Guidance forUtility Adequacy
Assessments
Steering Committee MeetingJanuary 29, 2010
January 29, 2010 Resource Adequacy Steering Committee Meeting
2
Outline
• Arguments For Utility Guidance
• Arguments Against Utility Guidance
• Current Regional Adequacy Standard
• Potential methodology to provide guidance
January 29, 2010 Resource Adequacy Steering Committee Meeting
3
Arguments For Utility Guidance
• Could help make utility planning more consistent throughout the region
• Would make utility planning consistent with the Council’s power plan
• Would help utilities with smaller long-term resource planning budgets
January 29, 2010 Resource Adequacy Steering Committee Meeting
4
Arguments Against Utility Guidance
• Could be perceived as infringing on the jurisdiction of individual utilities
• Would be very difficult to develop a precise tool
• Could be misused as a surrogate for a long-term planning process
January 29, 2010 Resource Adequacy Steering Committee Meeting
5
Current Regional Adequacy Standard Measures
• Energy: Annual average generating capability must equal annual average load– Includes an amount of non-firm resources derived from
an LOLP analysis • Capacity: Sustained-peak generating capability
must equal sustained-peak load plus a reserve margin– Sustained-peak generation includes some non-firm
resources– Reserve margin is derived from an LOLP analysis that
includes some non-firm resources
January 29, 2010 Resource Adequacy Steering Committee Meeting
6
Possible Approach for Utility Energy Measure
• Annual generating capability = annual load
• Amount of non-firm generation to include is a function of total non-firm available to the utility plus other factors
• This function has not yet been defined
January 29, 2010 Resource Adequacy Steering Committee Meeting
7
Possible Approach for Utility Capacity Measure
• Sustained-peak generating capability = sustained-peak load plus a reserve margin
• Sustained-peak generation includes some non-firm generation, which is a function of total non-firm available to the utility plus other factors
• The reserve margin is a function of the total non-firm available to the utility plus other factors
• This function has not yet been defined