Green Building Perspective

Embed Size (px)

Citation preview

  • 7/30/2019 Green Building Perspective

    1/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 1

    CHAPTER-10

    GREEN BUILDING PERSPECTIVE

  • 7/30/2019 Green Building Perspective

    2/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 2

    GREEN BUILDING PERSPECTIVE

    The Green building movement has gained tremendous momentum during the past 3-4

    years.The concept of green buildings is not as nascent as we think it is. For example,

    our own ancestors worshipped the five elements of nature - Earth as Prithvi, Water as

    Jal, Agni as Energy, Air as Vayu, and Sky as Akash. Green buildings basically

    seek to harness all these natural elements in its design & construction to an optimum

    level so as to have an eco-friendly, low energy & low water consumption building and

    at the same time providing fresh & healthy environment to its occupants. Threats of

    global warming & shrinking natural resources along with rise in power consumption

    has led to acceptance of need to construct all buildings as green buildings.

    A green building is one which encompasses the following important features

    (i) Site selection with full respect to ecology of the area & existingenvironment & use of local materials etc.

    (ii) Minimum consumption of energy by the building(iii) Minimum use of fresh water from external sources(iv) Maximum use of non toxic, recycled & renewable material(v) Highest indoor air quality without affecting the energy consumption(vi) Integrated Building Management System for control & monitoring,

    measurement & verification(vii) Innovation in design & construction technique.

    Green buildings are given ratings by rating agencies based on their performance on

    laid down standard criteria. Some of the popular rating systems are LEED, GRIHA

    etc. Incorporating green design requires an integrated effort on the part of all the team

    members the architect, builder, civil & horticulture engineers, consultants and the

    vendors. Achieving the targeted final rating becomes easier when every member is

    committed to the green design principles. As regards the cost impact in the design of a

    green building, the cost could be slightly higher than a conventional building.However green buildings, on account of their design features, consume less energy

    and less water vis--vis a conventional building. Thus this extra cost gets paid back in

    3-5 years time.

    India, being a fast developing country, is witnessing tremendous growth in

    construction thus putting pressure on both energy & water resources. Therefore it is

    imperative to adopt green construction to minimize impact on the environment and

    natural resources. Today a variety of green building projects are coming up in the

    countryresidential complexes, hospitals, educational institutions, IT parks, airports,

    government buildings and offices etc.

  • 7/30/2019 Green Building Perspective

    3/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 3

    The benefits

    On a broader scale, design & construction of green buildings will benefit the

    community at large with the improvement in environment by reducing GHG

    (greenhouse gas) emissions, improving energy security, and reducing the stress on

    natural resources.

    Green concepts and techniques in the residential sector can help address national

    issues like handling of consumer waste, water efficiency, reduction in fossil fuel use

    in commuting, energy efficiency and conserving natural resources. Most importantly,

    these concepts can enhance occupant health, happiness and wellbeing.

    Some of the benefits of a green design to a building owner, user, and the society as a

    whole are as follows :

    Reduced energy consumption without sacrificing the comfort levels

    Reduced destruction of natural areas, habitats, and biodiversity, and reduced

    soil loss from erosion, etc.

    Reduced air and water pollution (with direct health benefits)

    Reduced water consumption

    Limited waste generation due to recycling and reuseReduced pollution loads

    Increased user productivity

    Enhanced image and marketability

    Works Manual Provisions

    CPWD has also decided that henceforth all CPWD constructions shall be Green. A

    Chapter titled Green Building Norms has been introduced giving the approved

    guidelines regarding Green Buildings in CPWD Works Manual.

    Obtaining certificate from rating agencies for the building being certified as Green

    involves third party inspections / reviews / registration etc. and will involve both cost

    and time. The preliminary estimate should include extra provisions, if any to cover the

    probable cost on certification both internal and by third party if it is decided to obtain

    the green rating certificate.

    For internal certification, CPWD has adopted GRIHA rating system of TERI. The

    responsibility of internal certification indicating whether the specific criterion that

    falls under their respective domain has been achieved or not lie with Senior Architect

    for Architecture related criterion; Superintending Engineer (C) for Civil Engineering

  • 7/30/2019 Green Building Perspective

    4/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 4

    related criterion; Superintending Engineer (E) for Electrical Engineering related

    criterion and Director (Horticulture) / Superintending Engineer (C) for Horticulture

    related criterion. The overall internal green certification for the project shall be done

    by the authority who finalizes and submits the preliminary estimate of the project.

    The authority who finalised the preliminary estimate of the project shall develop

    appropriate methodology of construction as well as planning of the project and shall

    be responsible to include them in contract documents under a new chapter which may

    be named as "Particular Specifications/Methodologies for Green Building".

    The internal green building certification shall be expressed in following manner on

    following documents for the purpose of maintaining the same on permanent basis

    S.No. Satisfied by Standard Document where satisfaction is to be

    certified

    1 Senior Architect Preliminary Drawings / Working Drawings issued for

    the project. A Green Parameter Table shall be provided

    over the Title Block where all criteria pertaining to

    Architecture should be listed and satisfaction should be

    indicated. Reasons for dissatisfaction should be

    explicitly mentioned wherever the criteria are not

    satisfied.

    2 Director (H) / Completion Certificate if the same falls under his own

    SE (C/E) competency. If the Completion Certificate falls under

    as the case may be the competency of the authority other than Director (H)/

    SE (C/E), the said authority should obtain it from

    Director (H) / SE (C/E) before recording the

    Completion Certificate and mention the same in the

    Completion Certificate.

    A Green Parameter Table shall be provided in the

    Completion Certificate where all criteria pertaining to

    Civil / Electrical / Horticulture should be listed and

    satisfaction should be indicated. Reasons for

    dissatisfaction should be explicitly mentioned wherever

    a criterion is not satisfied.

    A copy of the Green Parameter Table of the respective components of the project

    shall be sent to the preliminary estimate framing authority within fifteen days of its

    incorporation in standard works document i.e. preliminary / working drawings in

    respect of Architectural criterion and Completion Certificate in respect of Civil /Electrical / Horticultural criterion for compilation of all components and to issue a

  • 7/30/2019 Green Building Perspective

    5/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 5

    final certification to the client for his record. Whenever a project is executed in

    packages, the internal rating shall be for (1) each package separately, and (2) project

    as a whole.

    EE (C/E) shall facilitate the rating agencies both internal and external (where it is

    decided to have Green Rating and certification from third party agencies) by

    providing documentary evidences as may be required in support thereof. No

    document shall be shared with the external rating agencies directly. Communication

    from the external rating agencies in respect of satisfaction / dissatisfaction of the

    criterion assessed by them should be indicated in Green Parameter Table in the

    Column Remarks indicating reasons for dissatisfaction if points earned are lesser

    than maximum points of the Table as per form attached.

    GRIHA Rating System

    GRIHA (an acronym for Green Rating for Integrated Habitat Assessment) Rating

    System, a tool developed by TERI (The Energy and Resources Institute) evaluates the

    environmental performance of a building holistically over its entire life cycle, thereby

    providing a definitive standard for what constitutes a green building. The rating

    system is based on accepted energy and environmental principles, and seek to strike a

    balance between the established practices and emerging concepts, both national and

    international

    The basic features

    GRIHA rating system has been developed to help design and evaluate new buildings

    (buildings that are still at the inception stages). A building is assessed based on its

    predicted performance over its entire life cycle inception through operation. The

    stages of the life cycle that have been identified for evaluation are the preconstruction,

    building design and construction, and building operation and maintenance stages. The

    issues that get addressed in these stages are as follows

    Pre-construction stage (intra- and inter-site issues)

    Building planning and construction stages (issues of resource conservation and

    reduction in resource demand, resource utilization efficiency, resource

    recovery and reuse, and provisions for occupant health and well being). The

    prime resources that are considered in this section are land, water, energy, air,

    and green cover.

    Building operation and maintenance stage (issues of operation and

    maintenance of building systems and processes, monitoring and recording of

    consumption, and occupant health and well being, and also issues that affect

    the global and local environment).

  • 7/30/2019 Green Building Perspective

    6/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 6

    Scoring points for GRIHA

    GRIHA is a guiding and performance-oriented system where points are earned for

    meeting the design and performance intent of the criteria. Each criterion has a number

    of points assigned to it. It means that a project intending to meet the criterion would

    qualify for the points. Compliances, as specified in the relevant criterion, have to be

    submitted in the prescribed format. The points related to these criteria (specified

    under the relevant sections) are awarded provisionally while certifying and are

    converted to firm points through monitoring, validation, and documents/photographs

    to support the award of point.

    GRIHA has a 100 point system consisting of some core points, which are mandatory

    to be met while the rest are optional points, which can be earned by complying withthe commitment of the criterion for which the point is allocated. The innovation

    points are available over and above the 100 point system. This means that a project

    can hypothetically apply for a maximum of 104 points. But the final scoring shall be

    done out of 100 points. Different levels of certification (one star to five star) are

    awarded based on the number of points earned. The minimum points required for

    certification is 50. Buildings scoring 50 to 60 points, 61 to 70 points, 71 to 80 points,

    and 81 to 90 points shall get one star, two stars, three stars and four stars

    respectively. A building scoring 91 to 100 points will get the maximum rating viz.

    five stars.

    Points scored Rating

    5060 One star

    6170 Two stars

    7180 Three stars

    8190 Four stars

    91100 Five stars

    The details of the points as given in TERI GRIHA Rating system and Proforma

    Green Parameter Table is given in Annexure-I.

    A typical road map to achieve GRIHA 3-Star or 4 Star rating for new buildings is

    given in Annexure-II. Also typical energy saving approaches that can be adopted in

    buildings is given in Annexure-III. Some of the green features that have been

    incorporated in a Platinum rated (LEED rating) residential & commercial project in

    India are listed in Annexure-IV.

  • 7/30/2019 Green Building Perspective

    7/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 7

    ANNEXURE -I

    TERIGRIHA Green Building Rating System

    Synopsis of the criteria for rating

    The criteria have been categorized as follows.

    1 Site Selection and Site planning

    1.1 Conservation and efficient utilization of resource

    ObjectiveTo maximize the conservation and utilization of resources (land, water,

    natural habitat, avi fauna, and energy) conservation and enhance efficiency of the

    systems and operations.

    Criterion 1 Site Selection

    Criterion 2 Preserve and protect the landscape during construction/compensatory

    depository forestation.

    Commitment- Proper timing of construction, preserve top soil and existing vegetation,

    staging and spill prevention and erosion and sedimentation control. Replant, on-site,

    trees in the ratio 1:3 to those removed during construction.

    Criterion 3 Soil conservation (till post-construction).

    Commitment- Proper top soil laying and stabilization of the soil and maintenance of

    adequate fertility of the soil to support vegetative growth.

    Criterion 4Design to include existing site features.

    Commitment- Minimize the disruption of natural ecosystem and design to harness

    maximum benefits of the prevailing micro-climate.

    Criterion 5Reduce hard paving on-site and /or provide shaded hard - paved surfaces.

    Commitment- Minimize storm water run-off from site by reducing hard paving onsite.

    Criterion 6Enhance outdoor lighting system efficiency.

    Commitment- Meet minimum allowable luminous efficacy (as per lamp type) and

    make progressive use of a renewable energy- based lighting system.

    Criterion 7Plan utilities efficiently and optimize on-site circulation efficiency

    Commitment- Minimize road and pedestrian walkway length by appropriate planning

    and provide aggregate corridors for utility lines.

  • 7/30/2019 Green Building Perspective

    8/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 8

    1.2 Health and well being

    ObjectiveTo protect the health of construction workers and prevent pollution.

    Criterion 8 Provide at least, the minimum level of sanitation/safety facilities for

    construction workers.

    Commitment- Ensure cleanliness of workplace with regard to the disposal of waste

    and effluent, provide clean drinking water and latrines and urinals as per applicable

    standard.

    Criterion 9Reduce air pollution during construction.

    Commitment- Ensure proper screening, covering stockpiles, covering bricks and loads

    of dusty materials, wheel-washing facility, and water spraying.

    2 Building planning and construction stage

    Conservation and efficient utilization of resources

    Objective To maximize resource (water, energy, and materials) conservation and

    enhance efficiency of the system and operations.

    2.1 Water

    Criterion 10Reduce landscape water requirement.

    Commitment- Landscape using native species and reduce lawn areas while enhancing

    the irrigation efficiency, reduction in water requirement for landscaping purposes.

    Criterion 11Reduce building water use.

    Commitment- Reduce building water use by applying low-flow fixtures, etc.

    Criterion 12Efficient water use during construction.

    Commitment- Use materials such as pre-mixed concrete for preventing loss during

    mixing. Use recycled treated water and control the waste of curing water.

  • 7/30/2019 Green Building Perspective

    9/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 9

    2.2 Energy: end use

    Criterion 13 Optimize building design to reduce the conventional energy demand.

    Commitment- Plan appropriately to reflect climate responsiveness, adopt an adequate

    comfort range, less air-conditioned areas, daylighting, avoid over-design of the

    lighting and air-conditioning systems.

    Criterion 14 Optimize the energy performance of the building within specified

    comfort limits.

    Commitment- Ensure that energy consumption in building under a specified category

    is 10%40% less than that benchmarked through a simulation exercise.

    2.3 Energy: embodied and construction

    Criterion 15 Utilization of fly ash in the building structure.

    Commitment- Use of fly ash for RCC (reinforced cement concrete) structures with

    infill walls and load bearing structures, mortar, and binders.

    Criterion 16Reduce volume, weight, and time of construction by adopting an efficient

    technology (e.g. pre-cast systems, ready-mix concrete, etc.).

    Commitment- Replace a part of the energy-intensive materials with less energy

    intensive materials and/or utilize regionally available materials, which use low

    energy/ energy-efficient technologies.

    Criterion 17Use low-energy material in the interiors.

    Commitment- Minimum 70% in each of the three categories of interiors (internal

    partitions, panelling/false ceiling/interior wood finishes/ in-built furnituredoor/window frames, flooring) from low-energy materials/finishes to minimize the

    usage of wood.

    2.4 Energy: renewable

    Criterion 18Renewable energy utilization.

    Commitment- Meet energy requirements for a minimum of 10% of the internal

    lighting load (for general lighting) or its equivalent from renewable energy sources

  • 7/30/2019 Green Building Perspective

    10/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 10

    (solar, wind, biomass, fuel cells, etc). Energy requirements will be calculated based

    on realistic assumptions which will be subject to verification during appraisal.

    Criterion 19Renewable energy - based hot- water system.

    Commitment- Meet 70% or more of the annual energy required for heating water

    through renewable energy based water-heating systems.

    2.5 Recycle, recharge, and reuse of water

    ObjectiveTo promote the recycle and reuse of water.

    Criterion 20 Wastewater treatment

    Commitment- Provide necessary treatment of water for achieving the desired

    concentration of effluents.

    Criterion 21 Water recycle and reuse (including rainwater).

    Commitment- Provide wastewater treatment on-site for achieving prescribed

    concentration, rainwater harvesting, reuse of treated waste water and rainwater for

    meeting the buildings water and irrigation demand.

    2.6 Waste management

    ObjectiveTo minimize waste generation, streamline waste segregation, storage, and

    disposal, and promote resource recovery from waste.

    Criterion 22Reduction in waste during construction.

    Commitment- Ensure maximum resource recovery and safe disposal of wastes

    generated during construction and reduce the burden on landfill.

    Criterion 23Efficient waste segregation.

    Commitment- Use different coloured bins for collecting different categories of waste

    from the building.

    Criterion 24 Storage and disposal of waste.

    Commitment- Allocate separate space for the collected waste before transferring it to

    the recycling/disposal stations.

  • 7/30/2019 Green Building Perspective

    11/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 11

    Criterion 25Resource recovery from waste.

    Commitment- Employ resource recovery systems for biodegradable waste as per the

    Solid Waste Management and handling Rules, 2000 of the MoEF. Make arrangementsfor recycling of waste through local dealers.

    2.7 Health and well-being

    ObjectiveTo ensure healthy indoor air quality, water quality, and noise levels, and

    reduce the global warming potential.

    Criterion 26 Use of low-VOC (volatile organic compounds) paints/ adhesives /

    sealants.

    Commitment- Use only low VOC paints in the interior of the building. Use water

    based rather than solvent based sealants and adhesives.

    Criterion 27Minimize ozonedepleting substances

    Commitment- Employ 100% zero ODP (ozone depletion potential) insulation; HCFC

    (hydro-chlorofluorocarbon)/ and CFC (chlorofluorocarbon) free HVAC and

    refrigeration equipments and/Halon-free fire suppression and fire extinguishing

    systems.

    Criterion 28 Ensure water quality.

    Commitment- Ensure groundwater and municipal water meet the water quality norms

    as prescribed in the Indian Standards for various applications (Indian Standards for

    drinking [IS 10500-1991], irrigation applications [IS 11624-1986]. In case the water

    quality cannot be ensured, provide necessary treatment of raw water for achieving the

    desired concentration for various applications.

    Criterion 29Acceptable outdoor and indoor noise levels.

    Commitment- Ensure outdoor noise level conforms to the Central Pollution Control

    BoardEnvironmental StandardsNoise (ambient standards) and indoor noise level

    conforms to the National Building Code of India, 2005, Bureau of Indian Standards,

    Part 8Building Services; Section 4Acoustics, sound insulation, and noise control.

    Criterion 30 Tobacco and smoke control.

    Commitment- Zero exposure to tobacco smoke for non-smokers and exclusive

    ventilation for smoking rooms.

  • 7/30/2019 Green Building Perspective

    12/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 12

    Criterion 31 Provide the minimum level of accessibility for persons with disabilities.

    Commitment- To ensure accessibility and usability of the building and its facilities by

    employees, visitors, and clients with disabilities.

    3 Building operation and maintenance

    Objective Validate and maintain green performance levels/adopt and propagate

    green practices and concepts.

    Criterion 32Energy audit and validation.

    Commitment- Energy audit report to be prepared by approved auditors of the Bureau

    of Energy Efficiency, Government of India.

    Criterion33Building operation and maintenance.

    Commitment- Validate and maintain 'green' performance levels/adopt and propogate

    green practices and concepts. Ensure the inclusion of a specific clause in the contract

    document for the commissioning of all electrical and mechanical systems to be

    maintained by the owner, supplier, or operator. Provide a core facility/service

    management group, if applicable, which will be responsible for the operation and

    maintenance of the building and the electrical and mechanical systems after the

    commissioning. Owner/builder/occupants/service or facility management group to

    prepare a fully documented operations and maintenance manual, CD, multimedia or

    an information brochure listing the best practices/dos and donts/maintenance

    requirements for the building and the electrical and mechanical systems along with

    the names and addresses of the manufacturers/suppliers of the respective system.

    Criterion 34Innovation points.

    Commitment- Four innovation points are available under the rating system for

    adopting criteria which enhance the green intent of a project, and the applicant can

    apply for the bonus points. Some of the probable points, not restricted to the ones

    enumerated below, could be

    1. Alternative transportation

    2. Environmental education

    3. Company policy on green supply chain

    4. Lifecycle cost analysis

    5. Enhanced accessibility for physically/mentally challenged.

    6. Any other criteria proposed by the client.

  • 7/30/2019 Green Building Perspective

    13/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 13

    Evaluation procedure

    List of criteria Points Remarks Unit of

    responsible for

    the criterionCriteria 1: Site Selection 1 Partly mandatory Architecture

    Criteria 2: Preserve and protect

    landscape during

    construction/compensatory depository

    forestation

    5 Partly mandatory 3 by Architecture,

    2 by Horticulture

    Criteria 3: Soil conservation (post

    construction)4 Civil

    Criteria 4: Design to include existing site

    features2 Mandatory Architecture

    Criteria 5: Reduce hard paving on site 2 Partly mandatory Architecture

    Criteria 6: Enhance outdoor lightingsystem efficiency

    3 Electrical

    Criteria 7: Plan utilities efficiently and

    optimize on site circulation

    efficiency

    3 Architecture

    Criteria 8: Provide, at least, minimum

    level of sanitation/safety facilities for

    construction workers

    2 Mandatory Civil

    Criteria 9: Reduce air pollution during

    construction

    2 Mandatory Civil

    Criteria 10: Reduce landscape water

    requirement3 Horticulture

    Criteria 11: Reduce building water use 2 Civil

    Criteria 12: Efficient water use during

    construction1 Civil

    Criteria 13: Optimize building design to

    reduce conventional energy

    demand

    6 Mandatory Architecture

    Criteria 14: Optimize energy

    performance of building within

    specified comfort

    12 Electrical

    Criteria 15: Utilization of flyash in

    building structure

    6 Civil

    Criteria 16: Reduce volume, weight and

    time of construction by adopting

    efficient technology (e.g. pre-cast

    systems, ready-mix concrete, etc.)

    4 Civil

    Criteria 17: Use low-energy material in

    interiors4 Architecture

    Criteria 18: Renewable energy

    utilization5 Electrical

  • 7/30/2019 Green Building Perspective

    14/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 14

    Criteria 19: Renewable energy based

    hot-water system3 Electrical

    Criteria 20: Waste water treatment 2 CivilCriteria 21: Water recycle and reuse

    (including rainwater)5 Civil

    Criteria 22: Reduction in waste during

    construction2 Civil

    Criteria 23: Efficient waste segregation 2 Civil

    Criteria 24: Storage and disposal of

    waste2 Civil

    Criteria 25: Resource recovery fromwaste

    2 Civil

    Criteria 26: Use of low - VOC paints/

    adhesives/ sealants.4 Civil

    Criteria 27: Minimize ozone depleting

    substances3 Mandatory Electrical

    Criteria 28: Ensure water quality 2 Mandatory Civil

    Criteria 29: Acceptable outdoor and

    indoor noise levels2 Architecture

    Criteria 30: Tobacco and smoke control 1 Architecture

    Criteria 31: Universal Accessibility1

    Architecture

    Criteria 32: Energy audit and validation Mandatory Electrical

    Criteria 33: Operations and maintenance

    protocol for electrical and mechanical

    equipment

    2 Mandatory Electrical

    Total Score 100 Architecture,

    Civil, Electrical,

    Horticulture

    Criteria 34: Innovation (Beyond 100) 4 Architecture,

    Civil, Electrical,Horticulture

    Total score 104

  • 7/30/2019 Green Building Perspective

    15/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 15

    GREEN PARAMETER TABLE

    PACKAGE

    PROJECT

    Nomenclature of

    criteria

    Maximum

    Points

    Points

    earned

    Remarks indicating reasons for

    dissatisfaction if points earned are

    lesser than maximum points

    Criteria 1

    Criteria 2

    .

    Criteria 34

    Total score 104

  • 7/30/2019 Green Building Perspective

    16/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 16

    ANNEXURE-II

    Road Map to achieve GRIHA 3-Star or 4 Star rating for new buildings

    A list of various actions is suggested below as a possible strategy to achieve a

    minimum of 3 star rating. Suggestions in brackets followed by a * shall enhance the

    score further and enable a 4 star rating. The set of actions suggested are however only

    a pointer in the direction of achieving a high star rating but not as a comprehensive

    and exhaustive checklist for achieving a high rating.

    Site Planning

    Select appropriate site as per GRIHA guidelines

    Ensure sedimentation /erosion control/save trees (If they exist) / plant more

    trees by appropriate planning of the construction work.

    Design the building as per site conditions

    Control Air pollution at all stages of construction

    Ensure safety and health of construction workers

    Control hard paving/run off/manage utilities efficiently

    Use energy efficient outdoor lighting (use Renewable Energy e.g. Solar based

    lighting)*

    Use native trees and shrubs for landscaping to reduce landscape water demand

    over GRIHA benchmark by 40% (reduce by 50%)*

    Energy/ Water/ Waste

    Reduce 25% water demand over GRIHA benchmarks (developed based on

    National Building Code) (by 50%)*

    Save water in construction

    Comply with the mandatory requirements within the ECBC (Energy

    Conservation Building Code)

    Meet prescriptive shading norms of ECBC, provide daylight, avoid over

    design of artificial lighting

    Reduce energy performance index over GRIHA benchmark by 10% (by

    30%)*

    Provide 1% equivalent connected load of lighting and HVAC through

    Renewable Energy power (meet 10% lighting consumption through

    Renewable Energy e.g. Solar based power)*

    Use fly ash based products in minimum two of the following three areas:

    (structure/ walling / finishing)

    Recycle wastewater and reuse 25% of treated wastewater (IF wastewater

    quantity is higher than 10kLday)

    Segregate and store waste appropriately

  • 7/30/2019 Green Building Perspective

    17/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 17

    Indoor environmental quality

    Minimize the usage of Ozone depleting products in the building structure and

    systems.

    Use low VOC (Volatile Organic Compound) paints

    Ensure compliance of water quality with relevant BIS standards

    Restrict Smoking in the building

    Provide Universal accessibility

  • 7/30/2019 Green Building Perspective

    18/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 18

    ANNEXURE-III

    Typical Energy Saving Approach in Buildings:

    Orientation:This is the first step to achieve energy efficiency, following measures can be adopted:

    Minimize exposure on the south and west

    Use simulation tools and techniques which can help in designing the

    orientation to minimize heat ingress and enhance energy efficiency

    Building EnvelopeSelect high performance glazing with low U-value, low Shading Coefficient

    and high VLT (Visual Light Transmittance).Insulate the wall. The options for insulation materials can be Extruded

    polystyrene, Expanded polystyrene (thermocol), Glass wool etc.,

    Brick wall with air cavity can also significantly reduce the heat ingress.

    Hollow blocks, Fly ash bricks and Autoclaved Aerated Concrete (AAC)

    Blocks are also good insulators.

    The heat ingress through the roof can be as high as 12-15%. Insulating the

    roof can substantially reduce the heat ingress.

    Consider shading devices for window openings.

    Equipment & systemsSelect chillers with high Coefficient of Performance (CoP).

    Install Variable Frequency Drives (VFD) for supply & return air fans and

    pumps.

    Select high efficiency cooling towers.

    Use high efficiency motors, transformers and pumps.

    Install Heat recovery wheels and economizers

    Consider night purging with ambient air to flush out the heat trapped within

    the building during the day

    Adopt Controls & Building Management Systems for effective control

    Engage a Commissioning Authority to ensure that savings are realized once

    the building becomes operational

    Lighting:Design in such a way that the building gets maximum day lighting.

    Overall lighting power density can be designed as less as 1.0 W/sq.ft.

    Use daylight-cum-dimmer controls

    Install occupancy sensors

    Select energy efficient luminaires like CFL, T-5, LED, etc.,

  • 7/30/2019 Green Building Perspective

    19/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    BSNL ,India For Internal Circulation of BSNL only Page 19

    ANNEXURE-IV

    Some of the Green features incorporated in a Platinum rated (LEED rating)

    residential project are

    Energy Saving Features:

    The building envelope is insulated with the use of fly ash blocks for walls,

    under deck roof insulation and double glazed low-E glass with low U and

    SHGC values for all air conditioned areas

    High efficiency HVAC equipment with heat recovery wheel has been

    provided

    Bureau of Energy Efficiency (BEE) Star rated lamps and motion sensors for

    lighting have also been provided3.84 kWp Hybrid Solar PV system which generates 10 kWh / day and Solar

    Water Heater of 300 LPD (Litres Per Day) capacity has been installed

    Day Lighting:

    Sufficient windows and skylight areas have been provided to achieve the

    daylight factor of 2% for 80% of the regularly occupied spaces

    Light pipes have been used to achieve daylight in the basement areas

    Water Saving Features:A sewage treatment plant of 5,000 liters/day capacity to treat all grey water

    generated within the site has been provided. The treated grey water is reused

    for flushing and landscaping

    Low flow water fixtures (showers, faucets and flush systems) have been

    provided

    Materials:

    Bamboo, which is a rapidly renewable material has been extensively used in

    the flooring

    Wood salvaged from old buildings has been used for doors and windows

  • 7/30/2019 Green Building Perspective

    20/20

    E5- E6 Civil Part-II Rev Date: 15-03-11

    Salient Green features incorporated in one Platinum rated (LEED rating)

    commercial building project in India Office space with a built-up area of

    37,362 sq.ft (3,470 sq.mtrs) are

    The whole building is 100% solar air-conditioned through the Vapour

    Absorption System

    In-situ wind turbine of 5 kW capacity

    Rs 40 lakhs worth of old furniture was re-processed & re-used in the building

    70% of energy savings over ASHRAE 90.1-2004 standard

    Zero water discharge site

    More than 75% of the spaces with good daylight