• Goal • Parameters • How • Tools • Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

Embed Size (px)

DESCRIPTION

PJM allows the following offer types for generation in the Day Ahead (DA) Security Constrained Economic Dispatch (SCED):  Must Run: Does not follow PJM economic signals in RT DA offer curve only two (2) points economic minimum or economic maximum Cost curve only  Economic Should follow PJM economic signals in RT DA offer curve has up to ten (10) points Can use either cost curve or price curve or multiple types Parameters

Citation preview

Page 1: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

• Goal

• Parameters

• How

• Tools

• Results

Increasing Revenues by Optimizing Generation

Relative to PJM Forecasted Price Signals

Page 2: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

• Gain additional revenues from the PJM Real-Time

(RT) market by adjusting generation output,

either up or down, while meeting PJM operational

requirements.

Goal

Page 3: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

• PJM allows the following offer types for generation in the Day Ahead (DA) Security Constrained Economic Dispatch (SCED):

Must Run: Does not follow PJM economic signals in RT DA offer curve only two (2) points economic

minimum or economic maximum Cost curve only

Economic Should follow PJM economic signals in RT DA offer curve has up to ten (10) points Can use either cost curve or price curve or multiple

types

Parameters

Page 4: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

• PJM desires that a generator follow its DA schedule in RT for a Must Run schedule. Those generators should follow their DA schedule to avoid Operating Reserve charges

• In RT, PJM will produce economic prices signals every five (5) minutes, for Economic scheduled generation. Those generators should follow economic price signal to avoid Operating Reserve charges

• PJM recognizes that generators aren’t perfect as to meeting generation schedules and/or direction, thus PJM allows a variance or buffer relative to the generator maximum rating

Parameters (cont.)

Page 5: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

Parameters (cont.)

Page 6: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

How

• Gaining additional revenues, relative from the DA schedule, from the PJM RT can be accomplished by moving generation in an economic direction as follows:

If the RT marginal price is > the DA marginal price and excess generation is available, the generation should be increased

If the RT marginal price is < the cost of generation, the generation should be decreased [1]

[1] Two schools of thought: (i) reduce generation if RT price below fuel cost; (ii) reduce generation if RT price is below incremental cost.

Page 7: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

How (cont.)

• Inputs needed:

Forecast RT marginal price for hour ending Estimate of operating reserve charges Actual generation output PJM economic generation signal Incremental and decremental cost curve

Page 8: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

Tools

• Program that will produce:

A forecast RT hour ending LMP, with a high degree of accuracy as to absolute value and direction

Monitor the aforementioned PJM inputs Respect PJM operating reserves charges and rules for

charges Provide generation direction from the above inputs and

calculations Monitor results and provide historical performance

Page 9: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

Results

Page 10: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

Results (cont.)

Seven Month Results Total Average Per MonthScheduled MWh Revenue 8,038,000$ 1,118,000$ Total MWh Revenue 8,388,000$ 1,171,000$ Value-Add Gross Revenue 359,000$ 54,000$ Value-Add Net Revenue 191,000$

Page 11: Goal Parameters How Tools Results Increasing Revenues by Optimizing Generation Relative to PJM Forecasted Price Signals

Questions / Contacts

• Pat Frazier, BFE Scheduling, (502) 581-0003 ext. 101

• Cris Williams, BFE Scheduling, (502) 581-0003 ext. 106