVL-1 UROLOGY IBN 20 20 0% 28-Oct-13 26-Nov-13 12-Sep-14 09-Oct-14 220
DATSLPY-0910 FRAMING/INWALL ROUGH - SERV LVL PHARMACY DAT 35 35 0% 05-Jun-13 24-Jul-13 22-Apr-14 10-Jun-14 220
DATSLST-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL STER DAT 15 15 0% 08-Aug-13 28-Aug-13 25-Jun-14 16-Jul-14 220
IBSL1PR-0977 INSTALL OWNER FIXED FF&E - LVL-1 PATIENT IBS 20 20 0% 28-Oct-13 26-Nov-13 12-Sep-14 09-Oct-14 220
CONL2AC-0910 FRAMING/ ROUGH-IN - LVL-2 AR-C CON 20 20 0% 23-Dec-13 22-Jan-14 07-Nov-14 08-Dec-14 221
CONL2AC-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-C CON 25 25 0% 23-Jan-14 27-Feb-14 09-Dec-14 14-Jan-15 221
CONL2AC-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-C CON 5 5 0% 28-Feb-14 06-Mar-14 15-Jan-15 22-Jan-15 221
IBSALAL-0555 ERECT STAIRS ST1 - ALL LVLS IBS 15 15 0% 01-Apr-13 19-Apr-13 18-Feb-14 10-Mar-14 221
IBSALAL-0556 ERECT STAIRS ST2 - ALL LVLS IBS 15 15 0% 15-Apr-13 03-May-13 04-Mar-14 24-Mar-14 221
PSNESRL-1600 INSTALL ROOF TRELLIS SYSTEM - ROOF LVL PSN 20 20 0% 08-Aug-13 10-Sep-13 19-Aug-14 22-Sep-14 222
PSNESRL-1610 INSTALL GLASS ROOFING SYSTEM - ROOF LVL PSN 40 40 0% 12-Sep-13 15-Nov-13 23-Sep-14 27-Nov-14 222
PSNESRL-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - ROOF LVL PSN 10 10 0% 18-Nov-13 03-Dec-13 28-Nov-14 12-Dec-14 222
AAAACBC-0100 START CBC CONSTRUCTION (start milestone) 0 0 0% 10-Jul-12 19-Feb-13 223
IBNSLCS-8880 CLEAN-UP/PRE PUNCH - SERV LVL SHELL IBN 15 15 0% 20-Nov-13 11-Dec-13 10-Oct-14 31-Oct-14 224
DATESAE-0780 INSTALL METAL PANEL - ALL ELEVS AR-E DAT 19 19 0% 31-May-13 02-Jul-13 16-Jun-14 17-Jul-14 224
DATESAD-0780 INSTALL METAL PANEL - ALL ELEVS AR-D DAT 5 5 0% 23-May-13 30-May-13 06-Jun-14 13-Jun-14 224
IBNSLMR-0910 FRAMING/INWALL ROUGH - SERV LVL MAIL IBN 55 55 0% 19-Jun-13 05-Sep-13 13-May-... 30-Jul-14 225
ENCPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (ENC) 20 20 0% 09-Nov-12 11-Dec-12 04-Oct-13 01-Nov-13 225
DATSLEM-0977 INSTALL OWNER FIXED FF&E - SERV LVL EMER MGMT DAT 20 20 0% 18-Dec-13 16-Jan-14 10-Nov-14 09-Dec-14 225
DATSLEM-8880 CLEAN-UP/PRE PUNCH - SERV LVL EMER MGMT DAT 10 10 0% 17-Jan-14 31-Jan-14 10-Dec-14 23-Dec-14 225
CONL3AC-0910 FRAMING/ ROUGH-IN - LVL-3 AR-C CON 20 20 0% 16-Dec-13 14-Jan-14 07-Nov-14 08-Dec-14 226
CONL3AC-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-C CON 25 25 0% 15-Jan-14 20-Feb-14 09-Dec-14 14-Jan-15 226
CONL3AC-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-C CON 5 5 0% 21-Feb-14 27-Feb-14 15-Jan-15 22-Jan-15 226
CLC-5310 AWARD CONTRACT - CLC 20 20 0% 25-Jul-12 21-Aug-12 20-Jun-13 18-Jul-13 226
CLC-4920 VA REVIEW BID TABS - CLC 5 5 0% 18-Jul-12 24-Jul-12 13-Jun-13 19-Jun-13 226
CLC-3650 VA PROVIDES CONSENT TO SUBCONTRACT - CLC 0 0 0% 24-Jul-12 19-Jun-13 226
CLC-4930 PREPARE BID TABS - CLC 15 15 0% 26-Jun-12 17-Jul-12 22-May-... 12-Jun-13 226
CLCOPO-4890 KT APPROVE CRITICAL PROCUREMENT - CLC 15 15 0% 04-Oct-12 25-Oct-12 30-Aug-13 20-Sep-13 226
CLCOPO-4770 PREPARE/SUBMIT CRITICAL PROCUREMENT - CLC 30 30 0% 22-Aug-12 03-Oct-12 19-Jul-13 29-Aug-13 226
CLCOPO-4780 VA APPROVE CRITICAL PROCUREMENT - CLC 20 20 0% 26-Oct-12 27-Nov-12 23-Sep-13 18-Oct-13 226
CLCOPO-4790 DELIVER CRITICAL PROCUREMENT - CLC 20 20 0% 28-Nov-12 26-Dec-12 18-Oct-13 19-Nov-13 226
CBPPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (CBC/CBN) 20 20 0% 15-Aug-12 12-Sep-12 16-Jul-13 12-Aug-13 228
IBNL1PR-0977 INSTALL OWNER FIXED FF&E - LVL-1 PT/OT IBN 20 20 0% 11-Oct-13 08-Nov-13 12-Sep-14 09-Oct-14 230
CS1-4820 AWARD ELEVATOR CONTRACT 20 20 0% 05-Jan-12 02-Feb-12 05-Dec-12 03-Jan-13 230
PVSPOPO-4830 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 15 15 0% 02-Apr-12 20-Apr-12 05-Mar-13 25-Mar-13 230
PVSPOPO-4800 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 40 40 0% 03-Feb-12 30-Mar-12 04-Jan-13 04-Mar-13 230
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
49 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 130
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
PVSPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVS) 45 45 0% 23-Apr-12 25-Jun-12 26-Mar-13 28-May-13 230
PVSPOPO-4810 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (PVS) 90 90 0% 26-Jun-12 01-Nov-12 29-May-... 03-Oct-13 230
DATSLSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL DAT 15 15 0% 08-May-12 01-Jun-12 03-Jun-13 27-Jun-13 230
IBSSLCA-0977 INSTALL OWNER FIXED FF&E - SERV LVL CANTEEN IBS 20 20 0% 11-Oct-13 08-Nov-13 12-Sep-14 09-Oct-14 230
IBSSLCA-8880 CLEAN-UP/PRE PUNCH - SERV LVL CANTEEN IBS 15 15 0% 12-Nov-13 03-Dec-13 10-Oct-14 31-Oct-14 230
IBSSLCA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CANTEEN IBS 30 30 0% 27-Sep-13 08-Nov-13 28-Aug-14 09-Oct-14 230
PVSP3AF-3240 FORM/PLACE/FINISH RAMP - PKG LVL-3 AREA F PVS 10 10 0% 30-Oct-12 16-Nov-12 28-Nov-13 12-Dec-13 231
IBNRLRL-0320 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ROOF IBN 9 9 0% 06-May-13 20-May-13 03-Jun-14 17-Jun-14 232
IBNRLRL-0750 INSTALL ROOFING - ROOF IBN 20 20 0% 21-May-13 24-Jun-13 19-Jun-14 22-Jul-14 232
CBNALAL-0555 ERECT STAIRS ST1 - ALL LVLS CBN 15 15 0% 12-Feb-13 04-Mar-13 14-Jan-14 04-Feb-14 232
CBNALAL-0556 ERECT STAIRS ST2 - ALL LVLS CBN 15 15 0% 05-Mar-13 25-Mar-13 05-Feb-14 26-Feb-14 232
IFO-4980 VA REVIEW BID TABS (GROUP #3) - IFO-1 5 5 0% 24-May-12 31-May-12 02-May-... 08-May-13 234
IFO-4990 VA PROVIDES CONSENT TO SUBCONTRACT (GROUP #3) - IFO-1 0 0 0% 31-May-12 08-May-13 234
IFO-5000 SUBCONTRACTOR PRICING (GROUP #3)- IFO-1 25 25 0% 29-Mar-12 02-May-12 07-Mar-13 10-Apr-13 234
IFO-5010 PREPARE BID TABS (GROUP #3) - IFO-1 15 15 0% 03-May-12 23-May-12 11-Apr-13 01-May-13 234
RESPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (RES) 30 30 0% 28-Dec-11 09-Feb-12 05-Dec-12 17-Jan-13 235
RESPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (RES) 20 20 0% 10-Feb-12 09-Mar-12 18-Jan-13 18-Feb-13 235
CONABLR-0710 PARAPET/BLOCKING/ROOFING - LOW ROOF AR-B CON 15 15 0% 09-Sep-13 02-Oct-13 10-Oct-14 04-Nov-14 236
CONESAB-890 INSTALL EXTERIOR FINISHES (LVL-1 BUMP OUTS) - AR-B CON 15 15 0% 09-Sep-13 02-Oct-13 10-Oct-14 04-Nov-14 236
DATPOPO-5090 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(gen imaging) INFO- IFO-1 (DAT) 15 15 0% 13-Aug-12 31-Aug-12 25-Jul-13 14-Aug-13 237
DATPOPO-3970 VA APPROVE MEDICAL EQUIPMENT(gen imaging) - IFO-1 (DAT) 20 20 0% 04-Sep-12 01-Oct-12 15-Aug-13 12-Sep-13 237
PVNSLST-0315 FORM/PLACE FINISH EQUIPMENT PADS - SERV LVL DOCK PVN 5 5 0% 11-Dec-13 17-Dec-13 24-Nov-14 28-Nov-14 238
PVNSLST-1620 CONNECT/PIPE-UP EQUIPMENT - SERV LVL DOCK PVN 25 25 0% 18-Dec-13 24-Jan-14 01-Dec-14 06-Jan-15 238
PSNPOPO-4910 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PSN) 15 15 0% 22-Aug-12 12-Sep-12 06-Aug-13 26-Aug-13 238
PSNPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PSN) 20 20 0% 25-Jul-12 21-Aug-12 09-Jul-13 05-Aug-13 238
PSNPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PSN) 20 20 0% 13-Sep-12 10-Oct-12 27-Aug-13 24-Sep-13 238
PSNPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (PSN) 20 20 0% 11-Oct-12 08-Nov-12 25-Sep-13 23-Oct-13 238
PSNL2L2-1580 ROUGH-IN MEP/FIRE PROTECTION - LVL-2 PSN 25 25 0% 07-Aug-13 11-Sep-13 22-Jul-14 25-Aug-14 239
PSNL3L3-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-3 PSN 25 25 0% 21-Aug-13 25-Sep-13 05-Aug-14 09-Sep-14 239
PSNL4L4-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-4 PSN 25 25 0% 05-Sep-13 09-Oct-13 19-Aug-14 23-Sep-14 239
PSNL5L5-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-5 PSN 25 25 0% 19-Sep-13 24-Oct-13 03-Sep-14 07-Oct-14 239
PSNL6L6-1600 ROUGH-IN MEP/FIRE PROTECTION - LVL-6 PSN 25 25 0% 03-Oct-13 07-Nov-13 17-Sep-14 22-Oct-14 239
PSNL6L6-1610 GARAGE FINISHES - LVL-6 PSN 25 25 0% 08-Nov-13 16-Dec-13 23-Oct-14 28-Nov-14 239
PSNL6L6-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-6 PSN 10 10 0% 17-Dec-13 31-Dec-13 01-Dec-14 12-Dec-14 239
PSNCOCO-1592 TEST & BALANCE - PSN 20 20 0% 31-Jan-14 28-Feb-14 14-Jan-15 12-Feb-15 239
PSNCOCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - PSN 20 20 0% 02-Jan-14 30-Jan-14 15-Dec-14 13-Jan-15 239
PSNCOCO-1594 PRE-FUNCTIONAL TESTING/CORRECTIONS - PSN 15 15 0% 31-Jan-14 21-Feb-14 14-Jan-15 04-Feb-15 239
PSNCOCO-1596 FUNCTIONAL TESTING/CORRECTIONS - PSN 15 15 0% 24-Feb-14 14-Mar-14 05-Feb-15 26-Feb-15 239
IBNSLWH-8880 CLEAN-UP/PRE PUNCH - SERV LVL WAREHOUSE IBN 15 15 0% 29-Oct-13 19-Nov-13 10-Oct-14 31-Oct-14 239
IBNSLWH-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL WAREHOUSE IBN 30 30 0% 16-Sep-13 28-Oct-13 28-Aug-14 09-Oct-14 239
ENCL1ME-1590 START-UP MECH EQUIP - LVL-1 MECH RMS ENC 10 10 0% 05-Dec-13 18-Dec-13 18-Nov-14 02-Dec-14 239
ENCALCO-1592 FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS ENC 20 20 0% 21-Jan-14 18-Feb-14 02-Jan-15 30-Jan-15 239
ENCALCO-10009 TEST & BALANCE - ALL LVLS ENC 15 15 0% 19-Dec-13 10-Jan-14 03-Dec-14 23-Dec-14 239
ENCALCO-10019 PRE FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS ENC 20 20 0% 19-Dec-13 17-Jan-14 03-Dec-14 31-Dec-14 239
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
50 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 131
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATESAC-0780 INSTALL METAL PANEL - ALL ELEVS AR-C DAT 15 15 0% 29-Mar-13 23-Apr-13 09-May-... 05-Jun-14 239
IBSL1IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-1 INTER IBS 25 25 0% 28-Nov-13 03-Jan-14 10-Nov-14 16-Dec-14 239
DATSLPY-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL PHARMACY DAT 20 20 0% 03-Jul-13 31-Jul-13 18-Jun-14 16-Jul-14 240
DATSLIL-1801 TRIM-OUT MEP (EMER MGMNT) (AHU18) - SERV LVL INTER LVL DAT 5 5 0% 27-Nov-13 03-Dec-13 10-Nov-14 17-Nov-14 240
CONL2AB-0910 FRAMING/ ROUGH-IN - LVL-2 AR-B CON 20 20 0% 25-Nov-13 20-Dec-13 07-Nov-14 08-Dec-14 241
CONL2AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-B CON 25 25 0% 23-Dec-13 29-Jan-14 09-Dec-14 14-Jan-15 241
CONL2AB-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-B CON 5 5 0% 30-Jan-14 05-Feb-14 15-Jan-15 22-Jan-15 241
DATPOPO-5040 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 15 15 0% 30-Apr-12 18-May-12 17-Apr-13 07-May-13 241
DATPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 20 20 0% 21-May-12 18-Jun-12 08-May-... 05-Jun-13 241
DATPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (DAT) 55 55 0% 19-Jun-12 05-Sep-12 06-Jun-13 22-Aug-13 241
DATSLSS-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL STER SUPP DAT 20 20 0% 02-Oct-13 30-Oct-13 19-Sep-14 16-Oct-14 242
PLSW-0228 CONSTRUCT ROADWAY - 17TH PLACE 25 25 0% 26-Jul-13 06-Sep-13 11-Sep-14 21-Oct-14 242
PLSW-0215 PLACE EROSION PROTECTION/TRAFFIC CONTROL - 17TH PLACE 4 4 0% 16-May-13 21-May-13 01-Jul-14 07-Jul-14 242
PLSW-0218 DEMO/GRADING - 17TH PLACE 12 12 0% 23-May-13 11-Jun-13 08-Jul-14 28-Jul-14 242
PLSW-0220 INSTALL UTILITIES - 17TH PLACE 25 25 0% 13-Jun-13 25-Jul-13 29-Jul-14 09-Sep-14 242
IBSPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENT ELEC IBS 10 10 0% 31-Oct-13 14-Nov-13 17-Oct-14 31-Oct-14 242
ENCALAL-1416 INSTALL ELEVATOR (SE14) - ALL LVLS ENC 60 60 0% 08-Aug-13 15-Nov-13 25-Sep-14 31-Dec-14 243
IBSSLES-0977 INSTALL OWNER FIXED FF&E - SERV LVL ENVIRO IBS 20 20 0% 24-Sep-13 22-Oct-13 12-Sep-14 09-Oct-14 243
PVNSWHL-0220 FINE GRADE/HARDSCAPE - SITEWORK PVN 10 10 0% 15-Apr-13 29-Apr-13 17-Oct-14 31-Oct-14 244
PVNSWHL-0290 LANDSCAPING/SITE FURNISHINGS - SITEWORK PVN 8 8 0% 30-Apr-13 10-May-13 03-Nov-14 14-Nov-14 244
ENCPOPO-5729 KT APPROVE CHILLER SHOP DRAWINGS- ENC EQUIPMENT 20 20 0% 28-Dec-11 26-Jan-12 18-Dec-12 16-Jan-13 244
ENCPOPO-5739 KT APPROVE BOILER SHOP DRAWINGS- ENC EQUIPMENT 20 20 0% 28-Dec-11 26-Jan-12 18-Dec-12 16-Jan-13 244
ENCPOPO-5759 PREPARE/SUBMIT CHILLER SHOP DRAWINGS- ENC EQUIPMENT 40 40 0% 27-Oct-11 27-Dec-11 18-Oct-12 17-Dec-12 244
ENCPOPO-5769 VA APPROVE CHILLER SHOP DRAWINGS- ENC EQUIPMENT 35 35 0% 27-Jan-12 16-Mar-12 17-Jan-13 08-Mar-13 244
ENCPOPO-5779 FABRICATE/DELIVER CHILLERS- ENC EQUIPMENT 80 80 0% 19-Mar-12 10-Jul-12 11-Mar-13 01-Jul-13 244
ENCPOPO-5789 PREPARE/SUBMIT BOILER SHOP DRAWINGS- ENC EQUIPMENT 40 40 0% 27-Oct-11 27-Dec-11 18-Oct-12 17-Dec-12 244
ENCPOPO-5799 VA APPROVE BOILER SHOP DRAWINGS- ENC EQUIPMENT 35 35 0% 27-Jan-12 16-Mar-12 17-Jan-13 08-Mar-13 244
ENCPOPO-5809 FABRICATE/DELIVER BOILERS- ENC EQUIPMENT 80 80 0% 19-Mar-12 10-Jul-12 11-Mar-13 01-Jul-13 244
IBNL1IL-1517 TRIM-OUT MEP/FIRE PROTECTION - LVL-1 INTER IBN 25 25 0% 19-Nov-13 24-Dec-13 10-Nov-14 16-Dec-14 245
DATSLST-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL STER DAT 45 45 0% 22-Aug-13 25-Oct-13 14-Aug-14 16-Oct-14 245
CONL3AB-0910 FRAMING/ ROUGH-IN - LVL-3 AR-B CON 20 20 0% 15-Nov-13 13-Dec-13 07-Nov-14 08-Dec-14 246
CONL3AB-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-B CON 25 25 0% 16-Dec-13 22-Jan-14 09-Dec-14 14-Jan-15 246
CONL3AB-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-B CON 5 5 0% 23-Jan-14 29-Jan-14 15-Jan-15 22-Jan-15 246
PVNPOPO-4910 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVN) 15 15 0% 08-Oct-12 29-Oct-12 02-Oct-13 23-Oct-13 246
PVNPOPO-4770 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVN) 32 32 0% 22-Aug-12 05-Oct-12 16-Aug-13 01-Oct-13 246
PVNPOPO-4780 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (PVN) 20 20 0% 30-Oct-12 29-Nov-12 24-Oct-13 22-Nov-13 246
PVNPOPO-4790 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (PVN) 20 20 0% 30-Nov-12 28-Dec-12 25-Nov-13 20-Dec-13 246
ALLPOPO-4900 KT APPROVE SHOP DRAWINGS - IFO-1 GROUP #3 15 15 0% 13-Aug-12 31-Aug-12 08-Aug-13 28-Aug-13 247
ALLPOPO-4910 PREPARE/SUBMIT SHOP DRAWINGS - IFO-1 GROUP #3 50 50 0% 01-Jun-12 10-Aug-12 29-May-... 07-Aug-13 247
ALLPOPO-4920 VA APPROVE SHOP DRAWINGS - IFO-1 GROUP #3 20 20 0% 04-Sep-12 01-Oct-12 29-Aug-13 26-Sep-13 247
ALLPOPO-4930 FAB/DELIVER MATERIALS & EQUIPMENT - IFO-1 GROUP #3 45 45 0% 02-Oct-12 07-Dec-12 27-Sep-13 03-Dec-13 247
PLSW-238 INSTALL UTILIDOR - 17TH PLACE 15 15 0% 21-Jun-13 16-Jul-13 15-Aug-14 09-Sep-14 247
PVNSLST-8890 CLEAN-UP/PRE PUNCH/FINAL PUNCH - SERV LVL DOCK PVN 5 5 0% 27-Jan-14 31-Jan-14 22-Jan-15 28-Jan-15 248
IBNPHEL-0920 HANG/TAPE/FINISH DRYWALL - PENT ELEC IBN 10 10 0% 23-Oct-13 05-Nov-13 17-Oct-14 31-Oct-14 248
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
51 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 132
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
PSNL5L5-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-5 PSN 10 10 0% 03-Dec-13 16-Dec-13 01-Dec-14 12-Dec-14 249
PSNL5L5-1610 GARAGE FINISHES - LVL-5 PSN 25 25 0% 25-Oct-13 02-Dec-13 23-Oct-14 28-Nov-14 249
DATSLPY-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL PHARMACY DAT 55 55 0% 25-Jul-13 10-Oct-13 24-Jul-14 09-Oct-14 250
CONL2AA-0910 FRAMING/ ROUGH-IN - LVL-2 AR-A CON 25 25 0% 24-Oct-13 29-Nov-13 24-Oct-14 01-Dec-14 251
CONL2AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-2 AR-A CON 30 30 0% 02-Dec-13 14-Jan-14 02-Dec-14 14-Jan-15 251
CONL2AA-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 AR-A CON 5 5 0% 15-Jan-14 22-Jan-14 15-Jan-15 22-Jan-15 251
PSNL1L1-1560 ROUGH-IN MEP/FIRE PROTECTION - LVL-1 PSN 25 25 0% 08-Jul-13 09-Aug-13 08-Jul-14 11-Aug-14 251
CONESAD-900 INSTALL PVS TO CON ENTRY - AR-D CON 35 35 0% 04-Jun-13 02-Aug-13 07-Aug-14 03-Oct-14 252
PSNESES-0320 INSTALL EXTERIOR SKIN FINISHES - ALL ELEVATIONS PSN 40 40 0% 08-Aug-13 11-Oct-13 08-Oct-14 12-Dec-14 252
ENCESSE-0880 SET/CONNECT SOLAR TUBES - SOUTH ELEV ENC 40 40 0% 26-Jul-13 02-Oct-13 29-Sep-14 02-Dec-14 252
IBPOPO-5720 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (IBS/IBN) 15 15 0% 30-Jul-12 17-Aug-12 02-Aug-13 22-Aug-13 253
IBPOPO-4820 PREPARE/SUBMIT ELEC SHOP DRAWINGS - IFO-1 (IBS/IBN) 50 50 0% 17-May-12 27-Jul-12 22-May-... 01-Aug-13 253
IBPOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (IBS/IBN) 25 25 0% 20-Aug-12 24-Sep-12 23-Aug-13 27-Sep-13 253
IBPOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (IBS/IBN) 65 65 0% 25-Sep-12 31-Dec-12 30-Sep-13 03-Jan-14 253
ENCPOPO-4870 KT/VA APPROVE BLAST ANALYSIS - CS-1/IFO-3 (ENC) 20 20 0% 27-Feb-12 23-Mar-12 05-Mar-13 01-Apr-13 255
ENCPOPO-3690 BLAST ANALYSIS - CS-1/IFO-3 (ENC) 30 30 0% 12-Jan-12 24-Feb-12 18-Jan-13 04-Mar-13 255
CONESAD-0540 ERECT EXTERIOR STUDS/SHEATHING - AR-D CON 15 15 0% 02-May-13 28-May-13 11-Jul-14 05-Aug-14 256
CBNLRLR-0710 PARAPET/BLOCKING/WATERPROOFING - LOW ROOF CBN 10 10 0% 17-Jun-13 02-Jul-13 28-Aug-14 12-Sep-14 257
CBNLRLR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF CBN 15 15 0% 03-Jul-13 29-Jul-13 15-Sep-14 07-Oct-14 257
CBNLRLR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF CBN 3 3 0% 30-Jul-13 02-Aug-13 08-Oct-14 10-Oct-14 257
PSNL4L4-1610 GARAGE FINISHES - LVL-4 PSN 25 25 0% 10-Oct-13 15-Nov-13 23-Oct-14 28-Nov-14 259
PSNL4L4-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-4 PSN 10 10 0% 18-Nov-13 02-Dec-13 01-Dec-14 12-Dec-14 259
CONPOPO-4920 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CON) 15 15 0% 22-Aug-12 12-Sep-12 05-Sep-13 25-Sep-13 259
CONPOPO-4850 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CON) 60 60 0% 29-May-12 21-Aug-12 11-Jun-13 04-Sep-13 259
CONPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CON) 45 45 0% 13-Sep-12 16-Nov-12 26-Sep-13 02-Dec-13 259
CONPOPO-4860 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (CON) 90 90 0% 19-Nov-12 01-Apr-13 03-Dec-13 11-Apr-14 259
CBPOPO-4850 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 40 40 0% 02-Apr-12 25-May-12 15-Apr-13 10-Jun-13 259
DATPOPO-4850 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 40 40 0% 05-Mar-12 27-Apr-12 18-Mar-13 10-May-13 259
IBPOPO-4850 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 40 40 0% 30-Apr-12 25-Jun-12 13-May-... 09-Jul-13 259
DATSLPC-0990 INSTALL INTERIOR FINISHES - SERV LVL PHARMACY CORR DAT 20 20 0% 11-Oct-13 08-Nov-13 27-Oct-14 25-Nov-14 260
CONPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (CON) 20 20 0% 09-Apr-12 04-May-12 24-Apr-13 21-May-13 261
ENCESNE-0440 LAY STACKED STONE - NORTH ELEV ENC 25 25 0% 25-Oct-12 06-Dec-12 09-Jan-14 18-Feb-14 261
ENCESSE-0440 LAY STACKED STONE - SOUTH ELEV ENC 25 25 0% 20-Nov-12 31-Dec-12 03-Feb-14 11-Mar-14 261
ENCESEE-0440 LAY STACKED STONE - EAST ELEV ENC 25 25 0% 14-Dec-12 24-Jan-13 26-Feb-14 07-Apr-14 261
DATPOPO-5050 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 15 15 0% 30-Apr-12 18-May-12 16-May-... 06-Jun-13 262
DATPOPO-1400 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (DAT) 45 45 0% 21-May-12 24-Jul-12 07-Jun-13 09-Aug-13 262
DATPOPO-4860 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (DAT) 90 90 0% 25-Jul-12 04-Dec-12 12-Aug-13 19-Dec-13 262
CONESAE-0540 ERECT EXTERIOR STUDS/SHEATHING - AR-E CON 15 15 0% 07-May-13 31-May-13 29-Jul-14 22-Aug-14 263
PVNSLST-0910 FRAMING/IN-WALL ROUGH IN - SERV LVL DOCK PVN 10 10 0% 18-Dec-13 02-Jan-14 07-Jan-15 21-Jan-15 263
IBPOPO-4810 FAB/DELIVER AHUS - IFO-1 (IBS/IBN) 80 80 0% 30-Jul-12 21-Nov-12 16-Aug-13 11-Dec-13 263
IBPOPO-5710 KT APPROVE AHU SHOP DRAWINGS - IFO-1 (IBS/IBN) 20 20 0% 01-Jun-12 28-Jun-12 20-Jun-13 18-Jul-13 263
IBPOPO-4800 PREPARE/SUBMIT AHU SHOP DRAWINGS - IFO-1 (IBS/IBN) 40 40 0% 05-Apr-12 31-May-12 24-Apr-13 19-Jun-13 263
IBPOPO-556 VA APPROVE AHU SHOP DRAWINGS - IFO-1 (IBS/IBN) 20 20 0% 29-Jun-12 27-Jul-12 19-Jul-13 15-Aug-13 263
CONL3AA-0910 FRAMING/ ROUGH-IN - LVL-3 AR-A CON 20 20 0% 16-Oct-13 14-Nov-13 07-Nov-14 08-Dec-14 266
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
52 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 133
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CONL3AA-0920 HANG/TAPE/FINISH DRYWALL - LVL-3 AR-A CON 25 25 0% 15-Nov-13 20-Dec-13 09-Dec-14 14-Jan-15 266
CONL3AA-8880 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 AR-A CON 5 5 0% 23-Dec-13 30-Dec-13 15-Jan-15 22-Jan-15 266
DATPOPO-4870 SUBMIT MEDICAL EQUIPMENTSHOPS (dental) - IFO-1 (DAT) 60 60 0% 15-Jun-12 10-Sep-12 11-Jul-13 03-Oct-13 267
DATSLSS-0977 INSTALL OWNER FIXED FF&E - SERV LVL STER DAT 20 20 0% 02-Oct-13 30-Oct-13 27-Oct-14 25-Nov-14 267
DATSLSS-8880 CLEAN-UP/PRE PUNCH - SERV LVL STER SUPP DAT 10 10 0% 31-Oct-13 14-Nov-13 26-Nov-14 09-Dec-14 267
IBNPOPO-3641 KT APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBN) 25 25 0% 24-Feb-12 29-Mar-12 21-Mar-13 24-Apr-13 268
IBNPOPO-3590 PREPARE/SUBMIT INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBN) 30 30 0% 11-Jan-12 23-Feb-12 06-Feb-13 20-Mar-13 268
IBNPOPO-3600 VA APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBN) 20 20 0% 30-Mar-12 26-Apr-12 25-Apr-13 22-May-13 268
IBNPOPO-3610 FABRICATE/DELIVER INTERSTITIAL STEEL - STR-2 (IBN) 40 40 0% 27-Apr-12 22-Jun-12 23-May-... 19-Jul-13 268
IBNPOPO-3620 FIRST DELIVERY OF INTERSTITIAL STEEL - STR-2 (IBN) 0 0 0% 22-Jun-12 19-Jul-13 268
IBSPOPO-4860 PREPARE/SUBMIT INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBS) 30 30 0% 27-Dec-11 08-Feb-12 23-Jan-13 06-Mar-13 268
IBPPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (IBS/IBN) 20 20 0% 03-Jul-12 31-Jul-12 30-Jul-13 26-Aug-13 268
IBSPBPB-8880 CLEAN-UP/PRE PUNCH - PIPE BSMT IBS 15 15 0% 17-Sep-13 07-Oct-13 10-Oct-14 31-Oct-14 268
IBSPBPB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - PIPE BSMT IBS 10 10 0% 03-Sep-13 16-Sep-13 26-Sep-14 09-Oct-14 268
IBSPBPB-0920 HANG/TAPE/FINISH DRYWALL - PIPE BSMT IBS 15 15 0% 12-Aug-13 30-Aug-13 05-Sep-14 25-Sep-14 268
PSNL3L3-1610 GARAGE FINISHES - LVL-3 PSN 25 25 0% 26-Sep-13 31-Oct-13 23-Oct-14 28-Nov-14 269
PSNL3L3-8910 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-3 PSN 10 10 0% 01-Nov-13 15-Nov-13 01-Dec-14 12-Dec-14 269
DATSLEM-1516 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL EMER MGMT DAT 25 25 0% 07-May-13 11-Jun-13 04-Jun-14 09-Jul-14 270
DATSLEM-0910 FRAMING/INWALL ROUGH - SERV LVL EMER MGMT DAT 20 20 0% 21-May-13 18-Jun-13 18-Jun-14 16-Jul-14 270
PSNCOCO-0520 PEDESTRIAN BRIDGE CONSTRUCTION - PSN 120 120 0% 20-Mar-13 11-Oct-13 26-Jun-14 13-Jan-15 271
IBSRLRL-2610 INSTALL GREEN ROOF SYSTEM - ROOF IBS 15 15 0% 03-Jul-13 29-Jul-13 08-Oct-14 31-Oct-14 272
CONESAE-890 INSTALL EXTERIOR FINISHES (LVL-1 BUMP OUTS) - AR-E CON 20 20 0% 03-Jun-13 05-Jul-13 11-Sep-14 10-Oct-14 273
CONALAL-1402 INSTALL SERVICE ELEVATOR - AREA A CON 60 60 0% 28-Nov-13 25-Feb-14 31-Dec-14 27-Mar-15 273
IBSPOPO-4910 KT APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBS) 25 25 0% 09-Feb-12 15-Mar-12 14-Mar-13 17-Apr-13 273
IBSPOPO-4880 FABRICATE/DELIVER INTERSTITIAL STEEL - STR-2 (IBS) 40 40 0% 13-Apr-12 08-Jun-12 16-May-... 12-Jul-13 273
IBSPOPO-4890 FIRST DELIVERY OF INTERSTITIAL STEEL - STR-2 (IBS) 0 0 0% 08-Jun-12 12-Jul-13 273
IBSPOPO-4870 VA APPROVE INTERSTITIAL STEEL SHOP DRAWINGS - STR-2 (IBS) 20 20 0% 16-Mar-12 12-Apr-12 18-Apr-13 15-May-13 273
CBNHRPR-0750 BLOCKING/ICE WATER SHIELD- PENT ROOF CBN 20 20 0% 26-Apr-13 31-May-13 07-Aug-14 09-Sep-14 273
CBNHRPR-0788 APPLY ROOFING SYSTEM - PENT ROOF CBN 15 15 0% 01-Apr-13 25-Apr-13 11-Jul-14 05-Aug-14 273
CBNHRPR-0740 INSTALL/CONNECT PV PANELS - PENT ROOF CBN 20 20 0% 03-Jun-13 05-Jul-13 11-Sep-14 10-Oct-14 273
CONAELR-0710 PARAPET/BLOCKING/ROOFING - LOW ROOF AR-E CON 12 12 0% 03-Jun-13 21-Jun-13 15-Sep-14 02-Oct-14 275
CONAELR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF AR-E CON 12 12 0% 24-Jun-13 12-Jul-13 03-Oct-14 22-Oct-14 275
CONSLAD-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-D CON 14 14 0% 18-Oct-13 07-Nov-13 26-Nov-14 15-Dec-14 275
CONSLAD-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-D CON 15 15 0% 08-Nov-13 02-Dec-13 16-Dec-14 07-Jan-15 275
CREDIT-1458 VA REVIEWS/APPROVES DEMOLITION PLAN FOR CREDIT UNION 20 20 0% 13-Dec-11 11-Jan-12 18-Jan-13 18-Feb-13 275
CREDIT-1428 AWARD CREDIT UNION DEMO CONTRACT 20 20 0% 28-Sep-11 26-Oct-11 02-Nov-12 04-Dec-12 275
CREDIT-1438 PREPARE DEMOLITION PLAN FOR CREDIT UNION 20 20 0% 27-Oct-11 28-Nov-11 05-Dec-12 03-Jan-13 275
CREDIT-1448 KT REVIEW/APPROVE DEMOLITION PLAN FOR CREDIT UNION 10 10 0% 29-Nov-11 12-Dec-11 04-Jan-13 17-Jan-13 275
IBNRLRL-2610 INSTALL GREEN ROOFING SYSTEM - ROOF IBN 15 15 0% 25-Jun-13 19-Jul-13 08-Oct-14 31-Oct-14 277
CBNPHME-1520 CONNECT/PIPE-UP MECH EQUIP - PENTHOUSE MECH CBN 25 25 0% 20-Aug-13 24-Sep-13 26-Sep-14 31-Oct-14 277
DATSLIL-0701 TRIM-OUT MEP (STERILIZATION) (AHU7) - SERV LVL INTER LVL DAT 5 5 0% 02-Oct-13 08-Oct-13 10-Nov-14 17-Nov-14 277
PSNL2L2-1590 GARAGE FINISHES - LVL -2 PSN 25 25 0% 12-Sep-13 16-Oct-13 23-Oct-14 28-Nov-14 279
PSNL2L2-8900 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-2 PSN 10 10 0% 17-Oct-13 31-Oct-13 01-Dec-14 12-Dec-14 279
CONSLAD-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-D CON 5 5 0% 03-Dec-13 09-Dec-13 15-Jan-15 22-Jan-15 280
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
53 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 134
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATSLPY-0977 INSTALL OWNER FIXED FF&E - SERV LVL PHARMACY DAT 20 20 0% 13-Sep-13 10-Oct-13 27-Oct-14 25-Nov-14 280
DATSLPY-8880 CLEAN-UP/PRE PUNCH - SERV LVL PHARMACY DAT 10 10 0% 11-Oct-13 25-Oct-13 26-Nov-14 09-Dec-14 280
DATSLST-0977 INSTALL OWNER FIXED FF&E - SERV LVL STER DAT 20 20 0% 27-Sep-13 25-Oct-13 10-Nov-14 09-Dec-14 280
DATSLST-8880 CLEAN-UP/PRE PUNCH - SERV LVL STER DAT 10 10 0% 28-Oct-13 08-Nov-13 10-Dec-14 23-Dec-14 280
ENCALCO-9999 CREATE/COMPLETE FINAL PUNCHLIST - ALL LVLS ENC 20 20 0% 18-Nov-13 16-Dec-13 02-Jan-15 30-Jan-15 281
ENCESEE-870 INSTALL GLASS - EAST ELEV ENC 5 5 0% 14-Dec-12 21-Dec-12 31-Mar-14 07-Apr-14 281
17SW-0215 PLACE EROSION PROTECTION/TRAFFIC CONTROL - 17TH AVE 2 2 0% 16-May-13 17-May-13 08-Sep-14 09-Sep-14 281
17SW-0218 DEMO/GRADING - 17TH AVE 5 5 0% 20-May-13 28-May-13 11-Sep-14 18-Sep-14 281
17SW-0220 INSTALL UTILITIES - 17TH AVE 15 15 0% 29-May-13 21-Jun-13 19-Sep-14 10-Oct-14 281
17SW-0228 CONSTRUCT ROADWAY - 17TH AVE 15 15 0% 24-Jun-13 18-Jul-13 14-Oct-14 06-Nov-14 281
DATPOPO-4720 VA APPROVE CURTIANWALL SHOPS - CS-1/IFO-3 (DAT) 20 20 0% 21-May-12 18-Jun-12 12-Jul-13 08-Aug-13 286
CONSLAB-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-B CON 15 15 0% 22-Oct-13 12-Nov-13 16-Dec-14 07-Jan-15 288
CONSLAB-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-B CON 5 5 0% 13-Nov-13 19-Nov-13 15-Jan-15 22-Jan-15 293
EEEEPSN-0000 PSN BLDG AVAILABLE FOR ENERGIZE 0 0 0% 07-Nov-13 13-Jan-15 294
CONESAD-890 INSTALL EXTERIOR FINISHES (LVL-1 BUMP OUTS) - AR-D CON 15 15 0% 29-May-13 21-Jun-13 10-Oct-14 04-Nov-14 295
ENCLRLR-2600 INSTALL GREEN ROOF SYSTEM - LOW ROOF ENC 15 15 0% 26-Jul-13 20-Aug-13 09-Dec-14 31-Dec-14 295
ENCESPH-0777 INSTALL LOUVERS - WEST ELEV ENC 15 15 0% 01-Jul-13 25-Jul-13 13-Nov-14 08-Dec-14 295
ENCESPH-0870 INSTALL CURTAIN WALL - PENTHOUSE ENC 10 10 0% 13-Jun-13 28-Jun-13 27-Oct-14 12-Nov-14 295
CONESAA-0540 ERECT EXTERIOR STUDS/SHEATHING - AR-A CON 15 15 0% 28-Mar-13 22-Apr-13 18-Aug-14 11-Sep-14 296
PVSINL0-0320 INSTALL RIDGID INSULATION/PLACE TOPPING SLAB - PKG LVL-0 PVS 15 15 0% 13-May-13 03-Jun-13 17-Jul-14 06-Aug-14 296
PVSINL0-0750 APPLY WATERPROOFING- PKG LVL-0 PVS 30 30 0% 08-Apr-13 17-May-13 11-Jun-14 23-Jul-14 296
C-DEM-1400 APARTMENT COMPLEX ABATEMENT 20 20 0% 06-Sep-11 06-Oct-11 17-Jan-13 15-Feb-13 296
C-DEM-1403 APARTMENT COMPLEX DEMOLITION & EXCAVATION/FILL 25 25 0% 25-Oct-11 05-Dec-11 05-Mar-13 15-Apr-13 296
C-DEM-1404 POOL BUILDING DEMOLITION & EXCAVATION/FILL 25 25 0% 06-Dec-11 17-Jan-12 16-Apr-13 30-May-13 296
C-DEM-1409 MOBILIZE ABATEMENT 10 10 0% 18-Aug-11 02-Sep-11 02-Jan-13 15-Jan-13 296
C-DEM-1412 APARTMENT COMPLEX POST ABATEMENT AIR QUALITY REV 10 10 0% 07-Oct-11 24-Oct-11 19-Feb-13 04-Mar-13 296
C-DEM-1413 COMPLETE RFP 3 APT AND POOL COMPLEX DEMO 0 0 0% 17-Jan-12 30-May-13 296
DATPOPO-5130 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(MRI/CT) INFO- IFO-1 (DAT) 15 15 0% 27-Aug-12 17-Sep-12 04-Nov-13 26-Nov-13 297
DATPOPO-5000 VA APPROVE MEDICAL EQUIPMENT(MRI/CT) - IFO-1 (DAT) 20 20 0% 18-Sep-12 16-Oct-12 27-Nov-13 24-Dec-13 297
CONADLR-0710 PARAPET/BLOCKING/ROOFING - LOW ROOF AR-D CON 12 12 0% 29-May-13 17-Jun-13 17-Oct-14 04-Nov-14 298
PSNALAL-1400 INSTALL ELEVATOR - ALL LVLS PSN 60 60 0% 07-Aug-13 31-Oct-13 15-Oct-14 13-Jan-15 299
CONABHR-0755 INSTALL STANDING SEAM ROOF - HIGH ROOF AR-B CON 30 30 0% 23-Sep-13 08-Nov-13 06-Feb-15 27-Mar-15 300
ENCESWE-0777 INSTALL SCREEN WALL - WEST ELEV ENC 15 15 0% 18-Jul-13 12-Aug-13 09-Dec-14 31-Dec-14 300
DATSLIL-0201 TRIM-OUT MEP (PHARMACY) (AHU2) - SERV LVL INTER LVL DAT 5 5 0% 29-Aug-13 05-Sep-13 10-Nov-14 17-Nov-14 300
CONABLR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF AR-B CON 12 12 0% 03-Oct-13 22-Oct-13 20-Feb-15 10-Mar-15 301
CONABLR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF AR-B CON 10 10 0% 23-Oct-13 07-Nov-13 12-Mar-15 27-Mar-15 301
PSNL1L1-1570 GARAGE FINISHES - LVL-1 PSN 25 25 0% 12-Aug-13 16-Sep-13 23-Oct-14 28-Nov-14 301
PSNL1L1-8890 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 PSN 10 10 0% 17-Sep-13 30-Sep-13 01-Dec-14 12-Dec-14 301
C-DEM-1401 POOL BUILDING ABATEMENT 20 20 0% 07-Oct-11 09-Nov-11 26-Feb-13 28-Mar-13 301
C-DEM-1414 POOL BUILDING POST ABATEMENT AIR QUALITY REVIEW 10 10 0% 10-Nov-11 28-Nov-11 29-Mar-13 15-Apr-13 301
DATESAB-0440 LAY STACKED STONE - ALL ELEVS AR-B DAT 20 20 0% 27-Jun-13 30-Jul-13 21-Nov-14 23-Dec-14 302
DATESAA-0440 LAY STACKED STONE - ALL ELEVS AR-A DAT 20 20 0% 10-Jun-13 12-Jul-13 04-Nov-14 08-Dec-14 302
IBSSLIL-1517 TRIM-OUT MEP/FIRE PROTECTION - SERV LVL INTER LVL IBS 25 25 0% 23-Aug-13 27-Sep-13 10-Nov-14 16-Dec-14 304
PSNSLSL-3100 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL PSN 15 15 0% 26-May-12 13-Jun-12 31-May-... 17-Jun-13 306
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
54 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 135
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATPHNP-1623 SET/CONNECT PHOTOVOLTAIC PANELS- NORTH PENT DAT 50 50 0% 20-Mar-13 14-Jun-13 26-Aug-14 17-Nov-14 306
CONAAHR-0755 INSTALL STANDING SEAM ROOF - LOW ROOF AR-A CON 25 25 0% 19-Sep-13 28-Oct-13 17-Feb-15 27-Mar-15 307
P-CD4-4930 AWARD LAB CASEWORK CONTRACT 20 20 0% 05-Apr-12 02-May-12 26-Jun-13 24-Jul-13 307
DATPOPO-4901 KT REVIEW LAB CASEWORK MOCK- UP DESIGN - IFO-1 (DAT) 20 20 0% 15-Jun-12 13-Jul-12 06-Sep-13 03-Oct-13 307
DATPOPO-4911 KT REVIEW LAB CASEWORK MOCK-UP - IFO-1 (DAT) 20 20 0% 09-Oct-12 06-Nov-12 03-Jan-14 31-Jan-14 307
DATPOPO-4881 VA APPROVE LAB CASEWORK MOCK-UP - IFO-1 (DAT) 20 20 0% 07-Nov-12 07-Dec-12 03-Feb-14 03-Mar-14 307
DATPOPO-4891 FABRICATE/DELIVER LAB CASEWORK - IFO-1 (DAT) 65 65 0% 10-Dec-12 14-Mar-13 04-Mar-14 03-Jun-14 307
DATPOPO-1500 LAB CASEWORK MOCK-UP SHOP DRAWINGS - IFO-1 (DAT) 30 30 0% 03-May-12 14-Jun-12 25-Jul-13 05-Sep-13 307
DATPOPO-1501 VA APPROVE LAB CASEWORK MOCK- UP DESIGN - IFO-1 (DAT) 20 20 0% 16-Jul-12 10-Aug-12 04-Oct-13 01-Nov-13 307
DATPOPO-1052 LAB CASEWORK MOCK- UP MATERIAL PROCURMENT AND FAB - IFO-1 (DAT) 40 40 0% 13-Aug-12 08-Oct-12 04-Nov-13 02-Jan-14 307
DATPHSP-1690 SET/CONNECT PHOTOVOLTAIC PANELS- SOUTH PENT DAT 50 50 0% 15-Mar-13 10-Jun-13 26-Aug-14 17-Nov-14 309
CONESAA-890 INSTALL EXTERIOR FINISHES (LVL-1 BUMP OUTS) - AR-A CON 15 15 0% 23-Apr-13 20-May-13 06-Oct-14 28-Oct-14 310
IBNSLIL-1517 TRIM-OUT MEP/FIRE PROTECTION - SERV LVL INTER LVL IBN 25 25 0% 15-Aug-13 19-Sep-13 10-Nov-14 16-Dec-14 310
ZZZZOFF-10019 FINISH OFF-SITE IMPROVEMENTS (finish milestone) 0 0 0% 22-May-14 28-Mar-15 310
SITSWNP-0200 RFP 3 UNDERGROUND DEMOLITION/ABATEMENT - NORTH PARCEL 30 30 0% 04-Nov-11 22-Dec-11 08-Apr-13 30-May-13 310
SITSWNP-0280 RFP 3 ABOVE GROUND DEMOLITION - NORTH PARCEL 25 25 0% 27-Oct-11 06-Dec-11 29-Mar-13 13-May-13 310
C-DEM-1411 UTILITY DISCONNECTS 5 5 0% 06-Sep-11 12-Sep-11 08-Feb-13 15-Feb-13 311
IBSRLRL-2600 SET/CONNECT PHOTOVOLTAIC PANELS - ROOF IBS 40 40 0% 03-Jul-13 10-Sep-13 12-Dec-14 16-Feb-15 311
DATPOPO-5020 MEDICAL EQUIPMENT ARRIVES (MRI/CT) - IFO-1 (DAT) 0 0 0% 07-Jun-13 04-Sep-14 312
DATPOPO-5010 FABRICATE MEDICAL EQUIPMENT (MRI/CT) - IFO-1 (DAT) 160 160 0% 17-Oct-12 07-Jun-13 17-Jan-14 04-Sep-14 312
DATESAE-0440 LAY STACKED STONE - ALL ELEVS AR-E DAT 20 20 0% 06-May-13 07-Jun-13 20-Oct-14 19-Nov-14 312
CONAALR-0710 PARAPET/BLOCKING/ROOFING - LOW ROOF AR-A CON 12 12 0% 23-Apr-13 14-May-13 09-Oct-14 28-Oct-14 313
DATPGPG-3220 BACKFILL FOUNDATION WALLS - SERV LVL DAT 5 5 0% 23-Aug-12 30-Aug-12 31-Jan-14 06-Feb-14 313
SITSWNP-0100 MOBILIZE RFP 3 CONSTRUCTION RESOURCES - NORTH PARCEL 5 5 0% 14-Oct-11 20-Oct-11 21-Mar-13 28-Mar-13 313
DATPHNP-1520 CONNECT/PIPE-UP MECH EQUIP - NORTH PENT MECH DAT 60 60 0% 22-May-13 15-Aug-13 21-Aug-14 17-Nov-14 314
IBNRLRL-2600 SET/CONNECT PHOTOVOLTAIC PANELS - ROOF IBN 40 40 0% 25-Jun-13 03-Sep-13 12-Dec-14 16-Feb-15 316
CLC-5040 VA REVIEWS/APPROVES COST/RESOURCE LOADED CONSTRUCTION SCHEDULE- CLC 30 30 0% 26-Aug-12 24-Sep-12 08-Jul-13 06-Aug-13 316
CLC-3710 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - CLC 60 60 0% 28-Apr-12 26-Jun-12 10-Mar-13 08-May-13 316
CLC-5020 COST/RESOURCE LOAD BALANCE OF SCHEDULE - CLC 60 60 0% 27-Jun-12 25-Aug-12 09-May-... 07-Jul-13 316
ENCSLSL-0390 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL ENC 15 15 0% 02-Oct-12 24-Oct-12 13-Mar-14 07-Apr-14 316
IBPOPO-5730 KT REVIEW HEADWALL MOCK- UP DESIGN - IFO-1 (IBS/IBN) 10 10 0% 17-May-12 31-May-12 22-Aug-13 05-Sep-13 317
IBPOPO-5740 KT REVIEW HEADWALL MOCK-UP - IFO-1 (IBS/IBN) 15 15 0% 27-Aug-12 17-Sep-12 04-Dec-13 24-Dec-13 317
IBPOPO-5750 HEADWALLS ARRIVE - IFO-1 (IBS/IBN) 0 0 0% 11-Apr-13 16-Jul-14 317
IBPOPO-4880 VA APPROVE HEADWALL MOCK-UP - IFO-1 (IBS/IBN) 20 20 0% 18-Sep-12 16-Oct-12 26-Dec-13 24-Jan-14 317
IBPOPO-4890 FABRICATE/DELIVER HEADWALLS - IFO-1 (IBS/IBN) 120 120 0% 17-Oct-12 11-Apr-13 27-Jan-14 16-Jul-14 317
IBPOPO-1500 HEADWALL MOCK-UP SHOP DRAWINGS - IFO-1 (IBS/IBN) 30 30 0% 05-Apr-12 16-May-12 11-Jul-13 21-Aug-13 317
IBPOPO-1501 VA APPROVE HEADWALL MOCK- UP DESIGN - IFO-1 (IBS/IBN) 20 20 0% 01-Jun-12 28-Jun-12 06-Sep-13 03-Oct-13 317
IBPOPO-1052 HEADWALL MOCK- UP MATERIAL PROCURMENT AND FAB - IFO-1 (IBS/IBN) 40 40 0% 29-Jun-12 24-Aug-12 04-Oct-13 03-Dec-13 317
PSNALAL-0555 ERECT STAIRS - ALL LVLS PSN 20 20 0% 10-Jul-13 06-Aug-13 15-Oct-14 13-Nov-14 319
PSNALAL-0991 FINISH STAIR CORES - ALL LVLS PSN 20 20 0% 07-Aug-13 04-Sep-13 14-Nov-14 12-Dec-14 319
DATRLRL-1650 INSTALL GREEN ROOF SYSTEM - NORTH LOW ROOF DAT 18 18 0% 13-May-13 11-Jun-13 07-Nov-14 08-Dec-14 320
DATRLRL-1660 INSTALL ROOF ACCESSORIES - NORTH LOW ROOF DAT 10 10 0% 13-Jun-13 28-Jun-13 09-Dec-14 23-Dec-14 320
DATPHSP-1520 CONNECT/PIPE-UP MECH EQUIP - SOUTH PENT MECH DAT 60 60 0% 14-May-13 07-Aug-13 21-Aug-14 17-Nov-14 320
DATSLIL-1901 TRIM-OUT MEP (SHELL) (AHU19) - SERV LVL INTER LVL DAT 5 5 0% 01-Aug-13 07-Aug-13 10-Nov-14 17-Nov-14 320
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
55 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 136
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
DATESNP-0520 ERECT STUDS/SHEATHING/VAPOR BARRIER - ALL ELEVS NORTH PNTHSE DAT 15 15 0% 25-Feb-13 19-Mar-13 25-Aug-14 18-Sep-14 320
DATESNP-0780 INSTALL METAL PANEL - ALL ELEVS NORTH PNTHSE DAT 20 20 0% 05-Apr-13 10-May-13 06-Oct-14 06-Nov-14 320
DATESNP-0555 ERECT TRELLIS - ALL ELEVS NORTH PNTHSE DAT 10 10 0% 20-Mar-13 04-Apr-13 19-Sep-14 03-Oct-14 320
DATPOPO-5100 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(dental) INFO - IFO-1 (DAT) 15 15 0% 11-Sep-12 01-Oct-12 26-Dec-13 16-Jan-14 322
DATPOPO-4880 VA APPROVE MEDICAL EQUIPMENT(dental) - IFO-1 (DAT) 20 20 0% 02-Oct-12 30-Oct-12 17-Jan-14 17-Feb-14 322
DATPOPO-4890 FABRICATE MEDICAL EQUIPMENT (dental) - IFO-1 (DAT) 140 140 0% 31-Oct-12 23-May-13 18-Feb-14 04-Sep-14 322
DATPOPO-4900 MEDICAL EQUIPMENT ARRIVES (dental) - IFO-1 (DAT) 0 0 0% 23-May-13 04-Sep-14 322
ENCESWE-0870 TIE-INS @ CONCOURSE - WEST ELEV ENC 20 20 0% 01-Nov-12 04-Dec-12 25-Apr-14 30-May-14 322
19SW-0238 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - 19TH PLACE 10 10 0% 20-Jul-12 06-Aug-12 30-Oct-14 14-Nov-14 324
CLC-0100 CLC CONSTRUCTION (16 months) 480 480 0% 13-Dec-12 06-Apr-14 04-Nov-13 26-Feb-15 326
ZZZZCLC-10009 FINISH CLC CONSTRUCTION (finish milestone) 0 0 0% 06-Apr-14 26-Feb-15 326
XXXXCLC-0500 CLC OVERALL DURATION 480 480 0% 13-Dec-12 06-Apr-14 04-Nov-13 26-Feb-15 326
DATPOPO-3990 MEDICAL EQUIPMENT ARRIVES (gen imaging) - IFO-1 (DAT) 0 0 0% 25-Apr-13 13-Aug-14 327
DATPOPO-4910 SUBMIT MEDICAL EQUIPMENT SHOPS (surgery) - IFO-1 (DAT) 60 60 0% 29-Jun-12 24-Sep-12 18-Oct-13 16-Jan-14 327
DATPOPO-3980 FABRICATE MEDICAL EQUIPMENT (gen imaging) - IFO-1 (DAT) 140 140 0% 02-Oct-12 25-Apr-13 27-Jan-14 13-Aug-14 327
CONSLAC-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-C CON 18 18 0% 13-Aug-13 06-Sep-13 04-Dec-14 30-Dec-14 328
CONSLAC-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-C CON 5 5 0% 09-Sep-13 13-Sep-13 31-Dec-14 07-Jan-15 328
DATRLNR-1670 INSTALL GREEN ROOF SYSTEM - SOUTH LOW ROOF DAT 18 18 0% 25-Apr-13 28-May-13 07-Nov-14 08-Dec-14 329
DATRLNR-1680 INSTALL ROOF ACCESSORIES - SOUTH LOW ROOF DAT 10 10 0% 29-May-13 13-Jun-13 09-Dec-14 23-Dec-14 329
DATESSP-0520 STUDS/SHEATHING/VAPOR BARRIER - ALL ELEVS SOUTH PNTHSE DAT 15 15 0% 08-Feb-13 04-Mar-13 25-Aug-14 18-Sep-14 329
DATESSP-0780 INSTALL METAL PANEL - ALL ELEVS SOUTH PNTHSE DAT 20 20 0% 21-Mar-13 23-Apr-13 06-Oct-14 06-Nov-14 329
DATESSP-0555 ERECT TRELLIS - ALL ELEVS SOUTH PNTHSE DAT 10 10 0% 05-Mar-13 20-Mar-13 19-Sep-14 03-Oct-14 329
STR2-4820 AWARD CAST-IN-PLACE GARAGES (PVN/PSN) CONTRACT 20 20 0% 26-Oct-11 23-Nov-11 27-Feb-13 26-Mar-13 332
PSNPOPO-4880 KT APPROVE GARAGE SHOP DRAWINGS - STR-2 (PSN) 25 25 0% 11-Jan-12 16-Feb-12 08-May-... 12-Jun-13 332
PSNPOPO-4820 PREPARE/SUBMIT GARAGE SHOP DRAWINGS - STR-2 (PSN) 30 30 0% 28-Nov-11 10-Jan-12 27-Mar-13 07-May-13 332
PSNPOPO-4830 VA APPROVE GARAGE SHOP DRAWINGS - STR-2 (PSN) 20 20 0% 17-Feb-12 15-Mar-12 13-Jun-13 11-Jul-13 332
PSNPOPO-4840 FABRICATE/DELIVER STRUCTURAL MATERIALS - STR-2 (PSN) 20 20 0% 16-Mar-12 12-Apr-12 12-Jul-13 08-Aug-13 332
PSNPOPO-4850 FIRST DELIVERY OF STRUCTUAL MATERIALS - STR-2 (PSN) 0 0 0% 12-Apr-12 08-Aug-13 332
CONSLAC-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-C CON 5 5 0% 16-Sep-13 20-Sep-13 15-Jan-15 22-Jan-15 333
DATESNP-780 INSTALL LOUVERS - ALL ELEVS NORTH PNTHSE DAT 10 10 0% 20-Mar-13 04-Apr-13 22-Oct-14 06-Nov-14 340
C-RF3-1408 VA APPROVAL OF ABATEMENT PLAN - RFP 3 30 16 46.67% 12-Jul-11 A 16-Aug-11 07-Dec-12 31-Dec-12 342
IFO-5041 VA REVIEWS/APPROVES COST/RESOURCE LOADED CONSTRUCTION SCHEDULE- IFO-1 30 30 0% 31-Jul-12 29-Aug-12 08-Jul-13 06-Aug-13 342
IFO-1999 VA APPROVAL OF FINAL COST/RESOURCE LOADED CONSTRUCTION SCHEDULE - IFO-1 0 0 0% 29-Aug-12 06-Aug-13 342
IFO-5040 COST/RESOURCE LOAD SCHEDULE (GROUP #3) - IFO-1 60 60 0% 01-Jun-12 30-Jul-12 09-May-... 07-Jul-13 342
CS1-4940 AWARD ROOFING CONTRACT 20 20 0% 05-Jan-12 02-Feb-12 17-May-... 14-Jun-13 343
ENCSLSH-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHOP ENC 22 22 0% 07-Mar-13 05-Apr-13 22-Jul-14 20-Aug-14 346
ENCSLSH-0910 FRAMING/INWALL ROUGH - SERV LVL SHOP ENC 30 30 0% 15-Jan-13 27-Feb-13 02-Jun-14 14-Jul-14 346
ENCSLSH-0920 HANG/TAPE/FINISH DRYWALL - SERV LVL SHOP ENC 15 15 0% 14-Feb-13 06-Mar-13 30-Jun-14 21-Jul-14 346
ENCALAL-0561 STAIR CORE FINISHES (ST1) - ALL LVLS ENC 30 30 0% 08-Apr-13 17-May-13 21-Aug-14 02-Oct-14 346
ENCALAL-0562 STAIR CORE FINISHES (ST2) - ALL LVLS ENC 30 30 0% 20-May-13 01-Jul-13 03-Oct-14 17-Nov-14 346
ENCALAL-0563 STAIR CORE FINISHES (ST3) - ALL LVLS ENC 30 30 0% 02-Jul-13 13-Aug-13 18-Nov-14 31-Dec-14 346
ZZZZENC-9999 FINISH ENC CONSTRUCTION (finish milestone) 0 0 0% 28-Feb-14 11-Feb-15 348
XXXXENC-0500 ENC OVERALL DURATION 695 695 0% 05-Apr-12 28-Feb-14 09-Aug-12 11-Feb-15 348
ENCALCO-1599 BUILDING FLUSH - ALL LVLS ENC 10 10 0% 19-Feb-14 28-Feb-14 02-Feb-15 11-Feb-15 348
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
56 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 137
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ZZZZPSN-9999 FINISH PSN CONSTRUCTION (finish milestone) 0 0 0% 14-Mar-14 26-Feb-15 349
XXXXPSN-0500 PSN OVERALL DURATION 639 639 0% 14-Jun-12 14-Mar-14 09-Aug-13 26-Feb-15 349
DATESSP-780 INSTALL LOUVERS - ALL ELEVS SOUTH PNTHSE DAT 10 10 0% 05-Mar-13 20-Mar-13 22-Oct-14 06-Nov-14 349
PVNPOPO-4880 KT APPROVE GARAGE SHOP DRAWINGS - STR-2 (PVN) 25 25 0% 09-Feb-12 15-Mar-12 09-Jul-13 12-Aug-13 354
PVNPOPO-4820 PREPARE/SUBMIT GARAGE SHOP DRAWINGS - STR-2 (PVN) 30 30 0% 27-Dec-11 08-Feb-12 24-May-... 08-Jul-13 354
PVNPOPO-4830 VA APPROVE GARAGE SHOP DRAWINGS - STR-2 (PVN) 20 20 0% 16-Mar-12 12-Apr-12 13-Aug-13 10-Sep-13 354
PVNPOPO-4840 FABRICATE/DELIVER STRUCTURAL MATERIALS - STR-2 (PVN) 20 20 0% 13-Apr-12 10-May-12 11-Sep-13 08-Oct-13 354
PVNPOPO-4850 FIRST DELIVERY OF STRUCTURAL MATERIALS - STR-2 (PVN) 0 0 0% 10-May-12 08-Oct-13 354
RESPOPO-3760 CURTAIN WALL 1ST DELIVERY ARRIVES - CS-1/IFO-3 (RES) 0 0 0% 29-Apr-13 24-Sep-14 354
RESPOPO-3730 CURTAIN WALL MATERIALS PROCUREMENT - CS-1/IFO-3 (RES) 30 30 0% 12-Feb-13 25-Mar-13 09-Jul-14 19-Aug-14 354
RESPOPO-3740 FABRICATE/DELIVER CURTAINWALL - CS-1/IFO-3 (RES) 25 25 0% 26-Mar-13 29-Apr-13 20-Aug-14 24-Sep-14 354
RESPOPO-4720 CURTAIN WALL MOCK- UP FABRICATION/ERECT/TEST - CS-1/IFO-3 (RES) 60 60 0% 09-Nov-12 08-Feb-13 14-Apr-14 08-Jul-14 354
RESPOPO-4890 KT APPROVE CURTAINWALL SHOPS - SHOPS - CS-1/IFO-3 (RES) 30 30 0% 15-Aug-12 26-Sep-12 16-Jan-14 28-Feb-14 354
RESPOPO-4900 ORDER CUSTOM DIES - CS-1/IFO-3 (RES) 30 30 0% 27-Sep-12 08-Nov-12 03-Mar-14 11-Apr-14 354
ENCHRHR-2600 SET/CONNECT PHOTOVOLTAIC PANELS - HIGH ROOF ENC 50 50 0% 15-Mar-13 10-Jun-13 12-Nov-14 30-Jan-15 355
IBSPBPB-0910 FRAMING/INWALL ROUGH - PIPE BSMT IBS 10 10 0% 26-Mar-13 08-Apr-13 21-Aug-14 04-Sep-14 355
PVSSWHL-0210 INSTALL UNDERGROUND UTILITIES @ SOUTH ENTRY - SITEWORK PVS 8 8 0% 20-Sep-12 02-Oct-12 09-May-... 22-May-14 356
PVSSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK PVS 20 20 0% 28-Sep-12 29-Oct-12 19-May-... 23-Jun-14 356
CBPOPO-4870 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 15 15 0% 02-Apr-12 20-Apr-12 03-Sep-13 23-Sep-13 357
CBPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 20 20 0% 23-Apr-12 18-May-12 24-Sep-13 22-Oct-13 357
CBPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (CBS/CBN) 55 55 0% 21-May-12 07-Aug-12 23-Oct-13 13-Jan-14 357
PVNSWHL-0210 INSTALL UNDERGROUND UTILITIES @ NORTH ENTRY- SITEWORK PVN 25 25 0% 31-Dec-12 06-Feb-13 02-Sep-14 09-Oct-14 359
PVNSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK PVN 20 20 0% 11-Jan-13 11-Feb-13 15-Sep-14 16-Oct-14 359
ENCL1OF-0910 FRAMING/INWALL ROUGH - LVL-1 OFFICES ENC 15 15 0% 18-Dec-12 09-Jan-13 23-May-... 13-Jun-14 359
ENCL1OF-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 OFFICES ENC 12 12 0% 10-Jan-13 28-Jan-13 16-Jun-14 01-Jul-14 359
ENCL1OF-0990 INSTALL INTERIOR FINISHES & SPECIALTIES- LVL-1 OFFICES ENC 35 35 0% 29-Jan-13 19-Mar-13 02-Jul-14 20-Aug-14 359
CONAELR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF AR-E CON 10 10 0% 15-Jul-13 30-Jul-13 12-Mar-15 27-Mar-15 360
CONSLAA-0990 INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-A CON 15 15 0% 10-Jul-13 30-Jul-13 16-Dec-14 07-Jan-15 360
CONADLR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF AR-D CON 12 12 0% 18-Jun-13 08-Jul-13 20-Feb-15 10-Mar-15 363
CONADLR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF AR-D CON 10 10 0% 09-Jul-13 25-Jul-13 12-Mar-15 27-Mar-15 363
PSNPOPO-4860 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 40 40 0% 25-Jul-12 19-Sep-12 09-Jan-14 07-Mar-14 364
ENCPOPO-5409 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 40 40 0% 26-Jun-12 21-Aug-12 10-Dec-13 06-Feb-14 364
PVNPOPO-4900 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 15 15 0% 19-Oct-12 08-Nov-12 07-Apr-14 25-Apr-14 364
PVNPOPO-4860 PREPARE/SUBMIT ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 40 40 0% 22-Aug-12 18-Oct-12 07-Feb-14 04-Apr-14 364
PVNPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 45 45 0% 09-Nov-12 17-Jan-13 28-Apr-14 30-Jun-14 364
PVNPOPO-4870 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (PVN) 90 90 0% 18-Jan-13 28-May-13 01-Jul-14 06-Nov-14 364
CONSLAA-8880 CLEAN-UP/PRE PUNCH - SERV LVL AR-A CON 5 5 0% 31-Jul-13 06-Aug-13 15-Jan-15 22-Jan-15 365
IFO-4910 KT APPROVE SOLARVOLTAIC EQUIPMENT - IFO-1 25 25 0% 15-Jun-12 20-Jul-12 02-Dec-13 07-Jan-14 365
IFO-4020 VA APPROVE SOLARVOLTAIC EQUIPMENT - IFO-1 20 20 0% 23-Jul-12 17-Aug-12 08-Jan-14 05-Feb-14 365
IFO-4030 FABRICATE SOLARVOLTAIC EQUIPMENT - IFO-1 140 140 0% 20-Aug-12 14-Mar-13 06-Feb-14 25-Aug-14 365
IFO-4040 SOLARVOLTAIC EQUIPMENT ARRIVES - IFO-1 0 0 0% 14-Mar-13 25-Aug-14 365
IFO-4010 SUBMIT SOLARVOLTAIC EQUIPMENT - IFO-1 50 50 0% 05-Apr-12 14-Jun-12 18-Sep-13 29-Nov-13 365
CBCSLSL-0380 FINE GRADE FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL CBC 8 8 0% 03-Dec-12 14-Dec-12 14-Aug-14 26-Aug-14 365
PSNPOPO-4900 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 15 15 0% 20-Sep-12 10-Oct-12 14-Mar-14 03-Apr-14 368
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
57 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 138
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
PSNPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 45 45 0% 11-Oct-12 18-Dec-12 04-Apr-14 06-Jun-14 368
PSNPOPO-4870 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (PSN) 90 90 0% 19-Dec-12 29-Apr-13 09-Jun-14 14-Oct-14 368
CBSSTST-3680 ELECTRICAL POWER - SYSTEM TRANSFER CBS 10 10 0% 16-Dec-13 30-Dec-13 08-Jun-15 19-Jun-15 370
CBSSTST-3690 PHONE, SECURITY, FIRE ALARM - SYSTEM TRANSFER CBS 5 5 0% 31-Dec-13 07-Jan-14 22-Jun-15 26-Jun-15 370
CBSSTST-3700 NATURAL GAS - SYSTEM TRANSFER CBS 5 5 0% 08-Jan-14 14-Jan-14 29-Jun-15 06-Jul-15 370
CBSSTST-3710 DEMO EXISTING ROOF TOP DX SYSTEM - SYSTEM TRANSFER CBS 10 10 0% 15-Jan-14 29-Jan-14 07-Jul-15 20-Jul-15 370
CBSTUTU-3870 MAINTAIN TEMPERARY HVAC - TEMP UTILITIES CBS 617 617 0% 31-Aug-11 20-Feb-14 23-Jan-12 10-Aug-15 370
CBSTUTU-3930 DISCONNECT TEMPERARY HVAC - TEMP UTILITIES CBS 15 15 0% 30-Jan-14 20-Feb-14 21-Jul-15 10-Aug-15 370
IBPOPO-5690 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 15 15 0% 26-Jun-12 17-Jul-12 18-Dec-13 09-Jan-14 370
IBPOPO-5670 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 45 45 0% 18-Jul-12 19-Sep-12 10-Jan-14 17-Mar-14 370
IBPOPO-4860 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (IBS/IBN) 90 90 0% 20-Sep-12 01-Feb-13 18-Mar-14 23-Jul-14 370
IFO-5030 COST/RESOURCE LOAD SCHEDULE (GROUP #2) - IFO-1 60 60 0% 03-May-12 01-Jul-12 09-May-... 07-Jul-13 371
ENCPOPO-5479 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 15 15 0% 22-Aug-12 12-Sep-12 24-Feb-14 14-Mar-14 374
ENCPOPO-556 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (ENC) 45 45 0% 13-Sep-12 16-Nov-12 17-Mar-14 16-May-14 374
ENCPOPO-5419 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (ENC) 90 90 0% 19-Nov-12 01-Apr-13 19-May-... 24-Sep-14 374
CLC-5030 VA REVIEWS/COMMENTS ON CONSTRUCTION SCHEDULE (90-days cost only)- CLC 30 30 0% 27-Jun-12 26-Jul-12 08-Jul-13 06-Aug-13 376
CONSLAB-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-B CON 14 14 0% 24-May-13 13-Jun-13 26-Nov-14 15-Dec-14 377
DATPOPO-4970 FABRICATE MEDICAL EQUIPMENT (pharmacy) - IFO-1 (DAT) 140 140 0% 18-Sep-12 11-Apr-13 25-Mar-14 09-Oct-14 377
DATPOPO-4980 MEDICAL EQUIPMENT ARRIVES (pharmacy) - IFO-1 (DAT) 0 0 0% 11-Apr-13 09-Oct-14 377
PSNSWHL-0210 INSTALL UNDERGROUND UTILITIES - SITEWORK PSN 34 34 0% 20-Sep-12 14-Nov-12 19-Jun-14 15-Aug-14 378
PSNSWHL-0215 INSTALL PERIMETER DUCTBANK - SITEWORK PSN 30 30 0% 03-Oct-12 20-Nov-12 02-Jul-14 22-Aug-14 378
CBCSLSL-3200 UNDERSLAB UTILITIES - SERV LVL CBC 15 15 0% 11-Oct-12 05-Nov-12 18-Jul-14 12-Aug-14 381
CONAALR-0750 INSTALL GREEN ROOF SYSTEM - LOW ROOF AR-A CON 12 12 0% 16-May-13 04-Jun-13 20-Feb-15 10-Mar-15 382
CONAALR-0760 INSTALL ROOF ACCCESSORIES - LOW ROOF AR-A CON 10 10 0% 06-Jun-13 21-Jun-13 12-Mar-15 27-Mar-15 382
CBPOPO-4880 KT APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 15 15 0% 29-May-12 18-Jun-12 11-Dec-13 02-Jan-14 385
CBPOPO-4832 VA APPROVE ELEVATOR SHOP DRAWINGS - CS-1/IFO-3 (CBS/CBN) 45 45 0% 19-Jun-12 21-Aug-12 03-Jan-14 10-Mar-14 385
CBPOPO-4860 FAB/DELIVER ELEVATORS - CS-1/IFO-3 (CBS/CBN) 90 90 0% 22-Aug-12 03-Jan-13 11-Mar-14 16-Jul-14 385
CBSTUTU-3910 DISCONNECT TEMPERARY NATURAL GAS - TEMP UTILITIES CBS 5 5 0% 15-Jan-14 22-Jan-14 04-Aug-15 10-Aug-15 390
CBSTUTU-3850 MAINTAIN TEMPERARY NATURAL GAS - TEMP UTILITIES CBS 514 623 0% 20-May-11A
22-Jan-14 20-May-... 10-Aug-15 390
CBCSLSL-3110 SET/BACKFILL DUCTBANKS - SER LVL CBC 5 5 0% 18-Sep-12 27-Sep-12 11-Jul-14 18-Jul-14 391
CBCSLSL-0390 PERIMETER DRAINS/BACKFILL PIERCAPS/GRADE BEAMS - SERV LVL CBC 14 14 0% 27-Sep-12 19-Oct-12 21-Jul-14 12-Aug-14 391
DATPOPO-5110 KT REVIEW/DISTRIBUTE MEDICAL EQUIPMENT(surgery) INFO - IFO-1 (DAT) 15 15 0% 25-Sep-12 16-Oct-12 22-Apr-14 12-May-14 392
DATPOPO-4920 VA APPROVE MEDICAL EQUIPMENT(surgery) - IFO-1 (DAT) 20 20 0% 17-Oct-12 14-Nov-12 13-May-... 10-Jun-14 392
DATPOPO-4930 FABRICATE MEDICAL EQUIPMENT (surgery) - IFO-1 (DAT) 140 140 0% 15-Nov-12 07-Jun-13 11-Jun-14 31-Dec-14 392
DATPOPO-4940 MEDICAL EQUIPMENT ARRIVES (surgery) - IFO-1 (DAT) 0 0 0% 07-Jun-13 31-Dec-14 392
CBSSTST-3640 FIRE SPRINKLER - SYSTEM TRANSFER CBS 5 5 0% 28-Nov-13 04-Dec-13 29-Jun-15 06-Jul-15 397
CBSSTST-3650 WATER - SYSTEM TRANSFER CBS 5 5 0% 05-Dec-13 11-Dec-13 07-Jul-15 13-Jul-15 397
CBSSTST-3660 DOMESTIC HOT WATER - SYSTEM TRANSFER CBS 10 10 0% 12-Dec-13 26-Dec-13 14-Jul-15 27-Jul-15 397
CBSSTST-3670 STEAM - SYSTEM TRANSFER CBS 10 10 0% 27-Dec-13 10-Jan-14 28-Jul-15 10-Aug-15 397
IBPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (IBS/IBN) 55 55 0% 23-Apr-12 10-Jul-12 25-Nov-13 13-Feb-14 398
IBPOPO-5680 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 15 15 0% 05-Mar-12 23-Mar-12 02-Oct-13 23-Oct-13 398
IBPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (IBS/IBN) 20 20 0% 26-Mar-12 20-Apr-12 24-Oct-13 22-Nov-13 398
IFO-5020 COST/RESOURCE LOAD SCHEDULE (GROUP #1) - IFO-1 60 60 0% 05-Apr-12 03-Jun-12 09-May-... 07-Jul-13 399
CBSTUTU-3830 MAINTAIN TEMPERARY BOILER - TEMP UTILITIES CBS 585 585 0% 31-Aug-11 03-Jan-14 23-Jan-12 10-Aug-15 402
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
58 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 139
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBSTUTU-3890 DISCONNECT TEMPERARY BOILER - TEMP UTILITIES CBS 5 5 0% 27-Dec-13 03-Jan-14 04-Aug-15 10-Aug-15 402
IFO-3710 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - IFO-1 60 60 0% 01-Feb-12 31-Mar-12 10-Mar-13 08-May-13 403
CBSTUTU-3840 MAINTAIN TEMPERARY ELECTRICAL / COMMS - TEMP UTILITIES CBS 557 609 0% 01-Jul-11 A 31-Dec-13 01-Jul-11 10-Aug-15 404
CBSTUTU-3900 DISCONNECT TEMPERARY ELECTRICAL / COMMS - TEMP UTILITIES CBS 1 1 0% 31-Dec-13 31-Dec-13 10-Aug-15 10-Aug-15 404
CS1-4950 AWARD ON-SITE UTILITIES CONTRACT 20 20 0% 05-Jan-12 02-Feb-12 14-Aug-13 11-Sep-13 404
UTIPOPO-4870 KT APPROVE ON SITE UTILITIES SHOP DRAWINGS - CS-1/IFO-3 25 25 0% 16-Apr-12 18-May-12 26-Nov-13 31-Dec-13 404
UTIPOPO-556 VA APPROVE ON SITE UTILITIES SHOP DRAWINGS - CS-1/IFO-3 20 20 0% 21-May-12 18-Jun-12 02-Jan-14 30-Jan-14 404
UTIPOPO-4860 FAB/DELIVER ON SITE UTILITY MATERIALS - CS-1/IFO-3 65 65 0% 19-Jun-12 19-Sep-12 31-Jan-14 02-May-14 404
UTIPOPO-4850 PREPARE/SUBMIT ON-SITE UTILITIES SHOP DRAWINGS - CS-1/IFO-3 50 50 0% 03-Feb-12 13-Apr-12 12-Sep-13 25-Nov-13 404
CONSLAA-0910 LAY CMU/INWALL ROUGH - SERV LVL AR-A CON 31 31 0% 15-Mar-13 26-Apr-13 30-Oct-14 15-Dec-14 410
PVNOPO-4850 KT APPROVE ELEC SHOP DRAWINGS - IFO-1 (PVN) 15 15 0% 13-Aug-12 31-Aug-12 14-Apr-14 02-May-14 416
PVNOPO-4820 PREPARE/SUBMIT ELEC SHOP DRAWINGS - IFO-1 (PVN) 50 50 0% 01-Jun-12 10-Aug-12 31-Jan-14 11-Apr-14 416
PVNOPO-4830 VA APPROVE ELEC SHOP DRAWINGS - IFO-1 (PVN) 25 25 0% 04-Sep-12 08-Oct-12 05-May-... 09-Jun-14 416
PVNOPO-4840 FAB/DELIVER ELECTRICAL EQUIPMENT - IFO-1 (PVN) 65 65 0% 09-Oct-12 15-Jan-13 10-Jun-14 10-Sep-14 416
CBSSTST-3720 PATCH ROOF - SYSTEM TRANSFER CBS 5 5 0% 30-Jan-14 05-Feb-14 28-Sep-15 02-Oct-15 418
AAAAPSN-0100 START PSN CONSTRUCTION (start milestone) 0 0 0% 14-Jun-12 09-Aug-13 421
RESPOPO-3720 VA APPROVE CURTAIN WALL SHOPS - CS-1/IFO-3 (RES) 20 20 0% 27-Sep-12 25-Oct-12 10-Jun-14 08-Jul-14 424
ENCSLSH-8880 CLEAN-UP/PRE PUNCH - SERV LVL SHOP ENC 8 8 0% 08-Apr-13 17-Apr-13 19-Dec-14 31-Dec-14 428
P-CD3-4900 KT APPROVE FORCE PROTECTION - CS-1/IFO-3 30 30 0% 05-Mar-12 13-Apr-12 18-Nov-13 31-Dec-13 429
P-CD3-3800 FABRICATE FORCE PROTECTION - CS-1/IFO-3 100 100 0% 14-May-12 03-Oct-12 31-Jan-14 23-Jun-14 429
P-CD3-3810 FORCE PROTECTION MATERIALS ARRIVE - CS-1/IFO-3 0 0 0% 03-Oct-12 23-Jun-14 429
P-CD3-3780 SUBMIT FORCE PROTECTION - CS-1/IFO-3 40 40 0% 05-Jan-12 02-Mar-12 19-Sep-13 15-Nov-13 429
P-CD3-3790 VA PPROVE FORCE PROTECTION - CS-1/IFO-3 20 20 0% 16-Apr-12 11-May-12 02-Jan-14 30-Jan-14 429
RESPOPO-4911 KT REVIEW LAB CASEWORK MOCK-UP - IFO-1 (RES) 20 20 0% 26-Nov-12 21-Dec-12 22-Aug-14 19-Sep-14 438
RESPOPO-4901 KT REVIEW LAB CASEWORK MOCK- UP DESIGN - IFO-1 (RES) 20 20 0% 30-Jul-12 24-Aug-12 30-Apr-14 28-May-14 438
RESPOPO-1052 LAB CASEWORK MOCK- UP MATERIAL PROCURMENT AND FAB - IFO-1 (RES) 40 40 0% 25-Sep-12 21-Nov-12 26-Jun-14 21-Aug-14 438
RESPOPO-4881 VA APPROVE LAB CASEWORK MOCK-UP - IFO-1 (RES) 20 20 0% 24-Dec-12 23-Jan-13 22-Sep-14 17-Oct-14 438
RESPOPO-4891 FABRICATE/DELIVER LAB CASEWORK - IFO-1 (RES) 65 65 0% 24-Jan-13 25-Apr-13 21-Oct-14 26-Jan-15 438
RESPOPO-1500 LAB CASEWORK MOCK-UP SHOP DRAWINGS - IFO-1 (RES) 30 30 0% 15-Jun-12 27-Jul-12 19-Mar-14 29-Apr-14 438
RESPOPO-1501 VA APPROVE LAB CASEWORK MOCK- UP DESIGN - IFO-1 (RES) 20 20 0% 27-Aug-12 24-Sep-12 29-May-... 25-Jun-14 438
AAAACLC-100 START CLC CONSTRUCTION (start milestone) 0 0 0% 22-Aug-12 04-Nov-13 439
ENCL1OF-8880 CLEAN-UP/PRE PUNCH - LVL-1 OFFICES ENC 10 10 0% 20-Mar-13 02-Apr-13 17-Dec-14 31-Dec-14 439
IFO-5031 VA REVIEWS/COMMENTS ON CONSTRUCTION SCHEDULE (90-days cost only)- IFO-1 30 30 0% 01-Apr-12 30-Apr-12 08-Jul-13 06-Aug-13 463
PSNPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 20 20 0% 29-May-12 25-Jun-12 07-Apr-14 02-May-14 464
PVNPOPO-4890 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 15 15 0% 25-Jul-12 14-Aug-12 03-Jun-14 23-Jun-14 464
PVNPOPO-0555 PREPARE/SUBMIT STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 20 20 0% 26-Jun-12 24-Jul-12 05-May-... 02-Jun-14 464
PVNPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PVN) 20 20 0% 15-Aug-12 12-Sep-12 24-Jun-14 22-Jul-14 464
PVNPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (PVN) 55 55 0% 13-Sep-12 04-Dec-12 23-Jul-14 08-Oct-14 464
ENCL1ME-1520 SET/CONNECT AHU - 1 - LVL-1 MECH RMS ENC 25 25 0% 04-Dec-12 09-Jan-13 10-Oct-14 17-Nov-14 466
PSNPOPO-4890 KT APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 15 15 0% 26-Jun-12 17-Jul-12 09-Jun-14 27-Jun-14 488
PSNPOPO-0556 VA APPROVE STAIR SHOP DRAWINGS - CS-1/IFO-3 (PSN) 20 20 0% 18-Jul-12 14-Aug-12 30-Jun-14 28-Jul-14 488
PSNPOPO-0557 FAB/DELIVER STAIRS - CS-1/IFO-3 (PSN) 55 55 0% 15-Aug-12 01-Nov-12 29-Jul-14 14-Oct-14 488
CS1-5040 VA REVIEWS/APPROVES COST/RESOURCE LOADED CONSTRUCTION SCHEDULE- CS-1/IFO-3 30 30 0% 05-Mar-12 03-Apr-12 08-Jul-13 06-Aug-13 490
CS1-5020 COST/RESOURCE LOAD BALANCE OF SCHEDULE - CS-1/IFO-3 60 60 0% 05-Jan-12 04-Mar-12 09-May-... 07-Jul-13 490
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
59 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 140
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
ALLPOPO-4740 KT APPROVE GREEN ROOF MOCK- UP DESIGN - CS-1/IFO-3 15 15 0% 19-Mar-12 06-Apr-12 05-Mar-14 25-Mar-14 491
ALLPOPO-4730 GREEN ROOF MOCK- UP INSTALL AND TEST - CS-1/IFO-3 15 15 0% 03-Jul-12 24-Jul-12 19-Jun-14 10-Jul-14 491
ALLPOPO-3690 GREEN ROOF MOCK-UP SHOP DRAWINGS - CS-1/IFO-3 30 30 0% 03-Feb-12 16-Mar-12 21-Jan-14 04-Mar-14 491
ALLPOPO-3720 GREEN ROOF ARCH APPROVALS - SHOPS - CS-1/IFO-3 14 14 0% 25-Jul-12 13-Aug-12 11-Jul-14 30-Jul-14 491
ALLPOPO-3730 GREEN ROOF MATERIALS PROCUREMENT (dry-in material only) - CS-1/IFO-3 30 30 0% 14-Aug-12 25-Sep-12 31-Jul-14 11-Sep-14 491
ALLPOPO-3760 GREEN ROOF (dry-in material only) 1ST DELIVERY - CS-1/IFO-3 0 0 0% 25-Sep-12 11-Sep-14 491
ALLPOPO-4710 VA APPROVE GREEN ROOF MOCK- UP DESIGN - CS-1/IFO-3 20 20 0% 09-Apr-12 04-May-12 26-Mar-14 22-Apr-14 491
ALLPOPO-4720 GREEN ROOF MOCK- UP MATERIAL PROCURMENT AND FAB - CS-1/IFO-3 40 40 0% 07-May-12 02-Jul-12 23-Apr-14 18-Jun-14 491
19SW-0215 PLACE EROSION PROTECTION/TRAFFIC CONTROL - 19TH PLACE 4 4 0% 01-May-12 07-May-12 14-Aug-14 19-Aug-14 491
19SW-0218 DEMO/GRADING - 19TH PLACE 12 12 0% 08-May-12 29-May-12 21-Aug-14 09-Sep-14 491
19SW-0220 INSTALL UTILITIES - 19TH PLACE 15 15 0% 30-May-12 22-Jun-12 11-Sep-14 03-Oct-14 491
19SW-0228 CONSTRUCT ROADWAY - 19TH PLACE 15 15 0% 25-Jun-12 19-Jul-12 06-Oct-14 28-Oct-14 491
CS1-3710 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - CS-1/IFO-3 60 60 0% 27-Oct-11 25-Dec-11 10-Mar-13 08-May-13 500
ENCL1EL-0920 HANG/TAPE/FINISH DRYWALL - LVL-1 ELEC RMS ENC 15 15 0% 11-Dec-12 02-Jan-13 10-Dec-14 31-Dec-14 501
STR2-5040 VA REVIEWS/APPROVES COST/RESOURCE LOADED CONSTRUCTION SCHEDULE- STR-2 30 30 0% 05-Jan-12 03-Feb-12 08-Jul-13 06-Aug-13 550
STR2-3710 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - STR-2 60 60 0% 07-Sep-11 05-Nov-11 10-Mar-13 08-May-13 550
STR2-5020 COST/RESOURCE LOAD BALANCE OF SCHEDULE - STR-2 60 60 0% 06-Nov-11 04-Jan-12 09-May-... 07-Jul-13 550
CS1-5030 VA REVIEWS/COMMENTS ON CONSTRUCTION SCHEDULE (90-days cost only)- CS-1/IFO-3 30 30 0% 26-Dec-11 24-Jan-12 08-Jul-13 06-Aug-13 560
STR2-5030 VA REVIEWS/COMMENTS ON CONSTRUCTION SCHEDULE (90-days cost only)- STR-2 30 30 0% 06-Nov-11 05-Dec-11 08-Jul-13 06-Aug-13 610
OSI-4450 PREPARE/SUBMIT SHOP DRAWINGS - OSI-1 20 20 0% 17-Oct-11 14-Nov-11 31-Mar-14 25-Apr-14 612
OSI-4460 VA SUBMITTAL REVIEW - OSI-1 20 20 0% 01-Dec-11 29-Dec-11 12-May-... 09-Jun-14 612
OSI-4470 MATERIAL PROCUREMENT - OSI-1 15 15 0% 30-Dec-11 23-Jan-12 10-Jun-14 30-Jun-14 612
OSI-4480 MATERIALS ARRIVE - OSI-1 0 0 0% 23-Jan-12 30-Jun-14 612
OSI-4880 KT REVIEWS SHOP DRAWINGS - OSI-1 10 10 0% 15-Nov-11 30-Nov-11 28-Apr-14 09-May-14 612
OSI-4810 CITY OF AURORA PLAN REVIEW AND APPROVAL - OSI-1 129 84 34.88% 10-Feb-11 A 23-Nov-11 11-Feb-14 09-Jun-14 635
CBSADAL-3600 NEW ELEVATOR - ALL LVLS ADD CBS 15 15 0% 04-Jan-13 25-Jan-13 14-Sep-15 02-Oct-15 676
CBSESES-3590 CANOPY GLAZING - SKINS CBS 10 10 0% 05-Jun-12 18-Jun-12 31-Jul-15 13-Aug-15 791
P-CD3-4750 PAINT/FINISH/GLASS SAMPLES - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 30 30 0% 05-Jan-12 17-Feb-12 04-Mar-15 14-Apr-15 791
P-CD3-4760 KT APPROVE CURTAINWALL SHOP DRAWINGS - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 10 10 0% 20-Feb-12 02-Mar-12 15-Apr-15 28-Apr-15 791
P-CD3-4810 EXTRUDE CURTAINWALL MULLIONS - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 30 30 0% 19-Mar-12 27-Apr-12 13-May-... 24-Jun-15 791
P-CD3-4820 CURTAINWALL SHOP ASSEMBLY - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 25 25 0% 30-Apr-12 04-Jun-12 25-Jun-15 30-Jul-15 791
P-CD3-4840 DELIVER CURTAINWALL - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 0 0 0% 04-Jun-12 30-Jul-15 791
P-CD3-4850 VA/JVT APPROVE CURTAINWALL SHOP DRAWINGS - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 20 20 0% 20-Feb-12 16-Mar-12 15-Apr-15 12-May-15 791
P-CD3-4860 DETAIL CBS CURTAINWALL SHOP DRAWINGS - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 30 30 0% 05-Jan-12 17-Feb-12 04-Mar-15 14-Apr-15 791
P-CD3-4870 VA/JVT APPROVE PAINT/FINISH/GLASS SAMPLES - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 20 20 0% 20-Feb-12 16-Mar-12 02-Jul-15 30-Jul-15 846
CBSDEES-2440 SKIN PENETRATIONS FOR TRELLIS ATTACHMENT - EXT DEMO CBS 10 10 0% 26-Jul-11 08-Aug-11 01-Jul-15 17-Jul-15 849
P-CD3-4740 AWARD CURTAINWALL - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 20 20 0% 07-Sep-11 04-Oct-11 03-Feb-15 03-Mar-15 851
CBSESES-4130 REMOVE TEMP BUILDING ENCLOSURE - SKINS CBS 10 10 0% 06-Jan-12 20-Jan-12 17-Jul-15 30-Jul-15 885
CBSRLRL-3550 CANOPY ROOFING - ROOF CBS 5 5 0% 24-Aug-11 30-Aug-11 24-Jul-15 30-Jul-15 980
CBSSTST-2380 CANOPY FRAMING - STRUCTURE CBS 5 5 0% 18-Aug-11 23-Aug-11 18-Jul-15 23-Jul-15 1189
CBSSTST-2330 CANOPY FOUNDATION - STRUCTURE CBS 15 15 0% 01-Aug-11 17-Aug-11 30-Jun-15 17-Jul-15 1189
CBSSWSW-3770 TRASH ENCLOSURE DEMO - SITEWORK CBS 10 0 100% 01-Jul-11 A 15-Jul-11 A 28-Jul-11 28-Jul-11
CBSSWSW-4190 RELOCATE EXISTING XCEL TRANSFORMER - SITEWORK CBS 10 0 100% 27-Jun-11 A 01-Jul-11 A 28-Jul-11 28-Jul-11
CBSSWSW-4200 NATURAL GAS SITE UTILITY - SITEWORK CBS 7 0 100% 06-May-11A
13-May-11A
28-Jul-11 28-Jul-11
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
60 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 141
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
CBSSWSW-2270 SITE ELECTRICAL DEMO - SITEWORK CBS 10 0 100% 09-May-11A
20-May-11A
28-Jul-11 28-Jul-11
CBSSWSW-2280 RELOCATE SERVICE ENTRANCE TO SOUTH - SITEWORK CBS 75 0 100% 16-May-11A
20-May-11A
31-Dec-11 31-Dec-11
CBSPCPC-2000 INSTALL TEMP. BUILDING PROTECTION - PRECON INSP CBS 5 0 100% 13-May-11A
20-May-11A
27-Jul-11 27-Jul-11
CBSPCPC-2170 SECURE SITE - PRECON INSP CBS 4 0 100% 11-Apr-11 A 29-Apr-11 A 27-Jul-11 27-Jul-11
CBSPCPC-3740 BUILDING SURVEY - PRECON INSP CBS 6 0 100% 29-Apr-11 A 06-May-11A
27-Jul-11 27-Jul-11
CBSPCPC-4070 ELECTRICAL BUILDING SAFE-OFF - PRECON INSP CBS 10 0 100% 02-May-11A
13-May-11A
27-Jul-11 27-Jul-11
CBSPCPC-4150 MOBILIZE CONSTRUCTION RESOURCES - PRECON INSP CBS 5 0 100% 11-Apr-11 A 29-Apr-11 A 27-Jul-11 27-Jul-11
CBSDEES-2420 FRONT CANOPY DEMO - EXT DEMO CBS 10 0 100% 20-Jun-11 A 01-Jul-11 A 05-Aug-11 05-Aug-11
CBSDEES-2430 EAST SKIN DEMO - EXT DEMO CBS 15 0 100% 27-Jun-11 A 19-Jul-11 A 28-Jul-11 28-Jul-11
CBSDEES-4120 INSTALL TEMP BUILDING ENCLOSURE - EXT DEMO CBS 15 0 100% 06-Jun-11 A 10-Jun-11 A 05-Aug-11 05-Aug-11
CBSDEIN-2450 LEVEL 4 DEMOLITION - INT DEMO CBS 10 0 100% 19-May-11A
22-Jun-11 A 05-Aug-11 05-Aug-11
CBSDEIN-2460 LEVEL 3 DEMOLITION - INT DEMO CBS 10 0 100% 26-May-11A
24-Jun-11 A 05-Aug-11 05-Aug-11
CBSDEIN-2480 LEVEL 1 DEMOLITION - INT DEMO CBS 15 0 100% 15-Jun-11 A 11-Jul-11 A 27-Jul-11 27-Jul-11
CBSDEIN-4080 LEVEL 4 SALVAGE - INT DEMO CBS 5 0 100% 19-May-11A
01-Jul-11 A 27-Jul-11 27-Jul-11
CBSDEIN-4090 LEVEL 3 SALVAGE - INT DEMO CBS 5 0 100% 26-May-11A
02-Jun-11 A 27-Jul-11 27-Jul-11
CBSDEIN-4110 LEVEL 1 SALVAGE - INT DEMO CBS 5 0 100% 15-Jun-11 A 11-Jul-11 A 27-Jul-11 27-Jul-11
CBSMIMI-4210 REQUEST FOR NATURAL GAS RELOCATION AND WORK - CBS MILESTONE 22 0 100% 29-Apr-11 A 06-May-11A
28-Jul-11 28-Jul-11
P-RF3-4820 VA APPROVES FIRM FIXED PRICE 100% AND ISSUES MOD - RFP-3 0 0 100% 25-Mar-11 A 07-Dec-12
P-CBS-4030 VA AUTHORIZES JVT TO PROCEED WITH 100% CD DOCS - CBS-1 0 0 100% 15-Jul-11 A 19-Jan-12
P-CBS-4760 VA APPROVES FIRM FIXED PRICE 95% AND ISSUES MOD - CBS-1 0 0 100% 06-May-11A
03-Aug-11
P-CBS-3940 VA APPROVES FIRM FIXED PRICE 100% AND ISSUES MOD - CBS DEMO 0 0 100% 08-Apr-11 A 08-Feb-12
P-CBS-4740 VA APPROVES FIRM FIXED PRICE 95% AND ISSUES MOD - CBS DEMO 0 0 100% 25-Mar-11 A 27-Jul-11
P-CD1-3250 VA AUTHORIZES JVT TO PROCEED WITH 100% CD DOCS - STR-1 0 0 100% 12-Apr-11 A 14-Sep-11
AAAACBS-0100 START CBS CONSTRUCTION (start milestone) 0 0 100% 09-May-11A
28-Jul-11
AAAA-1020 DESIGN KICKOFF 0 0 100% 01-Nov-10A
27-Jul-11
P-CBS-3020 SHORING PROCUREMENT - CBS DEMO 59 0 100% 28-Mar-11 A 31-May-11A
03-Aug-11 03-Aug-11
P-CBS-3950 PROCUREMENT - CBS DEMO 20 0 100% 28-Mar-11 A 20-Apr-11 A 28-Jul-11 28-Jul-11
P-CBS-4520 START PROCUREMENT - CBS DEMO 0 0 100% 28-Mar-11 A 28-Jul-11
P-CBS-4800 SKIN DEMOLITION ENGINEERING DESIGN - CBS DEMO 15 0 100% 20-Apr-11 A 06-May-11A
28-Jul-11 28-Jul-11
P-CBS-4810 SKIN DEMOLITION ENGINEERING APPROVAL - CBS DEMO 10 0 100% 06-May-11A
17-Jun-11 A 28-Jul-11 28-Jul-11
P-CBS-4500 VA REVIEWS FIRM FIXED PRICE 95% AND ISSUES - CBS DEMO 30 0 100% 14-Feb-11 A 25-Mar-11 A 27-Jul-11 27-Jul-11
P-CBS-3880 JVT DESIGNS 100% CD DOCUMENTS - CBS DEMO 10 0 100% 28-Feb-11 A 11-Mar-11 A 08-Feb-12 08-Feb-12
P-CBS-3890 WK 6-7: BACK CHECK OF JVT'S RESPONSES IN 100% CD DR CHECK - CBS DEMO 10 0 100% 28-Feb-11 A 11-Mar-11 A 08-Feb-12 08-Feb-12
P-CBS-3900 100% CD DESIGN COMPLETION - CBS DEMO 0 0 100% 28-Mar-11 A 08-Feb-12
P-CBS-3910 100% CD DESIGN PACKAGE PROVIDED TO KT - CBS DEMO 0 0 100% 28-Mar-11 A 08-Feb-12
P-CBS-3920 KT PROVIDES FIRM FIXED PRICE 100% TO VA - CBS DEMO 25 0 100% 28-Mar-11 A 31-Mar-11 A 08-Feb-12 08-Feb-12
P-CBS-3930 VA REVIEWS FIRM FIXED PRICE 100% - CBS DEMO 15 0 100% 31-Mar-11 A 08-Apr-11 A 08-Feb-12 08-Feb-12
P-CD1-4020 JVT RESPONDS TO CFM'S COMMENTS 100% CD - CBS DEMO 5 0 100% 07-Mar-11 A 11-Mar-11 A 08-Feb-12 08-Feb-12
P-CD1-4030 CFM BACK CHECK OF JVT RESPONSE IN 100 % CD DR CHECKS - CBS DEMO 10 0 100% 14-Mar-11 A 25-Mar-11 A 08-Feb-12 08-Feb-12
P-CD1-4010 CFM ENTERS COMMENTS IN 100% CD DR CHECKS - CBS DEMO 5 0 100% 28-Feb-11 A 04-Mar-11 A 08-Feb-12 08-Feb-12
P-CD1-3280 JVT DESIGNS 100% CD DOCUMENTS - STR-1 15 0 100% 12-Apr-11 A 12-Apr-11 A 14-Sep-11 14-Sep-11
P-CD1-3290 100% CD DESIGN COMPLETION - STR-1 0 0 100% 15-Jul-11 A 14-Sep-11
P-CD1-3300 100% CD DESIGN PACKAGE PROVIDED TO KT - STR-1 0 0 100% 15-Jul-11 A 14-Sep-11
P-CD1-3360 WK 6-7: BACK CHECK OF JVT'S RESPONSES IN 100% CD DR CHECK - STR-1 10 0 100% 12-Apr-11 A 12-Apr-11 A 14-Sep-11 14-Sep-11
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
61 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 142
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
P-CD1-3630 CFM ENTERS COMMENTS IN 100% CD DR CHECKS - STR-1 5 0 100% 12-Apr-11 A 18-Apr-11 A 14-Sep-11 14-Sep-11
P-CD1-3640 JVT RESPONDS TO CFM'S COMMENTS 100% CD - STR-1 5 0 100% 19-Apr-11 A 26-Apr-11 A 14-Sep-11 14-Sep-11
P-CD1-3650 CFM BACK CHECK OF JVT RESPONSE IN 100% CD DR CHECKS - STR-1 10 0 100% 26-Apr-11 A 14-Jul-11 A 14-Sep-11 14-Sep-11
P-CD1-3105 DESIGN 95% CDS - STR-1 85 0 100% 01-Nov-10A
04-Mar-11 A 06-Sep-11 06-Sep-11
P-CD1-3110 DESIGN COMPLETION 95% CDS - STR-1 0 0 100% 11-Mar-11 A 06-Sep-11
P-CD1-3130 95% CD DESIGN PACKAGE PROVIDED TO KT - STR-1 1 0 100% 11-Mar-11 A 11-Mar-11 A 06-Sep-11 06-Sep-11
P-CD1-3160 WK 1-3: KT PROVIDES 95% CD DESIGN REVIEW REPORT TO VA - STR-1 15 0 100% 08-Mar-11 A 28-Mar-11 A 14-Sep-11 14-Sep-11
P-CD1-3170 WK 1-3: ENTER COMMENTS INTO 95% CD DR CHECKS - STR-1 15 0 100% 08-Mar-11 A 28-Mar-11 A 14-Sep-11 14-Sep-11
P-CD1-3180 WK 4: PROJECT TEAM REVIEWS 95% CD DR CHECKS COMMENTS - STR-1 5 0 100% 29-Mar-11 A 29-Mar-11 A 14-Sep-11 14-Sep-11
P-CD1-3340 WK 4: PROJECT TEAM RECONCILES 95% CD COST ESTIMATE - STR-1 15 0 100% 31-Mar-11 A 15-Apr-11 A 14-Sep-11 14-Sep-11
P-CD1-3350 WK 5: JVT RESPONDS TO 95% CD DR CHECKS COMMENTS - STR-1 5 0 100% 04-Apr-11 A 11-Apr-11 A 14-Sep-11 14-Sep-11
P-CD1-3410 VA PROVIDES JVT'S 95% CD COST ESTIMATE TO KT - STR-1 1 0 100% 28-Mar-11 A 28-Mar-11 A 14-Sep-11 14-Sep-11
P-CD1-3610 VA DIRECTOR'S BRIEFING 95% CD - STR-1 3 0 100% 04-Apr-11 A 07-Apr-11 A 14-Sep-11 14-Sep-11
P-CD1-3620 VACO CO APPROVAL 95% CD - STR-1 2 0 100% 08-Apr-11 A 11-Apr-11 A 14-Sep-11 14-Sep-11
P-CD1-4570 KT PROVIDES FIRM FIXED PRICE 95% CDTO VA - STR-1 15 0 100% 14-Mar-11 A 31-Mar-11 A 06-Sep-11 06-Sep-11
P-CD2-3135 95% CD DESIGN - STR-2 147 0 100% 01-Nov-10A
07-Jul-11 A 01-Sep-11 01-Sep-11
P-CD2-3180 95% CD DESIGN COMPLETE - STR-2 0 0 100% 07-Jul-11 A 01-Sep-11
P-CD2-3390 95% CD DESIGN PACKAGE PROVIDED TO KT - STR-2 1 0 100% 07-Jul-11 A 07-Jul-11 A 01-Sep-11 01-Sep-11
STR23-3030 DESIGN COMMENCE - STR-2 0 0 100% 15-Apr-11 A 01-Sep-11
STR23040 95% DESIGN - STR-2 78 0 100% 18-Apr-11 A 08-Jul-11 A 01-Sep-11 01-Sep-11
STR2-3510 95% CD DESIGN COMPLETE - STR-2 0 0 100% 07-Jul-11 A 01-Sep-11
C-S&U-1060 SECURE SITE 15 0 100% 16-May-11A
27-May-11A
17-Jan-13 17-Jan-13
P-CD3-3030 DESIGN COMMENCE - CS-1/IFO-3 0 0 100% 15-Apr-11 A 17-Aug-11
P-CD1-3720 VACO CO APPROVAL DD2 - CS-1/IFO-3 5 0 100% 11-Apr-11 A 15-Apr-11 A 17-Aug-11 17-Aug-11
P-CD1-3730 CFM ENTERS COMMENTS IN DD2 DR CHECKS - CS-1/IFO-3 5 0 100% 18-Apr-11 A 22-Apr-11 A 21-Sep-11 21-Sep-11
P-CD1-3740 JVT RESPONDS TO CFM'S COMMENTS DD2 - CS-1/IFO-3 5 0 100% 25-Apr-11 A 29-Apr-11 A 21-Sep-11 21-Sep-11
P-CD1-3750 CFM BACK CHECK OF JVT RESPONSE IN DD2 DR CHECKS - CS-1/IFO-3 10 0 100% 02-May-11A
13-May-11A
21-Sep-11 21-Sep-11
P-CD3-3120 DD2 DESIGN COMPLETE - CS-1/IFO-3 0 0 100% 14-Mar-11 A 17-Aug-11
P-CD3-3130 DD2 DESIGN - CS-1/IFO-3 90 0 100% 01-Nov-10A
11-Mar-11 A 17-Aug-11 17-Aug-11
P-CD3-3140 DD2 DESIGN PACKAGE PROVIDED TO KT - CS-1/IFO-3 0 0 100% 14-Mar-11 A 17-Aug-11
P-CD3-3150 WK 1-3: ENTER COMMENTS INTO DD2 DR CHECKS - CS-1/IFO-3 15 0 100% 14-Mar-11 A 01-Apr-11 A 17-Aug-11 17-Aug-11
P-CD3-3190 WK 4: PROJECT TEAM REVIEWS DD2 DR CHECKS COMMENTS - CS-1/IFO-3 5 0 100% 30-Mar-11 A 08-Apr-11 A 17-Aug-11 17-Aug-11
P-CD3-3200 WK 5: JVT RESPONDS TO DD2 DR CHECKS COMMENTS - CS-1/IFO-3 5 0 100% 11-Apr-11 A 15-Apr-11 A 17-Aug-11 17-Aug-11
P-CD3-3210 WK 6-7: BACK CHECK OF JVT'S RESPONSES IN DD2 DR CHECK - CS-1/IFO-3 10 0 100% 18-Apr-11 A 29-Apr-11 A 21-Sep-11 21-Sep-11
P-CD3-3230 WK 1-3: KT PROVIDES DD2 DESIGN REVIEW REPORT TO VA - CS-1/IFO-3 27 0 100% 14-Mar-11 A 18-Apr-11 A 21-Sep-11 21-Sep-11
P-CD3-3240 WK 4: PROJECT TEAM RECONCILES DD2 COST ESTIMATE - CS-1/IFO-3 2 0 100% 04-Apr-11 A 05-Apr-11 A 17-Aug-11 17-Aug-11
P-CD3-3250 WK 5: VA AUTHORIZES JVT TO PROCEED WITH CD'S - CS-1/IFO-3 0 0 100% 18-Apr-11 A 17-Aug-11
P-CD1-3490 VA PROVIDES JVT'S DD2 COST ESTIMATE TO KT - CS-1/IFO-3 1 0 100% 14-Mar-11 A 14-Mar-11 A 17-Aug-11 17-Aug-11
P-CD1-3710 VA DIRECTOR'S BRIEFING DD2 - CS-1/IFO-3 5 0 100% 04-Apr-11 A 08-Apr-11 A 17-Aug-11 17-Aug-11
P-OFS-4380 100% CD DESIGN COMPLETION - OFS-1 0 0 100% 18-Apr-11 A 04-Apr-12
P-OFS-4390 DESIGN PACKAGE PROVIDED TO KT - OFS-1 0 0 100% 18-Apr-11 A 04-Apr-12
P-OFS-4360 JVT DESIGNS 100% CD DOCUMENTS - OFS-1 10 0 100% 04-Apr-11 A 18-Apr-11 A 04-Apr-12 04-Apr-12
P-CD4-3390 WK 4: PROJECT TEAM REVIEWS DD2 DR CHECKS COMMENTS - IFO-1 5 0 100% 04-Apr-11 A 06-Apr-11 A 01-Sep-11 01-Sep-11
P-CD4-3140 DD2 DESIGN PACKAGE PROVIDED TO KT - IFO-1 0 0 100% 14-Mar-11 A 01-Sep-11
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
62 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 143
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
P-CD4-3160 WK 1-3: ENTER COMMENTS INTO DD2 DR CHECKS - IFO-1 15 0 100% 14-Mar-11 A 01-Apr-11 A 01-Sep-11 01-Sep-11
P-CD4-3170 DD2 DESIGN - IFO-1 DD2 70 0 100% 02-Dec-10A
11-Mar-11 A 01-Sep-11 01-Sep-11
P-CD4-3180 DD2 DESIGN COMPLETE - IFO-1 0 0 100% 14-Mar-11 A 01-Sep-11
P-CD4-3200 WK 5: JVT RESPONDS TO DD2 DR CHECKS COMMENTS - IFO-1 5 0 100% 11-Apr-11 A 15-Apr-11 A 01-Sep-11 01-Sep-11
P-CD4-3210 WK 6-7: BACK CHECK OF JVT'S RESPONSES IN DD2 DR CHECK - IFO-1 10 0 100% 18-Apr-11 A 29-Apr-11 A 01-Sep-11 01-Sep-11
P-CD4-3230 WK 1-3: KT PROVIDES DD2 DESIGN REVIEW REPORT TO VA - IFO-1 27 0 100% 14-Mar-11 A 15-Apr-11 A 30-Dec-11 30-Dec-11
P-CD4-3240 WK 4: PROJECT TEAM RECONCILES DD2 COST ESTIMATE - IFO-1 2 0 100% 06-Apr-11 A 07-Apr-11 A 01-Sep-11 01-Sep-11
P-CD4-3250 WK 5: VA AUTHORIZES JVT TO PROCEED WITH CD'S - IFO-1 0 0 100% 15-Apr-11 A 01-Sep-11
P-CD1-3860 CFM ENTERS COMMENTS IN DD2 DR CHECKS - IFO-1 5 0 100% 18-Apr-11 A 22-Apr-11 A 30-Dec-11 30-Dec-11
P-CD1-3870 JVT RESPONDS TO CFM'S COMMENTS DD2 - IFO-1 5 0 100% 25-Apr-11 A 29-Apr-11 A 30-Dec-11 30-Dec-11
P-CD1-3880 CFM BACK CHECK OF JVT RESPONSE IN DD2 DR CHECKS - IFO-1 10 0 100% 02-May-11A
13-May-11A
30-Dec-11 30-Dec-11
P-CD1-3920 VA DIRECTOR'S BRIEFING DD2 - IFO-1 5 0 100% 04-Apr-11 A 06-Apr-11 A 01-Sep-11 01-Sep-11
P-CD1-3930 VACO CO APPROVAL DD2 - IFO-1 5 0 100% 11-Apr-11 A 15-Apr-11 A 01-Sep-11 01-Sep-11
P-CD4-3490 VA PROVIDES JVT'S DD2 COST ESTIMATE TO KT - IFO-1 1 0 100% 14-Mar-11 A 14-Mar-11 A 01-Sep-11 01-Sep-11
P-CD4-3100 95% CD DESIGN COMMENCE - IFO-1 0 0 100% 18-Apr-11 A 30-Dec-11
P-RF3-4870 COMPLETION - RFP 3 0 0 100% 28-Mar-11 A 07-Dec-12
P-RF3-4980 START PROCUREMENT - RFP 3 0 0 100% 28-Mar-11 A 07-Dec-12
P-RF3-4990 PROCUREMENT - FENCE - RFP 3 10 0 100% 28-Mar-11 A 08-Apr-11 A 17-Jan-13 17-Jan-13
P-RF3-5000 PROCUREMENT - DEMO AND ABATEMENT SUB - RFP 3 20 0 100% 28-Mar-11 A 11-Jul-11 A 07-Dec-12 07-Dec-12
C-RF3-1406 UTILITY LOCATES/POT HOLING - RFP 3 15 0 100% 04-Apr-11 A 15-Apr-11 A 07-Dec-12 07-Dec-12
C-RF3-1407 DEVELOP ABATEMENT PLAN - RFP 3 20 0 100% 01-Jul-11 A 12-Jul-11 A 07-Dec-12 07-Dec-12
C-RF3-1410 AURORA/XCEL UTILITY DISCONNECT AGREEMENTS - RFP 3 10 0 100% 26-Apr-11 A 26-Apr-11 A 08-Feb-13 08-Feb-13
P-CD1-4070 VACO CO APPROVAL 95% CD - CBS-1 5 0 100% 05-Apr-11 A 15-Jul-11 A 19-Jan-12 19-Jan-12
P-CBS-3125 95% CD DESIGN - CBS-1 75 0 100% 15-Nov-10A
04-Mar-11 A 03-Aug-11 03-Aug-11
P-CBS-3960 DESIGN COMPLETE 95% CD - CBS-1 0 0 100% 07-Mar-11 A 03-Aug-11
P-CBS-3970 WK 1-3: ENTER COMMENTS INTO 95% CD DR CHECKS - CBS-1 15 0 100% 08-Mar-11 A 28-Mar-11 A 19-Jan-12 19-Jan-12
P-CBS-3980 WK 1-3: KT PROVIDES 95% CD DESIGN REVIEW REPORT TO VA - CBS-1 15 0 100% 08-Mar-11 A 28-Mar-11 A 19-Jan-12 19-Jan-12
P-CBS-3990 95% CD DESIGN PACKAGE PROVIDED TO KT - CBS-1 1 0 100% 07-Mar-11 A 07-Mar-11 A 03-Aug-11 03-Aug-11
P-CBS-4000 WK 4: PROJECT TEAM REVIEWS 95% CD DR CHECKS COMMENTS - CBS-1 5 0 100% 21-Mar-11 A 28-Mar-11 A 19-Jan-12 19-Jan-12
P-CBS-4010 WK 4: PROJECT TEAM RECONCILES 95% CD COST ESTIMATE - CBS-1 2 0 100% 29-Mar-11 A 30-Mar-11 A 03-Aug-11 03-Aug-11
P-CBS-4020 WK 5: JVT RESPONDS TO 95% CD DR CHECKS COMMENTS - CBS-1 5 0 100% 28-Mar-11 A 31-Mar-11 A 19-Jan-12 19-Jan-12
P-CBS-4530 KT PROVIDES FIRM FIXED PRICE 95% CD TO VA - CBS-1 15 0 100% 08-Mar-11 A 28-Mar-11 A 03-Aug-11 03-Aug-11
P-CBS-4600 VA REVIEWS FIRM FIXED PRICE AND ISSUES MOD 95% CD - CBS-1 30 0 100% 29-Mar-11 A 06-May-11A
03-Aug-11 03-Aug-11
P-CD1-3520 VA PROVIDES JVT'S 95% CD COST ESTIMATE TO KT - CBS-1 1 0 100% 28-Mar-11 A 28-Mar-11 A 19-Jan-12 19-Jan-12
P-CD1-4060 VA DIRECTOR'S BRIEFING 95% CD - CBS-1 5 0 100% 29-Mar-11 A 04-Apr-11 A 19-Jan-12 19-Jan-12
P-CBS-4050 WK 6-7: BACK CHECK OF JVT'S RESPONSES IN 100 % CD DR CHECK - CBS-1 10 0 100% 18-Apr-11 A 14-Jul-11 A 19-Jan-12 19-Jan-12
P-CBS-4060 100% CD DESIGN COMPLETION - CBS-1 0 0 100% 18-Jul-11 A 19-Jan-12
P-CBS-4070 100% CD DESIGN PACKAGE PROVIDED TO KT - CBS-1 0 0 100% 18-Jul-11 A 19-Jan-12
P-CBS-4080 KT PROVIDES FIRM FIXED PRICE 100% CD TO VA - CBS-1 25 0 100% 31-Mar-11 A 22-Apr-11 A 19-Jan-12 19-Jan-12
P-CD1-4080 CFM ENTERS COMMENTS IN 100% CD DR CHECKS - CBS-1 5 0 100% 04-Apr-11 A 08-Apr-11 A 19-Jan-12 19-Jan-12
P-CD1-4090 JVT RESPONDS TO CFM'S COMMENTS 100% CD - CBS-1 5 0 100% 11-Apr-11 A 18-Apr-11 A 19-Jan-12 19-Jan-12
P-CD1-4100 CFM BACK CHECK OF JVT RESPONSE IN 100 % CD DR CHECKS - CBS-1 10 0 100% 18-Apr-11 A 18-Jul-11 A 19-Jan-12 19-Jan-12
P-CBS-4040 JVT DESIGNS 100% CD DOCUMENTS - CBS-1 10 0 100% 08-Apr-11 A 15-Jul-11 A 19-Jan-12 19-Jan-12
P-CBS-4560 START PROCUREMENT - CBS-1 0 0 100% 09-May-11A
03-Aug-11
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
63 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 144
Activity ID Activity Name Orig Dur Rem Dur %Complete
Start Finish Late Start Late Finish Total Float
P-CBS-4210 AWARD CONTRACT (mechanical) - CBS-1 5 0 100% 16-May-11A
11-Jul-11 A 19-Aug-11 19-Aug-11
P-CBS-4470 SUBMITTAL DEVELOPMENT INITIAL MATERIAL (mechanical) - CBS-1 10 0 100% 12-Jul-11 A 25-Jul-11 A 08-Sep-11 08-Sep-11
P-CBS-4430 SUBMITTAL DEVELOPMENT (interior steel) - CBS-1 20 0 100% 24-Jun-11 A 24-Jun-11 A 03-Aug-11 03-Aug-11
P-CBS-4730 AWARD CONTRACT (interior steel) - CBS-1 5 0 100% 23-May-11A
24-Jun-11 A 03-Aug-11 03-Aug-11
P-CBS-4360 AWARD CONTRACT (structural steel) - CBS-1 5 0 100% 16-May-11A
20-May-11A
19-Aug-11 19-Aug-11
P-CBS-4260 AWARD CONTRACT (electrical) - CBS-1 5 0 100% 16-May-11A
27-May-11A
19-Aug-11 19-Aug-11
P-CD1-4640 WK 1-3: ENTER COMMENTS INTO 95% CD DR CHECKS - STR-1A/IFO-2 15 0 100% 26-Apr-11 A 16-May-11A
06-Sep-11 06-Sep-11
P-CD1-4650 WK 4: PROJECT TEAM REVIEWS 95% CD DR CHECKS COMMENTS - STR-1A/IFO-2 5 0 100% 17-May-11A
23-May-11A
06-Sep-11 06-Sep-11
P-CD1-4660 95% CD DESIGN - STR-1A/IFO-2 73 0 100% 12-Jan-11 A 22-Apr-11 A 06-Sep-11 06-Sep-11
P-CD1-4670 95% CD DESIGN PACKAGE PROVIDED TO KT - STR-1A/IFO-2 1 0 100% 25-Apr-11 A 25-Apr-11 A 06-Sep-11 06-Sep-11
P-CD1-4740 WK 5: JVT RESPONDS TO 95% CD DR CHECKS COMMENTS - STR-1A/IFO-2 5 0 100% 24-May-11A
31-May-11A
06-Sep-11 06-Sep-11
P-CD1-4760 VA PROVIDES JVT'S 95% CD COST ESTIMATE TO KT - STR-1A/IFO-2 1 0 100% 16-May-11A
16-May-11A
06-Sep-11 06-Sep-11
P-CD1-4770 VA DIRECTOR'S BRIEFING 95% CD- STR-1A/IFO-2 3 0 100% 24-May-11A
26-May-11A
06-Sep-11 06-Sep-11
P-CD1-4820 WK 1-3: KT PROVIDES DESIGN REVEIW REPORT TO VA 95% CD - STR-1A/IFO-2 15 0 100% 26-Apr-11 A 16-May-11A
06-Sep-11 06-Sep-11
P-CD1-4830 DESIGN COMPLETION 95% CD - STR-1A/IFO-2 0 0 100% 22-Apr-11 A 06-Sep-11
P-CD1-4850 KT PROVIDES FIRM FIXED PRICE 95% CD TO VA - STR-1A/IFO-2 21 0 100% 26-Apr-11 A 24-May-11A
06-Sep-11 06-Sep-11
P-CD1-5460 PACKAGE RECONCILIATION 95% CDS - STR-1A/IFO-2 15 0 100% 25-May-11A
15-Jun-11 A 06-Sep-11 06-Sep-11
P-CD1-4790 CFM ENTERS COMMENTS IN 100% CD DR CHECKS- STR-1A/IFO-2 5 0 100% 01-Jun-11 A 07-Jun-11 A 06-Sep-11 06-Sep-11
P-CD1-4800 JVT RESPONDS TO CFM'S COMMENTS 100% CD - STR-1A/IFO-2 5 0 100% 08-Jun-11 A 14-Jun-11 A 06-Sep-11 06-Sep-11
P-CD1-4810 CFM BACK CHECK OF JVT RESPONSE IN 100% CD DR CHECKS- STR-1A/IFO-2 10 0 100% 15-Jun-11 A 28-Jun-11 A 06-Sep-11 06-Sep-11
W-OFS-5280 BID WATERLINE PACKAGE -WHEELING WATERLINE 11 0 100% 18-Apr-11 A 02-May-11A
13-Sep-11 13-Sep-11
W-OFS-5290 KT RECEIVE & REVIEW BIDS - WHEELING WATERLINE 47 0 100% 02-May-11A
16-May-11A
13-Sep-11 13-Sep-11
W-OFS-5300 VA APPROVE SUBCONTRACTOR SELECTION - WHEELING WATERLINE 30 0 100% 16-May-11A
30-May-11A
13-Sep-11 13-Sep-11
W-OFS-5380 WHEELING ST. WATERLINE DESIGN COMPLETE - WHEELING WATERLINE 1 0 100% 18-Apr-11 A 18-Apr-11 A 13-Sep-11 13-Sep-11
PROJECT COMPLETION: 03-Oct-15
RUN DATE: 12-Aug-11
DENVER VA MEDICAL CENTER - FTP SCHEDULE
DATA DATE: 26-Jul-11
KIEWIT-TURNER
DVFTP-04 8.12.11
64 of 64
LT05 - TOTAL FLOAT REPORT
TASK filter: All Activities
Date Revision Checked Approved
Page 145
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
OSI-4850 62 84 CITY OF AURORA WHEELING WATER LINE REVIEW AND AP - OSI-1 10-Feb-11 A 23-Nov-11 23-Aug-11 23-Dec-11 20
CS1-3040 78 25 95% DESIGN - CS-1/IFO-3 18-Apr-11 A 29-Aug-11 17-Aug-11 21-Sep-11 16
XXXXCBS-0500 936 1528 CBS OVERALL DURATION 09-May-11 A 30-Sep-15 09-May-11 03-Oct-15 3
P-CBS-4370 20 6 SUBMITTAL DEVELOPMENT (structural steel) - CBS-1 14-Jun-11 A 02-Aug-11 19-Aug-11 26-Aug-11 18
P-CBS-4270 20 16 SUBMITTAL DEVELOPMENT (electrical) - CBS-1 24-Jun-11 A 16-Aug-11 19-Aug-11 12-Sep-11 18
P-CBS-4440 30 11 SUBMITTAL REVIEW (interior steel) - CBS-1 27-Jun-11 A 09-Aug-11 03-Aug-11 17-Aug-11 6
CBSSWSW-4140 7 7 RELOCATE FIRE DEPARTMENT CONNECTION - SITEWORK CBS 26-Jul-11 03-Aug-11 27-Jul-11 04-Aug-11 1
CBSSTST-4040 5 5 DRILLED PIERS - CANOPY - STRUCTURE CBS 26-Jul-11 30-Jul-11 28-Jul-11 02-Aug-11 2
CBSL1L1-3285 10 10 BELOW GRADE PLUMBING ROUGH-IN - LVL-1 CBS 26-Jul-11 05-Aug-11 11-Aug-11 22-Aug-11 14
CBSSTST-3760 15 15 EXCAVATION AND SHORING - STRUCTURE CBS 01-Aug-11 17-Aug-11 03-Aug-11 19-Aug-11 2
P-CBS-4380 20 20 SUBMITTAL REVIEW (structural steel) - CBS-1 03-Aug-11 30-Aug-11 29-Aug-11 26-Sep-11 18
CBSINL4-2490 15 15 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-4 CBS 04-Aug-11 20-Aug-11 05-Aug-11 22-Aug-11 1
CBSL3L3-2760 15 15 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-3 CBS 04-Aug-11 20-Aug-11 05-Aug-11 22-Aug-11 1
P-CBS-4450 20 20 MATERIAL PROCUREMENT (interior steel) - CBS-1 10-Aug-11 07-Sep-11 18-Aug-11 15-Sep-11 6
P-CBS-4280 30 30 SUBMITTAL VA REVIEW (electrical) - CBS-1 17-Aug-11 28-Sep-11 13-Sep-11 25-Oct-11 18
CBSSTST-4050 5 5 DRILLED PIERS - BUILDING ADDITION - STRUCTURE CBS 18-Aug-11 23-Aug-11 20-Aug-11 25-Aug-11 2
CBSL1L1-3290 5 5 FIRE SPRINKLER ROUGH-IN - LVL-1 CBS 22-Aug-11 26-Aug-11 23-Aug-11 27-Aug-11 1
CBSINL4-2500 10 10 FIRE SPRINKLER ROUGH-IN - LVL-4 CBS 22-Aug-11 01-Sep-11 23-Aug-11 02-Sep-11 1
CBSL3L3-2770 5 5 FIRE SPRINKLER ROUGH-IN - LVL-3 CBS 22-Aug-11 26-Aug-11 23-Aug-11 27-Aug-11 1
CBSSTST-2340 16 16 STAIR CORE AND ELEVATOR FOUNDATION - STRUCTURE CBS 24-Aug-11 12-Sep-11 26-Aug-11 14-Sep-11 2
CBSL1L1-3300 10 10 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-1 CBS 27-Aug-11 08-Sep-11 29-Aug-11 09-Sep-11 1
CS1-3510 0 0 95% CD DESIGN COMPLETE - CS-1/IFO-3 29-Aug-11 21-Sep-11 16
CS1-3660 15 15 KT PROVIDES RED LINE COMMENTS 95% CD - CS-1/IFO-3 30-Aug-11 20-Sep-11 22-Sep-11 13-Oct-11 16
P-CBS-4390 25 25 MATERIAL PROCUREMENT (structural steel) - CBS-1 31-Aug-11 05-Oct-11 27-Sep-11 01-Nov-11 18
CBSINL4-2510 10 10 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-4 CBS 02-Sep-11 14-Sep-11 03-Sep-11 15-Sep-11 1
AAAA-1010 0 0 NTP FOR CONSTRUCTION 06-Sep-11* 06-Sep-11 0
STR1-5560 15 15 SUBCONTRACTOR PRICING - TEMP REDIRECTION OF STORMWATER 06-Sep-11 26-Sep-11 12-Sep-11 30-Sep-11 4
AAAA-4630 0 0 VA PROVIDES CONSENT TO SUBCONTRACT - DESIGN ASSIST SUBCONTRACTORS 06-Sep-11 06-Sep-11 0
AAAA-5600 0 0 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1A 06-Sep-11 06-Sep-11 0
AAAA-5590 0 0 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1 06-Sep-11 06-Sep-11 0
STR1-5420 20 20 AWARD SHORING CONTRACT 07-Sep-11 04-Oct-11 07-Sep-11 04-Oct-11 0
SITSWTP-5230 15 15 SUBCONTRACTOR PRICING - TEMP PARKING CBS 07-Sep-11 27-Sep-11 07-Sep-11 27-Sep-11 0
W-OSI-5310 20 20 AWARD CONTRACT - WHEELING WATERLINE 07-Sep-11 04-Oct-11 13-Sep-11 11-Oct-11 4
AAAA-1040 0 0 NTP FOR POTHOLING FOR SHORING TIE-BACKS (start milestone) 07-Sep-11 15-Sep-11 8
STR1-5200 20 20 AWARD ROOF DRAIN CONTRACT - CBS ROOF DRAIN 07-Sep-11 04-Oct-11 23-Sep-11 21-Oct-11 12
P-CBS-4460 0 0 MATERIALS ARRIVE (interior steel) - CBS-1 07-Sep-11 15-Sep-11 6
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 1 of 19
Page 146
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
CBSL1L1-3303 20 20 NEW ELECTRICAL ROOM ROUGH-IN - LVL-1 CBS 09-Sep-11 01-Oct-11 10-Sep-11 03-Oct-11 1
SITWSSW-0288 15 15 SURVEYOR MAP/PROVIDE AS-BUILTS - POTHOLING 12-Sep-11 05-Oct-11 15-Sep-11 07-Oct-11 2
SITSWSW-0150 10 10 LOCATE ALL UTILITIES - POTHOLING 12-Sep-11 27-Sep-11 15-Sep-11 30-Sep-11 2
AAAA-1030 0 0 NTP FOR POTHOLING FOR WHEELING WATERLINE (start milestone) 12-Sep-11 15-Sep-11 3
CBSSTST-2350 40 40 STAIR CORE WALLS - STRUCTURE CBS 13-Sep-11 29-Oct-11 15-Sep-11 01-Nov-11 2
CBSSTST-2360 40 40 ELEVATOR CORE WALLS - STRUCTURE CBS 13-Sep-11 29-Oct-11 15-Sep-11 01-Nov-11 2
CBSINL4-2520 10 10 FRAMING - LVL-4 CBS 15-Sep-11 26-Sep-11 16-Sep-11 27-Sep-11 1
CS1-3670 5 5 PAGE FLIP 95% CD - CS-1/IFO-3 21-Sep-11 27-Sep-11 14-Oct-11 20-Oct-11 16
CBSINL4-2530 20 20 WALL ROUGH-IN - LVL-4 CBS 27-Sep-11 20-Oct-11 28-Sep-11 21-Oct-11 1
STR1-5570 10 10 PREPARE BID TABS - TEMP REDIRECTION OF STORMWATER 27-Sep-11 11-Oct-11 03-Oct-11 17-Oct-11 4
SITSWTP-5700 10 10 PREPARE BID TABS - TEMP PARKING CBS 28-Sep-11 12-Oct-11 28-Sep-11 12-Oct-11 0
CS1-3680 15 15 JVT REVISE DOCUMENTS 95% CD - CS-1/IFO-3 28-Sep-11 19-Oct-11 21-Oct-11 10-Nov-11 16
P-CBS-4290 15 15 INITIAL MATERIAL PROCUREMENT (electrical) - CBS-1 29-Sep-11 20-Oct-11 26-Oct-11 16-Nov-11 18
CBSL1L1-3307 20 20 NEW ELECTRICAL ROOM FIT-OUT - LVL-1 CBS 03-Oct-11 26-Oct-11 04-Oct-11 27-Oct-11 1
SITSWSW-0102 5 5 SHORING SUB COORDINATE WITH DESIGN - POTHOLING 05-Oct-11 11-Oct-11 05-Oct-11 11-Oct-11 0
STR1-5490 50 50 PROCURE SHORING MATERIALS STR-1 05-Oct-11 19-Dec-11 12-Oct-11 23-Dec-11 4
W-OSI-4450 10 10 PREPARE/SUBMIT SHOP DRAWINGS - WHEELING WATER 05-Oct-11 19-Oct-11 12-Oct-11 25-Oct-11 4
STR1-5210 20 20 PREPARE PERMIT/APPROVAL - CBS ROOF DRAIN 05-Oct-11 02-Nov-11 24-Oct-11 21-Nov-11 12
W-OSI-5320 10 10 SUB SUBMIT WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 05-Oct-11 19-Oct-11 26-Oct-11 08-Nov-11 14
P-CBS-4400 0 0 MATERIALS ARRIVE (structural steel) - CBS-1 05-Oct-11 01-Nov-11 18
STR1-5430 20 20 PREPARE/SUBMIT SHOP DRAWINGS FOR SHORING STR-1 12-Oct-11 08-Nov-11 12-Oct-11 08-Nov-11 0
AAAA-5520 2 2 VA REVIEW BID TABS - TEMP REDIRECTION OF STORMWATER 12-Oct-11 13-Oct-11 18-Oct-11 19-Oct-11 4
SITSWTP-5720 5 5 VA REVIEW BID TABS - TEMP PARKING CBS 13-Oct-11 19-Oct-11 13-Oct-11 19-Oct-11 0
AAAA-5630 0 0 VA PROVIDES CONSENT TO SUBCONTRACT - TEMP REDIRECTION OF STORMWATER 13-Oct-11 19-Oct-11 4
STR1-5540 10 10 AWARD DESIGN CONTRACTOR FOR TEMP REDIRECTION OF STORMWATER 14-Oct-11 27-Oct-11 20-Oct-11 02-Nov-11 4
SITSWTP-5620 0 0 VA PROVIDES CONSENT TO SUBCONTRACT - TEMP PARKING CBS 19-Oct-11 19-Oct-11 0
SITSWTP-4440 10 10 AWARD SUBCONTRACTS -TEMP PARKING CBS 20-Oct-11 02-Nov-11 20-Oct-11 02-Nov-11 0
W-OSI-4490 10 10 KT REVIEWS SHOP DRAWINGS - WHEELING WATER 20-Oct-11 02-Nov-11 26-Oct-11 08-Nov-11 4
W-OSI-5390 20 20 VA APPROVE WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 20-Oct-11 17-Nov-11 09-Nov-11 09-Dec-11 14
CS1-3690 5 5 JVT QA/QC DOCUMENTS 95% CD - CS-1/IFO-3 20-Oct-11 26-Oct-11 14-Nov-11 18-Nov-11 16
CBSINL4-2540 15 15 DRYWALL / FINISH - LVL-4 CBS 21-Oct-11 07-Nov-11 22-Oct-11 08-Nov-11 1
P-CBS-4420 25 25 REMAINING MATERIAL PROCUREMENT (electrical) - CBS-1 21-Oct-11 29-Nov-11 17-Nov-11 23-Dec-11 18
CS1-3610 0 0 100% CD DESIGN COMPLETION - CS-1/IFO-3 26-Oct-11 18-Nov-11 16
CBSL1L1-3310 10 10 FRAMING - LVL-1 CBS 27-Oct-11 07-Nov-11 28-Oct-11 08-Nov-11 1
DATPOPO-4770 40 40 PREPARE/SUBMIT UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 27-Oct-11 27-Dec-11 21-Nov-11 20-Jan-12 16
STR1-5550 8 8 KT DESIGN TEMP REDIRECTION OF STORMWATER 28-Oct-11 08-Nov-11 03-Nov-11 15-Nov-11 4
CBSSTST-4160 10 10 ERECT STRUCTURAL STEEL AT ADDITION - CBS - STRUCTURE CBS 31-Oct-11 10-Nov-11 02-Nov-11 14-Nov-11 2
SITSWTP-5550 15 15 KT DESIGN TEMP PARKING CBS 03-Nov-11 28-Nov-11 03-Nov-11 28-Nov-11 0
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 2 of 19
Page 147
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
W-OSI-4460 20 20 VA SUBMITTAL REVIEW - WHEELING WATER 03-Nov-11 05-Dec-11 09-Nov-11 09-Dec-11 4
STR1-5610 20 20 VA REVIEW/APPROVE SHOP DRAWINGS - CBS ROOF DRAIN 03-Nov-11 05-Dec-11 22-Nov-11 21-Dec-11 12
CBSL1L1-3320 5 5 WALL ROUGH-IN - LVL-1 CBS 05-Nov-11 10-Nov-11 07-Nov-11 12-Nov-11 1
CBSINL4-2550 10 10 INTERIOR PAINT - LVL-4 CBS 08-Nov-11 19-Nov-11 09-Nov-11 21-Nov-11 1
CBSL3L3-2810 5 5 DRYWALL / FINISH - LVL-3 CBS 08-Nov-11 14-Nov-11 06-Dec-11 10-Dec-11 22
STR1-5410 30 30 KT APPROVE SHOP DRAWINGS FOR SHORING STR-1 09-Nov-11 23-Dec-11 09-Nov-11 23-Dec-11 0
AAAA-5570 5 5 VA REVIEW/APPROVE TEMP REDIRECTION OF STORMWATER 09-Nov-11 16-Nov-11 16-Nov-11 22-Nov-11 4
CBSL1L1-3330 15 15 DRYWALL / FINISH - LVL-1 CBS 12-Nov-11 30-Nov-11 14-Nov-11 01-Dec-11 1
CBSADAL-2410 10 10 STEEL STAIRS - ALL LVLS ADD CBS 14-Nov-11 29-Nov-11 15-Nov-11 30-Nov-11 1
STR1-5580 11 11 PROCURE VAULT/PUMP FOR TEMP REDIRECTION OF STORMWATER 17-Nov-11 05-Dec-11 23-Nov-11 09-Dec-11 4
CBSSTST-4170 8 8 PLACE/FINISH COMD AT ADDITION - CBS - STRUCTURE CBS 19-Nov-11 29-Nov-11 21-Nov-11 30-Nov-11 1
CBSINL4-2560 12 12 CEILING - LVL-4 CBS 21-Nov-11 05-Dec-11 22-Nov-11 06-Dec-11 1
CBSL3L3-2820 10 10 INTERIOR PAINT - LVL-3 CBS 21-Nov-11 02-Dec-11 12-Dec-11 22-Dec-11 17
OSI-250 0 0 VA LICENSE AGREEMENTS WITH FRA/COA/UCD 23-Nov-11* 23-Nov-11 0
W-OSI-5610 20 20 FRA/COA APPROVE WORK/TRAFFIC CONTROL PLAN - WHEELING WATERLINE 28-Nov-11 23-Dec-11 28-Nov-11 23-Dec-11 0
SITSWTP-7800 0 0 JVT DESIGN COMPLETE - TEMP PARKING 28-Nov-11 06-Dec-11 6
SITSWTP-4450 14 14 PREPARE/SUBMIT SHOP DRAWINGS - TEMP PARKING CBS 29-Nov-11 16-Dec-11 29-Nov-11 16-Dec-11 0
SITSWTP1-5530 15 15 VA REVIEW/APPROVE TEMP PARKING 29-Nov-11 19-Dec-11 07-Dec-11 28-Dec-11 6
P-CBS-4300 0 0 ALL MATERIALS ARRIVE (electrical) - CBS-1 29-Nov-11 23-Dec-11 18
CBSSTST-4180 6 6 APPLY FIREPROOFING - CBS - STRUCTURE CBS 30-Nov-11 06-Dec-11 01-Dec-11 07-Dec-11 1
CBSL1L1-3340 8 8 INTERIOR PAINT - LVL-1 CBS 01-Dec-11 09-Dec-11 02-Dec-11 10-Dec-11 1
CBSINL4-2570 10 10 MILLWORK - LVL-4 CBS 06-Dec-11 16-Dec-11 07-Dec-11 17-Dec-11 1
W-OSI-4470 10 10 MATERIAL PROCUREMENT - WHEELING WATER 06-Dec-11 19-Dec-11 12-Dec-11 23-Dec-11 4
STR1-5730 20 20 INSTALL TEMP/TEMP REDIRECTION OF STORMWATER 06-Dec-11 04-Jan-12 12-Dec-11 10-Jan-12 4
STR1-5620 20 20 PROCURE MATERIALS - CBS ROOF DRAIN 06-Dec-11 04-Jan-12 22-Dec-11 23-Jan-12 12
CBSL3L3-2830 5 5 CEILING - LVL-3 CBS 06-Dec-11 10-Dec-11 23-Dec-11 29-Dec-11 15
CBSESES-3580 20 20 INSTALL TEMPORARY EXTERIOR SKIN @ NEW ADITION - SKINS CBS 07-Dec-11 05-Jan-12 08-Dec-11 06-Jan-12 1
CBSESES-4140 20 20 INSTALL EXTERIOR SKIN @ NEW ADITION - SKINS CBS 07-Dec-11 05-Jan-12 09-Dec-11 09-Jan-12 2
CBSADL4-2630 5 5 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL 4 ADD CBS 07-Dec-11 12-Dec-11 14-Dec-11 19-Dec-11 6
CBSADL3-2900 4 4 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-3 ADD CBS 07-Dec-11 10-Dec-11 28-Dec-11 31-Dec-11 17
CBSADL2-3160 4 4 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-2 ADD CBS 07-Dec-11 10-Dec-11 31-Dec-11 05-Jan-12 20
CBSL1L1-3350 10 10 CEILING - LVL-1 CBS 10-Dec-11 21-Dec-11 12-Dec-11 22-Dec-11 1
CBSADL4-2640 4 4 FIRE SPRINKLER ROUGH-IN - LVL-4 ADD CBS 13-Dec-11 16-Dec-11 20-Dec-11 23-Dec-11 6
CBSINL4-2580 10 10 FLOORING - LVL-4 CBS 17-Dec-11 29-Dec-11 19-Dec-11 30-Dec-11 1
CBSADL4-2650 4 4 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-4 ADD CBS 17-Dec-11 21-Dec-11 24-Dec-11 29-Dec-11 6
CBSL3L3-2840 5 5 MILLWORK - LVL-3 CBS 17-Dec-11 22-Dec-11 30-Dec-11 05-Jan-12 10
CBSADL3-2910 2 2 FIRE SPRINKLER ROUGH-IN - LVL-3 ADD CBS 17-Dec-11 19-Dec-11 03-Jan-12 04-Jan-12 12
CBSADL2-3170 2 2 FIRE SPRINKLER ROUGH-IN - LVL-2 ADD CBS 17-Dec-11 19-Dec-11 06-Jan-12 07-Jan-12 15
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 3 of 19
Page 148
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
CBSADL1-3430 2 2 FIRE SPRINKLER ROUGH-IN - LVL-1 ADD CBS 17-Dec-11 19-Dec-11 11-Jan-12 12-Jan-12 19
SITSWTP-4880 10 10 KT REVIEWS SHOP DRAWINGS - TEMP PARKING CBS 19-Dec-11 03-Jan-12 19-Dec-11 03-Jan-12 0
W-OSI-4480 0 0 MATERIALS ARRIVE - WHEELING WATER 19-Dec-11 23-Dec-11 4
SITSWTP-18 10 10 GRADING - TEMP PARKING 20-Dec-11 05-Jan-12 29-Dec-11 13-Jan-12 5
CBSL1L1-3360 10 10 MILLWORK - LVL-1 CBS 22-Dec-11 04-Jan-12 23-Dec-11 05-Jan-12 1
CBSADL4-2660 4 4 FRAMING - LVL-4 ADD CBS 22-Dec-11 27-Dec-11 30-Dec-11 04-Jan-12 6
CBSADL3-2920 4 4 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-3 ADD CBS 22-Dec-11 27-Dec-11 05-Jan-12 09-Jan-12 10
CBSADL2-3180 4 4 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-2 ADD CBS 22-Dec-11 27-Dec-11 09-Jan-12 12-Jan-12 13
CBSADL1-3440 3 3 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-1 ADD CBS 22-Dec-11 24-Dec-11 13-Jan-12 17-Jan-12 17
SITWSSW-328 2 2 PLACE EROSION PROTECTION/TRAFFIC CONTROL - WHEELING ST. 23-Dec-11 28-Dec-11 27-Dec-11 28-Dec-11 0
STR1-4260 10 10 MOBILIZE EXCAVATOR STR-1 27-Dec-11 10-Jan-12 27-Dec-11 10-Jan-12 0
STR1-5450 10 10 FABRICATE SHORING MATERIALS STR-1 27-Dec-11 10-Jan-12 27-Dec-11 10-Jan-12 0
CBSADL4-2670 4 4 WALL ROUGH-IN - LVL-4 ADD CBS 28-Dec-11 31-Dec-11 05-Jan-12 09-Jan-12 6
CBSADL3-2930 4 4 FRAMING - LVL-3 ADD CBS 28-Dec-11 31-Dec-11 10-Jan-12 13-Jan-12 10
CBSADL2-3190 4 4 FRAMING - LVL-2 ADD CBS 28-Dec-11 31-Dec-11 13-Jan-12 18-Jan-12 13
CBSADL1-3450 3 3 FRAMING - LVL-1 ADD CBS 28-Dec-11 30-Dec-11 18-Jan-12 20-Jan-12 16
DATPOPO-5060 15 15 KT APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 28-Dec-11 19-Jan-12 23-Jan-12 10-Feb-12 16
SITWSSW-288 5 5 DEMO/GRADING - WHEELING ST. 28-Dec-11 05-Jan-12 29-Dec-11 05-Jan-12 0
CBSINL4-2590 12 12 MEP TRIMOUT - LVL-4 CBS 30-Dec-11 13-Jan-12 31-Dec-11 14-Jan-12 1
CBSL3L3-2850 10 10 FLOORING - LVL-3 CBS 30-Dec-11 11-Jan-12 06-Jan-12 18-Jan-12 5
CBSADL3-2940 2 2 WALL ROUGH-IN - LVL-3 ADD CBS 03-Jan-12 04-Jan-12 14-Jan-12 17-Jan-12 10
SITSWTP-4470 8 8 MATERIAL PROCUREMENT - TEMP PARKING CBS 04-Jan-12 13-Jan-12 04-Jan-12 13-Jan-12 0
CBSL1L1-3370 10 10 FLOORING - LVL-1 CBS 05-Jan-12 17-Jan-12 06-Jan-12 18-Jan-12 1
CBSADL2-3200 2 2 WALL ROUGH-IN - LVL-2 ADD CBS 05-Jan-12 06-Jan-12 19-Jan-12 20-Jan-12 11
CBSADL1-3460 2 2 WALL ROUGH-IN - LVL-1 ADD CBS 05-Jan-12 06-Jan-12 21-Jan-12 23-Jan-12 13
SITWSSW-0205 15 15 INSTALL/TEST NEW WATERLINE - WHEELING ST. 05-Jan-12 30-Jan-12 06-Jan-12 30-Jan-12 0
CBSRLRL-3540 10 10 NEW ADDITION ROOFING - ROOF CBS 06-Jan-12 20-Jan-12 09-Jan-12 23-Jan-12 1
CBSADL4-2680 5 5 DRYWALL / FINISH - LVL-4 ADD CBS 06-Jan-12 11-Jan-12 10-Jan-12 14-Jan-12 3
CBSADL1-3470 5 5 DRYWALL / FINISH - LVL-1 ADD CBS 07-Jan-12 12-Jan-12 24-Jan-12 28-Jan-12 13
CBSADL3-2950 5 5 DRYWALL / FINISH - LVL-3 ADD CBS 10-Jan-12 14-Jan-12 18-Jan-12 23-Jan-12 6
STR1-5440 0 0 MATERIALS ARRIVE ON SITE STR-1 10-Jan-12 10-Jan-12 0
DATPGPG-3100 25 25 SHORING/MASS EXCAVATION/RECONDITIONING - PIPE GALLERY DAT 11-Jan-12 09-Feb-12 11-Jan-12 09-Feb-12 0
CBSADL4-2690 3 3 INTERIOR PAINT - LVL-4 ADD CBS 12-Jan-12 14-Jan-12 17-Jan-12 19-Jan-12 3
IBSPBPB-3130 10 10 DRIVE SOLDIER PILES - PIPE BSMT IBS 12-Jan-12 26-Jan-12 18-Jan-12 31-Jan-12 3
CBSADL2-3210 5 5 DRYWALL / FINISH - LVL-2 ADD CBS 13-Jan-12 19-Jan-12 21-Jan-12 26-Jan-12 6
CBSINL4-2600 10 10 HANDRAIL - LVL-4 CBS 14-Jan-12 26-Jan-12 17-Jan-12 27-Jan-12 1
CBSL3L3-2860 10 10 MEP TRIMOUT - LVL-3 CBS 14-Jan-12 26-Jan-12 19-Jan-12 30-Jan-12 3
CBSINL4-3940 5 5 TEST AND BALANCE - LVL-4 CBS 14-Jan-12 20-Jan-12 23-Jan-12 27-Jan-12 6
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 4 of 19
Page 149
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
SITSWTP-20 10 10 INSTALL UTILITIES - TEMP PARKING 17-Jan-12 30-Jan-12 17-Jan-12 30-Jan-12 0
CBSADL4-2700 5 5 CEILING - LVL-4 ADD CBS 17-Jan-12 21-Jan-12 20-Jan-12 25-Jan-12 3
CBSADL3-2960 2 2 INTERIOR PAINT - LVL-3 ADD CBS 17-Jan-12 18-Jan-12 25-Jan-12 26-Jan-12 7
CBSL1L1-3380 10 10 MEP TRIMOUT - LVL-1 CBS 18-Jan-12 28-Jan-12 19-Jan-12 30-Jan-12 1
CBSL1L1-3390 10 10 HANDRAIL - LVL-1 CBS 18-Jan-12 28-Jan-12 31-Jan-12 10-Feb-12 11
CBSADL3-2970 4 4 CEILING - LVL-3 ADD CBS 19-Jan-12 23-Jan-12 27-Jan-12 31-Jan-12 7
CBSADL2-3220 2 2 INTERIOR PAINT - LVL-2 ADD CBS 20-Jan-12 21-Jan-12 27-Jan-12 28-Jan-12 6
CBSADL1-3480 2 2 INTERIOR PAINT - LVL-1 ADD CBS 20-Jan-12 21-Jan-12 30-Jan-12 31-Jan-12 8
DATPOPO-4780 20 20 VA APPROVE UNDERGROUND MEP SHOP DRAWINGS - CS-1/IFO-3 (DAT) 20-Jan-12 17-Feb-12 14-Feb-12 12-Mar-12 16
CBSRLRL-3560 5 5 LIGHTNING PROTECTION - ROOF CBS 23-Jan-12 27-Jan-12 24-Jan-12 30-Jan-12 1
CBSADL4-2720 5 5 FLOORING - LVL-4 ADD CBS 23-Jan-12 27-Jan-12 26-Jan-12 31-Jan-12 3
CBSRLRL-3570 5 5 NEW EXHAUST FANS - ROOF CBS 23-Jan-12 27-Jan-12 26-Jan-12 01-Feb-12 3
CBSADL4-2730 5 5 MEP TRIMOUT - LVL-4 ADD CBS 23-Jan-12 27-Jan-12 27-Jan-12 01-Feb-12 4
CBSADL2-3230 3 3 CEILING - LVL-2 ADD CBS 23-Jan-12 25-Jan-12 30-Jan-12 01-Feb-12 6
CBSADL4-2740 2 2 HANDRAIL - LVL-4 ADD CBS 23-Jan-12 24-Jan-12 01-Feb-12 02-Feb-12 8
CBSADL1-3490 2 2 CEILING - LVL-1 ADD CBS 23-Jan-12 24-Jan-12 01-Feb-12 02-Feb-12 8
PVSSWSW-3210 10 10 RELOCATE CBS ROOF DRAIN - PVS SITEWORK 23-Jan-12 06-Feb-12 24-Jan-12 06-Feb-12 0
PVSSWSW-3130 10 10 DRIVE SOLDIER PILES - PVS SITEWORK 23-Jan-12 06-Feb-12 24-Jan-12 06-Feb-12 0
SITSWTP-07800 7 7 PLACE CURB/GUTTER/SIDEWALK/PARKING LOT - TEMP PARKING 26-Jan-12 03-Feb-12 26-Jan-12 03-Feb-12 0
CBSSTST-2610 10 10 PUNCHLIST - LVL-4 CBS 27-Jan-12 07-Feb-12 28-Jan-12 08-Feb-12 1
CBSL3L3-3960 3 3 TEST AND BALANCE - LVL-3 CBS 27-Jan-12 30-Jan-12 31-Jan-12 02-Feb-12 3
IBSPBPB-3100 28 28 SHORING/MASS EXCAVATION/RECONDITIONING - PIPE BSMT IBS 27-Jan-12 29-Feb-12 01-Feb-12 05-Mar-12 4
IBNSLSL-3130 10 10 DRIVE SOLDIER PILES - SERV LVL IBN 27-Jan-12 09-Feb-12 09-Feb-12 24-Feb-12 9
CBSADL3-2980 2 2 FLOORING - LVL-3 ADD CBS 28-Jan-12 30-Jan-12 01-Feb-12 02-Feb-12 3
CBSADL2-3240 2 2 FLOORING - LVL-2 ADD CBS 28-Jan-12 30-Jan-12 02-Feb-12 03-Feb-12 4
CBSADL4-3950 1 1 TEST AND BALANCE - LVL-4 ADD CBS 28-Jan-12 28-Jan-12 02-Feb-12 02-Feb-12 4
CBSADL1-3500 2 2 FLOORING - LVL-1 ADD CBS 28-Jan-12 30-Jan-12 03-Feb-12 04-Feb-12 5
CBSL1L1-3400 8 8 PUNCHLIST - LVL-1 CBS 30-Jan-12 07-Feb-12 31-Jan-12 08-Feb-12 1
CBSL1L1-4000 5 5 TEST AND BALANCE - LVL-1 CBS 30-Jan-12 03-Feb-12 31-Jan-12 04-Feb-12 1
CBSADL4-2750 5 5 PUNCHLIST - LVL-4 ADD CBS 30-Jan-12 03-Feb-12 03-Feb-12 08-Feb-12 4
ZZZZWS-9999 0 0 NEW WATERLINE COMPLETE @ WHEELING ST (finish milestone) 30-Jan-12 30-Jan-12 0
CBSADL3-2990 2 2 MEP TRIMOUT - LVL-3 ADD CBS 31-Jan-12 01-Feb-12 03-Feb-12 04-Feb-12 3
CBSADL3-3000 2 2 HANDRAIL - LVL-3 ADD CBS 31-Jan-12 01-Feb-12 04-Feb-12 06-Feb-12 4
CBSADL2-3250 2 2 MEP TRIMOUT - LVL-2 ADD CBS 31-Jan-12 01-Feb-12 04-Feb-12 06-Feb-12 4
CBSADL1-3510 2 2 MEP TRIMOUT - LVL-1 ADD CBS 31-Jan-12 01-Feb-12 06-Feb-12 07-Feb-12 5
RFP3-0100 10 10 VACATE CREDIT UNION 01-Feb-12* 11-Feb-12 01-Feb-12 11-Feb-12 0
CBSL3L3-2880 5 5 PUNCHLIST - LVL-3 CBS 02-Feb-12 07-Feb-12 03-Feb-12 08-Feb-12 1
CBSADL3-3970 1 1 TEST AND BALANCE - LVL-3 ADD CBS 02-Feb-12 02-Feb-12 06-Feb-12 06-Feb-12 3
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 5 of 19
Page 150
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
CBSADL1-3530 3 3 PUNCHLIST - LVL-1 ADD CBS 02-Feb-12 04-Feb-12 06-Feb-12 08-Feb-12 3
CBSADL2-3260 2 2 HANDRAIL - LVL-2 ADD CBS 02-Feb-12 03-Feb-12 07-Feb-12 08-Feb-12 4
CBSADL2-3990 1 1 TEST AND BALANCE - LVL-2 ADD CBS 02-Feb-12 02-Feb-12 08-Feb-12 08-Feb-12 5
CBSADL1-4010 1 1 TEST AND BALANCE - LVL-1 ADD CBS 02-Feb-12 02-Feb-12 08-Feb-12 08-Feb-12 5
CBSADL1-3520 1 1 HANDRAIL - LVL-1 ADD CBS 02-Feb-12 02-Feb-12 08-Feb-12 08-Feb-12 5
CBSADL3-3010 2 2 PUNCHLIST - LVL-3 ADD CBS 03-Feb-12 04-Feb-12 07-Feb-12 08-Feb-12 3
CBSADL2-3270 2 2 PUNCHLIST - LVL-2 ADD CBS 03-Feb-12 04-Feb-12 07-Feb-12 08-Feb-12 3
SITSWTP-28 3 3 STRIPE PARKING LOT & INSTALL FINISHES- TEMP PARKING 06-Feb-12 08-Feb-12 06-Feb-12 08-Feb-12 0
XXXXPVS-0500 724 724 PVS OVERALL DURATION 06-Feb-12 30-Jan-14 22-Jun-12 30-Jan-14 0
PVSSWSW-3100 115 115 SHORING/MASS EXCAVATION/RECONDITIONING - PVS SITEWORK 06-Feb-12 21-Jun-12 07-Feb-12 21-Jun-12 0
CBSMIMI-3610 0 0 DOD/VA ACCEPT LEVELS 1,3 & 4 - CBS MILESTONE 08-Feb-12* 08-Feb-12 0
XXXXRES-500 722 722 RES TEMPORARY PARKING OVERALL DURATION 09-Feb-12 30-Jan-14 09-Feb-12 30-Jan-14 0
XXXXDAT-0500 1113 1113 DAT OVERALL DURATION 10-Feb-12 26-Feb-15 21-Feb-12 26-Feb-15 0
DATPGPG-0320 15 15 DRILL/PLACE CAISSONS - PIPE GALLERY DAT 10-Feb-12 05-Mar-12 10-Feb-12 05-Mar-12 0
DATSLSL-0340 35 35 FORM/PLACE TOWER CRANE #1 BASE (DAT & CON C/D) 10-Feb-12 06-Apr-12 16-Feb-12 12-Apr-12 3
AAAADAT-0100 0 0 START DAT CONSTRUCTION (start milestone) 10-Feb-12 21-Feb-12 11
DATPOPO-4790 15 15 PREFAB/MATERIAL DELIVERY UNDERGROUND MEP - CS-1/IFO-3 (DAT) 20-Feb-12 09-Mar-12 13-Mar-12 02-Apr-12 16
DATPGPG-0330 27 27 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY DAT 21-Feb-12 02-Apr-12 21-Feb-12 02-Apr-12 0
IBNSLSL-3100 20 20 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL IBN 21-Feb-12 14-Mar-12 25-Feb-12 19-Mar-12 4
CONAASL-3100 8 8 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-A CON 27-Feb-12 06-Mar-12 02-Mar-12 10-Mar-12 4
CONABSL-3100 8 8 MASS EXCAVATION/RECONDITIONING - SERV LVL AR-B CON 06-Mar-12 14-Mar-12 10-Mar-12 19-Mar-12 4
ENCPGPG-3100 25 25 MASS EXCAVATION/RECONDITIONING - PIPE GALLERY ENC 07-Mar-12 04-Apr-12 12-Mar-12 09-Apr-12 4
ENCSLSL-3100 25 25 MASS EXCAVATION/RECONDITIONING - SERV LVL ENC 07-Mar-12 04-Apr-12 24-Mar-12 21-Apr-12 15
IBSPBPB-0320 25 25 DRILL/PLACE CAISSONS - PIPE BSMT IBS 14-Mar-12 26-Apr-12 19-Mar-12 03-May-12 3
CONABSL-3210 7 7 INSTALL DUCTBANK DRAINAGE - SERV LVL AR-B CON 15-Mar-12 26-Mar-12 20-Mar-12 30-Mar-12 3
CONABSL-3110 15 15 EXCAVATE/SET/BACKFILL DUCTBANK/VAULTS - SERV LVL AR-B CON 27-Mar-12 23-Apr-12 02-Apr-12 27-Apr-12 3
DATPGPG-3110 7 7 SET/BACKFILL DUCTBANKS - PIPE GALLERY DAT 03-Apr-12 16-Apr-12 03-Apr-12 16-Apr-12 0
DATPGPG-3200 7 7 UNDERSLAB UTILITIES - PIPE GALLERY DAT 03-Apr-12 16-Apr-12 03-Apr-12 16-Apr-12 0
ENCPGPG-0320 6 6 DRILL/PLACE CAISSONS - PIPE GALLERY ENC 05-Apr-12 16-Apr-12 10-Apr-12 20-Apr-12 3
HOITCTC-0110 10 10 ERECT TOWER CRANE #1 (DAT & CON C/D) 07-Apr-12 16-Apr-12 16-Apr-12 25-Apr-12 9
DATPGPG-0380 5 5 FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY DAT 17-Apr-12 24-Apr-12 17-Apr-12 24-Apr-12 0
ENCSLSL-0320 20 20 DRILL/PLACE CAISSONS - SERV LVL ENC 17-Apr-12 22-May-12 23-Apr-12 29-May-12 3
XXXXCON-0500 1064 1064 CON OVERALL DURATION 24-Apr-12 23-Mar-15 22-Jun-12 28-Mar-15 5
CONABSL-0320 9 9 DRILL/PLACE CAISSONS - SERV LVL AR-B CON 24-Apr-12 10-May-12 01-Jun-12 15-Jun-12 21
DATSLSL-0322 15 15 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - SERV LVL DAT 26-Apr-12 22-May-12 26-Apr-12 22-May-12 0
ENCSLSL-0330 60 60 FORM/PLACE PIER CAPS/CORES/ WALLS/COLUMNS - SERV LVL ENC 26-Apr-12 09-Aug-12 03-May-12 14-Aug-12 3
IBNSLSL-0320 25 25 DRILL/PLACE CAISSONS - SERV LVL IBN 27-Apr-12 11-Jun-12 04-May-12 15-Jun-12 3
CLC-3610 0 0 100% CD DESIGN COMPLETION - CLC 27-Apr-12* 27-Apr-12 0
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 6 of 19
Page 151
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
CONAASL-0320 18 18 DRILL/PLACE CAISSONS - SERV LVL AR-A CON 11-May-12 11-Jun-12 18-Jun-12 17-Jul-12 21
DATSLSL-0380 15 15 FORM/PLACE/FINISH SLAB ON GRADE (AREA C) - SERV LVL DAT 15-May-12 08-Jun-12 15-May-12 08-Jun-12 0
DATPGPG-3210 5 5 BACKFILL FOUNDATION WALLS (INTERIOR) - PIPE GALLERY DAT 24-May-12 31-May-12 24-May-12 31-May-12 0
DATSLSL-3210 10 10 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - SERV LVL DAT 24-May-12 08-Jun-12 24-May-12 08-Jun-12 0
DATSLSL-0381 10 10 FORM/PLACE/FINISH SLAB ON GRADE (AREA D) - SERV LVL DAT 24-May-12 08-Jun-12 19-Jun-12 05-Jul-12 15
DATSLSL-0383 10 10 FORM/PLACE/FINISH SLAB ON GRADE (AREA F) - SERV LVL DAT 01-Jun-12 18-Jun-12 06-Jul-12 23-Jul-12 20
DATL1L1-0330 15 15 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-1 DAT 11-Jun-12 05-Jul-12 11-Jun-12 05-Jul-12 0
IBNSLSL-0330 110 110 FORM/PLACE/PIER CAPS/TIE BEAMS/ELEV/ WALLS/CORES - SERV LVL IBN 12-Jun-12 14-Dec-12 18-Jun-12 20-Dec-12 3
CONAASL-0330 40 40 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-A CON 12-Jun-12 20-Aug-12 19-Jul-12 25-Sep-12 21
DATSLSL-0388 10 10 FORM/PLACE/FINISH SLAB ON GRADE (AREA A) - SERV LVL DAT 19-Jun-12 05-Jul-12 24-Jul-12 09-Aug-12 20
PVSP3AA-0320 14 14 DRILL/PLACE CAISSONS - PKG LVL-3 AREA A PVS 21-Jun-12 16-Jul-12 22-Jun-12 16-Jul-12 0
PVSP3AD-0320 14 14 DRILL/PLACE CAISSONS - PKG LVL-3 AREA D PVS 21-Jun-12 16-Jul-12 22-Jun-12 16-Jul-12 0
DATL1L1-0340 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-1 DAT 06-Jul-12 13-Jul-12 06-Jul-12 13-Jul-12 0
CONACSL-0330 30 30 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-C CON 09-Jul-12 28-Aug-12 14-Aug-12 03-Oct-12 21
XXXXCBC-0500 961 961 CBC OVERALL DURATION 10-Jul-12 26-Feb-15 19-Feb-13 26-Feb-15 0
DATL1L1-0350 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-1 DAT 16-Jul-12 23-Jul-12 16-Jul-12 23-Jul-12 0
PVSP3AE-0320 14 14 DRILL/PLACE CAISSONS - PKG LVL-3 AREA E PVS 16-Jul-12 09-Aug-12 17-Jul-12 09-Aug-12 0
PVSP3AB-0320 14 14 DRILL/PLACE CAISSONS - PKG LVL-3 AREA B PVS 16-Jul-12 09-Aug-12 16-Aug-12 07-Sep-12 17
DATL1L1-0360 10 10 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-1 DAT 24-Jul-12 09-Aug-12 24-Jul-12 09-Aug-12 0
PVSP3AF-0320 14 14 DRILL/PLACE CAISSONS - PKG LVL-3 AREA F PVS 09-Aug-12 04-Sep-12 10-Aug-12 04-Sep-12 0
PVSP3AC-0320 14 14 DRILL/PLACE CAISSONS - PKG LVL-3 AREA C PVS 09-Aug-12 04-Sep-12 10-Sep-12 02-Oct-12 17
PVSP3AB-0332 20 20 FORM/PLACE FTGS/WALLS/COLUMNS - PKG LVL-3 AREA B PVS 09-Aug-12 13-Sep-12 13-Sep-12 12-Oct-12 19
PVSP3AB-0335 20 20 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA B PVS 09-Aug-12 13-Sep-12 17-Sep-12 18-Oct-12 21
DATL1L1-0320 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-1 DAT 10-Aug-12 17-Aug-12 10-Aug-12 17-Aug-12 0
ENCALAL-0510 20 20 ERECT STRUCTURAL STEEL/DECK (LEVEL 1(incl. deck) - PH ROOF) - ALL LEVELS ENC 10-Aug-12 13-Sep-12 16-Aug-12 18-Sep-12 3
DATL1L1-0321 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-1 DAT 20-Aug-12 27-Aug-12 20-Aug-12 27-Aug-12 0
PVSP3AF-0330 35 35 FORM/PLACE TOWER CRANE #2 BASE - (PVS) 24-Aug-12 23-Oct-12 27-Aug-12 23-Oct-12 0
DATL2L2-0330 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-2 DAT 28-Aug-12 05-Sep-12 28-Aug-12 05-Sep-12 0
DATL2L2-0360 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-2 DAT 28-Aug-12 05-Sep-12 28-Aug-12 05-Sep-12 0
CONACSL-3200 11 11 UNDERSLAB UTILITIES - SERV LVL AR-C CON 30-Aug-12 17-Sep-12 04-Oct-12 22-Oct-12 21
PVSP3AC-0332 15 15 FORM/PLACE FTGS/COLUMNS - PKG LVL-3 AREA C PVS 04-Sep-12 28-Sep-12 03-Oct-12 25-Oct-12 17
PVSP3AC-0335 12 12 APPLY SHOTCRETE TO EXTERIOR WALLS - PKG LVL-3 AREA D PVS 04-Sep-12 24-Sep-12 08-Oct-12 25-Oct-12 20
DATL2L2-0320 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-2 DAT 06-Sep-12 13-Sep-12 06-Sep-12 13-Sep-12 0
DATL2L2-0340 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-2 DAT 06-Sep-12 13-Sep-12 06-Sep-12 13-Sep-12 0
PVSP3AB-3200 5 5 UNDERSLAB UTILITIES - PKG LVL-3 AREA B PVS 13-Sep-12 21-Sep-12 19-Oct-12 25-Oct-12 21
DATL2L2-0321 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-2 DAT 14-Sep-12 21-Sep-12 14-Sep-12 21-Sep-12 0
DATL2L2-0350 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-2 DAT 14-Sep-12 21-Sep-12 14-Sep-12 21-Sep-12 0
ENCALAL-1426 10 10 ERECT/DETAIL METAL DECK (LEVEL 2 - PH ROOF) - LVLS 2 - PH ROOF) ENC 14-Sep-12 01-Oct-12 20-Sep-12 04-Oct-12 3
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 7 of 19
Page 152
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
ENCL1L1-0320 10 10 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 ENC 14-Sep-12 01-Oct-12 20-Sep-12 04-Oct-12 3
CONACSL-0380 12 12 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-C CON 18-Sep-12 05-Oct-12 23-Oct-12 09-Nov-12 21
PVSP3AB-0380 10 10 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA B PVS 21-Sep-12 08-Oct-12 26-Oct-12 13-Nov-12 21
DATL3L3-0330 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - LVL-3 DAT 24-Sep-12 01-Oct-12 24-Sep-12 01-Oct-12 0
PVSP3AC-3200 5 5 UNDERSLAB UTILITIES - PKG LVL-3 AREA C PVS 28-Sep-12 05-Oct-12 26-Oct-12 02-Nov-12 17
CONACL1-1527 15 15 ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1) - LVL-1 AR-C CON 01-Oct-12 23-Oct-12 02-Nov-12 27-Nov-12 21
DATL3L3-0340 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - LVL-3 DAT 02-Oct-12 08-Oct-12 02-Oct-12 08-Oct-12 0
ENCLRLR-0320 10 10 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LOW ROOF ENC 02-Oct-12 16-Oct-12 05-Oct-12 22-Oct-12 3
DVAPOPO-4950 60 60 VA PROVIDE MED EQUIP COORDINATED CDS (pharmacy) - DAT 04-Oct-12 03-Jan-13 04-Oct-12 03-Jan-13 0
PVSP3AC-0380 10 10 FORM/PLACE/FINISH SLAB ON GRADE - PKG LVL-3 AREA C PVS 05-Oct-12 23-Oct-12 05-Nov-12 20-Nov-12 17
CONACSL-0322 8 8 FORM/REINFORCE/PLACE/FINISH/CONCRETE BEAMS/GRADE BEAMS- SERV LVL AR-C CON 08-Oct-12 19-Oct-12 13-Nov-12 23-Nov-12 21
DATL3L3-0350 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - LVL-3 DAT 09-Oct-12 16-Oct-12 09-Oct-12 16-Oct-12 0
DATL3L3-0360 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - LVL-3 DAT 18-Oct-12 24-Oct-12 18-Oct-12 24-Oct-12 0
ENCL1L1-0720 7 7 SPRAY ON FIREPROOFING - LVL-1 ENC 18-Oct-12 26-Oct-12 23-Oct-12 01-Nov-12 3
HOITCTC-0102 10 10 ERECT TOWER CRANE #2 (PVS) 23-Oct-12 03-Nov-12 24-Oct-12 03-Nov-12 0
CONACL1-0390 8 8 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 AR-C CON 24-Oct-12 05-Nov-12 29-Nov-12 11-Dec-12 21
DATL3L3-0320 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - LVL-3 DAT 25-Oct-12 01-Nov-12 25-Oct-12 01-Nov-12 0
ENCL1EL-1650 210 210 ROUGH-IN/CONNECT TRANSFORMERS - LVL-1 ELEC RMS ENC 29-Oct-12 29-Aug-13 02-Nov-12 05-Sep-13 4
ENCL1EL-1660 210 210 ROUGH-IN/CONNECT SUBSTATION - LVL-1 ELEC RMS ENC 29-Oct-12 29-Aug-13 02-Nov-12 05-Sep-13 4
ENCL1EL-1620 210 210 ROUGH-IN/CONNECT SWITCHGEAR - LVL-1 ELEC RMS ENC 29-Oct-12 29-Aug-13 02-Nov-12 05-Sep-13 4
ENCL1EL-1640 210 210 ROUGH-IN/CONNECT GENERATORS - LVL-1 ELEC RMS ENC 29-Oct-12 29-Aug-13 02-Nov-12 05-Sep-13 4
DATL3L3-0321 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA B) - LVL-3 DAT 02-Nov-12 09-Nov-12 02-Nov-12 09-Nov-12 0
HOITCTC-0200 153 153 MAINTAIN TOWER CRANE #2 (PVS) 03-Nov-12 05-Apr-13 03-Nov-12 05-Apr-13 0
PVSP2AA-0330 12 12 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA A PVS 05-Nov-12 23-Nov-12 05-Nov-12 23-Nov-12 0
CONACSL-0390 19 19 PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-C CON 06-Nov-12 07-Dec-12 12-Dec-12 10-Jan-13 21
DATPHPH-0330 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA C) - PENT DAT 13-Nov-12 19-Nov-12 13-Nov-12 19-Nov-12 0
PVSP2AB-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA B PVS 14-Nov-12 29-Nov-12 14-Nov-12 29-Nov-12 0
DATSLIL-1537 15 15 ERECT INTER STEEL/TOPPING (AREA C) - SERV LVL INTER LVL DAT 20-Nov-12 13-Dec-12 20-Nov-12 13-Dec-12 0
DATPHPH-0340 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA D) - PENT DAT 20-Nov-12 27-Nov-12 29-Nov-12 06-Dec-12 5
PVSP2AC-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA C PVS 21-Nov-12 07-Dec-12 21-Nov-12 07-Dec-12 0
PVSP2AA-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA A PVS 26-Nov-12 13-Dec-12 03-Dec-12 20-Dec-12 4
DATPHPH-0350 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA E) - PENT DAT 29-Nov-12 06-Dec-12 14-Dec-12 21-Dec-12 10
PVSP2AD-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA D PVS 30-Nov-12 14-Dec-12 30-Nov-12 14-Dec-12 0
PVSP2AB-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA B PVS 30-Nov-12 18-Dec-12 11-Dec-12 28-Dec-12 6
DATSLIL-1547 15 15 ERECT INTER STEEL/TOPPING (AREA D) - SERV LVL INTER LVL DAT 07-Dec-12 31-Dec-12 07-Dec-12 31-Dec-12 0
DATPHPH-0360 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA F) - PENT DAT 07-Dec-12 13-Dec-12 02-Jan-13 08-Jan-13 15
PVSP1AA-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA A PVS 10-Dec-12 24-Dec-12 10-Dec-12 24-Dec-12 0
PVSP2AE-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-2 AREA E PVS 10-Dec-12 24-Dec-12 10-Dec-12 24-Dec-12 0
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 8 of 19
Page 153
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
PVSP2AC-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA C PVS 10-Dec-12 27-Dec-12 18-Dec-12 07-Jan-13 6
CONL2AB-0990 512 512 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-B CON 10-Dec-12 23-Dec-14 04-Dec-13 07-Jan-15 9
CONL3AA-0990 512 512 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-A CON 10-Dec-12 23-Dec-14 27-Sep-13 14-Jan-15 14
CONL3AD-0990 512 512 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-D CON 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL3AB-0990 512 512 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-B CON 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL3AC-0990 512 512 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-C CON 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL2AC-0990 512 512 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-C CON 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL2AD-0990 512 512 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-D CON 10-Dec-12 23-Dec-14 04-Dec-13 14-Jan-15 14
CONL2AA-0990 512 512 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-A CON 10-Dec-12 23-Dec-14 27-Sep-13 14-Jan-15 14
CBNSLSL-0320 5 5 DRILL/PLACE CAISSONS (balance @ bench) - SERV LVL CBN 10-Dec-12 14-Dec-12 11-Jan-13 18-Jan-13 21
DATPHPH-0320 5 5 FORM/REINFORCE/PLACE/FINISH DECK (AREA A) - PENT DAT 14-Dec-12 21-Dec-12 17-Jan-13 24-Jan-13 20
PVSP1AB-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA B PVS 17-Dec-12 02-Jan-13 17-Dec-12 02-Jan-13 0
IBNL1L1-0510 15 15 ERECT STRUCTURAL STEEL/DECK - LVL-1 IBN 17-Dec-12 09-Jan-13 21-Dec-12 14-Jan-13 3
PVSP2AD-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-2 AREA D PVS 17-Dec-12 04-Jan-13 27-Dec-12 14-Jan-13 6
CBNSSSS-0510 35 35 ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBN 17-Dec-12 08-Feb-13 22-Jan-13 15-Mar-13 21
DATSLIL-1557 15 15 ERECT INTER STEEL/TOPPING (AREA E) - SERV LVL INTER LVL DAT 24-Dec-12 15-Jan-13 24-Dec-12 15-Jan-13 0
PVSP1AC-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA C PVS 26-Dec-12 09-Jan-13 26-Dec-12 09-Jan-13 0
PVSP1AA-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA A PVS 26-Dec-12 11-Jan-13 11-Jan-13 30-Jan-13 11
PVSP1AD-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA D PVS 03-Jan-13 17-Jan-13 03-Jan-13 17-Jan-13 0
PVSP1AB-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA B PVS 03-Jan-13 22-Jan-13 25-Jan-13 11-Feb-13 14
DVAPOPO-3960 60 60 VA PROVIDE MED EQUIP COORDINATED CDS(gen imaging) - DAT 04-Jan-13 01-Apr-13 04-Jan-13 01-Apr-13 0
DATSLIL-1567 15 15 ERECT INTER STEEL/TOPPING (AREA F) - SERV LVL INTER LVL DAT 09-Jan-13 31-Jan-13 09-Jan-13 31-Jan-13 0
IBNL2L2-0510 15 15 ERECT STRUCTURAL STEEL/DECK - LVL-2 IBN 10-Jan-13 01-Feb-13 15-Jan-13 06-Feb-13 3
PVSP1AE-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA E PVS 10-Jan-13 25-Jan-13 06-Feb-13 21-Feb-13 17
PVSP1AC-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA C PVS 10-Jan-13 29-Jan-13 06-Feb-13 25-Feb-13 17
PVSP0AA-0333 10 10 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA A PVS 18-Jan-13 01-Feb-13 18-Jan-13 01-Feb-13 0
PVSP1AF-0330 10 10 FORM/REINF/PLACE/FINISH/TENSION DECK - PKG LVL-1 AREA F PVS 18-Jan-13 01-Feb-13 14-Feb-13 28-Feb-13 17
PVSP1AD-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA D PVS 18-Jan-13 05-Feb-13 20-Feb-13 08-Mar-13 20
DATSLIL-0510 15 15 ERECT INTER STEEL/TOPPING (AREA A) - SERV LVL INTER LVL DAT 25-Jan-13 15-Feb-13 25-Jan-13 15-Feb-13 0
PVSP0AB-0333 10 10 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA B PVS 31-Jan-13 14-Feb-13 31-Jan-13 14-Feb-13 0
IBNL3L3-0510 15 15 ERECT STRUCTURAL STEEL/DECK - LVL-3 IBN 04-Feb-13 26-Feb-13 07-Feb-13 01-Mar-13 3
PVSP1AF-0335 12 12 FORM/REINFORCE/PLACE/STRIP WALLS/COLUMNS - PKG LVL-1 AREA F PVS 04-Feb-13 21-Feb-13 01-Mar-13 20-Mar-13 17
DATSLIL-1527 15 15 ERECT INTER STEEL/TOPPING (AREA B) - SERV LVL INTER LVL DAT 08-Feb-13 04-Mar-13 08-Feb-13 04-Mar-13 0
CBNPHPH-0320 19 19 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT LVL CBN 11-Feb-13 12-Mar-13 18-Mar-13 16-Apr-13 21
PVSP0AC-0333 10 10 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA C PVS 12-Feb-13 27-Feb-13 12-Feb-13 27-Feb-13 0
PVSP0AD-0333 10 10 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA D PVS 26-Feb-13 12-Mar-13 26-Feb-13 12-Mar-13 0
IBNL1L1-0320 9 9 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 IBN 27-Feb-13 12-Mar-13 04-Mar-13 18-Mar-13 3
IBNESNE-0870 10 10 INSTALL PRECAST PANELS - NORTH ELEV IBN 27-Feb-13 14-Mar-13 08-Mar-13 22-Mar-13 6
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 9 of 19
Page 154
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
DATSLIL-1800 45 45 ROUGH-IN MEP/FIRE PROTECTION (EMER MGMNT) (AHU18) - SERV LVL INTER LVL DAT 05-Mar-13 06-May-13 05-Mar-13 06-May-13 0
DVAPOPO-4990 60 60 VA PROVIDE MED EQUIP COORDINATED CDS (MRI/CT) - DAT 05-Mar-13 28-May-13 02-Apr-13 25-Jun-13 20
PVSP0AE-0333 10 10 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA E PVS 11-Mar-13 25-Mar-13 11-Mar-13 25-Mar-13 0
IBNSLSL-0390 14 14 PERM DRAINS/BACKFILL - SERV LVL IBN 14-Mar-13 04-Apr-13 19-Mar-13 09-Apr-13 3
CBNPHPR-0320 11 11 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT ROOF CBN 14-Mar-13 29-Mar-13 18-Apr-13 07-May-13 21
IBNESNE-870 15 15 INSTALL STRIP WINDOWS - NORTH ELEV IBN 15-Mar-13 08-Apr-13 25-Mar-13 18-Apr-13 6
CONABL1-0330 30 30 FORM/PLACE PIER CAPS/GRADE BEAMS - LVL-1 AR-B CON 19-Mar-13 09-May-13 22-Mar-13 14-May-13 3
PVSP0AF-0333 10 10 FORM/REINF/PLACE/FINISH/STRIP DECK - PKG LVL-0 AREA F PVS 21-Mar-13 05-Apr-13 21-Mar-13 05-Apr-13 0
CBNL3L3-0320 11 11 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 CBN 26-Mar-13 12-Apr-13 03-May-13 21-May-13 21
CBCSLSL-0320 15 15 DRILL/PLACE CAISSONS (balance @ bench) - SERV LVL CBC 29-Mar-13 23-Apr-13 29-Mar-13 23-Apr-13 0
DATSLIL-0200 45 45 ROUGH-IN MEP/FIRE PROTECTION (PHARMACY) (AHU2) - SERV LVL INTER LVL DAT 02-Apr-13 04-Jun-13 02-Apr-13 04-Jun-13 0
CONABL1-0320 9 9 DRILL/PLACE CAISSONS (EAST BALANCE) - LVL-1 AR-B CON 05-Apr-13 19-Apr-13 11-Apr-13 25-Apr-13 3
PVSALAL-0555 20 20 ERECT STAIRS ST1 - ALL LVLS PVS 08-Apr-13 03-May-13 08-Apr-13 03-May-13 0
IBNESNE-880 15 15 INSTALL METAL PANELS - NORTH ELEV IBN 09-Apr-13 06-May-13 19-Apr-13 16-May-13 6
CBNL2L2-0320 11 11 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 CBN 12-Apr-13 02-May-13 21-May-13 07-Jun-13 21
SITSWBW-278 20 20 INSTALL HARDSCAPE/LANDSCAPE/FINISHES - INTERSEC WHEELING ST. 15-Apr-13 14-May-13 15-Apr-13 14-May-13 0
CBCSSSS-510 45 45 FORM/PLACE/STRIP SHEAR WALLS (southwest corner) - ALL LVLS CBC 16-Apr-13 03-Jul-13 16-Apr-13 03-Jul-13 0
PVSALAL-0556 20 20 ERECT STAIRS ST2 - ALL LVLS PVS 18-Apr-13 15-May-13 18-Apr-13 15-May-13 0
PVSALAL-0557 20 20 ERECT STAIRS ST3 - ALL LVLS PVS 30-Apr-13 28-May-13 30-Apr-13 28-May-13 0
DATSLIL-0700 45 45 ROUGH-IN MEP/FIRE PROTECTION (STERILIZATION) (AHU7) - SERV LVL INTER LVL DAT 30-Apr-13 02-Jul-13 30-Apr-13 02-Jul-13 0
CBNL1L1-0320 11 11 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 CBN 06-May-13 23-May-13 11-Jun-13 28-Jun-13 21
ENCTSTS-3100 5 5 MASS EXCAVATION/RECONDITIONING - WATER TANK ENC 07-May-13 11-May-13 17-May-13 22-May-13 9
CONABL1-3200 9 9 UNDERSLAB UTILITIES - LVL-1 AR-B CON 10-May-13 24-May-13 16-May-13 30-May-13 3
SITSWBW-288 4 4 PLACE EROSION PROTECTION/TRAFFIC CONTROL - SOUTH WHEELING ST. 16-May-13 21-May-13 16-May-13 21-May-13 0
SITSWBW-298 15 15 DEMO/GRADING - SOUTH WHEELING ST. 23-May-13 17-Jun-13 23-May-13 17-Jun-13 0
CBNL1L1-0725 10 10 SPRAY-ON FIREPROOFING - LVL-1 CBN 24-May-13 10-Jun-13 01-Jul-13 16-Jul-13 21
CONABL1-0380 9 9 FORM/REINFORCE/PLACE/FINISH/STRIP STRUCT SLABS - LVL-1 AR-B CON 28-May-13 10-Jun-13 31-May-13 14-Jun-13 3
PVSINP1-1620 30 30 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-3 PVS 29-May-13 10-Jul-13 29-May-13 10-Jul-13 0
DATSLIL-1900 45 45 ROUGH-IN MEP/FIRE PROTECTION (SHELL) (AHU19) - SERV LVL INTER LVL DAT 29-May-13 31-Jul-13 29-May-13 31-Jul-13 0
ENCTSTS-3200 15 15 UNDERSLAB UTILITIES- WATER TANK ENC 30-May-13 24-Jun-13 10-Jun-13 03-Jul-13 6
CONABSS-0510 26 26 ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-B CON 11-Jun-13 25-Jul-13 17-Jun-13 30-Jul-13 3
CBNL1L1-0540 15 15 ERECT EXTERIOR STUDS - LVL-1 CBN 11-Jun-13 05-Jul-13 18-Jul-13 12-Aug-13 21
SITSWBW-308 25 25 INSTALL REMAINING UTILITIES - SOUTH WHEELING ST. 18-Jun-13 30-Jul-13 18-Jun-13 30-Jul-13 0
ENCTSTS-0380 7 7 FORM/PLACE/FINISH/TENSION SLAB ON GRADE - WATER TANK ENC 25-Jun-13 05-Jul-13 05-Jul-13 16-Jul-13 6
PVSINP2-1620 30 30 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-2 PVS 26-Jun-13 07-Aug-13 26-Jun-13 07-Aug-13 0
DATL1IL-0400 55 55 ROUGH-IN MEP/FIRE PROTECTION (GEN RADIOLOGY) (AHU4) - LVL-1 INTER LVL DAT 26-Jun-13 12-Sep-13 26-Jun-13 12-Sep-13 0
CBCSSSS-0510 33 33 ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBC 05-Jul-13 30-Aug-13 05-Jul-13 30-Aug-13 0
ENCTSTS-0390 20 20 FORM/PLACE/FINISH WALLS/COLUMNS/CURBS - WATER TANK ENC 08-Jul-13 09-Aug-13 18-Jul-13 20-Aug-13 6
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 10 of 19
Page 155
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
CBNESNE-0520 10 10 SHEATHING/VAPOR BARRIER - NORTH ELEV CBN 08-Jul-13 23-Jul-13 13-Aug-13 29-Aug-13 21
PVSINP3-1620 30 30 ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-1 PVS 25-Jul-13 05-Sep-13 25-Jul-13 05-Sep-13 0
DATL1IL-0100 50 50 ROUGH-IN MEP/FIRE PROTECTION (PRE ADMIN) (AHU1) - LVL-1 INTER LVL DAT 25-Jul-13 03-Oct-13 25-Jul-13 03-Oct-13 0
CBNESWE-0520 5 5 SHEATHING/VAPOR BARRIER - WEST ELEV CBN 25-Jul-13 01-Aug-13 30-Aug-13 06-Sep-13 21
CONABSS-0320 10 10 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - ALL LVLS AR-B CON 26-Jul-13 12-Aug-13 01-Aug-13 16-Aug-13 3
PVNSLSL-3130 10 10 DRIVE SOLDIER PILES - SERV LVL PVN 01-Aug-13 16-Aug-13 01-Aug-13 16-Aug-13 0
CBNESSE-0520 10 10 SHEATHING/VAPOR BARRIER - SOUTH ELEV CBN 02-Aug-13 19-Aug-13 09-Sep-13 24-Sep-13 21
PVSINP2-0990 30 30 GARAGE FINISHES - PKG LVL-2 PVS 08-Aug-13 19-Sep-13 06-Sep-13 17-Oct-13 20
ENCTSTS-3220 53 53 FORM/PLACE/FINISH/TENSION LID - WATER TANK ENC 12-Aug-13 07-Nov-13 22-Aug-13 18-Nov-13 6
CONABHR-0510 9 9 FRAMING @ CLEARSTORY - HIGH ROOF AR-B CON 13-Aug-13 27-Aug-13 19-Aug-13 03-Sep-13 3
PVNSLSL-3100 30 30 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL PVN 17-Aug-13 21-Sep-13 19-Aug-13 23-Sep-13 1
CBNESEE-0520 5 5 SHEATHING/VAPOR BARRIER - EAST ELEV CBN 20-Aug-13 27-Aug-13 26-Sep-13 02-Oct-13 21
DATL1IL-0500 50 50 ROUGH-IN MEP/FIRE PROTECTION (NUC MED) (AHU5) - LVL-1 INTER LVL DAT 22-Aug-13 01-Nov-13 06-Sep-13 18-Nov-13 10
DATL1IL-1500 65 65 ROUGH-IN MEP/FIRE PROTECTION (SPECIAL RADIOLOGY) (AHU15) - LVL-1 INTER LVL DAT 22-Aug-13 26-Nov-13 20-Sep-13 24-Dec-13 20
CONABHR-0750 14 14 PARAPET/BLOCKING/ICE WATER SHIELD- HIGH ROOF AR-B CON 29-Aug-13 20-Sep-13 04-Sep-13 26-Sep-13 3
ZZZCAMP-1000 0 0 XCEL PROVIDE ENERGY TO ENC 29-Aug-13 05-Sep-13 4
EEEEENC-0990 0 0 ENC BLDG AVAILABLE FOR ENERGIZE 29-Aug-13 05-Sep-13 4
ENCPBPB-1606 30 30 START UP CAMPUS ELEC EQUIPMENT - FULL CAMPUS 30-Aug-13 11-Oct-13 06-Sep-13 17-Oct-13 4
CBCPHPH-0320 19 19 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT LVL CBC 03-Sep-13 02-Oct-13 03-Sep-13 02-Oct-13 0
PVSINP3-0990 30 30 GARAGE FINISHES - PKG LVL-1 PVS 06-Sep-13 17-Oct-13 06-Sep-13 17-Oct-13 0
DATL1IL-1600 65 65 ROUGH-IN MEP/FIRE PROTECTION (ER) (AHU16) - LVL-1 INTER LVL DAT 20-Sep-13 24-Dec-13 18-Oct-13 24-Jan-14 20
PVNSLDO-0320 10 10 DRILL/PLACE CAISSONS - SERV LVL DOCK PVN 23-Sep-13 07-Oct-13 24-Sep-13 08-Oct-13 1
XXXXPVN-0500 520 520 PVN OVERALL DURATION 23-Sep-13 24-Feb-15 09-Oct-13 26-Feb-15 2
CONHBAA-1516 15 15 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-A CON 23-Sep-13 11-Oct-13 27-Sep-13 17-Oct-13 4
AAAAPVN-0100 0 0 START PVN CONSTRUCTION (start milestone) 23-Sep-13 09-Oct-13 16
CONABHR-0888 12 12 INSTALL GLAZING @ CLEARSTORY - HIGH ROOF AR-B CON 23-Sep-13 09-Oct-13 22-Oct-13 08-Nov-13 18
CBCPHPH-0310 7 7 FORM/REINFORCE/FINISH HOUSEKEEPING PADS - PENT LVL CBC 03-Oct-13 11-Oct-13 03-Oct-13 11-Oct-13 0
CBCPHPR-0320 11 11 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - PENT ROOF CBC 03-Oct-13 21-Oct-13 18-Oct-13 04-Nov-13 9
CBCPHPH-0725 10 10 SPRAY-ON FIREPROOFING - PENTLVL CBC 03-Oct-13 18-Oct-13 21-Oct-13 04-Nov-13 10
PVSALAL-1400 60 60 INSTALL ELEVATOR PGE15/PGE16X - ALL LVLS PVS 04-Oct-13 02-Jan-14 04-Oct-13 02-Jan-14 0
DATL1PA-1516 30 30 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 PRE-ADMIT DAT 04-Oct-13 18-Nov-13 04-Oct-13 18-Nov-13 0
PVNSLPK-0320 10 10 DRILL/PLACE CAISSONS - SERV LVL PARK PVN 04-Oct-13 21-Oct-13 17-Oct-13 31-Oct-13 7
DVAPOPO-5000 30 30 VA PROVIDE FIXED FF&E SHOP DRAWINGS - CBC 04-Oct-13 18-Nov-13 30-Oct-13 12-Dec-13 17
PVNSLDO-0322 45 45 FORM/PLACE FOUNDATION WALLS/ELEVATOR PITS - SERV LVL DOCK PVN 08-Oct-13 20-Dec-13 09-Oct-13 23-Dec-13 1
CBCL3L3-0320 11 11 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-3 CBC 10-Oct-13 28-Oct-13 25-Oct-13 13-Nov-13 9
PVNSLPK-0322 30 30 FORM/PLACE FOUNDATION WALLS - SERV LVL PARK PVN 11-Oct-13 02-Dec-13 24-Oct-13 12-Dec-13 7
CBCPHPH-1500 5 5 SET MECH EQUIPMENT - PENTLVL CBC 14-Oct-13 18-Oct-13 14-Oct-13 18-Oct-13 0
CONHBAA-0910 15 15 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-A CON 14-Oct-13 04-Nov-13 18-Oct-13 08-Nov-13 4
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 11 of 19
Page 156
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
ENCPBPB-1590 30 30 START-UP CAMPUS PUMPS- SERV LVL MECH RMS ENC 14-Oct-13 27-Nov-13 01-Nov-13 16-Dec-13 13
ENCSLME-1590 30 30 START-UP CAMPUS BOILERS/CHILLERS - SERV LVL MECH RMS ENC 14-Oct-13 27-Nov-13 01-Nov-13 16-Dec-13 13
ENCPHPH-1590 30 30 START-UP CAMPUS COOLING TOWERS - PENTHOUSE ENC 14-Oct-13 27-Nov-13 01-Nov-13 16-Dec-13 13
COMMISS-1616 30 30 SYSTEM CONTROLS/STABILIZATION - FULL CAMPUS 14-Oct-13 27-Nov-13 08-Nov-13 23-Dec-13 18
EEEEPVS-0000 0 0 PVS BLDG AVAILABLE FOR ENERGIZE 17-Oct-13 17-Oct-13 0
PVSP1AA-1641 30 30 START-UP ELECTRICAL SYSTEMS (pvs/con) - PKG LVL-1 AREA A PVS 18-Oct-13 03-Dec-13 18-Oct-13 03-Dec-13 0
PVSP1AE-1641 20 20 START-UP ELECTRICAL SYSTEMS (pvs/con) - PKG LVL-1 AREA E PVS 18-Oct-13 18-Nov-13 12-Nov-13 10-Dec-13 15
CBCPHPH-1600 10 10 SET ELECTRICAL EQUIPMENT - PENTLVL CBC 22-Oct-13 04-Nov-13 22-Oct-13 04-Nov-13 0
CBCL2L2-0320 11 11 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-2 CBC 28-Oct-13 14-Nov-13 20-Nov-13 09-Dec-13 14
CBCL3L3-0725 10 10 SPRAY-ON FIREPROOFING - LVL-3 CBC 29-Oct-13 14-Nov-13 14-Nov-13 29-Nov-13 9
CBCPHPH-0540 15 15 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTLVL CBC 05-Nov-13 29-Nov-13 05-Nov-13 29-Nov-13 0
CONHBAA-0920 15 15 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-A CON 05-Nov-13 27-Nov-13 12-Nov-13 03-Dec-13 4
ENCTRTR-0750 20 20 APPLY WATERPROOFING - WATER TANK ENC 08-Nov-13 11-Dec-13 19-Nov-13 20-Dec-13 6
PVNSLDO-0350 10 10 POUR PIER CAPS - SERV LVL DOCK PVN 12-Nov-13 26-Nov-13 13-Nov-13 28-Nov-13 1
PVNSLDO-0390 10 10 FORM/PLACE COLUMNS - SERV LVL DOCK PVN 15-Nov-13 02-Dec-13 18-Nov-13 03-Dec-13 1
CBCL2L2-0725 10 10 SPRAY-ON FIREPROOFING - LVL-2 CBC 15-Nov-13 02-Dec-13 10-Dec-13 24-Dec-13 14
CBCL1L1-0320 11 11 FORM/REINFORCE/ROUGH-IN/PLACE TOPPING SLAB - LVL-1 CBC 18-Nov-13 05-Dec-13 16-Dec-13 02-Jan-14 17
DATL1NM-1516 20 20 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 NUC MED DAT 19-Nov-13 17-Dec-13 19-Nov-13 17-Dec-13 0
PVNSLPK-0244 10 10 BACKFILL FOUNDATION WALLS - SERV LVL PARK PVN 25-Nov-13 10-Dec-13 06-Dec-13 20-Dec-13 7
DATL1NM-0910 25 25 FRAMING/INWALL ROUGH - LVL-1 NUC MED DAT 27-Nov-13 02-Jan-14 27-Nov-13 02-Jan-14 0
CONHBAA-0990 15 15 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-A CON 28-Nov-13 18-Dec-13 04-Dec-13 24-Dec-13 4
COMMISS-1626 5 5 LOAD TEST - FULL CAMPUS 28-Nov-13 04-Dec-13 17-Dec-13 23-Dec-13 13
CBCL3L3-0540 15 15 ERECT EXTERIOR STUDS - LVL-3 CBC 02-Dec-13 24-Dec-13 02-Dec-13 24-Dec-13 0
CBCPHPH-0710 10 10 INSTALL LOUVERS - PENTLVL CBC 02-Dec-13 16-Dec-13 27-Dec-13 10-Jan-14 16
PVNSLDO-0366 21 21 FORM/PLACE/TENSION DOCK LID - SERV LVL DOCK PVN 03-Dec-13 06-Jan-14 05-Dec-13 07-Jan-14 1
PVSALCO-9999 30 30 CREATE/COMPLETE FINAL PUNCHLIST - ALL LVLS PVS 04-Dec-13 16-Jan-14 17-Dec-13 30-Jan-14 9
CBCL1L1-0725 10 10 SPRAY-ON FIREPROOFING - LVL-1 CBC 06-Dec-13 20-Dec-13 03-Jan-14 17-Jan-14 17
PVNSLPK-0266 10 10 BELOW GRADE UTILITY ROUGH-IN - SERV LVL PARK PVN 11-Dec-13 26-Dec-13 23-Dec-13 07-Jan-14 7
ENCFTFT-3100 13 13 MASS EXCAVATION/PREP GRADE - FUEL TANK ENC 12-Dec-13 27-Dec-13 21-Dec-13 07-Jan-14 8
CBCPHPH-0777 10 10 INSTALL METAL PANEL - PENTLVL CBC 17-Dec-13 02-Jan-14 13-Jan-14 28-Jan-14 16
DATL1NM-0920 20 20 HANG/TAPE/FINISH DRYWALL - LVL-1 NUC MED DAT 18-Dec-13 16-Jan-14 18-Dec-13 16-Jan-14 0
CONHBAA-8880 10 10 CLEAN-UP/PRE PUNCH/FINAL PUNCH- HIGH BAY AR-A CON 19-Dec-13 03-Jan-14 26-Dec-13 09-Jan-14 4
XXXCAMP-1600 315 315 COMMISSION - FULL CAMPUS 24-Dec-13 27-Mar-15 24-Dec-13 27-Mar-15 0
PVSALCO-1592 20 20 TEST & BALANCE - ALL LVLS PVS 24-Dec-13 12-Jan-14 24-Dec-13 12-Jan-14 0
PVSALCO-1594 10 10 PRE-FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS PVS 24-Dec-13 08-Jan-14 24-Dec-13 08-Jan-14 0
CBCL2L2-0540 15 15 ERECT EXTERIOR STUDS - LVL-2 CBC 26-Dec-13 17-Jan-14 26-Dec-13 17-Jan-14 0
DATL1ER-1516 35 35 PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 ER DAT 26-Dec-13 17-Feb-14 27-Jan-14 17-Mar-14 20
DATL1PA-0910 25 25 FRAMING/INWALL ROUGH - LVL-1 PRE-ADMIT DAT 26-Dec-13 31-Jan-14 27-Jan-14 03-Mar-14 20
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 12 of 19
Page 157
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
ENCFTFT-0378 18 18 FORM/PLACE/FINISH/TENSION SLAB ON GRADE - FUEL TANK ENC 30-Dec-13 27-Jan-14 08-Jan-14 04-Feb-14 6
CBCPHME-0420 15 15 LAY CMU WALLS - PENTHOUSE MECH CBC 03-Jan-14 24-Jan-14 29-Jan-14 19-Feb-14 17
CONHBAA-8890 7 7 TEAR DOWN STAGE - HIGH BAY AR-A CON 06-Jan-14 14-Jan-14 10-Jan-14 21-Jan-14 4
PVNSLPK-0245 10 10 BACKFILL DOCK FOUNDATION WALLS - SERV LVL PARK PVN 07-Jan-14 22-Jan-14 08-Jan-14 23-Jan-14 1
PVSALCO-1596 15 15 FUNCTIONAL TESTING/CORRECTIONS - ALL LVLS PVS 09-Jan-14 30-Jan-14 09-Jan-14 30-Jan-14 0
DATL1NM-0990 65 65 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NUC MED DAT 10-Jan-14 14-Apr-14 10-Jan-14 14-Apr-14 0
DATL1ER-0910 30 30 FRAMING/INWALL ROUGH - LVL-1 ER DAT 10-Jan-14 24-Feb-14 11-Feb-14 24-Mar-14 20
CONHBAC-1516 15 15 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-C CON 15-Jan-14 05-Feb-14 22-Jan-14 12-Feb-14 4
DATL1PA-0920 20 20 HANG/TAPE/FINISH DRYWALL - LVL-1 PRE-ADMIT DAT 17-Jan-14 17-Feb-14 11-Feb-14 10-Mar-14 15
CBCL1L1-0540 7 7 ERECT EXTERIOR STUDS - LVL-1 CBC 21-Jan-14 29-Jan-14 21-Jan-14 29-Jan-14 0
PVNSLPK-0344 20 20 FORM/PLACE SOG/EQUIPMENT PADS - SERV LVL PARK PVN 23-Jan-14 20-Feb-14 24-Jan-14 21-Feb-14 1
PVNSLPK-1676 5 5 DRILL/PLACE BALANCE OF CAISSONS - SERV LVL PARK PVN 23-Jan-14 29-Jan-14 24-Jan-14 30-Jan-14 1
CBCPHME-1516 30 30 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECH CBC 27-Jan-14 10-Mar-14 20-Feb-14 02-Apr-14 17
DATL1ER-0920 25 25 HANG/TAPE/FINISH DRYWALL - LVL-1 ER DAT 27-Jan-14 03-Mar-14 25-Feb-14 31-Mar-14 20
ENCFTFT-0380 3 3 SET TANKS- FUEL TANK ENC 28-Jan-14 30-Jan-14 05-Feb-14 07-Feb-14 6
CBCESNE-0520 10 10 SHEATHING/VAPOR BARRIER - NORTH ELEV CBC 30-Jan-14 14-Feb-14 30-Jan-14 14-Feb-14 0
ZZZZPVS-9999 0 0 FINISH PVS CONSTRUCTION (finish milestone) 30-Jan-14 30-Jan-14 0
RESSLSL-3130 10 10 DRIVE SOLDIER PILES - SERV LVL RES 31-Jan-14 17-Feb-14 31-Jan-14 17-Feb-14 0
XXXXPVS-510 422 422 PVS (UNDERGROUND) TEMPORARY PARKING OVERALL DURATION 31-Jan-14 28-Mar-15 31-Jan-14 28-Mar-15 0
XXXXRES-0500 611 611 RES OVERALL DURATION 31-Jan-14 03-Oct-15 07-Apr-14 03-Oct-15 0
ENCFTFT-3200 25 25 INSTALL FUEL TANK PIPING - FUEL TANK ENC 31-Jan-14 10-Mar-14 11-Feb-14 20-Mar-14 6
CONHBAC-0910 15 15 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-C CON 06-Feb-14 27-Feb-14 13-Feb-14 05-Mar-14 4
DATL1FL-0920 25 25 HANG/TAPE/FINISH DRYWALL - LVL-1 FLURO/UTLSND DAT 11-Feb-14 17-Mar-14 11-Mar-14 14-Apr-14 20
CBCESWE-0520 5 5 SHEATHING/VAPOR BARRIER - WEST ELEV CBC 17-Feb-14 21-Feb-14 17-Feb-14 21-Feb-14 0
RESSLSL-3100 18 18 SHORING/MASS EXCAVATION/RECONDITIONING - SERV LVL RES 18-Feb-14 10-Mar-14 18-Feb-14 10-Mar-14 0
CBCPHEL-0910 8 8 FRAMING/INWALL ROUGH - PENT ELEC CBC 18-Feb-14 27-Feb-14 13-Mar-14 24-Mar-14 17
PVNALAL-0310 100 100 FORM/PLACE/TENSION DECKS - LVLS 1-5 PVN 21-Feb-14 12-Aug-14 24-Feb-14 14-Aug-14 1
CBCESSE-0520 10 10 SHEATHING/VAPOR BARRIER - SOUTH ELEV CBC 24-Feb-14 07-Mar-14 24-Feb-14 07-Mar-14 0
DATL1PA-0990 55 55 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PRE-ADMIT DAT 25-Feb-14 12-May-14 25-Feb-14 12-May-14 0
DATL1FL-0990 65 65 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 FLURO/UTLSND DAT 25-Feb-14 27-May-14 25-Mar-14 24-Jun-14 20
CONHBAC-0920 18 18 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-C CON 28-Feb-14 25-Mar-14 06-Mar-14 31-Mar-14 4
CBCPHEL-0920 15 15 HANG/TAPE/FINISH DRYWALL - PENT ELEC CBC 28-Feb-14 20-Mar-14 25-Mar-14 14-Apr-14 17
CBCESEE-0520 5 5 SHEATHING/VAPOR BARRIER - EAST ELEV CBC 10-Mar-14 17-Mar-14 10-Mar-14 17-Mar-14 0
CBCESSE-0870 40 40 INSTALL CURTAIN WALL - SOUTH ELEV CBC 10-Mar-14 16-May-14 07-Apr-14 16-Jun-14 16
RESSLSL-0320 26 26 DRILL/PLACE CAISSONS - SERV LVL RES 11-Mar-14 24-Apr-14 11-Mar-14 24-Apr-14 0
ENCFTFT-0390 5 5 TEST FUEL TANKS - FUEL TANK ENC 11-Mar-14 18-Mar-14 21-Mar-14 28-Mar-14 6
CBCL3AA-1516 20 20 R-I OVERHEAD MEP/FIRE PRO- LVL-3 AREA A CBC 18-Mar-14 14-Apr-14 18-Mar-14 14-Apr-14 0
ENCFTFT-3220 20 20 BACKFILL - FUEL TANK ENC 20-Mar-14 22-Apr-14 31-Mar-14 02-May-14 6
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 13 of 19
Page 158
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
CBCPHEL-1620 75 75 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC CBC 21-Mar-14 07-Jul-14 15-Apr-14 30-Jul-14 17
CONHBAC-0990 15 15 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-C CON 26-Mar-14 15-Apr-14 01-Apr-14 21-Apr-14 4
CBCL3AB-1516 20 20 R-I OVERHEAD MEP/FIRE PRO - LVL-3 AREA B CBC 01-Apr-14 28-Apr-14 01-Apr-14 28-Apr-14 0
RESSLSL-0330 30 30 FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL RES 07-Apr-14 29-May-14 07-Apr-14 29-May-14 0
DATL1RO-0990 40 40 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 RAD OFFICES DAT 08-Apr-14 03-Jun-14 08-Apr-14 03-Jun-14 0
DATL1ER-0990 65 65 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 ER DAT 08-Apr-14 09-Jul-14 06-May-14 06-Aug-14 20
CBCL2AA-1516 18 18 R-I OVERHEAD MEP/FIRE PRO- LVL-2 AREA A CBC 15-Apr-14 08-May-14 15-Apr-14 08-May-14 0
CONHBAC-8880 10 10 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-C CON 16-Apr-14 29-Apr-14 22-Apr-14 05-May-14 4
ENCSWHL-0210 15 15 INSTALL UNDERGROUND UTILITIES - SITEWORK ENC 24-Apr-14 19-May-14 05-May-14 30-May-14 6
CBCL2AB-1516 17 17 R-I OVERHEAD MEP/FIRE PRO - LVL-2 AREA B CBC 29-Apr-14 21-May-14 29-Apr-14 21-May-14 0
CONHBAC-8890 7 7 TEAR DOWN STAGE - HIGH BAY AR-C CON 30-Apr-14 08-May-14 06-May-14 14-May-14 4
RESSLSL-3200 15 15 UNDERSLAB UTILITIES (DUCTBANKS/VAULTS/PLUMBING) - SERV LVL RES 02-May-14 29-May-14 02-May-14 29-May-14 0
ENCSWHL-0215 20 20 INSTALL PERIMETER DUCTBANK - SITEWORK ENC 08-May-14 12-Jun-14 19-May-14 23-Jun-14 6
CONHBAE-1516 15 15 SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-E CON 09-May-14 30-May-14 15-May-14 05-Jun-14 4
CBCL1AA-1516 18 18 R-I OVERHEAD MEP/FIRE PRO- LVL-1 AREA A CBC 13-May-14 06-Jun-14 13-May-14 06-Jun-14 0
CONL1AC-1516 25 25 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-C CON 19-May-14 23-Jun-14 17-Jun-14 22-Jul-14 20
DATL2CA-0990 55 55 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CARDIO DAT 20-May-14 06-Aug-14 20-May-14 06-Aug-14 0
DATL2DE-0990 55 55 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 DENTAL DAT 20-May-14 06-Aug-14 18-Jun-14 04-Sep-14 20
CBCL1AB-1516 17 17 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AREA B CBC 28-May-14 19-Jun-14 28-May-14 19-Jun-14 0
RESSLSL-0380 10 10 FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL RES 30-May-14 16-Jun-14 30-May-14 16-Jun-14 0
CONHBAE-0910 15 15 CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-E CON 02-Jun-14 20-Jun-14 06-Jun-14 26-Jun-14 4
CBCL1AB-0910 14 14 FRAMING/INWALL ROUGH - LVL-1 AREA B CBC 09-Jun-14 26-Jun-14 09-Jun-14 26-Jun-14 0
ENCSWHL-0220 40 40 FINE GRADE/HARDSCAPE - SITEWORK ENC 13-Jun-14 21-Aug-14 24-Jun-14 02-Sep-14 6
CBCL1AA-0910 14 14 FRAMING/INWALL ROUGH - LVL-1 AREA A CBC 16-Jun-14 03-Jul-14 16-Jun-14 03-Jul-14 0
RESL1L1-0320 15 15 FORM/REINFORCE/PLACE/FINISH - LVL-1 RES 17-Jun-14 11-Jul-14 17-Jun-14 11-Jul-14 0
CONHBAE-0920 15 15 HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-E CON 23-Jun-14 14-Jul-14 27-Jun-14 18-Jul-14 4
CBCL2AB-0910 14 14 FRAMING/INWALL ROUGH - LVL-2 AREA B CBC 23-Jun-14 11-Jul-14 02-Jul-14 22-Jul-14 7
CBCALAL-1400 60 60 INSTALL ELEVATOR SE5 - ALL LVLS CBC 23-Jun-14 16-Sep-14 17-Jul-14 09-Oct-14 17
CONL1AC-0910 20 20 FRAMING/ ROUGH-IN - LVL-1 AR-C CON 24-Jun-14 22-Jul-14 23-Jul-14 19-Aug-14 20
CBCL1AA-0920 13 13 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA A CBC 30-Jun-14 17-Jul-14 30-Jun-14 17-Jul-14 0
CBCL2AA-0910 14 14 FRAMING/INWALL ROUGH - LVL-2 AREA A CBC 30-Jun-14 18-Jul-14 10-Jul-14 29-Jul-14 7
DATL2SL-0990 45 45 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SLEEP DAT 02-Jul-14 04-Sep-14 02-Jul-14 04-Sep-14 0
EEEECBC-0000 0 0 CBC BLDG AVAILABLE FOR ENERGIZE 07-Jul-14 30-Jul-14 17
CBCL1AB-0920 12 12 HANG/TAPE/FINISH DRYWALL - LVL-1 AREA B CBC 08-Jul-14 23-Jul-14 08-Jul-14 23-Jul-14 0
CBCL3AB-0910 14 14 FRAMING/INWALL ROUGH - LVL-3 AREA B CBC 08-Jul-14 25-Jul-14 17-Jul-14 05-Aug-14 7
CBCPHME-1641 30 30 START-UP ELECTRICAL SYSTEMS - PENT MECH CBC 08-Jul-14 18-Aug-14 31-Jul-14 11-Sep-14 17
RESL2L2-0320 15 15 FORM/REINFORCE/PLACE/FINISH - LVL-2 RES 14-Jul-14 07-Aug-14 14-Jul-14 07-Aug-14 0
RESSLSL-0390 25 25 PERM DRAINS/WATERPROOFING/BACKFILL FOUNDATION WALLS - SERV LVL RES 14-Jul-14 25-Aug-14 12-Aug-14 23-Sep-14 17
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 14 of 19
Page 159
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
CONHBAE-0990 15 15 INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-E CON 15-Jul-14 04-Aug-14 21-Jul-14 08-Aug-14 4
CBCL2AA-0920 13 13 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA A CBC 15-Jul-14 31-Jul-14 24-Jul-14 11-Aug-14 7
CBCL3AA-0910 14 14 FRAMING/INWALL ROUGH - LVL-3 AREA A CBC 15-Jul-14 01-Aug-14 24-Jul-14 12-Aug-14 7
CBCL1AB-0990 22 22 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA B CBC 22-Jul-14 20-Aug-14 22-Jul-14 20-Aug-14 0
CBCL2AB-0920 12 12 HANG/TAPE/FINISH DRYWALL - LVL-2 AREA B CBC 22-Jul-14 06-Aug-14 31-Jul-14 15-Aug-14 7
CONL1AC-0920 15 15 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-C CON 23-Jul-14 12-Aug-14 20-Aug-14 10-Sep-14 20
CBCL3AA-0920 13 13 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA A CBC 29-Jul-14 14-Aug-14 07-Aug-14 25-Aug-14 7
CBCL2AA-0990 23 23 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA A CBC 29-Jul-14 28-Aug-14 27-Aug-14 29-Sep-14 21
CONHBAE-8880 10 10 CLEAN-UP/PRE PUNCH/FINAL PUNCH - HIGH BAY AR-E CON 05-Aug-14 18-Aug-14 11-Aug-14 22-Aug-14 4
CBCL3AB-0920 12 12 HANG/TAPE/FINISH DRYWALL - LVL-3 AREA B CBC 05-Aug-14 20-Aug-14 14-Aug-14 29-Aug-14 7
CBCL2AB-0990 22 22 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA B CBC 05-Aug-14 04-Sep-14 28-Aug-14 29-Sep-14 17
DVAPOPO-5020 30 30 VA PROVIDE FIXED FF&E SHOP DRAWINGS - RES 06-Aug-14 17-Sep-14 15-Aug-14 26-Sep-14 7
DATL2SC-0990 55 55 INSTALL INTERIOR FINISHES - LVL-2 SOUTH CORR DAT 07-Aug-14 24-Oct-14 05-Sep-14 25-Nov-14 20
RESL3L3-0320 15 15 FORM/REINFORCE/PLACE/FINISH - LVL-3 RES 08-Aug-14 03-Sep-14 08-Aug-14 03-Sep-14 0
CBCL2AA-0977 15 15 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBC 08-Aug-14 28-Aug-14 09-Sep-14 29-Sep-14 21
CBCL3AA-0990 23 23 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA A CBC 12-Aug-14 12-Sep-14 27-Aug-14 29-Sep-14 11
CONL1AC-0990 65 65 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-C CON 13-Aug-14 14-Nov-14 11-Sep-14 15-Dec-14 20
DATL3CA-0990 65 65 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CATH LABS DAT 14-Aug-14 17-Nov-14 14-Aug-14 17-Nov-14 0
PVNSLDO-0560 25 25 ERECT STRUCTURAL STEEL/CORES/ROOF - SERV LVL DOCK PVN 14-Aug-14 25-Sep-14 15-Aug-14 26-Sep-14 1
CBCL2AB-0977 15 15 INSTALL OWNER FIXED FF&E - LVL-2 AREA-B CBC 14-Aug-14 04-Sep-14 09-Sep-14 29-Sep-14 17
CONL1AE-1516 20 20 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-E CON 19-Aug-14 16-Sep-14 25-Aug-14 22-Sep-14 4
CONL1DI-1516 18 18 R-I OVERHEAD MEP/FIRE PRO - LVL-1 DINING CON 19-Aug-14 12-Sep-14 25-Aug-14 18-Sep-14 4
CBCL3AB-0990 22 22 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA B CBC 19-Aug-14 18-Sep-14 28-Aug-14 29-Sep-14 7
CONL1SE-1516 25 25 R-I OVERHEAD MEP/FIRE PRO - LVL-1 SERVING CON 19-Aug-14 23-Sep-14 02-Sep-14 06-Oct-14 9
CONL1SL-1516 22 22 R-I OVERHEAD MEP/FIRE PRO - LVL-1 SOUTH LOBBY CON 19-Aug-14 18-Sep-14 15-Sep-14 14-Oct-14 18
CONL1ER-1516 20 20 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-E RESTRMS CON 19-Aug-14 16-Sep-14 16-Sep-14 13-Oct-14 19
CONL1AU-1516 25 25 R-I OVERHEAD MEP/FIRE PRO - LVL-1 AUDITRM CON 19-Aug-14 23-Sep-14 18-Sep-14 23-Oct-14 21
CBCSLEL-0910 5 5 FRAMING/INWALL ROUGH - SERV LVL CORR CBC 21-Aug-14 27-Aug-14 21-Aug-14 27-Aug-14 0
CBCALAL-0990 15 15 FINISH STAIR CORE ST1 - ALL LVLS CBC 21-Aug-14 11-Sep-14 21-Aug-14 11-Sep-14 0
ENCSWHL-0290 45 45 LANDSCAPING/SITE FURNISHINGS - SITEWORK ENC 22-Aug-14 04-Nov-14 03-Sep-14 14-Nov-14 6
CBCL3AA-0977 15 15 INSTALL OWNER FIXED FF&E - LVL-3 AREA-A CBC 22-Aug-14 12-Sep-14 09-Sep-14 29-Sep-14 11
CBCSLEL-0990 10 10 HANG/TAPE/FINISH/PAINT - SERV LVL CORR CBC 28-Aug-14 11-Sep-14 28-Aug-14 11-Sep-14 0
CBCL3AB-0977 15 15 INSTALL OWNER FIXED FF&E - LVL-3 AREA-B CBC 28-Aug-14 18-Sep-14 09-Sep-14 29-Sep-14 7
CBCL2AA-8880 8 8 CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBC 29-Aug-14 10-Sep-14 30-Sep-14 09-Oct-14 21
RESPHPH-0320 30 30 FORM/REINFORCE/PLACE/FINISH (INCL CORE COMP)- PENTHOUSE RES 04-Sep-14 22-Oct-14 04-Sep-14 22-Oct-14 0
RESESNE-0520 15 15 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - NORTH ELEV RES
04-Sep-14 29-Sep-14 22-Sep-14 14-Oct-14 10
RESESSE-0870 20 20 INSTALL CURTAIN WALL - SOUTH ELEV RES 04-Sep-14 06-Oct-14 25-Sep-14 24-Oct-14 12
PVNSLDO-0370 5 5 FORM/REINFORCE/PLACE COMD - SERV LVL DOCK PVN 05-Sep-14 12-Sep-14 19-Sep-14 26-Sep-14 8
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 15 of 19
Page 160
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
CBCL2AB-8880 8 8 CLEAN-UP/PRE PUNCH - LVL-2 AREA B CBC 05-Sep-14 16-Sep-14 30-Sep-14 09-Oct-14 17
CBCALAL-0991 20 20 FINISH STAIR CORE ST2 - ALL LVLS CBC 12-Sep-14 09-Oct-14 12-Sep-14 09-Oct-14 0
DATL3OR-0990 75 75 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 ORS DAT 12-Sep-14 31-Dec-14 12-Sep-14 31-Dec-14 0
CBCSLEL-8880 5 5 CLEAN-UP/PRE PUNCH - SERV LVL CORR CBC 12-Sep-14 18-Sep-14 03-Oct-14 09-Oct-14 15
DATL3HY-0990 30 30 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 HYBRID CVOR DAT 12-Sep-14 24-Oct-14 10-Oct-14 25-Nov-14 20
CONL1DI-0910 17 17 FRAMING/INWALL ROUGH - LVL-1 AR-D DINING CON 15-Sep-14 07-Oct-14 19-Sep-14 13-Oct-14 4
CBCL3AA-8880 8 8 CLEAN-UP/PRE PUNCH - LVL-3 AREA A CBC 15-Sep-14 24-Sep-14 30-Sep-14 09-Oct-14 11
RESESEE-0520 15 15 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - EAST ELEV RES 16-Sep-14 08-Oct-14 02-Oct-14 24-Oct-14 10
CONL1AE-0910 18 18 FRAMING/ ROUGH-IN - LVL-1 AR-E CON 17-Sep-14 10-Oct-14 02-Oct-14 28-Oct-14 11
CONL1SL-0910 18 18 FRAMING/INWALL ROUGH - LVL-1 SOUTH LOBBY CON 17-Sep-14 10-Oct-14 06-Oct-14 30-Oct-14 13
CONL1ER-0910 15 15 FRAMING/INWALL ROUGH - LVL-1 AR-E RESTRMS CON 17-Sep-14 07-Oct-14 14-Oct-14 04-Nov-14 19
CONL1AU-0910 17 17 FRAMING/INWALL ROUGH - LVL-1 AUDITRM CON 17-Sep-14 09-Oct-14 14-Oct-14 06-Nov-14 19
CONALAL-1455 60 60 INSTALL ELEVATOR CAR (GRIDLINE 25-26) - AREA C CON 18-Sep-14 15-Dec-14 16-Oct-14 14-Jan-15 20
CBCL3AB-8880 8 8 CLEAN-UP/PRE PUNCH - LVL-3 AREA B CBC 19-Sep-14 30-Sep-14 30-Sep-14 09-Oct-14 7
PVNESES-750 25 25 INSTALL CURTAIN WALL @ ELEVATOR/STAIR CORE - ALL ELEVATIONS PVN 26-Sep-14 04-Nov-14 29-Sep-14 06-Nov-14 1
PVNALAL-0555 20 20 ERECT STAIR 3A - ALL LVLS PVN 26-Sep-14 24-Oct-14 24-Oct-14 24-Nov-14 19
CONL1SE-0910 6 6 FRAMING/INWALL ROUGH - LVL-1 SERVING CON 30-Sep-14 07-Oct-14 13-Oct-14 21-Oct-14 9
CONL1SL-0920 16 16 HANG/TAPE/FINISH DRYWALL - LVL-1 SOUTH LOBBY CON 01-Oct-14 23-Oct-14 23-Oct-14 14-Nov-14 15
CONL1AU-0920 17 17 HANG/TAPE/FINISH DRYWALL - LVL-1 AUDITRM CON 01-Oct-14 24-Oct-14 29-Oct-14 24-Nov-14 19
RESESNE-0870 15 15 INSTALL CURTAIN WALL- NORTH ELEV RES 07-Oct-14 30-Oct-14 27-Oct-14 19-Nov-14 12
CONL1DI-0920 17 17 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D DINING CON 08-Oct-14 31-Oct-14 14-Oct-14 06-Nov-14 4
CONL1ER-0920 12 12 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-D AR-E RESTRMS CON 08-Oct-14 24-Oct-14 05-Nov-14 24-Nov-14 19
RESESWE-0520 15 15 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER (LEVEL 1-LEVEL 3) - WEST ELEV RES
09-Oct-14 03-Nov-14 27-Oct-14 19-Nov-14 10
CBCCOCO-9999 35 35 CREATE/COMPLETE FINAL PUNCHLIST - CBC 10-Oct-14 02-Dec-14 10-Oct-14 02-Dec-14 0
CONL1AE-0920 12 12 HANG/TAPE/FINISH DRYWALL - LVL-1 AR-E CON 13-Oct-14 29-Oct-14 29-Oct-14 14-Nov-14 11
CONL1SL-0990 40 40 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SOUTH LOBBY CON 13-Oct-14 10-Dec-14 31-Oct-14 30-Dec-14 13
CONL1SE-0920 18 18 HANG/TAPE/FINISH DRYWALL - LVL-1 SERVING CON 14-Oct-14 07-Nov-14 28-Oct-14 24-Nov-14 9
DATALCL-1592 60 60 TEST & BALANCE - DAT 17-Oct-14 15-Jan-15 17-Oct-14 15-Jan-15 0
DATALCL-1594 45 45 PRE-FUNCTIONAL TESTING/CORRECTIONS - DAT 17-Oct-14 23-Dec-14 17-Oct-14 23-Dec-14 0
DATL3CA-0977 20 20 INSTALL OWNER FIXED FF&E - LVL-3 CATH LABS DAT 17-Oct-14 17-Nov-14 10-Nov-14 09-Dec-14 15
RESPHPH-1600 7 7 SET ELECTRICAL EQUIPMENT - ROOF RES 23-Oct-14 31-Oct-14 03-Nov-14 12-Nov-14 7
CONALAL-1445 60 60 INSTALL ELEVATOR CAR (GRIDLINE 20-21) - AREA C CON 24-Oct-14 22-Jan-15 25-Nov-14 20-Feb-15 20
CONL1ER-0990 30 30 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D AR-E RESTRMS CON 27-Oct-14 09-Dec-14 25-Nov-14 07-Jan-15 19
CONL1AU-0990 30 30 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AUDITRM CON 27-Oct-14 09-Dec-14 25-Nov-14 07-Jan-15 19
RESSLIL-0320 15 15 ERECT INTERSTITIAL STEEL/TOPPING (INCL CURE)- INTERSTITIAL LVL RES 30-Oct-14 24-Nov-14 07-Nov-14 02-Dec-14 5
CONL1AE-0990 35 35 INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-E CON 30-Oct-14 19-Dec-14 17-Nov-14 07-Jan-15 11
RESESEE-0870 10 10 INSTALL CURTAIN WALL - EAST ELEV RES 31-Oct-14 17-Nov-14 21-Nov-14 08-Dec-14 12
CONL1DI-0990 35 35 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D DINING CON 03-Nov-14 23-Dec-14 07-Nov-14 30-Dec-14 4
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 16 of 19
Page 161
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
RESRLRL-0520 15 15 INSTALL ROOF CANOPY STRUCTURE - ROOF RES 04-Nov-14 28-Nov-14 21-Nov-14 15-Dec-14 10
PVNALAL-1400 44 44 INSTALL ELEVATOR - ALL LVLS PVN 05-Nov-14 09-Jan-15 07-Nov-14 13-Jan-15 2
PVNALAL-0991 44 44 FINISH STAIR CORES - ALL LVLS PVN 05-Nov-14 09-Jan-15 25-Nov-14 28-Jan-15 12
RESPHPH-1500 2 2 SET MECH EQUIPMENT - ROOF RES 10-Nov-14 12-Nov-14 10-Nov-14 12-Nov-14 0
CONL1SE-0990 30 30 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SERVING CON 10-Nov-14 23-Dec-14 25-Nov-14 07-Jan-15 9
RESPHPH-0510 20 20 ERECT PENTHOUSE STEEL/METAL DECK - ROOF RES 13-Nov-14 15-Dec-14 13-Nov-14 15-Dec-14 0
RESL2L2-0520 6 6 ERECT STRUCTURAL STEEL FOR LOW ROOF - LVL-2 RES 17-Nov-14 25-Nov-14 08-Dec-14 15-Dec-14 12
DATALAL-0992 30 30 FINISH STAIR CORE (ST2) - ALL LVLS DAT 18-Nov-14 31-Dec-14 26-Nov-14 08-Jan-15 5
DATALAL-0991 30 30 FINISH STAIR CORE (ST1) - ALL LVLS DAT 18-Nov-14 31-Dec-14 26-Nov-14 08-Jan-15 5
DATL3CA-8880 10 10 CLEAN-UP/PRE PUNCH - LVL-3 CATH LABS DAT 18-Nov-14 02-Dec-14 10-Dec-14 23-Dec-14 15
RESSLIL-1516 110 110 ROUGH-IN MEP/FIRE PROTECTION - INTER LVL RES 25-Nov-14 01-May-15 04-Dec-14 12-May-15 7
RESESWE-0870 15 15 INSTALL CURTAIN WALL - WEST ELEV RES 27-Nov-14 19-Dec-14 16-Dec-14 08-Jan-15 12
CONALAL-1465 60 60 INSTALL ELEVATOR CAR (GRIDLINE 28-29)- AREA D CON 02-Dec-14 27-Feb-15 31-Dec-14 27-Mar-15 20
CBCCOCO-1620 30 30 TEST & BALANCE - CBC 03-Dec-14 15-Jan-15 03-Dec-14 15-Jan-15 0
CBCCOCO-1594 20 20 PRE-FUNCTIONAL TESTING/CORRECTIONS - CBC 03-Dec-14 31-Dec-14 03-Dec-14 31-Dec-14 0
DATALCL-1596 45 45 FUNCTIONAL TESTING/CORRECTIONS - DAT 03-Dec-14 06-Feb-15 03-Dec-14 06-Feb-15 0
DATL3OR-0977 20 20 INSTALL OWNER FIXED FF&E - LVL-3 CATH LABS DAT 03-Dec-14 31-Dec-14 17-Dec-14 15-Jan-15 10
RESL1LA-1516 25 25 R-I OVERHEAD MEP/FIRE PRO - LVL-1 LAB RES 09-Dec-14 14-Jan-15 18-Dec-14 26-Jan-15 7
DATALAL-0993 30 30 FINISH STAIR CORE (ST3) - ALL LVLS DAT 10-Dec-14 23-Jan-15 17-Dec-14 30-Jan-15 5
DATALAL-0995 30 30 FINISH STAIR CORE (ST5) - ALL LVLS DAT 10-Dec-14 23-Jan-15 17-Dec-14 30-Jan-15 5
CONL1ER-8880 10 10 CLEAN-UP/PRE PUNCH - LVL-1 AR-D AR-E RESTRMS CON 10-Dec-14 23-Dec-14 08-Jan-15 22-Jan-15 19
CONL1AU-8880 10 10 CLEAN-UP/PRE PUNCH - LVL-1 AUDITRM CON 10-Dec-14 23-Dec-14 08-Jan-15 22-Jan-15 19
CONL1SL-8880 15 15 CLEAN-UP/PRE PUNCH - LVL-1 SOUTH LOBBY CON 11-Dec-14 02-Jan-15 31-Dec-14 22-Jan-15 13
RESRLRL-0750 20 20 PARAPET/BLOCKING/ROOFING - ROOF RES 16-Dec-14 16-Jan-15 16-Dec-14 16-Jan-15 0
RESL1LA-0910 20 20 FRAMING/INWALL ROUGH - LVL-1 LAB RES 16-Dec-14 14-Jan-15 26-Dec-14 26-Jan-15 7
RESESPH-0520 15 15 ERECT EXTERIOR STUDS/SHEATHING/VAPOR BARRIER - PENTHOUSE ELEV RES 16-Dec-14 08-Jan-15 31-Dec-14 23-Jan-15 9
RESPHME-0420 15 15 LAY CMU WALLS - PENTHOUSE MECH RES 16-Dec-14 07-Jan-15 02-Jan-15 23-Jan-15 11
DATALCL-9999 30 30 CREATE/COMPLETE FINAL PUNCHLIST - DAT 17-Dec-14 30-Jan-15 24-Dec-14 06-Feb-15 5
CONL1AE-8880 10 10 CLEAN-UP/PRE PUNCH/FINAL PUNCH - LVL-1 AR-E CON 22-Dec-14 06-Jan-15 08-Jan-15 22-Jan-15 11
RESESWE-0780 5 5 INSTALL METAL PANEL - WEST ELEV RES 22-Dec-14 29-Dec-14 09-Jan-15 16-Jan-15 12
CONL1DI-8880 15 15 CLEAN-UP/PRE PUNCH - LVL-1 AR-D DINING CON 24-Dec-14 15-Jan-15 31-Dec-14 22-Jan-15 4
CONL1SE-8880 10 10 CLEAN-UP/PRE PUNCH - LVL-1 SERVING CON 24-Dec-14 08-Jan-15 08-Jan-15 22-Jan-15 9
CONALCO-1592 20 20 TEST & BALANCE - CON 24-Dec-14 23-Jan-15 08-Jan-15 05-Feb-15 9
CONALCO-1594 15 15 PRE-FUNCTIONAL TESTING/CORRECTIONS - CON 24-Dec-14 15-Jan-15 08-Jan-15 29-Jan-15 9
CBCCOCO-1596 25 25 FUNCTIONAL TESTING/CORRECTIONS - CBC 02-Jan-15 06-Feb-15 02-Jan-15 06-Feb-15 0
DATL3OR-8880 10 10 CLEAN-UP/PRE PUNCH - LVL-3 ORS DAT 02-Jan-15 15-Jan-15 16-Jan-15 30-Jan-15 10
RESPHME-1516 45 45 ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECH RES 09-Jan-15 16-Mar-15 26-Jan-15 30-Mar-15 10
RESESPH-0710 5 5 INSTALL LOUVERS - PENTHOUSE ELEV RES 09-Jan-15 16-Jan-15 05-Feb-15 13-Feb-15 17
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 17 of 19
Page 162
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
PVNCOCO-1592 20 20 TEST & BALANCE - PVN 12-Jan-15 10-Feb-15 14-Jan-15 12-Feb-15 2
PVNCOCO-1594 15 15 PRE-FUNCTIONAL TESTING/CORRECTIONS - PVN 12-Jan-15 02-Feb-15 14-Jan-15 04-Feb-15 2
PVNCOCO-9999 20 20 CREATE/COMPLETE FINAL PUNCHLIST - PVN 12-Jan-15 10-Feb-15 29-Jan-15 26-Feb-15 12
RESL2LA-1516 25 25 R-I OVERHEAD MEP/FIRE PRO - LVL-2 LAB RES 15-Jan-15 20-Feb-15 03-Feb-15 10-Mar-15 12
CONALCO-9999 20 20 CREATE/COMPLETE FINAL PUNCHLIST - CON 16-Jan-15 16-Feb-15 23-Jan-15 20-Feb-15 4
CONALCO-1596 15 15 FUNCTIONAL TESTING/CORRECTIONS - CON 16-Jan-15 06-Feb-15 30-Jan-15 20-Feb-15 9
RESL1LA-0920 15 15 HANG/TAPE/FINISH DRYWALL - LVL-1 LAB RES 20-Jan-15 10-Feb-15 20-Jan-15 10-Feb-15 0
RESESPH-0777 7 7 INSTALL METAL PANELS - PENTHOUSE ELEV RES 20-Jan-15 28-Jan-15 16-Feb-15 24-Feb-15 17
RESL1LA-0990 45 45 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 LAB RES 27-Jan-15 31-Mar-15 27-Jan-15 31-Mar-15 0
RESPHEL-0910 10 10 FRAMING/INWALL ROUGH - PENTHOUSE ELEC RES 27-Jan-15 10-Feb-15 11-Feb-15 24-Feb-15 10
PVNCOCO-1596 15 15 FUNCTIONAL TESTING/CORRECTIONS - PVN 03-Feb-15 24-Feb-15 05-Feb-15 26-Feb-15 2
CBCCOCO-1599 20 20 BUILDING FLUSH - CBC 07-Feb-15 26-Feb-15 07-Feb-15 26-Feb-15 0
DATALCL-1599 20 20 BUILDING FLUSH - DAT 07-Feb-15 26-Feb-15 07-Feb-15 26-Feb-15 0
RESPHEL-0920 10 10 HANG/TAPE/FINISH DRYWALL - PENTHOUSE ELEC RES 11-Feb-15 24-Feb-15 25-Feb-15 10-Mar-15 10
COMMISS-1596 45 45 INTEGRATED SYSTEMS TEST - FULL CAMPUS 12-Feb-15 28-Mar-15 12-Feb-15 28-Mar-15 0
RESL2LA-0910 20 20 FRAMING/INWALL ROUGH - LVL-2 LAB RES 16-Feb-15 13-Mar-15 04-Mar-15 31-Mar-15 12
CONALCO-1599 35 35 BUILDING FLUSH - ALL LVLS CON 17-Feb-15 23-Mar-15 22-Feb-15 28-Mar-15 5
ZZZZPVN-9999 0 0 FINISH PVN CONSTRUCTION (finish milestone) 24-Feb-15 26-Feb-15 2
RESPHEL-1620 65 65 ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - PENTHOUSE ELEC RES 25-Feb-15 27-May-15 11-Mar-15 10-Jun-15 10
ZZZZDAT-9999 0 0 FINISH DAT CONSTRUCTION (finish milestone) 26-Feb-15 26-Feb-15 0
ZZZZCBC-9999 0 0 FINISH CBC CONSTRUCTION (finish milestone) 26-Feb-15 26-Feb-15 0
RESL2LA-0920 15 15 HANG/TAPE/FINISH DRYWALL - LVL-2 LAB RES 02-Mar-15 20-Mar-15 01-Apr-15 21-Apr-15 22
RESPHME-1520 60 60 CONNECT/PIPE-UP MECH EQUIP - PENTHOUSE MECH RES 17-Mar-15 09-Jun-15 15-Apr-15 09-Jul-15 21
ZZZZCON-9999 0 0 FINISH CON CONSTRUCTION (finish milestone) 23-Mar-15 28-Mar-15 5
CBS-0100 10 10 KT AND VA VACATE CBS LEVEL 2 24-Mar-15 02-Apr-15 28-Mar-15 06-Apr-15 4
ZZZZZZZ-10009 0 0 CAMPUS SUBSTANTIAL COMPLETION LESS THE RESEARCH BUILDING (finish milestone) 28-Mar-15* 28-Mar-15 0
RESL2LA-0990 45 45 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 LAB RES 01-Apr-15 03-Jun-15 01-Apr-15 03-Jun-15 0
CBSDEIN-4100 2 2 LEVEL 2 SALVAGE - INT DEMO CBS 03-Apr-15 06-Apr-15 07-Apr-15 08-Apr-15 2
CBSDEIN-2470 3 3 LEVEL 2 DEMOLITION - INT DEMO CBS 10-Apr-15 14-Apr-15 14-Apr-15 16-Apr-15 2
CBSL2L2-3020 10 10 MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-2 CBS 15-Apr-15 28-Apr-15 17-Apr-15 30-Apr-15 2
CBSL2L2-3030 5 5 FIRE SPRINKLER ROUGH-IN - LVL-2 CBS 29-Apr-15 05-May-15 01-May-15 07-May-15 2
RESALAL-1400 60 60 INSTALL ELEVATOR SE13 - ALL LVLS RES 29-Apr-15 23-Jul-15 28-May-15 20-Aug-15 20
RESALAL-1401 60 60 INSTALL ELEVATOR SE12- ALL LVLS RES 29-Apr-15 23-Jul-15 28-May-15 20-Aug-15 20
CBSL2L2-3040 5 5 ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-2 CBS 06-May-15 12-May-15 08-May-15 14-May-15 2
CBSL2L2-3050 12 12 FRAMING - LVL-2 CBS 13-May-15 29-May-15 15-May-15 02-Jun-15 2
CBSL2L2-3060 10 10 WALL ROUGH-IN - LVL-2 CBS 22-May-15 05-Jun-15 27-May-15 09-Jun-15 2
EEEERES-0000 0 0 RES BLDG AVAILABLE FOR ENERGIZE 27-May-15 10-Jun-15 10
RESPHME-1641 20 20 START-UP ELECTRICAL SYSTEMS - PENT MECH RES 28-May-15 24-Jun-15 11-Jun-15 09-Jul-15 10
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 18 of 19
Page 163
HOT LIST
Activity ID
OrigDur
RemDur
Area Code TradeCode
Activity Name Start Finish Late Start Late Finish
TotalFloat
RESL3LA-0990 45 45 INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 LAB RES 04-Jun-15 06-Aug-15 04-Jun-15 06-Aug-15 0
CBSL2L2-3070 15 15 DRYWALL / FINISH - LVL-2 CBS 08-Jun-15 26-Jun-15 10-Jun-15 30-Jun-15 2
RESPHME-1590 15 15 START-UP MECH EQUIP - PENT MECH RES 25-Jun-15 16-Jul-15 10-Jul-15 30-Jul-15 10
CBSL2L2-3080 6 6 INTERIOR PAINT - LVL-2 CBS 29-Jun-15 07-Jul-15 01-Jul-15 09-Jul-15 2
CBSL2L2-3090 7 7 CEILING GRID- LVL-2 CBS 08-Jul-15 16-Jul-15 10-Jul-15 20-Jul-15 2
RESL3LA-0977 20 20 INSTALL OWNER FIXED FF&E - LVL-3 LAB RES 10-Jul-15 06-Aug-15 10-Jul-15 06-Aug-15 0
CBSL2L2-3110 13 13 FLOORING - LVL-2 CBS 13-Jul-15 29-Jul-15 15-Jul-15 31-Jul-15 2
CBSL2L2-3100 5 5 MILLWORK - LVL-2 CBS 17-Jul-15 23-Jul-15 21-Jul-15 27-Jul-15 2
RESCOCL-1592 20 20 TEST & BALANCE - RES 24-Jul-15 20-Aug-15 31-Jul-15 27-Aug-15 5
RESCOCO-1594 15 15 PRE-FUNCTIONAL TESTING/CORRECTIONS - RES 24-Jul-15 13-Aug-15 31-Jul-15 20-Aug-15 5
CBSL2L2-3120 6 6 MEP TRIMOUT - LVL-2 CBS 30-Jul-15 06-Aug-15 03-Aug-15 10-Aug-15 2
RESL3LA-8880 10 10 CLEAN-UP/PRE PUNCH - LVL-3 LAB RES 07-Aug-15 20-Aug-15 07-Aug-15 20-Aug-15 0
CBSL2L2-3980 3 3 TEST AND BALANCE - LVL-2 CBS 07-Aug-15 11-Aug-15 11-Aug-15 13-Aug-15 2
CBSL2L2-3140 5 5 PUNCHLIST - LVL-2 CBS 12-Aug-15 18-Aug-15 14-Aug-15 20-Aug-15 2
RESCOCO-1596 20 20 FUNCTIONAL TESTING/CORRECTIONS - RES 14-Aug-15 11-Sep-15 21-Aug-15 18-Sep-15 5
CBSCOCO-4020 10 10 WHOLE BUILDING TEST AND BALANCE - ALL LVLS CBS 19-Aug-15 01-Sep-15 21-Aug-15 03-Sep-15 2
RESCOCL-9999 20 20 CREATE/COMPLETE FINAL PUNCHLIST - RES 21-Aug-15 18-Sep-15 21-Aug-15 18-Sep-15 0
CBSCOCO-2120 20 20 COMMISSIONING - ALL LVLS CBS 02-Sep-15 30-Sep-15 04-Sep-15 02-Oct-15 2
RESCOCL-1599 15 15 BUILDING FLUSH - RES 19-Sep-15 03-Oct-15 19-Sep-15 03-Oct-15 0
ZZZZCBS-9999 0 0 FINISH CBS CONSTRUCTION (finish milestone) 30-Sep-15 03-Oct-15 3
ZZZZRES-9999 0 0 FINISH RES CONSTRUCTION (finish milestone) 03-Oct-15 03-Oct-15 0
ZZZZZZZ-10019 0 0 CAMPUS FINAL COMPLETION (finish milestone) 03-Oct-15* 03-Oct-15 0
DENVER VA MEDICAL CENTER - FTP SCHEDULE Report Date 12-Aug-11 17:16
Project Start 01-Nov-10Project Finish 03-Oct-15
Data Date 26-Jul-11
Page 19 of 19
Page 164
Activity ID OrigDur
RemDur
DaysLeft
Late Start Actual Start Actual Finish Building Activity Name %Complete
MILESTONESMILESTONESMILESTONESMILESTONESMILESTONESMILESTONESMILESTONESMILESTONESMILESTONESMILESTONESAAAA-1040 0 0 15-Sep-11 MIL NTP FOR POTHOLING FOR SHORING TIE-BACKS (start milestone) 0%
AAAA-1030 0 0 15-Sep-11 MIL NTP FOR POTHOLING FOR WHEELING WATERLINE (start milestone) 0%
CAISSONSCAISSONSCAISSONSCAISSONSCAISSONSCAISSONSCAISSONSCAISSONSCAISSONSCAISSONSCBSSTST-4040 5 5 28-Jul-11 CBS DRILLED PIERS - CANOPY - STRUCTURE CBS 0%
CBSSTST-4050 5 5 20-Aug-11 CBS DRILLED PIERS - BUILDING ADDITION - STRUCTURE CBS 0%
ELECTRICALELECTRICAL EQELECTRICAL EQUIPMELECTRICAL EQUIPMENTELECTRICAL EQUIPMENTELECTRICAL EQUIPMENTELECTRICAL EQUIPMENTELECTRICAL EQUIPMENTELECTRICAL EQUIPMENTELECTRICAL EQUIPMENTCBSL1L1-3303 20 20 10-Sep-11 CBS NEW ELECTRICAL ROOM ROUGH-IN - LVL-1 CBS 0%
VA REVIEW/AVA REVIEW/APPVA REVIEW/APPROVVA REVIEW/APPROVE SHVA REVIEW/APPROVE SHOP DRAVA REVIEW/APPROVE SHOP DRAWINGS/VA REVIEW/APPROVE SHOP DRAWINGS/PRODUCTVA REVIEW/APPROVE SHOP DRAWINGS/PRODUCT DATVA REVIEW/APPROVE SHOP DRAWINGS/PRODUCT DATAVA REVIEW/APPROVE SHOP DRAWINGS/PRODUCT DATAP-CBS-4440 30 11 03-Aug-11 27-Jun-11 CBS SUBMITTAL REVIEW (interior steel) - CBS-1 63.33%
C-RF3-1408 30 16 07-Dec-12 12-Jul-11 CBS VA APPROVAL OF ABATEMENT PLAN - RFP 3 46.67%
P-CBS-4480 15 15 22-Sep-11 CBS VA/JVT REVIEW INITIAL MATERIAL SUBMITTAL (mechanical) - CBS-1 0%
P-CBS-4380 20 20 29-Aug-11 CBS SUBMITTAL REVIEW (structural steel) - CBS-1 0%
AAAA-5580 0 0 21-Nov-11 VA APPROVE LOW VOLTAGE CONTRACTOR DESIGN ASSIST 0%
AAAA-4800 0 0 13-Dec-11 VA APPROVE MECHANICAL AND PLUMBING CONTRACTOR DESIGN ASSIST 0%
AAAA-4810 0 0 07-May-12 VA APPROVE ELECTRICAL CONTRACTOR DESIGN ASSIST 0%
P-CD3-3660 0 0 12-Jun-12 VA APPROVE CURTAIN WALL CONTRACTOR DESIGN ASSIST 0%
P-CBS-4830 15 15 14-Oct-11 CBS VA/JVT REVIEW BALANCE OF MATERIAL SUBMITTALS (mechanical) - CBS-1 0%
P-CBS-4280 30 30 13-Sep-11 CBS SUBMITTAL VA REVIEW (electrical) - CBS-1 0%
KT REVIEW/AKT REVIEW/APPRKT REVIEW/APPROVKT REVIEW/APPROVE SHKT REVIEW/APPROVE SHOP DRAKT REVIEW/APPROVE SHOP DRAWINGS/PKT REVIEW/APPROVE SHOP DRAWINGS/PRODUCTKT REVIEW/APPROVE SHOP DRAWINGS/PRODUCT DATKT REVIEW/APPROVE SHOP DRAWINGS/PRODUCT DATAKT REVIEW/APPROVE SHOP DRAWINGS/PRODUCT DATAP-CBS-4820 10 10 08-Sep-11 CBS KT REVIEW INITIAL MATERIAL SUBMITTAL (mechanical) - CBS-1 0%
P-CBS-4230 10 10 29-Sep-11 CBS KT REVIEW BALANCE OF MATERIAL SUBMITTALS (mechanical) - CBS-1 0%
VA ACTIVITIEVA ACTIVITIES/MVA ACTIVITIES/MILESVA ACTIVITIES/MILESTONVA ACTIVITIES/MILESTONESVA ACTIVITIES/MILESTONESVA ACTIVITIES/MILESTONESVA ACTIVITIES/MILESTONESVA ACTIVITIES/MILESTONESVA ACTIVITIES/MILESTONESP-CBS-4100 0 0 VA APPROVES FIRM FIXED PRICE 100% AND ISSUES MOD - CBS-1 0%
P-CBS-4090 15 15 19-Jan-12 CBS VA REVIEWS FIRM FIXED PRICE 100% CD - CBS-1 0%
STR2-3680 15 15 16-Sep-11 JVT REVISE DOCUMENTS 95% CD - STR-2 0%
AAAA-1010 0 0 06-Sep-11 MIL NTP FOR CONSTRUCTION 0%
AAAA-4630 0 0 VA PROVIDES CONSENT TO SUBCONTRACT - DESIGN ASSIST SUBCONTRACTORS 0%
AAAA-5600 0 0 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1A 0%
DENVER VA MEDICAL CENTER - FTP SCHEDULE
LT09 - 4 WEEK LOOKAHEAD BY SYSTEM KIEWIT-TURNER
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11
Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 5 Date Revision Checked Approved
Page 165
Activity ID OrigDur
RemDur
DaysLeft
Late Start Actual Start Actual Finish Building Activity Name %Complete
AAAA-5590 0 0 VA PROVIDES CONSENT TO SUBCONTRACT - STR-1 0%
STR2-3690 5 5 07-Oct-11 JVT QA/QC DOCUMENTS 95% CD - STR-2 0%
OSI-4410 5 5 06-Apr-12 VA REVIEWS/SIGN-OFF ON BID TABS- OSI-1 0%
AWARD SUBAWARD SUBCONAWARD SUBCONTRAAWARD SUBCONTRACTSAWARD SUBCONTRACTSAWARD SUBCONTRACTSAWARD SUBCONTRACTSAWARD SUBCONTRACTSAWARD SUBCONTRACTSAWARD SUBCONTRACTSSTR1-5200 20 20 23-Sep-11 AWARD ROOF DRAIN CONTRACT - CBS ROOF DRAIN 0%
STR1-5650 20 20 08-Nov-11 AWARD CONTRACT - DEWATERING 0%
STR1-5420 20 20 07-Sep-11 AWARD SHORING CONTRACT 0%
P-CD3-4740 20 20 03-Feb-15 CBS AWARD CURTAINWALL - CBS-1 WITH CS-1/IFO-3 DESIGN PKG 0%
STR1A-5020 20 20 18-Nov-11 AWARD DRILLED PIERS CONTRACT - STR-1A/IFO-2 0%
STR1-5330 20 20 20-Dec-11 AWARD CONTRACT TO SUBCONTRACTOR - TEMP ELEC 0%
PREPARE/SUPREPARE/SUBMPREPARE/SUBMIT SHPREPARE/SUBMIT SHOP PREPARE/SUBMIT SHOP DRAWINPREPARE/SUBMIT SHOP DRAWINGS/PROPREPARE/SUBMIT SHOP DRAWINGS/PRODUCT DAPREPARE/SUBMIT SHOP DRAWINGS/PRODUCT DATAPREPARE/SUBMIT SHOP DRAWINGS/PRODUCT DATAPREPARE/SUBMIT SHOP DRAWINGS/PRODUCT DATAP-CBS-4370 20 6 19-Aug-11 14-Jun-11 CBS SUBMITTAL DEVELOPMENT (structural steel) - CBS-1 70%
P-CBS-4220 20 9 16-Sep-11 12-Jul-11 CBS SUBMITTAL DEVELOPMENT BALANCE OF MATERIAL (mechanical) - CBS-1 55%
P-CBS-4270 20 16 19-Aug-11 24-Jun-11 CBS SUBMITTAL DEVELOPMENT (electrical) - CBS-1 20%
STR1A-4930 20 20 13-Dec-11 PREPARE/SUBMIT DUCTBANK/VAULT SHOP/DRAINAGE DRAWINGS (CON) - STR-1A/IFO-2 0%
FABRICATE/FABRICATE/DELFABRICATE/DELIVERFABRICATE/DELIVER MATFABRICATE/DELIVER MATERIALSFABRICATE/DELIVER MATERIALS/EQUIPMFABRICATE/DELIVER MATERIALS/EQUIPMENTFABRICATE/DELIVER MATERIALS/EQUIPMENTFABRICATE/DELIVER MATERIALS/EQUIPMENTFABRICATE/DELIVER MATERIALS/EQUIPMENTP-CBS-4450 20 20 18-Aug-11 CBS MATERIAL PROCUREMENT (interior steel) - CBS-1 0%
P-CBS-4460 0 0 CBS MATERIALS ARRIVE (interior steel) - CBS-1 0%
P-CBS-4240 15 15 14-Oct-11 CBS INITIAL MATERIAL PROCUREMENT (mechanical) - CBS-1 0%
P-CBS-4390 25 25 27-Sep-11 CBS MATERIAL PROCUREMENT (structural steel) - CBS-1 0%
CBS TEMPOCBS TEMPORARCBS TEMPORARY UTCBS TEMPORARY UTILITICBS TEMPORARY UTILITIES ANDCBS TEMPORARY UTILITIES AND BLDG MCBS TEMPORARY UTILITIES AND BLDG MAINTENACBS TEMPORARY UTILITIES AND BLDG MAINTENANCECBS TEMPORARY UTILITIES AND BLDG MAINTENANCECBS TEMPORARY UTILITIES AND BLDG MAINTENANCECBSTUTU-3790 5 5 13-Jan-12 CBS INSTALL TEMPERARY BOILER - TEMP UTILITIES CBS 0%
CBSTUTU-3840 557 609 01-Jul-11 01-Jul-11 CBS MAINTAIN TEMPERARY ELECTRICAL / COMMS - TEMP UTILITIES CBS 0%
CBSTUTU-3830 585 585 23-Jan-12 CBS MAINTAIN TEMPERARY BOILER - TEMP UTILITIES CBS 0%
CBSTUTU-3850 514 623 20-May-11 20-May-11 CBS MAINTAIN TEMPERARY NATURAL GAS - TEMP UTILITIES CBS 0%
CBSTUTU-3870 617 617 23-Jan-12 CBS MAINTAIN TEMPERARY HVAC - TEMP UTILITIES CBS 0%
PLUMBING RPLUMBING ROUGPLUMBING ROUGH-INPLUMBING ROUGH-IN UNPLUMBING ROUGH-IN UNDERSLAPLUMBING ROUGH-IN UNDERSLABPLUMBING ROUGH-IN UNDERSLABPLUMBING ROUGH-IN UNDERSLABPLUMBING ROUGH-IN UNDERSLABPLUMBING ROUGH-IN UNDERSLABCBSL1L1-3285 10 10 11-Aug-11 CBS BELOW GRADE PLUMBING ROUGH-IN - LVL-1 CBS 0%
SERVICE RESERVICE RELOCSERVICE RELOCATIOSERVICE RELOCATIONSSERVICE RELOCATIONSSERVICE RELOCATIONSSERVICE RELOCATIONSSERVICE RELOCATIONSSERVICE RELOCATIONSSERVICE RELOCATIONS
DENVER VA MEDICAL CENTER - FTP SCHEDULE
LT09 - 4 WEEK LOOKAHEAD BY SYSTEM KIEWIT-TURNER
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11
Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 2 of 5 Date Revision Checked Approved
Page 166
Activity ID OrigDur
RemDur
DaysLeft
Late Start Actual Start Actual Finish Building Activity Name %Complete
CBSSWSW-4140 7 7 27-Jul-11 CBS RELOCATE FIRE DEPARTMENT CONNECTION - SITEWORK CBS 0%
OVERALL DUOVERALL DURATOVERALL DURATIONOVERALL DURATIONSOVERALL DURATIONSOVERALL DURATIONSOVERALL DURATIONSOVERALL DURATIONSOVERALL DURATIONSOVERALL DURATIONSXXXXCBS-0500 936 1528 09-May-11 09-May-11 MIL CBS OVERALL DURATION 0%
POTHOLINGPOTHOLINGPOTHOLINGPOTHOLINGPOTHOLINGPOTHOLINGPOTHOLINGPOTHOLINGPOTHOLINGPOTHOLINGSITSWSW-0150 10 10 15-Sep-11 SIT LOCATE ALL UTILITIES - POTHOLING 0%
CITY OF AURCITY OF AURORACITY OF AURORA APCITY OF AURORA APPROCITY OF AURORA APPROVALCITY OF AURORA APPROVALCITY OF AURORA APPROVALCITY OF AURORA APPROVALCITY OF AURORA APPROVALCITY OF AURORA APPROVALOSI-4810 129 84 11-Feb-14 10-Feb-11 CITY OF AURORA PLAN REVIEW AND APPROVAL - OSI-1 34.88%
OSI-4850 62 84 23-Aug-11 10-Feb-11 CITY OF AURORA WHEELING WATER LINE REVIEW AND AP - OSI-1 0%
PRICINGPRICINGPRICINGPRICINGPRICINGPRICINGPRICINGPRICINGPRICINGPRICINGSTR1-5230 25 25 14-Sep-11 SUBCONTRACTOR PRICING (earthwork) - STR-1 0%
CREDIT-1418 25 25 14-Sep-11 RFP3 SUBCONTRACTOR PRICING FOR CREDIT UNION DEMO 0%
OSI-4400 25 2 04-Apr-12 18-Apr-11 PREPARE/SUBMIT BID TABS TO VA - OSI-1 92%
STR1-5700 15 15 20-Oct-11 PREPARE BID TABS (earthwork) - STR-1 0%
CREDIT-1468 15 15 20-Oct-11 RFP3 PREPARE BID TABS - CREDIT UNION DEMO 0%
STR2-4830 14 14 17-Oct-11 SUBCONTRACTOR PRICING - STR-2 0%
STR1-5560 15 15 12-Sep-11 SUBCONTRACTOR PRICING - TEMP REDIRECTION OF STORMWATER 0%
SITSWTP-5230 15 15 07-Sep-11 SIT SUBCONTRACTOR PRICING - TEMP PARKING CBS 0%
SCHEDULE CSCHEDULE CREASCHEDULE CREATIOSCHEDULE CREATIONSCHEDULE CREATIONSCHEDULE CREATIONSCHEDULE CREATIONSCHEDULE CREATIONSCHEDULE CREATIONSCHEDULE CREATIONSTR2-3710 60 60 10-Mar-13 PREPARE/SUBMIT CONSTRUCTION SCHEDULE (90-days cost only) - STR-2 0%
ROOFING ACROOFING ACTIVROOFING ACTIVITIESROOFING ACTIVITIESROOFING ACTIVITIESROOFING ACTIVITIESROOFING ACTIVITIESROOFING ACTIVITIESROOFING ACTIVITIESROOFING ACTIVITIESCBSRLRL-3550 5 5 24-Jul-15 CBS CANOPY ROOFING - ROOF CBS 0%
DEMOLITIONDEMOLITIONDEMOLITIONDEMOLITIONDEMOLITIONDEMOLITIONDEMOLITIONDEMOLITIONDEMOLITIONDEMOLITIONCBSDEES-2440 10 10 01-Jul-15 CBS SKIN PENETRATIONS FOR TRELLIS ATTACHMENT - EXT DEMO CBS 0%
C-DEM-1400 20 20 17-Jan-13 CBS APARTMENT COMPLEX ABATEMENT 0%
MOBILIZATIOMOBILIZATION AMOBILIZATION ACTIVMOBILIZATION ACTIVITIESMOBILIZATION ACTIVITIESMOBILIZATION ACTIVITIESMOBILIZATION ACTIVITIESMOBILIZATION ACTIVITIESMOBILIZATION ACTIVITIESMOBILIZATION ACTIVITIESC-DEM-1409 10 10 02-Jan-13 CBS MOBILIZE ABATEMENT 0%
STR1-5240 15 15 21-Oct-11 KT PREPARES EROSION CONTROL PLAN - FILE FOR NOI 0%
W-OSI-5310 20 20 13-Sep-11 AWARD CONTRACT - WHEELING WATERLINE 0%
DENVER VA MEDICAL CENTER - FTP SCHEDULE
LT09 - 4 WEEK LOOKAHEAD BY SYSTEM KIEWIT-TURNER
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11
Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 3 of 5 Date Revision Checked Approved
Page 167
Activity ID OrigDur
RemDur
DaysLeft
Late Start Actual Start Actual Finish Building Activity Name %Complete
UTILITIESUTILITIESUTILITIESUTILITIESUTILITIESUTILITIESUTILITIESUTILITIESUTILITIESUTILITIESC-DEM-1411 5 5 08-Feb-13 CBS UTILITY DISCONNECTS 0%
SITWSSW-0288 15 15 15-Sep-11 OSI SURVEYOR MAP/PROVIDE AS-BUILTS - POTHOLING 0%
DESIGN ACTDESIGN ACTIVITDESIGN ACTIVITIESDESIGN ACTIVITIESDESIGN ACTIVITIESDESIGN ACTIVITIESDESIGN ACTIVITIESDESIGN ACTIVITIESDESIGN ACTIVITIESDESIGN ACTIVITIESSTR2-3660 5 5 01-Sep-11 KT PROVIDES RED LINE COMMENTS 95% CD - STR-2 0%
STR2-3670 5 5 09-Sep-11 PAGE FLIP 95% CD - STR-2 0%
CS1-3040 78 25 17-Aug-11 18-Apr-11 95% DESIGN - CS-1/IFO-3 67.95%
CS1-3510 0 0 95% CD DESIGN COMPLETE - CS-1/IFO-3 0%
STR2-3610 0 0 100% CD DESIGN COMPLETION - STR-2 0%
CS1-3660 15 15 22-Sep-11 KT PROVIDES RED LINE COMMENTS 95% CD - CS-1/IFO-3 0%
IFO-3040 87 87 30-Dec-11 95% DESIGN - IFO-1 0%
OVERHEAD OVERHEAD MEPOVERHEAD MEP/FIROVERHEAD MEP/FIRE PROVERHEAD MEP/FIRE PROTECTIOVERHEAD MEP/FIRE PROTECTION ROUOVERHEAD MEP/FIRE PROTECTION ROUGH-IN ACOVERHEAD MEP/FIRE PROTECTION ROUGH-IN ACTIVITOVERHEAD MEP/FIRE PROTECTION ROUGH-IN ACTIVITIESOVERHEAD MEP/FIRE PROTECTION ROUGH-IN ACTIVITIESCBSINL4-2490 15 15 05-Aug-11 CBS MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-4 CBS 0%
CBSL3L3-2760 15 15 05-Aug-11 CBS MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-3 CBS 0%
CBSL1L1-3280 15 15 26-Oct-11 CBS MECHANICAL / PLUMBING OVERHEAD ROUGH-IN - LVL-1 CBS 0%
CBSL1L1-3290 5 5 23-Aug-11 CBS FIRE SPRINKLER ROUGH-IN - LVL-1 CBS 0%
CBSL3L3-2770 5 5 23-Aug-11 CBS FIRE SPRINKLER ROUGH-IN - LVL-3 CBS 0%
CBSINL4-2500 10 10 23-Aug-11 CBS FIRE SPRINKLER ROUGH-IN - LVL-4 CBS 0%
CBSL3L3-4030 10 10 06-Jan-12 CBS NEW EXHAUST FANS - LVL-3 CBS 0%
CBSL1L1-3300 10 10 29-Aug-11 CBS ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-1 CBS 0%
CBSINL4-2510 10 10 03-Sep-11 CBS ELECTRICAL / IT OVERHEAD ROUGH-IN - LVL-4 CBS 0%
EXCAVATIONEXCAVATION ACEXCAVATION ACTIVIEXCAVATION ACTIVITIESEXCAVATION ACTIVITIESEXCAVATION ACTIVITIESEXCAVATION ACTIVITIESEXCAVATION ACTIVITIESEXCAVATION ACTIVITIESEXCAVATION ACTIVITIESCBSSTST-3760 15 15 03-Aug-11 CBS EXCAVATION AND SHORING - STRUCTURE CBS 0%
FOUNDATIOFOUNDATION ACFOUNDATION ACTIVIFOUNDATION ACTIVITIESFOUNDATION ACTIVITIESFOUNDATION ACTIVITIESFOUNDATION ACTIVITIESFOUNDATION ACTIVITIESFOUNDATION ACTIVITIESFOUNDATION ACTIVITIESCBSSTST-2330 15 15 30-Jun-15 CBS CANOPY FOUNDATION - STRUCTURE CBS 0%
CBSSTST-2340 16 16 26-Aug-11 CBS STAIR CORE AND ELEVATOR FOUNDATION - STRUCTURE CBS 0%
WALL FRAMWALL FRAMING/WALL FRAMING/INWAWALL FRAMING/INWALL WALL FRAMING/INWALL R-I ACTWALL FRAMING/INWALL R-I ACTIVITIESWALL FRAMING/INWALL R-I ACTIVITIESWALL FRAMING/INWALL R-I ACTIVITIESWALL FRAMING/INWALL R-I ACTIVITIESWALL FRAMING/INWALL R-I ACTIVITIESCBSSTST-2400 15 15 16-Sep-11 CBS INTERIOR STEEL FRAMING LEVEL 1,2,3,4 - STRUCTURE CBS 0%
STEEL STRUSTEEL STRUCTUSTEEL STRUCTURESTEEL STRUCTURESTEEL STRUCTURESTEEL STRUCTURESTEEL STRUCTURESTEEL STRUCTURESTEEL STRUCTURESTEEL STRUCTURE
DENVER VA MEDICAL CENTER - FTP SCHEDULE
LT09 - 4 WEEK LOOKAHEAD BY SYSTEM KIEWIT-TURNER
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11
Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 4 of 5 Date Revision Checked Approved
Page 168
Activity ID OrigDur
RemDur
DaysLeft
Late Start Actual Start Actual Finish Building Activity Name %Complete
CBSSTST-2380 5 5 18-Jul-15 CBS CANOPY FRAMING - STRUCTURE CBS 0%
DENVER VA MEDICAL CENTER - FTP SCHEDULE
LT09 - 4 WEEK LOOKAHEAD BY SYSTEM KIEWIT-TURNER
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11
Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 5 of 5 Date Revision Checked Approved
Page 169
SHORING SUB COORDINATE WITH DESIGN - POTHOLING
SITSWSW-0102SIT
5 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - SOUTH WHEELING ST.
SITSWBW-288OSI
4 $0.00
INSTALL REMAINING UTILITIES - SOUTH WHEELING ST.
SITSWBW-308OSI
25 $0.00
INSTALL HARDSCAPE/LANDSCA- SOUTH WHEELING ST.
SITSWBW-328OSI
25 $0.00
CONSTRUCT ROADWAY - SOUTH WHEELING ST.
SITSWBW-318OSI
25 $0.00
DEMO/GRADING - SOUTH WHEELING ST.
SITSWBW-298OSI
15 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - NORTH WHEELING ST.
SITSWBW-0215OSI
4 $0.00
INSTALL REMAINING UTILITIES - NORTH WHEELING ST.
SITSWBW-0205OSI
25 $0.00
INSTALL HARDSCAPE/LANDSCA- NORTH WHEELING ST.
SITSWBW-0238OSI
25 $0.00
CONSTRUCT ROADWAY - NORTH WHEELING ST.
SITSWBW-0228OSI
25 $0.00
DEMO/GRADING - NORTH WHEELING ST.
SITSWBW-0218OSI
15 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - INTERSEC WHEELING ST.
SITSWBW-238OSI
4 $0.00
INSTALL REMAINING UTILITIES - INTERSEC WHEELING ST.
SITSWBW-258OSI
17 $0.00
INSTALL HARDSCAPE/LANDSCA- INTERSEC WHEELING ST.
SITSWBW-278OSI
20 $0.00
CONSTRUCT ROADWAY - INTERSECWHEELING ST.
SITSWBW-268OSI
15 $0.00
DEMO/GRADING - INTERSEC WHEELING ST..
SITSWBW-248OSI
10 $0.00
LOCATE ALL UTILITIES- POTHOLING
SITSWSW-0150SIT
10 $0.00
SURVEYOR MAP/PROVIDE AS-BUILTS - POTHOLING
SITWSSW-0288OSI
15 $0.00
KT ATTAIN APPROVAL FOR TIE-BACKS UNDER ROADWAYS - POTHOLING
SITSWSW-0001SIT
20 $0.00
CONSTRUCT ROADWAY - MONTVIEW BLVD.
MBSW-268OSI
25 $0.00
INSTALL UTILITIES - MONTVIEW BLVD.
MBSW-258OSI
15 $0.00
DEMO/GRADING - MONTVIEW BLVD.
MBSW-248OSI
15 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - MONTVIEW BLVD.
MBSW-238OSI
4 $0.00
INSTALL HARDSCAPE/LANDSCA- 17TH AVE
17SW-0238OSI
5 $0.00
CONSTRUCT ROADWAY - 17TH AVE
17SW-0228OSI
15 $0.00
INSTALL UTILITIES - 17TH AVE
17SW-0220OSI
15 $0.00
DEMO/GRADING - 17TH AVE
17SW-0218OSI
5 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - 17TH AVE
17SW-0215OSI
2 $0.00
INSTALL/TEST NEW WATERLINE - WHEELING ST.
SITWSSW-0205OSI
15 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - WHEELINGST.
SITWSSW-328OSI
2 $0.00
INSTALL HARDSCAPE/LANDSCA- WHEELING ST.
SITWSSW-308OSI
10 $0.00
CONSTRUCT ROADWAY - WHEELING ST.
SITWSSW-298OSI
8 $0.00
DEMO/GRADING - WHEELING ST.
SITWSSW-288OSI
5 $0.00
INSTALL HARDSCAPE/LANDSCA- 19TH PLACE
19SW-0238OSI
10 $0.00
CONSTRUCT ROADWAY - 19TH PLACE
19SW-0228OSI
15 $0.00
INSTALL UTILITIES - 19TH PLACE
19SW-0220OSI
15 $0.00
DEMO/GRADING - 19TH PLACE
19SW-0218OSI
12 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - 19TH PLACE
19SW-0215OSI
4 $0.00
INSTALL UTILITIES - 17TH PLACE
PLSW-0220OSI
25 $0.00
DEMO/GRADING - 17TH PLACE
PLSW-0218OSI
12 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - 17TH PLACE
PLSW-0215OSI
4 $0.00
INSTALL UTILIDOR - 17TH PLACE
PLSW-238OSI
15 $0.00
INSTALL HARDSCAPE/LANDSCA- 17TH PLACE
PLSW-0238OSI
15 $0.00
CONSTRUCT ROADWAY - 17TH PLACE
PLSW-0228OSI
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 2
LT07 - VA MILESTONE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 170
INSTALL HARDSCAPE/LANDSCA- MONTVIEW BLVD.
MBSW-278OSI
25 $0.0000
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 2 of 2
LT07 - VA MILESTONE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 171
SHORING SUB COORDINATE WITH DESIGN - POTHOLING
SITSWSW-0102SIT
5 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - SOUTH WHEELING ST.
SITSWBW-288OSI
4 $0.00
INSTALL REMAINING UTILITIES - SOUTH WHEELING ST.
SITSWBW-308OSI
25 $0.00
INSTALL HARDSCAPE/LANDSCA- SOUTH WHEELING ST.
SITSWBW-328OSI
25 $0.00
CONSTRUCT ROADWAY - SOUTH WHEELING ST.
SITSWBW-318OSI
25 $0.00
DEMO/GRADING - SOUTH WHEELING ST.
SITSWBW-298OSI
15 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - NORTH WHEELING ST.
SITSWBW-0215OSI
4 $0.00
INSTALL REMAINING UTILITIES - NORTH WHEELING ST.
SITSWBW-0205OSI
25 $0.00
INSTALL HARDSCAPE/LANDSCA- NORTH WHEELING ST.
SITSWBW-0238OSI
25 $0.00
CONSTRUCT ROADWAY - NORTH WHEELING ST.
SITSWBW-0228OSI
25 $0.00
DEMO/GRADING - NORTH WHEELING ST.
SITSWBW-0218OSI
15 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - INTERSEC WHEELING ST.
SITSWBW-238OSI
4 $0.00
INSTALL REMAINING UTILITIES - INTERSEC WHEELING ST.
SITSWBW-258OSI
17 $0.00
INSTALL HARDSCAPE/LANDSCA- INTERSEC WHEELING ST.
SITSWBW-278OSI
20 $0.00
CONSTRUCT ROADWAY - INTERSECWHEELING ST.
SITSWBW-268OSI
15 $0.00
DEMO/GRADING - INTERSEC WHEELING ST..
SITSWBW-248OSI
10 $0.00
LOCATE ALL UTILITIES- POTHOLING
SITSWSW-0150SIT
10 $0.00
SURVEYOR MAP/PROVIDE AS-BUILTS - POTHOLING
SITWSSW-0288OSI
15 $0.00
KT ATTAIN APPROVAL FOR TIE-BACKS UNDER ROADWAYS - POTHOLING
SITSWSW-0001SIT
20 $0.00
CONSTRUCT ROADWAY - MONTVIEW BLVD.
MBSW-268OSI
25 $0.00
INSTALL UTILITIES - MONTVIEW BLVD.
MBSW-258OSI
15 $0.00
DEMO/GRADING - MONTVIEW BLVD.
MBSW-248OSI
15 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - MONTVIEW BLVD.
MBSW-238OSI
4 $0.00
INSTALL HARDSCAPE/LANDSCA- 17TH AVE
17SW-0238OSI
5 $0.00
CONSTRUCT ROADWAY - 17TH AVE
17SW-0228OSI
15 $0.00
INSTALL UTILITIES - 17TH AVE
17SW-0220OSI
15 $0.00
DEMO/GRADING - 17TH AVE
17SW-0218OSI
5 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - 17TH AVE
17SW-0215OSI
2 $0.00
INSTALL/TEST NEW WATERLINE - WHEELING ST.
SITWSSW-0205OSI
15 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - WHEELINGST.
SITWSSW-328OSI
2 $0.00
INSTALL HARDSCAPE/LANDSCA- WHEELING ST.
SITWSSW-308OSI
10 $0.00
CONSTRUCT ROADWAY - WHEELING ST.
SITWSSW-298OSI
8 $0.00
DEMO/GRADING - WHEELING ST.
SITWSSW-288OSI
5 $0.00
INSTALL HARDSCAPE/LANDSCA- 19TH PLACE
19SW-0238OSI
10 $0.00
CONSTRUCT ROADWAY - 19TH PLACE
19SW-0228OSI
15 $0.00
INSTALL UTILITIES - 19TH PLACE
19SW-0220OSI
15 $0.00
DEMO/GRADING - 19TH PLACE
19SW-0218OSI
12 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - 19TH PLACE
19SW-0215OSI
4 $0.00
INSTALL UTILITIES - 17TH PLACE
PLSW-0220OSI
25 $0.00
DEMO/GRADING - 17TH PLACE
PLSW-0218OSI
12 $0.00
PLACE EROSION PROTECTION/TRAFFICCONTROL - 17TH PLACE
PLSW-0215OSI
4 $0.00
INSTALL UTILIDOR - 17TH PLACE
PLSW-238OSI
15 $0.00
INSTALL HARDSCAPE/LANDSCA- 17TH PLACE
PLSW-0238OSI
15 $0.00
CONSTRUCT ROADWAY - 17TH PLACE
PLSW-0228OSI
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 2
LT07 - OFF-SITE INFRASTRUCTURE NETWORK D
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 172
INSTALL HARDSCAPE/LANDSCA- MONTVIEW BLVD.
MBSW-278OSI
25 $0.0000
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 2 of 2
LT07 - OFF-SITE INFRASTRUCTURE NETWORK D
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 173
FORM/REINFORCE/ROUTOPPING SLAB - ALL LVLS AR-C CON
CONACSS-0320CON
15 $0.00
ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-C CON
CONACSS-0510CON
24 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - LVL-1 AR-C CON
CONACL1-0390CON
8 $0.00
FORM/REINFORCE/PLASTRUCT SLABS - LVL-1AR-C CON
CONACL1-0380CON
7 $0.00
ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1)- LVL-1 AR-C CON
CONACL1-1527CON
15 $0.00
DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-C CON
CONACL1-0320CON
6 $0.00
UNDERSLAB UTILITIES- LVL-1 AR-C CON
CONACL1-3200CON
7 $0.00
FORM/PLACE PIER CAPS/GRADE BEAMS -LVL-1 AR-C CON
CONACL1-0330CON
9 $0.00
FORM/REINFORCE/PLABEAMS/GRADE BEAMS- SERV LVL AR-C CON
CONACSL-0322CON
8 $0.00
INSTALL DUCTBANK DRAINAGE - SERV LVL AR-C CON
CONACSL-3210CON
7 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-C CON
CONACSL-0390CON
19 $0.00
MASS EXCAVATION/RECONDI- SERV LVL AR-C CON
CONACSL-3100CON
8 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-C CON
CONACSL-0380CON
12 $0.00
DRILL/PLACE CAISSONS - SERV LVL AR-C CON
CONACSL-0320CON
12 $0.00
UNDERSLAB UTILITIES- SERV LVL AR-C CON
CONACSL-3200CON
11 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-C CON
CONACSL-0330CON
30 $0.00
EXCAVATE/SET/BACKFDUCTBANK/VAULTS - SERV LVL AR-C CON
CONACSL-3110CON
15 $0.00
FRAMING @ CLEARSTORY - HIGH ROOF AR-C CON
CONACHR-0510CON
12 $0.00
INSTALL GLAZING @ CLEARSTORY - LOW ROOF AR-C CON
CONACHR-0888CON
15 $0.00
INSTALL STANDING SEAM ROOF - LOW ROOF AR-C CON
CONACHR-0755CON
42 $0.00
PARAPET/BLOCKING/ICWATER SHIELD- LOW ROOF AR-C CON
CONACHR-0750CON
18 $0.00
FRAMING @ CLEARSTORY - HIGH ROOF AR-E CON
CONAEHR-0510CON
9 $0.00
PARAPET/BLOCKING/WATER SHIELD- LOW ROOF AR-E CON
CONAEHR-0750CON
5 $0.00
INSTALL ROOF ACCCESSORIES - LOW ROOF AR-E CON
CONAELR-0760CON
10 $0.00
INSTALL GREEN ROOFSYSTEM - LOW ROOF AR-E CON
CONAELR-0750CON
12 $0.00
PARAPET/BLOCKING/RO- LOW ROOF AR-E CON
CONAELR-0710CON
12 $0.00
INSTALL DUCTBANK DRAINAGE - SERV LVL AR-E CON
CONAESL-3211CON
7 $0.00
INSTALL GREASE TRAP AND SANITARY - SERV LVL AR-E CON
CONAESL-3210CON
10 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-E CON
CONAESL-0390CON
19 $0.00
MASS EXCAVATION/RECONDI- SERV LVL AR-E CON
CONAESL-3100CON
8 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-E CON
CONAESL-0380CON
11 $0.00
DRILL/PLACE CAISSONS - SERV LVL AR-E CON
CONAESL-0320CON
11 $0.00
UNDERSLAB UTILITIES- SERV LVL AR-E CON
CONAESL-3200CON
18 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-E CON
CONAESL-0330CON
25 $0.00
EXCAVATE/SET/BACKFDUCTBANK/VAULTS - SERV LVL AR-E CON
CONAESL-3110CON
15 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - ALL LVLS AR-E CON
CONAESS-0320CON
6 $0.00
ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-E CON
CONAESS-0510CON
25 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - LVL-1 AR-E CON
CONAEL1-0390CON
7 $0.00
ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1)- LVL-1 AR-E CON
CONAEL1-1527CON
19 $0.00
FORM/REINFORCE/PLASTRUCT SLABS - LVL-1AR-E CON
CONAEL1-0380CON
3 $0.00
DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-E CON
CONAEL1-0320CON
4 $0.00
UNDERSLAB UTILITIES- LVL-1 AR-E CON
CONAEL1-3200CON
3 $0.00
FORM/PLACE PIER CAPS/GRADE BEAMS -LVL-1 AR-E CON
CONAEL1-0330CON
8 $0.00
FORM/REINFORCE/PLABEAMS/GRADE BEAMS- SERV LVL AR-E CON
CONAESL-0322CON
8 $0.00
INSTALL DUCTBANK DRAINAGE - SERV LVL AR-B CON
CONABSL-3210CON
7 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-B CON
CONABSL-0390CON
18 $0.00
MASS EXCAVATION/RECONDI- SERV LVL AR-B CON
CONABSL-3100CON
8 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-B CON
CONABSL-0380CON
9 $0.00
DRILL/PLACE CAISSONS - SERV LVL AR-B CON
CONABSL-0320CON
9 $0.00
UNDERSLAB UTILITIES- SERV LVL AR-B CON
CONABSL-3200CON
14 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-B CON
CONABSL-0330CON
30 $0.00
EXCAVATE/SET/BACKFDUCTBANK/VAULTS - SERV LVL AR-B CON
CONABSL-3110CON
15 $0.00
FORM/REINFORCE/PLABEAMS/GRADE BEAMS- SERV LVL AR-B CON
CONABSL-0322CON
8 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - LVL-1 AR-B CON
CONABL1-0390CON
6 $0.00
ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1)- LVL-1 AR-B CON
CONABL1-1527CON
10 $0.00
FORM/REINFORCE/PLASTRUCT SLABS - LVL-1AR-B CON
CONABL1-0380CON
9 $0.00
DRILL/PLACE CAISSONS (EAST BALANCE) - LVL-1 AR-BCON
CONABL1-0320CON
9 $0.00
UNDERSLAB UTILITIES- LVL-1 AR-B CON
CONABL1-3200CON
9 $0.00
FORM/PLACE PIER CAPS/GRADE BEAMS -LVL-1 AR-B CON
CONABL1-0330CON
30 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - ALL LVLS AR-B CON
CONABSS-0320CON
10 $0.00
ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-B CON
CONABSS-0510CON
26 $0.00
FRAMING @ CLEARSTORY - HIGH ROOF AR-B CON
CONABHR-0510CON
9 $0.00
INSTALL GLAZING @ CLEARSTORY - HIGH ROOF AR-B CON
CONABHR-0888CON
12 $0.00
INSTALL STANDING SEAM ROOF - HIGH ROOF AR-B CON
CONABHR-0755CON
30 $0.00
PARAPET/BLOCKING/ICWATER SHIELD- HIGH ROOF AR-B CON
CONABHR-0750CON
14 $0.00
INSTALL ROOF ACCCESSORIES - LOWROOF AR-B CON
CONABLR-0760CON
10 $0.00
INSTALL GREEN ROOFSYSTEM - LOW ROOF AR-B CON
CONABLR-0750CON
12 $0.00
PARAPET/BLOCKING/RO- LOW ROOF AR-B CON
CONABLR-0710CON
15 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - LVL-1 AR-A CON
CONAAL1-0390CON
5 $0.00
ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1)- LVL-1 AR-A CON
CONAAL1-1527CON
12 $0.00
FORM/REINFORCE/PLASTRUCT SLABS - LVL-1AR-A CON
CONAAL1-0380CON
8 $0.00
DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-A CON
CONAAL1-0320CON
8 $0.00
UNDERSLAB UTILITIES- LVL-1 AR-A CON
CONAAL1-3200CON
6 $0.00
FORM/REINFORCE/PLABEAMS/GRADE BEAMS- SERV LVL AR-A CON
CONAASL-0322CON
8 $0.00
INSTALL DUCTBANK DRAINAGE - SERV LVL AR-A CON
CONAASL-3210CON
7 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-A CON
CONAASL-0390CON
40 $0.00
MASS EXCAVATION/RECONDI- SERV LVL AR-A CON
CONAASL-3100CON
8 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-A CON
CONAASL-0380CON
11 $0.00
DRILL/PLACE CAISSONS - SERV LVL AR-A CON
CONAASL-0320CON
18 $0.00
UNDERSLAB UTILITIES- SERV LVL AR-A CON
CONAASL-3200CON
17 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-A CON
CONAASL-0330CON
40 $0.00
EXCAVATE/SET/BACKFDUCTBANK/VAULTS - SERV LVL AR-A CON
CONAASL-3110CON
15 $0.00
PARAPET/BLOCKING/RO- LOW ROOF AR-A CON
CONAALR-0710CON
12 $0.00
INSTALL ROOF ACCCESSORIES - LOWROOF AR-A CON
CONAALR-0760CON
10 $0.00
INSTALL GREEN ROOFSYSTEM - LOW ROOF AR-A CON
CONAALR-0750CON
12 $0.00
INSTALL STANDING SEAM ROOF - LOW ROOF AR-A CON
CONAAHR-0755CON
25 $0.00
PARAPET/BLOCKING/ICWATER SHIELD- LOW ROOF AR-A CON
CONAAHR-0750CON
12 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - ALL LVLS AR-A CON
CONAASS-0320CON
5 $0.00
ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-A CON
CONAASS-0510CON
23 $0.00
INSTALL DUCTBANK DRAINAGE - SERV LVL AR-D CON
CONADSL-3210CON
7 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL AR-D CON
CONADSL-0390CON
17 $0.00
MASS EXCAVATION/RECONDI- SERV LVL AR-D CON
CONADSL-3100CON
8 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL AR-D CON
CONADSL-0380CON
10 $0.00
DRILL/PLACE CAISSONS - SERV LVL AR-D CON
CONADSL-0320CON
7 $0.00
UNDERSLAB UTILITIES- SERV LVL AR-D CON
CONADSL-3200CON
12 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL AR-D CON
CONADSL-0330CON
28 $0.00
EXCAVATE/SET/BACKFDUCTBANK/VAULTS - SERV LVL AR-D CON
CONADSL-3110CON
15 $0.00
FRAMING @ CLEARSTORY - HIGH ROOF AR-D CON
CONADHR-0510CON
11 $0.00
INSTALL GLAZING @ CLEARSTORY - LOWROOF AR-D CON
CONADHR-0888CON
13 $0.00
INSTALL STANDING SEAM ROOF - LOW ROOF AR-D CON
CONADHR-0755CON
31 $0.00
PARAPET/BLOCKING/ICWATER SHIELD- HIGH ROOF AR-D CON
CONADHR-0750CON
11 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - ALL LVLS AR-D CON
CONADSS-0320CON
11 $0.00
ERECT STRUCTURAL STEEL/DECK - ALL LVLS AR-D CON
CONADSS-0510CON
23 $0.00
PARAPET/BLOCKING/RO- LOW ROOF AR-D CON
CONADLR-0710CON
12 $0.00
INSTALL ROOF ACCCESSORIES - LOWROOF AR-D CON
CONADLR-0760CON
10 $0.00
INSTALL GREEN ROOFSYSTEM - LOW ROOF AR-D CON
CONADLR-0750CON
12 $0.00
ERECT STEEL/MTL DECK (PIPE SUPPORTS AND LVL-1)- LVL-1 AR-D CON
CONADL1-1527CON
15 $0.00
FORM/REINFORCE/PLASTRUCT SLABS - LVL-1AR-D CON
CONADL1-0380CON
8 $0.00
DRILL/PLACE CAISSONS (BALANCE) - LVL-1 AR-D CON
CONADL1-0320CON
6 $0.00
UNDERSLAB UTILITIES- LVL-1 AR-D CON
CONADL1-3200CON
7 $0.00
FORM/REINFORCE/PLABEAMS/GRADE BEAMS- SERV LVL AR-D CON
CONADL1-0322CON
8 $0.00
FORM/PLACE PIER CAPS/GRADE BEAMS -LVL-1 AR-D CON
CONADL1-0330CON
9 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - LVL-1 AR-D CON
CONADL1-0390CON
8 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 2
LT07 - CON STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 174
INSTALL GLAZING @ CLEARSTORY - LOW ROOF AR-E CON
CONAEHR-0888CON
11 $0.00
INSTALL STANDING SEAM ROOF - LOW ROOF AR-E CON
CONAEHR-0755CON
17 $0.00
/ICW
00
W
00
00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 2 of 2
LT07 - CON STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 175
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B RESTRMS CON
CONL1BR-1516CON
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-B RESTRMS CON
CONL1BR-0990CON
30 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 AR-B RESTRMSCON
CONL1BR-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-BRESTRMS CON
CONL1BR-0920CON
12 $0.00
FRAMING/INWALL ROUGH - LVL-1 AR-B RESTRMS CON
CONL1BR-0910CON
15 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-A RESTRMS CON
CONL1AR-1516CON
20 $0.00
FRAMING/INWALL ROUGH - LVL-1 AR-A RESTRMS CON
CONL1AR-0910CON
15 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-ARESTRMS CON
CONL1AR-0920CON
12 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-A RESTRMS CON
CONL1AR-0990CON
30 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 AR-A RESTRMSCON
CONL1AR-8880CON
10 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AUDITRM CON
CONL1AU-0990CON
30 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 AUDITRM CON
CONL1AU-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AUDITRM CON
CONL1AU-0920CON
17 $0.00
FRAMING/INWALL ROUGH - LVL-1 AUDITRM CON
CONL1AU-0910CON
17 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AUDITRM CON
CONL1AU-1516CON
25 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SOUTH LOBBY CON
CONL1SL-0990CON
40 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 SOUTH LOBBY CON
CONL1SL-8880CON
15 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 SOUTH LOBBY CON
CONL1SL-0920CON
16 $0.00
FRAMING/INWALL ROUGH - LVL-1 SOUTHLOBBY CON
CONL1SL-0910CON
18 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 SOUTH LOBBY CON
CONL1SL-1516CON
22 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D AR-E RESTRMS CON
CONL1ER-0990CON
30 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 AR-D AR-E RESTRMS CON
CONL1ER-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-DAR-E RESTRMS CON
CONL1ER-0920CON
12 $0.00
FRAMING/INWALL ROUGH - LVL-1 AR-E RESTRMS CON
CONL1ER-0910CON
15 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-E RESTRMS CON
CONL1ER-1516CON
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 COFFEE SHOP CON
CONL1CS-0990CON
30 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 COFFEE SHOP CON
CONL1CS-8880CON
15 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 COFFEE SHOP CON
FRAMING/INWALL ROUGH - LVL-1 COFFEE SHOP CON
CONL1CS-0910CON
12 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 COFFEE SHOP CON
CONL1CS-1516CON
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D RESTRMS CON
CONL1DR-0990CON
30 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 AR-D RESTRMSCON
CONL1DR-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-DRESTRMS CON
CONL1DR-0920CON
12 $0.00
FRAMING/INWALL ROUGH - LVL-1 AR-D RESTRMS CON
CONL1DR-0910CON
15 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-D RESTRMS CON
CONL1DR-1516CON
20 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 SERVING CON
CONL1SE-8880CON
10 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SERVING CON
CONL1SE-0990CON
30 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 SERVING CON
CONL1SE-0920CON
18 $0.00
FRAMING/INWALL ROUGH - LVL-1 SERVING CON
CONL1SE-0910CON
6 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 SERVING CON
CONL1SE-1516CON
25 $0.00
FRAMING/INWALL ROUGH - LVL-1 AR-D DINING CON
CONL1DI-0910CON
17 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 DINING CON
CONL1DI-1516CON
18 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-D DINING CON
CONL1DI-0990CON
35 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 AR-D DINING CON
CONL1DI-8880CON
15 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-DDINING CON
CONL1DI-0920CON
17 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NORTH LOBBY CON
CONL1NL-0990CON
32 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 NORTH LOBBY CON
CONL1NL-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 NORTH LOBBY CON
CONL1NL-0920CON
5 $0.00
FRAMING/INWALL ROUGH - LVL-1 NORTHLOBBY CON
CONL1NL-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 NORTH LOBBY CON
CONL1NL-1516CON
25 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AR-B CHAPEL CON
CONL1CH-0990CON
25 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 AR-B CHAPEL CON
CONL1CH-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-BCHAPEL CON
CONL1CH-0920CON
15 $0.00
FRAMING/INWALL ROUGH - LVL-1 AR-B CHAPEL CON
CONL1CH-0910CON
15 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B CHAPEL CON
CONL1CH-1516CON
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 2
LT07 - CON INTERIOR BUMPOUT NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 176
COFFEE SHOP CON
CONL1CS-0920CON
12 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 2 of 2
LT07 - CON INTERIOR BUMPOUT NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 177
INSTALL BLAST PROOF PANELS @ LVL1 (WEST ELEV) - AR-B CON
CONESAB-0867CON
12 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (EAST ELEV) - AR B CON
CONESAB-0866CON
12 $0.00
INSTALL EXTERIOR FINISHES (LVL-1 BUMPOUTS) - AR-B CON
CONESAB-890CON
15 $0.00
ERECT EXTERIOR STUDS/SHEATHING - AR-B CON
CONESAB-0540CON
15 $0.00
INSTALL CURTAIN WALL (EAST ELEV) - AR-B CON
CONESAB-880CON
20 $0.00
INSTALL CURTAIN WALL (WEST ELEV) - AR-B CON
CONESAB-0870CON
20 $0.00
INSTALL PVS TO CON ENTRY - AR-D CON
CONESAD-900CON
35 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (WEST ELEV) - AR-D CON
CONESAD-0867CON
12 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (EAST ELEV) - AR-D CON
CONESAD-0866CON
12 $0.00
INSTALL CURTAIN WALL (EAST ELEV) - AR-D CON
CONESAD-880CON
20 $0.00
INSTALL EXTERIOR FINISHES (LVL-1 BUMPOUTS) - AR-D CON
CONESAD-890CON
15 $0.00
ERECT EXTERIOR STUDS/SHEATHING - AR-D CON
CONESAD-0540CON
15 $0.00
INSTALL CURTAIN WALL (WEST ELEV) - AR-D CON
CONESAD-0870CON
20 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (WEST ELEV) - AR-E CON
CONESAE-0867CON
12 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (EAST ELEV) - AR-E CON
CONESAE-0866CON
12 $0.00
INSTALL BLAST PROOF PANELS @ LVL-1 (SOUTH ELEV) - AR-E CON
CONESAE-0855CON
12 $0.00
INSTALL EXTERIOR FINISHES (LVL-1 BUMPOUTS) - AR-E CON
CONESAE-890CON
20 $0.00
ERECT EXTERIOR STUDS/SHEATHING - AR-E CON
CONESAE-0540CON
15 $0.00
INSTALL CURTAIN WALL (WEST ELEV) - AR-E CON
CONESAE-880CON
20 $0.00
INSTALL CURTAIN WALL (EAST ELEV) - AR-E CON
CONESAE-870CON
20 $0.00
INSTALL CURTAIN WALL (SOUTH ELEV) - AR-E CON
CONESAE-0870CON
20 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (WEST ELEV) - AR-C CON
CONESAC-0867CON
12 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (EAST ELEV) - AR-C CON
CONESAC-0866CON
12 $0.00
INSTALL CURTAIN WALL (WEST ELEV) - AR-C CON
CONESAC-0870CON
15 $0.00
INSTALL CURTAIN WALL (EAST ELEV) - AR-C CON
CONESAC-880CON
15 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (WEST ELEV) - AR-A CON
CONESAA-0867CON
12 $0.00
INSTALL BLAST PROOF PANELS @ LVL1 (EAST ELEV) - AR-A CON
CONESAA-0866CON
12 $0.00
INSTALL BLAST PROOF PANELS @ LVL-1 (NORTH ELEV) - AR-A CON
CONESAA-0855CON
12 $0.00
INSTALL EXTERIOR FINISHES (LVL-1 BUMPOUTS) - AR-A CON
CONESAA-890CON
15 $0.00
ERECT EXTERIOR STUDS/SHEATHING - AR-A CON
CONESAA-0540CON
15 $0.00
INSTALL CURTAIN WALL (EAST ELEV) - AR-A CON
CONESAA-880CON
20 $0.00
INSTALL CURTAIN WALL (WEST ELEV) - AR-A CON
CONESAA-870CON
20 $0.00
INSTALL CURTAIN WALL (NORTH ELEV) - AR-A CON
CONESAA-0870CON
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CON EXTERIOR NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 178
FRAMING/INWALL ROUGH - SERV LVL KITCHEN AR-E CON
CONSLKI-0910CON
15 $0.00
R-I OVERHEAD MEP/FIRE PRO/HOODS- SERV LVL KITCHEN AR-E CON
CONSLKI-1516CON
35 $0.00
HANG/TAPE/FINISH DRYWALL - SERV LVL KITCHEN AR-E CON
CONSLKI-0920CON
15 $0.00
INSTALL WALK-IN COOLERS/FREEZERS- SERV LVL KITCHEN AR-E CON
CONSLKI-1120CON
10 $0.00
SET/CONNECT/TEST/INKITCHEN EQUIP- SERVLVL KITCHEN AR-E CON
CONSLKI-1110CON
20 $0.00
INSTALL INTERIOR FINISHES - SERV LVL KITCHEN AR-E CON
CONSLKI-0990CON
20 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL KITCHEN AR-E CON
CONSLKI-8880CON
15 $0.00
R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVLAR-E CON
CONSLAE-1516CON
30 $0.00
PULL 13.2 KVA WIRE - SERV LVL AR-E CON
CONSLAE-8900CON
5 $0.00
R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-E CON
CONSLAE-8890CON
68 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-E CON
CONSLAE-0990CON
15 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL AR-E CON
CONSLAE-8880CON
5 $0.00
LAY CMU/INWALL ROUGH - SERV LVL AR-E CON
CONSLAE-0910CON
23 $0.00
PULL 13.2 KVAWIRE - SERV LVL AR-C CON
CONSLAC-8900CON
5 $0.00
R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-C CON
CONSLAC-8890CON
55 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-C CON
CONSLAC-0990CON
5 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL AR-C CON
CONSLAC-8880CON
5 $0.00
LAY CMU/INWALL ROUGH - SERV LVL AR-C CON
CONSLAC-0910CON
18 $0.00
R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVLAR-C CON
CONSLAC-1516CON
30 $0.00
PULL 13.2 KVA WIRE - SERV LVL AR-A CON
CONSLAA-8900CON
5 $0.00
R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-A CON
CONSLAA-8890CON
60 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-A CON
CONSLAA-0990CON
15 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL AR-A CON
CONSLAA-8880CON
5 $0.00
LAY CMU/INWALL ROUGH - SERV LVL AR-A CON
CONSLAA-0910CON
31 $0.00
R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVLAR-A CON
CONSLAA-1516CON
30 $0.00
PULL 13.2 KVAWIRE - SERV LVL AR-D CON
CONSLAD-8900CON
5 $0.00
R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-D CON
CONSLAD-8890CON
47 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-D CON
CONSLAD-0990CON
15 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL AR-D CON
CONSLAD-8880CON
5 $0.00
LAY CMU/INWALL ROUGH - SERV LVL AR-D CON
CONSLAD-0910CON
14 $0.00
R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVLAR-D CON
CONSLAD-1516CON
30 $0.00
PULL 13.2 KVA WIRE - SERV LVL AR-B CON
CONSLAB-8900CON
5 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL AR-B CON
CONSLAB-8880CON
5 $0.00
R-I OVERHEAD MEP/FIRE PRO (ABOVE PIPE SUPPORT) - SERV LVL AR-B CON
CONSLAB-8890CON
50 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL AR-B CON
CONSLAB-0990CON
15 $0.00
LAY CMU/INWALL ROUGH - SERV LVL AR-B CON
CONSLAB-0910CON
14 $0.00
R-I OVERHEAD MEP/FIRE PRO (BELOW PIPE SUPPORT) - SERV LVLAR-B CON
CONSLAB-1516CON
30 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CON INTERIOR SERVICE LEVEL NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 179
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-A CON
CONL2AA-0990CON
512 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-2 AR-A CON
CONL2AA-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 AR-A CON
CONL2AA-0920CON
30 $0.00
FRAMING/ ROUGH-IN - LVL-2 AR-A CON
CONL2AA-0910CON
25 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-A CON
CONL2AA-1516CON
25 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-E CON
CONL2AE-0990CON
20 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-2 AR-E CON
CONL2AE-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 AR-E CON
CONL2AE-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-2 AR-E CON
CONL2AE-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-E CON
CONL2AE-1516CON
20 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-2 AR-D CON
CONL2AD-8880CON
5 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-D CON
CONL2AD-0990CON
512 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 AR-D CON
CONL2AD-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-2 AR-D CON
CONL2AD-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-D CON
CONL2AD-1516CON
20 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-B CON
CONL2AB-0990CON
512 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-2 AR-B CON
CONL2AB-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 AR-B CON
CONL2AB-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-2 AR-B CON
CONL2AB-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-B CON
CONL2AB-1516CON
20 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-2 AR-C CON
CONL2AC-0990CON
512 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-2 AR-C CON
CONL2AC-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 AR-C CON
CONL2AC-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-2 AR-C CON
CONL2AC-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-2 AR-C CON
CONL2AC-1516CON
20 $0.00
INSTALL ELEVATOR CAR (GRIDLINE 28-29)-AREA D CON
CONALAL-1465CON
60 $0.00
INSTALL ELEVATORS CAR (GRIDLINE 15-16) -AREA B CON
CONALAL-1435CON
60 $0.00
INSTALL ELEVATOR CAR (GRIDLINE 6-7) - AREA A CON
CONALAL-1425CON
60 $0.00
INSTALL ELEVATOR CAR (GRIDLINE 20-21) - AREA C CON
CONALAL-1445CON
60 $0.00
INSTALL ELEVATOR CAR (GRIDLINE 25-26) -AREA C CON
CONALAL-1455CON
60 $0.00
INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 28-29)- AREA D CON
CONALAL-1415CON
25 $0.00
INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 25-26) - AREA C CON
CONALAL-1405CON
25 $0.00
INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 20-21) - AREA C CON
CONALAL-1404CON
25 $0.00
INSTALL ELEVATORS SHAFT WALLS (GRIDLINE 15-16) - AREA B CON
CONALAL-1403CON
25 $0.00
INSTALL SERVICE ELEVATOR - AREA A CON
CONALAL-1402CON
60 $0.00
INSTALL ELEVATOR SHAFT WALLS (GRIDLINE 6-7) - AREA A CON
CONALAL-1401CON
25 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-D CON
CONL1AD-0990CON
60 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-1 AR-D CON
CONL1AD-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-DCON
CONL1AD-0920CON
12 $0.00
FRAMING/ ROUGH-IN - LVL-1 AR-D CON
CONL1AD-0910CON
18 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-D CON
CONL1AD-1516CON
20 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-ECON
CONL1AE-0920CON
12 $0.00
FRAMING/ ROUGH-IN - LVL-1 AR-E CON
CONL1AE-0910CON
18 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-E CON
CONL1AE-1516CON
20 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-E CON
CONL1AE-0990CON
35 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-1 AR-E CON
CONL1AE-8880CON
10 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-A CON
CONL1AA-1516CON
20 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-A CON
CONL1AA-0990CON
60 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH- LVL-1 AR-A CON
CONL1AA-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-ACON
CONL1AA-0920CON
12 $0.00
FRAMING/ ROUGH-IN - LVL-1 AR-A CON
CONL1AA-0910CON
18 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-1 AR-C CON
CONL1AC-8880CON
10 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-C CON
CONL1AC-0990CON
65 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-CCON
CONL1AC-0920CON
15 $0.00
FRAMING/ ROUGH-IN - LVL-1 AR-C CON
CONL1AC-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-C CON
CONL1AC-1516CON
25 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-1 AR-B CON
CONL1AB-0990CON
60 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-1 AR-B CON
CONL1AB-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 AR-BCON
CONL1AB-0920CON
12 $0.00
FRAMING/ ROUGH-IN - LVL-1 AR-B CON
CONL1AB-0910CON
18 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AR-B CON
CONL1AB-1516CON
20 $0.00
TEAR DOWN STAGE - HIGH BAY AR-A CON
CONHBAA-8890CON
7 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-A CON
CONHBAA-0990CON
15 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH- HIGH BAY AR-A CON
CONHBAA-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-A CON
CONHBAA-0920CON
15 $0.00
CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-A CON
CONHBAA-0910CON
15 $0.00
SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-A CON
CONHBAA-1516CON
15 $0.00
CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-E CON
CONHBAE-0910CON
15 $0.00
SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-E CON
CONHBAE-1516CON
15 $0.00
TEAR DOWN STAGE - HIGH BAY AR-E CON
CONHBAE-8890CON
7 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-E CON
CONHBAE-0990CON
15 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -HIGH BAY AR-E CON
CONHBAE-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-E CON
CONHBAE-0920CON
15 $0.00
TEAR DOWN STAGE - HIGH BAY AR-D CON
CONHBAD-8890CON
7 $0.00
SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-D CON
CONHBAD-1516CON
15 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-D CON
CONHBAD-0990CON
15 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -HIGH BAY AR-D CON
CONHBAD-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-D CON
CONHBAD-0920CON
16 $0.00
CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-D CON
CONHBAD-0910CON
15 $0.00
TEAR DOWN STAGE - HIGH BAY AR-C CON
CONHBAC-8890CON
7 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -HIGH BAY AR-C CON
CONHBAC-8880CON
10 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-C CON
CONHBAC-0990CON
15 $0.00
HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-C CON
CONHBAC-0920CON
18 $0.00
CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-C CON
CONHBAC-0910CON
15 $0.00
SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-C CON
CONHBAC-1516CON
15 $0.00
SET STAGE/R-I OVERHEAD MEP/FIRE PRO - HIGH BAY AR-B CON
CONHBAB-1516CON
15 $0.00
TEAR DOWN STAGE - HIGH BAY AR-B CON
CONHBAB-8890CON
7 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - HIGH BAY AR-B CON
CONHBAB-0990CON
15 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -HIGH BAY AR-B CON
CONHBAB-8880CON
10 $0.00
HANG/TAPE/FINISH DRYWALL - HIGH BAY AR-B CON
CONHBAB-0920CON
15 $0.00
CEILING/SOFFIT FRAMING/ ROUGH-IN - HIGH BAY AR-B CON
CONHBAB-0910CON
15 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-E CON
CONL3AE-0990CON
20 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-3 AR-E CON
CONL3AE-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 AR-E CON
CONL3AE-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-3 AR-E CON
CONL3AE-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-E CON
CONL3AE-1516CON
20 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-C CON
CONL3AC-0990CON
512 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-3 AR-C CON
CONL3AC-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 AR-C CON
CONL3AC-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-3 AR-C CON
CONL3AC-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-C CON
CONL3AC-1516CON
20 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-B CON
CONL3AB-0990CON
512 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-3 AR-B CON
CONL3AB-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 AR-B CON
CONL3AB-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-3 AR-B CON
CONL3AB-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-B CON
CONL3AB-1516CON
20 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-D CON
CONL3AD-0990CON
512 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-3 AR-D CON
CONL3AD-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 AR-D CON
CONL3AD-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-3 AR-D CON
CONL3AD-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-D CON
CONL3AD-1516CON
20 $0.00
INSTALL INTERIOR FINISHES/TRIM OUT - LVL-3 AR-A CON
CONL3AA-0990CON
512 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-3 AR-A CON
CONL3AA-8880CON
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 AR-A CON
CONL3AA-0920CON
25 $0.00
FRAMING/ ROUGH-IN - LVL-3 AR-A CON
CONL3AA-0910CON
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 AR-A CON
CONL3AA-1516CON
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CON INTERIOR GENERAL SEATING NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 180
ROUGH-IN MEP/FIRE PROTECTION (PRE ADMIN) (AHU1) - LVL-1 INTER LVL DAT
DATL1IL-0100DAT
50 $0.00
ROUGH-IN MEP/FIRE PROTECTION (GEN RADIOLOGY) (AHU4) - LVL-1 INTER LVL DAT
DATL1IL-0400DAT
55 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PRE-ADMIT DAT
DATL1PA-0990DAT
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 PRE-ADMIT DAT
DATL1PA-1516DAT
30 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 RAD OFFICES DAT
DATL1RO-0990DAT
40 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NUC MED DAT
DATL1NM-0990DAT
65 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 NUC MED DAT
DATL1NM-0920DAT
20 $0.00
FRAMING/INWALL ROUGH - LVL-1 NUC MED DAT
DATL1NM-0910DAT
25 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 NUC MED DAT
DATL1NM-1516DAT
20 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 GEN RADIOLGY DAT
DATL1GR-0920DAT
30 $0.00
FRAMING/INWALL ROUGH - LVL-1 GEN RADIOLGY DAT
DATL1GR-0910DAT
25 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 GEN RADIOLOGY DAT
DATL1GR-1516DAT
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 GEN RADIOLOGY DAT
DATL1GR-0990DAT
65 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 GEN RADIOLGYDAT
DATL1GR-8880DAT
10 $0.00
INSTALL OWNER FIXED FF&E - LVL-1 GEN RADIOLOGY DAT
DATL1GR-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES - LVL-1 SOUTH CORR DAT
DATL1SC-0990DAT
55 $0.00
TRIM-OUT MEP (NUC MED) (AHU5) - LVL-1 INTER LVL DAT
DATL1IL-0501DAT
20 $0.00
ROUGH-IN MEP/FIRE PROTECTION (NUC MED) (AHU5) - LVL-1 INTER LVL DAT
DATL1IL-0500DAT
50 $0.00
TRIM-OUT MEP (OFFICE) (AHU8) - LVL-1 INTER LVL DAT
DATL1IL-0801DAT
15 $0.00
ROUGH-IN MEP/FIRE PROTECTION (OFFICES) (AHU8) - LVL-1 INTER LVL DAT
DATL1IL-0800DAT
50 $0.00
TRIM-OUT MEP (GEN RADIOLOGY) (AHU4) - LVL-1 INTER LVL DAT
DATL1IL-0401DAT
15 $0.00
TRIM-OUT MEP (SPECIAL RADIOLOGY)(AHU15) - LVL-1 INTER LVL DAT
DATL1IL-1501DAT
20 $0.00
ROUGH-IN MEP/FIRE PROTECTION (SPECIAL RADIOLOGY)(AHU15) - LVL-1 INTER LVL DAT
DATL1IL-1500DAT
65 $0.00
TRIM-OUT MEP (ER) (AHU16) - LVL-1 INTER LVL DAT
DATL1IL-1601DAT
15 $0.00
ROUGH-IN MEP/FIRE PROTECTION (ER) (AHU16) - LVL-1 INTER LVL DAT
DATL1IL-1600DAT
65 $0.00
TRIM-OUT MEP (PRE ADMIN) (AHU1) - LVL-1 INTER LVL DAT
DATL1IL-0101DAT
15 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 PRE-ADMIT DAT
DATL1PA-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 PRE-ADMIT DAT
DATL1PA-0920DAT
20 $0.00
FRAMING/INWALL ROUGH - LVL-1 PRE-ADMIT DAT
DATL1PA-0910DAT
25 $0.00
INSTALL OWNER FIXED FF&E - LVL-1 PRE-ADMIT DAT
DATL1PA-0977VA DAT
20 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 RAD OFFICES DAT
DATL1RO-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 RAD OFFICES DAT
DATL1RO-0920DAT
15 $0.00
FRAMING/INWALL ROUGH - LVL-1 RAD OFFICES DAT
DATL1RO-0910DAT
20 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 RAD OFFICES DAT
DATL1RO-1516DAT
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-1 RAD OFFICES DAT
DATL1RO-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 MRI/CT DAT
DATL1MR-0990DAT
55 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 MRI/CT DAT
DATL1MR-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 MRI/CT DAT
DATL1MR-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-1 MRI/CTDAT
DATL1MR-0910DAT
40 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 MRI/CT DAT
DATL1MR-1516DAT
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-1 MRI/CT DAT
DATL1MR-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 FLURO/UTLSND DAT
DATL1FL-0990DAT
65 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 FLURO/UTLSNDDAT
DATL1FL-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 FLURO/UTLSND DAT
DATL1FL-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-1 FLURO/UTLSND DAT
DATL1FL-0910DAT
30 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 FLURO/UTLSND DAT
DATL1FL-1516DAT
25 $0.00
INSTALL OWNER FIXED FF&E - LVL-1 FLURO.UTLSND DAT
DATL1FL-0977VA DAT
20 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 NUC MED DAT
DATL1NM-8880DAT
10 $0.00
INSTALL OWNER FIXED FF&E - LVL-1 NUC MED DAT
DATL1NM-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 ER DAT
DATL1ER-0990DAT
65 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 ER DAT
DATL1ER-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 ER DAT
DATL1ER-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-1 ER DAT
DATL1ER-0910DAT
30 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-1 ER DAT
DATL1ER-1516DAT
35 $0.00
INSTALL OWNER FIXED FF&E - LVL-1 ERDAT
DATL1ER-0977VA DAT
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 181
FINISH STAIR CORE (ST5) - ALL LVLS DAT
DATALAL-0995DAT
30 $0.00
ERECT STAIRS (ST5) - ALL LVLS DAT
DATALAL-0505DAT
15 $0.00
FINISH STAIR CORE (ST3) - ALL LVLS DAT
DATALAL-0993DAT
30 $0.00
ERECT STAIRS (ST3) - ALL LVLS DAT
DATALAL-0503DAT
15 $0.00
INSTALL ELEVATORS (SE6/7) - ALL LVLS DAT
DATALAL-1467DAT
120 $0.00
INSTALL ELEVATOR (SE9) - ALL LVLS DAT
DATALAL-1409DAT
60 $0.00
FINISH STAIR CORE (ST1) - ALL LVLS DAT
DATALAL-0991DAT
30 $0.00
ERECT STAIRS (ST1) - ALL LVLS DAT
DATALAL-0501DAT
15 $0.00
INSTALL ELEVATORS (PE5/6) - ALL LVLS DAT
DATALAL-1456DAT
120 $0.00
FINISH STAIR CORE (ST2) - ALL LVLS DAT
DATALAL-0992DAT
30 $0.00
ERECT STAIRS (ST2)- ALL LVLS DAT
DATALAL-0502DAT
15 $0.00
INSTALL ELEVATOR (SE10) - ALL LVLS DAT
DATALAL-1410DAT
60 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT INTERIOR ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 182
INSTALL METAL PANEL- ALL ELEVS AR-D DAT
DATESAD-0780DAT
5 $0.00
INSTALL CURTAIN WALL - ALL ELEVS AR-D DAT
DATESAD-0870DAT
20 $0.00
SHEATHING/VAPOR BARRIER - ALL ELEVS AR-D DAT
DATESAD-0520DAT
15 $0.00
ERECT EXTERIOR STUDS - ALL ELEVS AR-D DAT
DATESAD-0540DAT
15 $0.00
LAY STACKED STONE -ALL ELEVS AR-A DAT
DATESAA-0440DAT
20 $0.00
INSTALL METAL PANEL- ALL ELEVS AR-A DAT
DATESAA-0780DAT
15 $0.00
INSTALL CURTAIN WALL - ALL ELEVS AR-A DAT
DATESAA-0870DAT
20 $0.00
SHEATHING/VAPOR BARRIER - ALL ELEVS AR-A DAT
DATESAA-0520DAT
15 $0.00
ERECT EXTERIOR STUDS - ALL ELEVS AR-A DAT
DATESAA-0540DAT
15 $0.00
INSTALL METAL PANEL- ALL ELEVS AR-B DAT
DATESAB-0780DAT
20 $0.00
ERECT EXTERIOR STUDS - ALL ELEVS AR-B DAT
DATESAB-0540DAT
15 $0.00
LAY STACKED STONE -ALL ELEVS AR-B DAT
DATESAB-0440DAT
20 $0.00
INSTALL CURTAIN WALL - ALL ELEVS AR-B DAT
DATESAB-0870DAT
25 $0.00
SHEATHING/VAPOR BARRIER - ALL ELEVS AR-B DAT
DATESAB-0520DAT
15 $0.00
INSTALL METAL PANEL- ALL ELEVS AR-C DAT
DATESAC-0780DAT
15 $0.00
INSTALL CURTAIN WALL - ALL ELEVS AR-C DAT
DATESAC-0870DAT
20 $0.00
SHEATHING/VAPOR BARRIER - ALL ELEVS AR-C DAT
DATESAC-0520DAT
15 $0.00
ERECT EXTERIOR STUDS - ALL ELEVS AR-C DAT
DATESAC-0540DAT
15 $0.00
HOIST INFILL - ALL ELEVS AR-C DAT
DATESAC-0550DAT
10 $0.00
INSTALL LOUVERS - ALL ELEVS NORTH PNTHSE DAT
DATESNP-780DAT
10 $0.00
ERECT TRELLIS - ALL ELEVS NORTH PNTHSE DAT
DATESNP-0555DAT
10 $0.00
INSTALL METAL PANEL- ALL ELEVS NORTH PNTHSE DAT
DATESNP-0780DAT
20 $0.00
ERECT STUDS/SHEATHING/VABARRIER - ALL ELEVS NORTH PNTHSE DAT
DATESNP-0520DAT
15 $0.00
LAY STACKED STONE -ALL ELEVS AR-E DAT
DATESAE-0440DAT
20 $0.00
INSTALL METAL PANEL- ALL ELEVS AR-E DAT
DATESAE-0780DAT
19 $0.00
INSTALL CURTAIN WALL - ALL ELEVS AR-E DAT
DATESAE-0870DAT
30 $0.00
SHEATHING/VAPOR BARRIER - ALL ELEVS AR-E DAT
DATESAE-0520DAT
15 $0.00
ERECT EXTERIOR STUDS - ALL ELEVS AR-E DAT
DATESAE-0540DAT
15 $0.00
INFILL FOR MRI EQUIPMENT INSTALL - ALL ELEVS AR-E DAT
DATESAF-0890DAT
5 $0.00
INSTALL LOUVERS - ALL ELEVS SOUTH PNTHSE DAT
DATESSP-780DAT
10 $0.00
ERECT TRELLIS - ALL ELEVS SOUTH PNTHSE DAT
DATESSP-0555DAT
10 $0.00
INSTALL METAL PANEL- ALL ELEVS SOUTH PNTHSE DAT
DATESSP-0780DAT
20 $0.00
STUDS/SHEATHING/VABARRIER - ALL ELEVS SOUTH PNTHSE DAT
DATESSP-0520DAT
15 $0.00
INSTALL CURTAIN WALL - ALL ELEVS AR-F DAT
DATESAF-0870DAT
25 $0.00
INSTALL METAL PANEL- ALL ELEVS AR-F DAT
DATESAF-0780DAT
20 $0.00
SHEATHING/VAPOR BARRIER - ALL ELEVS AR-F DAT
DATESAF-0520DAT
15 $0.00
ERECT EXTERIOR STUDS - ALL ELEVS AR-F DAT
DATESAF-0540DAT
15 $0.00
HOIST INFILL - ALL ELEVS AR-F DAT
DATESAF-0550DAT
10 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 183
D&T BUILDING (DAT) - COMMISSIONING
FUNCTIONAL TESTING/CORRECTION- DAT
DATALCL-1596DAT
45 $0.00
PRE-FUNCTIONAL TESTING/CORRECTION- DAT
DATALCL-1594DAT
45 $0.00
BUILDING FLUSH - DAT
DATALCL-1599DAT
20 $0.00
TEST & BALANCE - DAT
DATALCL-1592DAT
60 $0.00
CREATE/COMPLETE FINAL PUNCHLIST - DAT
DATALCL-9999DAT
30 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID
2222 - RESPONSI
2222-BUILD...
OriginalDuration
BudgetedTotal Cost
Page 184
FORM/REINFORCE/PLADECK (AREA F) - LVL-2 DAT
DATL2L2-0360DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA E) - LVL-2 DAT
DATL2L2-0350DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA D) - LVL-2DAT
DATL2L2-0340DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA C) - LVL-2DAT
DATL2L2-0330DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA B) - LVL-2 DAT
DATL2L2-0321DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA A) - LVL-2 DAT
DATL2L2-0320DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA B) - LVL-3 DAT
DATL3L3-0321DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA F) - LVL-3 DAT
DATL3L3-0360DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA E) - LVL-3 DAT
DATL3L3-0350DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA D) - LVL-3DAT
DATL3L3-0340DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA C) - LVL-3DAT
DATL3L3-0330DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA A) - LVL-3 DAT
DATL3L3-0320DAT
5 $0.00
FORM/REINFORCE/PLDECK (AREA C) - PENT DAT
DATPHPH-0330DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA B) - SERVLVL DAT
DATSLSL-3210DAT
10 $0.00
FORM/REINFORCE/PLADECK (AREA A) - SERVLVL DAT
DATSLSL-0322DAT
15 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA C) - SERV LVL DAT
DATSLSL-0380DAT
15 $0.00
BACKFILL FOUNDATION WALLS (INTERIOR) - PIPE GALLERY DAT
DATPGPG-3210DAT
5 $0.00
UNDERSLAB UTILITIES- PIPE GALLERY DAT
DATPGPG-3200DAT
7 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY DAT
DATPGPG-0330DAT
27 $0.00
SET/BACKFILL DUCTBANKS - PIPE GALLERY DAT
DATPGPG-3110DAT
7 $0.00
SHORING/MASS EXCAVATION/RECONDI- PIPE GALLERY DAT
DATPGPG-3100DAT
25 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY DAT
DATPGPG-0380DAT
5 $0.00
DRILL/PLACE CAISSONS - PIPE GALLERY DAT
DATPGPG-0320DAT
15 $0.00
FORM/REINFORCE/PLADECK (AREA F) - LVL-1 DAT
DATL1L1-0360DAT
10 $0.00
FORM/REINFORCE/PLADECK (AREA E) - LVL-1 DAT
DATL1L1-0350DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA D) - LVL-1DAT
DATL1L1-0340DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA C) - LVL-1DAT
DATL1L1-0330DAT
15 $0.00
FORM/REINFORCE/PLADECK (AREA B) - LVL-1 DAT
DATL1L1-0321DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA A) - LVL-1 DAT
DATL1L1-0320DAT
5 $0.00
BACKFILL FOUNDATION WALLS - SERV LVL DAT
DATPGPG-3220DAT
5 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA F) - SERV LVL DAT
DATSLSL-0383DAT
10 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA E) - SERV LVL DAT
DATSLSL-0382DAT
10 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA D) - SERV LVL DAT
DATSLSL-0381DAT
10 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL DAT
DATSLSL-0390DAT
15 $0.00
MASS EXCAVATION/RECONDI- SERV LVL DAT
DATSLSL-3100DAT
33 $0.00
DRILL/PLACE CAISSONS - SERV LVL DAT
DATSLSL-0320DAT
25 $0.00
UNDERSLAB UTILITIES- SERV LVL DAT
DATSLSL-3200DAT
30 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL DAT
DATSLSL-0330DAT
30 $0.00
FORM/PLACE TOWER CRANE #1 BASE (DAT & CON C/D)
DATSLSL-0340DAT
35 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA A) - SERV LVL DAT
DATSLSL-0388DAT
10 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - PIPE GALLERY DAT
DATPGPG-0390DAT
8 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 2
LT07 - DAT STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 185
LAT
00
ERECT INTER STEEL/TOPPING (AREA E) - SERV LVL INTER LVL DAT
DATSLIL-1557DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA D) - SERV LVL INTER LVL DAT
DATSLIL-1547DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA C) - SERV LVL INTER LVL DAT
DATSLIL-1537DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA B) - SERV LVL INTER LVL DAT
DATSLIL-1527DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA A) - SERV LVL INTER LVL DAT
DATSLIL-0510DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA F) - SERV LVL INTER LVL DAT
DATSLIL-1567DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA D) - LVL-2 INTERLVL DAT
DATL2IL-1547DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA F) - LVL-2 INTERLVL DAT
DATL2IL-1567DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA E) - LVL-2 INTERLVL DAT
DATL2IL-1557DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA C) - LVL-2 INTERLVL DAT
DATL2IL-1537DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA B) - LVL-2 INTERLVL DAT
DATL2IL-1527DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA A) - LVL-2 INTERLVL DAT
DATL2IL-0510DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA C) - LVL-3 INTERLVL DAT
DATL3IL-1537DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA B) - LVL-3 INTERLVL DAT
DATL3IL-1527DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA A) - LVL-3 INTERLVL DAT
DATL3IL-0510DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA F) - LVL-3 INTERLVL DAT
DATL3IL-1567DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA E) - LVL-3 INTERLVL DAT
DATL3IL-1557DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA D) - LVL-3 INTERLVL DAT
DATL3IL-1547DAT
15 $0.00
BLOCKING/ROOFING- SOUTH PENT DAT
DATPHSP-0750DAT
15 $0.00
SET/CONNECT PHOTOVOLTAIC PANELS- SOUTH PENTDAT
DATPHSP-1690DAT
50 $0.00
SET ELECTRICAL EQUIPMENT - SOUTH PENT DAT
DATPHSP-1600DAT
10 $0.00
SET MECH EQUIPMENT - SOUTH PENT DAT
DATPHSP-1500DAT
2 $0.00
ERECT PENTHOUSE STEEL/METAL DECK/TOPPING- SOUTH PENT DAT
DATPHSP-0510DAT
18 $0.00
BLOCKING/ROOFING- NORTH PENT DAT
DATPHNP-0750DAT
15 $0.00
SET/CONNECT PHOTOVOLTAIC PANELS- NORTH PENTDAT
DATPHNP-1623DAT
50 $0.00
SET ELECTRICAL EQUIPMENT - NORTH PENT DAT
DATPHNP-1621DAT
10 $0.00
SET MECH EQUIPMENT- NORTH PENT DAT
DATPHNP-1610DAT
2 $0.00
ERECT PENTHOUSE STEEL/METAL DECK/TOPPING- NORTH PENT DAT
DATPHNP-1631DAT
18 $0.00
INSTALL ROOF ACCESSORIES - NORTH LOW ROOF DAT
DATRLRL-1660DAT
10 $0.00
INSTALL GREEN ROOFSYSTEM - NORTH LOWROOF DAT
DATRLRL-1650DAT
18 $0.00
PARAPET/BLOCKING/W- NORTH LOW ROOF DAT
DATRLRL-1610DAT
15 $0.00
INSTALL ROOF ACCESSORIES - SOUTH LOW ROOF DAT
DATRLNR-1680DAT
10 $0.00
INSTALL GREEN ROOFSYSTEM - SOUTH LOWROOF DAT
DATRLNR-1670DAT
18 $0.00
PARAPET/BLOCKING/W- SOUTH LOW ROOF DAT
DATRLNR-1640DAT
15 $0.00
FORM/REINFORCE/PLAEQUIPMENT PADS (north penthouse) - PENT DAT
DATPHPH-0370DAT
7 $0.00
FORM/REINFORCE/PLAEQUIPMENT PADS (south penthouse) - PENT DAT
DATPHPH-0322DAT
7 $0.00
FORM/REINFORCE/PLADECK (AREA F) - PENT DAT
DATPHPH-0360DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA E) - PENTDAT
DATPHPH-0350DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA D) - PENTDAT
DATPHPH-0340DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA B) - PENTDAT
DATPHPH-0321DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA A) - PENTDAT
DATPHPH-0320DAT
5 $0.00
ERECT INTER STEEL/TOPPING (AREA F) - LVL-1 INTERLVL DAT
DATL1IL-1567DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA E) - LVL-1 INTERLVL DAT
DATL1IL-1557DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA D) - LVL-1 INTERLVL DAT
DATL1IL-1547DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA C) - LVL-1 INTERLVL DAT
DATL1IL-1537DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA B) - LVL-1 INTERLVL DAT
DATL1IL-1527DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA A) - LVL-1 INTERLVL DAT
DATL1IL-0510DAT
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 2 of 2
LT07 - DAT STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 186
ROUGH-IN MEP/FIRE PROTECTION (PHARMACY) (AHU2) - SERV LVL INTER LVL DAT
DATSLIL-0200DAT
45 $0.00
ROUGH-IN MEP/FIRE PROTECTION (SHELL) (AHU19) - SERV LVL INTER LVL DAT
DATSLIL-1900DAT
45 $0.00
ROUGH-IN MEP/FIRE PROTECTION (EMER MGMNT) (AHU18) - SERV LVL INTER LVL DAT
DATSLIL-1800DAT
45 $0.00
ROUGH-IN MEP/FIRE PROTECTION (STERILIZATION) (AHU7) - SERV LVL INTER LVL DAT
DATSLIL-0700DAT
45 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL EMER MGMT DAT
DATSLEM-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - SERV LVL EMER MGMT DAT
DATSLEM-0920DAT
20 $0.00
FRAMING/INWALL ROUGH - SERV LVL EMER MGMT DAT
DATSLEM-0910DAT
20 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL EMER MGMT DAT
DATSLEM-1516DAT
25 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL EMER MGMT DAT
DATSLEM-0990DAT
55 $0.00
INSTALL OWNER FIXED FF&E - SERV LVL EMER MGMT DAT
DATSLEM-0977VA DAT
20 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL SHELL DAT
DATSLSH-1516DAT
15 $0.00
TRIM-OUT MEP (PHARMACY) (AHU2) - SERV LVL INTER LVL DAT
DATSLIL-0201DAT
5 $0.00
TRIM-OUT MEP (SHELL) (AHU19) - SERV LVL INTER LVL DAT
DATSLIL-1901DAT
5 $0.00
TRIM-OUT MEP (EMER MGMNT) (AHU18) - SERV LVL INTER LVL DAT
DATSLIL-1801DAT
5 $0.00
TRIM-OUT MEP (STERILIZATION) (AHU7) - SERV LVL INTER LVL DAT
DATSLIL-0701DAT
5 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL STER SUPP DAT
DATSLSS-0990DAT
20 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL STER SUPP DAT
DATSLSS-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - SERV LVL STER SUPP DAT
DATSLSS-0920DAT
8 $0.00
FRAMING/INWALL ROUGH - SERV LVL STER SUPP DAT
DATSLSS-0910DAT
15 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL STER SUPP DAT
DATSLSS-1516DAT
15 $0.00
INSTALL OWNER FIXED FF&E - SERV LVL STER DAT
DATSLSS-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL STER DAT
DATSLST-0990DAT
45 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL STER DAT
DATSLST-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - SERV LVL STER DAT
DATSLST-0920DAT
15 $0.00
FRAMING/INWALL ROUGH - SERV LVL STER DAT
DATSLST-0910DAT
35 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL STER DAT
DATSLST-1516DAT
25 $0.00
INSTALL OWNER FIXED FF&E - SERV LVL STER DAT
DATSLST-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES - SERV LVL PHARMACY CORR DAT
DATSLPC-0990DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL PHARMACY DAT
DATSLPY-0990DAT
55 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL PHARMACY DAT
DATSLPY-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - SERV LVL PHARMACY DAT
DATSLPY-0920DAT
20 $0.00
FRAMING/INWALL ROUGH - SERV LVL PHARMACY DAT
DATSLPY-0910DAT
35 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - SERV LVL PHARMACY DAT
DATSLPY-1516DAT
20 $0.00
INSTALL OWNER FIXED FF&E - SERV LVL PHARMACY DAT
DATSLPY-0977VA DAT
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT INTERIOR SERVICE LEVEL NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 187
START-UP ELECTRICAL SYSTEMS- SOUTH PENT MECH DAT
DATPHSP-1641DAT
30 $0.00
START-UP MECH EQUIP - SOUTH PENT MECH DAT
DATPHSP-1590DAT
30 $0.00
CONNECT/PIPE-UP MECH EQUIP - SOUTH PENT MECH DAT
DATPHSP-1520DAT
60 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - SOUTH PENT MECH DAT
DATPHSP-1516DAT
50 $0.00
LAY CMU WALLS - SOUTH PENT DAT
DATPHSP-0420DAT
15 $0.00
ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - SOUTH PENT ELEC DAT
DATPHSP-1620DAT
75 $0.00
HANG/TAPE/FINISH DRYWALL - SOUTH PENT ELEC DAT
DATPHSP-0920DAT
15 $0.00
FRAMING/INWALL ROUGH - SOUTH PENTELEC DAT
DATPHSP-0910DAT
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT INTERIOR S PENTHOUSE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 188
R-I OVERHEAD MEP/FIRE PROT - PIPEGALLERY DAT
DATPGPG-1516DAT
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT INTERIOR PIPE GALLERY NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 189
ROUGH-IN/CONNECT ELECTRICAL EQUIP/PULL WIRE FROM CON - NORTH PENT ELEC DAT
DATPHNP-1620DAT
75 $0.00
HANG/TAPE/FINISH DRYWALL - NORTH PENT ELEC DAT
DATPHNP-0920DAT
15 $0.00
FRAMING/INWALL ROUGH - NORTH PENTELEC DAT
DATPHNP-0910DAT
25 $0.00
START-UP ELECTRICAL SYSTEMS- NORTH PENT MECH DAT
DATPHNP-1641DAT
30 $0.00
START-UP MECH EQUIP - NORTH PENT MECH DAT
DATPHNP-1590DAT
30 $0.00
CONNECT/PIPE-UP MECH EQUIP - NORTH PENT MECH DAT
DATPHNP-1520DAT
60 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - NORTH PENT MECH DAT
DATPHNP-1516DAT
45 $0.00
LAY CMU WALLS - NORTH PENT MECH DAT
DATPHNP-0420DAT
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT INTERIOR N PENTHOUSE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 190
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CATH LABS DAT
DATL3CA-0990DAT
65 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 ORS DAT
DATL3OR-0990DAT
75 $0.00
CLEAN-UP/PRE PUNCH- LVL-3 CATH LABS DAT
DATL3CA-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 CATH LABS DAT
DATL3CA-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-3 CATH LABS DAT
DATL3CA-0910DAT
35 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 CATH LABS DAT
DATL3CA-1516DAT
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-3 CATH LABS DAT
DATL3CA-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 HYBRID CVOR DAT
DATL3HY-0990DAT
30 $0.00
CLEAN-UP/PRE PUNCH- LVL-3 HYBRID CVOR DAT
DATL3HY-8880DAT
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 HYBRID CVOR DAT
DATL3HY-0920DAT
10 $0.00
FRAMING/INWALL ROUGH - LVL-3 HYBRID CVOR DAT
DATL3HY-0910DAT
20 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 HYBRID CVOR DAT
DATL3HY-1516DAT
5 $0.00
INSTALL OWNER FIXED FF&E - LVL-3 HYBRID CVOR DAT
DATL3HY-0977VA DAT
20 $0.00
CLEAN-UP/PRE PUNCH- LVL-3 ORS DAT
DATL3OR-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 ORS DAT
DATL3OR-0920DAT
35 $0.00
FRAMING/INWALL ROUGH - LVL-3 ORS DAT
DATL3OR-0910DAT
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 ORS DAT
DATL3OR-1516DAT
45 $0.00
INSTALL OWNER FIXED FF&E - LVL-3 CATH LABS DAT
DATL3OR-0977VA DAT
20 $0.00
TRIM-OUT MEP (ORS) (AHU9) - LVL-3 INTER LVL DAT
DATL3IL-0901DAT
5 $0.00
ROUGH-IN MEP/FIRE PROTECTION (ORS) (AHU9) - LVL-3 INTER LVL DAT
DATL3IL-0900DAT
50 $0.00
TRIM-OUT MEP (CATH)(AHU3) - LVL-3 INTER LVL DAT
DATL3IL-0301DAT
5 $0.00
ROUGH-IN MEP/FIRE PROTECTION (CATH) (AHU3) - LVL-3 INTER LVL DAT
DATL3IL-0300DAT
55 $0.00
TRIM-OUT MEP (OFFICES) (AHU13) - LVL-3 INTER LVL DAT
DATL3IL-1301DAT
5 $0.00
ROUGH-IN MEP/FIRE PROTECTION (OFFICES) (AHU13) - LVL-3 INTER LVL DAT
DATL3IL-1300DAT
65 $0.00
TRIM-OUT MEP (PACU)(AHU6) - LVL-3 INTER LVL DAT
DATL3IL-0601DAT
5 $0.00
ROUGH-IN MEP/FIRE PROTECTION (PACU) (AHU6) - LVL-3 INTER LVL DAT
DATL3IL-0600DAT
55 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SOUTH CORR DAT
DATL3SC-0990DAT
20 $0.00
CLEAN-UP/PRE PUNCH- LVL-3 SOUTH CORR DAT
DATL3SC-8880DAT
5 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 SOUTH CORR DAT
DATL3SC-0920DAT
7 $0.00
FRAMING/INWALL ROUGH - LVL-3 OFFICES DAT
DATL3OF-0910DAT
25 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 OFFICESDAT
DATL3OF-1516DAT
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-3 CATH OFFICES DAT
DATL3OF-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 OFFICES DAT
DATL3OF-0990DAT
40 $0.00
CLEAN-UP/PRE PUNCH- LVL-3 OFFICES DAT
DATL3OF-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 OFFICES DAT
DATL3OF-0920DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 DIGEST DIS DAT
DATL3DI-0990DAT
45 $0.00
CLEAN-UP/PRE PUNCH- LVL-3 DIGEST DIS DAT
DATL3DI-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 DIGEST DIS DAT
DATL3DI-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-3 DIGEST DIS DAT
DATL3DI-0910DAT
30 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 DIGEST DIS DAT
DATL3DI-1516DAT
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-3 DIGEST DIS DAT
DATL3DI-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PACU DAT
DATL3PA-0990DAT
65 $0.00
CLEAN-UP/PRE PUNCH- LVL-3 PACU DAT
DATL3PA-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-3 PACU DAT
DATL3PA-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-3 PACU DAT
DATL3PA-0910DAT
45 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-3 PACU DAT
DATL3PA-1516DAT
35 $0.00
INSTALL OWNER FIXED FF&E - LVL-3 PACU LABS DAT
DATL3PA-0977VA DAT
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT INTERIOR LEVEL 3 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 191
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SLEEP DAT
DATL2SL-0990DAT
45 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CARDIO DAT
DATL2CA-0990DAT
55 $0.00
CLEAN-UP/PRE PUNCH- LVL-2 SLEEP DAT
DATL2SL-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 SLEEP DAT
DATL2SL-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-2 SLEEP DAT
DATL2SL-0910DAT
30 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 SLEEP DAT
DATL2SL-1516DAT
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-2 LABS DAT
DATL2SL-0977VA DAT
20 $0.00
CLEAN-UP/PRE PUNCH- LVL-2 CARDIO DAT
DATL2CA-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 CARDIO DAT
DATL2CA-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-2 CARDIO DAT
DATL2CA-0910DAT
35 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 CARDIO DAT
DATL2CA-1516DAT
35 $0.00
INSTALL OWNER FIXED FF&E - LVL-2 CARDIO DAT
DATL2CA-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 LABS DAT
DATL2LA-0990DAT
65 $0.00
CLEAN-UP/PRE PUNCH- LVL-2 LABS DAT
DATL2LA-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 LABS DAT
DATL2LA-0920DAT
35 $0.00
FRAMING/INWALL ROUGH - LVL-2 LABS DAT
DATL2LA-0910DAT
30 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 LABS DAT
DATL2LA-1516DAT
35 $0.00
INSTALL OWNER FIXED FF&E - LVL-2 LABS DAT
DATL2LA-0977VA DAT
20 $0.00
INSTALL INTERIOR FINISHES - LVL-2 SOUTH CORR DAT
DATL2SC-0990DAT
55 $0.00
TRIM-OUT MEP (DENTAL) (AHU14) - LVL-2 INTER LVL DAT
DATL2IL-1401DAT
5 $0.00
ROUGH-IN MEP/FIRE PROTECTION (DENTAL) (AHU14) - LVL-2 INTER LVL DAT
DATL2IL-1400DAT
65 $0.00
TRIM-OUT MEP (LABS) (AHU17) - LVL-2 INTER LVL DAT
DATL2IL-1701DAT
5 $0.00
ROUGH-IN MEP/FIRE PROTECTION (LABS) (AHU17) - LVL-2 INTER LVL DAT
DATL2IL-1700DAT
45 $0.00
TRIM-OUT MEP (SLEEPLABS) (AHU8) - LVL-2 INTER LVL DAT
DATL2IL-0801DAT
5 $0.00
ROUGH-IN MEP/FIRE PROTECTION (SLEEP LABS) (AHU8) - LVL-2 INTER LVL DAT
DATL2IL-0800DAT
65 $0.00
TRIM-OUT MEP (CARDIO) (AHU3) - LVL-2 INTER LVL DAT
DATL2IL-0301DAT
5 $0.00
ROUGH-IN MEP/FIRE PROTECTION (CARDIO) (AHU3) - LVL-2 INTER LVL DAT
DATL2IL-0300DAT
60 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 DENTAL DAT
DATL2DE-0990DAT
55 $0.00
CLEAN-UP/PRE PUNCH- LVL-2 DENTAL DAT
DATL2DE-8880DAT
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-2 DENTAL DAT
DATL2DE-0920DAT
25 $0.00
FRAMING/INWALL ROUGH - LVL-2 DENTAL DAT
DATL2DE-0910DAT
45 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PROT - LVL-2 DENTAL DAT
DATL2DE-1516DAT
45 $0.00
INSTALL OWNER FIXED FF&E - LVL-2 DENTAL DAT
DATL2DE-0977VA DAT
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - DAT INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 192
INSTALL GLASS - EAST ELEV ENC
ENCESEE-870ENC
5 $0.00
INSTALL METAL PANELS/LOUVERS - EAST ELEV ENC
ENCESEE-0870ENC
15 $0.00
LAY STACKED STONE -EAST ELEV ENC
ENCESEE-0440ENC
25 $0.00
INSTALL CURTAINWALL - WESTELEV ENC
ENCESWE-870ENC
10 $0.00
TIE-INS @ CONCOURSE - WEST ELEV ENC
ENCESWE-0870ENC
20 $0.00
INSTALL SCREEN WALL - WEST ELEV ENC
ENCESWE-0777ENC
15 $0.00
INSTALL CURTAINWALL - SOUTH ELEV ENC
ENCESSE-880ENC
10 $0.00
SET/CONNECT SOLAR TUBES - SOUTH ELEV ENC
ENCESSE-0880ENC
40 $0.00
LAY STACKED STONE -SOUTH ELEV ENC
ENCESSE-0440ENC
25 $0.00
INSTALL METAL PANELS - SOUTH ELEVENC
ENCESSE-0870ENC
15 $0.00
INSTALL CURTAINWALL - NORTH ELEV ENC
ENCESNE-870ENC
10 $0.00
INSTALL METAL PANELS - NORTH ELEVENC
ENCESNE-0870ENC
15 $0.00
LAY STACKED STONE -NORTH ELEV ENC
ENCESNE-0440ENC
25 $0.00
INSTALL CURTAIN WALL - PENTHOUSE ENC
ENCESPH-0870ENC
10 $0.00
INSTALL LOUVERS - WEST ELEV ENC
ENCESPH-0777ENC
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - ENC EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 193
STAIR CORE FINISHES(ST3) - ALL LVLS ENC
ENCALAL-0563ENC
30 $0.00
STAIR CORE FINISHES(ST2) - ALL LVLS ENC
ENCALAL-0562ENC
30 $0.00
STAIR CORE FINISHES(ST1) - ALL LVLS ENC
ENCALAL-0561ENC
30 $0.00
ERECT STAIR (ST2) - ALL LVLS ENC
ENCALAL-0552ENC
15 $0.00
ERECT STAIR (ST1) - ALL LVLS ENC
ENCALAL-0551ENC
15 $0.00
INSTALL ELEVATOR (SE14) - ALL LVLS ENC
ENCALAL-1416ENC
60 $0.00
ERECT STAIR (ST3) - ALL LVLS ENC
ENCALAL-0553ENC
15 $0.00
ROUGH-IN/CONNECT ELECTRICAL EQUIP - SERV LVL ELEC RMS ENC
ENCSLEL-1620ENC
30 $0.00
HANG/TAPE/FINISH DRYWALL - SERV LVL ELEC RMS ENC
ENCSLEL-0920ENC
15 $0.00
FRAMING/INWALL ROUGH - SERV LVL ELEC RMS ENC
ENCSLEL-0910ENC
10 $0.00
LAY CMU WALLS - SERV LVL ELEC RMS ENC
ENCSLEL-0420ENC
10 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - SERV LVL MECH RMS ENC
ENCSLME-1516ENC
30 $0.00
SET/CONNECT/PIPE-UPMECH EQUIP (BALANCE) - SERV LVLMECH RMS ENC
ENCSLME-1600ENC
60 $0.00
CONNECT/PIPE-UP CHILLERS - SERV LVL MECH RMS ENC
ENCSLME-1525ENC
20 $0.00
SET CHILLERS - SERV LVL MECH RMS ENC
ENCSLSL-3210ENC
5 $0.00
SET BOILERS - SERV LVL MECH RMS ENC
ENCSLSL-1520ENC
5 $0.00
CONNECT/PIPE-UP BOILERS - SERV LVL MECH RMS ENC
ENCSLME-1520ENC
60 $0.00
LAY CMU WALLS - SERV LVL MECH RMS ENC
ENCSLME-0420ENC
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHOP ENC
ENCSLSH-1516ENC
20 $0.00
HANG/TAPE/FINISH DRYWALL - SERV LVL SHOP ENC
ENCSLSH-0920ENC
15 $0.00
FRAMING/INWALL ROUGH - SERV LVL SHOP ENC
ENCSLSH-0910ENC
30 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHOP ENC
ENCSLSH-0990ENC
22 $0.00
CLEAN-UP/PRE PUNCH- SERV LVL SHOP ENC
ENCSLSH-8880ENC
8 $0.00
SET/CONNECT/PIPE-UPMECH EQUIP (BALANCE) - PENTHOUSE ENC
ENCPHPH-1600ENC
20 $0.00
CONNECT/PIPE-UP AHUS - PENTHOUSE ENC
ENCPHPH-1525ENC
30 $0.00
CONNECT/PIPE-UP COOLING TOWERS - PENTHOUSE ENC
ENCPHPH-1520ENC
60 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE ENC
ENCPHPH-1516ENC
30 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES- LVL-1 OFFICES ENC
ENCL1OF-0990ENC
35 $0.00
CLEAN-UP/PRE PUNCH- LVL-1 OFFICES ENC
ENCL1OF-8880ENC
10 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 OFFICES ENC
ENCL1OF-0920ENC
12 $0.00
FRAMING/INWALL ROUGH - LVL-1 OFFICES ENC
ENCL1OF-0910ENC
15 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 OFFICES ENC
ENCL1OF-1516ENC
20 $0.00
ROUGH-IN/CONNECT GENERATORS - LVL-1 ELEC RMS ENC
ENCL1EL-1640ENC
210 $0.00
FRAMING/INWALL ROUGH - LVL-1 ELEC RMS ENC
ENCL1EL-0910ENC
10 $0.00
ROUGH-IN/CONNECT SWITCHGEAR - LVL-1 ELEC RMS ENC
ENCL1EL-1620ENC
210 $0.00
HANG/TAPE/FINISH DRYWALL - LVL-1 ELEC RMS ENC
ENCL1EL-0920ENC
15 $0.00
LAY CMU WALLS - LVL-1 ELEC RMS ENC
ENCL1EL-0420ENC
15 $0.00
ROUGH-IN/CONNECT SUBSTATION - LVL-1 ELEC RMS ENC
ENCL1EL-1660ENC
210 $0.00
ROUGH-IN/CONNECT TRANSFORMERS - LVL-1 ELEC RMS ENC
ENCL1EL-1650ENC
210 $0.00
SET GENERATORS - LVL-1 ENC
ENCL1L1-1650ENC
3 $0.00
SET SUBSTATION - LVL-1 ENC
ENCL1L1-1640ENC
5 $0.00
SET TRANFORMERS - LVL-1 ENC
ENCL1L1-1630ENC
3 $0.00
SET SWITCHGEAR - LVL-1 ENC
ENCL1L1-1620ENC
5 $0.00
START-UP MECH EQUIP - LVL-1 MECH RMS ENC
ENCL1ME-1590ENC
10 $0.00
SET/CONNECT AHU - 1- LVL-1 MECH RMS ENC
ENCL1ME-1520ENC
25 $0.00
LAY CMU WALLS - LVL-1 MECH RMS ENC
ENCL1ME-0420ENC
10 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - LVL-1 MECH RMS ENC
ENCL1ME-1516ENC
15 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - SERV LVL MECH RMS ENC
ENCPBPB-1516ENC
15 $0.00
SET/CONNECT/PIPE-UPPUMPS - SERV LVL MECH RMS ENC
ENCPBPB-1520ENC
90 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - ENC ALL LEVELS INTERIOR NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 194
FORM/REINFORCE/PLADECK (AREA F) - LVL-2 DAT
DATL2L2-0360DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA E) - LVL-2 DAT
DATL2L2-0350DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA D) - LVL-2DAT
DATL2L2-0340DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA C) - LVL-2DAT
DATL2L2-0330DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA B) - LVL-2 DAT
DATL2L2-0321DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA A) - LVL-2 DAT
DATL2L2-0320DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA B) - LVL-3 DAT
DATL3L3-0321DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA F) - LVL-3 DAT
DATL3L3-0360DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA E) - LVL-3 DAT
DATL3L3-0350DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA D) - LVL-3DAT
DATL3L3-0340DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA C) - LVL-3DAT
DATL3L3-0330DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA A) - LVL-3 DAT
DATL3L3-0320DAT
5 $0.00
FORM/REINFORCE/PLDECK (AREA C) - PENT DAT
DATPHPH-0330DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA B) - SERVLVL DAT
DATSLSL-3210DAT
10 $0.00
FORM/REINFORCE/PLADECK (AREA A) - SERVLVL DAT
DATSLSL-0322DAT
15 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA C) - SERV LVL DAT
DATSLSL-0380DAT
15 $0.00
BACKFILL FOUNDATION WALLS (INTERIOR) - PIPE GALLERY DAT
DATPGPG-3210DAT
5 $0.00
UNDERSLAB UTILITIES- PIPE GALLERY DAT
DATPGPG-3200DAT
7 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY DAT
DATPGPG-0330DAT
27 $0.00
SET/BACKFILL DUCTBANKS - PIPE GALLERY DAT
DATPGPG-3110DAT
7 $0.00
SHORING/MASS EXCAVATION/RECONDI- PIPE GALLERY DAT
DATPGPG-3100DAT
25 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY DAT
DATPGPG-0380DAT
5 $0.00
DRILL/PLACE CAISSONS - PIPE GALLERY DAT
DATPGPG-0320DAT
15 $0.00
FORM/REINFORCE/PLADECK (AREA F) - LVL-1 DAT
DATL1L1-0360DAT
10 $0.00
FORM/REINFORCE/PLADECK (AREA E) - LVL-1 DAT
DATL1L1-0350DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA D) - LVL-1DAT
DATL1L1-0340DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA C) - LVL-1DAT
DATL1L1-0330DAT
15 $0.00
FORM/REINFORCE/PLADECK (AREA B) - LVL-1 DAT
DATL1L1-0321DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA A) - LVL-1 DAT
DATL1L1-0320DAT
5 $0.00
BACKFILL FOUNDATION WALLS - SERV LVL DAT
DATPGPG-3220DAT
5 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA F) - SERV LVL DAT
DATSLSL-0383DAT
10 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA E) - SERV LVL DAT
DATSLSL-0382DAT
10 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA D) - SERV LVL DAT
DATSLSL-0381DAT
10 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL DAT
DATSLSL-0390DAT
15 $0.00
MASS EXCAVATION/RECONDI- SERV LVL DAT
DATSLSL-3100DAT
33 $0.00
DRILL/PLACE CAISSONS - SERV LVL DAT
DATSLSL-0320DAT
25 $0.00
UNDERSLAB UTILITIES- SERV LVL DAT
DATSLSL-3200DAT
30 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - SERV LVL DAT
DATSLSL-0330DAT
30 $0.00
FORM/PLACE TOWER CRANE #1 BASE (DAT & CON C/D)
DATSLSL-0340DAT
35 $0.00
FORM/PLACE/FINISH SLAB ON GRADE (AREA A) - SERV LVL DAT
DATSLSL-0388DAT
10 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - PIPE GALLERY DAT
DATPGPG-0390DAT
8 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 2
LT07 - DAT STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 195
LAT
00
ERECT INTER STEEL/TOPPING (AREA E) - SERV LVL INTER LVL DAT
DATSLIL-1557DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA D) - SERV LVL INTER LVL DAT
DATSLIL-1547DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA C) - SERV LVL INTER LVL DAT
DATSLIL-1537DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA B) - SERV LVL INTER LVL DAT
DATSLIL-1527DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA A) - SERV LVL INTER LVL DAT
DATSLIL-0510DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA F) - SERV LVL INTER LVL DAT
DATSLIL-1567DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA D) - LVL-2 INTERLVL DAT
DATL2IL-1547DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA F) - LVL-2 INTERLVL DAT
DATL2IL-1567DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA E) - LVL-2 INTERLVL DAT
DATL2IL-1557DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA C) - LVL-2 INTERLVL DAT
DATL2IL-1537DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA B) - LVL-2 INTERLVL DAT
DATL2IL-1527DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA A) - LVL-2 INTERLVL DAT
DATL2IL-0510DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA C) - LVL-3 INTERLVL DAT
DATL3IL-1537DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA B) - LVL-3 INTERLVL DAT
DATL3IL-1527DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA A) - LVL-3 INTERLVL DAT
DATL3IL-0510DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA F) - LVL-3 INTERLVL DAT
DATL3IL-1567DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA E) - LVL-3 INTERLVL DAT
DATL3IL-1557DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA D) - LVL-3 INTERLVL DAT
DATL3IL-1547DAT
15 $0.00
BLOCKING/ROOFING- SOUTH PENT DAT
DATPHSP-0750DAT
15 $0.00
SET/CONNECT PHOTOVOLTAIC PANELS- SOUTH PENTDAT
DATPHSP-1690DAT
50 $0.00
SET ELECTRICAL EQUIPMENT - SOUTH PENT DAT
DATPHSP-1600DAT
10 $0.00
SET MECH EQUIPMENT - SOUTH PENT DAT
DATPHSP-1500DAT
2 $0.00
ERECT PENTHOUSE STEEL/METAL DECK/TOPPING- SOUTH PENT DAT
DATPHSP-0510DAT
18 $0.00
BLOCKING/ROOFING- NORTH PENT DAT
DATPHNP-0750DAT
15 $0.00
SET/CONNECT PHOTOVOLTAIC PANELS- NORTH PENTDAT
DATPHNP-1623DAT
50 $0.00
SET ELECTRICAL EQUIPMENT - NORTH PENT DAT
DATPHNP-1621DAT
10 $0.00
SET MECH EQUIPMENT- NORTH PENT DAT
DATPHNP-1610DAT
2 $0.00
ERECT PENTHOUSE STEEL/METAL DECK/TOPPING- NORTH PENT DAT
DATPHNP-1631DAT
18 $0.00
INSTALL ROOF ACCESSORIES - NORTH LOW ROOF DAT
DATRLRL-1660DAT
10 $0.00
INSTALL GREEN ROOFSYSTEM - NORTH LOWROOF DAT
DATRLRL-1650DAT
18 $0.00
PARAPET/BLOCKING/W- NORTH LOW ROOF DAT
DATRLRL-1610DAT
15 $0.00
INSTALL ROOF ACCESSORIES - SOUTH LOW ROOF DAT
DATRLNR-1680DAT
10 $0.00
INSTALL GREEN ROOFSYSTEM - SOUTH LOWROOF DAT
DATRLNR-1670DAT
18 $0.00
PARAPET/BLOCKING/W- SOUTH LOW ROOF DAT
DATRLNR-1640DAT
15 $0.00
FORM/REINFORCE/PLAEQUIPMENT PADS (north penthouse) - PENT DAT
DATPHPH-0370DAT
7 $0.00
FORM/REINFORCE/PLAEQUIPMENT PADS (south penthouse) - PENT DAT
DATPHPH-0322DAT
7 $0.00
FORM/REINFORCE/PLADECK (AREA F) - PENT DAT
DATPHPH-0360DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA E) - PENTDAT
DATPHPH-0350DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA D) - PENTDAT
DATPHPH-0340DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA B) - PENTDAT
DATPHPH-0321DAT
5 $0.00
FORM/REINFORCE/PLADECK (AREA A) - PENTDAT
DATPHPH-0320DAT
5 $0.00
ERECT INTER STEEL/TOPPING (AREA F) - LVL-1 INTERLVL DAT
DATL1IL-1567DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA E) - LVL-1 INTERLVL DAT
DATL1IL-1557DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA D) - LVL-1 INTERLVL DAT
DATL1IL-1547DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA C) - LVL-1 INTERLVL DAT
DATL1IL-1537DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA B) - LVL-1 INTERLVL DAT
DATL1IL-1527DAT
15 $0.00
ERECT INTER STEEL/TOPPING (AREA A) - LVL-1 INTERLVL DAT
DATL1IL-0510DAT
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 2 of 2
LT07 - DAT STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 196
FORM/PLACE/FINISH/TESLAB ON GRADE - FUEL TANK ENC
ENCFTFT-0378ENC
18 $0.00
BACKFILL - FUEL TANKENC
ENCFTFT-3220ENC
20 $0.00
TEST FUEL TANKS - FUEL TANK ENC
ENCFTFT-0390ENC
5 $0.00
MASS EXCAVATION/PREP GRADE - FUEL TANK ENC
ENCFTFT-3100ENC
13 $0.00
SET TANKS- FUEL TANK ENC
ENCFTFT-0380ENC
3 $0.00
INSTALL FUEL TANK PIPING - FUEL TANK ENC
ENCFTFT-3200ENC
25 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - SERV LVL ENC
ENCSLSL-0390ENC
15 $0.00
MASS EXCAVATION/RECONDI- SERV LVL ENC
ENCSLSL-3100ENC
25 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL ENC
ENCSLSL-0380ENC
12 $0.00
DRILL/PLACE CAISSONS - SERV LVL ENC
ENCSLSL-0320ENC
20 $0.00
UNDERSLAB UTILITIES- SERV LVL ENC
ENCSLSL-3200ENC
28 $0.00
FORM/PLACE PIER CAPS/CORES/ WALLS/COLUMNS - SERV LVL ENC
ENCSLSL-0330ENC
60 $0.00
ERECT EXTERIOR STUDS/SHEATHING - SERV LVL ENC
ENCSLSL-0540ENC
15 $0.00
SPRAY ON FIREPROOFING - SERV LVL ENC
ENCSLSL-0720ENC
5 $0.00
FORM/REIN/R-I/PLACE TOPPING SLAB (PIPE BSMT LID) - SERV LVL ENC
ENCSLSL-0322ENC
3 $0.00
ERECT STRUCTURAL STEEL/DECK (PIPE BSMT LID)- SERV LVL ENC
ENCSLSL-0510ENC
8 $0.00
SPRAY ON FIREPROOFING - HIGH ROOF ENC
ENCHRHR-0720ENC
3 $0.00
APPLY ROOFING - HIGH ROOF ENC
ENCHRHR-0750ENC
10 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - HIGH ROOF ENC
ENCHRHR-0320ENC
5 $0.00
SET/CONNECT PHOTOVOLTAIC PANELS - HIGH ROOF ENC
ENCHRHR-2600ENC
50 $0.00
FORM/REINFORCE/PLAEQUIPMENT PADS - LVL-1 ENC
ENCL1L1-1660ENC
5 $0.00
SPRAY ON FIREPROOFING - LVL-1 ENC
ENCL1L1-0720ENC
7 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - LVL-1 ENC
ENCL1L1-0320ENC
10 $0.00
ERECT EXTERIOR STUDS/SHEATHING - LVL-1 ENC
ENCL1L1-0540ENC
15 $0.00
SPRAY ON FIREPROOFING - LOWROOF ENC
ENCLRLR-0720ENC
5 $0.00
SET COOLING TOWERS - LOW ROOF ENC
ENCLRLR-3210ENC
5 $0.00
APPLY WATERPROOFING - LOW ROOF ENC
ENCLRLR-0750ENC
7 $0.00
FORM/REINFORCE/ROUTOPPING SLAB - LOW ROOF ENC
ENCLRLR-0320ENC
10 $0.00
INSTALL GREEN ROOFSYSTEM - LOW ROOF ENC
ENCLRLR-2600ENC
15 $0.00
FORM/PLACE/FINISH WALLS/COLUMNS/CUR- WATER TANK ENC
ENCTSTS-0390ENC
20 $0.00
FORM/PLACE/FINISH/TELID - WATER TANK ENC
ENCTSTS-3220ENC
53 $0.00
MASS EXCAVATION/RECONDI- WATER TANK ENC
ENCTSTS-3100ENC
5 $0.00
FORM/PLACE/FINISH/TESLAB ON GRADE - WATER TANK ENC
ENCTSTS-0380ENC
7 $0.00
UNDERSLAB UTILITIES- WATER TANK ENC
ENCTSTS-3200ENC
15 $0.00
APPLY WATERPROOFING - WATER TANK ENC
ENCTRTR-0750ENC
20 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PIPE GALLERY ENC
ENCPGPG-0380ENC
5 $0.00
DRILL/PLACE CAISSONS - PIPE GALLERY ENC
ENCPGPG-0320ENC
6 $0.00
UNDERSLAB UTILITIES- PIPE GALLERY ENC
ENCPGPG-3200ENC
8 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS - PIPE GALLERY ENC
ENCPGPG-0330ENC
15 $0.00
PERM DRAINS/BACKFILL FOUNDATION WALLS - PIPE GALLERY ENC
ENCPGPG-3210ENC
3 $0.00
MASS EXCAVATION/RECONDI- PIPE GALLERY ENC
ENCPGPG-3100ENC
25 $0.00
ERECT/DETAIL METAL DECK (LEVEL 2 - PH ROOF) - LVLS 2 - PH ROOF) ENC
ENCALAL-1426ENC
10 $0.00
ERECT STRUCTURAL STEEL/DECK (LEVEL 1(incl. deck) - PH ROOF)- ALL LEVELS ENC
ENCALAL-0510ENC
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - ENC STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 197
GARAGE FINISHES - PKG LVL-1 PVS
PVSINP3-0990PVS
30 $0.00
ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-1 PVS
PVSINP3-1620PVS
30 $0.00
CLEAN-UP/PRE PUNCH- PKG LVL-1 PVS
PVSINP3-8880PVS
10 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVS INTERIOR LEVEL 3 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 198
ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-2 PVS
PVSINP2-1620PVS
30 $0.00
CLEAN-UP/PRE PUNCH- PKG LVL-2 PVS
PVSINP2-8880PVS
10 $0.00
GARAGE FINISHES - PKG LVL-2 PVS
PVSINP2-0990PVS
30 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVS INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 199
ROUGH-IN MEP/FIRE PROTECTION - PKG LVL-3 PVS
PVSINP1-1620PVS
30 $0.00
CLEAN-UP/PRE PUNCH- PKG LVL-3 PVS
PVSINP1-8880PVS
10 $0.00
GARAGE FINISHES - - PKG LVL-3 PVS
PVSINP1-0990PVS
30 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVS INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 200
APPLY WATERPROOFING- PKG LVL-0 PVS
PVSINL0-0750PVS
30 $0.00
INSTALL RIDGID INSULATION/PLACE TOPPING SLAB - PKG LVL-0 PVS
PVSINL0-0320PVS
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVS INTERIOR LEVEL 0 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 201
ERECT STAIRS ST1 - ALL LVLS PVS
PVSALAL-0555PVS
20 $0.00
INSTALL ELEVATOR PGE15/PGE16X - ALL LVLS PVS
PVSALAL-1400PVS
60 $0.00
ERECT STAIRS ST3 - ALL LVLS PVS
PVSALAL-0557PVS
20 $0.00
ERECT STAIRS ST2 - ALL LVLS PVS
PVSALAL-0556PVS
20 $0.00
FINISH STAIR CORES ST1/ST2/ST3 - ALL LVLS PVS
PVSALAL-0990PVS
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVS INERIOR ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 202
FUNCTIONAL TESTING/CORRECTION- ALL LVLS PVS
PVSALCO-1596PVS
15 $0.00
PRE-FUNCTIONAL TESTING/CORRECTION- ALL LVLS PVS
PVSALCO-1594PVS
10 $0.00
TEST & BALANCE - ALLLVLS PVS
PVSALCO-1592PVS
20 $0.00
CREATE/COMPLETE FINAL PUNCHLIST - ALL LVLS PVS
PVSALCO-9999PVS
30 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVS COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 203
BACKFILL RAMP (EASTSIDE) - PVS SITEWORK
PVSSWSW-3250PVS
5 $0.00
DRIVE SOLDIER PILES (REMAINING EAST SIDE) - PVS SITEWORK
PVSSWSW-3230PVS
10 $0.00
SHORING(REMAINING EAST SIDE) - PVS SITEWORK
PVSSWSW-3240PVS
15 $0.00
DRIVE SOLDIER PILES - PVS SITEWORK
PVSSWSW-3130PVS
10 $0.00
RELOCATE CBS ROOF DRAIN - PVS SITEWORK
PVSSWSW-3210PVS
10 $0.00
SHORING/MASS EXCAVATION/RECONDI- PVS SITEWORK
PVSSWSW-3100PVS
115 $0.00
INSTALL DEWATERINGSYSTEM - PVS SITEWORK
PVSSWSW-3220PVS
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVS ALL AREAS NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 204
FORM/REINF/PLACE/FINDECK - PKG LVL-2 AREA C PVS
PVSP2AC-0330PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-2 AREA A PVS
PVSP2AA-0330PVS
12 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-2 AREA D PVS
PVSP2AD-0330PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-2 AREA B PVS
PVSP2AB-0330PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-2 AREA E PVS
PVSP2AE-0330PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-0 AREA B PVS
PVSP0AB-0333PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-0 AREA D PVS
PVSP0AD-0333PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-0 AREA C PVS
PVSP0AC-0333PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-0 AREA F PVS
PVSP0AF-0333PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-0 AREA A PVS
PVSP0AA-0333PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-0 AREA E PVS
PVSP0AE-0333PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-1 AREA C PVS
PVSP1AC-0330PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-1 AREA B PVS
PVSP1AB-0330PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-1 AREA D PVS
PVSP1AD-0330PVS
10 $0.00
START-UP ELECTRICAL SYSTEMS(pvs/con) - PKG LVL-1 AREA A PVS
PVSP1AA-1641PVS
30 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-1 AREA A PVS
PVSP1AA-0330PVS
10 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-2 AREA C PVS
PVSP2AC-0335PVS
12 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-2 AREA A PVS
PVSP2AA-0335PVS
12 $0.00
FORM/PLACE FINISH RAMP - PKG LVL-2 AREA F PVS
PVSP2AF-0325PVS
15 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-2 AREA F PVS
PVSP2AF-0330PVS
10 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-2 AREA F PVS
PVSP2AF-0335PVS
12 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-2 AREA D PVS
PVSP2AD-0335PVS
12 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-2 AREA B PVS
PVSP2AB-0335PVS
12 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-2 AREA E PVS
PVSP2AE-0335PVS
12 $0.00
FORM/PLACE/FINISH RAMP - PKG LVL-3 AREA F PVS
PVSP3AF-3240PVS
10 $0.00
BACKFILL RAMP - PKG LVL-3 AREA F PVS
PVSP3AF-3230PVS
5 $0.00
REMOVE ACCESS RAMP/INFILL WALL - PKG LVL-3 AREA F PVS
PVSP3AF-3220PVS
20 $0.00
FORM/PLACE PIER CAPS - PKG LVL-3 AREA F PVS
PVSP3AF-3210PVS
4 $0.00
APPLY SHOTCRETE TO EXTERIOR WALLS -PKG LVL-3 AREA F PVS
PVSP3AF-0335PVS
25 $0.00
FORM/PLACE TOWER CRANE #2 BASE - (PVS)
PVSP3AF-0330PVS
35 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PKGLVL-3 AREA F PVS
PVSP3AF-0380PVS
10 $0.00
DRILL/PLACE CAISSONS - PKG LVL-3AREA F PVS
PVSP3AF-0320PVS
14 $0.00
UNDERSLAB UTILITIES- PKG LVL-3 AREA F PVS
PVSP3AF-3200PVS
5 $0.00
FORM/PLACE ELEV PITS/ FTGS/WALLS/COLUMNS- PKG LVL-3 AREA F PVS
PVSP3AF-0332PVS
15 $0.00
FORM/PLACE PIER CAPS - PKG LVL-3 AREA C PVS
PVSP3AC-3210PVS
4 $0.00
APPLY SHOTCRETE TO EXTERIOR WALLS -PKG LVL-3 AREA D PVS
PVSP3AC-0335PVS
12 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PKGLVL-3 AREA C PVS
PVSP3AC-0380PVS
10 $0.00
DRILL/PLACE CAISSONS - PKG LVL-3AREA C PVS
PVSP3AC-0320PVS
14 $0.00
UNDERSLAB UTILITIES- PKG LVL-3 AREA C PVS
PVSP3AC-3200PVS
5 $0.00
FORM/PLACE FTGS/COLUMNS - PKGLVL-3 AREA C PVS
PVSP3AC-0332PVS
15 $0.00
FORM/PLACE PIER CAPS - PKG LVL-3 AREA D PVS
PVSP3AD-3210PVS
4 $0.00
WATERPROOF/REINFOEAST WALL - PKG LVL-3 AREA D PVS
FL2P3AD-0355PVS
12 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PKGLVL-3 AREA D PVS
PVSP3AD-0380PVS
10 $0.00
DRILL/PLACE CAISSONS - PKG LVL-3AREA D PVS
PVSP3AD-0320PVS
14 $0.00
UNDERSLAB UTILITIES- PKG LVL-3 AREA D PVS
PVSP3AD-3200PVS
5 $0.00
FORM/PLACE FTGS/WALLS/COLUMNS- PKG LVL-3 AREA D PVS
PVSP3AD-0332PVS
15 $0.00
FORM/PLACE FTGS/ COLUMNS - PKG LVL-3 AREA E PVS
PVSP3AE-0332PVS
15 $0.00
FORM/PLACE PIER CAPS - PKG LVL-3 AREA E PVS
PVSP3AE-3220PVS
4 $0.00
APPLY SHOTCRETE TO EXTERIOR WALLS -PKG LVL-3 AREA E PVS
PVSP3AE-0335PVS
21 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PKGLVL-3 AREA E PVS
PVSP3AE-0380PVS
10 $0.00
DRILL/PLACE CAISSONS - PKG LVL-3AREA E PVS
PVSP3AE-0320PVS
14 $0.00
UNDERSLAB UTILITIES- PKG LVL-3 AREA E PVS
PVSP3AE-3200PVS
5 $0.00
FORM/PLACE PIER CAPS - PKG LVL-3 AREA B PVS
PVSP3AB-3210PVS
4 $0.00
APPLY SHOTCRETE TO EXTERIOR WALLS -PKG LVL-3 AREA B PVS
PVSP3AB-0335PVS
20 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PKGLVL-3 AREA B PVS
PVSP3AB-0380PVS
10 $0.00
DRILL/PLACE CAISSONS - PKG LVL-3AREA B PVS
PVSP3AB-0320PVS
14 $0.00
UNDERSLAB UTILITIES- PKG LVL-3 AREA B PVS
PVSP3AB-3200PVS
5 $0.00
FORM/PLACE FTGS/WALLS/COLUMNS- PKG LVL-3 AREA B PVS
PVSP3AB-0332PVS
20 $0.00
UNDERSLAB UTILITIES- PKG LVL-3 AREA A PVS
PVSP3AA-3200PVS
5 $0.00
FORM/PLACE FTGS/COLUMNS - PKGLVL-3 AREA A PVS
PVSP3AA-0332PVS
15 $0.00
WATERPROOF/REINFOSOUTH WALL - PKG LVL-3 AREA A PVS
PVSP3AA-0355PVS
30 $0.00
FORM/PLACE PIER CAPS - PKG LVL-3 AREA A PVS
PVSP3AA-3210PVS
4 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - PKGLVL-3 AREA A PVS
PVSP3AA-0380PVS
10 $0.00
DRILL/PLACE CAISSONS - PKG LVL-3AREA A PVS
PVSP3AA-0320PVS
14 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-1 AREA C PVS
PVSP1AC-0335PVS
12 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-1 AREA B PVS
PVSP1AB-0335PVS
12 $0.00
START-UP ELECTRICAL SYSTEMS(pvs/con) - PKG LVL-1 AREA E PVS
PVSP1AE-1641PVS
20 $0.00
PULL WIRE FROM CON- PKG LVL-1 AREA E PVS
PVSP1AE-1666PVS
5 $0.00
ROUGH-IN/INSTALL SUBSTATION - PKG LVL-1 AREA E PVS
PVSP1AE-1620PVS
10 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-1 AREA E PVS
PVSP1AE-0330PVS
10 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-1 AREA E PVS
PVSP1AE-0335PVS
12 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-1 AREA D PVS
PVSP1AD-0335PVS
12 $0.00
ROUGH-IN/INSTALL SUBSTATION - PKG LVL-1 AREA A PVS
PVSP1AA-1620PVS
10 $0.00
PULL WIRE FROM CON- PKG LVL-1 AREA A PVS
PVSP1AA-1666PVS
5 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-1 AREA A PVS
PVSP1AA-0335PVS
12 $0.00
FORM/PLACE FINISH RAMP - PKG LVL-1 AREA F PVS
PVSP1AF-0332PVS
15 $0.00
FORM/REINF/PLACE/FINDECK - PKG LVL-1 AREA F PVS
PVSP1AF-0330PVS
10 $0.00
FORM/REINFORCE/PLAWALLS/COLUMNS - PKG LVL-1 AREA F PVS
PVSP1AF-0335PVS
12 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVS STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 205
CONNECT/PIPE-UP EQUIPMENT - SERV LVL DOCK PVN
PVNSLST-1620PVN
25 $0.00
FRAMING/IN-WALL ROUGH IN - SERV LVL DOCK PVN
PVNSLST-0910PVN
10 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -SERV LVL DOCK PVN
PVNSLST-8890PVN
5 $0.00
FORM/PLACE FINISH EQUIPMENT PADS - SERV LVL DOCK PVN
PVNSLST-0315PVN
5 $0.00
LAY CMU WALLS - SERV LVL DOCK/MAINTENANCE PVN
PVNSLLM-0412PVN
10 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -SERV LVL DOCK/MAINTENANCE PVN
PVNSLLM-8890PVN
10 $0.00
GARAGE FINISHES - SERV LVL DOCK/MAINTENANCE PVN
PVNSLLM-1570PVN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - SERV LVL DOCK/MAINTENANCE PVN
PVNSLLM-1560PVN
40 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 206
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-6 PVN
PVNL6L6-8910PVN
10 $0.00
GARAGE FINISHES - LVL-6 PVN
PVNL6L6-1610PVN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-6 PVN
PVNL6L6-1600PVN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN INTERIOR LEVEL 6 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 207
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-5 PVN
PVNL5L5-8910PVN
10 $0.00
GARAGE FINISHES - LVL-5 PVN
PVNL5L5-1610PVN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-5 PVN
PVNL5L5-1600PVN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN INTERIOR LEVEL 5 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 208
ROUGH-IN MEP/FIRE PROTECTION - LVL-4 PVN
PVNL4L4-1600PVN
25 $0.00
GARAGE FINISHES - LVL-4 PVN
PVNL4L4-1610PVN
25 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-4 PVN
PVNL4L4-8910PVN
10 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN INTERIOR LEVEL 4 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 209
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-3 PVN
PVNL3L3-8910PVN
10 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-3 PVN
PVNL3L3-1600PVN
25 $0.00
GARAGE FINISHES - LVL-3 PVN
PVNL3L3-1610PVN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN INTERIOR LEVEL 3 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 210
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-2 PVN
PVNL2L2-8900PVN
10 $0.00
GARAGE FINISHES - LVL -2 PVN
PVNL2L2-1590PVN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-2 PVN
PVNL2L2-1580PVN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 211
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-1 PVN
PVNL1L1-8890PVN
10 $0.00
GARAGE FINISHES - LVL-1 PVN
PVNL1L1-1570PVN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-1 PVN
PVNL1L1-1560PVN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 212
CLEAN-UP/PRE PUNCH/FINAL PUNCH -ROOF LVL PVN
PVNESRL-8910PVN
10 $0.00
INSTALL GLASS ROOFING SYSTEM - ROOF LVL PVN
PVNESRL-1610PVN
40 $0.00
INSTALL ROOF TRELLIS SYSTEM - ROOF LVL PVN
PVNESRL-1600PVN
20 $0.00
INSTALL CURTAIN WALL @ ELEVATOR/STAIR CORE - ALL ELEVATIONS PVN
PVNESES-750PVN
25 $0.00
INSTALL EXTERIOR SKIN FINISHES @ GARAGE - ALL ELEVATIONS PVN
PVNESES-0750PVN
50 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 213
PRE-FUNCTIONAL TESTING/CORRECTION- PVN
PVNCOCO-1594PVN
15 $0.00
FUNCTIONAL TESTING/CORRECTION- PVN
PVNCOCO-1596PVN
15 $0.00
CREATE/COMPLETE FINAL PUNCHLIST - PVN
PVNCOCO-9999PVN
20 $0.00
TEST & BALANCE - PVN
PVNCOCO-1592PVN
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 214
INSTALL ELEVATOR - ALL LVLS PVN
PVNALAL-1400PVN
44 $0.00
ERECT STAIR 3A - ALL LVLS PVN
PVNALAL-0555PVN
20 $0.00
FINISH STAIR CORES -ALL LVLS PVN
PVNALAL-0991PVN
44 $0.00
ERECT STAIR 2 - ALL LVLS PVN
PVNALAL-3130PVN
20 $0.00
ERECT STAIR 1 - ALL LVLS PVN
PVNALAL-3120PVN
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 215
DRIVE SOLDIER PILES - SERV LVL PVN
PVNSLSL-3130PVN
10 $0.00
FORM/PLACE/TENSIONDECKS - LVLS 1-5 PVN
PVNALAL-0310PVN
100 $0.00
WATERPROOFING/FINISDOCK LID - SERV LVL DOCK PVN
PVNSLDO-0730PVN
20 $0.00
FORM/PLACE/TENSIONDOCK LID - SERV LVL DOCK PVN
PVNSLDO-0366PVN
21 $0.00
FORM/REINFORCE/PLACOMD - SERV LVL DOCK PVN
PVNSLDO-0370PVN
5 $0.00
ERECT STRUCTURAL STEEL/CORES/ROOF - SERV LVL DOCK PVN
PVNSLDO-0560PVN
25 $0.00
BELOW GRADE UTILITY ROUGH-IN - SERV LVL PARK PVN
PVNSLPK-0266PVN
10 $0.00
FORM/PLACE FOUNDATION WALLS - SERV LVL PARK PVN
PVNSLPK-0322PVN
30 $0.00
BACKFILL DOCK FOUNDATION WALLS - SERV LVL PARK PVN
PVNSLPK-0245PVN
10 $0.00
BACKFILL FOUNDATION WALLS - SERV LVL PARK PVN
PVNSLPK-0244PVN
10 $0.00
FORM/PLACE RAMP WALLS - SERV LVL PARK PVN
PVNSLPK-0323PVN
30 $0.00
DRILL/PLACE CAISSONS - SERV LVL PARK PVN
PVNSLPK-0320PVN
10 $0.00
DRILL/PLACE BALANCE OF CAISSONS - SERV LVLPARK PVN
PVNSLPK-1676PVN
5 $0.00
POUR PIER CAPS - SERV LVL PVN - SERV LVL PARK PVN
PVNSLPK-0350PVN
10 $0.00
START-UP ELECTRICAL SYSTEMS(pvn/con) - SERV LVL PARK PVN
PVNSLPK-1641PVN
30 $0.00
PULL WIRE FROM CON- SER LVL PARK PVN
PVNSLPK-1666PVN
5 $0.00
ROUGH-IN/INSTALL SUBSTATION - SERV LVL PARK PVN
PVNSLPK-1620PVN
10 $0.00
FORM/PLACE SOG/EQUIPMENT PADS - SERV LVL PARK PVN
PVNSLPK-0344PVN
20 $0.00
FORM/PLACE FOUNDATION WALLS/ELEVATOR PITS - SERV LVL DOCKPVN
PVNSLDO-0322PVN
45 $0.00
DRILL/PLACE CAISSONS - SERV LVL DOCK PVN
PVNSLDO-0320PVN
10 $0.00
BACKFILL DOCK WALLS - SERV LVL DOCK PVN
PVNSLDO-0288PVN
5 $0.00
FORM/PLACE COLUMNS - SERV LVL DOCK PVN
PVNSLDO-0390PVN
10 $0.00
POUR PIER CAPS - SERV LVL DOCK PVN
PVNSLDO-0350PVN
10 $0.00
FORM/PLACE/FINISH SLAB ON GRADE - SERV LVL DOCK PVN
PVNSLDO-0352PVN
5 $0.00
SHORING/MASS EXCAVATION/RECONDI- SERV LVL PVN
PVNSLSL-3100PVN
30 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PVN STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 216
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-6 PSN
PSNL6L6-8910PSN
10 $0.00
GARAGE FINISHES - LVL-6 PSN
PSNL6L6-1610PSN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-6 PSN
PSNL6L6-1600PSN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN INTERIOR LEVEL 6 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 217
GARAGE FINISHES - LVL-5 PSN
PSNL5L5-1610PSN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-5 PSN
PSNL5L5-1600PSN
25 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-5 PSN
PSNL5L5-8910PSN
10 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN INTERIOR LEVEL 5 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 218
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-4 PSN
PSNL4L4-8910PSN
10 $0.00
GARAGE FINISHES - LVL-4 PSN
PSNL4L4-1610PSN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-4 PSN
PSNL4L4-1600PSN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN INTERIOR LEVEL 4 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 219
ROUGH-IN MEP/FIRE PROTECTION - LVL-3 PSN
PSNL3L3-1600PSN
25 $0.00
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-3 PSN
PSNL3L3-8910PSN
10 $0.00
GARAGE FINISHES - LVL-3 PSN
PSNL3L3-1610PSN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN INTERIOR LEVEL 3 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 220
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-2 PSN
PSNL2L2-8900PSN
10 $0.00
GARAGE FINISHES - LVL -2 PSN
PSNL2L2-1590PSN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-2 PSN
PSNL2L2-1580PSN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 221
CLEAN-UP/PRE PUNCH/FINAL PUNCH -LVL-1 PSN
PSNL1L1-8890PSN
10 $0.00
GARAGE FINISHES - LVL-1 PSN
PSNL1L1-1570PSN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-1 PSN
PSNL1L1-1560PSN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 222
CLEAN-UP/PRE PUNCH/FINAL PUNCH -ROOF LVL PSN
PSNESRL-8910PSN
10 $0.00
INSTALL GLASS ROOFING SYSTEM - ROOF LVL PSN
PSNESRL-1610PSN
40 $0.00
INSTALL ROOF TRELLIS SYSTEM - ROOF LVL PSN
PSNESRL-1600PSN
20 $0.00
INSTALL EXTERIOR SKIN FINISHES - ALL ELEVATIONS PSN
PSNESES-0320PSN
40 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 223
FUNCTIONAL TESTING/CORRECTION- PSN
PSNCOCO-1596PSN
15 $0.00
PRE-FUNCTIONAL TESTING/CORRECTION- PSN
PSNCOCO-1594PSN
15 $0.00
CREATE/COMPLETE FINAL PUNCHLIST - PSN
PSNCOCO-9999PSN
20 $0.00
TEST & BALANCE - PSN
PSNCOCO-1592PSN
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 224
FINISH STAIR CORES -ALL LVLS PSN
PSNALAL-0991PSN
20 $0.00
ERECT STAIRS - ALL LVLS PSN
PSNALAL-0555PSN
20 $0.00
INSTALL ELEVATOR - ALL LVLS PSN
PSNALAL-1400PSN
60 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 225
UNDERSLAB UTILITIES/PLACE SLABON GRADE - ALL LVLS PSN
PSNALAL-0300PSN
35 $0.00
FORM/PLACE/POST TENSION DECKS - ALL LVLS PSN
PSNALAL-0310PSN
125 $0.00
FORM/PLACE/PIER CAPS/FTGS/ELEV PITS/ WALLS/ COLUMNS - ALL LVLS PSN
PSNALAL-0290PSN
45 $0.00
DRILL/PLACE CAISSONS - SERV LVL PSN
PSNSLSL-3150PSN
30 $0.00
SHORING/MASS EXCAVATION/RECONDI- SERV LVL PSN
PSNSLSL-3100PSN
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - PSN STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - RESPONSIB
2222-BUIL...Original
DurationBudgeted
Total Cost
Page 226
INTERFACE TESTS/INSPECTION SERV LVL BIO IBS
IBSSLBM-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - SERV LVL BIO IBS
IBSSLBM-1190IBS
35 $0.00
FRAMING/INWALL ROUGH - SERV LVL BIO IBS
IBSSLBM-0910IBS
55 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL BIO IBS
IBSSLBM-0990IBS
30 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL BIO IBS
IBSSLBM-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL BIO IBS
IBSSLBM-0920IBS
20 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL BIO IBS
IBSSLBM-1516IBS
15 $0.00
INSTALL OWNER FIXED FF&E - SERVLVL BIO IBS
IBSSLBM-0977VA IBS
20 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL CORR IBS
IBSSLCO-8880IBS
15 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CORR IBSIBSSLCO-0990
IBS25 $0.00
TRIM-OUT MEP/FIRE PROTECTION - SERV LVL INTER LVL IBSIBSSLIL-1517
IBS25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - SERV LVL INTER LVL IBSIBSSLIL-1516
IBS60 $0.00
INTERFACE TESTS/INSPECTION SERV LVL ENVIRO IBS
IBSSLES-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - SERV LVL ENVIRO IBS
IBSSLES-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL ENVIRO IBSIBSSLES-0990
IBS35 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL ENVIRO IBS
IBSSLES-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL ENVIRO IBS
IBSSLES-0920IBS
20 $0.00
FRAMING/INWALL ROUGH - SERV LVL ENVIRO IBS
IBSSLES-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL ENVIRO IBSIBSSLES-1516
IBS15 $0.00
INSTALL OWNER FIXED FF&E - SERVLVL ENVIRO IBS
IBSSLES-0977VA IBS
20 $0.00
INSTALL MEDICAL HEADWALLS - SERV LVL PATH IBS
IBSSLPA-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL PATH IBSIBSSLPA-0990
IBS35 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL PATH IBS
IBSSLPA-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL PATH IBS
IBSSLPA-0920IBS
20 $0.00
FRAMING/INWALL ROUGH - SERV LVL PATH IBS
IBSSLPA-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL PATH IBSIBSSLPA-1516
IBS15 $0.00
INTERFACE TESTS/INSPECTION SERV LVL PATH IBS
IBSSLPA-8890IBS
10 $0.00
INSTALL OWNER FIXED FF&E - SERVLVL PATH IBS
IBSSLPA-0977VA IBS
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CANTEEN IBSIBSSLCA-0990
IBS30 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL CANTEEN IBS
IBSSLCA-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL CANTEEN IBS
IBSSLCA-0920IBS
20 $0.00
FRAMING/INWALL ROUGH - SERV LVL CANTEEN IBS
IBSSLCA-0910IBS
45 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 CANTEEN IBSIBSSLCA-1516
IBS15 $0.00
INSTALL OWNER FIXED FF&E - SERVLVL CANTEEN IBS
IBSSLCA-0977VA IBS
20 $0.00
INSTALL MEDICAL HEADWALLS - SERV LVL SHELL IBS
IBSSLCS-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHELL IBSIBSSLCS-0990
IBS30 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL SHELL IBS
IBSSLCS-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL SHELL IBS
IBSSLCS-0920IBS
20 $0.00
INSTALL OWNER FIXED FF&E - SERVLVL SHELL IBS
IBSSLCS-0977VA IBS
15 $0.00
FRAMING/INWALL ROUGH - SERV LVL SHELL IBS
IBSSLCS-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHELL IBSIBSSLCS-1516
IBS10 $0.00
INTERFACE TESTS/INSPECTION SERV LVL SHELL IBS
IBSSLCS-8890IBS
10 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS INTERIOR SERVICE LEVEL NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 227
HANG/TAPE/FINISHDRYWALL - PIPE BSMT IBS
IBSPBPB-0920IBS
15 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - PIPE BSMT IBS
IBSPBPB-0990IBS
10 $0.00
CLEAN-UP/PRE PUNCH - PIPE BSMT IBS
IBSPBPB-8880IBS
15 $0.00
FRAMING/INWALL ROUGH - PIPE BSMT IBS
IBSPBPB-0910IBS
10 $0.00
R-I OVERHEAD MEP/FIRE PRO - PIPE BSMT IBS
IBSPBPB-1516IBS
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS INTERIOR PIPE BASEMENT NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 228
ROUGH-IN/CONNECELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC IBSIBSPHEL-1620
IBS70 $0.00
HANG/TAPE/FINISHDRYWALL - PENT ELEC IBS
IBSPHEL-0920IBS
10 $0.00
FRAMING/INWALL ROUGH - PENT ELEC IBS
IBSPHEL-0910IBS
10 $0.00
START-UP ELECTRICAL SYSTEMS - PENT MECH IBS
IBSPHME-1641IBS
30 $0.00
START-UP MECH EQUIP - PENT MECH IBS
IBSPHME-1590IBS
20 $0.00
CONNECT/PIPE-UPMECH EQUIP - PENT MECH IBS
IBSPHME-1520IBS
60 $0.00
LAY CMU WALLS - PENT MECH IBS
IBSPHME-0420IBS
15 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENT MECH IBS
IBSPHME-1516IBS
45 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS INTERIOR PENTHOUSE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 229
INTERFACE TESTS/INSPECTION- LVL-3 SHELL IBS
IBSL3CS-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-3 SHELL IBS
IBSL3CS-1190IBS
35 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 SHELL IBS
IBSL3CS-1516IBS
15 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SHELL IBS
IBSL3CS-0990IBS
25 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 SHELL IBS
IBSL3CS-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 SHELL IBS
IBSL3CS-0920IBS
25 $0.00
FRAMING/INWALL ROUGH - LVL-3 SHELL IBS
IBSL3CS-0910IBS
55 $0.00
INSTALL OWNER FIXED FF&E - LVL-3SHELL IBS
IBSL3CS-0977VA IBS
20 $0.00
FRAMING/INWALL ROUGH - LVL-3 PATIENT IBS
IBSL3PR-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-3 PATIENT IBS
IBSL3PR-1516IBS
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-3PATIENT IBS
IBSL3PR-0977VA IBS
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-3 PATIENT IBS
IBSL3PR-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-3 PATIENT IBS
IBSL3PR-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PATIENT IBS
IBSL3PR-0990IBS
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 PATIENT IBS
IBSL3PR-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 PATIENT IBS
IBSL3PR-0920IBS
40 $0.00
TRIM-OUT MEP/FIRE PROTECTION - LVL-3 INTER IBS
IBSL3IL-1517IBS
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-3 INTER IBS
IBSL3IL-1516IBS
100 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CORR IBS
IBSL3CO-0990IBS
20 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 CORR IBS
IBSL3CO-8880IBS
10 $0.00
INTERFACE TESTS/INSPECTION- LVL-3 NURSING IBS
IBSL3NR-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-3 NURSING IBS
IBSL3NR-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 NURSING IBS
IBSL3NR-0990IBS
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 NURSING IBS
IBSL3NR-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 NURSING IBS
IBSL3NR-0920IBS
45 $0.00
FRAMING/INWALL ROUGH - LVL-3 NURSING IBS
IBSL3NR-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 NURSING IBS
IBSL3NR-1516IBS
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-3NURSING IBS
IBSL3NR-0977VA IBS
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS INTERIOR LEVEL 3 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 230
INTERFACE TESTS/INSPECTION- LVL-2 SHELL IBS
IBSL2CS-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-2 SHELL IBS
IBSL2CS-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SHELL IBS
IBSL2CS-0990IBS
15 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 SHELL IBS
IBSL2CS-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 SHELL IBS
IBSL2CS-0920IBS
25 $0.00
FRAMING/INWALL ROUGH - LVL-2 SHELL IBS
IBSL2CS-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SHELL IBS
IBSL2CS-1516IBS
15 $0.00
INSTALL OWNER FIXED FF&E - LVL-2SHELL IBS
IBSL2CS-0977VA IBS
20 $0.00
TRIM-OUT MEP/FIRE PROTECTION - LVL-2I NTER IBS
IBSL2IL-1517IBS
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-2 INTER IBS
IBSL2IL-1516IBS
100 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CORR IBS
IBSL2CO-0990IBS
20 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 CORR IBS
IBSL2CO-8880IBS
10 $0.00
INTERFACE TESTS/INSPECTION- LVL-2 PATIENT IBS
IBSL2PR-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-2 PATIENT IBS
IBSL2PR-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 PATIENT IBS
IBSL2PR-0990IBS
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 PATIENT IBS
IBSL2PR-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 PATIENT IBS
IBSL2PR-0920IBS
35 $0.00
FRAMING/INWALL ROUGH - LVL-2 PATIENT IBS
IBSL2PR-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-2 PATIENT IBS
IBSL2PR-1516IBS
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-2PATIENT IBS
IBSL2PR-0977VA IBS
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-2 NURSING IBS
IBSL2NR-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-2 NURSING IBS
IBSL2NR-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 NURSING IBS
IBSL2NR-0990IBS
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 NURSING IBS
IBSL2NR-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 NURSING IBS
IBSL2NR-0920IBS
35 $0.00
FRAMING/INWALL ROUGH - LVL-2 NURSING IBS
IBSL2NR-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 NURSING IBS
IBSL2NR-1516IBS
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-2NURSING IBS
IBSL2NR-0977VA IBS
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 231
INSTALL MEDICAL HEADWALLS - LVL-1 NURSING IBS
IBSL1NR-1190IBS
35 $0.00
INTERFACE TESTS/INSPECTION- LVL-1 NURSING IBS
IBSL1NR-8890IBS
10 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 NURSING IBS
IBSL1NR-0920IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 NURSING IBS
IBSL1NR-0990IBS
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 NURSING IBS
IBSL1NR-8880IBS
15 $0.00
FRAMING/INWALL ROUGH - LVL-1 NURSING IBS
IBSL1NR-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 NURSING IBS
IBSL1NR-1516IBS
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-1NURSING IBS
IBSL1NR-0977VA IBS
20 $0.00
TRIM-OUT MEP/FIRE PROTECTION - LVL-1 INTER IBS
IBSL1IL-1517IBS
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-1 INTER IBS
IBSL1IL-1516IBS
100 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 CORR IBS
IBSL1CO-0990IBS
20 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 CORR IBS
IBSL1CO-8880IBS
10 $0.00
INTERFACE TESTS/INSPECTION- LVL-1 PATIENT IBS
IBSL1PR-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-1 PATIENT IBS
IBSL1PR-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PATIENT IBS
IBSL1PR-0990IBS
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 PATIENT IBS
IBSL1PR-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 PATIENT IBS
IBSL1PR-0920IBS
35 $0.00
FRAMING/INWALL ROUGH - LVL-1 PATIENT IBS
IBSL1PR-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-1 PATIENT IBS
IBSL1PR-1516IBS
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-1PATIENT IBS
IBSL1PR-0977VA IBS
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-1 SHELL IBS
IBSL1CS-8890IBS
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-1 SHELL IBS
IBSL1CS-1190IBS
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SHELL IBS
IBSL1CS-0990IBS
20 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 SHELL IBS
IBSL1CS-8880IBS
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 SHELL IBS
IBSL1CS-0920IBS
25 $0.00
FRAMING/INWALL ROUGH - LVL-1 SHELL IBS
IBSL1CS-0910IBS
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 SHELL IBS
IBSL1CS-1516IBS
10 $0.00
INSTALL OWNER FIXED FF&E - LVL-1SHELL IBS
IBSL1CS-0977VA IBS
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 232
FINISH STAIR CORE ST2 - ALL LVLS IBS
IBSALAL-0991IBS
15 $0.00
FINISH STAIR CORE ST1 - ALL LVLS IBS
IBSALAL-0990IBS
15 $0.00
ERECT STAIRS ST2- ALL LVLS IBS
IBSALAL-0556IBS
15 $0.00
ERECT STAIRS ST1- ALL LVLS IBS
IBSALAL-0555IBS
15 $0.00
INSTALL ELEVATOR PE3/PE4 - ALL LVLSIBS
IBSALAL-1401IBS
60 $0.00
INSTALL ELEVATOR SE04 - ALL LVLS IBS
IBSALAL-1400IBS
60 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS INTERIOR ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 233
INSTALL METAL PANELS - NORTH ELEV IBN
IBSESNE-890IBS
15 $0.00
INSTALL STRIP WINDOWS - NORTH ELEV IBS
IBSESNE-0820IBS
15 $0.00
INSTALL PRECAST PANELS - NORTH ELEV IBS
IBSESNE-0870IBS
10 $0.00
INSTALL STRIP WINDOWS - WEST ELEV IBS
IBSESWE-0880IBS
5 $0.00
INSTALL STOREFRONT - WEST ELEV IBS
IBSESWE-0870IBS
10 $0.00
ERECT/CONNECT PEDESTRIAN BRIDGE - SOUTH ELEV IBS
IBSESSE-0580IBS
22 $0.00
INSTALL CURTAIN WALL - SOUTH ELEV IBS
IBSESSE-0870IBS
50 $0.00
INSTALL METAL PANELS - SOUTH ELEV IBS
IBSESSE-0880IBS
15 $0.00
INSTALL PRECAST PANELS - SOUTH ELEV IBS
IBSESSE-0877IBS
5 $0.00
INSTALL METAL PANELS - EAST ELEV IBS
IBSESEE-0880IBS
12 $0.00
INSTALL STRIP WINDOWS - EAST ELEV IBS
IBSESEE-870IBS
5 $0.00
INSTALL PRECAST PANELS - EAST ELEV IBS
IBSESEE-0870IBS
10 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 234
FUNCTIONAL TESTING/CORRECT- IBS
IBSCOCO-1596IBS
20 $0.00
PRE-FUNCTIONAL TESTING/CORRECT- IBS
IBSCOCO-1594IBS
20 $0.00
CREATE/COMPLETEFINAL PUNCHLIST -IBS
IBSCOCO-9999IBS
30 $0.00
BUILDING FLUSH - IBS
IBSCOCO-1599IBS
10 $0.00
TEST & BALANCE - IBS
IBSCOCO-1592IBS
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 235
FORM/PLACE TOWER CRANE #3 BASE (IBS/IBN CON B)
IBSPBPB-0103IBS
35 $0.00
DRIVE SOLDIER PILES - PIPE BSMT IBS
IBSPBPB-3130IBS
10 $0.00
SET/BACKFILL DUCTBANKS - PIPEBSMT IBS
IBSPBPB-3110IBS
5 $0.00
UNDERSLAB UTILITIES - PIPE BSMT IBS
IBSPBPB-3200IBS
15 $0.00
PERM DRAINS/BACKFILL -PIPE BSMT IBS
IBSPBPB-0390IBS
14 $0.00
SHORING/MASS EXCAVATION/RECO- PIPE BSMT IBS
IBSPBPB-3100IBS
28 $0.00
FORM/PLACE/PIER CAPS/TIE BEAMS/ELEV PITS/ WALLS/ COLUMNS/COREIBSPBPB-0330
IBS125 $0.00
FORM/PLACE/FINISHSLAB ON GRADE - PIPE BSMT IBS
IBSPBPB-0380IBS
5 $0.00
DRILL/PLACE CAISSONS - PIPE BSMT IBS
IBSPBPB-0320IBS
25 $0.00
FORM/PLACE EQUIPMENT PADS - PENT IBS
IBSPHPH-1610IBS
5 $0.00
INSTALL METAL PANEL - PENT IBS
IBSPHPH-0777IBS
10 $0.00
INSTALL LOUVERS - PENT IBS
IBSPHPH-0710IBS
10 $0.00
ERECT EXTERIOR STUDS/SHEATHINGBARRIER - PENT IBS
IBSPHPH-0540IBS
15 $0.00
SPRAY-ON FIREPROOFING - PENT IBS
IBSPHPH-0725IBS
8 $0.00
FORM/REINFORCE/TOPPING SLAB - PENT IBS
IBSPHPH-0320IBS
9 $0.00
ERECT STRUCTURAL STEEL/DECK - PENT IBS
IBSPHPH-0510IBS
15 $0.00
SET ELECTRICAL EQUIPMENT - PENT IBS
IBSPHPH-1600IBS
10 $0.00
SET MECH EQUIPMENT - PENT IBS
IBSPHPH-1500IBS
15 $0.00
ERECT INTERSTITIAL STEEL/TOPPING - LVL-2 INTERSTITIAL LVIBSL2IL-0510
IBS35 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-2 IBS
IBSL2L2-0320IBS
9 $0.00
ERECT EXTERIOR STUDS/SHEATHING- LVL-2 IBS
IBSL2L2-0540IBS
20 $0.00
ERECT STRUCTURAL STEEL/DECK - LVL-2 IBS
IBSL2L2-0510IBS
15 $0.00
SPRAY-ON FIREPROOFING - LVL-2 IBS
IBSL2L2-0725IBS
8 $0.00
SET/CONNECT PHOTOVOLTAIC PANELS - ROOF IBS
IBSRLRL-2600IBS
40 $0.00
INSTALL GREEN ROOF SYSTEM - ROOF IBS
IBSRLRL-2610IBS
15 $0.00
INSTALL ROOFING - ROOF IBS
IBSRLRL-0750IBS
20 $0.00
FORM/REINFORCE/TOPPING SLAB - ROOF IBS
IBSRLRL-0320IBS
9 $0.00
ERECT STRUCTURAL STEEL/DECK - ROOF IBS
IBSRLRL-0510IBS
15 $0.00
ERECT INTERSTITIAL STEEL/TOPPING - LVL-3 INTERSTITIAL LVIBSL3IL-0510
IBS35 $0.00
SPRAY-ON FIREPROOFING - LVL-3 IBS
IBSL3L3-0725IBS
8 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-3 IBS
IBSL3L3-0320IBS
9 $0.00
ERECT EXTERIOR STUDS/SHEATHING- LVL-3 IBS
IBSL3L3-0540IBS
20 $0.00
ERECT STRUCTURAL STEEL/DECK - LVL-3 IBS
IBSL3L3-0510IBS
15 $0.00
ERECT INTERSTITIAL STEEL/TOPPING - LVL-1 INTERSTITIAL LVIBSL1IL-0510
IBS35 $0.00
SPRAY-ON FIREPROOFING - LVL-1 IBS
IBSL1L1-0725IBS
8 $0.00
FORM/REINFORCE/RTOPPING SLAB - LVL-1 IBS
IBSL1L1-0320IBS
9 $0.00
ERECT EXTERIOR STUDS/SHEATHING- LVL-1 IBS
IBSL1L1-0540IBS
20 $0.00
ERECT STRUCTURAL STEEL/DECK - LVL-1 IBS
IBSL1L1-0510IBS
15 $0.00
ERECT INTERSTITIAL STEEL/TOPPING - SERVICE LEVEL INTERSTITIAL LVIBSSLIL-0510
IBS35 $0.00
SPRAY-ON FIREPROOFING - SERVICE LEVEL IBS
IBSSLSL-0725IBS
8 $0.00
FORM/REINFORCE/TOPPING SLAB - SERVICE LEVEL IBS
IBSSLSL-0320IBS
9 $0.00
ERECT STRUCTURAL STEEL/DECK - SERVICE LEVEL IBSIBSSLSL-0510
IBS15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBS STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 236
TRIM-OUT MEP/FIRE PROTECTION - SERV LVL INTER LVL IBNIBNSLIL-1517
IBN25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - SERV LVL INTER LVL IBNIBNSLIL-1516
IBN60 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL CORR IBN
IBNSLCO-8880IBN
15 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL CORR IBNIBNSLCO-0990
IBN20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL MAIL IBN
IBNSLMR-0990IBN
30 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL MAIL IBN
IBNSLMR-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL MAIL IBN
IBNSLMR-0920IBN
30 $0.00
FRAMING/INWALL ROUGH - SERV LVL MAIL IBN
IBNSLMR-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 MAIL IBN
IBNSLMR-1516IBN
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL SHELL IBNIBNSLCS-0990
IBN15 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL SHELL IBN
IBNSLCS-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL SHELL IBN
IBNSLCS-0920IBN
20 $0.00
FRAMING/INWALL ROUGH - SERV LVL SHELL IBN
IBNSLCS-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL SHELL IBNIBNSLCS-1516
IBN15 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - SERV LVL WAREHOUSE IBNIBNSLWH-1516
IBN20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - SERV LVL WAREHOUSE IBNIBNSLWH-0990
IBN30 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL WAREHOUSE IBN
IBNSLWH-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL WAREHOUSE IBN
IBNSLWH-0920IBN
35 $0.00
FRAMING/INWALL ROUGH - SERV LVL WAREHOUSE IBN
IBNSLWH-0910IBN
55 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN INTERIOR SERVICE LEVEL NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 237
ROUGH-IN/CONNECELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC IBNIBNPHEL-1620
IBN70 $0.00
HANG/TAPE/FINISHDRYWALL - PENT ELEC IBN
IBNPHEL-0920IBN
10 $0.00
FRAMING/INWALL ROUGH - PENT ELEC IBN
IBNPHEL-0910IBN
10 $0.00
START-UP ELECTRICAL SYSTEMS - PENT MECH IBN
IBNPHME-1641IBN
30 $0.00
START-UP MECH EQUIP - PENT MECH IBN
IBNPHME-1590IBN
20 $0.00
CONNECT/PIPE-UPMECH EQUIP - PENT MECH IBN
IBNPHME-1520IBN
60 $0.00
LAY CMU WALLS - PENT MECH IBN
IBNPHME-0420IBN
15 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENT MECH IBN
IBNPHME-1516IBN
45 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN INTERIOR PENTHOUSE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 238
INTERFACE TESTS/INSPECTION- LVL-3 PATIENT IBN
IBNL3PR-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-3 PATIENT IBN
IBNL3PR-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 PATIENT IBN
IBNL3PR-0990IBN
35 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 PATIENT IBN
IBNL3PR-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 PATIENT IBN
IBNL3PR-0920IBN
35 $0.00
FRAMING/INWALL ROUGH - LVL-3 PATIENT IBN
IBNL3PR-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-3 PATIENT IBN
IBNL3PR-1516IBN
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-3PATIENT IBN
IBNL3PR-0977VA IBN
25 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 CORR IBN
IBNL3CO-0990IBN
20 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 CORR IBN
IBNL3CO-8880IBN
10 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 REHAB IBN
IBNL3RH-0990IBN
25 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 REHAB IBN
IBNL3RH-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 REHAB IBN
IBNL3RH-0920IBN
35 $0.00
FRAMING/INWALL ROUGH - LVL-3 REHAB IBN
IBNL3RH-0910IBN
60 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 REHAB IBN
IBNL3RH-1516IBN
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-3REHAB IBN
IBNL3RH-0977VA IBN
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-3 REHAB IBN
IBNL3RH-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-3 REHAB IBN
IBNL3RH-1190IBN
35 $0.00
TRIM-OUT MEP/FIRE PROTECTION - LVL-3 INTER IBN
IBNL3IL-1517IBN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-3 INTER IBN
IBNL3IL-1516IBN
100 $0.00
FRAMING/INWALL ROUGH - LVL-3 NURSING IBN
IBNL3NR-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 NURSING IBN
IBNL3NR-1516IBN
25 $0.00
INTERFACE TESTS/INSPECTION- LVL-3 NURSING IBN
IBNL3NR-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-3 NURSING IBN
IBNL3NR-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 NURSING IBN
IBNL3NR-0990IBN
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 NURSING IBN
IBNL3NR-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 NURSING IBN
IBNL3NR-0920IBN
35 $0.00
INSTALL OWNER FIXED FF&E - LVL-3PATIENT IBN
IBNL3NR-0977VA IBN
20 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 SHELL IBN
IBNL3CS-0920IBN
35 $0.00
INTERFACE TESTS/INSPECTION- LVL-3 SHELL IBN
IBNL3CS-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-3 SHELL IBN
IBNL3CS-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SHELL IBN
IBNL3CS-0990IBN
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 SHELL IBN
IBNL3CS-8880IBN
15 $0.00
FRAMING/INWALL ROUGH - LVL-3 SHELL IBN
IBNL3CS-0910IBN
35 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-3 SHELL IBN
IBNL3CS-1516IBN
15 $0.00
INSTALL OWNER FIXED FF&E - LVL-3SHELL IBN
IBNL3CS-0977VA IBN
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 239
HANG/TAPE/FINISHDRYWALL - LVL-2 NURSING IBN
IBNL2NR-0920IBN
35 $0.00
INTERFACE TESTS/INSPECTION- LVL-2 NURSING IBN
IBNL2NR-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-2 NURSING IBN
IBNL2NR-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 NURSING IBN
IBNL2NR-0990IBN
35 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 NURSING IBN
IBNL2NR-8880IBN
15 $0.00
FRAMING/INWALL ROUGH - LVL-2 NURSING IBN
IBNL2NR-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 NURSING IBN
IBNL2NR-1516IBN
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-2NURSING IBN
IBNL2NR-0977VA IBN
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-2 PATIENT IBN
IBNL2PR-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-2 PATIENT IBN
IBNL2PR-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 PATIENT IBN
IBNL2PR-0990IBN
35 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 PATIENT IBN
IBNL2PR-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 PATIENT IBN
IBNL2PR-0920IBN
35 $0.00
FRAMING/INWALL ROUGH - LVL-2 PATIENT IBN
IBNL2PR-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-2 PATIENT IBN
IBNL2PR-1516IBN
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-2PATIENT IBN
IBNL2PR-0977VA IBN
20 $0.00
TRIM-OUT MEP/FIRE PROTECTION - LVL-2 INTER IBN
IBNL2IL-1517IBN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-2 INTER IBN
IBNL2IL-1516IBN
100 $0.00
INTERFACE TESTS/INSPECTION- LVL-2 SUPPORT IBN
IBNL2SS-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-2 SUPPORT IBN
IBNL2SS-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SUPPORT IBNIBNL2SS-0990
IBN25 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 SUPPORT IBN
IBNL2SS-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 SUPPORT IBN
IBNL2SS-0920IBN
45 $0.00
FRAMING/INWALL ROUGH - LVL-2 SUPPORT IBN
IBNL2SS-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SUPPORT IBNIBNL2SS-1516
IBN20 $0.00
INSTALL OWNER FIXED FF&E - LVL-2SUPPORT IBN
IBNL2SS-0977VA IBN
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-2 SHELL IBN
IBNL2CS-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-2 SHELL IBN
IBNL2CS-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SHELL IBN
IBNL2CS-0990IBN
20 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 SHELL IBN
IBNL2CS-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 SHELL IBN
IBNL2CS-0920IBN
20 $0.00
FRAMING/INWALL ROUGH - LVL-2 SHELL IBN
IBNL2CS-0910IBN
15 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-2 SHELL IBN
IBNL2CS-1516IBN
15 $0.00
INSTALL OWNER FIXED FF&E - LVL-2SHELL IBN
IBNL2CS-0977VA IBN
15 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 CORR IBN
IBNL2CO-8880IBN
10 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 CORR IBN
IBNL2CO-0990IBN
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 240
TRIM-OUT MEP/FIRE PROTECTION - LVL-1 INTER IBN
IBNL1IL-1517IBN
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - LVL-1 INTER IBN
IBNL1IL-1516IBN
100 $0.00
INSTALL MEDICAL HEADWALLS - LVL-1 OFFICE IBN
IBNL1OF-1190IBN
35 $0.00
INTERFACE TESTS/INSPECTION- LVL-1 OFFICE IBN
IBNL1OF-8890IBN
10 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 OFFICE IBN
IBNL1OF-0990IBN
30 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 OFFICE IBN
IBNL1OF-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 OFFICE IBN
IBNL1OF-0920IBN
25 $0.00
FRAMING/INWALL ROUGH - LVL-1 OFFICE IBN
IBNL1OF-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 OFFICE IBN
IBNL1OF-1516IBN
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-1PT/OT IBN
IBNL1OF-0977VA IBN
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 CORR IBN
IBNL1CO-0990IBN
20 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 CORR IBN
IBNL1CO-8880IBN
10 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SHELL IBN
IBNL1CS-0990IBN
15 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 SHELL IBN
IBNL1CS-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 SHELL IBN
IBNL1CS-0920IBN
15 $0.00
FRAMING/INWALL ROUGH - LVL-1 SHELL IBN
IBNL1CS-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 SHELL IBN
IBNL1CS-1516IBN
15 $0.00
INSTALL OWNER FIXED FF&E - LVL-1PT/OT IBN
IBNL1CS-0977VA IBN
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-1 PT/OT IBN
IBNL1PR-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-1 PT/OT IBN
IBNL1PR-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PT/OT IBN
IBNL1PR-0990IBN
25 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 PT/OT IBN
IBNL1PR-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 PT/OT IBN
IBNL1PR-0920IBN
35 $0.00
FRAMING/INWALL ROUGH - LVL-1 PT/OT IBN
IBNL1PR-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO- LVL-1 PT/OT IBN
IBNL1PR-1516IBN
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-1PT/OT IBN
IBNL1PR-0977VA IBN
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-1 PHARMACYIBN
IBNL1PY-8890IBN
10 $0.00
INSTALL MEDICAL HEADWALLS - LVL-1 PHARMACY IBN
IBNL1PY-1190IBN
35 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 PHARMACY IBNIBNL1PY-0990
IBN25 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 PHARMACY IBN
IBNL1PY-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 PHARMACY IBN
IBNL1PY-0920IBN
25 $0.00
FRAMING/INWALL ROUGH - LVL-1 PHARMACY IBN
IBNL1PY-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 PHARMACY IBNIBNL1PY-1516
IBN20 $0.00
INSTALL OWNER FIXED FF&E - LVL-1PHARMACY IBN
IBNL1PY-0977VA IBN
20 $0.00
INTERFACE TESTS/INSPECTION- LVL-1 UROLOGY IBN
IBNL1UR-8890IBN
10 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 UROLOGY IBNIBNL1UR-0990
IBN30 $0.00
INSTALL MEDICAL HEADWALLS - LVL-1 UROLOGY IBN
IBNL1UR-1190IBN
35 $0.00
INSTALL OWNER FIXED FF&E - LVL-1UROLOGY IBN
IBNL1UR-0977VA IBN
20 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 UROLOGY IBN
IBNL1UR-8880IBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 UROLOGY IBN
IBNL1UR-0920IBN
25 $0.00
FRAMING/INWALL ROUGH - LVL-1 UROLOGY IBN
IBNL1UR-0910IBN
55 $0.00
PUNCH THRU/R-I OVERHEAD MEP/FIRE PRO - LVL-1 UROLOGY IBNIBNL1UR-1516
IBN20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 241
FINISH STAIR CORE ST1 - ALL LVLS IBN
IBNALAL-0990IBN
15 $0.00
FINISH STAIR CORE ST2 - ALL LVLS IBN
IBNALAL-0991IBN
15 $0.00
ERECT STAIRS ST1- ALL LVLS IBN
IBNALAL-0555IBN
15 $0.00
INSTALL ELEVATOR PE1/PE2 - ALL LVLSIBN
IBNALAL-1401IBN
60 $0.00
INSTALL ELEVATOR SE1/SE2 - ALL LVLSIBN
IBNALAL-1400IBN
60 $0.00
ERECT STAIRS ST2- ALL LVLS IBN
IBNALAL-0556IBN
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN INTERIOR ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 242
INSTALL METAL PANELS - NORTH ELEV IBN
IBNESNE-880IBN
15 $0.00
INSTALL STRIP WINDOWS - NORTH ELEV IBN
IBNESNE-870IBN
15 $0.00
INSTALL PRECAST PANELS - NORTH ELEV IBN
IBNESNE-0870IBN
10 $0.00
INSTALL CURTAIN WALL - SOUTH ELEV IBN
IBNESSE-0870IBN
20 $0.00
INSTALL METAL PANELS - SOUTH ELEV IBN
IBNESSE-870IBN
20 $0.00
INSTALL METAL PANELS - EAST ELEV IBN
IBNESEE-880IBN
12 $0.00
INSTALL CURTAIN WALL - EAST ELEV IBN
IBNESEE-870IBN
15 $0.00
INSTALL PRECAST PANELS - EAST ELEV IBN
IBNESEE-0870IBN
10 $0.00
INSTALL METAL PANELS - WEST ELEV IBN
IBNESWE-0870IBN
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 243
FUNCTIONAL TESTING/CORRECT- IBN
IBNCOCO-1596IBN
20 $0.00
PRE-FUNCTIONAL TESTING/CORRECT- IBN
IBNCOCO-1594IBN
20 $0.00
CREATE/COMPLETEFINAL PUNCHLIST -IBN
IBNCOCO-9999IBN
30 $0.00
BUILDING FLUSH - IBN
IBNCOCO-1599IBN
10 $0.00
TEST & BALANCE - IBN
IBNCOCO-1592IBN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 244
ERECT INTERSTITIAL STEEL/TOPPING - LVL-1 INTERSTITIAL LVIBNL1IL-0510
IBN35 $0.00
SPRAY-ON FIREPROOFING - LVL-1 IBN
IBNL1L1-0725IBN
8 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-1 IBN
IBNL1L1-0320IBN
9 $0.00
ERECT EXTERIOR STUDS/SHEATHING- LVL-1 IBN
IBNL1L1-0540IBN
20 $0.00
ERECT STRUCTURAL STEEL/DECK - LVL-1 IBN
IBNL1L1-0510IBN
15 $0.00
ERECT INTERSTITIAL STEEL/TOPPING - SERVICE LEVEL INTERSTITIAL LVIBNSLIL-0510
IBN35 $0.00
PERM DRAINS/BACKFILL -SERV LVL IBN
IBNSLSL-0390IBN
14 $0.00
FORM/PLACE/FINISHSLAB ON GRADE - SERV LVL IBN
IBNSLSL-0380IBN
5 $0.00
DRILL/PLACE CAISSONS - SERV LVL IBN
IBNSLSL-0320IBN
25 $0.00
FORM/PLACE/PIER CAPS/TIE BEAMS/ELEV/ WALLS/CORES - SERV LVL IBNIBNSLSL-0330
IBN110 $0.00
SHORING/MASS EXCAVATION/RECO- SERV LVL IBN
IBNSLSL-3100IBN
20 $0.00
DRIVE SOLDIER PILES - SERV LVL IBN
IBNSLSL-3130IBN
10 $0.00
SET/BACKFILL DUCTBANKS - SERV LVL IBN
IBNSLSL-3110IBN
5 $0.00
UNDERSLAB UTILITIES - SERV LVL IBN
IBNSLSL-3200IBN
15 $0.00
INSTALL GREEN ROOFING SYSTEM - ROOF IBN
IBNRLRL-2610IBN
15 $0.00
INSTALL ROOFING - ROOF IBN
IBNRLRL-0750IBN
20 $0.00
FORM/REINFORCE/TOPPING SLAB - ROOF IBN
IBNRLRL-0320IBN
9 $0.00
ERECT STRUCTURAL STEEL/DECK - ROOF IBN
IBNRLRL-0510IBN
15 $0.00
SET/CONNECT PHOTOVOLTAIC PANELS - ROOF IBN
IBNRLRL-2600IBN
40 $0.00
ERECT INTERSTITIAL STEEL/TOPPING - LVL-2 INTERSTITIAL LVIBNL2IL-0510
IBN35 $0.00
SPRAY-ON FIREPROOFING - LVL-2 IBN
IBNL2L2-0725IBN
8 $0.00
FORM/REINFORCE/RTOPPING SLAB - LVL-2 IBN
IBNL2L2-0320IBN
9 $0.00
ERECT EXTERIOR STUDS/SHEATHING- LVL-2 IBN
IBNL2L2-0540IBN
20 $0.00
ERECT STRUCTURAL STEEL/DECK - LVL-2 IBN
IBNL2L2-0510IBN
15 $0.00
ERECT INTERSTITIAL STEEL/TOPPING - LVL-3 INTERSTITIAL LVIBNL3IL-0510
IBN35 $0.00
SPRAY-ON FIREPROOFING - LVL-3 IBN
IBNL3L3-0725IBN
8 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-3 IBN
IBNL3L3-0320IBN
9 $0.00
ERECT EXTERIOR STUDS/SHEATHING- LVL-3 IBN
IBNL3L3-0540IBN
20 $0.00
ERECT STRUCTURAL STEEL/DECK - LVL-3 IBN
IBNL3L3-0510IBN
15 $0.00
FORM/PLACE FINISH EQUIPMENT PADS - PENT IBN
IBNPHPH-1610IBN
5 $0.00
SET ELECTRICAL EQUIPMENT - PENT IBN
IBNPHPH-1600IBN
10 $0.00
SPRAY-ON FIREPROOFING - PENT IBN
IBNPHPH-0725IBN
8 $0.00
FORM/REINFORCE/TOPPING SLAB - PENT IBN
IBNPHPH-0320IBN
9 $0.00
ERECT STRUCTURAL STEEL/DECK - PENT IBN
IBNPHPH-0510IBN
15 $0.00
INSTALL METAL PANELS - PENT IBN
IBNPHPH-0777IBN
10 $0.00
INSTALL LOUVERS - PENT IBN
IBNPHPH-0710IBN
10 $0.00
ERECT EXTERIOR STUDS/SHEATHINGBARRIER - PENT IBN
IBNPHPH-0540IBN
15 $0.00
SET MECH EQUIPMENT - PENT IBN
IBNPHPH-1500IBN
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - IBN STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 245
FRAMING/INWALL ROUGH - SERV LVL CBN
CBNSLSL-0910CBN
5 $0.00
HANG/TAPE/FINISH/- SERV LVL CORR CBN
CBNSLSL-0990CBN
10 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL CORR CBN
CBNSLSL-8880CBN
5 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN INTERIOR SERVICE LEVEL NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 246
LAY CMU WALLS - PENTHOUSE MECHCBN
CBNPHME-0420CBN
15 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECHCBNCBNPHME-1516
CBN30 $0.00
START-UP ELECTRICAL SYSTEMS - PENT MECH CBN
CBNPHME-1641CBN
30 $0.00
START-UP MECH EQUIP - PENT MECH CBN
CBNPHME-1590CBN
20 $0.00
CONNECT/PIPE-UPMECH EQUIP - PENTHOUSE MECHCBN
CBNPHME-1520CBN
25 $0.00
INTERIOR FINISHES - PENT ELEC CBN
CBNPHEL-1630CBN
30 $0.00
ROUGH-IN/CONNECELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC CBNCBNPHEL-1620
CBN75 $0.00
HANG/TAPE/FINISHDRYWALL - PENT ELEC CBN
CBNPHEL-0920CBN
15 $0.00
FRAMING/INWALL ROUGH - PENT ELEC CBN
CBNPHEL-0910CBN
10 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN INTERIOR PENTHOUSE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 247
FRAMING/INWALL ROUGH - LVL-3 AREA B CBN
CBNL3AB-0910CBN
14 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 AREA B CBN
CBNL3AB-1516CBN
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA B CBN
CBNL3AB-0990CBN
22 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 AREA B CBN
CBNL3AB-8880CBN
8 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 AREA B CBN
CBNL3AB-0920CBN
12 $0.00
INSTALL OWNER FIXED FF&E - LVL-3AREA-A CBN
CBNL3AB-0977VA CBN
15 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA A CBN
CBNL3AA-0990CBN
23 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 AREA A CBN
CBNL3AA-8880CBN
8 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 AREA A CBN
CBNL3AA-0920CBN
13 $0.00
FRAMING/INWALL ROUGH - LVL-3 AREA A CBN
CBNL3AA-0910CBN
14 $0.00
R-I OVERHEAD MEP/FIRE PRO- LVL-3 AREA A CBN
CBNL3AA-1516CBN
20 $0.00
INSTALL OWNER FIXED FF&E - LVL-3AREA-A CBN
CBNL3AA-0977VA CBN
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN INTERIOR LEVEL 3 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 248
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA B CBN
CBNL2AB-0990CBN
22 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 AREA B CBN
CBNL2AB-8880CBN
8 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 AREA B CBN
CBNL2AB-0920CBN
12 $0.00
FRAMING/INWALL ROUGH - LVL-2 AREA B CBN
CBNL2AB-0910CBN
14 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-2 AREA B CBN
CBNL2AB-1516CBN
17 $0.00
INSTALL OWNER FIXED FF&E - LVL-2AREA-B CBN
CBNL2AB-0977VA CBN
15 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 AREA A CBN
CBNL2AA-0920CBN
13 $0.00
FRAMING/INWALL ROUGH - LVL-2 AREA A CBN
CBNL2AA-0910CBN
14 $0.00
R-I OVERHEAD MEP/FIRE PRO- LVL-2 AREA A CBN
CBNL2AA-1516CBN
18 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA A CBN
CBNL2AA-0990CBN
23 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBN
CBNL2AA-8880CBN
8 $0.00
INSTALL OWNER FIXED FF&E - LVL-2AREA-A CBN
CBNL2AA-0977VA CBN
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 249
R-I OVERHEAD MEP/FIRE PRO- LVL-1 AREA A CBN
CBNL1AA-1516CBN
18 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA A CBN
CBNL1AA-0990CBN
23 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBN
CBNL1AA-8880CBN
8 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 AREA A CBN
CBNL1AA-0920CBN
13 $0.00
FRAMING/INWALL ROUGH - LVL-1 AREA A CBN
CBNL1AA-0910CBN
14 $0.00
INSTALL OWNER FIXED FF&E - LVL-1AREA-A CBN
CBNL1AA-0977VA CBN
15 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AREA B CBN
CBNL1AB-1516CBN
17 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA B CBN
CBNL1AB-0990CBN
22 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 AREA B CBN
CBNL1AB-8880CBN
8 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 AREA B CBN
CBNL1AB-0920CBN
12 $0.00
FRAMING/INWALL ROUGH - LVL-1 AREA B CBN
CBNL1AB-0910CBN
14 $0.00
INSTALL OWNER FIXED FF&E - LVL-3AREA-A CBN
CBNL1AB-0977VA CBN
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 250
FINISH STAIR CORE ST2 - ALL LVLS CBN
CBNALAL-0991CBN
15 $0.00
FINISH STAIR CORE ST1 - ALL LVLS CBN
CBNALAL-0990CBN
15 $0.00
ERECT STAIRS ST2- ALL LVLS CBN
CBNALAL-0556CBN
15 $0.00
ERECT STAIRS ST1- ALL LVLS CBN
CBNALAL-0555CBN
15 $0.00
INSTALL ELEVATOR SE5 - ALL LVLS CBN
CBNALAL-1400CBN
60 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN INTERIOR ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 251
INSTALL PRECAST PANELS - NORTH ELEV CBN
CBNESNE-0440CBN
8 $0.00
SHEATHING/VAPORBARRIER - NORTH ELEV CBN
CBNESNE-0520CBN
10 $0.00
INSTALL CURTAIN WALL - NORTH ELEV CBN
CBNESSE-877CBN
35 $0.00
SHEATHING/VAPORBARRIER - SOUTH ELEV CBN
CBNESSE-0520CBN
10 $0.00
INSTALL CURTAIN WALL - SOUTH ELEV CBN
CBNESSE-0870CBN
35 $0.00
INSTALL CURTAIN WALL - WEST ELEV CBN
CBNESSE-887CBN
20 $0.00
INSTALL PRECAST PANELS - WEST ELEV CBN
CBNESWE-0440CBN
4 $0.00
SHEATHING/VAPORBARRIER - WEST ELEV CBN
CBNESWE-0520CBN
5 $0.00
INSTALL METAL PANELS - EAST ELEV CBN
CBNESEE-0440CBN
5 $0.00
SHEATHING/VAPORBARRIER - EAST ELEV CBN
CBNESEE-0520CBN
5 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 252
PRE-FUNCTIONAL TESTING/CORRE...
CBNCOCO-1594CBN
20 $0.00
TEST & BALANCE - CBN
CBNCOCO-1620CBN
30 $0.00
CREATE/COMPLETEFINAL PUNCHLIST -CBN
CBNCOCO-9999CBN
33 $0.00
BUILDING FLUSH - CBN
CBNCOCO-1599CBN
20 $0.00
FUNCTIONAL TESTING/CORRECT- CBN
CBNCOCO-1596CBN
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 253
INSTALL ROOF ACCCESSORIES - LOW ROOF CBN
CBNLRLR-0760CBN
3 $0.00
INSTALL GREEN ROOF SYSTEM - LOW ROOF CBN
CBNLRLR-0750CBN
15 $0.00
PARAPET/BLOCKING- LOW ROOF CBN
CBNLRLR-0710CBN
10 $0.00
DRILL/PLACE CAISSONS (with concourse) - SERV LVL CBN
CBNSLSL-8890CBN
15 $0.00
SET/BACKFILL DUCTBANKS - SERV LVL CBN
CBNSLSL-3110CBN
5 $0.00
DRILL/PLACE CAISSONS (balance@ bench) - SERV LVL CBN
CBNSLSL-0320CBN
5 $0.00
UNDERSLAB UTILITIES - SERV LVL CBN
CBNSLSL-3200CBN
15 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/WALLS/GRD BEAMS - SERV LVL CBNCBNSLSL-0330
CBN35 $0.00
PERIMETER DRAINS/BACKFILL PIERCAPS/GRADE BEAMS - SERV LVL CBNCBNSLSL-0390
CBN14 $0.00
MASS EXCAVATION/RECO- SERV LVL CBN
CBNSLSL-3100CBN
15 $0.00
FINE GRADE/FORM/PLACSLAB ON GRADE - SERV LVL CBN
CBNSLSL-0380CBN
8 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-3 CBN
CBNL3L3-0320CBN
11 $0.00
SPRAY-ON FIREPROOFING - LVL-3 CBN
CBNL3L3-0725CBN
10 $0.00
ERECT EXTERIOR STUDS - LVL-3 CBN
CBNL3L3-0540CBN
15 $0.00
FORM/REINFORCE/RTOPPING SLAB - LVL-2 CBN
CBNL2L2-0320CBN
11 $0.00
SPRAY-ON FIREPROOFING - LVL-2 CBN
CBNL2L2-0725CBN
10 $0.00
ERECT EXTERIOR STUDS - LVL-2 CBN
CBNL2L2-0540CBN
15 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-1 CBN
CBNL1L1-0320CBN
11 $0.00
SPRAY-ON FIREPROOFING - LVL-1 CBN
CBNL1L1-0725CBN
10 $0.00
ERECT EXTERIOR STUDS - LVL-1 CBN
CBNL1L1-0540CBN
15 $0.00
INSTALL/CONNECTPV PANELS - PENT ROOF CBN
CBNHRPR-0740CBN
20 $0.00
APPLY ROOFING SYSTEM - PENT ROOF CBN
CBNHRPR-0788CBN
15 $0.00
BLOCKING/ICE WATER SHIELD- PENT ROOF CBN
CBNHRPR-0750CBN
20 $0.00
FORM/REINFORCE/TOPPING SLAB - PENT ROOF CBN
CBNPHPR-0320CBN
11 $0.00
FORM/REINFORCE/HOUSEKEEPING PADS - PENT LVL CBN
CBNPHPH-0310CBN
7 $0.00
SPRAY-ON FIREPROOFING - PENTLVL CBN
CBNPHPH-0725CBN
10 $0.00
SET ELECTRICAL EQUIPMENT - PENTLVL CBN
CBNPHPH-1600CBN
10 $0.00
SET MECH EQUIPMENT - PENTLVL CBN
CBNPHPH-1500CBN
5 $0.00
INSTALL METAL PANEL - PENTLVL CBN
CBNPHPH-0777CBN
10 $0.00
INSTALL LOUVERS - PENTLVL CBN
CBNPHPH-0710CBN
10 $0.00
ERECT EXTERIOR STUDS/SHEATHINGBARRIER - PENTLVL CBN
CBNPHPH-0540CBN
15 $0.00
FORM/REINFORCE/TOPPING SLAB - PENT LVL CBN
CBNPHPH-0320CBN
19 $0.00
FORM/PLACE/STRIPSHEAR WALLS - SERV LVL CBN
CBNSLSL-0352CBN
45 $0.00
ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBN
CBNSSSS-0510CBN
35 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBN STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 254
DRILL/PLACE CAISSONS (balance@ bench) - SERV LVL CBC
CBCSLSL-0320CBC
15 $0.00
ERECT EXTERIOR STUDS - LVL-3 CBC
CBCL3L3-0540CBC
15 $0.00
SET ELECTRICAL EQUIPMENT - PENTLVL CBC
CBCPHPH-1600CBC
10 $0.00
SET MECH EQUIPMENT - PENTLVL CBC
CBCPHPH-1500CBC
5 $0.00
ERECT EXTERIOR STUDS/SHEATHINGBARRIER - PENTLVL CBC
CBCPHPH-0540CBC
15 $0.00
FORM/REINFORCE/HOUSEKEEPING PADS - PENT LVL CBC
CBCPHPH-0310CBC
7 $0.00
FORM/REINFORCE/TOPPING SLAB - PENT LVL CBC
CBCPHPH-0320CBC
19 $0.00
ERECT EXTERIOR STUDS - LVL-2 CBC
CBCL2L2-0540CBC
15 $0.00
ERECT EXTERIOR STUDS - LVL-1 CBC
CBCL1L1-0540CBC
7 $0.00
FORM/PLACE/STRIPSHEAR WALLS (southwest corner) - ALL LVLS CBC
CBCSSSS-510CBC
45 $0.00
ERECT STRUCTURAL STEEL/DECK - ALL LVLS CBC
CBCSSSS-0510CBC
33 $0.00
PERIMETER DRAINS/BACKFILL PIERCAPS/GRADE BEAMS - SERV LVL CBCCBCSLSL-0390
CBC14 $0.00
MASS EXCAVATION/RECO- SERV LVL CBC
CBCSLSL-3100CBC
15 $0.00
FINE GRADE FORM/PLACE/FINISHSLAB ON GRADE - SERV LVL CBC
CBCSLSL-0380CBC
8 $0.00
UNDERSLAB UTILITIES - SERV LVL CBC
CBCSLSL-3200CBC
15 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ GRD BEAMS/WALLS/COL
SERV LVL CBCCBCSLSL-0330CBC
35 $0.00
SET/BACKFILL DUCTBANKS - SER LVL CBC
CBCSLSL-3110CBC
5 $0.00
DRILL/PLACE CAISSONS (with concourse) - SERV LVL CBC
CBCSLSL-3210CBC
5 $0.00
INSTALL GREEN ROOF SYSTEM - LOW ROOF CBC
CBCLRLR-0750CBC
15 $0.00
PARAPET/BLOCKING- LOW ROOF CBC
CBCLRLR-0710CBC
10 $0.00
INSTALL ROOF ACCCESSORIES - LOW ROOF CBC
CBCLRLR-0760CBC
3 $0.00
SPRAY-ON FIREPROOFING - LVL-3 CBC
CBCL3L3-0725CBC
10 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-3 CBC
CBCL3L3-0320CBC
11 $0.00
INSTALL ROOFING SYSTEM- PENT ROOF CBC
CBCHRPR-0755CBC
15 $0.00
PARAPET/BLOCKINGWATER SHIELD- PENT ROOF CBC
CBCHRPR-0750CBC
20 $0.00
INSTALL PV PANELS - PENT ROOF CBC
CBCHRPR-755CBC
20 $0.00
FORM/REINFORCE/RTOPPING SLAB - PENT ROOF CBC
CBCPHPR-0320CBC
11 $0.00
SPRAY-ON FIREPROOFING - PENTLVL CBC
CBCPHPH-0725CBC
10 $0.00
INSTALL METAL PANEL - PENTLVL CBC
CBCPHPH-0777CBC
10 $0.00
INSTALL LOUVERS - PENTLVL CBC
CBCPHPH-0710CBC
10 $0.00
SPRAY-ON FIREPROOFING - LVL-2 CBC
CBCL2L2-0725CBC
10 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-2 CBC
CBCL2L2-0320CBC
11 $0.00
SPRAY-ON FIREPROOFING - LVL-1 CBC
CBCL1L1-0725CBC
10 $0.00
FORM/REINFORCE/TOPPING SLAB - LVL-1 CBC
CBCL1L1-0320CBC
11 $0.00
FORM/PLACE/STRIPSHEAR WALLS - ALL LVLS CBC
CBCSSSS-0352CBC
45 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 255
HANG/TAPE/FINISH/- SERV LVL CORR CBC
CBCSLEL-0990CBC
10 $0.00
FRAMING/INWALL ROUGH - SERV LVL CORR CBC
CBCSLEL-0910CBC
5 $0.00
CLEAN-UP/PRE PUNCH - SERV LVL CORR CBC
CBCSLEL-8880CBC
5 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC INTERIOR SERVICE LEVEL NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 256
ROUGH-IN/CONNECELECTRICAL EQUIP/PULL WIRE FROM CON - PENT ELEC CBCCBCPHEL-1620
CBC75 $0.00
HANG/TAPE/FINISHDRYWALL - PENT ELEC CBC
CBCPHEL-0920CBC
15 $0.00
FRAMING/INWALL ROUGH - PENT ELEC CBC
CBCPHEL-0910CBC
8 $0.00
INTERIOR FINISHES - PENT ELEC CBC
CBCPHEL-1630CBC
30 $0.00
START-UP ELECTRICAL SYSTEMS - PENT MECH CBC
CBCPHME-1641CBC
30 $0.00
START-UP MECH EQUIP - PENT MECH CBC
CBCPHME-1590CBC
20 $0.00
CONNECT/PIPE-UPMECH EQUIP - PENTHOUSE MECHCBC
CBCPHME-1520CBC
25 $0.00
LAY CMU WALLS - PENTHOUSE MECHCBC
CBCPHME-0420CBC
15 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECHCBCCBCPHME-1516
CBC30 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC INTERIOR PENTHOUSE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 257
R-I OVERHEAD MEP/FIRE PRO- LVL-3 AREA A CBC
CBCL3AA-1516CBC
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 AREA B CBC
CBCL3AB-1516CBC
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA A CBC
CBCL3AA-0990CBC
23 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 AREA A CBC
CBCL3AA-8880CBC
8 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 AREA A CBC
CBCL3AA-0920CBC
13 $0.00
FRAMING/INWALL ROUGH - LVL-3 AREA A CBC
CBCL3AA-0910CBC
14 $0.00
INSTALL OWNER FIXED FF&E - LVL-3AREA-A CBC
CBCL3AA-0977VA CBC
15 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 AREA B CBC
CBCL3AB-0990CBC
22 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 AREA B CBC
CBCL3AB-8880CBC
8 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 AREA B CBC
CBCL3AB-0920CBC
12 $0.00
FRAMING/INWALL ROUGH - LVL-3 AREA B CBC
CBCL3AB-0910CBC
14 $0.00
INSTALL OWNER FIXED FF&E - LVL-3AREA-B CBC
CBCL3AB-0977VA CBC
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC INTERIOR LEVEL 3 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 258
R-I OVERHEAD MEP/FIRE PRO - LVL-2 AREA B CBC
CBCL2AB-1516CBC
17 $0.00
R-I OVERHEAD MEP/FIRE PRO- LVL-2 AREA A CBC
CBCL2AA-1516CBC
18 $0.00
INSTALL OWNER FIXED FF&E - LVL-2AREA-B CBC
CBCL2AB-0977VA CBC
15 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 AREA B CBC
CBCL2AB-8880CBC
8 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA B CBC
CBCL2AB-0990CBC
22 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 AREA B CBC
CBCL2AB-0920CBC
12 $0.00
FRAMING/INWALL ROUGH - LVL-2 AREA B CBC
CBCL2AB-0910CBC
14 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 AREA A CBC
CBCL2AA-0990CBC
23 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBC
CBCL2AA-8880CBC
8 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 AREA A CBC
CBCL2AA-0920CBC
13 $0.00
FRAMING/INWALL ROUGH - LVL-2 AREA A CBC
CBCL2AA-0910CBC
14 $0.00
INSTALL OWNER FIXED FF&E - LVL-3AREA-A CBC
CBCL2AA-0977VA CBC
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 259
HANG/TAPE/FINISHDRYWALL - LVL-1 AREA A CBC
CBCL1AA-0920CBC
13 $0.00
FRAMING/INWALL ROUGH - LVL-1 AREA A CBC
CBCL1AA-0910CBC
14 $0.00
R-I OVERHEAD MEP/FIRE PRO- LVL-1 AREA A CBC
CBCL1AA-1516CBC
18 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA B CBC
CBCL1AB-0990CBC
22 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 AREA B CBC
CBCL1AB-0920CBC
12 $0.00
FRAMING/INWALL ROUGH - LVL-1 AREA B CBC
CBCL1AB-0910CBC
14 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 AREA B CBC
CBCL1AB-1516CBC
17 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 AREA A CBC
CBCL1AA-0990CBC
23 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 AREA A CBC
CBCL1AA-8880CBC
8 $0.00
INSTALL OWNER FIXED FF&E - LVL-31AREA-A CBC
CBCL1AA-0977VA CBC
15 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 AREA B CBC
CBCL1AB-8880CBC
8 $0.00
INSTALL OWNER FIXED FF&E - LVL-31AREA-A CBC
CBCL1AB-0977VA CBC
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 260
FINISH STAIR CORE ST2 - ALL LVLS CBC
CBCALAL-0991CBC
20 $0.00
FINISH STAIR CORE ST1 - ALL LVLS CBC
CBCALAL-0990CBC
15 $0.00
INSTALL ELEVATOR SE5 - ALL LVLS CBC
CBCALAL-1400CBC
60 $0.00
ERECT STAIRS ST1- ALL LVLS CBC
CBCALAL-0555CBC
15 $0.00
ERECT STAIRS ST2- ALL LVLS CBC
CBCALAL-0556CBC
15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC INTERIOR ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 261
SHEATHING/VAPORBARRIER - SOUTH ELEV CBC
CBCESSE-0520CBC
10 $0.00
SHEATHING/VAPORBARRIER - WEST ELEV CBC
CBCESWE-0520CBC
5 $0.00
SHEATHING/VAPORBARRIER - EAST ELEV CBC
CBCESEE-0520CBC
5 $0.00
SHEATHING/VAPORBARRIER - NORTH ELEV CBC
CBCESNE-0520CBC
10 $0.00
INSTALL CURTAIN WALL - SOUTH ELEV CBC
CBCESSE-0870CBC
40 $0.00
INSTALL CURTAIN WALL - WEST ELEVCBC
CBCESWE-0870CBC
20 $0.00
INSTALL PRECAST PANELS - WEST ELEV CBC
CBCESWE-0440CBC
4 $0.00
INSTALL METAL PANELS - EAST ELEV CBC
CBCESEE-0440CBC
5 $0.00
INSTALL CURTAIN WALL - NORTH ELEV CBC
CBCESNE-0870CBC
40 $0.00
INSTALL PRECAST PANELS - NORTH ELEV CBC
CBCESNE-0440CBC
8 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 262
FUNCTIONAL TESTING/CORRECT- CBC
CBCCOCO-1596CBC
25 $0.00
PRE-FUNCTIONAL TESTING/CORRECT- CBC
CBCCOCO-1594CBC
20 $0.00
TEST & BALANCE - CBC
CBCCOCO-1620CBC
30 $0.00
CREATE/COMPLETEFINAL PUNCHLIST -CBC
CBCCOCO-9999CBC
35 $0.00
BUILDING FLUSH - CBC
CBCCOCO-1599CBC
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - CBC COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 263
FORM/REINFORCE/- LVL-3 RES
RESL3L3-0320RES
15 $0.00
ERECT PENTHOUSE STEEL/METAL DECK - ROOF RES
RESPHPH-0510RES
20 $0.00
FORM/REINFORCE/(INCL CORE COMP)- PENTHOUSE RES
RESPHPH-0320RES
30 $0.00
SET MECH EQUIPMENT - ROOF RES
RESPHPH-1500RES
2 $0.00
FORM/REINFORCE/P- LVL-1 RES
RESL1L1-0320RES
15 $0.00
PARAPET/BLOCKING- ROOF RES
RESRLRL-0750RES
20 $0.00
FORM/PLACE PIER CAPS/ELEV PITS/ WALLS/COLUMNS -SERV LVL RES
RESSLSL-0330RES
30 $0.00
FORM/PLACE/FINISHSLAB ON GRADE - SERV LVL RES
RESSLSL-0380RES
10 $0.00
DRILL/PLACE CAISSONS - SERV LVL RES
RESSLSL-0320RES
26 $0.00
DRIVE SOLDIER PILES - SERV LVL RES
RESSLSL-3130RES
10 $0.00
SHORING/MASS EXCAVATION/RECO- SERV LVL RES
RESSLSL-3100RES
18 $0.00
UNDERSLAB UTILITIES (DUCTBANKS/VAULT- SERV LVL RES
RESSLSL-3200RES
15 $0.00
FORM/REINFORCE/- LVL-2 RES
RESL2L2-0320RES
15 $0.00
SET ELECTRICAL EQUIPMENT - ROOF RES
RESPHPH-1600RES
7 $0.00
SET/CONNECT PHOTOVOLTAIC PANELS - ROOF RES
RESRLRL-1600RES
40 $0.00
INSTALL ROOF CANOPY STRUCTURE - ROOF RES
RESRLRL-0520RES
15 $0.00
PERM DRAINS/WATERPROFOUNDATION WALLS - SERV LVL RESRESSLSL-0390
RES25 $0.00
ERECT STRUCTURAL STEEL FOR LOW ROOF - LVL-2 RES
RESL2L2-0520RES
6 $0.00
FORM/PLACE RAMP & STAIRS - LOADING DOCK RES
RESLDLD-0320RES
12 $0.00
ERECT INTERSTITIAL STEEL/TOPPING (INCL CURE)- INTERSTITIAL LVRESSLIL-0320
RES15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES STRUCTURE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 264
INTERIOR FINISHES (SURGURY) - SERVLVL RES
RESSLSL-0994RES
30 $0.00
INTERIOR FINISHES (CART WASH) - SERV LVLRES
RESSLSL-0992RES
30 $0.00
LAY CMU WALLS - SERV LVL RES
RESSLSL-0420RES
10 $0.00
CLEAN-UP/PRE PUNCH - SERV LVLRES
RESSLSL-8880RES
15 $0.00
HANG/TAPE/FINISHDRYWALL - SERV LVL RES
RESSLSL-0920RES
30 $0.00
FRAMING/INWALL ROUGH - SERV LVLRES
RESSLSL-0910RES
30 $0.00
ROUGH-IN OVERHEAD PIPING(PROCESS/MED GAS/FIRE PROT) - SERV LVL RESRESSLSL-1516
RES20 $0.00
INTERIOR FINISHES (GENERAL) - SERV LVL RES
RESSLSL-0990RES
45 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES INTERIOR SERVICE LEVEL NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 265
ROUGH-IN/CONNECELECTRICAL EQUIP/PULL WIRE FROM CON - PENTHOUSE ELERESPHEL-1620
RES65 $0.00
HANG/TAPE/FINISHDRYWALL - PENTHOUSE ELEC RES
RESPHEL-0920RES
10 $0.00
FRAMING/INWALL ROUGH - PENTHOUSE ELEC RES
RESPHEL-0910RES
10 $0.00
START-UP ELECTRICAL SYSTEMS - PENT MECH RES
RESPHME-1641RES
20 $0.00
START-UP MECH EQUIP - PENT MECH RES
RESPHME-1590RES
15 $0.00
CONNECT/PIPE-UPMECH EQUIP - PENTHOUSE MECHRES
RESPHME-1520RES
60 $0.00
LAY CMU WALLS - PENTHOUSE MECHRES
RESPHME-0420RES
15 $0.00
ROUGH-IN OVERHEAD MEP (NOT UNITS) - PENTHOUSE MECHRESRESPHME-1516
RES45 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES INTERIOR PENTHOUSE NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 266
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 LAB RES
RESL3LA-0990RES
45 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 LABRES
RESL3LA-8880RES
10 $0.00
INSTALL OWNER FIXED FF&E - LVL-3LAB RES
RESL3LA-0977VA RES
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-3 SUPP RES
RESL3SO-0990RES
45 $0.00
CLEAN-UP/PRE PUNCH - LVL-3 SUPP RES
RESL3SO-8880RES
10 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 SUPP RES
RESL3SO-0920RES
15 $0.00
FRAMING/INWALL ROUGH - LVL-3 SUPP RES
RESL3SO-0910RES
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 SUPP RES
RESL3SO-1516RES
25 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-3 LAB RES
RESL3LA-0920RES
15 $0.00
FRAMING/INWALL ROUGH - LVL-3 LABRES
RESL3LA-0910RES
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-3 LAB RES
RESL3LA-1516RES
35 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES INTERIOR LEVEL 3 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 267
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 LAB RES
RESL2LA-0990RES
45 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 LAB RES
RESL2LA-0920RES
15 $0.00
FRAMING/INWALL ROUGH - LVL-2 LABRES
RESL2LA-0910RES
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-2 LAB RES
RESL2LA-1516RES
25 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 LABRES
RESL2LA-8880RES
10 $0.00
INSTALL OWNER FIXED FF&E - LVL-2LAB RES
RESL2LA-0977VA RES
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-2 SUPP RES
RESL2SO-1516RES
25 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-2 SUPP RES
RESL2SO-0990RES
45 $0.00
CLEAN-UP/PRE PUNCH - LVL-2 SUPP RES
RESL2SO-8880RES
10 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-2 SUPP RES
RESL2SO-0920RES
15 $0.00
FRAMING/INWALL ROUGH - LVL-2 SUPP RES
RESL2SO-0910RES
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES INTERIOR LEVEL 2 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 268
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 LAB RES
RESL1LA-0990RES
45 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 LAB RES
RESL1LA-0920RES
15 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 LABRES
RESL1LA-8880RES
10 $0.00
FRAMING/INWALL ROUGH - LVL-1 LABRES
RESL1LA-0910RES
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 LAB RES
RESL1LA-1516RES
25 $0.00
INSTALL OWNER FIXED FF&E - LVL-1LAB RES
RESL1LA-0977VA RES
20 $0.00
INSTALL INTERIOR FINISHES & SPECIALTIES - LVL-1 SUPP RES
RESL1SO-0990RES
45 $0.00
CLEAN-UP/PRE PUNCH - LVL-1 SUPP RES
RESL1SO-8880RES
10 $0.00
HANG/TAPE/FINISHDRYWALL - LVL-1 SUPP RES
RESL1SO-0920RES
15 $0.00
FRAMING/INWALL ROUGH - LVL-1 SUPP RES
RESL1SO-0910RES
20 $0.00
R-I OVERHEAD MEP/FIRE PRO - LVL-1 SUPP RES
RESL1SO-1516RES
25 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES INTERIOR LEVEL 1 NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 269
TRIM-OUT MEP/FIRE PROTECTION - INTER LVL RES
RESSLIL-1517RES
25 $0.00
ROUGH-IN MEP/FIRE PROTECTION - INTER LVL RES
RESSLIL-1516RES
110 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES INTERIOR INTERSTITIAL LEVEL NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 270
FINISH STAIR CORE ST2 - ALL LVLS RES
RESALAL-0991RES
20 $0.00
FINISH STAIR CORE ST1 - ALL LVLS RES
RESALAL-0990RES
15 $0.00
ERECT STAIRS ST2- ALL LVLS RES
RESALAL-0556RES
15 $0.00
ERECT STAIRS ST1- ALL LVLS RES
RESALAL-0555RES
15 $0.00
INSTALL ELEVATOR SE12- ALL LVLS RES
RESALAL-1401RES
60 $0.00
INSTALL ELEVATOR SE13 - ALL LVLS RES
RESALAL-1400RES
60 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES INTERIOR ALL LEVELS NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 271
ERECT EXTERIOR STUDS/SHEATHINGBARRIER (LEVEL 1-LEVEL 3) - NORTH ELEV RESRESESNE-0520
RES15 $0.00
INSTALL METAL PANEL - NORTH ELEV RES
RESESNE-0780RES
10 $0.00
INSTALL CURTAIN WALL- NORTH ELEV RES
RESESNE-0870RES
15 $0.00
EXTERIOR SKIN TIE INTO CONCOURSE - WEST ELEV RES
RESESWE-0530RES
15 $0.00
INSTALL METAL PANEL - WEST ELEV RES
RESESWE-0780RES
5 $0.00
INSTALL CURTAIN WALL - WEST ELEVRES
RESESWE-0870RES
15 $0.00
ERECT EXTERIOR STUDS/SHEATHINGBARRIER (LEVEL 1-LEVEL 3) - WEST ELEV RESRESESWE-0520
RES15 $0.00
INSTALL METAL PANELS - PENTHOUSE ELEV RES
RESESPH-0777RES
7 $0.00
INSTALL LOUVERS - PENTHOUSE ELEV RES
RESESPH-0710RES
5 $0.00
ERECT EXTERIOR STUDS/SHEATHINGBARRIER - PENTHOUSE ELEV RESRESESPH-0520
RES15 $0.00
INSTALL CURTAIN WALL - SOUTH ELEV RES
RESESSE-0870RES
20 $0.00
INSTALL SOLAR TUBES - SOUTH ELEV RES
RESESSE-1600RES
50 $0.00
INSTALL STRUCTURAL STEEL FRAME FORSOLAR TUBES - SOUTH ELEV RESRESESSE-1610
RES15 $0.00
INSTALL SOLAR TUBES - EAST ELEV RES
RESESEE-1600RES
30 $0.00
INSTALL METAL PANEL - EAST ELEV RES
RESESEE-0780RES
5 $0.00
INSTALL CURTAIN WALL - EAST ELEV RES
RESESEE-0870RES
10 $0.00
ERECT EXTERIOR STUDS/SHEATHINGBARRIER (LEVEL 1-LEVEL 3) - EAST ELEV RESRESESEE-0520
RES15 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES EXTERIOR SKIN NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 272
CREATE/COMPLETEFINAL PUNCHLIST -RES
RESCOCL-9999RES
20 $0.00
BUILDING FLUSH - RES
RESCOCL-1599RES
15 $0.00
FUNCTIONAL TESTING/CORRECT- RES
RESCOCO-1596RES
20 $0.00
PRE-FUNCTIONAL TESTING/CORRECT- RES
RESCOCO-1594RES
15 $0.00
TEST & BALANCE - RES
RESCOCL-1592RES
20 $0.00
DENVER VA MEDICAL CENTER - FTP SCHEDULE
Schedule File: DVFTP-04 8.12.11 Run Date: 12-Aug-11 Project Start: 01-Nov-10 Data Date: 26-Jul-11
Page 1 of 1
LT07 - RES COMMISSIONING NETWORK DIAGRAM
Activity Name
Activity ID2222 - R... 2222-BUI...
OriginalDuration
BudgetedTotal Cost
Page 273
REPLACEMENT MEDICAL FACILITY, VAMC – DENVER, CO KIEWIT-TURNER - A JOINT VENTURE ASSUMPTIONS & NOTES FOR FTP SCHEDULE – SCHEDULE FILE DVFTP-03
Page 1 of 7
August 12, 2011
FULL CAMPUS FTP SCHEDULE NARRATIVE
Milestones
Campus Notice to Proceed: September 6, 2011
Campus Construction Start (mass excavation): January 11, 2012
Campus Substantial Completion less the Research Building: March 28, 2015 o Kiewit-Turner has identified a substantial completion activity in the FTP schedule. Kiewit-Turner
defines substantial completion for any given building as the point in time when the functional performance testing is complete and the Owner can utilize the space for its intended purpose while Kiewit-Turner completes punchlist items and exterior landscape/hardscape activities.
o The Campus Substantial Completion date occurs when the integrated systems test is complete o The Campus Substantial Completion date does not include the Research Building that is pushed
by the temporary CBS parking.
Campus Final Completion : October 3, 2015
Critical Path through Substantial Completion less the Research Building
There are two critical paths driving the Substantial Completion date, one through the DAT and the other through the PVS and CBC. The critical path through the DAT starts with NTP for Construction which is September 6, 2011. This will release the preconstruction for the shoring and the Redirection of the Children’s Hospital storm sewer. These drive the mass excavation and shoring for the DAT. The DAT structure is critical through the penthouse structural deck placements and interstitial steel. After the service level of interstitial slab on deck is placed, the critical path turns to MEP/Fire Protection rough-in on the interstitial levels. Concurrently with the work on the interstitial levels, partition framing and rough-in occurs below. The critical path moves to interior finishes on Level 1 and sequences up the building through Level 3. Commissioning of the DAT drives the completion of the integrated systems test for the full campus. Once the integrated systems test for the full campus is complete, the campus is substantially complete, less the Research building. The critical path through the PVS starts with the NTP, September 6, 2011. This will release the Wheeling waterline relocation work which is driven by the VA license agreements being completed by November 23, 2011. The Wheeling water relocation drives the PVS shoring and excavation work. The critical path then goes through the PVS caissons, PVS deck placements through parking level 0 and then jumps to the CBC caissons. The critical path then goes through the CBC structure to the exterior skin and through the interior finishes. Commissioning of the CBC drives the completion of the integrated systems test for the full campus. Once the integrated systems test for the full campus is complete, the campus is substantially complete, less the Research building.
Page 274
Page 2 of 7
Critical Path through Campus Final Completion
The critical path through Campus Final Completion starts with NTP for Construction which is September 6, 2011. The critical path runs through the PVS until the PVS is substantially complete. Once the PVS is substantially complete, CBS temporary parking that’s located at the RES building site can be relocated to the PVS. This allows RES construction to begin. The critical path at RES runs through shoring, excavation, caissons, concrete decks, building enclosure/dryin and through finishes. Once the building punch list is complete, the critical path runs through the RES building flush which drives full Campus Final Completion.
Schedule Assumptions
General 1. The FTP schedule is based upon KT receiving a NTP by September 6, 2011. This includes VA consent to
subcontract for all work included in STR-1, STR-1A as well as the design/assist subcontracts, i.e. mechanical, electrical, low voltage and curtain wall.
2. The FTP schedule is based upon VA providing Consent to Subcontract per VA Milestones identified in the schedule. The schedule provides 5 working days for VA review/approval and provision for consent to subcontract.
3. The FTP schedule is based upon VA executing all license agreements with FRA/COA/UCD/CDOT by November 23, 2011. The FTP schedule assumes that the license agreements are not required to be executed in order to perform on-site utility demolition or off-site potholing. The FTP schedule assumes that the license agreements and design approvals must be complete in order for COA/FRA/UCD/CDOT to approve OSI permits and traffic plans.
4. The FTP schedule is based upon the list of Contract Documents provided with the FTP pricing proposal (specify exhibit)
5. The FTP schedule is based upon the 95% Construction Documents for the STR-1, STR-1A and CBS design packages and that submittals will be approved based upon the 95% design packages.
6. The FTP schedule is based upon KT receiving 100% Construction Documents for STR-2 by September 5, 2011, 100% Construction Documents for CS-1/IFO-3 by October 24, 2011 and 100% Construction Documents for IFO-1 by January 30, 2012.
7. The FTP schedule assumes typical VA submittal review times of 20 workdays except for durations noted on the CPM-1 drawing.
8. The CS-1/IFO-3 design package will include a major MEP equipment procurement package. It will include at a minimum: chillers, boilers, cooling towers, AHUs, switchgear, substations, generators, ATS’s and ATO’s.
9. The STR-1A/IFO-2 design package will include, at a minimum, the building ductbank and underslab plumbing design.
10. The FTP schedule assumes that the Credit Union will be vacated by February 11, 2012. 11. The FTP schedule includes the accepted VE identified in the FTP pricing proposal (specify exhibit). It also
assumes that all previously accepted VE design will be included in the respective 100% design packages (i.e. STR-2, CS-1/IFO-3, IFO-1).
12. The FTP schedule is based on VA - provided medical equipment shop drawings being provided per the milestones in the schedule (See Medical Equipment Procurement Log on page 7)
13. The FTP schedule assumes no restrictions to site access or work day/hours by the VA or other authorities having jurisdiction. The schedule assumes industry standards and City of Aurora guidelines for noise and does not recognize the sound restrictions included in section 01 57 19 of the Specifications. It’s also assumed that KT will close E 17
th Place during the constriction, through substantial completion.
14. The FTP schedule assumes that 120 temporary parking spaces will be provided to accommodate the CBS occupants and patients at the Research Building footprint only. Once the PVS parking garage is substantially complete, the parking will be moved to the PVS.
15. The FTP schedule is based upon KT receiving 100% Construction Documents for CLC by April 30, 2012 and receiving VA consent to subcontract by July 24, 2012.
Page 275
Page 3 of 7
16. The FTP schedule assumes that KT and the VA will temporarily occupy the 2nd
floor of the CBS building until March 24, 2015.
17. The FTP schedule assumes that there will be no schedule impact due to the treatment of ground water. 18. Kiewit-Turner excludes the Construction Schedule Risk Analysis/ Mitigation Plan identified in Section 01
32 16.13 of the Specifications and associated costs from this proposal. 19. The FTP schedule assumes an overall construction schedule of 16 months for the CLC Building. 20. The FTP schedule includes the Preconstruction activities for the CBS and RFP-3 work. The FTP schedule
excludes impacts from the relocation of the CBS fire water service and the 100% CBS construction documents.
Schedule Allowances 1. Ground Water Treatment at PVS - 306 calendar days (duration accounts for engineering through start-
up of dewatering system) 2. CBS Temporary Parking - 174 calendar days (duration includes provisions for design, approvals,
procurement and construction) Sitework
1. Based upon discussions with the VA and Fitzsimons Campus authorities, the proposed Wheeling Street OSI work will be completed in four phases: Wheeling water main relocation at PVS, work north of E 17
th
Place, work at the E 17th
Place intersection and work south of E 17th
Place. 2. The FTP schedule assumes that the existing CBS roof drains will temporarily discharge into the temporary
Redirection of the TCH Dental Clinic storm water. The temporary storm water solution is assumed to be complete by January 4, 2011. The temporary solution is assumed to match the existing 18” RCP pipe size.
3. The FTP schedule assumes that KT will gain approval for SOE tie-backs to be installed in FRA/COA/UCD/CDOT properties by November 23, 2011. Tie backs will be abandoned in place.
4. The FTP schedule assumes that Primary XCEL electrical service to the ENC Building will be provided by August 29, 2013.
5. The FTP schedule is based upon utility removals/relocations that are specifically indicated on the drawings.
6. If encountered, subsurface contaminated or hazardous material will be treated as a differing site condition. The FTP schedule allows no time for investigation or remediation/abatement of such conditions.
7. The FTP schedule assumes that ground water will be encountered only at the PVS and at drilled pier locations.
8. The FTP schedule assumes that tower crane foundations will be left in place once the cranes are removed. 9. The FTP schedule assumes that landscape/hardscape work will continue beyond substantial completion to
final completion. 10. Materials stored on site will be billed through cost loaded procurement activities that will be placed into
the approved Construction schedule
Structure 1. Spray on fireproofing at interstitial decks will not be required. 2. The FTP schedule is based upon shotcrete being accepted as a method of constructing the PVS perimeter
foundation walls.
Exterior Skin
1. Building enclosures (curtain wall/metal panels) are unitized to facilitate installation. 2. MRI equipment will be delivered by June 2014 so as not to delay the work.
Page 276
Page 4 of 7
Commissioning
1. The campus systems will be designed so that buildings can be commissioned individually. 2. Integrated systems testing will occur prior to Campus Substantial Completion and will not include the
Research or CLC buildings. The Research and CLC buildings will be commissioned separately at completion. The Campus MEP and Low Voltage systems will be rebalanced following Campus Final Completion.
Calendars
The following calendars are used in the FTP schedule:
1. 5D (5 day no weather)
2. 7D (7 day no weather/holidays)
3. 5DS (5 day no winter work) – No work from mid November through mid April
4. 5DW (5 day weather sensitive)
5. 6D (6 day no weather) – Only assigned to CBS structure, CBS demo, and CBS remodel activities.
Holidays
The following days are counted as non-work days in calendars 1, 3, 4, and 5 above. Holidays that take place on
weekends will be accounted for on either the Friday before or the Monday after the holiday.
January 1st - New Years Day
Third Monday of January – Martin Luther King Day
Third Monday in February – President’s Day
Last Monday of May - Memorial Day
July 4th - Independence Day
First Monday of September - Labor Day
Second Monday in October – Columbus Day
November 11th
– Veteran’s Day
Last Thursday of November - Thanksgiving
December 25th - Christmas Day
Page 277
Page 5 of 7
Weather Contingency
The schedule assumes adverse weather impacts to construction based upon the 10-year NOAA average for
precipitation greater than .1 inches that occur within a work day. This is in compliance with the FAR clause that
lists protocol for weather delay claims. The weather calendar detailing the 35 day annual weather impact is
summarized below:
Month J F M A M J J A S O N D
Adverse Weather Days 1 1 3 5 4 4 4 4 3 2 2 2
Weather days in excess of these numbers are deemed unusually severe weather days and, as such, are subject to
an excusable time extension.
The post-event impact of adverse weather on construction will be calculated and included in the delay.
Construction Schedule Development
In an effort to minimize schedule re-work, the Kiewit-Turner team will utilize a rolling baseline schedule creation
process. In lieu of submitting a detailed baseline schedule 60 calendar days after the project NTP for construction,
which is prior to the 100% CD design packages being issued, the rolling baseline schedule will allow the team to
create the schedule as the completed design packages are issued.
To ensure all accurate detail is incorporated into the schedule, the detailed baseline schedule will be complete 60
calendar days after the given 100% CD design package has been issued. This schedule will be detailed and
cost/resource loaded for 90-days only. The VA will review and comment on this schedule prior to full
cost/resource loading. The schedule will be fully cost and resource loaded 60 calendar days after VA provides
consent to subcontract for each bid tab set and after comments have been provided for each 90-day/detailed
schedule submission.
Equipment loading is not a requirement in the scheduling specification provided. The FTP schedule assumes that
GC/GR costs will be managed separately from the detailed construction activities. Please see the timeline below:
Page 278
Page 6 of 7
DESIGN PACKAGE
DATE RECEIVED
DETAILED BASELINE SCHEDULE
COMPLETION DATE (minus cost and
resource loading)
VA CONSENT TO SUBCONTRACT
COST & RESOURCE
LOADED SCHEDULE
COMPLETION DATE
KT SUBMITTAL DATE
STR-2 9/5/2011 11/5/2011 10/25/2011 1/4/2012
CS-1/IFO-3 10/24/2011 12/26/2011 1/4/2012 3/4/2012
IFO-1 1/30/2012 3/31/2012
GROUP 1 4/4/2012 6/3/2012
GROUP 2 5/2/2012 7/1/2012
GROUP 3 5/31/2012 7/30/2012
Schedule Management
Future applications for progress payments will meet the requirements per Network Analysis Schedules except
General Requirements, General Conditions, Bond, Insurance, Fee and G&A costs. These costs will be loaded
against five activities labeled “General Requirements”, “General Conditions”, “Bond”,” Insurance”, “Fee and G&A”
that overlap all the CLINs on the project. These five activities will have durations that span the entire project
duration and percent complete will be progressed in coordination with the entire project percent complete.
Page 279