Upload
lexuyen
View
218
Download
4
Embed Size (px)
Citation preview
GOVERNMENT OF NEPAL DEPARTMENT OF HYDROLOGY & METEOROLOGY
COMMUNITY BASED FLOOD AND GLACIER LAKE OUTBURST RISK REDUCTION PROJECT (CFGORRP)
BABARMAHAL, KATHMANDU
Submitted by:
Cegelec Engineering Pvt. Ltd.
Buddha Nagar-P.O. Box. No. 13138-Kathmandu
Email:[email protected]
(Tell)+977 4780811
Final Report to
Validation of Detail Design
Report to Sediment, Flood
Proofing Drainage System
under Component II of the
CFGORRP
July 2014
4 Terai districts ( Mahottari, Siraha, Saptari and Udayapur)
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
i | P a g e
Table of Contents List of Table ........................................................................................................................................ iii
List of Figure ....................................................................................................................................... iii
1. Introduction .......................................................................................................................... 1
1.1 Background ................................................................................................................................... 1
1.2 Objectives ..................................................................................................................................... 2
1.3 Scope of the work ......................................................................................................................... 2
2. Methodology ......................................................................................................................... 3
2.1 Preparation of Checklists, Questionnaires and Formats ................................................................ 3
2.2 Field Work .................................................................................................................................... 4
2.3VDRMC Meetings ......................................................................................................................... 4
3. Field Verification of ETW, FPDS and EC ......................................................................... 6
3.1 Verification and Prioritization of ETW and Sanitation ................................................................. 6
3.1.1 Siraha District ........................................................................................................................ 6
3.1.2 Saptari District ....................................................................................................................... 8
3.1.3 Udayapur District ................................................................................................................... 9
3.1.4 Mahotari District .................................................................................................................. 10
3.2Verification of Rehabilitation of Flood Proofing Drainage System (FPDS) ............................... 10
3.2.1Siraha District ....................................................................................................................... 12
3.2.2 Saptari District ..................................................................................................................... 13
3.2.3 Udayapur District ................................................................................................................. 14
3.2.4Mahottari District .................................................................................................................. 15
3.3Verification of Evacuation Centre and Location.......................................................................... 15
4. Sediment Control ............................................................................................................... 16
4.1Structural Measures for watershed Management ......................................................................... 16
4.1.1 Gagan River ......................................................................................................................... 16
4.1.2 Khando River ....................................................................................................................... 19
4.1.3 Hadiya and Kong River ........................................................................................................ 21
4.1.4Ratu River ............................................................................................................................. 24
5. Cost Estimate of Prioritized Embankment & Bio-engineering ..................................... 29
5.1 Unit Rate ..................................................................................................................................... 29
5.2 Cost of Prioritized hot spot section for first phase implementation ............................................ 29
6. Non-structural Measures ................................................................................................... 31
6.1 Bioengineering ............................................................................................................................ 31
7. Photographs: ...................................................................................................................... 34
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
ii | P a g e
Appendix ........................................................................................................................................... 37
Appendix 1: Elevated Tube well, West Water Drain around ETW in study report and Field
Verification ................................................................................................................................... 38
Appendix 2: Rehabilitation of Flood Proofing Drainage system (FPDS) along Access Road in
study report and Field Verification ............................................................................................... 39
Appendix 3: Evacuation centers (EC) proposed in study report and Field Verification ............... 40
Appendix 4: Structural Measure: Embankments Proposed in study report and Field Verification
...................................................................................................................................................... 41
Appendix 5: Structural Measure: Spur Proposed in study report and Field Verification ............. 42
Appendix 6: Cost Estimate of River embankment, Spur and Bioengineering in study report and
Field Verification .......................................................................................................................... 43
Appendix 7: Cost of Bio-engineering ........................................................................................... 44
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
iii | P a g e
List of Table Table 1: Study VDCs, River Basin and VDRMC meeting date and field verification date ................................... 5
Table 2: Field Verified Tube well location and west water drain around Tube Well in Siraha .............................. 7
Table 3: Field Verified Tube well location and west water drain around Tube Well in Saptari ............................. 8
Table 4: Field Verified Tube well location and west water drain around Tube Well in Udayapur ........................ 9
Table 5: Field Verified Tube well location and west water Drain around Tube Well in Mahotari ...................... 10
Table 6: Rehabilitation of FPDS verified along the access roads in Tulsipur& PipraPra Pi VDCs ..................... 12
Table 7: Rehabilitation of FPDS verified along the access roads in Pakari & Dighawa VDCs ........................... 13
Table 8: Rehabilitation of FPDS verified along the access roads in Hadiya & Jogidaha VDCs .......................... 14
Table 9: Rehabilitation of FPDS verified along the access roads in Nahini & Sarpallo VDCs ........................... 15
Table 10: Proposed EC site location and Field verified Evacuation Centre in districts ....................................... 16
Table 11: Field verified length and location for earthen embankment in Gagan river ......................................... 17
Table 12: Prioritized hotspot for construction of earthen embankment & Bio-engineering in Gagan River ........ 18
Table 13: Field verified length and location for earthen embankment in Khando River ...................................... 19 Table 14: Table 14: Prioritized hotspot for construction of earthen embankment & Bio-engineering in Khando
River ............................................................................................................................................................ 20
Table 15: Field verified length for earthen embankment and location in Kong and Hadiya river ........................ 22 Table 16: Prioritized hotspot for construction of earthen embankment & Bio-engineering in Kong & Hadiya
River ............................................................................................................................................................ 23
Table 17: Field verified length and location of Gabion Spur in Ratu River ......................................................... 26 Table 18: Field Verified length, location for earthen embankment in Ratu and Ankushi River in Sarpallo VDC
..................................................................................................................................................................... 27 Table 19: Field Verified length, location for earthen embankment in Ratu and Ankushi River in Sarpallo VDC
..................................................................................................................................................................... 28
Table 20: Summary of embankment cost including Bio-engineering study period cost, Field Verified cost ....... 29
Table 21: Field verified list of Plants, species with their use for bioengineering ................................................. 31
List of Figure Figure 1: Verification of location of ETW in Pakari and ETW drain length measured in Nahini VDC ............... 4
Figure 2: VDRMC meeting in Mahottari, Sirah, & Udayapur ............................................................................... 5
Figure 3: Existing drain in Jogidaha and Nahini Mahottari ................................................................................ 12
Figure 5: Location of Earthen Embankment in Gagan River ............................................................................... 18
Figure 6: Sediment deposition and Bank cutting in Khando River....................................................................... 19
Figure 8: Proposed embankment and existing river training work in Kong River ............................................... 21
Figure 9: Location of Earthen Embankment in Kong River ................................................................................. 23
Figure 10: Location of Proposed Embankment in Hadiya River ......................................................................... 24
Figure 11: Proposed location of Spur and embankment in Ratu River ................................................................ 25
Figure 12: Ratu River Left bank cutting about 3+000 area ................................................................................. 25
Figure 13: Locations of Proposed Spur and Embankment in Ratu River in Mahotari ......................................... 26
Figure 14: Ratu river approaching towards farm land and bank cutting ............................................................ 27
Figure 15: Proposed embankment site in Ankusi & Jangahariver U/S of Bajharang chowk ............................... 27
Figure 16: Locations of Earthen Embankment in Ankush and Jangaha in Sarpolla, Mahatari ........................... 28
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
1 | P a g e
1. Introduction
1.1 Background
Community Based Flood and Glacial Lake Outburst Risk Reduction Project (CFGORRP) is a joint
program undertaking of the Government of Nepal (GoN), Global Environment Facility (GEF) and
the United Nations Development Programee (UNDP). The project is being implemented by the
Department of Hydrology and Meteorology (DHM) under the Ministry of Science, Technology
and Environment (MoSTE) as the lead Implementing Agency. The project has two components:
component I focuses on the GLOF risk reduction from Imja Lake and the Component II is about
the flood risk management in four Terai districts through structural and non-structural measures,
preparedness activities, capacity building etc.
CFGORRP under component II has an objective to reduce human and material losses from
recurrent flooding events in four flood prone districts of Terai and will have increased adaptive
capacity of local communities in eight study VDCs through locally appropriate structural and non–
structural measures, a sediment control programme, river bank, and slope stabilization and the
implementation of CBEWS.
The project covered watersheds (Ratu, Khando, Gagan, Hadiya/Kong) are originated from Churia
hills. The river channels originated from Churia hills in the Terai are also unstable leading to
prolonged inundation, damage to river banks causing bank erosion and sediment deposits in the
farmlands. Due to concentrated rainfall during monsoon, fragile/rugged and unstable land natures
of Churia region, Churia originating rivers are responsible for intensive soil erosion, landslides,
flash floods, and ultimately massive sedimentation in Terai. The sediments deposition on flat lands
blocks the waterways which results several meandering of the river. Many people are displaced,
and hundreds of hectares of lands are wasted. The selected VDCs of the four districts (Mahottari,
Saptari, Siraha, and Udayapur) lie in the Terai Region (low lying flat zone) and being affected
every year by flood and sediment deposition in the fertile land resulting in to loss of property, land,
and human lives.
The Community Based Flood and Glacial Lake Outburst Risk Reduction Project (CFGORRP) has
recently received the Final Report of two studies from the respective service providers. The report
has highlighted need of project related various activities (i.e. slope stabilization, watershed
management, elevated tube wells and flood proofing drainage systems) in the project area.
Technical design, dimensions, location, quantity and cost estimates of these components as well
as project prioritization based on vulnerability assessment are the main theme of the studies.
However, their validation is important in the final decision making process because validation
ensures that the dimensions, and locations of the project components are properly checked.
This is the final report prepared and submitted to CFGORRP in accordance with the contract
between CFGORRP/DHM (hereinafter referred as Client) and Cegelec Engineering Pvt. Ltd
(hereafter referred as consultant) to carry out the validation and verification of Detail Design Study
related to (i) Sediment Control and Stabilization of Hazard–prone Slope & River Banks through
Structural and Non-Structural Mechanism and (ii) Flood Proofing of Water and Sanitation Systems
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
2 | P a g e
in Sarpallo and Nainhi in Ratu Watershed (Mahottari), Tulsipur and Pipra Pra Pi in Gagan
Watershed (Siraha), Dighawa and Pakari in Khando Watershed (Saptari) and Hadiya and Jogidaha
in Triyuga Watershed (Udayapur) and hired a monitoring expert to conduct validation of Study
Reports as per ToR.
The consultant has completed all the assigned work as mentioned in the ToR which includes
Submitted Inception Report
Completed field verification work
Prepared and Submitted Draft Report
Presented Findings of the Draft Report
1.2 Objectives
The main objective of the assignment is to validate project components proposed in the study 1
and 2. The specific objectives of the assignment are
To validate requirement of all structural measures proposed in study 1 in terms of location and
dimension in the actual field condition
To ground verify bio-engineering species proposed in the study 1 with regard to availability,
quantity, costing etc. for each project area (i.e. VDC and community)
To confirm the information provided for the watershed management plan in the project area
under study 1 through ground verification
To validate the proposed elevated tube wells in the most vulnerability communities of the 8
selected VDCs in terms of location and length of screen made in the study 2 with respect to
actual field condition
To conduct ground verification of the flood proofing drainage system in terms of length,
location, cross-section etc. proposed in the study 2
To validate the prioritized activities proposed in the studies 1 and 2.
1.3 Scope of the work
The scope of the work are listed below
Undertake a thorough study of task 1 and 2 prior to field mobilization, prepare necessary check
lists and prepare and submit inception report
Verify and validate all structural and non-structural measures proposed in design study in terms
of their location and dimension in field.
Confirm the available information provided by the study reports for undertaking the watershed
management interventions/ plan under study area
Validate and confirm the proposed elevated tube wells for the most vulnerable communities of
the 8 selected VDCs in terms of their location, and prioritized under study 2 with respect to
actual field locations and conditions.
Verify the major hotspots and prioritize their best conservation measures and location.
Share with community member, ground truth and verify the bio-engineering species proposed
in the study areas with regard to availability, quantity etc. for each project area.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
3 | P a g e
Undertake ground verification of the flood proofing drainage system in terms of length,
location, section etc.
Visit the proposed site with VDRMC member, DPO for spot verification and clarify all the
related issues (if any) and validated the technical and social data.
Compile the field verified data of sediment control, watershed management and list out the
best vegetative and engineering measures for flood and soil erosion control on different
locations of the river systems.
Based on the above field assessment and verification, prepare a draft report of the study
findings for presentation to PMU/DHM and partners for soliciting comments and feedbacks.
2. Methodology
The Consultant reviewed the Terms of Reference (ToR) provided by the CFGORRP/DHM and
prepared checklist and formats to conduct field verification of Elevated Tube Well (ETWs) for
safe water supply in inundation prone areas, finalization of location of proposed ETW, Evacuation
Centre and sanitation, measured length of drain for drain out water from ETW to near
drain/Pokhari, verified design data of flood proofing drainage systems in 4 Terai districts (8 VDCs)
and verification of river training structure and non-structural parameter.
In each district, study data were checked and verified in close coordination with VDRMC and
vulnerable communities. The VDC secretaries of all VDCs were contacted during validation of
design data and confirm in field using checklist. Basically the validation work was divided into
three parts, (i) validation of ETW location, ranking and prioritization, (ii) validation of flood
proofing drainage system and (iii) validation of sediment control measures (location, dimension &
prioritization). The draft report was prepared and submitted and final report has now been prepared
and submitted after incorporating comments, and feedbacks made in the draft report and
presentation.
2.1 Preparation of Checklists, Questionnaires and Formats
Checklists for field verification survey were prepared during the inception reporting phase to cover
sediment control measures, ETW and Flood Proofing Drainage System (FPDS).The Checklists,
questionnaires and formats were prepared for field verification for which the consultant paid
attention on the following issues:
Confirmation of the site for flood proofing drainage system & access to drinking water
supplies communities in 8 VDCs of 4 Terai districts with consultation of community,
VDRMC, DPO.
Checklist for verification of structural measures proposed in the study in terms of size,
requirement, adequacy and location.
Study, validate and confirm the plan proposed in the study report with understanding
of watershed management in Ratu, Hadiya, Kong, Gagan and Khando River.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
4 | P a g e
Confirm the location and site of proposed structures for sediment control
Verify and confirm whether the proposed Evacuation Centre is required or not and
finalize the location shearing with VDRMC and community member.
2.2 Field Work
After the study of design report and preparation of filed plan and checklists, the Consultant
proceeded to the field. The consultant (individual expert) had visited FCO office Lahan and
finalized the visit plan. The expert visited all four districts with DPOs to verify the proposed ETWs,
FPDS and sediment control measures.
The consultant undertook site specific measurement (size, length, location) using measuring tape
and handled GPS to validate the proposed project data and location. With the help of checklist,
questionnaires, the field data were collected jointly with VDRMC member, community members,
and DPOs. The consultant prioritized the ETW, Sediment Control Measures and FPDS sites during
VDRMC meeting and considering field condition.
Figure 1: Verification of location of ETW in Pakari and ETW drain length measured in Nahini VDC
2.3VDRMC Meetings
The VDRMC consultative meeting is exceedingly important part of the current assignment and
VDRMC meeting was conducted in all the VDCs in the respective VDC buildings facilitated by
the CFGORRP’s DPOs The prioritized ETW, sediment control measures, FPDS were verified in
site and recorded in minutes of meeting. After VDRMC meeting, the consultant, VDRMC
members and respective DPO jointly inspected, measured and verified the sites of proposed
sediment control measures, ETW, flood proofing drainage system.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
5 | P a g e
Figure 2: VDRMC meeting in Mahottari, Sirah, & Udayapur
Data of aggradations/degradation, inundation, breaching of bank were verified in 8 VDCs of four
flood prone districts. In case of Ratu River, numerous sections along the river stretches were visited
and consultations and interaction were conducted in Nahini, Sarpallo and other VDCs upstream of
East West Highway (Garuribas, Tulsi) adjoining to the river system. The VDRMC meeting and
field verification date is given in the Table 1.
Table 1: Study VDCs, River Basin and VDRMC meeting date and field verification date
SN Districts River VDCs VDRMC meeting and field
Verification date
1 Siraha Gagan Tulsipur, PipraPra Pi 08 &09 June 014
2 Saptari Khando Dighawa, Pakari 10 & 11 June 014
3 Udayapur Hadiya,
Kong
Hadiya, Jogidaha 12 & 13 June 014
4 Mahottari Ratu River Sarpallo, Nainhi and River System
North to east-west highway (Gauribas
and Tulsi)
14 & 15 June 014
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
6 | P a g e
3. Field Verification of ETW, FPDS and EC
Field verification to confirm the designed location of the Elevated Tube Well (ETW), Flood
Proofing Drainage System (FPDS), Evacuation Centre (EC) and Sediment Control Measures in
eight VDCs, and five river basins were carried out in coordination and consultation with DPO,
VDRMC members and other communities. The field verification was basically divided in four
parts and carried out rigorously in field which basically covered;
Verification of Elevated Tube Well, Drainage and Sanitation system,
Verification of Flood Proofing Drainage System along Access Road
Verification of Evacuation Centre, and
Verification of watershed management, disaster prone areas and hotspots.
3.1 Verification and Prioritization of ETW and Sanitation
The verification and prioritization of ETW was carried out in each VDC based on vulnerability
ranking of the communities, impacts of flooding to the communities, proximity to flood hazard.
These sites were jointly visited in actual field and discussed in the VDRMC meeting. The
prioritization was done in actual field based situation and position. Entire communities are
classified into three groups; such as high vulnerable (H), medium vulnerable (M) and low
vulnerable (L). In Siraha, Saptari, and Mahottari districts, the under-privileged Dalits such as the
Mushar and Chamars, and the Janajaatis in Udaypur who were ranked as excluded groups have
got high priority. Similarly, landless and disabled people also received highest priority for ETW.
The Dalit, Mushar and Chamars and Janajati and landless people and those who lives near river
bank and high inundation and are directly affected by floods are preferred high vulnerable
communities.
Medium level priority was applied to those communities where the effect of flood is minimal, such
as large open areas, comparatively wealthier villagers with abundant land, less inundation, and
higher literacy. Accordingly these were ranked and prioritized during verification.
In ensuring proper drainage system around the proposed ETWs, provisions of either pipe and/or
open drains are made and the lengths of such drainage systems were measured during field
verification. However in case of non-availability of land and local drains near tube well locations,
construction of soak pits was proposed and verified the soak pit for implementation.
3.1.1 Siraha District
Tulsipur and PipraPra Pi fall in high vulnerable community in Gagan. The list of prioritized ETWs
and their rank, type and length of drain around ETW has presented in table below after verification
in the field and interaction with the local community at VDRMC meeting.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
7 | P a g e
Table 2: Field Verified Tube well location and west water drain around Tube Well in Siraha
District VDC
Field Verified (FV) ETW and west water drain
Name of community
to construct ETW
Ward
no
Type of
ETW
Rank/Pri
ority
Length
(m) of
Drain
Remarks
Siraha
Tulsip
ur
ChamarTole 1 1-ii High/5 6 Soak pit
BaniniyaTole 2 1-ii High/1 80 At Pokhari
BaluTole 5 3-ii High/2 20 Drain
Ramjankitole 6 1-ii Medium/1 15 Soak pit
ChamarTole 7 1-ii High/3 9 Soak pit
Ramjankitole 7&6 Omitted
Mandaltole (Khatbe) 4 1-ii High/4 34 Drain
PipraP
ra Pi
KadarhawaTole 3 1-ii High/4 10 NaiakPokhari
Drain
KadarhawaTole 2 1-ii High/2 15 Soak pit
KadarhawaTole 2 1-ii High/5 15 Soak pit
KadarhawaTole 1 1-ii Medium/2 8 MahadavMa
tha, Drain
Jamuwatole,Musar
(Dalit)
6 1-ii High/1 10 near
Jamuwapok
hari
JamuwaRamjanakitole 6 1-ii Omitted
Khajanpurtole
(RamjanakiMandir)
7 1-ii Medium/4 15 Canal
Chamartole 7 1-ii Medium/3 15 Soak pit
Khajanpurtole 9 1-ii Medium/5 30 Drain
Khajanpurtole 8 1-ii Medium/6 20 Drain
Chamartole 4 1-ii High/3 20 Drain
Paschimbaritole 5 1-ii Medium/1 12 Drain
334
There were altogether 7 ETWs proposed in the study report in Tulsipur VDC out of which, 5 got
high priority (H), one medium and the rest 1was omitted. The discarded ETW was proposed at
Ram Janaki Tole 7& 6 but it was noticed inappropriate in terms of location and does not meet the
requirement of ETW. The ETW proposed in Ram Janaki Tole (ward 6) and Chamar Tole (ward 7)
mostly covered the same community and ETW in Ram Janki tole (ward 6 &7) was proposed in
border of ward 6 & 7 and the proposed land owner oppose to provide the land. Similarly in Pipra
Pra Pi VDC, out of 12 proposed ETWs; 5 falls in high priority, 6 in medium (M) and one ETW
proposed in Jamuwa Ramjanaki Tole (ward 6) was discarded as the ETW proposed in Jamuwa
Ramjanakitole (ward 6) of Pipra Pra Pi VDC has also been proposed in debatable location of same
ward 6 and it is significantly far away from the vulnerable communities and does not necessarily
serve them at the time of inundation.
The drainage length from ETW to the nearest possible outlet was verified in field. The length of
drain measured to drain out the ETW waste water was measured to be 164 m. and 170 m. in
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
8 | P a g e
Tulsipur and Pipra Pra Pi against the proposed lengths of 142 m and 205 m respectively. A
comparison between proposed and field verified lengths of waste water with regard to location,
ward, and length of proposed drain around ETW is presented in Appendix1.
3.1.2 Saptari District
The Pakari and Diguwa VDCs are highly vulnerable areas in the Khando River basin because of
prolonged inundation, sediment deposition in the agricultural land, bank cutting along river
corridor in the VDCs. The study report has proposed 7 ETWs in Pakari VDCs which were split up
as 4 under high priority, 2 medium and 1 low priorities. All ETWs were field verified as correctly
proposed in terms of location and community to be served. Four ETWs were prioritized as high, 1
as medium and the rest 1 as low totaling of 6 proposed and verified in Dighwa VDC. Table 3
shows the field verified ETWs in Pakari and Dighwa under different priorities as mentioned.
Table 3: Field Verified Tube well location and west water drain around Tube Well in Saptari
District VDC
Field Verified (FV) ETW and west water drain
Name of community
to construct ETW
Ward
no
Type
of
ETW
Rank/Priority
Length
(m) of
Drain
Remarks
Saptari
Pakari
Pakaritole 5 1-iii Medium/2 20 Drain
Chamartole,Ramtole 4 2-iii High/1 20 Drain
Devsthaltole 3 3-iii Medium/1 20 Drain
Musslimtole,
JumiMasjit
3 2-iii High/3 55 Drain
Musharitole 4 1-iii High/2 15 Soak pit
Musaharitole, Ra-
PraVidalaya
2 1-iii Low/1 16 Drain
Sonahara (Musahar)
tole
2 1-iii High/4 37 Drain
Dighwa
Musahar (Sada)tole,
ChiyaChowk
9 1-iii High/4 15 Soak pit
Ram Chamar&
Yadav tole
7 1-iii High/2 32 Drain
Khang/Yadav tole 5 2-iii High/3 15 Soak pit
Diguwa (Mandal&
Yadav)
8 1-iii Medium/1 15 Drain
Rampur (Mushar)/
Sadhatole
9 1-iii High/1 45 Drain
BirolBazzarChowk 1,2&
3
1-iii Low/1 15 Soak pit
320
The length of waste water drain around proposed ETW has also been verified. The drainage length
verified in Pakari and Dighawa was about 183 and 137 m, respectively. Whereas the study has
estimated 162 and 140 m respectively. The detail comparison of length and location is presented
in Appendix 1 of this report.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
9 | P a g e
3.1.3 Udayapur District
Hadiya and Jogidaha VDCs are identified as highly vulnerable communities respectively in Hadiya
and Kong River watersheds. There are 7 vulnerable human settlements spread in 4 wards of
Hadiya. Similarly, in Jogidaha VDC, four settlements in 5 wards have been identified as vulnerable
communities. The sites of designed ETWs were verified in terms of location of ETW, ranking and
length of waste water drain from ETW to the nearest possible outlet and are presented in table 4
in below.
Table 4: Field Verified Tube Well Location and Waste Water Drain around Tube Well in Udayapur
District VDC
Field Verified (FV) ETW and west water drain
Name of community to
construct ETW
Ward
no
Type of
ETW
Rank/Priori
ty
Length
(m) of
Drain
Remarks
Udayapur
Hadiya
Dhimkitole,umal,B.K
Basti
5 1-i High/2 15
Soak pit
Dungaha Dhar
(Musartole)
5 1-i High/1 15
Soak pit
Rajajitole 5 1-i Low/2 15 Soak pit
Bakainiyatole 7 1-i Medium/1 28 Drain
Ramjanakitole 6 1-i Medium/2 50 Drain
Khoriyatole 6 2-i High/3 38 Drain
DevnagarNayaBastitole 7 1-i Medium/4 25 Drain
BhimaTole 2 3-i Medium/3 10 Drain
Devdhartole 1 1-i Low/1 15 Soak pit
Jogidaha
Dachhintole, near Pokhari 3 1-i High/1 12 Drain
Khudiyahitole 3 1-i Medium/1 15 Drain
Nayabasti (Mushar) tole 7 2-i High/2 15 Soak pit
Baluwaitole 5 1-i High/4 15 Soak pit
VDC land Jogidaha 6 1-i Low/1 15 Soak pit
UttarbariTole 2 1-i High/3 15 Soak pit
Total 298
Out of the 9 numbers of ETW designed in Hadiya VDC, 3 are ranked as high priority (H), 4
medium and the rest 2 low priority. Similarly in Jogidaha VDC, out of 6 ETWs proposed in study,
4 are highly (H) prioritized, 1 medium (M) and one in low priority. The measured lengths of the
drainage were 211 m and 87 m in Hadiya and Jogidaha respectively, whereas the proposed lengths
were 200 and 88 m respectively indicating that proposed and field verified lengths are nearly same.
The field verified ETW location and drain length for ETW sanitation are presented in Appendix
1.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
10 | P a g e
3.1.4 Mahotari District
Sarpollo and Nahini are the study areas in Mahottari district under Ratu watershed. Sarpallo is
severely affected by Jangha and Aunsi River, tributaries of Ratu River whereas Nainhi is inundated
by the Ankar River.
All the three ETWs proposed for Naini VDC are under high priority (H) and VDRMC meeting
requested an additional ETW in Nainhi Primary School. Since, the school building is centrally
located and may be used as an evacuation zone at the time of flood, one ETW has now been
recommended for the installation. Similarly, out of three ETW proposed in Sarpallo VDC, 2 fall
in high ranking and one in medium.
Table 5: Field Verified Tube well location and west water Drain around Tube Well in Mahotari
District VDC
Field Verification (FV)
Name of
community to
construct ETW
Ward
no
Type
of
ETW
Rank/P
riority
Length
(m) of
Drain Remarks
Mahotari
Nahini
Chamartole,
Tharuaihai
8 3-iv High/2 10 In Existing Drain
DachhinbariTole,
Tharuaihai
6 1-iv High/3 58 Hume pipe (30 cm) to
cross road to Drain out
MahilbariTole 4 1-iv High/1 30 6” HDP pipe to Drain
Nahinitole 2&3 NahiniPri. School area,
Flood affected. Requested
to add an ETW.
Sarpallo
Bajhranga Chock 5 2-iv Medium
/1
26 River
uttarbariTole 8 1-iv High/1 38 River
JhingasthanTole 9 2-iv High/2 76 Drain
238
The length of drainage around ETW has been verified and length measured in Nahini and Sarpallo
is about 98 and 140 m, where as in design the length was about 93 m and 139 m respectively. The
comparison list of ETW, location, ranking and drainage around ETW are presented in Appendix
1.
3.2Verification of Rehabilitation of Flood Proofing Drainage System (FPDS)
The existing drainage systems are not properly functioning mainly due to lack of inadequate
longitudinal slope gradient in the drain, O&M, inadequate size (10 – 15 cm depth) and lack of fund
for regular operation and maintenance. It was observed that the drains are constructed without
proper side slope along earthen roads resulting in the drains’ side collapse and ultimately causing
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
11 | P a g e
inundation at the time of floods. Blockage of the drainage is mainly due to siltation and collapses
of the drainage are the main reasons of diminishing the drains’ cross-sectional size. The consultant
with VDRMC and DPO conducted transect walk interacting with community to identify the most
water logging areas for estimation and verification of designed drain length for rehabilitation and
verified the rehabilitation length for FPDS in field.
During discussion, the local communities and VDRMC representatives attempted to assure that
rehabilitation of the existing drainage may minimize the duration and spatial extent of inundation.
There will be no prolonged inundation and the flood level will be reduced after drain out the flood
water through rehabilitated drainage system and also prevent the entry of flood in the communities.
Rehabilitation of the existing drainage system should include recovery of the original shape size,
side slope with proper longitudinal slope so that there would be no inundation.
Siltation and inundations are natural phenomenon in most of the project VDCs because they lie in
the middle Terai plane where groundwater is found shallow and spring line encounters and
affluent/effluent of the flow occurs. In such places water level in the river rises immediately after
the rain starts during monsoon. Basically, most of the cases are similar in Siraha, Saptari, and
Mahottari district. However, in Jogidaha and Hadiya of Udayapur district, it is somehow different.
Tributaries of the Triyuga are Hadiya and Kong which flow from south to north with
approximately 1 to 2% gradient in the terrain and comparatively less inundation occurs. However,
to drain out the flood the rehabilitation of drain has been proposed and verified in field.
VDRMC members and VDC secretaries of Siraha, Saptari and Mohattari shared that most of the
low land and affected area remains inundated for two to three days or more than that depending
upon rainfall duration and extent of flood in the area and the stagnated water is generally drained
out half to one day depending on recession of water level in the corresponding river. The existing
drains along the road sides in the settlements are blocked at most of the places so they need to be
rehabilitated and reconstructed in places where there is no proper drainage system.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
12 | P a g e
Figure 3: Existing drain in Jogidaha and Nahini Mahottari
It was noted that about 1/3rd of total drains ns have been blockage in the existing drain per the field
observation and verification, there are about 1/3rd of total length that have been blockages in the
existing drains on the side of the roads and the VDRMC member suggested that after rehabilitation
of existing blocked drains, the rainy water as well as flood water passes towards river through
these drains.
3.2.1Siraha District
The cause of inundation in Tulsipur and Pipra Pra Pi VDC is Gagan River. Most of the vulnerable
communities within Tulshipur are located about 30 to 50 m to the Gagan River bank. Most of the
households within ward 1, 2, 4, 5, 6 and 7 are prone to inundation during floods in Tulsipur. Also
in Pipra Pra Pi VDC, most of the affected wards are 1, 2, and 3, and wards 4, 5, and 6 by Sugawati
River, and wards 7, 8, and 9 are by Sahaja River.
The rehabilitation of flood proofing drainage verified in field is about 635 m in Tulsipur and 1470
m in Pipra Pra Pi VDCs, whereas these figures are about 645 m and 1266 m respectively in the
study report. The summary is presented in table 6 of this report.
Table 6: Rehabilitation of FPDS verified along the access roads in Tulsipur& PipraPra Pi VDCs
Distric
t
VDCs Location of ETW Ward no Ranking
Field Verified
Length (m) (FV)
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
13 | P a g e
Siraha
Tulsipur
Baniniyatole, ward no 1,2 2 High/1 130
Chamartole, ward no 1 1 High/5 120
Balutole, ward no 5 5 High/2 120
Mandal(khatbe) , ward no 4 4 High/4 80
Ramjanakitole, ward no 6 6 Medium/1 85
Chamartole, ward no 7 7 High/3 100
Ramjanakitole, ward no 6 & 7 6 & 7 0
Sub total 635
PipraPra
Pi
Karaharbatole(mahadev), ward 1 1 Medium/2 60
Karaharbatole, ward no 3 3 High/4 150
Ramjanakitole, evacuation center 2 High/5 70
Karaharbatole, ward no 3 2 High/2 120
Jabuwa school, ward no 6 6 Omitted
Jamuwatole, ward no 4 6 High/1 240
Chamartole 4 4 High/3 120
Paschimbaritole, ward no 5 5 Medium/1 200
Khajanpurtole, ward no 9 9 Medium/5 120
Khajanpurtole, ward no 8 8 Medium/6 90
Chamartole ward no 7 7 Medium/3 100
Khajanpur, ramjanakitole, ward 7 7 Medium/4 200
Sub-Total 1470
A detailed comparison between study and field verified length of flood proofing drainage is
presented in Appendix 2
3.2.2 Saptari District
Wards 1, 1, 2, 3, 4, and 5 of Pakari and 1,2 5, 7,8 & 9 of Dighwa are being severely affected by
Khado, Mahuwa and Wokado Rivers. Wards 3 and 5 of Pakari are severely affected by the Khando
River. The vulnerable communities are within 30m to 100m from the Khando River, indicating
that the communities are very proximity to flood hazard. The proposed length of flood proofing
drainage to be rehabilitated in study report was 632 m in Dighawa and 662 m in Pakari VDC but
field verified lengths are 765 m and 770 m respectively. The summary of verified length of flood
proofing drainage is presented in the table 7 of this report:
Table 7: Rehabilitation of FPDS verified along the access roads in Pakari & Dighawa VDCs
District VDCs Location of ETW Ward no Ranking
Field Verified
Length (m) (FV)
Saptari Dighawa
Birolebazzar, ward 1,2 1,2&3 Low/1 105
Musahartole, ward 5 9 High/4 150
Mandal and Yadav tole, ward no 8 8 Medium/1 60
Chamar and Yadav tole, ward no 7 7 High/2 60
Kamalpurtole, ward no 5 5 High/3 150
Rampur tole, ward no 9 9 High/1 240
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
14 | P a g e
Sub total 765
Pakari
Pakaritole,Chamarbasti, ward 4 5 Medium/2 80
Chamartole, ward no 3 4 High/1 60
Devisthal, ward no 3 3 Medium/1 120
Musslimtole, ward no 3 3 High/3 160
Sonahara(Musahar ) tole, ward 2 2 Low/1 200
Musharitole, ward no 4 4 High/2 80
Sonahara(Musahar ) tole, ward 2 2 High/4 70
Sub total 770
A detailed comparison between the design and field verification length of flood proofing drainage
is presented in Appendix 2
3.2.3 Udayapur District
In Udayapur district, there are several tributaries of the Triyuga rivers and two of them are Hadiya
and Kong which flow from south to north and join Triyuga. Although terrain in both river is
slopping towards the rivers, there is low and flat land in downstream reach of Hadiya and Kong
river indicating that there is a need of FPDS and field verification was also conducted. River banks
in both Hadiya and Kong Rivers are severely eroded and communities located at low flat lands or
near river side are flooded and submerged during peak flood. Jogidaha VDC is mainly affected by
Kong River, Bhadua, and River. Vulnerable communities in wards 2,3,5,7 and 8 are being severely
impacted by the flood and inundation. Moreover, the Kong River joins with the Veduwa River that
helps to intensify the inundation problem in the VDC. The field verified flood proofing drains
slightly went down compared to the study figures because few side drains along the access road
may work as FPDS. The field verified length of FPDS is 1250 in Hadiya and 500 m in Jogidaha
respectively whereas in study, the lengths of FPDS were proposed 2157 m and 652 m respectively
in Hadiya and Jogidaha VDCs. The summaries of field verified FPDS are presented in Table 8.
Table 8: Rehabilitation of FPDS verified along the access roads in Hadiya & Jogidaha VDCs
District VDCs Location of ETW Ward Ranking
Field Verified
Length (m) (FV)
Udayapur
Hadiya
Devdhartole, ward no 1 1 Low/1 150
Bhimatole, ward no 2 2 Medium/3 200
DungahaDhartole (Musar) tole ward 5 5 High/1 150
DhimkiTole, ward no 5 5 High/2 180
RajajiTole, ward no 5 5 Low/2 150
BakainiyaTole, ward no 7 7 Medium/1 150
RamjanakiTole, ward no 6 6 Medium/2 100
KhodiyaTole, ward no 6 6 High/3 120
DevnagarNayaBastiTole, ward 7 7 Medium/4 50
Sub total 1250
Jogidaha Jogidaha VDC - - -
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
15 | P a g e
Dachhintole, Ward no 3 3 High/1 120
Khudiyahitole, ward no 3 3 Medium/1 80
Uttarbaritole, ward no 2 2 Higgh/3 150
Baluwaitole, ward no 5 5 High/4 150
Nayabasti(Musahar) tole, ward 7 7 High/2 0
VDC land Jogidaha, ward no 6
Sub Total 500
The comparison list of study period and field verified length of flood proofing drainage is in
Appendix 2 of this report.
3.2.4Mahottari District
Nahini VDC is not directly flooding from Ratu, but wards 4, 6 and 8 are mainly affected due to
the irrigation canal that is fed by the floodwater of Ratu; the canal is known as Ankar canal. The
inlet to this canal is about 4 km east from Nahini, in the adjacent of Gonarpuwa VDC in the east
and is closer to the Ratu River. In Sarpallo VDC, the main sources of flooding are the Janga and
Aakusi River (wards 1, 2, and 9), tributaries of Ratu River. FPDS is proposed to drain the flooded
and inundated water from Janga and Aakusi Rivers. The length of FPDS verified in field is about
580 m. and 343 m respectively in Nahini and Sarpallo VDC whereas the proposed in study/or
design phase were 311 and 292 m. respectively. The summary of finding is presented in Table 9.
Table 9: Rehabilitation of FPDS verified along the access roads in Nahini & Sarpallo VDCs
District VDCs Location of ETW Ward
no
Ranking Field Verified
Length (m)
Mahotari
Nahini
Chamartole, ward no 8 8 High/2 200
Dakshinbaritole, ward no 6 6 High/3 180
Mahilbaritole, ward no 4 4 High/1 200
Sub total 580
Sarpallo
BajhrangChowk, ward no 5 5 Medium/1 100
Uttarbaritole, ward no 8 8 High/1 120
Jhingasthantole, ward no 9 9 High/2 123
Sub total 343
The comparison list of FPDS in study period and field verification is presented in Appendix 2
3.3Verification of Evacuation Centre and Location
Basically elevated open public land could be used as an evacuation zone. In each evacuation zone,
one ETW along with proper sanitation system is proposed, which includes one toilet, septic tank
and soak pit. There is an Evacuation Centre proposed study report in Mahottari (in Bajharang
temple ward 1 & 5 in Sarpallo VDC) and one in Saptari (Birol Bazaar Chowk 1,2&3 in Dighawa
VDC) which are duly verified. The other field verified ECs include one in Ram Janki Tole ward 2
of Pipra Pra Pi VDC and one in VDC building ward 5 of Tulsipur VDC of Siraha, 1 EC has
proposed in Rajaji tole ward 5 of Hadiya VDC and 1 EC in VDC compound ward 6 of Jogidaha
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
16 | P a g e
VDC in Udayapur. As per field verification, the EC in Udayapur is likely in low priority. However,
the community member and VDRMC members requested for EC in VDC compound in Jogidaha
and Rajaji tole ward 5 in Hadiys VDC. The proposed location and area has verified and confirmed
in site.
Table 10: Proposed EC site location and Field verified Evacuation Centre in districts
Districts VDCs Community War
d
No.
No.
of
ET
Ws
No.
of
Toilet
s
Coordinates HFL EC location
Latitude Longitude (m) From
GL
(degree) (degrees)
Mahotta
ri
Sarpollo BajhrangaCh
owk
1&5 1 1 26.7418 85.7842 1.045 Bajharang
Temple
Nahini
Siraha PipraPra
Pi
RamjanakiT
ole
2 1 1 26.6482 86.3116 0.3 Ramjanakito
le/ Temple
Tulsipur VDC
building,
Tulsipur
5 1 1 0.4
Udayap
ur
Hadiya RajajiTole 5 1 1 26.7813 86.8353 0.3 Rajaji
School
Jogidaha VDC land
Jogidaha
6 1 1 26.7629 86.7698 0.4 VDC Land
Saptari Dighawa BirolBazzar
Chowk
1,2&
3
1 1 26.5581 86.7764 0.4 Birol Market
Pakari
Total 6 6
The detail list of design and field verified Evacuation Centre is presented in Appendix 3
4. Sediment Control
4.1Structural Measures for watershed Management
The consultant visited all five rivers with VDRMC member, community member and DPOs for
verification of location and dimension of proposed spur and embankment. The check lists were
used to collect data and verified location of proposed structural measures. The observation and
verification information are presented in following para.
4.1.1 Gagan River
Bank cutting and deposition of sediment (basically fine particles – sand and silt) in river bed was
observed throughout the Gagan River in project covered VDCs, mostly in downstream of
Banainya. Bank cutting has resulted in meandering of river and high sediment volume and bank
cutting is resulted by the high stream discharge during monsoon and in some cases by insufficient
river channel width. As the river approaches Tulsipur VDC, the bank cutting is severe and
cultivated lands are washed out each year. The photographs presented below show the changes of
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
17 | P a g e
river course and sediment deposition. Bank cutting and river frequently changing of river course
are the serious concerns in ward no 2, 5, 6 & 7 of Tulsipur VDC. Local people reported that about
25 to 30 % of total households of these wards are Dalit followed by 26 % Muslim. These vulnerable
groups are adversely impacted by Gagan flooding.
Figure 4:Edge cutting and meandering of Gagan River in Siraha
During monsoon, the river water along sediment inundates agriculture land of ward 3 of Tulsipur
and ward 1, 2 &3 of Pipra Pra Pi VDC. With the reduced velocity, sediment slowly deposits into
the agriculture land. The river meandered in upstream of Hanuman/Mahadev temple of Tulsipur,
Bananiya ward 2, Balutole ward 5 and just east side of VDC building at ward 5. The hotspots were
verified and measured along Gagan river stretch from downstream of Banainya tole in Tulsipur.
The verified river embankment is about 4200 m in both sides, whereas in study period, it has
proposed an embankment of 4000 m along both bank of Gagan River. Most of hotspots where the
meandering took place need to be protected by earthen embankment with bio-engineering measure
in first phase as shown in map. The actual field measurement and verification depicted that there
is an additional 200 m embankment both side of Goiryawa (260 41' 40" N & 860 20' 59"E). The
starting point of embankment is Goiryanwa in Tulsipur, 800 m upstream of Hanuman temple,
Tulsipur.
Table 11: Field verified length and location for earthen embankment in Gagan river
S
N
Distric
t
Name of
River
Field Verification (FV) status
Location/Chainage Length (m) Left/Right Remarks
01 Siraha Gagan A1/ 0+000 – 0+200 200 Both side A1 is additional length
considered in FV. Goiryawa
(0+000)
260 41' 40" N & 860 20' 59"E
(1)/ 0+200 – 4+200 4000 Both side
The location of earthen embankment proposed is shown in map below and A1 refers to additional
length proposed after field verification survey in Gagan river. The list of embankment length
proposed in study and field verified is presented in Appendix 4.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
18 | P a g e
Figure 5: Location of Earthen Embankment in Gagan River
Prioritization of hotspot for embankment & bio-engineering work: The most hotspot was identified along
the river during field verification and the length was measured (2,700 m) for estimation and implementation.
However total length in study period for embankment and Bio-engineering in Gagan was 4,200 rm. The
remaining embankment length of about (4,200-2,700)1500 m will be plan in 2nd phase. The location of
prioritized embankment is shown in fig. 5 of Gagan River. The summary of prioritized length is also
presented in the Table 12.
Table 12: Prioritized hotspot for construction of earthen embankment & Bio-engineering in Gagan River
District/
VDC
Name
of
River
Most hotspot of Gagan river
Location /Chainage
Length
(m)
left/R
ight Prioritized Remark
Siraha/T
ulsipur Gagan
0+000 -0+350; Banainya/Gauriyarwa
and Tulsipur boarder
350 R/B P1
Tulsipur-2, East of Mushari tole 500 R/B P1
Mahadav Manth temple, Tulsipur-1&2 600 R/B P2
Bananiya tole ward 2 opposite of
KushaLaxminiya
400 R/B P3
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
19 | P a g e
Tulsipur-5, East south of Balutole; D/S
of Bariyarpati Kulo
550 R/B P1
Tulsipur-6, East of Tulsipur VDC
building
300 R/B P2
Total 2,700
4.1.2 Khando River
Major loss was observed in Dighawa VDC as seen from the annual loss of agricultural land in the
area due to bank cutting, flooding, inundation and sedimentation in agriculture land. As the
difference between river bed and bank level is merely a feet, inundation and sediment deposition
is quite common during monsoon. Farmers reported that agriculture production has been
drastically reduced because of sedimentation over the agricultural land.
Figure 6: Sediment deposition and Bank cutting in Khando River
River bank Cutting and Inundation have been a big threat to ward numbers 4, 5& 6 of Dighawa
VDC. Every year a chunk of land is turned to river channel while ward number 1-4 and 7-9 of
Dighawa VDC and wards1 - 4 of Pakari VDC have a problem with inundation. Local community
reported us that water comes up to 2-3 feet and even more during monsoon.
To connect Dighawa and Pakari VDC, Department of Road is undertaking construction of RCC
Bridge in “Hulaki Road” and has also a plan to construct guide bank in both upstream and
downstream of the newly constructing bridge. The hotspots are to be protected by constructing
earthen embankment which is further to be strengthened by bio-engineering measures in first
phase as shown in figure 7 below. The Bhim Badha of left side also needs to be rehabilitated
for about approximately 150 m length at different locations. The length of embankment
proposed in study phase and field verification is presented in Appendix 4
Table 13: Field verified length and location for earthen embankment in Khando River
S
N
District Name of
River
Field Verification (FV) status
Location/Chainage Length (m) Left/Right Remarks
1
Saptari Khando
A1/ 0+000 – 1+000 1000 Both side Chainage considered at DS of
Dighwa VDC 9(SadhaTole).
A1 and A2 is additional 2 (1) / 1+000 – 2+500 1500 Both side
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
20 | P a g e
embankment length after FV
of site.
3 A2/ 3+500 – 4+200 700 Right side D/S of RCC Bridge under
construction in Hulaki Road
The earthen embankment verified for sediment control in Khando River in Saptrai is about
2,500 m in both side and 700 m in right side, whereas in study phase, the proposed length of
earthen embankment is about 1,500 m in both side and 500 m in right side. A1 & A2 refer as
additional length after field verification survey. The verified location and additional length
proposed in field verification survey is presented in figure 7 below.
Prioritization of hotspot for embankment & bio-engineering work: The most potential hotspot was
identified along the Khando River during field verification. The length was measured (3,700 m) for
estimation and implementation. The summary of prioritized length is presented in table 14.
Table 14: Table 14: Prioritized hotspot for construction of earthen embankment & Bio-engineering in Khando
River
District/
VDC
Name of
River
Prioritized length verified in field
Location /Chainage Length
(m)
left/R
ight
Prioritized Remarks
Saptari/
Dighwa Khando
Starting Diguwa VDC-9, Mushari Tole
Via d/s Diguwa -8 /Ch. 0+00 - 0+1500
1500 R/B P1
Diguwa-3, D/S bridge under construction
along Hulki road and U/S of sediment post
installed/ Ch. 3+500 - 4+200
700 R/B P1
U/S of Hulaki road (U/S of Proposed
bridge River training work) /Ch. 1+500 -
2+500
1000 R/B P2
Left bank of Khando River, Kadmaha,
Dighwa VDC
500 L/B P3
Total 3,700
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
21 | P a g e
Figure 7: Location of proposed Earthen Embankment in Khando River, Saptari
4.1.3 Hadiya and Kong River
Similar issues exist in both Hadia and Kong watersheds because these two possess similar
catchment characteristics within Triyuga watershed. Erosion, land slip, and landslide during
monsoon in the upstream of Hadiya and Kong watershed causes sediment transport in the lower
reach of the watersheds. This is further enhanced by the intensified deforestation along with open
grazing in Churia region. The ultimate effect is the sediment deposition along the river stretch and
adjoining agricultural land in the downstream during monsoon, river bed level rising and reduced
productivity. Significant supports are being received from DWIDP, GIZ, DSCO, CF, DDC, and
VDC in embankment and spur construction. Additionally, numbers of bio-engineering species
(locally available1) are used to protect along the constructed river bank.
Figure 8: Proposed embankment and existing river training work in Kong River
11 Bamboo, Simal, fruit trees (banana, Mango), Karme (Besharam in local language), Khayar
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
22 | P a g e
The hotspots were measured and verified in field. It was also observed that people campaign and
awareness programs are to be implemented to conserve Churia, re-afforestation and need to stop
open grazing in forest area to control sediment. There are certain sections (see red circle in figure
9 & 10) of the river from where water enters to the agricultural land then to vicinity of settlement
and these locations were identified and mitigation measures were proposed. In Kong River, a small
stretch of about 200 m long embankment in the left bank of the river was constructed by District
Soil Conservation Office (DSCO) Udayapur. Moreover, the embankment verified in field in
Khong is about 1,050 m in Left bank and about 1,050 m in Right bank respectively and shown in
table 15 whereas in study period, the proposed length was 1,250 m in left bank and 800 m in right
bank. The additional length and location has been marked by A1 in river shown in figure 9.
Similarly, in Hadiya River, the field verified length of earthen embankment is1,200 m in right
side and 1,500 m in left side (table 15) whereas the proposed length of embankment in study phase
is about 1,600 m and 400 m in right and left bank respectively. The additional embankment lengths
verified in field are represented by A1 & A2 in Left bank of Hadiya River (figure 10). The proposed
embankment length in study period and field verification length and location is presented in
Appendix 4
Table 15: Field verified length for earthen embankment and location in Kong and Hadiya river
S
N
District Name of
River
Field Verification (FV) status
Location/Chainage Length (m) Left/Right Remarks
1 Udayap
ur
Kong (1)/ 0+450 – 0+950 500 Left bank Chainage considered from
confluence of Trijuga& Kong
river at upstream
2 (4)/ 0+800 – 0+950 150 Right bank
3 A1/1+680 – 1+880 200 Right bank A1 is additional embankment
4 (3)/2+750 – 2+950 200 Left bank DSCO completed
5 (2)/2+100 – 2+650 550 Left bank
6 (5)/ 2+300 – 3+000 700 Right bank
1 Hadiya A1/0+400 – 0+600 200 Left bank A1additional emba. length
2 (1)/1+250 – 2+050 800 Right bank
A2/1+920-2+420 500 Left bank A2 additional emban.Length
(3)/4+000 – 4+800 800 Left bank
(2)/ 4+900 – 5+300 400 Right side
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
23 | P a g e
Figure 9: Location of Earthen Embankment in Kong River
Prioritization of hotspot for embankment& bio-engineering work: The most hotspot (p1) is identified along
the Kong (1,450 m) and P2 is identified (650 m). Similarly in Hadiya River length of embankments are
1,400 m. in 1st priority and 1300 m. in second priority during field verification. The length was measured
in field for cost estimation. The priority (P1) only has considered in cost estimate for 1st phase of
implementation. The summary of prioritized length is presented in table 16.
Table 16: Prioritized hotspot for construction of earthen embankment & Bio-engineering in Kong & Hadiya
River
Districts/
VDC
Mark
in
map
Prioritized embankment length and location
Location /Chainage Length
(m)
Left/Right Prioritized Remarks
Udayapu
r/Jogida
ha/Kong
1 0+450 - 0+950 500 L/B P2 Chainage
consider from
confluence of
Trijuga and
Kong river at
upstream
4 0+800 - 0+950 150 R/B P2
A1 1+680 - 1+880; Dhangadhi tole area 200 R/B P1
2 2+100 - 2+650; Dhangadhi tole area 550 L/B P1
5 2+300 - 3+000; Upper belt of Khudai 700 R/B P1
Total length priority (P1) only 1450 m in P1and 650
in P2
(A1 +2+5 nos) are priority
P1
Udayapur
/Hadiya/
A1 0+400 - 0+600 200 L/B P1 A1 additional
length
A2 1+920 - 2+420 500 L/B P2 A2 additional
length
1 1+250 - 2+050 800 R/B P2
3 4+000 - 4+800 800 L/B P1
2 4+900 - 5+300 400 R/B P1
Total length priority (P1) 1400rm in (A1+2+3) and 1400 rm and 1300 rm in Priority 2
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
24 | P a g e
Figure 10: Location of Proposed Embankment in Hadiya River
4.1.4Ratu River
At chainage 1+900 to 0+800 m: At a confluence of Ratu and Sunjhari Khola and downstream, Ratu pushes
flow (during monsoon) to the left bank. The ultimate effect is left bank cutting of the River. To control the
bank cutting in left bank, the spur has been proposed in design. The location was visited and verified in site
with DPO and confirmed the design data. The picture of proposed site is presented in this report for
reference.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
25 | P a g e
Figure 11: Proposed location of Spur and embankment in Ratu River
At chainage3+000 m to 3+540 m: Bank Cutting and Inundation in upstream of Sunjhari Khola:
The chainage was considered from upstream of Ratu Bridge in East-West highway. The locations
severely affected by bank cutting and hotspots were visited in verification period and local
community informed that every year the area is losing land mass due to bank cutting. The spurs
have to be essential to control the bank cutting around 3+000 to 3+540 in left bank (Tulsi VDC
side). As the bank cutting height is about 2.5 m to 4 m gravel mixed soil and suggested to spur in
left bank of Ratu River. To protect bank cutting in these chainages, five spurs have been
additionally proposed with 25 m length with 100 m spacing in left bank normal to river.
Figure 12: Ratu River Left bank cutting about 3+000 area
Similarly in Chainage 5+400 to 4+900 the river is approaching/ shifting towards Patu village
resulting in to bank cutting in Patu Village. There is a small tributary at the left side of river
(opposite to Patu village) contributing noticeable amount of sediments during monsoon. As the
flow of Ratu pushed water and debris of this tributary to the left bank, a deposition occurs leading
to shift of waterway towards right bank and ultimately cutting the right bank (at Patu village area).
The spur has been proposed in right bank in design and the location has been verified jointly with
DPC, DPO and local users in site. The field verified location and length of spur is presented in
table 17 in below. The proposed gabion spurs in study period and Field Verification are presented
in Appendix 5.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
26 | P a g e
Table 17: Field verified length and location of Gabion Spur in Ratu River
S
N
District Name
of
River
Location/
Chainage
No
of
spur
Length
of
spur(m)
Spur
spacin
g (m)
Orientation Remarks
1 Mahotar
i
Ratu
River
(3)/ 1+900
– 0+800
9 40 120 Spur with embankment, Normal
to flow, at Ratu (L/B)
Chainage
considerfr
om U/S of
Ratu
bridge at
E-W
highway
A1/3+000
– 3+580
5 25 100 A1 proposed additional supr as
per Field Verification of
site.Normal to River. At Tulsi
VDC (Leftbank)
(2)/ 4+900
– 5+400
5 25 100 Upper Part of Laalgadh where
SunjhariKhola meet Ratu (R/B)
Figure 13: Locations of Proposed Spur and Embankment in Ratu River in Mahotari
At chainage 12+100 m to 11+600 m): Bank Cutting and Inundation in Kalapani of Gauribas
VDC: In the first 500 m (11+600 m to 12+100 chainage), the river bends towards right side and
just is about to enter the flood water in farm land. The debris deposits in left bank. The discussion
with local revealed that every year the area is losing land mass due to bank cutting. In the later
section (chainge 12+100 m to 11+600 m), there is an inundation in agricultural land during
monsoon. The elevation difference of river bed and the bank of the river is only 0.40 m to1.5 m.
The field was visited with DPC, DPO and local people and field visit and discussion between local
people and FCO staffs recommended to provide embankment of about 500 lengths in Right bank.
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
27 | P a g e
Figure 14: Ratu river approaching towards farm land and bank cutting
Jaganha River starts to drain in Ankushi and encroaches, turns to agricultural land and human
settlement area. To protect right bank of Ankushi and Jaganha River in Sarpallo VDC, earthen
embankment of about 1000 m is proposed in right bank after Field Verification, whereas in design
has proposed embankment along both bank. The chainage is considered at u/s of Bajharang
Chowk, Sarpallo VDC.
Figure 15: Proposed embankment site in Ankusi & Jangahariver U/S of Bajharang chowk
Table 18: Field Verified length, location for earthen embankment in Ratu and Ankushi River in Sarpallo VDC
Distric
t
Name of
River
Field Verification (FV) status
Location/Chainage Length (m) Left/Right Remarks
Mahot
ari
Ratu
River
(1) 11+600 –
12+100
500 Right bank Ratu U/S Bahunamara. Chainage
carried from the Ratu bridge U/S of
E-W Highway
Ankushi 0+000 – 1+000 1000 Right bank RATU D/S Sarpallo, Chainage are
considered at U/S of
BajharangChowk, Sarpallo VDC
ward 5
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
28 | P a g e
Figure 16: Locations of Earthen Embankment in Ankush and Jangaha in Sarpolla, Mahatari
Prioritization of hotspot for Embankment & bio-engineering work: The most hotspot was identified along
the Ratu and Ankushi River during field verification. The length was measured in field for cost estimation.
In Ratu River, the gabion spur and bio-engineering were designed. But in first phase of implementation/or
in priority basis, only bio-engineering works are considered in Ratu River as protection work. The cost
estimate has been prepared only for earthen embankment (1000m) with bio engineering in Ankushi.
Jangaha in Sarpallo VDC (table19). In Ratu river upstream only bio-engineering work are suggested for 1st
phase of implementation.
Table 19: Field Verified length, location for earthen embankment in Ratu and Ankushi River in Sarpallo VDC
Districts/
VDC
Name of
River
Prioritized embankment length and location
Location /Chainage Length, m Left/Right Prioritized Remark
Mahotari/
Sarpallo
/Ankushi,
Jangaha
0+000 - 1+000 Sarpallo-5 starting
from Sarpallo suspension Bridge
prgressing towards North of
Bajharang Chowk, Sarpallo VDC
ward 5
1000 Right side P1
Total length of most priority 1000
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
29 | P a g e
5. Cost Estimate of Prioritized Embankment & Bio-engineering
Based on the field verification, the most hotspots were identified and length were measured for
earthen embankment in Gagan River, Khando River, Kong River, Hadiya river, Ratu River and
Ankushi River in Siraha, Spatari, Udayapur and Mahottari districts respectively. The most hotspots
with prioritized length with quantity of earthen embankment and bioengineering works have been
estimated. In Ratu River, gabion spur wasdesigned but in 1stphase of implementation plan only the
bioengineering work in Ratu at Ch. 0+800–1+900; 4+900 – 5+400 and 12+ 10 –12+550 was
measured in cost estimate. Standard practice rules have been used to calculate the earthwork
quantities and vegetative measures plantation and care taking etc. District Rate of Saptari, Siraha,
Dhanusa and Udayapur for FY 2070/071 was used for analysis of Unit Rates for different civil
works items in study report and same rate has been used in verification report and cost estimate
purpose in this report. The Quantity Estimate for embankment and bioengineering in study period,
field verification and cost of prioritized section is given in Table 20. The cost Estimate of
Embankment, Spur and bio-engineering is given in Appendix 6 & 7.
5.1 Unit Rate
The Unit Rate is used same as study report rate based on the construction works Rate Analysis
Norms. Similarly, for bioengineering work, same unit rate of study period has also been used. The
basic rate taken is as per District Rate. The analysis has been done taking into account 15% of
contractor overhead (o/h) and 13% of Value Added Tax (VAT)
5.2 Cost of Prioritized hot spot section for first phase implementation
The cost estimate of the most potential hotspots has calculated. In Gagan River, 2800 m (P1, P2
&P3), in Khando 3,700 m (P1, P2& P3), in Kong (1450 m) (P1 only), in Hadiya (1400 m) (P1only)
and in Sarpallo (1000 m, P1 only) and bio-engineering works in Ratu has measured and cost
estimate was prepared. The cost for earthen embankment and bio engineering work for 1st phase
implementation on the base of priority is estimated Nrs 11.74 million in Gagan, NRs. 10.92 million
in Khando, NRs 4.71 million in Kong, NRs 4.43 million in Hadiya and Nrs 26.32 million in
(Jangaha, Ankushi) Sarpallo & Ratu respectively.
Table 20: Summary of embankment cost including Bio-engineering study period cost, Field Verified cost
Distircts River Chainage Proposed in Design Field Verified (FV) Prioritized (P1, P2...)
section Remarks
Length (m) Cost (NRs) Length (m) Cost (NRs) Length (m) Cost (NRs)
Siraha Gagan 0+000 -
4+200
8000 31,464,582 8400 33,015,327 2800 11,741,251 All
prioritized
section (P1,
P2 & P3) is
considered in
cost estimate
Saptari Khando 0+000 -
2+500,
3+500 -
4+200
3500 10,757,762 5700 17,519,870 3700 10,920,840
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
30 | P a g e
Udayapu
r
Kong 1350 m At
chainage
(0+800-
0+900,
2+750-
2+950,
2+099-
2+650,
0+000-
0+950)
1350 4,384,339 2150 m At
chainage (0+450-
0+950, 0+800-
0+900, 1+680-
1+880, 2+100-
2+650)
6,982,477 1450m At
chainage (
1+680-
1+880,
2+100-
2+650)
4,709,087 In Kong
River cost of
Prioritized
(P2) is not
considered
Hadiya 2000m At
chainage
1+250-
2+050,
4+000-
4+800,
4+900-
5+300
2000 6,327,723 2700m At
chainage 0+400-
0+600, 1+920-
2+420, 1+250-
2+050, 4+000-
4+800, 4+900-
5+300
8,528,116 1400m At
chainage
0+400-
0+600,
4+000-
4+800,
4+900-
5+300
4,429,420 In Hadiya
River, cost of
Prioritized
(P2) is not
considered
Mahotari Sarpallo
& Ratu
2000m At
chainage
0+000-
1+000 in
Sarpallo
and 500 at
11+600 to
12+100 at
Ratu
2500& 18
nos of Spur
in Ratu with
bio-
engineering
80,983,000 1000m At
chainage 0+000-
1+000 in Sarpallo
and 500 at 11+600
to 12+100 at Ratu
35,140,212 1000m At
chainage
0+000-
1+000 in
Sarpallo
26,319,672 Including
Bioengineeri
ng in Ratu
river at ch
0+800-
1+900,
4+900-
5+400,12+10
0-12+550.
SPUR is not
considered
Total cost of Prioritized section
133,917,406 101,186,001 58,120,271
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
31 | P a g e
6. Non-structural Measures
6.1 Bioengineering
Bioengineering is a vegetative measure which holds the soil and is supportive component for flood
protection work. The Bioengineering alone cannot be the absolute solution for Churia originated
river system as these rivers are characterized by flash floods, high current and inundation in the
downstream areas. In general bioengineering is combination of civil structures (Gabion wall, dry
wall, embankment etc.) and non-structures, which may increase the durability of the whole flood
protection infrastructures. So, it is high potential to the use of vegetative measures (bioengineering)
at the both sides of the river run for river bank protection against erosion due floods in low grade
river in Terai. The vegetative measures have also been recommended along sides of embankments
and spurs. The availability of local plant and list of vegetation, species, herbs, grass, bamboo,
shrub and tree which are locally available and can survive in local climate and also can as
bioengineering measures were verified with discussion in community. Some of the species that are
popular and locally available in study area in Siraha and Spatari are Dangre Khar, Kans, Dhanu
Bas, Mal Bas, Narkat, local, Khayar, Simal, Fruits (banana, mango, litchi, pineapple), Karmi
(Besharam), Jatropha, Masala plant, Babul, Kans etc. Likely, in Udayapur, the locally available
species are Karme Jhar, Kush, Napier, Kimbu, Aak and Simli. In Mahotari, the locally available
and popular species are Narkat, Sisam, Kaus, Dhanu bas, Tharu bas with fruit (Banana, mango,
Litchi)
The field verified list of plants, species with their botanical name and use for bioengineering that
fits in local situation and their use in project districts is listed in table 21.
Table 21: Field verified list of Plants, species with their use for bioengineering
Nepali
name Botanical name Character Altitude Sites Best
propagation
technique
Mostly survive in
Districts
Grasses
Babiyo Eulaliopsis
binata
Medium-sized
clumping
Terai-1500m Hot and
dry
Slip
cuttings/seeds
Udayapur
Dangre
khar
Cymbopogon
pendulus
Large
clumping
Terai-1200 m Varied Seeds Siraha, Saptari
Dubo Cynodon
dactylon
Small
creeping
Terai-1800 m Varied Stem cuttings Siraha, Saptari,
Udayapur
Kagati
ghans
Cymbopogon
citratus
Medium-large
clumping
Terai-1500 m Varied Slip
cuttings/seeds
Saptari, Udayapur
Kans Saccharum
spontaneum
Large
clumping and
spreading
Terai-2000m Hot and
dry to
moist
Slip cuttings Siraha, Mahotari,
Spatari
Katara
khar
Themeda
species
Large
clumping
Terai-2000m Varied Slip
cuttings/seeds
Siraha, Saptari
Khus Vetiveria
lawsoni
Medium-large
clumping
Terai-1500m Varied Slip cuttings Udayapur
Kikiyu,
thulo dubo
Pennisetum
clandestinum
Small
creeping
(exotic)
Terai-1800 m Varied Stem/slip
cuttings
Siraha, Saptari
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
32 | P a g e
Napier Pennisetum
purpureum
Large semi
clumping
(exotic)
Terai-1750 m Varied;
needs
fertile
soil
Stem cuttings Udayapur
Narkat Arundo clonax Large
clumping and
spreading
Terai-1500m Hot and
dry;
varied
Stem/slip
cuttings
Saptari, Sirha,
Mahotari
Large bamboos
Dhanu bans Bambusa
balcooa
Thick culm,
heavy
branching
Terai-1600
m
Varied Culm
cuttings
Siraha, Saptari,
Mahotari
Mal bans Bambusa
nutans
Strong,
straight culms
Terai-1500
m
Dry/varied Tradition
al method
Siraha, Saptari
Tharu bans Bambusa
nutans
Strong,
straight culms
Terai-1500
m
Varied Tradition
al method
Siraha, Saptari
Shrubs and small trees
Aak Calatropha
giganteum
Small shrub,
large fleshy
leaves
Terai-1000 m Hot and dry;
harsh
Seeds /
polypots
Udayapur
Bayer Zizyphus
mauritiana
Thorny shrub
up to 4 m high
Terai-1200 m Hot and dry;
harsh
Seeds/polypot
s
Udayapur
Assuro Adhatoda vasica Shrub up to 3
m high
Terai-1000m Varied Hardwood
cuttings
Udayapur
Kera Musa
Paradisiaca
Tee upto 5
mhigh
Tera-1300 Varied and
dry
Root suckers Siraha, Saptari
Kettuke Agave
americana
Large cactus;
sub-species
with and
without thorns
Terai-2400m Hot and dry Root suckers Udayapur
Kimbu Morus alba Small tree Terai-2000 m Varied and
dry
Hardwood
cuttings/ seeds
Udayapur
Rahar Cajanus Shrub up to 4m Terai- 1500m Varied &
Dry
Seeds Siraha
Rato chulsi Osbeckia
stellata
Shrub Terai-1500 m Varied Saptari
Sajiwan/
kadam
Jatropha curcas Shrub up to 4 m
high
Terai-1000 m Varied Hardwood
cuttings
Saptari
Simali Vitex negundo Shrub up to 6 m
high
Terai-1750m Hot and dry;
varied
Hardwood
cuttings
Saptari,
Udayapur
Thakal Phoenix humilis Small stature
palm tree
Terai-1000 m Hot and dry;
needs shade
Direct seeding
on site
Udayapur
Tilka Wendlandia
puberula
Tree up to 10 m
high
Terai-1500m Hot and dry;
harsh
Seeds/polypot
s
Saptari
Large trees
Australian
khayer
Acacia
auriculiformis
Small non-
thorny tree
(exotic)
Terai-1000
m
Hot and
dry; harsh
Seeds/polypots Siraha, Saptari
Amp/aap Mangifera
indica
Medium-sized
fruit tree
Terai-1200
m
Hot and
dry but
not stony
Seeds/polypots Siraha, Saptari
Badahar Artocarpus
lakoocha
Medium to large
deciduous tree
Terai-1300
m
Varied
and moist
Seeds/polypots Siraha, Saptari
Bakaino Melia azedarach Medium to large
deciduous tree
Terai-
1800m
Hot and
dry; harsh
Seeds/polypots Siraha, Saptari
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
33 | P a g e
Banghi Anogeissus
latifolia
Large deciduous
tree
Terai-1700
m
Hot and
dry
Seeds/polypots Saptari
Jamun Syzygium cumini Medium-sized
evergreen tree
Terai-1600
m
Moist Seeds/polypots Siraha, Saptari
Khayer Acacia catechu Large, thorny
tree
Terai-
1000m
Hot and
dry; harsh
Seeds/polypots Udayapur,
Sirhaha
Lahare
papal
Populus ×
euramerica
Large deciduous
varieties
(exotics)
Terai-1700
m
Moist Hardwood cuttings Saptari
Mashala Eucalyptus
camaldulensis
Large tree with a
thin crown
Terai-1800
m
Hot and
dry; harsh
Seeds/polypots Saptari
Nim Azadirachta
indica
Large evergreen
tree
Terai-900
m
Hot and
dry
Seeds/polypots Siraha, Saptari
Sal Shorea robusta Large forest tree Terai-1000
m
Varied;
dry to
moist
Seeds/polypots Udayapur
Seto siris Albizia procera Medium-sized
deciduous tree
Terai-
1350m
Moist Seeds/polypots Saptari
Sisau Dalbergia
sissoo
Large broad-
leaved tree
Terai-
1400m
Varied Seeds/polypots /
stump cuttings
Saptari
Karme
Jhar
Corydalis
chaerophylla
- Terai-1000
m
Varied;
dry to
moist
Papaveraceae Udayapur
Simli Vitex negundol - Terai-1000
m
Varied;
dry to
moist
Rutaceae Udayapur
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
34 | P a g e
7. Photographs:
Minutes of meeting in Sarpallo&Nahini
Pakari VDC orientation, Ranking of ETW and Khando River site
Sharing meeting with local people and Hadiya ETW location in Udayapur
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
35 | P a g e
Drain to be improve and ETW site fixed in NahiniMahotari
Sediment deposition in Ratu River. Proposed Spur and embankment in Ratu River, Mahottari
Existing Spur in Ratu River about 7+000 km VDRMC meeting in Sarpallo VDC
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
36 | P a g e
Women participation during field verification of ETW in Pakari
Existing road side drain in Nahini VDC, Mahottari and VDRMC meeting
River bank cutting in Khando river in Saptari and bank cutting in Gagan River in Siraha
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
37 | P a g e
Appendix
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
38 | P a g e
Appendix 1: Elevated Tube well, Waste Water Drain around ETW in study
report and Field Verification
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
39 | P a g e
Appendix 2: Rehabilitation of Flood Proofing Drainage system (FPDS) along
Access Road in study report and Field Verification
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
40 | P a g e
Appendix 3: Evacuation centers (EC) proposed in study report and Field
Verification
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
41 | P a g e
Appendix 4: Structural Measure: Embankments Proposed in study report
and Field Verification
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
42 | P a g e
Appendix 5: Structural Measure: Spur Proposed in study report and Field
Verification
Final Report of Validation of Detail Design Report to Sediment, Flood Proofing Drainage System under Component II of the CFGORRP
43 | P a g e
Appendix 6: Cost Estimate of River embankment, Spur and Bioengineering in
study report and Field Verification