Construction Kickoff PresentationApril 26th 2017
Goldwind AmericasConstruction Kickoff:Landowner Presentation
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
Goldwind at a GlanceWorld Leader in PMDD Technology
No.1 Globally
No.1 PMDD
98+%
32GW
Goldwind is the world’s largest WTG manufacturer according to 2015 installations
Industry leader in Permanent Magnet Direct-Driveturbine technology
Goldwind’s fleet-wide turbine availability is 98+%
More than 32 gigawatts installed worldwide with a fleet of more than 19,000 turbines
20+years Over 20 years of experience in wind
WORLD LEADER
IN PMDDTECHNOLOGY
Established in 1998, Goldwind pioneered the Chinese wind market by becoming one of the first companies to explore the potential of wind power. Today, Goldwind is a leader in the global wind industry with mature manufacturing capabilities, innovative permanent magnet direct-drive (PMDD) technology, and a proven track record.
More than 6,000 employees around the world, of which approximately 1,000 employees dedicated to R&D and technical development
Public ally traded on 2 stock exchangesShenzhen A share: 002202 Hong Kong H share:2208
More than 32 GW of installed wind powercapacity
More than 19,000 of Goldwind's wind turbines have been installed around the world, with more than 15,000 units utilizing PMDD
North American HeadquartersChicago, IL
Goldwind Americas
Established in 2005 and currently employing approximately100 people in a full-time capacity, Goldwind Americas isresponsible for sales and service of Goldwind turbines inNorth and South America.
2005 2017
Our U.S.-based leadership team has over 150 cumulativeyears experience in wind and renewable energy relatedindustries.
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas
This is a construction site
Things to keep in mind
■ Long, wide and heavy trucks will be delivering parts and cranes to the site.
■ Cement trucks will be lined up to pour concrete foundations.
■ Equipment will be on the road –forklifts, rubber-tire cranes, aerial man lifts, etc.
■ Stay away if ice is present
■ Do not approach the turbine if trucks are present
■ Do not park near work areas
■ Do not contact Underground Collector System
■ Limit deep ripping to no more than 36-inches
■ Do not contact overhead wires
■ Do not contact junction boxes
■ Call before you dig
Call if anything seems wrong
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas©Goldwind Americas
Rattlesnake Construction Schedule
April-Roads
April-Foundations
August- O&M Building
August-Underground Electrical
August-Substation
September-Transmission Line
October – Turbine Delivery and Installation
April 2018 –Commercial Operation
©Goldwind Americas
Rattlesnake Layout
©Goldwind Americas
Rattlesnake Layout
©Goldwind Americas©Goldwind Americas
Daily Progress Updates
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas©Goldwind Americas
Road Construction
■ Turbine String Road Construction
– New access roads (approx. 21 miles)■ Wide travel path to
accommodate crane walks
■ 16’ wide permanent graveled surface
■ Culvert and low water crossing installation
■ Fence and gate and cattle guard installation
April 2017-October 2017
©Goldwind Americas
Road Construction
©Goldwind Americas
Road Construction
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas
Foundation Installation
April 2017- July 2017
Typical GW 2.5 MW Foundation:
58’6” circular footprint10’ deep at Pedestal412 cubic yards of Concrete35 tons of Steel
• Backfilled to ensure positive drainage away from foundation
• Concrete produced on site batch plant
©Goldwind Americas
Foundation Installation
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas
Collection Line Installation
August 2017- February 2018
■ Underground cable– Approx. 39 miles of 3-phase 34.5kV
cable installed between turbines and back to substation
– 4ft trench depth at 4ft below ground surface.
– Trench excavation with heavy rock trenchers
– Fiber optic and ground cable run in the same trench
– Fine screening of excavated material for cable bedding
– Backfilled to the surface and reclaimed to blend in with surroundings
Short spans of overhead collection
©Goldwind Americas
Collection Line Installation
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas
Turbine Delivery and Erection
©Goldwind Americas
Turbine Erection and Delivery
October 2017- February 2018
■ 64 x Goldwind 2.5MW turbines– 90m (300ft) hub height, 109m
(360ft) rotor diameter– Four piece steel tubular tower– Delivery rate of 8 complete turbines
per week, staged at each turbine location
■ Multiple crane activities– Two 300T-class crawler cranes for
setting lower tower sections and building rotors
– Two 600T-class crawler cranes for erecting turbines
– Up to ten rough-terrain hydraulic cranes to unload and provide assists
– Crane walks and breakdowns
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas©Goldwind Americas
The GW109/2.5 MW Turbine
Turbine Height
Foundation Volume
Product
Cut-in Wind Speed
Rated Wind Speed
Max Tip Speed
2.5MW
3 m/s (7 mph)
10.3 m/s (23 mph)
174 mph
300 Foot Tubular Steel Tower
Total Height 474 Feet
102 Tons
709 cy (536.7cm) of Concrete
79 tons (71,667.6kg) of Steel
Goldwind 2.5 MW Turbine Product Summary
Copyright © Goldwind Americas
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas
Substation Construction
August 2017- January 2018
• LCRA’s Bow Wood Substation goes online 04/28/2017
• Energization of the Rattlesnake Substation January 2018
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas
Transmission Line Construction
September 2017- January 2018
• Approximately 16 miles in length
•Runs from the Rattlesnake Substation to Bow Wood Substation
•Poles approx. every 800-1000ft
• Steel monopole construction
• Limited use of guy wires
1 Introduction to Goldwind
2 Site Safety Awareness
3 Construction Schedule
4 Road Construction
5 Foundation Construction
6 Collection Line Installation
7 Turbine Delivery & Erection
8 Turbine Information
9 Substation Construction
10 Transmission Line Construction
11 Additional Q&A
©Goldwind Americas
Project Contact Information
Keith Kurtz
Project Development & Asset Manager
(312) 858-0383
James Blount
Site Construction Manager
(903) 517-6417
Site Office Trailers775 CR146 Melvin TX