Guidelines for Implementing Contractor Development Programmes

Embed Size (px)

Citation preview

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    1/36

    National Contractor Development Programme

    GUIDELINES FOR IMPLEMENTING

    CONTRACTOR DEVELOPMENT PROGRAMMES

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    2/36II

    SEPTEMBER 2011

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    3/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    1

    CONTENTS

    1. BACKGROUND 3

    2. PURPOSE OF THIS DOCUMENT  5

    3. WHAT IS A SUCCESSFUL CONTRACTOR DEVELOPMENT PROGRAMME?  7

    4. IMPLEMENTING CONTRACTOR DEVELOPMENT 9

    4.1. Establishing the needs, programme goals & strategy for contractor development  104.2. Getting started 11

    4.2.1. Developing a programme business case  11

    4.2.2. Establish a contractor development steering committee 11

    4.2.3. Identify required role players and establish stakeholder forum  11

    4.3. Staff resource planning 11

    4.4. Targeting 12

    4.4.1. Target groups  12

    4.4.2. Identication of projects 12

    4.5. Identifying support initiatives 12

    4.6. Contractor assessment 13

    4.6.1. Criteria for access 13

    4.6.2. Competence 13

    4.6.3. Financial upgrading factor  13

    4.6.4. Contractor rating 14

      4.6.4.1 Grade 2-8 contractors  14

      4.6.4.2 Contractor prioritisation 15

    4.6.5. Awarding points for socio-economic goals  15

    4.6.6. Selecting contractors for development 15

    5. MANAGING CONTRACTOR DEVELOPMENT 17

    5.1 Training strategy 17

    5.2 Training attendance: sharing the cost of contractor development 17

    5.3 Dispute resolution 18

    6 EVALUATION AND EXITING OF CONTRACTORS 20

    7 MONITORING AND EVALUATION 22

     Annexures: 

     Annexure: Standard Operating Procedures Legends 24

    Procedure for Implementing Contractor Development Programme 25

    Targeting Procedure 26

    Contractor Assessment Procedure 27 

    Cost Sharing Principles for Contractor Development 28

    Dispute Resolution Procedure for Contractor Development 29Procedure for Evaluation and Exiting of Contractor’s 30

    Monitoring and Evaluation Procedure 31 

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    4/362

    01

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    5/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    3

    BACKGROUND

    The National Contractor Development Programme (NCDP) is a public sector led programme comprising of a partnership

    between the cidb, National and Provincial Public Works and other willing stakeholders and partners.

    The objective of the NCDP is to increase the capacity, equity ownership, sustainability, quality and performance of ci db

    registered contractors – effectively raising the contribution of the construction industry to South Africa’s accelerated and

    shared growth initiative.

    To achieve this objective, participants within the NCDP should commit to all or some of the following developmental

    outcomes:

    • Improve the grading status of contractors in targeted categories and grades;

    • Increase the number of black women, disabled, and youth-owned companies in targeted categories;

    • Create sustainable contracting enterprises by enabling continuous work through a competitive process;

    • Improve the performance of contractors in terms of quality, employment practices, skills development, safety, health

    and the environment; and

    • Improve the business management and technical skills of these contractors.

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    6/364

    02

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    7/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    5

    PURPOSE OF THIS DOCUMENT

    The purpose of this document is to assist committed clients to design and implement appropriate Contractor Development

    Programmes (CDPs) through direct targeting of contractors1

     . The guidelines address the following aspects:

    • Guidance for designing or implementing CDPs. These include:

    o Targeting of budgets, projects and contractors;

    o Evaluation of contractors when entering a programme;

    o Training and mentoring;

    o Sharing the cost of contractor development;

    o Risk and cost sharing in contracts;

    o Payment dispute resolution;

    o Exiting from the programme; and

    o Monitoring and evaluating the programme.

    These guidelines are generally for government clients that intend establishing a CDP using direct procurement as a means

    of engaging contractors. It is applicable to Grade 2 to 9 contractors with a track record and excludes newly established

    contracting enterprises, but certain principles can be applied to other grades where clients deem it appropriate.

    The guidelines only apply in detail to contractors in the General Building or Civil Engineering Classes of Works, but the

    principles can be applied to other Classes of Works.

    1 For a discussion of “direct” and “indirect” targeting mechanisms, see “Targeting for Contractor Development

    Programmes; Background”, Construction Industry Development Board (2010), available on the ci d  b website

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    8/366

    03

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    9/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    7

    WHAT IS A SUCCESSFUL CONTRACTOR DEVELOPMENT PROGRAMME?

     A CDP should be a well-planned operation that aims to exit and graduate contractors from the programme with measurable

    improvements (e.g. NQF level or improvement in contractor grading) and involves commitment of nancial and humanresources by both the client and the contractor. Clients that commit to contractor development must use an appropriate

    portion of their procurement of infrastructure budget to support the objectives of the NCDP.

    The table below summarises the key requirements for a successful CDP.

    Item Requirements  Tick If Completed

     √ or ×

    Programme

    Strategy

     A well designed and funded programme strategy aligned with the needs of the

    client

    Projects specically selected for their characteristics that support the contractordevelopment requirements and ensure sustainable development opportunities

    Committed clients that use an appropriate portion of their procurement of

    infrastructure budget to support the objectives of the NCDP

    Contractor /

    Participants

    Contractor selection must be based on predetermined criteria, aligned to

    envisaged development outcomes

    Selection must be transparent based on the criteria for selection as identied

    above

    Contractors must be assessed against predetermined criteria

    Measure improvement against predetermined criteria on a regular basis and at

    exit

    Client

    Capacity

    Sufcient capacity for the management of the CDP

     Appropriate monitoring, evaluation and quality control measures

    Management of stakeholder expectations

     An in-depth understanding of relevant procurement methods

     Appropriate training programmes that lead to relevant NQF qualications

    Business mentorship by experienced mentors

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    10/368

    04

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    11/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    9

    IMPLEMENTING CONTRACTOR DEVELOPMENT

    The purpose of this section is to guide clients through the key elements of implementing a contractor development

    programme. The key steps a client must follow to implement a CDP are listed in the table below and discussed insubsequent sections.

    Item Description  Tick If Completed

     √ or ×

    Needs,

    Programme

    Goals &

    Strategy

     Assess and determine the need for contractor development

    Set measurable long-term programme goals and objectives for each of the years

    (duration) of the programme

    Determine contractor development outcomes for the programme

     Assign a programme implementation timeline

    Getting

    Started

    Establish a Contractor Development Steering Committee

    Identify required role players to support the implementation of contractor

    development , e.g. nancial institutions, mentors, training institutions, etc.

    Conduct role player consultation sessions

    Prepare a programme business case providing:

    • Programme goals and description

    • Scope of programme and interventions

    • Contractor, organisational and institutional arrangements

    • Resources and budget to support the programme and attain desired

    results

    • Programme implementation timescale

    • Measurable outcomes

    • Programme operations monitoring and evaluation mechanisms

    Resource

    Planning

    Select appropriate organogram for contractor development

    Determine manager, supervisors, and other staff roles and expected tasks in the

    programme

    Determine mentor roles and expected tasks in the programme

    Dene resources and budget needed to support the programme

    Targeting Collect portfolio of projects to be used in the targeting process

    Select projects and determine (quantify) targets for each year where possible

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    12/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    10

    Identify

    Projects

    Determine complexity of projects

    Map locality of projects and determine contractor development opportunities

    Identify

    Support

    Initiatives

    Determine mentoring approach

    Develop training strategy and programme

    Contractor

     Assessment

    Determine criteria for inclusion in the programme

    Invite contractors to register for contractor development

     Apply assessment model

    The diagram below depicts the overall process for implementing contractor development.

    4.1. Establishing the needs, programme goals & strategy for contractor development

     As in any supplier development programme, clients must consider their own needs when designing a targeting strategy

    for a CDP. For example, if the typical delivery problems experienced by the client are construction quality related, the client

    may decide to only target contractors to ensure quality improvement. If there are not enough women-owned contractors in

    a specic grade, the client may target women-owned contractors in a specic grade.

    4. Training &Mentorship

    3. WorkOpportunities

    ContractorDevelopmentProgramme

    To develop keycontracting

    competencies

    5. Evaluationand Exiting of

    Contractors

    6. Monitoring &Evaluation of the

    Programme

    1. Programmestrategy &

    Targeting

    2. Contractor

     Assessment

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    13/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    11

    4.2. Getting started

     As a sector, CDPs development initiative normally require signicant support from the political stakeholders in the process.

    It is important that the key role players in a CDP are involved from the start of the process.

    4.2.1. Developing a programme business case

    The Programme Manager: Contractor Development must develop a programme business case that

    addresses the following aspects:

    • Programme goals and description;

    • Scope of programme and interventions;

    • Contractor, organisational and institutional arrangements;

    • Resources and budget to support the programme and attain desired results;

    • Programme implementation timescale;

    • Measurable outcomes; and

    • Programme operations monitoring and evaluation mechanisms.

    4.2.2. Establish a contractor development steering committee

     A steering committee is an important part of the success of any CDP as this will ensure buy-in and improved

    communication. The purpose of the steering committee is to direct initiatives that do not fall directly under

    the management of the Programme Manager: Contractor Development. Examples of this would include

    supply chain management arrangements and payments and contract conditions. The steering committee

    must approve the business case for contractor development.

    4.2.3. Identify required role players and establish stakeholder forum

     Appropriate consultation with key role players will ensure that there is a common understanding of the CDP

    and it will signicantly increase the chances of success. Although specic key role players must be identied

    by the client, the following participants are recommended:

    • The contractor development steering committee members;

    • The local Construction Contact Centre (CCC) manager;

    • Other clients that may want to participate in CDPs;

    • Construction sector representative; and

    • Training authorities and training institutions

    4.3. Staff resource planning

     As contractor development is an initiative of the client, the client must ensure appropriate resourcing of the contractor

    development initiative. The structure should incorporate a unit which is focused on contractor development, with the

    following functions:

    • Planning contractor development interventions;

    • Coordinating contractor training during the programme;

    • Coordinating mentoring activities;

    • Procurement specialisation specically focusing on sourcing strategies that will promote contractor development;

    • Stakeholder management and communication of contractor development activities, including coordination with

    nancial institutions; and

    • Monitoring and evaluation.

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    14/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    12

    4.4. Targeting

    Targeting of specic contractors forms an integral part of the design of a CDP. An ill-conceived CDP will not support the

    objectives of either the client or the contractors. It is important that the interrelationship between the targeted groups, the

    needs of the contractors, the supply-side support initiatives and the projects identied for contractor development are

    aligned. Targeting should be read in conjunction with the Targeting for Contractor Development Programmes: Guidelines

    available on the cidb website.

    4.4.1. Target groups

    CDPs should apply the following guidelines in identifying target groups:

    i) Ownership: CDPs should target the development of black, women, disabled, and youth-owned

    companies. Specically, CDPs should target the development of companies in those Classes of

    Works (CoWs) and Grades where imbalances in such ownership exist.

    ii) Supply and Demand: CDPs should target the development of new contracting capacity only where

    demonstrable shortages exist that are aligned with the service delivery objectives of the client.

    iii) Performance Improvement (or competence development): CDPs should target to improving the

    performance of contractors – in particular in those areas which are aligned with the service delivery

    objectives of the client.

    iv) Local Economic Objectives: Where feasible, targeting of contractors should reect local economic

    objectives.

    4.4.2. Identication of projects

    Clients should identify the projects for contractor development based on the cidb grade of contractors

    targeted. Project identication should consider project complexity and locality, and must be matched with

    the capability of the contractor.

    4.5. Identifying support initiatives

    The most critical element in any CDP is the support initiatives provided or arranged by clients which includes mentoring,

    technical skills development, business and nancial management training, access to nance or a combination of the above.

    • Training: This initiative requires the client to organise training with an accredited institution. The training should be

    aligned with the Requirements and Guidelines for ci d  b Contractor Competence Accreditation which is available

    from the cidb, which are deemed to be minimum standards necessary for running a contracting enterprise and for

    supervising building and construction works within the elds off:

    o Business management;

    o Building and construction works management (operational and supervision); ando Legislative issues.

    • Mentoring:  A contractor’s mentorship needs are to be identied and an appropriate mentorship intervention

    should be developed. Mentorship should revolve primarily around the contractor’s business management skills and

    knowledge, such as tendering and marketing. Mentors must be registered as mentors with the Council of Project

    and Construction Management Professionals.

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    15/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    13

    4.6. Contractor Assessment

    The purpose of the assessment is to select contractors that meet the entry level requirements in line with the focus of the

    CDP and to determine their developmental needs. All contractors applying for development must be registered in the cidb

    Register of Contractors.

    4.6.1. Criteria for access

    Clients should apply the following criteria to determine which contractors get access to contractor development

    programmes:

    • Competence

    • Financial upgrading; and

    • Socio-economic goals

    4.6.2. Competence

    The contractor must be assessed to determine their level of competence, as outlined in the Requirements

    and Guidelines for cidb Contractor Competence Accreditation. The competence assessment can be done

    in terms of formal qualications and experience requirements, or in terms of the requirements for an external

    competence assessment undertaken by a cidb recognised external Competence Assessment Panel.

    Once the contractors’ competence has been determined, contractors should be rated as indicated in the

    table below for assessing their suitability for enrolment into the CDP. The competence assessment will then

    also be used for evaluating the mentoring and training requirements of contractors that are enrolled within

    a CDP.

    Description Rating

    Contractor possessing the required qualications and minimum experience 2

    Contractor possessing the minimum experience but without the required qualication. 1

    Contractor possessing the required qualication but without the minimum experience 0

    Contractor without the required qualication and experience -1

    4.6.3. Financial upgrading factor

    The contractor must be assessed to determine a nancial upgrading factor and to measure how close the

    contractor is to upgrading to the next grade designation.

    The nancial upgrading factor is determined in line with the requirements of the cidb Register of Contractors

    based on best annual turnover, largest contract and available capital as indicated in the table below (based

    on the current cidb requirements).

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    16/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    14

    Grade

    Upper limit of

    tender value

    range

    Best annual turnover Largest contract Available capital

    Turnover Rating Value Rating Amount Rating

    2 R 650 000 R 1 000 000 2 R 500 000 2 R 100 000 2

      R 750 000 1 R 383 333 1 R 75 000 1

      R 500 000 0 R 266 666 0 R 50 000 0

      R 250 000 -1 R 150 000 -1 R 25 000 -1

    3 R 2 000 000 R 2 000 000 2 R 1 000 000 2 R 200 000 2

      R 1 666 666 1 R 833 333 1 R 166 666 1

      R 1 333 333 0 R 666 666 0 R 133 333 0

      R 1 000 000 -1 R 500 000 -1 R 100 000 -1

    4 R 4 000 000 R 3 250 000 2 R 1 600 000 2 R 650 000 2

      R 2 833 333 1 R 1 400 000 1 R 500 000 1

      R 2 416 666 0 R 1 200 000 0 R 350 000 0

      R 2 000 000 -1 R 1 000 000 -1 R 200 000 -1

    5 R 6 500 000 R 7 800 000 2 R 3 250 000 2 R 1 300 000 2

      R 6 283 333 1 R 2 700 000 1 R 1 083 333 1

      R 4 766 666 0 R 2 150 000 0 R 866 666 0

      R 3 250 000 -1 R 1 600 000 -1 R 650 000 -1

    6 R 13 000 000 R 24 000 000 2 R 10 000 000 2 R 4 000 000 2

      R 18 600 000 1 R 7 750 000 1 R 3 100 000 1

      R 13 200 000 0 R 5 500 000 0 R 2 200 000 0

      R 7 800 000 -1 R 3 250 000 -1 R 1 300 000 -1

    Once the rate for each area has been determined, the client should allocate an overall nancial upgrading factor rating using

    the following formula:

     

    4.6.4. Contractor Rating

    Contractor rating should be based on the following principles for:

    • Grade 2- 6 contractors

    4.6.4.1 Grade 2-6 Contractors

    The nancial upgrading factor rating can be cross referenced against the contractors’ competence

    rating to identify the contractors which are close to upgrading to the next grade designation but

    require assistance on competency, for Grade 2 – 6 contractors. A score of 20, 40, 60 or 80 out of

    a maximum of 80 is then given to contractors that fall within the highlighted areas as shown in the

    following table.

    Best annual turnover + largest contract + available capital

    3  = Overall nancial upgrading factor rating

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    17/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    15

    Determining Contractor Rating for Grade 2 - 6 Contractors

    Grade 2 – 6 Competence Rating

    Financial

    Upgrading Rating

    -1

    No qualications or

    Experience

    0

    Qualications & No

    Experience

    1

    Experience & No

     Qualication

    2

    Experience

    & Qualications

    2 Very close 0 0 0 0

    1 Close 0 80 60 0

    0 Far 0 40 20 0

    -1 Very far 0 0 0 0

    4.6.4.2 Contractor Prioritisation

    The focus of the CDPs should be on contractors functioning within the highlighted area for further

    assessment on socio-economic goals. However the client may select contractors functioning

    outside the recommended area at their own discretion.

    4.6.5. Awarding points for socio-economic goals

    The selection process for the contractors should give preference to enterprises with Historically

    Disadvantaged Individual equity ownership which have Women, Disabled and Youth ownership. Therefore

    contractors must be scored out of a maximum of 20 points for socio-economic goals in line with the

    Preferencing policy of the department. The table above depicts an example of how the socio-economic

    goals can be determined and scored.

    Example of how socio-economic goals can be determined

    Goal Points

    HDI equity ownership 4

    Women 6

    Disability 4

    Youth 6

    Total 20

    4.6.6. Selecting contractors for development

    The contractor rating (out of 80) should be added to the points awarded for socio-economic objectives

    (out of 20) to determine the overall score awarded to the contractor. Contractors should then be ranked

    from highest score to lowest score and the cut-off point is determined by the budget available. In order for

    a contractor to be selected for contractor development, a minimum score of 20 should be obtained for the

    overall score awarded.

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    18/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    1616

    05

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    19/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    17

    MANAGING CONTRACTOR DEVELOPMENT

    During the operational phase of a contractor development programme, a number of key processes need to be implemented.

    The following list contains most of the critical functions relating to contractor development which will be further discussed

    below:

    • Implement training and mentorship;

    • Sharing the cost of contractor development; and

    • Facilitating dispute resolution.

    5.1 Training strategy 

     A training strategy determines the overall training programme and logistics to conduct training. It should address the

    training approach, objectives and outcomes, based on the contractors training requirements (section 4.5.2), and also the

    process of identifying and mobilising training institutions which can provide the required training. The following logistical

    arrangements should be addressed:

    • The number of people to be trained

    • The venue and date of the training

    • The training materials required

    • The expected input and output of the training

    • The training service provider must identify suitable training service providers to provide the training. The training

    should be accredited with the Construction Education and Training Authority.

    The training should be provided and structured so that the contractor can meet the requirements for ci db Contractor

    Competence Accreditation (see Section 4.4.2). This typically involves the attainment of formal NQF level qualications, or

    work place training and experience leading to the equivalent competence.

    5.2 Training attendance: sharing the cost of contractor development

    It is considered good practice to require contractors to contribute to their own development. Such contribution may take

    many forms, for example some contractor development programmes insist that contractors attend night classes to improve

    their skills while delivering on the contract. Other programmes require contractors to contribute 1% of turnover towards

    defraying the cost of mentorship. Such commitment ensures that contractors are not just participating in the CDP to obtain

    work, but actually progresses towards attaining the contractor development goals.

    Clients should introduce measures to ensure commitment from contractors as follows:

    • A contractor should at least bear 20% of the direct cost of skills development and training courses and 100% of the

    indirect cost by making employees own time available to attend training courses.

    • A contractor should at least contribute 20% of the direct cost of mentorship to a maximum of 1% of turnover.

    Should a contractor fail to pass the training courses or needs continuous mentorship, the contribution of the contractor

    should increase as follows:

    • A contractor bear the full direct cost of skills development and training and 100% of the indirect cost by making its

    employees time available to attend training courses.

    • A contractor should at least contribute 40% of the direct cost of mentoring to a maximum of 2.5% of turnover.

    If a contractor does not meet the requirements as stated above, the contractor should exit the programme.

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    20/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    18

    5.3 Dispute resolution

    Where there are established processes in respect of a particular form of contract, the Dispute Resolution Procedure for a

    CDP contract will be as set out in this guideline. The intention is to ensure that:

    • Contractors are not disadvantaged due to lengthy dispute resolution processes; and

    • Matters which are subject to disputes are separated from matters which are not.

    Disputes arising in contracts awarded through the CDP should be resolved as expeditiously as possible. At all times

    the parties to a CDP contract should attempt to settle any claim without the need to enter into formal dispute resolution

    processes. However where it is not possible to resolve a claim, the dispute resolution process should be followed as set

    out in this guideline.

     A dispute will arise where a claim by one party is rejected by the other party and attempts to resolve the matter amicably

    within the stipulated timeframe has failed. A claim will be considered as being rejected if the party to whom the claim is

    submitted, either:

    • Expressly rejects the claim;

    • Does not respond to the claim within the prescribed timeframe; or

    • The parties fail to reach a resolution within the stipulated timeframe and there is no agreement between the partiesto extend the timeframe for the purpose of resolving the claim.

    Claims will not be rejected in its entirety if there is a problem with only certain aspects of it. The parties must ensure that

    aspects of the claim which are not rejected are settled. All disputes arising in a CDP contract will be subjected to an

    adjudication process. At the time of entering into the contract with the CDP contractor, the parties to the CDP contract

    should choose an adjudicator.

    The party to a CDP contract, instituting a claim that arises out of any act or omission by another party to a CDP contract

    would rst give notice to the other party to settle the claim within 5 days of receipt of the claim. The claim should be

    supported with relevant details and any documentary evidence that will allow the other party to deal with the matter

    adequately.

    Should the claim be rejected, the parties must attempt to resolve the matter amicably within ve days of the claim being

    rejected. Should the parties not be able to resolve the matter in the prescribed time, the party that is not satised with the

    outcome must issue a notice of dispute to the other party within two days after the expiry of the stipulated time period.

    The notice of dispute should provide sufcient information and documentary evidence related to the dispute to give

    the other party adequate opportunity to prepare its response. The aggrieved party will simultaneously give notice to the

    adjudicator appointed through the adjudicator’s contract as contained in any form of contract calling on the adjudicator to

    set the matter down for adjudication within 5 days of the dispute notice date.

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    21/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    1919

    06

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    22/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    20

    EVALUATION AND EXITING OF CONTRACTORS

    In order to graduate from a CDP, contractors should be re-evaluated and should meet the requirements for:

    cidb Contractor Competence Accreditation; and• Upgrading to a higher grade designation.

    Furthermore, a formal application must have been submitted to the cidb for an accreditation of the contractor’s competence

    and for a contractor upgrade.

    Notwithstanding the requirements for graduating from a CDP, all contractors should exit contractor development after the

    agreed period specied in the CDP business case, whether they graduate or not. Generally this should not exceed three

    years, (which is the time it normally takes to acquire the competence and experience) except in the case of contractors

    who have shown signicant progress but have not yet graduated. In these cases, the client can decide whether to provide

    additional support for a specied period or by extending the contractor`s period within the CDP.

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    23/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    2121

    07

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    24/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    22

    MONITORING AND EVALUATION

     As part of the NCDP, the cidb intends to monitor and evaluate CDPs. Clients are expected to monitor their own programmes

    and report to the cidb on a quarterly basis. The table on the next page provides the key performance indicators per CDPwhich must be measured to determine the success of the CDP.

    Indicator Description Frequency  

    Budget Annual budget put aside for the CDP Annually

    Enrolments Number of contractors enrolled Quarterly

    Project

    awards

    Number of tender awards within CDP

    Value of tender awards within CDP

    Quarterly

    Mentoring &

    training

    Total number of mentors appointed

     Approximate total contact time between mentors and contractors

    Quarterly

    Loans Total number of loans accessed

    Total value of loans accessed

    Quarterly

    Costs Cumulative planned expenditure on CDP

    Cumulative actual expenditure on CDP

    Quarterly

    Cost-sharing Total contractor direct contributions to mentoring and training Quarterly

    Qualications Total number of NQF qualications awarded Annually

    Upgrades Number of contractors that meet the requirements improved their cidb grading Annually

    Graduations Number of contractors graduating Annually

    Exits Number of contractors exiting CDP (inclusive of graduations) Annually

    The table below provides the key reporting requirements to the cidb for a CDP.

    Report Description Frequency  

    Enrolments Name and CRS numbers of contractors enrolled Annually

    Graduations Name and CRS Number of contractors graduating Annually

    Qualications Name and CRS numbers of contracting entity, together with names of individuals

    and the cidb recognised NQF qualications awarded

     Annually

    Exits Name and CRS numbers of contractors exiting Annually

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    25/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    2323

     ANNEXURE

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    26/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    24

       S

       T   A   N   D   A   R   D   O   P   E   R   A   T   I   N   G   P   R   O

       C   E   D   U   R   E   S   (   S   O   P  s   )   F   O   R   I   M   P

       L   E   M   E   N   T   I   N   G   C   O   N   T   R   A   C   T   O   R

       D

       E   V   E   L   O   P   M   E   N   T   P   R   O   G   R   A   M   M

       E   S

       C   l   i  e

      n   t   D  e  p  a  r   t  m  e  n   t

       S   t  r  a   t  e  g   i  c   P

       l  a  n  n   i  n  g

       C  o  m  m

       i   t   t  e  e

       C  o  n   t  r  a  c   t  o  r

       A   d   j  u   d   i  c  a   t   i  o  n   C  o  m  m   i   t   t  e  e

       (   D   i  s  p  u   t  e   R  e  s  o   l  u   t   i  o  n   )

       A  p  p  o   i  n   t  e   d

       A   d   j  u   d   i  c  a   t  o  r

       C   D   P   S   t  a   k  e   h  o   l   d  e

      r

       A

       N   N   E   X   U   R   E  :   S   T   A   N   D   A   R   D   O   P   E   R   A   T   I   N   G   P   R   O   C   E   D   U   R   E   S   L   E

       G   E   N   D   S

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    27/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    25

       P

       R   O   C   E   D   U   R   E   F   O   R   I   M   P   L   E   M   E

       N   T   I   N   G   C   O   N   T   R   A   C   T   O   R   D   E   V   E

       L   O   P   M   E   N   T   P   R   O   G   R   A   M   M   E

       D  e   t  e  r  m   i  n  e   t  r  a   i  n   i  n  g

      s   t  r  a   t  e  g  y  a  n   d

      p  r  o  g  r  a  m  m  e

       D  e   t  e  r  m   i  n  e

      c  o  m  p   l  e  x   i   t  y  o   f

      p  r  o   j  e  c   t  s

       M  a  p  p  r  o   j  e  c   t   l  o  c  a   l   i   t  y  a  n   d

       d  e   t  e  r  m   i  n  e  c  o  n   t  r  a  c   t  o

      r

       d  e  v  e   l  o  p  m  e  n   t

      o  p  p  o  r   t  u  n   i   t   i  e  s

       I  n  v   i   t  e   C  o  n   t  r  a  c   t  o  r  s   t  o

      r  e  g   i  s

       t  e  r   f  o  r  c  o  n   t  r  a  c   t  o  r

       d  e  v  e   l  o  p  m  e  n   t

       A  s  s  e  s  s  c  o  n   t  r  a  c   t  o  r  s

       D  e   t  e  r  m   i  n  e

       i  n  c   l  u  s   i  o  n  c  r   i   t  e  r   i  a

       D  e   t  e  r  m   i  n  e  p  r  o  g  r  a  m  m  e

      n  e  e   d ,  g  o  a   l  s  a  n   d  s   t  r  a   t  e  g  y   f  o  r

      c

      o  n   t  r  a  c   t  o  r   d  e  v  e   l  o  p  m  e  n   t

       E  s   t  a   b   l   i  s   h  c  o  n   t  r  a  c   t  o  r

       d  e  v  e   l  o  p

      m  e  n   t  s   t  e  e  r   i  n  g

      c  o

      m  m   i   t   t  e  e

       I   d  e  n   t   i   f  y  p  r  o  g  r  a  m  m  e

      r  o   l  e  p   l  a  y  e  r  s

       D  e  v  e   l  o  p  p  r  o  g  r  a  m  m  e

       b

      u  s   i  n  e  s  s  c  a  s  e

       S  e   l  e  c   t  o  r  g  a  n  o  g  r  a  m   f  o  r

      c  o  n   d  u  c   t  o  r   d  e  v  e   l  o  p  m  e  n   t

       C  o  n   d  u  c   t  r  o   l  e

      p   l  a  y  e  r  s

      c  o  n  s  u   l   t  a   t   i  o  n

      s  e  s  s   i  o  n

       D  e   t  e  r  m   i  n  e  m  e  n   t  o  r   i  n  g

      a  p  p  r  o  a  c   h

       S  e   l  e  c   t  p  r  o   j  e  c   t  s

      a  n   d   d  e   t  e  r  m

       i  n  e   t  a  r  g  e   t  s

       C  o   l   l  e  c   t  p  o  r   t   f  o   l   i  o  o   f

      p  r  o   j  e  c   t  s

       D  e   t  e  r

      m   i  n  e  m  e  n   t  o  r  r  o   l  e  s

      a  n   d

      e  x  p  e  c   t  e   d   t  a  s   k  s

       D  e   t  e  r  m   i  n  e  s   t  a   f   f  r  o   l  e  s

      a  n   d  e  x  p  e  c   t  e   d

       t  a  s   k  s

       i  n   t   h  e  p  r  o  g  r  a  m  m  e

       D  e     n  e  r  e  s  o  u  r  c  e  s  a  n   d

       b  u   d  g  e   t  n  e  e   d  e   d

       C  o  n   d  u  c   t  c  o  n

       t   i  n  u  o  u  s

      m  o  n   i   t  o  r   i  n  g  a  n   d

      r  e  p  o  r   t   i  n  g

       D  e  v  e   l  o  p   M   &   E  a  p  p  r  o  a  c   h

       D  e  v  e   l  o  p  e  x   i  s   t   i  n  g  c  r   i   t  e  r   i  a

       E  s   t  a   b   l   i  s   h  c  o

      s   t

      s   h  a  r   i  n  g  p  r   i  n  c   i  p   l  e  s

       E  s   t  a   b   l   i  s   h   d   i  s  p  u   t  e

      r  e  s  o   l  u   t   i  o  n  p  r  o  c  e  s  s

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    28/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    26

       T

       A   R   G   E   T   I   N   G   P   R   O   C   E   D   U   R   E

       I   d  e  n   t   i   f  y   t  a  r  g  e   t  g  r  o  u  p  s   f  o  r

      c  o  n   t  r  a  c   t  o  r   d  e  v  e   l  o  p  m  e  n   t

       O   b

       t  a   i  n  p  r  o   j  e  c   t   l   i  s   t

       M  e  a  s  u  r  e  p  r  o   j  e  c   t

      c  o  m  p   l  e  x   i   t  y  p  e  r  p  r  o   j  e  c   t

       M  e  a  s  u  r  e   t   h  e  o  r  g  a  n   i  s

      a   t   i  o  n  a   l

      c  a  p  a  c   i   t  y  p  e  r  p  r  o   j  e  c   t

       B  a  s  e   d  o  n   t   h  e  m  e  a  s  u  r  e  m  e  n   t

      o  u   t  c  o  m  e ,

       i   d  e  n   t   i   f  y  p  r  o   j  e  c   t  s

       f  o  r  c  o  n   t  r  a  c   t  o  r   d  e  v  e   l  o

      p  m  e  n   t

       M  e  a  s  u  r  e  p  r  o   j  e  c   t

      s  u   i   t  a   b   i   l   i   t  y   i  n   t  e  r  m  s  o   f

       l  o  c  a   l   i   t  y  p  e  r  p  r  o   j  e  c   t

       P  r  o   j  e  c   t   L   i  s   t

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    29/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    27

       C

       O   N   T   R   A   C   T   O   R   A   S   S   E   S   S   M   E   N

       T   P   R   O   C   E   D   U   R   E

       C  o

      n   t  r  a  c   t  o  r   i  s  n  o   t  s  u   i   t  a   b   l  e

       f  o  r   f  u  r   t   h  e  r  s  c  r  e  e  n   i  n  g

       D  e   t  e  r  m   i  n  e   i   f   t   h  e  c  o  n   t  r  a  c   t  o  r

       i  s  r  e  g

       i  s   t  e  r  e   d   i  n   t   h  e  r  e  g   i  s   t  e  r

      o   f  c  o  n   t  r  a  c   t  s

       A  s  s  e  s  s  a  n   d  s  c  o  r  e

      c  o  n

       t  r  a  c   t  o  r  s  c  o  m  p  e   t  e  n  c  e

       b  a

      s  e   d  o  n  c  o  m  p  e   t  e  n  c  e

      r  e  q  u   i  r  e  m  e  n   t  s

       A  s  s  e  s  s  a  n   d  s  c  o  r  e

      c  o  n   t

      r  a  c   t  o  r  s     n  a  n  c   i  a   l

      u  p

      g  r  a   d   i  n  g   f  a  c   t  o  r

       A  w  a  r   d  p  o   i  n

       t  s   f  o  r

      s  o  c   i  o  -  e  c  o  n  o  m

       i  c  g  o  a   l  s

       D  e   t  e  r  m   i  n  e  c  o

      n   t  r  a  c   t  o  r  r  a   t   i  n  g

       S  e   l  e  c   t  c  o  n   t  r  a  c   t  o  r  s   f  r  o  m   h   i  g   h   t  o   l  o  w  w   i   t   h

       t   h  e  c  u   t  -  o   f   f  p  o   i  n   t   d  e   t

      e  r  m   i  n  e   d   b  y

       t   h  e  a  v  a   i   l  a   b   l  e   b

      u   d  g  e   t

       A   d   d  c  o  n   t  r  a  c   t  o  r  r  a   t   i  n  g  s  c  o  r  e   t  o  p  o   i  n   t  s

      a  w  a  r   d  e   d   f  o  r  s  o  c   i  o  -  e  c  o  n  o  m   i  c  g  o  a   l

       N  o

       Y  e  s

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    30/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    28

       C

       O   S   T   S   H   A   R   I   N   G   P   R   I   N   C   I   P   L   E   S

       F   O   R   C   O   N   T   R   A   C   T   O   R   D   E   V   E   L   O   P   M   E   N   T

       C  o  n   t  r  a  c   t  o  r   b  e  a  r  s   2   0   % 

      o   f   t   h  e   d   i  r  e  c   t  c  o  s   t  o   f  s   k   i   l   l  s

       d  e  v  e   l  o  p  m  e  n   t  a  n   d   t  r  a   i  n   i  n  g

      c  o  u  r  s  e  s  a  n   d   1   0   0   %   o

       f   t   h  e

       i  n   d   i  r  e  c   t  c  o  s   t ,  a  n   d  c  o  n   t  r   i   b  u   t  e  s

       2   0   %   o

       f   t   h  e   d   i  r  e  c   t  c  o  s   t  o   f

      m  e  n   t  o  r  s   h   i  p   t  o  a  m  a  x   i  m  u  m  o   f

       1   %    t

      u  r  n  o  v  e  r

       C  o  n   t  r  a  c   t  o  r   b  e  a  r  s   f  u   l   l   d   i  r  e  c   t

      c  o  s   t  o   f  s   k   i   l   l  s   d  e  v  e   l  o  p  m  e  n   t

      a  n   d   t  r  a   i  n   i  n  g  a  n   d   1   0   0   %   o   f

       t   h  e   i  n   d   i  r  e  c   t  c  o  s   t

       C  o  n   t  r  a  c   t  o  r  c  o  n   t  r   i   b  u   t  e  s

       2   0   %   o

       f   t   h  e

       d   i  r  e  c   t  c  o  s   t

      o   f  m  e  n   t  o  r  s   h   i  p   t  o  a

      m  a  x   i  m  u  m  o   f   1   %    t

      u  r  n  o  v  e  r

       C  o  n   t  r  a  c   t  o  r  c  o  n   t  r   i   b  u   t  e  s

       4   0   %   o

       f   t   h  e   d   i  r  e  c   t  c  o  s   t  o   f

      m  e  n   t  o  r   i  n  g   t  o  a  m  a  x   i  m  u  m

      o   f   2 .   5

       %   o

       f   t  u  r  n  o  v  e  r

       D  o  e  s  c  o  n   t  r  a  c   t  o  r  r  e  q  u   i  r  e

      c  o  n   t   i  n  u  o  u  s  m  e  n   t  o  r   i  n  g   ?

       C  o  n   t  r  a  c   t  o  r   b  e  a  r  s   2   0   %   o

       f   t   h  e   d   i  r  e  c   t

      c  o  s   t  o   f  s   k   i   l   l   d  e  v  e   l  o  p  m  e  n   t  a  n   d   t  r  a   i  n   i  n  g

      c  o  u  r  s  e

      s  a  n   d   1   0   0   %   o

       f   t   h  e   i  n   d   i  r  e  c   t  c  o  s   t

       C  o  n   t  r  a  c   t  o  r  a   t   t  e  n   d  s

      s  u  p  p  o  r   t   i  n   i   t   i  a   t   i  v  e

       D   i   d   t   h  e  c  o  n   t  r  a  c   t  o  r  p  a  s  s

       t   h  e   t  r  a   i  n   i  n  g  c  o  u  r  s  e  s   ?

       N  o

       N  o

       Y  e  s

       Y  e  s

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    31/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    29

       D

       I   S   P   U   T   E   R   E   S   O   L   U   T   I   O   N   P   R   O

       C   E   D   U   R   E   F   O   R   C   O   N   T   R   A   C   T   O

       R   D   E   V   E   L   O   P   M   E   N   T

       A  w

      a  r   d  c  o  n   t  r  a  c   t

       t  o   C

       D   P  c  o  n   t  r  a  c   t  o  r

       A  p  p  o   i  n   t  a  n

       A   d   j  u   d   i  c  a   t  o  r

       f  o  r  c   i   d   b   ’  s   P  a  n  e   l  o   f

       A   d   j  u   d

       i  c  a   t  o  r  s

       S  u   b  m   i   t  n  o   t   i  c  e   t  o

      s  e   t   t   l  e  c   l  a   i  m

      w   i   t   h   i  n

       5   d  a  y  s

       S  e   t   t   l  e  m  e  n   t

      r  e  a  c   h  e   d   ?

       C  o  n   t   i  n  u  e  w   i   t   h

      p  r  o   j  e  c   t

       R  e  c  e   i  v  e  n  o   t   i  c  e

      o   f   d   i  s  p  u   t  e

       R  e  c  e   i  v  e  n  o   t   i  c  e

      o   f   d   i  s  p  u   t  e

       S  u   b  m   i   t  n  o   t   i  c  e  o

       f

       d   i  s  p  u   t  e

       S  c   h  e   d  u

       l  e  m  e  e   t   i  n  g

       f  o  r  a   d   j  u

       d   i  c  a   t   i  o  n  o   f

       t   h  e   d   i  s  p  u   t  e

       N  o

       Y  e  s

       D  o  c  u  m  e  n   t  a  r  y  e  v

       i   d  e  n  c  e

       t  o  s  u  p  p  o  r   t   t   h  e  c   l  a   i  m

       D  o  c  u  m  e  n   t  a  r  y  e  v   i   d  e

      n  c  e

       t   h  a   t  s  u  p  p  o  r   t   d   i  s  p  u   t  e

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    32/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    30

       P

       R   O   C   E   D   U   R   E   F   O   R   E   V   A   L   U   A   T   I   O   N   A   N   D   E   X   I   T   I   N   G   O   F   C   O   N   T   R   A   C   T   O   R   ’   S

       C  o  n   t  r  a  c   t  o  r  e  x   i   t

       C

       O   P  u  n  s  u  c  c  e  s  s   f  u   l   l  y

       C  o  n   t  r  a  c   t  o  r  e  x   i   t

       C   O   P  s  u  c  c  e  s  s   f  u   l   l  y

       R  e  -  a  s  s  e  s  s  c  o  n   t  r  a  c   t  o  r

      a   f   t  e  r   t   h  e   d  e     n  e   d  p  e  r   i  o   d

      w   h  e   t   h  e  r   h  e   /  s   h  e  c  o  m  p   l   i  e  s

      w   i   t   h   t   h  e  g  r  a   d  u  a   t   i  o  n

      c  r   i   t  e  r   i  a   ?

       P  r  o  v   i   d  e  a   d   d   i   t   i  o  n  a   l

      s  u  p  p  o  r   t   f  o  r  a   d  e     n  e   d

      p  e  r   i  o   d   (  p  r  e   f  e  r  a   b   l  y

      o  n  e  y  e  a  r   )

       D  e  c   i   d

      e  w   h  e   t   h  e  r  c  o  n   t  r  a  c   t  o  r

       h  a  s

      s   h  o  w  n  s   i  g  n   i     c  a  n   t

      p  r  o  g  r  e  s  s   t  o  p  r  o  v   i   d  e

      a   d   d   i   t   i  o  n  a   l  s  u  p  p  o  r   t

      w   i   t   h

       i  n   t   h  e  p  r  o  g  r  a  m  m  e   ?

       C  o  n   t  r  a  c   t  o

      r  e  x   i   t  s

      c  o  n   t  r  a  c   t  o  r   d  e

      v  e   l  o  p  m  e  n   t

      u  n  s  u  c  c  e  s  s   f  u   l   l  y

       A  s  s  e  s  s  w

       h  e   t   h  e  r  c  o  n   t  r  a  c   t  o  r

      c  o  m  p   l   i  e  s  w   i   t   h   t   h  e  g  r  a   d  u  a   t   i  o  n

      c  r   i   t  e  r   i  a  a   t   t   h  e  e  n   d  o   f  c  o  n   t  r  a  c   t  o  r

       d  e  v  e

       l  o  p  m  e  n   t   t  e  r  m

       C  o  n   t  r  a  c   t  o  r  e  x   i   t  s

      c  o  n   t  r  a  c   t  o  r   d  e

      v  e   l  o  p  m  e  n   t

      p  r  o  g  r  a  m  m  e  s  u  c  c  e  s  s   f  u   l

       Y  e  s

       Y  e  s

       Y  e  s

       N  o

       N  o

       N  o

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    33/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    31

       M

       O   N   I   T   O   R   I   N   G   A   N   D   E   V   A   L   U   A   T

       I   O   N   P   R   O   C   E   D   U   R   E

       D

      e  v  e   l  o  p   M  o  n   i   t  o  r   i  n  g  a  n   d

       E  v  a   l  u  a   t   i  o  n   P   l  a  n  w   i   t   h

      s  p  e  c   i     c  g  o  a   l  s

       D  e   t  e  r  m   i  n  e   t   h  e   i  n   d   i  c  a   t  o  r  s

       t  o   b  e  m  e  a  s  u  r  e   d

       M  e  a  s

      u  r  e   t   h  e  v  a  r   i  o  u  s

       i  n   d   i  c  a   t  o  r  s

       O   b   t  a   i  n  r  e

      s  u   l   t  s   f  o  r

      e  a  c   h  m  e  a

      s  u  r  e  m  e  n   t

       C  o  m  p  a  r  e  r  e  s  u   l   t  s   t  o

       i   d  e  n   t   i     e   d  g  o  a   l  s   f  r  o  m   t   h  e

      m  e  a  s  u  r  e  m  e  n   t  c  o  n   d  u  c   t  e   d

       W  e  r  e   t   h  e   i   d  e

      n   t   i     e   d  g  o  a   l  s

      a  c   h   i  e

      v  e   d   ?

       T   h  e   C  o  n   t  r  a  c   t  o  r   D  e  v  e   l  o  p  m  e  n   t

       P  r  o  g  r  a  m  m  e   (   C   D   P   )  w  a  s  s  u  c  c  e  s  s   f  u   l

       Y  e  s   N

      o

       D  e  v  e   l  o  p  a   C  o  n   t  r  a  c   t  o  r

       D  e  v  e   l  o  p  m  e  n   t

       I  m  p  r  o  v  e  m  e  n   t   P   l  a  n

       M  o  n   i   t  o  r   i  n  g  a  n   d

       E  v  a   l  u  a   t   i  o  n   P   l  a  n

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    34/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    32

    Notes:

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    35/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    33

    Notes:

  • 8/17/2019 Guidelines for Implementing Contractor Development Programmes

    36/36

    cidb | NCDP GUIDELINES FOR IMPLEMENTING CONTRACTOR DEVELOPMENT PROGRAMMES | SEPTEMBER 2011

    Website: www.cidb.org.zaE-mail: [email protected]

    Tel: +27 12 482 7200 or +27 86 100 cidbFax: +27 12 349 8986 or +27 86 681 9995

     Anonymous Fraud line: 080 011 2432Postal address: PO Box 2107, Brooklyn Square, 0075

    Physical address: Blocks N&R, SABS Campus,2 Dr. Lategan Rd, Groenkloof, Pretoria, South Africa