Upload
constance-gallagher
View
221
Download
0
Embed Size (px)
Citation preview
Moving toward a FinalResource Adequacy
Standard
Resource Adequacy Forum Steering Committee Meeting
September 27, 2007
September 27, 2007 2
Outline
• Review current standard• Changes that will not alter the
standard• Changes that will alter the standard• Future considerations for the Forum• A look at curtailment events
September 27, 2007 3
PNW ResourceAdequacy Standard
• Based on the assumption that the region will tolerate a 1-in-20 year likelihood of a significant curtailment due to lack of supply
• The underlying standard is a 5 percent loss-of-load-probability (LOLP) • The LOLP standard is “translated” into an annual
load/resource balance target to gauge the energy supply
• And into a peak period surplus reserve margin target to gauge the capacity supply
September 27, 2007 4
Metrics for the NW Standard
• The choice of metrics is almost arbitrary.
• The metric must show some relationship between resources and loads.
• The adequacy target for the metric is derived from a scenario with a 5-percent LOLP.
September 27, 2007 5
Metrics for the NW Standard
• The metric can be the annual, monthly or even hourly difference between loads and resources, calculated from the 5% LOLP scenario.
• It can be portrayed in terms of absolute megawatts or in terms of percent.
September 27, 2007 6
Metrics for the NW Standard
• The metric can include a line item for market supplies in the tally of resources, but it doesn’t have to.
• The load is usually based on normal weather, but it doesn’t have to be.
• It can be based on critical hydro, but it doesn’t have to be.
September 27, 2007 7
Caveat• Whatever assumptions are used to define the
metric must also be used when evaluating the status of the power supply.
• When one or more of the assumptions in the definition of the metric changes, the underlying standard does not change.
• Updating resource and load data or improving the simulation program does not change the standard.
• Under any of these cases, real life resource acquisition decisions will not be altered.
September 27, 2007 8
What can change the Standard?
• Any change in assumptions that alters the underlying 5 percent LOLP will change the standard.
• Examples include:• The definition for a significant energy event.• The definition for a significant capacity event.• The months over which events are counted.• Adding or subtracting random variables to the
simulation.• Directly changing the 5 percent target to something
else.
September 27, 2007 9
Adequacy Forum’s Charge• The Forum is charged with reevaluating the
energy and capacity targets each year.• As conditions change, the targets may
change but the underlying standard remains intact.
• The Forum is also charged with reviewing the underlying 5 percent LOLP standard and altering it if appropriate.
• Altering the LOLP standard will change resource acquisition actions.
September 27, 2007 10
Future Considerations that may change the
Standard• The definition for a significant energy event.• The definition for a significant capacity
event.• Consider using all months of the year.• Consider calculating a single LOLP instead of
a separate energy and capacity LOLP.• Should only “bad” years be counted or
should the LOLP be based on bad events?• Review the 5 percent LOLP target.
September 27, 2007 11
January 1930
-5000
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
1 27 53 79 105
131
157
183
209
235
261
287
313
339
365
391
417
443
469
495
521
547
573
599
625
651
677
703
729
Hour in Month
Meg
awat
ts
Net Demand NW Thermal NW Hydro Unserved Net Imports
Cold
Hydro Limited
GENESYS Simulation Illustrative Example Only
September 27, 2007 12
Curtailment Events(Peaking problems and energy shortages)
0
1000
2000
3000
4000
Hourly Curtailments Dec-Apr (Not all hours shown)
Curt
aile
d M
egaw
att
s
Peak Event > 3,000 MW
Energy Event > 28,800 MW-hrs
Each event has a peak and duration.
September 27, 2007 13
Curtailment EventsL/R Bal approximately -1,500 aMW
Curtailment Events - LOLP = 4%Capacity LOLP = 0% ???
0
1000
2000
3000
4000
5000
6000
1 2 2 2 2 2 2 9 9 9 9 9 9 9 9 9 9 9 27 27 41
Cu
rta
ilme
nt
(MW
)
Game 2
Game 9
This is a scenario that is just adequate for energy needs.
September 27, 2007 14
Curtailment EventsL/R Bal approximately -2,000 aMW
Or, 500 aMW higher load than @energy target
Curtailment Events - LOLP = 10%Capacity LOLP 6% ???
0
1000
2000
3000
4000
5000
6000
1 2 2 2 2 2 2 2 2 2 2 8 8 8 8 8 8 8 8 8 8 8 8 8 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 2727 27272727 272741
Cu
rta
ilme
nt
(MW
)
Game 2
Game 9
Game 27
Game 2 Game 9Game 8 Game 27 Game 41
September 27, 2007 15
Additional Slides
September 27, 2007 16
Energy Metric Assumptions
• Averaged over all hours of the year • Load is based on normal weather and
includes net interregional firm contracts• Resources include
• In-region spot market (uncommitted IPPs)• Critical-year hydroelectric generation• A 1500 MWa planning adjustment (derived
from the LOLP analysis) accounting for out-of-region spot markets and non-firm hydro generation
September 27, 2007 17
Capacity Metric Assumptions
• Averaged over the peak load duration hours• Load is based on normal weather and
includes net interregional firm contracts • Resources include
• In-region spot market (uncommitted IPPs) • Critical-year hydroelectric generation• A planning adjustment accounting for out-of-
region spot markets and non-firm hydro generation
September 27, 2007 18
Resource Assumptions• In-region spot market (uncommitted
IPPs)• Nov-May full IPP capability• Jun-Oct 1,000 MW only
• Out-of-region spot market• Nov-May 3,000 MW • Jun-Oct 0 MW
• Non-firm hydro and hydro flex• Nov-May 2,000 MW • Jun-Oct 1,000 MW
September 27, 2007 19
Targets for the NW Standard
• Targets are set so that the resulting Loss-of-Load Probability (LOLP) is 5 percent
• Energy – zero, that is, annual average loads and resources should be in balance
• Capacity• 25 percent for winter months• 19 percent for summer months