15
NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, operated by the Alliance for Sustainable Energy, LLC. Grid Interconnection and Performance Testing Procedures for Vehicle-to-Grid (V2G) Power Electronics Dr. Sudipta Chakraborty WREF 2012 - Denver, Colorado May 15, 2012

Grid Interconnection and Performance Testing Procedures ... · steps ‘n’ and ‘o’ of the anti-islanding tests in IEEE 1547.1 cannot be performed for some V2G interconnection

  • Upload
    dangdan

  • View
    221

  • Download
    1

Embed Size (px)

Citation preview

NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, operated by the Alliance for Sustainable Energy, LLC.

Grid Interconnection and Performance Testing Procedures for Vehicle-to-Grid (V2G) Power Electronics

Dr. Sudipta Chakraborty

WREF 2012 - Denver, Colorado

May 15, 2012

2

Background on V2G

• Bidirectional power flow can add vehicle-to-grid (V2G) capability in a plug-in electric or hybrid-electric vehicle

• Required a reliable, high-power, high-energy battery pack with bidirectional power electronics

• The controller module controls the power electronics to operate in charge, discharge, or standby modes

Power

Electronics

Wheel

Wheel

M/G

Battery

Battery

Battery

Battery

Battery

Battery

VEHICLE

UTILITY

Power Control/Data

Control

3

Objective of Paper

• Discuss a recently published NREL technical report on interim test procedures for V2G vehicles

• V2G capability allows the vehicle to operate as a distributed energy resource (DER)

- need of specific test procedures

• Some sample test results are

provided in the paper based

on electrical testing of prototype

V2G vehicles at NREL

4

Test Setup and Requirements

• Requirements such as safety, measurement repeatability and environmental requirements should be followed

• Manufacturers’ specifications for the V2G-capable vehicle will determine the specifics

• In this example system, the charging/discharging is controlled using cellular signals - test setup uses grid simulator, load bank

Motor

Controller

Wheel

Wheel

Battery

Battery

Battery

Battery

Battery

Battery

Battery Charger /

Inverter

Programmable

AC Grid Simulator

Emergency

Battery

Disconnect

PLUG-IN VEHICLE WITH V2G CAPABILITY

V2G Control

Computer

Battery Charge/

Discharge ControlVariable

RLC Load Bank

12 VDC

M/G

Modem

Cell Tower

5

Grid Interconnection Tests

• To determine the safe V2G interconnection to the utility grid

• Most of these tests are described based on the IEEE Std. 1547.1-2005 that gives the conformance test procedures for equipment that interconnects distributed resources with electric power systems

• For the V2G vehicles, capable of connecting to the utility at different voltage levels (e.g. 120 V, 240 VAC rms), all of the interconnection testing discussed in this paper will need to be conducted for all practical utility connection voltages

• Some of the IEEE 1547.1 tests are unfeasible or redundant for V2G power electronics

6

Grid Interconnection Tests (Contd.)

• List of typical interconnection tests includes: - Response to Abnormal Voltages

- Response to Abnormal Frequencies

- Synchronization and Seamless Transfer

- Unintentional Islanding

- Open Phase

- Reconnect Following Abnormal-Condition Disconnect

- DC Current Injection

- Harmonics

• Example of modification:

steps ‘n’ and ‘o’ of the anti-islanding tests in IEEE 1547.1 cannot be performed

for some V2G interconnection equipment because both the input power from the battery and the output power level are not adjustable

7

Grid Interconnection Tests (Contd.)

• List of additional interconnection tests includes: - Temperature Stability

- Interconnection Integrity Test

1. Test of protection from electromagnetic interference (EMI)

2. Test of surge-withstand performance

3. Dielectric test of the paralleling device

• Such tests are often difficult to conduct in laboratory setup because of safety concerns, the requirement of special instruments, and the possibility that the V2G unit under test could be damaged

• A certified factory test results (i.e., those performed by the manufacturer) may suffice in lieu of further third-party or owner testing

8

V2G Electrical Performance Tests

• Tests are designed to verify or establish the relevant converter’s operational characteristics

• List of electrical performance tests includes: - Continuous Output Power

- Conversion Efficiency

• These two test procedures were developed from Sandia Inverter Test Protocol for photovoltaic inverters - several modifications are required to apply it to the V2G testing (in NREL report)

9

Advanced Grid Support Tests

• The most promising markets for V2G are ancillary services, such as frequency regulation and spinning reserve

• With today’s battery technology, designing a V2G-capable vehicle that can provide reserve capability will be easier than designing a vehicle that provides regulation

• A general test procedure is developed for typical V2G vehicles that desire to provide reserve functions

• Additionally another test procedure is developed that determines the charging time for the vehicle - this charging time test is important to understand how often one can use the V2G vehicle to support grid reserve

10

V2G Self-Protection Tests

• To evaluate the V2G power electronics’ ability to protect themselves under various abnormal conditions

• Obtained from UL Standard 1741 “Standard for Inverters, Converters, Controllers and Interconnection System Equipment for Use With Distributed Energy Resources”

• List of tests includes: - Output Overload

- Short Circuit

- Loss of Control Circuit

• If the V2G vehicle comes with power converters that are UL1741 certified, factory test results may suffice in lieu of further third-party or owner testing

11

Sample Test Results

• Results from Abnormal Voltage Tests (under voltage)

• Result from Unintentional Islanding Test

212.1 Vrms

83 ms

0.37 s

12

Sample Test Results (contd.)

• Result from Harmonics Test

• Result from Continuous Output Power Test

(a)

(b)

(a)

(b)

5000

5100

5200

5300

5400

5500

5600

5700

5800

5900

6000

0 10 20 30 40 50 60 70 80 90

Po

wer

[W]

Time [min]

13

Conclusions

• Advancement of power electronics and battery technology will lead to the next generation of plug-in vehicles that are V2G capable

• In this paper, a recently published NREL technical report on interim test procedures for V2G vehicles was discussed

• Some sample test results were shown from a particular V2G-capable vehicle that was tested at NREL

• NREL is continuing to perform these tests on V2G vehicles

• Once testing is expanded to a larger variety of vehicles, these procedures could become the basis for testing standards for V2G applications

14

Acknowledgements

• This work was supported by the U.S. Department of Energy under Contract No. DE-AC36-08GO28308 with the National Renewable Energy Laboratory

• We’d like to thank Xcel Energy for their support in this work

• We also like to thank Peter McNutt and Mike Kuss from NREL for their participation in this project

15

Questions ??

Motor

Controller

Wheel

Wheel

Battery

Battery

Battery

Battery

Battery

Battery

Battery Charger /

Inverter

Programmable

AC Grid Simulator

Emergency

Battery

Disconnect

PLUG-IN VEHICLE WITH V2G CAPABILITY

V2G Control

Computer

Battery Charge/

Discharge ControlVariable

RLC Load Bank

12 VDC

M/G

Modem

Cell Tower