Granville Street Bridge Preliminary Assessment report

Embed Size (px)

Citation preview

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    1/63

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    2/63

    DRAFT

    Revision Record Sheet

    Rev.No

    Date Changes ImplementedOriginated

    ByVerified

    ByApproved

    By

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    3/63

    Amendments Record Sheet

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    4/63

    Executive Summary

    This preliminary assessment report investigates the condition and alternatives for

    rehabilitating the expansion bearings in the steel truss spans of the Granville Bridge. The

    feasibility and costing of alternatives to recondition the expansion bearings are examined.

    There are a total of fourteen steel roller type bearings in the steel truss spans of the

    Granville Bridge. In general, the bearings have been well maintained and are in goodworking condition, but the potential for PCB spills and contamination of the environment has

    become a concern. The bearings included an oil bath, using Aroclor 1248 which is a

    synthetic oil product comprised of Poly-Chlorinated Biphenyls (PCBs), to clean and

    lubricate the steel rollers contained inside the bearings. To mitigate potential contamination,

    the oil from the bearings has been drained and transferred to a hazardous waste facility for

    disposal.

    For all of the rehabilitation options considered, the cleaning and encapsulation of the pier

    caps has been included as a measure to reduce the potential for PCB contamination. Any

    options that retain the bearings will include decontamination of the steel portions to a

    predetermined level. Materials used or removed from the site that are contaminated with

    PCBs will be disposed of at a hazardous materials disposal facility.

    Key options considered include the reduction of PCB contaminated materials at the bridge

    site, through decontamination or material removal. The continued use of lubricating

    materials that would be constantly present in the bearings is not considered as a long term

    option.

    The alternatives assessed for rehabilitating the expansion bearings include: maintaining the

    existing bearings without an oil bath; replacing all the existing bearings; and replacing the

    smaller bearings while reconfiguring the larger expansion bearings as fixed bearings instead

    of replacing them.

    The existing bearings may be retained. However, it may not be possible to completely clean

    the interior of the bearings such that they can be considered free of contamination. In this

    case, the future maintenances costs will need to account for handling the bearings as

    contaminated by PCBs. s.13(1); s.17(1)(c), (d), (e) & (f) and s.21(1)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    5/63

    All of the bearings can be replaced with conventional expansion bearings to remove allcontaminated steel components from the bridge. However, the four largest bearings will be

    technically very difficult and very costly to remove and replace with new bearings, in particular,

    the two largest bearings at Pier M7. s.13(1); s.17(1)(c), (d), (e) & (f) and s.21(1)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    6/63

    Table of Contents

    1 Introduction...........................................................................................................................1

    1.1 Description of Bridge Expansion Bearings....................................................................11.2 Current Condition at the Bridge Expansion Bearings....................................................4

    1.2.1 Expansion Bearings...........................................................................................4

    1.2.2 Surfaces on the Pier Tops.................................................................................51.3 Bearing Decontamination Trial......................................................................................5

    2 PCB Contamination Mitigation..............................................................................................7

    2.1 Decontamination of Existing Bearings...........................................................................72.1.1 Flushing Existing Bearings................................................................................72.1.2 Removing Bearing Boxes & Flushing Existing Bearings ...................................82.1.3 Removing Existing Bearings to Clean Off-site...................................................8

    2.2 Decontamination of Pier Caps.......................................................................................83 Bearing Revitalization.........................................................................................................10

    3.1 Recondition Existing Bearings.....................................................................................103.1.1 Periodic Lubrication.........................................................................................103.1.2 New Oil Bath....................................................................................................11

    3.2 Structurally Alter Bearings...........................................................................................113.2.1 Typical Bearing Replacement..........................................................................113.2.2 Bearing Options at Piers M2 and M7...............................................................13

    4 Load Rating Analysis ..........................................................................................................18

    4.1 Computer Modeling.....................................................................................................184.2 Loading........................................................................................................................18

    4.2.1 Dead Load.......................................................................................................184.2.2 Live Load.........................................................................................................194.2.3 Wind Load.......................................................................................................204.2.4 Temperature Effects........................................................................................20

    4.2.5 Earthquake Load.............................................................................................214.3 Load Combinations.....................................................................................................224.4 Member Demands.......................................................................................................224.5 Member Capacities .....................................................................................................224.6 Pier Demands..............................................................................................................234.7 Comparison Summary.................................................................................................23

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    7/63

    6 Recommendations..............................................................................................................27

    6.1 Bearing Revitalization Programme..............................................................................276.2 Staged Revitalization...................................................................................................27

    6.2.1 Engineering .....................................................................................................286.2.2 Stage 1............................................................................................................286.2.3 Stage 2............................................................................................................286.2.4 Stage 3............................................................................................................28

    Appendix A..................................................................................................................................29

    Appendix B..................................................................................................................................33

    Appendix C .................................................................................................................................34

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    8/63

    1 Introduction

    This preliminary assessment report investigates alternatives for rehabilitating the

    expansion bearings for the steel truss spans of the Granville Bridge. To provide a

    comprehensive assessment: the existing condition, environmental concerns, bearing

    alternatives, load rating of the steel trusses, staged construction and cost estimates

    are considered and discussed.

    1.1 Description of Bridge Expansion Bearings

    The Granville Bridge was constructed in 1954. The bridge has seven spans, from

    Piers M1 to M8, constructed of structural steel (see Figure 1). These structural steel

    spans consist of an arrangement of steel trusses with appropriate placement of fixed

    bearings, expansion bearings and internal pins to provide a statically determinate

    system for expansion and vertical load.

    s.15(1)(l) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    9/63

    s.15(1)(l) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    10/63

    The expansion bearings were originally designed to be kept in an oil bath, as showninFigure 2. The oil bath served to both lubricate the internal steel components of the

    bearing and protect them from corrosion and contaminates that may get inside the

    bearing box.

    Expansion bearings of this type are susceptible to water entering the bearing box

    through leaks or condensation. Originally, the oil bath used whale oil that, because

    of its relatively lower density, allowed water entering the bearing box to sink to the

    bottom. As water continued to enter the bearing box the oil could eventually be

    displaced and overflow from the box. To avoid this condition, the lubricating oil used

    in the expansion bearings was substituted with Aroclor 1248 (a synthetic oil product

    comprised of Poly-Chlorinated Biphenyls, or PCBs) in the early 1960s, selected for

    its unique quality of being denser than water. By using this dense lubricating oil, any

    water entering the bearing box would float on top of the oil bath and be spotted

    during regular inspections to be removed.s.15(1)(l) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    11/63

    1.2 Current Condition at the Bridge Expansion BearingsIn general, the expansion bearings are well-maintained and in good working

    condition.

    1.2.1 Expansion Bearings

    The primary issue concerning the expansion bearings was the consequence of a

    potential oil spill from leaking bearings. When Aroclor 1248 was selected for use,

    sometime during the early 1960s, PCBs were not recognized as a hazardous

    material and government environmental regulations concerning PCBs did not exist.

    PCBs are now known as a hazardous material and the disposal of PCBs and PCB-

    contaminated materials are regulated by environmental legislation.

    s.13(1); s.15(1)(l) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    12/63

    To mitigate the environmental damage potential and attempt to satisfy environmentalregulations, the PCB-contaminated oil from all expansion bearings was drained in

    2006. The cost of draining and disposing of the PCB-contaminated oil was on

    average $5,000 per bearing.

    1.3 Bearing Decontamination Trial

    A pilot project to develop a protocol for the removal of the PCB-contaminated oil at

    the expansion bearings and subsequent decontamination of the bearings was

    s.13(1); s.15(1)(l) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    13/63

    The West expansion bearing at Pier M8 was selected for the pilot project. Theprotocol, methods, testing and results are contained in the Envirochem Services Inc.

    report Pilot Project Decontamination of the Granville Bridge Bearing Boxes

    Containing PCB dated J une 2006 (draft). In summary, the decontamination process

    included:

    rinsing the bearing box with kerosene to dissolve residual oil after draining,

    flushing the bearing box and bearing components three times with about 20 litresof kerosene each time, which is about 10% of the original volume,

    filling the bearing box with kerosene to soak,

    draining the kerosene from the bearing box,

    filling the bearing box again with kerosene,

    draining the kerosene, and

    wiping down the accessible internal surfaces with absorbent pads.

    The test results for residual PCB contamination, for the Pilot Project, indicated that

    the interior surfaces of the M8 bearing could not be decontaminated sufficiently to

    reduce the PCB concentrations to acceptable levels, but were dramatically reduced

    from the untouched state. The PCB levels were reduced to 2800 mg/kg PCB in the

    kerosene solvent removed in the final rinse. It has been learned that, proposedregulations will require the PCB level to be below 500 mg/kg by 2014. Further

    flushing is to be undertaken at the Pilot Project bearing in an attempt to achieve the

    proposed regulation level.

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    14/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    15/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    16/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    17/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    18/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    19/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    20/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    21/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    22/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    23/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    24/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    25/63

    4 Load Rating AnalysisThis section is a summary of the load rating analysis of Granville Bridge to date. It is

    a detailed assessment of the effects of the modified bearing configuration on the live

    load distribution in the steel truss bridge spans, compared to that of the existing

    structure. In addition, wind, temperature, and seismic loads are also considered.

    The assessment accounts for the seismic rehabilitation of the steel truss spans that

    was completed in 1994, but does not account for any potential deterioration of thestructural elements.

    Assessment of the steel bridge truss components was carried out using CAN/CSA-

    S6-00, Canadian Highway Bridge Design Code (S6-00) design loads and capacities.

    The bridge floor system (i.e., deck slabs, stringers, floor beams, etc.) is not affected

    by the proposed bearing modifications and therefore was not included in the

    assessment. The substructure is assessed by comparison of demands in thecomponents of the piers for the two cases of the M2 and M7 bearings being fixed or

    in the present condition.

    4.1 Computer Modeling

    The computer analysis model originally developed for the 1992 seismic rehabilitation

    design was used in this analysis. There have been no modifications to the structure

    since that time that would warrant modifications to the computer model.s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    26/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    27/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    28/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    29/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    30/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    31/63

    5 ConclusionsIn general, the steel roller expansion bearings have been well maintained and are in

    good working condition. The steps that the City of Vancouver has taken to safely

    drain and dispose of the PCB contaminated oil from the expansion bearings has

    greatly mitigated potential environmental damage due to leaks from the bearing

    boxes.

    Alternatives that clean and retain the existing roller bearings in service have the least

    present costs. However, these options have long-term maintenance costs

    associated with handling the bearing components as items contaminated with

    hazardous materials. Also, it may not be possible to get the PCB level to an

    acceptable level under the regulations.s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    32/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    33/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    34/63

    6 Recommendationss.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    35/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

    s. ; s. ; s. c , an s.

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    36/63

    s. ; s. ; s. c , an s.

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    37/63

    s. ; s. ; s. c , an s.

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    38/63

    s. ; s. ; s. c , an s.

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    39/63

    s. ; s. ; s. c , an s.

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    40/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    41/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    42/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    43/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    44/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    45/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    46/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    47/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    48/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    49/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    50/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    51/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    52/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    53/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    54/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    55/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    56/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    57/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    58/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    59/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    60/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    61/63

    s. ; s. ; s. c , an s.

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    62/63

    s.13(1); s.15(1)(l); s.17(1)(c), (d) & (f) and s.19(1)(b)

  • 7/28/2019 Granville Street Bridge Preliminary Assessment report

    63/63