50
Guadalupe River – Tasman Dr. to I880 Conceptual Alternatives Presented by: Katie Muller, Project Manager

Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Guadalupe River – Tasman Dr. to I880Conceptual AlternativesPresented by: Katie Muller, Project Manager

Page 2: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Presentation Agenda

Engineering Planning Process• Phase 1: Problem Definition• Phase 2: Conceptual Alternatives Analysis  (19 Alternatives)• Phase 3: Feasible Alternatives Analysis  (8 Alternatives)Questions and Public Input

Page 3: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Public Feedback

Analyze & Refine Alternatives

Develop Report

The Planning Process

1. Problem Definition

2. Conceptual Alternatives

3. Feasible Alternatives

4. Staff‐Recommended Alternative

Final Project

Page 4: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Phase 1: Problem DefinitionGuadalupe River Background and History

Page 5: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Guadalupe Watershed• All rain ends up in Guadalupe River

• 7 Reservoirs• Three “sections” of river:• Upper• Downtown• Lower

Page 6: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Lower Guadalupe River Project 

• Completed 2004

• 100‐Year flood protection

• Levees and Floodwalls

• Bridge Improvements

Page 7: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Phase 1: Problem DefinitionDefining the Problem and the Project’s Objectives 

Page 8: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Problem• Channel is under design capacity

Causes• Vegetation overgrowth

• Levee encroachment in to channel

Page 9: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

9

valleywate

r.org

Project Objectives

• Restore 1‐percent flood capacity 

Other Criteria• Minimize future O&M activities • Maintain/enhance public recreation and access

• Obtain community support for the Project

Page 10: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Image Placeholder

10What is 100‐Year?1% probability of occurrence in a given year • 1 in 100 chance• 26% chance over life of 30‐year mortgage

Why 100‐Year?• FEMA National Flood Insurance Program MapsNote: Does not eliminate 

all flood risk!

Page 11: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

11

valleywate

r.org

Sediment removed from side channels to add flow capacity

Sediment Removal

Operate Reservoir for Flood Risk Reduction

Lexington Operations

Valley Water Field Information Teams (FIT), City Coordination, and Emergency Action Plans

Storm PreparednessVegetation RemovalTrees cleared from levees and 15 feet from levee toe

Preparations for This Winter

Page 12: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Phase 2: Conceptual Alternatives Analysis

Page 13: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternatives Hierarchy

Conceptual Alternatives

Feasible Alternatives

Staff‐Recommended Alternative

Conceptual Alternatives• High‐level• Anything within realm of 

possibility

• 19 Alternatives identified

Page 14: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative A – No Project

Page 15: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

15

valleywate

r.org

Types of Flood Risk Reduction

Change Geometry to carry more flow

Taller

Wider

Page 16: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Common Flood Risk Reduction Elements

FloodwallConcrete or sheet pile barrier

HeadwallFloodwall on a bridge

Page 17: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Common Flood Risk Reduction Elements

Passive BarrierSelf‐raising barrier activated by 

water pressure

LeveeEarthen barrier

Page 18: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative B – Floodwalls  Cost: $65 ‐ 180 million

Bridge Headwalls

OR

Passive Barriers

Page 19: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative C – Raise Levees Cost: $70 – 80 million

Page 20: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative E – Raise Bridges Cost: $190 million

Page 21: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative G – Replace Levee with High Floodwall

Cost: $190 million

Page 22: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative K – Channel Widening 

Cost: $650 million

Page 23: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

23

valleywate

r.org

Types of Flood Risk Reduction

Reduce “Roughness” Water moves faster, has more space

Page 24: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative L – Vegetation Removal 

Cost: $100 to $840 million

Page 25: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative M – Channel Paving 

Cost: $170 million

Page 26: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

26

valleywate

r.org

Types of Flood Risk Reduction

Reduce High FlowsLess flow in channel

Large open space to hold flood water

Large bypass Pipe (culvert)

OR

Page 27: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Common Flood Risk Reduction Elements

Bypass CulvertConcrete pipe that diverts water

Detention BasinOpen space area that holds 

floodwaters

Bypass entrance

Page 28: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Common Flood Risk Reduction Elements

Operate Reservoirs for Flood StorageUse reservoir to store flood water

Bypass entrance

Page 29: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative D – Off‐stream DetentionCost: $85 ‐ 200 million

Page 30: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative F – Bypass Culvert Cost: $300 million

Page 31: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative H – Add Outlet Capacity to Lenihan Dam

Cost: $33 ‐ 110 million

Page 32: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative I – Raise Lenihan Dam

Cost: $110 million

Page 33: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative J – Re‐Operate Lenihan Dam

Cost: $11 million

Page 34: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternatives Hierarchy

Conceptual Alternatives

Feasible Alternatives

Staff‐Recommended Alternative

Feasible Alternatives• More detailed• Must be practical• Must pass screening

• 8 Alternatives identified

“Level 1” Screening

Page 35: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Meets Project Objectives

Cost ($80 M)

Technical Feasibility

Property Availability

Conceptual Alternative

Feasible Alternative

“Level 1” Screening:

Conceptual Alternatives Screening

Page 36: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Next Phase: Feasible Alternatives Analysis

Page 37: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative A – No Project

Page 38: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative B – Floodwalls  Cost: $65 million

Page 39: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative B.2 – Floodwalls & Closed Roadways

Cost: $75 million

Page 40: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative C – Raise Levees Cost: $80 million

Page 41: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative C.1 – 3 ft Floodwalls & Raised Levees

Cost: $70 million

Page 42: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative D.2– Off‐stream Detention: 5 ft

Cost: $85 million

Page 43: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative H.1 – Outlet Capacity in Exist Tunnel

Cost: $33 million

Page 44: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Alternative J – Re‐Operate Lenihan Dam

Cost: $11 million

Page 45: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

Public Feedback

Re‐Analyze & Refine 

Alternatives

Develop Report

The Planning Process: Next Steps

Problem Definition

Conceptual Alternatives

Feasible Alternatives

Staff‐Recommended Alternative

Final Project

Page 46: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

valleywate

r.org

46Project Next Steps

Page 47: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

valleywate

r.org

471. What did you like about the Alternatives?

2. What didn’t you like about the Alternatives?

3. Is there anything else we didn’t consider?

Questions

Page 48: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

48

valleywate

r.org

Alternative A: No Project

Alternative B: Floodwalls/Headwalls

Alternative B.2: Floodwalls/Close Bridges

Alternative C: Raise Levees

Alternative C.1: Floodwalls +Levees

Alternative D.2: Detention Basin

Alternative H.1: Upsize Lenihan Outlet

Alternative J: Re‐Operate Lenihan

Page 49: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual

@valleywater

@valleywater

@valleywater

Subscribe, Follow & Contact us

Katie Muller, Project Manager408‐630‐[email protected]

Jose VillarrealCommunity Liaison408‐630‐2879 [email protected]

Email notifications: www.valleywater.org/guadalupe‐river‐tasman‐i880

Page 50: Guadalupe River –Tasman Dr. to I880...Presented by: Katie Muller, Project Manager. Presentation Agenda Engineering Planning Process • Phase 1: Problem Definition • Phase 2: Conceptual