9
Good Samaritan Medical Center High Density Concrete Placement

Good Samaritan Medical Center

  • Upload
    lapis

  • View
    29

  • Download
    0

Embed Size (px)

DESCRIPTION

Good Samaritan Medical Center. High Density Concrete Placement. Walls Blockouts around door for borated polyethelene and lead plates Physics port Allows staff to check radiation levels in the vault before entering - PowerPoint PPT Presentation

Citation preview

Page 1: Good Samaritan Medical Center

Good Samaritan Medical Center

High Density Concrete Placement

Page 2: Good Samaritan Medical Center

Walls • Blockouts around door for borated polyethelene and lead plates• Physics port

•Allows staff to check radiation levels in the vault before entering•Sleeve through wall at 45 degrees vertical: Location was critical to prevent radiation leak

Page 3: Good Samaritan Medical Center

• Lid shoring• Wet weight of lid = over 1.6 million pounds• Designed by engineer; installation checked by engineer

• Fireproofing of beams• Before placement of lid• Use of HD fireproofing to prevent damage by forming and reinforcing activities: No addit’l patching required• OFI – sheet metal cap detail

• Allowed for fireproofing of beams before deck was placed

Page 4: Good Samaritan Medical Center

Test run: Checked maximum free-fall of aggregate

Page 5: Good Samaritan Medical Center

PlacementHigh Density Concrete supplied by Central Concrete

Page 6: Good Samaritan Medical Center

Placement continued…• 187.5 CY placed total• 4.5 CY of concrete batched in each 12 CY truck• Rate of placement

• Started at 30 minutes per truck or more• Ended at 12-15 minutes per truck

Page 7: Good Samaritan Medical Center

Placement continued ….Central concrete quality control manager onsite: Only person allowed to add chemicals to the mix

Page 8: Good Samaritan Medical Center

Placement continued…Placement of high density concrete required normal size crew

Page 9: Good Samaritan Medical Center

Finished vault• Due to high density, concrete finished with few imperfections, even with minimal vibrating• Maximum deflection of the lid measured at 3/16”• 12.5 hour pour• 14 hour day